MS Project - 24 January 2016

1

Click here to load reader

Transcript of MS Project - 24 January 2016

Page 1: MS Project - 24 January 2016

ID Task Name Duration Start Finish Predecessors

0 24 January 2016 15 days? Mon 25/01/16 Mon 15/02/161

2 Australia Day 26 January 1 day Mon 25/01/16 Wed 27/01/16

3

4 Roof 1 day Mon 25/01/16 Wed 27/01/16

5 Roof Cowells Dektites 1 day Mon 25/01/16 Wed 27/01/16

6 Capping 1 day Mon 25/01/16 Wed 27/01/16

7

8 GCS Scaffold 5.6 days Mon 25/01/16 Tue 2/02/16

9 West 0.2 days Mon 25/01/16 Mon 25/01/16

10 Hop Ups 15 and 16 0.2 days Mon 25/01/16 Mon 25/01/16

11 East and North 3.5 days Thu 28/01/16 Tue 2/02/16

12 Remove Roof and 1st Floor 1 day Thu 28/01/16 Fri 29/01/16 36

13 Remove Ground 0.5 days Fri 29/01/16 Sat 30/01/16 12

14 Hoists and Chute TBA 1 day Sat 30/01/16 Mon 1/02/16 13

15 Remove from Site 1 day Mon 1/02/16 Tue 2/02/16 14

16

17 Camillo 1st Aid 0458 109 454 1 day? Mon 25/01/16 Wed 27/01/16

18 Cover Windows Herdsman Pde and Eas 1 day? Mon 25/01/16 Wed 27/01/16

19

20 EuroRock 4.6 days Mon 25/01/16 Mon 1/02/16

21 Float Garage reveals 1, 5 and 9 0.1 days Mon 25/01/16 Mon 25/01/16

22 Float Stairwells 12 - 16 1 day Mon 25/01/16 Wed 27/01/16 21

23 Float West 1st 15 and 16 1 day Wed 27/01/16 Thu 28/01/16 22

24 Float South 16 0.5 days Thu 28/01/16 Fri 29/01/16 23

25 Float East 12 - 16 1 day Fri 29/01/16 Sat 30/01/16 24

26 Float Balconies Type A 1 day Sat 30/01/16 Mon 1/02/16 25

27

28 Marten Set 7 days Mon 25/01/16 Thu 4/02/16

29 Units 1-5 3 days Mon 25/01/16 Fri 29/01/16

30 Stairwells 2 days Fri 29/01/16 Mon 1/02/16 29

31 Patching 2 days Mon 1/02/16 Thu 4/02/16 30

32

33 Pacific West 4.1 days Mon 25/01/16 Sat 30/01/16

34 Reveals Garages 1, 5 and 9 0.3 days Mon 25/01/16 Mon 25/01/16

35 Unit 11 and Roof Level 1 day Mon 25/01/16 Wed 27/01/16 21

36 !st Floor 1 day Wed 27/01/16 Thu 28/01/16 35

37 Ground 12 - 16 2 days Thu 28/01/16 Sat 30/01/16 36

38

39 ICP Ceilings 5 days Mon 25/01/16 Mon 1/02/16

40 Gap & Sand 6 - 11 2 days Mon 25/01/16 Thu 28/01/16

41 Complete Units 1 & 2 3 days Thu 28/01/16 Mon 1/02/16 40

42

43 Cool and Cosy Glass 8.6 days Mon 25/01/16 Sat 6/02/16

44 Glaze West 12 -16 1 day Mon 25/01/16 Wed 27/01/16

45 Note Ground 6-11 Early Feb 3 days Tue 2/02/16 Sat 6/02/16 15

46

47 New Hope Tiling 14 days Mon 25/01/16 Sat 13/02/16

48 Grout 12 - 16 Floors 1 day Mon 25/01/16 Wed 27/01/16

49 Wall Tiling 3 days Wed 27/01/16 Sat 30/01/16 48

50 Grout 12 - 16 Walls 1 day Sat 30/01/16 Mon 1/02/16 49

51 Waterproof 6 - 11 2 days Mon 1/02/16 Thu 4/02/16 50

52 Floor Tile 6 - 11 2 days Thu 4/02/16 Sat 6/02/16 51

53 Kung Hei Fat Choy 2 days Mon 8/02/16 Wed 10/02/16

54 Grout 6 - 11 0.5 days Wed 10/02/16 Wed 10/02/16 53

55 Wall Tiling 6 - 11 3 days Fri 5/02/16 Wed 10/02/16 61

56 Screed 1 - 5 1 day Wed 10/02/16 Thu 11/02/16 55

57 Grout Walls 6 - 11 1 day Wed 10/02/16 Thu 11/02/16 55

58 Waterproof 1 - 6 2 days Thu 11/02/16 Sat 13/02/16 57

59

60 BF Cabinets 8 days Thu 4/02/16 Mon 15/02/16

61 Vanities 6 - 11 1 day Thu 4/02/16 Fri 5/02/16 51

62 Vanities 1 - 5 1 day Sat 13/02/16 Mon 15/02/16 58

63

64 WCG Carpentry 4 days Mon 25/01/16 Sat 30/01/16

65 Doors 12 - 16 1 day Mon 25/01/16 Wed 27/01/16

66 Skirtings 12 - 16 1 day Wed 27/01/16 Thu 28/01/16 65

67 Doors 6 - 11 1 day Thu 28/01/16 Fri 29/01/16 66

68 Skirtings 6 - 11 1 day Fri 29/01/16 Sat 30/01/16 67

69

70 Exclusive Painting 4 days Wed 27/01/16 Mon 1/02/16

71 Capping 1 day Wed 27/01/16 Thu 28/01/16 6

72 Ceilings 6 - 11 3 days Thu 28/01/16 Mon 1/02/16 71

73 Gap and prime 12 - 16 1 day Thu 28/01/16 Fri 29/01/16 66

74

75 Ben Survey 1 day Mon 25/01/16 Wed 27/01/16

76 Peg 1 day Mon 25/01/16 Wed 27/01/16

77

78 Hank Concretor 4 days Wed 27/01/16 Mon 1/02/16

79 Footings 4 days Wed 27/01/16 Mon 1/02/16 76

80

81 Shift Bricks 1 day Mon 25/01/16 Wed 27/01/16

82

83 Declan Bricklayer 4 days Mon 1/02/16 Sat 6/02/16

84 Screen Walls 4 days Mon 1/02/16 Sat 6/02/16 79

Australia Day 26 January 27/01

Roof Cowells Dektites 27/01

Capping 27/01

Hop Ups 15 and 16 25/01

Remove Roof and 1st Floor 29/01

Remove Ground 30/01

Hoists and Chute TBA 1/02

Remove from Site 2/02

Cover Windows Herdsman Pde and Eas 27/01

Float Garage reveals 1, 5 and 9 25/01

Float Stairwells 12 - 16 27/01

Float West 1st 15 and 16 28/01

Float South 16 29/01

Float East 12 - 16 30/01

Float Balconies Type A 1/02

Units 1-5 29/01

Stairwells 1/02

Patching 4/02

Reveals Garages 1, 5 and 9 25/01

Unit 11 and Roof Level 27/01

!st Floor 28/01

Ground 12 - 16 30/01

Gap & Sand 6 - 11 28/01

Complete Units 1 & 2 1/02

Glaze West 12 -16 27/01

Note Ground 6-11 Early Feb 6/02

Grout 12 - 16 Floors 27/01

Wall Tiling 30/01

Grout 12 - 16 Walls 1/02

Waterproof 6 - 11 4/02

Floor Tile 6 - 11 6/02

Kung Hei Fat Choy 10/02

Grout 6 - 11 10/02

Wall Tiling 6 - 11 10/02

Screed 1 - 5 11/02

Grout Walls 6 - 11 11/02

Waterproof 1 - 6 13/02

Vanities 6 - 11 5/02

Vanities 1 - 5

Doors 12 - 16 27/01

Skirtings 12 - 16 28/01

Doors 6 - 11 29/01

Skirtings 6 - 11 30/01

Capping 28/01

Ceilings 6 - 11 1/02

Gap and prime 12 - 16 29/01

Peg 27/01

Footings 1/02

Shift Bricks 27/01

Screen Walls 6/02

T F S S M T W T F S S M T W T F S S M T W T F S S25 Jan '16 1 Feb '16 8 Feb '16