ms NewsNotes Fall/Winter 2011

download ms NewsNotes Fall/Winter 2011

of 16

Transcript of ms NewsNotes Fall/Winter 2011

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    1/16

    ms consultants, inc. engineers, architects, plann

    Pi t t sburgh br idges being rehabi l i t a tedConstruction underway on multiple bridge projects

    See story starting on page

    all 2011 -- volume 20, issue 2

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    2/162

    Bridges, br idgesever yw here!

    If youve ever spent any time driving in and arou

    Pittsburgh you quickly realize that you cant go anywhe

    without crossing a bridge. There are bridges everywhe

    you turn and bridges of all shapes and sizes - arch bridg

    beam bridges, truss bridges, suspension bridges - y

    name it, theyve got it.

    In fact, a study published in 2006 counted 446 bridg

    within the city limits, and that didnt count the many mobridges within surrounding Allegheny County.

    Pittsburgh beat out the city of Venice, Italy, as t

    world record holder for the most bridges within any city

    Pittsburgh Public Works is spend$7 million replacing the McArdleViaduct No. 1 in what is the cityslargest road or bridge project in 2

    Photo at right: The Jacks Run Bron Lincoln Avenue just finished brehabilitated and is now open to t

    Cover photo: The Boston Bridge

    southeastern Allegheny County isbeing rehabilitated.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    3/16

    With the city located at the junction of three rivers and with a

    topography made up of sizeable hills, valleys and ravines in every

    direction, bridges and tunnels quickly became integral to the

    Pittsburgh areas transportation network. So its probably no

    surprise that maintenance for all of those structures becomes a

    major issue.

    Thats where ms consultants has been able to step in and help.

    ms has worked on a number of bridges in the region over theyears, providing structural analysis, engineering design and

    construction inspection and administration.

    The firm currently has three area bridges in various stages of

    construction rehabilitation - the Jacks Run Bridge, the McArdle

    Viaduct (No. 1) and the Boston Bridge.

    All are important transportation links within their respective

    parts of the city or county, and all are different types of bridges

    that span different types of topography.

    The Jacks Run Bridge is located in the Borough of Bellevue.

    Bellevue is an older community just northeast of downtown

    3

    Pittsburgh and the bridge on Lincoln Avenue carries vehicles an

    pedestrians over Jacks Run, a deep ravine that cuts through th

    neighborhood.

    This project involved the rehabilitation of an open spandr

    concrete deck arch, built in 1926. The deck arch includes

    approach spans, 15 feet to 20 feet long, and a 320-foot-long ma

    span for a total length of 590 feet. The deck arch supports a two

    lane roadway with 7-foot shoulders and two sidewalks.The bridge replacement included expansion dams, s

    concrete floorbeams, four concrete columns and utilized galvan

    anode corrosion protection. ms consultants replaced the drainag

    system and bearings, and installed decorative lighting along th

    sidewalks on the bridge.

    To maintain some connectivity for the neighborhood durin

    construction, the bridge was closed to vehicles but pedestria

    traffic was maintained at all times.

    The Jacks Run Bridge was an American Recovery an

    Reinvestment Act of 2009 (ARRA) funded project.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    4/164

    Pittsburgh Public Works is also spending

    million replacing the McArdle Viaduct No

    in what is the citys largest road or brid

    project in 2011.

    Built in 1933, the bridge stretches ov

    Norfolk Southern Railway tracks near Windo

    Street and is a gateway to the South Side f

    motorists coming from the Liberty Tunnel a

    Mt. Washington.The McArdle Viaducts are included in

    Pittsburgh History and Landmarks Foundati

    survey of potentially important sites, structur

    objects, and buildings in Allegheny County.

    Viaduct No. 1 is a 541-foot-long structu

    consisting of 11 simple-span, multi-gird

    spans varying in length from 25 feet to 31 fe

    and one 215-foot-long through truss span ov

    railroad tracks.

    ms consultants provided complete consuing engineering services, including an in-dep

    inspection for both Viaducts 1 and 2 to det

    mine the approach to rehabilitating these stru

    tures. This process included general inspe

    tions, field inspections and material testing, a

    structural analyses. Design work for t

    rehabilitation included structural, roadway a

    traffic engineering. Final design involv

    reconstruction of the roadway approach

    including maintenance of alignment at t

    intersection with Arlington Avenue.

    ms was responsible for collecting a

    analyzing data for development of the Catego

    cal Exclusion Evaluation (CEE) and Prelim

    nary Area Reconnaissance (PAR), which iden

    fies the potential for contaminated areas.

    More specifically, the team collected de

    information, assessed potential social impac

    located any known hazardous waste site

    conducted soil samples, and developed

    historical and archaeological submission f

    historic review at the Pennsylvania Historic

    and Museum Commission. The submissi

    included additional coordination with a histo

    cal consultant for the development of a Histo

    Structures Survey, Criteria of Effects Rep

    and a Historic American Engineering Record

    Rehabilitation of the viaducts includ

    replacement of the superstructure and all of t

    steel bents. The simple-span superstructue Jacks Run Bridge carriescoln Avenue over a deep

    vine that cuts through therough of Bellevue.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    5/16

    will be replaced with continuous girders, eliminating several

    existing expansion dams. The existing sidewalk was replaced, but

    due to the historic nature of the structure, the original pedestrian

    hand railing was modified and reused. New decorative light poles

    were designed to meet the original design.

    To verify the condition of the existing concrete piles support-

    ing the foundations, test pits and pile integrity tests were

    performed. It was determined that the existing unreinforced

    concrete piles supporting the steel bents and abutments were

    overstressed. To strengthen the substructure, rock anchors were

    utilized to reinforce the shear resistance of the foundations.

    The Boston Bridge project involves the rehabilitation of an

    existing steel cantilever through-truss and twin girder approach

    spans, built in 1931. There are five twin-girder approach spans, 60

    feet to 107 feet long, and three main truss spans, measuring 150

    feet, 420 feet and 150 feet, totaling 1,182 feet.

    The bridge carries S.R. 48 over the Youghiogheny River in

    Versailles Borough and Elizabeth Townships in Allegheny

    County. S.R. 48 tapers from two to three lanes over the length of

    the structure with a sidewalk on each side of the bridge.

    ms planned the replacement of the deck, including stringers

    and expansion dams, the drainage system and bearings. The

    existing decorative bridge railing was reused. Approximately 200

    feet of roadway on each side of the bridge was also upgraded.

    5

    Other work included seismic retrofit of existing truss bearing

    replacement of truss pins and tie-downs and strengthening of tru

    gusset plate connections. The new deck was comprised of 5 3/16

    steel grid with half-depth concrete in-fill. This deck type wa

    selected to reduce the dead load on the truss and speed up dec

    replacement.

    One of the most challenging project aspects was replaceme

    of four truss tie-down pin and linkage assemblies that anchor th

    end of truss to the piers. The project team evaluated a number o

    different options to replace these members within the very tig

    existing construction schedule. The non-redundant member

    under dead load tension, and therefore a temporary tie-dow

    system was designed to anchor the bridge during replacemen

    The new linkage was designed to be fully internally redundant.

    Because of the long detour route vehicles would have t

    endure, required bridge closures were compressed into an 85-da

    schedule. Pedestrian traffic was accommodated across the bridg

    for the entire project with the exception of 14 days for the pin an

    linkage replacement.

    The project is scheduled for completion by the end of 2011.

    For more information about any of these bridge project

    please contact Gary Gardner or Dan Wills in the Pittsburg

    office at (412) 264-8701, or e-mail [email protected].

    The Boston Bridge carries S.R. 48 overhe Youghiogheny River in VersaillesBorough and Elizabeth Townships insoutheastern Allegheny County.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    6/166

    Colum bus Innerbe l t p ro jec t beg in

    consultants created this photorealisticmputer rendering to show what the0/I-71 (east) interchange will look likeon completion.

    e view is looking slightly northwest.

    e photo at right shows the eastrchange as it looks today.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    7/16

    ons t ruc t i onThe reconstruction of the I-70/I-71 Columbus Crossroa

    Project has officially begun as the Ohio Department of Tra

    portation (ODOT) started closing certain ramps and lan

    along the downtown route in September.

    The massive and complex project will be completed

    phases, with the I-71/I-670 interchange rebuild as the first

    three scheduled projects designed to reduce crashes, weavi

    traffic and congestion.

    The interchange averages approximately 137,000 vehic

    per day, twice as many as it was designed to accommodate.

    Construction crews are beginning work on the und

    ground drainage system.

    The rebuild is estimated to cost $200 million.

    After that project is completed, ODOT plans to rebuild t

    I-70/I-71 interchange, a little further south near Nationw

    Childrens Hospital (shown at left).

    The third phase will be the reconstruction of I-71 betwe

    the two interchanges.

    Those two projects will cost an estimated $368 million apush construction into 2015.

    More phases are planned, including reconstruction of t

    I-70/I-71/SR 315 interchange to the west and I-70/I-71 alo

    the southern edge of downtown.

    Periodic updates will be published in this newsletter and

    www.msconsultants.com as the projects progress.

    For more information, please contact project manager T

    Hibbard in the Columbus office at 614.898.7100, or em

    [email protected].

    7

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    8/16

    New sec t ion o f US 35opens in West V i r g in ia

    8

    U.S. Route 35 runs northwest-southeast for more than 400

    miles from northern Indiana into West Virginia, where it connects

    to Interstate 64. Most of the portion that runs through Ohio has

    already been upgraded to a four-lane highway/freeway, starting

    west of Dayton all the way to the West Virginia state line.

    In West Virginia, from the Ohio River to Interstate 64, U.S. 35

    is being expanded to a four-lane expressway. Currently the route is

    four lanes from I-64 to the junction with the bridge to Buffalo, and

    continues as a two-lane route for 12 miles to another four lane

    section of eight miles to the Ohio River.

    As one of the main connectors between Columbus, Ohio, and

    Charleston, West Virginia, the highway carries a heavy volume of

    vehicles, including numerous semi-trailers. Completion of all

    sections of the highway on the West Virginia side would create a

    four-lane route (with I-64) between the two cities.

    ms consultants prepared construction plans, specification

    construction cost estimates and right-of-way plans for th

    construction of a three and eight tenths mile section of U.S. 3

    just west of C.R. 40 in Mason County, West Virginia.

    The project starts with a high speed connector tying into o

    U.S. 35 (now designated WV 817), which transitions into a fo

    lane divided highway with a 46-foot median. The new alignme

    extends northwest for almost four miles before tying back into th

    existing four-lane section of U.S. 35 just south of the Ohio Rive

    The scope of services included right-of-way plans th

    involved more than 30 parcels. The high-speed connector run

    adjacent to various small residential parcels, which containe

    driveways, utilities and septic tanks.

    As a result, many existing utilities needed to be relocate

    during construction.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    9/169

    Due to the fast-track nature of this project, the property was

    acquired even before the final roadway plans were finished.

    Various revisions and accommodations were made during the

    acquisition process to satisfy local residents.

    A number of new bridges were necessary to cross existing

    creeks and local roads, including a two span, 304-foot bridge that

    spans Lower Ninemile Creek and CR 38. Curved steel plate

    girders are provided with a concrete deck, cap and column piers

    on piles, and a combination of integral and semi-integral

    abutments on spread footings and piles.

    Ten major culverts were included with this project and

    approximately 3,500 feet of creek was relocated using Natural

    Stream Channel Design procedures.

    Many of the connector roads to the highway traverse steep

    slopes, deep cuts and sharp turns because of the topography, and

    the four-lane highway itself experiences significant changes in

    elevation over its length.

    The remaining 12-mile section of U.S. 35 that is still two lanes

    is currently unfunded.For more information about this project or others currently

    underway in West Virginia, please contact our Charleston office at

    304.346.1211 or [email protected].

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    10/16

    Indoor at h let i c t ra in ing fac i l i t y opensYSU welcomes addition of WATTS to athletic program

    10

    ms consultants provided final design services and construction

    administration for a new indoor sports practice facility for various

    athletic teams at Youngstown State University (YSU). The facility

    provides athletes with year-round training amenities and protec-

    tion from weather conditions.In order to determine the necessary requirements and potenti-

    alities, ms was previously hired to conduct a preliminary program

    assessment. Several program options were developed to provide a

    main field house and support spaces. The main field house was

    envisioned to encompass an indoor football field, 300-meter track,

    batting cages, long jump pits, high jump pads, pole vault pads, and

    other indoor field activities. The support space includes a lobby,

    public restroom, mens and womens locker rooms, and athlet

    storage with a total square footage was 125,000.

    Due to the size of the facility, ms reviewed four possible sit

    located on the YSU campus. These sites were evaluated for bo

    positive and negative attributes regarding site conditions, proximity to existing athletic infrastructure, available parking, pedestri

    and traffic control, site densities, and visual impact analysis.

    Additionally, the architects reviewed three building types

    accommodate the required program. The building types reviewe

    consisted of a steel frame structure with fabric sheathing;

    conventional metal building system; and an inflatable air structu

    with tension cables.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    11/1611

    The steel fabric structure (SFS) and the metal building are

    permanent facilities. The inflatable air structure was a temporary

    proposal. A cost analysis was also conducted for each building and

    program combination.

    University officials collaborated with ms in selecting a

    preferred site (Elm Street at Eastbound Service Road) and a build-

    ing type (a conventional metal facility), and worked with the

    project team on final design details. Design development, contract

    documents, specifications, and bidding assistance were providedby the team for the architectural, electrical and structural elements

    of the building with assistance of teammates CJL Engineering for

    mechanical/electrical/plumbing design and Resource Interna-

    tional for site civil engineering.

    The design team worked with LEED Certification as a goal.

    The project addresses sustainable site design through the use of

    reflective paving surfaces in the limited parking area and reflec-

    tive roof material to limit heat island effects on the building and

    surrounding campus area. The proposed building is anticipated

    have an energy consumption savings of 22% annually. The facilityreduces water consumption by 44% through efficient water

    fixtures and regional plant materials that eliminate the need for

    irrigation. Construction waste was recycled and diverted from

    local landfills. The building utilizes recycled materials sourced

    from regional manufacturers within a 500 mile radius, and the

    interior envelope utilizes low emitting finishes to improve the

    indoor air quality for building occupants. Finally, the site is

    located on multiple public transportation routes and accessible to

    basic community services that encourage pedestrian interaction.

    For more information, please contact Anthony Hayek

    Summer Barker in the Youngstown office at 330.744.5321,

    e-mail [email protected].

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    12/16

    m s renovat esYoungst ow n o f f i ceRenovation and expansion createsmore efficient work environment

    12

    The downtown office building occupied by ms consultants recently underwent

    a complete renovation that enabled the entire Youngstown staff to reunite in the

    same building for the first time in years. Prior to the construction, 23 of theemployees worked next door on the second floor of the Ohio Edison Credit Bureau

    building.

    The office at 333 East Federal Street has been transformed inside and out.

    Project manager Anthony Hayek, AIA, NCARB, says the firm wanted to

    create a pleasant and high-end working environment for everyone. We had

    outgrown the space and we wanted to consolidate all of our staff.

    A 7,600-square-foot addition at the south side of the existing 20,000-square-

    foot building allowed that consolidation to happen.

    The building was originally constructed in 1986 and is the third Youngstown

    location for the company since it was founded in 1963.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    13/1613

    ms consultants now has 10 offices located in five states, and is

    ranked number 246 in the latest Top 500 Design Firms list annu-

    ally compiled byEngineering News Record.

    The renovation/addition was a design/build project with ms

    consultants acting as the architect and B&B Contractors & Devel-

    opers, Inc., as the general contractor.

    The interior of the building was completely gutted, but the

    construction was done in phases so the ms staff could continue

    working all through the process. Because of the tight schedule, theplanning and managing of the different construction phases and

    employee moves was critical to the success of the project.

    The basement was renovated first, creating a staging area for

    subsequent phases. The company set up about 80 portable tables

    in the finished basement as a temporary workspace. As one section

    of the building was completed, employees would shift spaces

    allowing the next phase of construction to take place.

    It was challenging to work through the construction going on

    and the multiple moves some of the staff had to make, but we all

    knew it would be worth it when it was done, says Hayek.The basement now houses the cafeteria, the IT department and

    storage area where all of the northeast Ohio records are kept.

    The technology aspect of the project was also important as the

    IT staff had to dismantle and reassemble computer stations numer-

    ous times to keep the office staff operational, and a videoconfer-

    encing system was added.

    A white noise system and soundproof walls were installed

    throughout the building to reduce sound in the open office

    environment.

    Enhancing that open floor plan are energy efficient lighting,

    carpeting and floor tile consistent with Leadership in Energy and

    Environmental Design (LEED) standards.

    Natural light is also utilized in all interior areas of the building,

    which is welcome during the long northeast Ohio winters.

    The entrance lobby is much roomier, with comfortable seating

    for visitors and a flatscreen monitor mounted on the wall showing

    a collection of projects completed by the firm.

    Outside the lobby at the front entrance is the most noticeable

    difference between the old and new building, a 400-square-foot,

    custom-designed metal canopy that provides a strong visual

    element that draws visitors to the front door. The bronze-colored

    canopy complements the brick facade of the building, which

    matches many of the other buildings in downtown Youngstown.

    Summer Barker, AIA, LEED AP, project architect and

    designer for ms, says the interior design will be contemporary for

    years to come and notes that the space is already being used as a

    showcase to present design ideas and qualities to clients.

    For more information about this project or to set up an office

    visit, please contact Anthony Hayek or Summer Barker at

    330.744.5321, or send an e-mail to info@msconsultants.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    14/16

    Colum bus Com m ons an urban oasisThe downtown park opens on former City Center Mall sit

    14

    City Center Mall was a 1.2 million-square-foot, 3-levelshopping center in the heart of downtown Columbus, Ohio. It was

    developed by the city as part of the Capital South development

    and officially opened in August of 1989.

    Less than 20 years later, newer suburban, mixed-use shopping

    centers on the northwest, north and east sides of the city had

    brought an end to City Center. The mall officially closed in March

    of 2009, and demolition began later that year.

    Corna-Kokosing and ms consultants worked together on the

    complete demolition and reconstruction of the mall site. Corna-

    Kokosing is the general contractor and ms consultants provided allof the mechanical, electrical, plumbing, fire protection and

    security system design for the project.

    The scope of work required the removal of the existing struc-

    ture while maintaining full operations of the underground parking

    facility, security operations, and healing of connections to

    adjacent buildings. All major systems had to be assessed prior to

    making design decisions. Numerous scenarios of phasing and

    system configurations were evaluated before selecting a final

    solution. The final demolition/reconfiguration documents

    included documenting systems that were to be removed, systems

    that were to remain in place temporarily and completely nesystems. The evaluation process also determined that securi

    office systems and operations needed to be completely relocate

    to a remote building, while maintaining full operations. All of th

    demolition/reconfiguration was accomplished while maintainin

    full operation of the parking facility, all of the mechanical an

    electrical systems, and the security systems.

    As part of the project, Corna-Kokosing created detaile

    programs for recycling waste materials and reusing the maximu

    amount of existing materials to bring a high level of environme

    tal responsiveness to the project.In February 2009, plans were announced to redevelop the ma

    site with a project that includes an urban park, homes, office

    restaurants and shops. The first phase of the project cost a total

    $20 million, and the park portion of the project opened to th

    public on Memorial Day weekend 2011.

    Corna-Kokosing and ms consultants are currently working o

    the stage area for the park. This includes a covered canopy an

    permanent stage attached to the rear of the Ohio Theater buildin

    which sits at the north end of the park. Construction is schedule

    to be complete during the first half of 2012.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    15/16

    New h i res and promot ions s t reng thenf i rm s pos i t ion in mu l t ip le m arke t s

    Indiana, northeast Ohio and government clients to benefit

    15

    Jayson Thorne has joined ms in Indianapolis as the Director

    of Indiana operations.

    For the City of Indianapolis Long-Term Control Plan, he was

    responsible for the day to day oversight and management of

    projects and project staff which includes a

    team of 30 engineers, technicians, and

    clerical staff and up to 60 concurrently

    active projects.

    His program management experience

    includes work for the City of Omaha,

    Nebraska, Department of Public Works, and

    City of Ft. Wayne, Indiana, Department of

    Utilities.

    His design experience includes the

    preliminary design of highways and highway infrastructure,traffic analysis, and drainage design.

    Jayson was the chairman for the 5 Cities Plus Conference in

    2011, responsible for all coordination, planning and logistical

    support of the conference and conference staff.

    He is a graduate of Purdue University and is working toward

    his Professional Engineers license.

    In northeast Ohio, Bill Ruggles, PE, has been promoted to

    Structures Technical Service Manager for the Youngstown office.

    In this position he is responsible for

    managing the day-to-day operations of the

    structural engineering team. His responsi-

    bilities include the initial planning of struc-ture projects, determining personnel and

    budget requirements, and follow-through to

    completion. He is responsible for the

    technical accuracy of work and compliance

    with governing design codes and regula-

    tions.

    Bill is a graduate of Youngstown State

    University with a Master of Science, and started working for ms

    consultants right out of school.

    Also in Youngstown, architect David Kiraly, AIA, has

    joined the staff as a senior project manager after running his own

    design firm for a number of years.His design experience includes hospi-

    tals and medical facilities, schools, restau-

    rants, retail, hotels and hospitality, fitness

    facilities, and industrial processing and

    manufacturing plants.

    In 2005, he served as the architect on

    ABCs Extreme Home Makeover televi-

    sion show for a residential renovation

    project in Boardman, Ohio.

    David is a graduate of Kent State University.

    Louis Berroteran has joined the firm in Akron, Ohio, as

    community and government affairs specialist.

    He has a background in local, state and federal governmen

    most recently as the Senior Director of the

    Government Affairs/Workforce for the

    Greater Akron Chamber of Commerce.

    He coordinated the public/private

    partnerships for the more than 2,000 mem-

    bers of the chamber, which serves

    businesses in Summit, Portage and Medina

    counties in northeast Ohio.

    Lou also served in the private sector as

    the Director of Communications for a

    professional consulting firm practicing in the fields of enginee

    ing, landscape architecture and site development.He is a graduate of Kent State University, and has a Master

    Public Administration from the University of Akron.

    The year w as 1963

    Did you know that ms consultants was founded in 196

    That was the same year the Beatles released their first album an

    the first James Bond film (Dr. No) opened in U.S. theaters.

    To reach any of the ms staff mentioned in this issu

    please contact the nearest office or send an e-mai

    [email protected].

    Akron, OH 330.258.9920

    Columbus, OH 614.898.7100

    Cleveland, OH 216.581.4035

    Youngstown, OH 330.744.5321

    Indianapolis, IN 317.566.0050

    Pittsburgh, PA 412.264.8701

    Harrisburg, PA 717.697.2373

    Charleston, WV 304.346.1211

    Raleigh, NC 919.772.5565

    Roanoke Rapids, NC 252.519.2135

    We can also be reached via our website at:

    www.msconsultants.com

    For more information about the website and socmedia connections, please see the story on the ba

    page.

  • 8/3/2019 ms NewsNotes Fall/Winter 2011

    16/16

    new ms w ebs it e in teg ra tes net w ork ing media

    ms consultants is pleased to announce the newly redesigcompany website (www.msconsultants.com) officially launc

    on October 18.

    The last time the site was completely revamped was in 20

    but with the firm offering new services and many projects get

    underway or completing construction in recent months,

    companys online presence was in need of an update.

    And with the proliferation of business and social media s

    as LinkedIn, Facebook and Twitter, those tools needed to

    integrated into the site.

    ms consultants can now be found at:

    www.facebook.com/pages/Ms-consultants-inc/127446720690

    www.twitter.com/ms_consultants

    www.linkedin.com/company/ms-consultants-inc.

    Columbus-based Cement Marketing guided the rede

    process, with much input and assistance from ms staff.

    For more information, please contact Monica Mosure or Ch

    Campbell in the Columbus office at 614.898.7100, or e

    [email protected].

    ms consultants, inc.engineers, architect, planners

    PRSRT STDU.S. POSTAGE

    PAIDPERMIT NO. 225

    YOUNGSTOWN, OH