MR 2015 Case Study Group Project 240752.pdf

download MR 2015 Case Study Group Project 240752.pdf

of 17

Transcript of MR 2015 Case Study Group Project 240752.pdf

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    1/17

      RL4 M4A:1

    GROUP PROJECT (LTG © 2015) MR LTD  –  PALMERSTON NORTH

    (240.752 INTEGRATED LOGISTICS)

    What are the underlying problems at MR Ltd?

    The following information has been made available to you regards this MR Ltd Project.

    ORGANIGRAM

    MANAGING DIRECTOR

    Finance Logistics Marketing

    Director Director Director

    Operations Planning

    Manager Manager

    Materials Distribution

    Manager Manager

    Warehouse Transport

    Supervisor Supervisor

    Operatives Drivers

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    2/17

      RL4 M4A:2

    Note: Only the Distr ibut ion Structure is expanded so us e cos t centre approach.

    SITE DATA

    Warehouse and Site Plans are attached in MR Ltd 2.

    You und ertook a si te tour and noted the fol lowing : -

    1. Entrance

      Drove onto site unchallenged.  Unclear directions where to park.  Turned into Vehicle Assembly area.  Went into Distribution Office first, then directed to Main Office when asking for

    Managing Director.

    2. Yard

      Vehicles parked haphazardly.  Cars being washed.  Fuel pumps unattended.  Pallet store area full of damaged pallets.  Broken fork trucks with parts missing sitting beside pallets.  Cars parked alongside fuel pump.

    3. Warehouse

      Walked in unchallenged.  Vehicles being off-loaded outside.  "Careless" fork lift driving.  No procedures available for stock location.  No written safety policy displayed.  People standing around talking, some smoking.  Above average absenteeism apparent (upon discussion)  Damaged product lying around.  Congested despatch area.  Morale seems low.  Fork trucks covered with stickers.  Graffiti on walls.

      Toilets unclean, dirty sinks, grubby towels.  Lighting good, no space heating system.

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    3/17

      RL4 M4A:3

    SITE PLAN 

    NOT TO SCALE

    FENCING (Rest of Perimeter Building Walls)

    Grassed Area

    Grassed PRODUCTIONGrassed

     Area AREA Area

    IN OUT

    INMain

    Office PALLET Area STORE

    WAREHOUSE

    VEHICLECAR PARK

    PARK

    OUTFUEL PUMP

    VEHICLEWASH VEHICLE

     ASSEMBLY

    OUTIN

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    4/17

      RL4 M4A:4

    Grassed Area

    WAREHOUSE PLAN

    SCALE 10MM = 5 METRES Building Stanchions/Pillars< 70 metres >

    IN (Ground FireLevel) Exit

    Receipt

     Area

    STORAGE AREA

    90CLEAR HEIGHT metres

     AVAILABLE = 15 METRES

    20 PICKING DESPATCHm AREA AREAetr

    e (BANKED)s W C

    Fire OUTCANTEEN Exit

    Office VEHICLE ASSEMBLY (RAMPED)Distribution AREA (GROUND LEVEL)

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    5/17

      RL4 M4A:5

    INFORMATION AND QUESTIONS

    In add i t ion to the in format ion a lready g iven you are passed the fo l lowing descr ip t ion of

    the warehouse and transport op erat ions

    WAREHOUSE METHODS AND DATA

    Open

    Monday to Saturday, 0800 to 1800 hours, 51 weeks per annum (closed 1 week for holiday).Overtime is worked from 1800 to 2000 hours to load transport vehicles.Note . Site Access is possible 24 hours a day, 7 days a week.

    Receive

    From on site production by production trailer shuttle system (Flat 40 foot trailers).Product palletised, 1 Line per pallet.Pallets size 1.0 x 1.2 metre.Offloaded by CBT from ground level.

    Put Away to Storage Area

    By Counterbalance diesel forklift truck (CBT).

    Storage

    Random locations.Blockstacked on pallets, two high maximum, otherwise product "crushes".

    Bring Down to Pick Area

    By CBT.

    Picking

    Manual onto pallets, placed on Hand Pallet Truck (HPT).

    Pick Area to Despatch Area

    By HPT.

    Loading to Transport Vehicle

    By CBT.

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    6/17

      RL4 M4A:6

    TRANSPORT METHODS AND DATA

    Loading

    Picked pallets by CBT.1600 - 2000 hours each day.

    Delivery

    0900 - 1500 hours, Monday to Saturday, 51 weeks per annum.Daily deliveries.Each vehicle has a driver’s assistant. 

    Unloading at Customers

    Pallets removed by HPT (supplied by customer).Cartons hand stacked onto conveyor belts by driver and his assistant.Empty pallets are returned to vehicle.Customer, tally counts/checks cartons only.

    FIRST IMPRESSIONS - QUESTION (1)

    From ALL of the information given to you so far:-

      What comments would you make about observations? Why?

      What possible operational short falls can be identified in the MR operation?

      What logistics management practices appear questionable?

      What loss aspects might apply at MR Ltd?

    o  Identify what types of losses you believe could exist, where, and what causesyou to believe this?

    o  How might MR Ltd minimise losses.

      What immediate improvements would you suggest? (Note: the site cannot beextended)

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    7/17

      RL4 M4A:7

    PRODUCT DATA

    You are given the following data in addition to that already provided.

    PRODUCT DATA

    Product is dry, kept at ambient temperature.

    Number of Lines 350

    Gross Kilos per carton 13 Kg

    Dimensions, metres (L.W.H) per carton 0.5 x 0.4 x 0.4

    Cartons per pallet 24

    Pallet dimensions 1.0 x 1.2 metres.

    PRODUCTION TO WAREHOUSE METHODS and DATA

    Open

      Monday to Saturday, 0800 to 1800 hours, 51 weeks per annum (closed 1 week forholiday).

      Overtime is worked from 1800 to 2000 hours to load transport vehicles.

      Note.  Site Access is possible 24 hours a day, 7 days a week.

    Receive

      From on site production by production trailer shuttle system (Flat 40 foot trailers).

      Product palletised, 1 Line per pallet.

      Pallets size 1.0 x 1.2 metre.

      Offloaded by CBT from ground level.

    Put Away to Storage Area

      By Counterbalance diesel Fork Lift Truck (CBT).

    Storage

      Random locations.  Blockstacked on pallets.

      Two high maximum, otherwise product "crushes".

    Bring Down to Pick Area

      By CBT.

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    8/17

      RL4 M4A:8

    Picking

      Manual onto pallets, placed on Hand Pallet Truck (HPT).

    Pick Area to Despatch Area

      By HPT.

    Loading to Transport Vehicle

      By CBT.

    MATERIALS MOVEMENTS AND DATA

    Loading

      Picked pallets by CBT.

      1600 - 2000 hours each day.

    Delivery

      0900 - 1500 hours, Monday to Saturday, 51 weeks per annum.

      Daily deliveries.

      Each vehicle has a driver’s assistant. 

    Unloading at Customer

      Pallets removed by HPT (supplied by customer).

      Cartons hand stacked onto conveyor belts by driver and his assistant.

      Empty pallets are returned to vehicle.

      Customer, tally counts/checks cartons only.

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    9/17

      RL4 M4A:9

    RESOURCE DATA

    (People and Equipment)

    Warehouse

      Pickers 6  CBT drivers 6  CBT equipment 6  HPT equipment 6

    Transport

      Drivers 60  Driver's Assistants 60  Vehicle numbers 60

    GVW - Rigid 7.5 tonnepayload - Tonnes 3.5capacity - Pallets 10

    Administration

      Order clerks 2  Transport clerks 2  Supervisors 2  Manager (Distribution) 1

    Note: Al l equ ipment is own ed, but is external ly main ta ined on Sunday.

    COST DATA

     All per annum (unless otherwise stated).

    Manpower

    Based on 40 hour week, 52 weeks with 4 weeks holiday.

      Warehouseman $30000  Vehicle Driver upto 7.5 tonne GVW $30000

    over 7.5 tonne GVW $35000  Supervisor $40000  Admin. Assistant $28000  Vehicle Assistant $28000

    (Note. Overt ime is paid pro rata at t ime and half . eg, if work 60 hours , are paid 40hours basic and the overt ime of 20 hours, is pa id as 30 hours). 

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    10/17

      RL4 M4A:10

    Establishment Costs  – ops/yr

      Rent and Rates $160.00 per sq metre  Heat and light $80.00 per sq metre  Manager $80000  Security (night) $120000

      Other overheads $160000  Product damage $350000  Pallets $700000

    Warehouse Equipment/unit/yr

      HPT $150  CBT $14500

    Transport Equipment

      Fixed Cost, excluding people $25000  Variable cost, per KM $0.30

    (Note. Variable cost includ es external maintenanc e).

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    11/17

      RL4 M4A:11

    CUSTOMER DATA

      Two major JIT manufacturers are supplied.  Throughputs are shown on the volume data sheet.  The percentage split of volume is:-

    Wellington Customer 70%

    New Plymouth Customer 30%

    Customer Service

      Is paramount, as daily deliveries are required. (Because of this MR Ltd hadtaken the decision to gear up to cover peak requirements with all their ownresources. Management is sure this should continue, so it is currently BoardPolicy).

    Customer Orders

      Orders typically must follow a daily cycle as below:-

    Orders Taken By. Delivered By.

    1000 hours Monday 1500 hours Tuesdayto to

    1000 hours Friday 1500 hours Saturday1000 hours Saturday 1500 hours Monday

      Each customer order would typically include each product line.

    VOLUME DATA

    In Cartons

    MONTH  RECEIVE  DELIVER  STOCK 

    JANUARY 75000 90000 170520FEBRUARY 75000 108000 137520

    MARCH 75000 162000 50520 APRIL 75000 99000 26520

    MAY 75000 72000 29520JUNE 75000 63000 41520

    JULY 75000 54000 62520 AUGUST 75000 36000 101520

    SEPTEMBER 75000 45000 131520OCTOBER 75000 54000 152520

    NOVEMBER 75000 63000 164520DECEMBER 75000 54000 185520

    900000 900000

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    12/17

      RL4 M4A:12

    PRODUCTIVITY - QUESTION (2)

      What is the current warehouse capacity?

      Is it adequate for monthly throughput?

      What key cost elements within MR Ltd. Your answer should include the elements andtheir values.

      What are the monthly operational costings for MR Ltd.

      What is your “possible” warehouse capacity? (Options must be justified and costed)

      Can you justify would be the Cost/Benefit of the investment

    NOTE: You should us e your profess iona l judgement to decide what areas you are going to cos t

    and at what depth! Show just i f ica t ion for your d ecis ion. Note however , that you wi l l use these

    costs la ter in the course to com pare them against the costs you calcu la te af ter recomm ending

    improvements.

    NOTE: Vehicles c urrent ly average three del iveries per w eek and 45,000 kms per year,

    each veh icle.

    CURRENT UTILISATION - QUESTION (3)

      What is the current utilisation of resources across MR Ltd?

      Select and define the areas within MR Ltd where you believe that method study is asuitable means of improving productivity.

    Performance data

    The Supervisors believe the following currently apply:

    1. Warehouse CBT can move about 15 pallets per hour per operation.

    2. Each Picker can manage about 150 cartons per hour (which includes moving pickedpallet to despatch area).

    3. Transport Vehicles currently average 3 deliveries per week, and around 45000miles per annum. (The Transport Supervisor is aware vehicles are not always fullyloaded, but says "customer service is King around here").

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    13/17

      RL4 M4A:13

    NOTE: You should be looking at those areas w here resources of people , space and equipment

    are used. Do not try to u se standards which can be calcu la ted from formal methods of

    investigation , - just us e the “historical standards”. 

    Note: See the fol low ing info rmation t o aid analysis .

    ANALYSIS DATA - PERFORMANCE

    You may find the following performance data will help in your analysis.

    Warehouse Performance Data

    Fixed Times

      Simple Manual OperationsPick up/Put down 20 seconds per piece/package.

      Truck Operations

    Pick up/Put down 65 seconds per piece/package.  Hoist up/Hoist down 6 seconds/metre

    19.7 seconds/metre

    Variable Times

      Man walking, empty handed 61m/min

      Man walking with HPT 30.5m/min

      Man driving CBT 122m/min

      Man driving other trucks 91.5m/min

    Transport performance data - Loading/Unloading

      Fixed Time 10 mins per stop(eg, stopping vehicle, opening doors, documentation, etc.)

     And, to cover physical unloading per piece/package, add the following:-

    Fixed/Variable Times, as warehouse performance data.

    Travel Times

      Average Road Speeds Motorway 80 kphClass 2 Roads 75 kph

    Urban Roads 40 kph.  Distance. (Crow Fly Factor) Straight line plus 20 per cent.

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    14/17

      RL4 M4A:14

    IMPROVEMENT DATA

    You may find the following data useful for improvement purposes.

    Warehouse

    Capital Cost Cost per annum

    CBT LPG $32000 $16000CBT Electric $25000 $12000

    Narrow Aisle Reach Truck (NART) $44000 $16000

    Turret Truck (TT) $80000 $24000Multi Level Picker Truck (MLPT) $40000 $18000

    Conveyor $1500 per metre $150 per metre p.a.

    Racking - Normal APR $120 per pallet space $12.00 per pallet space

    Racking - Drive In $200 per pallet space $20.00 per pallet space

    Racking - Flow $300 per pallet space $35.00 per pallet space

     Aisle Width requirements Shortside Longside

    - CBT 3.3m 3.0m- NART 2.5m 2.13m- TT/MLPT 1.5m 1.32m

    (Based on pallet 1.0 x 1.2m)

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    15/17

      RL4 M4A:15

    Building changes

    CAPITAL COST COST PER ANNUM

    FIRE EXIT $2000 -

    GOODS DOOR $20000 $2000

    OPEN CANOPY $500 per square metre $30 per square metre

    SPACE HEATING $40 per square metre $20per square metre

    WAREHOUSE EXTENSION $1000 per square metre $55 per square metre

    YARD EXTENSION $600 per square metre $60 per square metre

    Transport

    TYPE CAPACITYCAPITAL

    COSTFIXED COSTPER ANNUM

    VARIABLECOST PER

    KMTONNES PALLETS

    3.5T GVW RIGID  1.75  6  $45000  $5000  $1.00

    7.5T GVW RIGID  3.5  10  $56000  $12000  $1.00 

    17T GVW 

    RIGID  11  14  $120000  $40000  $1.65 24T GVW 

    RIGID  16  14  $240000  $88000  $1.95 32T GVW 

     ARTIC/12M TRAILER 19  24  $480000  $140000  $2.70 35T GVW 

    Drawbar/2 bodies  21  28  $550000  $150000  $3.00 38T GVW 

     ARTIC/12M TRAILER  24  24  $490000  $140000  $2.30 12 METRE TRAILER  -  24  $45000  $4500  $0.50 

    DRAWBAR DEMOUNT

    BODY -  14  $25000  $2500  $0.30 

    DRAWBAR TRAILER  -  -  $15000  $2500  $0.24

    Note: Fixed cos ts exclud e people.

    Variable cos ts includ e maintenanc e.

    Pal let capacity based o n s ize of 1.0 x 1.2 x 2.5 metres.

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    16/17

      RL4 M4A:16

    IMPROVED PERFORMANCE - QUESTION (4)

      Carry out work measurement/time study in those areas of MR Ltd that you feel are

    appropriate.

      Using the cost elements given above and apply these to improve ALL operations toproduce better operational costings.

    Note: Your answer shou ld show storage costs, warehouse hand l ing cos ts for each part

    o f the ov eral l opera t ion , and transp ort costs for each custo mer.

      Draw up a budget for MR Ltd for the next year based on the current cost elements butapplied to the improved operation.

      How you present the budget is up to you but it should identify the individual costs for

    each part of the business. (Note: You do not need to consider income, as this is not

    available to you).

    FUTURE OPERATIONAL QUESTIONS (5)

    The Managing Director of Mr Ltd is looking to expand, and requires your outlinerecommendations on these possible future changes: -

    1. The effect of a two-fold volume increase.

    2. The introduction of different product types.

    3. The introduction of Europallets.

    Volumes

    Current volumes are to double.

    Product

    Introduce to same customer base the following: -

      Toxic chemicals, in plastic kegs, weighing 30 kilos each keg.  Paint in aerosols, in cartons, weighing 10 kilos each carton. (No volume

    indications available.)

  • 8/17/2019 MR 2015 Case Study Group Project 240752.pdf

    17/17

      RL4 M4A:17

    Pallets

    Possible changes to Euro-pallets (1.2 x 0.8 metres).

    [Recall the Managing Director is looking for your outline recommendations only on the

    above].

    FUTURE TASK REQUIREMENTS (6)

    Using the information to you along with any previous calculations that you have made,what are: -

     The current resource use?

     The intended resource use (i.e. after your improvements)?

    OVERALL PROJECT OUTPUTS

    1. You are required to answer ALL questions within the above sections and formulateyour responses into a professionally written and presented Group Project Report which will be submitted for assessment at the end of the Block Course.

    2. Your report must be summarised to a Powerpoint presentation that all members of

    your group will present part of to the class on the last day of the Block Course. Youwill be given a fixed time to present and will be stopped once you exceed the time.This Powerpoint will also be submitted and assessed at the end of this blockcourse.

    3. You will individually be required to submit your own assessment of the workcontributions that each of the other team members of your project team made to theoverall work effort.

    4. WORKLOAD  – you will be expected to work outside class hours to complete thisGroup Project. It is over to each group as to how much time they will allocate.Consider this project in the same manner as one you would do in the workplace.