MOY Producing gold - Millennium Minerals · MOY : Producing gold Visible mineralisation outside...

23
Millennium Minerals (MOY.ASX) 23 November 2015 MOY : Producing gold Visible mineralisation outside existing Resources Expect good success in exploration drilling Page 1 See Page 23 for Disclaimer and Disclosures 23 November 2015 Recommendation Following a write-down to its Reserves in March 2015, MOY now has 2 years of Reserves. MOY has visible mineralisation outside of its Resources and many large intercepts of high grade and ore grade material. In our base case, Beer & Co allows $10m of drilling each year, for 2.0Mt at 1.5g/t to be added to mining inventory. Our base case valuation of 14.5c/share assumes current AUD-USD rate and a gold price rising slowly to $1200/oz. MOY is highly leveraged to better exploration results as well as the AUD gold price. BUY, High Risk Price 4.6c Valuation 14.5c Commodity Gold Snapshot Market Cap $10.0m Cash on hand (31 Sept 2015) $5.05m Net Debt ($19.5m) Equity being raised $20m $21m Shares on Issue 271.7m Shares to be issued : 500m – 525m 52 Week High 7.9c 52 Week Low 2.3c 1 month / 6 month VWAP 5.0c / 5.0c MOY : daily share price v. value traded $0 $ 50,000 $ 100,000 $ 150,000 $ 200,000 $ 250,000 $ 300,000 $ 350,000 0c 5c 10c 15c 20c 25c 30c 35c 1 Oct. 2013 1 Jan. 2014 1 Apr. 2014 1 Jul. 2014 1 Oct. 2014 1 Jan. 2015 1 Apr. 2015 1 Jul. 2015 1 Oct. 2015 MOY value traded Millenium Minerals MOY began mining operations at Nullagine in September 2012. The operations were declared commercial in February 2013. While the operations generated cash, the cash generated was, for 2014 and the first half of 2015, not enough to meet the required debt repayments. The operations have been turned around, but there is further to go. Success in converting known mineralisation into mining inventory is essential, and Beer & Co expects MOY to outperform. Author : Pieter Bruinstroop [email protected] Mining Operations at Nullagine are now (out)performing MOY’s Nullagine mine has JORC Resources in 14 separate deposits across a tenement area of 264km 2 in the West Pilbara region. First gold was poured in September 2012, but not enough net cash was generated to service and pay down the $50m in project finance taken on to develop the $83m project. This was due to Unit costs being higher than expected; and AUD gold prices being lower than expected. This led to a write down in the carrying value of $76m. With the change in CEO in December 2014, mill throughput has been ramped up to about 1.9Mt/yr and has processed oxide material grading around 1.7g/t to generate strong cashflows. MOY forced to Raise Equity MOY is now able to repay its bank debt, but will not be able to generate the cash required to pay back its subordinated debt, which is now about $15m, by its due date of July 2016. With only 5Mt in Reserves at the start of 2015, MOY needs to drill known mineralisation to extend its mine life, which requires capital. Drilling WILL be successful MOY will invest $10m annually to increase its mining inventory. Beer & Co expects to add at least 2.0Mt each year, grading 1.5g/t, which is a discovery cost of over $120/oz, which is a high cost given there are significant areas of visible mineralisation. Beer & Co risked valuation 14.5c/share Given our expected exploration success, and a gold price of $1,200/oz, at an AUDUSD rate of 0.700, Beer & Co generates a risked value of 14.5c/share. Beer & Co conclusions Drilling success is expected, and necessary. BUY, High Risk. This report was produced by Beer & Co Research, an independent research and advisory firm. It is intended for wholesale investors ONLY. If you do not wish to receive our research, please email to [email protected] with “unsubscribe” If you wish to receive, free of charge, Beer & Co research, please register at http://beerandco.com.au/allresearch/

Transcript of MOY Producing gold - Millennium Minerals · MOY : Producing gold Visible mineralisation outside...

 

Millennium Minerals (MOY.ASX)  23 November 2015

MOY : Producing goldVisible mineralisation outside existing Resources 

Expect good success in exploration drilling 

Page 1  See Page 23 for Disclaimer and Disclosures  23 November 2015  

Recommendation  ■ Following a write-down to its Reserves in March 2015, MOY now has 2 years of Reserves.

■ MOY has visible mineralisation outside of its Resources and many large intercepts of high grade and ore grade material. In our base case, Beer & Co allows $10m of drilling each year, for 2.0Mt at 1.5g/t to be added to mining inventory.

■ Our base case valuation of 14.5c/share assumes current AUD-USD rate and a gold price rising slowly to $1200/oz.

■ MOY is highly leveraged to better exploration results as well as the AUD gold price.

BUY, High Risk 

Price 

4.6c 

Valuation 

14.5c 

Commodity 

Gold 

 

Snapshot Market Cap  $10.0m 

Cash on hand (31 Sept 2015)  $5.05m 

Net Debt  ($19.5m) 

Equity being raised                              $20m ‐ $21m 

Shares on Issue  271.7m 

Shares to be issued :                          500m – 525m 

52 Week High  7.9c 

52 Week Low  2.3c 

1 month / 6 month VWAP                      5.0c / 5.0c  

MOY : daily share price v. value traded 

$ 0

$ 50,000

$ 100,000

$ 150,000

$ 200,000

$ 250,000

$ 300,000

$ 350,000

0c

5c

10c

15c

20c

25c

30c

35c

1 Oct. 2013 1 Jan. 2014 1 Apr. 2014 1 Jul. 2014 1 Oct. 2014 1 Jan. 2015 1 Apr. 2015 1 Jul. 2015 1 Oct. 2015

  MOY value traded

  Millenium Minerals

  

MOY began mining operations at Nullagine in September 2012.  The operations were declared commercial in February 2013. 

While the operations generated cash, the cash generated was, for 2014 and the first half of 2015, not enough to meet the required debt repayments.   

The operations have been turned around, but there is further to go.   

Success in converting known mineralisation into mining inventory is essential, and Beer & Co expects MOY to out‐perform.   

Author : Pieter Bruinstroop [email protected] 

 

Mining Operations at Nullagine are now (out‐)performing 

MOY’s Nullagine mine has JORC Resources in 14 separate deposits across a tenement area of 264km2 in the West Pilbara region.  First gold was poured in September 2012, but not enough net cash was generated to service and pay down the $50m in project finance taken on to develop the $83m project.  This was due to  

Unit costs being higher than expected; and 

AUD gold prices being lower than expected.   

This led to a write down in the carrying value of $76m.   

With the change in CEO in December 2014, mill throughput has been ramped up to about 1.9Mt/yr and has processed oxide material grading around 1.7g/t to generate strong cashflows.   

MOY forced to Raise Equity 

MOY is now able to repay its bank debt, but will not be able to generate the cash required to pay back its subordinated debt, which is now about $15m, by its due date of July 2016.   

With only 5Mt in Reserves at the start of 2015, MOY needs to drill known mineralisation to extend its mine life, which requires capital.   

Drilling WILL be successful 

MOY will invest $10m annually to increase its mining inventory.  Beer & Co expects to add at least 2.0Mt each year, grading 1.5g/t, which is a discovery cost of over $120/oz, which is a high cost given there are significant areas of visible mineralisation.   

Beer & Co risked valuation 14.5c/share 

Given our expected exploration success, and a gold price of $1,200/oz, at an AUD‐USD rate of 0.700, Beer & Co generates a risked value of 14.5c/share.   

Beer & Co conclusions 

Drilling success is expected, and necessary.  BUY, High Risk.  

This report was produced by Beer & Co Research, an independent research and advisory firm. It is intended for wholesale investors ONLY. 

If you do not wish to receive our research, please email to [email protected] with “unsubscribe” If you wish to receive, free of charge, Beer & Co research, please register at http://beerandco.com.au/all‐research/

Millennium Minerals (MOY.ASX) 

 

Page 2  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

 

 Millennium Minerals  

,  

  Nullagine Gold Mine  

 

 

MOY operates a gold mine at Nullagine in the West Pilbara region of WA.   

 

 

 

 

 

 

 

 

 

 

 

First gold was poured in September 2012.   

 

Millennium Minerals operates a gold mine in the Pilbara region of WA, as shown in Figure 1.   

MOY has a tenement area of 264km2, with some in Mining Licences and the rest in Exploration Leases.  

MOY announced the results of its feasibility study in October 2009.  The expected capital cost was $87m.   

MOY then proceeded to finance the project, including $50m in project finance plus an $8m lease finance facility.   

The operations were brought into production in September 2012 with first gold poured on 30 September, 2012.   

  Figure 1 : Nullagine Gold operations 

Source : MOY presentation, November 2015 

 

 

 

 

Figure 2 shows that MOY has progressively increased its gold production.   

It shows that during 2014, the production was roughly in line with the projections in the October 2009 feasibility study. 

 

 

 

 

 

During 2013 and 2014, gold produced was in line with that projected in the feasibility study 

 

  Figure 2 : Gold produced, and expected production   

10,000 oz

12,500 oz

15,000 oz

17,500 oz

20,000 oz

22,500 oz

25,000 oz

27,500 oz

Dec. 12 Jun. 13 Dec. 13 Jun. 14 Dec. 14 Jun. 15 Dec. 15 Jun. 16 Dec. 16 Jun. 17 Dec. 17 Jun. 18 Dec. 18

     Actual gold produced

     Expected gold produced

      Feasibility Study

Source : MOY quarterly reports, Beer & Co estimates  

  However, as shown in Figure 3, the costs of production were only a small premium to the gold price in the period to December 2014.  Note that the All In costs in Figure 3 exclude the costs of servicing the debt, including the repayment of principal, taken on to finance the development of the project, which is about $300/oz.   

 

Millennium Minerals (MOY.ASX) 

 

Page 3  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

However, not enough cash was generated to service and repay the $50m in project finance taken on to construct the project 

 

 

 

Some of this shortfall was due to lower than expected AUD gold prices, but also due to higher costs 

  Figure 3 : Costs of production v. gold price, actual v expected   

$A 800/oz

$A 900/oz

$A 1,000/oz

$A 1,100/oz

$A 1,200/oz

$A 1,300/oz

$A 1,400/oz

$A 1,500/oz

$A 1,600/oz

$A 1,700/oz

$A 1,800/oz

Dec. 12 Jun. 13 Dec. 13 Jun. 14 Dec. 14 Jun. 15 Dec. 15 Jun. 16 Dec. 16 Jun. 17 Dec. 17 Jun. 18 Dec. 18

    A I S C  ‐  actual     A I S C  ‐  expected

    A I S C  ‐  feasibility    gold price ‐ actual

    gold price ‐ expected     gold price ‐ feasibility

Source : MOY quarterly reports, Beer & Co estimates  

 

 

 

Due to the shortfall in cash, MOY : 

Took on 2 tranches, totalling $12m, in subordinated debt; 

Sold a project nearby for $3.8m;  

Wrote down the asset value by $76m, leaving only 2 years of reserves; and 

Changed the CEO 

 

 

 

 

Since the change in CEO, gold production has increased 

MOY Response to (under‐)Performance 

Looking at the period to December 2014, and bearing in mind the additional cost for debt servicing, shows that MOY came under significant financial distress.  The first response, on 31 December 2013, was to defer some of the principal on the loans due to be paid to the senior debt providers.  This was followed by  

Taking on $7m in subordinated debt, from the major shareholder, IMC Resources on 19 March 2014; 

Extending the term of the senior debt from September 2015 to June 2016; 

The MD announcing his intention to resign on 27 August 2014 and a new CEO being appointed on 18 December 2014; 

An extra $5m in subordinated debt announced on 23 December 2014;  

Selling their interest in the Beatons Creek JV, for $3.8m, on 27 March 2015; 

Announcing an asset impairment charge of $76m (compared with the original construction cost of $83m), together with a write‐down in Reserves to leave a mine life of just over 2 years, on 27 March 2015 

Figure 2 shows that following the change in CEO, there was a significant increase in the amount of gold produced, while Figure 3 shows that this was accompanied by a significant fall in the cost of gold produced.   

Figure 4 shows that the first action was to increase mill throughput.  

 

Particularly due to an increase in the mill throughput rate 

 

 

And higher yielding ore 

 

 

  Figure 4 : Ore treated,. Actual v projected   

300 kt

325 kt

350 kt

375 kt

400 kt

425 kt

450 kt

475 kt

500 kt

Dec. 12 Jun. 13 Dec. 13 Jun. 14 Dec. 14 Jun. 15 Dec. 15 Jun. 16 Dec. 16 Jun. 17 Dec. 17

    Actual Ore Treated

    Expected Ore Treated

    Nominal Mill capacity

Source : MOY quarterly reports, Beer & Co estimates 

Millennium Minerals (MOY.ASX) 

 

Page 4  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

 

 

 

 

While MOY is able to repay the senior debt, it needs to raise equity to repay the sub‐debt by the time it is due 

 

 

 

 

 

 

MOY needs to drill to extend its mine life, as it has reserves only until about mid 2017.   

 

As well as increased throughput, other actions included a much tighter review of costs and review of the mine plan to focus on total net benefit to MOY.   

Refinancing 

The subordinated debt that had been taken on so that commitments to the senior lenders could be met, as the sub‐debt :  

Had a high interest rate, as expected from subordinated debt, including the issue of options with an exercise price linked to any future raising; and 

Had a term to 30 days after the expiry of the senior debt.   

While MOY has generated enough cash to repay the senior debt, Beer & Co calculate that it would not be able to generate the roughly $15m, including accumulated interest, in total required to be re‐paid by July 2016.   

Also, part of the cost cutting to survive was to cease exploration and with only 2 years of reserves, money is needed to develop the mining inventory.   

This has led to the raising of $20m ‐ $21m in new equity.   

Expected Exploration Success 

Figure 4 shows that Beer & Co expects that MOY will process about 1.9Mt/yr of ore for many years.   

 

 

 

MOY will invest $10m in drilling to increase its mining inventory 

 

However, Figure 5 shows that MOY has Reserves that will last only until about July 2017.  

MOY have stated that the company will invest $10m a year in drilling to increase mine life.   

  Figure 5 : Nullagine Reserves, Dec. 2014 

Proved 3.68 Mt 1.5 g/t 174 koz

Probable 0.64 Mt 1.5 g/t 30 koz

Stockpiles 0.64 Mt 0.9 g/t 19 koz

TOTAL 4.97 Mt 1.40 g/t 223 koz

Source : MOY ASX announcement, 27 March 2015 plus 25 September 2015, Beer & Co.   

 

  As a base case, Beer & Co expects that MOY will add at least 2.0Mt to mining inventory, at a grade of about 1.5g/t, as shown by Figure 6.   

 

 

 

 

 

Beer & Co’s analysis assumes that MOY is able to add 2.0Mt a year to its mining inventory at a grade that is around the Reserve grade, despite history showing higher grading ore.   

 

  Figure 6 : Actual grade of ore processed v. expected v. Reserves   

1.00 g/t

1.20 g/t

1.40 g/t

1.60 g/t

1.80 g/t

2.00 g/t

Dec. 12 Jun. 13 Dec. 13 Jun. 14 Dec. 14 Jun. 15 Dec. 15 Jun. 16 Dec. 16 Jun. 17 Dec. 17 Jun. 18 Dec. 18 Jun. 19 Dec. 19

    Actual gold grade

    Expected gold grade

    Reserve grade

Source : MOY ASX quarterly announcements,  Reserve statements, Beer & Co estimates  

  Figure 6 shows that while MOY has focussed recent operations on higher grades, Beer & Co is not basing its analysis on a continuation of this trend.   

Millennium Minerals (MOY.ASX) 

 

Page 5  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Figure 6 shows that Beer & Co mine plan assumes that Reserves, on a deposit by deposit basis, are mined before new discoveries.  However, we expect that MOY will be smarter than this.   

Figure 7 shows that MOY has delineated Resources at 14 deposits and has a further 15 prospects for drilling, each of which has evidence of gold.   

 

 

At Nullagine, MOY has delineated Resources at 14 separate deposits and has a further 15 prospects that have some evidence of mineralisation.   

 

 

 

Mineralisation is found immediately north of the Middle Creek fault, and along splays of this fault 

 

 

  Figure 7 : Mineralised areas at Nullagine 

Source : MOY ASX announcement, 23 November 2015  

 

 

Historical drilling has already shown large intercepts at ore grades and higher 

 

 

Figure 7 also shows that the gold is located to the immediate north of the Middle Creek fault and also along splays off this fault, to the north.   

Figure 8 shows Infill potential at Otways, plus extension to the east, and extensions to both north and south of Shearers with historical results to the south of Shearers including : 

5m at 7.51g/t; 

20m at 2.09g/t; and 

21m at 1.31g/t.  

 

 

 

 

MOY has delineated extensions to existing operations 

 

 

  Figure 8 : Shearers – Otways deposits plus drilling   

Source : MOY ASX announcement, 23 November 2015 

Millennium Minerals (MOY.ASX) 

 

Page 6  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Recently announced results from drilling to the south of Shearers include :  

11m at 4.16g/t, from 40m; and 

7m at 3.83g/t, form 15m and 

13m at 1.33g/t from surface.   

Figure 9 shows that mineralisation extends beyond the ore reserve, with ore grade results in 2 lodes.   

 

 

 

Known mineralisation extends beyond the bounds of the present reserves 

 

 

  Figure 9 : Extensions at Shearers   

Source : MOY ASX announcement, 23 November 2015  

 

Outcomes 

Figure 10 shows the actual outcomes from MOY’s operations, and Beer & Co’s projections.   

 

Figure 10 : Actual and projected operational outcomes 

2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Waste moved 6,779 kt 8,778 kt 8,763 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 2,029 kt

waste : ore 4.2  : 1 5.5  : 1 4.8  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1

Ore Mined 1,615 kt 1,583 kt 1,840 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 451 kt

Gold head grade 1.56 g/t 1.66 g/t 1.68 g/t 1.41 g/t 1.47 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.16 g/t

Recovery 88.2 % 87.1 % 90.9 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 %

Gold produced 63,247 oz 74,375 oz 88,631 oz 79,231 oz 82,534 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 37,473 oz

Source : Beer & Co estimates  

Beer & Co projects continuing production of around 85koz a year, slightly below guidance for 2015 

Figure 10 shows that Beer & Co’s projections effectively capitalise the turn‐around that has already taken place in the operational performance at Nullagine, with 

Mill operations continuing at 1.9Mt/yr, even though the most recent quarter was at a higher rate, as shown in Figure 4; 

Ore grade being slightly below the historical average, especially in the next 2 years; and 

Recovery of gold in ore at 92%, despite MOY’s September quarterly stating that recoveries were at 93%. 

Figure 11 shows Beer & Co’s base case commodity price assumptions and projected financial outcomes.   

Millennium Minerals (MOY.ASX) 

 

Page 7  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

Figure 11 : Beer & Co’s base case projected financial outcomes, Nullagine Mining 

AUD m 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

AUD/USD 0.968 0.903 0.747 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700

Gold $ 1,411/oz $ 1,272/oz $ 1,149/oz $ 1,163/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz

Revenue 92.4 106.9 136.9 131.7 141.5 144.5 144.5 144.5 144.5 144.5 144.5 144.5 64.2

Cash Costs (60.9) (70.8) (84.0) (79.0) (82.8) (76.4) (77.1) (77.9) (78.7) (79.5) (80.2) (82.5) (28.9)

Royalties (2.7) (3.1) (4.0) (5.9) (5.4) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (1.9)

Dep'cn & Amort'sn (22.0) (27.2) (22.5) (20.0) (22.5) (15.7) (13.8) (13.2) (13.0) (13.0) (12.9) (14.8) (4.5)

E B I T 6.8 5.8 26.4 26.8 30.8 48.3 49.4 49.2 48.6 47.9 47.2 43.0 29.0

Sus Cap Ex ‐ driling 0.0 0.0 0.0 (10.0) (10.0) (10.0) (10.0) (10.0) (10.0) (10.0) (10.0) (5.0) 0.0

Sus Cap Ex ‐ other (3.1) (3.0) (3.5) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (0.9)

Project Cashflow, p 25.8 30.0 45.4 33.1 39.6 50.4 49.6 48.8 48.0 47.3 46.5 49.2 32.6

Source : MOY reports, Beer & Co estimates  

  Figure 11 shows that Beer & Co projects that MOY invests $10m in drilling each year, for 8.5 years, with the final 12 months is unsuccessful, so the low grade stockpiles are processed.   

MOY Valuation 

Figure 12 shows the detail of Beer & Co’s base case valuation of MOY, which is 14.5c/share.   

 

 

 

Beer & Co’s risked, base case valuation is 14.5c/share 

 

 

  Figure 12: Beer & Co’s base case valuation of MOY   

23‐Nov‐15

risk :  100% Product per share

Nullagine Reserves 100% $ 82m $ 82m 10.8 c 6.6 c

franking credits 60% $ 7m $ 4m 0.5 c 0.6 c

Nullagine Extension 80% $ 141m $ 113m 14.9 c 16.5 c

franking credits 48% $ 33m $ 16m 2.1 c 2.3 c

Exploration 90% ($ 46m) ($ 41m) (5.5c) (6.0c)

Hedge  100% ($ 8m) ($ 8m) (1.0c) (0.6c)

Corporate 100% ($ 30m) ($ 30m) (3.9c) (3.7c)

Cash / Debt 100% ($ 36m) ($ 36m) (4.7c) (1.3c)

Equity raisings 100% $ 19m $ 19m 2.5 c 0.3 c

TOTAL $ 163m $ 119m 15.7 c 14.6 c

Shares on issue 217.7m F P O shares 18.0m Options

525.0m issued 2015 16.0m Ops. Ex'd

discount rate =    12.0 % 31 December 2014

 Source : Beer & Co estimates 

 

  Figure 12 shows that while Beer & Co is confident of exploration success, we have still discounted the success for risk, while the investment has a lower risk weighting, despite our assumption that the last 12 months has zero success.   

 

 

Sensitivity Analyses  

 

Sensitivity analysis suggests that the current MOY share price factors in some exploration success  and current commodity prices 

Beer & Co’s base case valuation is a precise answer to a large number of assumptions, each of which is subject to a degree of error.   

  Figure 13 : Commodity prices 

USD / oz $ 1,100/oz $ 1,200/oz $ 1,250/oz $ 1,300/oz

AUD‐USD = 0.700 $A 1,571/oz $A 1,714/oz $A 1,786/oz $A 1,857/oz

Reserves 3.0 c 4.2 c 4.4 c 4.7 c

Exploration 6.0 c 10.4 c 12.6 c 14.6 c

TOTAL 9.0 c 14.6 c 17.0 c 19.3 c

Source : Beer & Co estimates 

Millennium Minerals (MOY.ASX) 

 

Page 8  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

 

 

 

Beer & Co’s valuation is very sensitive to being able to add 2.0Mt/yr to the mining inventory 

Figure 13 attempts to break the valuation up between existing Reserves and Beer & Co’s expected exploration success.  It shows that the current share price : 

Assumes some exploration success; and 

Reflects current commodity prices.   

The other key variables are the degree of exploration success.  Figure 14 shows that a positive view on investment in MOY requires success in finding 2.0Mt/yr of mining inventory.   

 

 

 

Grade is also important 

 

Figure 14a : Exploration Success     Figure 14b : Exploration Success  

Gold price :  $A 1,714/oz Years :  7.5 years

Tonnes by Grade 1.30 g/t 1.50 g/t 1.70 g/t

1.5 Mt/yr (1.0c) 0.4 c 2.2 c

2.0 Mt/yr 8.9 c 14.6 c 21.3 c

2.5 Mt/yr 10.2 c 16.7 c 24.3 c

Gold price :  $A 1,571/oz Years :  7.5 years

Tonnes by Grade 1.30 g/t 1.50 g/t 1.70 g/t

1.5 Mt/yr (5.3c) (3.9c) (2.3c)

2.0 Mt/yr 3.8 c 9.0 c 15.2 c

2.5 Mt/yr 4.6 c 10.6 c 17.5 c

Source : Beer & Co estimates  Source : Beer & Co estimates  

 

 

 

 

 

 

 

 

 

 

MOY is raising equity at 4c/share.   

 

 

Beer & Co’s risked valuation is 14.5c/share 

 

Our valuation is sensitive to commodity prices, volume and grade of exploration success 

 

We believe that we have been conservative in our base case for exploration success, which is $121/oz, which is a high cost 

 

 

Beer & Co has a BUY, High Risk recommendation on MOY 

Figure 14b shows that at current commodity prices, of $1100/oz gold and AUD‐USD rate of 0.700 , MOY gains significant benefit from either or both of higher grade and higher volume of exploration success.   

Beer & Co’s analysis showed muted sensitivity to the number of years of expected exploration success. 

Conclusions 

MOY’s operations at Nullagine produced first gold in September 2012.  From then until the most recent quarter, MOY failed to generate sufficient cash to service and repay the $58m in debt it had taken on to develop the $83m project.   

This had been due to a range of operational issues.   

For the September quarter, a strong cashflow was generated by running the operations well, with higher throughput, better recoveries, lower costs and focus on ore with a better net return.   

MOY is raising equity to repay the subordinated debt it had taken on to service the senior debt, as the sub‐debt must be repaid quickly.   

With this raising, MOY will be generating good cash.   

Beer & Co’s base case valuation is based on : 

The gold price rising slowly to $1200/oz, which is lower than the average of 2014, while the AUD‐USD rate stays level, when most expect it to fall; 

An investment of $10m/yr in exploration for 8½ years, yielding 2.0Mt each year of material grading 1.5g/t, which is less than the grade or ore treated to date, for the first 7 ½ years before generating nothing in the final year.  

The exploration cost is $121/oz, which is high, especially for an area that is as prospective as Nullagine.   

Our valuation is quite sensitive to the volume of exploration success, but we feel that MOY is likely to be more successful than we have projected.   

Our valuation shows that MOY is fair value at current commodity prices and our projected, very modest, exploration success.   

Beer & Co initiates research on MOY with a BUY, High Risk, recommendation.   

Millennium Minerals (MOY.ASX) 

 

Page 9  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

 Millennium Minerals - History 

 

 October 2009 Feasibility Study 

Figure 15 shows the tenement area held by MOY in late 2009.    

    Figure 15 : MOY tenements at Nullagine   

 Source : MOY ASX announcement, 17 October 2009 

 

  At that time, MOY reported a total of 1.1Moz of gold contained in 28.1Mt of Resources, as shown in Figure 16, over 6 different deposits. 

 

  Figure 16 : MOY Resources, October 2009, 28Mt for 1.1Moz gold 

Deposit

Golden Eagle 11.43 Mt 1.26 g/t 465 koz 4.60 Mt 1.02 g/t 151 koz 4.04 Mt 1.00 g/t 130 koz 20.07 Mt 1.16 g/t 749 koz

Bartons 1.33 Mt 1.47 g/t 63 koz 0.85 Mt 1.48 g/t 41 koz 0.37 Mt 1.70 g/t 20 koz 2.55 Mt 1.52 g/t 125 koz

Shearers 0.59 Mt 1.09 g/t 21 koz 1.04 Mt 0.87 g/t 29 koz 0.40 Mt 0.90 g/t 12 koz 2.03 Mt 0.93 g/t 61 koz

All Nations 1.11 Mt 1.30 g/t 46 koz 0.19 Mt 1.04 g/t 6 koz 0.14 Mt 1.10 g/t 5 koz 1.44 Mt 1.25 g/t 58 koz

Little Wonder 0.44 Mt 1.13 g/t 16 koz 0.40 Mt 1.2 g/t 16 koz 0.85 Mt 1.17 g/t 31.8 koz

Golden Gate (ABCD Reef) 0.58 Mt 3.24 g/t 60 koz 0.11 Mt 2.6 g/t 9 koz 0.68 Mt 3.12 g/t 69 koz

Golden Gate Satellites 0.33 Mt 3.0 g/t 32 koz 0.13 Mt 3.4 g/t 14 koz 0.46 Mt 3.07 g/t 45 koz

TOTAL 14.46 Mt 1.28 g/t 595 koz 8.03 Mt 1.30 g/t 335 koz 5.59 Mt 1.14 g/t 206 koz 28.09 Mt 1.26 g/t 1,138 koz

    Measured Resources          Indicated Resources          Inferred Resources                TOTAL           

Source : MOY ASX announcement, 17 October 2009  

  As shown in Figure 17, MOY had reserves of 7.97Mt grading 1.8g/t for 463koz of contained gold.   

 

    Figure 17 : MOY tenements at Nullagine   Deposit

Golden Eagle 5.15 Mt 1.6 g/t 272.5 koz 0.58 Mt 1.5 g/t 28.3 koz 5.73 Mt 1.6 g/t 300.7 koz

Bartons 0.66 Mt 1.8 g/t 39.2 koz 0.31 Mt 1.9 g/t 19.6 koz 0.98 Mt 1.9 g/t 58.8 koz

All Nations 0.31 Mt 1.8 g/t 18.6 koz 0.02 Mt 1.6 g/t 1.1 koz 0.33 Mt 1.8 g/t 19.7 koz

Shearers 0.17 Mt 1.7 g/t 9.3 koz 0.20 Mt 1.3 g/t 8.2 koz 0.37 Mt 1.5 g/t 17.5 koz

Golden Gate 0.31 Mt 3.7 g/t 37.6 koz 0.07 Mt 3.9 g/t 8.3 koz 0.38 Mt 3.8 g/t 45.9 koz

Golden Gate Area 0.19 Mt 3.4 g/t 20.6 koz 0.19 Mt 3.4 g/t 20.6 koz

TOTAL 6.61 Mt 1.77 g/t 377 koz 1.37 Mt 1.96 g/t 86 koz 7.98 Mt 1.81 g/t 463 koz

    Proven Reserves          Probable Reserves                TOTAL           

Source : MOY ASX announcement, 17 October 2009  

Millennium Minerals (MOY.ASX) 

 

Page 10  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  The initial plan was for  

a 7 year mine life,  

processing 1.25Mt/yr of ore for the first four years, and then 1.0Mt/yr, at  

C1 cost of USD 594/oz from  

AUD 17/t of ore mined, at a rate of 3.45t of waste per tonne of ore; 

AUD 18/t of ore milled; and 

AUD 3/t of ore for other costs 

Expected capital cost was AUD 78m.   

Finance was arranged, including AUD 50m in project finance, that was due to be re‐paid by June 2015, plus AUD 8m in facilities finance.   

Early Operations 

Construction was completed on time and in line with the revised budget and first gold was poured in September 2012 and operations were declared commercial in February 2013.   

As shown in Figure 18, production was roughly in line with the projected in the feasibility study.   

 

  Figure 18 : Actual v expected production.   

10,000 oz

12,500 oz

15,000 oz

17,500 oz

20,000 oz

22,500 oz

Dec. 12 Jun. 13 Dec. 13 Jun. 14 Dec. 14

     Actual gold produced       Feasibility Study

 Source : MOY Quarterly reports, 17 October 2009 ASX announcement, Beer & Co 

 

  However, as shown in Figure 19, while the realised gold price was higher than the expected gold price, the realised C1 costs were much higher than the expected C1 costs of USD 594/oz or AUD 711/oz (the AUD‐USD rate rose during 2009 from 0.65 in March to 0.88 by the end of September) 

 

    Figure 19 :Costs v Actual and Expected AUD gold price 

$A 600/oz

$A 700/oz

$A 800/oz

$A 900/oz

$A 1,000/oz

$A 1,100/oz

$A 1,200/oz

$A 1,300/oz

$A 1,400/oz

$A 1,500/oz

$A 1,600/oz

$A 1,700/oz

Dec. 12 Mar. 13 Jun. 13 Sep. 13 Dec. 13 Mar. 14 Jun. 14 Sep. 14 Dec. 14

     Realised, actual C1 cost      Feasibility Study C1 cost

     Realised gold price      Feasibility Study gold price

 

Source : MOY Quarterly reports, 17 October 2009 ASX announcement, Beer & Co 

Millennium Minerals (MOY.ASX) 

 

Page 11  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  A number of factors contributed to the higher than expected costs, including :  

Higher costs in the sector generally as demand for resources boomed 

A more significant impact than the cost was the fall in the average quality of the resources that were able to be secured, across all categories 

Poorer recoveries as it was found that some material in the Golden Eagle pit, which was the dominant source of ore supply, was refractory and not able to be recovered in the CIL circuit; 

Flooding in early 2014 which meant that supplies, especially diesel fuel, could not be trucked to site so low grade stocks, which did not require mining, were treated; and 

Some delays in permitting in early 2014, which delayed the opening of new, higher grade, pits.  

Not enough cash was being generated to adequately service and repay the senior debt, as evidenced by : 

Taking on $7m in subordinated debt, from the major shareholder, IMC Resources on 19 March 2014; 

Extending the term of the senior debt from September 2015 to June 2016; 

The MD announcing his intention to resign on 27 August 2014 and a new CEO being appointed on 18 December 2014; 

An extra $5m in subordinated debt announced on 23 December 2014;  

MOY selling its interest in the Beatons Creek JV, for $3.8m, on 27 March 2015.   

Write Down by $76m 

On 27 March 2015, MOY announced that its reserves at Nullagine had been written down by nearly 60%, due to a combination of : 

Mining depletion; 

Issues with recoveries from refractory ores; and 

A slightly lower AUD gold price, from AUD 1500/oz to AUD 1400/oz.   

The impact of this revision is shown in Figure 20.    

  Figure 20 : Revision to Reserves 

Change 

Proved 6.95 Mt 1.6 g/t 374.6 koz 2.99 Mt 1.5 g/t 143.3 koz (61%)

Probable 1.28 Mt 1.9 g/t 78.4 koz 0.54 Mt 1.5 g/t 25.5 koz (67%)

Stockpiles 0.45 Mt 0.8 g/t 11.4 koz 0.64 Mt 0.9 g/t 19.0 koz 66 %

TOTAL 8.7 Mt 1.66 g/t 464 koz 4.16 Mt 1.40 g/t 188 koz (59%)

       10 March 2014                   27 March 2015          

Source : MOY ASX announcement, 27 March 2015, Beer & Co  

  The reduction in gold reserves also caused a reduction in mine life, down to just over 2 years.  This caused a write down of the asset value of $76m, and a diminution in the carrying value of tax loss asset of $12m.   

This write down was despite the operations performing in line with the projections in the feasibility study for most parameters.   

Arguably the operations did not under‐perform, but instead failed to respond to cost, price and corporate circumstances.   

Millennium Minerals (MOY.ASX) 

 

Page 12  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  The Response  

  New CEO and Operations 

On 27 August 2014, MOY announced that the MD would be resigning.   

The new CEO formally began in the role on 18 December 2014 and changes in operational performance followed : 

Figure 21 shows that the volume of milled increased; 

Figure 22 shows that the average grade rose; while 

Figure 23 shows that the recovery of gold in ore improved.   

    Figure 21 : Change in mill throughput   

 

Source : MOY quarterly reports, Beer & Co 

 

    Figure 22 : Change in average grade of ore milled   

 Source : MOY quarterly reports, Beer & Co 

 

    Figure 23 : Change in recovery of gold in ore milled   

 Source : MOY quarterly reports, Beer & Co 

Millennium Minerals (MOY.ASX) 

 

Page 13  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  As a result of improved tonnes, grade and recovery, gold output has risen, as shown in Figure 24.   

 

    Figure 24 : Change in gold produced   

 Source : MOY quarterly reports, Beer & Co 

 

  Figure 24 shows the end result of a lot of work, including :  

Restructuring company and site management; 

Reducing total personnel, and moving some positions from site to Perth, to eliminate the Fly‐In – Fly‐Out cost, so that only those who need to be on‐site incur the expense of being there; 

Reducing costs by optimising and re‐negotiating contracts; 

Improving understanding of geological complexities;  

Optimising mining practices, including mine fleet efficiencies; and 

Optimising process flow.   

 

Finance 

As well as selling their interest in the Beatons Creek JV, which is the highlighted area in Figure 15 to the immediate north of the Nullagine township, for $3.8m, MOY took on a total of $12m of subordinated debt so that commitments to the senior lenders could be met.  This sub‐debt  : 

Had a high interest rate, as expected from subordinated debt, including the issue of options with an exercise price linked to any future raising; and 

Had a term to 30 days after the expiry of the senior debt.   

While MOY has generated enough cash to repay the senior debt, Beer & Co estimate that it would not be able to generate the $15m in total required to be re‐paid by July 2016.   

Also, part of the cost cutting to survive was to cease exploration and with only 2 years of reserves, investment is required to develop the mining inventory.   

This has led to the raising of $20m ‐ $21m in new equity.   

This equity raising is only able to be undertaken as the operations have been turned around and are now generating sufficient cash to give investors confidence.   

When this raising has been completed, MOY will be effectively debt free and able to properly develop its potential.  

Millennium Minerals (MOY.ASX) 

 

Page 14  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Expected Exploration Success  

 Resources and Reserves 

Figure 25 shows MOY’s 246km2 of tenements near Nullagine, showing 14 deposits with defined resources and a further 15 prospects with known mineralisation.   

It also indicates the distance that ore needs to be transported from it mine to the processing plant in the south‐west corner of the tenement area, adjacent to the Golden Eagle mine.  The present maximum distance is nearly 50km, though most of this is on existing (council) roads and haul roads.   

 

    Figure 25 : MOY’s Nullagine tenements, over 246km2   

 Source : MOY ASX announcement, 25 September 2015 

 

  Figure 26 : Detail of MOY’s Mineral Resources Estimate for Nullagine 

Deposit

Golden Eagle 10.56 Mt 0.9 g/t 310 koz 4.37 Mt 0.9 g/t 128 koz 4.29 Mt 0.9 g/t 126 koz 19.22 Mt 0.9 g/t 564 koz

Bartons 1.72 Mt 1.2 g/t 66 koz 1.44 Mt 1.2 g/t 56 koz 0.55 Mt 1.1 g/t 19 koz 3.71 Mt 1.2 g/t 141 koz

Shearers 0.59 Mt 1.3 g/t 25 koz 1.48 Mt 1.0 g/t 48 koz 0.26 Mt 1.0 g/t 8 koz 2.33 Mt 1.1 g/t 81 koz

Otways 1.15 Mt 0.8 g/t 29 koz 0.90 Mt 0.9 g/t 26 koz 0.69 Mt 0.9 g/t 20 koz 2.74 Mt 0.9 g/t 75 koz

All Nations 1.26 Mt 1.4 g/t 57 koz 0.55 Mt 1.1 g/t 19 koz 0.42 Mt 1.0 g/t 14 koz 2.23 Mt 1.3 g/t 90 koz

Little Wonder 0.47 Mt 1.4 g/t 21 koz 0.25 Mt 1.4 g/t 11 koz 0.22 Mt 1.7 g/t 12 koz 0.94 Mt 1.4 g/t 43.7 koz

Golden Gate 0.19 Mt 3.0 g/t 18 koz 0.14 Mt 2.9 g/t 13 koz 0.14 Mt 2.4 g/t 11 koz 0.47 Mt 2.8 g/t 42 koz

Falcon 0.00 Mt 0.0 g/t 0 koz 0.09 Mt 3.9 g/t 12 koz 0.04 Mt 4.4 g/t 6 koz 0.14 Mt 4.0 g/t 18 koz

Condor 0.15 Mt 2.6 g/t 12 koz 0.04 Mt 2.8 g/t 4 koz 0.03 Mt 3.7 g/t 4 koz 0.22 Mt 2.7 g/t 19 koz

Harrier 0.00 Mt 0.0 g/t 0 koz 0.10 Mt 1.7 g/t 6 koz 0.04 Mt 1.8 g/t 2 koz 0.14 Mt 1.8 g/t 8 koz

Crow 0.04 Mt 3.1 g/t 4 koz 0.04 Mt 2.6 g/t 3 koz 0.05 Mt 2.3 g/t 4 koz 0.12 Mt 2.7 g/t 10.5 koz

G_Reef 0.00 Mt 0.0 g/t 0 koz 0.02 Mt 4.0 g/t 3 koz 0.02 Mt 3.9 g/t 3 koz 0.04 Mt 4.0 g/t 5 koz

Au 81 0.35 Mt 1.6 g/t 18 koz 0.34 Mt 1.2 g/t 13 koz 0.90 Mt 0.9 g/t 26 koz 1.59 Mt 1.1 g/t 57 koz

Camel Ck 1.25 Mt 1.3 g/t 52 koz 0.73 Mt 1.2 g/t 28 koz 0.71 Mt 1.1 g/t 25 koz 2.68 Mt 1.2 g/t 105 koz

TOTAL 17.72 Mt 1.1 g/t 612 koz 10.49 Mt 1.1 g/t 369 koz 8.35 Mt 1.0 g/t 278 koz 36.57 Mt 1.1 g/t 1,259 koz

     Measured Resources          Indicated Resources          Inferred Resources                TOTAL           

Source : MOY ASX announcement, 27 March 2015 plus 25 September 2015, Beer & Co.    

  Figure 26 shows the detail of MOY’s Resource estimate.  It modifies the detail in the 27 March 2015 announcement by the subsequent 25 September announcement that MOY had moved to 100% of the Camel Creek JV, the areas of which are shown in blue in Figure 25, in exchange for royalties, payable to the vendors, of  

6.44% on the first 20,000 ounces of gold produced from these tenements; and 

1.5% on the value of all other minerals produced from these tenements.   

Figure 26 shows 1.26Moz in Resources.   

Millennium Minerals (MOY.ASX) 

 

Page 15  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Figure 27 shows the detail of MOY’s Reserves, as at 31 December 2014, adjusted for MOY’s 100% ownership of the Camel Creek JV.   

This shows just about 28 months of high grade and about 4 further months using low grade stockpiles, from January 2015, or to 2017 Q3. 

 

  Figure 27 : Detail of MOY’s Ore Reserves Estimate for Nullagine Deposit

Golden Eagle 1.10 Mt 1.5 g/t 54 koz 0.02 Mt 1.4 g/t 1 koz 1.12 Mt 1.5 g/t 55.2 koz

Au 81 0.16 Mt 1.5 g/t 8 koz 0.04 Mt 1.0 g/t 1 koz 0.20 Mt 1.4 g/t 9.0 koz

Bartons 0.57 Mt 1.4 g/t 26 koz 0.15 Mt 1.4 g/t 7 koz 0.72 Mt 1.4 g/t 32.5 koz

All Nations 0.34 Mt 1.6 g/t 18 koz 0.03 Mt 1.4 g/t 1 koz 0.38 Mt 1.6 g/t 19.2 koz

Shearers 0.22 Mt 1.4 g/t 10 koz 0.12 Mt 1.2 g/t 5 koz 0.34 Mt 1.3 g/t 14.3 koz

Otways 0.21 Mt 1.1 g/t 7 koz 0.07 Mt 1.0 g/t 2 koz 0.27 Mt 1.0 g/t 9.2 koz

Little Wonder (MML) 0.09 Mt 1.7 g/t 5 koz 0.01 Mt 4.6 g/t 1 koz 0.10 Mt 2.0 g/t 6.3 koz

Golden Gate 0.01 Mt 4.2 g/t 2 koz 0.00 Mt 3.5 g/t 0 koz 0.01 Mt 4.1 g/t 1.8 koz

Condor 0.04 Mt 2.4 g/t 3 koz 0.01 Mt 2.9 g/t 1 koz 0.05 Mt 2.5 g/t 4.0 koz

Crow 0.00 Mt 1.1 g/t 0 koz 0.01 Mt 2.3 g/t 0 koz 0.01 Mt 2.2 g/t 0.4 koz

Falcon 0.00 Mt 0.0 g/t 0 koz 0.03 Mt 3.5 g/t 3 koz 0.03 Mt 3.5 g/t 3.0 koz

Harrier 0.00 Mt 0.0 g/t 0 koz 0.02 Mt 1.8 g/t 1 koz 0.02 Mt 1.8 g/t 1.1 koz

G_Reef 0.00 Mt 0.0 g/t 0 koz 0.00 Mt 3.2 g/t 0 koz 0.00 Mt 3.2 g/t 0.2 koz

Little Wonder (CCJV) 0.27 Mt 1.5 g/t 13 koz 0.00 Mt 1.4 g/t 0 koz 0.28 Mt 1.5 g/t 13.1 koz

Junction 0.14 Mt 2.0 g/t 9 koz 0.01 Mt 2.0 g/t 1 koz 0.15 Mt 2.0 g/t 9.4 koz

Roscoes Reward 0.53 Mt 1.2 g/t 21 koz 0.12 Mt 1.3 g/t 5 koz 0.65 Mt 1.2 g/t 25.8 koz

ROM stocks 0.64 Mt 0.9 g/t 19 koz 0.64 Mt 0.9 g/t 18.5 koz

TOTAL 4.32 Mt 1.39 g/t 193 koz 0.64 Mt 1.47 g/t 30 koz 4.97 Mt 1.40 g/t 223 koz

    Proven Reserves          Probable Reserves                TOTAL           

Source : MOY ASX announcement, 27 March 2015 plus 25 September 2015, Beer & Co.    

 Drilling Results 

Figure 25 also shows that the gold is located to the immediate north of the Middle Creek fault and also along splays off this fault, to the north.   

Bartons pit is the pit currently being mined by MOY.  Figure 27 shows that the Reserve grade for Bartons is 1.4g/t, while the quarterly reports shows the average grade of ore being processed for the September quarter was 1.94g/t. 

 

    Figure 28 : Bartons Pit drill results   

 Source : MOY Presentation, October 2015 

 

  This shows that the results from Bartons has been much better than expected.   

Figure 28 shows the potential for extensions to the south and west and to the east.  MOY had previously reported drill results, in May 20111 and October 2011, of  

10m at 9.6g/t, 8m at 9.3g/t and 8m at 2.0g/t to the south and west; and 

3m at 12.2g/t, 3m at 6.0g/t, 5m at 1.5g/t and 1m at 6.7g/t to the east. 

Millennium Minerals (MOY.ASX) 

 

Page 16  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  MOY has recently conducted drilling in the region to the south of Shearers Pit, investigating the potential for extensions to the main lode. 

 

    Figure 29 : Extensions to Shearers Pit   

Source : MOY ASX announcement, 23 November 2015  

  As well as identifying extensions to the main lode, drilling identified a secondary lode, with results of 

7m at 3.83g/t, 13m ar 1.55g/t and 13m at 1.33g/t for the main lode; and 

11m at 4.16g/t, 20m at 2.1g/t and 8m at 2.2g/t from the secondary lode.   

Figure 30 shows results from Anne de Vidia including 6m at 4.8g/t, 8m at 32g/t and 16m at 5.5g/t, even though this is not included in Resources.   

 

    Figure 30 : Anne de Vidia and Castlemaine   

 Source : MOY ASX announcement, 23 November 2015 

 

  Figure 30 also shows Castlemaine which has historic shafts that have reported a total of 1,326oz of production and a single RC drill hole which returned 2m at 3.6g/t but was not followed up.   

Expected Results 

MOY is now committed to investing $10m into exploration within its tenement areas.

Beer & Co has assumed that MOY is able to delineate 2.0Mt of material to be included in its mining inventory.   

Millennium Minerals (MOY.ASX) 

 

Page 17  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Beer & Co assumes that the average grade is 1.5g/t, which is in line with the Reserve grade, despite evidence that the mining operations have consistently out‐performed the reserve grade.  

This gives a cost of $A 121 for each ounce added to mining inventory, which is about 4x the average in Australia.   

Beer & Co expects that the actual results will do better than we have assumed for this analysis.   

 

  Expected Outcomes  

  Operations 

Due to the expected success in exploration, Beer & Co expects operations to continue beyond 2017 Q3.   

In this analysis, Beer & Co assumes that MOY spends $10m a year on exploration, but delineating 2.0Mt of mining inventory grading 1.5g/t each year, except in the final year of the program which has zero success; in other words, keep going until no longer successful.    

In this analysis, Beer & Co assumes that MOY is successful to 7½ years.    

Figure 31 : Operational Outcomes 

2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Waste moved 6,779 kt 8,778 kt 8,763 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 8,550 kt 2,029 kt

waste : ore 4.2  : 1 5.5  : 1 4.8  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1 4.5  : 1

Ore Mined 1,615 kt 1,583 kt 1,840 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 1,900 kt 451 kt

Gold head grade 1.56 g/t 1.66 g/t 1.68 g/t 1.41 g/t 1.47 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.50 g/t 1.16 g/t

Recovery 88.2 % 87.1 % 90.9 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 % 92.0 %

Gold produced 63,247 oz 74,375 oz 88,631 oz 79,231 oz 82,534 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 84,309 oz 37,473 oz

Source : MOY quarterly announcements, Beer & Co estimates  

  Figure 31 shows that Beer & Co’s operational projections are not as good as recent operational experience, suggesting potential upside.   

 

Figure 32 : Details of operating costs 

2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Waste Removal $A 18.7m $A 23.2m $A 24.1m $A 23.5m $A 23.5m $A 23.5m $A 23.5m $A 23.5m $A 23.5m $A 23.5m $A 23.5m $A 23.5m $A 5.6m

AUD /t ore $A 11.6/t $A 14.7/t $A 13.1/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t $A 12.3/t

AUD /t material $A 2.8/t $A 2.6/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t $A 2.7/t

Ore extraction $A 4.0m $A 4.1m $A 4.8m $A 4.9m $A 4.9m $A 4.9m $A 4.9m $A 4.9m $A 4.9m $A 4.9m $A 4.9m $A 4.9m $A 1.2m

AUD /t ore $A 4.1/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t $A 4.2/t

Ore Transport $A 0.0m $A 3.0m $A 10.4m $A 5.0m $A 8.8m $A 2.3m $A 3.1m $A 3.9m $A 4.6m $A 5.4m $A 6.2m $A 8.5m $A 1.8m

AUD /t ore $A 0.0/t $A 1.9/t $A 5.7/t $A 2.6/t $A 4.6/t $A 1.2/t $A 1.6/t $A 2.0/t $A 2.4/t $A 2.9/t $A 3.3/t $A 4.5/t $A 3.9/t

Mining Overhead $A 4.8m $A 4.8m $A 4.9m $A 5.0m $A 5.0m $A 5.0m $A 5.0m $A 5.0m $A 5.0m $A 5.0m $A 5.0m $A 5.0m $A 1.2m

AUD /t ore $A 3.0/t $A 3.0/t $A 2.7/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.6/t $A 2.7/t

Processing $A 26.8m $A 29.0m $A 32.5m $A 33.3m $A 33.3m $A 33.3m $A 33.3m $A 33.3m $A 33.3m $A 33.3m $A 33.3m $A 33.3m $A 16.8m

AUD /t ore $A 18.8/t $A 18.3/t $A 17.6/t $A 17.5/t $A 17.5/t $A 17.5/t $A 17.5/t $A 17.5/t $A 17.5/t $A 17.5/t $A 17.5/t $A 17.5/t $A 15.4/t

Site Admin $A 3.9m $A 4.2m $A 4.4m $A 4.3m $A 4.4m $A 4.4m $A 4.4m $A 4.4m $A 4.4m $A 4.4m $A 4.4m $A 4.4m $A 1.6m

AUD /t ore $A 2.7/t $A 2.7/t $A 2.4/t $A 2.3/t $A 2.3/t $A 2.3/t $A 2.3/t $A 2.3/t $A 2.3/t $A 2.3/t $A 2.3/t $A 2.3/t $A 1.5/t

TOTAL C1 $A 58.3m $A 68.2m $A 81.1m $A 76.0m $A 79.8m $A 73.4m $A 74.1m $A 74.9m $A 75.7m $A 76.5m $A 77.2m $A 79.5m $A 28.2m

AUD/t of ore $A 37.7/t $A 44.7/t $A 45.7/t $A 41.6/t $A 43.6/t $A 40.2/t $A 40.6/t $A 41.0/t $A 41.4/t $A 41.8/t $A 42.2/t $A 43.4/t $A 64.2/t

$A 963/oz $A 952/oz $A 948/oz $A 997/oz $A 1,003/oz $A 906/oz $A 915/oz $A 924/oz $A 933/oz $A 942/oz $A 952/oz $A 979/oz $A 772/oz

Source : MOY quarterly announcements, Beer & Co estimates 

Millennium Minerals (MOY.ASX) 

 

Page 18  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Figure 32 complements Figure 31 by showing the detail of Beer & Co’s estimated C1 costs by cost component.   

Figure 33 shows the detail, in AUD/oz terms, of our projections for All In Sustaining Costs.   

 

Figure 33 : Detail of Beer & Co’s projected cash costs for Nullagine operations AUD / oz LoM 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Waste Removal 280 312 271 296 284 278 278 278 278 278 278 278 149

Ore extraction 93 90 87 100 96 94 94 94 94 94 94 94 50

Ore Transport 61 40 118 64 106 28 37 46 55 64 73 101 47

Mining Overhead 60 64 56 63 60 59 59 59 59 59 59 59 33

Processing 400 389 366 420 403 395 395 395 395 395 395 395 449

Site Admin 53 56 50 55 53 52 52 52 52 52 52 52 44

Royalties 52 42 45 75 66 50 50 50 50 50 50 50 50

Corporate Costs 64 71 56 63 61 59 59 59 59 59 59 59 133

Sus. Capital 125 40 39 172 165 161 161 161 161 161 161 102 23

TOTAL 1,188 1,105 1,088 1,307 1,295 1,176 1,185 1,195 1,204 1,213 1,222 1,190 978

Source : Beer & Co estimates  

 Financial Outcomes 

Figure 34 shows the gold prices and the AUD‐USD rate since January 2005.   

It shows that our AUD‐USD projection is the current rate, while there are many who project a lower rate.  Also, our projection is only a little lower than the average since 

the AUD was first floated in 1983 (0.764).  

  Figure 34 : Historical and projected gold prices and AUD‐USD rate 

0.600

0.650

0.700

0.750

0.800

0.850

0.900

0.950

1.000

1.050

1.100

$ 400/oz

$ 650/oz

$ 900/oz

$ 1,150/oz

$ 1,400/oz

$ 1,650/oz

$ 1,900/oz

4 Jan. 2005 4 Jan. 2007 4 Jan. 2009 4 Jan. 2011 4 Jan. 2013 4 Jan. 2015 4 Jan. 2017 4 Jan. 2019 4 Jan. 2021 4 Jan. 2023

  Gold price, in USD   Projected gold price

  AUD‐USD rate    projecjed AUD‐USD

Source : IRESS, Beer & Co estimates  

  Our projection is for the gold price to recover from the current level, but only to the average for 2014.   

 

Figure 35 : Projected financial outcomes for MOY’s Nullagine operations 

AUD m 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024

AUD/USD 0.968 0.903 0.747 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700

Gold $ 1,411/oz $ 1,272/oz $ 1,149/oz $ 1,163/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz $ 1,200/oz

Revenue 92.4 106.9 136.9 131.7 141.5 144.5 144.5 144.5 144.5 144.5 144.5 144.5

Cash Costs (60.9) (70.8) (84.0) (79.0) (82.8) (76.4) (77.1) (77.9) (78.7) (79.5) (80.2) (82.5)

Royalties (2.7) (3.1) (4.0) (5.9) (5.4) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2) (4.2)

Dep'cn & Amort'sn (22.0) (27.2) (22.5) (20.0) (22.5) (15.7) (13.8) (13.2) (13.0) (13.0) (12.9) (14.8)

E B I T 6.8 5.8 26.4 26.8 30.8 48.3 49.4 49.2 48.6 47.9 47.2 43.0

Sus Cap Ex ‐ driling 0.0 0.0 0.0 (10.0) (10.0) (10.0) (10.0) (10.0) (10.0) (10.0) (10.0) (5.0)

Sus Cap Ex ‐ other (3.1) (3.0) (3.5) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6) (3.6)

Project Cashflow, pre‐tax 25.8 30.0 45.4 33.1 39.6 50.4 49.6 48.8 48.0 47.3 46.5 49.2

Source : MOY reports, Beer & Co estimates 

Millennium Minerals (MOY.ASX) 

 

Page 19  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Figure 35 shows the detail of Beer & Co’s financial projections, based on the commodity prices shown in Figure 33 and the costs in Figure 32.   

It shows that Beer & Co projects that MOY spends $10m each year on drilling to maintain its mining inventory, and also generates significant cash flow.   

 

  Valuation of MOY  

  Figure 35 shows Beer & Co’s financial projections for the Nullagine operations.  

Figure 36 shows the financial outcomes for MOY as a corporate entity.    

Figure 36 : Beer & Co’s projected financial outcomes for MOY AUD m 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Total Revenue 116 137 132 142 145 146 146 146 147 147 147 67

Cost of Goods Sold (88) (84) (79) (83) (76) (77) (78) (79) (79) (80) (83) (29)

Royalties (4) (4) (6) (5) (4) (4) (4) (4) (4) (4) (4) (2)

Corporate Costs (5) (5) (5) (5) (5) (5) (5) (5) (5) (5) (5) (5)

Exploration Expense 0 0 0 0 0 0 0 0 0 0 0 0

Dep'cn & Amort'sn (27) (22) (20) (22) (16) (14) (13) (13) (13) (13) (15) (4)

Interest Expense (5) (3) (0) 0 0 0 0 0 0 0 0 0

Tax Expense (12) (4) (5) (8) (13) (14) (14) (14) (13) (13) (12) (8)

NPAT  (118) 10 12 18 31 32 32 32 31 31 28 19

Shares on Issue 218 m 349 m 743 m 754 m 759 m 759 m 759 m 759 m 759 m 759 m 759 m 759 m

Earnings per Share (2.1c) 2.8 c 1.6 c 2.4 c 4.1 c 4.2 c 4.2 c 4.2 c 4.1 c 4.1 c 3.8 c 2.5 c

Operating Cashflow 5 25 40 47 60 47 47 47 47 46 45 25

Investing Cashflow (3) (3) (14) (14) (14) (14) (14) (14) (14) (14) (9) (1)

Source : MOY 2014 Annual Report, 2015 Half Year report, Beer & Co estimates  

  Figure 36 shows the impact of the present equity raising.  It also shows that we project earnings of 1.6c/share for 2016, which is P/E of 3.0x, and that earnings rise over time, partly due to our assumed rise in the gold price.   

Figure 37 shows the detail of Beer & Co’ risked base case valuation of MOY, which is 14.5c/share (rounded to the nearest half cent, which is how trades are done).   

 

    Figure 37 : Beer & Co’s base case valuation of MOY   

23‐Nov‐15

risk :  100% Product per share

Nullagine Reserves 100% $ 82m $ 82m 10.8 c 6.6 c

franking credits 60% $ 7m $ 4m 0.5 c 0.6 c

Nullagine Extensions 80% $ 141m $ 113m 14.9 c 16.5 c

franking credits 48% $ 33m $ 16m 2.1 c 2.3 c

Exploration 90% ($ 46m) ($ 41m) (5.5c) (6.0c)

Hedge  100% ($ 8m) ($ 8m) (1.0c) (0.6c)

Corporate 100% ($ 30m) ($ 30m) (3.9c) (3.7c)

Cash / Debt 100% ($ 36m) ($ 36m) (4.7c) (1.3c)

Equity raisings 100% $ 19m $ 19m 2.5 c 0.3 c

TOTAL $ 163m $ 119m 15.7 c 14.6 c

Shares on issue 217.7m F P O shares 18.0m Options

525.0m issued 2015 16.0m Ops. Ex'd

discount rate =    12.0 % 31 December 2014

 Source : Beer & Co estimates 

Millennium Minerals (MOY.ASX) 

 

Page 20  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  Figure 37 shows that while Beer & Co is confident of exploration success, we have still discounted the success for risk, while the investment has a lower risk weighting, despite our assumption that the last 12 months has zero success. 

Sensitivity Analyses 

Beer & Co’s base case valuation is a precise answer to a large number of assumptions, each of which is subject to a degree of error.   

Figure 38 attempts to break the valuation up between existing Reserves and Beer & Co’s expected exploration success.  It shows that the current share price : 

Assumes some exploration success; and 

Reflects current commodity prices.    

    Figure 38 : Commodity prices   

USD / oz $ 1,100/oz $ 1,200/oz $ 1,250/oz $ 1,300/oz

AUD‐USD = 0.700 $A 1,571/oz $A 1,714/oz $A 1,786/oz $A 1,857/oz

Reserves 3.0 c 4.2 c 4.4 c 4.7 c

Exploration 6.0 c 10.4 c 12.6 c 14.6 c

TOTAL 9.0 c 14.6 c 17.0 c 19.3 c  Source : Beer & Co estimates 

 

  The other key variables are the degree of exploration success.  Figure 39 shows that a positive view on investment in MOY requires success in finding 2.0Mt/yr of mining inventory.   

 

 

 

Figure 39a : Exploration Success     Figure 39b : Exploration Success  

Gold price :  $A 1,714/oz Years :  7.5 years

Tonnes by Grade 1.30 g/t 1.50 g/t 1.70 g/t

1.5 Mt/yr (1.0c) 0.4 c 2.2 c

2.0 Mt/yr 8.9 c 14.6 c 21.3 c

2.5 Mt/yr 10.2 c 16.7 c 24.3 c

Gold price :  $A 1,714/oz Years :  7.5 years

Tonnes by Grade 1.30 g/t 1.50 g/t 1.70 g/t

1.5 Mt/yr (5.3c) (3.9c) (2.3c)

2.0 Mt/yr 3.8 c 9.0 c 15.2 c

2.5 Mt/yr 4.6 c 10.6 c 17.5 c

Source : Beer & Co estimates  Source : Beer & Co estimates  

 

 

 

 

Figure 39b shows that at current commodity prices, of $1100/oz gold and AUD‐USD rate of 0.700 , MOY gains significant benefit from either or both of higher grade and higher volume of exploration success.   

Beer & Co’s analysis showed muted sensitivity to number of years of expected exploration success. 

Conclusions 

MOY’s operations at Nullagine produced first gold in September 2012.  From then until the most recent quarter, MOY failed to generate sufficient cash to service and repay the $58m in debt it had taken on to develop the $83m project.   

This had been due to a range of operational issues which drove costs higher and may be seen as outside the control of the management.   

However, management failed to respond to these changed conditions and instead focused on the operational projections in the feasibility study.   

For the September quarter, a strong cashflow was generated by running the operations well, with higher throughput, better recoveries, lower costs and focus on ore with a better net return.    

Millennium Minerals (MOY.ASX) 

 

Page 21  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

  MOY is raising equity to repay the subordinated debt it had taken on to service the senior debt, as the sub‐debt must be repaid quickly.   

With this raising, MOY will be generating good cash.   

Beer & Co’s base case valuation is based on : 

The gold price rising slowly to $1250/oz, which is lower than the average of 2014, while the AUD‐USD rate stays level, when most expect it to fall; 

An investment of $10m/yr in exploration for 8½ years, yielding 2.0Mt each year of material grading 1.5g/t, which is less than the grade or ore treated to date, for the first 7 ½ years before generating nothing in the final year.  

The exploration cost is $121/oz, which is high, especially for an area that is as prospective as Nullagine.   

Our valuation is quite sensitive to the volume of exploration success, but we feel that MOY is likely to be more successful than we have projected.   

Our valuation shows that MOY is fair value at current commodity prices and our projected, very modest, exploration success.   

Beer & Co initiates research on MOY with a BUY, High Risk, recommendation.   

 

 

Millennium Minerals (MOY.ASX) 

 

Page 22  See Page 23 for Disclaimer and Disclosures  23 November 2015  

Beer & Co ResearchMillenium Minerals (MOY.ASX)

Year ended December 2014 2015 2016 2017 2018 2019 2020 2021 Commodity price assumptions

Section 1 - P&L 2015 2016 2017 2018 2019 2020

Sales revenue $A m 107 137 132 141 145 145 145 145 AUD‐USD 0.747 0.700 0.700 0.700 0.700 0.700

Interest revenue $A m 0 0 0 0 1 1 1 2 Gold             US$ / oz 1,149 1,163 1,200 1,200 1,200 1,200

Other revenue $A m 9 0 0 0 0 0 0 0 AUD / oz 1,537 1,661 1,714 1,714 1,714 1,714

Total Revenue $A m 116 137 132 142 145 146 146 146

Mine Production

Cost of Goods Sold $A m (88) (84) (79) (83) (76) (77) (78) (79) Nullagine

Royalties (4) (4) (6) (5) (4) (4) (4) (4) Ore processed     '000t 1,841 1,900 1,900 1,900 1,900 1,900

Corporate Costs $A m (5) (5) (5) (5) (5) (5) (5) (5)    Gold grade 1.68 g/t 1.41 g/t 1.47 g/t 1.50 g/t 1.50 g/t 1.50 g/t

Exploration Expense $A m 0 0 0 0 0 0 0 0    Gold produced  (ounces) 88,631 79,231 82,534 84,309 84,309 84,309

Other Operating Expenses $A m (17) (5) (5) 0 0 0 0 0

Total Operating Expenses $A m (114) (98) (95) (93) (86) (86) (87) (88) Resources

Deposit   Gold  

EBITDA $A m 2 39 37 48 60 59 59 58 Golden Eagle 10.6 Mt 0.9 g/t 4.4 Mt 0.9 g/t 4.3 Mt 0.9 g/t 564 koz

Dep'cn & Amort'sn $A m (27) (22) (20) (22) (16) (14) (13) (13) Bartons 1.7 Mt 1.2 g/t 1.4 Mt 1.2 g/t 0.6 Mt 1.1 g/t 141 koz

EBIT $A m (25) 17 17 26 44 45 46 45 Shearers 0.6 Mt 1.3 g/t 1.5 Mt 1.0 g/t 0.3 Mt 1.0 g/t 81 koz

Interest Expense $A m 0 0 0 (1) (1) (1) (1) (1) Otways 1.2 Mt 0.8 g/t 0.9 Mt 0.9 g/t 0.7 Mt 0.9 g/t 75 koz

Other $A m (1) 0 0 0 0 0 0 0 All Nations 1.3 Mt 1.4 g/t 0.6 Mt 1.1 g/t 0.4 Mt 1.0 g/t 90 koz

Pre‐Tax Profit $A m (26) 17 17 25 43 44 45 44 Little Wonder 0.5 Mt 1.4 g/t 0.3 Mt 1.4 g/t 0.2 Mt 1.7 g/t 44 koz

Tax Expense $A m 0 0 0 (1) (3) (5) (5) (7) Golden Gate 0.2 Mt 3.0 g/t 0.1 Mt 2.9 g/t 0.1 Mt 2.4 g/t 42 koz

NPAT  $A m (26) 17 17 24 39 39 40 37 Falcon 0.0 Mt 0.0 g/t 0.1 Mt 3.9 g/t 0.0 Mt 4.4 g/t 18 koz

Condor 0.2 Mt 2.6 g/t 0.0 Mt 2.8 g/t 0.0 Mt 3.7 g/t 19 koz

Section 2 - Key Data Harrier 0.0 Mt 0.0 g/t 0.1 Mt 1.7 g/t 0.0 Mt 1.8 g/t 8 koz

Ordinary shares ‐  year end m 217.7 742.7 742.7 758.7 758.7 758.7 758.7 758.7 Crow 0.0 Mt 3.1 g/t 0.0 Mt 2.6 g/t 0.0 Mt 2.3 g/t 11 koz

Fully diluted shares on issue m 217.7 742.7 742.7 758.7 758.7 758.7 758.7 758.7 G_Reef 0.0 Mt 0.0 g/t 0.0 Mt 4.0 g/t 0.0 Mt 3.9 g/t 5 koz

Weighted # shares m 217.7 348.9 742.7 754.2 758.7 758.7 758.7 758.7 Au 81 0.4 Mt 1.6 g/t 0.3 Mt 1.2 g/t 0.9 Mt 0.9 g/t 57 koz

Earnings per Share (2.1c) 2.8 c 1.6 c 2.4 c 4.1 c 4.2 c 4.2 c 4.2 c Camel Ck 1.2 Mt 1.3 g/t 0.7 Mt 1.2 g/t 0.7 Mt 1.1 g/t 105 koz

Dividends Per Share 0.0 c 0.0 c 0.0 c 0.0 c 0.0 c 0.0 c 0.0 c 0.0 c TOTAL 17.7 Mt 1.1 g/t 10.5 Mt 1.1 g/t 8.4 Mt 1.0 g/t 1,259 koz

Section 3 - Balance Sheet Reserves (includes 100% of Camel Ck JV)

Cash $A m 2 5 6 31 67 89 110 131 Proved 3.7 Mt 1.5 g/t 174 koz

Receivables $A m 2 9 11 12 11 11 11 11 Probable 0.6 Mt 1.5 g/t 30 koz

Inventory $A m 17 13 14 12 13 13 13 13 Stockpiles 0.6 Mt 0.9 g/t 19 koz

Other $A m 2 2 2 2 2 2 2 2 TOTAL 5.0 Mt 1.4 g/t 223 koz

CURRENT ASSETS $A m 23 30 33 58 92 115 136 157

Costs, AUD / oz

Receivables $A m 0 0 0 0 0 0 0 0 LoM 2015 2016 2017 2018 2019 2020

P , P & E $A m 43 28 16 7 5 4 4 4 C 1 cash costs 947 948 997 1,003 906 915 924

Mining Properties / Exploration $A m 8 4 10 10 10 10 11 11 All‐In 1,188 1,088 1,307 1,295 1,176 1,185 1,195

Other $A m 0 0 0 0 0 0 0 0

NON‐CURRENT ASSETS $A m 51 32 26 17 15 15 15 16 Asset based Valuation

TOTAL ASSETS $A m 74 62 59 75 107 129 151 173 23‐Nov‐15

risk :  100% Product per share

Payables $A m 16 7 7 6 6 6 6 6 Nullagine Reserves 100% $ 82m $ 82m 10.8 c 6.6 c

Debt $A m 20 12 0 0 0 0 0 0 franking credits 60% $ 7m $ 4m 0.5 c 0.6 c

Other $A m 1 0 0 0 0 0 0 0 Nullagine Extensions 80% $ 141m $ 113m 14.9 c 16.5 c

CURRENT LIABILITIES $A m 36 18 7 6 6 6 6 6 franking credits 48% $ 33m $ 16m 2.1 c 2.3 c

Exploration 90% ($ 46m) ($ 41m) (5.5c) (6.0c)

Long Term Debt $A m 17 0 0 0 0 0 0 0 Hedge  100% ($ 8m) ($ 8m) (1.0c) (0.6c)

Other $A m 2 2 2 2 2 2 2 2 Corporate 100% ($ 30m) ($ 30m) (3.9c) (3.7c)

Provisions $A m 6 6 6 6 6 6 6 6 Cash / Debt 100% ($ 36m) ($ 36m) (4.7c) (1.3c)

NON‐CURRENT LIABILITIES $A m 26 8 8 8 8 8 8 8 Equity raisings 100% $ 19m $ 19m 2.5 c 0.3 c

TOTAL LIABILTIES $A m 62 27 16 14 14 15 15 15 TOTAL $ 163m $ 119m 15.7 c 14.6 c

NET ASSETS $A m 12 35 43 61 93 115 137 158 Shares on issue 217.7m F P O shares 18.0m Options

525.0m issued 2015 16.0m Ops. Ex'd

Accumulated Profit (Loss) $A m (135) (125) (113) (95) (64) (33) (1) 31

Reserves $A m 3 (4) (8) (9) (8) (17) (27) (37) Financial Ratios

Contributed Equity $A m 144 165 165 165 165 165 165 165 2014 2015 2016 2017 2018 2019

Total Equity $A m 12 35 43 61 93 115 137 158 Revenue $A m 116 137 132 142 145 146

EBITDA $A m 2 39 37 48 60 59

Section 4 - Cashflow EBIT  $A m (25) 17 17 26 44 45

Net Cashflow from operations $A m 19 44 42 48 60 59 59 58 NPAT (reported $A m (26) 17 17 24 39 39

Hedging $A m (5) 0 0 0 0 0 0 0 Adjusted EPS (cps) (2.1c) 2.8 c 1.6 c 2.4 c 4.1 c 4.2 c

Interest Paid $A m (5) (3) (0) 0 1 1 1 2 EPS Growth (%) (45%) 54 % 68 % 4 %

Taxes Paid $A m 0 0 0 0 (1) (14) (14) (14) DPS (c) 0.0 c 0.0 c 0.0 c 0.0 c 0.0 c 0.0 c

Change in Working Capital $A m (4) (16) (1) (2) 1 0 0 0 Dividend Yield (%) 0 % 0 % 0 % 0 % 0 % 0 %

Other $A m PE adj. (x) x (1.8) 1.8 3.2 2.1 1.2 1.2

OPERATING CASHFLOW $A m 5 25 40 47 60 47 47 47 EV / EBITDA (x) x 19.4 1.1 0.8 0.1 (0.5) (0.9)

EV / EBIT (x) x (1.7) 2.6 1.8 0.2 (0.7) (1.1)

Exploration Expenditures $A m 0 0 (10) (10) (10) (10) (10) (10) Gearing (%) 50 % 19 % 0 % 0 % 0 % 0 %

Maintenace Capex $A m (3) (3) (4) (4) (4) (4) (4) (4) Return on Assets (34%) 27 % 29 % 35 % 41 % 35 %

Expansion Capex $A m 0 0 0 0 0 0 0 0 Return on Equity (211%) 48 % 39 % 40 % 42 % 34 %

PPE Acquisitions (Total Capex)$A m (3) (3) (14) (14) (14) (14) (14) (14) EBITDA Margin (%) 2 % 29 % 28 % 34 % 41 % 41 %

PPE Divestments $A m 0 0 0 0 0 0 0 0 Interest Cover ( x n/a n/a n/a n/a n/a n/a

INVESTING CASHFLOW $A m (3) (3) (14) (14) (14) (14) (14) (14)

Change in Equity $A m 0 21 0 1 0 0 0 0 Major shareholders

Dividends Paid $A m 0 0 0 0 0 0 0 0 IMC Resource Holdings

Change in Debt $A m (2) (25) (12) 0 0 0 0 0 existing 75.4m 34.6 % 91.4m 39.1 %

FINANCING CASHFLOW $A m (2) (5) (12) 1 0 0 0 0 new 181.7m 34.6 % 181.7m 34.6 %

Total 257.1m 34.6 % 273.1m 36.0 %

Free Cashflow $A m 2 22 27 33 47 33 33 33

Net Cashflow $A m 0 17 15 34 47 33 33 33

   fully diluted   

discount rate = 12 % 31 December 2014

Year ended December

    Measured         Indicated         Inferred    

November 2015

Year ended December

 

Millennium Minerals (MOY.ASX) 

 

Page 23  See Page 23 for Disclaimer and Disclosures  23 November 2015  

 

Important Information  Confidential This  document  is  for  the  confidential  use  of  the  recipients  only  and  is  not  to  be  reproduced without  the authority of Beer & Co Pty Ltd. It has been prepared at the request of Millennium Minerals Limited and Beer & Co Pty Ltd will receive a fee for its preparation.  Disclaimer The  persons  involved  in  or  responsible  for  the  preparation  and  publication  of  this  report  believe  that  the information herein has been obtained from reliable sources and that any estimates, opinions, conclusions or recommendations are reasonably held at the time of compilation. No warranty is made as to the accuracy of the  information  in  this document and,  to  the maximum extent permitted by  law, Beer & Co Pty Ltd and  its related entities, their respective directors and officers disclaim all liability for any loss or damage which may be suffered by any recipient through relying on anything contained or omitted from this document.  General Advice The  content  is of  a  general nature  and  is based on  a  consideration of  the  securities  alone,  and  as  such  is conditional and must not be relied upon without advice from a securities adviser as to the appropriateness to you given your individual investment objectives, financial situation and particular needs. Whilst this document is based on information and assessments that are current at the date of publication, Beer & Co Pty Ltd has not undertaken  detailed  due  diligence  on  the  information  provided  and  has  no  obligation  to  provide  revised assessments in the event of changed circumstances.  Disclosure Beer & Co Pty Ltd has been engaged by Millennium Minerals Limited  to prepare  this research report and  is being paid a  fee  for  its preparation.  In  the  future, Beer & Co Pty Ltd may provide capital  raising services  to Millennium Minerals Limited on commercial terms.  Directors of Beer & Co or other associate companies may own securities  in Millennium Minerals Limited.   Beer & Co Pty Ltd seeks to do work with those companies  it researches.  As a result, investors should be aware that Beer & Co Pty Ltd may have a conflict of interest that could affect the objectivity of this report.  Analyst Certification The analyst  responsible  for  this  research  report certifies  that all of  the views expressed  reflect his personal views about the securities and the issuer.   Report prepared by : Pieter Bruinstroop    [email protected]  

BEER & CO PTY LTD ABN 88 158 837 186, AUTHORISED REPRESENTATIVE MELBOURNE VENTURE SECURITIES PTY LTD AFSL No. 224 313 

 

Melbourne Office: Suite 4, Level 2, Bank House 11 - 19 Bank Place, Melbourne, Vic, Australia 3000 Telephone: Facsimile: Email: 

(+613) 9600 3599 (+613) 9602 2291 [email protected] 

 

Web:                                       www.beerandco.com.au