Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory...

41
The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone: +32 2-894-9300 web: www.raponline.org Moving the Market Design Discussion Beyond Capacity Markets” Meg Gottstein, Principal, Regulatory Assistance Project International Conference on the European Energy Market Florence, May 10-12, 2012 This presentation includes material from a paper copyrighted © 2012 IEEE under the title “Beyond Capacity Markets- Delivering Capability Resources to Europe’s Decarbonised Power System” Permission to use copyrighted information must be obtained directly from IEEE.

Transcript of Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory...

Page 1: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium

Phone: +32 2-894-9300 web: www.raponline.org

Moving the Market Design Discussion

“Beyond Capacity Markets”

Meg Gottstein, Principal, Regulatory Assistance Project

International Conference on the European Energy Market

Florence, May 10-12, 2012

This presentation includes material from a paper copyrighted © 2012 IEEE under the title “Beyond Capacity Markets-Delivering Capability Resources to Europe’s Decarbonised Power System”

Permission to use copyrighted information must be obtained directly from IEEE.

Page 2: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

The Regulatory Assistance Project ("RAP")

RAP is a global NGO providing technical and policy assistance to government officials and agency staff on energy and environmental issues. RAP Principals and senior staff are all former regulators, government officials or senior policy advisors, and RAP’s work is funded exclusively by foundations and government agencies. RAP has worked in more than 20 nations and 50 provinces and states. RAP's European offices are headquartered in Brussels, with a second office in Berlin.

Meg Gottstein is a Principal with RAP working on European Programmes out of RAP's Berlin office.

Prior to coming to RAP in 2008, Ms. Gottstein served for over 20 years as a senior regulatory judge for the Commission overseeing California's electric and gas industry. She has also held positions with the California Energy Commission and the US Department of Energy, and provided consultancy services to the National Governor’s Association and other organisations. She has a BA in Economics and German from Tufts University, including two years of study at the University of Tübingen, Germany. Meg received her Masters in Public Policy from Harvard University and is also an Honorary Fellow at the University of Exeter, UK.

Recent RAP assignments include work with: UK Department of Energy and Climate Change, European Climate Foundation (Policy Volume II, Roadmap 2050 and Power Perspectives 2030), Council of European Energy Regulators, Sustainable Development Task Force, and Chilean Ministry of Energy.

2 www.raponline.org

Page 3: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Does Power Sector Decarbonisation Turn Traditional “Wisdom” about ensuring Reliability on its head?

3

YES!

But not in the way it is currently being discussed!

“strategic reserve” of capacity?

full-market “capacity auction”?

capacity auction with “reliability option” contracts?

Can energy-only markets secure system reliability?

DO we need something else? WE NEED TO THINK BEYOND “CAPACITY” MARKETS

Page 4: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

What’s the “Answer”? What’s the Question?

Let’s Start With: What Does a Reliable Power System Require?

4

Page 5: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Electrons “in” Electrons “out”

Continuous Balance of Supply and Demand

All Power Systems Require

5/14/2012 5

Page 6: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

If you primarily have Dispatchable, Increasing Marginal Cost Generation in the mix….

nuclear lignite coal hard coal gas combined-cycle gas open-cycle oil

or “merit order”

mar

gin

al c

ost

5/14/2012 6

Total Demand

Page 7: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Western Denmark system—winter demand patterns

Source: Security of Supply from a UCTE Perspective, Paul-Frederik Bach, April 2004 5/14/2012 7

Peak

Mid-

Baseload

Reliability Challenge: Do you have enough firm capacity (# of MWs) to cover

the few hours of highest (peak) demand?

Page 8: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

ALL CAPACITY PAYMENT designs (in theory or practice) focus on a single reliability dimension:

Pay to ensure there is enough MWs of firm capacity during the system peak demand

Baseload, mid-merit and peaking generation each has an equal role/value

New investment in peakers is key focus-- quickest/cheapest to build MWs that can economically operate just a few hours a year

This approach will not ensure reliability for Europe’s decarbonised power system

8

Page 9: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

To Ensure Reliability of Europe’s Future Decarbonised Power System:

“Net” or “Residual” Demand becomes a critical reliability dimension

Net Demand = Total Demand

minus energy available from variable renewables (e.g., solar, wind)*

9

*Variable renewables are those whose output is not controllable (except through curtailment) due to the nature of their primary energy source

Page 10: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Western Denmark system with ≈18% of energy from wind

The reliability challenge is rapidly shifting to one of following frequent changes in “net demand”

Source: Security of Supply from a UCTE Perspective, Paul-Frederik Bach, April 2004 5/14/2012 10

Page 11: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

KEY MESSAGE OF PAPER:

Market Design for a reliable, decarbonised power system

Must address “NET” DEMAND and deliver the RESOURCE CAPABILITIES to meet it!

11

Page 12: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Modelled for the power system operated by the WestConnect group of utilities in Arizona, Colorado, Nevada, New Mexico and Wyoming.

Source: Western Interconnection Wind and Solar Integration Study, December 2010, (NREL/TP-5500-50057) http://www.nrel.gov/docs;

Net demand: more volatile than overall demand, lacking a repeatable pattern. Demand and availability of variable renewables can be moving in opposite directions, any day, every day, several times a day

A Challenging Week for WestConnect (US), assuming 35% Wind Penetration 12

Page 13: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

13 Source: Deutsche Umwelthilfe, Background Paper--Extension of operating time for atomic power stations: Federal government

propels society into new fundamental conflict. (2011)

Net Demand Projected for Germany, 24th calendar week in 2020

Demand “flexing” in both directions will be needed in the future, not just peak “shaving”

5/14/2012

Page 14: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Paying for MW capacity that is inflexible, or not flexible enough will increasingly:

threaten system reliability

impose more costs on consumers

pressure to curtail/restrict renewables needed to decarbonise the power system

14

All full-market Capacity Auctions* developed to date (in theory or practice) suffer from this “Fatal Flaw”

*e.g., “forward capacity markets” (PJM, ISO-NE model) or capacity auctions with reliability option contracts (Colombia)

Page 15: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

The Market-Wide Capacity Auction (3 years “Forward”)

R1

R5

R3

R6

R7

R4

R1 R2

R3 R4

R5

R1-R7 = Capacity offered by Supply-Side (New built, Existing, Uprates) and Demand-Side (Energy Efficiency, Demand Response, Distrib. Gen); Self-supply (R1) bids in a “zero” price; New Resources set clearing price

R6 R7

Supply = Capacity Committed “Forward”

Demand = System Operator Forecast of Total Peak MWs

Quantity = MW

Bid Price = $ per MW-day

P*

P* clearing price paid to all capacity clearing auction

Cleared Capacity = 100,000 MW

15

R2

15

Page 16: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Source: Market Monitoring Analytics (PJM) 16

Cumulative PJM Capacity Revenues ($42 billion over 6 annual auctions)

Demand Resources2.43%

Energy Efficiency Resources0.07%

Coal (Existing)30.01%

Coal (Planned)0.16%

Gas (Existing)31.83%

Gas (Planned)0.66%

Hydro (Existing)4.91%

Hydro (Planned)0.00%

Nuclear (Existing)21.06%

Nuclear (Planned)0.00% Oil (Existing)

8.14%

Oil (Planned)0.00%

Other Renewables (Existing)0.68%

Other Renewables (Planned)0.05%

Coal--Existing

Gas--Existing

Hydro-Existing

Nuclear-Existing

Oil-Existing

Energy Efficiency

70% to existing fossil-

fueled plants;

20% to “legacy” nuclear;

Where are the new gas,

flexible peakers?

Demand Response

Renewables-Existing

Renewables-Planned

16

Page 17: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

What Resource Capabilities are required to Operate the System from a “Net Demand Perspective?

Generators that can respond to rapidly changing net demand, e.g.:

generators with frequent stop-start capability (daily)

fast and “far” ramping, minimum run times

Responsive demand (in both directions) has a much larger role to play, along with storage technologies

Experience in real markets shows that demand-side can and has provided this flexibility reliably, and much cheaper than supply-side alternatives (see extra slides)

Enabling grid development and cross-border balancing

18

Page 18: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

-

5.000

10.000

15.000

20.000

25.000

30.000

1 1001 2001 3001 4001 5001 6001 7001 8001

UK_South

How Flexible? Profile of mid-merit CCGTs in 2030

Source data compiled by RAP Europe in consultation with KEMA for four representative centers of gravity reflected in the model runs for Power Perspectives 2030, European Climate Foundation, full report available at: http://www.roadmap2050.eu/attachments/files/PowerPerspectives2030_FullReport.pdf

Example of large combined-cycle gas turbine fleet with “typical” average load factor (58%)* ( ~ 50% renewables in the mix, including hydro)

But requiring 264 start-stops per year of those “mid-merit” generators Compared to < 50 typical start-stops for those plants today

*load factor = amount of plant output relative to maximum output it could produce

Meg

awat

ts

Hours in the year

5/14/2012 19

Page 19: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

“Demand-response aggregator”= Virtual powerplant

(not only demand reduction—both directions of response needed!)

“ISO” = system operator/TSO

Page 20: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Demand Response “Virtual Powerplant” offers

flexible capabilities to the system Representative Simulation (US Aggregator = Enbala)*

*Slide graphics/animation reproduced with permission of Ron Dizy, President and CEO, Enbala Power Networks; available at: http://www.enbala.com/gridbalancedemo.html

Response of all resources = “Regulation” capability delivered

Signal sent by system operator

5/14/2012 21

Page 21: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

ENBALA Power Network Client Pool beginning to respond to

ISO signal.

5/14/2012 22

Page 22: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 23

Page 23: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 24

Page 24: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 25

Page 25: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 26

Page 26: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 27

Page 27: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 28

Page 28: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 29

Page 29: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 30

Page 30: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 31

Page 31: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 32

Page 32: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 33

Page 33: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 34

Page 34: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

5/14/2012 35

Page 35: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

The aggregate response of each resource in the

network is compiled to form a unified

regulation response.

5/14/2012 36

Page 36: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

KEY MESSAGE OF PAPER: The Proposed Market Design…

Must Address “NET DEMAND” and Deliver the Resource

CAPABILITIES to Meet it!

37

Page 37: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Key Design “Check List” for Evaluation: Does the Market Design Proposal …?

1) Deliver capabilities required to meet net demand?

– Does the proposal even assess net demand at all?

2) Make the most of existing resources with the required capabilities, before turning to more expensive new ones?

3) Secure services from all potential resources, in particular demand-side?

4) Ensure that resources without the necessary range of capabilities (e.g., inflexible generation) are not remunerated (or much less than those that can)?

5) Recognise the carbon content of resources delivering capabilities?

38

Page 38: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

Does the Market Design Proposal …(cont.)?

6) Avoid adverse impact on renewable investments that can undermine Europe’s ability to meet its carbon reduction targets?

7) Promote future cost reductions and innovation, avoid foreclosure of market to future providers of flexible capabilities (including consumers)?

8) Create a potentially scalable design, including future integration of neighboring balancing areas and sharing of capability resources?

Positive response to these questions suggests “robust proposal” whilst any negative responses should raise significant concerns

39

Page 39: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

“You can’t solve a problem with the same thinking that created it.”

- Albert Einstein

40

Page 40: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

“You can’t solve a problem with the same market rules that created it.”

- Meg Gottstein

41

Page 41: Moving the Market Design Discussion Beyond Capacity Markets” · 2012. 5. 10. · The Regulatory Assistance Project 48 Rue de Stassart Building C, BE-1050 Brussels, Belgium Phone:

About RAP

The Regulatory Assistance Project (RAP) is a global, non-profit team of experts that focuses on the long-term economic and environmental

sustainability of the power and natural gas sectors. RAP has deep expertise in regulatory and market policies that:

▪ Promote economic efficiency ▪ Protect the environment ▪ Ensure system reliability ▪ Allocate system benefits fairly among all consumers

Learn more about RAP at www.raponline.org

Meg Gottstein, Principal; [email protected]