Mov 555 y 556 How to Scrapping Finished Goods to Cost Center
-
Upload
ricardo-baeza -
Category
Documents
-
view
215 -
download
1
description
Transcript of Mov 555 y 556 How to Scrapping Finished Goods to Cost Center
-
1
How To Scrapping finished goods from blocked stock to cost
center
Motion class: 555 GI scrapping blocked
Motion class: 556 RE scrapping blocked
1- Login to the transaction MMBE:
Enter the material, Plant, Storage location and unit of measure. Then execute "F8"
Display the blocked stock in the plant, in this case 2 BOT
-
2
2- Consume blocked stock to Cost center
You must enter the transaction MB1A.
Enter the movement type 555, Plant, Storage location (you can put a document header text for
reference), then click enter
Now you must enter the cost center, material code, quantity, unit of measure BOT, Storage
location and batch, then click enter
-
3
Finally only it is necessary to save,
3- Reversal of scrapping
You must enter the transaction MBST.
-
4
Enter the posting date, material document (the same as previous step) and year, then click
enter:
Finally you have to save:
4- Visualization of material consumption
-
5
Execute transaction MB03.
Enter the material document number and the year, then click enter:
It is possible to display the information of the document:
5- Review of stock after the scrapping from blocked.
Previously we saw the material 10083864 had 2 bottles (BOT) in stock, now we will
check the stock after scrapping.
- Execute transaction MMBE,
Enter SAP material code, Plant, Storage location and unit of measure:
-
6
We see the blocked stock was reduced.