MONTHLY REPORT NO. 13
Transcript of MONTHLY REPORT NO. 13
Engineering Consultants for Loan 2856 BAN: Dhaka Chittagong Expressway Public Private Partnership Design Project
October 2018 Doc. No. 5022160-034.2-013.1
SMEC International Pty Ltd in Joint Venture with Stantec Australia Pty Ltd
with
PT. Infra Tama Yakti, PT. SMEC Denka Indonesia,
PT. Amurwa International and PT. Widyagraha Asana as Sub-Consultants
MONTHLY REPORT NO. 13
Monthly Report No. 13, October 2018
Project Name: Metropolitan Sanitation Management Investment Project
Project Number: 5022160
Report for Directorate General of Human Settlements, Ministry of Public Works and Housing
Report Monthly Report No 13
PREPARATION, REVIEW AND AUTHORISATION
Revision # Date Prepared by Reviewed by Approved for Issue
by
0 12/11/18 SB BS SB
ISSUE REGISTER
Distribution List Date Issued Number of Copies
CPMU 27 hardcopies
SMEC International Pty Ltd in Joint Venture with Stantec Australia Pty Ltd with PT Infratama Yakti, PT SMEC Denka Indonesia, PT. Amurwa International and PT. Widyagraha Asana as Sub-Consultants
Jakarta: NHB Building, Jl. Melawai Raya No. 14 Kebayoran Baru, Jakarta Selatan 12160
Ph. 021 720 6334
Project Office: KMO Building 2nd Floor, Jl. Kyai Maja No. 1 Kebayoran Baru, Jakarta Selatan 12120 Ph. 021 2751 4511; 2751 4755
The information within this document is and shall remain the property of the Consulta
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 i
TABLE OF CONTENTS
EXECUTIVE SUMMARY ............................................................................................................................. 1
PERIOD OF THIS REPORT .............................................................................................................................. 1
CONTRACT SUMMARY ................................................................................................................................. 1
SUMMARY OF ACTIVITIES ............................................................................................................................. 2
Preparation of Tender Documents .................................................................................................... 2
Tendered Contracts ........................................................................................................................... 2
Detailed Engineering Design (DED) ................................................................................................... 2
Socialisation ...................................................................................................................................... 2
PROGRESS ................................................................................................................................................ 3
CONTRACT STATUS ..................................................................................................................................... 4
KEY ISSUES ................................................................................................................................................ 5
Design Flows at Makassar WWTP .................................................................................................... 5
Low Connection Rate in Initial Years ................................................................................................. 5
Pekanbaru WWTP Site ...................................................................................................................... 5
Social Safeguards, Resettlement and Gender Awareness ................................................................. 6
ACTIVITIES PLANNED FOR THE NEXT REPORTING PERIOD .................................................................................... 6
Makassar .......................................................................................................................................... 6
Pekanbaru ......................................................................................................................................... 6
Jambi ................................................................................................................................................. 7
ACRONYMS AND ABBREVIATIONS ........................................................................................................... 8
PISC ACTIVITIES ..................................................................................................................................... 10
PROJECT SUMMARY .................................................................................................................................. 10
REPORTING PERIOD .................................................................................................................................. 10
MEETINGS HELD ...................................................................................................................................... 10
DUTY TRIPS ............................................................................................................................................. 11
PROJECT CORRESPONDENCE ....................................................................................................................... 12
STAFF INPUTS TO DATE ............................................................................................................................. 15
SUMMARY OF INPUTS TO DATE ................................................................................................................... 18
DEVELOPMENT OF MSMIP WEBSITE ........................................................................................................... 20
Status of Website Development ...................................................................................................... 20
Required Interim Outputs ............................................................................................................... 21
ADDENDUM NO. 2 ................................................................................................................................... 21
ENVIRONMENTAL, GENDER, AND SOCIAL SAFEGUARDS ........................................................................ 22
ENVIRONMENTAL ASPECT .......................................................................................................................... 22
AMDAL Document (GOI Requirement) ............................................................................................ 22
IEE Document (ADB Requirement) .................................................................................................. 22
Semi-Annual Environmental Monitoring Report (ADB Requirement) ............................................. 22
GENDER AND SOCIAL DEVELOPMENT ........................................................................................................... 22
Current Status ................................................................................................................................. 22
4.3 SOCIAL SAFEGUARD ACTIVITIES FOR NEXT PERIOD .......................................................................................... 25
CONTRACT IMPLEMENTATION .............................................................................................................. 28
COVERAGE OF PROJECT ............................................................................................................................. 28
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 ii
CONTRACT SUMMARY ............................................................................................................................... 28
CONTRACT STATUS ................................................................................................................................... 29
SUMMARY OF COMPLETED ACTIVITIES .......................................................................................................... 29
Makassar WWTP ............................................................................................................................ 29
Makassar Networks ........................................................................................................................ 30
Pekanbaru WWTP ........................................................................................................................... 31
Pekanbaru Networks ....................................................................................................................... 31
Jambi WWTP ................................................................................................................................... 32
Jambi Networks .............................................................................................................................. 32
PROGRESS DURING THE REPORTING PERIOD .................................................................................................. 33
TRAINING/WORKSHOPS ............................................................................................................................ 34
ARRANGEMENT FOR O&M OF PROJECT FACILITIES ......................................................................................... 34
MAJOR ISSUES AND PROPOSED REMEDIAL ACTIONS ............................................................................ 35
KEY ISSUES .............................................................................................................................................. 35
Design Flows at Makassar WWTP ................................................................................................. 35
Low Connection Rate in Initial Years ............................................................................................. 35
Pekanbaru WWTP Site ................................................................................................................... 35
Social Safeguards, Resettlment and Gender Awareness .............................................................. 35
FINANCIAL STATUS ................................................................................................................................ 36
CONTRACT AWARDS ................................................................................................................................. 36
PISC PAYMENTS TO DATE .......................................................................................................................... 37
PISC CURRENT INVOICES ........................................................................................................................... 39
COMPLIANCE WITH LOAN COVENANTS ................................................................................................. 40
ACTIVITIES PLANNED FOR NEXT REPORTING PERIOD ............................................................................ 41
Makassar ........................................................................................................................................ 41
Pekanbaru ....................................................................................................................................... 41
Jambi ............................................................................................................................................... 41
APPENDIX A: UPDATED PROCUREMENT PLAN ............................................................................................... 42
APPENDIX B: MINUTES OF MEETINGS ............................................................................................................ 44
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 1
EXECUTIVE SUMMARY
Period of this Report
The period of this report is from 02/10/2018 until 01/11/2018
Contract Summary
A summary of all 12 contracts is given in Table 1-1 below:
Table 1-1: Summary of Contract Packages
* local tender in accordance with ADB Guidelines
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 2
Summary of Activities
The following activities were carried out during the reporting period:
Preparation of Tender Documents
Draft bidding documents based on ADB General Conditions for Design-Build were completed for the
international design-build contract B1 of Makassar WWTP and the cost estimate was finalized. These
were submitted to ADB for approval
Draft bidding documents for Contracts B2 (Makassar Network) and NC (Pekanbaru Network) were
submitted to ADB for approval.
Tendered Contracts
During the previous reporting period, PISC had completed bidding documents for:
- Contracts C1 and C2 for Makassar
- Contracts SC1 and SC2 for Pekanbaru
These contracts C1, C2, SC1 and SC2 have now been procured and contract signature is imminent.
Detailed Engineering Design (DED)
The detailed engineering design (DED) for Wastewater Sewer Collection of Makassar (B3/C3)
has complete and await for source of funding, whether it is funded by additional APBN (will
nameny C3) or by remaining funds from the calculation of WWTP costs in Pekanbaru or Jambi
(will namely B3)
The detailed engineering design (DED) for Pekanbaru WWTP is proceeding. The geotechnical
design was completed and costed at c.$5-$7 million. The process design was further
progressed and the site layout and tank sizes are being worked up. However, PISC expressed
great concern to CPMU and to LG that the available site (comprising 10-15m of peat subsoil)
is totally unsuitable for construction and the many technical constraints arising were leading
to delays in design progress.
The detailed engineering design (DED) for Jambi Sewer System West (funded by APBN) and
Jambi Sewer System East (funded by ADB) is proceeding.
Socialisation
The following socialization activities were undertaken:
Preparation of Socialisation Activities for SKPD, AP (affected people) and beneficiary for
Pekanbaru.
Training on package procurement auction using ADB documents and procedures
Conduct preliminary survey for affected person in the Pekanbaru project area.
Preparation of ToR and Cost Estimate for Vulnerable Survey for Makassar, Pekanbaru and
Jambi.
Updating of Semi-Annual Environmental Monitoring Report.
Updating of Semi-Annual Involuntary Resettlement Monitoring Report.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 3
Preparation for Gender Workshop.
Site Visit to Pekanbaru for updating of LARAP.
Progress
The following specific tasks have been completed during the reporting period:
Value engineering reviews of existing designs and peak factors.
Finalisation of the MBBR Concept Design and Cost Estimate for Design-Build Contract B1 in
Makassar.
Revision of Bidding documents for International Design-Build Contract B1 in Makassar in
accordance with comments from ADB of Bidding Documents
Commence preparation of DED of CAS (Conventional Activated Sludge) WWTP for Pekanbaru.
Preparation of geotechnical design for Pekanbaru WWTP site (founded on peat sub-soil).
Revision of Bidding documents for Makassar (B2)
Revision of Bidding documents for Pekanbaru (NC) which include:
Preparation of cost estimate and tender documents foe sewerage packages finance by Loan
and ABPN for Jambi (B2 and C) which include:
o Development of specifications
o Development of tender forms
o Development of Drawings
o Development of Bill Quanties
Development of solutions for expected low wastewater flows in initial WWTP operation.
Preparation of Socialisation Activities for SKPD, AP (affected people) and beneficiary.
Preparation of Vulnerable Persons Survey for Makassar, Pekanbaru and Jambi.
Submission of draft final version of Addendum No. 2.
Submission of Monthly Reports Nos. 10 (July 2018) and 11 (August 2018).
Provision of updated Project Schedule (attached to this report).
Continuous updating of the Risk Register.
Development of Project Website.
Regular meetings held with CPMU and PPK.
Activities in offices and fields for preparation of Pekanbaru and Makassar construction
supervision (Team Mobilization, site inspections, checking routes and prepare socialization
programs)
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 4
Contract Status
The current status of the contract preparation is given in Table 1-2 below:
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 5
Table 1-2: Current Status of Contract Packages
Key Issues
The key issues at this stage are:
Design Flows at Makassar WWTP
Because of the change in treatment process at Makassar WWTP from ABR to MBBR, the peak flow
factor used in MWH Design for the WWTP (3.6) were re-assessed by PISC as part of a value engineering
exercise. The bidding documents were then finalized and submitted using a peak factor of 2
throughout; this has resulted in a cost saving of almost $2 million.
Because of the complex interaction between PS B and WWTP, PS B has been included in the B1 design-
build package. In addition, the rising main between has been re-designed as a gravity main thereby
reducing the unwieldy size of the pumps.
Low Connection Rate in Initial Years
If the minimum number of connections are not realized at the completion of construction of the plant;
the Contractor will be unable to properly commission the works and could thus evade his
responsibilities under the contract. PISC continues to encourage the CPMU to allocate additional
budgets through additional APBN FY 2019/2020 or the remaining contracts to finance 2,000-3,000
connections in order to achieve the minimum flow
In addition, for Makassar Design-Build project, he Contractor would also escape his contractual
obligation that the operating cost (OPEX) of the WWTP would be less than his guaranteed tender OPEX
value.
Pekanbaru WWTP Site
The Pekanbaru WWTP site is highly unsuitable for the construction of the plant. Not only is it located
in the floodplain of the nearby Sail and Siak rivers and at the time of writing, it and the public road
leading thereto are currently wholly submerged. Furthermore, the existing ground conditions
Ref Location ContractBid
TypeType
Estimated
Cost (USD M)
Design
Completion
Date
Status
1 Makassar C1 NCB Sewerage System Northwest 13.72 Completed Contractor Selected
2 Makassar C2 NCB Sewerage System Northwest 13.43 Completed Contractor Selected
3 Pekanbaru SC1 NCB Sewerage System South 15.33 Completed Contract Signed
4 Pekanbaru SC2 NCB Sewerage System South 10.68 Completed Contract Signed
5 Makassar B2 NCB* Sewerage System 13.70 31.08.2018 Bidding Documents Submitted, Comments Received
6 Pekanbaru NC NCB* Sewerage System Northwest 21.09 31.08.2018 Bidding Documents Submitted, Comments Received
7 Makassar (B3)C3 NCB Sewerage System 11.72 01.04.2019 Awaiting Finalisation of Cost Estimates
8 Makassar B1 ICB* WWTP 17.70 30.09.2018 Bidding Documents Submitted
9 Pekanbaru B1 NCB* WWTP 12.15 31.01.2019 Local tender, treatment process selected, design development
10 Jambi B1 NCB* WWTP 6.6 28.02.2019 Local tender, treatment process selected, design development
11 Jambi B2 NCB* Sewerage System East 18.25 31.11.2018 Under preparation
12 Jambi C NCB Sewerage System West 14.1 31.11.2018 Under preparation
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 6
comprise 10-15 metres of peat subsoil which require that all main structures, (including the 60m long
access road from the existing public road to the site) will require to be piled at significant extra cost
(c. $5m).
Social Safeguards, Resettlement and Gender Awareness
It is unclear if Local Government are undertaking key tasks required to meet the demands for Social
Safeguards, Resettlement, and Gender Awareness. Due to a new regulation concerning effluent
standard, the technology changes for all three WWTPs need AMDAL review which should be
conducted by Local Government followed by issuance of an environmental permit from the Mayor’s
office.
Although the 1,000 connections for Makassar and Pekanbaru have been identified; this is not yet the
case for Jambi. However, although the identification has been carried out, until now, the local
government has not conducted socialization programmes for prospective users. The current
socialization is just limited to government officers and not yet directly for the people.
PISC also continues to coordinate with PPK and the Regional Government to ensure and for Pump
House in Pekanbaru and land access to the Pump House in Jambi are available this year.
Activities Planned for the Next Reporting Period
The following activities are planned for the next reporting period (i.e. November 2018):
Makassar
The following activities are planned for Makassar during the next reporting period.
- Commence of construction; Contract C1 and C2 (APBN funded).
- Tendering of Contract B2 (Loan Funded).
- Preparation of Socialisation Activities for SKPD, AP (affected people) and continue with
socialization for 1,000 connections (benefeciaries).
- Vulnerable Survey for 200 respondents in the target areas.
- ADB review mission (28th – 29th Nov ).
Pekanbaru
The following activities are planned for Pekanbaru during the next reporting period.
- Commencement of construction; Contract SC1 and SC2 (APBN funded).
- Tendering of Contract NC (Loan Funded).
- Continue design for WWTP and preparation of Bidding Documents.
- Continuing to conduct socialization for 1,000 connections.
- Vulnerable Survey for 200 respondents in the target areas.
- ADB review mission (26th – 27th Nov)
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 7
Jambi
The following activities are planned for Jambi during the next reporting period.
- Prepare tendering for Contract West (APBN funded).
- Complete bidding documents for Contract East (APBN funded) - (Drawings, Engineering
Estimate and Technical Specifications) and ready for tender.
- Commence design for WWTP and prepare Bidding Documents.
- Preparation of Socialisation Activities for SKPD, AP (affected people) and continue with
socialization for 1,000 connections (benefeciaries).
- Vulnerable Survey for 200 respondents in the target areas.
- ADB review mission (21th – 22th Nov).
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 8
ACRONYMS AND ABBREVIATIONS
ADB Asian Development Bank
ADF
APBD
Asian Development Fund
Anggaran Pendapatan dan Belanja Daerah/Regional Government
Budget
APBN Anggaran Pendapatan dan Belanja Negara/ National
Government Budget
AusAid Australian Agency for International Development
BLH Biro/Badan Lingkungan Hidup/Environmental Agency
BLUD Badan Layanan Umum Daerah/Regional Public Service Agency
CBD Central Business District
CDTA Capacity Development Technical Assistance
CEMP
CPMU
Contractor’s Environmental Management Plan
Central Project Management Unit
CSS City Sanitation Strategy
DAK Dana Alokasi Khusus/Special Allocation Fund
DAU Dana Alokasi Umum/General Allocation Fund
DD
DED
Due Diligence
Detailed Engineering Design
DESD
DFAT
Directorate of Environmental and Sanitation Development
Department of Foreign Affairs and Trade (Australia), formerly
AusAid
DGHS Directorate General of Human Settlements (Cipta Karya)
DKK Dinas Kebersihan Kota/City Sanitation Agency
DMF Design and Monitoring Framework
EA
EIA
EMP
FOPIP
GIS
Executing Agency
Environmental Impact Assessment
Environmental Management Plan
Financial and Operating Performance Improvement
Geographic Information System
GoI Government of Indonesia
HH
IMB
Household
Ijin Mendirikan Bangunan/Building Permit
IndII Indonesia Infrastructure Initiative
ICB
IEE
INDII
WWTP
International Competitive Bidding
Initial Environmental Examintation
Indonesian Infrastructure Initiative
Instalasi Pengolahan Air Limbah/Wastewater Treatment Plant
IPLT Instalasi Pengolahan Lumpur Tinja/Septage Treatment Plant
IUWASH Indonesia Urban Water, Sanitation and Hygiene Project (United
States International Agency for Development)
LARAP
LIBOR
Land Acquisition and Resettlement Action Plan
London Interbank Offered Rate
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 9
LPMU Local Project Management Unit
MIS Management Information System
MLD
MOF
MOHA
Megalitres per Day
Ministry of Finance
Minster of Home Affairs
MPWH Ministry of Public Works and Housing
MSMHP Metropolitan Sanitation Management and Health Project
MSMIP Metropolitan Sanitation Management Investment Project
NCB
NGOs
O&M
National Competitive Bidding
Non Government Organization
Operation and Maintenance
PAM Project Administration Manual
PIU Program Implementation Unit
PISC Project Implementation Support Consultant
PPMU Provincial Project Management Unit
POKJA Kelompok Kerja/Working Group PPLP
PPLP Direktorat) Pengembangan Penyehatan Lingkungan Pemukiman/
Directorate of Environmental Sanitation Development,
Directorate General of Human Settlements, Ministry of Public
Works and Housing
PPP Public Private Partnership
PPSP Program Percepatan Sanitasi Permukiman/Acceleration of Urban
Sanitation Development Program
PPTA Project Preparation Technical Assistance
PROLEGDA Program Legislasi Daerah/Local Legislation Procedure
PUPR Ministry of Public Works and Housing (Kementerian Pekerjaan
Umum dan Perumahan Rakyat)
PISC
AIIG
Project Implementation Support Consultants
Australia Indonesia Infrastructure Grants for Sanitation
SANIMAS Program Sanitasi Berbasis Masyarakat/Community Based
Sanitation Program
SATKER Satuan Kerja/Work Unit
SDO Service Delivery Organization
SPS
SOP
Safeguards Policy Statement
Standard Operational Procedure
SSK Strategi Sanitasi Kota/City Sanitation Strategy
UPTD Unit Pelaksana Teknis Daerah/Local Government Technical
Implementation Unit
USRI Urban Sanitation and Rural Infrastructure Support to PNPM
Mandiri Project (ADB funded)
WA
WWTP or WWTW
Withdrawal Application
Wastewater Treatment Plant or Works
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 10
PISC ACTIVITIES
Project Summary
A summary of the project data is given in Table 3-1 below:
Table 3-1: Summary of Project Data
Project Name: Metropolitan Sanitation Management Investment Project (MSMIP)
Project Number: International 5022160 / National 7022119
Date of Award: 2nd October 2017
Due Date for Completion: January 31st 2021
Client Organisation: Directorate General Human Settlement (DGHS) – Ministry of Indonesia
Client Address / Contact Details Office Address : Jl. Pattimura 20, Kebayoran Baru Jakarta Selatan 12110 Indonesia Officer's Name : Asri Indiyani Position : Head of CPMU Telephone : +62-21 72797175 Email address: [email protected]
Opportunity Number 1022536
Project Fee Value: USD 7,476,484 and IDR 63,808,886,200 excluding VAT 10%
SMEC Team Leader Seamus BAYNES
SMEC Project Director Brian HAYDEN
Brief Project Description
The Design Review and Update and Construction Supervision of Sewerage Treatment Facilities and Sewer Networks for three cities of Makassar, Pekenbaru and Jambi in Indonesia.
Reporting Period
The period of this report is from 02.10.2018 until 01.11.2018.
Meetings Held
The following meetings were held during the reporting period:
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 11
Table 3-2: Meetings Held
Date Location Topic
Tuesday –
October 2
KMO Building Discussion of Progress Review Design of Makassar,
Pekanbaru and Jambi Cities; Discussion on the
Preparation of the Vulnerable Household Survey and
Social & Gender Workshop; Advanced Discussion on
SOP of the MSMIP PISC Supervision Activities.
Wednesday –
October 10
KMO Building Addendum No. 2 PISC - MSMIP
Friday –
October 19
KMO Building Contract Preparation for Pekanbaru NC, SC1 & SC2
Friday –
October 19
KMO Building Social Safeguards & Resettlement Activities
Monday –
October 22
KMO Building Website Progress Meeting
Thursday –
October 25
Meeting Room 2nd floor
of Bappeda of
Pekanbaru City
Updating LARP (Land Acquisition and Resettlement
Plan) of Pekanbaru; Public Disclosure of LARP
(Information Disclosure); Complaint Handling
Mechanism; Discussion Regarding Social Safeguard
Monitoring.
Wednesday –
October 31
Meeting Room of Satker
Pengembangan PLP
Strategis
Discussion of the Proposed Addendum No. 2
Duty Trips
The following duty trips were made during the reporting period:
Table 3-3: Duty Trips
No Personnel Date City Agenda
1 Lutfi Basit October 16-17, 2018
Pekanbaru Obtaining Data for Flood Level of Siak River from River Areas Office
2 Vicky, Budi, Della and Fiana October 25-26, 2018
Pekanbaru Social Safeguard meeting and preparation for PAP survey
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 12
Project Correspondence
The following correspondence was issued during the reporting period:
Table 3-4: Correspondence Log
Type Date Reference Content Response
Letter –
PISC to
CPMU
2nd October 5022160-031.3-144/X/18 Draft Bidding Documents
for Makassar Design and
Build Project B1.
Letter –
PISC to PPK
2nd October 5022160-031.3-145/X/18 Proposed Candidate and
Mobilization Plan of Guard
2 and Office Boy for
Pekanbaru Office.
UM0103-
CL/PPLPS/1347
Letter –
PISC to
CPMU
3rd October 5022160-031.3-146/X/18 Updated Initial
Environmental
Examination.
Letter –
PISC to PPK
3rd October 5022160-031.3-147/X/18 Request for Approval to
Purchase a Network
Attached Storage (NAS)
Server.
UM0103-
CL/PPLPS/1369
Letter –
PISC to PPK
3rd October 5022160-031.3-
148/X/18.r1
Invitation for the Meeting
of the Social Safeguard
Document.
Letter –
PISC to PT.
Putera
Mandiri
8th October 5022160-031.3-153/X/18 Permohonan Price List
Cover Manhole.
Letter –
PISC to
CPMU
10th
October
5022160-031.3-154/X/18 Request for Document of
Land Acquisition and
Resettlement Plan (LARP)
Makassar.
Letter –
PISC to PPK
10th
October
5022160-031.3-155/X/18 Proposed Visit of Social
Safeguards/Resettlement
Specialist.
Letter –
PISC to
CPMU
12th
October
5022160-031.3-156/X/18 Design Flows for Makassar
Contract B1 – WWTP.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 13
Type Date Reference Content Response
Letter –
PISC to PPK
12th
October
5022160-031.3-157/X/18 Proposed Candidate and
Mobilization Plan of 4 Field
Supervisors for Pekanbaru
Office
UM0103-
CL/PPLPS/1412
Letter –
PISC to PPK
12th
October
5022160-031.3-158/X/18 Proposed Candidate and
Mobilization Plan of Office
Boy and Guard 1 for
Makassar Office
UM0103-
CL/PPLPS/1411
Letter –
PISC to
CPMU
12th
October
5022160-031.3-159/X/18 Submission of Monthly
Report No. 10 English
Version
Letter –
PISC to
CPMU
12th
October
5022160-031.3-160/X/18 Submission of Monthly
Report No. 10 Bahasa
Version
Letter –
PISC to
CPMU
16th
October
5022160-031.3-161/X/18 Final Bidding Documents
for Contract B1 - Makassar
WWTP
Letter –
PISC to PPK
17th
October
5022160-031.3-162/X/18 Leave Notification
Letter –
PISC to PPK
17th
October
5022160-031.3-163/X/18 Revised ToR and Cost
Estimate for Vulnerable
Household Survey
Letter –
PISC to PPK
16th
October
5022160-031.3-164/X/18 Mobilisation of our Social
Safeguards / Resettlement
Specialist
Letter –
PISC to PPK
19th
October
5022160-031.3-165/X/18 Pekanbaru WWTP –
Maximum Flood Level
Letter –
PISC to Mr.
Steven
Moore
19th
October
5022160-031.3-166/X/18 Draft Design Review
Report for Makassar
WWTP (using ABR
technology, PS B and
Effluent Disposal)
Letter –
PISC to PPK
22nd
October
5022160-031.3-
167/X/18.r1
Social Safeguard and
Resettlement Coordination
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 14
Type Date Reference Content Response
Meeting and Site Visit
(Revision)
Letter –
PISC to PPK
19th
October
5022160-031.3-168/X/18 Proposed Candidate and
Mobilization Plan of Field
Supervisor 1 & 3 for
Pekanbaru Office
UM0103-
CL/PPLPS/1451
Letter –
PISC to
CPMU
23rd
October
5022160-031.3-169/X/18 Submission of Monthly
Report No. 7 (2nd Revision)
English and Bahasa Version
Letter –
PISC to
CPMU
23rd
October
5022160-031.3-
170/IX/18
Submission of Monthly
Report No. 8 (2nd Revision)
English and Bahasa Version
Letter –
PISC to PPK
23rd
October
5022160-031.3-171/X/18 Revised ToR and Cost
Estimate for Vulnerable
Household Survey
Letter –
PISC to PPK
23rd
October
5022160-031.3-172/X/18 Revised ToR and Cost
Estimator for Social
Development and Gender
Workshop
Letter –
PISC to
CPMU
23rd
October
5022160-031.3-173/X/18 Revised Semi-Annual
Environmental Safeguards
Monitoring Report
(Jan - June 2018)
Letter –
PISC to
CPMU
23rd
October
5022160-031.3-174/X/18 Revised Semi-Annual
Social Safeguards and
Involuntary Resettlement
Monitoring Report (Jan -
June 2018)
Letter –
PISC to PPK
24th
October
5022160-031.3-175/X/18
Addendum No. 2 – Final
Letter –
PISC to PPK
24th
October
5022160-031.3-176/X/18 Proposed Candidate for
Interim Replacement
Wastewater Treatment
Process Engineer
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 15
Type Date Reference Content Response
Letter –
PISC to PPK
25th
October
5022160-031.3-177/X/18 Proposed Candidate and
Mobilization Plan of
Engineering Support 1 /
Drafting for Pekanbaru
Office
UM0103-
CL/PPLPS/1458
Letter –
PISC to PPK
25th
October
5022160-031.3-178/X/18 Proposed Candidate and
Mobilization Plan of Guard
1 for Makassar Office
UM0103-
CL/PPLPS/1459
Letter –
PISC to PPK
25th
October
5022160-031.3-179/X/18 Resignation Letter of
Geotechnical Specialist
Letter –
PISC to PPK
29th
October
5022160-031.3-
180/X/18.r1
Proposed Candidate and
Mobilization Plan of
Sewerage Engineer 2 for
Makassar Office
Letter –
PISC to PPK
29th
October
5022160-031.3-181/X/18 Proposed Candidate and
Mobilization Plan of
Sewerage Engineer 2 and
Quantity Surveyor for
Pekanbaru Office
Letter –
PISC to PPK
30th
October
5022160-031.3-182/X/18 TOR and Cost Estimate for
Pekanbaru Socialisation
Activities
Letter –
PISC to PPK
31st October 5022160-031.3-183/X/18 Social Safeguard and
Resettlement Coordination
Meeting and Site Visit to
Makassar
Letter –
PISC to PPK
31st October 5022160-031.3-184/X/18 Response to Supervision
Team Mobilization
Guidance - Pekanbaru
Letter –
PISC to PPK
31st October 5022160-031.3-
185/X/18.r1
Leave Notification of
Seamus Baynes
Staff Inputs to Date
Staff inputs (person-months) to date are given in Table 3-5 below:
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 16
Table 3-5: Staff Inputs to Date (Person-months)
No. Name Position Key or Non Key
Person-months to date
Addendum No 2
Person-months balance
JAKARTA
Key Personnel (International)
1 Seamus Baynes Team Leader / Wastewater Specialist
Key 2.22 26.38 24.16
2 Anthony Gunadi Wastewater Treatment Process Engineer
Key 7.48 12 4.52
3 Ananda De Costa Civil/Structural Expert Key 5.52 6 0.48
4 Napolean Lagura Mechanical Expert Key 4.78 5.72 0.94
5 Rosemary Faletese Gender and Social Development Specialist
Key 2.25 5.71 3.46
6 Joselito Losario Environmental Specialist Key 1.68 6.22 4.54
7 Victoria R Pineda Social Safeguards / Resettlement Specialist
Key 2.71 5.22 2.51
8 Brian Hayden Senior Infrastructure Specialist (Start Up)
Key 7.74 8.58 0.84
9 Andrew Connell Sewer Line Expert Key 2.33 8 5.67
10 Bruce Beard Senior Electrical Expert Key 2.03 5.89 3.86
11 Rudy Tjandrajana Geotechnical Expert Key 2.73 3.73 1
12 Marivic Competente Senior Procurement & Contract Specialist
Key 2.36 4.5 2.14
Key Personnel (National)
1 Benny Aryanto Deputy Team Leader Key 12.18 38.19 26.01
2 Thariq Marzuki Financial Management Specialist
Key 11.79 33.8 22.01
3 Afdatira/Achyar Lubis
MIS Specialist Key 9.52 18 8.48
5 Treesnowati Benefit Monitoring Specialist Key 3.75 8 4.25
6 Sulikha Cost Estimator - Jakarta Key 7.87 7.88 0.01
7 Wildan Civil Engineer Key 9.91 14.92 5.01
8 Yan Haryadi Structural Engineer Key 9.78 13.79 4.01
9 Henry Pranajaya Mechanical Engineer Key 5.92 34.91 28.99
10 Luthfi Basit Sewerage Engineer 1 Key 7.85 35.86 28.01
11 Djati Wiryawan Procurement/Contract Expert Key 5.45 35.46 30.01
12 Fredericus Widaryanto
Geotechnical Specialist Key 6.91 31.5 24.59
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 17
13 Della Permata Social and Environmental Coordinator
Key 7.08 31.66 24.58
14 Gilbert Matheus Architect
Key 1.8 3 1.2
15 Budi Prati Social and Environmental Specialist
Key 1.5 10 8.5
Non Key Personnel (National)
1 Utami Kusumaningrum
Office Manager Non Key 12.2 37.98 25.78
2 Ermien Fatmajulia Accounting Specialist Non Key 9.94 35.98 26.04
3 Devi Ayudya Satriani Bilingual Secretary Non Key 10.14 36.68 26.54
4 Taufik Adi Wijaya GIS - IT Support Non Key 3.32 29.27 25.95
5 Darning Engineering Support 1 / Drafting
Non Key 10.93 36.71 25.78
6 Safrizal Atmawijaya Office Boy
Non Key 11.67 37.45 25.78
7 Fiana Fauzia Assistant Professional Staff/Technical Support for CPMU
Non Key 5.15 31.92 26.77
8 Harry Rachman Hermawan
Engineering Support 2 / Drafting
Non Key 8.95 13.49 4.54
9 Nur Kharismawati Utami
Engineering Support 3 / Drafting
Non Key 8.95 12 3.05
11 Siswanto Programmer
Non Key 1.9 4.8 2.9
12 G. Andi Wibowo Engineering Support 4 / Drafting
Non Key 4.78 4.89 0.11
13 Saipul Bahri Engineering Support 5 / Drafting
Non Key 5.32 11.99 6.67
14 Indra Gunawan Engineering Support 6 / Drafting
Non Key 5.32 11.99 6.67
15 Zefrey Yosep Zulfikar Engineering Support 7 / Drafting
Non Key 2.76 9.8 7.04
16 Khairunisa Pane Document Controller
Non Key 8.99 34.66 25.67
17 Kuswinarni Pranyati Technical Translator
Non Key 3.5 29.5 26
18 Ade Hayati Administrator
Non Key 8.81 34.82 26.01
MAKASSAR
Key Personnel (International)
1 David Kettlewell City Office Leader / Sewerage Construction Supervisor - Makassar
Key 2.1 25.1 23
Key Personnel (National)
1 Supiyanto Sewerage Engineer Key 1.5 26.5 25
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 18
9 Nursiah Nukma Public Relations / Sanitation Marketing Specialist
Key 1.7 26.7 25
Non Key Personnel (National)
1 Andi Yuliandar Office Manager Non Key 2 26.57 24.57
2 Erni Mansyur Accounting Specialist Non Key 1.56 26.6 25.04
3 Marlina Bilingual Secretary Non Key 1.9 26.83 24.93
4 Sakriandi Ikhwan Upara
GIS - IT Support Non Key 1.4 26 24.6
17 Abdur Rahman Office Boy Non Key 1.93 26.83 24.9
PEKANBARU
Key Personnel (National)
9 Johan Khadafi Public Relations / Sanitation Marketing Specialist
Key 2.1 23.1 21
Non Key Personnel (National)
1 Titisari Hermani Office Manager Non Key 1.8 25.23 23.43
2 Dea Arsitasari Accounting Specialist Non Key 1 25 24
3 Helen Ahyar Bilingual Secretary Non Key 1.2 25.25 24.05
9 Widya Wannenda Reza
Field Supervisor 1 Non Key 0.06 24 23.94
10 Abdul Gafar Field Supervisor 2 Non Key 0.06 24 23.94
11 Meidinel Field Supervisor 3 Non Key 0.06 24 23.94
12 Busra Effendi Field Supervisor 4 Non Key 0.06 24 23.94
17 Aldi Norman Office Boy Non Key 1.2 24.9 23.7
18 MHD Fizlal Padli Guard 1 Non Key 0.8 25.2 24.4
19 Muhammad Faisal Guard 2 Non Key 0.8 24.9 24.1
Summary of Inputs to Date
A summary of the overall person-month inputs to date is given in Table No. 3-6 below:
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 19
Table 3-6: Summary of Staff Inputs to Date (Person-Months)
CITY TOTAL
ADDENDUM NO. 2
USED TO LAST PERIOD
USED THIS PERIOD
TOTAL USED
REMAINING
JAKARTA
Key International 102.45 36.57 7.26 43.83 58.62
Key Local 340.97 82.88 7 89.88 251.09
Non-Key Local 420.85 111.1 15.02 126.12 294.73
TOTAL 864.27 230.55 29.28 259.83 604.44
MAKASSAR
Key International 37.1 1.13 1 2.13 34.97
Key Local 148.69 1.09 1 2.09 146.6
Non-Key Local 446.98 5.34 5 10.34 436.64
TOTAL 632.77 7.56 7 14.56 618.21
PEKANBARU
Key International 36.1 0 0 0 36.1
Key Local 140.6 1.1 1 2.1 138.5
Non-Key Local 431.04 1.2 5 6.2 424.84
TOTAL 607.74 2.3 6 8.3 599.44
JAMBI
Key International 32 0 0 0 32
Key Local 100.5 0 0 0 100.5
Non-Key Local 346 0 0 0 346
TOTAL 478.5 0 0 0 478.5
GRAND TOTAL 2583.28 240.41 42.28 282.69 2300.59
MSMIP TOTAL
ADDENDUM NO. 2
USED TO LAST PERIOD
USED THIS PERIOD
TOTAL USED
REMAINING
Key International 207.65 37.7 8.26 45.96 161.69
Key Local 730.76 85.07 9 94.07 636.69
Non-Key Local 1644.87 117.64 25.02 142.66 1502.21
TOTAL 2583.28 240.41 42.28 282.69 2300.59
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 20
This is shown graphically in Figure below:
Figure 1: Person Months Used and Remaining
Development of MSMIP Website
Status of Website Development
The updated status of the website development is given in Table 3-7 below:
Table 3-7: Website Features
No Contents Status
1 Web Site MSMIP 1. Schedule : create and develop form February until July 2018 2. Approval : already presented on PPLP & KIP Cipta Karya PUPR 3. Framework : Bootstraph and Codeigniter CSS and Java Script 4. Hosting : just propose to Pusdatin PUPR for online web this week by CPMU
2 GIS for all infrastructures is built especially the wastewater piping network
1. Makassar: C1, C2, B2 & B3 already build 2. Pekanbaru : SC1, SC2 & NC already build 3. All of the UTM Model still converting to Geo Mode 4. All GIS Data will install in Hosting SIGI.GIS.PUPR next week
3 MIS Monev Application that can be logged in is limited by the parties according to their needs
Will be created after e-project management reporting already developt by programmer
4 E-project management reporting, where in time it will be integrated with MIS Monev Application from the Ministry of PUPR
SMEC still negotiating with CPMU regarding the vendor that will create and developt the application which is needed
143
94
46
1,502
637
162
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Non-Key Experts - Local
Key Experts - Local
Key Experts - International
Days Used Days Remaining
Period Elapsedto Date 36%
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 21
Required Interim Outputs
At a meeting held on 22 October 2018, CPMU set out some interim requirements which were to be
completed by 10 November 2018. PISC will endeavor to achieve this milestone.
Addendum No. 2
Addendum No. 2 was submitted on 24 October. This was reviewed by PKK Contracts Evaluation Committee
who requested further justification for some positions.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 22
ENVIRONMENTAL, GENDER, AND SOCIAL SAFEGUARDS
Environmental Aspect
AMDAL Document (GOI Requirement)
As mentioned in the previous report, all three subprojects (in Makassar, Jambi, and Pekanbaru) under
MSMIP are required to update their Environmental Document due to the change in WWTP technology. In
accommodating this updating process, PISC has provided detail information on the WWTP technology and
the coverage area of the subprojects in Makassar and Pekanbaru which should then be included in the
environmental screening form. This screening will be followed by the issuance of an official letter from the
Local Environmental Agency on the recommendation of the type of environmental document (AMDAL,
UKL-UPL, or others). Refer to this letter, Local Government must prepare the recommended
environmental document as a basis to request Environmental Permit.
In October 2018, PISC obtained a copy of official letter from Pekanbaru Environmental Agency (Letter No.
660/DLIHK/11/664, dated 24 September 2018) confirming that Local Government of Pekanbaru is
required to update the UKL-UPL document for their subproject activity.
IEE Document (ADB Requirement)
The IEE document for Makassar (Losari) Off-Site Wastewater Collection System and Treatment (January
2013) has been updated and sent to CPMU and ADB on 3rd October 2018. Meanwhile the IEE document
for Pekanbaru City Off-Site Wastewater Collection System and Treatment (January 2013) is still under
preparation awaiting final DED of WWTP process option and other supporting secondary data from
Pekanbaru City Statistical Office.
Semi-Annual Environmental Monitoring Report (ADB Requirement)
The first Semi Annual Environmental Monitoring Report (revised) has been submitted to CPMU and ADB
on 23rd October 2018.
Gender and Social Development
Current Status
4.2.1.1 Socialization
As of September 2018, Makassar City Government (LG), represented by the Publics Work Agency, has
carried out 8 socializations in 8 urban villages ‘kelurahan’. These socializations were funded by Makassar
City 2018’s budget. The future socialization will be covered under 2019’s budget.
For Pekanbaru city, one public consultation was carried out on 30 August 2018. This public consultation
was spearheaded by Satker PSPLP Riau Province. Next public consultation will be scheduled in the
beginning of November 2018.
The PISC’s Public Relation Specialist of Makassar and Pekanbaru has been deployed to their respective
cities on 10 September 2018 and 26 September 2018 to assist the socialization activities in each city.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 23
4.2.1.2 LARP Pekanbaru
PISC conducted the coordination meeting in Bappeda Pekanbaru City, 25 October 2018 concerning
Coordination Meeting with Bappeda Pekanbaru City, BPN Pekanbaru City, CPMU, LPMU, Satker and PPK
on Social Safeguard and Involuntary Resettlement and Capacity Building on LARAP in 26 October 2018;
update data of Inventory of Losses-Pekanbaru through meeting with APs in Bambu Kuning; and conducted
survey/inventory of temporary AHs/APs along the CWS network/pipe alignment (3 streets: Jl. Sudirman,
Jl. Tanjung Datuk, and Sumber Sari).
4.2.1.3 Public Disclosure Pekanbaru
The draft of Project Information Booklet (FIP) is under updated by PISC, which is consider environmental,
social and gender.
4.2.1.4 Survey to Identify Criteria for Vulnerable Households
All locations (Makassar, Jambi, and Pekanbaru) are supportive of undertaking a survey to better
understand the necessary criteria to select ‘vulnerable’ households for connection under the project. The
2nd revision of TOR - Identify Criteria for Vulnerable Households - survey for WWTP Makassar, Pekanbaru
and Jambi has been submitted to CPMU and PPK on 23 October 2018.
4.2.1.5 Sanitation and Gender in Policy (Workshop)
Mainstreaming Sanitation and Gender into policy training. CPMU has suggested that it may be most
effective to host a one-day workshop to cover this topic consisting of 30-40 participants and this is
proposed for February 2019.
The 2nd revision of Workshop TOR has been submitted to CPMU and PPK along with the vulnerable household TOR on 23 October 2018.
4.2.1.6 Summary
A summary of all activities is given in Table 4.1 below:
Table 4-1 Summary Table of Socialisation Activies Completed in this Reporting Period
No Tasks Action By
Status update (9 November 2018)
I. MAKASSAR CITY
A. Preconstruction Phase
1 IEE updated PISC Completed, waiting for ADB Review comments.
2 AMDAL & Environmental Permit Status
LAC On going process,
6 Monitoring and reporting on social safeguards/resettlement aspect
PISC and CPMU 1st semi-annual monitoring report submittedAwaiting further ADB comments.
B. Construction & Operation and Maintenance Phases
1 Implementation and monitoring of construction mitigation plan and measures
Contractor, LPMU, PISC/National
No construction yet
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 24
No Tasks Action By
Status update (9 November 2018)
Social Safeguards Specialist
3 Monitor implementation of Grievance Redress Mechanism (GRM)
LC City Sewerage Environmental Complaints Committee (CSECC) not organized
4 Reporting on safeguards/Environmental aspects
1st semi-annual monitoring report submitted. Awaiting further ADB comments.
II. JAMBI CITY
A. Preconstruction Phase
1 IEE updated PISC On-going and draft partial update will be made available before end of month. Completion depends on DED information and recent public consultation results
2 AMDAL & Environmental Permit Status
LAC
6 Monitoring and reporting on safeguards/environmental aspect
PISC and CPMU 1st semi-annual monitoring report submitted. Awaiting further ADB comments.
B. Construction & Operation and Maintenance Phases
1 Implementation and monitoring of construction mitigation plan and measures
Contractor, LPMU, PISC/National Environmental Safeguards Specialist
Construction not yet started
3 Monitor implementation of Grievance Redress Mechanism (GRM)
-do- City Sewerage Environmental Complaints Committee (CSECC) not organized
III. PEKANBARU CITY
A. Preconstruction Phase
1 IEE updated PISC On going. Draft partial update will be made available before end of month. Completion depends on DED information and recent public consultation results
2 AMDAL & Environmental Permit Status
LAC
6 Monitoring and reporting on safeguards/environmental aspect
PISC and CPMU 1st semi-annual monitoring report submitted. Awaiting further ADB comments.
B. Construction & Operation and Maintenance Phases
1 Implementation and monitoring of construction mitigation plan and measures
Contractor, LPMU, PISC/National Environmental
Construction not yet started
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 25
No Tasks Action By
Status update (9 November 2018)
Safeguards Specialist
3 Monitor implementation of Grievance Redress Mechanism (GRM)
-do- City Sewerage Environmental Complaints Committee (CSECC) not organized
4.3 Social Safeguard Activities for Next Period
The social safeguard activities to be carried out in the next reporting period are given in Table 4.2 below:
Table 4-2: Social Safeguards Activities for Next Period
No Tasks Action By
I. MAKASSAR CITY
A. Preconstruction Phase
1 Data Analysis and reporting on survey results. -do-
2 Land Acquisition (Information disclosure/consultation with APs on entitlement/compensation) and actual payments.
LAC
3 Complete all land acquisition documentation including decision of higher court on the ownership claim by one person.
LPMU (Specifically Dinas PU and LAC).
4 Full Disclosure of Construction Impacts and Mitigation Plan including grievance redress mechanism (GRM) prior to commencement of sewerage Civil works. Formulate and distribute brochures.
PPIU/Satker, LPMU and PISC.
5 Due Diligence Report and Corrective Action Plan (DDR and CAP) updated and submitted to CPMU for review and forwarding to DGHS for submission to ADB and request for No Objection.
PISC/International Social Safeguards Specialist and CPMU.
6 Monitoring and reporting on social safeguards/resettlement aspect. PISC and CPMU.
B. Construction & Operation and Maintenance Phases
1 Implementation and monitoring of construction mitigation plan and measures.
Contractor, LPMU, PISC/National Social Safeguards Specialist.
2 Implement and monitor income restoration and other safeguards outcomes and their impacts on the standards of living of Aps.
LPMU and PISC/National Social Safeguards Specialist.
3 Monitor implementation of Grievance Redress Mechanism (GRM) as outlined in the DDR and CAP.
-do-
4 Reporting on safeguards/resettlement aspects.
II. JAMBI CITY
A. Preconstruction Phase
1 Complete land acquisition documentation for WWTP and Pumping Station: a. Copies of checks/proof of payment issued to the 4 landowners b. Copy of check/proof of payment for the acquired land for the pumping station (500m2).
Dinas PU with support from Pemda and BPN.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 26
No Tasks Action By
2 Mapping and identification of construction affected persons/households along pumping station access road and CWS/pipeline network.
PISC and Dinas PU.
3 Conduct socio economic survey interviews with APs/AHs along access road to pumping station and CWS/pipeline network.
LPMU (PU, Bappeda and LAC).
4 Data Analysis and reporting on survey results. -do-
5 Land Acquisition (Information disclosure/consultation with APs on entitlement/compensation) and actual payments.
LAC with support from City Government.
6 Issuance of land certificate for acquired WWTP land by BPN. Assistant Secretary, Pemda and Dinas PU.
7 Full Disclosure of Construction Impacts and Mitigation Plan including grievance redress mechanism (GRM) prior to commencement of sewerage Civil works. Formulate and distribute brochures.
PPIU/Satker, LPMU and PISC.
8 LARAP updated and submitted to CPMU for review and forwarding to DGHS for submission to ADB and request for No Objection.
PISC/International Social Safeguards Specialist and CPMU.
9 Monitoring and reporting on social safeguards/resettlement aspect. PISC and CPMU.
B. Construction & Operation and Maintenance Phases
1 Implementation and monitoring of construction mitigation plan and measures.
Contractor, LPMU, PISC/National Social Safeguards Specialist.
2 Implement and monitor income restoration program for specific APs based on Final LARAP.
LPMU and PISC/National Social Safeguards Specialist.
3 Monitor implementation of Grievance Redress Mechanism (GRM) as outlined in the LARAP.
-do-
4 Reporting on safeguards/resettlement aspects.
III. PEKANBARU CITY
A. Preconstruction Phase
1 Send photocopy of land documentation for WWTP (Berita Pembayaran between land owners and Pemda) to PISC.
BPN and Dinas PU.
2 identify impacts and APs/AHs based on DED final alignment of the sewers that may affect the entrance of the houses or business establishments.
PISC, CPMU, LPMU.
4 Data Analysis and reporting on survey results. -do-
5 Land Acquisition (Information disclosure/consultation with APs on entitlement/compensation) and actual payments.
LAC.
6 Full Disclosure of Construction Impacts and Mitigation Plan including grievance redress mechanism (GRM) prior to commencement of sewerage Civil works. Formulate and distribute brochures.
PPIU/Satker, LPMU and PISC.
7 LARAP updated and submitted to CPMU for review and forwarding to DGHS for submission to ADB and request for No Objection.
PISC/International Social Safeguards Specialist and CPMU.
8 Monitoring and reporting on social safeguards/resettlement aspect. PISC and CPMU.
B. Construction & Operation and Maintenance Phases
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 27
No Tasks Action By
1 Implementation and monitoring of construction mitigation plan and measures.
Contractor, LPMU, PISC/National Social Safeguards Specialist.
2 Implement and monitor income restoration program for specific APs based on Final LARAP.
LPMU and PISC/National Social Safeguards Specialist.
3 Monitor implementation of Grievance Redress Mechanism as outlined in the LARAP.
-do-
4 Reporting on safeguards/resettlement aspects.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 28
CONTRACT IMPLEMENTATION
Coverage of Project
The planned coverage of the project is given in Table 5-1 below:
Table 5-1: Project Coverage by City
No Description Units Makassar Pekanbaru Jambi
1 Connections
Domestic nr. 9,000 9,900 8,900
Commercial nr. 4,100 1,100 1,400
2 Sewer km..
115 130 103
3 WWTP
Capacity MLD 16.1 8.1 7.6
Area Ha 6.0 8.0 6.0
Contract Summary
A summary of all 12 contracts is given in Table below:
Table 5-2: Summary of Contract Packages
Note : * procurement in accordance with ADB Guidelines
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 29
Contract Status
The current status of the contract preparation is given in Table 5-3 below:
Table 5-3: Current Status of Contract Preparation
Summary of Completed Activities
The following activites were carried out during the reporting period:
Draft bidding documents for the design-build contract B1 of Makassar WWTP were completed and
submitted to ADB for review; their comments were received.
Bidding documents for Contracts B2 in Makassar and NC in Pekanbaru were completed and
submitted to ADB for review; their comments were received.
During the previous reporting period, PISC had completed bidding documents for:
Contracts C1 and C2 for Makassar.
Contracts SC1 and SC2 for Pekanbaru.
These contracts C1, C2, SC1 and SC2 have now been procured and contract signature is imminent.
Makassar WWTP
5.4.1.1 Bidding Documents for ICB Design Build Procedure
Bidding documents were prepared for a 2-stage procedure. PISC then carried out a Value Engineering
Review of the peak factors used in the MWH Design together with a Design Review of the entire project.
This resulted in a recommendation to CPMU that the peak factors used by MWH were too high and that
a more usual peak factor of 2 was appropriate. Accordingly, the bidding documents were finalized using
a peak factor of 2 which then resulted in a cost saving to the project of approx. $2 million.
Ref Location Contract Bid Type TypeEstimated
Cost (USD M)
Design
Completion
Date
Status
1 Makassar C1 NCB Sewerage System Northwest 13.72 Completed Contractor Selected
2 Makassar C2 NCB Sewerage System Northwest 13.43 Completed Contractor Selected
3 Pekanbaru SC1 NCB Sewerage System South 15.33 Completed Contract Signed
4 Pekanbaru SC2 NCB Sewerage System South 10.68 Completed Contract Signed
5 Makassar B2 NCB* Sewerage System 13.70 31.08.2018 Bidding Documents Submitted, Comments Received
6 Pekanbaru NC NCB* Sewerage System Northwest 21.09 31.08.2018 Bidding Documents Submitted, Comments Received
7 Makassar (B3)C3 NCB Sewerage System 11.72 30.09.2018 Design development
8 Makassar B1 ICB* WWTP 20.06 30.09.2018 Bidding Documents Submitted
9 Pekanbaru B1 NCB* WWTP 12.15 31.01.2019 Local tender, treatment process selected, design development
10 Jambi B1 NCB* WWTP 6.60 28.02.2019 Local tender, treatment process selected, design development
11 Jambi B2 NCB* Sewerage System East 18.25 31.11.2018 Under preparation
12 Jambi C NCB Sewerage System West 14.10 31.11.2018 Under preparation
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 30
The lower peak factor adopted also resulted in a reduction in pump size at PS B which further allowed the
line between PS B and WWTP to operated as a gravity main. For ease of design, PS B was included with
the WWTP in the B1 design-build package.
PISC still has not received the maximum flood discharge level for the Jongaya Canal, despite numerous
requests.
5.4.1.2 Insufficient Number of Connections at WWTP Commissioning Stage
In the event that there is an insufficient number of connections (and hence insufficient wastewater flow)
to the WWTP at the time of commissioning, the Contractor will be unable to commission the plant and
the investment cannot be properly utilized until such time as sufficient wastewater is received.
5.4.1.3 Remedy for Contractors Inability to Properly Operate the Plant during DNP
In the event that there is an insufficient number of connections (and hence insufficient wastewater flow)
to the WWTP at the time of OPEX verification during DNP, the aggregate OPEX cost of the individual
modules will be taken.
Makassar Networks
5.4.2.1 Package B2
The final bidding documents were issued to CPMU; it is expected that the tender will be launched in early
2019.
5.4.2.2 Package B3
The preparation of Contract B3 (drawings, cost and bidding documents) is on-going and will be finalized
after the final cost of WWTP Pekanbaru or Jambi has been determined, as the re-allocation budget is set
and approved by ADB.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 31
5.4.2.3 Package C1 and C2
The trunk sewer, pumping station and pumping main Contract C1 and the network sewerage and 1,000
connections Contract C2 are nearing the end of the proposal evaluation period. The schedule given in the
LPSE website indicates that the Contract will be signed on November 07, 2018.
PISC’s supervision team has been coordinating with PPK Sulsel and communicating with all authorities to
obtain the Standard Operating Procedures to be followed to facilitate approval for the Contractors
working in the streets of Makassar.
The PISC supervision team has also been engaged in a series of site inspections and walking the pipe routes
to ensure the final design is appropriate for the current site condition. Furthermore, the team has been
working on the formats and procedures to be followed by the Contractor during the implementation of
the works.
Pekanbaru WWTP
The ground conditions at the WWTP site are extremely poor comprising approximately 10-14 m of peat
and very soft organic clay underlain by interlayered medium dense sandy and stiff clayey soils. The
settlement of these thick layers of peat and very soft organic clay under fill and structures will be very
large. For this reason, it has been found necessary to support the main structures, the roadways and the
interconnecting pipework on a grid of precast prestressed piles with pile caps and structural fill (basal
reinforcement piled embankment). Green areas are unsupported and will be re-filled as settlement
occurs. The cost of these foundation works is substantial amounting to in excess of $5 million.
The construction of the access road has been completed but no provision has been made for the poor soil
conditions. As a result, a new access road on piled foundations shall be included as part of the worjks
contract.
Sludge will be treated by chemical conditioning, dewatering and liming and is planned to be disposed
off-site (at the city’s landfill site).
Pekanbaru Networks
The layout of the Pekanbaru Catchment Area is given in Figure 2 below:
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 32
Figure 2: Layout of Pekanbaru Sewerage Collection Catchment
Tendering of the two network contracts SC1 and SC1 were completed during the reporting period and
contract award is imminent.
Bidding documents for Contracts NC have been prepared during this reporting period and were submitted
to CPMU. Comments from ADB have now been received and are being addressed.
Jambi WWTP
No WWTP design work was carried out during the reporting period.
Jambi Networks
The layout of the Jambi Catchment Area is given in Figure 4 below:
SC1
SC2
NC
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 33
Figure 3: Layout of Jambi Sewerage Collection Catchment
Drawings, cost estimate and bidding document for B2 (Loan funded) and C (APBN funded) are currently
under preparation.
The land expropriation for the access road to the transfer pumping station still has not been resolved.
Progress during the Reporting Period
Completion of the MBBR Design and Tender Documents for Design and Build Scheme in Makassar. Preparation of Cost Estimate and Tender Documents for sewerage packages financed by Loan for
both Makassar (B2 and C3 / B3). Commence preparation of DED of CAS (Conventional Activated Sludge) WWTP for Pekanbaru. Preparation of the MBBR Concept Design for Design and Build Scheme in Makassar.
Preparation of the MBBR Cost Estimate. Prepare WWTP Technology for Jambi. Preparation of Socialisation Activities for SKPD, AP (affected people) and beneficiary. Preparion of Vulnerable Persons Survey for Makassar, Pekanbaru and Jambi.
o Development of Drawings.
o Development of Bills of Quantities.
Preparation of Cost Estimate and Tender Document for sewerage packages financed by Loan for both Makassar (B3) including;
o Development of Specifications.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 34
o Development of Tender Forms.
o Development of Drawings.
o Development of Bills of Quantities.
Prepare Design, Cost Estimate and Tender Document for sewerage packages financed by APBN (Package C) /Loan (Package B2) for Jambi.
Awaiting Signed for Network Contracts C1 and C2 for Makassar. Awaiting approval from ADB Contract B1 and B2 in Makassar and Contract NC in Pekanbaru. Tendering of Network Contracts SC1 and SC2 for Pekanbaru.
Value engineering reviews of existing designs. Submission of Addendum No. 2. Submission of Monthly Reports Nos. 10 (July 2018) and 11 (August 2018). Provision of updated Project Schedule (attached to this report). Continuous updating of the Risk Register.
Development of Project Website. Regular meetings held with CPMU and PPK.
Mobilisation of Pekanbaru City Office with support staff.
Training/Workshops
There is procurement clinic for ADB Bidding Documents and procedure for 3 Bidding Committee in
Makassar, Pekanbaru and Jambi held by ADB-IRM on October 18, 2018
Arrangement for O&M of Project Facilities
No current actions have been undertaken regarding O+M of Project Facilities. As a result, it may be
necessary to add some component in the works contracts to allow for operation and personnel costs for
the initial 1-year period.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 35
MAJOR ISSUES AND PROPOSED REMEDIAL ACTIONS
Key Issues
The key issues from this reporting period are:
Design Flows at Makassar WWTP
Because of the change in treatment process at Makassar WWTP from ABR to MBBR, the peak flow factor
used in MWH Design for the WWTP (3.6) were re-assessed by PISC as part of a value engineering exercise.
The bidding documents were then finalized and submitted using a peak factor of 2 throughout; this has
resulted in a cost saving of almost $2 million.
Because of the complex interaction between PS B and WWTP, PS B has been included in the B1 design-
build package. In addition, the rising main between has been re-designed as a gravity main thereby
reducing the unwieldy size of the pumps.
Low Connection Rate in Initial Years
If the minimum number of connections are not realized at the completion of construction of the plant; the
Contractor will be unable to properly commission the works and could thus evade his repsonsibilities
under the contract.
In addition, for Makassar Design-Build project, he Contractor would also escape his contractual obligation
that the operating cost (OPEX) of the WWTP would be less than his guaranteed tender OPEX value.
Pumping House
Currently, it is still being processed to purchase land for Pekanbaru Pump House and Pump House access
road in Jambi
Pekanbaru WWTP Site
The Pekanbaru WWTP site is highly unsuitable for the construction of the plant. Not only is it located in
the floodplain of the nearby Sail and Siak rivers and at the time of writing, it and the public road leading
thereto are currently wholly submerged. Furthermore, the existing ground conditions comprise 10-15
metres of peat subsoil which require that all main structures, (including the 60m long access road from
the existing public road to the iste) will require to be piled at significant extra cost (c. $5m).
Social Safeguards, Resettlment and Gender Awareness
It is unclear if Local Government are undertaking key tasks required to meet the demands for Social
Safeguards, Resettlement, and Gender Awareness. Due to new regulation concerning effluent standard,
the technology changes for all three WWTP need AMDAL review that should be conducted by Local
Government and following by environmental permit from Mayor.
The 1,000 connections for Makassar have been identified and also for Pekanbaru, however, this is not yet
the case for Jambi. However, although the identification has been carried out, until now, the local
government has not conducted socialization programmes for prospective users. The socialization is just
limited to government officers and not yet directly for the people.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 36
FINANCIAL STATUS
Contract Awards
No contracts have yet been signed; accordingly, no payment drawdowns have been made and the financial
status remains unchanged from Table 7.1 below except for payments to PISC.
Table 7-1: Loan and Disbursed Amount
Description ADB Government
Total OCR AIF Central Local
A. Investment Cost
1. Land Acquisition and Site Preparation
-
-
-
11.55
11.55
Sub Total 11.55 11.55
2. Civil Works
A. Jambi
- Waste Water Treatment Plant/ WWTP
- Wastewater Sewer System/ WSS –West
- Wastewater Sewer System/ WSS –East
- Property Connection
- Community - based System
14.75
-
-
-
-
-
19.30
-
-
-
-
-
14.36
0.50
-
-
-
-
4.95
0.88
14.75
19.30
14.36
5.45
0.88
Sub Total 14.75 19.30 14.86 5.83 54.74
B. Makassar
- Waste Water Treatment Plant/ WWTP
- Wastewater Sewer System/ WSS –C
- Wastewater Sewer System/ WSS –NW
- Property Connection
- Community - based System
27.20
13.40
-
-
-
-
-
-
-
-
-
-
24.31
0.50
-
-
-
-
5.06
1.10
27.20
13.40
24.31
5.56
1.10
Sub Total 40.60 - 24.81 6.16 71.57
C. Pekanbaru
- Waste Water Treatment Plant/ WWTP
- Wastewater Sewer System/ WSS –N
- Wastewater Sewer System/ WSS –S
- Property Connection
- Community - based System
12.90
-
-
-
-
-
20.70
-
-
-
-
-
22.44
0.44
-
-
-
-
4.95
1.10
12.90
20.70
22.44
5.39
1.10
Sub Total 12.90 20.70 22.88 6.05 62.53
3. Consulting Services
- PISC – ADB
- Central Government
- Local Government
11.75
-
-
-
-
-
-
0.44
-
-
-
0.19
11.75
0.44
0.19
Sub Total 11.75 - 0.44 0.19 12.38
4. Recurrent Cost
- Project Management by Government
- Project Management by Local Government
-
-
-
-
0.77
-
-
1.54
0.77
1.54
Sub Total - - 0.77 1.54 2.31
5. Financial Charge During Construction
- Interest during Construction
- Commitment fee
-
-
-
-
8.44
0.32
-
-
8.44
0.32
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 37
Description ADB Government
Total OCR AIF Central Local
Sub Total - - 8.76 - 8.76
Grand Total 80.00 40.00 72.52 31.32 223.84
Based on PAM –Revised -Nov-2016 ( PN 43251-025 )
Source: MSMIP PAM (Revised), November 2016
PISC Payments to Date
PISC received payments for July and August invoices (nos. 007 and 008) as set out in Table 7.2 below.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 38
Table 7-2: Disbursements to date to PISC
Allocated
( USD )( USD )
in Mill
( IDR )
in Billion
( USD )
in Mill
( IDR )
in Billion
( USD )
in Mill
( IDR )
in Billion
1 2 3 4 5 6 7 8 9 10 11 12
ADB OCR 11.75
Total - 6,508,205.00 60,706,784,200.00
DIP - 6,508,205.00 60,706,784,200.00
Tax - - -
Total disbursement last period 1,222,548.24 12,066,758,029.00 0.00 0.00
Disbursement plan :
- Invoice JK 007 to JK 008 144,850.61 1,469,527,237.00 0.00 0.00
TOTAL 0.00 11.75 6,508,205.00 60,706,784,200.00 1,367,398.85 13,536,285,266.00 5,140,806.15 47,170,498,934.00
No Location Category Works /City/PCSS
Source
of
Fund
Amount
Contract No /Date / type of proc / Duration
Use of Fund Balance of Fund
Contracted
1. Jambi City
2. Makasar City
3.Pekan Baru
Project Implementation Support /PSIC -
Metropol i tan Sanitation Management
Investment Project /MSMIP
SMEC International Py LTD in JV with
Stantec Austra l ia Pty Ltd With Sub
Consultant PT.Infratama Yakti ,PT SMEC
Denka Indones ia , PT Amurwa
International and PT.Widyagraha Asana ,
No contract : HK.02.03./MSMIP-KONS
/X/11/207 , Duration 2 Oct 2017 - 31 Oct
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 39
PISC Current Invoices
PISC did not submit any invoice during the reporting period.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 40
COMPLIANCE WITH LOAN COVENANTS
Since no physical and financial activities has been carried out during the reporting period, no audit
activities were conducted. In any case, PISC financial activities had been audited in July 2018 (advance
payment only), and a draft findings report was issued. The final version of this report is now awaited.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 41
ACTIVITIES PLANNED FOR NEXT REPORTING PERIOD
The following activities are planned for the next reporting period (i.e. Nov. 2018):
Makassar
The following activities are planned for Makassar during the next reporting period.
Commencement of construction; Contract C1 and C2 (APBN funded).
Tendering of Contract B2 (Loan Funded). Continue to conduct socialization for 1,000 connections. Vulnerable Survey for 200 respondents in the target areas. ADB review mission.
Pekanbaru
The following activities are planned for Pekanbaru during the next reporting period.
Commencement of construction; Contract SC1 and SC2 (APBN funded). Tendering of Contract NC (Loan Funded). Continue design for WWTP and preparation of Bidding Documents.
Continuing to conduct socialization for 1,000 connections. Vulnerable Survey for 200 respondents in the target areas.
ADB review mission.
Jambi
The following activities are planned for Jambi during the next reporting period.
Preparation of Procurement for Contract West (APBN funded) - (Drawings, Engineering
Estimate and Technical Specifications) and ready for tender. Complete bidding documents for Contract East (APBN funded) - (Drawings, Engineering
Estimate and Technical Specifications) and ready for tender.
Commence design for WWTP and prepare Bidding Documents. Conducting socialization for 1,000 connections.
Vulnerable Survey for 200 respondent in the target areas. ADB review mission.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 42
APPENDIX A: UPDATED PROCUREMENT PLAN
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
43
No.
Contracts/
Packages
Sources
of Funds
Cost
(USD
Million)
BID Type
Q1 Mar Apr May Jun Jul Aug Sept Oct Nov Dec Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
A APBD 0.48 NCB
Connections for 9,300 units A2 APBD 4.65 NCB T T T T
WWTP B1 ADB - OCR 6.60 NCB*
Wastewater Sewer System East B2 ADB - AIF 18.25 NCB*
Wastewater Sewer System West C APBN 14.10 NCB
Wet Connections C
A APBD 2.19 NCB
Connections for 13,000 units A2 APBD 6.50 NCB T T T T
WWTP B1 ADB - OCR 17.70 ICB*
Wastewater Sewer System Collection B2 ADB - OCR 16.35 NCB* PQ + Tender
Wastewater Sewer System Collection C3 APBN 11.72 NCB PQ+ Tender
Wastewater Sewer System North West C1 APBN 13.72 NCB
Wastewater Sewer System North West C2 APBN 13.43 NCB
Wet Connections C2
PEKANBARU
A APBD 1.65 NCB Tender
Connections for 10,000 units A2 APBD 5.00 NCB T T T T
WWTP B1 ADB - OCR 12.15 NCB* PQ + Tender
Wastewater Sewer System North NC ADB - AIF 18.78 NCB*
Wastewater Sewer System South SC-1 APBN 15.04 NCB
Wastewater Sewer System South SC-2 APBN 10.44 NCB
Wet Connections SC2
DL
Construction DL
Site Preparation (Land Purchase and Earthworks)
Site Preparation (Land Purchase and Earthworks)
Site Preparation (Land Purchase and Earthworks)
MAKASSAR
PQ + Tender
DL
C C
Construction (30 months) DL
Construction
DL
DL
PQ + Tender DL
C C
Construction (33 months) DL
Construction DL
C
Construction (30 months) DL
DL
Construction
C C C
EEWConstruction (33 months)
2023
C C C C
PQ + Tender
PQ + Tender
Construction (24 months)
2018 2019 2020 2021 2022
PQ + Tender
JAMBI
DL
Name
Tender
PQ+Tender
PQ+Tender
Construction (30 months)
Construction (30 months)
Construction DL
PQ + Tender
PQ + Tender
Construction (30 months)
Construction (30 months)
Construction (30 months)
Construction (30 months)
DL
DL
Construction
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 44
APPENDIX B: MINUTES OF MEETINGS
MINUTES OF MEETING
ATTENDEES:
No Name Company Email Address Mobile Phone
1 Asri Indiyani CPMU [email protected] 0818225754
2 Panggih Hidayat PLP Strategis [email protected] 081327063089
3 Benny S PISC [email protected] 081314301436
4 Budi Prati PISC [email protected] 08161861563
5 Della Permata PISC [email protected] 081296456307
6 M. Naufan D. Subdit AL PPLP [email protected] 0812115117493
7 Taufik Hidayat Subdit AL PPLP
8 MK. Eko Budi S. Asst. CPU MSMIP (021) 72797681
9 Seamus Baynes PISC [email protected] 085219000701
10 Fiana Fauzia PISC [email protected] 081281026113
11 Riana Puspasari ADB [email protected] 08128300030
12 Kuswinarni Pranyati ADB [email protected] 08174883834
Ref Discussion Item Action When Status
PROGRESS OF REVIEW DESIGN FOR MAKASSAR,
PEKANBARU AND JAMBI
1 Pak Seamus reported progress of PISC
Concerning Output and Reporting, the status is as
follows :
Ref :
Meeting Subject : Progress for Review Design for 3 Cities, Preparation for the Vulnerable Household Survey and Social & Gender Workshop, SOP Supervision Consultant
Day/Date of Meeting : Tuesday, 02/10/2018
Time : 02.00 – 04.45 pm
Venue : Meeting Room of KMO Building 7th floor
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 45
Ref Discussion Item Action When Status
a. Bidding Document of Makassar Treatment Plant
(submitted on 01 October 2018)
b. MPR No. 10 (submitted on 01 October 2018)
c. MPR No. 11 (will be submitted today, on 02
October 2018)
d. PMP (Project Management Plan) and RMK
(Rencana Mutu Kontrak) (this week)
e. QPR 4 (this week)
The other issues are :
PISC need more time to prepare design
Pekanbaru and Jambi Waste Water Treatment
Plant due to the change of technology. The initial
design with Aerated Lagoon technology was
made by Local Consultant in 2013 and does not
provides a additional value.
The design of CAS (conventional activated sludge)
will usually need 1 year to prepare but PISC will
be prepare it shorter and the full design of
Pekanbaru will be completed by February 2019,
and for the similar project (Jambi Sub project) will
be completed on 1-2 months after.
However, both propose schedule of DED for
Pekanbaru and Jambi does not affect the overall
schedule of project which is December 2022.
Pak Benny added that Jambi sewerage (Jambi
package): Drawings, Cost Estimate and Bidding
Document are one-month delay from the
previous schedule).
2 Pak Eko asked whether PISC can complete the
DED for WWTP Pekanbaru and Jambi earlier that
PISC proposed.
Pak Seamus explained that for full design, 1 year
normally end of 2020 and 2 year averagely. So, it
cannot squeeze it anymore.
Pak Seamus said that there is mis-information,
due to initially the existing drawings, but we
should review the existing drawings.
Pak Benny said that delay of construction will
occur within 3 months but still in project period.
Bu Asri mentioned that the final administration
process of MSMIP at end of 2022, and the
constructions should be complete before that.
She asked about the closing loan date and how
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 46
Ref Discussion Item Action When Status
about the payment for Consultant. PISC should be
on board until Dec 2022.
Pak Seamus said that the fund from ADB and in
the General Condition of ADB, it is stated that “no
retention”. It is not unusual in any project. PISC
propose to have 5-10% retention in Bidding
Document
Bu Asri asked during the DLP, do they still have
Consultant? Due to they still need it although
Intermittent only.
Bu Asri asked about during the DLP of the 1st year,
who will pay the salary for operator, the
Operation and Maintenance (electricity cost,
chemical). Due to for their internal regulations,
the Asset Hand Over process from PU to Local
Government takes almost 2 years.
Pak Seamus said that the LG should pay it.
Bu Asri explained that based on her experience
from the other project, as the common ways in
Indonesia, as Partial Hand Over. After
construction completion before DNP, After DNP it
is called Final Hand Over (FHO).
- firstly, the Operational Hand Over (LG will
operate)
- secondly, after 2 years, the Asset Hand Over,
as the Final Hand Over (official hand over
from the PU to LG). Some LG thinks that they
only responsible to pay costs like electricity
and chemical only.
Bu Asri is worried if LG cannot provide the fund.
How if the LG cannot provide it, maybe we can
pay it from project through the Provisional Sum
(regarding this, we should not inform the LG yet,
due to they have to fund it by themselves first).
In the Cooperation Agreement (PKS) stated that
the Operational Maintenance cost is not from
MPW.
Bu Asri recommended to start it before DNP 6 months before (for personal cost)
She also requests PISC to make the scheme for all cities, due to she will bring it to the Director for requesting the decision for OM cost, and maybe we should pay the Trainer for the Operators
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 47
Ref Discussion Item Action When Status
there. She will send the scheme of Jakarta and she will send it to TL. For Pekanbaru, Pak Seamus will make it today,
(completed with Partial and Final Hand Over).
Bu Asri requested PISC to calculate Indicative Cost for Project, on the next year budget data, including the added amount. In the next QPR, PISC shall submit the update of this issue.
Also, she requested the justification about the construction of WWTP in Makassar, why Pekanbaru needs 2 months longer than Jambi? Pak Seamus said that WWTP in Pekanbaru is
bigger than in Jambi.
The site in Pekanbaru is the worst, peat soil,
mainly for piling. We also handle about the road,
landscape, and foundation.
And for Pekanbaru Subproject, it is simpler (no
design and build method).
Regarding of O/M how?
Pak Seamus said that we assume that for
Makassar Sub project is more urgent.
According to pak Eko, if we can do the saving cost
much in Makassar, it can be transferred to fund
Pekanbaru Sewer (B3).
3 Bu Asri requested to Pak Seamus to provide the good
quality of the drawings in more technical,
justification, new schedule (6 months delay schedule)
4 Pak Taufik asked PISC to finish the DED and BOQ
for WWTP Pekanbaru in January 2019
Pak Seamus said we can. Due to most of
Mechanical Electrical, all identified. We will have
information and we will expedite it.
5 Bu Asri said that their Inspectorate will conduct
audit, so we should provide them the time line
of Engineering, and she requested Pak Seamus
to make one clear justification regarding the
project.
Pak Seamus said that the duration of
construction, for e.g. Package B1 Makassar 900
days (partial it takes over 2 years) and it can be
shorten into 2 years
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 48
Ref Discussion Item Action When Status
Pak Benny said that we also consider about the
connection issues in preparing construction time
for WWTP.
Then Pak Seamus said to discuss about this issue
later and not in today meeting.
6 Regarding the Pump Sta B in Makassar, Bu Asri
hoped that the MWH will agree it. Due to if the
MWH agrees with it, some revision will be made
on the Bidding Document. ADB only check the
Bidding Document and not the Technical
Specification.
Pak Benny said that the MWH requested 1 week
more to answer this issue.
6 Pak Eko asked when we will finish all documents,
in all forms of Hardcopy, softcopy (CD); before
sending it to ADB, send the Covering Letter to
PPK and cc to CPMU first. Due to they have to
review it first.
Pak Seamus said that we have sent them all
already by email, and hardcopy.
Bu Asri said that regarding the procedure, Pak
Panggih should check to make it safe during the
audit session.
7 Regarding Procurement, Pak Benny said that we have
duties to assist Pokja, see the last status of
Procurement.
8 Bu Asri asked about the establishment the website of
the project, to disclose everything. They contact the
Public Works website (Data and Information
Center/Pusdatin), and she asked about the content of
this website.
Pak Seamus said that we will discuss it with CPMU in
2 weeks later.
Bu Asri hopes that this system will be able to be used
by another project and just simply by log in and can
access data (for internal system)
9 Bu Riana from ADB recommended us to add some
sex/gender disaggregated data mostly in Chapter 8.
10 Regarding the PMP, Bu Asri requested us to send her
later, so shell will give us her comments.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 49
Ref Discussion Item Action When Status
11 Regarding the RMK.
Bu Asri recommended us to discuss with Pak Panggih
only and not with her.
PREPARATION OF WORKSHOP
11 The recent AMDAL (EIA) Status:
For AMDAL Makassar was made in 2016, but due
to the change of technology, it will be reviewed
next year.
For AMDAL Jambi is available, but they will repeat
the process due to the land is still incomplete
For AMDAL Pekanbaru, they will allocate it next
year.
Bu Asri commented that we should report the
updating information of project such as for AMDAL,
IT once a month not only for CPMU also LG.
Pak Seamus said that the Administrator will provide
it.
Pak Eko asked about the fund for the survey whether
is available or not.
Pak Eko also ask for the persons who do survey
whether they have the Surveyor Certificate issued
from PT Sucofindo due to related to the
accountability.
Pak Benny explained that they should come from the
Legal Entity not individual, and they should have
experience as surveyor before.
Bu Riana asked about the Makassar map, it shows
that the yellow one includes as the commercial area,
so we should make the Justification to the Review
Mission of ADB.
Bu Asri said that Satker has fund, if we will hold FGD,
we can use the Satker’s fund, except Training which
we should provide the fund. She recommended us to
contact the Satker first.
Bu Asri also requested us to change the Bill of
Quantity based on the format of DJK. Due to it should
be described in detail about the activities and the
amount.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 50
Ref Discussion Item Action When Status
Pak Eko also recommended us to see the billing rate
from Inkindo.
WORKSHOP IN JAKARTA
Regarding the ticket (flight ticket) for the Participants,
according to Bu Asri, they should pay it by
themselves. We only pay room only. Full board
meeting and 1 night only: opening at afternoon and
closing at night or the next day afternoon (half day
meeting package). This is due to the flight schedule
for these 3 cities are many. (so the participants have
not found difficulties to return to their origin regions).
The workshop will be held on February 2019.
Prepared by,
Kuswinarni Pranyati
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 51
MINUTES OF MEETING
Ref :
Meeting Subject : Meeting on The Discussion of Environmental and Social Safeguard
Document
Day/Date of Meeting : Jumat, 05/10/2018
Time : 10.30 – 12.30 WIB
Venue : ADB Meeting room, The Plaza Office Tower 11th Floor
ATTENDEES:
No Name Institution/
Company
Email Address Mobile Phone
1 Siti Hasanah ADB [email protected] 081514923234
2 Naning ADB [email protected] 087880084226
3 Budi Prati PISC [email protected] 08161861563
4 Della Permata PISC [email protected] 081296456307
5 Naufan
Dzikrurrahman
CPMU [email protected] 082115117493
6 Fiana Fauzia PISC [email protected] 081281026113
7 Ristradianti D.A PPLP Strategis [email protected] 081282823993
Ref Discussion Item Action Time Status
1 Discusion on Semi-Annual Monitoring Report:
a) Regarding the status of AMDAL document that
need to be revised, it is required to update the
recent progress to date. This also relates to
Environmental Permit process.
b) Monitoring report needs to explain not only
technical aspect, but also needs to provide
supporting administration data (activities, photos,
payment proof, budget, expert / related to the
requirement in the Addendum)
c) Monitoring report shall be more comprehensive
and the progress is explained in systematic
structure and consistent for each city. The report
could be divided per city using the same parameter,
or divided per parameter describing those 3 cities.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 52
Ref Discussion Item Action Time Status
d) If using “ADB Resettlement plan”, then the
evaluation parameter used must be the same and
included in the report along with its supporting
documents
e) It should be noted regarding the document
submission date (on the cover). The date of the
action plan contained in the report must be in line
with the report submission date.
f) Compliance status needs to consider previous
activities / progress.
g) Disclosure related to socialization needs to be input
(also additional information about socialization
assisted by PISC, not only CPMU and Local
Government). Public disclosure must be carried
out, if there is a new are, for example before pipe
installation.
h) It is necessary to include the Gender Action Plan
(GAP) parameter as well as affected persons, and
this will be submitted to CPMU and Local
Government.
i) The Semi-Annual Social Safeguard Monitoring
Report must follow the chapters in the
Resettlement Plan (RP) which include Grievance
Redress Mechanism (GRM), Institutional
Arrangement, Livelihood Restoration, Income
Restoration Program (Relocation Strategy). It is also
needed to put more narrative inside the report.
j) With regards to GRM, the focal point for each city
must be set. This report shall explain the GRM
implementation as of today. Are there complaints?
(put into narration).
k) The public consultation covered in the Social
Safeguard Monitoring report shall be only related
to Social Safeguard. It shall define the affected
person involved in the public consultation. Please
also emphasize the participation of vulnerable
groups and women.
l) Social impacts must be covered in the report.
m) Report not only submitted to ADB, but CPMU needs
to inform the affected person in the form of a
progress summary.
2 Additional revision:
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 53
Ref Discussion Item Action Time Status
a) The progress of Palembang city needs to be
included in each component of the report
b) Report related to action plan needs to be same in
format for each city so that they are easy to read.
c) PISC needs to provide capacity building to the local
government.
d) ADB requested that the new Resettlement Plan
(RP) for Makassar City in regards to the change on
pipe alignment must be immediately prepared and
submitted to ADB.
3 Deadline Report:
a) 1st Semi Annual Monitoring report: 22 October
2018
b) Pekanbaru: Update LARP - 25 October 2018
c) Makassar: new RP + PIP Disclosure – mid November
2018
d) Jambi: will be discussed further because it is
necessary to ensure the new components are
updated.
4 ADB requested that the PISC team shall consult with
ADB during the preparation of the report
Attachment:
A. Selected Photos
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 54
Prepared by,
Fiana Fauzia
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 55
MINUTES OF MEETING
Ref :
Meeting Subject : Discussion of Addendum No.2
Day/Date of Meeting : Wednesday, 10/10/2018
Time : 15.00 – 16.30 WIB
Venue : PISC’s meeting room, KMO Building Lt. 2
ATTENDEES:
No Name Institution/
Company Email Address Mobile Phone
1 Panggih Hidayat PPLP Strategis [email protected] 081327063084
2 Asri Indiyani PPLP [email protected] 0818215754
3 Fachril Luthi Dit PLPP [email protected] 081310374458
4 M Naufan D Dit PLPP [email protected] 08211517493
5 Taufik Hidayat Dit PPLP [email protected] 081280876404
6 Benny Sihaloho DTL PISC [email protected] 081314301436
7 Genniya N H Dit PLPP [email protected] -
9 Seamus Baynes PISC [email protected]
8 Rully Rizaldi SMEC [email protected] 085921513309
11 Fiana Fauzia PISC [email protected] 081281026113
Ref Discussion Item Action Time Status
1 PISC offers several changes in Addendum No. 2
a) Wastewater Process Engineer: will be extended
with new expert who is ready to join within 2
weeks. Unfortunately, the xpert (Alice) has only
+10 years of experience whereas requirement
required 20 years of experience
b) Procurement expert in each city will be removed.
All tasks manage by procurement expert in Jakarta
c) Social safeguards, Gender and environmental
specialists in each city will also be removed with
centralized control in Jakarta
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 56
Ref Discussion Item Action Time Status
d) Structural engineer in Jakartan that will be placed
in Pekanbaru as a sewerage engineer needs to be
ascertained regarding availability
e) Extension of Engineering support/drafter 4, 5, 6
and 7 to 3 months time input
Additional discussion:
PISC said about the lack of transport for field supervisors
in each city to move from certain place to another. This
facility has not been fully provided so that the process
of controlling construction activities has not been
optimal.
2 CPMU responded and give guidance:
a) Wastewater process engineers will be discussed
further in relation to decreasing the billing rate for
the Addendum 2
b) Pekanbaru HSE specialist has met the qualifications
and will be immediately approved with formal
letter of approval
c) Instruction to PISC to revise several part of C3
package procurement plan
d) The results of the revision NC, B1 and B2 package
procurement plan including the QPR draft will be
submitted to CPMU by October 11, 2018
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 57
A. Selected Photo
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 58
Prepared by,
Fiana Fauzia
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani
Kepala CPMU ……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 59
MINUTES OF MEETING
ATTENDEES:
No Name Company Email Address Mobile Phone
1 See the list
attendance
attached
Ref Discussion Item Action When Status
1 Rito as the Staff of the Sub-Directorate of
Wastewater Management and the PISC Team said
that in the MSMIP activity, there is an ADB request to
provide a web-based application to monitor and
evaluate all MSMIP activities so this Information
System will be developed which will load the Progress
data and map data of the wastewater piping network
in 3 cities of MSMIP project namely Makassar,
Pekanbaru and Jambi Cities.
The pipeline network map includes pipe data as well
as the depth of pipes installed in each zone.
2 Mr. Leo as the Section Head of the Information
System Development said that the Sub Directorate of
PDSI already has a Geodatabase Application which
includes geospatial data that can display map data
that is able to analyze, and display one infrastructure
with other infrastructure, so PISC only provides data
that is in the form of SHP and KMZ with scale 1: 5000
which later the data can be submitted to Rentek Dit.
Ref :
Meeting Subject :
MSMIP Geographic Information System (GIS) Development Procedure with the Infrastructure Geographic Information System (SIGI) Ministry of PUPR
Day/Date of Meeting : Tuesday, 16/10/2018
Time : 09.00 – 2.00 pm
Venue : Ambhara Hotel
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 60
Ref Discussion Item Action When Status
PLP, because later each work unit will be provided a
Login to import the GIS data.
All data mapping activities in the form of ArcGIS
should be saved on the Cipta Karya Server which is
managed by the Sub Directorate of PDSI of Cipta
Karya. The procedure for uploading and using the GIS
application at the Pusdatin should go through an
inquiry letter to KIP.
Related to All web creation Applications should use
Frame Work, to use a CMS (Content Management
System) is not allowed because it is vulnerable to
hackers. Applications that are built expected to be as
easy as possible without putting aside the data inside
because the data should be very important. All
applications that will be developed and placed online
through VPS to the Cipta Karya server, with a permit
from the Directorate of PPLP to the Directorate of
KIP. The Sub-directorate of PDSI will support this
activity and hope that later the application built can
be useful and facilitate this activity and can be
developed if the similar activities take place.
3 Mr. Deden as the GIS Expert Team said that for all files
with the specified format, it can be directly inputted
into Cipta Karya Geodatabase. Data collection is
carried out by PISC Consultant, in Geographic format.
The data field description should be equipped in the
ArcGIS attribute, and later the PISC will only provide
data to be inputted to the Cipta Karya Geodatabase
application, and complete the data periodically so
that the data is visible. Also due to the existing GIS
data is already good.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 61
A. Attendees
1.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 62
B. Selected Photo
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 63
Prepared by,
Achyar Lubis
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 64
MINUTES OF MEETING
Ref :
Meeting Subject : Various
Day/Date of Meeting : Thursday, 18/10/2018
Time : 09.00 – 10.00 am
Venue : Gedung Cipta Karya 7th Floor
ATTENDEES:
No Name Institution Email Address Mobile
1 Asri, Taufik, Efry CPMU
2 - PPK
3 Brian, Seamus, Benny, Vicky PISC
4 - SMEC and Consortium
Ref Subject of Discussion Action Time Status
0
The purpose of the meeting was for Mr. Brian HAYDEN,
who has recently been appointed to the position of SMEC
Functional General Manager for Water – Asia Pacific to pay
a courtesy visit to CPMU and to formally introduce Mr.
Seamus BAYNES as the new PISC Team Leader. Mr. BAYNES
will shortly become the signatory for all SMEC
documentation and correspondence.
1 Socialisation Activities
PISC Social Safeguards/Resettlement Specialist verbally
presented the action plan of her proposed activities for this
mission. These will comprise:
Revision of the 1st Semi-Annual Report on Involuntary
Resettlement
Preparation of the list of social safeguards data for
regular monitoring to be included in the website
Updating of Pekanbaru LARAP
Assist in preparing LARAP for Makassar
Prepare & compile data for the 2nd Semi-annual
Monitoring Report for IR
2 International Expert
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 65
Ref Subject of Discussion Action Time Status
Although Team Leader had stated at the meeting in KMO
on 10 October that no additional inputs for international
experts beyond the process expert were required; on
review, it was found that the current Civil/Structural
expert, Mr. Ananda de Costa, has a new assignment and is
thus unable to extend his inputs beyond his original
contract. He will leave the project in early November. He
has completed the structural design of the tanks and his
concepts will be translated into working drawings by our
local structural expert, Pak Yan. However, he has not had
time to work on the civil drawing details (because 3 months
of the initial inputs were abortive due to the change in
treatment technology at Pekanbaru from Aerated Lagoons
to CAS). CPMU agreed a further 3-month input for a new
international civil engineer. PISC hoped to recruit him
swiftly under an open slot in Ministry of Manpower
allocation.
3 Makassar Contract B1 Bidding Documents
1. PISC had submitted final Bid Documents for B1 using the
lower peak factors as previously discussed and this had
resulted in a saving of almost $2M to the cost estimate.
Mr. HAYDEN confirmed that full liability for this design
change rests with SMEC.
Prepared by,
Benny Sihaloho
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 66
MINUTES OF MEETING
Ref :
Meeting Subject : Progress of Information System Development Web in Project
Management Unit
Day/Date of Meeting : Monday, 22/10/2018
Time : 10.00 – 12.00 WIB
Venue : PISC’s meeting room, KMO Building Suite 201
ATTENDEES:
No Name Institution/
Company Email Address
Mobile Phone
1 Panggih Hidayat PPLP Strategis [email protected] 081327063084
2 Asri Indiyani PPLP [email protected] 0818215754
3 Fachril Luthi Dit PLPP [email protected] 081310374458
4 M Naufan D Dit PLPP [email protected] 08211517493
5 Taufik Hidayat Dit PPLP [email protected] 081280876404
6 Benny Sihaloho DTL PISC [email protected] 081314301436
7 Genniya N H Dit PLPP [email protected] -
8 Achyar Lubis PISC [email protected] 085346949178
9
10 Fiana Fauzia PISC [email protected] 081281026113
Ref Discussion Item Action Time Status
1 PISC started to explain the progress of the MSMIP
Website. Issues found:
1. The existing programmer is not fully able to assist
in the making of the MSMIP website
2. The progress made by PISC has been slow and not
able to provide the CPMU's needs
2 CPMU explained some web feature for MSMIP website:
1. PISC must provide the baseline before straight in to
web component. This baseline includes input
parameter and layout.
2. Deadline before 10 November, 2018: layouting,
background explanations for each cities, and
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 67
Ref Discussion Item Action Time Status
calender with the upcoming events namely
meetings with its MoM, attendance list, and
documentation
3. Deadline 10 November, 2018: Database for data
storing including every letter documents. Also,
question feature for CPMU and LPMU to
communicate and progres control in each city. This
is important to ensure monitoring stage. Question
feature consists of 5 question answer slots,
connects to email notification, regular question
slot, and chat room
4. Upcoming discussion will perform on 31 October,
2018 at 2 PM.
B. Selected Photo
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 68
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 69
Prepared by,
Fiana Fauzia
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani
Kepala CPMU ……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 70
MINUTES OF MEETING
Ref :
Meeting Subject : 1. Coordination Meeting on Social Safeguard and Involuntary
Resettlement
2. Capacity Building on LARAP
Day/Date of Meeting : Thursday, 25/10/2018
Time : 10.00 – 17.00 WIB
Venue : Meeting Room Bappeda Pekanbaru 2nd Floor
ATTENDEES:
No Name Institution/Company Email Address Mobile Phone
1 See attendance
sheet attached
2
3
4
Ref Discussion Item Action Time Status
Coordination Meeting on Social Safeguard and Involuntary Resettlement
1 The meeting was opened by Pak Rahmad (Bappeda)
which then continued by Bu Vicki (PISC) thanking
Bappeda and other agencies for coming to the meeting.
Bu Vicki explained the objective of this meeting which
was mainly to review the and update LARP. LARP of
Pekanbaru was formulated back then in 2012, which
operasionalized Safeguard Policy of ADB as outlined in
SPS 2009 and SR2. LARP contains detailed description
about the process of land acquisition, the compensation
for WWTP and pump station area, the affected assets
during construction, etc. Therefore, LARP document is a
very important document.
Bu Vicki also said that ADB is very strict regarding Social
Safeguards. ADB wants to protect the condition of
affected persons (AP) in relation to the impacts of the
project. ADB wants the socio-economic condition of the
affected persons to be the same or even improve more
by the project.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 71
Ref Discussion Item Action Time Status
2 Regarding to the Social Safeguards activity, Bapak
Rahmad (Bappeda) responded that they have done land
acquisition process for WWTP. He then asked Dinas
PUPR to explain the current status of WWTP in which it
is found that there is no decision yet on the access road
to WWTP. The old access still exists, the new access is
still under review and consideration.
3 Bu Vicki (PISC) presented her presentation file on the
status of Social Safeguard (as of October 2018). It is
mentioned that:
- The land acquisition for WWTP (27 land owners) has
been completed. The new issue is regarding the
access road.
- The inventory of temporary AH and AP need to be
conducted (survey and identification how many AH
and AP temporarily affected by construction along
the CWS network/pipe alignment). The public
consultation / socialization also needs to be
conducted, especially regarding construction
impacts and mitigation measures
- The 2nd Semi Annual Involuntary Resettlement
Monitoring Report needs to be submitted by January
2019. LPMU shall provide the data for this.
PISC and City
government
needs to
conduct
inventory of
AP/AH along
pipe
alignment
4 Pak Kautsar (Bappeda) expressed about the survey and
census that need to be carried out to the AP / AH. It
needs to be conducted after getting the final design of
the pipe alignment.
Bu Vicki then responded in addition to that, we also
need to address the construction impacts and
mitigation measures with the APs/AHs before start of
construction for example, construction will disturb the
accessibility and their business.
5 Pak Aribudi (Land Agency of Pekanbaru) responded that
the land purchase for the 27 land owners has been
completed, and all documents has been handed over to
the PISC. However, there is no detail information on the
number of trees, type of trees, etc. in which Pak Aribudi
said he will give the data later tomorrow (26 Oct 2018)
in his office.
He also mentioned in the past there were Pak Supriyadi
(ADB consultant) that conducted socio- economic
interview to the land owner, so he might probably have
Pak Aribudi
will give
complete
compensation
data of 27
WWTP land
owners
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 72
Ref Discussion Item Action Time Status
the data we requested. Furthermore, he also mentioned
the name of Pak Suganda (ex – RW) who knows the story
of land acquisition process at that time.
For the pump station (1,800 m2), he stated, the city
government has allocated the budget to the revision of
APBD 2018 with the amount of IDR 900,000,000. The
issue on this is they need to complete the measurement
requirement to BPN, however, the owner of this land is
not available at the moment. The certified independent
appraisal team has been formed in October 2018. It is
targeted to be completed in November 2018. The
estimated price for this land is not known yet, it will be
known after deliberation. The appraisal team has not
yet submitted the official report, it could be submitted
by November 2018.
Pak Aribudi is requested to send the socio-economic
questionnaire to his email again. He will facilitate the
interview with the pumping station land owner.
6 Pak Kautsar (Bappeda) then asked about the
compensation for temporary AP/AH. How about it?
Bu Vicki (PISC) responded that there are 2 types of APs:
1. Permanently affected: by replacement cost
2. Temporarily affected: along pipe alignment
We need to address to the AP/AH, how is the mitigation
in order to minimize the construction impact to their
business. The impacts are divided into full impact and
partial impact.
There are two types of pipe construction, open cut and
pipe jacking. We need to identify which areas using
open cut and which areas using pipe jacking. We need
to address the technical aspect, construction impact,
and mitigation of these to the AP/AHs.
7 LARP document of Pekanbaru Table 6.2 Budget shall be
updated. The Bappeda cannot decide the allocated
budget for LARP. They need to discuss internally among
them. In regards to this budget, it is also need to know:
- how much the budget has been used?
- Who monitor this budget allocation?
- The budget for social safeguard monitoring data
also needs to be accommodated in the updated
LARP budget.
Bappeda will
have internal
meeting for
this issue
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 73
Ref Discussion Item Action Time Status
Capacity Building on LARP and Updating LARP
8 Before the capacity building carried out, PISC refreshed
the meeting’s participant with the ADB Social Safeguard
Policy.
9 Bu Budi (PISC) presented the old LARP prepared by PPTA
Consultant in 2012. Bu Budi then explained one by one
the definition of terms found in LARP document.
In the LARP document, there was an issue on income
restoration program, one AP will lose 41% of his income
(how this been solved?). Bappeda is suggested to
discuss with this one AP. It is needed to know the
current socio-economic condition of this AP. If the socio-
economic condition of this AP is better, then there is no
need to do future monitoring.
However, this is unknown yet. Pak Aribudi or Pak
Suganda (ex RW) may know about this.
10 Regarding LARP, we also need to know the existence of
vulnerable group in the area at WWTP & Pipe Alignment
sites.
11 Regarding the name of village stated in LARP 2012, it
needs to be updated into LURAH, because village is no
longer used and no longer exist.
12 Bu Vicki and Budi (PISC) then explained about the
importance of Public Consultation. The public
consultation needs to be carried out not only during
preparation planning, but also before and during
construction and operation & maintenance. The report
of public consultation is also important to be
documented.
Regarding the LARP monitoring document, it is still need
to be monitored post project implementation semi-
annually for 2 years or so until resettlement and income
restoration program have been fully implemented and
other project impacts have been fully mitigated.
13 In the LARP document, there is subchapter of Grievance
Redress Mechanism (GRM). PISC then asked about the
GRM implementation in Pekanbaru so far. Has this been
implemented? The GRM in the LARP is still general, it
shall be specific and concrete for implementation.
Bappeda will
have internal
meeting for
this issue
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 74
Ref Discussion Item Action Time Status
In which then Bappeda explained, they will discuss
among LPMU regarding this. Bappeda (as a chairman of
LPMU) will follow up on the matter of:
- Determination of focal point of GRM
- The mechanism of GRM
- Who will monitor and be responsible for the GRM
- Who will record any grievance raised
14 The next chapter in the LARP document is about the
legal framework, which needs to be updated based on
the recent and current ADB and Government of
Indonesia’s Regulation.
The project commitment and policy in LARP document
shall be guidelines for the institution conducting Land
Acquisition.
15 The discussion then moved to Entitlement Matrix. There
are few discussions in the entitlement matrix:
- Regarding illegal street vendors, based on ADB
safeguard policy, the illegal shall be accommodated
as well.
- The disturbance of business, the compensation will
be paid based on lost daily income.
- The compensation of the AP/AH not only in the
form of CASH. The compensation for illegal street
vendors shall be the same with the legal one (no
difference).
- The discussion or disclosure to the AP/AH needs to
be carried out soon, because the construction is
going to be started.
- The compensation for the AP/AH needs to be
discussed internally among LPMU
Bappeda will
have internal
meeting for
this issue
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 75
Attachment:
A. Attendance Sheet
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 76
B. Presentation Material
Presentation Social
Safeguard 25 Oct 2018.pptx
Ppt for LARP
Progress Oct 2018 - B.Indo.pptx
LARAP Pekanbaru -
B.Indo.docx
C. Photos
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 77
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 78
Prepared by,
Della Permata
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………
Monthly Report No. 13, October 2018 79
MINUTES OF MEETING
Ref :
Meeting Subject : Proposed Alternative Pipeline to WWTP and DNP clause in SBD for B1
Day/Date of Meeting : Friday, 26/10/2018
Time : 14.00 – 17.30 pm
Venue : PISC’s Office, KMO Building
ATTENDEES:
No Name Institution Email Address Mobile
1 Asri, Evry Taufik, CPMU
3 Yenni, Riza Satker PSPLP Riau
2 Panggih and Irfan PPK
3 Seamus, Andrew, Benny, Marivic, Utami PISC
Ref Subject of Discussion Action Time Status
A Alternative Pipeline
1. Mr. Andrew was showing three drawings that
reflect current inlet pipe and road alignment for
Pekanbaru and described that the existing road is
not on piles – PISC analysis tells that all structures
at the plant site should be on piles if they are to last
and assuming that it need to build a new road on
piles, the capital cost will be very high. The total
road length from the pump station is about 800
meters long and any shortening of the road carries
a significant cost benefit (2 alternative proposed).
2. Basically Pa Yenny and Pa Riza had no objection
revise the pipe laying for inlet pipe to get more
efficient cost, but it should be planned carefully for
access road, considering this requires land
acquisition which should be discussed with the LG,
and the LG may object if there has to be land
acquisition, while they have prepared the access
road to the WWTP location even though it is
technically not feasible because it is not supported
by the right road construction.
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 80
Ref Subject of Discussion Action Time Status
3. Bu Asri said that realizing this plan would take a
long time starting from surveys, LG approval,
community approval and pipeline redesign. While
ADB's approval for the NC package will be released
soon, and PISC is asked to use the old design and
still prepare the design and calculation of costs for
the proposed alternative pipeline (pro-con table)
4. PISC was asked to conduct a field survey to ensure
the possibility of transferring the pipeline could be
done technically.
B DNP clause for B1’s SBD
1. Mr. Seamus proposed the addition of DNP to 2-
year period for:
Ensure the final commissioning process occurs
at the maximum capacity (although not 100%)
that can be achieved related to the volume of
wastewater.
Ensuring the growth of biomass is sufficient for
the biological processing to take place
perfectly.
If this is accepted then a Loan extension is required
until December 2023 and not 2022 as CPMU will
propose to ADB.
2. Bu Asri said that if the Loan extension was only to
accommodate this issue, it would be difficult to get
ADB approval. The solution that can be done is to
transfer LG's additional 1-year financing obligation
and this is stated in the Contract.
2. Instead of extending DNP due to minimal waste
water volumes, Pa Evry suggest that the funds that
the contract should be used should be diverted to
increase the target of installing house connections
until December 2022. The target of 13,000
connections to LG's obligations will be assisted by
the APBN, so that in the first year at least there is
an installed connection of 1,000 + 3,000 financed
by the Project. But this should be done with the
amendment of the Agreement between PUPR and
LG related to the connection installation
commitment.
C Others
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 81
Ref Subject of Discussion Action Time Status
1. Regarding social safeguard and environmental
work, Bu Asri asked Pa Seamus to push Della's
performance and ability in completing her
assignment.
2. Bu Asri asked SMEC International to be more
serious in preparing experts for supervision, and it
should be accompanied by technical justification
and supporting documents.
3. To evaluate the Addendum # 2 proposal, the Satker will assign a Contract Examination Committee related to the proposal from the SMEC
4. Bu Asri reminds Mr. Seamus to monitor the progress of Website development work carried out by Achyar and there should be progress until the meeting on Wednesday 31.10.208.
5. Additional input to Process Specialists and Civil
Specialists should be accompanied by strong and
accurate justification. Likewise, the role of the
National Procurement Specialist should be clarified
(including assignments related to contractual and
contractor claims) if it is to be mobilized until the
end of the project.
A. Selected Photos
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 82
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 83
Prepared by,
Benny Sihaloho
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 84
MINUTES OF MEETING
Ref :
Meeting Subject : Clarification of ADB Procurement Team to B1, B2 and NC Packages
Day/Date of Meeting : Wednesday, 31/10/2018
Time : 14.00 – 17.00 pm
Venue : PISC’s Office, KMO Building
ATTENDEES:
No Name Institution Email Address Mobile
1 Asri, Evry Taufik, and Tyas CPMU
2 Riza (Riau) and Setia South Sulawesi Satker Province
3 Sani, Joris, Vijay ADB
4 Seamus, Andrew, Benny, Marivic, Djati and Anthony PISC
Ref Discussion Item Action When Status
A Bidding Documents
1. Mr. Seamus explain the background of all
package especially Package B1. The main issue is
the peak factor for design flow that too high.
And opposite to that the initial flow for WWTP is
very low at the end of construction.
2. The consultant plans to commission the WWTP
units in stages per module due to the minimum
flow that goes into the WWTP. For example,
there are 4 Aeration Tank units that will be
tested and commissioned for 12 months as
follows: AT1 for 3 months, then AT2 for 3
months, AT3 for 3 months, and finally AT4 for 3
months.
3. Bidding Documents for Design and Build
Package B1 prepared by the PISC and in
coordination with ADB's Procurement Specialist
in Jakarta turned out to be wrong. ADB Head
Office has a special document (2017 issue) and
Vijay requests a Bidding Document that has
been sent to be replaced immediately and sent
back to ADB no later than November 9. Vijay will
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 85
Ref Discussion Item Action When Status
send the file to the CPMU and PISC as a
reference.
4. Related to the response from ADB for B2 and NC
packages, where there was still no agreement
related to Price Adjudication and Contingency, It
was agreed by the ADB and CPMU to eliminate
the Price Adjudication and Contingency clauses,
and PISC was asked to check the consistency of
each part. The revised results of the Bid
Documents will be sent to ADB no later than
November 5, 2018.
B House Connections
1. The CPMU is concerned that the installation of
connections by the Local Government cannot be
achieved in accordance with the Cooperation
Agreement between PUPR and the Local
Government. For this reason, an additional
commitment from PUPR will be planned from
the initial number of 1,000 pilot projects to
3,000-4,000 at the beginning of the year. This
will be discussed with the Director of PPLP for
approval. 2023 and not 2022 as CPMU will
propose to ADB. The budget for additional SR
will from Contract Addendum (max 10%)
2. ADB will encourage CDTA Consultants to be
more active in disseminating information to the
community to get more connection
commitments than planned. PISC and CDTA in
order to coordinate more in an intensive
manner to ensure that the socialization process
by the Local Government can run maximally
captures the commitment of the population.
3. ADB was informed that CDTA had calculated the
estimated waste water tariff to be paid by the
community in 2-3 year after the construction
was completed. In Year 1-2 people are exempt
from payment.
4. Another solution is to maximize the installation
of commercial connections at the beginning of
the year so that it can produce higher flow.
Installation of house connections will be carried
out at the beginning of the project but only until
the inspection chamber (IC), while installation
until inside the house will be done as soon as the
WWTP is finished
ADB Loa n No 3123-INO: Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 86
Ref Discussion Item Action When Status
C Others
1. Director PPLP has sent 3 letters regarding the
commitment of LG’s Jambi to the project
especially concerning land ownership certificate
for WWTP and Pumping Station and progress of
purchase of Access road to Pumping Station. But
no official respond from Mayor, but informally
there has been an agreement between the
Director and the Mayor to continue the project.
CPMU believe Jambi can fulfil the commitment
before the end of this year.
2. 2. ADB want PISC and CPMU to check the
market for this project in order to get more
qualified contractors.
A. Selected Photo
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 87
Metropolitan Sanitation Management Investment Project
Monthly Report No. 13, October 2018 88
Prepared by,
Benny Sihaloho
PISC MSMIP
……………………………………
Approved by,
Seamus Baynes
PISC MSMIP
……………………………………
Asri Indiyani Head of CPMU
……………………………………