Page 1: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

MONTHLY REPORTMONTHLY REPORTJune 2009June 2009

IT DIVISIONIT DIVISION

Tien Dang

Page 2: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

2

System Development

• Develop BCS (Business Core System).

• Develop B2E (Business to Employee).

• Develop B2C (Business to Customers).

System Support

• Email Support.

• Can Tho Project

• PBX Setting.

• Maintain Data Centre.

ENGAGED PROJECT THIS MONTH

Page 3: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

3

• Discharge and charge UPS battery for maintenance.

• Check and maintain chiller machine.

• Design the network and telephone port for Norch Branch Office.

Maintain Data Centre

Page 4: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

4

Maintain Data Centre (cont)

•UPS Batteries•Air Cooled Water Chiller

Page 5: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

5

• Check and listen the voice recording files on all PBX

Systems.

• Backup the recording files of all Service Centers to System Backup.

• Setup Access Code for Fax Machine at 6F in The World Center (Agency Office).

PBX Setting

Page 6: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

6

Check & listen the voice recording files

Page 7: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

7

• Make the guideline about how to deleted emails by Webmail support for agencies.

• Check the schedule to compact email databases.

Email Support

Page 8: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

8

• Collect all quotations and discuss with suppliers.

• Make the approval report and waiting approved it.

Can Tho Project

Page 9: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

9

Developing the BCS

• Install to BCS system support the C05, C06 product.

• Implement the batch files support the Happy Kits Activity.

• Improved the function Going Abroad.

• Implement the Budget System.

Page 10: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

10

Going Abroad Demonstration

Page 11: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

11

Budget System Demonstration

Page 12: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

12

Developing the B2E

• Install the salary calculation on-line for agents.

Page 13: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

13

Salary calculation online for agents

Page 14: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

14

Developing the B2C

• Install the web page of happy kids activity to B2C.

• Install the web page introducing new C05, C06 products.

Page 15: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

15

The web page of Happy Kids Activity

Page 16: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

16

The web page of new product C05, C06

Page 17: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

17

• Setup network and telephone in N’orch Branch Office.• Continue to progress Can Tho Service Center Project.• Sign the Scanner MA, IBM Middleware MA contract.

System Support

PLANNING PROJECT FOR NEXT MONTH

• Maintain BCS, B2E System.

System Support

Page 18: MONTHLY REPORT June 2009 IT DIVISION Tien Dang. 2 System Development Develop BCS (Business Core System). Develop B2E (Business to Employee). Develop B2C.

18