Sr.
No.
GS. No.
NewName of Scheme District Type Approved Cost
Exp Upto
June 2018
Provision for
2018-19
Funds
Released by
F.D
Funds
utilized
till 31.01.19
%age
utilization
on release
31.01.19
Physical
progress till
current month
(%age)
Remarks (including detailed physical
progress)
(i) Date of Start of the Project
(ii) Date of completion of the Project
Ongoing Schemes
1 1604 R/W/S Scheme Dhamial RawalpindiOn-going
Schemes181.407 164.389 5.673 2.255 0.837 37% 91%
Scheme completed & handed over to CBO only
work for restoration of desmantled streets in
progress.
2 1605
Construction of Road/Streets in Village Ghoon UC -
Beor and Construction of Road/Streets & Hand
Pumps in UC -Punjar & UC -Narar, District
Rawalpindi
RawalpindiOn-going
Schemes8.000 6.000 0.667 0.166 0.000 0% 75% Scheme completed in saving.
3 1606Water Supply Scheme in Kahuta Town Tesil
Kahuta, District RawalpindiRawalpindi
On-going
Schemes8.000 2.143 1.952 1.464 0.976 67% 39% Work in Progress.
4 1607
P/I Tube Well in Latori Syedan & P/I Hand Pumps
in Dhok Naka and Village Matore UC -Matore,
District Rawalpindi
RawalpindiOn-going
Schemes5.650 0.120 0.667 2.834 2.668 94% 49% Work in Progress.
5 1608Rehabilitation & Augmentation &Ext of water
Supply Scheme for Village Dhullian Attock
On-going
Schemes43.515 41.514 0.667 0.500 0.334 67% 96%
A.A Date 03.09.2015.T.S Date 23.09.2015. Date of
Start of Scheme 10.11.2015.Date of Completion of
Scheme 30.06.2019.Work is in progress.
6 1609Augmentation / Rehabilitation of Water Supply
Scheme Khour Tehsil Pindi Gheb District AttockAttock
On-going
Schemes69.989 12.510 3.333 2.500 1.667 67% 20%
A.A Date 10.09.2016. T.S Date 02.05.2017.Date of
Start of Scheme 16.06.2017.Date of Completion of
Scheme 30.06.2019.Work is in progress.
7 1610Rehabilitation of Rural water Supply Scheme
SarkalanChakwal
On-going
Schemes25.000 18.475 2.175 0.543 0.000 0% 74%
Date of A.A 08.01.2015.Date of T.S
21.01.2015.Date of Start 20.04.2015.Date of
completion .30.06.2019.Percolation well, Ground
Storage Tank and Rising main completed. Work on
the scheme suspended due to loss of water
in.ewly..eveloped.source as some blasting was done
by Mining epartment. Revised Rough Cost Estimate
submitted to D.C Chakwal vide T/O No.01/CH dated
01-01-2018 for according Revised A.A.
8 1611Rehabilitation of Rural Water Supply Scheme
Dhoke Khour Tehsil Talagang, Chakwal.Chakwal
On-going
Schemes1.620 0.719 0.300 0.075 0.000 0% 44%
Date of A.A 11.03.2015. Date of T.S
21.01.2015.Date of Start 20.03.2015..Date of
completion 30.06.2019 .Work suspended at site due
to sever conflicts among the CBO / community
members. Community Development Unit trying to
resolve the issues. Excessive funds surrendered
through re-appropriation.
9 1612Extension of water Supply scheme Khewra, Tehsil
Pind Dadan Khan, District JhelumJhelum
On-going
Schemes161.845 28.504 13.333 3.653 0.320 9% 18%
Date of A.A 11-04-2016.Revised A.A 31-03-
2017.Date of T.S 19-08-2016.Work awarded on 06-
02-2017.Work in progress
10 1613Authority to maintain & Regulate Naroomi Dhan
water Supply Scheme Tehsil P.D.KhanJhelum
On-going
Schemes361.446 10.000 26.667 20.000 13.334 67% 6%
Date of A.A 11/2017.Revised A.A 30-111-2017.•
Work award on 16.02.2018.Work in progress
11 1614Rural Water Supply Scheme Chal No 61/SB
Sargodah Sargodha
On-going
Schemes15.000 0.039 3.333 2.500 1.913 77% 13% Work in progress.
12 1615Installation of 300 Hand Pumps Noushera
Khushab Khushab
On-going
Schemes132.000 111.498 1.833 1.375 1.370 100% 86%
Date of AA 15-10-2015 Date of TS 09-11-2015 Date
of award 05.01.2016 Date of completion 30.06.2019
Work is in progress.
13 1616 water Supply Scheme Jhunge Walan of UC
Khabeki.Khushab
On-going
Schemes24.058 14.550 3.167 2.375 2.145 90% 69%
Date of AA 27.08.2016 Date of TS 03-09-2016 Date
of Award 21.01.2017. Date of Completion
30.06.2019 Work is in progress.
14 1617 water Supply Scheme Kalial UC Khura. KhushabOn-going
Schemes25.996 15.996 3.333 2.500 2.250 90% 70%
Date of AA 27.08.2016 Date of TS 03-09-2016 Date
of Award 24.01.2017 Date of Completion
30.06.2019 work is in progress.
15 1618Rehabilitation / Improvement of Water Supply
Scheme, Khoora UC Khoora, District KhushabKhushab
On-going
Schemes12.695 1.998 1.000 0.750 0.500 67% 20%
Date of AA 29.7.2017 Date of TS 04.09.2017 Date
of award 14.12.2017 Date of completion 13.12.2019
Tube Well 1 No. Pump House 1 No. Pumping
Machinery 1 No. Rising Main 3640/19400 Rft The
Scheme remained unfunded in interim budget
however it has been included in ADP 2018-19. work
is in progress.
MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT PROGRAMME 2018-19
WATER SUPPLY & SANITATION
16 1619Installation of Submersible Water Pumps, Tehsil
Isa Khel District Mianwali.Mianwali
On-going
Schemes50.000 37.423 3.387 2.540 1.688 66% 78%
Date of A.A. 13-01-2017, Date of T.S. 24-01-2017,
Date of Start of Work. 08-05-2017, Remarks
E.R.S=130/144, Trail Bore=6/6, T/Well boring=
61/72, P/Machinery= 61/72, G.S.Tank= 7/72. Work
is in progress.
17 1620
Provision of Submersible Pumps (UC Bani Afghan,
Sawance, Ghundi, Chakrala, Ban Hafiz Gee,
Thamay Wali, Namal)
MianwaliOn-going
Schemes49.980 33.415 5.520 4.140 2.760 67% 72%
Date of A.A.27-08-2016, Date of T.S.15-10-2016,
Date of Start of Work.03-12-2016, Remarks.
E.R.S=35/50, T/Well boring= 87/110,
P/Machinery=87/110, G.S.Tank=0/62-No. Work is in
progress.
18 1621Extension of Sewerage and water Supply,
Mankera.Bhakkar
On-going
Schemes71.300 38.133 10.934 8.201 8.201 100% 65%
"Date of A.A 25.08.2015 Date of T.S 11.11.2015
Date of Commencement 28.12.2015 Date of
completion 30.06.2019
19 1622Construction of PCC in Different Streets in UC -64
District Faisalabad Faisalabad
On-going
Schemes5.000 2.000 1.000 0.750 0.500 67% 50%
Date of A.A 05-08-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
20 1623Construction of PCC in Different Streets in UC -65
District Faisalabad Faisalabad
On-going
Schemes5.000 1.000 1.333 1.000 0.666 67% 33%
Date of A.A 05-08-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 &24.1.19
21 1624Construction of PCC in Different Streets in UC -66
District Faisalabad Faisalabad
On-going
Schemes5.000 2.000 1.000 0.750 0.500 67% 50%
Date of A.A 05-08-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
22 1625Construction of PCC in Different Streets in UC -67
District Faisalabad Faisalabad
On-going
Schemes5.000 1.000 1.333 1.000 0.667 67% 33%
Date of A.A 05-08-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
23 1626Construction of PCC in Different Streets in UC -72
District Faisalabad Faisalabad
On-going
Schemes5.000 1.000 1.333 1.000 0.667 67% 33%
Date of A.A 05-08-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
24 1627Installation of Water Filetartion Plant in UC 463
Teshil Smundri District Faisalabad Faisalabad
On-going
Schemes3.000 0.000 1.000 0.000 0.000 #DIV/0! 0%
Case submitted for Change of Nomenclature UC-
463 to Chak No. 463/GB vide SE No. 2414 dated
07.08.2018.
25 1628Rehab: of Rural Water Supply Scheme Chak No.
215/RB Tehsil & Distt: FaisalabadFaisalabad
On-going
Schemes87.765 84.043 1.000 0.750 0.390 52% 96%
AA issued on 21.04.2017. Date of T.S 23.05.2017
Work order issued on 11.05.2009. Work is in
progress. Funds released on 23.11.2018 & 24.1.19.
26 1629 Rural Water Supply Scheme at Chak No.84/JB FaisalabadOn-going
Schemes7.955 6.725 1.230 0.923 0.500 54% 91%
AA issued on 20.10.2016. Date of T.S 24.10.2016
Work order issued on 12.01.2017. Work is in
progress. Funds released on 23.11.2018 & 24.1.19.
27 1630Rehab. of rural water Supply scheme Chak No.
343/GB T.T. SinghToba Tek Singh
On-going
Schemes23.943 18.826 1.318 0.489 0.159 33% 79%
1-Date of A.A 20.10.2016 2- Date of T.S 21.10.2016
3-Date of invitation of tenders. 13.02.2017 4- Date
of Receipt of tenders -15.02.2017 5- Date of
completion as per PC-I 30.06.2018 6- Date of work
order - 06.03.2017 7- Anticipated date of completion
30.06.2018 8- No. of Beneficiary - 5333 Persons 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
10-Re-appropriation of funds(+/-) Scheme
completed in saving.
28 1631 Rural water Supply Scheme Chak No.674/15/GB Toba Tek SinghOn-going
Schemes31.298 18.962 3.011 0.752 0.000 0% 61%
1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016
3-Date of invitation of tenders.13.02.2017 4- Date of
Receipt of tenders -15.02.2017 5- Date of
completion as per PC-I 30.06.2018 6- Date of work
order - 09.03.2017 7- Anticipated date of completion
30.06.2018 8- No. of Beneficiary - 6390 Persons 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
10-Re-appropriation of funds(+/-) .Work could not
be started due to site dispute in laying of distribution
system. Progress will be achieved in next month.
29 1632 Rural water Supply Scheme Chak No.675/16/GB Toba Tek SinghOn-going
Schemes28.057 20.000 2.686 1.205 0.533 44% 73%
1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016
3-Date of invitation of tenders.13.02.2017 4- Date of
Receipt of tenders -15.02.2017 5- Date of
completion as per PC-I 30.06.2018 6- Date of work
order - 09.03.2017 7- Anticipated date of completion
30.06.2018 8- No. of Beneficiary - 3561 Persons 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
10-Re-appropriation of funds(+/-) Work could not be
started due to site dispute in laying of distribution
system. Progress will be achieved in next month.
30 1633 Rural water Supply Scheme Chak No.685 26 GB Toba Tek SinghOn-going
Schemes21.024 16.243 0.508 0.127 0.000 0% 77%
1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016
3-Date of invitation of tenders.13.02.2017 4- Date of
Receipt of tenders -15.02.2017 5- Date of
completion as per PC-I 30.06.2018 6- Date of work
order - 04.03.2017 7- Anticipated date of completion
30.06.2018 8- No. of Beneficiary - 3381 Persons 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
10-Re-appropriation of funds(+/-) - Work could not
be started due to site dispute in laying of distribution
system. Progress will be achieved in next month.
31 1634Rural water Supply Scheme for Chak No.407/JB,
409/JB, 410/JB & 411/JBToba Tek Singh
On-going
Schemes99.832 74.101 3.333 2.500 1.740 70% 76%
1-Date of A.A 10.09.2015 2- Date of T.S 25.02.2016
3-Date of Prequalification -07.03.2016 4-Date of
invitation of tenders 18.03.2016 5- Date of Receipt
of tenders 26.03.2016 6- Date of work order -
27.04.2016 7- Date of completion as per PC-I
09.09.2017 8- Anticipated date of completion -
09.09.2017 9- No. of Beneficiary - 15516 Person 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
11-Re-appropriation of funds(+/-) Work in progress.
32 1635
Rural water Supply Scheme, Chak No.709/GB
and 710/GB, Tehsil Kamalia, District Toba Tek
Singh
Toba Tek SinghOn-going
Schemes18.232 14.000 0.744 0.186 0.000 0% 77%
1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016
3-Date of invitation of tenders. 13.02.2017 4- Date
of Receipt of tenders -15.02.2017 5- Date of
completion as per PC-I 30.06.2018 6- Date of work
order - 09.03.2017 7- Anticipated date of completion
30.06.2018 8- No. of Beneficiary - 5867 Persons 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
10-Re-appropriation of funds(+/-) Work could not be
started due to site dispute in laying of distribution
system. Progress will be achieved in next month.
33 1636
Rural water Supply Scheme, Chak No.712/GB
and Jamal Pahar, Tehsil Kamalia, District Toba
Tek Singh
Toba Tek SinghOn-going
Schemes22.981 17.000 1.994 0.499 0.000 0% 74%
1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016
3-Date of invitation of tenders.13.02.2017 4- Date of
Receipt of tenders -15.02.2017 5- Date of
completion as per PC-I 30.06.2018 6- Date of work
order - 03.03.2017 7- Anticipated date of completion
30.06.2018 8- No. of Beneficiary - 4430 Persons 9-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
10-Re-appropriation of funds(+/-) Work could not be
started due to site dispute in laying of distribution
system. Progress will be achieved in next month.
34 1637 water Supply & Sewerage Scheme Rajana District
Toba Tek SinghToba Tek Singh
On-going
Schemes179.779 104.999 8.333 6.250 6.000 96% 62%
1-Date of A.A 06.12.2014 2- Date of T.S 02.03.2015
3-Date of Rev: AA 28.05.2015 4-Date of
Prequalification - 16.08.2016 5-Date of invitation of
tenders 03.10.2016 6- Date of Receipt of tenders
04.10.2016 7- Date of work order 27.10.2016 8-
Date of completion as per PC-I 26.10.2018 9-
Anticipated date of completion 26.10.2018 10- No.
of Beneficiary -21302 Person 11 -Funds Released
by F.D 03.08.2018 & 24.01.2019 12-Re-
appropriation of funds(+/-) Work in progress.
35 1638
Rural water Supply schemes Chak No.285/GB,
383/JB, 390/JB, 380/JB, 382/JB Feroz and
336/GB, T.T. Singh
Toba Tek SinghOn-going
Schemes90.000 69.965 3.333 2.500 2.200 88% 80%
1-Date of A.A 28.12.2015 2- Date of T.S 25.02.2016
3-Date of Prequalification -07.03.2016 4-Date of
invitation of tenders 06.03.2016 5- Date of Receipt
of tenders 26.03.2016 6- Date of work order -
28.04.2016 7- Date of Completion as per PC-I
30.07.2017 8- Anticipated date of completion
30.07.2017 9- No. of Beneficiary - 37501 Person 10-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
11-Re-appropriation of funds(+/-) Work in progress.
36 1639
Installation of 02 No Water Filetration Plants in
Chak no 771/GB & Mouza Akbar Sau & UC Jussa
tehsil Per Mehal District Toba Tek Singh
Toba Tek SinghOn-going
Schemes6.000 0.000 2.000 2.000 1.000 50% 17%
1-Date of A.A 14.11.2018 2- Date of T.S 20.11.2018
3-Date of Prequalification 4-Date of invitation of
tenders 19.12.2018 5- Date of Receipt of tenders
21.12.2018 6- Date of work order 7- Date of
completion as per PC-I 8- Anticipated date of
completion 9- No. of Beneficiary -3233 Person 10-
Funds Released by F.D 18.01.2019 11-Re-
appropriation of funds (+/-) work in progress.
37 1640
Provision of Water Supply and Drainage Scheme
in Village Sher Garh UC Machiwal Tehsil & District
Gujrat
GujratOn-going
Schemes49.971 0.400 3.333 2.500 1.667 67% 4% A.A Date =28.2.2018.work in progress
38 1641Construction of street / PCC / Soling / Nallian in
various Ucs of District M.B.Din
Mandi
Bahauddin
On-going
Schemes150.000 69.978 3.333 5.150 4.317 84% 50%
* A.A Date. 25.08.2017* T.S Date. 13.09.2017* Start
Date. 06.01.2018* Completion date
05.01.2020*Work in progress.
39 1642Rural water Supply & Drainage Scheme Village
Badshah Pur Tehsil Malikwal District M.B.Din
Mandi
Bahauddin
On-going
Schemes85.587 75.587 3.333 2.500 1.667 67% 90%
* A.A Date. 19.03.2015* T.S Date. 02.04.2015* Start
Date 22.05.2015.* Completion date 30.06.2019.*
Work in progress.
40 1643Rural water Supply & Drainage Scheme Village
Jayya Tehsil & District M.B.Din
Mandi
Bahauddin
On-going
Schemes62.780 57.780 1.667 0.650 0.234 36% 92%
* A.A Date. 19.03.2015* T.S Date. 02.04.2015* Start
Date 22.05.2015.* Completion date 30.06.2019.*
Work in progress.
41 1644
Rural water Supply and drainage Scheme
Bhaagowal & Noor Pur Peeran with adjecent
abadies tehsil Mailk waal district mandi bahuddin
Mandi
Bahauddin
On-going
Schemes50.000 45.000 1.667 0.450 0.034 8% 90%
* A.A Date. 28.04.2015* T.S Date. 19.05.2015* Start
Date 18.06.2015.* Completion date 30.06.2019.*
Work in progress
42 1645Installation of 02 tubewells at Tahayat & Chandrai
Village, Green Town, Lahore Lahore
On-going
Schemes36.878 20.044 5.600 2.200 0.800 36% 57%
Scheme completed. Funds are for the operation &
maintenance of scheme.
43 1646 Rural water Supply Scheme Mohlanwal LahoreOn-going
Schemes53.594 42.378 2.734 2.051 1.367 67% 82%
Scheme completed. Funds are for the operation &
maintenance of scheme.
44 1647 Rural water Supply Scheme Sundar LahoreOn-going
Schemes24.475 22.331 0.715 0.536 0.358 67% 93%
Scheme completed. Funds are for the operation &
maintenance of scheme.
45 1648 Rural water Supply Scheme Village Bath LahoreOn-going
Schemes39.469 29.475 3.331 2.498 1.666 67% 79%
Scheme completed. Funds are for the operation &
maintenance of scheme.
46 1649 Rural water Supply Scheme Village Chah Tamoli LahoreOn-going
Schemes16.930 12.038 1.308 0.981 0.654 67% 75%
Scheme completed. Funds are for the operation &
maintenance of scheme.
47 1650
Establishment/ Construction of water Supply
Scheme at UC 30, 31, 32 wanadala dial singh and
dhaka nizampura tehsil feroz wala District
Sheikhupura
SheikhupuraOn-going
Schemes152.044 85.000 8.332 6.249 4.166 67% 59% Work in Progress
48 1651 Water Supply Scheme Pind burj Attari SheikhupuraOn-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress
49 1652Rural water Supply and Drainage Scheme Javed
Nagar, District SheikhupuraSheikhupura
On-going
Schemes198.903 72.367 6.667 5.000 3.334 67% 38% Work in Progress
50 1653Rural water Supply Drainage Scheme Iqbal Town
District SheikhupuraSheikhupura
On-going
Schemes140.161 83.696 3.333 2.500 1.667 67% 61% Work in Progress
51 1654Rural water Supply Drainage Scheme UC Kot
Ranjeet Singh SheikhupuraSheikhupura
On-going
Schemes95.061 54.999 3.333 2.500 1.667 67% 60% Work in Progress
52 1655Rural Warter Supply and Drainage P.C.C Scheme
Tibbi Kamboh, Mochi Pura, Kasur City.Kasur
On-going
Schemes199.551 29.782 6.667 5.000 3.334 67% 17% Work in Progress
53 1656Rural Water Drainage PCC Scheme Bhoojke,
Naike & Adjoining Abadies District Kasur.Kasur
On-going
Schemes114.522 97.085 5.812 1.509 0.056 4% 85% Work in Progress
54 1657
Rural water Supply & Drainage PCC Scheme at
Marali Hithar and Adjoining Abadies District Kasur
(Revised)
KasurOn-going
Schemes97.453 52.295 5.072 1.324 0.056 4% 54% Work in Progress
55 1658
Rural water Supply & Drainage Scheme Chak
No.14 & Ghandhi Otar Tehsil Pattoki District
Kasur.
KasurOn-going
Schemes105.412 84.160 20.000 15.000 10.000 67% 89% Work in Progress
56 1659
water Supply & Drainage Scheme They Kalay,
Basti Balochi, Jhalar Qadir, Jhalar Rehmani, Jhalar
Choudhry & Jhalar Baglian Wali i/c Tubewell of
Rao Tamkeen District Kasur.
KasurOn-going
Schemes119.701 83.750 3.333 4.600 3.767 82% 73% Work in Progress
57 1660
Water Supply and Drainage Scheme Gondy
Warha, Lambey Jagir, Dhaban, Sherpur, Lambey
Mahtam & Fatey Wala.
KasurOn-going
Schemes82.108 78.345 1.254 0.314 0.000 0% 95% Work in Progress
58 1661
water Supply & Drainage Scheme Chak
No.31,32,33 Phullani, Dhoop Sarri & Saharankey
District Kasur
KasurOn-going
Schemes199.992 84.797 5.000 3.750 2.500 67% 44% Work in Progress
59 1662
Rural water Supply and Drainage PCC Scheme at
Mandi Usmanwala and Adjoining Abadies District
Kasur.
KasurOn-going
Schemes158.978 138.348 6.877 8.279 6.560 79% 91% Work in Progress
60 1663
Rural water Supply and Drainage PCC Scheme
Hardo Ban Bodla and Adjoining Abadies District
Kasur.
KasurOn-going
Schemes99.851 71.924 3.333 2.500 1.667 67% 74% Work in Progress
61 1664
Rural water Supply and Drainage PCC Scheme
Maan Bhamni Wala and Adjoining Abadies District
Kasur.
KasurOn-going
Schemes178.985 170.646 2.778 0.695 0.000 0% 95% Work in Progress
62 1665Rural water Supply and Drainage PCC Scheme
Rajuwal and adjoining Abadies District Kasur.Kasur
On-going
Schemes113.943 111.586 0.786 0.197 0.000 0% 98% Work in Progress
63 1666Rural Water Supply & Drainage Scheme, Qila
Dewan Singh Depaplur, Okara.Okara
On-going
Schemes22.250 5.481 7.252 5.439 3.625 67% 41%
Date of A.A 22-04-2017 Date of T.S 29.09.2016
Date of invitation of tenders 25-05-2017 Date of
Receipt of tenders 26-05-2017 Date of work order
02-06-2017 Date of completion as per PC-I
Anticipated date of completion 30-06-2018 No. of
Beneficiary 11550 Person, Work is in progress.
64 1667 water Supply Scheme Chak No.120/9.L Kameer. SahiwalOn-going
Schemes105.498 91.699 4.599 3.449 3.100 90% 90%
Date of AA 23.11.2016, Date of TS 07.12.2016,
Date of receipt of tender 07.01.2017, Date of Work
Order 08.02.2017, Date of completion as per PC-1
31.01.2018, Anticipated date of completion
30.06.2019 subject to availablity of balance funds,
Work in progress.
65 1668 R/W/S/Scheme Gareywala, Nawabpur,Basti Nau MultanOn-going
Schemes70.476 52.661 2.333 1.750 1.167 67% 76%
1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010
3. Date of Pre-Qualification: - 4.Date of invitation of
tender 04.03.2010 5.Date of Receipt of tenders
06.03.2010 6.Date of work order 14.04.2010 7.Date
of Completion as per PC-l 13.02.2013 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018. 24.01.2019 10. No. of
beneficiaries 51946 Persons. Work is in Progress.
66 1669R/W/S/Scheme Raja Pur, Siddiquebad,
Hirwat,Yere WalaMultan
On-going
Schemes77.962 64.018 0.667 0.500 0.334 67% 83%
1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010
3. Date of Pre-Qualification: - 4.Date of invitation of
tender 06.02.2010 5.Date of Receipt of tenders
08.02.2010 6.Date of work order 14.04.2010 7.Date
of Completion as per PC-l 13.02.2013 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018. 24.01.2019 10. No. of
beneficiaries 43334 Persons. Work is in Progress.
67 1670 R/W/S/Scheme Taraggar. MultanOn-going
Schemes61.140 51.141 3.333 2.500 1.667 67% 86%
1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010
3. Date of Pre-Qualification: - 4.Date of invitation of
tender 06.02.2010 5.Date of Receipt of tenders
08.02.2010 6.Date of work order 18.06.2010 7.Date
of Completion as per PC-l 17.06.2012 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018. 24.01.2019 10.No. of
beneficiaries 20623 Persons. Work is in Progress.
68 1671Rural Water Supply & Sewerage Scheme Nai
Wala Multan
On-going
Schemes45.238 41.886 1.000 0.750 0.500 67% 94%
1. Date of A.A: 17.09.2015 (28.05.2016) 2. Date of
T.S: 08.06.2016 3. Date of Pre-Qualification:
11.06.2016 4. Date of Invitation of Tender:
18.07.2016 5. Date of receipt of Tender: 20.07.2016
6. Date of Award: 22.07.2016 7. Date of Completion
as per PC-I: 16.09.2016 8. Anticipated date of
completion 30.06.2018 9. Date of released of funds
23.11.2018. 24.01.2019 10. No. of Benificiary=6508
Persons. Work is in progress.
69 1672Sewerage Drainage Scheme Qasba Jalalpur Khaki
ShujabadMultan
On-going
Schemes46.177 43.912 1.000 2.015 1.490 74% 98%
1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date
of Pre-Qualification: 30.09.2016 4. Date Invitation of
Tender: 01.11.2016 5. Date of Receipt of Tender:
02.11.2016 6. Date of Award: 12.11.2016 7. Date of
Completion as per PC-I: 11.05.2018 8. Anticipated
date of completion 30.06.2018 9. Date of released
of funds 23.11.2018 10.No. of Benificiary= Persons.
Work is in progress.
70 1673 water Supply / Sewerage Mouza Rawani. LodhranOn-going
Schemes29.450 24.182 1.721 1.291 0.950 74% 85%
1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-
2016 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 14-11-2016 5. Date of Receipt
of Tender: 15-11-2016 6. Date of Award: 03-12-
2016 7. Date of Completion as per PC-I: 31-12-2017
8. Anticipated Date of Completion: 02-12-2017
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
8834 Persons. Work is in Progress.
71 1674
Rural water Supply Scheme Chak No.12/M &
14/M (East & West) Tehsil Dunyapur, District
Lodhran
LodhranOn-going
Schemes29.922 21.446 2.784 2.088 1.600 77% 77%
1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-
2016 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 14-11-2016 5. Date of Receipt
of Tender: 15-11-2016 6. Date of Award: 08-12-
2016 7. Date of Completion as per PC-I: 31-12-2017
8. Anticipated Date of Completion: 07-12-2017
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
6980 Persons. Work is in Progress.
72 1675Rural Water Supply Scheme Quatabpur Dunyapur,
Tehsil Dunyapur, District Lohdran Lodhran
On-going
Schemes29.850 9.623 6.742 1.686 0.000 0% 32%
1. Date of A.A. 22-08-2015. 2. Date of T.S. 27-08-
2015 Rev. T.S 07-02-2017 3. Date of Pre-
Qualification: 4. Date of invitation of tender 01-12-
2015 5. Date of Receipt of tenders 02-12-2015 6.
Date of work order 16-12-2015. 7. Date of
Completion as per PC-l 21-08-2016 8. Anticipated
date of completion 30-06-2017 9.Date of released of
funds 03-08-2018 24.01.2019 10. Reason of Slow
Moving: 11.No. of beneficiaries 13535 Persons.
Scheme completed & under test operation. Rs.1.686
million proposed for re-appropriation
73 1676Provision of water Supply Schemes in Chak No.
135/10.R, District Khanewal.Khanewal
On-going
Schemes60.664 47.747 4.306 3.230 3.230 100% 84%
1. Date of A.A (Amended) 04.04.2016 2. Date of
T.S: 12.04.2016 3. Date of Pre-Qualification:
02.04.2016 4. Date of Invitation of Tender:
21.04.2016 5. Date of Receipt of Tender:
23.04.2016 6. Date of Work order: 30.04.2016 7.
Date of Completion as per PC-I: 16.09.2017 8.
Anticipated Date of completion: 31.12.2018 9. Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ------ 11No. of beneficiaries
15048 Persons Work is in progress.
74 1677Provision of Water Supply Schemes in Chak No.
136/10.R, District Khanewal.Khanewal
On-going
Schemes62.211 49.998 1.000 0.750 0.750 100% 82%
1. Date of A.A (Amended) 17.09.2015 2. Date of
T.S: 07.03.2016 3. Date of Pre-Qualification:
02.04.2016 4. Date of Invitation of Tender:
21.04.2016 5. Date of Receipt of Tender:
23.04.2016 6. Date of Work order: 30.04.2016 7.
Date of Completion as per PC-I: 29.10.2016 8.
Anticipated Date of completion: 31.12.2018 9. Date
of released of funds 23.11.2018 24.01.2019 10.
Reason of Slow Moving: _____ 11No. of
beneficiaries 12907 Persons Work is in progress.
75 1678Rural Sewerage / Drianage scheme chak No.
146/EB and Dalan, District VehariVehari
On-going
Schemes18.710 8.742 3.319 4.149 1.820 44% 56%
1. Date of A.A: 04.04.2017. 2. Date of T.S:
10.04.2017 3. Date of Pre-Qualification: 4. Date of
Invitation of Tender: 08.05.2017 5. Date of Receipt
of Tender: 09.05.2017 6. Date of Work order:
25.11.2017 7. Date of Completion as per PC-I:
24.11.2018 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ----- 11. No.
of Beneficiary= 20316 Persons Work is in progress.
76 1679Provision of water Supply Scheme in Kundi Wala
UC shadan Lund
Dera Ghazi
Khan
On-going
Schemes50.325 38.936 3.789 2.842 2.132 75% 82% "• Date of A.A = 22.08.2015
77 1680Provision of water Supply Scheme in Notak
Sakhani UC Kala
Dera Ghazi
Khan
On-going
Schemes47.463 29.182 5.834 4.376 3.107 71% 68% "• Date of A.A = 22.08.2015
78 1681Provision of water Supply Scheme in Sabzani UC
Kala
Dera Ghazi
Khan
On-going
Schemes36.579 28.136 2.556 1.917 1.438 75% 81% "• Date of A.A = 22.08.2015
79 1682Extension & Augmentation of water Supply
Scheme Sakhi Sarwar
Dera Ghazi
Khan
On-going
Schemes87.805 77.753 0.333 0.250 0.167 67% 89% "• Date of A.A = 16.12.2014
80 1683Provision of Rural water Supply Scheme Nutkani,
District D.G. Khan
Dera Ghazi
Khan
On-going
Schemes82.680 59.914 7.577 5.683 4.149 73% 77% "• Date of A.A = 23.09.2016
81 1684 water Supply Scheme at Councilor Muhammad Ali
Basti Rojhani Sakhi Sarwar
Dera Ghazi
Khan
On-going
Schemes25.000 24.000 0.333 0.250 0.188 75% 97% "• Date of A.A = 23.09.2016
82 1685
Reheblitiation/Extension of Water Supply Scheme
Tunga Menhal Phase-II (Basti Ouroo, Basti Jora,
Basti Rind, Basti Bun Dhola, Basti Gabolan, Basti
Manka & Basti Mahool jee)
Dera Ghazi
Khan
On-going
Schemes20.000 4.844 5.051 3.788 2.841 75% 38% "• Date of A.A = 25.7.2017
83 1686Rehabilitation of Water Supply in Pir Qatal PP-244
District Dg Khan
Dera Ghazi
Khan
On-going
Schemes10.000 4.998 1.667 1.250 0.913 73% 59% "• Date of A.A = 25.7.2017
84 1687Rehabilitation of Water Supply in Shehzada Sultan
Town PP-244 District Dg Khan
Dera Ghazi
Khan
On-going
Schemes10.000 4.000 2.000 1.500 1.125 75% 51% "• Date of A.A = 25.7.2017
85 1688Rehabilitation of Water Supply in Mehboob Abad
PP-244 District Dg Khan
Dera Ghazi
Khan
On-going
Schemes10.000 4.999 1.667 1.250 0.888 71% 59% "• Date of A.A = 25.7.2017
86 1689 Improvement of Rural water Supply Scheme Dajal RajanpurOn-going
Schemes228.679 217.875 3.601 2.701 1.801 67% 96% "• Date of A.A = 23.12.2014
87 1690 water Supply Schemes in Mouza Fateh Pur and
Ali Pur District MuzaffargarhMuzaffargarh
On-going
Schemes70.000 18.680 4.173 3.130 2.087 67% 30% "• Date of A.A 22-09-2016
88 1691
Provision of Fund for Restortaion of water Supply
Scheme in his Constituency District Bahwalnagar
(i) RWSS Khattan,(ii) RWSS Jananay wala, (iii)
RWSS Ghulab Ali,(iv) RWSS Bajak & Khamay
Wala
BahawalnagarOn-going
Schemes67.817 49.499 5.339 2.248 1.900 85% 76%
Date of AA(DDWP) 06.10.2015. . Date of TS. 22-02-
2016. Date of invitation of tenders=28-01-2016.
Date of receipt of tenders = 02-03-2016. Date of
award= 30-04-2016. Date of completion 29-04-2018.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Completed & handed over. Excess
funds Rs.1.756 million surrendered dated
19.10.2018.
89 1692
Rehabilitation of Rural water Supply Scheme
Chak No 62 4R Tehsil Haroonabad District
Bahawalnagar
BahawalnagarOn-going
Schemes38.959 36.550 0.320 0.240 0.205 85% 94%
Date of A.A: 22-01-2015. . Date of T.S 26-01-2015.
Date of revised T.S 12-01-2017. Date of receipt of
tenders =15-04-2015 . Date of work order= 22-05-
2015. Date of completion as per agreement= 21-11-
2015.Anticipated date of completion= 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Completed
90 1693Rehabilitation of rural water Supply scheme chak
no. 69/4-R, 80/1-L & Azafi Abadis Chak No. 85/5-RBahawalnagar
On-going
Schemes39.568 38.934 0.211 0.054 0.054 100% 99%
Date of AA. 08.08.2016. Date of T.S. 21.10.2016.
Tender received on 02.11.2016. Date of award.
25.11.2016. Date of completion 24.11.2017.
Anticipated date of completion 31-12-2018. Date of
receipt of funds by F.D. 20.07.2018 &
11.01.2019.Scheme completed. Excess funds
Rs.0.104 million surrendered dated 19.10.2018.
91 1694
Rehabilitation of Rural water Supply Schemes
Muga Chandna Mirdin Hakim Mirdin Mohib Ali
Khazan Singh
BahawalnagarOn-going
Schemes99.971 53.035 6.667 5.000 4.000 80% 57%
Date of AA. 19.08.2016. Date of T.S. 25.10.2016.
.Date of receipt of tenders= 14-12-2016 . Date of
award=29-12-2016. Date of completion=28-11-
2017. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
92 1695Rural water Supply Scheme Jand wala and Jand
wala saniBahawalnagar
On-going
Schemes25.000 19.550 1.817 0.459 0.415 90% 80%
Date of AA(DDWP). 18-08-2015 . Date of TS. 06-10-
2015. Date of receipt of tenders = 20-10-2015 . Date
of work order= 04.11.2015. . Date of completion as
per agreement= 03.11.16. .Anticipated date of
completion 30-06-2019. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Scheme Completed
in saving & handed over. Excess funds Rs.0.904
million surrendered dated 19.10.2018.
93 1696 water Supply Scheme Doonga Boonga BahawalnagarOn-going
Schemes174.252 120.139 6.667 5.000 4.300 86% 71%
Date of AA (DDSC). 15-10-2015. Date of TS. 22-02-
201`6. Date of prequalification on 22-03-2016. Date
of receipt of tenders = 07-04-2016. Date of work
awarded 18.05.2016. Date of completion as per
Agreement: 18.11.2017 .Anticipated date of
completion 30-06-2019.Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Work is in progress.
94 1697
Rural water Supply Schemes Mouza Janu Khan
Basti Kapooran and kot Ganga Singh District
Bahawalnagar
BahawalnagarOn-going
Schemes97.808 43.343 6.667 5.000 4.300 86% 49%
Date of AA. 19.08.2016. Date of T.S. 25.10.2016.
.Date of receipt of tender=14-12-2016. Date of
award +19-01-2017. Date of completion+18-12-
2017. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
95 1698 water Supply Scheme Noor Sar (New & Old) BahawalnagarOn-going
Schemes72.817 42.617 3.333 2.500 2.050 82% 61%
Date of AA(DDWP). 06.10.2015. . Date of TS. 22-
02-2016. Date of receipt of tenders = 02-03-2016.
Date of work order=01-04-2016. Date of completion
as per agreement= 30-10-2017.Anticipated date of
completion 30-06-2019. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Work is in progress.
96 1699Rural water Supply scheme chak no. 128/6-R
including all adjoining abadies.Bahawalnagar
On-going
Schemes22.200 20.273 0.536 0.134 0.122 91% 92%
Date of AA. 08.08.2016. Date of T.S. 21.10.2016.
Tender received on 02.11.2016. Date of award.
28.11.2016. Date of completion 27.11.2017.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Scheme completed in saving & handed over to
CBO for O & M . Excess funds Rs.0.268 million
surrendered dated 19.10.2018.
97 1700Rural water Supply Scheme, Kalowal Thathi Bala
Raja Tehsil Lalian District ChiniotChiniot
On-going
Schemes13.322 6.430 2.297 1.723 0.800 46% 54%
1. Date of AA = 15.12.2016 2. Date of TS =
23.12.2016 3.Date of Award of work . 19.05.2017
4.Dated of Released Funds 4. No. of Beneficiaries =
5375 Persons Funds Released upto 24.01.2019 by
the Chief Engineer (South) PHED Lahore and work
is in progress. Target progress will be achieved in
coming month.
98 1701
Rehabilitation and Repair of Sewerage Scheme
of Housing Scheme , Gujar Khan City, Tehsil Gujar
Khan, District Rawalpindi
RawalpindiOn-going
Schemes29.980 15.158 3.333 3.500 2.667 76% 59% Work in progress.
99 1702
Drainage / Sewerage System in Village
Ghourgushti (Phase II), Tehsil Hazro, District
attock
AttockOn-going
Schemes88.786 85.975 0.937 0.703 0.469 67% 97%
A.A Date 03.09.2014.T.S Date 29.09.2014. Date of
Start of Scheme 16.12.2014.Date of Completion of
Scheme 30.06.2019.Work is in progress.
100 1703Drainage and Sanitation scheme in village
Hameed, Tehsil Hazro, District attockAttock
On-going
Schemes44.134 26.243 5.960 1.490 0.000 0% 59%
A.A Date 01.10.2013. T.S Date 27.01.2014. Date of
Start of Scheme 06.03.2014.Date of Completion of
Scheme 30.06.2019. Dispute of land.
101 1704
Construction of Street Pavement in Village Kalu
Kalan (Phase II), (PP 16) Tehsil Hazro District
attock
AttockOn-going
Schemes26.227 24.730 1.497 2.023 0.749 37% 97%
A.A Date 23.01.2015. T.S Date 18.04.2015.Date of
Start of Scheme 05.06.2015.Date of Completion of
Scheme 30.06.2019.Work is in progress.
102 1705Extension of Rural Drainage Scheme in Villages
Haroon, Saleem Khan & AdalzaiAttock
On-going
Schemes60.055 46.834 4.405 3.304 2.203 67% 82%
A.A Date 05.08.2016.T.S Date 15.08.2016. Date of
Start of Scheme 28.11.2016. Date of Completion of
Scheme 30.06.2019.Work is in progress.
103 1706Rural Drainage Scheme in Villages Chachi,
Saiden, YasinAttock
On-going
Schemes29.955 20.816 3.046 2.285 1.523 67% 75%
A.A Date 12.04.2017. T.S Date 18.04.2017. Date of
Start of Scheme 10.06.2017.Date of Completion of
Scheme 30.06.2019.Work is in progress.
104 1707Rural drainage Scheme in Village Mirza Phase2
Tehsil and District attock.Attock
On-going
Schemes104.909 28.955 6.667 5.000 3.334 67% 31%
A.A Date 05.08.2016.T.S Date 09.09.2016.Date of
Start of Scheme 16.03.2017. Date of Completion of
Scheme 30.06.2019.Work is in progress.
105 1708Rural drainage scheme in villages Formli,haider
Mallah,District attock.Attock
On-going
Schemes55.840 42.497 4.448 3.336 2.224 67% 80%
A.A Date 01.04.2016. T.S Date 22.04.2016. Date of
Start of Scheme 30.05.2016.Date of Completion of
Scheme 30.06.2019.Work is in progress.
106 1709Rural drainage scheme in villages Perzai, Muraria,
Pandak, District attockAttock
On-going
Schemes29.604 26.725 0.602 0.882 0.731 83% 93%
A.A Date 01.04.2016. T.S Date 09.09.2016.Date of
Start of Scheme 24.11.2016. Date of Completion of
Scheme 30.06.2019.Work is in progress.
107 1710Rural drainage scheme in villages Ramu,Bhadar
Khan,District attockAttock
On-going
Schemes29.208 28.717 0.491 0.368 0.246 67% 99%
A.A Date 01.04.2016. T.S Date 20.04.2016.Date of
Start of Scheme 31.05.2016.Date of Completion of
Scheme 30.06.2019.Work is in progress.
108 1711Rural drainage scheme in villages, Nartopa,
Khagwani, District attockAttock
On-going
Schemes55.106 26.472 3.333 3.670 2.837 77% 53%
A.A Date 05.08.2016. T.S Date 15.08.2016.Date of
Start of Scheme 24.11.2016.Date of Completion of
Scheme 30.06.2019.Work is in progress.
109 1712Const. of Sewerage & Drainage Scheme Kallar
KaharChakwal
On-going
Schemes98.759 47.426 3.333 4.325 3.492 81% 52%
Date of A.A 17.09.2015. Date of T.S 08.10.2015.
ateof Start 18.03.2016.Date of completion
31.12.2019.Woork is in progress. Funds to the tune
of Rs.1.825 Million re-appropriated from other
schemes to meetup the progress of work.
110 1713 Rural Drainage Scheme Mangwal District Chakwal ChakwalOn-going
Schemes11.000 9.773 0.392 0.098 0.000 0% 89%
Date of A.A 20.04.2017. Date of T.S
22.04.2017.Date of Start 12.06.2017.Date of
scheme.completed.Excessive funds surrendered
through reappropriation.
111 1714Rural Drainage Scheme UC Udherwal District
ChakwalChakwal
On-going
Schemes14.000 12.424 0.482 0.121 0.000 0% 89%
Date of A.A 20.04.2017 .Date of T.S
22.04.2017.Date of Start 10.06.2017.Date of
scheme completed. Excessive funds surrendered
through re-appropriation.
112 1715Rural Drainage Scheme UC Nara Mogla District
ChakwalChakwal
On-going
Schemes11.000 9.563 0.476 0.119 0.000 0% 87%
Date of A.A 20.04.2017. Date of T.S
22.04.2017.Date of Start 08.06.2017.Scheme
completed. Excessive funds surrendered through re-
appropriation.
113 1716 Sewerage Scheme Lawa, District Chakwal ChakwalOn-going
Schemes78.169 49.975 3.333 2.500 1.667 67% 66%
Date of A.A 24.08.2016. Date of T.S 01.11.2016.
Date of Start 23.12.2016. Date of completion
31.12.2019.Full funds utilized. Scheme is short
funded.
114 1717 Rural Drainage Scheme Khanpur ChakwalOn-going
Schemes150.000 52.462 5.000 5.750 4.495 78% 38%
"Date of A.A 24.08.2016 . Date of T.S
01.11.2016.Date of Start 16.01.2017.Date of
completion 30.06.2020
115 1718Improvement/Rehabilitation of Sewerage System in
Bilal Town Tehsil & District JhelumJhelum
On-going
Schemes29.800 27.764 0.676 0.169 0.000 0% 93%
Date of A.A 16-03-16.Date of T.S 28-03-
2016.Revised T.S 18-10-2017.Date of
Commencement 07-05-2016.Scheme Completed in
saving funds are reappropriated to other scheme.
116 1719Rural drainage scheme Pinanwal, Tehsil Pind
Dadan Khan.Jhelum
On-going
Schemes100.000 19.985 3.333 2.500 1.667 67% 22%
Date of A.A 26-08-2016.Date of T.S 15-12-2016.•
Work awarded on 02-03-2017. • Work in progress.
117 1720Sewerage scheme Mouza Ahmaday Wala District
Sargodha Sargodha
On-going
Schemes23.426 19.959 1.149 0.575 0.575 100% 88%
Date of A.A 27.08.2016, Date of T.S 03.09.2016,
Date of Award 06.12.2016, Scheduled date of
Completion on 05.12.2017, Date of
Commencement, 06.12.2016, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.Sullage
Carrier 3250-Rft & Drain 9841-Rft constructed. PCC
Slab 18393-Cft & Soling 19458-Cft laid. Work in
progress.
118 1721Sewerage/Sullage Carrier for Jalpana/Chak
Muzafarabad/Masar/Sardarpur etc.Sargodha
On-going
Schemes30.000 20.807 2.795 2.096 1.548 74% 75%
"Date of A.A 27.08.2016, Date of T.S 03.09.2016,
Date of Award 08.12.2016, Scheduled date of
Completion on 07.12.2017, Date of
Commencement, 08.12.2016, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
119 1722RSD Scheme Chak No 4 SP Chak No 5 NB Chak
No 7 ML Chak No 65 SB Hujjan District Sargodha Sargodha
On-going
Schemes105.642 44.397 3.333 2.500 2.500 100% 44%
"Date of A.A 27.08.2016, Date of T.S 28.10.2016,
Date of Award 14.02.2017, Scheduled date of
Completion on 13.02.2018, Date of
Commencement, 14.02.2017, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
120 1723Rural Sewerage / Drainage PCC Scheme for
Jhawarian Sargodha
On-going
Schemes100.000 34.967 3.333 2.500 2.500 100% 37%
Date of A.A 27.08.2016, Date of T.S 07.11.2016,
Date of Award 10.02.2017, Scheduled date of
Completion on 09.02.2018, Date of
Commencement, 10.02.2017, Funds released on
30.07.2018, Funds on-lined on 30.07.2018. 6661-
Rft, Nallah, Drain, 2866-Rft 01- No. collecting tank
constructed. PCC slab 27375-Cft laid and Work in
progress.
121 1724 Rural Sewerage / Drainage Scheme Bhagtanwala SargodhaOn-going
Schemes84.030 28.600 3.333 2.500 1.934 77% 36%
"Date of A.A 27.08.2016, Date of T.S 28.10.2016,
Date of Award 31.01.2017, Scheduled date of
Completion on 30.01.2018, Date of
Commencement, 31.01.2017, Funds released on
04.08.2017, Funds on-lined on 04.08.2017.
122 1725
Construction / Rehablitation of streets, Drains ,
Nullah and Soling 2 Shummali, Village Lak Ditrict
Sargodha
SargodhaOn-going
Schemes6.000 0.100 1.000 0.750 0.000 0% 2%
"The nomenclature of scheme is wrongly printed in
ADP as the correct nomenclature is “Construction /
Rehabilitation of Street Drains, Nallah and Soling 20
Shumali, 61 Shumali, Village Lak District
Sargodha.""
123 1726Provision of Sewerage System and PCC Slabs in
Village Roda.Khushab
On-going
Schemes92.683 14.299 3.333 2.500 2.370 95% 18%
Date of AA 18.08.2017 Date of TS 11.09.2017 Date
of award 22.01.2018 Date of completion 30.06.2020
Work is in progress.
124 1727Construction of Rural water Supply Scheme
Marmandi Tehsil & District MianwaliMianwali
On-going
Schemes13.500 12.707 0.256 0.192 0.128 67% 95%
Date of A.A.27-05-2016, Date of T.S.19-05-2017,
Date of Start of Work. 10-05-2017, Remarks.
E.R.S=3/3, Tube Well=1/1, Pump House=1/1,
P/Machinery= Arranged/1, R/FMain= 6"i/d G.I
Pipe=1150/1200, 4"i/d G.I Pipe= 2250/2250, 3"i/d
G.I Pipe=3012/3020, 2"i/d G.I Pipe=1400/1400,
6"i/d PVC Pipe=1960/1900, 3"i/d PVC= 9633/9805,
G.S. Tank 20000-Glns=1/1, T/Line= Demand Notice
paid to Wapda Connection awaited/1. Work is in
progress.
125 1728 Sewerage & Sanitation Scheme Daud Khel MianwaliOn-going
Schemes98.377 19.928 6.667 5.000 3.334 67% 24%
Date of A.A.27-08-2016, Date of T.S.09-12-2016,
Date of Start of Work.03-02-2017, Remarks RCC
Sewer=9"i/d=1240-Arrange/20356, 12"i/d=1130-Rft
Laid & 992-arranged /12812, 15"i/d=728-Rft Laid &
630-Arranged /6645, 18"i/d=1850-Rft Laid/3348,
21"i/d=832-Arranged/1768, 24"i/d=1573/4870,
27"i/d=3841/5505, 33"i/d=2294/3128,
S/Carrier=0/200, PCC Slab=0/33597. Work is in
progress.
126 1729 Sewerage & Sanitation Scheme Shahbaz Khel MianwaliOn-going
Schemes95.743 29.964 6.667 5.000 3.334 67% 35%
Date of A.A.27-08-2016, Date of T.S.06-10-2016,
Date of Start of Work.22-12-2016, Remarks RCC
Sewer=9" i/d=15294/33286, 12"i/d= 14502/21045,
15"i/d= 3381/3659, 21"i/d= 766/864,
24"i/d=2253/2445, PCC Slab= 0/62379. Work is in
progress.
127 1730Sewerage / Drainage Scheme Mouch, District
Mianwali Mianwali
On-going
Schemes100.000 46.431 7.856 5.892 3.928 67% 50%
Date of A.A.04-08-2015, Date of T.S.14-09-2015,
Date of Start of Work 16-11-2015, Remarks RCC
Sewer=9" i/d= 23007/35130, 12"i/d= 18238/12053,
15"i/d= 3239/4564, 18"i/d=5720/4902, 21"i/d= 1608
/1126. Sullage Carrier= 230/2411. Work is in
progress.
128 1731 Sewerage / Drainage Scheme UC Rokhari MianwaliOn-going
Schemes50.000 22.466 4.476 3.357 2.237 67% 49%
Date of A.A.27-08-2016, Date of T.S.03-09-2016,
Date of Start of Work 03-12-2016 Remarks RCC
Sewer=9" i/d=10551/13484, 12"i/d= 10290/7642,
15"i/d= 5982/6288, 18"i/d=1294/1299, Sullage
Carrier= 0/200. Work is in progress.
129 1732Rural Sewerage Scheme Harnoli Tehsil Piplan,
MianwaliMianwali
On-going
Schemes94.000 44.953 5.000 3.750 2.498 67% 50%
Date of A.A. 27-08-2016, Date of T.S.09-12-2016,
Date of Start of Work.27-01-2017, Remarks RCC
Sewer=9"i/d=3200-Rft Arranged/19157,12"i/d=8504-
Rft Arranged/8786,15"i/d=418-Rft Laid & 2374-Rft
Arranged/2826,18"i/d=655-Rft & 945-Rft
Arranged/1624, 21"i/d=1173-Laid & 183-Rft
Arranged/1356,24"i/d=900-Laid & 412-Rft
Arranged/1329, 30"i/d=380-Rft Laid/392, Screening
Chamber =1/1, Collecting Tank 20'dia =1/1,Control
Room= 1/1,Discharge Sump=0/1, P/Machinery=0/2,
S/Carrier=0/1250, S/Drain= 600/4175, PCC
Slab=111243/142412, Culvert=0/1, Electric
T/Line=0/1. Work is in progress.
130 1733PCC Slab and Sewerage Scheme in Street Noon
Dager UC Tehsil Kaloor Kot District Bhakkar Bhakkar
On-going
Schemes48.600 29.681 3.333 2.500 2.500 100% 66%
Date of A.A 27.08.2016 Date of T.S 03.09.2016
Date of Commencement 28.11.2016 Date of
completion 31.12.2019
131 1734
PCC Slab and Sewerage Scheme Shahyan Wala
U.C Noora Sharif Tehsil Kaloor Kot District
Bhakkar
BhakkarOn-going
Schemes30.000 14.397 3.333 2.500 1.667 67% 54%
Date of A.A 27.08.2016 Date of T.S 03.09.2016
Date of Commencement 09.11.2016 Date of
completion 31.12.2019
132 1735Provision of Sewerage/Drainage/Nali UC Mullah
WaliBhakkar
On-going
Schemes30.000 7.000 3.333 2.500 2.000 80% 30%
Date of A.A 10.08.2017 Date of T.S 21.10.2017
Date of Commencement 03.11.2017 Date of
completion 30.06.2020
133 1736Provision of Sewerage/Drainage/Nali UC
PeerashabBhakkar
On-going
Schemes30.000 10.000 6.667 5.000 4.334 87% 48%
Date of A.A 10.08.2017 Date of T.S 21.10.2017
Date of Commencement 03.11.2017 Date of
completion 30.06.2020
134 1737
Sewerage Drainage and PCC Slab and Drain in
Town Punjgrain Tehsil Darya Khan District
Bhakkar.
BhakkarOn-going
Schemes100.000 46.648 6.667 5.000 5.000 100% 52%
Date of A.A 27.08.2016 Date of T.S 21.10.2016
Date of Commencement 24.11.2016 Date of
completion 30.06.2020
135 1738Rural Sewerage Drainage Scheme PCC Slab and
Brick Pavement in Behal City Bhakkar
On-going
Schemes49.998 18.599 3.333 2.500 2.161 86% 42%
Date of A.A 27.08.2016 Date of T.S 03.09.2016
Date of Commencement 03.11.2016 Date of
completion 30.06.2020
136 1739Rural Sewerage Drainage Scheme PCC Slab and
Brick Pavement in Notak City Bhakkar
On-going
Schemes39.022 17.991 3.333 2.500 2.167 87% 52%
Date of A.A 27.08.2016 Date of T.S 03.09.2016
Date of Commencement 28.11.2016 Date of
completion 30.06.2020
137 1740
Rural drainage Scheme inculding Tuff Tiles and
Water Supply Lines for left over streets for Chak
No 411/GB darbar Peer Kandhari tehsil
Tandlianwala District Faisalabad
FaisalabadOn-going
Schemes10.000 5.000 1.667 1.250 0.520 42% 55%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 23.08.2018 & 24.1.19.
138 1741
Construction of Drainage Nala at Chak No.
197/RB Wahga Wala Tehsil Saddar, District
Faisalabad
FaisalabadOn-going
Schemes3.000 2.000 0.333 0.250 0.167 67% 72%
Date of A.A 05-08-2017. Date of T.S.05-09-2017.
Work order issued on 28-09-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
139 1742Construction of Rural Drainage and PCC Road ,
UC 63 District Faisalabad Faisalabad
On-going
Schemes10.000 1.000 3.000 2.250 1.500 67% 25%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 22-11-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
140 1743Construction of Rural Drainage and PCC Road at
U.C. 52 District Faisalabad Faisalabad
On-going
Schemes10.000 1.000 3.000 2.250 1.500 67% 25%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 22-11-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
141 1744
Rehab: of Rural Water Supply Scheme Chak No.
228/GB Tehsil Sammundari Distt: Faisalabad
(Court Case)
FaisalabadOn-going
Schemes21.240 18.698 2.542 1.907 0.720 38% 91%
AA issued on 14.04.2015. Date of T.S 18.10.2016
Work order issued on 18.05.2015. Work is in
progress. Funds relased 23.11.2018 & 24.1.19.
142 1745Construction of sewerage drain at Chak
No.469/GB, Samundri, District FaisalabadFaisalabad
On-going
Schemes59.879 42.328 1.000 0.750 0.470 63% 71%
AA issued on 16.03.2017 Date of T.S 31.03.2017
work order issued on 08.06.2017. Work is in
progress. Funds released on 23.11.2018 & 24.1.19
143 1746
Construction of TST Road (2200 feet) at Chak No.
353/GB Kot Kabir, (Cahk No. 353/GB to New
Abadi) at District Faisalabad
FaisalabadOn-going
Schemes4.000 1.000 1.000 0.750 0.750 100% 44% Funds transfer to xen Highway Divison Faisalabad.
144 1747
Widening / improvement of at TST Road from 12
feet to 20 feet Chak No.353 to 354 at District,
Faisalabad
FaisalabadOn-going
Schemes10.000 4.500 1.000 0.750 0.750 100% 53% Funds transfer to xen Highway Divison Faisalabad.
145 1748Provision of Soling/Drainage at Kannal Awan and
Abadies District Faisalabad.Faisalabad
On-going
Schemes2.500 0.479 1.000 0.750 0.500 67% 39%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017 Work is in
progress.
146 1749Provision of Soling/Drainage at UC No. 50 Chak
No.144/GB District FaisalabadFaisalabad
On-going
Schemes2.000 1.000 1.000 0.750 0.500 67% 75%
AA issued on 15.11.2017.Funds received on 23-11-
2018. Work order issued on 13.12.2017.
147 1750Provision of Soling /Drainage at Bhaman Da Chak
and Pathan Da Goth District Faisalabad.Faisalabad
On-going
Schemes2.000 1.000 1.000 0.750 0.500 67% 75%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
Progress.
148 1751Provision of Soling/Drainage Chak No.651/2 GB
District FaisalabadFaisalabad
On-going
Schemes1.000 0.499 0.501 0.376 0.250 66% 75%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
Progress.Funds released on 23.11.2018 & 24.1.19
149 1752
Provision of Soling /Drainage at Chak No.653/4 GB
Abadies Karam Chand and abadi Plots District
Faisalabad.
FaisalabadOn-going
Schemes2.500 0.998 1.502 1.127 0.750 67% 70%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
Progress.Funds released on 23.11.2018 & 24.1.19
150 1753Provision of Soling/Drainage Chak No.652/3GB
District FaisalabadFaisalabad
On-going
Schemes1.000 0.500 0.500 0.375 0.250 67% 75%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
Progress.Funds released on 23.11.2018 & 24.1.19
151 1754Construction of TST Road Jhangar Awan and
Abaedies District, Faisalabad.Faisalabad
On-going
Schemes5.000 1.500 1.000 0.750 0.750 100% 45% Funds transfer to xen Highway Divison Faisalabad.
152 1755Provision of Soling/Drainage Chak No.147/GB
District FaisalabadFaisalabad
On-going
Schemes1.000 0.471 0.529 0.397 0.260 65% 73%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Funds
could not be utilized due to site Problems. Work is
in progress.Funds released on 23.11.2018 & 24.1.19
153 1756Provision of Soling /Drainage at Chak No.144/GB
District Faisalabad.Faisalabad
On-going
Schemes2.000 0.500 1.500 1.125 0.690 61% 60%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
Progress.Funds released on 23.11.2018 & 24.1.19
154 1757Provision of Soling /Drainage at Chak No.145/GB
District Faisalabad.Faisalabad
On-going
Schemes2.500 0.997 1.503 1.127 0.700 62% 68%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
Progress.Funds released on 23.11.2018 & 24.1.19
155 1758Provision of Soling/Drainage Chak No.459/GB
Bhooli de Jhok District FaisalabadFaisalabad
On-going
Schemes1.500 0.479 1.021 0.766 0.500 65% 65%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
progress.Funds released on 23.11.2018 & 24.1.19
156 1759Provision of Soling/Drainage at UC No. 51 Pind
Essa FaisalabadFaisalabad
On-going
Schemes2.500 0.486 1.000 0.750 0.480 64% 39%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
progress.Funds released on 23.11.2018 & 24.1.19
157 1760Provision of Soling /Drainage at Chak No.569/Gb
Abadi Abdullah Khan District faisalabad.Faisalabad
On-going
Schemes3.500 0.988 1.000 0.750 0.490 65% 42%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. work is in
progress.Funds released on 23.11.2018 & 24.1.19
158 1761Provision of Soling /Drainage at RosheShani
Awana and Abadies District Faisalabad. Faisalabad
On-going
Schemes1.000 0.389 0.611 0.458 0.300 66% 69%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
progress.Funds released on 23.11.2018 & 24.1.19
159 1762
Provision of Soling /Drainage at UC 45 Chak
No.644/GB Abadi KaluKa Thatha and Saidpur
District Faisalabad.
FaisalabadOn-going
Schemes2.000 0.475 1.525 1.144 0.650 57% 56%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. Work is in
progress.Funds released on 23.11.2018 & 24.1.19
160 1763Provision Main Drainage at Chak No.120/GB
District Faisalabad.Faisalabad
On-going
Schemes1.497 0.994 0.503 0.377 0.240 64% 82%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. work is in
progress.Funds released on 23.11.2018 & 24.1.19
161 1764Sewerage / Drainage Scheme Garh Mor,
Ahmedpur SialJhang
On-going
Schemes81.940 20.000 8.333 6.250 4.858 78% 30%
Date of A.A 16.03.2017 Date of T.S 24.03.2017
Date of Receipt of tender 20.04.2017 Date of work
order 07.07.2017. Date of Completion As per PC-
I06.07.2019 Anticipated date of completion
06.07.2019 Agreement Amount 74.993-Million Work
is in progress.
162 1765Sewerage Drainage and Street Pavement,
Sandhilianwali, District Toba Tek Singh Phase IToba Tek Singh
On-going
Schemes100.000 30.000 3.333 1.800 1.100 61% 31%
1-Date of A.A 20.10.2016 2- Date of T.S 11.11.2016
3-Date of Prequalification - 21.11.2016 4-Date of
invitation of tenders 16.12.2016 5- Date of Receipt
of tenders 17.12.2016 6- Date of work order -
27.12.2016 7- Date of completion as per PC-I
26.12.2018 8- Anticipated date of completion
26.12.2018 9- No. of Beneficiary - 33312 Person 10-
Funds Released by F.D 03.08.2018 & 24.01.2019 -
11-Re-appropriation of funds(+/-) Work in progress.
163 1766
Construction of disposal Sewerage Drainage PCC
Scheme Morr Eminabad Sharqi UC Dhillanwali
Tehsil and Distt. Gujranwala
GujranwalaOn-going
Schemes199.920 117.216 6.667 5.000 3.334 67% 60% Work in progress
164 1767 Construction of Drains / PCC and Sewerage
Scheme at UC Bhikhu Pura, District GujranwalaGujranwala
On-going
Schemes67.393 17.393 6.667 5.000 3.334 67% 31% Work in progress
165 1768 Construction of Drains / PCC and Sewerage
Scheme at UC Shaheenabad, District GujranwalaGujranwala
On-going
Schemes64.261 19.260 5.000 3.750 2.500 67% 34% Work in progress
166 1769PCC and Sewerage Schemes at Khiali Shahpur
District Gujranwala. Gujranwala
On-going
Schemes198.537 153.991 20.000 21.218 16.218 76% 86% Work in progress
167 1770
PCC Sewerage Drainage Scheme Disposal UC
City Ladhywala Warraich Qila Dedar Singh Madu
Khalil Ghakh
GujranwalaOn-going
Schemes149.647 140.598 3.016 2.262 1.508 67% 95% Work in progress
168 1771Provision of Sewerage Drainage and water Supply
scheme in Qila Dedar Singh GujranwalaGujranwala
On-going
Schemes196.624 138.865 6.667 5.000 3.334 67% 72% Work in progress
169 1772
Provision of Sewerage, New Disposal & PCC at
Kot Qazi & Mudhokhalil, Tehsil Saddar,
Gujranwala
GujranwalaOn-going
Schemes186.266 89.505 30.000 22.500 15.000 67% 56% Work in progress
170 1773
Provision of Sewerage, New Disposal & PCC at
Ladhay wala Warraich & Mughal Chak, Tehsil
Saddar, Gujranwala
GujranwalaOn-going
Schemes195.240 100.000 30.000 22.500 15.000 67% 59% Work in progress
171 1774Provision of Drainage PCC Facilities at UC Artali
Virkan Tehsil Nowshera Virkan District GujranwalaGujranwala
On-going
Schemes30.000 19.958 3.335 2.501 1.668 67% 72% Work in progress
172 1775Provision of Drainage PCC Facilities at UC Baddo
Ratta Tehsil Nowshera Virkan District Gujranwala Gujranwala
On-going
Schemes30.000 19.870 3.334 2.501 1.667 67% 72% Work in progress
173 1776Provision of Drainage / PCC Schem at UC Chahal
Kalan, District GujranwalaGujranwala
On-going
Schemes77.757 19.999 3.333 2.500 1.667 67% 28% Work in progress
174 1777Drainage Sewerage and PCC UC atawa UC Rakh
Kikran WaliGujranwala
On-going
Schemes280.818 151.994 14.117 10.588 7.059 67% 57% Work in progress
175 1778PCC and Drainage Facility at Sadoki,Dargahapur
and others in Tahsil KamokiGujranwala
On-going
Schemes158.153 84.945 3.333 2.500 1.667 67% 55% Work in progress
176 1779Provision of PCC/Drainage Sewerage Schemes at
UC No 14, 15, 46, 50, 51, 52, 53 Gujranwala Gujranwala
On-going
Schemes131.295 110.646 6.883 1.720 0.000 0% 84% Scheme completed
177 1780Provision of PCC/Drainage/Sewerage Scheme at
Municipal Committee, Ghakar MandiGujranwala
On-going
Schemes194.226 75.000 20.000 15.000 10.000 67% 44% Work in progress
178 1781
Const. of disposal Sewerage Drainage PCC
Scheme Morr Eminabad Gharbi Audo Rai UC
Maraliwala Tehsil and Distt. Gujranwala
GujranwalaOn-going
Schemes178.291 99.864 6.667 5.000 3.334 67% 58% Work in progress
179 1782
Const. of Sewerage Drainage- PPC Soling in
UCs Tehsil Noshera Virkan including UCs No.
Wala Jhatan wali & Sahran Chahta
GujranwalaOn-going
Schemes467.500 89.888 1.000 0.750 0.500 67% 19% Work in progress.
180 1783
Rural Drainage and PCC Scheme at Wandala
Virkan Taly Aali Badhay new Abadi Gaibi Lunj
Sharif Kolo wala, Matu Bhanake Al Ditta, Ratta
Goraya, Chak Poryan ana Paryan, Karyal Khan
and and Adjoining Dera Jattan.
GujranwalaOn-going
Schemes50.000 19.997 3.333 2.500 1.667 67% 43% Work in progress
181 1784
Rural Drainage PCC Scheme Kot Nisar Shah
Boopara Khurd Dhairr Virkan Bhirri Shah Rehman
Dharoke Sadu
GujranwalaOn-going
Schemes109.270 46.942 6.667 5.000 3.334 67% 46% Work in progress
182 1785Sewerage Scheme Kamoke of Leftover Area
GujranwalaGujranwala
On-going
Schemes199.100 65.949 5.000 3.750 2.500 67% 34% Work in progress
183 1786Imrovement of Sewerage, Solling, Drain Tatley Aali
Road KamokayGujranwala
On-going
Schemes103.000 10.000 20.000 15.000 10.000 67% 19% Work in progress.
184 1787
Provision of PCC/Sewerage/Drainage/Solling etc.
in village Chachoke Tehsil Noshera Virkan District
Gujranwala
GujranwalaOn-going
Schemes15.000 9.941 1.667 1.250 0.834 67% 72% Work in progress.
185 1788
Provision of PCC/Drainage Scheme in UC
Kalaske, Kot Amar singh, Kot Shaira, Batla Janda
Sigh, Uggu Chak Paponakha, UC 71 Khiyali # 14
MC Qila Didar Singh
GujranwalaOn-going
Schemes197.800 19.996 30.000 22.500 15.000 67% 18% Work in progress
186 1789
Provision of Clean Drinking Water/Sewerage
Scheme at Ldhay wala Waraich, Madhu Khalil,
Chain Wala etc
GujranwalaOn-going
Schemes199.779 50.000 30.000 22.500 15.000 67% 33% Work in progress.
187 1790Provision of Sewerage / Drainage and PCC
facilities Qila didar singh GujranwalaGujranwala
On-going
Schemes40.000 10.000 5.000 3.750 2.500 67% 31% Work in progress.
188 1791Provision of Sewerage Drainage and PCC facilities
Gakhar City GujranwalaGujranwala
On-going
Schemes40.000 10.000 5.000 3.750 2.500 67% 31% Work in progress.
189 1792Sewerage and PCC Scheme for Bismillah Colony
Wania and Adjacent Area GujranwalaGujranwala
On-going
Schemes105.000 96.046 2.985 2.239 1.493 67% 93% Work in progress
190 1793
RSD/ PCC Scheme UC Shamsa Dada UC Majju
Chak UC Bhoopra Kalan UC Argan UC Philloke
and UC Abidabad Gujranwala
GujranwalaOn-going
Schemes168.000 46.983 3.333 2.500 1.667 67% 29% Work in progress
191 1794
Rural Drainage/PCC Scheme in U.C. Garmula
Virkan, U.C Budha Goraya, Dogranwala, U.C
Phama Sara, Kalsian Dhutran, Kot Bilal and
Madan Chak, Tehsil Nowshera Virkan, Dist.
Gujranwala (Revised)
GujranwalaOn-going
Schemes109.270 29.914 5.000 3.750 2.500 67% 30% Work in progress
192 1795Rural Drainage Scheme UC Kot Hassan Khan
Kassoki Karyala & Allied AbbadiesHafizabad
On-going
Schemes98.000 10.000 3.333 2.500 1.667 67% 12%
A.A. 98.000(M) T.S.98.000 (M) work is in progress
Fund release but not yet online.
193 1796
Rural Drainage Scheme UC Chak Chattha Sabir
Kalan Kallian Wala & Allied Abbadies, District
Hafizabad
HafizabadOn-going
Schemes98.000 10.000 1.000 4.084 3.330 82% 14%
A.A. 98.000(M) T.S.98.000 (M) work is in progress
Fund release but not yet online.
194 1797Drainage/Sewerage and water Supply Scheme of
Mangat and Rasul
Mandi
Bahauddin
On-going
Schemes102.080 73.238 3.333 2.600 2.600 100% 74%
* Org. A.A Date. 03.10.2011* Rev. A.A Date.
23.02.2013* T.S Date. 18.11.2011* Start Date
02.11.2011* Completion date 30.06.2019.* Work in
progress.
195 1798
Construction of street, Drainage and Soling of
Kakka and Kot Jafar, Chak No.18 & 19, District
M.B.Din
Mandi
Bahauddin
On-going
Schemes6.500 5.737 0.167 0.100 0.059 59% 89%
* A.A Date. 09.03.2017* T.S Date. 10.03.2017* Start
Date 12.04.2017
196 1799
Construction of street, Drainage and Soling of
Khizar and Chak No.52, UC Chot Dheeran, District
M.B.Din
Mandi
Bahauddin
On-going
Schemes13.000 10.726 0.644 0.433 0.272 63% 85%
* A.A Date. 09.03.2017* T.S Date. 10.03.2017* Start
Date 11.04.2017
197 1800Provision of Sewerage / Drainage / Pavement in
Halian & Ghanian, Tehsil Phalia
Mandi
Bahauddin
On-going
Schemes50.000 48.643 0.252 0.189 0.126 67% 98%
* A.A Date. 28.01.2015* T.S Date. 08.02.2015* Start
Date 11.04.2015
198 1801
Provision of Sewerage / Drainage / Pavement in
Jano Chak Khurd & Kalan , Basi Khurd & Kalan,
Channi Mast, Aado Sarwani.
Mandi
Bahauddin
On-going
Schemes75.571 52.495 3.333 1.250 0.417 33% 70%
* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start
Date 24.12.2016* Completion date 30.06.2019.*
Work in progress.
199 1802Provision of Sewerage / Drainage / Pavement in
Narang / Saadullaha Pur / Khoosor
Mandi
Bahauddin
On-going
Schemes64.664 50.171 4.824 1.668 0.462 28% 78%
* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start
Date 24.12.2016
200 1803
Provision of Sewerage / Drainage / Pavement in
Sarlay,Lasoori Kalan,Duggal, Phalia Boota (Incl.
THQ Hospital), Tehsil Pahila
Mandi
Bahauddin
On-going
Schemes50.000 44.765 1.579 0.594 0.200 34% 90%
* A.A Date. 28.01.2015* T.S Date. 08.02.2015* Start
Date 11.04.2015* Completion date 30.06.2019.*
Work in progress.
201 1804Rural Sewerage/Drainage scheme village Bosal,
Tehsil Malikwal, District M.B. Din
Mandi
Bahauddin
On-going
Schemes90.500 79.269 3.744 2.808 1.872 67% 90%
* A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start
Date 17.12.2015* Completion date 30.06.2019.*
Work in progress.
202 1805Rrural/Sewerage/Drainage Scheme pindi Kalu
Tehsil Phalian District Mandi bahauddin
Mandi
Bahauddin
On-going
Schemes50.000 14.942 11.667 11.750 8.834 75% 48%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
203 1806Sewerage Drainage Scheme UC Dhok Kasib
Tehsil & District M B Din
Mandi
Bahauddin
On-going
Schemes20.000 19.500 0.166 0.104 0.062 60% 98%
* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start
Date 23.12.2016.* Completion date 30.06.2019.*
Scheme completed in saving.* A.A Date.
23.09.2016* T.S Date. 24.09.2016* Start Date
23.12.2016.* Completion date 30.06.2019.* Scheme
completed in saving.
204 1807Sewerage & Drainage Scheme U.C Rasul Tehsil &
District M.B.Din.
Mandi
Bahauddin
On-going
Schemes20.000 19.421 0.184 0.099 0.053 54% 97%
* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start
Date 21.12.2016.* Completion date 30.06.2019.*
Scheme completed in saving.
205 1808Sewerage / Drainage of Village Rerka Mumdana,
Tehsil Malikwal
Mandi
Bahauddin
On-going
Schemes41.684 24.326 5.753 3.415 1.977 58% 63%
* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start
Date 29.12.2016* Completion date 28.12.2019.*
Work in progress
206 1809
Rural Sewerage, Drainage/Soling & PCC Scheme
in Chak No. 20 With Abadies Tehsil Malikwal Distt.
M.B Din
Mandi
Bahauddin
On-going
Schemes50.000 45.999 1.334 1.001 0.667 67% 93%
* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start
Date 19.11.2016* Completion date 30.06.2019.*
Work in progress
207 1810
Rural Sewerage, Drainage/Soling & PCC Scheme
in Villages Main Mandi Mona Depot Pind Makko
Tehsil Malilwal District M.B.Din
Mandi
Bahauddin
On-going
Schemes53.052 42.556 2.629 0.972 0.315 32% 81%
* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start
Date 07.02.2017* Completion date 30.06.2019*
Work in progress
208 1811Rural Sewerage / Drainage Scheme of Village
Bherowal Tehsil Phalia Distt. Mandi Bahauddin
Mandi
Bahauddin
On-going
Schemes73.499 29.396 5.000 3.750 2.500 67% 43%
* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start
Date 24.12.2016* Completion date 30.06.2019.*
Work in progress
209 1812Rural Sewerage / Drainage Scheme of Village Khai
and Bukkan Tehsil & Distt. M.B. Din
Mandi
Bahauddin
On-going
Schemes74.464 61.888 4.180 1.485 0.440 30% 84%
* A.A Date. 23.09.2016* T.S Date. 28.10.2016 *
Start Date 06.12.2016* Completion date
30.06.2019.* Work in progress
210 1813Rural Sewerage / Drainage Scheme Village
Kuthiala Sheikhan, Tehsil & District M.B. DIN
Mandi
Bahauddin
On-going
Schemes55.150 45.574 3.192 1.079 0.281 26% 83%
* A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start
Date 17.12.2015* Completion date 30.06.2019.*
Work in progress
211 1814
Sewerage / Drainage Schemes in Adda
Pharainwali, Sandhanwala, Haigerwala, Murala,
Dhall, Dhola, Chhani, Lakhia, Chak No. 38., and
Ahdi in District M.B.Din
Mandi
Bahauddin
On-going
Schemes247.904 79.958 6.667 2.000 0.334 17% 32%
* A.A Date. 06.09.2017* T.S Date. 24.10.2017* Start
Date. 08.01.2018* Completion date
07.01.2021*Work in progress.
212 1815Provision of PCC / Sewerage / Drainage and allied
faiclities in PP-120, District M.B.Din
Mandi
Bahauddin
On-going
Schemes50.000 28.500 7.167 5.375 3.584 67% 64%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
213 1816Sewerage and Drainage scheme of Sahna and
Khanana, District Mandi Baha Ud Din
Mandi
Bahauddin
On-going
Schemes100.000 22.099 8.333 6.250 4.167 67% 26%
* A.A Date. 25.08.2017* T.S Date. 07.09.2017* Start
Date. 06.01.2018* Completion date
05.01.2020*Work in progress.
214 1817
Construction of Brick Pavement PCC Street &
Drain / Nullah U.C Mundeke, Ghuinke, Baddokey
Cheema, Allomahar, Jamke Cheema, Tehsil
Daska District Sialkot
SialkotOn-going
Schemes50.000 29.900 1.667 1.250 0.834 67% 61% Work in progress.
215 1818
Construction of PCC, Solling & Drain / Nullah UCs
Head Marala, Machrala, Gondal, Bolwanwala ,
Pindi Punjorian, Kaman Wala Kundan pur,
Dallowali, Katchi Maund, Pholkin, Wadhgran Tehsil
Sialkot District Sialkot
SialkotOn-going
Schemes150.000 34.566 3.333 2.500 1.667 67% 24% Work in progress.
216 1819
Construction of RCC Sewer & RCC from Zohara
Memorial Hospital Chowk to Railway Crossing to
Ajmal Garden to Shetab Garha to Adalat Pur road
to Nullah Aik, Tehsil & District Sialkot
SialkotOn-going
Schemes175.320 87.576 6.667 5.000 3.334 67% 52% Work in progress.
217 1820 Construction of Sewerage and Drainage Scheme
Village Kapooro Wali Tehsil & District Sialkot Sialkot
On-going
Schemes30.000 24.983 1.667 1.250 0.834 67% 86% Work in progress.
218 1821
Provision of PCC / Soling / Nallain /Streets at
Baigo wali bsmulla kot marth ,kot muhmmad
hussain ,pipli wala ,begowala adda ,bhola musa
kotli bawarian, kot kuda yar ,kot qadar daad
,randeer ,bagrian ,chak kupa ,gulab garh, doburji
chanda sing ,chowkey ,r
SialkotOn-going
Schemes80.000 34.470 3.333 2.500 1.667 67% 45% Work in progress.
219 1822
Provision of PCC / Soling / Nallain /Streets
Schemes at Malkhanwala Bshmula Wan, Pasia,
Firdospur, Bangla Nai Abadi, Chak Bassawa, Dhop
Sari, Hameed Colony, Mehlowal, Abdullah abad,
Dera Roshan Gujjar, Amreekh pura District Sialkot
SialkotOn-going
Schemes80.000 34.000 3.333 2.500 1.667 67% 45% Work in progress.
220 1823
Provision of PCC / Soling / Nullah / Street Scheme
at Khambranwala Bashamula, Dogree, Gorian,
Sundar Pur, Bidar, Chak Simanwali etc., Tehsil
Sambrial, District Sialkot [LO160068845].
SialkotOn-going
Schemes60.000 34.403 3.333 2.500 1.667 67% 60% Work in progress.
221 1824
Provision of PCC / Soling / Nullah / Street Scheme
at Bakhray Wali Bashamula, Dogranwala,
Kathiala, Habibpur etc., Tehsil Sambrial, District
Sialkot [LO16006884].
SialkotOn-going
Schemes55.000 19.960 1.667 1.250 0.834 67% 38% Work in progress.
222 1825
Provision of PCC / Soling / Nullah / Street Scheme
at Kulowal Bashamula , Aurtala Sharif, Chak
Mughal , Tika , Tambray, Gaghar. Baseer, Jay,
Ditowali, Chanigondal, etc., Tehsil Sambrial,
District Sialkot
SialkotOn-going
Schemes100.000 19.980 3.333 2.500 1.667 67% 22% Work in progress.
223 1826
Provision of PCC / Soling / Nullah / Street Scheme
at Gohad Pur Bashamula, Handlapur, Korpur,
Nawan Pind, Nangal, Ghiti Shekan, Kansarour,
Tibbi, Arrian, Saleempur, Malkay, Kalan, Malkay
Khurd, Olkh Awana etc., Tehsil & District Sialkot
[LO16006880].
SialkotOn-going
Schemes399.852 29.955 3.333 2.500 1.667 67% 8% Work in progress.
224 1827
Provision of PCC / Soling / Nullah / Street Scheme
at Kapurwali, Bashamula Ajjowali, Basant Pur,
Dagaray, Malo Chak , Jorian Khurd / Kalan ,
Sukhnian, Bhindar, Olakh, Saidpur,
Jatta,Dusri,Kala Ghumna,Khambranwala, Kansar
Pur, Canday Wali etc., Tehsil & D
SialkotOn-going
Schemes70.000 19.987 3.333 2.500 1.667 67% 31% Work in progress.
225 1828
Provision of PCC / Soling / Nullah / Street Scheme
at Jaithi Kay Bashaula, Joluki, Maja Khurd,
Haddokay, Kot Deena, Tibbi Inayat Shah, Deera
Tibbi Inayat Shah, Deera Tarraran, Dra Gujjran,
Dera Arrian, Karan Wali etc.,Teshil & District
Sialkot
SialkotOn-going
Schemes50.000 19.990 3.333 2.500 1.667 67% 43% Work in progress.
226 1829
Provision of PCC / Soling / Nullah / Street Scheme
at Jassor Wala Bashamula, Chak Gillan Sharki,
Chak Gillan Magrabi, Pandorian, Muhammad Pura,
Gega, Addowali, Rajjokay etc.,Teshil & District
Sialkot
SialkotOn-going
Schemes50.000 20.000 1.667 1.250 0.834 67% 42% Work in progress.
227 1830
Provision of PCC / Soling / Nullah / Street Scheme
Roras, Bashamula Mango Behram , Pidian, Kot
Bagaa, Chak Maluk, Chak Janta, Dhana Wali
Mehad Pur, Dadowali, Manair etc., Tehsil
Sambrial, District Sialkot [LO16006879].
SialkotOn-going
Schemes60.000 20.000 1.667 1.250 0.834 67% 35% Work in progress.
228 1831
Provision of PCC Sewerage Schemes in UC
Dhuda Goraya, MaloMahay, Bogray SEO KE
District Sialkot
SialkotOn-going
Schemes40.000 20.000 3.333 2.500 1.655 66% 54% Work in progress.
229 1832
Provision of Sewerage and Tuff Tile in Various
UCs of District Sialkot, UCs, kotli Behram, Mubarik
pura, Miana pura, Model Town, Fateh Garh,
Muzafar pur, Haji pura, Ban, Haji pura-II, Imam
Sahib, Shahab pura, Pacca Garha, Hamza Ghous.
SialkotOn-going
Schemes120.000 75.000 3.333 2.500 1.667 67% 64% Work in progress.
230 1833
Providing and Laying Tuff Tile RCC Sewer and
Construction of Drain /Nullah Mohallah Shahab
Pura Bajli Mohallah Darbar Shahab Shah U/C.
Shahab pura Tehsil & District Sialkot
SialkotOn-going
Schemes35.000 31.000 1.333 0.333 0.225 68% 89% Work in progress.
231 1834
Construction of PCC Street Drain/ Nullah
Providing and Laying of RCC Sewer and Tuff Tile
U/C Water Works (Silver star road Mohallah
Islamia Park) Tehsil & District Sialkot.
SialkotOn-going
Schemes24.400 14.991 3.133 2.350 1.565 67% 68% Work in progress.
232 1835
Construction of PCC Street, Drain/ Nullah
Providing and Laying of RCC Sewer and Tuff Tile
U/C Duburj Arraian (Moh. Baba Bari, Habib pura)
Tehsil & District Sialkot
SialkotOn-going
Schemes29.500 20.000 3.167 2.375 1.584 67% 73% Work in progress.
233 1836
Construction of PCC Street, Drain/ Nullah
Providing and Laying of RCC Sewer and Tuff Tile
U/C Muhammad pura (Nishat park) Tehsil &
District Sialkot
SialkotOn-going
Schemes28.600 19.938 2.867 2.150 1.434 67% 75% Work in progress.
234 1837
Construction of PCC Street, Drain/ Nullah
Providing and Laying of RCC Sewer and Tuff Tile
U/C Water Works (Moh. Pak pura) Tehsil & District
Sialkot
SialkotOn-going
Schemes25.500 19.975 1.833 1.375 0.917 67% 82% Work in progress.
235 1838
Providing & Laying of RCC Sewer, Tuff Tile and
Construction of Disposal Station Mohallah Water
Works to Abbot Road Phatak and along the
Railway line to Dara Arrian U/C Water Works,
Tehsil & District Sialkot
SialkotOn-going
Schemes50.000 8.000 5.000 1.450 0.964 66% 18% Work in progress.
236 1839
Providing & Laying of RCC Sewer, Tuff Tile and
Construction of Disposal Station Nasir Road Prem
Nagar Road EIC School to Nullah Bhed U/C Model
Town, Tehsil & District Sialkot
SialkotOn-going
Schemes50.000 10.000 5.000 2.350 1.450 62% 23% Work in progress.
237 1840
Providing and Laying of Tuff Tile RCC Sewer and
Construction of Drain / Nullah Mohallah Kashmiri
Sarray Bhabrian Alamgir Bazar Nikhas U/C. Imam
Sahib Tehsil & District Sialkot
SialkotOn-going
Schemes32.000 25.933 2.000 0.700 0.468 67% 83% Work in progress.
238 1841
Provision of PCC/Soling /Nalian/Streets Schemes
at Bohalwala Bashamula Chak Kheena, Kotli
Nonaan, Kotli Nonaan, Dot Dharan Baddoke
Cheema, Kot Bhagat, Jalianwala Ahmadabad
District Sialkot
SialkotOn-going
Schemes80.000 40.500 3.333 5.067 4.230 83% 56% Work in progress.
239 1842
Provision of PCC/Soling/nalian/Streets Scehmes at
Majra kalan, Chak Ekhtiar, Dingowal, Mahiwal,
rakh noshra ,kothy pardansing (islambad)khothay
chistian ,Dorarbe Malianwala Jattan & Arrian, Pano
attari Hussain Pur, Jamal Pur District Sialkot
SialkotOn-going
Schemes90.000 69.860 3.333 2.500 1.667 67% 79% Work in progress.
240 1843
Provision of PCC/Soling/Nalian/Streets Schemes
at Barath Bhoth Bashamula Markiwal, Khorta
Syedan, Ballanwala, Machi Khokhar, Gul Bahar
Khurd, Gul Bahar Kalan
SialkotOn-going
Schemes50.000 29.945 1.667 1.250 0.834 67% 62% Work in progress.
241 1844
Provision of PCC/Soling/Nalian/Streets Schemes
at Chaprar Bashamula Punowal, Najwal, Parwal,
Sagarpu, Medhi pur, Bagh pur, Sagri pur etc
SialkotOn-going
Schemes55.000 29.978 3.333 2.500 1.667 67% 58% Work in progress.
242 1845
Provision of PCC/Soling/Nalian/Streets Schemes
at Gojra Bashamula Thatha Lathi, Qila Tek Singh,
Bhonawali, Phangat, Dheera Sanda, Islam pura,
Kotli wala, Kandan Sian
SialkotOn-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress.
243 1846
Provision of PCC/Soling/Nalian/Streets Schemes
at Mandran Wala Bashamula Adamkay Cheema,
Nai Abadi,
SialkotOn-going
Schemes75.000 49.601 3.333 2.500 1.667 67% 68% Work in progress.
244 1847
Provision of PCC/Soling/Nalian/Streets Schemes
at Saidowali Bashamula Hambokay, Kot Mahraj,
Merian Pindi, Lalaywali, Easa pur, Khorray, Suraj,
Chak Hana etc
SialkotOn-going
Schemes70.000 20.000 3.333 2.500 1.667 67% 31% Work in progress.
245 1848
Provision of PCC/Soling/Nalian/Streets Schemes
at Shahuwala Bashamula Balo Chak, Nashtar
Abad, Zafarwali, Kamalpur, Manpur etc.
SialkotOn-going
Schemes28.000 19.920 2.667 2.000 1.334 67% 76% Work in progress.
246 1849
Provision of PCC/Soling/nalian/Streets Schemes at
Sheeni Bashamula Chaila, bjola, Muljhan, Sagar,
punwal ratwal ,chogpur District Sialkot
SialkotOn-going
Schemes90.000 77.698 3.333 2.500 1.667 67% 88% Work in progress.
247 1850
Provision of PCC/Soling/Nalian/Streets Schemes
at Verowala Bashamula Wassankay, Magokaman,
Nandpur, Baryar, Wan Garthal Umarkey Kalan,
Umarkey Khurd, Ahmad abad, Veeramkay etc
SialkotOn-going
Schemes50.000 19.925 3.333 2.500 1.667 67% 43% Work in progress.
248 1851Const of Streets/drains & PCC in Village
PartanwaliSialkot
On-going
Schemes60.000 12.990 1.667 1.250 0.834 67% 23% Work in progress.
249 1852Const of Streets/drains & PCC in Village Saidpur
KalanSialkot
On-going
Schemes65.000 16.490 3.333 2.500 1.660 66% 28% Work in progress.
250 1853
Const. of Nullah from Sublime Chowk to Uggoki
More to Sahowala Bridge to Syphonof Nullah Aik,
Sialkot
SialkotOn-going
Schemes394.111 244.942 16.667 12.500 8.334 67% 64% Work in progress.
251 1854 Const. of PCC Drains / Sewerage Sialkot SialkotOn-going
Schemes90.000 62.984 3.333 7.700 6.867 89% 78% Work in progress.
252 1855Provision of Sewerage & PCC Schemes in Pero
Chak, Sego Wala, Adha Kanwamlit District SialkotSialkot
On-going
Schemes40.000 19.855 1.667 0.550 0.350 64% 51% Work in progress.
253 1856Provision of Sewerage & PCC Schemes UC
Jharah Wala Salhoke, Bharlham WalaSialkot
On-going
Schemes40.000 19.940 1.667 1.250 0.834 67% 52% Work in progress.
254 1857
Provision of Sewerage / Drainage Scheme at UC
Dhodha Tehsil Pasrur District Sialkot (under
revision)
SialkotOn-going
Schemes165.000 90.000 1.673 4.555 4.137 91% 57% Work in progress.
255 1858 Construction of Drains, Soling / PCC and Sullage
Carrier of Ghughiat, District SargodhaSialkot
On-going
Schemes18.164 15.000 1.055 0.791 0.611 77% 86%
"Date of A.A 25.01.2016, Date of T.S 30.01.2016,
Date of Award 25.01.2017, Scheduled date of
Completion on 30.06.2018, Date of
Commencement, 25.01.2017, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
256 1859 Construction of PCC / Drain in Dhera Sardha
District SialkotSialkot
On-going
Schemes50.000 47.970 0.667 0.500 0.330 66% 97% Work in progress.
257 1860
Construction of PCC Drain / Tuff Tile Ward No. 1
to 30 Daska Kalan, Daska Kot, U. C Galotian
Kalan, Ranganwala, Moseywala, Gaga, Ladhey
Bhanbanwal, Thatha, Sukhar Nahar &
Bhadeywala, Daska City, District Sialkot.
SialkotOn-going
Schemes70.000 39.545 3.333 2.500 1.667 67% 59% Work in progress.
258 1861
Construction of Drain/Nullah for Diposal of
Sewerage at Bhadewal Tehsil Daska District
Sialkot
SialkotOn-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
259 1862Reheblitiation of Sewerage/Drainage Scheme
Mitranwali Tehsil Daska District SialkotSialkot
On-going
Schemes20.000 10.000 3.333 7.500 6.667 89% 83% Work In Progress
260 1863
Sanitation Schemes in UCs, Gadgore, Khanawali,
Alhar, Jassoran, Baddiana and Chawinda, Tehsil
Pasrur
SialkotOn-going
Schemes40.000 26.000 4.667 3.500 2.334 67% 71% Work in progress.
261 1864Construction of PCC Streets, Drains,Tuff tiles and
Soling in Adalat Garah, District SialkotSialkot
On-going
Schemes30.000 14.935 5.000 3.750 2.500 67% 58% Work in progress.
262 1865Construction of PCC Streets, Drains,Tuff tiles and
Soling in Mahal Kingra & Dhanney, District SialkotSialkot
On-going
Schemes6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress.
263 1866Construction of PCC Streets, Drains,Tuff tiles and
Soling in Muzafar Pur, District SialkotSialkot
On-going
Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.
264 1867Construction of PCC Streets, Drains,Tuff tiles and
Soling in Shatab Garah, District SialkotSialkot
On-going
Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.
265 1868Construction of PCC Streets, Drains,Tuff tiles and
Soling in Bonkam, District SialkotSialkot
On-going
Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.
266 1869
Construction of PCC Streets, Drains,Tuff tiles and
Soling in Ganjianwali & Roheel Garah, District
Sialkot
SialkotOn-going
Schemes6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress.
267 1870
Construction of PCC streets, Drains,Tuff tiles and
Soling in Chak Adil,Chitti Shikhan,Nawan Pind,
District Sialkot
SialkotOn-going
Schemes10.000 5.000 1.000 0.834 0.834 100% 58% Work in progress.
268 1871Construction of PCC Streets, Drains,Tuff tiles and
Soling in Murad Pur, District SialkotSialkot
On-going
Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in progress.
269 1872Construction of PCC Streets, Drains,Tuff tiles and
Soling in Gohad Pur, District SialkotSialkot
On-going
Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in progress.
270 1873Construction of PCC Streets, Drains,Tuff tiles and
Soling in Dhanwali, District SialkotSialkot
On-going
Schemes5.000 2.500 1.000 0.750 0.500 67% 60% Work in progress.
271 1874
Construction of PCC Streets, Drains,Tuff tiles and
Soling in Village Monger to Nehar Upper Chanab &
Village Ranjhai to Burj Cheema Link Way, District
Sialkot
SialkotOn-going
Schemes6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress.
272 1875
Construction of PCC Streets, Drains,Tuff tiles and
Soling in Monger Sofen to Barthanwala, District
Sialkot
SialkotOn-going
Schemes7.000 3.500 1.167 0.875 0.584 67% 58% Work in progress.
273 1876Construction of PCC Streets, Drains,Tuff tiles and
Soling in Hunter Pura, District SialkotSialkot
On-going
Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.
274 1877Drainage / PCC scheme for village Gorala
Maanpur Narowal
On-going
Schemes50.000 34.743 3.333 2.500 1.659 66% 73%
A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start
Date 16.11.2016 *Completion date 30.06.2019 work
in progress. Funds not received on spending end yet
275 1878
PCC , Soling and Drainage Scheme in Village
Babral, Kallah, Mahlo, Sahlo,Tehsil Shakargarh,
District Narowal
NarowalOn-going
Schemes41.395 24.992 3.333 2.500 1.663 67% 64%
A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start
Date 16.11.2016*Completion date 30.06.2019.work
in progress. Funds not received on spending end
yet.
276 1879
PCC / Soling / Filtration Plant in Village Noor Kot
Manngri and Bagha Madan Thakrian Pagla,
District Narowal.
NarowalOn-going
Schemes46.000 18.730 1.000 0.750 0.480 64% 42%
A.A. dated 3.08.17 *Start Date
16.11.2016*Completion date 30.06.2020 Work in
progress. Fund not received on spending end yet.
277 1880
Construction of Nalian, Soling, PCC & Boundary
Walls of Graveyard in UCs Nallah, Bua, Melo Salo,
Kalah, Mainagty, Bara Manga, Kot Naina, Bahree,
Ikhras Pur, Jalala, Sujowal, Pehgwari, Malik Pur,
Fateh Pur Afghana, Sahari, Ghona, Ghumtala,
Kanjror, Lang
NarowalOn-going
Schemes85.000 49.192 3.333 2.500 1.659 66% 60%
A.A. dated 23.9.2016. T.S. dated 24.9.2016. *Start
Date 16.11.2016*Completion date 30.05.2019.work
in progress. Funds not received on spending end yet
278 1881 Sewerage scheme for Ghaziwal, Narowal. NarowalOn-going
Schemes34.648 33.308 0.378 0.284 0.188 66% 97%
"A.A. dated 03.05.2014 T.S. dated 23.05.2014
*Start Date 18.09.2014 *Completion date
30.06.2019 work in progress. Fund not received on
spending end yet
279 1882Urban / Sewerage / PCC & Tuff Tile Scheme
Narowal City Narowal
On-going
Schemes174.705 84.160 6.667 5.000 3.321 66% 50%
A.A Date.23.9.2016.T.S Date*28.10.2016 Date of
start 17.2.2017Date of completion 30.06.2019.
Work in progress.
280 1883 Sewerage scheme for Oncha Sadawala, Narowal. NarowalOn-going
Schemes49.284 47.265 0.611 0.458 0.305 67% 97%
"A.A. dated 03.05.2014 T.S. dated 23.05.2014 Start
Date 18.09.2014 Completion date 30.06.2019 work
in progress. Fund not received on spending end yet
281 1884 PCC and Drainage Scheme in UC 197 at Dhalloki LahoreOn-going
Schemes100.082 91.500 2.861 2.146 1.431 67% 93%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
282 1885PCC and Drainage Scheme in UC 243 at attari
Saroba Pind Lahore
On-going
Schemes130.989 90.510 6.667 5.000 3.334 67% 72% Work stopped due to awaiting funds.
283 1886PCC and Drainage Scheme in UC 246 at
Youhanabad Lahore
On-going
Schemes100.838 100.494 0.344 0.258 0.172 67% 100%
Scheme Completed. Funds required to clear the
contractor's liabilities against Price Variation.
284 1887PCC and Drainage Scheme in UC 247 at Kahna
KohnaLahore
On-going
Schemes201.357 130.000 6.667 7.500 5.834 78% 67% Work stopped due to awaiting funds.
285 1888PCC and Drainage Scheme in UC 248 at
Shehzada and Pura KahnaLahore
On-going
Schemes151.603 128.300 7.201 5.401 3.601 67% 87% Work stopped due to awaiting funds.
286 1889PCC and Drainage Scheme in UC 249 at
Kamahan Lahore
On-going
Schemes80.384 70.070 3.438 2.579 1.719 67% 89%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
287 1890 PCC and Drainage Scheme in UC 252 at Pandoki LahoreOn-going
Schemes113.315 106.999 2.105 0.759 0.233 31% 95%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
288 1891 PCC and Drainage Scheme in UC 253 at Suraich LahoreOn-going
Schemes120.660 96.245 8.138 6.004 3.969 66% 83% Work stopped due to awaiting funds.
289 1892PCC and Drainage Scheme in UC 254 Deo Khurd
and Kalan Lahore
On-going
Schemes102.533 83.173 4.187 3.040 1.994 66% 83% Work stopped due to awaiting funds.
290 1893PCC and Drainage Scheme in UC 268 at Judho
DheerLahore
On-going
Schemes102.003 89.361 4.001 2.501 1.501 60% 89% Work stopped due to awaiting funds.
291 1894PCC and Drainage Scheme in UC 271 at Jia
Bhagga and RO Plant at Jia Bhagga Lahore
On-going
Schemes103.300 100.032 1.086 4.815 4.543 94% 101% Scheme completed
292 1895 PCC and Drainage Scheme in UC191 at Gawind LahoreOn-going
Schemes100.000 92.500 2.500 1.875 1.250 67% 94%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
293 1896
Construction of PCC Sewerage & Drainage
System at UC 262 Shamke Bhattian, District
Lahore
LahoreOn-going
Schemes30.000 18.497 3.833 2.875 1.917 67% 68% Work stopped due to awaiting funds.
294 1897 Construction of PCC Sewerage & Drainage
System at UC 267 Manak, District LahoreLahore
On-going
Schemes30.000 14.521 5.160 2.370 1.080 46% 52% Work stopped due to awaiting funds.
295 1898Disposal of Waste Water of Manga Mandi upto
River RaviLahore
On-going
Schemes161.107 125.649 6.667 8.463 6.797 80% 82%
Physically scheme is completed and put
operational, balance funds are for O&M for 1st
Year..
296 1899PCC and Drainage Scheme in Khananapal Kangra
Karyal Dhoondy Lahore
On-going
Schemes83.175 72.510 3.555 2.666 1.778 67% 89%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
297 1900PCC and Drainage Scheme in Nanghar Katcha
Tibba Katcha Islampura Halloki SadhukeLahore
On-going
Schemes93.775 81.140 4.212 1.309 0.256 20% 87% Scheme completed
298 1901PCC and Drainage Scheme in UC 145 Gajjumatta
and Adjoining Abadies. Lahore
On-going
Schemes200.014 185.659 4.785 3.589 2.393 67% 94%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
299 1902PCC and Drainage Scheme in UC 176 at Awan
DhaiwaLahore
On-going
Schemes70.128 43.914 8.737 6.553 4.369 67% 69% Work stopped due to awaiting funds.
300 1903 PCC and Drainage Scheme in UC 179 at Bhaseen LahoreOn-going
Schemes90.000 68.013 7.329 5.497 3.665 67% 80% Work stopped due to awaiting funds.
301 1904 PCC and Drainage Scheme in UC 180 at Minhala LahoreOn-going
Schemes155.697 49.805 5.000 8.750 7.500 86% 37% Work stopped due to awaiting funds.
302 1905 PCC and Drainage Scheme in UC 181 at Narwar LahoreOn-going
Schemes45.000 43.000 0.667 0.500 0.334 67% 96%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
303 1906PCC and Drainage Scheme in UC 182 at Jallo
More & Batapur LahoreLahore
On-going
Schemes56.817 31.060 8.585 2.339 0.193 8% 55% Work stopped due to awaiting funds.
304 1907 PCC and Drainage Scheme in UC 190 at Hadiara LahoreOn-going
Schemes162.606 50.000 5.000 4.070 2.820 69% 32% Work stopped due to awaiting funds.
305 1908 PCC and Drainage Scheme in UC 194 at Liddhar LahoreOn-going
Schemes101.739 63.707 6.667 5.000 3.334 67% 66% Work stopped due to awaiting funds.
306 1909 PCC and Drainage Scheme in UC 195 at Hair LahoreOn-going
Schemes120.468 104.533 5.312 11.084 9.756 88% 95% Scheme completed
307 1910 PCC and Drainage Scheme in UC 196 at Jaman LahoreOn-going
Schemes115.347 101.472 1.500 1.125 0.750 67% 89%
Scheme Completed. Funds required to clear the
contractor's liabilities against Price Variation.
308 1911
Provision of Sanitation Facilities including
Construction of Lift Station at Tahayat & Chandrai
Village, Lahore
LahoreOn-going
Schemes94.210 81.441 4.254 3.191 2.127 67% 89% Work stopped due to awaiting funds.
309 1912 Construction of PCC and Drainage at Adda
Talaab SaralLahore
On-going
Schemes30.140 28.294 0.608 0.356 0.204 57% 95%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
310 1913 Construction of PCC and Drainage at Chung LahoreOn-going
Schemes128.380 73.594 3.333 2.400 1.567 65% 59% Work stopped due to awaiting funds.
311 1914 Construction of PCC and Drainage at Khurd Pur LahoreOn-going
Schemes74.249 28.893 3.333 2.500 1.667 67% 41% Work stopped due to awaiting funds.
312 1915 Construction of PCC and Drainage at Manga
MandiLahore
On-going
Schemes199.606 42.995 5.000 2.050 0.800 39% 22% Work stopped due to awaiting funds.
313 1916 Construction of PCC and Drainage at Mohlanwal LahoreOn-going
Schemes52.966 52.184 0.261 0.996 0.931 93% 100% scheme completed
314 1917 Construction of PCC and Nallah from Hadyara
Drain to Dulam Village Lahore
On-going
Schemes29.345 18.612 3.577 2.683 1.789 67% 70% Work stopped due to awaiting funds.
315 1918 Construction of PCC Sewerage & Drainage
System at UC 260 Maraka, District LahoreLahore
On-going
Schemes30.000 12.371 5.876 3.107 1.638 53% 47% Work stopped due to awaiting funds.
316 1919Up Gradation of Streets PCC Flooring in Asif Town
I & II Galaxo Town and Adjoining abadiesLahore
On-going
Schemes150.678 108.993 6.667 4.800 3.134 65% 74% Work stopped due to awaiting funds.
317 1920Rural Drainage Scheme Kamahan & Adjoining
Abadies Lahore
On-going
Schemes143.277 126.501 5.137 2.353 1.069 45% 89% Work stopped due to awaiting funds.
318 1921
Balance work of Sewerage, water Supply and
PCC Scheme Town Committtee Kot Abdul Malik,
District Sheikhupura
SheikhupuraOn-going
Schemes195.462 167.947 3.333 2.500 1.667 67% 87% Work in Progress
319 1922
Const and Rehabilitation of PCC Sewerage
Scheme of Ravi Rayan Mannu Abad and Nazar
Abad (Revised)
SheikhupuraOn-going
Schemes95.313 41.645 3.333 2.500 1.667 67% 45% Work in Progress
320 1923 Construction of Drainage & PCC Scheme at
Mariam Abad District SheikhupuraSheikhupura
On-going
Schemes25.000 20.000 1.667 1.250 0.834 67% 83% Work in Progress
321 1924 Construction of Drainage & PCC Scheme at Mian
Ali Dogran District SheikhupuraSheikhupura
On-going
Schemes30.000 20.000 3.333 2.500 1.667 67% 72% Work in Progress
322 1925 Construction of Drainage /PCC/Soling Scheme at
Khanqah Dogran SafdarabadSheikhupura
On-going
Schemes125.450 49.569 3.333 2.500 1.667 67% 41% Work in Progress
323 1926 Construction of PCC, Drains, Soling in District
SheikhupuraSheikhupura
On-going
Schemes100.000 30.000 3.333 2.500 1.667 67% 32% Work in Progress
324 1927 Provision of PCC and draniage at Manawala SheikhupuraOn-going
Schemes30.000 20.000 3.333 2.500 1.667 67% 72% Work in Progress
325 1928 Construction of PCC, Drain/Soling & Nullah at UC
75, Kakar Gill, District SheikhupuraSheikhupura
On-going
Schemes46.000 14.046 3.333 2.500 1.667 67% 34% Work in Progress
326 1929 Construction of PCC, Drain/Soling & Nullah at UC
77, Ajnianwala, District SheikhupuraSheikhupura
On-going
Schemes76.000 20.000 3.333 2.500 1.667 67% 29% Work in Progress
327 1930 Construction of PCC, Drain/Soling & Nullah at UC
83, Jatri Kohna, District SheikhupuraSheikhupura
On-going
Schemes57.000 18.000 3.333 2.500 1.667 67% 35% Work in Progress
328 1931 Construction of PCC, Drain/Soling & Nullah at UC
84, Makki 460, District SheikhupuraSheikhupura
On-going
Schemes58.000 27.000 3.333 2.500 1.667 67% 49% Work in Progress
329 1932 Construction of PCC, Drain/Soling & Nullah at UC
85, Farooqabad, District SheikhupuraSheikhupura
On-going
Schemes40.000 15.000 3.333 2.500 1.667 67% 42% Work in Progress
330 1933 Construction of PCC, Drain/Soling & Nullah at UC-
97, Ferozwatuan-I, District SheikhupuraSheikhupura
On-going
Schemes15.000 11.509 1.000 0.750 0.582 78% 81% Work in Progress
331 1934 Construction of PCC, Drain/Soling & Nullah at UC-
98, Ferozwatuan-II, District SheikhupuraSheikhupura
On-going
Schemes15.000 8.138 1.000 1.144 1.144 100% 62% Work in Progress
332 1935
Construction of Soling / Sewerage & Drainage
Scheme at UC Anjianwala, UC Jhabran, UC Kakar
Gill, UC Gujiana Nau, UC Kot Sohnda, UC
Esserkay, UC Bahalikay, UC Jatri Kohna, UC
85Farooqabad, UC Ghazi Minara, UC Buttar, UC
Jhandian Wali, UC Warn, UC Kalokay
SheikhupuraOn-going
Schemes100.000 20.000 3.333 4.167 3.334 80% 23% Work in Progress
333 1936
Const. and Rehabilitation of PCC / Sewerage
Scheme of City Muridke, District Sheikhupura
(Revised)
SheikhupuraOn-going
Schemes96.536 61.500 5.000 3.750 2.500 67% 66% Work in Progress
334 1937 Construction of PCC Tuff Tiles Sewerage
Drainage Scheme in PP 163 District SheikhupuraSheikhupura
On-going
Schemes373.950 131.468 3.333 2.500 1.667 67% 36% Work in Progress
335 1938 Rural Drainage & PCC Scheme U.C. Keelay SheikhupuraOn-going
Schemes48.000 20.000 1.667 1.250 0.834 67% 43% Work in Progress
336 1939 Rural Drainage & PCC Scheme U.C. Kot Sonda SheikhupuraOn-going
Schemes45.000 24.000 3.333 2.500 1.667 67% 57% Work in Progress
337 1940 Rural Drainage & PCC Scheme U.C. Muridke SheikhupuraOn-going
Schemes45.000 24.000 3.333 2.500 1.667 67% 57% Work in Progress
338 1941 Rural Drainage & PCC Scheme U.C. Nookhar SheikhupuraOn-going
Schemes45.000 24.000 1.667 1.250 0.834 67% 55% Work in Progress
339 1942 Rural Drainage & PCC Scheme U.C. Sacha Souda SheikhupuraOn-going
Schemes78.000 24.000 3.333 2.500 1.667 67% 33% Work in Progress
340 1943 Rural Drainage & PCC Scheme UC Bhaianwala SheikhupuraOn-going
Schemes25.000 10.425 4.858 3.644 2.429 67% 51% Work in Progress
341 1944 Rural Drainage & PCC Scheme UC Ghang SheikhupuraOn-going
Schemes20.000 16.000 1.333 1.000 0.667 67% 83% Work in Progress
342 1945 Rural Drainage & PCC Scheme UC Mojoki SheikhupuraOn-going
Schemes28.000 23.000 1.667 1.250 0.834 67% 85% Work in Progress
343 1946 Rural Drainage & PCC Scheme UC Warn SheikhupuraOn-going
Schemes25.000 10.510 4.830 3.623 2.415 67% 52% Work in Progress
344 1947Rural Drainage & PCC scheme Union Council Burj
attari, District SheikhupuraSheikhupura
On-going
Schemes99.509 30.000 3.333 2.500 1.667 67% 32% Work in Progress
345 1948Rural Drainage & PCC scheme Union Council Kot
Mehmood, District SheikhupuraSheikhupura
On-going
Schemes91.385 30.000 3.333 2.500 1.667 67% 35% Work in Progress
346 1949
Rural Drainage Construction of Street Scheme
Chak No 44,45 and Village Jair District
Sheikhupura
SheikhupuraOn-going
Schemes199.486 74.950 3.333 2.500 1.667 67% 38% Work in Progress
347 1950
Rural Drainage Construction Of Street Scheme
Dograi Gill Qadeem Dograi Gill District
Sheikhupura
SheikhupuraOn-going
Schemes195.462 125.646 3.333 2.500 1.667 67% 65% Work in Progress
348 1951Rural Drainage Scheme UC Chapa Minera
SheikhupuraSheikhupura
On-going
Schemes87.910 54.975 3.333 2.500 1.667 67% 64% Work in Progress
349 1952Rural Drainage Scheme UC Chichoki Malian
SheikhupuraSheikhupura
On-going
Schemes85.423 48.694 3.333 2.500 1.667 67% 59% Work in Progress
350 1953 Rural Drainage Scheme UC Jahamke Sheikhupura SheikhupuraOn-going
Schemes94.134 54.999 3.333 2.500 1.667 67% 60% Work in Progress
351 1954Rural Drainage Scheme UC Mallian Kalan
SheikhupuraSheikhupura
On-going
Schemes92.869 50.900 3.333 2.500 1.667 67% 57% Work in Progress
352 1955Rural Drainage Scheme Abdullah Pur Kolar Chak
No 1/RB Tehsil Safdarabad District SheikhupuraSheikhupura
On-going
Schemes50.000 10.000 3.333 2.500 1.667 67% 23% Work in Progress
353 1956
Rural Sewerage Drainage System at Village Kot
Pindi Das Tehsil Ferozewala, Distt. Sheikhupura
(Revised)
SheikhupuraOn-going
Schemes199.993 185.231 4.921 3.691 2.461 67% 94% Work in Progress
354 1957Rural Drainage PCC Scheme UC Dhamkey
Sheikhupura FerozwalaSheikhupura
On-going
Schemes199.308 88.690 3.333 2.500 1.667 67% 45% Work in Progress
355 1958Rural Drainage PCC Scheme UC Mahmood Kot,
Sheikhupura , Sharqpur (Revised)Sheikhupura
On-going
Schemes180.146 78.279 3.333 2.500 1.667 67% 44% Work in Progress
356 1959Rural Drainage PCC Scheme UC Mandain Wala
Sheikhupura , Sharqpur (Revised)Sheikhupura
On-going
Schemes191.008 10.687 3.333 2.500 1.667 67% 6% Work in Progress
357 1960Rural Drainage PCC Scheme UC Mhar
Bhanguwan District Sheikhupura Sheikhupura
On-going
Schemes95.862 83.000 4.287 3.215 2.144 67% 89% Work in Progress
358 1961Rural Drainage PCC Scheme UC Quershian
Sheikhupura , Sharqpur (Revised)Sheikhupura
On-going
Schemes87.395 66.200 3.333 2.500 1.667 67% 78% Work in Progress
359 1962Rural Drainage PCC Scheme, UC Sehjowal
District Sheikhupura (Revised)Sheikhupura
On-going
Schemes93.090 74.136 3.333 2.500 1.667 67% 81% Work in Progress
360 1963Rural Drainage PCC Scheme, Wandala Dial Shah
UC 24 District Sheikhupura (Revised) Sheikhupura
On-going
Schemes144.546 142.456 0.697 0.523 0.349 67% 99% Work in Progress
361 1964Rural Drainage PCC Tuff Tile Scheme UC
Sharqpur, SheikhupuraSheikhupura
On-going
Schemes97.335 72.267 3.333 2.500 1.667 67% 76% Work in Progress
362 1965Rural drainage scheme at UC Bhadro District
SheikhupuraSheikhupura
On-going
Schemes15.110 13.100 0.670 0.503 0.335 67% 89% Scheme Completed
363 1966 RSD Scheme Faizpur Khurd District Sheikhupura SheikhupuraOn-going
Schemes40.000 16.500 3.333 2.500 1.667 67% 45% Work in Progress
364 1967Rural drainage & Const of streets scheme UC
Khan pur Sheikhupura Sheikhupura
On-going
Schemes134.768 81.863 3.333 2.500 1.667 67% 62% Work in Progress
365 1968Rural drainage & Const of streets scheme UC
Mandialy Sheikhupura (Revised)Sheikhupura
On-going
Schemes196.571 57.986 3.333 2.500 1.667 67% 30% Work in Progress
366 1969Rural drainage & Const of streets scheme UC Qila
Sattar Shah Sheikhupura (Revised)Sheikhupura
On-going
Schemes182.244 72.431 3.333 2.500 1.667 67% 41% Work in Progress
367 1970Rural drainage & Const of streets scheme Zia
abad Sheikhupura (Revised)Sheikhupura
On-going
Schemes177.038 45.905 3.333 2.500 1.667 67% 27% Work in Progress
368 1971 Rural Drainage & PCC Scheme U.C. Ajnianwala SheikhupuraOn-going
Schemes75.000 25.595 5.000 3.750 2.500 67% 37% Work in Progress
369 1972 Rural Drainage & PCC Scheme U.C. Buttar SheikhupuraOn-going
Schemes57.000 39.000 1.667 1.250 0.834 67% 70% Work in Progress
370 1973 Rural Drainage & PCC Scheme U.C. Easerkey SheikhupuraOn-going
Schemes38.000 25.000 2.667 2.000 1.334 67% 69% Work in Progress
371 1974Rural Drainage & PCC Scheme U.C. Gujiana Nu
District SheikhupuraSheikhupura
On-going
Schemes55.000 11.629 3.333 2.500 1.667 67% 24% Work in Progress
372 1975 Rural Drainage & PCC Scheme U.C. Harchand SheikhupuraOn-going
Schemes35.000 11.629 2.333 1.750 1.167 67% 37% Work in Progress
373 1976Rural Drainage Scheme Chak No 8/RB
Sheikhupura Sheikhupura
On-going
Schemes75.000 17.987 3.333 2.500 1.667 67% 26% Work in Progress
374 1977Rural Drainage Scheme Faizpur Khurd IIc abadis,
Tehsil FerozewalaSheikhupura
On-going
Schemes152.400 74.217 3.333 2.500 1.667 67% 50% Work in Progress
375 1978Rural Drainage/PCC Scheme at Moran Wala
District SheikhupuraSheikhupura
On-going
Schemes90.000 80.000 0.667 0.500 0.334 67% 89% Work in Progress
376 1979Rural PCC & Drainage Scheme, UC Bhaiwala
Kalan, District Sheikhupura.Sheikhupura
On-going
Schemes29.000 22.000 2.333 1.750 1.167 67% 80% Work in Progress
377 1980
Beautification of Sharqpur Sharif, Provision of
PCC, Tufftiles, Fountains, Monuments, LED Street
lights and construction of roof of Main Bazar
SheikhupuraOn-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress
378 1981Rural Drainage & PCC Scheme UC Mirza Virkan
District Sheikhupura.Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
379 1982Rural Drainage & PCC Scheme UC Chichoki
Mallian District Sheikhupura.Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
380 1983Rural Drainage & PCC Scheme Village Madar
District Sheikhupura.Sheikhupura
On-going
Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in Progress
381 1984Rural Drainage & PCC Scheme UC Mohallah
Rehman Pura District Sheikhupura.Sheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
382 1985Rural Drainage & PCC Scheme UC kot Ranjeet
District Sheikhupura.Sheikhupura
On-going
Schemes10.000 7.500 0.833 0.625 0.417 67% 79% Work in Progress
383 1986Rural Drainage & PCC Scheme UC Kurlkey
District Sheikhupura.Sheikhupura
On-going
Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in Progress
384 1987Rural Drainage & PCC Scheme UC Mallian Kalan
District Sheikhupura.Sheikhupura
On-going
Schemes15.000 7.500 2.500 1.875 1.250 67% 58% Work in Progress
385 1988Rural Water Supply & Drainage Scheme Murady
Kalan, ShiekpuraSheikhupura
On-going
Schemes95.246 20.000 1.121 0.841 0.561 67% 22% Work in Progress
386 1989 Construction of Sewerage and PCC at Bucheki
Town.Nankana Sahib
On-going
Schemes195.998 164.782 3.333 2.500 1.667 67% 85% Work is in progress.
387 1990Provision of Sewerage System at Warburton Town
Nankana Sahib.Nankana Sahib
On-going
Schemes130.000 61.000 3.333 2.500 1.667 67% 48% Work is in progress.
388 1991Provision of Rural Drainage / PCC Scheme for 16
Nos. of Union Councils in , District SheikhupuraNankana Sahib
On-going
Schemes50.000 32.599 3.333 1.500 0.667 44% 67% Work is in progress.
389 1992PCC and drainage scheme Thieng More /Illah
abad, Tehsil Chunian, District KasurKasur
On-going
Schemes256.672 89.991 6.667 5.000 3.334 67% 36% Work in Progress
390 1993 Construction of Sullage Carrier at Chah
Kalalanwala, Tehsil Pattoki, District KasurKasur
On-going
Schemes88.300 36.983 6.667 5.000 3.334 67% 46% Work in Progress
391 1994Const. of Soling Nullah, PCC etc. Union Council
Chirrawan, Tehsil & District Kasur Kasur
On-going
Schemes30.000 27.991 0.669 0.502 0.335 67% 94% Work in Progress
392 1995
Const. of Soling, Nullah PCC etc. Badian, Rai
Kalan, Khurd, Baddar Pur and adjoining abadies,
Tehsil Kasur
KasurOn-going
Schemes30.000 24.991 1.669 1.252 0.835 67% 86% Work in Progress
393 1996Const. of Soling, Nullah, PCC etc. Katlohi, Wadara
and adjoining abadies, Tehsil & District Kasur Kasur
On-going
Schemes30.000 24.999 1.667 1.250 0.834 67% 86% Work in Progress
394 1997 Construction of PCC and Tuff Tile Phoolnagar
Phase-II, Tehsil Pattoki, District Kasur Kasur
On-going
Schemes188.416 30.350 10.000 7.500 5.000 67% 19% Work in Progress
395 1998
Rural Drainage PCC Brick pavement Schemes
Rao Khan wala and Beroon Rao Khan Wala and
Adjoining Abadies Tehsil & District Kasur
KasurOn-going
Schemes77.000 34.995 8.333 6.250 4.167 67% 51% Work in Progress
396 1999Rural Drainage PCC Scheme Dholan District
Kasur.Kasur
On-going
Schemes114.588 99.662 4.975 3.731 2.488 67% 89% Work in Progress
397 2000Rural Drainage Scheme Sarhali Kalan & Adjoining
Abadies, Tehsil & District Kasur.Kasur
On-going
Schemes94.174 66.977 9.063 6.797 4.532 67% 76% Work in Progress
398 2001
Water Supply & Drainage Scheme Nathey Jagir,
Lakhankay Abadies, Kamogill, Mega Jatt, Sardar
Mill & Choudharian Wala.
KasurOn-going
Schemes101.853 98.860 0.998 0.749 0.499 67% 98% Work in Progress
399 2002Provision of PCC & drainage Scheme Habib ababd
District KasurKasur
On-going
Schemes99.000 20.000 5.000 3.750 2.500 67% 23% Work in Progress
400 2003Rural Drainage Scheme Baggiana, kamogil
Jahuggian, dhinasing & Baroon AbadiesKasur
On-going
Schemes90.000 20.000 3.333 2.500 1.667 67% 24% Work in Progress
401 2004Rural Drainage Scheme Nathay Khasla Sardar
Mill, Garden Adda & Chohdry Jhlar & dhanaKasur
On-going
Schemes90.000 20.000 6.667 5.000 3.334 67% 26% Work in Progress
402 2005Rural Drainage Scheme Khanko more Chakoki
Chak No 04, Madarkhai Kasur
On-going
Schemes95.000 19.995 6.667 5.000 3.334 67% 25% Work in Progress
403 2006Rural Drainage PCC Scheme Theh Shaikham and
Adjoining Abadies District Kasur.Kasur
On-going
Schemes97.400 90.282 2.371 1.778 1.186 67% 94% Work in Progress
404 2007Rural Drainage & PCC Scheme Bhamba Kalan &
Khurd and Adjoining Abadies District Kasur.Kasur
On-going
Schemes95.000 77.499 5.834 4.376 2.917 67% 85% Work in Progress
405 2008Rural Drainage & PCC Scheme Bohar and
Adjoining Abadies District Kasur.Kasur
On-going
Schemes81.000 62.466 6.172 4.629 3.086 67% 81% Work in Progress
406 2009Rural Drainage & PCC Scheme Mudke UC District
Kasur.Kasur
On-going
Schemes97.014 75.826 6.667 5.000 3.334 67% 82% Work in Progress
407 2010Rural Drainage Scheme Baroon Raja Jang &
Adjoining Abadies, Tehsil & District Kasur.Kasur
On-going
Schemes99.998 74.698 3.333 2.500 1.667 67% 76% Work in Progress
408 2011
Rural drainage Scheme Hanjray Kalan & Allied
Abadies, Khudian, Bhaseen, Dello Multani,
Wander, Jagu Wal Tehsil Pattoki District Kasur
KasurOn-going
Schemes67.952 49.988 5.984 2.988 1.492 50% 76% Work in Progress
409 2012Rural drainage scheme Hardo Sahari, District
KasurKasur
On-going
Schemes87.235 60.798 20.000 16.500 11.500 70% 83% Work in Progress
410 2013 Rural Drainage Scheme Qadiwind KasurOn-going
Schemes99.677 61.497 5.000 3.750 2.500 67% 64% Work in Progress
411 2014Rural Drainage Scheme, Lakhankey, Tehsil &
District Kasur.Kasur
On-going
Schemes76.899 67.976 2.974 2.231 1.487 67% 90% Work in Progress
412 2015Rural PCC & Drainage Scheme Green Kot and
Ibrahimabad & Adjoining Abadies District Kasur.Kasur
On-going
Schemes75.000 64.963 3.343 2.507 1.672 67% 89% Work in Progress
413 2016Rural PCC & Drainage Scheme Handal and Rawal
Jhangar & adjoining abadies District Kasur.Kasur
On-going
Schemes69.000 60.768 2.741 0.685 0.000 0% 88% Work in Progress
414 2017Rural PCC & Drainage Scheme Khara and
Wadana & adjoining abadies District Kasur.Kasur
On-going
Schemes50.000 39.406 3.530 2.648 1.765 67% 82% Work in Progress
415 2018Rural PCC & Drainage Scheme Ramthaman and
Matta & adjoining abadies District Kasur.Kasur
On-going
Schemes74.724 65.000 3.241 0.810 0.000 0% 87% Work in Progress
416 2019Rural PCC & Drainage Scheme Zafarkey and
Ghanikey & adjoining abadies District Kasur.Kasur
On-going
Schemes50.000 47.306 0.898 0.674 0.449 67% 96% Work in Progress
417 2020Laying of Tuff Tiles / Sewerage and Sullage Carrier
in Left Over Streets in Ward No.1 to 50 City OkaraOkara
On-going
Schemes47.436 24.999 3.333 2.500 1.667 67% 56%
Date of AA 06.03.2017, Date of TS 11.03.2017,
Date of Invitation of Tender ,01.05.2017, Date of
Receipt of Tender,02.05.2017, Date of work
Order.10.05.2017, Date of completion As per PC-
I.30.06.2018 , Anticipated date of completion,
30.06.2019, Funds Release on 20-07-2018
Projected Population 409924 Person.
418 2021Drainage schemes and soling work at UC 103
Depalpur District OkaraOkara
On-going
Schemes28.107 12.598 4.836 1.227 0.000 0% 45%
Date of AA 23.03.2016, Date of TS 25.03.2016,
Date of Invitation of Tender 16.05.2016, Date of
Receipt of Tenders 17.05.2016 , ( No Tender
Received), Date of Re-Invitation of Tender
11.06.2016, Date of Receipt of Tenders,13.06.2016,
Date of work Order 24.06.2016, Date of completion
As per PC-I. 18.06.2017, Anticipated date of
completion,30.06.2019,Re-Appropreation (-) 2.400
Projected Population 51130 Person, Work is ini
progress.(TPV Awaited) The scope of work has
been completed in saving due to compitative rates.
419 2022Drainage Schemes and soling work at UC 105
Depalpur District OkaraOkara
On-going
Schemes27.990 21.521 1.080 0.270 0.000 0% 77%
Date of AA 23.03.2016, Date of TS 25.03.2016,
Date of Invitation of Tender 16.05.2016, Date of
Receipt of Tenders 17.05.2016 ,( No Tender
Received), Date of Re-Invitation of Tender
11.06.2016, Date of Receipt of Tenders,13.06.2016,
Date of work Order 18.06.2016, Date of completion
As per PC-I. 18.06.2017, Anticipated date of
completion,30.06.2019, Re-Appropreation (-) 0.540
Projected Population 51398 Person, Work is ini
progress.(TPV Awaited) The scope of work has
been completed in saving due to compitative rates.
420 2023Rural water Supply & Sewerage Drainage
Scheme, Behlolpur, Tehsil Depalpur, Okara.Okara
On-going
Schemes19.075 18.063 0.326 0.245 0.163 67% 96%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work
Order.02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion, 30-06-
2019 Funds Release on 20-07-2018 Projected
Population 24422 Person.
421 2024
Rural water Supply & Sewerage Drainage
Scheme, Arrora Mian Khan, Tehsil Depalpur,
Okara.
OkaraOn-going
Schemes28.303 22.499 1.934 1.451 0.967 67% 83%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work
Order.02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
30.06.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
422 2025Rural water Supply & Sewerage Drainage
Scheme, Bhai Rao Key, Tehsil Depalpur, Okara.Okara
On-going
Schemes15.441 11.056 1.460 1.095 0.730 67% 76%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work Order
02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
31.12.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
423 2026Rural water Supply & Sewerage Drainage
Scheme, Bhukan, Tehsil Depalpur, Okara.Okara
On-going
Schemes25.728 19.496 2.076 1.557 1.038 67% 80%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender,25.05.2017, Date of
Receipt of Tenders, 26.05.2017, Date of work
Order.02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
30.06.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
424 2027Rural water Supply & Sewerage Drainage
Scheme, Jhunjh Kalan, Tehsil Depalpur, Okara.Okara
On-going
Schemes25.728 22.607 1.039 0.779 0.520 67% 90%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work
Order.02.06.2017, Date of completion As per PC-
I.31.12.2017, Aniticipated date of completion, 30-06-
2019 Funds Release on 20-07-2018 Projected
Population 24422 Person.
425 2028
Rural water Supply & Sewerage Drainage
Scheme, Kot Shah Mushtaq, Tehsil Depalpur,
Okara.
OkaraOn-going
Schemes22.049 21.029 0.340 0.255 0.170 67% 96%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work Order
02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion, 30-06-
2019 Funds Release on 20-07-2018 Projected
Population 24422 Person.
426 2029Rural water Supply & Sewerage Drainage
Scheme, Lalay Wala, Tehsil Depalpur, Okara.Okara
On-going
Schemes21.017 18.798 0.398 0.299 0.199 67% 90%
Date of AA- 08.03.2017, Date of TS-20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work
Order.02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
31.12.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
427 2030
Rural water Supply & Sewerage Drainage
Scheme, Phularwa Wazirkey, Tehsil Depalpur,
Okara.
OkaraOn-going
Schemes23.747 18.351 1.797 1.348 0.896 66% 81%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work
Order.02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
31.12.2019 Funds Release on 20-07-2018 Projected
Population 24422 Person.
428 2031Rural water Supply & Sewerage Drainage
Scheme, Shah Pur, Tehsil Depalpur, Okara.Okara
On-going
Schemes19.862 18.978 0.294 0.221 0.147 67% 96%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work Order
02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
31.12.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
429 2032Rural water Supply & Sewerage Drainage
Scheme, Shinwal, Tehsil Depalpur, Okara.Okara
On-going
Schemes16.746 14.842 0.633 0.475 0.317 67% 91%
Date of AA 08.03.2017, Date of TS 20.03.2017,
Date of Invitation of Tender 25.05.2017, Date of
Receipt of Tenders 26.05.2017, Date of work Order
02.06.2017, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
31.12.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
430 2033Rural water Supply and Drainage Scheme,
Jaithpur DepalpurOkara
On-going
Schemes20.215 19.350 0.288 0.216 0.144 67% 96%
Date of AA 03.08.2016, Date of TS 20.03.2017,
Date of Invitation of Tender 11.10.2016, Date of
Receipt of Tenders 13.10.2016, Date of work Order
17.11.2016, Date of completion As per PC-
I.31.12.2017, Anticipated date of completion,
31.12.2019, Funds Release on 20-07-2018
Projected Population 10309 Person
431 2034
Rural Drainage Scheme Tuff Tiles PCC
Sewerage and Soling, 3SP, 43SP, Khurpy 44SP
Waltoya Matan Wala Amliya Key Suhag, Nihal
Muhar, Mahlo sheikhu, Mahant Darshan Nama
Jindida, District Okara
OkaraOn-going
Schemes97.984 95.372 0.868 0.651 0.433 67% 98%
Date of AA 31.08.2016, Date of TS 22.11.2016,
Date of Invitation of Tender 09.12.2016, Date of
Receipt of Tenders 10.12.2016, Date of work
Order.05.01.2017, Date of completion As per PC-
I.30.06.2018 , Anticipated date of completion,
30.06.2019, Funds Release on 20-07-2018
Projected Population 24422 Person.
432 2035 Sewerage Scheme in Sahiwal City SahiwalOn-going
Schemes27.844 22.271 0.748 0.561 0.500 89% 82%
Date of AA 22.02.2017, Date of TS 24.02.2017,
Date of receipt of tender 20.03.2017, Date of Work
Order 03.04.2017 , Date of completion as per PC-1
30.06.2018 , Anticipated date of completion
30.06.2019 subject to availablity of balance funds,
Work in progress.
433 2036Sewerage Scheme Sahiwal City, City Bund Road,
LBDC, High Street & Girls College RoadSahiwal
On-going
Schemes167.605 74.784 10.000 7.500 7.000 93% 49%
Date of AA 10.01.2017, Date of TS 03.03.2017,
Date of Pre-qualification 11.04.2017 , Date of
receipt of tender 17.04.2017, Date of Work Order
15.05.2017, Date of completion as per PC-1
30.06.2019 , Date of completion as per agreement
30.06.2019, Anticipated date of completion
30.06.2019 subject to availablity of balance funds,
Work in progress.
434 2037
Provision of Sewerage / Drainage / Street
Pavements, etc in Chak No. 147/EB Tehsil
Arifwala District Pakpattn
PakpattanOn-going
Schemes72.933 50.997 4.155 3.116 2.852 92% 74%
Date of A.A= 31.08.2016, Date of T.S= 09.09.2016,
Date of Prequalification = 05.01.2017, Date of
receipt of tenders = 23.01.2017, Date of work
order= 30.01.2017, Date of completion as per PC-
1= 30.06.2018, Date of completion as per
agreement= 30.06.2018, No. of beneficiaries=
14050 persons, Funds released by FD =
03.08.2018,Funds online = 13.08.2018,Disposal
station completed and made functional and handed
over to CBO.Work in progress.
435 2038Provision of Sewerage / Drainage Scheme Chak
No. 64/EB, Arifwala, District Pakpattan.Pakpattan
On-going
Schemes36.218 26.920 3.099 2.324 2.100 90% 80%
Date of A.A= 16.03.2017, Date of T.S= 20.03.2017,
Date of invitation of tenders=16.05.2017, Date of
receipt of tenders = 20.05.2017, Date of work
order= 24.05.2017, Date of completion as per PC-
1= 30.06.2018, Date of completion as per
agreement= 30.06.2018, No. of beneficiaries= 5749
persons, Funds released by FD = 03.08.2018,Funds
online = 13.08.2018,Work in progress.
436 2039 Rural Sewerage/Drainage Scheme 38/EB Arifwala PakpattanOn-going
Schemes32.095 13.986 3.333 2.500 1.667 67% 49%
Date of A.A= 13.10.2016, Date of T.S= 25.10.2016,
Date of invitation of tenders=18.11.2016, Date of
receipt of tenders = 10.12.2016, Date of work
order= 02.01.2017, Date of completion as per PC-
1= 30.06.2018, Date of completion as per
agreement= 30.06.2018, No. of beneficiaries=
14825 persons, Funds released by FD = 03.08.2018
,Funds online = 13.08.2018,Scheme made
functional. Work in progress.
437 2040Rural Drainage Nizam Wala Nawab Pur Road
District Multan Multan
On-going
Schemes19.295 14.295 1.667 0.416 0.000 0% 74%
1. Date of AA 09.03.2015 (16.05.2016) 2. Date of
T.S 15.05.2015 3. Dated of Prequalification __ 4.
Date of invitation of tender 24.03.2015 5. Date of
Receipt of tenders 25.03.2015 6. Date of work order
29.05.2015 7. Date of Completion as per PC-l
08.03.2016 8. Anticipated date of completion
30.06.2019 9. Date of released of funds 03.08.2018.
24.01.2019 10. No. of beneficiaries 2768 persons.
Scheme completed. Rs. 0.416 million proposed for
re-appropriation.
438 2041Rural Drainage Scheme Sewra Chok Adjoining
Abadies Mouza Mubarak Pur Taj Pur SandilaMultan
On-going
Schemes99.890 89.890 3.333 2.500 1.667 67% 92%
1.Date of AA 09.03.2015 2.Date of T.S 21.04.2015
3.Dated of Prequalification 28.01.2015 4.Date of
invitation of tender 27.04.2015 5.Date of Receipt of
tenders 02.05.2015 6.Date of work order 02.06.2015
7.Date of Completion as per PC-l 08.03.2016 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 46964 persons. Work is in progress
439 2042Sewerage Drainage Scheme Matotli Qaiserpur
ShujabadMultan
On-going
Schemes46.000 35.000 3.667 2.750 1.834 67% 80%
1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date
of Pre-Qualification: 30.09.2016 4. Date Invitation of
Tender: 01.11.2016 5. Date of Receipt of Tender:
02.11.2016 6. Date of Award: 10.11.2016 7. Date of
Completion as per PC-I: 09.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
Benificiary= Persons. Work is in progress
440 2043Rural Sewerage Drainage Scheme Chah Rattay
wala Mouza Jangal Barirah District MultanMultan
On-going
Schemes28.800 22.792 1.667 1.250 0.834 67% 82%
1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of
Prequalification 12.03.2016 4.Date of invitation of
tender 07.04.2016 5.Date of Receipt of tenders
09.04.2016 6.Date of work order 27.05.2016 7.Date
of Completion as per PC-l 26.11.2016 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 8253 Persons. Work is in progress
441 2044 Rural Sewerage Drainage Scheme Mill Sadiqabad MultanOn-going
Schemes87.080 75.000 4.027 3.020 3.012 100% 90%
1. Date of A.A: 27.10.2016 2. Date of T.S: - 3. Date
of Pre-Qualification: 30.09.2016 4. Date Invitation of
Tender: 01.11.2016 5. Date of Receipt of Tender:
02.11.2016 6. Date of Award: 18.11.2016 7. Date of
Completion as per PC-I: 17.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 10.No. of Benificiary= 23659
Persons. Work is in progress
442 2045Rural Sewerage Drainage Scheme Mouza
Jahangirabad MultanMultan
On-going
Schemes46.400 41.400 1.667 1.250 0.834 67% 91%
1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010
3.Dated of Prequalification - 4.Date of invitation of
tender 30.01.2010 5.Date of Receipt of tenders
15.03.2010 6.Date of work order 20.03.2010 7.Date
of Completion as per PC-l 08.03.2013 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 2250 persons. Work is in progress
443 2046Rural Sewerage Drainage Scheme Pakkay Wala
Anayat Pur Mahota Tehsil and District MultanMultan
On-going
Schemes29.930 25.833 1.167 0.875 0.584 67% 88%
1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date
of Pre-Qualification: - 4. Date Invitation of Tender:
09.11.2016 5. Date of Receipt of Tender:
10.11.2016 6. Date of Award: 16.12.2016 7. Date of
Completion as per PC-I: 15.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
Benificiary= Persons. Work is in progress
444 2047Rural Sewerage Drainage Scheme Saddiqabad
Hirawat and Yaray wala District MultanMultan
On-going
Schemes22.840 20.937 0.515 0.386 0.258 67% 93%
1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of
Prequalification 12.03.2016 4.Date of invitation of
tender 07.04.2016 5.Date of Receipt of tenders
09.04.2016 6.Date of work order 01.06.2016 7.Date
of Completion as per PC-l 31.11.2016 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 25285 Persons. Work is in progress
445 2048Rural Sewerage Scheme Chah Sunna Wala
Multan.Multan
On-going
Schemes13.360 8.887 1.490 1.118 0.745 67% 72%
1.Date of AA 25.03.2017 2.Date of T.S 01.04.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 20.04.2017 5.Date of Receipt of tenders
21.04.2017 6.Date of work order 23.05.2017 7.Date
of Completion as per PC-l 22.07.2017 8. Anticipated
date of completion 30.04.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 4648 persons. Work is in progress
446 2049 Rural Sewerage Schemes Ambala MultanOn-going
Schemes50.000 44.336 1.714 1.286 0.857 67% 90%
1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date
of Pre-Qualification: 30.09.2016 4. Date Invitation of
Tender: 01.11.2016 5. Date of Receipt of Tender:
02.11.2016 6. Date of Award: 10.11.2016 7. Date of
Completion as per PC-I: 09.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
Benificiary= Persons. Work is in progress
447 2050
Rural Drainage, Sewerage, Solding and Tuff Tiles
Scheme Gardezpur, Dhandho, Bagrain Ghangi,
Amanullah Shah Wains & Marha, District Multan
MultanOn-going
Schemes7.000 3.635 1.078 0.270 0.000 0% 52%
1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated
of Prequalification - 4. Date of invitation of tender
15.05.2017 5. Date of Receipt of tenders
16.05.2017 6. Date of work order 31.05.2017 7.
Date of Completion as per PC-l 30.07.2017 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018. 24.01.2019 10. No.
of beneficiaries=111527 persons. Scheme
completed in saving. Rs. 0.270 million proposed for
re-appropriation.
448 2051
Rural Drainage, Sewerage Scheme Mithu Shrqi,
Basti Mithu Gharbi, Basti Dad Shah Moosa
Muqeempur, District Multan
MultanOn-going
Schemes7.000 3.921 1.012 0.271 0.018 7% 56%
1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated
of Prequalification - 4. Date of invitation of tender
15.05.2017 5. Date of Receipt of tenders
16.05.2017 6. Date of work order 31.05.2017 7.
Date of Completion as per PC-l 30.07.2017 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018. 24.01.2019 10. No.
of beneficiaries=111527 persons. Scheme
completed in saving. Rs. 0.253 million proposed for
re-appropriation.
449 2052 Rural Drainage, Sewerage Scheme Basti
Dodwpur, Basti Shahpur, District MultanMultan
On-going
Schemes6.000 3.464 0.802 0.201 0.000 0% 58%
1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated
of Prequalification - 4. Date of invitation of tender
15.05.2017 5. Date of Receipt of tenders
16.05.2017 6. Date of work order 31.05.2017 7.
Date of Completion as per PC-l 30.07.2017 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018. 24.01.2019 10. No.
of beneficiaries=111527 persons. Scheme
completed in saving. Rs 0.201 million proposed for
re-appropriation.
450 2053 Rural Sewerage Scheme Basti Laar MultanOn-going
Schemes50.000 35.000 1.000 0.750 0.500 67% 71%
1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date
of Pre-Qualification: 30.09.2016 4. Date Invitation of
Tender: 01.11.2016 5. Date of Receipt of Tender:
02.11.2016 6. Date of Award: 12.11.2016 7. Date of
Completion as per PC-I: 11.05.2018 8. Anticipated
Date of Completion: 30.06.2018 9.Date of released
of funds 23.11.2018 24.01.2019 10.No. of
Benificiary= Persons. Work is in progress.
451 2054Sewerage, Tuff Tiles in Remaining Portion of Gaily
Wal City.Lodhran
On-going
Schemes62.170 28.077 6.667 5.000 3.800 76% 51%
1. Date of A.A: 27-08-2016. 2. Date of T.S: 26-09-
2016 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 14-11-2016 5. Date of Receipt
of Tender: 15-11-2016 6. Date of Award: 08-12-
2016 7. Date of Completion as per PC-I: 31-12-2017
8. Anticipated Date of Completion: 10-03-2018
9.Date of released of funds 03.08.2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
32835 Persons. Work is in Progress
452 2055Tuff Tiles & Sewerage Scheme for remaining
portion of Gogran City.Lodhran
On-going
Schemes45.795 32.717 4.359 2.269 1.112 49% 74%
1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-
2016 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 14-11-2016 5. Date of Receipt
of Tender: 15-11-2016 6. Date of Award: 24-11-
2016 7. Date of Completion as per PC-I: 30-06-2017
8. Anticipated Date of Completion: 23-01-2018
9.Date of released of funds 03.08.2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
16528 Persons. Scheme is functional & handed
over to the community. Rs. 1.157 million proposed
for re-appropriation
453 2056Provision / Laying of Sewer Lines in Missing Areas
of Khanewal City including new and old Azafi AbadKhanewal
On-going
Schemes100.000 55.895 6.667 5.000 4.769 95% 61%
1. Date of A.A: 27.08.2016 2. Date of T.S:
25.10.2016 3. Date of Pre-Qualification: 22.10.2016
4. Date of Invitation of Tender: 29.11.2016 5. Date
of Receipt of Tender: 05.12.2016 6. Date of Work
order: 15.12.2016 7. Date of Completion as per PC-
I: 30.06.2018 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: --------- 11
No. of beneficiaries 379227 Persons Work is in
progress.
454 2057Provision of Drains, Soling Culverts etc to different
abadies of PP-212, Tehsil Kabirwala, KhanewalKhanewal
On-going
Schemes40.000 22.000 6.000 4.500 4.029 90% 65%
1. Date of A.A: 25.04.2017 2. Date of T.S:
04.05.2017 3. Date of Pre-Qualification: ---------- 4.
Date of Invitation of Tender: 03.06.2017 5. Date of
Receipt of Tender: 05.06.2017 6. Date of Work
order: 07.06.2017 7. Date of Completion as per PC-
I: 30.06.2018 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
10. Reason of Slow Moving: -------- 11 No. of
beneficiaries 7819 Persons Work in progress.
455 2058Drainage Scheme Chak No.88/10-R District
KhanewalKhanewal
On-going
Schemes10.000 3.000 2.333 1.750 1.319 75% 43%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 09.11.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 5120 Persons Work is in
progress.
456 2059Provision of Tuff Pavement in Gaggo Mandi /
Dharian / Chak No. 187/EB Vehari
On-going
Schemes49.970 28.688 3.333 2.500 1.870 75% 61%
1. Date of A.A: 21.02.2017 2. Date of T.S:
25.02.2017 3. Date of Pre-Qualification: 4. Date of
Invitation of Tender: 20.05.2017 5. Date of Receipt
of Tender: 22.05.2017 6. Date of Work order: 7.
Date of Completion as per PC-I: 21.05.2019 8.
Anticipated Date of completion: 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of beneficiaries
13005 Persons Work is in progress.
457 2060Rehabilitation of Sewerage & Drainage Scheme
Machiwal, Tehsil and District Vehari.Vehari
On-going
Schemes22.396 19.450 0.982 0.737 0.670 91% 90%
1. Date of A.A: 27-08-2016 2. Date of T.S:
02.09.2016 3. Date of Pre-Qualification: ____ 4.
Date Invitation of Tender: 06.12.2016 5. Date of
Receipt of Tender: 07.12.2016 6. Date of Award:
22.12.2016 7. Date of Completion as per PC-I:
21.12.2017 8. Anticipated Date of Completion:
30.06.2018 9.Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: NIL 11 No.
of beneficiaries 11435 Persons Work is in progress.
458 2061Execution of Forty (40) Misc. Development
Schemes in NA-167, District Vehari Vehari
On-going
Schemes27.500 21.681 1.000 0.750 0.570 76% 81%
1. Date of A.A: 21.01.2013 2. Date of T.S:
22..01.2013 3. Date of Pre-Qualification: 4. Date
Invitation of Tender: 14.02.2013 5. Date of Receipt
of Tender: 16.02.2013 6. Date of Award: 26.02.2013
7. Date of Completion as per PC-I: 26.05.2013 8.
Anticipated Date of Completion: 30.06.2013 9.Date
of released of funds 23.11.2018 24.01.2019 10.
Reason of Slow Moving: - 11. No. of Beneficiary=
Persons Work is in progress.
459 2062 Provision of Sewerage & Tuff Tiles for Dajal City RajanpurOn-going
Schemes120.100 34.990 28.367 21.275 14.184 67% 41% "• Date of A.A = 05.11.2016
460 2063
Construction of Drain, Brick Pavement Sullage
Carrier Culverts, Tuff Tile Muhammad Pur Dewan
Rajanpur
RajanpurOn-going
Schemes29.990 25.694 1.000 0.750 0.000 0% 86% "• Date of A.A = 17.12.2014
461 2064Construction of Drain, Brick Pavement Sullage
Carrier Culverts, Tuff Tile Fazilpur RajanpurRajanpur
On-going
Schemes50.000 25.952 1.000 0.750 0.500 67% 53% "• Date of A.A = 17.12.2014
462 2065
Comprehensive Sewerage / Drainage / Soling /
PCC / Tuff Tile scheme at Sanawan Town, District
Muzaffargarh (Remaining Portion)
MuzaffargarhOn-going
Schemes25.000 22.152 0.949 0.712 0.425 60% 90% "• Date of A.A 22-09-2016
463 2066
Construction of Drain Brick Pavement, RCC
Culverts, VR Bridge and Sullage Carrier in UC
Wainse No. 76 Tehsil Jatoi
MuzaffargarhOn-going
Schemes42.270 10.000 10.757 8.068 5.279 65% 36% Date of AA 31.7.2017
464 2067
Construction of Drain Brick Pavement, RCC
Culverts, VR Bridge and Sullage Carrier in UC
Bairband No. 84 Tehsil Jatoi
MuzaffargarhOn-going
Schemes43.350 10.000 11.117 8.338 5.300 64% 35% Date of AA 31.7.2017
465 2068
Construction of Drain Brick Pavement, RCC
Culverts, VR Bridge and Sullage Carrier in UC
Kotla Gamoon No. 77 Tehsil Jatoi
MuzaffargarhOn-going
Schemes43.730 10.000 11.243 8.432 5.400 64% 35% Date of AA 31.7.2017
466 2069Sewerage / Drainage Scheme for Rangpur
MuzaffargarhMuzaffargarh
On-going
Schemes241.100 48.442 56.667 42.500 27.450 65% 31% "• Date of A.A 22.9.2016
467 2070 Rural Sewerage / drainage scheme Shah Jamal MuzaffargarhOn-going
Schemes68.504 63.220 1.000 0.500 0.000 0% 92%
Funds received on 12.11.2018 (Rs.0.500 M)
Balance funds of Rs.4.540 M released on
10.12.2018 for clearance of liabilities of the
contractor as per Court Order which is under
process.
468 2071
Rural Sewerage/Drainage Scheme Dhori Adda &
Adoining Abadies Chak No. 426AB & 438/TDA
(Revised)
LayyahOn-going
Schemes198.000 63.732 25.010 18.758 12.505 67% 39% • Date of AA = 25.10.2014
469 2072
Rural Drainage/Sewerage & Nallian Mosan Shah,
Mongarh, Ahsin & Waddeh wali UC Wara Sehran
Tehsil Karoor Lal Essen District Layyah
LayyahOn-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% • Date of AA = 29.07.2017
470 2073Sewerage scheme Chak No. 110/TDA, Tehsil
Karor, District LayyahLayyah
On-going
Schemes30.000 20.395 3.202 2.402 1.600 67% 73% • Date of AA = 22-09-2016
471 2074Sewerage scheme Chak No. 229/TDA, Tehsil
Karor, District LayyahLayyah
On-going
Schemes30.000 15.000 5.000 3.750 2.500 67% 58% • Date of AA = 22-09-2016
472 2075Sewerage scheme Chak No. 251/TDA, Tehsil
Karor, District LayyahLayyah
On-going
Schemes30.000 14.952 5.016 3.762 2.505 67% 58% • Date of AA = 22-09-2016
473 2076Construnction of soling & drain/Nallian in UC
Baseera Tehsil Karoor District Layyah NA-181Layyah
On-going
Schemes30.000 17.200 4.267 3.200 2.134 67% 64% • Date of AA = 29.07.2017
474 2077 Construction of Sewerage chak no. 63,DB. BahawalpurOn-going
Schemes18.845 14.803 1.340 1.455 1.100 76% 84%
Date of AA. 08.08.2016. Date of T.S. 13.10.2016.
Tender received on 14-11-2016. Date of award-03-
01-2017. Date of completion=02-12-2017.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Funds Rs.0.450 million provided through re-
appropriation dated 19.10.2018.Work is in progress.
475 2078
Provision of Sewerage / Tuff Tile in Basti Jhangara
Sharqi, Mouza Jhangara Sharqia, Union Council
Bahawalpur Ghalvan, Tehsil Ahmedpur Sharqia,
District Bahawalpur.
BahawalpurOn-going
Schemes29.895 26.878 1.003 0.752 0.500 66% 92%
Date of AA. 08.08.2016. Date of T.S. 13.10.2016.
.Tender received on 14-11-2016. Date of award-03-
01-2017. Date of completion=02-12-2017.
Anticipated date of completion 30.06.2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
476 2079 Sewerage & Tuff Tile Jamalpur BahawalpurOn-going
Schemes29.526 22.718 2.269 1.702 1.130 66% 81%
Date of AA. 08.08.2016. Date of T.S. 13.10.2016.
.Date of receipt of Tender 14.11.2016. Date of
award 30.11.2016. Date of completion 29.10.2017.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
477 2080 Sewerage / Drainage Scheme, Chak No. 110/DB BahawalpurOn-going
Schemes29.725 27.964 0.133 0.100 0.067 67% 94%
Date of A.A= 18-08-2015. Date of T.S= 28-08-2015.
Date of receipt of tenders = 08-03-2016. Date of
work order= 18.04.2016. . Date of completion as per
agreement=17.04.2017. Anticipated date of
completion = 30.06.2019. Date of receipt of funds
by F.D. 20.07.2018 & 11.01.2019. Work is in
progress.
478 2081Sewerage Scheme Chak no. 15/Ford wah, Tehsil
Hasilpur.Bahawalpur
On-going
Schemes15.616 8.287 1.855 0.891 0.428 48% 56%
Date of AA. 08.08.2016. Date of T.S. 13.10.2016.
.Date of receipt of tender 14-11-2016. Date of award
15-12-2016. Date of completion 14-11-2017.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Funds Rs.0.500 million surrendered vide Chief
Engineer(S),PHED Lahore No.72-78/B(4) dated
10.01.2019.Work is in progress.
479 2082 Rural Sewerage Scheme 17/F.W BahawalpurOn-going
Schemes25.000 13.450 3.833 2.075 1.110 53% 58%
Date of AA. 08.08.2016. Date of T.S. 13.10.2016.
Date of Receipt of tender 14.11.2016. Date of award
15.12.2016. Date of completion 14.11.2017.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Funds Rs.0.800 million surrendered vide Chief
Engineer(S),PHED Lahore No.72-78/B(4) dated
10.01.2019.Work is in progress.
480 2083 Rural Sewerage Scheme Basti Chohan BahawalpurOn-going
Schemes21.500 10.625 3.510 2.633 1.750 66% 58%
Date of AA. 08.08.2016. Date of T.S. 13.10.2016.
.Date of Receipt of tender 14.11.2016. Date of
award 15.12.2016. Date of completion 14.11.2017/.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress. . .
481 2084
Construction of Sewerage Drainage Schemes
Abadi Jodheka QasimKa Chak Sarkari Bagar Wala
Khoo Chavek, Toba Balochan Tehsil & Distt.
Bahawalnagar
BahawalnagarOn-going
Schemes99.996 29.990 23.335 17.501 15.000 86% 45%
Date of AA. 21.10.2016. Date of T.S. 26.10.2016.
Date of Tender 12.12.2016. Funds released by FD
04-07-2017 & 06-10-2017.Date of receipt of tender
14-12-2016 . Date of award 19-01-2017. Date of
completion 18-12-2017. Anticipated date of
completion 30-06-2019. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Work is in progress.
482 2085Sewererage and Drainage Scheme Maroot Tehsil
Fortabbas District BahawalnagarBahawalnagar
On-going
Schemes120.980 52.857 22.665 16.999 16.990 100% 58%
Date of AA. 15-10-2015 . Date of TS. 22-02-2016.
Prequalification of the contractor=22-03-2016. Date
of invitation of tenders=24-03-2016. Date of receipt
of tenders = 07-04-2016. Date of award= 30-04-
2016. Date of completion as per agreement=29-04-
2018.Expected date of completion 30-06-2019. Date
of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
483 2086Comprehensive Urban / Draiange Sewerage
Scheme Doonga BoongaBahawalnagar
On-going
Schemes72.683 69.236 1.000 0.500 0.500 100% 96%
Date of AA. 08.02.2011. Date of T.S. 08.02.2011.
Date of award. 11.03.2011. Date of completion
30.06.2012. Anticipated date of completion 30-06-
2019. Funds released by FD on 12-11-2018 &
11.01.2019 .Work is in progress.
484 2087Provision of water Supply /Sewerage scheme for
MC Tranda Saway Khan, Tehsil & District RYK
Rahim Yar
Khan
On-going
Schemes121.000 32.590 29.466 22.100 14.700 67% 39%
Date of AA(DDWP)=28-10-2016..Date of T.S.
13.02.2017..Tenders received on 13-03-2017 ..
Date of work awarded .25-04-2017. .Date of
completion 30-06-2019. .Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019..Funds of 3rd Quarter
is not credited/onlined to the District Accounsts
office RYK..Work is in progress.
485 2088 Construction of Sewerage Open Drain in
Chachran Sharif
Rahim Yar
Khan
On-going
Schemes97.240 52.148 14.698 11.024 8.847 80% 63%
Date of A.A= 26-02-2016.Date of T.S= 05-05-
2016.Date of prequalification. 03-08-2016..Date of
tender received on 10-10-2016.Date of award= 16-
11-2016.Date of completion= 15-04-2018.Expected
date of completion 30-06-2019. Date of receipt of
funds by F.D. 20.07.2018 & 11.01.2019. Work is in
progress.
486 2089Urban water Supply / Sewerage Scheme for City
Tranda Muhammad Pannah
Rahim Yar
Khan
On-going
Schemes121.750 49.980 23.917 17.938 13.989 78% 53%
Date of AA =17-09-2016.Date of TS=23-11-
2016.Prequalification of contractors 05-01-2017.
Date op receipt of Tenders 06-02-2017..Date of
work awarded 17.03.2017..Date of completion
16.09.2018..Expected date of completion. 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
487 2090Sewerage & Tuff tiles in UC 36, 37, 38, 40, 41, 42
and 71 under Rahim Yar Khan
Rahim Yar
Khan
On-going
Schemes35.000 20.000 1.000 0.750 0.601 80% 59%
Date of AA. 24.10.2016..Date of T.S. 29.11.2016.
Tenders received on 16-01-2017 .Date of work
awarded 08-02-2017. Date of completion 07-08-
2017. Anticipated date of completion 30-06-
2019.Funds released by FD on 11.01.2019. Work is
in progress.
488 2091
Sewerage Scheme R.Y.Khan City with Treatment
Plant-Construction of Intermediate Pumping
Station Near Niazi Colony & Installation of Force
Main
Rahim Yar
Khan
On-going
Schemes481.825 421.239 2.000 1.500 1.187 79% 88%
Date of A.A= 30-12-2015..Date of RAA= 23-09-
2016.Date of T.S. 30.09.2016..Date of
prequalification= 03-08-2016.Date of tender= 21-10-
2016.Date of work awarded=19-12-2016.Date of
completion=18-05-2017.Anticipated date of
completion: 30.06.2019.Funds released by FD on
11.01.2019. The scheme is completed and
functional. Libility of Contractor is yet to be cleared.
Estimate submitted to Chief Engineer(S), PHED
Lahore for revised A.A from the P&D Department.
489 2092Provision of Sewerage in Chak No 141JB
Khokhran Tehsil & District ChiniotChiniot
On-going
Schemes31.350 25.000 2.117 1.588 1.059 67% 83%
1. Date of AA = 20.10.2016 2. Date of TS =
25.10.2016 3.Date of Award of work 17.12.2016
4.Dated of Released Funds 5. No. of Beneficiaries =
1891 Persons Funds Released upto 24.01.2019 by
the Chief Engineer (South) PHED Lahore and work
is in progress.
490 2093Sewerage Scheme, PCC Slab Soling in Bhowana
city ChiniotChiniot
On-going
Schemes77.000 20.363 8.333 6.250 4.100 66% 32%
1. Date of AA = 19.09.2017 2. Date of TS =
25.10.2017 3. Date of Work Order = 09.12.2017
4.Dated of Released Funds 03.11.2017 Funds
Released upto 24.01.2019 by the Chief Engineer
(South) PHED Lahore and work is in progress.
491 2094Bulk water Supply Project from River Jhelum to
Murree Rawalpindi
On-going
Schemes4,254.770 1,068.566 1.000 0.750 0.000 0% 25% Work in Progress.
492 2095 water Supply Scheme Fazaiya Housing Colony
Turnol Tehsil & District RawalpindiRawalpindi
On-going
Schemes373.073 338.322 11.584 8.688 5.792 67% 92%
Work suspended at site due to change of intake site
by SPD Department, now NOC granted by SPD and
revised estiamte under process of approval.
493 2096
Improvement of Water Supply System in Murree
under PPP Rehabilitate, Operate and Transfer
(ROT Mode).
RawalpindiOn-going
Schemes24.500 14.500 3.333 2.500 0.000 0% 59% Funds Released by FD on 31st July 2018.
494 2097Installation of water Supply scheme for residents
of Fateh Jang attockAttock
On-going
Schemes469.913 400.994 10.000 7.500 5.000 67% 86%
A.A Date 21.10.2014.T.S Date 10.11.2014.Date of
Start of Scheme 22.01.2015.Date of Completion of
Scheme 30.06.2019.Work is in progress.
495 2098Rehabilitation of Urban water Supply Scheme
Kallar Kahar District ChakwalChakwal
On-going
Schemes73.390 61.987 3.801 2.851 1.901 67% 87%
Date of A.A 17.09.2015. Date of T.S.Date of Start
11.02.2016.Date of completion 30.06.2019.Full
funds utilized. Scheme is short funded.
496 2099 Est. of W.S. Scheme Talagang ChakwalOn-going
Schemes94.580 82.608 3.931 2.948 1.966 67% 89%
Date of A.A 17.09.2015 .Date of T.S
07.10.2015.Date of Start 26.01.2016.Date of
completion 30.06.2019.Full funds utilized. Scheme
is short funded.
497 2100 water Supply Scheme Chakwal Based on Khai
DamChakwal
On-going
Schemes1,018.160 341.465 33.333 9.488 0.506 5% 34%
"Date of A.A 03.04.2014.Date of T.S
16.04.2014.Date of Start 30.05.2014.Date of
completion 30.06.2021.Phase i of the scheme has
been completed. 2 Cusec water from Khai Dam is
being supplied to M.C Chakwal since 01-2018. The
amended A.A has been submitted in P&D for
according approval. The tendering process of Phase-
II will be started after getting amended approval.
498 2101Installation of 02 no. of Tubewells in choa Saiden
Shah, District ChakwalChakwal
On-going
Schemes18.460 17.730 0.730 0.548 0.365 67% 98%
Date of A.A 21.11.2017. Date of T.S
23.11.2017.Date of Start 12.01.2018. Date of
completion 30.06.2018.Work completed. However
further funds are required to clear the liability
against the above rates of awarded work.
499 2102Water Suplly Scheme based on Naroomi Dhan
Spring Phase IIJhelum
On-going
Schemes298.854 286.982 3.953 2.965 1.977 67% 97%
"A.A: 10-04-14.T.S: 16-4-14 .Date of
Commencement 24-10-2014.Work is in Progress.
Scheme is partially operational.
500 2103Lying of water Supply Pipelines in D Block Old
Satellite Town & Millat Abad Sargodha CitySargodha
On-going
Schemes5.386 4.139 0.416 0.312 0.312 100% 83%
Date of A.A 27.08.2016, Date of T.S 04.09.2016,
Date of Award 22.02.2017, Scheduled date of
Completion is 30.06.2018, Date of Commencement,
22.02.2017, Funds released on 30.07.2018, Funds
on-lined on 30.07.2018. R/Main / D-System 9395-
Rft laid. P.C.C Slab 3128-Cft laid. RCC Sewer 12"
i/d 531-Rft laid. Work in progress.
501 2104Augmentation of water Supply Scheme Sargodha
based on Canal water Supply Sargodha Phase ISargodha
On-going
Schemes268.210 197.713 16.667 12.500 9.628 77% 77%
Date of A.A 28.02.2014, Date of T.S 30.04.2014,
Date of Award 28.06.2014, Scheduled date of
Completion is 30.06.2017, Date of Commencement,
28.06.2014, Funds released on 30.07.2018, Funds
on-lined on 30.07.2018. 21-No. tube wells
completed out of provision 22-No. 21-No. Pump
Houses 90% completed out of provision 22-No. 31-
Sets of Pumping machinery arranged. R/Main / D-
System 122534-Rft laid out of provision 125047-Rft.
5-No. GSTs 90% completed out of 05-No. 05-No.
Staff Quarter 85% completed. Work in progress.
502 2105 water Supply Scheme for Farooq Colony,
Imtiazabad Abad Sargodha CitySargodha
On-going
Schemes98.971 65.957 6.667 5.000 5.000 100% 72%
Date of A.A 11.08.2015, Date of T.S 14.10.2015,
Date of Award 16.01.2016, Scheduled date of
Completion on 30.06.2017, Date of
Commencement, 16.01.2016, Funds released on
30.07.2018, Funds on-lined on 30.07.2018. 06-No.
trial bore, tube well bore & pump house completed
out of provision 06-No. 08-Sets of Pumping
machinery arranged. R/Main / D-System 40803-Rft
laid & 360-Rft arranged out of provision 112510-Rft.
02-No. GSTs 90% completed. Work in progress.
503 2106Comprehensive Urban water Supply and
Sewerage Scheme Khushab CityKhushab
On-going
Schemes358.444 342.647 5.261 2.946 2.940 100% 96%
Date of A.A 08.10.2009 Date of T.S 05.11.2009
Date of award 06.01.2010. Date of completion
30.06.2019 Scheme is functional and handed over
to Municipal Committee Khushab.v
504 2107Comprehensiver Urban water Supply and
Sewereage Scheme JauharabadKhushab
On-going
Schemes586.987 462.440 33.333 26.000 19.500 75% 82%
Date of A.A 08.10.2009 Date of T.S 05.11.2009
Date of award 11.08.2010 Date of completion
30.6.2019 All 10 No. Tubewell with pump house,
pumping machinary and GST 800000 Gln
completed. Work of laying of water supply pipe line
is in Progress. All 3 Nos disposal works completed
and functional. Work lying lataral sewer is in
progress.
505 2108Replacement of Old water Supply Pipeline in
Jauharabad.Khushab
On-going
Schemes90.000 21.943 3.333 2.500 1.870 75% 26%
Date of AA 27.08.2016 Date of TS 01.11.2016 Date
of award 06.02.2017 Date of Completion 30.06.2020
Work is in progress.
506 2109Replacement of Old water Supply Pipeline in
Khushab City.Khushab
On-going
Schemes130.000 44.202 16.667 12.500 9.800 78% 42%
Date of AA 27.08.2016 Date of TS 01.11.2016 Date
of award 06.02.2017 Date of Completion.
30.06.2020 Work is in progress.
507 2110Comprehensive water Supply Sewerage Scheme
MianwaliMianwali
On-going
Schemes494.444 462.274 6.667 4.300 2.634 61% 94%
Revised Date of A.A. 16-01-2014 Date of Revised
T.S.08-08-2014, Date of 2nd Revised A.A. 04-11-
2015, Date of 2nd Revised T.S.10-12-2015, Date of
Start of Work.03-12-2009, Remarks. Tube-
Well=8/8, Pump House=8/8, Pumping
Machinery=9/9, Rising Feeding Main=12"i/d A.C=
921/940, 10" i/d A.C= 11959 /11960, 8" i/d
PVC=26535 /26541, 6"i/d PVC= 30244 /30591,4"i/d
PVC= 40592/40583, 3"i/d PVC= 137262/137106,
OHR = 3/3, Chlorinator = 8/8, T/Line 5/8, RCC
Sewer=42"i/d= 480/480, 36"i/d =8385/8385, 30"i/d
=2159/2159, 27"i/d= 8694/8694, 24"i/d=12415
/12415, 21"i/d= 14020/14020, 18"i/d= 23255/23357,
15"i/d= 28803 /29337, 12"i/d=137955 /137918,
9"i/d=31456/31456, Sullage Carrier=8500/8500,
Oxidation Pond=2/2. Work is in progress.
508 2111Water Supply Scheme Iskandarabad, District
Mianwali.Mianwali
On-going
Schemes4.498 1.509 0.996 0.273 0.024 9% 34%
Date of A.A. 11-08-2015, Date of T.S. 15-08-2015,
Date of Start of Work 28-10-2015, Remarks. Rising
Main=4"i/d PVC= 1960/1960, D/System=4"i/d G.I=
0/50, 3"i/d PVC=6000/6000, 4"i/d PVC= 400/400,
6"i/d PVC 1900/1900, O.H.R=1/1 , Repair of
P/Machinery, R/F Main old=1/1. Scheme completed
in saving Fund proposed to be surrendered.
509 2112Comprehensive water Supply Scheme Kamalia
CityToba Tek Singh
On-going
Schemes426.211 307.725 25.000 18.750 13.450 72% 75%
1-Date of A.A 16.10.2014 2- Date of T.S 28.11.2014
3-Date of Prequalification 08.12.2014 4-Date of
invitation of tenders 07.12.2014 5- Date of Receipt
of tenders 23.12.2014 6- Date of work order
31.12.2014 7- Date of completion as per PC-I
15.10.2017 8- Anticipated date of completion
30.12.2017 9- No. of Beneficiary - 298364 Person
10-Funds Released by F.D 03.08.2018 &
24.01.2019. 11-Re-appropriation of funds (+/-) Work
in progress.
510 2113 Urban water Supply Scheme Gojra Phase II Toba Tek SinghOn-going
Schemes532.942 125.000 33.333 25.000 16.600 66% 27%
1-Date of A.A 01.01.2016 2- Date of T.S 30.03.2016
3-Date of Prequalification -31.03.2016 4-Date of
invitation of tenders 17.04.2016 5- Date of Receipt
of tenders 25.04.2016 6- Date of work order -
18.05.2016 7- Date of completion as per PC-I
11.11.2018 8- Anticipated date of completion
11.11.2018 9- No. of Beneficiary - 393651 Person
10-Funds Released by F.D 03.08.2018 &
24.01.2019. 11- Re-appropriation of funds(+/-)
.Work in progress.
511 2114
Provision of Brick Pavements, Drains, Tuff Tiles,
Water Supply, Play Grounds, Public Parks, etc., in
the Rural and Urban Areas of Tehsil Kamalia and
Tehsil Pir Mehal District T.T. Singh
Toba Tek SinghOn-going
Schemes245.000 120.000 16.667 12.500 8.200 66% 52%
1-Date of A.A 23.10.2017 2- Date of T.S
17.11.2017. 3-Date of Prequalification 4-Date of
invitation of tenders 05.12.2017 5- Date of Receipt
of tenders 07.12.2017 6- Date of work order
12.12.2017 7- Date of completion as per PC-I 8-
Anticipated date of completion 30.06.2018.9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
512 2115Provision of water Supply and Drainage Scheme
for Dinga City Distt Gujrat.Gujrat
On-going
Schemes197.050 138.416 10.000 7.500 5.000 67% 73%
A.A Date =5.9.2014.T/Well installed=4
Nos.functional= 3 Nos .PVC Pipe Laid=170825
Rft.PCC= 156462 Cft. S.C=7719 Rft. Soling=6069
sft, Tuff paver=19570 sft.1 No OHR 50000 Gln
completed.Work in porgress.
513 2116 Construction of water Supply System Gujrat GujratOn-going
Schemes742.379 487.503 33.333 10.000 1.667 17% 66%
A.A Date =10.02.2009.17 Nos Tube wells are
functional and Handed over to M.C Gujrat .3 Nos
OHR's are functional. 763906 Rft pipes laid &
functional.House Connection= 2155 Nos. 2 Nos
contracts are rescinded while 1 No has been
reinstated.
514 2117Extension of Urban water Supply and drainage
scheme Azafi Abadies in Kharian CityGujrat
On-going
Schemes122.416 79.911 5.000 3.750 2.500 67% 67%
A.A Date =23.9.2014.T/Well installed= 3 Nos
Functional= 2 Nos.PVC Pipe Laid=36194
Rft.PCC=104022 Cft. S.C=5986 Rft.Tuff Paver=
74392 Sft Work in porgress.
515 2118Extension of Urban water Supply and drainage
scheme Sarai Alamgir City.Gujrat
On-going
Schemes159.603 122.667 8.432 11.324 9.216 81% 83%
A.A Date =23.9.2014.T/Well installed= 2 Nos.PVC
Pipe Laid=77073 Rft.PCC= 328408 Cft. S.C=550
Rft.Work in porgress.
516 2119 water Supply & Sewerage Scheme in PP 114 GujratOn-going
Schemes47.981 22.984 8.332 6.249 4.166 67% 57%
Drain Type-I=23952 Rft. PCC. 1:2:4=91393
Cft.Work in progress.
517 2120 water Supply scheme Lalamusa and Rural Areas GujratOn-going
Schemes197.321 40.000 5.000 3.750 2.500 67% 22%
A.A Date =23.02.2017.3 T/Well installed.Pipe
8"=400 Rft, 4"=2000 Rft, 3'=1000 rft. Work in
porgress.
518 2121Improvement / Extension of Urban water Supply
Sewerage & Drainage Scheme M.B.Din City
Mandi
Bahauddin
On-going
Schemes345.995 114.976 16.667 14.700 10.534 72% 36%
* A.A Date. 25.03.2016* T.S Date. 29.03.2016* Start
Date 24.04.2016* Completion date 23.04.2019. *
Work in progress.
519 2122Improvement / Extension of Urban water Supply
Sewerage & Drainage Scheme Malikwal City
Mandi
Bahauddin
On-going
Schemes197.956 102.347 5.000 3.750 2.500 67% 53%
* A.A Date. 07.01.2016* T.S Date. 15.01.2016.*
Start Date 01.03.2016* Completion date
28.02.2019. * Work in progress.
520 2123 water Supply Scheme Chot Dhirian, M.B.DinMandi
Bahauddin
On-going
Schemes75.000 64.263 3.333 1.100 0.267 24% 86%
* A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start
Date 17.12.2015.* Completion date 30.06.2019.*
Work in progress
521 2124Rehabilitation / Augmentation of Urban water
Supply Scheme Narowal City Narowal
On-going
Schemes185.411 98.401 13.333 3.733 0.395 11% 53%
A.A Date.30.9.2014T.S Date.10.11.2014*Start Date
23.12.2014*Completion date 30.06.2019.Work in
progress. Fund not received on spending end yet
522 2125Urban water Supply Scheme Kahna Phase I and
IILahore
On-going
Schemes199.405 126.661 6.667 4.500 2.834 63% 65%
Scheme in nearing completion, 2-Nos. Tube wells
are put operational. Balance funds are required to
complete the scheme
523 2126Provision of Open water Supply Scheme
FerozwalaSheikhupura
On-going
Schemes175.524 125.000 3.333 2.500 1.667 67% 72% Work in Progress
524 2127 Urban water Supply Scheme Muridkey SheikhupuraOn-going
Schemes450.000 219.000 16.667 12.500 8.334 67% 51% Work in Progress
525 2128 water Supply Scheme Chunian Amended KasurOn-going
Schemes228.855 220.454 2.672 1.534 0.866 56% 97% Work in Progress
526 2129Urban water Supply and Sewerage/ Drainage
Scheme Phool NagarKasur
On-going
Schemes475.472 468.331 2.380 1.185 0.590 50% 99% Work in Progress
527 2130 water Supply, Drainage & PCC Scheme Outside
Khudian District KasurKasur
On-going
Schemes176.173 172.172 1.334 1.001 0.667 67% 98% Work in Progress
528 2131Extension / Improvement of water Supply Scheme
Southern City, Okara.Okara
On-going
Schemes864.000 701.498 26.667 20.000 13.334 67% 83%
Date of A.A (Revised) 22.01.2013, Date of T.S
(Revised) 28.01.2013, Date of Prequalification
11.09.2012, Date of invitation of tenders
16.02.2013, Date of Receipt of tenders 16.02.2013,
Date of work order 21.02.2013, Date of completion
as per PC-I 13.05.2015, Anticipated date of
completion 30.06.2019, No. of Beneficiary - 69380
Person, Funds Release on 20-07-2018 Work is in
progress.
529 2132
Provision and Installation of six (06) Water
Purification Plants at Matotli Qaisarpur, Shah Mosa
Shah Pipulwala, Basti Mahram Rukn Hatti, Chak
No.13- Faiz, Chak Sardarpur & Basti Nawan
Shehar, Tehsil Shujabad, District Multan
MultanOn-going
Schemes10.722 4.461 2.087 1.007 0.486 48% 46%
1. Date of AA 05.12.2016 2. Date of T.S - 3. Dated
of Prequalification - 4. Date of invitation of tender
01.02.2017 5. Date of Receipt of tenders
03.02.2017 6. Date of work order 11.02.2017 7.
Date of Completion as per PC-l 10.06.2017 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018. 24.01.2019 10. No.
of beneficiaries=111527 persons. Scheme
completed in saving. Rs 0.521 million proposed for
re-appropriation.
530 2133Rehabilitation of water Supply and Sewerage
Schemes in Tulamba City.Khanewal
On-going
Schemes106.963 68.841 6.667 5.000 4.519 90% 69%
1. Date of A.A: 17.09.2015 2. Date of T.S:
09.11.2015. 3. Date of Pre-Qualification: 18.01.2016
4. Date of Invitation of Tender: 16.02.2016 5. Date
of Receipt of Tender: 17.02-2016 6. Date of Work
order: 05.03.2016 7. Date of Completion as per PC-
I: 16-09-2017 8. Anticipated Date of completion: 30-
06-2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ---- 11 No.
of beneficiaries 53394Persons Work is in progress.
531 2134Urban water Supply & Sewerage Scheme
Khanewal CityKhanewal
On-going
Schemes191.232 147.091 14.714 11.036 10.971 99% 83%
1. Date of A.A: 05.09.2014 2. Date of T.S:
28.10.2014 3. Date of Pre-Qualification: 18.12.2014
4. Date of Invitation of Tender: 19.01.2015 5. Date
of Receipt of Tender: 20.01.2015 6. Date of Work
order: 18-02-2015 7. Date of Completion as per PC-
I: 04-09-2016 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: -------- 11
No. of beneficiaries 358569 Persons Work is in
progress.
532 2135Comprehensive water Supply & Sewerage
Scheme for Luddan City District Vehari.Vehari
On-going
Schemes99.982 78.470 6.970 5.228 3.885 74% 82%
1. Date of A.A: 11.01.2016. 2. Date of T.S:
25.02.2016 3. Date of Pre-Qualification: 11.04.2015
4. Date of Invitation of Tender: 24.03.2016 5. Date
of Receipt of Tender: 02.04.2016 6. Date of Work
order. 14.04.2016 7. Date of Completion as per PC-
I: 10.01.2018 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ----- 11. No.
of Beneficiary 20316 Persons Work is in progress.
533 2136Comprehensive water Supply & Sewerage
Scheme for Vehari city.Vehari
On-going
Schemes332.198 308.130 8.000 6.000 4.540 76% 94%
1. Date of A.A: 11.04.2016. 2. Date of T.S:
29.04.2016. 3. Date of Pre-Qualification:
11.04.2015. 4. Date of Invitation of Tender:
18.05.2016. 5. Date of Receipt of Tender:
28.05.2016. 6. Date of Award: 15.06.2016 G-I.
17.06.2016 G-II 7. Date of Completion as per PC-I:
14.06.2018 8. Anticipated Date of completion:
30.06.2018 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------ 11.
No. of Beneficiary= 140193 Persons Work is in
progress.
534 2137Comprehensive water Supply Scheme Taunsa
Sharif
Dera Ghazi
Khan
On-going
Schemes195.973 149.673 15.433 11.575 8.218 71% 81% "• Date of A.A = 12.12.2014
535 2138Rehabilitaion of Urban water Supply Scheme Fort
Minroe
Dera Ghazi
Khan
On-going
Schemes257.064 243.790 4.397 3.298 1.154 35% 95% "• Date of A.A =01.04.2015
536 2139Comprehensive Extension/Rehab. of Urban water
Supply Scheme Rojhan and adjoining abadiesRajanpur
On-going
Schemes49.569 25.000 8.190 6.143 4.095 67% 59% "• Date of A.A = 22.09.2016
537 2140Enhancement of Supply of Water for Rojhan City
District RajanpurRajanpur
On-going
Schemes30.000 20.000 3.333 2.500 1.667 67% 72% "• Date of A.A = 22.09.2016
538 2141Urban water Supply
Scheme,Muzaffargarh(Ammended) (PSDP)Muzaffargarh
On-going
Schemes419.689 398.484 4.110 3.083 2.054 67% 95% "• Date of A.A 10.11.2008
539 2142Rehabilitation and Agumentation of water Supply
Scheme, BahawalpurBahawalpur
On-going
Schemes282.533 254.014 3.805 1.654 0.700 42% 90%
Date of AA :29-11-2006. Date of TS :08-01-2007.
Date of RAA: 17-04-2014. Date of RTS. 17-04-
2014. Date of receipt of tender.14-02-2007. Date of
work order:17-03-2007. Date of completion as per
agreement 16-03-2008.Anticipated date of
completion 30-06-2019.Date of receipt of funds by
F.D 20.07.2018 & 11.01.2019.Funds Rs.1.200
million surrendered vide Chief Engineer(S),PHED
Lahore No.72-78/B(4) dated 10.01.2019 Three out
of four portions are completed and handed over to
TMA on 30-04-2014. Balance one portion at trust
colony, Model Town-B is under test operation.
540 2143 Urban water Supply Scheme for Hasilpur BahawalpurOn-going
Schemes100.000 76.466 7.844 5.883 3.900 66% 80%
Date of AA(DDWP)=24-10-2016. Date of TS=19-01-
2017. Prequalification of the contractors=05-01-
2017. Date of receipt of tender 27-02-2017 . Date of
award=03-03-2017. Date of completion. 02-03-2018.
Expected date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
541 2144
water Supply Scheme of Chak Sarkari and
Adjoining Abadies Tehsil Minchinabad District
Bahawalnagar
BahawalnagarOn-going
Schemes10.827 9.283 1.544 1.158 1.060 92% 96%
Date of AA. 08.08.2016. Date of T.S. 27.09.2016.
Date of receipt of tender 02.11.2016. Date of award.
30.11.2016. Date of completion 29.07.2017.
Anticipated date of completion 30-06-2019. Funds
released by FD on 12-11-2018 & 11.01.2019.Work
is in progress.
542 2145Water Supply Scheme Doonga Boonga, District
Bahawalnagar.Bahawalnagar
On-going
Schemes11.168 0.915 3.418 0.891 0.820 92% 16%
Date of AA 09.03.2010. Date of T.S 13.03.2010.
Date of award 14.05.2010. Date of completion
13.05.2011. Anticipated date of completion 30-04-
2019. Scheme remained unfunded during 2011-12.
Funds released on 20-07-2018 & 11.01.2019.
Scheme completed in saving. Excess funds
Rs.1.673 million surrendered dated 19.10.2018.
543 2146Replacement & Up-Gradation of Urban Water
Supply Scheme Bahawalnagr Bahawalnagar
On-going
Schemes214.155 211.310 0.947 0.441 0.441 100% 99%
Date of AA 11.08.2009. Date of T.S 31.10.2009.
Date of award 13.01.2010. Date of completion
30.06.2014. Scheme remained unfunded during
2013.14. Date of receipt of funds by F.D.
20.07.2018 & 11.01.2019. Scheme completed in
saving. Excess funds Rs.0.269 million surrendered
dated 19.10.2018.
544 2147 water Supply Scheme Sadiqabad, Tehsil
Sadiqabad, District R.Y. Khan.
Rahim Yar
Khan
On-going
Schemes692.527 454.150 67.779 50.834 40.405 79% 71%
A.A issued on 12-05-2014. .Date of T.S. 26-05-
2014. .Date of prequalification=21-07-2014.Date of
receipt of tenders = 22-12-2014. .Date of work
order= 03-01-2015..Date of completion as per
agreement 30.06.17.Anticipated date of completion
30.06.2019.No. of beneficiaries=405864
persons.Date of receipt of funds by F.D. 20.07.2018
& 11.01.2019. Work is in progress.
545 2148
Urban Water Supply Scheme Bismillah Town,
Thalli Road, Near Madrassa Kulyat ul Islam City
Rahim Yaar Khan
Rahim Yar
Khan
On-going
Schemes30.000 9.949 6.667 5.000 3.760 75% 46%
Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.
.Date of receipt of Tender: 07.09.2017..Date of
award: 31.10.2017..Date of completion:
31.1.2018..Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
546 2149Const. of Water Supply Scheme Tranda Sway,
R.Y.Khan.
Rahim Yar
Khan
On-going
Schemes2.610 0.603 0.669 0.252 0.252 100% 33%
Date of AA 18.08.2015..Date of T.S 14.09.2015.
.Date of award 07.01.2016..Date of completion
30.06.2016..Scheme remained unfunded during
2016-17..2018. Date of receipt of funds by F.D.
20.07.2018 & 11.01.2019. Scheme completed & put
in to operation.
547 2150Urban Sewerage / Drainage & PCC for Fateh Jang
City, Tehsil Fateh Jhang, District attock.Attock
On-going
Schemes99.948 80.231 5.341 5.006 3.671 73% 84%
A.A Date 09.01.2016.T.S Date 22.01.2016.Date of
Start of Scheme 09.03.2016.Date of Completion of
Scheme 30.06.2019.Work is in progress.
548 2151Urban Sewerage / drainage scheme for Hassan
Abdal City, Hassan Abdal, District attock Attock
On-going
Schemes195.317 167.071 8.336 7.232 5.148 71% 88%
A.A Date 28.08.2014.T.S Date 01.09.2014.Date of
Start of Scheme 26.01.2015.Date of Completion of
Scheme 30.06.2019.ork is in progress.
549 2152
Providing / laying of Sewerage, Construction /
Rehabilitation of storm water channel in Choa
Saiden Shah District Chakwal (Phase-I) (3rd
Revised)
ChakwalOn-going
Schemes239.300 225.507 2.429 1.822 1.215 67% 95%
Date of A.A 29.03.2016 (2nd Rev). Date of T.S
07.04.2016 (Rev).Date of Start 21.02.2014.Date of
completion 30.06.2019.Date of scheme almost
completed only contractor liabilities are to be clear.
550 2153 Urban Sewerage Scheme, Talagang City. ChakwalOn-going
Schemes99.667 80.853 5.067 2.800 1.530 55% 83%
Date of A.A 22.01.2015 (3rd Rev).Date of T.S
06.02.2015.Date of Start 13.04.2015.Date of
completion 30.06.2019.Work is in progress.
551 2154 Construction of Sewerage and Drianage Scheme
Sohawa CityJhelum
On-going
Schemes30.000 17.456 4.167 3.125 2.084 67% 65%
Date of A.A 26-08-2016.Date of T.S 30-09-
2016.Work awarded on 24-01-2017.Work in
progress
552 2155Urban Sewerage Scheme Jhelum with Treatment
Plant District JhelumJhelum
On-going
Schemes539.592 382.102 33.333 25.000 16.667 67% 74%
"Date of A.A .14-09-2009.Date of Revise A.A 29-03-
2016.Date of T.S 24-10-2009.Date of Revis T.S 31-
05-2016.Date of Commencement 17-08-2016.Date
of Completion 15-08-2018.Scheme has been
Revised and Administratively approved vide.
No.SO(PH-S)9-16/2015 (Jhelum)
553 2156Comprehensive Urban Sewerage Scheme Bhalwal
ColoniesSargodha
On-going
Schemes232.641 216.687 4.972 1.757 0.513 29% 93%
Date of A.A 25.06.2009, Revised Date of A.A
31.01.2014, 2nd Revised Date of A.A 19.09.2016,
Date of T.S 29.06.2009, Date of 2nd Revised T.S
30.09.2016, Date of Award 24.11.2009 &
04.12.2009, Scheduled date of Completion on
12.2010, Revised date of Completion 30.06.2018,
Date of Commencement, 24.11.2009 & 04.12.2009,
Funds released on 30.07.2018, Funds on-lined on
30.07.2018.Scheme completed in saving,
operational and handed over to Municipal
Committee Bhalwal.
554 2157Rehabilitation of Sewerage Scheme Kot Momin
District Sargodha Sargodha
On-going
Schemes152.397 32.809 3.333 0.893 0.059 7% 22%
Date of A.A 27.08.2016, Date of Revised A.A
15.06.2017, Date of T.S 10.10.2016, Date of Award
16.11.2016, Scheduled date of Completion is
15.11.2017, Date of Commencement, 16.11.2016,
Funds released on 30.07.2018, Funds on-lined on
30.07.2018. Drain Type-I, II & III 4807-Rft,
constructed. Land acquisition for construction of
disposal works is in process.
555 2158 Construction of Sewerage PCC Soling Resoling
Bashir Colony Sargodha CitySargodha
On-going
Schemes5.177 4.283 0.298 0.224 0.224 100% 87%
Date of A.A 27.08.2016, Date of T.S 04.09.2016,
Date of Award 22.02.2017, Scheduled date of
Completion is 30.06.2018, Date of Commencement,
22.02.2017, Funds released on 30.07.2018, Funds
on-lined on 30.07.2018. RCC Sewer 12" to 24" i/d
1845-Rft laid, PCC Slab 2257-Cft laid. Work in
progress
556 2159Costruction of Sewerage / PCC / soling / Sullage
Carrier Mulsim Town, Usman Park, Shiraz Park, Sargodha
On-going
Schemes5.927 4.376 0.500 0.375 0.375 100% 80%
Date of A.A 27.08.2016, Date of T.S 04.09.2016,
Date of Award 22.02.2017, Scheduled date of
Completion is 30.06.2018, Date of Commencement,
22.02.2017, Funds released on 30.07.2018, Funds
on-lined on 30.07.2018. Sullage Carrier 1653-Rft
constructed Soling 1639-Cft laid. RCC Sewer 12" i/d
961-Rft laid Work in progress
557 2160 Construction of Sewerage PCC Soling in Nawab
Colony Aziz Colony and Ghani Park Sargodha CitySargodha
On-going
Schemes5.430 4.789 0.214 0.161 0.161 100% 91%
Date of A.A 27.08.2016, Date of T.S 04.09.2016,
Date of Award 22.02.2017, Scheduled date of
Completion is 30.06.2018, Date of Commencement,
22.02.2017, Funds released on 30.07.2018, Funds
on-lined on 30.07.2018. RCC Sewer 12" i/d 1504-Rft
laid, PCC Slab 11550-Cft laid. Work in progress
558 2161Urban Drainage / PCC Flooring Scheme Miani
District SargodhaSargodha
On-going
Schemes93.181 35.964 5.000 3.750 3.750 100% 43%
Date of A.A 27.08.2016, Date of T.S 28.10.2016,
Date of Award 14.02.2017, Scheduled date of
Completion on 13.02.2018, Date of
Commencement, 14.02.2017, Funds released on
30.07.2018, Funds on-lined on 30.07.2018. 01-No.
Collecting tank completed, Sullage Carrier 23424-
Rft & Drain 2546-Rft constructed. P.C.C 27147-Cft
& Tuff Tile 22857-Sft laid Work in progress.
559 2162
Urban Sewerage Scheme for (Islam Pura, Zafar
Colony, Qartaba Town, Jauhar Colony, Sultan
Town, Shirazi park, Mujhid Colony, Ali Town,
Gilwala Including Adjacent Colonies) & Abadies of
(Yousaf park, Aziz Colony, Bashir Colony, Nawab
Colony
SargodhaOn-going
Schemes389.887 213.660 16.667 12.500 12.500 100% 58%
Date of A.A 09.06.2015, Date of T.S 17.06.2015,
Date of Award 31.07.2015, Scheduled date of
Completion is 30.07.2017, Date of Commencement,
31.07.2015, Funds released on 30.07.2018, Funds
on-lined on 30.07.2018.02-No. screening chamber,
collecting tank, pumping chamber 90% completed.
08-Sets Pumping Machinery out of 14-sets & 02-
Sets Generator arranged at site. RCC Sewer 1958-
Rft laid. RCC Box Channel 9139-Rft constructed.
Work in progress.
560 2163Sewerage and Drainage Scheme at Chak No.60
Shamali Khizarabad Ghosia Mehria ColonySargodha
On-going
Schemes60.000 49.976 3.334 2.501 2.500 100% 87%
Date of A.A 25.08.2015, Date of T.S 14.10.2015,
Date of Award 15.01.2016, Scheduled date of
Completion on 30.06.2017, Date of
Commencement, 15.01.2016, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.Drain
34406-Rft & Sullage carrier 8212-Rft constructed,
Soling 4484-Cft & PCC Slab 114865-Cft laid. work
in progress.
561 2164
Rural Drainage Scheme U.C Bhabra, U.C Halal
Pur, U.C Takhat Hazara and Adjoining Abadies
Tehsil Kot Momin District Sargodha
SargodhaOn-going
Schemes10.000 4.985 1.667 1.250 0.968 77% 60%
"Date of A.A 02.01.2018, Date of T.S 13.02.2018,
Date of Award 20.03.2018, Scheduled date of
Completion on 30.06.2019, Date of
Commencement, 20.03.2018, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
562 2165
Rural Drainage Scheme U.C Mouzamabd, U.C
Jalla Makhdoom, U.C Mateela including Adjoining
Abadies Tehsil Kot Momin District Sargodha
SargodhaOn-going
Schemes10.000 5.000 1.667 1.251 0.946 76% 59%
"Date of A.A 02.01.2018, Date of T.S 13.02.2018,
Date of Award 24.03.2018, Scheduled date of
Completion on 30.06.2019, Date of
Commencement, 24.03.2018, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
563 2166
Rural Drainage Scheme U.C Ghula Pur, U.C Chak
No.11/SB, U.C Garhi Kala and Adjoining Abadies
Tehsil Kot Momin District Sargodha
SargodhaOn-going
Schemes10.000 4.989 1.667 1.250 1.021 82% 60%
"Date of A.A 02.01.2018, Date of T.S 13.02.2018,
Date of Award 17.03.2018, Scheduled date of
Completion on 30.06.2019, Date of
Commencement, 17.03.2018, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
564 2167
Rural Drainage Scheme U.C Mela, U.C Naseer
Pur Kalan, U.C Mustafa Abad and Adjoining
Abadies Tehsil Kot Momin District Sargodha
SargodhaOn-going
Schemes10.000 4.957 1.667 1.250 1.159 93% 61%
"Date of A.A 02.01.2018, Date of T.S 13.02.2018,
Date of Award 20.03.2018, Scheduled date of
Completion on 30.06.2019, Date of
Commencement, 20.03.2018, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
565 2168
Rural Drainage Scheme U.C Dodha, U.C Gurna,
U.C Jan Muhammad Wala, U.C Laksian, U.C
Miana Kot and Adjoining Abadies Tehsil Kot
Momin District Sargodha
SargodhaOn-going
Schemes10.000 4.989 1.667 1.251 0.981 78% 60%
"Date of A.A 02.01.2018, Date of T.S 13.02.2018,
Date of Award 20.03.2018, Scheduled date of
Completion on 30.06.2019, Date of
Commencement, 20.03.2018, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
566 2169
Rural Drainage Scheme U.C Bucha Kalan, U.C
Wan Miana, U.C Midh Ranjha and Adjoining
Abadies Tehsil Kot Momin District Sargodha
SargodhaOn-going
Schemes10.000 4.984 1.667 1.250 1.155 92% 61%
"Date of A.A 02.01.2018, Date of T.S 13.02.2018,
Date of Award 20.03.2018, Scheduled date of
Completion on 30.06.2019, Date of
Commencement, 20.03.2018, Funds released on
30.07.2018, Funds on-lined on 30.07.2018.
567 2170Urban Sewerage / Drainag Scheme, Kamar
Mushani, Mianwali.Mianwali
On-going
Schemes190.611 117.953 16.667 12.500 8.320 67% 66%
Date of A.A. 05-09-2014, Date of T.S.03-10-2014,
Date of Start of Work,08-11-2014, , Remarks. RCC
Sewer=9" i/d=13629 /15205, 12"i/d= 3959/4960,
15"i/d= 8037/8695, 18"i/d= 3678/3675,
21"i/d=184/200, 24"i/d= 485/500, 27"i/d= 585/600,
30"i/d= 1106/1250, 33"i/d= 3232/3330, Screening
Chamber=1/1, Collecting Tank 25'dia= 2/2,
P/Machinery=0/4, Suction Delivery=1/1, Discharge
Sump=1/1, Generator Room=1/1, Staff
Quarter=1/1, Generator Set=1/1, Boundary
Wall=1/1, S/Carrier= 3120/4675, Out fall
Structure=0/1, S/Drain= 14933/51760, PCC Slab=
174131/294164, Electric T/Line=0/1. Work is in
progress.
568 2171Provision of PCC Slab and Sewerage Scheme in
Municipal Committee Dullay wala Bhakkar
On-going
Schemes68.340 48.098 3.333 2.500 2.500 100% 74%
Date of A.A 27.08.2016 Date of T.S 30.09.2016
Date of Commencement 28.11.2016 Date of
completion 30.06.2020
569 2172Urban Sewerage/Drainage scheme, PCC Slab &
Brick Pavement in Bhakkar CityBhakkar
On-going
Schemes833.933 39.633 50.000 37.500 25.000 67% 8%
Date of A.A 15.08.2017 Date of Amended A.A
16.12.2017 Date of T.S 07.02.2018 Date of
commencement 24.03.2018 Date of completion
30.06.2021 Work at Disposal Station is in progress.
Payment for land acquisition has been made. Target
will be acheived in the coming month.
570 2173Provision of Sewerage in Tandlianwala City District
Faisalabad Phase 1Faisalabad
On-going
Schemes100.000 69.988 9.366 7.025 4.683 67% 75%
Date of A.A 20-10-2016. Date of T.S.31-10-2016.
Work order issued on 17-12-2016. Work is in
progress. Funds released on 03.08.2018 & 24.1.19
571 2174Construction of Carpet Road (2200 feet) at Chak
No. 353/GB, District FaisalabadFaisalabad
On-going
Schemes4.000 1.000 1.000 0.750 0.750 100% 44% Funds transfer to xen Highway Divison Faisalabad.
572 2175Construction of Boundary Wall of at Football
Ground at Chak No.144/GB District Faisalabad.Faisalabad
On-going
Schemes1.500 0.500 1.000 0.750 0.750 100% 83% Funds transfer to xen Building Divison Faisalabad.
573 2176
Construction of Boundary Wall of Graveyard at
Chak No. 630/GB Abadi Rairoo, District
Faisalabad.
FaisalabadOn-going
Schemes2.099 0.500 1.000 0.750 0.750 100% 60% Funds transfer to xen Building Divison Faisalabad.
574 2177Provision of Soling /Drainage at Chak No.568/GB
Abadi Ahmad Khan District Faisalabad.Faisalabad
On-going
Schemes2.000 0.485 1.515 1.136 0.700 62% 59%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. work is in
progress.Funds released on 23.11.2018 & 24.1.19
575 2178Provision of Soling /Drainage at Abadi Bahadur
Khan District Faisalabad.Faisalabad
On-going
Schemes3.000 0.997 1.000 0.000 0.000 #DIV/0! 33%
AA issued on 15.11.2017. Tenders received on
28.11.2017. Funds received on 27-01-2018. Work
order issued on 13.12.2017. work is in progress.
Funds not yet been relased uptill now.
576 2179Provision of Soling /Drainage at UC- 51 District
Faisalabad.Faisalabad
On-going
Schemes1.000 0.499 0.501 0.376 0.250 66% 75%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. work is in
progress.Funds released on 23.11.2018 & 24.1.19
577 2180Construction of TST Road 12 feet wide4 at Abadi
Hayyat Ullah, District Faisalabad.Faisalabad
On-going
Schemes5.000 1.000 1.000 0.750 0.750 100% 35% Funds transferred to XEN High Way Division FSD.
578 2181Provision Main Drainage at UC 35 Chak
No.119/GB, District Faisalabad.Faisalabad
On-going
Schemes5.000 0.998 1.000 0.750 0.490 65% 30%
AA issued on 15.11.2017. Funds received on 23-11-
2018. Work order issued on 13.12.2017. work is in
progress.Funds released on 23.11.2018 & 24.1.19
579 2182Repair of Road (4400 feet) 01-KM at Bhagi Dhal to
Purana Wasiran, District Faisalabad.Faisalabad
On-going
Schemes3.000 0.600 1.000 0.750 0.750 100% 45% Funds transfer to xen Highway Divison Faisalabad.
580 2183Construction of TST Road at Chak No.119/GB,
District Faisalabad.Faisalabad
On-going
Schemes6.000 1.000 1.000 0.750 0.750 100% 29% Funds transfer to xen Highway Divison Faisalabad.
581 2184
Rehabilitation / Carpeting of Road (Length 4.00
KM) at Lahore Road Pull Sal to Dulchian Road to
Daand Gali, District Faisalabad.
FaisalabadOn-going
Schemes21.715 5.000 1.000 0.750 0.750 100% 26% Funds transfer to xen Highway Divison Faisalabad.
582 2185Comprehensive Sewerage/ Drainage scheme AP
Sial (Urban)Jhang
On-going
Schemes100.000 30.000 6.667 5.000 4.010 80% 34%
Date of A.A 20.10.2016 Date of T.S 24.11.2016
Date of Invitation of tenders 15.12.2016. Date of
Receipt of tender 24.12.2016 Date of work order
28.12.2016 Date of Completion As per PC-I
19.10.2019 Anticipated date of completion.
27.12.2019 No of Baneficiary 12731-Persons
Agreement Amount 96.709-Million Work is in
progress.
583 2186
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 1,2,3,4,5&6 and adjoining
abadies urban area Jhang
JhangOn-going
Schemes6.000 4.000 0.667 0.500 0.390 78% 73%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
07.09.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
06.07.2018 No of Baneficiary 12731-Persons
Agreement Amount 4.961-Million Work is in
progress.
584 2187
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 13,14,15,16,17 & 18 and
adjoining abadies urban area Jhang
JhangOn-going
Schemes6.000 3.900 0.667 0.500 0.401 80% 72%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
28.09.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
06.07.2018 No of Baneficiary 12709-Persons
Agreement Amount 5.006-Million Work is in
progress.
585 2188
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 19,20,21,22,23 & 24 and
adjoining abadies urban area Jhang
JhangOn-going
Schemes6.000 4.000 0.667 0.500 0.395 79% 73%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
07.09.2017 Date of work order 07.09.2017 Date of
Completion As per PC-I 19.10.2018 No of
Baneficiary 12709-Persons Agreement Amount
5.491-Million Work is in progress.
586 2189
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 25,26,27,28,29 & 30 and
adjoining abadies urban area Jhang
JhangOn-going
Schemes6.000 3.998 0.667 0.500 0.405 81% 73%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
07.09.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
06.07.2018 No of Baneficiary 112173-Persons
Agreement Amount 5.494-Million Work is in
progress.
587 2190
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 31,32,33,34,35 & 36 and
adjoining abadies urban area Jhang
JhangOn-going
Schemes6.000 3.993 0.667 0.500 0.398 80% 73%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
08.08.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
07.05.2018 No of Baneficiary 11596-Persons
Agreement Amount 4.920-Million Work is in
progress.
588 2191
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 37,38,39,40,41,42, & 43 and
adjoining abadies urban area Jhang
JhangOn-going
Schemes7.000 5.000 0.667 0.500 0.418 84% 77%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
07.09.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
06.07.2018 No of Baneficiary 13260-Persons
Agreement Amount 6.191-Million Work is in
progress.
589 2192
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 44,45,46,47,48,49, & 50 and
adjoining abadies urban area Jhang
JhangOn-going
Schemes7.000 4.963 0.667 0.500 0.412 82% 77%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
08.08.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
07.05.2018 No of Baneficiary 13015-Persons
Agreement Amount 6.084-Million Work is in
progress.
590 2193
Construction of Sewerage, PCC Slab, Drain &
Soling at Ward NO. 7,8,9,10,11&12 and adjoining
abadies urban area Jhang
JhangOn-going
Schemes6.000 3.906 0.667 0.500 0.415 83% 72%
Date of A.A 25.03.2017 Date of T.S 28.03.2017
Date of Invitation of tenders 18.04.2017. Date of
Receipt of tender 20.04.2017 Date of work order
07.09.2017 Date of Completion As per PC-I
19.10.2018 Anticipated date of completion.
06.07.2018 No of Baneficiary 12768-Persons
Agreement Amount 5.416-Million Work is in
progress.
591 2194Extension Rehabilitation of Urban Sewerage
Scheme Karnalia City Phase IIToba Tek Singh
On-going
Schemes488.756 239.700 33.333 25.000 23.000 92% 54%
1-Date of A.A 12.11.20152- Date of T.S
25.02.20163-Date of Prequalification -07.03.20164-
Date of invitation of tenders 18.03.20165- Date of
Receipt of tenders 26.03.20166- Date of work odder
-29.04.20167- Date of completion as per PC-I
11.11.20188- Anticipated date of completion
11.11.2018 9- No. of Beneficiary - 306625 Person10-
Funds Released by F.D 03.08.2018 & 24.01.2019
11-Re-appropriation of funds(+/-) Work in progress.
592 2195Extension/Rehabilitation of Urban Sewerage
Scheme Gojra Toba Tek Singh
On-going
Schemes400.000 224.900 16.667 12.500 10.000 80% 59%
1-Date of A.A 12.11.20152- Date of T.S
26.02.20163-Date of Prequalification -07.03.20154-
Date of invitation of tenders 18.03.20165- Date of
Receipt of tenders 26.03.20166- Date of work odder
-18.04.20167- Date of completion as per PC-I
11.11.20188- Anticipated date of completion
11.11.20189- No. of Beneficiary -393651 Person 10-
Funds Released by F.D 03.08.2018 & 24.01.2019.
11-Re-appropriation of funds(+/-) Work in progress.
593 2196 Urban Sewerage and Drainage Scheme Pir Mehal Toba Tek SinghOn-going
Schemes290.000 230.000 6.667 5.000 5.000 100% 81%
1-Date of A.A 16.10.20142- Date of T.S
03.12.20143-Date of Prequalification 08.12.20144-
Date of invitation of tenders 08.12.20145- Date of
Receipt of tenders 23.12.20146- Date of work order
31.12.20147- Date of Completion as per PC-I
15.10.20178- Anticipated date of completion
30.12.2018 9- No. of Beneficiary - 139496 Person
10-Funds Released by F.D 03.08.2018 1&
24.01.2019 1-Re-appropriation of funds(+/-) Work in
progress.
594 2197Improvement of Street / Roads of Rajana Town,
District T.T SinghToba Tek Singh
On-going
Schemes25.000 7.939 1.667 1.250 0.900 72% 35%
1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
595 2198Provision of Laying Tuff Tile, Sewerage and
Nullahs in Gojra, District T.T.SinghToba Tek Singh
On-going
Schemes150.000 75.000 8.333 6.250 4.167 67% 53%
1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-). Work in progress.
596 2199 Construction of Sewerage Drainage Tuff tiles in
Noshera VirkanGujranwala
On-going
Schemes208.986 25.000 3.333 2.500 1.667 67% 13% Work in progress
597 2200Const of Sewerage Drainage PCC Scheme Sodhra
Talwara Tehsil WazirabadGujranwala
On-going
Schemes120.754 84.455 5.306 3.980 2.653 67% 72% Work in progress
598 2201
Provision of Sewerage & water Supply Scheme at
Ghakhar & Ladhaywala, District Gujranwala
(Revised)
GujranwalaOn-going
Schemes199.871 130.786 30.000 22.500 15.000 67% 73% Work in progress
599 2202
Sewerage / Drainage & PCC / RCC Scheme at
Rahwali including Adjoining Abadies etc,
Gujranwala.
GujranwalaOn-going
Schemes392.400 100.600 20.000 21.218 16.218 76% 30% Work in progress.
600 2203
Provision of Drainage / PCC Scheme at Tehsil
Noshera Virkan & UC Sharan Kalan, District
Gujrnawala
GujranwalaOn-going
Schemes77.000 16.846 3.333 2.500 1.667 67% 24% Work in progress.
601 2204Provision of Sanitation / Drainage in City Pindi
BhattianHafizabad
On-going
Schemes167.781 109.933 10.000 6.300 3.800 60% 68%
A.A 167.781 Date 04/04/2016 T.S. 167.77 date 16-
05-2016 work in progress Fund release but not yet
online.
602 2205Provision of Sanitation facilities in City Sukhike
MandiHafizabad
On-going
Schemes141.332 129.643 3.796 2.847 1.897 67% 93%
The work was alloted to the contractor on dt: 26-11-
2016 and contractor started the work at site .A.A
141.240 Date 06/09/2016 T.S. 142.374 date 30-09-
2016 Drain 140910 Rft, Sullage Carrier /storm water
1.5x1.5=2225 Rft 2.0x2.0=1350 Rft 2.0x2.5=2350
Rft 3.0x3.0=5878 Rft Tuff tile 60mm thick=17292
Sft 80mm thick =3200 Sft Brick Pavement/Soling =
37645 Cft, PCC 3" thick= 69726 Cft,4" thcik=56945
Cft,thick=82872 Cft, work in progress.Fund release
but not yet online.
603 2206 Urban Drainage Scheme Jalapur Bhattian HafizabadOn-going
Schemes96.640 84.870 3.884 2.913 1.940 67% 90%
The work was alloted to the contractor on dt: 26-11-
2016 and contractor started the work at site .A.A
141.240 Date 06/09/2016 T.S. 142.374 date 30-09-
2016 Drain 140910 Rft,Sullage Carrier /storm Fund
release but not yet online.
604 2207Urban Sewerage / Drianage Scheme Eastern Side
Ghari Awan & Allied Abadies Hafizabad CityHafizabad
On-going
Schemes219.535 141.081 10.000 7.500 5.000 67% 67% work in progress Fund release but not yet online.
605 2208 Construction of Two Pumps Station at Old
G.T.Road Drain Gujrat.Gujrat
On-going
Schemes108.440 66.578 13.928 10.446 6.964 67% 68%
R.A.A Date =3.05.2017R.T.S date=29.9.2017.1 Nos
Screening Chamber, 1 Nos Collecting Tank 20' Dia
6set Machinery, Force main pipe i/d Dia 10"=50
Rft,12"=100 Rft, 16"=3300 Rft, 18"=400 Rft Drain
type-I=2862 Rft Sullage Carrier= 2500 Rft RCC
Sewer 15'=300 Rft,18"=346 Rft, 24"=1664 Rft
PCC=7568 Cft .work in progress
606 2209 Sewerage & water Supply Tank for Bhiki SharifMandi
Bahauddin
On-going
Schemes116.314 90.745 8.522 6.392 4.261 67% 82%
* A.A Date. 09.10.2014* T.S Date. 22.12.2014 *
Start Date 16.02.2015* Completion date
30.06.2019. * Work in progress.
607 2210Sewerage / Drainage Scheme Malikwal City,
Distt.M.B.Din
Mandi
Bahauddin
On-going
Schemes237.200 62.105 8.333 5.350 3.267 61% 28%
* A.A Date. 06.01.2016* T.S Date. 15.01.2016* Start
Date 11.03.2016* Completion date 10.03.2019.*
Work in progress.
608 2211Urban Sewerage/ Drainage PCC and Tuff Tiles in
City Phalia Tehsil Phalia District M.B.Din
Mandi
Bahauddin
On-going
Schemes270.500 27.095 10.000 7.500 5.000 67% 12%
* A.A Date. 06.09.2017* T.S Date. 24.10.2017* Start
Date. 07.01.2018* Completion date
06.01.2021.Work in progress.
609 2212Provision of Sewerage/PCC Streets/ Drain/Tuff
Tiles/Park and Janazgah District M.B.Din
Mandi
Bahauddin
On-going
Schemes75.000 55.000 6.667 5.000 3.337 67% 78%
* A.A Date. 25.08.2017* T.S Date. 06.09.2017* Start
Date. 06.01.2018* Completion date 05.01.2020*
Work in progress.
610 2213
Provision of PCC / Soling / Nullah / Street Scheme
at Adalat Garah Bashamula, Muzaffarpura,
Dhanay, phabarainawala, Gujayanwala, Ravail
pura, Stabgary, Burj / Butter etc.,Teshil & District
Sialkot
SialkotOn-going
Schemes200.000 25.000 3.333 2.500 1.667 67% 13% Work in progress.
611 2214Provision of Sewerage Drainage and and Tuff Tile
at Daska CitySialkot
On-going
Schemes100.000 30.000 3.333 2.500 1.667 67% 32% Work in progress.
612 2215
Construction of Street PCC / Tufff Tiles Drains &
Nullah Fazal Pura & adjoining Streets Sambrial
City
SialkotOn-going
Schemes80.000 49.845 3.333 2.500 1.667 67% 64% Work in progress.
613 2216
Construction of Street PCC / Tufff Tiles Drains &
Nullah in Mandi Samrial and old Sambrial Tehsil
Sambrial
SialkotOn-going
Schemes80.000 44.945 3.333 2.500 1.667 67% 58% Work in progress.
614 2217
Construction of Street PCC/Tuff Tiles Drains &
Nullah in Mohallah Rasoolpur & More Sambrial,
Tehsil Sambrial
SialkotOn-going
Schemes80.000 44.992 3.333 2.500 1.667 67% 58% Work in progress.
615 2218
Construction of Streets (Drains, PCC) Mohallah
Sharif Pur, Habib Pura, Bashir Pura, Nazir Abad
Colony and others.
SialkotOn-going
Schemes90.000 49.918 3.333 2.500 1.667 67% 57% Work in progress.
616 2219 Construction of Urban Drainage Scheme Pasrur
City, Tehsil Pasrur, District Sialkot.Sialkot
On-going
Schemes99.827 24.992 3.333 2.500 1.667 67% 27% Work in progress.
617 2220
Construction of Nallah Around Road from Uggoki
to Rai Pur Abba Baigowala Ganda Nallah Railway
Station etc. Tehsil Sambrial ,District Sialkot
SialkotOn-going
Schemes199.826 69.726 5.000 3.750 2.500 67% 36% Work in progress.
618 2221
Removal of ponds / construction of Pull and
establishment of Park at Moza Bahlor Tehsil
Pasrur, District Sialkot.
SialkotOn-going
Schemes36.043 20.643 5.133 1.283 0.000 0% 57% Scheme completed
619 2222Const of PCC / Tuff tiles of City Package Zafarwal
City Narowal
On-going
Schemes69.569 49.569 6.667 5.000 3.324 66% 76%
*Date of A.A 9.4.2016 *Date of T.S 19.4.2016 *Start
Date 6.6.2016 *Completion date 30.06.2019.Work in
progress.
620 2223Sewerage scheme for Talwandi Bhindran,
Narowal.Narowal
On-going
Schemes109.876 105.797 1.360 1.020 0.677 66% 97%
A.A Date.3.5.2014 T.S Date.23.5.2014 *Start Date
25.08.2014*Completion date 30.06.2019.Work in
progress. Fund not received on spending end yet.
621 2224
Provision of clean drinking water Sewerage system
PCC and allied facilities in Chung Mohlanwal
Manak
LahoreOn-going
Schemes200.742 171.650 9.697 11.073 8.649 78% 90%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
622 2225
Provision of clean drinking water, Sewerage
system, PCC and allied facilities in Babo Mehar
Town, Lidhar, Bedian Road and adjoining abadies
LahoreOn-going
Schemes200.012 171.650 9.454 7.091 4.727 67% 88%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
623 2226
Provision of clean drinking water, Sewerage
system, PCC and allied facilities in Jallo More,
Batapur
LahoreOn-going
Schemes509.268 219.523 26.667 20.000 13.334 67% 46% Work stopped due to awaiting funds.
624 2227PCC and drainage Scheme in UC 117 Mansoora
Lahore.Lahore
On-going
Schemes202.567 128.019 5.000 3.750 2.500 67% 64% Work stopped due to awaiting funds.
625 2228
Construction of PCC, Nallah at Maraka UC-122,
Shamke Bhattian, Chahram & mal, Manga Mandi
Sunder, Kot Fateh Muahammad Athul, District
Lahore
LahoreOn-going
Schemes24.200 7.634 5.522 2.642 1.261 48% 37%
Physically scheme is completed, balance funds are
required to clear the contractor's liability.
626 2229
Construction of PCC Sewerage & Drainage
System at UC-272 Raiwind Kalan & UC-273
Raiwind City, District Lahore
LahoreOn-going
Schemes8.000 5.581 0.806 0.202 0.000 0% 70% scheme completed
627 2230Katcha Storm / Sullage Water Channel in District
SheikhupuraSheikhupura
On-going
Schemes199.813 139.520 5.000 3.750 2.500 67% 71% Work in Progress
628 2231Provision of Sewerage Scheme Burjwala, Saleem
Kot, Housing Colony, City Sheikhupura Sheikhupura
On-going
Schemes174.527 165.000 3.176 2.382 1.588 67% 95% Work in Progress
629 2232Provision of Sewerage system in mohllah ghareeb
abad etc City Sheikhupura Sheikhupura
On-going
Schemes157.452 155.000 0.817 0.613 0.409 67% 99% Work in Progress
630 2233Provision of Open water Supply Scheme
Ferozwala.Sheikhupura
On-going
Schemes199.210 82.664 3.333 2.500 1.667 67% 42% Work in Progress
631 2234
Provision Of Sewerage and PCC Scheme Pir
Bahar Shah, Qazi Park Ramgarah & Purana
Shehar City Sheikhupura
SheikhupuraOn-going
Schemes175.000 95.000 3.333 2.500 1.667 67% 55% Work in Progress
632 2235Urban Sewerage / Drainage Scheme Sharqpur
Seikhupura , SharqpurSheikhupura
On-going
Schemes183.441 89.027 3.333 2.500 1.667 67% 49% Work in Progress
633 2236Urban Sewerage Scheme Ferozwala New Sewer
Lines District Sheikhupura Sheikhupura
On-going
Schemes199.330 184.330 5.000 3.750 2.500 67% 94% Work in Progress
634 2237Urban Drainage & PCC Scheme Northn Side of
Railway Track City SheikhupraSheikhupura
On-going
Schemes96.319 48.319 5.000 3.750 2.500 67% 53% Work in Progress
635 2238
Providing and laying of sewerage at Ghaloria
Colony Farooq Nagar Shah Colony District
Sheikhupura
SheikhupuraOn-going
Schemes97.683 47.683 5.000 3.750 2.500 67% 51% Work in Progress
636 2239Execution of Sanitation Sector Development
scheme Shah Kot City District Nankana Sahib Nankana Sahib
On-going
Schemes50.000 23.600 3.333 4.500 3.667 81% 55% Work is in progress.
637 2240
Const. of Storm Water Channel / Ext. &
Improvement Urban Sewerage / Drainage Scheme
Shahkot Phase-II
Nankana SahibOn-going
Schemes119.138 99.756 6.461 4.846 3.231 67% 86% Work is in progress.
638 2241Augmentation / Rehabilitation of Urban Sewerage
Scheme, Nankana SahibNankana Sahib
On-going
Schemes264.253 130.000 5.000 3.750 2.500 67% 50% Work is in progress.
639 2242
Construction of Sullage Carrier for Ultimate
Disposal of Phoolnagar City, Tehsil Pattoki, District
Kasur
KasurOn-going
Schemes337.971 18.614 20.000 15.000 10.000 67% 8% Work in Progress
640 2243Provision of Sewerage & Drainage System in
Chunian City, KasurKasur
On-going
Schemes99.011 76.401 20.000 16.520 11.520 70% 89% Work in Progress
641 2244 Urban Drainage Scheme Kasur city District kasur KasurOn-going
Schemes99.827 34.999 20.000 16.389 11.389 69% 46% Work in Progress
642 2245Urban Drainage, PCC & Brick Pavement scheme
Kasur city District KasurKasur
On-going
Schemes457.681 407.681 16.667 12.500 8.334 67% 91% Work in Progress
643 2246Urban PCC & Drainage Scheme Kot Radha
Kishan District Kasur.Kasur
On-going
Schemes112.887 104.597 2.758 0.690 0.000 0% 93% Work in Progress
644 2247Urban Sewerage Drainage Scheme, Pattoki
(Revised)Kasur
On-going
Schemes680.017 657.032 6.294 1.621 0.047 3% 97% Work in Progress
645 2248Sewerage Drainage Scheme Kangan Pur District
Kasur.Kasur
On-going
Schemes161.161 122.346 3.333 2.500 1.667 67% 77% Work in Progress
646 2249Drainage P.C.C. & Brick pavement in Mustafabad,
Kasur.Kasur
On-going
Schemes246.400 196.400 16.667 4.977 0.811 16% 80% Work in Progress
647 2250
Complete Repair and renovation of Sewerage
system including PCC, Drains, water channels,
soling, tuff tiles etc. in M.C. Mandi Ahmed Abad,
District Okara.
OkaraOn-going
Schemes184.048 172.023 4.006 3.005 1.926 64% 95%
Date of AA 03.03.2014, Date of TS 05.03.2014,
Date of Pre-qualification.05.05.2014, Date of
Receipt of Tenders,20.05.2014, Date of work Order.
30.05.2014, Date of completion As per PC-I.
30.06.2016, Anticipated date of
completion.30.06.2019, Projected Population 66950
Person, Funds Release on 20-07-2018 Release of
Funds 02.08.2017.
648 2251 Construction of Sewerage Scheme Renala Khurd
City, District Okara Okara
On-going
Schemes327.480 296.423 10.352 7.764 5.176 67% 92%
Date of AA 02.04.2014, Date of TS 14.04.2014,
Date of Pre-qualification.10.04.2014, Date of
Invitation of Tender 05.05.2014, Date of Receipt of
Tenders 05.05.2014, Date of work Order
13.05.2014, Date of completion As per PC-I.
30.06.2016., Anticipated date of
completion,30.06.2019, Funds Release on 20-07-
2018 Projected Population 119573 Person, Release
of Funds 02.08.2017.
649 2252 Sewerage Scheme Depal Pur City District Okara OkaraOn-going
Schemes300.355 269.408 3.620 2.715 1.810 67% 90%
Date of AA 09.04.2010 ( Original), Date of Revised
AA 31.10.2014 , Date of TS 18.08.2010 (Phase -I),
Date of Revised TS 05.03.2015 , Date of Pre-
qualification,20.03.2015, Date of Invitation of
Tender 09.05.2015, Date of Receipt of Tenders
10.05.2015, Date of work Order 20.06.2011 &
03.09.2015, Date of completion As per Revised PC-
I. 31.12.2017, Anticipated date of
completion,30.06.2019, Funds Release on 20-07-
2018 Projected Population 229210 Person,
650 2253 Sewerage Scheme Shergarh Renala Khurd Okara OkaraOn-going
Schemes99.224 94.810 1.424 1.068 0.841 79% 96%
Date of AA 16.05.2014, Date of TS 28.06.2014,
Date of Pre-qualification 17.06.2014, Date of
Invitation of Tender 30.06.2014, Date of Receipt of
Tenders 30.06.2014, Date of work Order
17.09.2014, Date of completion As per PC-
I.14.09.2016 , Anticipated date of
completion,30.06.2019, Funds Release on 20-07-
2018 Projected Population 26497 Person.
651 2254
Extension, Improvement Complete Repair,
Renovation of Sewerage and and Water Supply
System alongwith Provision of Strom Water
Channels, Street Lights and Tuff Tiles in Hujrah
Shah Muqeem, District Okara
OkaraOn-going
Schemes398.910 59.545 6.667 5.000 3.587 72% 16%
Date of A.A 30-11-2017 Date of T.S 24-01-2018
Date of Prequalification 13-09-2017 Date of
invitation of tenders 22-02-2018 Date of Receipt of
tenders 22-02-2018 Date of work order 22-03-2018
Date of completion as per PC-I 22-03-2021
Anticipated date of completion 30-06-2021 No. of
Beneficiary 47415 Person Work is in progress.
652 2255Rehabilitation/Augmentation of Sewerage System
at Harrappa CitySahiwal
On-going
Schemes78.583 56.389 7.398 5.549 5.000 90% 78%
Date of AA 13.10.2016 , Date of TS 07.12.2016,
Date of Pre-qualification 08.02.2017, Date of receipt
of tender 18.02.2017 , Date of Work Order
22.03.2017 , Date of completion as per PC-1
30.06.2018 , Date of completion as per agreement
30.06.2018, Anticipated date of completion
30.06.2019, Work in progress.
653 2256
Provision / Rehablitation / Improvement of water
Supply in Urban U/Cs-12 & 13 and Construction of
Drain, Tuff Tiles, Sewerage in Urban U/Cs-
23,24,26 & 41 Multan City
MultanOn-going
Schemes6.000 4.000 0.667 0.166 0.000 0% 67%
1.Date of AA 11.04.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 06.11.2017 7.Date
of Completion as per PC-l 05.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 4648 persons. Scheme completed.Rs
0.166 million proposed for re-appropriation.
654 2257Extension of Urban Sewerage Scheme Jalalpur
Pirwala, District Multan (Revised)Multan
On-going
Schemes196.830 158.627 12.289 9.217 6.145 67% 84%
1. Date of A.A. 15.01.2014 (21.04.2016) 2. Date of
T.S. 22.01.2014 (05.08.2016) 3. Date of
Prequalification 27.01.2014 4. Date of Invitation of
Tender 12.02.2014 5. Date of Receipt of Tenders
24.02.2014 6. Date of work order
10.03.2014/18.11.2016 7. Date of Completion as
per PC-l 14.01.2016 8. Anticipated date of
completion 30.06.2019 9. Date of released of funds
03.08.2018 24.01.2019 10. No. of beneficiaries=
170275 persons. Work is in progress.
655 2258Sewerage Water Disposal from North South
Shujabad City MultanMultan
On-going
Schemes145.222 118.112 8.989 2.247 0.000 0% 81%
1. Date of AA 26.08.2014. 2. Date of T.S
15.10.2014. 3. Dated of Prequalification 11.08.2014.
4. Date of invitation of tender 23.10.2014. 5. Date of
Receipt of tenders 24.10.2014. 6. Date of work
order 08.11.2014. 7. Date of Completion as per PC-l
25.08.2016 8. Anticipated date of completion
30.06.2019 9. Date of released of funds 03.08.2018.
24.01.2019 10. No. of beneficiaries=111527
persons. Scheme completed in saving and handed
over to TMA Shujabad.Rs 2.247 million proposed
for re-appropriation.
656 2259Rehabilitation / extension of Sewerage / drainage
system of Mian Channu City Khanewal
On-going
Schemes306.616 254.224 17.464 13.098 12.388 95% 87%
1. Date of A.A: 12.02.2015 2. Date of T.S:
05.03.2015. 3. Date of Pre-Qualification:
11.08.2014. 4. Date of Invitation of Tender:
23.10.2014. 5. Date of Receipt of Tender:
24.10.2014 6. Date of Work order: 05.11.2014 7.
Date of Completion as per PC-I: 25.08.2016 8.
Anticipated Date of completion: 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: -------- 11 No. of
beneficiaries 200428 Persons Work is in progress.
657 2260Revamping of Jahanian Sewerage System,
JahanianKhanewal
On-going
Schemes199.359 97.866 16.667 12.500 11.213 90% 55%
1. Date of A.A: 27.08.2016 2. Date of T.S:
25.10.2016 3. Date of Pre-Qualification: 26.10.2016
4. Date of Invitation of Tender: 03.12.2016 5. Date
of Receipt of Tender: 05.12.2016 6. Date of Work
order: 15.12.2016 7. Date of Completion as per PC-
I: 30.09.2019 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: -------- 11
No. of beneficiaries 65206Persons Work is in
progress.
658 2261Provision of Urban sewerage Scheme at Kabirwala
City, District Khanewal.Khanewal
On-going
Schemes99.676 49.676 10.000 7.500 6.719 90% 57%
1. Date of A.A: 18.11.2017 2. Date of T.S:
08.12.2017 3. Date of Pre-Qualification: 06.09.2017
4. Date of Invitation of Tender: 30.01.2018 5. Date
of Receipt of Tender: 31.01.2018 6. Date of Work
order: 10.02.2018 7. Date of Completion as per PC-
I: 31.03.2019 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: --------- 11
No. of beneficiaries 56299 Persons Work is in
progress.
659 2262Provision of drainage / Sewerage, soling & water
Supply in Municipal Area of Burewala City.Vehari
On-going
Schemes358.775 233.686 16.667 12.500 11.250 90% 68%
1. Date of A.A: 29.12.2014. 2. Date of T.S:
12.03.2015 3. Date of Pre-Qualification: 13.03.2015
4. Date of Invitation of Tender: 10.04.2015 5. Date
of receipt of Tender: 11.04.2015 6. Date of Award:
20.04.2015 7. Date of Completion as per PI:
28.12.2016 8. Anticipated Date of Complion:
30.06.2018 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ----- 11. No.
of Beneficiaries 226016 Persons. Work is in
progress.
660 2263
Comprehensive Sewerage / Drainage Scheme
Taunsa Sharif including Tuff Tilling of Streets -
InActive
Dera Ghazi
Khan
On-going
Schemes485.406 214.529 33.333 25.000 6.428 26% 46% • Date of A.A = 12.02.2015
661 2264
Construction of Nali Soling in UC Basti Jaam,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Ara Jafar,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Kotla Ahmad
Khan, District D.G. Khan.
Dera Ghazi
Khan
On-going
Schemes21.500 10.747 3.583 2.687 1.935 72% 59% "• Date of A.A = 04.10.2017
662 2265
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas Muza Chak Masso
U/C Nawan Shumali, Construction Of Nali
Soling,Tough Tiles Drainage,Culverts And Qulabas
U/C Jakhar Imam Shah, District D.G. Khan.
Dera Ghazi
Khan
On-going
Schemes6.000 2.973 1.000 0.750 0.548 73% 59% "• Date of A.A = 04.10.2017
663 2266
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Haji Kamand,
District D.G. Khan.
Dera Ghazi
Khan
On-going
Schemes9.000 4.442 1.500 1.125 0.844 75% 59% "• Date of A.A = 04.10.2017
664 2267
10930 Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Khan Pur
Janobi, Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Nawan
Shumali, Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C N
Dera Ghazi
Khan
On-going
Schemes33.700 16.843 5.617 4.213 2.991 71% 59% "• Date of A.A = 04.10.2017
665 2268
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Aali Wala,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Jalbani,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Basti Malana,
Dera Ghazi
Khan
On-going
Schemes52.000 25.955 8.667 6.500 4.875 75% 59% "• Date of A.A = 04.10.2017
666 2269
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Tibbi Kharak,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Chabri
Zareen, Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Kot,
Dera Ghazi
Khan
On-going
Schemes130.000 64.993 6.000 4.500 3.375 75% 53% "• Date of A.A = 04.10.2017
667 2270
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Darahma,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Samina,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Chorahatta,
Dist
Dera Ghazi
Khan
On-going
Schemes29.000 14.485 4.833 3.625 2.719 75% 59% "• Date of A.A = 04.10.2017
668 2271
Construction of Nali Soling V/C Aliwala C/O Fateh
Muhammad Bazgir, Construction of Nali Soling,
Tuff Tiles, Drainage, Culverts and Qulabas U/C
Mana Ahmadani, District D.G. Khan.
Dera Ghazi
Khan
On-going
Schemes10.000 4.978 1.667 1.250 0.888 71% 59% "• Date of A.A = 04.10.2017
669 2272
Construction of Nali Soling, Tuff Tiles, Drainage,
Culverts and Qulabas U/C Notak Mahmeed,
District D.G. Khan.
Dera Ghazi
Khan
On-going
Schemes11.000 5.474 1.833 1.375 1.045 76% 59% "• Date of A.A = 04.10.2017
670 2273
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Darkhast
Jamal Khan Darmiani, Construction Of Nali
Soling,Tough Tiles Drainage,Culverts And Qulabas
U/C Darkhast Jamal Khan Janobi, Construction Of
Nali Soling,Tough Tiles Drainage,
Dera Ghazi
Khan
On-going
Schemes10.000 5.000 1.667 1.250 0.938 75% 59% "• Date of A.A = 04.10.2017
671 2274
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Jhoke Utra,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Hazara,
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Haider
Quresh
Dera Ghazi
Khan
On-going
Schemes47.500 23.731 3.333 2.500 1.825 73% 54% "• Date of A.A = 04.10.2017
672 2275
Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Khan Pur
Janobi, Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C Nawan
Shumali, Construction Of Nali Soling,Tough Tiles
Drainage,Culverts And Qulabas U/C N
Dera Ghazi
Khan
On-going
Schemes40.000 20.000 1.000 3.334 2.809 84% 57% "• Date of A.A = 04.10.2017
673 2276
Construction of Urban Sewerage Drainage Earth
filling brick pavement and Tuff Tile scheme for
Rojhan
RajanpurOn-going
Schemes61.369 55.200 1.000 0.750 0.500 67% 91% " Date of A.A = 24.4.2015
674 2277
Urban drinage/Sewerage/tuff tile scheme in
Jampur City (replacement of outlived sewer and
new sewer system in Faisal Colony, Shah Jamal
Colony and Tattar Wala)
RajanpurOn-going
Schemes365.753 195.169 33.333 25.000 16.667 67% 58% "• Date of A.A = 23.12.2014
675 2278
Rural Drainage Sewerage PCC and Tuff Tile
flooring Rajan Pur City and Adjoining Abadies UC
Rajan Pur
RajanpurOn-going
Schemes40.500 25.600 4.967 3.725 2.484 67% 69% "• Date of A.A = 24.4.2015
676 2279
Construction of drain, brick pavement sullage
carrier culverts & tuff tile flooring scheme of fazilpur
tehsil & district rajanpur
RajanpurOn-going
Schemes50.000 25.000 8.333 6.250 0.000 0% 50% "• Date of A.A = 17.12.2014
677 2280Open Drainage & Tuff Tile Scheme in Remaining
Portion of Kot Addu City Muzaffargarh
On-going
Schemes49.850 32.404 5.815 4.361 2.908 67% 71% "• Date of A.A 22-09--2016
678 2281Sewerage System for Recep Tayyip Erdogan
Hospital Muzaffargarh Expansion ProjectMuzaffargarh
On-going
Schemes191.449 78.700 1.000 0.750 0.000 0% 41% Part-I is Completed
679 2282Comprehensive Sewerage Scheme alongwith Tuff
Tiles in City Chowk AzamLayyah
On-going
Schemes199.995 105.377 16.667 12.500 8.300 66% 57% • Date of AA = 22-09-2016
680 2283 Urban Sewerage / Drainage Scheme Chowk Azam LayyahOn-going
Schemes147.290 138.871 1.000 0.750 0.500 67% 95% "• Date of AA(Original) = 10-09-2007
681 2284 Urban Sewerage Scheme for Kot Sultan LayyahOn-going
Schemes191.440 152.935 6.667 5.000 3.334 67% 82% • Date of AA = 24-02-2009
682 2285Sewer Line from Bahawalpur Victoria Hospital to
Disposal Lal Bagh Tehsil & District Bahawalpur.Bahawalpur
On-going
Schemes172.906 139.513 11.131 8.348 5.560 67% 84%
Date of AA :26-02-2014. Date of TS :05-03-2014.
Date of RAA=12-05-2016. Date of pre-qualification:
07-03-2014. . Date of receipt of tenders. 02-04-
2014. Date of work order :29-04-2014. Date of
completion as per agreement:28.04.2016.
Anticipated date of completion=30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress. Date of AA :26-02-2014. Date
of TS :05-03-2014. Date of RAA=12-05-2016. Date
of pre-qualification: 07-03-2014. . Date of receipt of
tenders. 02-04-2014. Date of work order :29-04-
2014. Date of completion as per
agreement:28.04.2016. Anticipated date of
completion=30-06-2019. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Work is in progress.
683 2286Sewerage / Tuff Tile in Choti Karana Tehsil &
District Bahawalpur.Bahawalpur
On-going
Schemes1.288 0.883 0.135 0.033 0.000 0% 69%
Date of A.A 04.05.2016. Date of T.S 26-05-2016.
Date Awarded 11.06.2016. Date of completion 11-
09-2017. Expected date of completion 30-06-2018.
Funds released by FD 20.07.2018 & 11.01.2019. .
Work completed during 2017-2018. Liability of the
contractor cleared.Excess funds Rs. 0.068 million
surrendered dated 19.10.2018.
684 2287 Construction of Tuff Tile in Main Street Gillani City
Uch Sharif Tehsil Ahmed Pur East, Bahawalpur.Bahawalpur
On-going
Schemes3.089 0.801 0.763 0.190 0.000 0% 26%
Date of AA 19.03.2015. Date of T.S 18.04.2015.
Date of award 18.05.2015. Date of completion
17.09.2015. Expected date of completion 30-06-
2018. Funds released by FD 20.07.2018 &
11.01.2019. . Scheme remained unfunded during
2016-2017. Remaining work has been
executed/completed by Local Government due to
which funds not required. Excess funds Rs. 0.0382
million surrendered dated 19.10.2018.
685 2288Laying of Tuff Paver and provision of water Supply
Pipelines in City Bahawalnagar.Bahawalnagar
On-going
Schemes70.000 49.812 4.922 3.692 3.000 81% 75%
Date of AA: 11.01.2014. Date of TS: 17.01.2014.
Date of RTS 23-11-2016. Date of pre-qualification:
28.02.2014. Date of receipt of tenders = 19-03-
2014. Date of work order=11.04.2014. Date of
completion as per agreement=10.04.16. Anticipated
date of completion=30-06-2019. Date of receipt of
funds by F.D. 20.07.2018 & 11.01.2019. . Original
scope of work is completed. Revised scope of work
is in progress.
686 2289Provision of Sewerage Scheme Zone A with Tuff
Paver at BahawalnagarBahawalnagar
On-going
Schemes399.587 138.058 50.000 50.000 50.000 100% 47%
Date of AA = 29-09-2016(DDSC). Date of T.S.
08.02.2017. Funds released by FD= 04-07-2017 .
Prequalification of the contractor 26-01-2017.
Tender received on 22.03.2017 . Date of work
awarded.03-05-2017. . Date of completion 02-05-
2019. . Date of receipt of funds by F.D. 20.07.2018
and 19-12-2018. Work is in Progress.
687 2290Sewerage Scheme Chishtian City Uplift Package
ChishtianBahawalnagar
On-going
Schemes916.110 672.765 33.333 25.000 21.500 86% 76%
Date of A.A 25.05.2014 . . Date of T.S. 21-07-2014.
Date of Prequalification. 21-07-2014. Date of receipt
of tenders =12-08-2014. Date of work order= 16-09-
2014. Date of completion as per agreement=
15.09.2017.Anticipated date of completion =
30.06.2019 .No. of beneficiaries=342309 persons.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
688 2291 Mega Sewerage Scheme Liaqatpur CityRahim Yar
Khan
On-going
Schemes500.000 49.996 66.667 50.000 33.200 66% 17%
Date of A.A(PDWP) 19-01-2017.Date of T.S
16.02.2017.. Prequalification of the contractor
15.03.2017..Date of receipt of tender:- 03.04.2017.
.Date of award 24.07.2017 Date of completion. 23-
07-2019.Date of receipt of funds by F.D. 20.07.2018
& 11.01.2019..Funds of 3rd Quarter is not
credited/onlined to the District Accounsts office
RYK..Work is in progress.
689 2292Request for provision of Sewerage Scheme of
Feroza Town, Tehsil Liaqat Pur
Rahim Yar
Khan
On-going
Schemes199.970 160.769 13.063 9.797 8.150 83% 84%
Date of AA. 23-09-2014. Date of TS.. 27-11-2014.
Date of prequalification. 08-12-2014. Date of receipt
of tenders = 31-12-2014. Date of work order=10-2-
15. Date of completion as per agreement 09-8-16.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
690 2293 Rehabilitation of Sewerage City SadiqabadRahim Yar
Khan
On-going
Schemes70.326 52.373 5.984 1.688 0.192 11% 75%
Date of AA. 09-10-2014. .Date of TS. 21-11-
2014.Rev: TS 28.10.2016..Date of prequalification.
08-12-2014..Date of receipt of tenders = 31-12-
2014..Date of work order= 10-01-2015..Date of
completion as per agreement= 09-01-
2016.Anticipated date of completion=30-06-2018.
Scheme completd in saving. Date of receipt of
funds by F.D. 20.07.2018 & 11.01.2019. Funds not
required during 2018-2019. Excess funds Rs. 1.496
million proposed to Re-appropriate.
691 2294Laying of Soling, Water Supply, Sewerage Line
and Tuff Tiles in City Sadiq Abad.
Rahim Yar
Khan
On-going
Schemes40.000 19.958 6.667 5.000 3.888 78% 60%
Date of AA 19-12-2017.Date of T.S 15-02-
2018.Tenders received on 13-03-2018 .Date of
award 18.04.2018..Date of completion
12.04.2019..Date of receipt of funds by F.D.
20.07.2018 & 11.01.2019. Work is in progress.
692 2295Laying of Soling, Water Supply, Sewerage Line
and Tuff Tiles in Rural Area Tehsil Sadiq Abad.
Rahim Yar
Khan
On-going
Schemes35.000 17.468 5.833 4.375 3.501 80% 60%
Date of AA 19-12-2017.Date of T.S 15-02-
2018.Date of receipt of tenders 13-03-2018 .Date of
work awarded 30-03-2018.Date of completion 29-06-
2019..Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
693 2296
Laying of Soling, Water Supply, Sewerage Line
and Tuff Tiles in Chak No. 148/P Tehsil Sadiq
Abad.
Rahim Yar
Khan
On-going
Schemes8.000 3.984 1.333 1.000 0.799 80% 60%
Date of AA 19-12-2017.Date of T.S 16-02-
2018.Date of receipt of tenders 13-03-2018 .Date of
work awarded 07-04-2018.Date of completion 06-06-
2019..Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
694 2297Construction of Sewerage Line and Soling Wahid
Bux Mahar Tehsil Sadiq Abad.
Rahim Yar
Khan
On-going
Schemes5.000 2.471 0.833 0.625 0.493 79% 59%
Date of AA 19-12-2017.Date of T.S 16-02-
2018.Tenders received on 13-03-2018..Dated of
award 11.05.2018..Date of completion
26.06.2018..Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
695 2298
Rehabilitation / Augmentation of Sewerage
scheme Khan Pur city Phase-II District Rahim Yar
Khan
Rahim Yar
Khan
On-going
Schemes452.844 432.844 2.000 1.500 1.211 81% 96%
Date of AA =05.03.2014.Date of
TS=05.03.2014.Date op receipt of Tenders
25.03.2014.Date of work awarded 14.04.2014..Date
of completion 13.04.2016..Scheme remained
unfunded. Funds released by FD on 12-11-2018 &
11.01.2019. Scheme completed. Liability of the
contractor Rs. 20.00 Million is yet to be cleared.
696 2299Comprehensive Sewerage scheme Chenab Nagar
ChiniotChiniot
On-going
Schemes719.952 164.999 66.667 50.000 32.750 66% 27%
1. Date of AA =02.05.2016 2. Date of TS =
19.08.2016 . 3. Date of work order= 22.10.2016. 4.
Date of Completion as per PC-I = 3 Ye.5.
Anticipated Date of Comp = 30.06.2019 6. No. of
Beneficiaries= 116058.Funds Released upto
24.01.2019 by the Chief Engineer (South) PHED
Lahore and work is in progress.
697 2300
New urban Sewerage scheme for Mohallah Fateh
Abad Rashida Osmanaabad paris road Moazam
Shah Shahbaal
ChiniotOn-going
Schemes199.694 103.971 16.667 12.500 12.500 100% 58%
1. Date of AA =15.09.2014. 2. Date of TS
=28.11.2014 3. Date of Pre-qualification
=06.12.2014 4. Date of inviting Tenders=20.12.2014
5. Date receipt of Tenders= 20.12.2014 6. Date of
work order= 01.01.2015 7.Date of Completion as
per PC-I =2 Year 8. No. of Beneficiaries 94630
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
698 2301Soling / Drain, Pulian Hajiabad, Muradwala,
Sabowala,Colony, Sabowala, District ChiniotChiniot
On-going
Schemes4.998 0.800 1.000 0.750 0.500 67% 26%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
699 2302Construction of PCC / Soling / Drain, in Town
Committee Lalian, District ChiniotChiniot
On-going
Schemes10.000 9.410 0.590 0.443 0.295 67% 97%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
700 2303Extension Rehabilitation Sewerage Scheme
Chiniot City.Chiniot
On-going
Schemes212.366 209.621 1.000 0.750 0.500 67% 99%
1. Date of AA = 24.12.2012 2. Date of TS =
29.10.2013 (Revised) 3.Date of Award of work
31.01.2013. Work completed. Liability of the
contractor is pending.
701 2304
Construction of PCC / Soling / Drain,Pullian Mouza
Colony Mohammad Wala, Muhammad Wala,
Mamola, District Chiniot
ChiniotOn-going
Schemes4.000 2.539 1.461 1.096 0.731 67% 82%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
702 2305Construction of Sewerage Disposal Harsa Sheikh
Lahore road ChiniotChiniot
On-going
Schemes28.493 22.230 1.000 0.750 0.500 67% 80%
1. Date of AA = 31.07.2015 2. Date of TS =
27.08.2015 3.Date of Award of work 31.10.2015.
Work completed. Liability of the contractor is
pending.
703 2306Construction of PCC / Soling / Drain,Mouza Burj
Babal , District ChiniotChiniot
On-going
Schemes4.000 2.957 1.043 0.782 0.522 67% 87%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
704 2307Soling / Drains / Culverts / PCC Slabs / UC No.35
Tehsil Bhowana District Chiniot in PP-76, Chiniot Chiniot
On-going
Schemes5.000 4.729 0.271 0.203 0.136 67% 97%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
705 2308Soling / Drains / Culverts / PCC Slabs / Mc
Bhowana District Chiniot in PP-76, ChiniotChiniot
On-going
Schemes10.000 7.409 1.000 0.750 0.500 67% 79%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
706 2309Soling / Drains / Culverts / PCC Slabs /Uc No.34
Tehsil Bhowana District Chiniot PP- 76, Chiniot Chiniot
On-going
Schemes4.000 3.804 0.196 0.147 0.098 67% 98%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
707 2310Soling / Drains / Culverts / PCC Slabs / UC No.33
Tehsil Bhowana District Chiniot in PP-76, Chiniot Chiniot
On-going
Schemes5.000 2.669 1.000 0.750 0.500 67% 63%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
Work completed. Liability of the contractor is
pending.
708 2311Capacity Strenghthening of Design Cell of
HUD&PHED for projectPunjab
On-going
Schemes180.278 62.397 8.333 25.850 23.767 92% 48% In Progress
709 2312 Construction of Residential Buildings at Lahore
Head Quarter for officers BS 16 to BS 18 PHEDPunjab
On-going
Schemes277.000 81.706 10.000 7.500 5.000 67% 31% In Progress
710 2313Improvement and Extension of the Water Testing
Laboratories Phase IPunjab
On-going
Schemes260.000 19.590 50.000 12.500 0.000 0% 8% In Progress
711 2314 Renovation of PHED Head Quarter Building. PunjabOn-going
Schemes95.000 38.500 0.833 0.625 0.417 67% 41% In Progress
712 2315
Establishment of Management Information System
and Monitoring & Evaluation (MIS & ME) For
Capacity Building
PunjabOn-going
Schemes175.000 30.000 11.667 14.750 10.860 74% 23% In Progress
713 2316Establishment of PMU for WASH (Water,
Sanitataion & Hygiene)Punjab
On-going
Schemes35.000 4.200 3.267 4.850 3.710 76% 23% In Progress
714 2317Establishment of regional design cell at each civil
division / Circle levelPunjab
On-going
Schemes19.043 1.443 3.333 0.900 0.000 0% 8% In Progress
715 2318
Preparation of Water Quality Survey & Sewerage
Master Plan/Development Plan of Districts, Tehsil
and Urban Area
PunjabOn-going
Schemes18.235 12.435 1.650 1.238 0.000 0% 68% In Progress
716 2319 Survey & investigation of water source PunjabOn-going
Schemes9.436 0.456 2.993 0.845 0.000 0% 5% In Progress
717 2320Third Party Validation for Quality Control of the
New Initiatives through out PunjabPunjab
On-going
Schemes39.847 2.301 4.182 3.137 2.091 67% 11% In Progress
718 2321Upgradation / Strengthening of Existing
Laboratories at District Head QuarterPunjab
On-going
Schemes390.000 93.500 50.000 37.500 20.754 55% 29% In Progress
719 2322
Multi Sectoral Nutrition Strategy for WASH
Including Water Supply, Sanitation, Hygiene,
Waste Water
PunjabOn-going
Schemes1,013.037 100.000 166.667 125.000 75.524 60% 17% Work in Progress
720 2323Rehabilitation of 781 dysfunctional Rural Water
Supply SchemesPunjab
On-going
Schemes9,015.746 0.480 333.333 206.667 0.000 0% 0% Work in Progress
721 2324
Combined PC-II of Water Quality Survey,
Identification of outlived pipes, outsourcing of
water Supply schemes, Rationalization of staff in
WASAs, MC & PHED and pre qualification of
contractors and manufacturers
PunjabOn-going
Schemes327.683 30.600 33.333 25.000 16.667 67% 14% In Progress
722 2325Rehabilitation of need based (identified through
TPV) Dysfunctional Rural water Supply SchemesPunjab
On-going
Schemes1,146.048 707.664 66.667 50.000 14.816 30% 63% In Progress
723 2326Scaling up Pakistan Approach for Total Sanitation
(PATS) in Punjab (ODF)Punjab
On-going
Schemes399.705 287.317 16.667 12.500 7.500 60% 74% In Progress
724 2327Construction of PCC in Different Streets in UC -77
District Faisalabad Faisalabad
On-going
Schemes5.000 3.808 1.192 0.894 0.650 73% 89%
AA issued on 05.08.2017. Funds released on
23.11.2017. Work order issued on 13.12.2017.
Work is in progress.Funds released on 23.11.2018
& 24.1.19
725 2328Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Dheer Bain Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
726 2329Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Kotli Nawab Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
727 2330Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Wando Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
728 2331Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Kali Suba Gujranwala
On-going
Schemes10.000 4.807 1.667 0.416 0.000 0% 48% Scheme completed.
729 2332Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Sohawa Dhalwan Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
730 2333Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Nangal Dona Singh Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
731 2334Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Gona Osar Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
732 2335Construction of Streets and Drainage at Ward No.1
District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.
733 2336Construction of Streets and Drainage at Ward
No.2, District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.
734 2337Construction of Streets and Drainage at Ward
No.3, District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.
735 2338Construction of Streets and Drainage at Ward
No.4, District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.
736 2339Construction of Streets and Drainage at Ward
No.5, District Gujranwala Gujranwala
On-going
Schemes5.650 3.150 0.833 0.208 0.000 0% 56% Scheme completed.
737 2340Construction of Streets and Drainage at Ward
No.6, District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed
738 2341Construction of Streets and Drainage at Ward
No.7, District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.
739 2342Construction of Streets and Drainage at Ward
No.8, District Gujranwala Gujranwala
On-going
Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.
740 2343
Provision of PCC / Sewerage / Drainage / Soling
etc. in Village Jajoki, Teshil Nowsehra Virkan,
District Gujranwala
GujranwalaOn-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
741 2344Rehabilitatin Improvement of Streets in Village Pir
Kot Tehsil Wazirabad, District GujrnawalaGujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
742 2345Construction of PCC, Sewerage/Drains at UC 63
District GujranwalaGujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
743 2346Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Nadala Sindhowan Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
744 2347Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Mandiala Tabsa Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
745 2348Construction of Gallian Nallian PCC Soling and
Tuff Tile in UC Chak Ram Daas Gujranwala
On-going
Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.
746 2349
Construction of PCC Tuff Tile & Draiange at
Railway Road, Salamat Pura, Kamoki, District
Gujranwala
GujranwalaOn-going
Schemes6.755 3.930 0.942 0.236 0.000 0% 58% Scheme completed.
747 2350
Construction of PCC & Drainage at Street
Nos.13,14,15,16,17 and St. Masjid-E-Shuhda, Ahl-
E-Hadith, Tibba Muhammad Nagar, Kamoki,
District Gujranwala
GujranwalaOn-going
Schemes40.000 10.000 1.126 0.282 0.000 0% 25% Scheme completed.
748 2351Installation of Water Filteration Plant at Village
Class Marri Lahore.Lahore
On-going
Schemes5.350 2.833 0.839 0.229 0.020 9% 53%
Filtration Plant already installed in village Class
Mari during F.Y 2017-18, this is duplicate scheme,
required to be deleted for ADP.
749 2352Installation of Water Filteration Plant at Village
Gallian Khuda Bakhsh Lahore.Lahore
On-going
Schemes5.350 0.886 1.488 0.416 0.044 11% 17%
Filtration Plant already installed in village Gallian
Khuda Bakhsh under IPOR Package NA-130 during
F.Y 2017-18, this is duplicate scheme, required to
be deleted for ADP.
750 2353 Installation of filteration Plant Naseebabad LahoreOn-going
Schemes5.350 0.950 1.466 0.400 0.033 8% 18%
Due to change in political scenario, conflict with
community, site is not available for installation of
filtration plant, scheme need to be dropped from
ADP.
751 2354
Construction of PCC, Soling, Drain and Nallah in
Chak No. 11, 8, 7, 6, 18, 16, 15, 14 GB and Chak
No 01 (Khoti Wala) Nizam Pura District
nankanasahib
Nankana SahibOn-going
Schemes30.000 15.000 3.333 1.700 0.867 51% 53% Work is in progress.
752 2355Water Supply Dera Dogran Bhutta Colony Rukn
Deen Pur, District LodhranLodhran
On-going
Schemes39.263 9.986 9.754 7.316 5.300 72% 39%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 10-02-
2018 7. Date of Completion as per PC-I: 28-02-2018
8. Anticipated Date of Completion: 08-02-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
3821 Persons. Work is in Progress
753 2356Water Supply Scheme Kotli Wajjwah, District
LodhranLodhran
On-going
Schemes37.175 9.977 9.058 6.794 5.200 77% 41%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 07-02-
2018 7. Date of Completion as per PC-I : 28-02-
2018 8. Anticipated Date of Completion: 04-02-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
5367 Persons. Work is in Progress.
754 2357
Water Supply Scheme Haifzaabad Dunyapur
Gharbi Remainig Portion Dunyapur Sharqi, District
Lodhran
LodhranOn-going
Schemes49.805 9.900 13.268 14.322 8.953 63% 38%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 06-02-
2018 7. Date of Completion as per PC-I: 28-02-2018
8. Anticipated Date of Completion: 04-02-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
4731 Persons. Work is in Progress.
755 2358Water Supply Scheme in Chak No.359/Wb District
LodhranLodhran
On-going
Schemes19.309 9.896 3.103 2.327 1.850 80% 61%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 06-02-
2018 7. Date of Completion as per PC-I: 28-02-2018
8. Anticipated Date of Completion: 04-02-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
4235 Persons. Work is in Progress
756 2359Water Supply Scheme in Chak No.358/Wb District
LodhranLodhran
On-going
Schemes26.334 9.992 5.445 4.084 3.100 76% 50%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 10-02-
2018 7. Date of Completion as per PC-I: 28-02-2018
8. Anticipated Date of Completion: 08-02-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
4881 Persons. Work is in Progress.
757 2360Water Supply Scheme in Chak No.311/Wb District
LodhranLodhran
On-going
Schemes36.605 9.855 8.868 6.651 5.150 77% 41%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 30-03-
2018 7. Date of Completion as per PC- I: 28-02-
2018 8. Anticipated Date of Completion: 28-03-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
2996 Persons. Work is in Progress.
758 2361Water Supply Scheme in Chak No.13/M District
LodhranLodhran
On-going
Schemes28.934 9.927 6.311 4.733 3.650 77% 47%
1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-
2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 03-01-2018 5. Date of Receipt
of Tender: 04-01-2018 6. Date of Award: 10-02-
2018 7. Date of Completion as per PC-I: 28-02-2018
8. Anticipated Date of Completion: 08-02-2019
9.Date of released of funds 03-08-2018 24.01.2019
10. Reason of Slow Moving: 11.No. of Benificiary
1934 Persons. Work is in Progress.
759 2362Construction of Nali Soling Tuff Tile & Culverts UC
Shero Dasti Dg Khan
Dera Ghazi
Khan
On-going
Schemes7.000 2.000 1.000 0.750 0.548 73% 36% "• Date of A.A = 13.1.17
760 2363
Construction of Nali Soling Tuff Tiles On The West
of Mana Ahmadani Town Ship + Basti Budhan Dg
Khan
Dera Ghazi
Khan
On-going
Schemes10.000 2.000 1.000 0.750 0.000 0% 20% "• Date of A.A = 13.1.17
761 2364Rehabilitation of Water Supply in Fareed Abad PP-
244 District Dg Khan
Dera Ghazi
Khan
On-going
Schemes10.000 7.000 1.000 0.750 0.548 73% 75% "• Date of A.A = 25.7.2017
762 2365Rehabilitation of Water Supply in Gharib Abad PP-
244 District Dg Khan
Dera Ghazi
Khan
On-going
Schemes10.000 5.000 1.000 0.750 0.555 74% 56% "• Date of A.A = 25.7.2017
763 2366Rehabilitation of 10 Rural Water Supply Schemes
Tehsil Murree & Kotli Sattian, District RawalpindiRawalpindi
On-going
Schemes34.830 9.787 3.333 2.500 1.667 67% 33% Work in Progress.
764 2367
Const. of 02 Nos. Filtration Plants in each Ward of
Chaklala Cantt Ward No.5 to 10& Const. of 0.2 MG
capacity UGT at Sarwar Park LalKurti, District
Rawalpindi
RawalpindiOn-going
Schemes50.000 19.500 4.667 3.500 2.334 67% 44% Work in Progress.
765 2368
Const. of Bridge / Drain at Rawal Town, Tench
Road/Adra Bridge/ Kacha Stop under Railway
Track/Aliabad/Dk. Banaras/ Ahmadabad, District
Rawalpindi
RawalpindiOn-going
Schemes50.000 20.000 6.667 9.000 7.334 81% 55% Work in Progress.
766 2369
Const. of Road / Sewerage at each Ward No.1 to
10 of Rawalpindi Cantt and Ward No.5 to 10 &
Minority Member, District Rawalpindi
RawalpindiOn-going
Schemes50.000 20.909 6.667 7.500 5.834 78% 53% Work in Progress.
767 2370Construction of streets in UCs PP-03 including
Gujar Khan City, District RawalpindiRawalpindi
On-going
Schemes150.000 35.897 6.667 9.329 7.663 82% 29% Work in Progress.
768 2371
Laying of 4’’ Dia Water Supply Pipe Line Ward
No,1 to Ward No,10 Rawalpindi Cantonment
Board ., District Rawalpindi
RawalpindiOn-going
Schemes40.000 10.000 10.000 7.500 5.000 67% 38% Work in Progress.
769 2372
Const. of 02 Nos. Filtration Plants in each Ward of
Rawalpindi Cantt Ward No.1 to 10 and Const. of
0.2 MG capacity UGT at Dk. Gujran Ward No.10,
District Rawalpindi
RawalpindiOn-going
Schemes50.000 20.000 10.000 7.500 5.000 67% 50% Work in Progress.
770 2373Construction of Under Ground Water Tank
Rawalpindi Cantonment Board, District RawalpindiRawalpindi
On-going
Schemes25.000 21.156 1.114 0.836 0.557 67% 87%
Only payment of WAPDA Demand Notice pending
which will be paid after issuance of Demand Notice
by WAPDA.
771 2374Water Supply Scheme at Dhala, District
RawalpindiRawalpindi
On-going
Schemes10.200 5.000 1.733 1.300 0.867 67% 58% Work is in progress.
772 2375
Construction of PCC link road Wasla to Dhoke
Bhattian, length=2.00 Km UC Sui Chemian, Tehsil
Gujar Khan, District Rawalpindi
RawalpindiOn-going
Schemes12.815 5.000 2.605 0.651 0.000 0% 39% Work is in progress.
773 2376
Construction of PCC link road Sattal to Sabah Sher
and Dhoke Phugoo, length=2.00 Km, Tehsil Gujar
Khan, District Rawalpindi
RawalpindiOn-going
Schemes12.881 5.000 2.627 0.656 0.000 0% 39% Work is in progress.
774 2377
Construction of PCC road Dhoke Khumbail, Phase-
I, length=1.5 Km, UC Sui Chemian, Tehsil Gujar
Khan, District Rawalpindi
RawalpindiOn-going
Schemes10.569 5.000 1.856 0.464 0.000 0% 47% Work is in progress.
775 2378Constt. Of PCC link Road Mohri Barsal uc Jero
Ratial., District RawalpindiRawalpindi
On-going
Schemes14.000 8.969 1.677 1.258 0.839 67% 70% Work is in progress.
776 2379Constt. Of PCC link Road Paka Khanpur UC
Bhadana., District RawalpindiRawalpindi
On-going
Schemes14.000 4.917 3.000 0.750 0.000 0% 35% Work is in progress.
777 2380Constt. Of PCC link Road Dhoke Rajgan UC
Qazian., District RawalpindiRawalpindi
On-going
Schemes12.000 5.000 2.333 1.750 1.167 67% 51% Work is in progress.
778 2381Constt. Of PCC link Road Dhoke fateh Paharian
UC Qazian., District RawalpindiRawalpindi
On-going
Schemes11.000 4.500 2.000 1.500 1.000 67% 50% Work is in progress.
779 2382
Constt. Of PCC link Road Dhoke Channi Dakhali
Sohawa Mirzian, Islam Pura Jabbar / Bewal.,
District Rawalpindi
RawalpindiOn-going
Schemes11.000 5.000 2.000 1.500 1.000 67% 55% Work is in progress.
780 2383
Construction of PCC link road Jhawan to Kountrila
UC Kountrila, length=1.70 Km, Tehsil Gujar Khan,
District Rawalpindi
RawalpindiOn-going
Schemes10.530 4.773 1.843 0.460 0.000 0% 45% Work is in progress.
781 2384
Construction of PCC link road Kanyal to Dhoke
Jeaven, length=1.70 Km UC Mohra Noori, Tehsil
Gujar Khan, District Rawalpindi
RawalpindiOn-going
Schemes10.170 4.995 1.723 0.430 0.000 0% 49% Work is in progress.
782 2385Drainage scheme at Noorpur and Lundi, Tehsil
Hazro, District AttockAttock
On-going
Schemes26.139 9.977 5.380 1.535 1.090 71% 42%
A.A Date 02.08.2017. T.S Date 13.09.2017.Date of
Start of Scheme 29.01.2018.Date of Completion of
Scheme 30.06.19.Work is in progress.
783 2386Drainage scheme at Khudlathi and Sarwana,
Tehsil Hazro, District AttockAttock
On-going
Schemes28.306 9.977 6.102 4.577 3.051 67% 46%
A.A Date 02.08.2017.T.S Date 13.09.2017.Date of
Start of Scheme 07.12.2017.Date of Completion of
Scheme 30.06.19.Work is in progress.
784 2387Drainage scheme at Musa and Sherani, Tehsil
Hazro, District Attock Attock
On-going
Schemes26.931 14.976 3.977 2.983 1.989 67% 63%
A.A Date 02.08.2017.T.S Date 13.09.2017.Date of
Start of Scheme 27.11.2017.Date of Completion of
Scheme30.06.19.Work is in progress.
785 2388Rural drainage scheme in village Shakardara
Phase-II, District AttockAttock
On-going
Schemes32.394 9.980 3.333 2.500 1.667 67% 36%
A.A Date 02.08.2017. T.S Date 13.09.2017.Date of
Start of Scheme 09.12.2017.Date of Completion of
Scheme 30.06.2019.Work is in progress.
786 2389Rural draiange scheme in village Ghourgushti
Phase-II, Tehsil Hazro, District AttockAttock
On-going
Schemes19.313 9.914 3.104 2.328 1.552 67% 59%
A.A Date 02.08.2017. T.S Date 13.09.2017.Date of
Start of Scheme 09.12.2017.Date of Completion of
Scheme 30.06.2019.Work is in progress.
787 2390
Construction of PCC road from Kohat road
Bhandar to Dhok Sanakhi UC Langar Tehsil Jand
District Attock
AttockOn-going
Schemes28.500 9.979 6.167 4.625 3.084 67% 46%
A.A Date 02.08.2017. T.S Date 13.09.2017.Date of
Start of Scheme 06.12.2017.Date of Completion of
Scheme 30.06.19.Work is in progress.
788 2391Water Supply scheme of village Ferozwali UC
Gareebwal Tehsil Pindigheb District AttockAttock
On-going
Schemes22.500 7.961 4.833 3.625 2.417 67% 46%
A.A Date 02.08.2017. T.S Date 13.09.2017.Date of
Start of Scheme 10.01.2018.Date of Completion of
Scheme 30.06.2019.Work is in progress.
789 2392Drainage / sewerage scheme in village Painda,
Daman, Jalalia, District AttockAttock
On-going
Schemes61.838 25.999 3.333 2.500 1.667 67% 45%
A.A Date 16.09.2017.T.S Date 11.10.2017.Date of
Start of Scheme 06.11.2017.Date of Completion of
Scheme 30.06.2019.Dwork is in progress.
790 2393Drainage / sewerage scheme in village Shadi Khan
Phase-II, District AttockAttock
On-going
Schemes54.788 19.972 3.333 3.500 2.667 76% 41%
A.A Date 16.09.2017.T.S Date 10.10.2017. Date of
Start of Scheme 09.12.2017.Date of Completion of
Scheme 30.06.2019.Work is in progress.
791 2394Drainage / Sewerage System in village Barazai,
Tehsil Hazro, District AttockAttock
On-going
Schemes15.450 9.346 1.817 1.363 0.909 67% 66%
A.A Date 16.09.2017.T.S Date 10.10.2017. Date of
Start of Scheme 09.12.2017.Date of Completion of
Scheme 30.06.2019.Work is in progress.
792 2395Rural drainage scheme and water supply
Oudherwal and Mohallah Islam Pura ChakwalChakwal
On-going
Schemes18.000 10.000 2.667 2.600 1.934 74% 66%
Date of A.A 31.07.2017. Date of T.S 08.08.2017
.Date of Start 18.10.2017.Date of completion
30.06.2019.Work is in progress.
793 2396Rural drainage scheme and Water Supply in UC
Dub, District ChakwalChakwal
On-going
Schemes24.000 10.000 4.667 5.031 3.865 77% 58%
Date of A.A 31.07.2017.Date of T.S
08.08.2017.Date of Start 18.10.2017.Date of
completion 30.06.2019.Full funds utilized. Scheme
is short funded.
794 2397Urban sewerage and drainage scheme in Chakwal
City, Ward No.1 to Ward No.12, District ChakwalChakwal
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39%
"Date of A.A 31.07.2017.Date of T.S
08.08.2017.Date of Start 19.10.2017
795 2398
Urban Drainage & Sewerage scheme of Chakwal
City from Ward No.13 to Ward No.23, District
Chakwal
ChakwalOn-going
Schemes30.000 16.000 4.667 11.900 10.732 90% 89%
Date of A.A 31.07.2017. Date of T.S
08.08.2017.Date of Start 19.10.2017 .Date.of
fcompletion.30.06.2019.Allocated funds were
utilized. utilized. Additional funds Rs.8.4 M provided
through .reappropriation in Dec.2018 and will be
consumed during next month.
796 2399
Urban Drainage & Sewerage scheme of Chakwal
City from Ward No.28 to Ward No.37, District
Chakwal
ChakwalOn-going
Schemes30.000 9.970 3.333 2.500 1.667 67% 39%
Date of A.A 31.07.2017. Date of T.S 08.08.2017.
Date of Start 19.10.2017.Date of completion
30.06.2020.Full funds utilized. Scheme is short
funded.
797 2400Rural drainage scheme and retaining wall and
Cause Way in MC Bhaun, District ChakwalChakwal
On-going
Schemes27.000 13.000 4.667 7.000 5.834 83% 70%
Date of A.A 31.07.2017. Date of T.S
08.08.2017.Date of Start 23.10.2017.Date of
completion 30.06.2019.Allocated funds were
utilized. utilized. Additional funds Rs.3.5 M provided
through reappropriation in Dec.2018 and will be
consumed during next month.
798 2401Rural Drainage Scheme and Retaining wall and
Cause way in UC Mureed, District ChakwalChakwal
On-going
Schemes25.000 13.999 3.667 2.750 1.834 67% 63%
Date of A.A 31.07.2017. Date of T.S
08.08.2017.Date of Start 25.10.2017.Date of
completion 30.06.2019.Full funds utilized. Scheme
is short funded.
799 2402Rural Drainage Scheme and Retaining wall and
Cause way in UC Jand Awan, District ChakwalChakwal
On-going
Schemes20.000 9.997 3.333 2.500 1.667 67% 58%
Date of A.A 31.07.2017.Date of T.S
08.08.2017.Date of Start 26.10.2017.Date of
completion 30.06.2019.Full funds utilized. Scheme
is short funded.
800 2403Rural drainage and water supply village Tatral,
District ChakwalChakwal
On-going
Schemes20.000 10.000 3.333 0.969 0.136 14% 51%
Date of A.A 31.07.2017. Date of T.S
08.08.2017.Date of Start 26.10.2017 ..Date of
completion 30.06.2019.Work is in progress.
801 2404Rural Drainage scheme and Retaining wall in UC
Mulhal Mughllan, District ChakwalChakwal
On-going
Schemes17.000 9.996 2.333 1.150 0.567 49% 62%
Date of A.A 31.07.2017. Date of T.S
08.08.2017.Date of Start 26.10.2017.Date of
completion 30.06.2019.Full funds utilized. Scheme
is short funded.
802 2405Rural draiange scheme & Retaining wall and
causeway in UC Chak Umara, District ChakwalChakwal
On-going
Schemes13.000 8.000 1.667 3.750 3.333 89% 87%
Date of A.A 31.07.2017 .Date of T.S
08.08.2017.Date of Start 26.10.2017 .Date of
completion 30.06.2019.Allocated funds were
utilized. utilized. Additional funds Rs.8.4 M provided
through reappropriationin in Dec.2018 and will be
consumed during next month.
803 2406Rural drainage scheme UC -Jaswal, Tehsil &
District ChakwalChakwal
On-going
Schemes20.000 9.997 3.333 1.900 1.067 56% 55%
Date of A.A 31.07.2017 .Date of T.S 08.08.2017.
Date of Start 26.10.2017 .Date of completion
30.06.2019.Work is in progress.
804 2407Rural drainage scheme Nichandi & Dhapai, Tehsil
& District ChakwalChakwal
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58%
"Date of A.A 31.07.2017 .Date of T.S 08.08.2017
.Date of Start 27.10.2017
805 2408Construction of PCC, Streets, Drain & Water
Supply at Talagang, District ChakwalChakwal
On-going
Schemes147.248 29.998 3.333 2.500 1.667 67% 22%
Date of A.A 09.08.2017. Date of T.S 02.10.2017
.Date of Start 17.11.2017 .Date of completion
30.06.2020.Full funds utilized. Scheme is short
funded.
806 2409Construction of PCC, Streets, Drain & Water
Supply at Tehsil Lawa PP-23, District ChakwalChakwal
On-going
Schemes98.166 24.920 3.333 2.500 1.667 67% 27%
Date of A.A 09.08.2017.Date of T.S 08.08.2017
.Date of Start 21.11.2017 . Date of completion
30.06.2020.Full funds utilized. Scheme is short
funded.
807 2410
Restoration / Flood Rains Damages vented
causeway on Dhermond to Dk. Fateh Shah Road,
Vented causeway Darot & street / drains village
Wanhar, Tehsil Talagang, District Chakwal
ChakwalOn-going
Schemes14.239 10.000 1.413 1.060 0.707 67% 75%
Date of A.A 31.07.2017.Date of T.S
08.08.2017.Date of Start 27.10.2017.Date of
completion 30.06.2019.Scheme completed.
808 2411Provision of sewerage at Ward No.36 Tehsil &
District Jhelum, District JehlumJhelum
On-going
Schemes15.000 4.480 2.333 1.750 1.167 67% 38%
A.A Date 27-07-2017.T.S Date 09-08-2017.Date of
Work Award 09-09-2017.Work in progress
809 2412Provision of Sewerage system at UC Kotla Faqeer,
Tehsil & District JhelumJhelum
On-going
Schemes30.000 10.000 3.333 9.185 4.445 48% 48%
A.A Date 27-07-2017.T.S date 09-08-2017.Date of
Work Award 09-09-2017.Work in progress
810 2413Provision of Water Supply at Pind Sawika, Tehsil &
District JhelumJhelum
On-going
Schemes15.000 7.988 2.333 1.750 1.167 67% 61%
A.A Date 27-07-2017.T.S date 09-08-2017.Date of
Work Award 16-09-2017.Work in progress
811 2414Provision of Water supply at village Kundal, District
JhelumJhelum
On-going
Schemes21.747 9.941 3.916 2.937 1.958 67% 55%
A.A Date 27-07-2017.T.S date 09-08-2017.Date of
Work Award 13-09-2017.Work in progress
812 2415Water supply scheme at Chak No.165 Shumali,
Sillanwali, District SargodhaSargodha
On-going
Schemes10.673 4.947 1.891 1.418 1.411 100% 60% Work in progress.
813 2416
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No
45/SB Tehsil and District Sargodha
SargodhaOn-going
Schemes20.000 9.979 3.333 2.500 1.899 76% 59% Work in progress.
814 2417
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No
46/Sb tehsil and District Sargodha
SargodhaOn-going
Schemes20.000 9.977 3.333 2.500 2.226 89% 61% Work in progress.
815 2418
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No
107/Sb Tehsil and District Sargodha
SargodhaOn-going
Schemes20.003 9.920 3.334 2.501 2.120 85% 60% Work in progress.
816 2419
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No
85/NB tehsil and District Sargodha
SargodhaOn-going
Schemes10.004 6.036 1.323 0.993 0.993 100% 70% Work in progress.
817 2420
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No
84/NB Tehsil and District Sargodha
SargodhaOn-going
Schemes10.008 4.972 1.669 1.252 1.009 81% 60% Work in progress.
818 2421Water supply scheme at Chak No.129 Janobi,
Sillanwali, District SargodhaSargodha
On-going
Schemes23.594 7.000 4.531 3.398 3.364 99% 44% Work in progress.
819 2422Water supply scheme at Chak No.119 Janobi,
Sillanwali, District SargodhaSargodha
On-going
Schemes17.002 10.000 2.334 1.751 1.671 95% 69% Work in progress.
820 2423Water supply scheme at Chak No.111/107
Shumali, Sillanwali, District SargodhaSargodha
On-going
Schemes17.193 10.000 2.398 1.799 1.624 90% 68% Work in progress.
821 2424Water supply scheme at Chak No.140 Janobi,
Sillanwali, District SargodhaSargodha
On-going
Schemes12.961 5.997 2.320 1.740 1.353 78% 57% Work in progress.
822 2425
Construction of Drain / PCC / Soling / Sullage
Carrier at Midh Pergana Islam Pure More, Tehsil
Bhera. District Sargodha
SargodhaOn-going
Schemes16.130 10.000 2.043 1.532 1.204 79% 69% Work in progress.
823 2426
Construction of PCC / Soling / Sewerage / Nullah
Dera Abdul Sattar jhamat Chak No. 19 Shumali L=
2800 Feet, District Sargodha
SargodhaOn-going
Schemes20.000 9.972 3.333 2.500 1.889 76% 59% Work in progress.
824 2427
Construction of PCC / Soling / Sewerage / Chabar
Balooka Dera Mehar Muhammad Akhtar Lak and
PCC / Soling Mehar Qadir Yat Lak, UC Sakisar
Baar, District Sargodha
SargodhaOn-going
Schemes20.000 10.000 3.333 2.500 1.947 78% 60% Work in progress.
825 2428
Constructio of Soling / Sewerage / PCC, Dera Jaat
via Mehar Shahid Akram Lak, Ghulam Ahmed
Kamrana, Ahmed Yaar Gondal, Haji Muhammad
Sher, UC Mardi Lak, District Sargodha
SargodhaOn-going
Schemes20.000 10.000 3.333 2.500 2.026 81% 60% Work in progress.
826 2429
Construction of Soling / PCC / Nullah / Dera Mahar
Nasar Hayat Lak and Soling Lak More to Bonga
Minhas Colony, Dera Jaat Mahar Muhammad
Bakhsh Lak, Mahar Abdul Rehamn Lak, Salah
Muhammad Sipra, UC Lak More, District Sargodha
SargodhaOn-going
Schemes20.000 10.000 3.333 2.500 1.901 76% 60% Work in progress.
827 2430Construction of Soling / PCC / UC Chak No. 58
Shumali, District SargodhaSargodha
On-going
Schemes20.000 9.978 3.333 2.500 1.977 79% 60% Work in progress.
828 2431
Construciton of Soling Dera Jaat Badle Wala and
PCC / Sewerage and repair of road Chak No. 53
Shumali, District Sargodha
SargodhaOn-going
Schemes20.000 10.000 3.333 2.500 1.898 76% 59% Work in progress.
829 2432Rural Drainage scheme for Chak No 9/SB, District
SargodhaSargodha
On-going
Schemes29.294 11.100 3.333 2.500 2.241 90% 46% Work in progress.
830 2433Rural Drainage scheme for Chak No.18/SB &
Colonies, District SargodhaSargodha
On-going
Schemes25.885 13.609 3.333 2.500 1.967 79% 60% Work in progress.
831 2434Rural Drainage scheme Chak No.2/NB, District
SargodhaSargodha
On-going
Schemes30.261 9.966 3.333 2.500 2.352 94% 41% Work in progress.
832 2435 Rural Drainage Scheme Abdal, District Sargodha SargodhaOn-going
Schemes25.667 10.885 3.333 2.500 1.923 77% 50% Work in progress.
833 2436
Construciton of Drainage / Soling, Adjoining
Abadies of Mouza Ahmaday wala, District
Sargodha
SargodhaOn-going
Schemes15.000 5.000 3.333 2.500 2.069 83% 47% Work in progress.
834 2437Rural drainage scheme UC No.64, Dharema,
Sargodha, District SargodhaSargodha
On-going
Schemes19.991 8.500 3.330 2.498 1.891 76% 52% Work in progress.
835 2438Rural drainage scheme UC No.77, Hyderabaad
Town, District SargodhaSargodha
On-going
Schemes19.927 9.995 3.309 2.482 1.916 77% 60% Work in progress.
836 2439Rural drainage scheme UC No.76, Chak
No.71/NB, District SargodhaSargodha
On-going
Schemes19.955 10.000 3.318 2.489 2.033 82% 60% Work in progress.
837 2440Rural drainage scheme UC No.74, Chak
No.79/NB, District SargodhaSargodha
On-going
Schemes19.987 10.000 3.329 2.497 1.978 79% 60% Work in progress.
838 2441Drainage scheme at Chak No.132/136, Janobi,
Sillanwali, District Sargodha Sargodha
On-going
Schemes29.657 11.993 3.333 2.500 2.139 86% 48% Work in progress.
839 2442Drainage scheme at Chak No.125/129 Shumali,
Sillanwali, District SargodhaSargodha
On-going
Schemes32.611 10.000 3.333 2.500 2.500 100% 38% Work in progress.
840 2443Drainage scheme at Chak No.128/130 Janobi,
Sillanwali, District SargodhaSargodha
On-going
Schemes33.563 12.999 3.333 2.500 2.252 90% 45% Work in progress.
841 2444
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No 23-
ASB Tehsil and District Sargodha.
SargodhaOn-going
Schemes15.000 10.000 1.667 1.251 1.211 97% 75% Work in progress.
842 2445
Construction of road Drain / Soling / Re-Soling /
PCC / Tuff Pavers / Sullage Carrier in Chak No
73/SB Tehsil and District Sargodha
SargodhaOn-going
Schemes15.002 10.000 1.667 1.251 0.963 77% 73% Work in progress.
843 2446Urban Sewerage & Drainage Scheme in M.C-04
Sargodha City.Sargodha
On-going
Schemes50.000 19.981 3.333 2.500 2.500 100% 45% Work in progress.
844 2447Urban Sewerage & Drainage Scheme in M.C-19
Sargodha City.Sargodha
On-going
Schemes40.000 19.788 3.333 2.500 2.104 84% 55% Work in progress.
845 2448Urban Sewerage & Drainage Scheme in
Cantonment Ward No. 01 to 05 Sargodha City.Sargodha
On-going
Schemes50.000 20.675 3.333 2.500 2.500 100% 46% Work in progress.
846 2449Urban Sewerage & Drainage Scheme in
Cantonment Ward No. 06 to 10 Sargodha City.Sargodha
On-going
Schemes50.000 21.099 3.333 2.500 2.500 100% 47% Work in progress.
847 2450
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline including Disposal Station Gillwala
and Tiwana Park Sargodha City.
SargodhaOn-going
Schemes50.000 19.917 3.333 2.500 1.973 79% 44% Work in progress.
848 2451
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline including Disposal Station M.C No.
07 Street No. 01, 02, 03, 04 & 05 to Rehman Pura
Chowk via Pistool Marka Gali Sargodha City.
SargodhaOn-going
Schemes50.000 22.600 3.333 2.500 1.888 76% 49% Work in progress.
849 2452Urban Sewerage & Drainage Scheme / Water
Supply Pipeline in M.C No. 08 Sargodha City.Sargodha
On-going
Schemes40.000 20.000 3.333 2.500 2.500 100% 56% Work in progress.
850 2453
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline including Renovation of Disposal
Station Eid Gah M.C No. 09 Sargodha City.
SargodhaOn-going
Schemes45.000 19.996 3.333 2.500 2.500 100% 50% Work in progress.
851 2454
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline M.C No. 11 & M.C No. 13
Sargodha City
SargodhaOn-going
Schemes50.000 21.260 3.333 2.500 2.030 81% 47% Work in progress.
852 2455
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline including Disposal Station Iqbal
Colony and at Girls Degree College to Block No.
16 Sargodha City
SargodhaOn-going
Schemes50.000 13.000 3.333 2.500 2.500 100% 31% Work in progress.
853 2456
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline Madina Town, New Madina Town,
Muhammadi Colony including Disposal Station and
Main Water Works Chowk / Road Sargodha City.
SargodhaOn-going
Schemes50.000 20.309 3.333 2.500 2.500 100% 46% Work in progress.
854 2457
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline M.C No. 22 with Road Election
Commission Sargodha City.
SargodhaOn-going
Schemes50.000 21.488 3.333 2.500 2.500 100% 48% Work in progress.
855 2458
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline M.C No. 20 M.C No. 21 Sargodha
City.
SargodhaOn-going
Schemes40.000 19.969 3.333 2.500 2.142 86% 55% Work in progress.
856 2459
Urban Sewerage & Drainage Scheme / Water
Supply Pipeline Hameed Town, Society Colony
including Renovation of Main Disposal Works
Sillanwali Road Sargodha City.
SargodhaOn-going
Schemes45.000 19.994 3.333 2.500 2.168 87% 49% Work in progress.
857 2460Urban Sewerage & Drainage Scheme in M.C-01
Sargodha City.Sargodha
On-going
Schemes50.000 24.739 3.333 2.500 1.897 76% 53% Work in progress.
858 2461Urban Sewerage & Drainage Scheme in M.C-02
Sargodha City.Sargodha
On-going
Schemes30.000 14.684 3.333 2.500 1.932 77% 55% Work in progress.
859 2462Urban Sewerage & Drainage Scheme in M.C-03
Sargodha City.Sargodha
On-going
Schemes30.000 9.580 3.333 2.500 1.901 76% 38% Work in progress.
860 2463Rehabilitation water supply scheme Bhera Town,
District SargodhaPhase-ISargodha
On-going
Schemes80.000 33.978 3.333 4.472 4.472 100% 48% Work in progress.
861 2464
Urban Water Supply Scheme Distribution System
Factory Area, Essa Nagar, Istaqlalabad, Hameed
Town, Corporation Town, Society Colony and
Nallah including Slab Karkhana Bazar Sargodha
City.
SargodhaOn-going
Schemes30.000 14.911 3.333 2.500 1.986 79% 56% Work in progress.
862 2465
Additional Water Supply pipeline in Cheema
Colony, Kalyar Town, Rehmat Park, Pir
Muhammad Colony & Adjoining Colonies
Sargodha City.
SargodhaOn-going
Schemes30.000 15.000 3.333 2.500 1.893 76% 56% Work in progress.
863 2466Rehabilitation of Water Supply Scheme New
Satellite Town Sargodha CitySargodha
On-going
Schemes50.000 20.000 3.333 2.500 2.003 80% 44% Work in progress.
864 2467Providing / Fixing Ultra Filtration Plants U.F / R.O
in Wards / M.Cs in PP-34 Sargodha City 10-No.Sargodha
On-going
Schemes40.000 25.000 3.333 2.500 1.899 76% 67% Work in progress.
865 2468
Up-gradation of Disposal Works in New Satellite
Town & Ghani Park and laying of Distribution
System in New Satellite Town & adjoining abadies
Sargodha City
SargodhaOn-going
Schemes48.000 27.221 3.333 2.500 2.500 100% 62% Work in progress.
866 2469Water supply scheme at Sobaga, Sillanwali,
District SargodhaSargodha
On-going
Schemes23.195 9.943 3.333 2.500 2.108 84% 52% Work in progress.
867 2470
Construction of PCC Tuff Tiles / Tuff Pever road
Liaqat Shaheed road to Merydal School & Suger
Mil road to Lalazar Colony road & Merydal School
to Sail Nallah & Pathan Wala road, Street Masjid
Wali, Bhalwal, District Sargodha
SargodhaOn-going
Schemes20.000 10.000 3.333 2.500 2.500 100% 63% Work in progress.
868 2471Construciton of Sewerage Scheme, Tehsil
Sahiwal, District SargodhaSargodha
On-going
Schemes50.000 29.250 3.333 2.500 2.500 100% 64% Work in progress.
869 2472Construciton of Sewerage Scheme Farooqa,
District SargodhaSargodha
On-going
Schemes50.000 20.000 3.333 2.500 1.991 80% 44% Work in progress.
870 2473Construciton of Sewerage Scheme Vijh, Tehsil
Sahiwal, District SargodhaSargodha
On-going
Schemes30.000 8.200 3.333 2.500 1.894 76% 34% Work in progress.
871 2474Construciton of Sewerage Scheme Nehong, Tehsil
Sahiwal, District SargodhaSargodha
On-going
Schemes40.000 14.992 3.333 4.807 4.793 100% 49% Work in progress.
872 2475Extension of Rural Water Supply Scheme, Malwal,
District KhushabKhushab
On-going
Schemes24.530 9.979 4.843 3.632 3.630 100% 55%
Date of AA 29.7.2017 Date of award 09.12.2017
Date of completion 30.06.2019 Tube Well 1 No.
Pump House 1 No. Rising Main 9000/9000 Rft
D/System 5700/7970 Rft Work is in progress.
873 2476Provision of 100 Hand Pumps at Mahar Area,
District Khushab District KhushabKhushab
On-going
Schemes30.000 9.991 3.333 2.500 2.000 80% 40%
Date of AA 29.07.2017 Date of TS 5.9.2017 Date of
award 23.12.2017 Date of completion 30.06.2020
Hand Pump 23/34 Nos. Bore with submersible
pump 13/29 Nos. G.S Tank 500 Glns 5/29 Nos.
874 2477Extension / Improvement of Water Supply Scheme,
Kuradhi UC Uchhali, District KhushabKhushab
On-going
Schemes21.225 3.000 3.333 2.500 2.250 90% 25%
Date of AA 29.07.2017 Date of TS 04.9.2017 Date
of award 18.12.2017 Date of completion 30.06.2020
Tube Well 1 No. Pump House 1 No. Pumping
Machinery 1 No. Rising Main 3240/28525 Rft Work
is in progress.
875 2478
Rehabilitation / Improvement of Water Supply
Scheme, Fateh Pur Maira UC Gunjial Shumali,
District Khushab
KhushabOn-going
Schemes12.400 5.595 2.133 1.600 1.440 90% 57%
Date of AA 29.07.2017 Date of TS 15.8.2015 Date
of award 08.01.2018 Date of completion 30.06.2019
Rising Main 9600/11500 Rft D/System 1800/2355
Rft Work is in progress.
876 2479Rehabilitation of Water Supply Scheme, Warcha
UC Warcha, District KhushabKhushab
On-going
Schemes25.000 9.999 3.333 2.500 2.250 90% 49%
Date of AA 29.07.2017 Date of TS 5.9.2017 Date of
award 23.12.2017 Date of completion 30.06.2020
Tube Well 1 No. Pump House 1 No. Pumping
Machinery 1 No. Rising Main 11880/17875 Rft
D/System 0/1320 Rft Work is in progress.
877 2480Rehabilitation of Water Supply Scheme, Kufri UC
Kufri, District KhushabKhushab
On-going
Schemes15.230 8.750 1.743 1.307 1.180 90% 65%
Date of AA 29.07.2017 Date of TS 5.9.2017 Date of
award 16.12.2017 Date of completion 30.06.2020
Tube Well 1 No. Pump House 1 No. Pumping
Machinery 1 No. Rising Main 12800/12807 Rft Work
is in progress.
878 2481Construciton of Water Supply Scheme of Rehman
Colony MC Hadhali, District KhushabKhushab
On-going
Schemes30.000 15.000 3.333 2.500 2.250 90% 58%
Date of AA 29.07.2017 Date of TS 4.9.2017 Date of
award 11.12.2017 Date of completion 30.06.2020
Tube Well 6/6 Set. Pumping Machinery 6 Nos.
Rising Main 50800/53196 Rft Work is in porgress.
879 2482Construciton of Water Supply Scheme of Zaman
Colony MC Hadhali, District KhushabKhushab
On-going
Schemes30.000 15.999 4.667 3.500 2.980 85% 63%
Date of AA 29.07.2017 Date of TS 4.9.2017 Date of
award 11.12.2017 Date of completion 30.06.2019
Tube Well 6 Nos. Pumping Machinery 6/6 Set.
Rising Main 49480/52184 Rft Work is in progress .
880 2483Provision of sewerage scheme Roda, District
KhushabKhushab
On-going
Schemes100.000 23.486 3.333 2.500 1.870 75% 25%
Date of AA 16.10.2017 Date of TS 15.8.2015 Date
of award 04.01.2018 Date of completion 30.06.2020
RCC Sewer 0/1500 Rft. PCC Slab 28522/293128
Cft Work is in progress.
881 2484Provision of Drainage System in MC Mitha Tiwana,
District KhushabKhushab
On-going
Schemes49.900 14.997 3.333 2.500 1.875 75% 34%
Date of AA 29.07.2017 Date of TS 5.9.2017 Date of
award 08.12.2017 Date of completion 30.06.2020
PCC Slab 60101/89202 Cft Surface Drain 0/19550
Rft Sullage Carrier 0/10715 Rft Work is in progress.
882 2485Provision of Drainage System in MC QuaidaAbad,
District KhushabKhushab
On-going
Schemes49.831 16.993 3.333 2.500 1.880 75% 38%
Date of AA 29.07.2017 Date of TS 5.9.2017 Date of
award 08.12.2017 Date of completion 30.06.2020
RCC Sewer 5786/18305 Rft PCC Slab 40186/76862
Cft Surface Drain 0/3000 Rft work is in progrss .
883 2486Provision of Drainage System in UC Ukhli Mohla,
District KhushabKhushab
On-going
Schemes18.025 9.998 2.675 2.006 1.500 75% 64%
Date of AA 29.07.2017 Date of TS 05.09.2017 Date
of award 09.12.2017 Date of completion 30.06.2019
PCC Slab 27608/54740 Cft work is in progress.
884 2487Construction of Drainage / Sewerage scheme,
Rehman Colony, MC Hadhali, District KhushabKhushab
On-going
Schemes32.000 9.999 3.333 2.500 1.870 75% 37%
Date of AA 29.07.2017 Date of TS 04.09.2017 Date
of award 09.12.2017 Date of completion 30.06.2020
RCC Sewer 7320/8700 Rft PCC Slab 17510/39304
Cft Surface Drain 4401/6000 Rft Work is in
progress.
885 2488Construction of Drainage / Sewerage scheme,
Zaman Colony, MC Hadhali, District KhushabKhushab
On-going
Schemes30.000 10.000 3.333 2.500 1.879 75% 40%
Date of AA 29.07.2017 Date of TS 04.09.2017 Date
of award 09.12.2017 Date of completion 30.06.2020
PCC Slab 24015/27284 Cft Surface Drain 513/5000
Rft Sullage Carrier 1800/15540 Rft Work is in
progress.
886 2489Construction of PCC Derajat, UC Uttra, District
KhushabKhushab
On-going
Schemes20.000 9.998 3.333 2.500 1.880 75% 59%
Date of AA 29.7.2017 Date of TS 05.09.2017 Date
of award 07.12.2017 Date of completion 30.06.2019
PCC Slab 46175/66532 Cft Surface Drain 0/1470
Rft Work is in progress .
887 2490Construction of PCC Slab, UC Gunjial, District
KhushabKhushab
On-going
Schemes30.000 9.929 3.333 2.500 1.990 80% 40%
Date of AA 29.07.2017 Date of TS 05.09.2017 Date
of award 11.12.2017 Date of completion 30.06.2020
RCC Sewer 0/860 Rft Surface Drain 0/5000 Rft
PCC Slab 25515/63069 Cft Work is in progrss.
888 2491Construction of PCC Slab, UC 14 MB, District
KhushabKhushab
On-going
Schemes20.000 10.000 3.333 2.500 2.020 81% 60%
Date of AA 29.7.2017 Date of TS 05.09.2018 Date
of award 11.12.2017 Date of completion 30.06.2019
PCC Slab 42293/66326 Cft Surface Drain 900/1600
Rft Work is in progress.
889 2492Construction of Sewerage in, MC Mitha Twana,
District KhushabKhushab
On-going
Schemes100.000 15.490 3.333 2.500 1.870 75% 17%
Date of AA 11.08.2015 Date of TS 15.8.2015 Date
of award 28.03.2018 Date of completion 30.06.2020
PCC Slab 16620/78190 Cft Surface Drain
2661/18230 Rft Sullage Carrier 0/29400 Rft work is
in progress.
890 2493Provision of Sewerage and Sanitation at village
Dhoranka City, UC Namal, District MianwaliMianwali
On-going
Schemes20.000 1.996 3.333 2.500 1.667 67% 18%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks.RCC
Pipe Sewer 9"i/d=2900-Arranged/2957, 12"i/d=2800-
Arranged/2878, 15"i/d=1100-Arranged/1175,
18"i/d=800-Arranged/828, 21"i/d= 900-
Arranged/978, 24"i/d=0/942, Surface Drain=0/430,
PCC Slab=0/9035, Sullage Carrier
(1.25'x1.5')=0/100, (1.50'x2')=0/500,
(2.50'x4')=0/1400. Work is in progress.
891 2494Provision of Integrated Sewerage Scheme for Wan
Bhachran Town, District MianwaliMianwali
On-going
Schemes75.000 11.995 3.333 2.974 2.141 72% 19%
Date of A.A. 18-08-2017, Date of T.S. 13-11-2017,
Date of Start of Work 19-01-2018, Remarks. RCC
Sewer=9" i/d=0/6890, 12"i/d= 482-Laid & 5214-
Arranged/23310, 15"i/d= 6416-Arranged /6595,
18"i/d=2536-Arranged/2590, 21"i/d=0/150,
24"i/d=1600-Arranged/1635, 27"i/d=1656-
Arranged/1690, 30"i/d=1704-Arranged/1740,
33"i/d=407/510, Surface Drain= 0460, PCC Slab=
19713/98880, Sullage Carrier= 0/500, 0/150,
Screening Chamber=0/1, P/Machinery=0/1,
T/Line=0/1. Work is in progress.
892 2495Provision of Sewerage and Sanitation at UC Mari,
District MianwaliMianwali
On-going
Schemes20.000 12.997 2.333 1.750 1.165 67% 71%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks.RCC
Pipe Sewer 9"i/d=0/980, 12"i/d=0/2532,
15"i/d=0/1418, 18"i/d=0/930, Surface Drain=0/1040,
PCC Slab= 55632/28106, Sullage Carrier
(1.25'x1.5')=0/430, (1.50'x2') =0/1850, (2.50'x4')
=0/100 Work is in progress.
893 2496Provision of Sewerage and Sanitation at UC Kalon
Wala, District MianwaliMianwali
On-going
Schemes20.000 12.495 2.500 1.875 1.250 67% 69%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks.RCC
Pipe Sewer 12"i/d=372-Arranged/ 2393,
15"i/d=0/868, 18"i/d=0/636, Surface
Drain=700/4535, Sullage Carrier=0/955, PCC Slab=
47095/33241, Brick Pavement=0/51000. Work is in
progress.
894 2497Provision of Sewerage and Sanitation at UC
Manda Khel / Jalal Pur, District MianwaliMianwali
On-going
Schemes20.000 12.495 2.500 1.875 1.247 67% 69%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017-,
Date of Start of Work 29-10-2017, Remarks. RCC
Pipe Sewer 12"i/d=0/536, 24"i/d=0/257, Surface
Drain=491/3130, Sullage Carrier=350/850, PCC
Slab= 40772/56009. Work is in progress.
895 2498Installation of Submersible Pumps in PP-43 ,
District MianwaliMianwali
On-going
Schemes50.000 21.998 3.333 2.500 1.667 67% 47%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks.
ERS=116/116, Trial Bore=06/11, Tube Well =
28/58, Pumping Machinery= 28/58, G.S.Tank 500-
Glns=0/58. Work is in progress.
896 2499PCC Slab / Drainage Scheme UC Kot Chandna,
Tehsil Isa Khel, District MianwaliMianwali
On-going
Schemes20.000 12.499 2.500 1.875 1.250 67% 69%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks. PCC
Slab= 53864/ 59483, Surface Drain=1630/2900,
Sullage Carrier=0/350 Work is in progress.
897 2500Urban sewerage drainage scheme Isa Khel,
District MianwaliMianwali
On-going
Schemes20.000 9.999 3.333 2.500 1.662 66% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks. RCC
Pipe Sewer 12"i/d= 785/1284, 24"i/d =280/330,
Surface Drain= 1261/4540, Sullage Carrier=
540/1335, PCC Slab= 23154/28996, Tuff Tiles=
3238 /3564, Replacement of Rising Main 8"i/d
PE=2000/3335, 6"i/d PVC=0/60, 4"i/d PVC = 0/60,
3"i/d PVC= 0/660. Work is in progress.
898 2501 PCC Slab at U.C Khaglanwala, District Mianwali MianwaliOn-going
Schemes20.000 10.000 3.333 2.500 1.666 67% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks. PCC
Slab=44695 /53023, Surface Drain=984/9255,
Sullage Carrier=150/150, RCC Sewer 12" =
318/335. Work is in progress.
899 2502 PCC Slab at U.C Vanjari, District Mianwali MianwaliOn-going
Schemes20.000 9.999 3.333 2.500 1.667 67% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks. PCC
Slab= 44443 /63118, Surface Drain=0/1055, Sullage
Carrier=0/120. Work is in progress.
900 2503 PCC Slab at U.C Chapri, District Mianwali MianwaliOn-going
Schemes20.000 9.998 3.333 2.500 1.661 66% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017. Remarks. PCC
Slab= 41949/59804, Surface Drain= 0/4235, Sullage
Carrier=0/600. Work is in progress.
901 2504PCC Slab at U.C Paka Kamar Mushani, District
MianwaliMianwali
On-going
Schemes20.000 6.999 3.333 2.500 1.665 67% 43%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017
Date of Start of Work 29-10-2017, Remarks. RCC
Pipe Sewer 12"i/d=862/1530, Surface
Drain=0/1720, Sullage Carrier=400/400, PCC
Slab=40973/57767. Work is in progress.
902 2505Construction of PCC Slab & Drain Kala Bagh Lari
Adda, District MianwaliMianwali
On-going
Schemes15.250 6.999 2.750 2.063 1.370 66% 55%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks.
Surface Drain=0/7230, Sullage Carrier=0/100, PCC
Slab=24252/35699, Tuff Tiles=0/15800. Work is in
progress.
903 2506Sewerage and Sanitation for Paki Shah Mardan
District MianwaliMianwali
On-going
Schemes30.000 9.991 3.333 2.500 1.661 66% 39%
Date of A.A. 01-08-2017, (Rev)Date of T.S.08-03-
2018, Date of Start of Work 29-10-2017, Remarks.
RCC Pipe Sewer 9"i/d=0/938, 12"i/d=590/4320,
15"i/d=1314/1276, 18"i/d= 2504/3950,
21"i/d=1812/1664, 24"i/d=1291/2062, Surface
Drain=0/120, PCC Slab=0/4600, Sullage
Carrier=350/1060. Work is in progress.
904 2507PCC Slab / Drainage Scheme UC vanjari, Tehsil
Isa Khel, District MianwaliMianwali
On-going
Schemes20.000 9.994 3.333 2.500 1.667 67% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks.RCC
Pipe Sewer 12"i/d=2592-Arranged/2595, 15"i/d=480-
Arranged/480, Surface Drain=0/4535, Sullage
Carrier=0/955, PCC Slab= 35812/44680. Work is in
progress.
905 2508PCC Slab / Drainage Scheme UC Pacca Kama
Mushani, Tehsil Isa Khel, District MianwaliMianwali
On-going
Schemes40.000 20.000 6.667 5.000 3.330 67% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks. RCC
Pipe Sewer 12"i/d=2550/2785, 15"i/d=0/660,
Surface Drain=0/1270, Sullage Carrier=0/350, PCC
Slab= 77311/107505 Work is in progress.
906 2509PCC Slab / Drainage Scheme UC Sultan Khel,
Thesil Isa Khel, District MianwaliMianwali
On-going
Schemes20.000 9.996 3.333 2.500 1.660 66% 58%
Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,
Date of Start of Work 29-10-2017, Remarks. PCC
Slab= 41269/59297, Surface Drain 0/5945, Sullage
Carrier=0/200 Work is in progress.
907 2510
Construction of Sewerage / Drainage scheme i/c
PCC Pavement in Street village Hussasin Shah,
Tehsil Darya Khan District Bhakkar
BhakkarOn-going
Schemes64.920 10.000 3.333 2.500 2.500 100% 19%
"Date of A.A 10.08.2017 Date of T.S 13.09.2017
Date of Commencement 08.12.2017 Date of
completion 30.06.2020
908 2511
Construction of sullage carrier, surface drain, brick
pavement, PCC Slab, RCC Sewer and Disposal
Station in Sara-e-Mohajir, Chak No.250/TDA,
District Bhakkar.
BhakkarOn-going
Schemes48.600 10.500 3.333 2.500 2.500 100% 27%
"Date of A.A 10.08.2017Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
909 2512
Construction of sullage carrier, surface drain, brick
pavement, PCC Slab, RCC Sewer and Disposal
Station in Chak No.67/ML, District Bhakkar.
BhakkarOn-going
Schemes48.600 15.500 3.333 2.500 2.500 100% 37%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 02.11.2017 Date of
completion 30.06.2020
910 2513
Construction of sullage carrier, surface drain, brick
pavement, PCC Slab, RCC Sewer and Disposal
Station in Sara-e-Mohajir Chak No.71/ML, District
Bhakkar.
BhakkarOn-going
Schemes47.255 18.000 3.333 2.500 2.167 87% 43%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
911 2514
Construction of sullage carrier, surface drain, brick
pavement, PCC Slab, RCC Sewer and Disposal
Station at Adda Jahan Khan, Chak No.45/TDA,
District Bhakkar.
BhakkarOn-going
Schemes49.833 18.000 3.333 2.500 2.267 91% 41%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
912 2515
Rural sewerage, drainage, PCC Slab / brick
pavement scheme in UC Katchi Shahani, Tehsil &
District Bhakkar
BhakkarOn-going
Schemes57.023 17.500 3.333 2.500 2.500 100% 35%
"Date of A.A 10.08.2017 Date of T.S 06.11.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
913 2516
Rural sewerage, drainage, PCC Slab / brick
pavement scheme in UC Sial, Tehsil & District
Bhakkar
BhakkarOn-going
Schemes59.573 20.000 3.333 2.500 2.500 100% 38%
"Date of A.A 10.08.2017 Date of T.S 06.11.2017
Date of Commencement 13.12.2017 Date of
completion 30.06.2020
914 2517
PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian /
and soling scheme UC Fazal, UC Chak No. 40/ML
UC Chak No. 63/DB, Tshil Kallur Kot, District
Bhakkar
BhakkarOn-going
Schemes30.000 10.000 6.667 5.000 3.934 79% 46%
"Date of A.A 10.08.2017 Date of T.S 18.18.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2019
915 2518
PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian /
and soling scheme UC Dali Namdar UC Ghulaman
No.1, UC Ghulaman No.2, Tehsil Kallur Kot,
District Bhakkar
BhakkarOn-going
Schemes40.000 15.000 3.333 2.500 1.667 67% 42%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
916 2519
PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian /
and soling scheme UC Haitthu, UC Kalul, UC
Maibal, UC Kanjan and UC Noon Dagar, Tehsil
Kallur Kot, District Bhakkar
BhakkarOn-going
Schemes50.000 18.000 3.333 2.500 2.500 100% 41%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
917 2520
Provision of PCC Pavement / Slab, Sewerage,
Culverts and Soling in UC Khaawar kala, Majoka,
Lak Kalan, tehsil Darya Khan District Bhakkar
BhakkarOn-going
Schemes46.563 23.500 3.333 2.500 1.667 67% 54%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
918 2521
Provision of PCC Pavement / Slab, Sewerage,
Culverts and Soling in UC Dullaywala Rural,
Jhammat Shumali, Barranga, Tehsil Darya Khan
District Bhakkar
BhakkarOn-going
Schemes46.904 20.000 3.333 2.500 1.661 66% 46%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
919 2522
Provision of PCC Pavement / Slab, Sewerage,
Culverts and Soling in UC Daggar Qureshi,
Wahwara, Barkatwala, Tehsil Darya Khan District
Bhakkar.
BhakkarOn-going
Schemes36.304 15.000 3.333 2.500 1.660 66% 46%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
920 2523
Provision of PCC Pavement / Slab, Sewerage,
Culverts and Soling in UC Angra Daggar, Chak No
6/TDA, Gadai Tehsil Darya Khan District Bhakkar.
BhakkarOn-going
Schemes49.827 10.000 3.333 2.500 1.661 66% 23%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
921 2524
Provision of PCC Pavement / Slab, Sewerage,
Culverts and Soling in UC Punjigrain Daggar and
Nasheb, Tehsil Darya Khan District Bhakkar.
BhakkarOn-going
Schemes32.268 10.000 3.333 2.500 1.667 67% 36%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
922 2525
Construction of Sewerage / Drainage scheme i/c
PCC Pavement in Street village Sukha Shah,
Tehsil Darya Khan District Bhakkar
BhakkarOn-going
Schemes15.040 8.495 2.180 1.635 1.247 76% 65%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 03.11.2017 Date of
completion 30.06.2019
923 2526Construction of Sewerage / Drainage scheme
Baranga Tehsil Darya Khan, District BhakkarBhakkar
On-going
Schemes49.760 15.000 3.333 2.500 2.500 100% 35%
"Date of A.A 10.08.2017 Date of T.S 18.18.2017
Date of Commencement 02.11.2017 Date of
completion 30.06.2020
924 2527
Construction of Sewerage / Drainage scheme i/c
PCC Pavement in Street village Londi Nasheeb,
Tehsil Darya Khan, District Bhakkar
BhakkarOn-going
Schemes27.650 10.000 3.333 2.500 2.500 100% 45%
"Date of A.A 10.08.2017 Date of T.S 18.18.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
925 2528Rural Drainage scheme UC Goharwala and
Khansar., District BhakkarBhakkar
On-going
Schemes28.345 15.000 4.448 3.336 3.336 100% 65%
"Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 03.11.2017 Date of
completion 30.06.2019
926 2529Construction of sewerage / Drainage scheme in
Chak No. 49/TDA Tehsil and District BhakkarBhakkar
On-going
Schemes36.766 10.000 3.333 2.500 2.267 91% 33%
Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 02.11.2017 Date of
completion 30.06.2020
927 2530Construction of sewerage / Drainage scheme in
Chak No. 47/TDA Tehsil and District BhakkarBhakkar
On-going
Schemes45.685 5.000 3.333 2.500 2.500 100% 16%
Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 02.11.2017 Date of
completion 30.06.2020
928 2531
Extension of Sewerage / Drainage Scheme and
PCC pavement in left over streets Darya Khan
City, Tehsil Darya Khan District Bhakkar.
BhakkarOn-going
Schemes50.000 22.499 3.333 2.500 2.060 82% 49%
Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
929 2532Sewerage scheme Kotla Jam, Tehsil & District
BhakkarBhakkar
On-going
Schemes48.611 4.000 3.333 2.500 1.660 66% 12%
Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
930 2533PCC Slab and Sewerage scheme MC jandanwala,
Tehsil Kallut Kot, District BhakkarBhakkar
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39%
Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
931 2534PCC Slab and Sewerage scheme MC Kallut Kot,
District BhakkarBhakkar
On-going
Schemes50.000 21.500 3.333 2.500 2.500 100% 48%
Date of A.A 10.08.2017 Date of T.S 18.08.2017
Date of Commencement 31.10.2017 Date of
completion 30.06.2020
932 2535
Construction of PCC, Soling & drains schemes in
Chak No.409 GB, 420 GB, 410 GB, 405 GB, 407
GB, 424 GB District Faisalabad
FaisalabadOn-going
Schemes15.500 10.000 1.833 1.375 0.917 67% 70%
Date of A.A 29-09-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
933 2536
Construction of PCC, Soling & drains schemes in
Chak No. 430 GB, 422GB, 423 GB, 427 GB, 428
GB, 425 GB, 404 GB District Faisalabad
FaisalabadOn-going
Schemes12.500 7.000 1.833 1.375 0.917 67% 63%
Date of A.A 29-09-2017. Date of T.S.05-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
934 2537
Construction of PCC, soling & drainage and
boundary walls of graveyards in Pindi Sheikh
Musa, Mobarik Pura, Chak No.451 GB, 429 GB,
400 GB, 408 GB & Nazir Colony District
Faisalabad
FaisalabadOn-going
Schemes17.000 5.889 2.333 1.750 1.167 67% 42%
Date of A.A 29-09-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
935 2538 Rural Drainage Scheme of Villages in NA-76 FaisalabadOn-going
Schemes150.000 39.926 6.667 5.000 3.334 67% 29%
ate of A.A 04-10-2017. Date of T.S.14-12-2017.
Work order issued on 01-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
936 2539Construction of Rural Drainage and PCC Road UC
30, 194/RB, District FaisalabadFaisalabad
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 19-01-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
937 2540Construction of Rural Drainage and PCC Road
,UC 60 District Faisalabad Faisalabad
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44%
ate of A.A 04-10-2017. Date of T.S.14-12-2017.
Work order issued on 01-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
938 2541Construction of Rural Drainage and PCC Road ,
UC 71 District Faisalabad Faisalabad
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44%
ate of A.A 04-10-2017. Date of T.S.14-12-2017.
Work order issued on 01-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
939 2542Construction of Rural Drainage and PCC Road at
U.C. 62 District Faisalabad Faisalabad
On-going
Schemes15.000 3.495 2.667 2.000 1.330 67% 32%
ate of A.A 04-10-2017. Date of T.S.14-12-2017.
Work order issued on 01-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
940 2543Construction of Rural Drainage and PCC Road at
U.C. 65 District Faisalabad Faisalabad
On-going
Schemes15.000 2.049 1.667 1.250 0.834 67% 19%
ate of A.A 04-10-2017. Date of T.S.14-12-2017.
Work order issued on 01-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
941 2544Construction of Rural Drainage and PCC Road at
U.C. 67 District Faisalabad Faisalabad
On-going
Schemes15.000 4.928 1.667 1.250 0.834 67% 38%
ate of A.A 04-10-2017. Date of T.S.14-12-2017.
Work order issued on 01-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
942 2545
Provision of Sewerage/ Drainage Facilities in PP-
57, District Faisalabad FaisalabadOn-going
Schemes50.000 19.297 3.333 2.500 1.667 67% 42%
Date of A.A 27-10-2017. Date of T.S.28-10-2017.
Work order issued on 30-11-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
943 2546Rural Drainage Scheme for Muncipal committee
Samundri District Faisalabad Faisalabad
On-going
Schemes49.888 29.937 3.333 2.500 1.667 67% 63%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 19-01-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
944 2547Rural Drainage Scheme for Samundri District
Faisalabad Faisalabad
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 19-01-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
945 2548Rural Drainage Scheme at Chak No. 263/RB,
Dijkot Town Committee Tehsil ,District Faisalabad Faisalabad
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 19-01-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
946 2549Rural Water Supply Scheme chak No. 203\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes23.880 10.000 4.627 3.470 2.314 67% 52%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
947 2550Rural Water supply Scheme chak no. 199\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes13.434 10.000 1.145 0.859 0.573 67% 79%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
948 2551Rural Water supply Scheme chak no. 208\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes20.359 10.000 3.453 2.590 1.727 67% 58%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
949 2552PCC / Seewrage etc. Scheme Jaranwala City in
NA-76Faisalabad
On-going
Schemes100.000 20.877 6.667 5.000 3.334 67% 24%
Date of A.A 02-10-2017. Date of T.S.02-11-2017.
Work order issued on 01-03-2018. Work is in
progress.Funds released on 03.08.2018& 24.1.19.
950 2553
Provision of Solling / Nalian / Drainage in
Tandlianwala City , Mamu kanjan City, UC's
76,77,78,79,80,81,82,83,84,85,86,87, 88, 89, 90,
91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102,
103, 104, Tehsil Tandlianwala District Faisalabad
FaisalabadOn-going
Schemes126.000 24.631 6.667 5.000 3.334 67% 22%
Date of A.A 09-10-2017. Date of T.S.02-11-2017.
Work order issued on 01-02-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
951 2554Rural Water supply Scheme chak no. 209\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes19.412 10.000 3.137 2.353 1.569 67% 60%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
952 2555Rural Water supply Scheme chak no. 212\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes12.439 10.000 0.813 0.610 0.407 67% 84%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
953 2556Rural Water supply Scheme chak no. 207\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes26.341 10.000 3.333 2.500 1.667 67% 44%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
954 2557Rural Water supply Scheme chak no. 211\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes11.338 6.000 1.779 1.334 0.890 67% 61%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
955 2558Rural Water supply Scheme chak no. 202\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes12.378 6.000 2.126 1.595 1.063 67% 57%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
956 2559Rural Water supply Scheme chak no. 200\GB
Tehsil Samundari District Faisalabad Faisalabad
On-going
Schemes11.850 6.000 1.950 1.463 0.975 67% 59%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
957 2560
Construction of Soling, Nallian, Pullian, Nallah and
Water Supply at Chak No. 5 GB Kamal Pur UC
168 in District Faisalabad
FaisalabadOn-going
Schemes37.222 15.000 3.333 2.500 1.667 67% 45%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress.Funds released on 03.08.2018 & 24.1.19.
958 2561
Construction of Soling, Nallian, Pullian, Nallah and
Water Supply at Chak No. 52 GB malal Pur UC
166 in District Faisalabad
FaisalabadOn-going
Schemes22.692 10.000 4.231 3.173 2.116 67% 53%
Date of A.A 05-08-2017. Date of T.S.16-09-2017.
Work order issued on 31-10-2017. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
959 2562Construction of PCC different streets UC-4 UC-6
UC-7 UC-8 in District Faisalabad Faisalabad
On-going
Schemes40.000 18.000 1.000 0.750 0.500 67% 46%
AA issued on 05.08.2017. Date of T.S 16.09.2017
Work order issued on 23.11.2018. Work is in
progress. Funds released on 12.06.2018 & 24.1.19.
960 2563Construction of PCC different streets UC-9 UC-10
UC-11UC-12 in District Faisalabad Faisalabad
On-going
Schemes30.000 15.000 1.000 0.750 0.500 67% 52%
AA issued on 05.08.2017. Date of T.S 16.09.2017
Work order issued on 13.06.2018. Work is in
progress. Funds released on 23.11.2018 & 24.1.19.
961 2564Construction of PCC different streets UC-14 UC-15
UC-17 in District Faisalabad Faisalabad
On-going
Schemes20.000 10.000 1.000 0.750 0.500 67% 53%
AA issued on 05.08.2017. Date of T.S 16.09.2017
Work order issued on 12.06.2018. Work is in
progress. Funds released on 23.11.2018 & 24.1.19.
962 2565 Construction of PCC Streets in District Faisalabad FaisalabadOn-going
Schemes75.000 25.000 6.667 5.000 3.334 67% 38%
Date of A.A 02-10-2017. Date of T.S.01-11-2017.
Work order issued on 08-02-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
963 2566Sewerage Sheme in 240GB and additional
AbadiesFaisalabad
On-going
Schemes30.000 20.000 3.333 2.500 1.960 78% 73%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 19-01-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
964 2567Provision of PCC / Sewerage / Drainage / Tuff Tile
and etc in PP-53, District FaisalabadFaisalabad
On-going
Schemes50.000 25.000 3.333 2.500 1.667 67% 53%
Date of A.A 29-08-2017. Date of T.S.05-09-2017.
Work order issued on 19-01-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
965 2568Water Supply Schemes in Constitutency NA-80,
District Faisalabad Faisalabad
On-going
Schemes122.000 35.000 6.667 5.000 3.334 67% 31%
Date of A.A 19-09-2017. Date of T.S.20-11-2017.
Work order issued on 01-02-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
966 2569Provision of Installation of New Water Plant in
District Faisalabad Faisalabad
On-going
Schemes75.000 34.862 6.667 5.000 3.334 67% 51%
Date of A.A 02-10-2017. Date of T.S.17-11-2017.
Work order issued on 03-03-2018. Work is in
progress. Funds released on 03.08.2018 & 24.1.19.
967 2570Soling / Drains / Culverts / PCC Slabs / UC No.1 to
UC No.8 Tehsil & District Jhang Jhang
On-going
Schemes13.000 6.996 2.000 1.500 1.166 78% 63%
Date of A.A 01.08.2017 Date of T.S 06.09.2017
Work order issued on 31.10.2017 Work is in
progress.
968 2571 Drainage Scheme Chak no. 479/JB District Jhang. JhangOn-going
Schemes16.749 6.991 3.250 2.438 1.935 79% 53%
Date of A.A 01.08.2017 Date of T.S 06.09.2017
Work order issued on 31.10.2017 Work is in
progress.
969 2572 Drainage Scheme Chak no. 482/JB District Jhang. JhangOn-going
Schemes20.489 4.982 3.333 2.500 1.943 78% 34%
Date of A.A 01.08.2017 Date of T.S 06.09.2017
Work order issued on 31.10.2017 Work is in
progress.
970 2573 Drainage Scheme Chak no. 493/JB District Jhang. JhangOn-going
Schemes30.614 11.999 3.333 2.500 1.999 80% 46%
Date of A.A 01.08.2017 Date of T.S 06.09.2017
Work order issued on 31.10.2017 Work is in
progress.
971 2574
Construction of Soling, Drains, PCC and Sullage at
Sammunduana, Tehsil Ahmad Pur Sial District
Jhang.
JhangOn-going
Schemes14.354 9.855 1.451 1.088 0.846 78% 75%
Date of A.A 01.08.2017 Date of T.S 06.09.2017
Work order issued on 31.10.2017 Work is in
progress.
972 2575Rural Drainage Scheme at Different Villages, 18
Hazari, in District JhangJhang
On-going
Schemes40.000 19.996 3.333 2.500 2.010 80% 55%
Date of A.A 01.08.2017 Date of T.S 13.09.2017
Work order issued on 23.12.2017. Work is in
progress.
973 2576
Water Supply Scheme Chak No. 412 Cheemia
Wali, Tehsil Shorkot, District Jhang and
Construction of Tank for Water Supply Scheme
Chak No. 412 Cheemia Wali.
JhangOn-going
Schemes20.303 9.990 3.434 2.576 2.150 83% 60%
Date of A.A 01.08.2017 Date of T.S 13.09.2017
Work order issued on 23.11.2017 Work is in
progress.
974 2577Provision of Water Supply at Chak No. 498 Tehsil
Shorkot, District Jhang.Jhang
On-going
Schemes22.000 9.993 4.000 3.000 2.433 81% 56%
Date of A.A 01.08.2017 Date of T.S 13.09.2017
Work order issued on 23.11.2017 Work is in
progress.
975 2578Provision of Sewerage & drainage At UC-46
Rustam Sargana Tehsil shorkot.Jhang
On-going
Schemes15.000 6.899 2.667 2.000 1.554 78% 56%
Date of A.A 01.08.2017 Date of T.S 06.09.2017
Work order issued on 31.10.2017 Work is in
progress.
976 2579
Sewerage / Drainage Scheme for Tehsil
Headquartar Ahmad Pur Sial District Jhang Phase-
2.
JhangOn-going
Schemes100.000 39.962 6.667 5.000 3.900 78% 44%
Date of A.A 19.09.2017 Date of T.S 09.10.2017
Work order issued on 17.01.2018 Work is in
progress.
977 2580Hazrat Peer Abdur rehman Sewerage Scheme
District Jhang.Jhang
On-going
Schemes70.000 24.580 6.667 5.000 3.886 78% 41%
Date of A.A 19.09.2017 Date of T.S 28.09.2017
Work order issued on 13.01.2018 Work is in
progress.
978 2581Provision of 16 nos. Water Filtration Plants in
Tehsil 18 Hazari, District Jhang.Jhang
On-going
Schemes40.000 0.600 3.333 2.500 2.001 80% 7%
Date of A.A 18.10.2017 Date of T.S 31.10.2017
Work order issued on 13.08.2018. Work is in
progress.
979 2582
Provision of Drainage and Soling and Replacement
/ new Water Supply Pipelines in UC 18 District T.T.
Singh.
Toba Tek SinghOn-going
Schemes13.000 7.465 1.833 1.375 1.200 87% 67%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
980 2583
Provision of Drainage and Soling and Replacement
/ new Water Supply Pipelines in UC 34 District T.T.
Singh.
Toba Tek SinghOn-going
Schemes12.500 6.225 2.083 1.562 1.042 67% 58%
1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
981 2584
Laying of Soling, Resoling, Drain, Repair of Roads
and Piplelines Water and Sewerage in District
T.T.Singh.
Toba Tek SinghOn-going
Schemes315.000 65.000 3.333 2.500 1.900 76% 21%
1-Date of A.A 28.09.2017 2- Date of T.S 19.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
982 2585
Laying of PCC, Tuff Tiles, Soling and Resoling,
Drain, Repair of Roads and Pipelines of water and
Sewerage in District T.T.Singh.
Toba Tek SinghOn-going
Schemes85.000 34.899 1.000 1.667 1.650 99% 43%
1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 - 11-Re-appropriation of funds (+/-)
Work in progress.
983 2586
Rehablitation of Rural Water Supply Scheme Chak
# 148/ GB, 149/GB, 151/GB ,153/GB, Balgn,
294/JB, 350/GB, Rural Water Supply Scheme
Chak # 258/GB Noor Mahal and 292/GB Bara
Rasla in District T.T.Singh.
Toba Tek SinghOn-going
Schemes185.086 40.000 3.333 2.500 2.000 80% 23%
1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary 7006 Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
984 2587
Rehabalitation of Rural Water Supply Scheme
Chak # 402/JB Virkan348/GB Bajra, 296/GB,
297/GB, 299/GB, 290/GB, 349/GB, and 351/GB in
District T.T.Singh.
Toba Tek SinghOn-going
Schemes178.792 68.399 3.333 3.000 2.167 72% 39%
1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -4383 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
985 2588Water Supply Scheme in Chak no. 374/JB, 387/JB,
385/JB, District T.T.Singh.Toba Tek Singh
On-going
Schemes35.000 11.964 3.333 2.500 2.000 80% 40%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -3360 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
986 2589Drainage/Soling and Water Supply and Road
Repair UC No. 26 in District T.T.Singh.Toba Tek Singh
On-going
Schemes12.000 6.000 2.000 1.500 0.980 65% 58%
1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
987 2590Drainage/Soling and Water Supply and Road
Repair UC No. 28 in District T.T.Singh.Toba Tek Singh
On-going
Schemes12.000 5.956 2.000 1.500 0.985 66% 58%
1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
988 2591Drainage/Soling and Water Supply and Road
Repair UC No. 32 in District T.T.Singh.Toba Tek Singh
On-going
Schemes12.000 6.000 2.000 1.500 0.970 65% 58%
1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
989 2592Drainage/Soling and Water Supply and Road
Repair UC No. 30 in District T.T.Singh.Toba Tek Singh
On-going
Schemes12.000 5.984 2.000 1.500 0.967 64% 58%
1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
990 2593
Rural Water Supply Scheme Chak No. 321/GB
Khumanwala Tehsil Pirmahal District Toba Tek
Singh, Chak No. 700/42 GB Pir Kadhiana –
Christian Colony Tehsil Pirmahal District Toba Tek
Singh, Chak No. 294/GB azafi abadi Tehsil &
District Toba Tek Singh.
Toba Tek SinghOn-going
Schemes49.970 17.999 5.000 3.750 3.500 93% 43%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -5847 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
991 2594
Rehabilitation of Rural Water Supply Scheme
Chak No. 301/GB azafi abadi – New Chak Tehsil &
District Toba Tek Singh, Chak No. 303/GB azafi
abadi Tehsil & District Toba Tek Singh, Chak No.
333/GB, District Toba Tek Singh, Chak No.
341/GB Tehsil & District
Toba Tek SinghOn-going
Schemes72.396 20.000 3.333 2.500 1.665 67% 30%
1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 22.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
992 2595
Extension / Rehabilitation Rural Water Supply
Scheme Chak No.325 and 326/ GB, District T.T
Singh.
Toba Tek SinghOn-going
Schemes24.600 19.000 1.867 0.600 0.400 67% 79%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - 13647 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
993 2596Rural Water Supply Scheme Chak No. 671/12-
GBDistrict T.T. Singh.Toba Tek Singh
On-going
Schemes21.500 15.000 2.167 2.425 2.000 82% 79%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - 4716 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
994 2597Rural Water Supply Scheme Chak No.711/GB
District T.T. Singh.Toba Tek Singh
On-going
Schemes15.400 7.000 2.800 0.795 0.095 12% 46%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -5309 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work could not be started due to site
problem.
995 2598Rural Water Supply Scheme Chak No.662/3-GB
District T.T. Singh.Toba Tek Singh
On-going
Schemes29.500 10.000 3.333 2.500 1.667 67% 40%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - 8625 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
996 2599Rural Water Supply Scheme Chak No706/GB.
District T.T. SinghToba Tek Singh
On-going
Schemes27.300 11.998 5.100 3.825 2.500 65% 53%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - 6164 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
997 2600Rural Water Supply Scheme Chak No.720/GB
District T.T. Singh.Toba Tek Singh
On-going
Schemes24.750 17.000 2.583 1.937 1.500 77% 75%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -11853 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
998 2601Rural Water Supply Scheme Chak No.721/GB
District T.T. Singh.Toba Tek Singh
On-going
Schemes25.700 14.799 3.633 2.725 1.800 66% 65%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -8765 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work in progress.
999 2602Rural Water Supply Scheme Chak No.722/GB
District T.T. SinghToba Tek Singh
On-going
Schemes23.500 13.999 3.167 0.885 0.094 11% 60%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary -6826 Person 10-Funds Released by
F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation
of funds (+/-) Work could not be started due to site
problem.
1000 2603
Water Supply Scheme Chak No. 317/JB and
Installation of Filtration Plant in Chak No.401/JB
District T.T.Singh
Toba Tek SinghOn-going
Schemes24.587 10.000 4.862 3.647 3.200 88% 54%
1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018
3-Date of Prequalification 4-Date of invitation of
tenders 05.03.2018 5- Date of Receipt of tenders
06.03.2018 6- Date of work order 27.03.2018 7-
Date of completion as per PC-I 8- Anticipated date
of completion 9- No. of Beneficiary -.. Person 10-
Funds Released by F.D 03.08.2018 & 24.01.2019
11-Re-appropriation of funds (+/-) Work in progress.
1001 2604
Rehabilitation / Improvemnet of Rural Draiange
Scheme Chak no. 402/GB Virkan Tehsil and
District T.T.Singh
Toba Tek SinghOn-going
Schemes35.000 3.999 1.667 1.250 0.834 67% 14%
1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018
3-Date of Prequalification 4-Date of invitation of
tenders 05.03.2018 5- Date of Receipt of tenders
06.03.2018 6- Date of work order 03.04.2018 7-
Date of completion as per PC-I 8- Anticipated date
of completion 9- No. of Beneficiary -.. Person 10-
Funds Released by F.D 03.08.2018 & 24.01.2019
11-Re-appropriation of funds (+/-) Work in progress.
1002 2605
Provision of Soling / Re-Soling Nali / Sewerage /
PCC and Tuff Tile Schemes in City Kamalia In
District T.T.Singh
Toba Tek SinghOn-going
Schemes20.000 9.998 3.333 2.500 2.200 88% 61%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1003 2606
Soling Drainage Khalla Nalli and Pullian in UC 57,
58, 59, 60, 61, 62, 63, 66, 68, Chak No. 735/GB in
Tehsil Kamalia District T.T.Singh
Toba Tek SinghOn-going
Schemes60.000 20.000 3.333 2.500 2.000 80% 37%
1-Date of A.A 19.09.2017 2- Date of T.S 12.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 18.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1004 2607Tuff Tile PCC Soling / Drainage / Sewerage in
Kamalia City Tehsil Kamalia District T.T.Singh Toba Tek Singh
On-going
Schemes40.000 13.662 1.667 1.250 0.834 67% 36%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1005 2608Tuff Tile PCC Soling / Re-soling Drainag,
Sewerage etc for Kamalia City Toba Tek Singh
On-going
Schemes40.000 14.999 1.667 1.250 1.000 80% 40%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1006 2609Construction of PCC / Tuff tile/Soling/Resoling
Pirmahal City in District T.Tsingh Toba Tek Singh
On-going
Schemes25.000 10.000 5.000 3.750 3.000 80% 52%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1007 2610
Provision of Drainage and Soling and Replacement
/ new Water Supply Pipelines in UC 17 District T.T.
Singh.
Toba Tek SinghOn-going
Schemes32.000 12.000 1.667 1.250 1.000 80% 41%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-). Work in progress.
1008 2611Provision of Tuff Paver and Drains in Kamalia City,
District T.T.SinghToba Tek Singh
On-going
Schemes40.000 15.000 1.667 9.451 9.451 100% 61%
1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 11-Re-appropriation of
funds (+/-) Work in progress.
1009 2612Provision of Tuff Paver and Drains in Pir Mahal
City, District T.T.Singh.Toba Tek Singh
On-going
Schemes40.000 15.000 1.667 0.483 0.300 62% 38%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1010 2613
Provision of Drainage and Soling and Replacement
/ new Water Supply Pipelines in UC 14 District T.T.
Singh.
Toba Tek SinghOn-going
Schemes15.000 7.500 2.500 1.875 1.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1011 2614
Provision of Drainage and Soling and Replacement
/ new Water Supply Pipelines in UC 15 District T.T.
Singh.
Toba Tek SinghOn-going
Schemes31.000 20.000 3.333 2.500 1.667 67% 70%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1012 2615
Provision of Drainage and Soling and Replacement
/ new Water Supply Pipelines in UC 16 District T.T.
Singh.
Toba Tek SinghOn-going
Schemes13.000 7.500 1.833 1.375 0.912 66% 65%
1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1013 2616Rural Drainage/Brick Pavement/Resoling Chak No.
672/13 GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.455 0.500 0.375 0.249 66% 57%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1014 2617
Rural Drainage/Brick Pavement/Resoling Chak No.
673/14/GB Harisabad & azafi abadi in District
T.Tsingh
Toba Tek SinghOn-going
Schemes3.000 1.422 0.500 0.375 0.250 67% 56%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1015 2618Rural Drainage/Brick Pavement/Resoling Chak No.
675/16/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) .Work in progress.
1016 2619Rural Drainage/Brick Pavement/Resoling Chak No.
676/17/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.498 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1017 2620Rural Drainage/Brick Pavement/Resoling Mouza
Shahpur & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.000 0.667 0.500 0.334 67% 44%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1018 2621Rural Drainage/Brick Pavement/Resoling Mouza
Nakrari & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 0.997 0.667 0.500 0.334 67% 44%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1019 2622Rural Drainage/Brick Pavement/Resoling Mouza
Bub & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes2.500 0.952 1.548 1.161 0.700 60% 66%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
23.11.2018 - 11-Re-appropriation of funds (+/-)
Work in progress.
1020 2623Provision of Sewerage / Drainage / Tuff Tiles etc in
District T.T.Singh.Toba Tek Singh
On-going
Schemes199.924 99.996 5.000 3.750 2.500 67% 51%
1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 18.11.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1021 2624Rural Drainage/Brick Pavement/Resoling Plot-A &
azafi abadi in District T.TsinghToba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1022 2625Rural Drainage/Brick Pavement/Resoling Chak No.
718/GB & azafi abadi in District T.TsinghToba Tek Singh
On-going
Schemes3.000 1.499 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1023 2626Rural Drainage/Brick Pavement/Resoling Chak No.
719/GB & azafi abadi in District T.TsinghToba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1024 2627Rural Drainage/Brick Pavement/Resoling Chak No.
720/GB & azafi abadi in District T.TsinghToba Tek Singh
On-going
Schemes3.000 1.478 0.500 0.375 0.247 66% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1025 2628Rural Drainage/Brick Pavement/Resoling Chak No.
722/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.244 65% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1026 2629Rural Drainage/Brick Pavement/Resoling Chak No.
741/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.020 0.500 0.375 0.245 65% 42%
1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1027 2630Rural Drainage/Brick Pavement/Resoling Chak No.
747/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 0.595 0.500 0.375 0.246 66% 28%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1028 2631Rural Drainage/Brick Pavement/Resoling Chak No.
757/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes2.500 1.204 0.417 0.313 0.200 64% 56%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1029 2632Rural Drainage/Brick Pavement/Resoling Chak No.
759/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.248 66% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) .Work in progress.
1030 2633Rural Drainage/Brick Pavement/Resoling Chak No.
760/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes2.500 1.250 0.417 0.313 0.203 65% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1031 2634Rural Drainage/Brick Pavement/Resoling Chak No.
764/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1032 2635Rural Drainage/Brick Pavement/Resoling Chak No.
660/1/GB & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) Work in progress.
1033 2636Rural Drainage/Brick Pavement/Resoling Mouza
Inayat Shah & azafi abadi in District T.Tsingh Toba Tek Singh
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017
3-Date of Prequalification 4-Date of invitation of
tenders 5- Date of Receipt of tenders 6- Date of
work order 31.10.2017 7- Date of completion as per
PC-I 8- Anticipated date of completion 9- No. of
Beneficiary - Person 10-Funds Released by F.D
03.08.2018 & 24.01.2019 - 11-Re-appropriation of
funds (+/-) . Work in progress.
1034 2637Constructoin of Drains PCC / RCC in UC Qila Mian
Singh Uggu Chak District Gujranwala Gujranwala
On-going
Schemes50.000 13.000 5.000 3.750 2.500 67% 31% Work in progress
1035 2638Sewerage PCC Drainage in UC Wahndo / UC
Chak Ramdas in District Gujranwala Gujranwala
On-going
Schemes60.000 19.991 6.667 5.000 3.334 67% 39% Work in progress
1036 2639
Construction of PCC and Sewerage at Y-Block
Peoples Colony, X-Block Behari Colony, Shadman
Town, Green Town Ahsan Town, Hassan Town
District Gujranwala
GujranwalaOn-going
Schemes20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress
1037 2640
Construction of PCC and Sewerage at Kot
Abdullah, Kangni Wala, Rana Colony, Saddique
Colony, Nabi Pura, Illama Iqbal Town in District
Gujranwala
GujranwalaOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress
1038 2641
Provision of Sewerage, PCC, Street, Drain, Tuff
Tile, Water Supply in City Wazirabad, Sodra,
District Gujranwala
GujranwalaOn-going
Schemes200.000 75.000 3.333 2.500 1.667 67% 38% Work in progress
1039 2642
Drainage and PCC Soling in UCs Nokhar,
Pheloke, Udowali, in Saharan Chatha District
Gujranwala
GujranwalaOn-going
Schemes88.947 19.901 3.333 2.500 1.667 67% 24% Work in progress
1040 2643
Drainage and PCC Soling in UCs Noi wala, Jattan
wali, Bheri Shah Rehman, Jhallan in District
Gujranwala
GujranwalaOn-going
Schemes89.034 17.820 3.333 2.500 1.667 67% 22% Work in progress
1041 2644
Drainage and PCC Soling in UCs Phama Sara,
Arghan, Chak Chaudhary, Kot Ladha, in District
Gujranwla
GujranwalaOn-going
Schemes89.776 20.000 3.333 2.500 1.667 67% 24% Work in progress
1042 2645
Construction of PCC Streets and Drainage in
Botala Sharam Singh / Akbarian, Sansera Goraya
and Muslim Chack, Attawa, Therri Sansi and
Chand da Qila, Kotli Dianat Raye and Sheray wala,
Nangray Dadan, Dera Bhaghat Singh and Dera
Hakam Singh, Chddiala Kalan and Khurd, Murali
wala and Khuwasra, Dhillian wali, Chianwall, Kot
Shera and Sahnaya wala
GujranwalaOn-going
Schemes50.000 20.000 30.000 22.500 15.000 67% 70% Work in progress
1043 2646
Construction of PCC and Sewerage at sarfaraz
Colony, Hashimi Colony, Gulshan Adeel, Mumtaz
Colony, Karmabad District Gujranwala
GujranwalaOn-going
Schemes40.000 15.000 1.667 1.250 0.834 67% 40% Work in progress
1044 2647
Construction of PCC and Sewerage at Asghar
Colony, Salamat Pura, Allah Bukhsh Colony,
Nawaz Colony, Faisal Colony District Gujranwala
GujranwalaOn-going
Schemes40.000 15.000 1.667 1.250 0.834 67% 40% Work in progress
1045 2648
Construction of PCC and Sewerage at Jinnah
Colony, Rehman Colony, Ali Pura, Bukhari Colony,
Sanat Road, Jamia Muhammadiya District
Gujranwala
GujranwalaOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress
1046 2649
Construction of PCC and Sewerage at Rasheed
Colony, Ismail Pura, Abdullah Colony, W Block
Peoples Colony District Gujranwala
GujranwalaOn-going
Schemes20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress
1047 2650
Construction of PCC and Sewerage at Z- Block
Peoples Colony, X-Block Peoples Colony District
Gujranwala
GujranwalaOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress
1048 2651
Construction of PCC and Sewerage at Chamra
Mandi, Wahdat Colony, Chaman Shah Road, Taj
Colony, Arfat Colony, Ferozwala Road in District
Gujranwala
GujranwalaOn-going
Schemes20.000 9.910 3.333 2.500 1.667 67% 58% Work in progress
1049 2652
Construction of PCC and Sewerage at Arfat
Colony, Islam Pura, Haidry Road in District
Gujranwala
GujranwalaOn-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress
1050 2653
Construction of PCC and Sewerage at Mujahid
Pura, Camp No. 4, Saithy Palaza, Faisal Colony,
in District Gujranwala
GujranwalaOn-going
Schemes15.000 9.999 1.667 1.250 0.834 67% 72% Work in progress
1051 2654
Construction of PCC and Sewerage at Galla
Ghulam Thakedar Wala, Galla Mehar Noor Wala,
Islam Pura, Muslim Road in District Gujranwala
GujranwalaOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress.
1052 2655Drainage and PCC at UC, 31,40,46 at District
Gujranwala Gujranwala
On-going
Schemes150.000 29.998 5.000 3.750 2.500 67% 22% Work in progress
1053 2656Construction of PCC/ Tuff Tile, Drainage and Allied
Facilities etc in NA-96, District GujranwalaGujranwala
On-going
Schemes50.000 29.987 3.333 2.500 1.667 67% 63% Work in progress
1054 2657Construction of PCC, Sewerage/Drains at UC 48
District Gujranwala Gujranwala
On-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress
1055 2658Construction of PCC, Sewerage/Drains at UC 49
District Gujranwala Gujranwala
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress
1056 2659Construction of PCC, Sewerage/Drains at UC 50
District Gujranwala Gujranwala
On-going
Schemes15.000 9.948 1.667 1.250 0.834 67% 72% Work in progress
1057 2660Construction of PCC, Sewerage/Drains at UC 51
District Gujranwala Gujranwala
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress
1058 2661Construction of PCC, Sewerage/Drains at UC 52
District Gujranwala Gujranwala
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress
1059 2662Construction of PCC, Sewerage/Drains at UC 53
District Gujranwala Gujranwala
On-going
Schemes20.000 9.920 3.333 2.500 1.667 67% 58% Work in progress
1060 2663Construction of PCC, Sewerage/Drains at UC 54
District Gujranwala Gujranwala
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress
1061 2664Construction of PCC, Sewerage/Drains at UC 57
District Gujranwala Gujranwala
On-going
Schemes20.000 9.982 3.333 2.500 1.667 67% 58% Work in progress
1062 2665Construction of PCC, Sewerage/Drains at UC 58
District Gujranwala Gujranwala
On-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress
1063 2666Construction of PCC, Sewerage/Drains at UC 59
District Gujranwala Gujranwala
On-going
Schemes20.000 9.954 3.333 2.500 1.667 67% 58% Work in progress
1064 2667Construction of PCC, Sewerage/Drains at UC 60
District Gujranwala Gujranwala
On-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress
1065 2668Construction of PCC, Sewerage/Drains at UC 62
District Gujranwala Gujranwala
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress
1066 2669
Provision of Sewerage, Drainage and PCC
Scheme UC Aroop, UC Butteranwali, District
Gujranwala, Phase-I
GujranwalaOn-going
Schemes200.000 40.000 3.333 2.500 1.667 67% 21% Work in progress
1067 2670
Provision of Sewerage, Drainage and PCC
Scheme for Area Rahwali Sharqi, Kot Shahan And
Trigri District Gujranwala
GujranwalaOn-going
Schemes100.000 30.000 3.333 2.500 1.667 67% 32% Work in progress
1068 2671Construction of PCC/RCC/Drainage at
Shaheenabad, Gujranwala Gujranwala
On-going
Schemes30.000 7.992 20.000 15.000 10.000 67% 60% Work in progress
1069 2672Construction of PCC/RCC/Drainage at Pasban
Colony, GujranwalaGujranwala
On-going
Schemes50.000 15.000 3.333 2.500 1.667 67% 33% Work in progress
1070 2673Construction of PCC/RCC/Drainage at Samnabad,
GujranwalaGujranwala
On-going
Schemes50.000 15.000 3.333 2.500 1.667 67% 33% Work in progress
1071 2674Construction of PCC/RCC/Drainage at
Gondalwala, GujranwalaGujranwala
On-going
Schemes30.000 7.000 3.333 2.500 1.667 67% 29% Work in progress
1072 2675Construction of PCC/RCC/Drainage at Aminpur,
GujranwalaGujranwala
On-going
Schemes30.000 7.989 3.333 2.500 1.667 67% 32% Work in progress
1073 2676Construction of PCC/RCC/Drainage at Badoki
Gusaian, GujranwalaGujranwala
On-going
Schemes30.000 8.000 3.333 2.500 1.667 67% 32% Work in progress
1074 2677Construction of PCC/RCC/Drainage at
Dingranwali, GujranwalaGujranwala
On-going
Schemes30.000 8.000 3.333 2.500 1.667 67% 32% Work in progress
1075 2678
Provision of PCC / Sewerage schemes near
Bypass Surrounding Abadies of Timber Market,
District Gujranwala
GujranwalaOn-going
Schemes190.600 40.000 30.000 22.500 15.000 67% 29% Work in progress
1076 2679Constructoin of Drains PCC / RCC in UC Kalaskay,
Banka, Ladheywala Cheema District Gujranwala Gujranwala
On-going
Schemes50.000 13.000 5.000 3.750 2.500 67% 31% Work in progress
1077 2680
Construction of Drains, PCC/RCC and Sullage
Carrier in Villages of U.C Chianwali in District
Gujranwala
GujranwalaOn-going
Schemes30.000 9.848 8.333 6.250 4.167 67% 47% Work in progress
1078 2681
Construction of Drains, PCC/RCC and Sullage
Carrier in Villages of U.C Ladhaywala Goraya in
District Gujranwala
GujranwalaOn-going
Schemes30.000 9.970 20.000 15.000 10.000 67% 67% Work in progress
1079 2682Sewerage PCC Drainage in UC Malkay / UC Mari
Thakran / UC Ghoma in District Gujranwala Gujranwala
On-going
Schemes80.000 23.483 5.000 3.750 2.500 67% 32% Work in progress
1080 2683Sewerage PCC Drainage in UC Talwandi MK / UC
Jandiala in District Gujranwala Gujranwala
On-going
Schemes60.000 29.963 5.000 3.750 2.500 67% 54% Work in progress
1081 2684Water Supply / PCC / Drainage Facility in Sodhrar
Town, Tehsil Wazirabad, District GujranwalaGujranwala
On-going
Schemes134.586 18.000 20.000 26.218 21.218 81% 29% Work in progress
1082 2685Construction of Streets and Drainage at UC Marri
Thakran, District Gujranwala Gujranwala
On-going
Schemes30.000 9.975 3.333 2.500 1.667 67% 39% Work in progress
1083 2686Construction of Streets and Drainage at UC Akbar
Ghanoke, District Gujranwala Gujranwala
On-going
Schemes30.000 9.972 3.333 2.500 1.667 67% 39% Work in progress
1084 2687Construction of Streets and Drainage at UC
Ghaniya District Gujranwala Gujranwala
On-going
Schemes30.000 9.988 3.333 2.500 1.667 67% 39% Work in progress
1085 2688Construction of Streets and Drainage at UC Guna
Aur District Gujranwala Gujranwala
On-going
Schemes30.000 9.947 3.333 2.500 1.667 67% 39% Work in progress
1086 2689Construction of Streets and Drainage at UC
Ghoma/Harpoki District Gujranwala Gujranwala
On-going
Schemes30.000 9.997 6.667 5.000 3.334 67% 44% Work in progress
1087 2690Construction of Streets and Drainage at UC
Machrala District Gujranwala Gujranwala
On-going
Schemes30.000 9.958 3.333 2.500 1.667 67% 39% Work in progress
1088 2691Construction of Streets and Drainage at UC Sadoki
District Gujranwala Gujranwala
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in progress
1089 2692Provision of Clean Water Facility in NA-95, District
GujranwalaGujranwala
On-going
Schemes200.000 66.995 5.000 3.750 2.500 67% 35% Work in progress
1090 2693Constructoin of Drains PCC / RCC in UC Botal
Jhanda Singh District Gujranwala Gujranwala
On-going
Schemes32.000 12.500 1.667 1.250 0.834 67% 42% Work in progress
1091 2694Sewerage PCC Drainage in UC Mokhal / UC
Nadala / UC Feroz wala in District Gujranwala Gujranwala
On-going
Schemes80.000 23.412 3.333 2.500 1.667 67% 31% Work in progress
1092 2695Sewerage PCC Drainage in UC Nangal Dona / UC
Machrala in District Gujranwala Gujranwala
On-going
Schemes80.000 23.345 3.333 2.500 1.667 67% 31% Work in progress
1093 2696Sewerage PCC Drainage in UC Sohawa / UC Kali
Suba in District Gujranwala Gujranwala
On-going
Schemes60.000 19.898 3.333 2.500 1.667 67% 36% Work in progress
1094 2697Sewerage PCC Drainage in UC Sadhoki / UC
Gunaur / UC Mandiala Tega in District Gujranwala Gujranwala
On-going
Schemes80.000 23.473 5.000 3.750 2.500 67% 32% Work in progress
1095 2698
Construction of Drains,PCC Sullage Carrier UC
Budha Graya Tehsil Nowshera Virkan District
Gujranwala
GujranwalaOn-going
Schemes20.000 9.953 3.333 2.500 1.667 67% 58% Work in progress
1096 2699
Construction of Drains,PCC Sullage Carrier UC
Boopra Kalan Tehsil Nowshera Virkan District
Gujranwala
GujranwalaOn-going
Schemes20.000 9.897 3.333 2.500 1.667 67% 58% Work in progress
1097 2700
Construction of Drains,PCC Sullage Carrier UC
Tatlay Aali Tehsil Nowshera Virkan District
Gujranwala
GujranwalaOn-going
Schemes20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress
1098 2701
Construction of Drains,PCC Sullage Carrier UC
Matto Bbajme Tehsil Nowshera Virkan District
Gujranwala
GujranwalaOn-going
Schemes20.000 9.858 3.333 2.500 1.667 67% 58% Work in progress
1099 2702
Construction of Drains,PCC Sullage Carrier UC
Karyl Kalan Tehsil Nowshera Virkan District
Gujranwala
GujranwalaOn-going
Schemes20.000 9.997 3.333 2.500 1.667 67% 58% Work in progress
1100 2703
Provision of PCC / Sewerage / Drainage /Tuff Tiles
and allied facilities etc. in NA-101, District
Gujranwala
GujranwalaOn-going
Schemes100.000 28.000 5.000 3.750 2.500 67% 31% Work in progress
1101 2704
Provision of Water Filtration Plant / Drainage
System Chak Chatha U/C no. 15, District
Hafizabad
HafizabadOn-going
Schemes30.860 10.000 3.333 2.500 1.667 67% 38%
A.A.30.860 (M) T.S. 30.860 (M) work is in progress
Fund release but not yet online.
1102 2705
Constrcutinn of Drain / Nallah / PCC / Soling
Bateray, Kotli Amir Singh, Kallairwala, Muradian
U/C Sagar Khan, no. 12, District Hafizabad
HafizabadOn-going
Schemes50.000 19.999 3.333 2.500 1.667 67% 43%
A.A. 50.000 (M)T.S. 50.000 (M) work is in progress
Fund release but not yet online.
1103 2706Constrcutinn of Drain / Nallah / PCC / Soling U/C
No. 5, District HafizabadHafizabad
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43%
A.A. 50.000 (M) T.S. 50.000 (M) work is in progress
Fund release but not yet online.
1104 2707Constrcutinn of Drain / Nallah / PCC / Soling U/C
No. 14, District HafizabadHafizabad
On-going
Schemes50.000 19.810 3.333 4.167 3.334 80% 46%
A.A. 50.000 (M) T.S. 50.000 (M) work is in progress
Fund release but not yet online.
1105 2708
Constrcutinn of Drain / Nallah / PCC / Soling and
Sewer in village Vanike Tarar U/C No. 3, District
Hafizabad
HafizabadOn-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43%
A.A. 50.000 (M) T.S. 50.000 (M) work is in progress
Fund release but not yet online.
1106 2709
Rural Drainage Scheme Herdo Sagar, Dhnoi
Dogran, Praim Kot, Batairay, Wingay and
Bashmolajat District Hafizabad
HafizabadOn-going
Schemes25.005 10.000 5.002 2.352 1.090 46% 44%
A.A. 25.002 (M) T.S. 25.002 (M) work is in progress
Fund release but not yet online.
1107 2710
Rural Drainage Scheme Dhunni, Jaidkey, Chak
Chatha, Dahranwali, Thatha, Kharian, Peer Koot
and Bashmolajat District Hafizabad
HafizabadOn-going
Schemes25.002 9.999 5.001 3.751 2.490 66% 50%
A.A. 25.002 (M) T.S.25.002 (M) work is in progress
Fund release but not yet online.
1108 2711Construction of Streets Drains PCC/ Soling and
Nallah In Vilaage Kassesy District Hafizabad Hafizabad
On-going
Schemes20.000 10.000 3.333 4.000 1.667 42% 58%
A.A. 20.000 (M) T.S. 20.000 (M)work is in progress
Fund release but not yet online.
1109 2712Construction of Streets Drains PCC/ Soling and
Nalla In Village Tibba Shah Balol District Hafizabad Hafizabad
On-going
Schemes20.000 9.925 3.333 2.500 1.660 66% 58%
A.A. 20.000 (M) T.S. 20.000 (M) work is in progress
Fund release but not yet online.
1110 2713Construction of Streets Drains PCC/ Soling and
Nallah In Village Kot Khush hall District Hafizabad Hafizabad
On-going
Schemes20.000 9.978 3.333 2.500 1.660 66% 58%
A.A. 20.000 (M)T.S.20.000 (M) work is in progress
Fund release but not yet online.
1111 2714
Construction of Streets Drains PCC/ Soling and
Nallah In Village Tali Goraya and Jasso ke District
Hafizabad
HafizabadOn-going
Schemes25.000 9.763 5.000 3.750 2.490 66% 49%
A.A. 25.000 (M) T.S. 25.000 (M) work is in progress
Fund release but not yet online.
1112 2715
Construction of Streets Drains PCC/ Soling and
Nallah In Village Narowal Dera Jaat District
Hafizabad
HafizabadOn-going
Schemes20.000 10.000 3.333 2.500 1.660 66% 58%
A.A. 20.000 (M) T.S. 20.000 (M) work in progress.
Fund release but not yet online.
1113 2716Construction of Streets Drains PCC/ Soling and
Nallah In Village Chak No. 474 District Hafizabad Hafizabad
On-going
Schemes15.000 10.000 1.667 1.250 0.830 66% 72%
A.A. 15.000 (M) T.S. 15.000 (M) work is in progress
Fund release but not yet online.
1114 2717Construction of Streets Drains PCC/ Soling and
Nallah In Village Matay Ke District Hafizabad Hafizabad
On-going
Schemes15.000 9.719 1.667 0.750 0.330 44% 67%
A.A. 15.000 (M) T.S. 15.000 (M) work is in progress
Fund release but not yet online.
1115 2718Construction of Streets Drains PCC/ Soling and
Nallah In Village Badr Ali District Hafizabad Hafizabad
On-going
Schemes15.000 9.942 1.667 1.250 0.830 66% 72%
A.A. 15.000 (M) T.S.15.000 (M) work is in progress
Fund release but not yet online.
1116 2719Construction of Streets Drains PCC/ Soling and
Nallah In Village Mustafa Abad District Hafizabad Hafizabad
On-going
Schemes15.000 9.959 1.667 2.284 1.034 45% 73%
A.A. 15.000 (M) T.S.15.000 (M) work is in progress
Fund release but not yet online.
1117 2720Provision of Water Filtration Plant / Drainage
System Kolo Tarar U/C no. 8, District Hafizabad Hafizabad
On-going
Schemes36.585 11.209 3.333 2.500 1.660 66% 35%
A.A. 36.585 (M) T.S.36.585 (M) work is in progress
Fund release but not yet online.
1118 2721
Provision of Water Filtration Plant / Drainage
System Kot Said Muhammad U/C No. 1, District
Hafizabad
HafizabadOn-going
Schemes31.854 11.999 3.333 2.500 1.667 67% 43%
A.A. 31.854 (M) T.S.31.854 (M) work is in progress
Fund release but not yet online.
1119 2722Provision of Water Filtration Plant / Drainage
System, Kot Ishaq U/C No. 2, District Hafizabad Hafizabad
On-going
Schemes27.539 13.000 4.846 3.635 2.423 67% 56%
A.A. 27.539 (M) T.S.27.539 (M) work is in progress
Fund release but not yet online.
1120 2723Provision of Water Filtration Plant / Drainage
System Vanike Tarar U/C No. 3, District Hafizabad Hafizabad
On-going
Schemes61.830 20.000 6.667 5.000 3.330 67% 38%
A.A. 61.830 (M) T.S.61.830 (M) work is in progress
Fund release but not yet online.
1121 2724Provision of Water Filtration Plant / Drainage
System Alaudinkey U/C no. 4, District Hafizabad Hafizabad
On-going
Schemes38.225 15.920 3.333 2.500 1.660 66% 46%
A.A. 38.225 (M) T.S.38.225 (M) work is in progress
Fund release but not yet online.
1122 2725Provision of Water Filtration Plant / Drainage
System Sooianwala U/C No. 5, District Hafizabad Hafizabad
On-going
Schemes33.136 11.907 3.333 2.500 1.667 67% 41%
A.A. 33.136(M) T.S.33.136 (M) work is in progress
Fund release but not yet online.
1123 2726
Provision of Water Filtration Plant / Drainage
SystemRamke Chatha U/C no. 6, District
Hafizabad
HafizabadOn-going
Schemes31.145 12.000 3.333 2.500 1.667 67% 44%
A.A. 31.145(M) T.S.31.145 (M) work is in progress
Fund release but not yet online.
1124 2727
Provision of Water Filtration Plant / Drainage
System Dhiranke Lalke U/C no. 7, District
Hafizabad
HafizabadOn-going
Schemes42.320 20.000 3.333 2.500 1.667 67% 51%
A.A. 42.320(M) T.S.42.320 (M) work is in progress
Fund release but not yet online.
1125 2728
Provision of Water Filtration Plant / Drainage
System Sandhwan Tarar U/C no. 9, District
Hafizabad
HafizabadOn-going
Schemes32.850 12.000 3.333 2.500 1.667 67% 42%
A.A. 32.850(M) T.S.32.850 (M) work is in progress
Fund release but not yet online.
1126 2729Provision of Water Filtration Plant / Drainage
System Pind Bawray U/C no. 10, District Hafizabad Hafizabad
On-going
Schemes30.049 10.000 3.333 2.500 1.667 67% 39%
A.A. 30.049(M) T.S.30.049 (M) work is in progress
Fund release but not yet online
1127 2730
Provision of Water Filtration Plant / Drainage
System Sagar Kalan U/C No. 12, District
Hafizabad
HafizabadOn-going
Schemes28.414 10.000 6.138 4.604 3.069 67% 46%
A.A. 32.850(M) T.S.32.850 (M) work is in progress
Fund release but not yet online.
1128 2731Provision of Water Filtration Plant / Drainage
System Dhunni U/C No. 14, District Hafizabad Hafizabad
On-going
Schemes34.675 11.996 3.333 0.833 0.000 0% 35%
A.A. 34.675(M) T.S.34.675 (M) work is in progress
Fund release but not yet online.
1129 2732Provision of Water Filtration Plant / Drainage
System Kalianwala U/C no. 11, District Hafizabad Hafizabad
On-going
Schemes29.334 12.000 5.778 2.684 1.280 48% 45%
A.A.29.334(M) T.S.29.334 (M) work is in progress
Fund release but not yet online.
1130 2733Provision of Water Filtration Plant / Drainage
System Karyala U/C no. 19, District Hafizabad Hafizabad
On-going
Schemes28.045 12.000 5.348 7.061 5.724 81% 63%
A.A. 28.045(M) T.S.28.045(M) work is in progress
Fund release but not yet online.
1131 2734Provision of Water Filtration Plant / Drainage
System kassoke U/C no. 20, District Hafizabad Hafizabad
On-going
Schemes34.935 12.000 3.333 2.500 1.660 66% 39%
A.A. 34.935(M) T.S.34.935 (M) work is in progress
Fund release but not yet online.
1132 2735Provision of Water Filtration Plant / Drainage
System Vinni U/C no. 16, District Hafizabad Hafizabad
On-going
Schemes27.257 10.000 5.752 4.314 2.876 67% 47%
A.A. 27.257(M) T.S.27.257 (M) work is in progress
Fund release but not yet online.
1133 2736
Provision of Water Filtration Plant / Drainage
System Solangi Awan U/C no. 17, District
Hafizabad
HafizabadOn-going
Schemes29.376 10.000 3.333 2.500 1.660 66% 40%
A.A. 29.376(M) T.S.29.376 (M) work is in progress
Fund release but not yet online.
1134 2737Provision of Water Filtration Plant / Drainage
System Kot Nakka Hafizabad
On-going
Schemes47.862 19.864 3.333 2.500 1.667 67% 45%
A.A. 47.862(M) T.S.47.862 (M) work is in progress
Fund release but not yet online.
1135 2738Provision of Water Filtration Plant / Drainage
System Khana Bhattian Hafizabad
On-going
Schemes29.486 9.971 3.333 2.500 1.660 66% 39%
A.A. 29.486(M) T.S.29.486 (M) work is in progress
Fund release but not yet online.
1136 2739Provision of Water Filtration Plant / Drainage
System Thata Jhaid Amirwala Hafizabad
On-going
Schemes35.920 14.993 3.333 2.500 1.667 67% 46%
A.A. 35.920(M) T.S.35.920 (M) work is in progress
Fund release but not yet online.
1137 2740Provision of Water Filtration Plant / Drainage
System North Hafizabad
On-going
Schemes32.026 11.910 3.333 2.500 1.660 66% 42%
A.A. 32.026(M) T.S.32.026 (M) work is in progress
Fund release but not yet online.
1138 2741Provision of Water Filtration Plant / Drainage
System Kot Sarwer Hafizabad
On-going
Schemes53.655 20.000 3.333 2.500 1.650 66% 40%
A.A. 53.655(M) T.S.53.655 (M) work is in progress
Fund release but not yet online.
1139 2742Provision of Water Filtration Plant / Drainage
System Mowan Bhattian Hafizabad
On-going
Schemes25.650 10.000 5.217 3.913 2.600 66% 49%
A.A. 25.650(M) T.S.25.650 (M) work is in progress
Fund release but not yet online.
1140 2743Provision of Water Filtration Plant / Drainage
System Jalal Pur Bhattian in District Hafizabad Hafizabad
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39%
A.A. 30.000(M) T.S.30.000 (M) work is in progress
Fund release but not yet online.
1141 2744
Construction of PCC Street/ Drain, Soling and
Nullah in UC Fatta Band Tehsil Kharian District
Gujrat
GujratOn-going
Schemes20.027 10.000 3.342 2.507 1.671 67% 58%
A.A Date =28.7.2017.Drain Type-I=6937 Rft. PCC.
1:2:4=1000 Cft.Soling= 2741sft .Work in progress.
1142 2745
Construction of PCC Street/ Drain, Soling and
Nullah in U.C's Mirza Tahir, Nona Wali, Bumali,
Kolian Shah Hussain, Jora Kamana, Haji
Muhammad, Sikaryali, Chakori Bhailwal,
Warraichanwala, Nagranwala, Ali Chak, Kulewa,
Taplyala, Chak Pind in Tehsil Kharian
GujratOn-going
Schemes69.000 19.985 3.333 2.500 1.667 67% 31%
A.A Date =28.8.2017.Drain Type-I=6359 Rft. PCC.
1:2:4=43123 Cft.Soling= 8900 sft.Nullah 2x2=400
Rft.Work in progress.
1143 2746Provisino of Sewerage / Drainage / Soling etc in
Various UC's in PP-113, District GujratGujrat
On-going
Schemes50.000 25.000 1.667 1.250 0.834 67% 52%
A.A Date =28.8.2017.Drain Type-I=4629 Rft. PCC.
1:2:4=46666 Cft.Soling= 15646 sft .Nullah
2'x2'=100.Work in progress.
1144 2747
Exten: Construction of PCC Street / Drain, Soling,
Nullah and Eten: of Water Supply Scheme Fath
Bhand Tehsil Kharian District Gujrat
GujratOn-going
Schemes81.151 22.000 3.333 2.500 1.667 67% 29%
A.A Date =28.8.2017.1 Nos T/Well installed. Pipe
6"=10384 Rft, 4"=5678 Rft, 3'=14560 rft.
Soling=34508 sft, Nullah 2'x2'=1019 Rft. Work in
porgress.
1145 2748Rural Water Supply and Drainage Scheme Morala
Tehsil Kharian District Gujrat Gujrat
On-going
Schemes30.000 9.748 3.333 2.500 1.667 67% 38%
1 Nos T/Well installed.PVC Pipe of dias 3" =8032
Rft,4"= 5789 Rft,6"= 3074 Rft.PCC 6581 Cft. Work
in porgress.
1146 2749
Construction of PCC Street / Drain, Soling and
Nullah in U.C Gunjah, Thekarian Matwanawala,
Miana Chak, Punjan Khasana, Khawaspur,
Bhaddhar, Kotla Qasim Khan, Chakor Sher Ghazi,
Deona Mandi, 1 & 2 Dinga, Addowal, Saroki,
Machiana in Tehsil Kharian Distric
GujratOn-going
Schemes60.990 20.000 3.333 2.500 1.667 67% 36%
A.A Date =28.8.2017.Drain Type-I=9351 Rft. PCC.
1:2:4=41644 Cft.Soling= 17354 sft .Tuff
paver=4727. Work in progress.
1147 2750
Construction of PCC Street / Drain, Soling and
Nullah in U.C 1 to 4 Lalamusa City Tehsil Kharian
District Gujrat
GujratOn-going
Schemes18.400 10.000 2.800 2.100 1.400 67% 62%
A.A Date =28.7.2017.Drain Type-I= 1919 Rft. PCC.
1:2:4=18061 Cft .Tuff paver=16112. Work in
progress.
1148 2751
Construction of PCC Street/ Drain, Soling and
Nullah in Bagrianwala, Baho Ghaseet Pur, Sheikh
Sukha, Sabowal, Amra Kalan, Chak Jani in Tehsil
Kharian District Gujrat
GujratOn-going
Schemes27.604 15.000 3.333 2.500 1.667 67% 60%
A.A Date =28.7.2017.Drain Type-I=8360 Rft. PCC.
1:2:4=28683 Cft.Work in progress.
1149 2752
Provision of Streets and Drains in UC's Chak
Sada, Mandhiyala, Thatha Musa, Chopala, Bharaj,
Thim Ke, Manju Chak, Ikhlas Garh, Fateh Pur,
Daulta Nagar, Alam Garh, Doga, Chachian, Jaura
Jalalpur and Dhuma Malka District Gujrat
GujratOn-going
Schemes60.000 22.000 3.333 5.000 4.167 83% 44%
A.A Date =28.8.2017.Drain Type-I=11013 Rft. PCC.
1:2:4=52773 Cft.Sullage Carriar=1470 Rft.Work in
progress.
1150 2753Sewerage Scheme Jail Chowk to Bhimber Nullah,
Gujrat City District GujratGujrat
On-going
Schemes249.994 49.952 3.333 2.500 1.667 67% 21% A.A Date =17.3.2018.work in progress
1151 2754Construction of Nallahs in city Sarai Alamgir
District GujratGujrat
On-going
Schemes82.600 22.195 3.333 1.580 0.747 47% 28% PCC.1:2:4=63195 Cft.Work in progress.
1152 2755Provision of Sewerage / Drainage and streets / Tuff
Tiles etc in various UCs, District Gujrat Gujrat
On-going
Schemes480.000 44.979 6.667 13.420 11.754 88% 12%
A.A Date =29.12.2017.Drain Type-I=17111 Rft.
PCC. 1:2:4=95620Cft.Tuff paver= 53179 sft .Nullah
1.5'x1.5'=1078.RCC pavement=13422 cft.Work in
progress.
1153 2756
Sewerage / Drainage / PCC & Brick Pavement
Scheme in villages Adda PharIanwall, HaIgher
Khurd,Haslanwala,pindl Kalu,Loha Tibba ,Chak
Jano Khurd, Thatha Hast, Luk, Thatha Pheray,
Rajoa, Baghanwala,kot Sattar Duborji, Kotli Qazl,
Sandanwala, Charranwala a
Mandi
Bahauddin
On-going
Schemes30.000 11.977 3.333 4.500 3.667 81% 52%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
1154 2757
Sewerage / Drainage / PCC & Brick Pavement
Scheme in villages kailu, tuggal, channi syedian,
Ratoo, bahri, Chak Kamal, Melu Mahi Gheran,
Aghroa, Kotha Bhola, Maseetwali Komokay, Chak
Mitha, Heigherwala, Kot Phollay shah, Chak Zahir,
Bahu, Manga, Arzani, S
Mandi
Bahauddin
On-going
Schemes30.000 9.021 3.333 2.500 1.667 67% 36%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
1155 2758
Construction of Street Drains, Soling and PCC in
Village Gajjan, Slianman, Kot Hamid Shah, Jhanda
Chohan, Rasul Pur, Chicheranwali, Bhinder Kalan,
Bhinder Khurd, Chakora, Thatha Alia and Thatha
Naik District M B Din
Mandi
Bahauddin
On-going
Schemes23.000 8.494 4.333 3.250 2.167 67% 46%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
1156 2759
Construction of Street Drains, Soling and PCC in
Village Bhagat, Thathi Mureed Sahnpal, Channi
Sahnpal, Ranaml, Sharif Channi Mahram, Qila
Attar Singh, Ghagoki and Sarang District M B Din
Mandi
Bahauddin
On-going
Schemes26.500 14.991 3.833 3.375 2.417 72% 66%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
1157 2760
Construction of Street Drains, Soling and PCC in
Village Narrang, Saad Ullah Pur, Kot Pejo,
Karamawala, Dhudra, Long Charrhkey, Khoosar
and Pindi Dotharan District M B Din
Mandi
Bahauddin
On-going
Schemes26.000 9.541 5.333 5.390 4.057 75% 52%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
1158 2761
Construction of Street Drains, Soling and PCC in
Village Dhaul, Kotly Khurd, Khiyyan, Chak Jano
New Abadies, Addu Sarwani, Sheikh Alipur,
Ransikey, Pahrianwali, Sainthal and saida Saghar
District M B Din
Mandi
Bahauddin
On-going
Schemes31.500 9.595 7.167 9.825 8.034 82% 56%
* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start
Date. 06.01.2018* Completion date 05.01.2019*
Work in progress.
1159 2762Construction of PCC / Drainage, UC Chobara
District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1160 2763Construction of PCC / Drainage, US Kingra District
Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 1.000 0.698 70% 53% Work in progress.
1161 2764Construction of PCC / Drainage, UC Dogri District
Sialkot Sialkot
On-going
Schemes15.000 7.500 2.500 1.875 1.250 67% 58% Work in progress.
1162 2765Construction of PCC / Drainage, UC Balagan
District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1163 2766Construction of PCC / Drainage, UC Malipur
District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 1.500 0.987 66% 55% Work in progress.
1164 2767Construction of PCC / Drainage, UC Talawandi,
District Sialkot Sialkot
On-going
Schemes20.000 9.100 3.333 2.000 1.568 78% 53% Work in progress.
1165 2768Construction of PCC / Drainage, UC Chacharwali
District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1166 2769Construction of PCC / Drainage, UC Klasswala,
District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 1.000 0.689 69% 53% Work in progress.
1167 2770Construction of PCC / Drainage, UC Jodhala,
District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1168 2771
Construction of PCC, Street Drain/ Nullah Village
Kundan Pur Bashmola Tahthi Minderwal, Chan,
Khany Chak, Kajlewal, Mahal Tajer, Ossomata and
Khurra
SialkotOn-going
Schemes48.000 18.000 3.333 2.500 1.667 67% 41% Work in progress.
1169 2772
Construction of PCC, Street Drain/ Nullah Village
Chakrala Bashmula Machrala, Nandpurn Rang
Khokhran, Lalian, Gaiat, Bahadur and Madina
Town.
SialkotOn-going
Schemes49.000 20.000 3.333 2.500 1.667 67% 44% Work in progress.
1170 2773Construction of PCC, Streets Drains, Tuff Tiles and
Soling in UC Marakiwall in District Sialkot.Sialkot
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.
1171 2774Construction of PCC, Streets Drains, Tuff Tiles and
Soling in UC Berth in District Sialkot Sialkot
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.
1172 2775Construction of PCC, Streets Drains, Tuff Tiles and
Soling in UC Booth in District Sialkot Sialkot
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.
1173 2776Construction of PCC, Streets Drains, Tuff Tiles and
Soling in UC Machranal in District Sialkot Sialkot
On-going
Schemes12.000 9.000 1.000 0.750 0.500 67% 79% Work in progress.
1174 2777
Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Dhilum Balagon, District
Sialkot
SialkotOn-going
Schemes25.000 8.000 1.667 1.250 0.834 67% 35% Work in progress.
1175 2778
Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at Fardaus Pura, Nand Garh,
Wan, Dhoop Sarri, Kotli Miani, Malkhanwala,
District Sialkot
SialkotOn-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1176 2779
Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Bhopalwala Tehsil
Sambrial, District Sialkot
SialkotOn-going
Schemes50.000 19.399 3.333 2.500 1.667 67% 42% Work in progress.
1177 2780Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Alleali, District Sialkot Sialkot
On-going
Schemes20.000 7.000 1.667 1.250 0.834 67% 39% Work in progress.
1178 2781
Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at Villages Mundair Syedian,
Mundair Khothay, Roras, Sohowala, Kharolian etc.,
District Sialkot
SialkotOn-going
Schemes25.000 8.000 1.667 1.250 0.834 67% 35% Work in progress.
1179 2782
Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Berowala Tehsil Daska,
District Sialkot
SialkotOn-going
Schemes40.000 12.000 3.333 2.500 1.667 67% 34% Work in progress.
1180 2783Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Bagowala , District SialkotSialkot
On-going
Schemes20.000 7.000 1.667 1.250 0.834 67% 39% Work in progress.
1181 2784Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Ghuinke, District SialkotSialkot
On-going
Schemes149.892 20.000 3.333 2.500 1.667 67% 14% Work in progress.
1182 2785Construction of Streets / Drain / Nullah / Soling /
Tuff Tiles / PCC at UC Bharokey, District SialkotSialkot
On-going
Schemes40.000 12.000 3.333 2.500 1.667 67% 34% Work in progress.
1183 2786Construction of sewerage, Nallah, PCC at UC
Prochak and Alo Mahr District Sialkot.Sialkot
On-going
Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.
1184 2787Construction of Streets / Sewerage / Tuff Tile/
PCC/ Soling in Rural UC's of NA-113Sialkot
On-going
Schemes100.000 29.967 3.333 2.500 1.667 67% 32% Work in progress.
1185 2788Construction of PCC, Soling / Drains in Villages of
UC in Ghutalian District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1186 2789Construction of PCC, Soling / Drains in Villages of
UC in Chichar wali District Sialkot Sialkot
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.
1187 2790Construction of PCC, Soling / Drains in Villages of
UC in Pejoke Qila Kalarwala District Sialkot Sialkot
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.
1188 2791
Construction of Streets, Nullah, PCC, Soling at
villages Jasso Wali Pun, Sahn Gill, pajokay,
Mehmand Wali, Rata jathool, Baso Panu, alawal
Pur, Loharan Wali, Jhangi Shah Khaki, Jhans,
Sodian, Bhuda, Peera Baryar, Charwind, Deehr,
Bhojo, Alkry, Kala Pahar,
SialkotOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1189 2792Construction of PCC, Soling / Drains in Villages of
UC Sokan Wind District Sialkot Sialkot
On-going
Schemes25.000 12.000 1.667 1.250 0.834 67% 51% Work in progress.
1190 2793
Construction of Streets, Drains PCC/ Soling / Tuff
Tiles in Villages of UC's Kanwanlit, Adamkey
Cheema, Raja Gamman, Galotian Kalan, Galotian
Khurd, Goindkey, Banbanwala, Bharokey and
Mitranwali Tehsil Daska District Sialkot
SialkotOn-going
Schemes120.000 45.000 3.333 2.500 1.667 67% 39% Work in progress.
1191 2794
Constructon of Streets / Drain / Nullah / Soling at
UC, Moongar, Baqarpur, Pindi Khokharn etc.,
District Sialkot
SialkotOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1192 2795Constructon of Streets / Drain / Nullah / Soling at,
UC Kapoor Wali and Khamberwala District Sialkot Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1193 2796
Constructon of Streets / Drain / Nullah / Soling at
Village Satab Garah, Butter, Dhanney, Ganjaniwali
etc. District Sialkot
SialkotOn-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in progress.
1194 2797Construction of Street / Swerage / Tuff Tile ETC in
City Daska District Sialkot Sialkot
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress.
1195 2798Construction of PCC/Streets/Nalian at U.C.
Syedanwali District Sialkot Sialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1196 2799Construction of PCC/Streets/Nalian at U.C.Pargpur
District Sialkot Sialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1197 2800Construction of PCC/Streets/Nalian at U.C. Vario
District Sialkot Sialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1198 2801Construction of PCC/Streets/Nalian at U.C
Rasoolpur Balian District Sialkot Sialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1199 2802Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Kotli Barham Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1200 2803Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Paka Garh Sialkot
On-going
Schemes30.000 15.000 1.667 1.250 0.834 67% 53% Work in progress.
1201 2804Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Maina Pura Sialkot
On-going
Schemes30.000 15.000 1.667 1.250 0.834 67% 53% Work in progress.
1202 2805Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Muzafar Pur Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1203 2806Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Fathegarh Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1204 2807Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Haji Pura Ban Sialkot
On-going
Schemes20.000 9.995 3.333 2.500 1.667 67% 58% Work in progress.
1205 2808Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Imam Saheb Sialkot
On-going
Schemes20.000 9.986 3.333 1.000 0.660 66% 53% Work in progress.
1206 2809Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Mubarik Pura Sialkot
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.
1207 2810
Provision of PCC / Sewerage / Tuff Tiles /
Drainage and allied facilities in PP-122, District
Sialkot
SialkotOn-going
Schemes100.000 44.992 3.333 2.500 1.667 67% 47% Work in progress.
1208 2811
Provision of PCC / Sewerage / Tuff Tiles /
Drainage and allied facilities in PP-123, District
Sialkot
SialkotOn-going
Schemes199.950 100.000 3.333 2.500 1.667 67% 51% Work in progress.
1209 2812
Construction of PCC, Street Drain/ Nullah Village
Jallian Wala Bashamula Moma Khurd, Kalan
Virkan, Dulchikay, Lodhary Dogranwala and Rai
Pur.
SialkotOn-going
Schemes47.000 18.000 3.333 2.500 1.667 67% 42% Work in progress.
1210 2813
Construction of PCC, Street Drain/ Nullah Village
Ghari Gondal Bashmula Ahmal Pur, Sarhall,
Hadali, Minal Pathan, Bazpur and Romal Juttan.
SialkotOn-going
Schemes47.000 17.936 1.667 1.250 0.834 67% 40% Work in progress.
1211 2814
Construction of PCC, Street Drain/ Nullah Village
Baghwal Awan Bashmula Harar, Noul, Dumbola
and Dogran.
SialkotOn-going
Schemes46.000 17.956 5.000 1.350 0.903 67% 41% Work in progress.
1212 2815Construction of sewerage, Nallah, PCC at UC
Jaranwala and Barthanwala, District SialkotSialkot
On-going
Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.
1213 2816Construction of sewerage, Nallah, PCC at UC
Salhokay and Bhuda Gorya, District SialkotSialkot
On-going
Schemes20.000 10.938 3.000 2.250 1.500 67% 62% Work in progress.
1214 2817Construction of sewerage, Nallah, PCC at UC
Mundekay Gorya and Malomay, District SialkotSialkot
On-going
Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.
1215 2818Construction of sewerage, Nallah, PCC at UC
Boghray and Seo Ke, District Sialkot.Sialkot
On-going
Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.
1216 2819Construction of sewerage, Nallah, PCC at UC
Adha and Sehjo Kala District Sialkot.Sialkot
On-going
Schemes20.000 12.000 2.667 2.000 1.334 67% 67% Work in progress.
1217 2820Construction of sewerage, Nallah, PCC at UC
Ghuainkey and Badoke Cheema, District Sialkot.Sialkot
On-going
Schemes15.000 9.941 1.667 1.250 0.834 67% 72% Work in progress.
1218 2821Construction of sewerage, Nallah, PCC at UC
Jamkay Cheema and Kanwanliq, District Sialkot.Sialkot
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.
1219 2822Construction Street Drain PCC / and Nullah U/C
JaithkeSialkot
On-going
Schemes20.000 10.000 3.333 4.534 3.701 82% 69% Work in progress.
1220 2823Construction of Street Drain PCC / and Nullah U/C
Kopra Sialkot
On-going
Schemes20.000 9.920 3.333 2.500 1.667 67% 58% Work in progress.
1221 2824Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Dalowali Sialkot
On-going
Schemes40.000 14.963 3.333 2.500 1.667 67% 42% Work in progress.
1222 2825Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Talwara Sialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1223 2826Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Pindi Arian Sialkot
On-going
Schemes20.000 9.968 3.333 2.500 1.667 67% 58% Work in progress.
1224 2827Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Hamza Ghous Sialkot
On-going
Schemes30.000 9.920 1.667 1.250 0.834 67% 36% Work in progress.
1225 2828Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Naika Pura Sialkot
On-going
Schemes20.000 9.987 3.333 2.500 1.667 67% 58% Work in progress.
1226 2829Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Duborji Arian Sialkot
On-going
Schemes20.000 9.937 3.333 2.500 1.667 67% 58% Work in progress.
1227 2830Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Ahmed Pura Sialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1228 2831Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Pura Hiran Sialkot
On-going
Schemes20.000 9.970 3.333 2.500 1.667 67% 58% Work in progress.
1229 2832Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Rangpura Sialkot
On-going
Schemes40.000 15.000 3.333 2.500 1.667 67% 42% Work in progress.
1230 2833Providing & Laying of Tuff Tile PCC and Drainge
Lines in UC Islam Abad Sialkot
On-going
Schemes20.000 9.700 3.333 2.500 1.667 67% 57% Work in progress.
1231 2834Construction of Street Drain PCC/ and Nullah UC
Majra KalanSialkot
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.
1232 2835Construction of Street Drain PCC / and Nullah U/C
Village Srankey Sialkot
On-going
Schemes20.000 10.000 3.333 7.500 6.667 89% 83% Work in progress.
1233 2836Construction of Street Drain PCC/ and Nullah
U/C’s Verowala, Halewai, Habibpur Sialkot
On-going
Schemes80.000 30.000 1.667 1.250 0.834 67% 39% Work in progress.
1234 2837Construction of sewerage, PCC, Tuff Tile, District
Sialkot Sialkot
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress.
1235 2838Construction of PCC & Drains in Village Chobara
U/C Chobara District SialkotSialkot
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in progress.
1236 2839
Construction of Drainage System, PCC and Brick
Pavement in Villages of UC Rupo Chak Tehsil
Zafarwal District Narowal
NarowalOn-going
Schemes12.000 4.993 2.000 1.500 0.999 67% 50%
"A.A. dated 07.08.2017 T.S. dated 08.08.2017 Start
Date 28.09.2017 *Completion date 30.06.2019work
in progress. Fund not received on spending end yet.
1237 2840
Provision of Drains/Soling and PCC in UCs,
Datewal, Mangolay, Hallowal, Dhrug Miana and
Ghota Fateh Garh District Narowal
NarowalOn-going
Schemes30.000 12.308 3.333 2.500 1.659 66% 47%
"A.A. dated 03.08.2017 T.S. dated 12.08.2017
*Start Date 27.10.2017 *Completion date
30.06.2019 work in progress. "A.A. dated
03.08.2017 T.S. dated 12.08.2017 *Start Date
27.10.2017 *Completion date 30.06.2019 work in
progress. "A.A. dated 03.08.2017 T.S. dated
12.08.2017 *Start Date 27.10.2017 *Completion
date 30.06.2019 work in progress.Fund not recived
on spending end yet
1238 2841
Provision of Drains/Soling and PCC in UCs,
Talwandi Bhindran, Giddan, Niddokay, Kot Lakha
Singh and Domala, District Narowal
NarowalOn-going
Schemes30.000 9.960 3.333 2.500 1.661 66% 39%
"A.A. dated 03.08.2017 T.S. dated 12.08.2017
*Start Date 27.10.2017 *Completion date
30.06.2019 Work in progress. Fund not receive on
spending end yet.
1239 2842
Provision of Drains/Soling and PCC in UCs, Khan
Kassa, Dongian, Bubak Murali, Sadowala Uncha
and Falezpur District Narowal
NarowalOn-going
Schemes30.000 9.871 3.333 2.500 1.664 67% 38%
"A.A. dated 03.08.2017 T.S. dated 12.08.2017
*Start Date 27.10.2017 *Completion date
30.06.2019 Work in progress. "A.A. dated
03.08.2017 T.S. dated 12.08.2017 *Start Date
27.10.2017 *Completion date 30.06.2019 Work in
progress"A.A. dated 03.08.2017 T.S. dated
12.08.2017 *Start Date 27.10.2017 *Completion
date 30.06.2019 Work in progress. Funds not
received on spending end yet.
1240 2843
Provision of Drains/Soling and PCC in UCs,
Ahmadabad, Depokey, Jestiwala, Uncha, Lala and
Nonar, District Narowal
NarowalOn-going
Schemes30.000 9.940 3.333 2.500 1.659 66% 39%
"A.A. dated 03.08.2017 T.S. dated 12.08.2017
*Start Date 27.10.2017 *Completion date
30.06.2019 Work in progress. Funds not received
on spending end yet
1241 2844
Provision of Drains/Soling and PCC in UCs, Mehlu
Wala, Dhamthal, Langarkay, Tapiala and
Sankhtara District Narowal
NarowalOn-going
Schemes30.000 9.940 3.333 2.500 1.663 67% 39%
"A.A. dated 03.08.2017 T.S. dated 12.08.2017
*Start Date 27.10.2017 *Completion date
30.06.2019 Work in progress. Funds not received
on spending end yet
1242 2845
Provision of PCC/Streets/Nalian at Bado Malihi,
Chandarkay, Ransiwal, Manak, Qayampur, Agrian,
Pungarian, Salukay, Dawod, Chundowal, Klass
Gorya, Muhammad Rana Wala District Narowal
NarowalOn-going
Schemes130.000 34.991 6.667 5.000 3.320 66% 29%
"A.A. dated 19.10.17 T.S. dated*Start Date
18.10.2017 *Completion date 30.06.2019 Work in
progress. Funds not received on spending end yet.
1243 2846Provision of Tuff Tile from Zafarwal bypass to
Chowk Ghas Mandi, District Narowal Narowal
On-going
Schemes22.000 9.965 4.000 3.000 1.994 66% 54%
"A.A Date.03.08.2017 T.S Date*18.09.2017 Start
Date 28.09.2017*Completion date 30.06.2019 Work
in progress. Funds not received on spending end yet
1244 2847
Construction of Drainage System, PCC and Brick
Pavement in Villages of Jandiala Tehsil Zafarwal
District Narowal
NarowalOn-going
Schemes15.000 4.993 3.333 2.500 1.661 66% 44%
"A.A. dated 03.08.17T.S. dated 08.08.2017*Start
Date 18.08.2017*Completion date 30.06.2019 Work
in progress. Fund not received on spending end yet.
1245 2848Provision of PCC / Sewerage / Drainage etc. in PP-
133, District NarowalNarowal
On-going
Schemes25.000 9.812 1.667 1.250 0.831 66% 43%
"A.A. dated 03.08.17 T.S. dated 08.08.2017 *Start
Date 18.08.2017 *Completion date 30.06.2019
Work in progress. Funds not received on spending
end yet.
1246 2849PCC & Drainage & Sewerage System at UC-273,
Raiwind City, LhrLahore
On-going
Schemes50.000 38.992 3.667 5.090 4.174 82% 86% Work stopped due to awaiting funds.
1247 2850PCC & Drainage & Sewerage System at UC-112,
Mustafa Town, Lahore
On-going
Schemes50.000 39.986 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1248 2851Provision of PCC & Drainage Facilities in Attari &
allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed
1249 2852
Provision of PCC & Drainage Facilities in
Youhanabad, Dhullu Kalan & Khurd & allied
abadies.
LahoreOn-going
Schemes50.000 39.987 3.333 3.400 2.567 76% 85% Work stopped due to awaiting funds.
1250 2853Provision of PCC & Drainage Facilities in
Gajjumatta & allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed
1251 2854Provision of PCC & Drainage Facilities in Bhallar &
allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed
1252 2855Provision of PCC & Drainage Facilities in Dhalloki
& allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed
1253 2856Provision of PCC & Drainage Facilities in Jhulkey
& allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed
1254 2857Provision of PCC & Drainage Facilities in Jaman
and Gawind & allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 2.500 1.667 67% 83% Scheme completed
1255 2858Provision of PCC & Drainage Facilities in
Shahzada & allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed
1256 2859Provision of PCC & Drainage Facilities in Jia
Bhagga & allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed
1257 2860Provision of PCC & Drainage Facilities in Pandoki
& allied abadies.Lahore
On-going
Schemes50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed
1258 2861Provision of PCC & Drainage Facilities in Hair &
allied abadies.Lahore
On-going
Schemes73.000 54.100 3.333 0.900 0.067 7% 74%
Work stopped due to awaiting funds. Revised PC-I
is under review with DDWP.
1259 2862Construction of Sewerage and Disposal Manawan
Sky Land & Abadies Lahore
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work stopped due to awaiting funds.
1260 2863Construction of PCC/Sewerage and Link Streets
UC-147 Lahore.Lahore
On-going
Schemes50.000 34.992 5.000 3.750 2.500 67% 75% Work stopped due to awaiting funds.
1261 2864Construction of PCC/Sewerage and Link Streets
UC-148 Lahore.Lahore
On-going
Schemes50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1262 2865Construction of PCC/Sewerage and Link Streets
UC-149 Lahore.Lahore
On-going
Schemes50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1263 2866Construction of PCC/Sewerage and Link Streets
UC-150 Lahore.Lahore
On-going
Schemes50.000 39.992 3.333 2.300 1.467 64% 83% Work stopped due to awaiting funds.
1264 2867Construction of PCC/Sewerage and Link Streets
UC-151 Lahore.Lahore
On-going
Schemes50.000 39.538 3.333 2.400 1.567 65% 82% Work stopped due to awaiting funds.
1265 2868Construction of PCC/Sewerage and Link Streets
UC-152 Lahore.Lahore
On-going
Schemes50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1266 2869Construction of PCC/Sewerage and Link Streets
UC-174 Lahore.Lahore
On-going
Schemes50.000 29.984 3.333 2.500 1.667 67% 63% Work stopped due to awaiting funds.
1267 2870Construction of PCC/Sewerage and Link Streets
UC-175 Lahore.Lahore
On-going
Schemes50.000 39.991 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1268 2871Construction of PCC/Sewerage and Link Streets
UC-183 Lahore.Lahore
On-going
Schemes50.000 39.991 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1269 2872Construction of PCC/Sewerage and Link Streets
UC-108 Lahore.Lahore
On-going
Schemes50.000 34.968 5.000 3.750 2.500 67% 75% Work stopped due to awaiting funds.
1270 2873Construction of PCC/Sewerage and Link Streets
Bhangali Lahore.Lahore
On-going
Schemes100.000 75.000 5.000 3.750 2.500 67% 78%
Scheme completed physically, funds are required to
clear the contractor liabilities.
1271 2874PCC & Drainage & Sewerage System at UC-110,
Niaz Baig LahoreLahore
On-going
Schemes50.000 39.977 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1272 2875PCC & Drainage & Sewerage System at UC-111,
Hunjarwal, LahoreLahore
On-going
Schemes50.000 39.273 3.573 2.680 1.787 67% 82% Work stopped due to awaiting funds.
1273 2876PCC & Drainage & Sewerage System at UC-109,
Margzaar Colony, Lahore. Lahore
On-going
Schemes50.000 39.493 3.500 2.625 1.750 67% 82% Work stopped due to awaiting funds.
1274 2877PCC & Drainage & Sewerage System at UC-117,
Shahpur Kanjran, Lahore. Lahore
On-going
Schemes50.000 45.000 1.667 1.250 0.834 67% 92%
Scheme completed physically, funds are required to
clear the contractor liabilities.
1275 2878PCC & Drainage & Sewerage System at UC-262,
Shamke Bhattian, Lahore.Lahore
On-going
Schemes50.000 29.989 1.667 1.050 0.634 60% 61% Work stopped due to awaiting funds.
1276 2879PCC & Drainage & Sewerage System at UC-255,
Sattu Kattla, LahoreLahore
On-going
Schemes50.000 31.995 1.667 5.250 4.834 92% 74% Work stopped due to awaiting funds.
1277 2880PCC & Drainage & Sewerage System at UC-256,
Ali Raza Abad, LahoreLahore
On-going
Schemes50.000 39.556 3.333 2.500 1.667 67% 82% Work stopped due to awaiting funds.
1278 2881PCC & Drainage & Sewerage System at UC-272,
Raiwind Kalan, LahoreLahore
On-going
Schemes50.000 40.000 3.333 5.000 4.167 83% 88%
Physically scheme is completed, balance funds are
required to clear the contractor's liability
1279 2882Provision of PCC & Drainage in Streets UC-176
Awan Dhai Wala Lahore.Lahore
On-going
Schemes50.000 39.800 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1280 2883Provision of PCC & Drainage in Streets UC-190
Hadiara Lahore.Lahore
On-going
Schemes50.000 39.620 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1281 2884Provision of PCC & Drainage in Streets UC-180
Minhala Kallan Lahore.Lahore
On-going
Schemes50.000 39.599 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1282 2885Provision of PCC & Drainage in Streets UC-181
Wahga Lahore.Lahore
On-going
Schemes50.000 39.977 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.
1283 2886Provision of PCC & Drainage in Streets UC-194
Lidhar Lahore.Lahore
On-going
Schemes50.000 40.000 3.333 0.870 0.037 4% 80% Scheme completed
1284 2887
Provision of clean drinking water, sewerage
system, PCC and allied facilities in Manga Mandi,
Raiwind Village and adjoining Abadies.
LahoreOn-going
Schemes300.000 137.599 8.333 6.250 4.167 67% 47% Work stopped due to awaiting funds.
1285 2888Construction of PCC, Soling, Drain & Nallah at
Tibbi Humbo, UC 64, District SheikhupuraSheikhupura
On-going
Schemes15.000 2.500 1.667 1.250 0.834 67% 22% Work in Progress
1286 2889Provision of PCC, Drain, Soling, Nallah & culvert at
UC 87 Farooqabad , District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress
1287 2890Provision of PCC, Drain, Soling, Nallah & culvert at
UC Ghung, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress
1288 2891Provision of PCC, Drain, Soling, Nallah & culvert at
UC Nokhar Nau, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress
1289 2892Provision of PCC, Drain, Soling, Nallah & culvert at
UC Sucha Sauda, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress
1290 2893Provision of PCC, Drain, Soling, Nallah & culvert at
UC Hardev, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress
1291 2894Construction of soling, PCC, Drain & Nallah UC
Mojoki Mallian, District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1292 2895Construction of soling, PCC, Drain & Nallah UC
Jhamkay, District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1293 2896Construction of soling, PCC, Drain & Nallah UC
Kalokay, District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1294 2897Construction of soling, PCC, Drain & Nallah UC
Rakh Hiran Minara District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1295 2898Construction of soling, PCC, Drain & Nallah UC
Ghang District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1296 2899Construction of soling, PCC, Drain & Nallah UC
Warn Dera Bhikhi Ana District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1297 2900Rural drainage & PCC Scheme UC Jhabran,
District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1298 2901Rural drainage & PCC Scheme UC Ghazi Minara,
District Sheikhupura,Sheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1299 2902Rural drainage & PCC Scheme UC Hardev,
District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1300 2903Construction of PCC, Drain / Soling & Nallah at UC
Kakar Gill, District SheikhupuraSheikhupura
On-going
Schemes11.000 5.000 2.000 1.500 1.000 67% 55% Work in Progress
1301 2904Construction of PCC, Drain / Soling & Nallah at UC
83 Jatri Kohna, District SheikhupuraSheikhupura
On-going
Schemes14.000 5.000 3.000 2.250 1.500 67% 46% Work in Progress
1302 2905Construction of PCC, Drain / Soling & Nallah at UC
79 Harchand, District SheikhupuraSheikhupura
On-going
Schemes12.000 5.000 2.333 1.750 1.167 67% 51% Work in Progress
1303 2906Construction of PCC, Drain / Soling & Nallah at UC
81 Sucha Sauda, District SheikhupuraSheikhupura
On-going
Schemes16.000 5.000 3.667 2.750 1.834 67% 43% Work in Progress
1304 2907Construction of PCC, Drain / Soling & Nallah at UC
80 Esherke, District SheikhupuraSheikhupura
On-going
Schemes14.000 5.000 3.000 2.250 1.500 67% 46% Work in Progress
1305 2908
Construction of PCC, Drain / Soling & Nallah at UC-
85, 86 & 87 Farooqabad City & Muridke village UC-
70, District Sheikhupura
SheikhupuraOn-going
Schemes55.000 20.000 3.333 2.500 1.667 67% 39% Work in Progress
1306 2909Construction of PCC, Drain, Soling & Nallah Kala
Khatai UC-9, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1307 2910Construction of PCC, Drain, Soling & Nallah
Khatiala Virkan UC-18, District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress
1308 2911Construction of PCC, Drain, Soling & Nallah
Sheikhupura Bedad UC-15, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1309 2912Construction of PCC, Drain, Soling & Nallah
Nangal Kaswala UC-14, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1310 2913Construction of PCC, Drain, Soling & Nallah
Dharor Muslim UC-13, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1311 2914Construction of PCC, Drain, Soling & Nallah
Ahdian UC-7, District SheikhupuraSheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1312 2915Construction of PCC, Drain, Soling & Nallah
Lambray UC-10, District SheikhupuraSheikhupura
On-going
Schemes12.000 5.000 2.333 1.750 1.167 67% 51% Work in Progress
1313 2916Construction of PCC, Drain, Soling & Nallah
Nangal Sahdan UC-11, District SheikhupuraSheikhupura
On-going
Schemes20.000 5.000 1.667 1.250 0.834 67% 29% Work in Progress
1314 2917Rural Drainage and Construction of Streets
Scheme at UC Barth District Sheikhupura.Sheikhupura
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress
1315 2918Rural Drainage and Construction of Streets
Scheme at UC Chak No.22 District Sheikhupura.Sheikhupura
On-going
Schemes30.000 19.000 3.667 2.750 1.834 67% 69% Work in Progress
1316 2919Rural Drainage and Construction of Streets
Scheme at UC Faizpur Khurd District Sheikhupura.Sheikhupura
On-going
Schemes35.000 19.000 1.667 1.250 0.834 67% 57% Work in Progress
1317 2920Rural Drainage and Construction of Streets
Scheme at UC Luban Wala District Sheikhupura.Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1318 2921Rural Drainage and Construction of Streets
Scheme at UC Faizpur Kalan District Sheikhupura.Sheikhupura
On-going
Schemes30.000 19.000 3.667 2.750 1.834 67% 69% Work in Progress
1319 2922Rural Drainage and Construction of Streets
Scheme at UC Buraj Attari District Sheikhupura.Sheikhupura
On-going
Schemes25.000 10.000 1.667 1.250 0.834 67% 43% Work in Progress
1320 2923Rural Drainage and Construction of Streets
Scheme at UC Moran Wala District Sheikhupura.Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1321 2924Rural Drainage and Construction of Streets
Scheme at UC Rana Bhati District Sheikhupura.Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% scheme Completed
1322 2925
Rural Drainage and Construction of Streets
Scheme at UC Kashmir Town/Rana Town/ Galkxy
Block/ Kot Hadayat/ Haider Road District
Sheikhupura.
SheikhupuraOn-going
Schemes50.000 1.750 3.333 2.500 1.667 67% 7% Work in Progress
1323 2926
Rural Drainage and PCC at villages Samolana,
Mada Treda, Pherianwala, Khanni, Jalalpur,
Nizampura, Kukripur, Sikhanwala, Jogiwala and
adjoinging abdies, District Sheikhupura
SheikhupuraOn-going
Schemes30.000 15.000 1.667 1.250 0.834 67% 53% Work in Progress
1324 2927Construction of PCC, Drains and Nallah at UC-37
Chak 575 GB District SheikhupuraSheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1325 2928Construction of Rural Draiange PCC & Tuff tiles
scheme UC 27, District Sheikhupura Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1326 2929Construction of Rural Draiange PCC & Tuff tiles
scheme UC 28, District Sheikhupura Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1327 2930Construction of Rural Draiange PCC & Tuff tiles
scheme UC 29, District Sheikhupura Sheikhupura
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in Progress
1328 2931Construction of Rural Draiange PCC & Tuff tiles
scheme UC 30, District Sheikhupura Sheikhupura
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in Progress
1329 2932Construction of Rural drainage PCC & Tuff tiles
scheme UC Rana Bhatti, District Sheikhupura Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1330 2933Construction of Rural drainage PCC & Tuff tiles
scheme UC Mandianwala, District Sheikhupura Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1331 2934Construction of Rural drainage PCC & Tuff tiles
scheme UC Dhamkay, District Sheikhupura Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1332 2935Construction of Rural drainage PCC & Tuff tiles
scheme UC Chak No.22, District Sheikhupura Sheikhupura
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1333 2936Urban Drainage and Sewerage Scheme Narang
Mandi, District SheikhupuraSheikhupura
On-going
Schemes220.000 30.000 1.000 0.750 0.500 67% 14% Work in Progress
1334 2937
Urban Sewerage, Drainage & PCC Scheme MC
Ferozewala, Tehsil Ferozewala, District
Sheikhupura
SheikhupuraOn-going
Schemes160.000 20.000 5.000 3.750 2.500 67% 14% Work in Progress
1335 2938Construction of PCC, Drain & Nallah Muridke City,
District SheikhupuraSheikhupura
On-going
Schemes100.000 25.000 3.333 2.500 1.667 67% 27% Work in Progress
1336 2939Construction of PCC, Drain & Nallah Narang City,
District SheikhupuraSheikhupura
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress
1337 2940Provision of water supply and sewerage / drainage
scheme city SheikhupuraSheikhupura
On-going
Schemes450.000 17.500 16.667 12.500 8.334 67% 6% Work in Progress
1338 2941
Urban Sewerage, Drainage & PCC Scheme MC
Kot Adbul Malik, Tehsil Ferozewala, District
Sheikhupura
SheikhupuraOn-going
Schemes140.000 15.000 3.333 2.500 1.667 67% 12% Work in Progress
1339 2942
Urban Sewerage, Drainage & PCC Scheme UC
Momin Pura, Tehsil Ferozewala, District
Sheikhupura
SheikhupuraOn-going
Schemes20.000 5.427 4.858 3.644 2.429 67% 39% Work in Progress
1340 2943Urban Sewerage, Drainage & PCC Scheme UC
Shamkay, Tehsil Ferozewala, District SheikhupuraSheikhupura
On-going
Schemes100.000 9.254 3.535 2.651 1.768 67% 11% Work in Progress
1341 2944
Urban Sewerage, Drainage & PCC Scheme UC
Qilla Sattar Shah, Tehsil Muridkay, District
Sheikhupura
SheikhupuraOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Scheme completed
1342 2945Provision of PCC and Tuff Tiles in City
Sheikhupura PP-167, District SheikhupuraSheikhupura
On-going
Schemes180.000 140.000 3.333 2.500 1.667 67% 79% Work in Progress
1343 2946Construction of PCC, Drains and Nallah at UC-57
Jevanpura, District SheikhupuraSheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1344 2947Construction of PCC, Drains and Nallah at UC-58
Kadlathi, District SheikhupuraSheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1345 2948Construction of PCC, Drains and Nallah at UC-80
Khariyanwala. District SheikhupuraSheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1346 2949Construction of PCC, Drains and Nallah at UC-81
Bhikhi. District SheikhupuraSheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1347 2950Construction of PCC, Drains and Nallah at UC-82
Tibbi Hambo. District SheikhupuraSheikhupura
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1348 2951
Construction of sewerage, drains, tuff tiles, PCC &
LED Street lights at Wandala Dial Shah & Dhaka
Nizam Pura, District Sheikhupura
SheikhupuraOn-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress
1349 2952
Construction of drain / soling / PCC / Nullah and
Pulyat at vilalge Rato Ana, Kot Ghulam Rasool and
village Sheedi Kot UC Kot Hussain Khan, District
Nankana Sahib
Nankana SahibOn-going
Schemes29.500 10.000 3.333 2.500 1.667 67% 40% Work is in progress.
1350 2953Construction of PCC / Soling & Nallah at UC
Buchoke Pur Distirct Nankana Sahib Nankana Sahib
On-going
Schemes30.000 10.000 3.333 4.200 3.367 80% 45% Work is in progress.
1351 2954
Construction of Drain / Nullah / Culverts / PCC and
Soling at UC Kari Wala i/c Mashmoola Jat, Tehsil
Shah Kot, District Nankana Sahib
Nankana SahibOn-going
Schemes15.000 10.000 1.667 0.450 0.034 8% 67% Work is in progress.
1352 2955
Construction of drain / soling / PCC / Nullah and
Pulyat at village Nathowala 180/RB, Chak
No.181/RB, Kari Wala and Chak No.182/RB, UC
Nathowala, District Nankana Sahib
Nankana SahibOn-going
Schemes29.700 10.000 3.333 2.500 1.667 67% 39% Work is in progress.
1353 2956
Construction of drain / soling / PCC / Nullah and
Pulyat at village Chak No.184/RB Kot Nizam Din
and Chak No.186/RB Ghandran UC Kot Nizam
Din, District Nankana Sahib
Nankana SahibOn-going
Schemes29.300 10.000 3.333 2.500 1.667 67% 40% Work is in progress.
1354 2957Construction of Drain / Soling / Nallah at UC
Saleem Pur Pakka, District Nankana Sahib Nankana Sahib
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress.
1355 2958Construction of Drain / Soling / Nallah at UC
Mangtanwala, District Nankana Sahib Nankana Sahib
On-going
Schemes30.000 10.000 3.333 4.200 3.367 80% 45% Work is in progress.
1356 2959Construction of Drain / Soling / Nallah at UC
Chachke Gill, District Nankana Sahib Nankana Sahib
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress.
1357 2960Construction of Drain / Soling / Nallah at UC Haft
Madar, District Nankana Sahib Nankana Sahib
On-going
Schemes30.000 10.000 3.333 3.000 2.167 72% 41% Work is in progress.
1358 2961Construction of Drain / Soling / Nallah in left over
area of UC Ganaish Pur, District Nankana SahibNankana Sahib
On-going
Schemes30.000 10.000 3.333 4.100 3.267 80% 44% Work is in progress.
1359 2962Construction of Drain / Soling / Nallah in left over
area of UC Jawahar Pur, Distirct Nankana Sahib Nankana Sahib
On-going
Schemes40.000 13.000 3.333 1.100 0.267 24% 33% Work is in progress.
1360 2963Construction of Drain / Soling / Nallah in left over
area of UC Jogaykot, Distirct Nankana Sahib Nankana Sahib
On-going
Schemes30.000 10.000 3.333 1.100 0.267 24% 34% Work is in progress.
1361 2964Construction of Drain / Soling / Nullah at UC jalal
Nau, District Nankana SahibNankana Sahib
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work is in progress.
1362 2965
Construction of Drain / Soling / Nullah at Village
Balaqian, Dodhay, Chora, Mat Kalayian and
Dharian, District Nanakana Sahib
Nankana SahibOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work is in progress.
1363 2966Provision of sewerage, PCC & Nullah at Mouza
Khiyaray Kalan, Tehsil & District Nankana SahibNankana Sahib
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress.
1364 2967
Provision of water supply sanitation and drainage
facilities at Chak No.168/RB Machar Wali District
Nankana Sahib
Nankana SahibOn-going
Schemes112.768 23.200 3.333 2.500 1.667 67% 22% Work is in progress.
1365 2968
Construction of Nullah / Drain and PCC at Bucheki
City and at Chak No.22/75, Chak No.18/71, Chak
No.16/69, Chak No.641 Bohty Wala, Lurka Jangly,
District Nankana Sahib
Nankana SahibOn-going
Schemes50.000 40.000 3.333 0.850 0.017 2% 80% Work is in progress.
1366 2969
Construction of PCC / Drain / Nullah at Burala,
Maddo Ladoana, Juggian Nolan, Warra Narain
Singh, Jahana Nool, Peeray Wali, Chak Wattowan,
Nodhan, Sikhanwali, Kawanwali, Nizam Pura,
Baghoor, District Nankana Sahib
Nankana SahibOn-going
Schemes30.000 13.000 3.333 1.400 0.567 41% 45% Work is in progress.
1367 2970
Construction of Soling, Drains & PCC at village
Nathowala, Nizampura, Nodha, Fareedabad,
Kheokay Bhattian, Madu, Purana Syed wala ,
District Nankana Sahib
Nankana SahibOn-going
Schemes50.000 33.000 3.333 2.500 1.667 67% 69% Work is in progress.
1368 2971
Construction of PCC, Soling & Nullah at UC
Machrala i/c Bhagor, Wakeel Wala, Adampura &
Dolatpura, Distirct Nankana Sahib
Nankana SahibOn-going
Schemes30.000 10.000 3.333 4.000 3.167 79% 44% Work is in progress.
1369 2972Construction of PCC, Soling & Nullah at UC
Mustafaabad / Jislani, Distirct Nankana Sahib Nankana Sahib
On-going
Schemes25.000 10.000 3.333 3.150 2.317 74% 49% Work is in progress.
1370 2973Construction of PCC, Soling & Nullah at UC
Meeranpur, Distirct Nankana Sahib Nankana Sahib
On-going
Schemes25.000 10.000 3.333 0.850 0.017 2% 40% Work is in progress.
1371 2974Construction of PCC, Drains and Nallah at UC-51
Khiarraey Kalan District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress.
1372 2975Construction of PCC, Drains and Nallah at UC-52
Chokian Wala District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 0.950 0.117 12% 34% Work is in progress.
1373 2976Construction of PCC, Nallah, Drains at Syed Wala,
District Nankana SahibNankana Sahib
On-going
Schemes50.000 40.000 3.333 0.850 0.017 2% 80% Work is in progress.
1374 2977Construction of PCC, Drains and Nallah at UC-48
Rehanwala District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 0.950 0.117 12% 34% Work is in progress.
1375 2978Construction of PCC, Drains and Nallah at UC-36
Mashrala District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress.
1376 2979Construction of PCC, Drains and Nallah at UC-39
Meeranpur District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress.
1377 2980Construction of PCC, Drains and Nallah at UC-50
Ganaishpur District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 3.400 2.567 76% 50% Work is in progress.
1378 2981Construction of PCC, Drains and Nallah at UC-38
Warbutton District Nankana Sahib.Nankana Sahib
On-going
Schemes15.000 5.000 3.333 4.500 3.667 81% 58% Work is in progress.
1379 2982Construction of PCC, Drains and Nallah at UC-40
Shareen Jhangaar District SheikhupuraNankana Sahib
On-going
Schemes15.000 5.000 3.333 4.500 3.667 81% 58% Work is in progress.
1380 2983
Rural Drainage PCC Brick pavement Schemes
Beroon Mustafa Abad and Adjoining Abadies,
Tehsil & District Kasur
KasurOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress
1381 2984
Rural Drainage PCC Brick pavement Schemes
Weghal and Adjoining Abadies, Tehsil & District
Kasur
KasurOn-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1382 2985
Rural Drainage PCC Brick pavement Schemes
Badar Pur, Ray, Badian and Adjoining Abadies,
Tehsil & District Kasur
KasurOn-going
Schemes15.000 4.966 3.333 2.500 1.667 67% 44% Work in Progress
1383 2986
Rural Drainage PCC Brick pavement Schemes
Matta and Adjoining Abadies, Tehsil & District
Kasur
KasurOn-going
Schemes20.000 9.957 3.333 2.500 1.667 67% 58% Work in Progress
1384 2987
Rural Drainage PCC Brick pavement Schemes
Khara and Adjoining Abadies, Tehsil & District
Kasur
KasurOn-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress
1385 2988Const. of Soling Drains, PCC, Culverts U.C
Handal, Tehsil KRK, District KasurKasur
On-going
Schemes30.000 11.467 1.667 3.620 3.204 89% 49% Work in Progress
1386 2989Rural drainage scheme U.C Bhedian, District
KasurKasur
On-going
Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress
1387 2990Rural drainage scheme U.C Sheikhum, District
KasurKasur
On-going
Schemes25.000 9.993 5.000 3.750 2.500 67% 50% Work in Progress
1388 2991Rural drainage scheme U.C Fathe Pur, District
KasurKasur
On-going
Schemes30.000 9.981 1.967 1.475 0.984 67% 37% Work in Progress
1389 2992Rural drainage scheme U.C Hussain Khan Wala,
District KasurKasur
On-going
Schemes30.000 10.000 6.667 6.000 4.334 72% 48% Work in Progress
1390 2993Construction of Sewerage / Drainage / PCC
Scheme Kot Radha Kishan City, District KasurKasur
On-going
Schemes199.860 34.999 20.000 26.303 21.303 81% 28% Work in Progress
1391 2994Construction of Soling, Nallah, PCC & Drain at
Satoki, District Kasur.Kasur
On-going
Schemes15.000 4.992 3.333 2.500 1.667 67% 44% Work in Progress
1392 2995Construction of Soling, Nallah, PCC & Drain at UC
Cheena Arla and Nathoki, District KasurKasur
On-going
Schemes15.000 4.996 3.333 2.500 1.667 67% 44% Work in Progress
1393 2996Construction of Soling, Nallah, PCC & Drain at UC
Pemar, District KasurKasur
On-going
Schemes15.000 4.980 3.333 2.500 1.667 67% 44% Work in Progress
1394 2997Construction of soling / drains / PCC roads in Chak
No.38, District KasurKasur
On-going
Schemes3.000 2.500 0.167 0.125 0.084 67% 86% Work in Progress
1395 2998Construction of soling / drains / PCC roads in
village Chugian & Marathiwala, District KasurKasur
On-going
Schemes3.000 2.457 0.167 0.125 0.084 67% 85% Work in Progress
1396 2999Construction of soling / drains / PCC roads in
village Chaku , District KasurKasur
On-going
Schemes3.000 2.500 0.167 0.125 0.084 67% 86% Work in Progress
1397 3000Construction of Urban Sewerage, Drainage, PCC
Scheme Khudian Phase-II, District KasurKasur
On-going
Schemes360.000 35.000 10.090 7.568 5.045 67% 11% Work in Progress
1398 3001Construction of Urban Sewerage, Drainage, PCC
Scheme, Kanganpur, District KasurKasur
On-going
Schemes150.026 29.977 5.000 3.750 2.500 67% 22% Work in Progress
1399 3002Urban Water supply scheme, Kasur City, District
KasurKasur
On-going
Schemes70.526 20.000 5.000 3.750 2.500 67% 32% Work in Progress
1400 3003
Construction of drain, PCC, Tuff Tile, Culverts,
Sullage Carrier and Brick Pavement Sheikham,
Kacha Pakka, Padhana, Bath Kalan and Tara
Garh, Tehsil Pattoki, District Kasur
KasurOn-going
Schemes144.500 27.996 5.000 3.750 2.500 67% 21% Work in Progress
1401 3004
Construction of drain, PCC, Tuff Tile, Culverts,
Sullage Carrier and Brick Pavement Balloki,
Sandhu Kalan, Sarai Mughal, Beharwal and
Bhonikey, Tehsil Pattoki, District Kasur
KasurOn-going
Schemes149.000 28.000 5.000 3.750 2.500 67% 20% Work in Progress
1402 3005Rehabilitation & Re-construction of sullage carrier
at Waan Adhan, District KasurKasur
On-going
Schemes10.451 7.000 1.150 2.363 2.075 88% 87% Work in Progress
1403 3006
Construction of Drain, Brick Pavement & PCC in
Ghummankey and adjoining abadies, Tehsil
Pattoki, District Kasur
KasurOn-going
Schemes69.298 20.000 20.000 15.000 10.000 67% 43% Work in Progress
1404 3007
Construction of Drain, Brick Pavement & PCC in
Bonga Balochan and adjoining abadies, Tehsil
Pattoki, District Kasur
KasurOn-going
Schemes66.879 20.000 20.000 14.500 9.500 66% 44% Work in Progress
1405 3008
Construction of Drainage, Brick Pavement, PCC
and Sullage Carrier Scheme in Blair, Masradass i/c
adjoining abadies, Tehsil Pattoki, District Kasur
KasurOn-going
Schemes50.000 18.000 3.333 2.500 1.667 67% 39% Work in Progress
1406 3009Rural Sewerage / Drainage Scheme Chak
No.18/GD, District OkaraOkara
On-going
Schemes14.330 9.993 1.000 0.750 0.500 67% 73%
Date of A.A 26.07.2017, Date of T.S 01.08.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 26.09.2017, Date of Receipt of
tenders 27.09.2017, Date of work order ,12.10.2017
Date of completion as per PC-I ,30.06.2018
Anticipated date of completion ,30.06.2018 No. of
Beneficiary - 9878 Person,
1407 3010Rural Water Supply & Drainage Scheme, Sahbay
Wala, Depal Pur Okara
On-going
Schemes20.840 9.992 3.613 2.710 1.806 67% 57%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 9822
Person, Work is in progress.
1408 3011Rural Water Supply & Drainage Scheme, Bhakho
Shah, Depal Pur Okara
On-going
Schemes20.510 7.993 4.170 3.128 1.849 59% 48%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 6316
Person, Work is in progress.
1409 3012Rural Water Supply & Drainage Scheme, Dhool
Choor, Depal Pur Okara
On-going
Schemes20.325 7.992 4.108 3.081 0.539 17% 42%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 9804
Person, Work is in progress.
1410 3013Rural Water Supply & Drainage Scheme, Aman
Wala, Depal Pur Okara
On-going
Schemes19.930 9.991 3.310 2.483 1.325 53% 57%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 4246
Person, Work is in progress.
1411 3014Rural Water Supply & Drainage Scheme, Dhol
Gehla, Depal Pur Okara
On-going
Schemes17.400 7.987 3.133 2.350 1.523 65% 55%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 3302
Person Work is in progress.
1412 3015Rural Water Supply & Drainage Scheme, Mehro
Kalan, Depal Pur Okara
On-going
Schemes17.190 7.500 3.230 2.423 1.060 44% 50%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 6277
Person Work is in progress.
1413 3016Rural Water Supply & Drainage Scheme, Somian
Bholon, Depal Pur Okara
On-going
Schemes17.660 9.972 2.553 1.915 1.262 66% 64%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 3678
Person Work is in progress.
1414 3017Rural Water Supply & Drainage Scheme, Roori,
Depal Pur Okara
On-going
Schemes15.520 9.991 1.840 1.380 0.920 67% 70%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 3005
Person Work is in progress.
1415 3018Rural Water Supply & Drainage Scheme, Mali
Singh, Depal Pur Okara
On-going
Schemes17.900 7.912 3.300 2.475 1.613 65% 53%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 3813
Person Work is in progress.
1416 3019Rural Water Supply & Drainage Scheme, Khan
Bahadar, Depal Pur Okara
On-going
Schemes25.790 9.970 5.263 3.947 2.916 74% 50%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 5319
Person Work is in progress.
1417 3020Rural Water Supply & Drainage Scheme, Kalia
Ibrahim, Depal Pur Okara
On-going
Schemes22.970 4.992 5.990 4.493 2.234 50% 31%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 07-12-2017 Date of Receipt of
tenders 08-12-2017 Date of work order 14-12-2017
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 2866
Person Work is in progress.
1418 3021Rural Water Supply & Drainage Scheme,
Shamaskay, Depal Pur Okara
On-going
Schemes19.710 10.000 3.237 2.428 1.615 67% 59%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018, A
nticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 2619
Person Work is in progress.
1419 3022Rural Water Supply & Drainage Scheme, Subhan
Shah, Depal Pur Okara
On-going
Schemes22.450 9.995 4.150 3.113 1.841 59% 53%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 5870
Person Work is in progress.
1420 3023Rural Water Supply & Drainage Scheme, Bothana,
Depal Pur Okara
On-going
Schemes21.110 9.999 3.703 2.777 1.852 67% 56%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 5652
Person Work is in progress.
1421 3024Rural Water Supply & Drainage Scheme,
Sahniwal, Depal Pur Okara
On-going
Schemes21.510 11.000 3.503 2.627 1.774 68% 59%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary 4724
Person Work is in progress.
1422 3025Rural Water Supply & Drainage Scheme, Chak no.
7/D Rakh Dharma, Depal Pur Okara
On-going
Schemes17.270 9.993 2.423 1.817 1.163 64% 65%
Date of A.A 26.07.2017, Date of T.S 01.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 3781
Person, Work is in progress.
1423 3026Rural Water Supply & Drainage Scheme,
Kandowal Sarai, Depal Pur Okara
On-going
Schemes18.500 9.992 2.833 2.125 1.413 66% 62%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 07-12-2017 Date of Receipt of
tenders 08-12-2017 Date of work order 12-12-2017
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 6281
Person, Work is in progress.
1424 3027Rural Water Supply & Drainage Scheme, Chak no.
19/D, Depal Pur Okara
On-going
Schemes18.330 9.997 2.777 2.083 1.923 92% 65%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 4604
Person, Work is in progress.
1425 3028Rural Water Supply & Drainage Scheme, Sarai
Amar Singh, Depal Pur Okara
On-going
Schemes21.320 9.998 3.773 2.830 1.792 63% 55%
Date of A.A 26.07.2017, Date of T.S 01.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 6642
Person, Work is in progress.
1426 3029Rural Water Supply & Drainage Scheme, Chak
Kamboh, Depal Pur Okara
On-going
Schemes21.650 9.999 3.883 2.912 1.907 65% 55%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 5441
Person, Work is in progress.
1427 3030Rural Water Supply & Drainage Scheme, Doola
Mustakim , Depal Pur Okara
On-going
Schemes19.930 9.986 3.310 2.483 1.645 66% 58%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 10.10.2017, Date of Receipt of
tenders 11.10.2017, Date of work order 16-11-2017,
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 3942
Person, Work is in progress.
1428 3031Rural Water Supply & Drainage Scheme, Bonga
Saleh, Depal Pur Okara
On-going
Schemes21.580 9.992 3.860 2.895 1.874 65% 55%
Date of A.A 26.07.2017, Date of T.S 01.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 07-12-2017 Date of Receipt of
tenders 08-12-2017 Date of work order 14-12-2017
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 7909
Person, Work is in progress.
1429 3032
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara Chak no.
38-GD
OkaraOn-going
Schemes64.454 7.800 3.333 2.500 0.735 29% 13%
Date of A.A 11.08.2017, Date of T.S 15.08.2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 08.10.2017, Date of Receipt of
tenders 09.10.2017, Date of work order 18-11-2017,
Date of completion as per PC-I 30.06.2019,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary -14313
Person, Work is in progress.
1430 3033
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara Chak no.
4/GD
OkaraOn-going
Schemes25.000 9.999 3.333 2.500 1.297 52% 45%
Date of A.A 26.07.2017, Date of T.S 31-07-2017,
Date of Prequalification 13-09-2017, Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order ,07-02-2018
Date of completion as per PC-I 30.06.2018,
Anticipated date of completion 30.06.2019, Funds
Release on 20-07-2018 No. of Beneficiary - 10018
Person,
1431 3034Soling / Sewerage and Drainage of Chak No.
53/2L, 54/2L, 55/2L, District OkaraOkara
On-going
Schemes20.000 9.999 3.333 2.500 1.667 67% 58%
Date of A.A 26.07.2017, Date of T.S 31-07-2017,
Date of Prequalification ,13.09.2017 Date of
invitation of tenders 18-12-.2017, Date of Receipt of
tenders 19-12-2017, Date of work order 19-01-2018
Date of completion as per PC-I , Anticipated date of
completion, 30-06-2019 Funds Release on 20-07-
2018 No. of Beneficiary - 51657 Person,
1432 3035Provision of Soling and Drainage Scheme at U.C.
No.42/3R, District Okara Okara
On-going
Schemes14.000 6.986 2.333 1.750 0.875 50% 56%
Date of A.A 08.08.2017, Date of T.S 10.08.2017
Date of Prequalification ,13.09.2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 31-09-2017
Date of completion as per PC-I , Anticipated date of
completion , 30-06-2019 Funds Release on 20-07-
2018 No. of Beneficiary - 49251 Person, Work is in
progress.
1433 3036Provision of Soling and Drainage Scheme at U.C.
No.35/2RA, District Okara Okara
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58%
Date of A.A 26.07.2017, Date of T.S 02-08-2017
Date of Prequalification ,13.09.2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 12-12-2017
Date of completion as per PC-I , Anticipated date of
completion, 30-06-2019 Funds Release on 20-07-
2018 No. of Beneficiary - 33832 Person,
1434 3037Provision of Tuff Tiles Soling, PCC, and Drainage
Schemes at Haveli Lakha and Adjoining Abadies Okara
On-going
Schemes48.940 18.295 3.333 2.500 1.660 66% 41%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification ,13.09.2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 20-11-2017
Date of completion as per PC-I , Anticipated date of
completion, 30-06-2019 Funds Release on 20-07-
2018 No. of Beneficiary 42300 Person, Work is in
progress.
1435 3038
Installation of LED Street Light 120/W, 50/W
including Pools, Construction of Sullage Carrier /
sewerage & Construction of Tuff Paver different
places at Okara City approx. District Okara
OkaraOn-going
Schemes74.312 38.998 3.333 2.500 1.667 67% 55%
Date of A.A 11.08.2017, Date of T.S 27.09.2017,
Date of Prequalification 19-09-2017 Date of
invitation of tenders 03.11.2017, Date of Receipt of
tenders 03.11.2017, Date of work order 09-11-2017
Date of completion as per PC-I , Anticipated date of
completion, 30-06-2019 Funds Release on 20-07-
2018 No. of Beneficiary 215982 Person Work is in
progress.
1436 3039Construction of Tuff Tiles / Sewerage and
Drainage of Ward no. 1 to 50, District Okara Okara
On-going
Schemes40.000 14.957 3.333 2.500 1.762 70% 42%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 17-11-2017
Date of completion as per PC-I , 30-06-2018
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary -640401
Person,
1437 3040
City Package Renala Khurd Tuff Tile and
Sewerage Androon City Gilyat Renala Khurd In
District Okara
OkaraOn-going
Schemes35.000 15.584 3.333 2.500 1.667 67% 49%
Date of A.A 26.07.2017, Date of T.S 01.08.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 07-11-2017
Date of completion as per PC-I 30-06-2018
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - 64595
Person,
1438 3041
Sewerage Scheme at Mohallah Shakoor Abad,
Mohallah Eid Gah, Mohallah Masjid Basharat,
Akhter Town, Haveli Lakha, City.
OkaraOn-going
Schemes49.934 22.496 3.333 2.500 1.665 67% 48%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 18-11-2017
Date of completion as per PC-I ,30-06-2018
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - Person,
1439 3042 Water supply Schemes for NA-145 OkaraOn-going
Schemes300.000 74.642 20.000 20.990 20.990 100% 32%
Date of A.A 28-09-2017 Date of T.S 16-11-2017
Date of Prequalification 18-11-2017 Date of
invitation of tenders 13-12-2017 Date of Receipt of
tenders, 13-12-2017 Date of work order 23-12-2017
Date of completion as per PC-I 23-12-2020
Anticipated date of completion, 30-06-2020Re-
Appropreation (+)5.990 No. of Beneficiary 900043
Person,
1440 3043
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara:in Mouza
Jaboka
OkaraOn-going
Schemes23.299 11.494 3.333 2.500 1.669 67% 56%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 25-01-2018
Date of completion as per PC-I ,25-01-2019
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - 14607
Person,
1441 3044
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara Mouza
Lasharian
OkaraOn-going
Schemes49.895 17.413 3.333 2.500 1.713 69% 38%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 25-01-2018
Date of completion as per PC-I 25-01-2019
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - 17695
Person,
1442 3045
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara Mouza
Kohla
OkaraOn-going
Schemes26.331 4.996 3.333 2.500 1.705 68% 25%
Date of A.A 26.07.2017, Date of T.S 02.08.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 18-12-.2017, Date of Receipt of
tenders 19-12.2017, Date of work order 19-01-2018
Date of completion as per PC-I 19-01-2019
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - 21476
Person,
1443 3046
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara Mouza
Bama Bala
OkaraOn-going
Schemes18.346 13.991 1.282 0.962 0.682 71% 80%
Date of A.A 26.07.2017, Date of T.S 31.07.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 18-11-2017
Date of completion as per PC-I 30-06-2018
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - 12896
Person, Work is in progress.
1444 3047
Construction of Drain, Brick Pavement, Sullage
Carrier, Tuff Tile, PCC in District Okara Mouza
Maroula Sharif
OkaraOn-going
Schemes27.702 14.999 4.234 3.176 2.059 65% 62%
Date of A.A 08.08.2017, Date of T.S 12.08.2017,
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 23-12-2017
Date of completion as per PC-I 30-06-2018
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary - 09561
Person,
1445 3048Provision of Drainage, Sewerage and Tuff Till
Scheme at Civil Area Okara Cantt, District Okara Okara
On-going
Schemes20.000 5.377 4.833 3.625 2.467 68% 39%
Date of A.A 12-09-2017 Date of T.S 16-09-2017
Date of Prequalification 13-09-2017 Date of
invitation of tenders 27.10.2017, Date of Receipt of
tenders 28.10.2017, Date of work order 20-11-2017
Date of completion as per PC-I 30-06-2018
Anticipated date of completion, 30-06-2019 Funds
Release on 20-07-2018 No. of Beneficiary 98441
Person, Work is in progress.
1446 3049
Providing of Tuff Tile & Sewerage / Drainage in
Basirpur and Mandi Ahmad Abad Town, District
Okara
OkaraOn-going
Schemes26.398 9.999 3.333 4.167 0.816 20% 41% Work is in progress.
1447 3050Water Supply / Sewerage / Filtration Plants in 13
UCs of PP-221, SahiwalSahiwal
On-going
Schemes150.000 34.996 16.667 12.500 10.100 81% 30%
Date of AA 06.12.2017 , Date of receipt of tender
28.03.2018 , Work order 18.04.2018 , Work in
progress.
1448 3051 Water Supply Scheme for Chak No. 78/5L Sahiwal SahiwalOn-going
Schemes30.000 10.000 6.667 5.000 5.000 100% 50%
Date of AA 19.08.2017, Date of Pre-qualification ,
Date of Work Order 23.12.2017 , Anticipated date of
completion 30.06.2019 subject to availablity of
balance funds, Work in progress.
1449 3052
Construction of Drain / Soling Sewerage Nala
Chak no. 50/12L, 105/12L, 106/12/L, District
Sahiwal
SahiwalOn-going
Schemes15.000 5.000 3.333 2.500 2.000 80% 47%
Date of AA 01.08.2017 , Date of receipt of tender
20.11.2017 , Date of Work Order 02.12.2017 ,
Anticipated date of completion 30.06.2019 subject
to availablity of balance funds, Work in progress.
1450 3053
Construction of Drain / Soling Sewerage Nala
Chak no.38/14L,39/14L/40/14L, 41/14L , District
Sahiwal
SahiwalOn-going
Schemes15.000 4.998 3.333 2.500 1.660 66% 44%
Date of AA 01.08.2017 , Date of receipt of tender
09.11.2017 , Date of Work Order 24.11.2017 ,
Anticipated date of completion 30.06.2019 subject
to availablity of balance funds, Work in progress.
1451 3054
Construction of Drain / Soling Sewerage Nala
Chak no. 40/12L, 109/12L, Ghulshan Colony,
District Sahiwal
SahiwalOn-going
Schemes15.000 4.977 3.333 2.500 2.000 80% 47%
Date of AA 01.08.2017 , Date of receipt of tenders
09.11.2017 , Date of Work Order 24.11.2017 ,
Anticipated date of completion 30.06.2019 subject
to availablity of balance funds, Work in progress.
1452 3055
Construction of Drain / Soling Sewerage Nala
Chak no. 118/12L, 117/12L, Ada Kassowal, District
Sahiwal
SahiwalOn-going
Schemes15.000 7.488 2.500 1.875 1.500 80% 60%
Date of AA 01.08.2017 , Date of receipt of tender
20.11.2017 , Date of Work Order 02.12.2017 ,
Anticipated date of completion 30.06.2019 subject
to availablity of balance funds, Work in progress.
1453 3056
Contruction of Drain / Soling Sewerage Nala Chak
no. 119/7DR, 120/7ER, 121/7ER, 122/7ER,
117/7DR, District Sahiwal
SahiwalOn-going
Schemes15.000 7.495 2.500 1.875 1.600 85% 61%
Date of AA 01.08.2017, Date of receipt of tender
09.11.2017, Date of Work Order 24.11.2017,
Anticipated date of completion 30.06.2019 subject
to availablity of balance funds, Work in progress.
1454 3057
Construction of Drain / Soling Sewerage Nala
Chak no. 114/7R, 115/7CR, 116/7CR Sahwa,
Dharma, District Sahiwal
SahiwalOn-going
Schemes15.000 7.499 2.500 1.875 1.600 85% 61%
Date of AA 01.08.2017, Date of receipt of tender
09.11.2017, Date of Work Order
24.11.2017,Anticipated date of completion
30.06.2019 subject to availablity of balance funds,
Work in progress.
1455 3058
Construction of Drain / Soling Sewerage Nala
Chak no. 112/7r, 113/7r, Purani Chichawatni,
Sheikh Tayyab, District Sahiwal
SahiwalOn-going
Schemes15.000 7.497 2.500 1.875 1.700 91% 61%
Date of AA 01.08.2017 , Date of receipt of tender
09.11.2017 , Date of Work Order
02.12.2017,Anticipated date of completion
30.06.2019 subject to availablity of balance funds,
Work in progress,
1456 3059Installation of Filtration Plant at 60/5L in District
Sahiwal Sahiwal
On-going
Schemes3.000 1.500 0.500 0.375 0.250 67% 58%
Date of AA 01.08.2017, Date of receipt of tender
11.09.2017, Date of Work Order 31.10.2017, Date
of Completion 30.06.2019 , Scheme completed.
Balance funds will be re-appropriated.
1457 3060Installation of Filtration Plant at 79/5R in District
Sahiwal Sahiwal
On-going
Schemes3.000 1.500 0.500 0.375 0.072 19% 52%
Date of AA 01.08.2017, Date of receipt of tender
11.09.2017, Date of Work Order 31.10.2017, Date
of Completion 30.06.2019 , Scheme completed in
saving. Balance funds will be re-appropriated.
1458 3061Rural Water Supply Scheme ChakNo. 20/SP
Tehsil and District Pakpattan Pakpattan
On-going
Schemes31.190 9.000 7.397 5.548 4.498 81% 43%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 23.09.2017, Funds released by FD =
03.08.2018,Funds online = 13.08.2018,Work in
progress.
1459 3062Rural Water Supply Scheme Kumari Wala Tehsil
and District Pakpattan Pakpattan
On-going
Schemes34.670 14.978 5.223 3.917 2.612 67% 51%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 31.10.2017, Funds released by FD =
03.08.2018,Funds online = 13.08.2018,Work in
progress.
1460 3063Rural Water Supply Scheme Chak No. 67/D Tehsil
and District Pakpattan Pakpattan
On-going
Schemes32.440 8.700 7.813 5.860 4.120 70% 40%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 23.09.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1461 3064Rural Water Supply Scheme Dhupai Tehsil and
District Pakpattan Pakpattan
On-going
Schemes29.980 16.000 4.660 3.495 2.330 67% 61%
Date of A.A= 01.08.2017. Date of T.S= 04.08.2017.
Date of receipt of tenders = 24.08.2017. Date of
work order= 18.09.2017. Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1462 3065Rural Water Supply Scheme Chak No. 29/KB in
District Pakpattan Pakpattan
On-going
Schemes19.978 10.000 3.326 2.495 1.750 70% 59%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 31.10.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1463 3066Rural Water Supply Scheme Chak No. 111/EB in
District Pakpattan Pakpattan
On-going
Schemes29.412 8.000 7.137 5.353 4.270 80% 42%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 31.10.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1464 3067Rural Drainage Scheme Chak No. 74/D Tehsil and
District Pakpattan Pakpattan
On-going
Schemes27.671 15.000 4.224 3.168 2.112 67% 62%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 23.09.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1465 3068Rural Drainage Scheme 8/EB Tehsil and District
Pakpattn Pakpattan
On-going
Schemes23.979 13.979 3.333 2.500 1.667 67% 65%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 31.10.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1466 3069Rural Drainage Scheme 90/D Tehsil and District
Pakpattan Pakpattan
On-going
Schemes29.303 19.000 3.434 2.576 1.850 72% 71%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 23.09.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1467 3070Rural Drainage scheme in Various UCs of PP-228
District PakpattanPakpattan
On-going
Schemes74.312 25.000 8.333 6.250 4.356 70% 40%
Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,
Date of receipt of tenders = 21.10.2017, Date of
work order= 13.11.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1468 3071
Provision of Sewerage/ Tuff Tile / PCC / Soling /
Nallian in Various UC's of PP-228 in District
Pakpattan
PakpattanOn-going
Schemes74.312 25.000 16.437 12.328 8.450 69% 45%
Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,
Date of receipt of tenders = 21.10.2017, Date of
work order= 13.11.2017, Funds released by FD =
03.08.2018Funds online = 15.08.2018,Work in
progress.
1469 3072Rural Sewerage / Drainage Scheme Jamman
Shah in District Pakpattan Pakpattan
On-going
Schemes37.413 6.000 10.471 7.853 6.756 86% 34%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 31.10.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1470 3073Rural Sewerage / Drainage Scheme Chak No.
123/EB in District Pakpattan Pakpattan
On-going
Schemes31.582 20.000 1.304 0.978 0.652 67% 65%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 23.09.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1471 3074Rural Sewerage / Drainage Scheme Chak
No.211/EB in District PakpattanPakpattan
On-going
Schemes36.230 27.376 2.610 1.958 1.770 90% 80%
Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,
Date of receipt of tenders = 24.08.2017, Date of
work order= 23.09.2017, Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress.
1472 3075
Provision of Drainage/ Sewerage Schemes at
Chak No. 161/E.B and Union Council NO.35
(Headquarters 13/EB) Tehsil Arifwala District
Pakpattan
PakpattanOn-going
Schemes35.785 12.976 6.762 5.072 0.000 0% 36%
Amended A.A issued on 27.01.2018.Tender
received on 07.02.2018 and Additional performance
security received on 13.02.2018 and Work order
issued on 17.02.2018.Funds released by FD =
03.08.2018Funds online = 13.08.2018,Work in
progress. Contractor liability amounting to Rs.2.500
million stands. The case submitted to P&D
Department Lahore for correction of project code.
1473 3076Provision of PCC / Sewerage / Drainage / Tuff tiles
etc. in PP-227, District PakpattanPakpattan
On-going
Schemes150.000 33.142 8.333 6.250 6.250 100% 26%
Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,
Date of receipt of tenders = 21.10.2017, Date of
work order= 13.11.2017,Funds released by FD =
03.08.2018Funds online = 15.08.2018,Work in
progress.
1474 3077Provision of PCC / Sewerage / Drainage / Tuff tiles
etc. in NA-165, District PakpattanPakpattan
On-going
Schemes148.624 34.998 16.667 12.500 9.250 74% 30%
Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,
Date of receipt of tenders = 21.10.2017, Date of
work order= 13.11.2017,Funds released by FD =
03.08.2018Funds online = 15.08.2018,Work in
progress.
1475 3078Provision of PCC / Sewerage / Drainage / Tuff
Tiles etc. in PP-231Pakpattan
On-going
Schemes148.624 31.997 8.333 6.250 5.150 82% 25%
Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,
Date of receipt of tenders = 21.10.2017, Date of
work order= 13.11.2017,Funds released by FD =
03.08.2018Funds online = 15.08.2018,Work in
progress.
1476 3079
Rural Water Supply and Drainage Scheme Basti
Nazak Nagar, Tehsil Jalapur Pirwala, District
Multan
MultanOn-going
Schemes49.180 14.982 11.393 8.545 5.697 67% 42%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 10.01.2018
7.Date of Completion as per PC-l 30.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 4578 persons. Work is in progress
1477 3080Rural Drainage / Sewerage Scheme Basti Bahadur
Pur Tehsil Jalalpur Pirwala District MultanMultan
On-going
Schemes48.970 14.960 11.323 8.492 5.652 67% 42%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 22.12.2017
7.Date of Completion as per PC-l 21.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries = persons. Work is in progress
1478 3081Rural Drainage / Sewerage Scheme Shujat Pur
Tehsil Jalalpur Pirwala District MultanMultan
On-going
Schemes49.070 15.000 11.357 8.518 5.657 66% 42%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 23.12.2017
7.Date of Completion as per PC-l 22.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries - persons. Work is in progress
1479 3082Rural Water Supply Scheme Chak No.55/M and
56/M District MultanMultan
On-going
Schemes14.000 4.947 3.000 2.250 1.500 67% 46%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 03.11.2017 7.Date
of Completion as per PC-l 02.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 4572 persons. Work is in progress
1480 3083Rural Water Supply Scheme Chak No.71, 72 &
73/M District MultanMultan
On-going
Schemes21.000 9.834 3.667 2.750 1.832 67% 56%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 27.11.2017 7.Date
of Completion as per PC-l 26.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 6354 persons. Work is in progress
1481 3084Rural Water Supply Scheme Chak No.76, 77 and
78/M District MultanMultan
On-going
Schemes21.000 9.949 3.667 2.750 1.832 67% 56%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 27.11.2017 7.Date
of Completion as per PC-l 26.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 4687 persons. Work is in progress
1482 3085Rural Water Supply Scheme Chak No.79, 80 &
81/M District MultanMultan
On-going
Schemes21.000 9.853 3.667 2.750 1.834 67% 56%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 27.11.2017 7.Date
of Completion as per PC-l 26.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 6554 persons. Work is in progress
1483 3086
Rural Water Supply Scheme Mouza Obvra
Shumali Saray Khara and Jungle Ameer Hussain
District Multan
MultanOn-going
Schemes14.000 6.840 2.333 1.750 1.167 67% 57%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 03.11.2017 7.Date
of Completion as per PC-l 02.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 12354 persons. Work is in progress
1484 3087Rural Sewerage Scheme Basti Nandla North &
South District MultanMultan
On-going
Schemes45.000 14.990 3.333 2.500 2.459 98% 39%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 19.01.2018
7.Date of Completion as per PC-l 18.07.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 11358 persons. Work is in progress
1485 3088Rural Sewerage Scheme Adda band Bosan, Roye
Hatti & Mattay Hatti District MultanMultan
On-going
Schemes40.600 9.919 3.333 2.500 1.667 67% 29%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 01.01.2018
7.Date of Completion as per PC-l 30.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 13474 persons. Work is in progress
1486 3089Rural Sewerage Scheme Ghousabad, District
MultanMultan
On-going
Schemes37.000 8.690 3.333 2.500 1.667 67% 28%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 29.12.2017 7.Date
of Completion as per PC-l 28.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 14879 persons. Work is in progress
1487 3090Rural Drainage / Sewerage Scheme Chah
Bananwala District MultanMultan
On-going
Schemes14.970 9.995 1.657 1.243 0.829 67% 72%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 23.12.2017 7.Date
of Completion as per PC-l 22.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 9476 persons. Work is in progress
1488 3091
Rural Sewerage Scheme Taj Pur Sandila,
Dhareeban Thahti Sandila Faiz Town UC 95
Tehshil & District Multan
MultanOn-going
Schemes49.980 14.980 3.333 2.500 1.667 67% 33%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 29.12.2017
7.Date of Completion as per PC-l 28.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 4658 persons. Work is in progress
1489 3092Rural Sewerage Scheme Qasim Bela, Basti
Langrial Tehsil and District MultanMultan
On-going
Schemes32.410 13.975 3.333 2.500 1.667 67% 48%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.12.2017 7.Date
of Completion as per PC-l 27.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 4789 persons. Work is in progress
1490 3093Rural Sewerage Scheme Mouza Ajwani / Sharif
District MultanMultan
On-going
Schemes96.500 29.998 3.333 2.500 1.667 67% 33%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 05.01.2018
7.Date of Completion as per PC-l 04.07.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 6589 persons. Work is in progress
1491 3094Rural Drainage, Soling and Tuff Tile Scheme in
Union Council Bagrian District MultanMultan
On-going
Schemes50.000 19.949 3.333 2.500 1.667 67% 43%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 17.01.2018
7.Date of Completion as per PC-l 30.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries = persons. Work is in progress
1492 3095Rural Drainage, Soling and Tuff Tile Scheme in
Union Council Hilal Wajah District MultanMultan
On-going
Schemes50.000 19.973 3.333 2.500 1.667 67% 43%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 27.12.2017
7.Date of Completion as per PC-l 26.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries = persons. Work is in progress
1493 3096Rural Drainage, Soling and Tuff Tile Scheme in
Union Council Gardez Pur District MultanMultan
On-going
Schemes50.000 19.981 3.333 2.500 1.667 67% 43%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 23.12.2017
7.Date of Completion as per PC-l 22.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries = persons. Work is in progress
1494 3097Rural Drainage / Sewerage Scheme Kotla Chakar
Jalalpur Pirwala District MultanMultan
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 28.12.2017
7.Date of Completion as per PC-l 27.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 4587 persons. Work is in progress
1495 3098Rural Drainage / Sewerage Scheme Basti Mithu
Gharbi District MultanMultan
On-going
Schemes30.000 9.850 3.333 2.500 1.667 67% 38%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 10.11.2017 7.Date
of Completion as per PC-l 09.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 13254 persons. Work is in progress
1496 3099Rural Drainage / Sewerage Scheme Muqeempur
District MultanMultan
On-going
Schemes33.000 11.974 3.333 2.500 1.667 67% 41%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 21.12.2017 7.Date
of Completion as per PC-l 20.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 13546 persons. Work is in progress
1497 3100Rural Drainage / Sewerage Scheme Munshi Wala
District MultanMultan
On-going
Schemes39.000 11.994 3.333 2.500 1.667 67% 35%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 10.01.2018 7.Date
of Completion as per PC-l 09.07.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 12144 persons. Work is in progress
1498 3101Rural Drainage / Sewerage Scheme Lal Wah
District MultanMultan
On-going
Schemes25.000 9.931 3.333 2.500 1.667 67% 46%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 11.12.2017 7.Date
of Completion as per PC-l 10.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 14456 persons. Work is in progress
1499 3102Rural Drainage / Sewerage Scheme Obara
Shumali District MultanMultan
On-going
Schemes30.000 11.699 3.333 2.500 1.667 67% 45%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 10.11.2017 7.Date
of Completion as per PC-l 09.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 11243 persons. Work is in progress
1500 3103Rural Drainage / Sewerage Scheme Jagoo Wala
District MultanMultan
On-going
Schemes50.000 9.976 3.333 2.500 1.667 67% 23%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 01.02.2018
7.Date of Completion as per PC-l 30.07.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 3547 persons. Work is in progress
1501 3104Rural Sewerage / Drainage Scheme Kotla Abdul
Fateh District MultanMultan
On-going
Schemes20.000 9.990 3.333 2.500 1.667 67% 58%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.12.2017 7.Date
of Completion as per PC-l 27.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 6547 persons. Work is in progress
1502 3105
Rural Drainage Scheme Basti Kothy Wala, New
Kothy Wala, Basti Utar Wali and Haroo Wala
Mouza Kothy Wala District Multan
MultanOn-going
Schemes30.000 9.994 3.333 2.500 1.667 67% 39%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 19.02.2018 7.Date
of Completion as per PC-l 18.08.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries - persons. Work is in progress
1503 3106 Rural Drainage Scheme UC 18/MR, District Multan MultanOn-going
Schemes26.000 9.521 3.333 2.500 1.667 67% 43%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.01.2018 7.Date
of Completion as per PC-l 27.07.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries - persons. Work is in progress
1504 3107Rural Water Supply Scheme Mouza Matotli and
Qaiser Pur District MultanMultan
On-going
Schemes14.000 6.962 2.333 1.750 1.167 67% 58%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 03.11.2017 7.Date
of Completion as per PC-l 02.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 10452 persons. Work is in progress
1505 3108Rural Water Supply Scheme Mouza Sha Musa and
Muqeem Pur District MultanMultan
On-going
Schemes14.000 6.942 2.333 1.750 1.167 67% 58%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 03.11.2017 7.Date
of Completion as per PC-l 02.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 11365 persons. Work is in progress
1506 3109
Rural Water Supply Scheme Mouza Adu Wali,
Inayat Pur, Mochi Panhuwah, Basti Bairar District
Multan
MultanOn-going
Schemes21.000 9.849 3.667 2.750 1.834 67% 56%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 14.12.2017 7.Date
of Completion as per PC-l 13.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 9878 persons. Work is in progress
1507 3110Rural Water Supply Scheme Mouza Obvra Janubi,
Basti Lang and Nauraja Bhutta District MultanMultan
On-going
Schemes15.000 6.844 2.667 2.000 1.334 67% 55%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 03.11.2017 7.Date
of Completion as per PC-l 02.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 7458 persons. Work is in progress
1508 3111
Rural Sewerage/ Drainage scheme Katcha Talla,
ict Munirabad, Kot Shehbaz Pull 18-Kassi Bhdhla
Road Tehsil & district Multan
MultanOn-going
Schemes44.530 15.000 9.843 7.382 4.922 67% 45%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 13.01.2018
7.Date of Completion as per PC-l 30.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 11354 persons. Work is in progress
1509 3112
Rural Sewerage Scheme 18-Kassi Ghareeb Abad
and Adjoining Abadies UC Jhok Lashkar Pur
District Multan
MultanOn-going
Schemes44.470 14.956 9.823 7.367 4.912 67% 45%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 28.12.2017
7.Date of Completion as per PC-l 27.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 4687 persons. Work is in progress
1510 3113Rural Sewerage Scheme Asghar Pur and Munir
Abad, UC Jhok Lashkar Pur District MultanMultan
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 23.12.2017 7.Date
of Completion as per PC-l 22.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 4589 persons. Work is in progress
1511 3114Rural Drainage Scheme UC Kot Rab Nawaz, UC
120 District MultanMultan
On-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 14.12.2017 7.Date
of Completion as per PC-l 13.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries = persons. Work is in progress
1512 3115Rural Drainage Scheme UC 123 Jalal Abad
Shumali District MultanMultan
On-going
Schemes15.000 9.962 1.667 1.250 0.834 67% 72%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.12.2017 7.Date
of Completion as per PC-l 27.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries = persons. Work is in progress
1513 3116Rural Drainage Scheme UC 131 Chatha District
MultanMultan
On-going
Schemes20.000 9.997 3.333 2.500 1.667 67% 58%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 03.11.2017 7.Date
of Completion as per PC-l 02.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries = persons. Work is in progress
1514 3117Rural Drainage Scheme UC 134 Kiri Tamak
District MultanMultan
On-going
Schemes20.000 9.910 3.333 2.500 1.667 67% 58%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 21.11.2017 7.Date
of Completion as per PC-l 20.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries = persons. Work is in progress
1515 3118Rural Sewerage Scheme Basti Beat Wala Ajwain
Sharif Tehsil & District MultanMultan
On-going
Schemes11.540 4.982 2.180 1.635 1.090 67% 53%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.12.2017 7.Date
of Completion as per PC-l 27.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries= 12358 persons. Work is in progress
1516 3119Rural Sewerage Scheme Tiab Masood Pur, Tehsil
& District Multan Multan
On-going
Schemes33.470 12.346 3.333 2.500 1.667 67% 42%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 23.12.2017
7.Date of Completion as per PC-l 22.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries =14356 persons. Work is in
progress
1517 3120Rural Sewerage Scheme Sharif Pura New
Shalimar Tehsil & District MultanMultan
On-going
Schemes38.080 10.625 3.333 2.500 1.662 66% 32%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 19.01.2018 7.Date
of Completion as per PC-l 18.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries =10358 persons. Work is in progress
1518 3121Rural Sewerage Scheme Gareen Town Deen Pur
& Jarran Wala District MultanMultan
On-going
Schemes41.960 7.499 3.333 2.500 1.664 67% 22%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 14.02.2018
7.Date of Completion as per PC-l 13.08.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries =12548 persons. Work is in
progress
1519 3122Sewerage Scheme Zakaria Town Phase-III District
MultanMultan
On-going
Schemes16.500 9.908 2.167 1.625 1.084 67% 67%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 27.11.2017 7.Date
of Completion as per PC-l 26.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries =14225 persons. Work is in progress
1520 3123Main Sewerage Line for Farrukh Town & Raja Pur,
District MultanMultan
On-going
Schemes49.990 25.000 3.333 2.500 1.660 66% 53%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 04.01.2018
7.Date of Completion as per PC-l 03.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries =11658 persons. Work is in
progress
1521 3124 Water Purification Plants 10 District Multan MultanOn-going
Schemes20.000 9.940 3.333 2.500 1.667 67% 58%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 14.12.2017 7.Date
of Completion as per PC-l 13.06.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries =14212 persons. Work is in progress
1522 3125Rural Drainage Scheme UC-Khan Pur maral,
District MultanMultan
On-going
Schemes13.000 9.967 1.000 0.750 0.500 67% 81%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 30.01.2018 7.Date
of Completion as per PC-l 29.07.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries = persons. Work is in progress
1523 3126Funds for drain/sewerage and soling for UC 95 &
96 City Shujabad. District MultanMultan
On-going
Schemes80.000 26.735 3.333 8.884 8.783 99% 44%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 05.01.2018
7.Date of Completion as per PC-l 30.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 10.No. of
beneficiaries 5587 persons. Work is in progress
1524 3127Funds for drain/sewerage, soling from Raja Ram,
Bagrain and Shahpur. District MultanMultan
On-going
Schemes40.000 16.976 3.333 2.500 1.665 67% 47%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 23.12.2017
7.Date of Completion as per PC-l 22.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries= 6987 persons. Work is in progress
1525 3128
Rural Sewerage and Drainage Scheme, Tuff Tile
Pavement in Basti Ado Wali, Basti Adam Wali,
Basti Dhando, Basti Hayat Pur, Basti Balocha,
Wach Sandela, Basti Ali Pur Sadat and Basti Gull
Wala UC Ali Pur Sadat District Multan
MultanOn-going
Schemes28.000 14.999 4.333 3.250 2.167 67% 61%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 21.11.2017 7.Date
of Completion as per PC-l 20.05.2019 8. Anticipated
date of completion 30.06.2018 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries =15325 persons. Work is in progress
1526 3129
Rural Sewerage and Drainage Scheme, Tuff Tile
Pavement in Basti Brar, Basti Pathan Wala, Basti
Ahmad Wali, Basti Daya, Basti Barzawah, Basti
Lohar, Basti Inayat Pur, Basti Sial, Basti Saif Ullah
Shah, Basti Gakhar, Basti Bagh Arain Wali, Basti
Miani, Basti Ranojha, Basti Saich Wali, Basti
Deewan Wali and Basti Mochian Wali UC Inayat
Pur District Multan
MultanOn-going
Schemes30.000 9.972 6.667 5.000 3.334 67% 44%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 29.11.2017 7.Date
of Completion as per PC-l 28.05.2019 8. Anticipated
date of completion 30.06.2018 9. Date of released
of funds 30.08.2018 24.01.2019 10.No. of
beneficiaries 16358 persons. Work is in progress
1527 3130
Rural Sewerage and Drainage Scheme, Tuff Tile
Pavement in Basti Radal Pur, Basti Lutaf Pur,
Chak Numberabad, Molvi Wala, Basti Cut Wala,
Tibbi Qasian, Basti Balochan Wala UC Radal Pur
District Multan
MultanOn-going
Schemes30.000 9.800 3.333 2.500 1.667 67% 38%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.12.2017 7.Date
of Completion as per PC-l 27.06.2019 8. Anticipated
date of completion 30.06.2018 9. Date of released
of funds 30.08.2018 24.01.2019 10.No. of
beneficiaries 14325 persons. Work is in progress
1528 3131
Rural Sewerage and Drainage Scheme, Tuff Tile
Pavement in Basti Mari Noon, Basti Godar, Basti
Dogran, Basti Khokhran, Basti Ghous Pur UC Mari
Noon District Multan
MultanOn-going
Schemes30.000 11.997 3.333 2.500 1.667 67% 46%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 28.12.2017 7.Date
of Completion as per PC-l 27.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 12442 persons. Work is in progress
1529 3132
Rough Cost Estimates for replacement of Old
Sewer Lines at Muhalla Sharif Pura UC 65 Piran
Ghaib II in Sub Division New Multan Sewerage
Central Division WASA Multan
MultanOn-going
Schemes12.450 8.334 0.817 0.613 0.409 67% 70%
1.Date of AA 03.08.2017 2.Date of T.S 09.09.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 20.11.2017 7.Date
of Completion as per PC-l 19.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 13225 persons. Work is in progress
1530 3133
Ext. of Rual Drainage / Sewerage Scheme Chah
Muhammad Hussain wala & Adjoining Ababdies
District Multan
MultanOn-going
Schemes29.510 12.478 3.333 2.500 1.667 67% 48%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Dated of Prequalification - 4.Date of invitation of
tender 27.09.2017 5.Date of Receipt of tenders
18.10.2017 6.Date of work order 22.11.2017 7.Date
of Completion as per PC-l 21.05.2018 8. Anticipated
date of completion 30.06.2019 9. Date of released
of funds 03.08.2018 24.01.2019 10.No. of
beneficiaries 12455 persons. Work is in progress
1531 3134Scheme / Drainage Scheme Kotli Nijabat District
MultanMultan
On-going
Schemes69.500 21.924 3.333 2.500 1.667 67% 34%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 05.01.2018
7.Date of Completion as per PC-l 30.06.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 15654 persons. Work is in progress
1532 3135 Sewerage System in UC-90 District Multan MultanOn-going
Schemes65.000 4.958 3.333 2.500 1.667 67% 10%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 03.03.2018
7.Date of Completion as per PC-l 02.08.2018 8.
Anticipated date of completion 30.06.2019 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 9876 persons. Work is in progress
1533 3136 Sewerage System in UC-82 District Multan MultanOn-going
Schemes65.000 22.996 3.333 2.500 1.667 67% 38%
1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017
3.Date of Prequalification 28.08.2017 4.Date of
invitation of tender 02.12.2017 5.Date of Receipt of
tenders 05.12.2017 6.Date of work order 20.02.2018
7.Date of Completion as per PC-l 19.02.2020 8.
Anticipated date of completion 30.06.2020 9. Date
of released of funds 03.08.2018 24.01.2019 10.No.
of beneficiaries 15775 persons. Work is in progress
1534 3137Rural Drainage Scheme Chak No.7/9-R District
KhanewalKhanewal
On-going
Schemes12.000 6.000 2.000 1.500 1.169 78% 60%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2018 3. Date of Pre-Qualification: --------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
31.12.2018 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: -------- 11
No. of beneficiaries 6340 Persons Work is in
progress.
1535 3138Construction of Drainage Scheme Chak No.93/10-
R District KhanewalKhanewal
On-going
Schemes12.000 2.000 3.333 2.500 2.385 95% 37%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 09.11.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 5788Persons Work is in
progress.
1536 3139Rural Drainage Scheme Chak No.92/10-R District
KhanewalKhanewal
On-going
Schemes18.000 10.000 2.667 2.000 1.891 95% 66%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 09.12.2017 7. Date of Completion as per PC-
I: (8) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 8140 Persons Work is in
progress.
1537 3140Rural Drainage Scheme UC No. 48 Tehsil Mian
ChannuKhanewal
On-going
Schemes11.000 5.000 2.000 1.500 1.500 100% 59%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 8265 Persons Work is in
progress.
1538 3141Rural Drainage Scheme UC No. 51 Tehsil Mian
ChannuKhanewal
On-going
Schemes12.000 6.000 2.000 1.500 1.125 75% 59%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 09.12.2017 7. Date of Completion as per PC-
I: (5) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 6568 Persons Work is in
progress.
1539 3142Rural Drainage Scheme UC No. 55 Tehsil Mian
ChannuKhanewal
On-going
Schemes12.000 7.000 1.667 1.250 1.019 82% 67%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 65619 Persons Work is in
progress.
1540 3143Rural Drainage Scheme UC No. 56 Tehsil Mian
ChannuKhanewal
On-going
Schemes11.000 6.000 1.667 1.250 0.937 75% 63%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 17.11.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 5790 Persons Work is in
progress.
1541 3144Rural Drainage Scheme UC No. 62 Tehsil Mian
ChannuKhanewal
On-going
Schemes12.000 6.000 2.000 1.500 1.119 75% 59%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 5689 Persons Work is in
progress.
1542 3145Rural Drainage Scheme Chak No.134/16-L and
Adjoining Abadies Tehsil Mian ChannuKhanewal
On-going
Schemes12.000 6.000 2.000 1.500 1.211 81% 60%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 6132 Persons Work is in
progress.
1543 3146
Rural Drainage Scheme Chak No 20/8-BR, 1/8-R,
2/8-R, 3/8-R, 4/8-R and Adjoining Abadies Tehsil
Mian Channu
KhanewalOn-going
Schemes12.000 7.000 1.667 1.250 0.949 76% 66%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 6443 Persons Work is in
progress.
1544 3147 Drainage & Soling 122/15-L District Khanewal KhanewalOn-going
Schemes3.000 2.385 0.167 0.125 0.100 80% 83%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (6) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1936 Persons Scheme
Completed in saving.
1545 3148 Drainage & Soling 53/15-L District Khanewal KhanewalOn-going
Schemes3.000 2.500 0.167 0.125 0.094 75% 86%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (3) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1876 Persons Scheme
Completed in saving.
1546 3149 Drainage & Soling 58/15-L District Khanewal KhanewalOn-going
Schemes3.000 2.500 0.167 0.125 0.100 80% 87%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (3) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1916 Persons Work is in
Progress.
1547 3150 Drainage & Soling 117/15-L District Khanewal KhanewalOn-going
Schemes3.000 2.500 0.167 0.125 0.106 85% 87%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 19.10.2017 7. Date of Completion as per PC-
I: (3) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 2065 Persons Scheme
Completed in Saving.
1548 3151 Drainage & Soling 42/15-L District Khanewal KhanewalOn-going
Schemes3.000 2.500 0.167 0.125 0.094 75% 86%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (3) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1837 Persons Scheme
Completed in Saving.
1549 3152 Drainage & Soling 135/16-L District Khanewal KhanewalOn-going
Schemes3.000 2.500 0.167 0.125 0.105 84% 87%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (5) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1926 Persons Work is in
Progress.
1550 3153Drainage & Soling Pakka Haji Majeed District
KhanewalKhanewal
On-going
Schemes3.000 1.700 0.433 0.325 0.277 85% 66%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (3) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1966 Persons Work is in
Progress.
1551 3154Rehabilitation of Sewerage Scheme Tulamba City
in missed area Tehsil Mian ChannuKhanewal
On-going
Schemes49.990 15.000 3.333 2.500 2.258 90% 35%
1. Date of A.A: 26.07.2017 2. Date of T.S:
20.09.2017 3. Date of Pre-Qualification: 05.09.2017
4. Date of Invitation of Tender: 09.11.2017 5. Date
of Receipt of Tender: 11.11.2017 6. Date of Work
order: 23.11.2017 7. Date of Completion as per PC-
I: (12)months 8. Anticipated Date of completion:
31.12.2019 9. Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: -------- 11
No. of beneficiaries 2690 Persons Work is in
progress.
1552 3155Drainage & Soling Chak No.8-9/8-AR District
KhanewalKhanewal
On-going
Schemes3.000 2.500 0.167 0.125 0.112 90% 87%
1. Date of A.A: 26.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: -------- 4.
Date of Invitation of Tender: 28.09.2017 5. Date of
Receipt of Tender: 29.09.2017 6. Date of Work
order: 24.10.2017 7. Date of Completion as per PC-
I: (3) months 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 1896 Persons Scheme
Completed in Saving.
1553 3156
Constructino of Soling, Drains, Sullage Carrier,
RCC Culverts in Union Councils Salar Wahan,
Thull Najeeb, Man Kot, Chak Norang Shah, Boota
Singh, Mari Sahu Ibrahim Pur, Mubarak Pur, 5-
Kassi, Mula Pur, Nabi Pur, Chak Haider Abad &
Monga Wala Tehsil Kabirwala in PP-213 District
Khanewal
KhanewalOn-going
Schemes199.990 72.900 16.667 12.500 11.919 95% 42%
1. Date of A.A: 19.08.2017 2. Date of T.S:
22.09.2017 3. Date of Pre-Qualification: 05.09.2017
4. Date of Invitation of Tender: 09.11.2017 5. Date
of Receipt of Tender: 11.11.2017 6. Date of Work
order: 26.12.2017 7. Date of Completion as per PC-
I: 31.12.2018 8. Anticipated Date of completion:
30.06.2019 9. Date of released of funds 03-08-2018
24.01.2019 10. Reason of Slow Moving: ------- 11
No. of beneficiaries 11356 Persons Work is in
Progress. Rs. 118.765 Million are required to
complete the scheme.
1554 3157Water Supply Scheme Chak No.126/WB, 128/WB
District VehariVehari
On-going
Schemes28.966 9.995 6.322 4.742 3.570 75% 47%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 11.12.2017
7. Date of Completion as per PC-I: 10.12.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ------ 11. No. of
Beneficiary= Persons Work is in progress.
1555 3158Rehabiliation of Water Supply Scheme Chak
No.96/WB District VehariVehari
On-going
Schemes15.000 7.443 1.667 1.250 0.930 74% 56%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019+ 10.
Reason of Slow Moving: ----- 11. No. of
Beneficiary= Persons Work is in progress.
1556 3159
Provision of Water Supply / Filtration Plants &
Sewerage Scheme Chak No.233/EB District
Vehari
VehariOn-going
Schemes17.639 3.877 2.546 1.910 1.390 73% 30%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ----- 11. No. of
Beneficiary= Persons Work is in progress.
1557 3160
Provision of Water Supply / Filtration Plants &
Sewerage Scheme Chak No.249/EB District
Vehari
VehariOn-going
Schemes24.842 5.246 4.947 3.710 2.778 75% 32%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ----- 11. No. of
Beneficiary= Persons Work is in progress.
1558 3161
Provision of Water Supply / Filtration Plants &
Sewerage Scheme Chak No.251/EB District
Vehari
VehariOn-going
Schemes23.451 6.682 4.484 3.363 2.450 73% 39%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ----- 11. No. of
Beneficiary= Persons Work is in progress.
1559 3162
Provision of Water Supply / Filtration Plants &
Sewerage Scheme Chak No.243/EB District
Vehari
VehariOn-going
Schemes20.663 3.934 3.554 2.666 1.980 74% 29%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ----- 11. No. of
Beneficiary= Persons Work is in progress.
1560 3163Rural Sewerage / Drainage & Water Supply
Scheme Chak No.65/WB District VehariVehari
On-going
Schemes31.617 9.998 3.333 2.500 1.890 76% 38%
1. Date of A.A: 31.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: NIL 11. No. of Beneficiary=
Persons Work is in progress.
1561 3164
Construction of Water Filtration Plants 16-No in
Chak No.05/WB, 18/WB, 22/WB, 65/WB, 59/WB,
93/WB, 97/WB, 56/Wb, 34/WB, Pull-48, Pull
Mohsin Shah, 63/WB, 24/WB, 26/WB, Noor Shah
Melsi, Shittab Garh Melsi.
VehariOn-going
Schemes48.000 13.853 11.000 8.250 5.990 73% 41%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1562 3165Rural Water Supply Scheme 176/WB
Baghbanpura District VehariVehari
On-going
Schemes25.171 9.833 5.057 3.793 3.450 91% 53%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 20.11.2017
7. Date of Completion as per PC-I: 19.11.2018 8.
Anticipated Date of Completion: 30.06.2019. 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1563 3166Rural Water Supply Scheme Chak No.182/WB
District VehariVehari
On-going
Schemes16.073 9.999 2.024 1.518 1.150 76% 69%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 22.11.2017
7. Date of Completion as per PC-I: 19.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: --- 11. No. of Beneficiary=
Persons Work is in progress.
1564 3167Rural Water Supply Scheme Chak No.184/WB
District VehariVehari
On-going
Schemes28.673 9.991 6.224 4.668 3.388 73% 47%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1565 3168Rural Water Supply Scheme Chak No.161/WB
District VehariVehari
On-going
Schemes18.426 10.000 2.809 2.107 1.560 74% 63%
1. Date of A.A: 31.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 20.11.2017
7. Date of Completion as per PC-I: 19.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1566 3169Rural Water Supply Scheme Chak No.163/WB
District VehariVehari
On-going
Schemes31.485 9.960 7.162 5.372 4.980 93% 47%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 20.11.2017
7. Date of Completion as per PC-I: 19.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1567 3170Rural Water Supply Scheme Chak No.159/WB
District VehariVehari
On-going
Schemes17.583 9.978 2.528 1.896 1.450 76% 65%
1. Date of A.A: 31.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 23.10.2017 5. Date of Receipt
of Tender: 24.10.2017 6. Date of Award: 20.11.2017
7. Date of Completion as per PC-I: 19.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: --- 11. No. of Beneficiary=
Persons Work is in progress.
1568 3171Rural Water Supply Scheme Chak No.50/WB
Dahlu Hari Chand and 52 Sharqi District VehariVehari
On-going
Schemes123.590 34.755 16.667 12.500 9.370 75% 36%
1. Date of A.A: 21.08.2017 2. Date of T.S:
19.10.2017 3. Date of Pre-Qualification: 27.10.2017
4. Date Invitation of Tender: 29.11.2017 5. Date of
Receipt of Tender: 30.11.2017 6. Date of Award:
27.12.2017 7. Date of Completion as per PC-I:
26.12.2019 8. Anticipated Date of Completion:
30.06.2019 9.Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: --- 11. No.
of Beneficiary= Persons Work is in progress.
1569 3172Sewerage Schemes Chak No.5/WB, 24/WB, 88/
WB and 90/WB. District VehariVehari
On-going
Schemes40.000 8.323 3.333 2.500 1.870 75% 25%
1. Date of A.A: 31.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: NIL 11. No. of Beneficiary=
Persons Work is in progress.
1570 3173Drainage Sewer Scheme Chak No.110/WB District
VehariVehari
On-going
Schemes20.000 9.999 3.333 2.500 1.840 74% 59%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1571 3174Construction of Soling, Drainage & Culverts UC 46-
173/EB District VehariVehari
On-going
Schemes15.000 6.917 2.500 1.875 1.430 76% 56%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: NIL 11. No. of Beneficiary=
Persons Work is in progress.
1572 3175Construction of Soling, Drainage & Culverts UC 53-
275/EB District VehariVehari
On-going
Schemes15.000 7.165 2.500 1.875 1.410 75% 57%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: NIL 11. No. of Beneficiary=
Persons Work is in progress.
1573 3176Construction of Soling, Drainage & Culverts UC 40-
128/EB District VehariVehari
On-going
Schemes15.000 9.807 1.667 1.250 0.945 76% 72%
1. Date of A.A: 31.07.2017. 2. Date of T.S: - 3. Date
of Pre-Qualification: - 4. Date Invitation of Tender:
26.10.2017 5. Date of Receipt of Tender:
28.10.2017 6. Date of Award: 25.11.2017 7. Date of
Completion as per PC-I: 24.11.2018 8. Anticipated
Date of Completion: 30.06.2019 9.Date of released
of funds 03.08.2018 24.01.2019 10. Reason of Slow
Moving: NIL 11. No. of Beneficiary= Persons Work
is in progress.
1574 3177Construction of Soling, Drainage & Culverts UC 44-
199/EB District VehariVehari
On-going
Schemes15.000 9.967 1.667 1.250 0.940 75% 73%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1575 3178Construction of Soling, Drainage & Culverts UC 45-
175/EB District VehariVehari
On-going
Schemes15.000 7.499 2.500 1.875 1.420 76% 59%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1576 3179Construction of Soling , Drainage & Culverts UC49-
233/EB District VehariVehari
On-going
Schemes25.000 12.285 4.167 3.125 2.341 75% 59%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 26.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1577 3180Construction of Soling , Drainage & Culverts UC47-
215/EB District VehariVehari
On-going
Schemes25.000 12.500 4.167 3.125 2.325 74% 59%
1. Date of A.A: 31.07.2017 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1578 3181Construction of Soling , Drainage & Culverts UC48-
187/EB District VehariVehari
On-going
Schemes15.000 12.499 0.833 0.625 0.460 74% 86%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
07.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1579 3182Rural Sewerage / Drainage Scheme Chak No.
57/WB Tehsil & District VehariVehari
On-going
Schemes15.000 6.915 2.667 2.000 1.740 87% 58%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of Receipt
of Tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1580 3183Rural Sewerage / Drainage Scheme Chak No.
53/WB Tehsil & District VehariVehari
On-going
Schemes16.000 7.999 2.667 2.000 1.780 89% 61%
1. Date of A.A: 31.07.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: - 4. Date
Invitation of Tender: 26.10.2017 5. Date of receipt
of tender: 28.10.2017 6. Date of Award: 25.11.2017
7. Date of Completion as per PC-I: 24.11.2018 8.
Anticipated Date of Completion: 30.06.2019 9.Date
of released of funds 03.08.2018 24.01.2019 10.
Reason of Slow Moving: ---- 11. No. of Beneficiary=
Persons Work is in progress.
1581 3184
Rehabilitation and Extension of Water Supply &
Sewerage Schemes Mailsi and Adjoining Abadies.
District Vehari
VehariOn-going
Schemes279.804 74.459 33.333 25.000 18.570 74% 33%
1. Date of A.A: 06.09.2017. 2. Date of T.S:
08.08.2017 3. Date of Pre-Qualification: 27.10.2017
4. Date Invitation of Tender: 29.11.2017 5. Date of
receipt of tender: 30.11.2017 6. Date of Award:
19.01.2018 7. Date of Completion as per PC-I:
18.01.2021 8. Anticipated Date of Completion:
18.01.2021 9.Date of released of funds 03.08.2018
24.01.2019 10. Reason of Slow Moving: ---- 11. No.
of Beneficiary= Persons Work is in progress.
1582 3185Construction of Nali Soling Tuff Tile & Culverts UC
Kot Mubarak, Shero Satal and Yaroo DG Khan
Dera Ghazi
Khan
On-going
Schemes11.500 4.955 2.167 1.625 1.203 74% 54% "• Date of A.A = 13.1.17
1583 3186Construction of Nali Soling Culverts and Tuff Tile
U/C Palgah Chak NO.3 DG Khan
Dera Ghazi
Khan
On-going
Schemes20.000 9.975 3.333 2.500 1.875 75% 59% "• Date of A.A = 13.1.17
1584 3187Construction of Nali Soling & Culverts UC Dagar
Chitt. DG Khan
Dera Ghazi
Khan
On-going
Schemes13.000 6.999 2.000 1.500 1.140 76% 63% "• Date of A.A = 13.1.17
1585 3188Construction of Nali Soling Tuff Tile of Basti Foja
and Darkhast Jamal Janubi DG Khan
Dera Ghazi
Khan
On-going
Schemes14.000 6.643 2.333 1.750 1.313 75% 57% "• Date of A.A = 13.1.17
1586 3189Construction of Nali Soling Tuff Tiles in UC Basti
Malana DG Khan
Dera Ghazi
Khan
On-going
Schemes13.610 6.617 2.203 1.652 1.206 73% 57% "• Date of A.A = 13.1.17
1587 3190Construction of Sewerage Nali Soling & Culverts /
Bridge UC Khakhi. DG Khan
Dera Ghazi
Khan
On-going
Schemes11.000 4.986 2.000 1.500 1.065 71% 55% "• Date of A.A = 13.1.17
1588 3191Construction of Nali Soling Tuff Tile & Culverts UC
Kala DG Khan
Dera Ghazi
Khan
On-going
Schemes12.000 4.985 2.333 1.750 1.260 72% 52% "• Date of A.A = 13.1.17
1589 3192Construction of Nali Soling Tuff Tile & Culverts UC
Shadan Lund DG Khan
Dera Ghazi
Khan
On-going
Schemes14.000 6.000 2.667 2.000 1.460 73% 53% "• Date of A.A = 13.1.17
1590 3193Construction of Nali / Drainage Tuff Tile Choti City
and Colonies DG Khan
Dera Ghazi
Khan
On-going
Schemes40.000 14.264 8.333 6.250 4.500 72% 47% "• Date of A.A = 13.1.17
1591 3194Water Supply Scheme City Choti Zereen District
DG Khan
Dera Ghazi
Khan
On-going
Schemes50.000 14.999 11.667 8.750 6.388 73% 43% "• Date of A.A = 25.7.2017
1592 3195Rehabilitation and Augmentation of Water Supply
Scheme of Choti Zareen
Dera Ghazi
Khan
On-going
Schemes30.000 4.999 3.333 2.500 1.800 72% 23% "• Date of A.A = 25.7.2017
1593 3196Rural Water Supply Scheme Nutkani District DG
Khan
Dera Ghazi
Khan
On-going
Schemes80.000 29.999 10.000 7.500 5.325 71% 44% "• Date of A.A = 16.09.2017
1594 3197Construction of PCC Drainage / Tuff Tile in NA-171
DG Khan
Dera Ghazi
Khan
On-going
Schemes155.000 26.295 33.333 25.000 18.000 72% 29% "• Date of A.A = 16.09.2017
1595 3198Rehabilitation of Water Supply in Block Churatta
District DG Khan
Dera Ghazi
Khan
On-going
Schemes20.000 9.964 3.333 2.500 1.850 74% 59% "• Date of A.A = 25.7.2017
1596 3199Rehabilitation of Water Supply in Union Gaddai
District DG Khan
Dera Ghazi
Khan
On-going
Schemes20.000 9.999 3.333 2.500 1.825 73% 59% "• Date of A.A = 25.7.2017
1597 3200Construction of Nali Soling Tuff Tiles & Culverts
UC Shero Satai DG Khan
Dera Ghazi
Khan
On-going
Schemes3.000 2.354 0.167 0.125 0.088 70% 81% "• Date of A.A = 25.7.2017
1598 3201Construction of Nali Soling Culverts Jhok,Uttra DG
Khan
Dera Ghazi
Khan
On-going
Schemes3.000 2.438 0.167 0.125 0.091 73% 84% "• Date of A.A = 25.7.2017
1599 3202Construction of Nali Soling in Jukharr Imam &
Sherru Qasbas
Dera Ghazi
Khan
On-going
Schemes3.000 2.474 0.167 0.125 0.093 74% 86% "• Date of A.A = 25.7.2017
1600 3203Sewerage and Tuff Tiles in PP-244 District DG
Khan
Dera Ghazi
Khan
On-going
Schemes90.000 49.000 6.667 5.000 3.500 70% 58% "• Date of A.A = 16.09.2017
1601 3204
Rehabilitation of Rural Water Supply Scheme in
Thul Sirak & Thul Jaman Tehsil Jampur, District
Rajanpur.
RajanpurOn-going
Schemes15.000 10.000 1.667 1.250 0.834 67% 72% "• Date of A.A = 09.01.2018
1602 3205Provision of Sewerage & Tuff Tile Kot Tahir City
District Rajanpur Rajanpur
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017.
1603 3206Installation of 1000 Nos. Deep Hand Pumps at
Pachad Area, District Rajanpur.Rajanpur
On-going
Schemes35.000 12.000 7.667 5.750 3.834 67% 45% "• Date of A.A = 04.08.2017.
1604 3207Rehabilitation of water supply in scheme Basti
Tuski in District Rajan PurRajanpur
On-going
Schemes16.000 8.000 2.667 2.000 1.334 67% 58% "• Date of A.A = 04.08.2017.
1605 3208
Water supply scheme in Veeni Khosa to Hajoo Via
Basti Riaz hambae UC-Wah Lashari in District
Rajanpur
RajanpurOn-going
Schemes13.000 5.993 2.333 1.750 1.167 67% 55% "• Date of A.A = 04.08.2017.
1606 3209 Deep Hand Pump in Pachad Area 200No RajanpurOn-going
Schemes50.000 16.000 11.333 8.500 5.667 67% 43% "• Date of A.A = 04.08.2017.
1607 3210
Rural drainage / sewerage, PCC & Tuff Tile
Flooring Rajanpur City of left over area District
Rajanpur
RajanpurOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017.
1608 3211Construction of Tuff Tile, Soling, Sewerage,
Drainage and Street etc Rajan Pur CityRajanpur
On-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% "• Date of A.A = 04.08.2017.
1609 3212Construction of Street, Soling, Sewerage,
Drainage, Tuff tiles in District Rajan Pur CityRajanpur
On-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% "• Date of A.A = 04.08.2017.
1610 3213Provision of Sewerage & Tuff Tile at Basti Cheena,
Basti Talai Wala U/C Kot Janu. Disrict Rajan PurRajanpur
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% "• Date of A.A = 04.08.2017.
1611 3214Provision of Sewerage & Tuff Tile Noshera Gharbi.
Disrict Rajan PurRajanpur
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017.
1612 3215Provision of Sewerage and Tuff Tile Kotla
Mughlan. Disrict Rajan PurRajanpur
On-going
Schemes30.000 9.990 6.667 5.000 3.334 67% 44% "• Date of A.A = 04.08.2017.
1613 3216Construction of Soling and Drain UC Jhugi Wala
District MuzaffargarhMuzaffargarh
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 31.7.2017
1614 3217Construction of Soling, Tuff Tiles & Drain UC
Seetpur District MuzaffargarhMuzaffargarh
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 31.7.2017
1615 3218Provision of Soling Tuff Tiles & Drains in Union
Council Alludewall, District Muzaffargarh (Revised)Muzaffargarh
On-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018
1616 3219
Construction of Soling Tuff Tiles & Drains in Union
Council Meeran Pur, District Muzaffargarh
(Revised)
MuzaffargarhOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018
1617 3220
Construction of Soling Tuff Tiles & Drains in Union
Council Usman Koria, District Muzaffargarh
(Revised)
MuzaffargarhOn-going
Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018
1618 3221Construction of PCC/ Drainage and Tuff Tiles
District MuzaffargarhMuzaffargarh
On-going
Schemes90.000 25.000 6.667 5.000 3.200 64% 31% Date of A.A 06.9.2017
1619 3222
Provision of Tuff Tile, Sewerage and Drainage in
Urban Area Municipal Committee Chowk Sarwar
Shaheed District Muzaffargarh
MuzaffargarhOn-going
Schemes40.000 10.000 30.000 22.500 10.450 46% 51% • Date of AA 5.8.2017
1620 3223
Construction of Soling and Driange work in UC-
Dammar Wala and Kotla Gmaoon, District
Muzaffargarh
MuzaffargarhOn-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Date of AA 31.7.2017
1621 3224
Construction of Soling and Driange work in Calor
Wali Qadir Pur and Damar Wali, District
Muzaffargarh
MuzaffargarhOn-going
Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Date of AA 31.7.2017
1622 3225
Construction of Soling and Driange work in Janda
Wali Aluda Wali and Mahal Khakhi, District
Muzaffargarh
MuzaffargarhOn-going
Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017
1623 3226Const: of Soling Drain Tuff Tile VR Bridges UC
Kotla Gamon District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1624 3227Const: of Soling Drain Tuff Tile VR Bridges UC
Kotla Lal Shah District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1625 3228Const: of Soling Drain Tuff Tile VR Bridges UC
Shehr Sultan District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 13.250 3.333 2.500 1.667 67% 50% Date of AA 31.7.2017
1626 3229Const: of Soling Drain Tuff Tile VR Bridges UC
Vains District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1627 3230Const: of Soling Drain Tuff Tile VR Bridges UC
Jhalarin District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1628 3231Const: of Soling Drain Tuff Tile VR Bridges UC
Bair Bund District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1629 3232Const: of Soling Drain Tuff Tile VR Bridges UC
Binda Ishaq District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1630 3233Drainange / Soling / Tuff Tile / Culverts Gul Wala,
Khanpur Fazil Kalroo District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017
1631 3234Construction of Soling and Driange work in UC-
Vains and Basti Arif Wala, District MuzaffargarhMuzaffargarh
On-going
Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Date of AA 31.7.2017
1632 3235
Construction of Soling and Driange work in Jatoi,
Rampur, Nichrani, Baber, Azam Khan and Kasir
Gazlani, District Muzaffargarh
MuzaffargarhOn-going
Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017
1633 3236
Construction of Soling and Driange work in Rohilan
Wali, Binday Wali and Khakhi, District
Muzaffargarh
MuzaffargarhOn-going
Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017
1634 3237
Construction of Soling and Driange work in Miyan
Sawar Mochi Wala Ganga and Khakhi, District
Muzaffargarh
MuzaffargarhOn-going
Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017
1635 3238
Construction of Soling and Driange work in Baily
Wala and Bait Umar Draz and Bindi Pitafi, District
Muzaffargarh
MuzaffargarhOn-going
Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017
1636 3239
Cosntruction of Soling / Drainage and Culverts Tuff
Tiles Municipal Committee Daira Deen Panah
District Muzaffargarh
MuzaffargarhOn-going
Schemes20.000 9.000 3.333 2.500 2.167 87% 56% Date of AA 31.7.2017
1637 3240
Drainage / Soling / UC Thath Gurmani, U/C
Gurmani Sharqi, U/C Sheikh Umar, U/C Daya
Jokha Sharqi, U/C Gujrat U/C Allud District
Muzaffargarh
MuzaffargarhOn-going
Schemes100.000 33.500 6.667 5.000 3.300 66% 37% Date of A.A 06.9.2017
1638 3241Muzaffargarh City Sewerage Scheme Soling /
Drainage, Tuff Tiles District MuzaffargarhMuzaffargarh
On-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Date of AA 31.7.2017
1639 3242Construction of Soling / Drainage Tuff Tiles Union
Council Taleri Doaba District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Date of AA 31.7.2017
1640 3243Construction of Soling / Drainage Tuff Tiles Union
Council Bhutta Pur District MuzaffargarhMuzaffargarh
On-going
Schemes30.000 10.000 3.333 2.500 1.640 66% 39% Date of AA 31.7.2017
1641 3244
Drainage / Soling / Tuff Tiles / Culverts K.D Qurehi,
Gulqaim Mastoi, Budh, Wanpitafi, Sharif Chujra, Ali
Dah, Dawna, Mehmood Kot District Muzaffargarh
MuzaffargarhOn-going
Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Date of AA 31.7.2017
1642 3245
Construction of Soling / Drainage Tuff Tile Culverts
sullage Carrier Pull Pullet PPC Allied Work etc
Qureshi Aabwala Rahim Ali Mulan Walidad
Mazhay wala Tibbi Godar Chowk Sanwai Syed
Hassan Shah Bakhsh Wala Jada Chandai District
Muzaffargarh
MuzaffargarhOn-going
Schemes60.000 20.000 3.333 2.500 1.667 67% 36% Date of AA 31.7.2017
1643 3246
Const: of Soling/ Sewerage Drain UC Jhanday
Wali UC Manikpur UC Darien UC Shahjamal UC
Alludeywali District Muzaffargarh
MuzaffargarhOn-going
Schemes30.000 10.000 3.333 2.500 1.650 66% 39% Date of AA 31.7.2017
1644 3247Construction of PCC/Drainage and Tuff Tile in
NA179 and PP-258 District MuzaffargarhMuzaffargarh
On-going
Schemes65.000 25.000 6.667 5.000 3.334 67% 44% Date of A.A 06.9.2017
1645 3248
Construction of Tuff Tile Drainge Sewerage Soling
PCC Slab and different work PP-262 District
Layyah
LayyahOn-going
Schemes100.000 35.000 6.667 5.000 3.334 67% 38% • Date of AA = 15.08.2017
1646 3249
Construction of Tuff Tile Drainage Sewerage
Soling PCC Slab and different work PP-263 District
Layyah
LayyahOn-going
Schemes120.000 30.000 10.000 7.500 5.000 67% 29% • Date of AA = 15.08.2017
1647 3250
Construction of Tuff Tile Drainage Sewerage
Soling PCC Slab and different work PP-264 District
Layyah
LayyahOn-going
Schemes100.000 30.000 16.667 12.500 8.334 67% 38% • Date of AA = 15.08.2017
1648 3251Comprehensive sewerage / Drainage scheme
along with tuff Tile in Choubara city District Layyah.Layyah
On-going
Schemes100.000 30.000 23.333 17.500 11.667 67% 42% • Date of AA = 15.08.2017
1649 3252 Swerage Drainge / Tuff Tiles for Layyah city LayyahOn-going
Schemes300.000 75.000 50.000 37.500 25.000 67% 33% • Date of AA = 06.09.2017
1650 3253
Construction of Sewerage/Drains and Laying of
Tuff Tiles/Soling in UC, Sirishta Thal District
Layyah
LayyahOn-going
Schemes143.137 10.000 21.297 15.973 10.643 67% 14%
Administrative Approval issued on dated. 08-01-
2018.
1651 3254
Rural Sewerage/ Drainage / Brick Pavement / Tuff
Tiles in Union Council 164-A / TDA and Adjoining
Abadies Tehsil District Layyah
LayyahOn-going
Schemes20.000 10.000 3.333 2.500 1.660 66% 58% • Date of AA = 29.07.2017
1652 3255Const. of Road, Sewerage & tuff Tile Chak
No.5/BC District BahawalpurBahawalpur
On-going
Schemes11.889 5.990 1.963 1.472 0.980 67% 59%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of tender; 12-10-2017. Date of award:-26-10-
2017. Date of completion. 25-10-2018. Anticipated
date of completion 30-06-2019. Date of receipt of
funds by F.D. 20.07.2018 & 11.01.2019. Work is in
progress.
1653 3256Rehabilitation of water supply schemes in Chak
no.5/DNB Tehsil Yazman District BahawalpurBahawalpur
On-going
Schemes20.488 9.994 3.496 2.622 1.740 66% 57%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 12-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1654 3257Rehabilitation of water supply schemes in Chak
no.14/DNB Tehsil Yazman District BahawalpurBahawalpur
On-going
Schemes20.802 14.939 1.934 1.451 0.967 67% 76%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 23-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1655 3258Rehabilitation of water supply schemes in Chak
no.76/DNB Tehsil Yazman District BahawalpurBahawalpur
On-going
Schemes17.490 8.396 2.497 1.873 1.245 66% 55%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 23-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1656 3259Rehabilitation of water supply schemes in Chak
no.24/DNB Tehsil Yazman District BahawalpurBahawalpur
On-going
Schemes21.552 9.997 3.851 2.888 1.925 67% 55%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 23-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1657 3260Rehabilitation of water supply schemes in Chak
No.44/DB Tehsil Yazman, District Bahawalpur.Bahawalpur
On-going
Schemes46.980 25.000 3.333 2.500 1.660 66% 57%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 23-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1658 3261Rehabilitation of water supply schemes in Chak
No.143/DB Tehsil Yazman, District Bahawalpur.Bahawalpur
On-going
Schemes22.680 14.996 2.560 1.920 1.280 67% 72%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 23-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1659 3262Water Supply Scheme in Chak No.115/DB Kachi
Tehsil Yazman District Bahawalpur.Bahawalpur
On-going
Schemes20.000 9.928 3.333 2.500 1.660 66% 58%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of tender; 23-10-2017. Date of award:-31-10-
2017. Date of completion. 30-07-2018. Anticipated
date of completion 30-06-2019. Date of receipt of
funds by F.D. 20.07.2018 & 11.01.2019. Work is in
progress.
1660 3263 Water Supply scheme of Chak No.114/DNB BahawalpurOn-going
Schemes18.000 8.698 2.667 2.000 1.334 67% 56%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 23-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1661 3264Const. of Road, Sewerage & Tuff Tile Basti
Hansarah District BahawalpurBahawalpur
On-going
Schemes15.000 5.954 3.000 2.250 1.500 67% 50%
Date of AA = 27-07-2017. Date of T.S 29.09.2017. .
Date of receipt of tender: 12-10-2017. Date of
award: 31.10.2017. Date of completion: 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1662 3265P/L of Sewerage and Tuff Tile Basti Inayati Tehsil
Khairpur Tamewali District BahawalpurBahawalpur
On-going
Schemes29.000 14.991 4.667 3.500 2.330 67% 60%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1663 3266P/L of Sewerage and Tuff Tile Basti Bohran Tehsil
Khairpur Tamewali District Bahawalpur Bahawalpur
On-going
Schemes15.300 4.974 3.433 2.575 1.710 66% 44%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 12-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1664 3267Sewerage/Drainage/Tuff Tiles/ Sullage in
189/Murad adjoining Abadies District BahawalpurBahawalpur
On-going
Schemes22.000 9.999 4.000 3.000 2.000 67% 55%
Date of AA= 08.08.2017 . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1665 3268
Sewerage/Drainage/Tuff Tiles/ Sullage in
147/Murad and adjoining Abadies District
Bahawalpur
BahawalpurOn-going
Schemes35.000 9.990 3.333 2.500 1.660 66% 33%
Date of AA= 08.08.2017 . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1666 3269
Sewerage/Drainage/Tuff Tiles/ Sullage in
179/Murad and adjoining Abadies District
Bahawalpur
BahawalpurOn-going
Schemes35.100 14.341 3.333 2.500 1.660 66% 46%
Date of AA= 08.08.2017 . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1667 3270Sewerage/Drainage/Tuff Tiles/ Sullage in
160/Murad Adjoining Abadies, District BahawalpurBahawalpur
On-going
Schemes35.100 14.999 3.333 2.500 1.660 66% 47%
Date of AA= 08.08.2017 . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1668 3271Const. of Sewarage & Tuff Tile Basti Kori Wala,
Hoot Wala District BahawalpurBahawalpur
On-going
Schemes20.000 9.989 3.333 2.500 1.660 66% 58%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1669 3272
Rehabilitation of Sewerage Scheme/Drainage and
Tuff Tiles City Noor Pur Noranga District
Bahawalpur
BahawalpurOn-going
Schemes12.086 8.999 1.029 0.772 0.514 67% 79%
Date of AA= 27-07-2017. . Date of T.S= 31.07-
2017. Date of tender; 12-10-2017. Date of award:-
26-10-2017. Date of completion. 25-09-2018.
Anticipation date of completion.30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1670 3273P/L Sewerage /Tuff Tile City Hathaiji Mouza
Hathaiji Tehsil Ahmadpur East District BahawalpurBahawalpur
On-going
Schemes50.000 19.998 10.000 7.500 5.000 67% 50%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1671 3274P/L Sewerage /Tuff Tile Mubrakpur City Tehsil
Ahmadpur East District BahawalpurBahawalpur
On-going
Schemes40.000 6.903 3.333 2.500 1.659 66% 21%
Date of AA= 27-07-2017. . Date of T.S=09-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
. Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1672 3275Rehabilitation of Sewerage, City Yazman District
BahawalpurBahawalpur
On-going
Schemes300.000 59.999 33.333 25.000 16.500 66% 25%
Date of A.A (DDSC). 28-09-2017. Date of T.S. 17-
10-2017. Prequalification completed on 06-11-2017.
Date of receipt of tender from Prequalified
contractors on 05-12-2017 .Date of award. 01-01-
2018. Date of completion. 31-12-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1673 3276Sewerage Scheme Chak No.86/DB District
BahawalpurBahawalpur
On-going
Schemes19.359 8.000 3.786 2.840 1.890 67% 51%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1674 3277Sewerage Scheme Chak No.53/DB District
BahawalpurBahawalpur
On-going
Schemes20.588 8.999 3.863 2.897 1.927 67% 53%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1675 3278Sewerage Scheme Chak No.68/DB District
BahawalpurBahawalpur
On-going
Schemes16.397 4.998 3.799 2.849 1.900 67% 42%
Date of AA= 27-07-2017. . Date of T.S=08-08-2017.
Date of receipt of tender: 12-10-2017. Date of
award:-31-10-2017. Date of completion. 30.07.2018.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1676 3279Provision of Tuff Tile & Sanitation Scheme in Hatiji
Tehsil Ahmadpur East Ditrict BahawalpurBahawalpur
On-going
Schemes40.000 14.995 3.333 2.500 1.667 67% 42%
Date of AA= 27-07-2017. . Date of T.S=09-08-2017.
Date of receipt of tender: 16-10-2017. Date of
award:-31-10-2017. Date of completion. 30.01.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1677 3280
Provision of Water supply Chak No. 202-206/M,
128-132/M, 133-134/M, 176/M, 60/4/R District
Bahawalnagar
BahawalnagarOn-going
Schemes50.000 14.992 6.667 5.000 5.000 100% 40%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 31-12-
2018. Anticipation date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1678 3281
Provision and laying of water supply schemes
Chak No.53/F alongwith allied basties District
Bahawalnagar
BahawalnagarOn-going
Schemes25.000 10.000 5.000 3.750 3.750 100% 55%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 31-12-
2018. Anticipation date of compltion.30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1679 3282Rehabilitation of water supply schemes Chak
No.45/F Jattan wali District BahawalnagarBahawalnagar
On-going
Schemes15.000 9.984 1.667 1.250 1.250 100% 75%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 30-09-
2018. Anticipation date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1680 3283
Rehabilitation of Rural Water Supply Scheme
Chak No. 82/5-R &138-139/6-R Including All
Adjoining Abadies Tehsil Haroonabad District
Bahawalnagar
BahawalnagarOn-going
Schemes40.000 14.997 8.333 6.250 5.150 82% 50%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1681 3284
Rehabilitation of Rural Water Supply Scheme
Chak No. 53/4-R & 137/6-R Including All Adjoining
Abadies Tehsil Haroonabad District Bahawalnagar
BahawalnagarOn-going
Schemes44.000 15.652 9.447 7.085 5.750 81% 49%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1682 3285
Rural Water Supply Scheme/ Sewerage/ Drainage
scheme Sri Ram Pura, Khair Shah, Bhaluka, Puna,
Habibka, Allah Buksh Lalika, Bunga Machi Murad
Wala, Musa Bhota Jhulan Arrain, Sanateka,
Jurana Basti, Kup Quraishian, Chak Jodheka,
Bhaluka, Chakmadrass, Distr
BahawalnagarOn-going
Schemes80.000 34.980 8.333 6.250 6.250 100% 52%
Date of A.A 09-08-2017. . Date of T.S. 12.10.2017. .
prequalification of the contractors. 31.10.2017. Date
of receipt of Tender from prequalified contractors on
16-11-2017 .Date of award. 30-12-2017.Date of
completion. 29-12-2018.Anticipated date of
completion 30-06-2019. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Work is in progress.
1683 3286
Construction of Soling / Water Supply in Union
Councils Islam Pura, Fateh Kot, Malik Pura, Sawae
Wala, Muhammad Pur, Koryanwala, Denan,
Sondha, Gulaab Ali, Barah Sajwad Khan, Teko
Raam, Donga Bonga District Bahawalnagar
BahawalnagarOn-going
Schemes100.000 29.963 10.000 7.500 7.496 100% 37%
Date of A.A 09-08-2017. Date of T.S. 12.10.2017.
prequalification of the contractors completed on
31.10.2017. Date of receipt of tender. 16-11-2017 .
Date of work awarded. 11-12-2017. Date of
completion. 10-12-2018. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Work is in progress.
1684 3287Rural Water supply scheme of Khiraaj Pura and
Goband Pur District BahawalnagarBahawalnagar
On-going
Schemes15.000 6.996 2.667 2.000 2.000 100% 60%
Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .
Date of receipt of tender 11-09-2017. Date of work
awarded 31.10.2017. Date of completion
30.10.2018. Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1685 3288Rural Water supply scheme of Maakhe wali,
Mohan Pura, Jeeto, Jhugyan District BahawalnagarBahawalnagar
On-going
Schemes15.000 6.960 2.667 2.000 2.000 100% 60%
Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .
Date of receipt of tender received 27.11.2017. Date
of work awarded. 30-11-2017. Date of completion
29-12-2018 . Anticipated date of completion 30-06-
2019Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1686 3289Rural water supply scheme of Taalya and Dhaban
District BahawalnagarBahawalnagar
On-going
Schemes15.000 6.886 2.667 2.000 2.000 100% 59%
Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .
Date of receipt of tender 11-09-2017. Date of work
awarded 31.10.2017. Date of completion
30.10.2018. Anticipated date of completion 30-06-
2019 Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1687 3290
Rehabilitation of Rural Water Supply Scheme
Chak No. 143/6-R including all Adjoining Abadies
Tehsil Haroonabad District Bahawalnagar
BahawalnagarOn-going
Schemes28.807 9.944 6.269 4.702 3.800 81% 48%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1688 3291Rural Water Supply Scheme Chak No. 196/HB
Tehsil Fortabbas District BahawalnagarBahawalnagar
On-going
Schemes25.000 9.999 5.000 3.750 3.090 82% 52%
Date of A.A 03-08-2017. Date of T.S. 08.08.2017. .
Date of receipt of tender 11-11-2017. Date of work
award. 16-11-2017. Anticipated date of completion
30-06-2019. Date of completion 15-11-2018. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1689 3292
Rehabilitation of Rural Water Supply Scheme
Chak No. 70/4-R & 84/5-R Including All Adjoining
Abadies Tehsil Haroonabad District Bahawalnagar
BahawalnagarOn-going
Schemes50.000 19.949 10.000 7.500 6.300 84% 52%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 22-09-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1690 3293
Rural Water Supply Scheme Chak No.
237,238,239/9R & 239/HB Including All Adjoining
Abadies Tehsil Fortabbas. District Bahawalnagar
BahawalnagarOn-going
Schemes40.000 14.999 8.333 6.250 5.550 89% 51%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 02-10-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1691 3294
Construction of Sewer Lines and Tuff Tiles in City
Area Haroonabad Tehsil Haroonabad District
Bahawalnagar
BahawalnagarOn-going
Schemes18.000 9.990 2.667 1.400 1.400 100% 63%
Date of A.A 03-08-2017. . Date of T.S 08-08-2017.
Date of tender receipt 11-09-2017. Date of award
31.10.2017. Date of completion 31.10.2018. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress. Excess funds Rs.0.600 million
surrendered dated 19.10.2018.
1692 3295Construction of Tuff Paverment urban area City
Chistian Ward No.1 to 36 District BahawalnagarBahawalnagar
On-going
Schemes100.000 29.999 16.667 12.500 10.000 80% 40%
Date of A.A. 09-08-2017. Date of T.S. 04.10.2017. .
Tender received on 10-01-2018. Date of award:
23.01.2018. Date of completion 30.06.2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1693 3296
Provision of Soling, Drainage system, Erection of
Tuff Tiles in Mandi Sadiq Gunj city. District
Bahawalnagar
BahawalnagarOn-going
Schemes44.000 16.998 3.333 2.500 2.500 100% 44%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 02-10-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1694 3297
Provision of Soling, Drainage System, Erection of
Tuff Tiles in Macloed Gunj city. District
Bahawalnagart
BahawalnagarOn-going
Schemes50.000 19.985 3.333 2.500 2.498 100% 45%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 28-10-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1695 3298Provision of Soling, Drainage System Erection of
Tuff Tiles in Madhaniwal District BahawalnagarBahawalnagar
On-going
Schemes21.000 9.996 3.667 2.750 2.530 92% 60%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 28-10-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1696 3299Provision of Soling, Drainage System, Erection of
Tuff Tiles in Hasil Sarrhu. District BahawalnagarBahawalnagar
On-going
Schemes45.000 21.853 3.333 8.424 8.422 100% 67%
Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .
Date of Tender receipt 11-09-2017. Date of award
31.10.2017. Date of completion 30.01.2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress. Rs.5.924 million provided
through re-appropriation dated 19.10.2018.
1697 3300Provision of Soling, Tuff Tile, Drainage in Mouza
Muharram Cheena. District BahawalnagarBahawalnagar
On-going
Schemes12.000 9.998 0.667 0.500 0.500 100% 87%
Date of A.A 03-08-2017. . Date of T.S 05.08.2017. .
Date of tender receipt 11-09-2017. Date of award
31.10.2017. Date of completion 30.10.2017.
Anticipated date of completion 30-06-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Scheme completed in saving.
1698 3301Provision of Soling, Tuff Tile, Drainage in Mouza
Hassanwala. District BahawalnagarBahawalnagar
On-going
Schemes21.000 9.999 3.667 2.750 2.600 95% 60%
Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-
2017. Date of receipt of tender. 11-09-2017. Date of
work award. 02-10-2017. Date of completion. 31-12-
2018. Anticipated date of completion 30-06-2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1699 3302
Sewerage / drainage scheme Sri Ram Pura, Khair
Shah, Bhaluka, Puna, Habibka, Allah buksh Lalika,
Bunga Machi Murad wala, Musa Bhota Jhulan
Arrain, Sanateka, Jattu wal Deen Pure, Chak
Hotyana and Jurana Hafizabad District
Bahawalnagar
BahawalnagarOn-going
Schemes150.000 43.484 6.667 5.000 5.000 100% 32%
Date of A.A 09-08-2017. . Date of T.S. 12.10.2017. .
prequalification of the contractors. 31.10.2017. .
Date of receipt of Tender from prequalified
contractors on 16-11-2017 . Date of award. 30-12-
2017. Date of completion 29-03-2019. Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1700 3303
Providing and laying sewerage schemes Chak
No.98/F, Bakhshan Khan, Chak 54/F, 105/F,
10/FW, 174/M District Bahawalnagar
BahawalnagarOn-going
Schemes100.000 29.859 10.000 7.500 7.500 100% 37%
Date of A.A 09-08-2017. Date of T.S 06-11-2017.
Date of receipt of tender: 10-01-2018. Date of
award: 23.01.2018. Date of completion 30.06.2019.
Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1701 3304
Provision of Soling, Drainage System Eraction of
Tutt Tiles in BhainiSikandarJassoka and
MouzaShamonJassoka Tehsil Minchanabad
District Bahawalnagar
BahawalnagarOn-going
Schemes3.000 2.500 0.167 0.209 0.125 60% 88%
The scheme Provision of Soiling, Tuff Tile,
Drainage in Mouza Muharram Cheena District
Bahawalnagar reflected in ADP-2017-18 was
substituted by Standing Committee of the Cabinet
on Finance & Development in its meeting held on
20-09-2017 as proposed by Mian Fida Hussain
Watto EX-MPA PP-277 and minutes of meeting
issued vide S&GAD No.SO(CAB-II)1-2/2017(Fin-
170) dated 06-10-2017. Scheme approved on 02-11-
2017 by DDC. . Work awarded on 29-12-2017 but
work not started due to non availability of funds
during 2017-2018. Now funds have been released
by FD on 12-11-2018 & 11.01.2019. Date of
completion dated 28-03-2018. Anticipated dated of
competition 30-06-2019 Amended A.A is issued
from DC, office on 11-12-2018. Work in progress.
1702 3305
Provision of Soling Drainage System Erection of
Tuff Tile in Moti Pur, Qadir Pur, Munshi Other,
Basti Shah Bharamka, Manzoor Kot, Chak Saroo,
Chak Saroo, Chak Tehsil Minchanabad District
Bahawalnagar
BahawalnagarOn-going
Schemes15.000 9.999 1.667 0.900 0.899 100% 73%
Scheme approved on 02-11-2017 by DDC. Tender
received on 27-11-2017 .Date of receipt of funds by
FD.05-03-2018. Date of award. 29-12-2017. Date of
completion 26-06-2018. Anticipated date of
completion. 25.10.2018. Date of receipt of funds by
F.D. 20.07.2018 & 11.01.2019. Scheme completed
in saving. Excess funds Rs.0.350 million
surrendered dated 19.10.2018.
1703 3306Construction of Sewer Lines and Tuff Tiles in Faqir
Wali Tehsil Haroonabad District BahawalnagarBahawalnagar
On-going
Schemes40.000 14.367 3.333 5.000 4.142 83% 46%
Date of A.A(DDC) 03-08-2017. . Date of T.S. 08-08-
2017. . Date of receipt of tender.12-09-2017. Date
of work award. 22-09-2017. Date of completion. 21-
12-2018. Anticipated date of completion 30-06-
2019. Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Funds Rs.2.500 million Provided
through re-appropriation vide Chief
Engineer(S),PHED Lahore No.72-78/B(4) dated
10.01.2019.Work is in progress.
1704 3307Constuction PCC Draiinge / Soling in NA-193
District Rahim Yar Khan
Rahim Yar
Khan
On-going
Schemes40.013 12.987 3.333 2.500 1.951 78% 37%
Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.
.Date of receipt of Tender: 07.09.2017..Date of
award: 31.10.2017..Date of completion:
28.02.2018..Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress..
1705 3308Construction of laying Sewerage, Water Supply &
Tuff Tiles City Sadiqabad District Rahim Yar Khan
Rahim Yar
Khan
On-going
Schemes30.000 26.419 1.192 0.894 0.699 78% 90%
Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.
.Date of receipt of Tender: 07.09.2017..Date of
award: 31.10.2017..Date of completion:
31.06.2018..Anticipated date of completion 30-06-
2019. Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1706 3309Mega Sewerage Scheme Roads & Tuff Tile
Kotsamaba
Rahim Yar
Khan
On-going
Schemes100.000 14.996 16.667 12.500 9.989 80% 25%
Date of A.A. 09-08-2017. .Date of T.S 26-10-
2017.Date of receipt of Tenders from prequalified
contractors 27-12-2017..Date of award 21-02-
2018..Date of completion 20-10-2019. .Date of
receipt of funds by F.D. 20.07.2018 & 11.01.2019.
Work is in progress.
1707 3310
Providing / Lying of Tuff Tiles Both Sides of Road
from Attock Petrolium to Chowk Din Pur Sharif
Length: 1.50 KM District Rahim Yar Khan
Rahim Yar
Khan
On-going
Schemes31.500 9.999 3.333 2.500 2.156 86% 39%
Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.
.Date of receipt of Tender: 07.09.2017..Date of
award: 31.10.2017..Date of completion:
31.01.2018..Anticipated date of completion 30-06-
2019.Date of receipt of funds by F.D. 20.07.2018 &
11.01.2019. Work is in progress.
1708 3311Rural Drainage Scheme / PCC Slab For Mouza
Rao Bagh Tehsil and Distt. Chiniot Chiniot
On-going
Schemes29.995 7.498 3.333 2.500 1.550 62% 30%
1. Date of AA = 02.08.2017 2. Date of TS =
26.08.2017 3.Date of Award of work 31.10.2017
4.Dated of Released Funds 30.10.2017 Funds
Released upto 24.01.2019 by the Chief Engineer
(South) PHED Lahore and work is in progress.
1709 3312
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Adda Road Haidry
Chowk Lalian, Baldia Road Al Qaim Medical Store
Afzal Bhatti Mehar Sikandar Lali Chowk, Gala
Mandi Paka Bazar Abadi Bil Muqabil Baldiya office
Aqab Abadi Police
ChiniotOn-going
Schemes14.993 10.000 1.664 1.248 0.832 67% 72%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
4.Dated of Released Funds 30.10.2017 Funds
Released upto 24.01.2019 by the Chief Engineer
(South) PHED Lahore and work is in progress.
1710 3313
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Afzal Bhatti Doctor
Bashir Road Heli Chowk Laliyan, beli Chowk
Laliyan, Beli Chowk to soling/ Sheikh Muhammad
Hussain Airan Store Jhang Road via Hujra Mor,
Beli/ Hujra Road to
ChiniotOn-going
Schemes23.000 8.496 4.333 3.250 2.150 66% 46%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
4.Dated of Released Funds 30.10.2017 Funds
Released on 03.08.2018 by the Chief Engineer
(South) PHED Lahore and work is in progress.
1711 3314
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Ahmadabad Chowk
Bazar Kocha Bandi Ward no. 10, Chongi no. 5 to
Jamia Mosque Chowk Bangla Road,Bangla Road
to Chowk Bazar, Kot Muhammad Yar- Nawab
Chowk Aqeeb Baldiya Office Mo
ChiniotOn-going
Schemes17.907 10.000 2.636 1.977 1.257 64% 63%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
4.Dated of Released Funds 30.10.2017 Funds
Released upto 24.01.2019 by the Chief Engineer
(South) PHED Lahore and work is in progress.
1712 3315
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Jamiya Mosque Bangla
Road Nawab Chowk Imtiaz Lali Chowk, Old Eid
gah Changran - Qadirabad Wark No 3, Ghulam
Mustafabad Ward no 4, Dera Mehar Imtiaz Lali to
Haidery Chowk Police
ChiniotOn-going
Schemes26.900 4.938 3.333 2.500 1.667 67% 25%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1713 3316
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Allah Chowk to
Sargodha Road, Station Noorpur Ward no. 2,
Ward no. 5 Laliyan, Tariqabad Ward no. 6 Lalian
ChiniotOn-going
Schemes25.500 4.420 3.333 2.500 1.667 67% 24%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1714 3317
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Jamia Mosque ward no
7 Laliyan, Imtia Town New Eidgah Umerabad ward
no. 11 Phase I, Imtiaz Town New Eidgah
Umerabad ward no 11 Phase II, including Bangla
Road to Pir Qatbi Shah
ChiniotOn-going
Schemes21.499 4.850 3.333 2.500 1.650 66% 30%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1715 3318
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Dars Colony Bashir
Colony Jaly Dar Dakhli Laliyan, Miana Thatha
Zahoor Colony Dakhli Laliyan, Mouza oilywala
Hujra Hujra Colony Abadi near Petrol Pump Dakhli
Laliyan,Mouza Bhais
ChiniotOn-going
Schemes15.500 4.663 3.500 2.625 1.023 39% 37%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore. Work stopped by
the contractor and Notice issued from this office as
well as S.E PHE Circle Faisalabad Office to the
contractor for restart the work.
1716 3319
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles in Mohallah Pulliyan Abadi Rana
Colony Soling remaining Portion sargodha road to
Rana Colony Dakhli Laliyan, Soling, Mouza Wala,
Mouza Thathi Bala Raja, Mouza Kalu wal.
ChiniotOn-going
Schemes31.100 2.850 3.333 2.500 0.972 39% 12%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore. Work stopped by
the contractor and Notice issued from this office as
well as S.E PHE Circle Faisalabad Office to the
contractor for restart the work.
1717 3320
Construction of PCC / Soling / Drainage / Street
and Tuff Tiles Pullian Mouza Ahmad Nagar,
Carpet City Ladhiyan Phase-I, Carpet City
Ladhiyan Phase-II, and alongwith Road Mouza
Changarwala.
ChiniotOn-going
Schemes32.000 9.816 3.333 2.500 1.562 62% 36%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1718 3321
P/L Tuff Tile, Sewer Line PCC and Street Lights in
Mohallah Rehmanabad, Karamabad, Moqeet Town
and Sagheer Colony in Tehsil and District Chiniot
ChiniotOn-going
Schemes40.827 8.900 3.333 2.500 1.667 67% 26%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1719 3322
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
11, District Chiniot
ChiniotOn-going
Schemes49.988 10.000 3.333 2.500 1.667 67% 23%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1720 3323
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
12, District Chiniot
ChiniotOn-going
Schemes49.990 14.200 3.333 2.500 1.667 67% 32%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1721 3324
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
13, District Chiniot
ChiniotOn-going
Schemes49.982 15.000 3.333 2.500 2.500 100% 35%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1722 3325
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
14, District Chiniot
ChiniotOn-going
Schemes49.982 13.000 3.333 2.500 1.650 66% 29%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1723 3326
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
15, District Chiniot
ChiniotOn-going
Schemes49.986 20.000 5.000 3.750 2.500 67% 45%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1724 3327
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
21, District Chiniot
ChiniotOn-going
Schemes49.990 10.000 5.000 3.750 1.789 48% 24%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress. Target progress will be achieved in
coming month.
1725 3328
Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile
/Brick Pavement including all allied works of UC
22, District Chiniot
ChiniotOn-going
Schemes49.980 15.000 5.000 3.750 3.750 100% 38%
1. Date of AA = 02.08.2017 2. Date of TS =
28.08.2017 3.Date of Award of work 31.10.2017
Funds Released upto 24.01.2019 by the Chief
Engineer (South) PHED Lahore and work is in
progress.
1725 Total Ongoing 127182.789 59312.981 8408.757 6297.326 4256.283 68% 50%
New Schemes
1 3329Reheblitiation of Rural Water Supply Scheme
394/JB Tehsil & Distt Toba Tek SinghToba Tek Singh New 28.997 0.000 2.000 0.000 0.000 #DIV/0! 0%
"1-Date of A.A 07.12.2018 2- Date of T.S
12.12.2018 3-Date of Prequalification 4-Date of
invitation of tenders 08.01.2019 5- Date of Receipt
of tenders 09.01.2019 6- Date of work order 7- Date
of completion as per PC-I 8- Anticipated date of
completion 9- No. of Beneficiary -4536-Person 10-
Funds Released by F.D 11-Re-appropriation of
funds (+/-)
2 3330
Rural water supply scheme Saho Chak, Badi Pur &
Gurdanpur U/C Ghurri Tehsil & District Sialkot
(Court Direction)
Sialkot New 27.900 0.000 1.000 1.000 0.000 0% 0% Tender under process
3 3331Rural Drainage Sewerage Scheme of UC Rasulpur
BhallianSialkot New 5.000 0.000 1.000 0.000 0.000 #DIV/0! 0% Tender under process
4 3332
Construction of Sewerage System & Rehabilitation
of Roads, Municipal Committee Zahir Pir Tehsil
Khanpur, Distric R.Y.Khan
Rahim Yar
KhanNew 357.877 0.000 5.000 0.000 0.000 #DIV/0! 0%
Rough Cost Estimate of the scheme is under
preparation by Consultant. Consultant has been
asked for early submission of rough Cost
estimate/PC-1 of the scheme.
5 3333Construction of Waste Water Treatment Plant at
Mianwali.Mianwali New 468.000 0.000 5.000 0.000 0.000 #DIV/0! 0% unapproved
6 3334
Sewerage Drianage Scheme in 05 No. colonies of
chak No. 79/NB including desilting of exisitng
sewer lines, Sargodha (Court Direction)
Sargodha New 69.638 0.000 5.000 0.000 0.000 #DIV/0! 0%Estimate submitted for technical vetting to C.E (N).
Funds yet not released.
7 3335Rehabilitaion / Improvement Sewerage system
Jhang, Phase-IJhang New 700.000 0.000 5.000 0.000 0.000 #DIV/0! 0%
Date of A.A 18.10.2017 Date of T.S 31.10.2017
Work order issued on 13.08.2018. Work is in
progress.
8 3336Sewerage / Drianage scheme adjacent abadies of
ada Mohlanwal Lahore New 150.000 0.000 2.500 0.000 0.000 #DIV/0! 0% AA awaited.
9 3337
Water, Sanitation and Hygiene (WASH)
Programme under stunting reduction programme in
11 Districts of Multan, Bahawalpur and D.G.Khan
Civil Divisions
Punjab New 3,086.564 0.000 8.743 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
10 3338Feasibility Study for provision of surface water and
treatment of waste water across PunjabPunjab New 200.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
11 3339 Funding for Clearance of liablities Punjab New 40.000 0.000 40.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
12 3340
Public Awareness Campaign and strengthening of
communicty development & communication unit of
PHED
Punjab New 100.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
13 3341 Clean Water for Healthy Life Punjab New 5,000.000 0.000 5000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
14 3342 Rural sewerage & drainage schemes Punjab New 3,500.000 0.000 2000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
15 3343Water Quality testing Labortary at Township
Lahore (PPP Mode)Punjab New 395.000 0.000 1.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
16 3344Establishment of Project Support Unit for Clean
Water for Healthy LifePunjab New 500.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
17 3345Insaaf Program for Water Supply and Sanitation in
Rural Areas Punjab New 5,000.000 0.000 5000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.
17 Total New 19628.976 0.000 12091.243 1.000 0.000 0.000 0%
1742 Total Ongoing + New 146811.765 59312.981 20500.000 6298.326 4256.283 68% 43%