Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by F.D Funds utilized till 31.01.19 %age utilization on release 31.01.19 Physical progress till current month (%age) Remarks (including detailed physical progress) (i) Date of Start of the Project (ii) Date of completion of the Project Ongoing Schemes 1 1604 R/W/S Scheme Dhamial Rawalpindi On-going Schemes 181.407 164.389 5.673 2.255 0.837 37% 91% Scheme completed & handed over to CBO only work for restoration of desmantled streets in progress. 2 1605 Construction of Road/Streets in Village Ghoon UC - Beor and Construction of Road/Streets & Hand Pumps in UC -Punjar & UC -Narar, District Rawalpindi Rawalpindi On-going Schemes 8.000 6.000 0.667 0.166 0.000 0% 75% Scheme completed in saving. 3 1606 Water Supply Scheme in Kahuta Town Tesil Kahuta, District Rawalpindi Rawalpindi On-going Schemes 8.000 2.143 1.952 1.464 0.976 67% 39% Work in Progress. 4 1607 P/I Tube Well in Latori Syedan & P/I Hand Pumps in Dhok Naka and Village Matore UC -Matore, District Rawalpindi Rawalpindi On-going Schemes 5.650 0.120 0.667 2.834 2.668 94% 49% Work in Progress. 5 1608 Rehabilitation & Augmentation &Ext of water Supply Scheme for Village Dhullian Attock On-going Schemes 43.515 41.514 0.667 0.500 0.334 67% 96% A.A Date 03.09.2015.T.S Date 23.09.2015. Date of Start of Scheme 10.11.2015.Date of Completion of Scheme 30.06.2019.Work is in progress. 6 1609 Augmentation / Rehabilitation of Water Supply Scheme Khour Tehsil Pindi Gheb District Attock Attock On-going Schemes 69.989 12.510 3.333 2.500 1.667 67% 20% A.A Date 10.09.2016. T.S Date 02.05.2017.Date of Start of Scheme 16.06.2017.Date of Completion of Scheme 30.06.2019.Work is in progress. 7 1610 Rehabilitation of Rural water Supply Scheme Sarkalan Chakwal On-going Schemes 25.000 18.475 2.175 0.543 0.000 0% 74% Date of A.A 08.01.2015.Date of T.S 21.01.2015.Date of Start 20.04.2015.Date of completion .30.06.2019.Percolation well, Ground Storage Tank and Rising main completed. Work on the scheme suspended due to loss of water in.ewly..eveloped.source as some blasting was done by Mining epartment. Revised Rough Cost Estimate submitted to D.C Chakwal vide T/O No.01/CH dated 01-01-2018 for according Revised A.A. 8 1611 Rehabilitation of Rural Water Supply Scheme Dhoke Khour Tehsil Talagang, Chakwal. Chakwal On-going Schemes 1.620 0.719 0.300 0.075 0.000 0% 44% Date of A.A 11.03.2015. Date of T.S 21.01.2015.Date of Start 20.03.2015..Date of completion 30.06.2019 .Work suspended at site due to sever conflicts among the CBO / community members. Community Development Unit trying to resolve the issues. Excessive funds surrendered through re-appropriation. 9 1612 Extension of water Supply scheme Khewra, Tehsil Pind Dadan Khan, District Jhelum Jhelum On-going Schemes 161.845 28.504 13.333 3.653 0.320 9% 18% Date of A.A 11-04-2016.Revised A.A 31-03- 2017.Date of T.S 19-08-2016.Work awarded on 06- 02-2017.Work in progress 10 1613 Authority to maintain & Regulate Naroomi Dhan water Supply Scheme Tehsil P.D.Khan Jhelum On-going Schemes 361.446 10.000 26.667 20.000 13.334 67% 6% Date of A.A 11/2017.Revised A.A 30-111-2017.• Work award on 16.02.2018.Work in progress 11 1614 Rural Water Supply Scheme Chal No 61/SB Sargodah Sargodha On-going Schemes 15.000 0.039 3.333 2.500 1.913 77% 13% Work in progress. 12 1615 Installation of 300 Hand Pumps Noushera Khushab Khushab On-going Schemes 132.000 111.498 1.833 1.375 1.370 100% 86% Date of AA 15-10-2015 Date of TS 09-11-2015 Date of award 05.01.2016 Date of completion 30.06.2019 Work is in progress. 13 1616 water Supply Scheme Jhunge Walan of UC Khabeki. Khushab On-going Schemes 24.058 14.550 3.167 2.375 2.145 90% 69% Date of AA 27.08.2016 Date of TS 03-09-2016 Date of Award 21.01.2017. Date of Completion 30.06.2019 Work is in progress. 14 1617 water Supply Scheme Kalial UC Khura. Khushab On-going Schemes 25.996 15.996 3.333 2.500 2.250 90% 70% Date of AA 27.08.2016 Date of TS 03-09-2016 Date of Award 24.01.2017 Date of Completion 30.06.2019 work is in progress. 15 1618 Rehabilitation / Improvement of Water Supply Scheme, Khoora UC Khoora, District Khushab Khushab On-going Schemes 12.695 1.998 1.000 0.750 0.500 67% 20% Date of AA 29.7.2017 Date of TS 04.09.2017 Date of award 14.12.2017 Date of completion 13.12.2019 Tube Well 1 No. Pump House 1 No. Pumping Machinery 1 No. Rising Main 3640/19400 Rft The Scheme remained unfunded in interim budget however it has been included in ADP 2018-19. work is in progress. MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT PROGRAMME 2018-19 WATER SUPPLY & SANITATION

Transcript of MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme...

Page 1: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

Sr.

No.

GS. No.

NewName of Scheme District Type Approved Cost

Exp Upto

June 2018

Provision for

2018-19

Funds

Released by

F.D

Funds

utilized

till 31.01.19

%age

utilization

on release

31.01.19

Physical

progress till

current month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Ongoing Schemes

1 1604 R/W/S Scheme Dhamial RawalpindiOn-going

Schemes181.407 164.389 5.673 2.255 0.837 37% 91%

Scheme completed & handed over to CBO only

work for restoration of desmantled streets in

progress.

2 1605

Construction of Road/Streets in Village Ghoon UC -

Beor and Construction of Road/Streets & Hand

Pumps in UC -Punjar & UC -Narar, District

Rawalpindi

RawalpindiOn-going

Schemes8.000 6.000 0.667 0.166 0.000 0% 75% Scheme completed in saving.

3 1606Water Supply Scheme in Kahuta Town Tesil

Kahuta, District RawalpindiRawalpindi

On-going

Schemes8.000 2.143 1.952 1.464 0.976 67% 39% Work in Progress.

4 1607

P/I Tube Well in Latori Syedan & P/I Hand Pumps

in Dhok Naka and Village Matore UC -Matore,

District Rawalpindi

RawalpindiOn-going

Schemes5.650 0.120 0.667 2.834 2.668 94% 49% Work in Progress.

5 1608Rehabilitation & Augmentation &Ext of water

Supply Scheme for Village Dhullian Attock

On-going

Schemes43.515 41.514 0.667 0.500 0.334 67% 96%

A.A Date 03.09.2015.T.S Date 23.09.2015. Date of

Start of Scheme 10.11.2015.Date of Completion of

Scheme 30.06.2019.Work is in progress.

6 1609Augmentation / Rehabilitation of Water Supply

Scheme Khour Tehsil Pindi Gheb District AttockAttock

On-going

Schemes69.989 12.510 3.333 2.500 1.667 67% 20%

A.A Date 10.09.2016. T.S Date 02.05.2017.Date of

Start of Scheme 16.06.2017.Date of Completion of

Scheme 30.06.2019.Work is in progress.

7 1610Rehabilitation of Rural water Supply Scheme

SarkalanChakwal

On-going

Schemes25.000 18.475 2.175 0.543 0.000 0% 74%

Date of A.A 08.01.2015.Date of T.S

21.01.2015.Date of Start 20.04.2015.Date of

completion .30.06.2019.Percolation well, Ground

Storage Tank and Rising main completed. Work on

the scheme suspended due to loss of water

in.ewly..eveloped.source as some blasting was done

by Mining epartment. Revised Rough Cost Estimate

submitted to D.C Chakwal vide T/O No.01/CH dated

01-01-2018 for according Revised A.A.

8 1611Rehabilitation of Rural Water Supply Scheme

Dhoke Khour Tehsil Talagang, Chakwal.Chakwal

On-going

Schemes1.620 0.719 0.300 0.075 0.000 0% 44%

Date of A.A 11.03.2015. Date of T.S

21.01.2015.Date of Start 20.03.2015..Date of

completion 30.06.2019 .Work suspended at site due

to sever conflicts among the CBO / community

members. Community Development Unit trying to

resolve the issues. Excessive funds surrendered

through re-appropriation.

9 1612Extension of water Supply scheme Khewra, Tehsil

Pind Dadan Khan, District JhelumJhelum

On-going

Schemes161.845 28.504 13.333 3.653 0.320 9% 18%

Date of A.A 11-04-2016.Revised A.A 31-03-

2017.Date of T.S 19-08-2016.Work awarded on 06-

02-2017.Work in progress

10 1613Authority to maintain & Regulate Naroomi Dhan

water Supply Scheme Tehsil P.D.KhanJhelum

On-going

Schemes361.446 10.000 26.667 20.000 13.334 67% 6%

Date of A.A 11/2017.Revised A.A 30-111-2017.•

Work award on 16.02.2018.Work in progress

11 1614Rural Water Supply Scheme Chal No 61/SB

Sargodah Sargodha

On-going

Schemes15.000 0.039 3.333 2.500 1.913 77% 13% Work in progress.

12 1615Installation of 300 Hand Pumps Noushera

Khushab Khushab

On-going

Schemes132.000 111.498 1.833 1.375 1.370 100% 86%

Date of AA 15-10-2015 Date of TS 09-11-2015 Date

of award 05.01.2016 Date of completion 30.06.2019

Work is in progress.

13 1616 water Supply Scheme Jhunge Walan of UC

Khabeki.Khushab

On-going

Schemes24.058 14.550 3.167 2.375 2.145 90% 69%

Date of AA 27.08.2016 Date of TS 03-09-2016 Date

of Award 21.01.2017. Date of Completion

30.06.2019 Work is in progress.

14 1617 water Supply Scheme Kalial UC Khura. KhushabOn-going

Schemes25.996 15.996 3.333 2.500 2.250 90% 70%

Date of AA 27.08.2016 Date of TS 03-09-2016 Date

of Award 24.01.2017 Date of Completion

30.06.2019 work is in progress.

15 1618Rehabilitation / Improvement of Water Supply

Scheme, Khoora UC Khoora, District KhushabKhushab

On-going

Schemes12.695 1.998 1.000 0.750 0.500 67% 20%

Date of AA 29.7.2017 Date of TS 04.09.2017 Date

of award 14.12.2017 Date of completion 13.12.2019

Tube Well 1 No. Pump House 1 No. Pumping

Machinery 1 No. Rising Main 3640/19400 Rft The

Scheme remained unfunded in interim budget

however it has been included in ADP 2018-19. work

is in progress.

MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT PROGRAMME 2018-19

WATER SUPPLY & SANITATION

Page 2: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

16 1619Installation of Submersible Water Pumps, Tehsil

Isa Khel District Mianwali.Mianwali

On-going

Schemes50.000 37.423 3.387 2.540 1.688 66% 78%

Date of A.A. 13-01-2017, Date of T.S. 24-01-2017,

Date of Start of Work. 08-05-2017, Remarks

E.R.S=130/144, Trail Bore=6/6, T/Well boring=

61/72, P/Machinery= 61/72, G.S.Tank= 7/72. Work

is in progress.

17 1620

Provision of Submersible Pumps (UC Bani Afghan,

Sawance, Ghundi, Chakrala, Ban Hafiz Gee,

Thamay Wali, Namal)

MianwaliOn-going

Schemes49.980 33.415 5.520 4.140 2.760 67% 72%

Date of A.A.27-08-2016, Date of T.S.15-10-2016,

Date of Start of Work.03-12-2016, Remarks.

E.R.S=35/50, T/Well boring= 87/110,

P/Machinery=87/110, G.S.Tank=0/62-No. Work is in

progress.

18 1621Extension of Sewerage and water Supply,

Mankera.Bhakkar

On-going

Schemes71.300 38.133 10.934 8.201 8.201 100% 65%

"Date of A.A 25.08.2015 Date of T.S 11.11.2015

Date of Commencement 28.12.2015 Date of

completion 30.06.2019

19 1622Construction of PCC in Different Streets in UC -64

District Faisalabad Faisalabad

On-going

Schemes5.000 2.000 1.000 0.750 0.500 67% 50%

Date of A.A 05-08-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

20 1623Construction of PCC in Different Streets in UC -65

District Faisalabad Faisalabad

On-going

Schemes5.000 1.000 1.333 1.000 0.666 67% 33%

Date of A.A 05-08-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 &24.1.19

21 1624Construction of PCC in Different Streets in UC -66

District Faisalabad Faisalabad

On-going

Schemes5.000 2.000 1.000 0.750 0.500 67% 50%

Date of A.A 05-08-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

22 1625Construction of PCC in Different Streets in UC -67

District Faisalabad Faisalabad

On-going

Schemes5.000 1.000 1.333 1.000 0.667 67% 33%

Date of A.A 05-08-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

23 1626Construction of PCC in Different Streets in UC -72

District Faisalabad Faisalabad

On-going

Schemes5.000 1.000 1.333 1.000 0.667 67% 33%

Date of A.A 05-08-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

24 1627Installation of Water Filetartion Plant in UC 463

Teshil Smundri District Faisalabad Faisalabad

On-going

Schemes3.000 0.000 1.000 0.000 0.000 #DIV/0! 0%

Case submitted for Change of Nomenclature UC-

463 to Chak No. 463/GB vide SE No. 2414 dated

07.08.2018.

25 1628Rehab: of Rural Water Supply Scheme Chak No.

215/RB Tehsil & Distt: FaisalabadFaisalabad

On-going

Schemes87.765 84.043 1.000 0.750 0.390 52% 96%

AA issued on 21.04.2017. Date of T.S 23.05.2017

Work order issued on 11.05.2009. Work is in

progress. Funds released on 23.11.2018 & 24.1.19.

26 1629 Rural Water Supply Scheme at Chak No.84/JB FaisalabadOn-going

Schemes7.955 6.725 1.230 0.923 0.500 54% 91%

AA issued on 20.10.2016. Date of T.S 24.10.2016

Work order issued on 12.01.2017. Work is in

progress. Funds released on 23.11.2018 & 24.1.19.

27 1630Rehab. of rural water Supply scheme Chak No.

343/GB T.T. SinghToba Tek Singh

On-going

Schemes23.943 18.826 1.318 0.489 0.159 33% 79%

1-Date of A.A 20.10.2016 2- Date of T.S 21.10.2016

3-Date of invitation of tenders. 13.02.2017 4- Date

of Receipt of tenders -15.02.2017 5- Date of

completion as per PC-I 30.06.2018 6- Date of work

order - 06.03.2017 7- Anticipated date of completion

30.06.2018 8- No. of Beneficiary - 5333 Persons 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

10-Re-appropriation of funds(+/-) Scheme

completed in saving.

28 1631 Rural water Supply Scheme Chak No.674/15/GB Toba Tek SinghOn-going

Schemes31.298 18.962 3.011 0.752 0.000 0% 61%

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016

3-Date of invitation of tenders.13.02.2017 4- Date of

Receipt of tenders -15.02.2017 5- Date of

completion as per PC-I 30.06.2018 6- Date of work

order - 09.03.2017 7- Anticipated date of completion

30.06.2018 8- No. of Beneficiary - 6390 Persons 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

10-Re-appropriation of funds(+/-) .Work could not

be started due to site dispute in laying of distribution

system. Progress will be achieved in next month.

29 1632 Rural water Supply Scheme Chak No.675/16/GB Toba Tek SinghOn-going

Schemes28.057 20.000 2.686 1.205 0.533 44% 73%

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016

3-Date of invitation of tenders.13.02.2017 4- Date of

Receipt of tenders -15.02.2017 5- Date of

completion as per PC-I 30.06.2018 6- Date of work

order - 09.03.2017 7- Anticipated date of completion

30.06.2018 8- No. of Beneficiary - 3561 Persons 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

10-Re-appropriation of funds(+/-) Work could not be

started due to site dispute in laying of distribution

system. Progress will be achieved in next month.

Page 3: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

30 1633 Rural water Supply Scheme Chak No.685 26 GB Toba Tek SinghOn-going

Schemes21.024 16.243 0.508 0.127 0.000 0% 77%

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016

3-Date of invitation of tenders.13.02.2017 4- Date of

Receipt of tenders -15.02.2017 5- Date of

completion as per PC-I 30.06.2018 6- Date of work

order - 04.03.2017 7- Anticipated date of completion

30.06.2018 8- No. of Beneficiary - 3381 Persons 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

10-Re-appropriation of funds(+/-) - Work could not

be started due to site dispute in laying of distribution

system. Progress will be achieved in next month.

31 1634Rural water Supply Scheme for Chak No.407/JB,

409/JB, 410/JB & 411/JBToba Tek Singh

On-going

Schemes99.832 74.101 3.333 2.500 1.740 70% 76%

1-Date of A.A 10.09.2015 2- Date of T.S 25.02.2016

3-Date of Prequalification -07.03.2016 4-Date of

invitation of tenders 18.03.2016 5- Date of Receipt

of tenders 26.03.2016 6- Date of work order -

27.04.2016 7- Date of completion as per PC-I

09.09.2017 8- Anticipated date of completion -

09.09.2017 9- No. of Beneficiary - 15516 Person 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

11-Re-appropriation of funds(+/-) Work in progress.

32 1635

Rural water Supply Scheme, Chak No.709/GB

and 710/GB, Tehsil Kamalia, District Toba Tek

Singh

Toba Tek SinghOn-going

Schemes18.232 14.000 0.744 0.186 0.000 0% 77%

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016

3-Date of invitation of tenders. 13.02.2017 4- Date

of Receipt of tenders -15.02.2017 5- Date of

completion as per PC-I 30.06.2018 6- Date of work

order - 09.03.2017 7- Anticipated date of completion

30.06.2018 8- No. of Beneficiary - 5867 Persons 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

10-Re-appropriation of funds(+/-) Work could not be

started due to site dispute in laying of distribution

system. Progress will be achieved in next month.

33 1636

Rural water Supply Scheme, Chak No.712/GB

and Jamal Pahar, Tehsil Kamalia, District Toba

Tek Singh

Toba Tek SinghOn-going

Schemes22.981 17.000 1.994 0.499 0.000 0% 74%

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016

3-Date of invitation of tenders.13.02.2017 4- Date of

Receipt of tenders -15.02.2017 5- Date of

completion as per PC-I 30.06.2018 6- Date of work

order - 03.03.2017 7- Anticipated date of completion

30.06.2018 8- No. of Beneficiary - 4430 Persons 9-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

10-Re-appropriation of funds(+/-) Work could not be

started due to site dispute in laying of distribution

system. Progress will be achieved in next month.

34 1637 water Supply & Sewerage Scheme Rajana District

Toba Tek SinghToba Tek Singh

On-going

Schemes179.779 104.999 8.333 6.250 6.000 96% 62%

1-Date of A.A 06.12.2014 2- Date of T.S 02.03.2015

3-Date of Rev: AA 28.05.2015 4-Date of

Prequalification - 16.08.2016 5-Date of invitation of

tenders 03.10.2016 6- Date of Receipt of tenders

04.10.2016 7- Date of work order 27.10.2016 8-

Date of completion as per PC-I 26.10.2018 9-

Anticipated date of completion 26.10.2018 10- No.

of Beneficiary -21302 Person 11 -Funds Released

by F.D 03.08.2018 & 24.01.2019 12-Re-

appropriation of funds(+/-) Work in progress.

35 1638

Rural water Supply schemes Chak No.285/GB,

383/JB, 390/JB, 380/JB, 382/JB Feroz and

336/GB, T.T. Singh

Toba Tek SinghOn-going

Schemes90.000 69.965 3.333 2.500 2.200 88% 80%

1-Date of A.A 28.12.2015 2- Date of T.S 25.02.2016

3-Date of Prequalification -07.03.2016 4-Date of

invitation of tenders 06.03.2016 5- Date of Receipt

of tenders 26.03.2016 6- Date of work order -

28.04.2016 7- Date of Completion as per PC-I

30.07.2017 8- Anticipated date of completion

30.07.2017 9- No. of Beneficiary - 37501 Person 10-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

11-Re-appropriation of funds(+/-) Work in progress.

36 1639

Installation of 02 No Water Filetration Plants in

Chak no 771/GB & Mouza Akbar Sau & UC Jussa

tehsil Per Mehal District Toba Tek Singh

Toba Tek SinghOn-going

Schemes6.000 0.000 2.000 2.000 1.000 50% 17%

1-Date of A.A 14.11.2018 2- Date of T.S 20.11.2018

3-Date of Prequalification 4-Date of invitation of

tenders 19.12.2018 5- Date of Receipt of tenders

21.12.2018 6- Date of work order 7- Date of

completion as per PC-I 8- Anticipated date of

completion 9- No. of Beneficiary -3233 Person 10-

Funds Released by F.D 18.01.2019 11-Re-

appropriation of funds (+/-) work in progress.

37 1640

Provision of Water Supply and Drainage Scheme

in Village Sher Garh UC Machiwal Tehsil & District

Gujrat

GujratOn-going

Schemes49.971 0.400 3.333 2.500 1.667 67% 4% A.A Date =28.2.2018.work in progress

Page 4: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

38 1641Construction of street / PCC / Soling / Nallian in

various Ucs of District M.B.Din

Mandi

Bahauddin

On-going

Schemes150.000 69.978 3.333 5.150 4.317 84% 50%

* A.A Date. 25.08.2017* T.S Date. 13.09.2017* Start

Date. 06.01.2018* Completion date

05.01.2020*Work in progress.

39 1642Rural water Supply & Drainage Scheme Village

Badshah Pur Tehsil Malikwal District M.B.Din

Mandi

Bahauddin

On-going

Schemes85.587 75.587 3.333 2.500 1.667 67% 90%

* A.A Date. 19.03.2015* T.S Date. 02.04.2015* Start

Date 22.05.2015.* Completion date 30.06.2019.*

Work in progress.

40 1643Rural water Supply & Drainage Scheme Village

Jayya Tehsil & District M.B.Din

Mandi

Bahauddin

On-going

Schemes62.780 57.780 1.667 0.650 0.234 36% 92%

* A.A Date. 19.03.2015* T.S Date. 02.04.2015* Start

Date 22.05.2015.* Completion date 30.06.2019.*

Work in progress.

41 1644

Rural water Supply and drainage Scheme

Bhaagowal & Noor Pur Peeran with adjecent

abadies tehsil Mailk waal district mandi bahuddin

Mandi

Bahauddin

On-going

Schemes50.000 45.000 1.667 0.450 0.034 8% 90%

* A.A Date. 28.04.2015* T.S Date. 19.05.2015* Start

Date 18.06.2015.* Completion date 30.06.2019.*

Work in progress

42 1645Installation of 02 tubewells at Tahayat & Chandrai

Village, Green Town, Lahore Lahore

On-going

Schemes36.878 20.044 5.600 2.200 0.800 36% 57%

Scheme completed. Funds are for the operation &

maintenance of scheme.

43 1646 Rural water Supply Scheme Mohlanwal LahoreOn-going

Schemes53.594 42.378 2.734 2.051 1.367 67% 82%

Scheme completed. Funds are for the operation &

maintenance of scheme.

44 1647 Rural water Supply Scheme Sundar LahoreOn-going

Schemes24.475 22.331 0.715 0.536 0.358 67% 93%

Scheme completed. Funds are for the operation &

maintenance of scheme.

45 1648 Rural water Supply Scheme Village Bath LahoreOn-going

Schemes39.469 29.475 3.331 2.498 1.666 67% 79%

Scheme completed. Funds are for the operation &

maintenance of scheme.

46 1649 Rural water Supply Scheme Village Chah Tamoli LahoreOn-going

Schemes16.930 12.038 1.308 0.981 0.654 67% 75%

Scheme completed. Funds are for the operation &

maintenance of scheme.

47 1650

Establishment/ Construction of water Supply

Scheme at UC 30, 31, 32 wanadala dial singh and

dhaka nizampura tehsil feroz wala District

Sheikhupura

SheikhupuraOn-going

Schemes152.044 85.000 8.332 6.249 4.166 67% 59% Work in Progress

48 1651 Water Supply Scheme Pind burj Attari SheikhupuraOn-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress

49 1652Rural water Supply and Drainage Scheme Javed

Nagar, District SheikhupuraSheikhupura

On-going

Schemes198.903 72.367 6.667 5.000 3.334 67% 38% Work in Progress

50 1653Rural water Supply Drainage Scheme Iqbal Town

District SheikhupuraSheikhupura

On-going

Schemes140.161 83.696 3.333 2.500 1.667 67% 61% Work in Progress

51 1654Rural water Supply Drainage Scheme UC Kot

Ranjeet Singh SheikhupuraSheikhupura

On-going

Schemes95.061 54.999 3.333 2.500 1.667 67% 60% Work in Progress

52 1655Rural Warter Supply and Drainage P.C.C Scheme

Tibbi Kamboh, Mochi Pura, Kasur City.Kasur

On-going

Schemes199.551 29.782 6.667 5.000 3.334 67% 17% Work in Progress

53 1656Rural Water Drainage PCC Scheme Bhoojke,

Naike & Adjoining Abadies District Kasur.Kasur

On-going

Schemes114.522 97.085 5.812 1.509 0.056 4% 85% Work in Progress

54 1657

Rural water Supply & Drainage PCC Scheme at

Marali Hithar and Adjoining Abadies District Kasur

(Revised)

KasurOn-going

Schemes97.453 52.295 5.072 1.324 0.056 4% 54% Work in Progress

55 1658

Rural water Supply & Drainage Scheme Chak

No.14 & Ghandhi Otar Tehsil Pattoki District

Kasur.

KasurOn-going

Schemes105.412 84.160 20.000 15.000 10.000 67% 89% Work in Progress

56 1659

water Supply & Drainage Scheme They Kalay,

Basti Balochi, Jhalar Qadir, Jhalar Rehmani, Jhalar

Choudhry & Jhalar Baglian Wali i/c Tubewell of

Rao Tamkeen District Kasur.

KasurOn-going

Schemes119.701 83.750 3.333 4.600 3.767 82% 73% Work in Progress

57 1660

Water Supply and Drainage Scheme Gondy

Warha, Lambey Jagir, Dhaban, Sherpur, Lambey

Mahtam & Fatey Wala.

KasurOn-going

Schemes82.108 78.345 1.254 0.314 0.000 0% 95% Work in Progress

58 1661

water Supply & Drainage Scheme Chak

No.31,32,33 Phullani, Dhoop Sarri & Saharankey

District Kasur

KasurOn-going

Schemes199.992 84.797 5.000 3.750 2.500 67% 44% Work in Progress

Page 5: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

59 1662

Rural water Supply and Drainage PCC Scheme at

Mandi Usmanwala and Adjoining Abadies District

Kasur.

KasurOn-going

Schemes158.978 138.348 6.877 8.279 6.560 79% 91% Work in Progress

60 1663

Rural water Supply and Drainage PCC Scheme

Hardo Ban Bodla and Adjoining Abadies District

Kasur.

KasurOn-going

Schemes99.851 71.924 3.333 2.500 1.667 67% 74% Work in Progress

61 1664

Rural water Supply and Drainage PCC Scheme

Maan Bhamni Wala and Adjoining Abadies District

Kasur.

KasurOn-going

Schemes178.985 170.646 2.778 0.695 0.000 0% 95% Work in Progress

62 1665Rural water Supply and Drainage PCC Scheme

Rajuwal and adjoining Abadies District Kasur.Kasur

On-going

Schemes113.943 111.586 0.786 0.197 0.000 0% 98% Work in Progress

63 1666Rural Water Supply & Drainage Scheme, Qila

Dewan Singh Depaplur, Okara.Okara

On-going

Schemes22.250 5.481 7.252 5.439 3.625 67% 41%

Date of A.A 22-04-2017 Date of T.S 29.09.2016

Date of invitation of tenders 25-05-2017 Date of

Receipt of tenders 26-05-2017 Date of work order

02-06-2017 Date of completion as per PC-I

Anticipated date of completion 30-06-2018 No. of

Beneficiary 11550 Person, Work is in progress.

64 1667 water Supply Scheme Chak No.120/9.L Kameer. SahiwalOn-going

Schemes105.498 91.699 4.599 3.449 3.100 90% 90%

Date of AA 23.11.2016, Date of TS 07.12.2016,

Date of receipt of tender 07.01.2017, Date of Work

Order 08.02.2017, Date of completion as per PC-1

31.01.2018, Anticipated date of completion

30.06.2019 subject to availablity of balance funds,

Work in progress.

65 1668 R/W/S/Scheme Gareywala, Nawabpur,Basti Nau MultanOn-going

Schemes70.476 52.661 2.333 1.750 1.167 67% 76%

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010

3. Date of Pre-Qualification: - 4.Date of invitation of

tender 04.03.2010 5.Date of Receipt of tenders

06.03.2010 6.Date of work order 14.04.2010 7.Date

of Completion as per PC-l 13.02.2013 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018. 24.01.2019 10. No. of

beneficiaries 51946 Persons. Work is in Progress.

66 1669R/W/S/Scheme Raja Pur, Siddiquebad,

Hirwat,Yere WalaMultan

On-going

Schemes77.962 64.018 0.667 0.500 0.334 67% 83%

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010

3. Date of Pre-Qualification: - 4.Date of invitation of

tender 06.02.2010 5.Date of Receipt of tenders

08.02.2010 6.Date of work order 14.04.2010 7.Date

of Completion as per PC-l 13.02.2013 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018. 24.01.2019 10. No. of

beneficiaries 43334 Persons. Work is in Progress.

67 1670 R/W/S/Scheme Taraggar. MultanOn-going

Schemes61.140 51.141 3.333 2.500 1.667 67% 86%

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010

3. Date of Pre-Qualification: - 4.Date of invitation of

tender 06.02.2010 5.Date of Receipt of tenders

08.02.2010 6.Date of work order 18.06.2010 7.Date

of Completion as per PC-l 17.06.2012 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018. 24.01.2019 10.No. of

beneficiaries 20623 Persons. Work is in Progress.

68 1671Rural Water Supply & Sewerage Scheme Nai

Wala Multan

On-going

Schemes45.238 41.886 1.000 0.750 0.500 67% 94%

1. Date of A.A: 17.09.2015 (28.05.2016) 2. Date of

T.S: 08.06.2016 3. Date of Pre-Qualification:

11.06.2016 4. Date of Invitation of Tender:

18.07.2016 5. Date of receipt of Tender: 20.07.2016

6. Date of Award: 22.07.2016 7. Date of Completion

as per PC-I: 16.09.2016 8. Anticipated date of

completion 30.06.2018 9. Date of released of funds

23.11.2018. 24.01.2019 10. No. of Benificiary=6508

Persons. Work is in progress.

69 1672Sewerage Drainage Scheme Qasba Jalalpur Khaki

ShujabadMultan

On-going

Schemes46.177 43.912 1.000 2.015 1.490 74% 98%

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date

of Pre-Qualification: 30.09.2016 4. Date Invitation of

Tender: 01.11.2016 5. Date of Receipt of Tender:

02.11.2016 6. Date of Award: 12.11.2016 7. Date of

Completion as per PC-I: 11.05.2018 8. Anticipated

date of completion 30.06.2018 9. Date of released

of funds 23.11.2018 10.No. of Benificiary= Persons.

Work is in progress.

Page 6: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

70 1673 water Supply / Sewerage Mouza Rawani. LodhranOn-going

Schemes29.450 24.182 1.721 1.291 0.950 74% 85%

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-

2016 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 14-11-2016 5. Date of Receipt

of Tender: 15-11-2016 6. Date of Award: 03-12-

2016 7. Date of Completion as per PC-I: 31-12-2017

8. Anticipated Date of Completion: 02-12-2017

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

8834 Persons. Work is in Progress.

71 1674

Rural water Supply Scheme Chak No.12/M &

14/M (East & West) Tehsil Dunyapur, District

Lodhran

LodhranOn-going

Schemes29.922 21.446 2.784 2.088 1.600 77% 77%

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-

2016 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 14-11-2016 5. Date of Receipt

of Tender: 15-11-2016 6. Date of Award: 08-12-

2016 7. Date of Completion as per PC-I: 31-12-2017

8. Anticipated Date of Completion: 07-12-2017

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

6980 Persons. Work is in Progress.

72 1675Rural Water Supply Scheme Quatabpur Dunyapur,

Tehsil Dunyapur, District Lohdran Lodhran

On-going

Schemes29.850 9.623 6.742 1.686 0.000 0% 32%

1. Date of A.A. 22-08-2015. 2. Date of T.S. 27-08-

2015 Rev. T.S 07-02-2017 3. Date of Pre-

Qualification: 4. Date of invitation of tender 01-12-

2015 5. Date of Receipt of tenders 02-12-2015 6.

Date of work order 16-12-2015. 7. Date of

Completion as per PC-l 21-08-2016 8. Anticipated

date of completion 30-06-2017 9.Date of released of

funds 03-08-2018 24.01.2019 10. Reason of Slow

Moving: 11.No. of beneficiaries 13535 Persons.

Scheme completed & under test operation. Rs.1.686

million proposed for re-appropriation

73 1676Provision of water Supply Schemes in Chak No.

135/10.R, District Khanewal.Khanewal

On-going

Schemes60.664 47.747 4.306 3.230 3.230 100% 84%

1. Date of A.A (Amended) 04.04.2016 2. Date of

T.S: 12.04.2016 3. Date of Pre-Qualification:

02.04.2016 4. Date of Invitation of Tender:

21.04.2016 5. Date of Receipt of Tender:

23.04.2016 6. Date of Work order: 30.04.2016 7.

Date of Completion as per PC-I: 16.09.2017 8.

Anticipated Date of completion: 31.12.2018 9. Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ------ 11No. of beneficiaries

15048 Persons Work is in progress.

74 1677Provision of Water Supply Schemes in Chak No.

136/10.R, District Khanewal.Khanewal

On-going

Schemes62.211 49.998 1.000 0.750 0.750 100% 82%

1. Date of A.A (Amended) 17.09.2015 2. Date of

T.S: 07.03.2016 3. Date of Pre-Qualification:

02.04.2016 4. Date of Invitation of Tender:

21.04.2016 5. Date of Receipt of Tender:

23.04.2016 6. Date of Work order: 30.04.2016 7.

Date of Completion as per PC-I: 29.10.2016 8.

Anticipated Date of completion: 31.12.2018 9. Date

of released of funds 23.11.2018 24.01.2019 10.

Reason of Slow Moving: _____ 11No. of

beneficiaries 12907 Persons Work is in progress.

75 1678Rural Sewerage / Drianage scheme chak No.

146/EB and Dalan, District VehariVehari

On-going

Schemes18.710 8.742 3.319 4.149 1.820 44% 56%

1. Date of A.A: 04.04.2017. 2. Date of T.S:

10.04.2017 3. Date of Pre-Qualification: 4. Date of

Invitation of Tender: 08.05.2017 5. Date of Receipt

of Tender: 09.05.2017 6. Date of Work order:

25.11.2017 7. Date of Completion as per PC-I:

24.11.2018 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ----- 11. No.

of Beneficiary= 20316 Persons Work is in progress.

76 1679Provision of water Supply Scheme in Kundi Wala

UC shadan Lund

Dera Ghazi

Khan

On-going

Schemes50.325 38.936 3.789 2.842 2.132 75% 82% "• Date of A.A = 22.08.2015

77 1680Provision of water Supply Scheme in Notak

Sakhani UC Kala

Dera Ghazi

Khan

On-going

Schemes47.463 29.182 5.834 4.376 3.107 71% 68% "• Date of A.A = 22.08.2015

78 1681Provision of water Supply Scheme in Sabzani UC

Kala

Dera Ghazi

Khan

On-going

Schemes36.579 28.136 2.556 1.917 1.438 75% 81% "• Date of A.A = 22.08.2015

79 1682Extension & Augmentation of water Supply

Scheme Sakhi Sarwar

Dera Ghazi

Khan

On-going

Schemes87.805 77.753 0.333 0.250 0.167 67% 89% "• Date of A.A = 16.12.2014

80 1683Provision of Rural water Supply Scheme Nutkani,

District D.G. Khan

Dera Ghazi

Khan

On-going

Schemes82.680 59.914 7.577 5.683 4.149 73% 77% "• Date of A.A = 23.09.2016

81 1684 water Supply Scheme at Councilor Muhammad Ali

Basti Rojhani Sakhi Sarwar

Dera Ghazi

Khan

On-going

Schemes25.000 24.000 0.333 0.250 0.188 75% 97% "• Date of A.A = 23.09.2016

Page 7: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

82 1685

Reheblitiation/Extension of Water Supply Scheme

Tunga Menhal Phase-II (Basti Ouroo, Basti Jora,

Basti Rind, Basti Bun Dhola, Basti Gabolan, Basti

Manka & Basti Mahool jee)

Dera Ghazi

Khan

On-going

Schemes20.000 4.844 5.051 3.788 2.841 75% 38% "• Date of A.A = 25.7.2017

83 1686Rehabilitation of Water Supply in Pir Qatal PP-244

District Dg Khan

Dera Ghazi

Khan

On-going

Schemes10.000 4.998 1.667 1.250 0.913 73% 59% "• Date of A.A = 25.7.2017

84 1687Rehabilitation of Water Supply in Shehzada Sultan

Town PP-244 District Dg Khan

Dera Ghazi

Khan

On-going

Schemes10.000 4.000 2.000 1.500 1.125 75% 51% "• Date of A.A = 25.7.2017

85 1688Rehabilitation of Water Supply in Mehboob Abad

PP-244 District Dg Khan

Dera Ghazi

Khan

On-going

Schemes10.000 4.999 1.667 1.250 0.888 71% 59% "• Date of A.A = 25.7.2017

86 1689 Improvement of Rural water Supply Scheme Dajal RajanpurOn-going

Schemes228.679 217.875 3.601 2.701 1.801 67% 96% "• Date of A.A = 23.12.2014

87 1690 water Supply Schemes in Mouza Fateh Pur and

Ali Pur District MuzaffargarhMuzaffargarh

On-going

Schemes70.000 18.680 4.173 3.130 2.087 67% 30% "• Date of A.A 22-09-2016

88 1691

Provision of Fund for Restortaion of water Supply

Scheme in his Constituency District Bahwalnagar

(i) RWSS Khattan,(ii) RWSS Jananay wala, (iii)

RWSS Ghulab Ali,(iv) RWSS Bajak & Khamay

Wala

BahawalnagarOn-going

Schemes67.817 49.499 5.339 2.248 1.900 85% 76%

Date of AA(DDWP) 06.10.2015. . Date of TS. 22-02-

2016. Date of invitation of tenders=28-01-2016.

Date of receipt of tenders = 02-03-2016. Date of

award= 30-04-2016. Date of completion 29-04-2018.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Completed & handed over. Excess

funds Rs.1.756 million surrendered dated

19.10.2018.

89 1692

Rehabilitation of Rural water Supply Scheme

Chak No 62 4R Tehsil Haroonabad District

Bahawalnagar

BahawalnagarOn-going

Schemes38.959 36.550 0.320 0.240 0.205 85% 94%

Date of A.A: 22-01-2015. . Date of T.S 26-01-2015.

Date of revised T.S 12-01-2017. Date of receipt of

tenders =15-04-2015 . Date of work order= 22-05-

2015. Date of completion as per agreement= 21-11-

2015.Anticipated date of completion= 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Completed

90 1693Rehabilitation of rural water Supply scheme chak

no. 69/4-R, 80/1-L & Azafi Abadis Chak No. 85/5-RBahawalnagar

On-going

Schemes39.568 38.934 0.211 0.054 0.054 100% 99%

Date of AA. 08.08.2016. Date of T.S. 21.10.2016.

Tender received on 02.11.2016. Date of award.

25.11.2016. Date of completion 24.11.2017.

Anticipated date of completion 31-12-2018. Date of

receipt of funds by F.D. 20.07.2018 &

11.01.2019.Scheme completed. Excess funds

Rs.0.104 million surrendered dated 19.10.2018.

91 1694

Rehabilitation of Rural water Supply Schemes

Muga Chandna Mirdin Hakim Mirdin Mohib Ali

Khazan Singh

BahawalnagarOn-going

Schemes99.971 53.035 6.667 5.000 4.000 80% 57%

Date of AA. 19.08.2016. Date of T.S. 25.10.2016.

.Date of receipt of tenders= 14-12-2016 . Date of

award=29-12-2016. Date of completion=28-11-

2017. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

92 1695Rural water Supply Scheme Jand wala and Jand

wala saniBahawalnagar

On-going

Schemes25.000 19.550 1.817 0.459 0.415 90% 80%

Date of AA(DDWP). 18-08-2015 . Date of TS. 06-10-

2015. Date of receipt of tenders = 20-10-2015 . Date

of work order= 04.11.2015. . Date of completion as

per agreement= 03.11.16. .Anticipated date of

completion 30-06-2019. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Scheme Completed

in saving & handed over. Excess funds Rs.0.904

million surrendered dated 19.10.2018.

93 1696 water Supply Scheme Doonga Boonga BahawalnagarOn-going

Schemes174.252 120.139 6.667 5.000 4.300 86% 71%

Date of AA (DDSC). 15-10-2015. Date of TS. 22-02-

201`6. Date of prequalification on 22-03-2016. Date

of receipt of tenders = 07-04-2016. Date of work

awarded 18.05.2016. Date of completion as per

Agreement: 18.11.2017 .Anticipated date of

completion 30-06-2019.Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Work is in progress.

94 1697

Rural water Supply Schemes Mouza Janu Khan

Basti Kapooran and kot Ganga Singh District

Bahawalnagar

BahawalnagarOn-going

Schemes97.808 43.343 6.667 5.000 4.300 86% 49%

Date of AA. 19.08.2016. Date of T.S. 25.10.2016.

.Date of receipt of tender=14-12-2016. Date of

award +19-01-2017. Date of completion+18-12-

2017. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

95 1698 water Supply Scheme Noor Sar (New & Old) BahawalnagarOn-going

Schemes72.817 42.617 3.333 2.500 2.050 82% 61%

Date of AA(DDWP). 06.10.2015. . Date of TS. 22-

02-2016. Date of receipt of tenders = 02-03-2016.

Date of work order=01-04-2016. Date of completion

as per agreement= 30-10-2017.Anticipated date of

completion 30-06-2019. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Page 8: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

96 1699Rural water Supply scheme chak no. 128/6-R

including all adjoining abadies.Bahawalnagar

On-going

Schemes22.200 20.273 0.536 0.134 0.122 91% 92%

Date of AA. 08.08.2016. Date of T.S. 21.10.2016.

Tender received on 02.11.2016. Date of award.

28.11.2016. Date of completion 27.11.2017.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Scheme completed in saving & handed over to

CBO for O & M . Excess funds Rs.0.268 million

surrendered dated 19.10.2018.

97 1700Rural water Supply Scheme, Kalowal Thathi Bala

Raja Tehsil Lalian District ChiniotChiniot

On-going

Schemes13.322 6.430 2.297 1.723 0.800 46% 54%

1. Date of AA = 15.12.2016 2. Date of TS =

23.12.2016 3.Date of Award of work . 19.05.2017

4.Dated of Released Funds 4. No. of Beneficiaries =

5375 Persons Funds Released upto 24.01.2019 by

the Chief Engineer (South) PHED Lahore and work

is in progress. Target progress will be achieved in

coming month.

98 1701

Rehabilitation and Repair of Sewerage Scheme

of Housing Scheme , Gujar Khan City, Tehsil Gujar

Khan, District Rawalpindi

RawalpindiOn-going

Schemes29.980 15.158 3.333 3.500 2.667 76% 59% Work in progress.

99 1702

Drainage / Sewerage System in Village

Ghourgushti (Phase II), Tehsil Hazro, District

attock

AttockOn-going

Schemes88.786 85.975 0.937 0.703 0.469 67% 97%

A.A Date 03.09.2014.T.S Date 29.09.2014. Date of

Start of Scheme 16.12.2014.Date of Completion of

Scheme 30.06.2019.Work is in progress.

100 1703Drainage and Sanitation scheme in village

Hameed, Tehsil Hazro, District attockAttock

On-going

Schemes44.134 26.243 5.960 1.490 0.000 0% 59%

A.A Date 01.10.2013. T.S Date 27.01.2014. Date of

Start of Scheme 06.03.2014.Date of Completion of

Scheme 30.06.2019. Dispute of land.

101 1704

Construction of Street Pavement in Village Kalu

Kalan (Phase II), (PP 16) Tehsil Hazro District

attock

AttockOn-going

Schemes26.227 24.730 1.497 2.023 0.749 37% 97%

A.A Date 23.01.2015. T.S Date 18.04.2015.Date of

Start of Scheme 05.06.2015.Date of Completion of

Scheme 30.06.2019.Work is in progress.

102 1705Extension of Rural Drainage Scheme in Villages

Haroon, Saleem Khan & AdalzaiAttock

On-going

Schemes60.055 46.834 4.405 3.304 2.203 67% 82%

A.A Date 05.08.2016.T.S Date 15.08.2016. Date of

Start of Scheme 28.11.2016. Date of Completion of

Scheme 30.06.2019.Work is in progress.

103 1706Rural Drainage Scheme in Villages Chachi,

Saiden, YasinAttock

On-going

Schemes29.955 20.816 3.046 2.285 1.523 67% 75%

A.A Date 12.04.2017. T.S Date 18.04.2017. Date of

Start of Scheme 10.06.2017.Date of Completion of

Scheme 30.06.2019.Work is in progress.

104 1707Rural drainage Scheme in Village Mirza Phase2

Tehsil and District attock.Attock

On-going

Schemes104.909 28.955 6.667 5.000 3.334 67% 31%

A.A Date 05.08.2016.T.S Date 09.09.2016.Date of

Start of Scheme 16.03.2017. Date of Completion of

Scheme 30.06.2019.Work is in progress.

105 1708Rural drainage scheme in villages Formli,haider

Mallah,District attock.Attock

On-going

Schemes55.840 42.497 4.448 3.336 2.224 67% 80%

A.A Date 01.04.2016. T.S Date 22.04.2016. Date of

Start of Scheme 30.05.2016.Date of Completion of

Scheme 30.06.2019.Work is in progress.

106 1709Rural drainage scheme in villages Perzai, Muraria,

Pandak, District attockAttock

On-going

Schemes29.604 26.725 0.602 0.882 0.731 83% 93%

A.A Date 01.04.2016. T.S Date 09.09.2016.Date of

Start of Scheme 24.11.2016. Date of Completion of

Scheme 30.06.2019.Work is in progress.

107 1710Rural drainage scheme in villages Ramu,Bhadar

Khan,District attockAttock

On-going

Schemes29.208 28.717 0.491 0.368 0.246 67% 99%

A.A Date 01.04.2016. T.S Date 20.04.2016.Date of

Start of Scheme 31.05.2016.Date of Completion of

Scheme 30.06.2019.Work is in progress.

108 1711Rural drainage scheme in villages, Nartopa,

Khagwani, District attockAttock

On-going

Schemes55.106 26.472 3.333 3.670 2.837 77% 53%

A.A Date 05.08.2016. T.S Date 15.08.2016.Date of

Start of Scheme 24.11.2016.Date of Completion of

Scheme 30.06.2019.Work is in progress.

109 1712Const. of Sewerage & Drainage Scheme Kallar

KaharChakwal

On-going

Schemes98.759 47.426 3.333 4.325 3.492 81% 52%

Date of A.A 17.09.2015. Date of T.S 08.10.2015.

ateof Start 18.03.2016.Date of completion

31.12.2019.Woork is in progress. Funds to the tune

of Rs.1.825 Million re-appropriated from other

schemes to meetup the progress of work.

110 1713 Rural Drainage Scheme Mangwal District Chakwal ChakwalOn-going

Schemes11.000 9.773 0.392 0.098 0.000 0% 89%

Date of A.A 20.04.2017. Date of T.S

22.04.2017.Date of Start 12.06.2017.Date of

scheme.completed.Excessive funds surrendered

through reappropriation.

111 1714Rural Drainage Scheme UC Udherwal District

ChakwalChakwal

On-going

Schemes14.000 12.424 0.482 0.121 0.000 0% 89%

Date of A.A 20.04.2017 .Date of T.S

22.04.2017.Date of Start 10.06.2017.Date of

scheme completed. Excessive funds surrendered

through re-appropriation.

112 1715Rural Drainage Scheme UC Nara Mogla District

ChakwalChakwal

On-going

Schemes11.000 9.563 0.476 0.119 0.000 0% 87%

Date of A.A 20.04.2017. Date of T.S

22.04.2017.Date of Start 08.06.2017.Scheme

completed. Excessive funds surrendered through re-

appropriation.

113 1716 Sewerage Scheme Lawa, District Chakwal ChakwalOn-going

Schemes78.169 49.975 3.333 2.500 1.667 67% 66%

Date of A.A 24.08.2016. Date of T.S 01.11.2016.

Date of Start 23.12.2016. Date of completion

31.12.2019.Full funds utilized. Scheme is short

funded.

Page 9: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

114 1717 Rural Drainage Scheme Khanpur ChakwalOn-going

Schemes150.000 52.462 5.000 5.750 4.495 78% 38%

"Date of A.A 24.08.2016 . Date of T.S

01.11.2016.Date of Start 16.01.2017.Date of

completion 30.06.2020

115 1718Improvement/Rehabilitation of Sewerage System in

Bilal Town Tehsil & District JhelumJhelum

On-going

Schemes29.800 27.764 0.676 0.169 0.000 0% 93%

Date of A.A 16-03-16.Date of T.S 28-03-

2016.Revised T.S 18-10-2017.Date of

Commencement 07-05-2016.Scheme Completed in

saving funds are reappropriated to other scheme.

116 1719Rural drainage scheme Pinanwal, Tehsil Pind

Dadan Khan.Jhelum

On-going

Schemes100.000 19.985 3.333 2.500 1.667 67% 22%

Date of A.A 26-08-2016.Date of T.S 15-12-2016.•

Work awarded on 02-03-2017. • Work in progress.

117 1720Sewerage scheme Mouza Ahmaday Wala District

Sargodha Sargodha

On-going

Schemes23.426 19.959 1.149 0.575 0.575 100% 88%

Date of A.A 27.08.2016, Date of T.S 03.09.2016,

Date of Award 06.12.2016, Scheduled date of

Completion on 05.12.2017, Date of

Commencement, 06.12.2016, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.Sullage

Carrier 3250-Rft & Drain 9841-Rft constructed. PCC

Slab 18393-Cft & Soling 19458-Cft laid. Work in

progress.

118 1721Sewerage/Sullage Carrier for Jalpana/Chak

Muzafarabad/Masar/Sardarpur etc.Sargodha

On-going

Schemes30.000 20.807 2.795 2.096 1.548 74% 75%

"Date of A.A 27.08.2016, Date of T.S 03.09.2016,

Date of Award 08.12.2016, Scheduled date of

Completion on 07.12.2017, Date of

Commencement, 08.12.2016, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

119 1722RSD Scheme Chak No 4 SP Chak No 5 NB Chak

No 7 ML Chak No 65 SB Hujjan District Sargodha Sargodha

On-going

Schemes105.642 44.397 3.333 2.500 2.500 100% 44%

"Date of A.A 27.08.2016, Date of T.S 28.10.2016,

Date of Award 14.02.2017, Scheduled date of

Completion on 13.02.2018, Date of

Commencement, 14.02.2017, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

120 1723Rural Sewerage / Drainage PCC Scheme for

Jhawarian Sargodha

On-going

Schemes100.000 34.967 3.333 2.500 2.500 100% 37%

Date of A.A 27.08.2016, Date of T.S 07.11.2016,

Date of Award 10.02.2017, Scheduled date of

Completion on 09.02.2018, Date of

Commencement, 10.02.2017, Funds released on

30.07.2018, Funds on-lined on 30.07.2018. 6661-

Rft, Nallah, Drain, 2866-Rft 01- No. collecting tank

constructed. PCC slab 27375-Cft laid and Work in

progress.

121 1724 Rural Sewerage / Drainage Scheme Bhagtanwala SargodhaOn-going

Schemes84.030 28.600 3.333 2.500 1.934 77% 36%

"Date of A.A 27.08.2016, Date of T.S 28.10.2016,

Date of Award 31.01.2017, Scheduled date of

Completion on 30.01.2018, Date of

Commencement, 31.01.2017, Funds released on

04.08.2017, Funds on-lined on 04.08.2017.

122 1725

Construction / Rehablitation of streets, Drains ,

Nullah and Soling 2 Shummali, Village Lak Ditrict

Sargodha

SargodhaOn-going

Schemes6.000 0.100 1.000 0.750 0.000 0% 2%

"The nomenclature of scheme is wrongly printed in

ADP as the correct nomenclature is “Construction /

Rehabilitation of Street Drains, Nallah and Soling 20

Shumali, 61 Shumali, Village Lak District

Sargodha.""

123 1726Provision of Sewerage System and PCC Slabs in

Village Roda.Khushab

On-going

Schemes92.683 14.299 3.333 2.500 2.370 95% 18%

Date of AA 18.08.2017 Date of TS 11.09.2017 Date

of award 22.01.2018 Date of completion 30.06.2020

Work is in progress.

124 1727Construction of Rural water Supply Scheme

Marmandi Tehsil & District MianwaliMianwali

On-going

Schemes13.500 12.707 0.256 0.192 0.128 67% 95%

Date of A.A.27-05-2016, Date of T.S.19-05-2017,

Date of Start of Work. 10-05-2017, Remarks.

E.R.S=3/3, Tube Well=1/1, Pump House=1/1,

P/Machinery= Arranged/1, R/FMain= 6"i/d G.I

Pipe=1150/1200, 4"i/d G.I Pipe= 2250/2250, 3"i/d

G.I Pipe=3012/3020, 2"i/d G.I Pipe=1400/1400,

6"i/d PVC Pipe=1960/1900, 3"i/d PVC= 9633/9805,

G.S. Tank 20000-Glns=1/1, T/Line= Demand Notice

paid to Wapda Connection awaited/1. Work is in

progress.

125 1728 Sewerage & Sanitation Scheme Daud Khel MianwaliOn-going

Schemes98.377 19.928 6.667 5.000 3.334 67% 24%

Date of A.A.27-08-2016, Date of T.S.09-12-2016,

Date of Start of Work.03-02-2017, Remarks RCC

Sewer=9"i/d=1240-Arrange/20356, 12"i/d=1130-Rft

Laid & 992-arranged /12812, 15"i/d=728-Rft Laid &

630-Arranged /6645, 18"i/d=1850-Rft Laid/3348,

21"i/d=832-Arranged/1768, 24"i/d=1573/4870,

27"i/d=3841/5505, 33"i/d=2294/3128,

S/Carrier=0/200, PCC Slab=0/33597. Work is in

progress.

126 1729 Sewerage & Sanitation Scheme Shahbaz Khel MianwaliOn-going

Schemes95.743 29.964 6.667 5.000 3.334 67% 35%

Date of A.A.27-08-2016, Date of T.S.06-10-2016,

Date of Start of Work.22-12-2016, Remarks RCC

Sewer=9" i/d=15294/33286, 12"i/d= 14502/21045,

15"i/d= 3381/3659, 21"i/d= 766/864,

24"i/d=2253/2445, PCC Slab= 0/62379. Work is in

progress.

Page 10: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

127 1730Sewerage / Drainage Scheme Mouch, District

Mianwali Mianwali

On-going

Schemes100.000 46.431 7.856 5.892 3.928 67% 50%

Date of A.A.04-08-2015, Date of T.S.14-09-2015,

Date of Start of Work 16-11-2015, Remarks RCC

Sewer=9" i/d= 23007/35130, 12"i/d= 18238/12053,

15"i/d= 3239/4564, 18"i/d=5720/4902, 21"i/d= 1608

/1126. Sullage Carrier= 230/2411. Work is in

progress.

128 1731 Sewerage / Drainage Scheme UC Rokhari MianwaliOn-going

Schemes50.000 22.466 4.476 3.357 2.237 67% 49%

Date of A.A.27-08-2016, Date of T.S.03-09-2016,

Date of Start of Work 03-12-2016 Remarks RCC

Sewer=9" i/d=10551/13484, 12"i/d= 10290/7642,

15"i/d= 5982/6288, 18"i/d=1294/1299, Sullage

Carrier= 0/200. Work is in progress.

129 1732Rural Sewerage Scheme Harnoli Tehsil Piplan,

MianwaliMianwali

On-going

Schemes94.000 44.953 5.000 3.750 2.498 67% 50%

Date of A.A. 27-08-2016, Date of T.S.09-12-2016,

Date of Start of Work.27-01-2017, Remarks RCC

Sewer=9"i/d=3200-Rft Arranged/19157,12"i/d=8504-

Rft Arranged/8786,15"i/d=418-Rft Laid & 2374-Rft

Arranged/2826,18"i/d=655-Rft & 945-Rft

Arranged/1624, 21"i/d=1173-Laid & 183-Rft

Arranged/1356,24"i/d=900-Laid & 412-Rft

Arranged/1329, 30"i/d=380-Rft Laid/392, Screening

Chamber =1/1, Collecting Tank 20'dia =1/1,Control

Room= 1/1,Discharge Sump=0/1, P/Machinery=0/2,

S/Carrier=0/1250, S/Drain= 600/4175, PCC

Slab=111243/142412, Culvert=0/1, Electric

T/Line=0/1. Work is in progress.

130 1733PCC Slab and Sewerage Scheme in Street Noon

Dager UC Tehsil Kaloor Kot District Bhakkar Bhakkar

On-going

Schemes48.600 29.681 3.333 2.500 2.500 100% 66%

Date of A.A 27.08.2016 Date of T.S 03.09.2016

Date of Commencement 28.11.2016 Date of

completion 31.12.2019

131 1734

PCC Slab and Sewerage Scheme Shahyan Wala

U.C Noora Sharif Tehsil Kaloor Kot District

Bhakkar

BhakkarOn-going

Schemes30.000 14.397 3.333 2.500 1.667 67% 54%

Date of A.A 27.08.2016 Date of T.S 03.09.2016

Date of Commencement 09.11.2016 Date of

completion 31.12.2019

132 1735Provision of Sewerage/Drainage/Nali UC Mullah

WaliBhakkar

On-going

Schemes30.000 7.000 3.333 2.500 2.000 80% 30%

Date of A.A 10.08.2017 Date of T.S 21.10.2017

Date of Commencement 03.11.2017 Date of

completion 30.06.2020

133 1736Provision of Sewerage/Drainage/Nali UC

PeerashabBhakkar

On-going

Schemes30.000 10.000 6.667 5.000 4.334 87% 48%

Date of A.A 10.08.2017 Date of T.S 21.10.2017

Date of Commencement 03.11.2017 Date of

completion 30.06.2020

134 1737

Sewerage Drainage and PCC Slab and Drain in

Town Punjgrain Tehsil Darya Khan District

Bhakkar.

BhakkarOn-going

Schemes100.000 46.648 6.667 5.000 5.000 100% 52%

Date of A.A 27.08.2016 Date of T.S 21.10.2016

Date of Commencement 24.11.2016 Date of

completion 30.06.2020

135 1738Rural Sewerage Drainage Scheme PCC Slab and

Brick Pavement in Behal City Bhakkar

On-going

Schemes49.998 18.599 3.333 2.500 2.161 86% 42%

Date of A.A 27.08.2016 Date of T.S 03.09.2016

Date of Commencement 03.11.2016 Date of

completion 30.06.2020

136 1739Rural Sewerage Drainage Scheme PCC Slab and

Brick Pavement in Notak City Bhakkar

On-going

Schemes39.022 17.991 3.333 2.500 2.167 87% 52%

Date of A.A 27.08.2016 Date of T.S 03.09.2016

Date of Commencement 28.11.2016 Date of

completion 30.06.2020

137 1740

Rural drainage Scheme inculding Tuff Tiles and

Water Supply Lines for left over streets for Chak

No 411/GB darbar Peer Kandhari tehsil

Tandlianwala District Faisalabad

FaisalabadOn-going

Schemes10.000 5.000 1.667 1.250 0.520 42% 55%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 23.08.2018 & 24.1.19.

138 1741

Construction of Drainage Nala at Chak No.

197/RB Wahga Wala Tehsil Saddar, District

Faisalabad

FaisalabadOn-going

Schemes3.000 2.000 0.333 0.250 0.167 67% 72%

Date of A.A 05-08-2017. Date of T.S.05-09-2017.

Work order issued on 28-09-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

139 1742Construction of Rural Drainage and PCC Road ,

UC 63 District Faisalabad Faisalabad

On-going

Schemes10.000 1.000 3.000 2.250 1.500 67% 25%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 22-11-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

140 1743Construction of Rural Drainage and PCC Road at

U.C. 52 District Faisalabad Faisalabad

On-going

Schemes10.000 1.000 3.000 2.250 1.500 67% 25%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 22-11-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

141 1744

Rehab: of Rural Water Supply Scheme Chak No.

228/GB Tehsil Sammundari Distt: Faisalabad

(Court Case)

FaisalabadOn-going

Schemes21.240 18.698 2.542 1.907 0.720 38% 91%

AA issued on 14.04.2015. Date of T.S 18.10.2016

Work order issued on 18.05.2015. Work is in

progress. Funds relased 23.11.2018 & 24.1.19.

142 1745Construction of sewerage drain at Chak

No.469/GB, Samundri, District FaisalabadFaisalabad

On-going

Schemes59.879 42.328 1.000 0.750 0.470 63% 71%

AA issued on 16.03.2017 Date of T.S 31.03.2017

work order issued on 08.06.2017. Work is in

progress. Funds released on 23.11.2018 & 24.1.19

143 1746

Construction of TST Road (2200 feet) at Chak No.

353/GB Kot Kabir, (Cahk No. 353/GB to New

Abadi) at District Faisalabad

FaisalabadOn-going

Schemes4.000 1.000 1.000 0.750 0.750 100% 44% Funds transfer to xen Highway Divison Faisalabad.

Page 11: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

144 1747

Widening / improvement of at TST Road from 12

feet to 20 feet Chak No.353 to 354 at District,

Faisalabad

FaisalabadOn-going

Schemes10.000 4.500 1.000 0.750 0.750 100% 53% Funds transfer to xen Highway Divison Faisalabad.

145 1748Provision of Soling/Drainage at Kannal Awan and

Abadies District Faisalabad.Faisalabad

On-going

Schemes2.500 0.479 1.000 0.750 0.500 67% 39%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017 Work is in

progress.

146 1749Provision of Soling/Drainage at UC No. 50 Chak

No.144/GB District FaisalabadFaisalabad

On-going

Schemes2.000 1.000 1.000 0.750 0.500 67% 75%

AA issued on 15.11.2017.Funds received on 23-11-

2018. Work order issued on 13.12.2017.

147 1750Provision of Soling /Drainage at Bhaman Da Chak

and Pathan Da Goth District Faisalabad.Faisalabad

On-going

Schemes2.000 1.000 1.000 0.750 0.500 67% 75%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

Progress.

148 1751Provision of Soling/Drainage Chak No.651/2 GB

District FaisalabadFaisalabad

On-going

Schemes1.000 0.499 0.501 0.376 0.250 66% 75%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

Progress.Funds released on 23.11.2018 & 24.1.19

149 1752

Provision of Soling /Drainage at Chak No.653/4 GB

Abadies Karam Chand and abadi Plots District

Faisalabad.

FaisalabadOn-going

Schemes2.500 0.998 1.502 1.127 0.750 67% 70%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

Progress.Funds released on 23.11.2018 & 24.1.19

150 1753Provision of Soling/Drainage Chak No.652/3GB

District FaisalabadFaisalabad

On-going

Schemes1.000 0.500 0.500 0.375 0.250 67% 75%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

Progress.Funds released on 23.11.2018 & 24.1.19

151 1754Construction of TST Road Jhangar Awan and

Abaedies District, Faisalabad.Faisalabad

On-going

Schemes5.000 1.500 1.000 0.750 0.750 100% 45% Funds transfer to xen Highway Divison Faisalabad.

152 1755Provision of Soling/Drainage Chak No.147/GB

District FaisalabadFaisalabad

On-going

Schemes1.000 0.471 0.529 0.397 0.260 65% 73%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Funds

could not be utilized due to site Problems. Work is

in progress.Funds released on 23.11.2018 & 24.1.19

153 1756Provision of Soling /Drainage at Chak No.144/GB

District Faisalabad.Faisalabad

On-going

Schemes2.000 0.500 1.500 1.125 0.690 61% 60%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

Progress.Funds released on 23.11.2018 & 24.1.19

154 1757Provision of Soling /Drainage at Chak No.145/GB

District Faisalabad.Faisalabad

On-going

Schemes2.500 0.997 1.503 1.127 0.700 62% 68%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

Progress.Funds released on 23.11.2018 & 24.1.19

155 1758Provision of Soling/Drainage Chak No.459/GB

Bhooli de Jhok District FaisalabadFaisalabad

On-going

Schemes1.500 0.479 1.021 0.766 0.500 65% 65%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

progress.Funds released on 23.11.2018 & 24.1.19

156 1759Provision of Soling/Drainage at UC No. 51 Pind

Essa FaisalabadFaisalabad

On-going

Schemes2.500 0.486 1.000 0.750 0.480 64% 39%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

progress.Funds released on 23.11.2018 & 24.1.19

157 1760Provision of Soling /Drainage at Chak No.569/Gb

Abadi Abdullah Khan District faisalabad.Faisalabad

On-going

Schemes3.500 0.988 1.000 0.750 0.490 65% 42%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. work is in

progress.Funds released on 23.11.2018 & 24.1.19

158 1761Provision of Soling /Drainage at RosheShani

Awana and Abadies District Faisalabad. Faisalabad

On-going

Schemes1.000 0.389 0.611 0.458 0.300 66% 69%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

progress.Funds released on 23.11.2018 & 24.1.19

159 1762

Provision of Soling /Drainage at UC 45 Chak

No.644/GB Abadi KaluKa Thatha and Saidpur

District Faisalabad.

FaisalabadOn-going

Schemes2.000 0.475 1.525 1.144 0.650 57% 56%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. Work is in

progress.Funds released on 23.11.2018 & 24.1.19

160 1763Provision Main Drainage at Chak No.120/GB

District Faisalabad.Faisalabad

On-going

Schemes1.497 0.994 0.503 0.377 0.240 64% 82%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. work is in

progress.Funds released on 23.11.2018 & 24.1.19

161 1764Sewerage / Drainage Scheme Garh Mor,

Ahmedpur SialJhang

On-going

Schemes81.940 20.000 8.333 6.250 4.858 78% 30%

Date of A.A 16.03.2017 Date of T.S 24.03.2017

Date of Receipt of tender 20.04.2017 Date of work

order 07.07.2017. Date of Completion As per PC-

I06.07.2019 Anticipated date of completion

06.07.2019 Agreement Amount 74.993-Million Work

is in progress.

Page 12: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

162 1765Sewerage Drainage and Street Pavement,

Sandhilianwali, District Toba Tek Singh Phase IToba Tek Singh

On-going

Schemes100.000 30.000 3.333 1.800 1.100 61% 31%

1-Date of A.A 20.10.2016 2- Date of T.S 11.11.2016

3-Date of Prequalification - 21.11.2016 4-Date of

invitation of tenders 16.12.2016 5- Date of Receipt

of tenders 17.12.2016 6- Date of work order -

27.12.2016 7- Date of completion as per PC-I

26.12.2018 8- Anticipated date of completion

26.12.2018 9- No. of Beneficiary - 33312 Person 10-

Funds Released by F.D 03.08.2018 & 24.01.2019 -

11-Re-appropriation of funds(+/-) Work in progress.

163 1766

Construction of disposal Sewerage Drainage PCC

Scheme Morr Eminabad Sharqi UC Dhillanwali

Tehsil and Distt. Gujranwala

GujranwalaOn-going

Schemes199.920 117.216 6.667 5.000 3.334 67% 60% Work in progress

164 1767 Construction of Drains / PCC and Sewerage

Scheme at UC Bhikhu Pura, District GujranwalaGujranwala

On-going

Schemes67.393 17.393 6.667 5.000 3.334 67% 31% Work in progress

165 1768 Construction of Drains / PCC and Sewerage

Scheme at UC Shaheenabad, District GujranwalaGujranwala

On-going

Schemes64.261 19.260 5.000 3.750 2.500 67% 34% Work in progress

166 1769PCC and Sewerage Schemes at Khiali Shahpur

District Gujranwala. Gujranwala

On-going

Schemes198.537 153.991 20.000 21.218 16.218 76% 86% Work in progress

167 1770

PCC Sewerage Drainage Scheme Disposal UC

City Ladhywala Warraich Qila Dedar Singh Madu

Khalil Ghakh

GujranwalaOn-going

Schemes149.647 140.598 3.016 2.262 1.508 67% 95% Work in progress

168 1771Provision of Sewerage Drainage and water Supply

scheme in Qila Dedar Singh GujranwalaGujranwala

On-going

Schemes196.624 138.865 6.667 5.000 3.334 67% 72% Work in progress

169 1772

Provision of Sewerage, New Disposal & PCC at

Kot Qazi & Mudhokhalil, Tehsil Saddar,

Gujranwala

GujranwalaOn-going

Schemes186.266 89.505 30.000 22.500 15.000 67% 56% Work in progress

170 1773

Provision of Sewerage, New Disposal & PCC at

Ladhay wala Warraich & Mughal Chak, Tehsil

Saddar, Gujranwala

GujranwalaOn-going

Schemes195.240 100.000 30.000 22.500 15.000 67% 59% Work in progress

171 1774Provision of Drainage PCC Facilities at UC Artali

Virkan Tehsil Nowshera Virkan District GujranwalaGujranwala

On-going

Schemes30.000 19.958 3.335 2.501 1.668 67% 72% Work in progress

172 1775Provision of Drainage PCC Facilities at UC Baddo

Ratta Tehsil Nowshera Virkan District Gujranwala Gujranwala

On-going

Schemes30.000 19.870 3.334 2.501 1.667 67% 72% Work in progress

173 1776Provision of Drainage / PCC Schem at UC Chahal

Kalan, District GujranwalaGujranwala

On-going

Schemes77.757 19.999 3.333 2.500 1.667 67% 28% Work in progress

174 1777Drainage Sewerage and PCC UC atawa UC Rakh

Kikran WaliGujranwala

On-going

Schemes280.818 151.994 14.117 10.588 7.059 67% 57% Work in progress

175 1778PCC and Drainage Facility at Sadoki,Dargahapur

and others in Tahsil KamokiGujranwala

On-going

Schemes158.153 84.945 3.333 2.500 1.667 67% 55% Work in progress

176 1779Provision of PCC/Drainage Sewerage Schemes at

UC No 14, 15, 46, 50, 51, 52, 53 Gujranwala Gujranwala

On-going

Schemes131.295 110.646 6.883 1.720 0.000 0% 84% Scheme completed

177 1780Provision of PCC/Drainage/Sewerage Scheme at

Municipal Committee, Ghakar MandiGujranwala

On-going

Schemes194.226 75.000 20.000 15.000 10.000 67% 44% Work in progress

178 1781

Const. of disposal Sewerage Drainage PCC

Scheme Morr Eminabad Gharbi Audo Rai UC

Maraliwala Tehsil and Distt. Gujranwala

GujranwalaOn-going

Schemes178.291 99.864 6.667 5.000 3.334 67% 58% Work in progress

179 1782

Const. of Sewerage Drainage- PPC Soling in

UCs Tehsil Noshera Virkan including UCs No.

Wala Jhatan wali & Sahran Chahta

GujranwalaOn-going

Schemes467.500 89.888 1.000 0.750 0.500 67% 19% Work in progress.

Page 13: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

180 1783

Rural Drainage and PCC Scheme at Wandala

Virkan Taly Aali Badhay new Abadi Gaibi Lunj

Sharif Kolo wala, Matu Bhanake Al Ditta, Ratta

Goraya, Chak Poryan ana Paryan, Karyal Khan

and and Adjoining Dera Jattan.

GujranwalaOn-going

Schemes50.000 19.997 3.333 2.500 1.667 67% 43% Work in progress

181 1784

Rural Drainage PCC Scheme Kot Nisar Shah

Boopara Khurd Dhairr Virkan Bhirri Shah Rehman

Dharoke Sadu

GujranwalaOn-going

Schemes109.270 46.942 6.667 5.000 3.334 67% 46% Work in progress

182 1785Sewerage Scheme Kamoke of Leftover Area

GujranwalaGujranwala

On-going

Schemes199.100 65.949 5.000 3.750 2.500 67% 34% Work in progress

183 1786Imrovement of Sewerage, Solling, Drain Tatley Aali

Road KamokayGujranwala

On-going

Schemes103.000 10.000 20.000 15.000 10.000 67% 19% Work in progress.

184 1787

Provision of PCC/Sewerage/Drainage/Solling etc.

in village Chachoke Tehsil Noshera Virkan District

Gujranwala

GujranwalaOn-going

Schemes15.000 9.941 1.667 1.250 0.834 67% 72% Work in progress.

185 1788

Provision of PCC/Drainage Scheme in UC

Kalaske, Kot Amar singh, Kot Shaira, Batla Janda

Sigh, Uggu Chak Paponakha, UC 71 Khiyali # 14

MC Qila Didar Singh

GujranwalaOn-going

Schemes197.800 19.996 30.000 22.500 15.000 67% 18% Work in progress

186 1789

Provision of Clean Drinking Water/Sewerage

Scheme at Ldhay wala Waraich, Madhu Khalil,

Chain Wala etc

GujranwalaOn-going

Schemes199.779 50.000 30.000 22.500 15.000 67% 33% Work in progress.

187 1790Provision of Sewerage / Drainage and PCC

facilities Qila didar singh GujranwalaGujranwala

On-going

Schemes40.000 10.000 5.000 3.750 2.500 67% 31% Work in progress.

188 1791Provision of Sewerage Drainage and PCC facilities

Gakhar City GujranwalaGujranwala

On-going

Schemes40.000 10.000 5.000 3.750 2.500 67% 31% Work in progress.

189 1792Sewerage and PCC Scheme for Bismillah Colony

Wania and Adjacent Area GujranwalaGujranwala

On-going

Schemes105.000 96.046 2.985 2.239 1.493 67% 93% Work in progress

190 1793

RSD/ PCC Scheme UC Shamsa Dada UC Majju

Chak UC Bhoopra Kalan UC Argan UC Philloke

and UC Abidabad Gujranwala

GujranwalaOn-going

Schemes168.000 46.983 3.333 2.500 1.667 67% 29% Work in progress

191 1794

Rural Drainage/PCC Scheme in U.C. Garmula

Virkan, U.C Budha Goraya, Dogranwala, U.C

Phama Sara, Kalsian Dhutran, Kot Bilal and

Madan Chak, Tehsil Nowshera Virkan, Dist.

Gujranwala (Revised)

GujranwalaOn-going

Schemes109.270 29.914 5.000 3.750 2.500 67% 30% Work in progress

192 1795Rural Drainage Scheme UC Kot Hassan Khan

Kassoki Karyala & Allied AbbadiesHafizabad

On-going

Schemes98.000 10.000 3.333 2.500 1.667 67% 12%

A.A. 98.000(M) T.S.98.000 (M) work is in progress

Fund release but not yet online.

193 1796

Rural Drainage Scheme UC Chak Chattha Sabir

Kalan Kallian Wala & Allied Abbadies, District

Hafizabad

HafizabadOn-going

Schemes98.000 10.000 1.000 4.084 3.330 82% 14%

A.A. 98.000(M) T.S.98.000 (M) work is in progress

Fund release but not yet online.

194 1797Drainage/Sewerage and water Supply Scheme of

Mangat and Rasul

Mandi

Bahauddin

On-going

Schemes102.080 73.238 3.333 2.600 2.600 100% 74%

* Org. A.A Date. 03.10.2011* Rev. A.A Date.

23.02.2013* T.S Date. 18.11.2011* Start Date

02.11.2011* Completion date 30.06.2019.* Work in

progress.

195 1798

Construction of street, Drainage and Soling of

Kakka and Kot Jafar, Chak No.18 & 19, District

M.B.Din

Mandi

Bahauddin

On-going

Schemes6.500 5.737 0.167 0.100 0.059 59% 89%

* A.A Date. 09.03.2017* T.S Date. 10.03.2017* Start

Date 12.04.2017

196 1799

Construction of street, Drainage and Soling of

Khizar and Chak No.52, UC Chot Dheeran, District

M.B.Din

Mandi

Bahauddin

On-going

Schemes13.000 10.726 0.644 0.433 0.272 63% 85%

* A.A Date. 09.03.2017* T.S Date. 10.03.2017* Start

Date 11.04.2017

197 1800Provision of Sewerage / Drainage / Pavement in

Halian & Ghanian, Tehsil Phalia

Mandi

Bahauddin

On-going

Schemes50.000 48.643 0.252 0.189 0.126 67% 98%

* A.A Date. 28.01.2015* T.S Date. 08.02.2015* Start

Date 11.04.2015

198 1801

Provision of Sewerage / Drainage / Pavement in

Jano Chak Khurd & Kalan , Basi Khurd & Kalan,

Channi Mast, Aado Sarwani.

Mandi

Bahauddin

On-going

Schemes75.571 52.495 3.333 1.250 0.417 33% 70%

* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start

Date 24.12.2016* Completion date 30.06.2019.*

Work in progress.

Page 14: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

199 1802Provision of Sewerage / Drainage / Pavement in

Narang / Saadullaha Pur / Khoosor

Mandi

Bahauddin

On-going

Schemes64.664 50.171 4.824 1.668 0.462 28% 78%

* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start

Date 24.12.2016

200 1803

Provision of Sewerage / Drainage / Pavement in

Sarlay,Lasoori Kalan,Duggal, Phalia Boota (Incl.

THQ Hospital), Tehsil Pahila

Mandi

Bahauddin

On-going

Schemes50.000 44.765 1.579 0.594 0.200 34% 90%

* A.A Date. 28.01.2015* T.S Date. 08.02.2015* Start

Date 11.04.2015* Completion date 30.06.2019.*

Work in progress.

201 1804Rural Sewerage/Drainage scheme village Bosal,

Tehsil Malikwal, District M.B. Din

Mandi

Bahauddin

On-going

Schemes90.500 79.269 3.744 2.808 1.872 67% 90%

* A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start

Date 17.12.2015* Completion date 30.06.2019.*

Work in progress.

202 1805Rrural/Sewerage/Drainage Scheme pindi Kalu

Tehsil Phalian District Mandi bahauddin

Mandi

Bahauddin

On-going

Schemes50.000 14.942 11.667 11.750 8.834 75% 48%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

203 1806Sewerage Drainage Scheme UC Dhok Kasib

Tehsil & District M B Din

Mandi

Bahauddin

On-going

Schemes20.000 19.500 0.166 0.104 0.062 60% 98%

* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start

Date 23.12.2016.* Completion date 30.06.2019.*

Scheme completed in saving.* A.A Date.

23.09.2016* T.S Date. 24.09.2016* Start Date

23.12.2016.* Completion date 30.06.2019.* Scheme

completed in saving.

204 1807Sewerage & Drainage Scheme U.C Rasul Tehsil &

District M.B.Din.

Mandi

Bahauddin

On-going

Schemes20.000 19.421 0.184 0.099 0.053 54% 97%

* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start

Date 21.12.2016.* Completion date 30.06.2019.*

Scheme completed in saving.

205 1808Sewerage / Drainage of Village Rerka Mumdana,

Tehsil Malikwal

Mandi

Bahauddin

On-going

Schemes41.684 24.326 5.753 3.415 1.977 58% 63%

* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start

Date 29.12.2016* Completion date 28.12.2019.*

Work in progress

206 1809

Rural Sewerage, Drainage/Soling & PCC Scheme

in Chak No. 20 With Abadies Tehsil Malikwal Distt.

M.B Din

Mandi

Bahauddin

On-going

Schemes50.000 45.999 1.334 1.001 0.667 67% 93%

* A.A Date. 23.09.2016* T.S Date. 24.09.2016* Start

Date 19.11.2016* Completion date 30.06.2019.*

Work in progress

207 1810

Rural Sewerage, Drainage/Soling & PCC Scheme

in Villages Main Mandi Mona Depot Pind Makko

Tehsil Malilwal District M.B.Din

Mandi

Bahauddin

On-going

Schemes53.052 42.556 2.629 0.972 0.315 32% 81%

* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start

Date 07.02.2017* Completion date 30.06.2019*

Work in progress

208 1811Rural Sewerage / Drainage Scheme of Village

Bherowal Tehsil Phalia Distt. Mandi Bahauddin

Mandi

Bahauddin

On-going

Schemes73.499 29.396 5.000 3.750 2.500 67% 43%

* A.A Date. 23.09.2016* T.S Date. 28.10.2016* Start

Date 24.12.2016* Completion date 30.06.2019.*

Work in progress

209 1812Rural Sewerage / Drainage Scheme of Village Khai

and Bukkan Tehsil & Distt. M.B. Din

Mandi

Bahauddin

On-going

Schemes74.464 61.888 4.180 1.485 0.440 30% 84%

* A.A Date. 23.09.2016* T.S Date. 28.10.2016 *

Start Date 06.12.2016* Completion date

30.06.2019.* Work in progress

210 1813Rural Sewerage / Drainage Scheme Village

Kuthiala Sheikhan, Tehsil & District M.B. DIN

Mandi

Bahauddin

On-going

Schemes55.150 45.574 3.192 1.079 0.281 26% 83%

* A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start

Date 17.12.2015* Completion date 30.06.2019.*

Work in progress

211 1814

Sewerage / Drainage Schemes in Adda

Pharainwali, Sandhanwala, Haigerwala, Murala,

Dhall, Dhola, Chhani, Lakhia, Chak No. 38., and

Ahdi in District M.B.Din

Mandi

Bahauddin

On-going

Schemes247.904 79.958 6.667 2.000 0.334 17% 32%

* A.A Date. 06.09.2017* T.S Date. 24.10.2017* Start

Date. 08.01.2018* Completion date

07.01.2021*Work in progress.

212 1815Provision of PCC / Sewerage / Drainage and allied

faiclities in PP-120, District M.B.Din

Mandi

Bahauddin

On-going

Schemes50.000 28.500 7.167 5.375 3.584 67% 64%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

213 1816Sewerage and Drainage scheme of Sahna and

Khanana, District Mandi Baha Ud Din

Mandi

Bahauddin

On-going

Schemes100.000 22.099 8.333 6.250 4.167 67% 26%

* A.A Date. 25.08.2017* T.S Date. 07.09.2017* Start

Date. 06.01.2018* Completion date

05.01.2020*Work in progress.

214 1817

Construction of Brick Pavement PCC Street &

Drain / Nullah U.C Mundeke, Ghuinke, Baddokey

Cheema, Allomahar, Jamke Cheema, Tehsil

Daska District Sialkot

SialkotOn-going

Schemes50.000 29.900 1.667 1.250 0.834 67% 61% Work in progress.

215 1818

Construction of PCC, Solling & Drain / Nullah UCs

Head Marala, Machrala, Gondal, Bolwanwala ,

Pindi Punjorian, Kaman Wala Kundan pur,

Dallowali, Katchi Maund, Pholkin, Wadhgran Tehsil

Sialkot District Sialkot

SialkotOn-going

Schemes150.000 34.566 3.333 2.500 1.667 67% 24% Work in progress.

216 1819

Construction of RCC Sewer & RCC from Zohara

Memorial Hospital Chowk to Railway Crossing to

Ajmal Garden to Shetab Garha to Adalat Pur road

to Nullah Aik, Tehsil & District Sialkot

SialkotOn-going

Schemes175.320 87.576 6.667 5.000 3.334 67% 52% Work in progress.

Page 15: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

217 1820 Construction of Sewerage and Drainage Scheme

Village Kapooro Wali Tehsil & District Sialkot Sialkot

On-going

Schemes30.000 24.983 1.667 1.250 0.834 67% 86% Work in progress.

218 1821

Provision of PCC / Soling / Nallain /Streets at

Baigo wali bsmulla kot marth ,kot muhmmad

hussain ,pipli wala ,begowala adda ,bhola musa

kotli bawarian, kot kuda yar ,kot qadar daad

,randeer ,bagrian ,chak kupa ,gulab garh, doburji

chanda sing ,chowkey ,r

SialkotOn-going

Schemes80.000 34.470 3.333 2.500 1.667 67% 45% Work in progress.

219 1822

Provision of PCC / Soling / Nallain /Streets

Schemes at Malkhanwala Bshmula Wan, Pasia,

Firdospur, Bangla Nai Abadi, Chak Bassawa, Dhop

Sari, Hameed Colony, Mehlowal, Abdullah abad,

Dera Roshan Gujjar, Amreekh pura District Sialkot

SialkotOn-going

Schemes80.000 34.000 3.333 2.500 1.667 67% 45% Work in progress.

220 1823

Provision of PCC / Soling / Nullah / Street Scheme

at Khambranwala Bashamula, Dogree, Gorian,

Sundar Pur, Bidar, Chak Simanwali etc., Tehsil

Sambrial, District Sialkot [LO160068845].

SialkotOn-going

Schemes60.000 34.403 3.333 2.500 1.667 67% 60% Work in progress.

221 1824

Provision of PCC / Soling / Nullah / Street Scheme

at Bakhray Wali Bashamula, Dogranwala,

Kathiala, Habibpur etc., Tehsil Sambrial, District

Sialkot [LO16006884].

SialkotOn-going

Schemes55.000 19.960 1.667 1.250 0.834 67% 38% Work in progress.

222 1825

Provision of PCC / Soling / Nullah / Street Scheme

at Kulowal Bashamula , Aurtala Sharif, Chak

Mughal , Tika , Tambray, Gaghar. Baseer, Jay,

Ditowali, Chanigondal, etc., Tehsil Sambrial,

District Sialkot

SialkotOn-going

Schemes100.000 19.980 3.333 2.500 1.667 67% 22% Work in progress.

223 1826

Provision of PCC / Soling / Nullah / Street Scheme

at Gohad Pur Bashamula, Handlapur, Korpur,

Nawan Pind, Nangal, Ghiti Shekan, Kansarour,

Tibbi, Arrian, Saleempur, Malkay, Kalan, Malkay

Khurd, Olkh Awana etc., Tehsil & District Sialkot

[LO16006880].

SialkotOn-going

Schemes399.852 29.955 3.333 2.500 1.667 67% 8% Work in progress.

224 1827

Provision of PCC / Soling / Nullah / Street Scheme

at Kapurwali, Bashamula Ajjowali, Basant Pur,

Dagaray, Malo Chak , Jorian Khurd / Kalan ,

Sukhnian, Bhindar, Olakh, Saidpur,

Jatta,Dusri,Kala Ghumna,Khambranwala, Kansar

Pur, Canday Wali etc., Tehsil & D

SialkotOn-going

Schemes70.000 19.987 3.333 2.500 1.667 67% 31% Work in progress.

225 1828

Provision of PCC / Soling / Nullah / Street Scheme

at Jaithi Kay Bashaula, Joluki, Maja Khurd,

Haddokay, Kot Deena, Tibbi Inayat Shah, Deera

Tibbi Inayat Shah, Deera Tarraran, Dra Gujjran,

Dera Arrian, Karan Wali etc.,Teshil & District

Sialkot

SialkotOn-going

Schemes50.000 19.990 3.333 2.500 1.667 67% 43% Work in progress.

226 1829

Provision of PCC / Soling / Nullah / Street Scheme

at Jassor Wala Bashamula, Chak Gillan Sharki,

Chak Gillan Magrabi, Pandorian, Muhammad Pura,

Gega, Addowali, Rajjokay etc.,Teshil & District

Sialkot

SialkotOn-going

Schemes50.000 20.000 1.667 1.250 0.834 67% 42% Work in progress.

Page 16: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

227 1830

Provision of PCC / Soling / Nullah / Street Scheme

Roras, Bashamula Mango Behram , Pidian, Kot

Bagaa, Chak Maluk, Chak Janta, Dhana Wali

Mehad Pur, Dadowali, Manair etc., Tehsil

Sambrial, District Sialkot [LO16006879].

SialkotOn-going

Schemes60.000 20.000 1.667 1.250 0.834 67% 35% Work in progress.

228 1831

Provision of PCC Sewerage Schemes in UC

Dhuda Goraya, MaloMahay, Bogray SEO KE

District Sialkot

SialkotOn-going

Schemes40.000 20.000 3.333 2.500 1.655 66% 54% Work in progress.

229 1832

Provision of Sewerage and Tuff Tile in Various

UCs of District Sialkot, UCs, kotli Behram, Mubarik

pura, Miana pura, Model Town, Fateh Garh,

Muzafar pur, Haji pura, Ban, Haji pura-II, Imam

Sahib, Shahab pura, Pacca Garha, Hamza Ghous.

SialkotOn-going

Schemes120.000 75.000 3.333 2.500 1.667 67% 64% Work in progress.

230 1833

Providing and Laying Tuff Tile RCC Sewer and

Construction of Drain /Nullah Mohallah Shahab

Pura Bajli Mohallah Darbar Shahab Shah U/C.

Shahab pura Tehsil & District Sialkot

SialkotOn-going

Schemes35.000 31.000 1.333 0.333 0.225 68% 89% Work in progress.

231 1834

Construction of PCC Street Drain/ Nullah

Providing and Laying of RCC Sewer and Tuff Tile

U/C Water Works (Silver star road Mohallah

Islamia Park) Tehsil & District Sialkot.

SialkotOn-going

Schemes24.400 14.991 3.133 2.350 1.565 67% 68% Work in progress.

232 1835

Construction of PCC Street, Drain/ Nullah

Providing and Laying of RCC Sewer and Tuff Tile

U/C Duburj Arraian (Moh. Baba Bari, Habib pura)

Tehsil & District Sialkot

SialkotOn-going

Schemes29.500 20.000 3.167 2.375 1.584 67% 73% Work in progress.

233 1836

Construction of PCC Street, Drain/ Nullah

Providing and Laying of RCC Sewer and Tuff Tile

U/C Muhammad pura (Nishat park) Tehsil &

District Sialkot

SialkotOn-going

Schemes28.600 19.938 2.867 2.150 1.434 67% 75% Work in progress.

234 1837

Construction of PCC Street, Drain/ Nullah

Providing and Laying of RCC Sewer and Tuff Tile

U/C Water Works (Moh. Pak pura) Tehsil & District

Sialkot

SialkotOn-going

Schemes25.500 19.975 1.833 1.375 0.917 67% 82% Work in progress.

235 1838

Providing & Laying of RCC Sewer, Tuff Tile and

Construction of Disposal Station Mohallah Water

Works to Abbot Road Phatak and along the

Railway line to Dara Arrian U/C Water Works,

Tehsil & District Sialkot

SialkotOn-going

Schemes50.000 8.000 5.000 1.450 0.964 66% 18% Work in progress.

236 1839

Providing & Laying of RCC Sewer, Tuff Tile and

Construction of Disposal Station Nasir Road Prem

Nagar Road EIC School to Nullah Bhed U/C Model

Town, Tehsil & District Sialkot

SialkotOn-going

Schemes50.000 10.000 5.000 2.350 1.450 62% 23% Work in progress.

237 1840

Providing and Laying of Tuff Tile RCC Sewer and

Construction of Drain / Nullah Mohallah Kashmiri

Sarray Bhabrian Alamgir Bazar Nikhas U/C. Imam

Sahib Tehsil & District Sialkot

SialkotOn-going

Schemes32.000 25.933 2.000 0.700 0.468 67% 83% Work in progress.

238 1841

Provision of PCC/Soling /Nalian/Streets Schemes

at Bohalwala Bashamula Chak Kheena, Kotli

Nonaan, Kotli Nonaan, Dot Dharan Baddoke

Cheema, Kot Bhagat, Jalianwala Ahmadabad

District Sialkot

SialkotOn-going

Schemes80.000 40.500 3.333 5.067 4.230 83% 56% Work in progress.

Page 17: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

239 1842

Provision of PCC/Soling/nalian/Streets Scehmes at

Majra kalan, Chak Ekhtiar, Dingowal, Mahiwal,

rakh noshra ,kothy pardansing (islambad)khothay

chistian ,Dorarbe Malianwala Jattan & Arrian, Pano

attari Hussain Pur, Jamal Pur District Sialkot

SialkotOn-going

Schemes90.000 69.860 3.333 2.500 1.667 67% 79% Work in progress.

240 1843

Provision of PCC/Soling/Nalian/Streets Schemes

at Barath Bhoth Bashamula Markiwal, Khorta

Syedan, Ballanwala, Machi Khokhar, Gul Bahar

Khurd, Gul Bahar Kalan

SialkotOn-going

Schemes50.000 29.945 1.667 1.250 0.834 67% 62% Work in progress.

241 1844

Provision of PCC/Soling/Nalian/Streets Schemes

at Chaprar Bashamula Punowal, Najwal, Parwal,

Sagarpu, Medhi pur, Bagh pur, Sagri pur etc

SialkotOn-going

Schemes55.000 29.978 3.333 2.500 1.667 67% 58% Work in progress.

242 1845

Provision of PCC/Soling/Nalian/Streets Schemes

at Gojra Bashamula Thatha Lathi, Qila Tek Singh,

Bhonawali, Phangat, Dheera Sanda, Islam pura,

Kotli wala, Kandan Sian

SialkotOn-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress.

243 1846

Provision of PCC/Soling/Nalian/Streets Schemes

at Mandran Wala Bashamula Adamkay Cheema,

Nai Abadi,

SialkotOn-going

Schemes75.000 49.601 3.333 2.500 1.667 67% 68% Work in progress.

244 1847

Provision of PCC/Soling/Nalian/Streets Schemes

at Saidowali Bashamula Hambokay, Kot Mahraj,

Merian Pindi, Lalaywali, Easa pur, Khorray, Suraj,

Chak Hana etc

SialkotOn-going

Schemes70.000 20.000 3.333 2.500 1.667 67% 31% Work in progress.

245 1848

Provision of PCC/Soling/Nalian/Streets Schemes

at Shahuwala Bashamula Balo Chak, Nashtar

Abad, Zafarwali, Kamalpur, Manpur etc.

SialkotOn-going

Schemes28.000 19.920 2.667 2.000 1.334 67% 76% Work in progress.

246 1849

Provision of PCC/Soling/nalian/Streets Schemes at

Sheeni Bashamula Chaila, bjola, Muljhan, Sagar,

punwal ratwal ,chogpur District Sialkot

SialkotOn-going

Schemes90.000 77.698 3.333 2.500 1.667 67% 88% Work in progress.

247 1850

Provision of PCC/Soling/Nalian/Streets Schemes

at Verowala Bashamula Wassankay, Magokaman,

Nandpur, Baryar, Wan Garthal Umarkey Kalan,

Umarkey Khurd, Ahmad abad, Veeramkay etc

SialkotOn-going

Schemes50.000 19.925 3.333 2.500 1.667 67% 43% Work in progress.

248 1851Const of Streets/drains & PCC in Village

PartanwaliSialkot

On-going

Schemes60.000 12.990 1.667 1.250 0.834 67% 23% Work in progress.

249 1852Const of Streets/drains & PCC in Village Saidpur

KalanSialkot

On-going

Schemes65.000 16.490 3.333 2.500 1.660 66% 28% Work in progress.

250 1853

Const. of Nullah from Sublime Chowk to Uggoki

More to Sahowala Bridge to Syphonof Nullah Aik,

Sialkot

SialkotOn-going

Schemes394.111 244.942 16.667 12.500 8.334 67% 64% Work in progress.

251 1854 Const. of PCC Drains / Sewerage Sialkot SialkotOn-going

Schemes90.000 62.984 3.333 7.700 6.867 89% 78% Work in progress.

252 1855Provision of Sewerage & PCC Schemes in Pero

Chak, Sego Wala, Adha Kanwamlit District SialkotSialkot

On-going

Schemes40.000 19.855 1.667 0.550 0.350 64% 51% Work in progress.

253 1856Provision of Sewerage & PCC Schemes UC

Jharah Wala Salhoke, Bharlham WalaSialkot

On-going

Schemes40.000 19.940 1.667 1.250 0.834 67% 52% Work in progress.

254 1857

Provision of Sewerage / Drainage Scheme at UC

Dhodha Tehsil Pasrur District Sialkot (under

revision)

SialkotOn-going

Schemes165.000 90.000 1.673 4.555 4.137 91% 57% Work in progress.

Page 18: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

255 1858 Construction of Drains, Soling / PCC and Sullage

Carrier of Ghughiat, District SargodhaSialkot

On-going

Schemes18.164 15.000 1.055 0.791 0.611 77% 86%

"Date of A.A 25.01.2016, Date of T.S 30.01.2016,

Date of Award 25.01.2017, Scheduled date of

Completion on 30.06.2018, Date of

Commencement, 25.01.2017, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

256 1859 Construction of PCC / Drain in Dhera Sardha

District SialkotSialkot

On-going

Schemes50.000 47.970 0.667 0.500 0.330 66% 97% Work in progress.

257 1860

Construction of PCC Drain / Tuff Tile Ward No. 1

to 30 Daska Kalan, Daska Kot, U. C Galotian

Kalan, Ranganwala, Moseywala, Gaga, Ladhey

Bhanbanwal, Thatha, Sukhar Nahar &

Bhadeywala, Daska City, District Sialkot.

SialkotOn-going

Schemes70.000 39.545 3.333 2.500 1.667 67% 59% Work in progress.

258 1861

Construction of Drain/Nullah for Diposal of

Sewerage at Bhadewal Tehsil Daska District

Sialkot

SialkotOn-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

259 1862Reheblitiation of Sewerage/Drainage Scheme

Mitranwali Tehsil Daska District SialkotSialkot

On-going

Schemes20.000 10.000 3.333 7.500 6.667 89% 83% Work In Progress

260 1863

Sanitation Schemes in UCs, Gadgore, Khanawali,

Alhar, Jassoran, Baddiana and Chawinda, Tehsil

Pasrur

SialkotOn-going

Schemes40.000 26.000 4.667 3.500 2.334 67% 71% Work in progress.

261 1864Construction of PCC Streets, Drains,Tuff tiles and

Soling in Adalat Garah, District SialkotSialkot

On-going

Schemes30.000 14.935 5.000 3.750 2.500 67% 58% Work in progress.

262 1865Construction of PCC Streets, Drains,Tuff tiles and

Soling in Mahal Kingra & Dhanney, District SialkotSialkot

On-going

Schemes6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress.

263 1866Construction of PCC Streets, Drains,Tuff tiles and

Soling in Muzafar Pur, District SialkotSialkot

On-going

Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.

264 1867Construction of PCC Streets, Drains,Tuff tiles and

Soling in Shatab Garah, District SialkotSialkot

On-going

Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.

265 1868Construction of PCC Streets, Drains,Tuff tiles and

Soling in Bonkam, District SialkotSialkot

On-going

Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.

266 1869

Construction of PCC Streets, Drains,Tuff tiles and

Soling in Ganjianwali & Roheel Garah, District

Sialkot

SialkotOn-going

Schemes6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress.

267 1870

Construction of PCC streets, Drains,Tuff tiles and

Soling in Chak Adil,Chitti Shikhan,Nawan Pind,

District Sialkot

SialkotOn-going

Schemes10.000 5.000 1.000 0.834 0.834 100% 58% Work in progress.

268 1871Construction of PCC Streets, Drains,Tuff tiles and

Soling in Murad Pur, District SialkotSialkot

On-going

Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in progress.

269 1872Construction of PCC Streets, Drains,Tuff tiles and

Soling in Gohad Pur, District SialkotSialkot

On-going

Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in progress.

270 1873Construction of PCC Streets, Drains,Tuff tiles and

Soling in Dhanwali, District SialkotSialkot

On-going

Schemes5.000 2.500 1.000 0.750 0.500 67% 60% Work in progress.

271 1874

Construction of PCC Streets, Drains,Tuff tiles and

Soling in Village Monger to Nehar Upper Chanab &

Village Ranjhai to Burj Cheema Link Way, District

Sialkot

SialkotOn-going

Schemes6.000 3.000 1.000 0.750 0.500 67% 58% Work in progress.

272 1875

Construction of PCC Streets, Drains,Tuff tiles and

Soling in Monger Sofen to Barthanwala, District

Sialkot

SialkotOn-going

Schemes7.000 3.500 1.167 0.875 0.584 67% 58% Work in progress.

273 1876Construction of PCC Streets, Drains,Tuff tiles and

Soling in Hunter Pura, District SialkotSialkot

On-going

Schemes5.000 2.500 0.833 0.625 0.417 67% 58% Work in progress.

Page 19: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

274 1877Drainage / PCC scheme for village Gorala

Maanpur Narowal

On-going

Schemes50.000 34.743 3.333 2.500 1.659 66% 73%

A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start

Date 16.11.2016 *Completion date 30.06.2019 work

in progress. Funds not received on spending end yet

275 1878

PCC , Soling and Drainage Scheme in Village

Babral, Kallah, Mahlo, Sahlo,Tehsil Shakargarh,

District Narowal

NarowalOn-going

Schemes41.395 24.992 3.333 2.500 1.663 67% 64%

A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start

Date 16.11.2016*Completion date 30.06.2019.work

in progress. Funds not received on spending end

yet.

276 1879

PCC / Soling / Filtration Plant in Village Noor Kot

Manngri and Bagha Madan Thakrian Pagla,

District Narowal.

NarowalOn-going

Schemes46.000 18.730 1.000 0.750 0.480 64% 42%

A.A. dated 3.08.17 *Start Date

16.11.2016*Completion date 30.06.2020 Work in

progress. Fund not received on spending end yet.

277 1880

Construction of Nalian, Soling, PCC & Boundary

Walls of Graveyard in UCs Nallah, Bua, Melo Salo,

Kalah, Mainagty, Bara Manga, Kot Naina, Bahree,

Ikhras Pur, Jalala, Sujowal, Pehgwari, Malik Pur,

Fateh Pur Afghana, Sahari, Ghona, Ghumtala,

Kanjror, Lang

NarowalOn-going

Schemes85.000 49.192 3.333 2.500 1.659 66% 60%

A.A. dated 23.9.2016. T.S. dated 24.9.2016. *Start

Date 16.11.2016*Completion date 30.05.2019.work

in progress. Funds not received on spending end yet

278 1881 Sewerage scheme for Ghaziwal, Narowal. NarowalOn-going

Schemes34.648 33.308 0.378 0.284 0.188 66% 97%

"A.A. dated 03.05.2014 T.S. dated 23.05.2014

*Start Date 18.09.2014 *Completion date

30.06.2019 work in progress. Fund not received on

spending end yet

279 1882Urban / Sewerage / PCC & Tuff Tile Scheme

Narowal City Narowal

On-going

Schemes174.705 84.160 6.667 5.000 3.321 66% 50%

A.A Date.23.9.2016.T.S Date*28.10.2016 Date of

start 17.2.2017Date of completion 30.06.2019.

Work in progress.

280 1883 Sewerage scheme for Oncha Sadawala, Narowal. NarowalOn-going

Schemes49.284 47.265 0.611 0.458 0.305 67% 97%

"A.A. dated 03.05.2014 T.S. dated 23.05.2014 Start

Date 18.09.2014 Completion date 30.06.2019 work

in progress. Fund not received on spending end yet

281 1884 PCC and Drainage Scheme in UC 197 at Dhalloki LahoreOn-going

Schemes100.082 91.500 2.861 2.146 1.431 67% 93%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

282 1885PCC and Drainage Scheme in UC 243 at attari

Saroba Pind Lahore

On-going

Schemes130.989 90.510 6.667 5.000 3.334 67% 72% Work stopped due to awaiting funds.

283 1886PCC and Drainage Scheme in UC 246 at

Youhanabad Lahore

On-going

Schemes100.838 100.494 0.344 0.258 0.172 67% 100%

Scheme Completed. Funds required to clear the

contractor's liabilities against Price Variation.

284 1887PCC and Drainage Scheme in UC 247 at Kahna

KohnaLahore

On-going

Schemes201.357 130.000 6.667 7.500 5.834 78% 67% Work stopped due to awaiting funds.

285 1888PCC and Drainage Scheme in UC 248 at

Shehzada and Pura KahnaLahore

On-going

Schemes151.603 128.300 7.201 5.401 3.601 67% 87% Work stopped due to awaiting funds.

286 1889PCC and Drainage Scheme in UC 249 at

Kamahan Lahore

On-going

Schemes80.384 70.070 3.438 2.579 1.719 67% 89%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

287 1890 PCC and Drainage Scheme in UC 252 at Pandoki LahoreOn-going

Schemes113.315 106.999 2.105 0.759 0.233 31% 95%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

288 1891 PCC and Drainage Scheme in UC 253 at Suraich LahoreOn-going

Schemes120.660 96.245 8.138 6.004 3.969 66% 83% Work stopped due to awaiting funds.

289 1892PCC and Drainage Scheme in UC 254 Deo Khurd

and Kalan Lahore

On-going

Schemes102.533 83.173 4.187 3.040 1.994 66% 83% Work stopped due to awaiting funds.

290 1893PCC and Drainage Scheme in UC 268 at Judho

DheerLahore

On-going

Schemes102.003 89.361 4.001 2.501 1.501 60% 89% Work stopped due to awaiting funds.

291 1894PCC and Drainage Scheme in UC 271 at Jia

Bhagga and RO Plant at Jia Bhagga Lahore

On-going

Schemes103.300 100.032 1.086 4.815 4.543 94% 101% Scheme completed

292 1895 PCC and Drainage Scheme in UC191 at Gawind LahoreOn-going

Schemes100.000 92.500 2.500 1.875 1.250 67% 94%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

293 1896

Construction of PCC Sewerage & Drainage

System at UC 262 Shamke Bhattian, District

Lahore

LahoreOn-going

Schemes30.000 18.497 3.833 2.875 1.917 67% 68% Work stopped due to awaiting funds.

294 1897 Construction of PCC Sewerage & Drainage

System at UC 267 Manak, District LahoreLahore

On-going

Schemes30.000 14.521 5.160 2.370 1.080 46% 52% Work stopped due to awaiting funds.

295 1898Disposal of Waste Water of Manga Mandi upto

River RaviLahore

On-going

Schemes161.107 125.649 6.667 8.463 6.797 80% 82%

Physically scheme is completed and put

operational, balance funds are for O&M for 1st

Year..

296 1899PCC and Drainage Scheme in Khananapal Kangra

Karyal Dhoondy Lahore

On-going

Schemes83.175 72.510 3.555 2.666 1.778 67% 89%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

Page 20: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

297 1900PCC and Drainage Scheme in Nanghar Katcha

Tibba Katcha Islampura Halloki SadhukeLahore

On-going

Schemes93.775 81.140 4.212 1.309 0.256 20% 87% Scheme completed

298 1901PCC and Drainage Scheme in UC 145 Gajjumatta

and Adjoining Abadies. Lahore

On-going

Schemes200.014 185.659 4.785 3.589 2.393 67% 94%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

299 1902PCC and Drainage Scheme in UC 176 at Awan

DhaiwaLahore

On-going

Schemes70.128 43.914 8.737 6.553 4.369 67% 69% Work stopped due to awaiting funds.

300 1903 PCC and Drainage Scheme in UC 179 at Bhaseen LahoreOn-going

Schemes90.000 68.013 7.329 5.497 3.665 67% 80% Work stopped due to awaiting funds.

301 1904 PCC and Drainage Scheme in UC 180 at Minhala LahoreOn-going

Schemes155.697 49.805 5.000 8.750 7.500 86% 37% Work stopped due to awaiting funds.

302 1905 PCC and Drainage Scheme in UC 181 at Narwar LahoreOn-going

Schemes45.000 43.000 0.667 0.500 0.334 67% 96%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

303 1906PCC and Drainage Scheme in UC 182 at Jallo

More & Batapur LahoreLahore

On-going

Schemes56.817 31.060 8.585 2.339 0.193 8% 55% Work stopped due to awaiting funds.

304 1907 PCC and Drainage Scheme in UC 190 at Hadiara LahoreOn-going

Schemes162.606 50.000 5.000 4.070 2.820 69% 32% Work stopped due to awaiting funds.

305 1908 PCC and Drainage Scheme in UC 194 at Liddhar LahoreOn-going

Schemes101.739 63.707 6.667 5.000 3.334 67% 66% Work stopped due to awaiting funds.

306 1909 PCC and Drainage Scheme in UC 195 at Hair LahoreOn-going

Schemes120.468 104.533 5.312 11.084 9.756 88% 95% Scheme completed

307 1910 PCC and Drainage Scheme in UC 196 at Jaman LahoreOn-going

Schemes115.347 101.472 1.500 1.125 0.750 67% 89%

Scheme Completed. Funds required to clear the

contractor's liabilities against Price Variation.

308 1911

Provision of Sanitation Facilities including

Construction of Lift Station at Tahayat & Chandrai

Village, Lahore

LahoreOn-going

Schemes94.210 81.441 4.254 3.191 2.127 67% 89% Work stopped due to awaiting funds.

309 1912 Construction of PCC and Drainage at Adda

Talaab SaralLahore

On-going

Schemes30.140 28.294 0.608 0.356 0.204 57% 95%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

310 1913 Construction of PCC and Drainage at Chung LahoreOn-going

Schemes128.380 73.594 3.333 2.400 1.567 65% 59% Work stopped due to awaiting funds.

311 1914 Construction of PCC and Drainage at Khurd Pur LahoreOn-going

Schemes74.249 28.893 3.333 2.500 1.667 67% 41% Work stopped due to awaiting funds.

312 1915 Construction of PCC and Drainage at Manga

MandiLahore

On-going

Schemes199.606 42.995 5.000 2.050 0.800 39% 22% Work stopped due to awaiting funds.

313 1916 Construction of PCC and Drainage at Mohlanwal LahoreOn-going

Schemes52.966 52.184 0.261 0.996 0.931 93% 100% scheme completed

314 1917 Construction of PCC and Nallah from Hadyara

Drain to Dulam Village Lahore

On-going

Schemes29.345 18.612 3.577 2.683 1.789 67% 70% Work stopped due to awaiting funds.

315 1918 Construction of PCC Sewerage & Drainage

System at UC 260 Maraka, District LahoreLahore

On-going

Schemes30.000 12.371 5.876 3.107 1.638 53% 47% Work stopped due to awaiting funds.

316 1919Up Gradation of Streets PCC Flooring in Asif Town

I & II Galaxo Town and Adjoining abadiesLahore

On-going

Schemes150.678 108.993 6.667 4.800 3.134 65% 74% Work stopped due to awaiting funds.

317 1920Rural Drainage Scheme Kamahan & Adjoining

Abadies Lahore

On-going

Schemes143.277 126.501 5.137 2.353 1.069 45% 89% Work stopped due to awaiting funds.

318 1921

Balance work of Sewerage, water Supply and

PCC Scheme Town Committtee Kot Abdul Malik,

District Sheikhupura

SheikhupuraOn-going

Schemes195.462 167.947 3.333 2.500 1.667 67% 87% Work in Progress

319 1922

Const and Rehabilitation of PCC Sewerage

Scheme of Ravi Rayan Mannu Abad and Nazar

Abad (Revised)

SheikhupuraOn-going

Schemes95.313 41.645 3.333 2.500 1.667 67% 45% Work in Progress

320 1923 Construction of Drainage & PCC Scheme at

Mariam Abad District SheikhupuraSheikhupura

On-going

Schemes25.000 20.000 1.667 1.250 0.834 67% 83% Work in Progress

321 1924 Construction of Drainage & PCC Scheme at Mian

Ali Dogran District SheikhupuraSheikhupura

On-going

Schemes30.000 20.000 3.333 2.500 1.667 67% 72% Work in Progress

322 1925 Construction of Drainage /PCC/Soling Scheme at

Khanqah Dogran SafdarabadSheikhupura

On-going

Schemes125.450 49.569 3.333 2.500 1.667 67% 41% Work in Progress

Page 21: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

323 1926 Construction of PCC, Drains, Soling in District

SheikhupuraSheikhupura

On-going

Schemes100.000 30.000 3.333 2.500 1.667 67% 32% Work in Progress

324 1927 Provision of PCC and draniage at Manawala SheikhupuraOn-going

Schemes30.000 20.000 3.333 2.500 1.667 67% 72% Work in Progress

325 1928 Construction of PCC, Drain/Soling & Nullah at UC

75, Kakar Gill, District SheikhupuraSheikhupura

On-going

Schemes46.000 14.046 3.333 2.500 1.667 67% 34% Work in Progress

326 1929 Construction of PCC, Drain/Soling & Nullah at UC

77, Ajnianwala, District SheikhupuraSheikhupura

On-going

Schemes76.000 20.000 3.333 2.500 1.667 67% 29% Work in Progress

327 1930 Construction of PCC, Drain/Soling & Nullah at UC

83, Jatri Kohna, District SheikhupuraSheikhupura

On-going

Schemes57.000 18.000 3.333 2.500 1.667 67% 35% Work in Progress

328 1931 Construction of PCC, Drain/Soling & Nullah at UC

84, Makki 460, District SheikhupuraSheikhupura

On-going

Schemes58.000 27.000 3.333 2.500 1.667 67% 49% Work in Progress

329 1932 Construction of PCC, Drain/Soling & Nullah at UC

85, Farooqabad, District SheikhupuraSheikhupura

On-going

Schemes40.000 15.000 3.333 2.500 1.667 67% 42% Work in Progress

330 1933 Construction of PCC, Drain/Soling & Nullah at UC-

97, Ferozwatuan-I, District SheikhupuraSheikhupura

On-going

Schemes15.000 11.509 1.000 0.750 0.582 78% 81% Work in Progress

331 1934 Construction of PCC, Drain/Soling & Nullah at UC-

98, Ferozwatuan-II, District SheikhupuraSheikhupura

On-going

Schemes15.000 8.138 1.000 1.144 1.144 100% 62% Work in Progress

332 1935

Construction of Soling / Sewerage & Drainage

Scheme at UC Anjianwala, UC Jhabran, UC Kakar

Gill, UC Gujiana Nau, UC Kot Sohnda, UC

Esserkay, UC Bahalikay, UC Jatri Kohna, UC

85Farooqabad, UC Ghazi Minara, UC Buttar, UC

Jhandian Wali, UC Warn, UC Kalokay

SheikhupuraOn-going

Schemes100.000 20.000 3.333 4.167 3.334 80% 23% Work in Progress

333 1936

Const. and Rehabilitation of PCC / Sewerage

Scheme of City Muridke, District Sheikhupura

(Revised)

SheikhupuraOn-going

Schemes96.536 61.500 5.000 3.750 2.500 67% 66% Work in Progress

334 1937 Construction of PCC Tuff Tiles Sewerage

Drainage Scheme in PP 163 District SheikhupuraSheikhupura

On-going

Schemes373.950 131.468 3.333 2.500 1.667 67% 36% Work in Progress

335 1938 Rural Drainage & PCC Scheme U.C. Keelay SheikhupuraOn-going

Schemes48.000 20.000 1.667 1.250 0.834 67% 43% Work in Progress

336 1939 Rural Drainage & PCC Scheme U.C. Kot Sonda SheikhupuraOn-going

Schemes45.000 24.000 3.333 2.500 1.667 67% 57% Work in Progress

337 1940 Rural Drainage & PCC Scheme U.C. Muridke SheikhupuraOn-going

Schemes45.000 24.000 3.333 2.500 1.667 67% 57% Work in Progress

338 1941 Rural Drainage & PCC Scheme U.C. Nookhar SheikhupuraOn-going

Schemes45.000 24.000 1.667 1.250 0.834 67% 55% Work in Progress

339 1942 Rural Drainage & PCC Scheme U.C. Sacha Souda SheikhupuraOn-going

Schemes78.000 24.000 3.333 2.500 1.667 67% 33% Work in Progress

340 1943 Rural Drainage & PCC Scheme UC Bhaianwala SheikhupuraOn-going

Schemes25.000 10.425 4.858 3.644 2.429 67% 51% Work in Progress

341 1944 Rural Drainage & PCC Scheme UC Ghang SheikhupuraOn-going

Schemes20.000 16.000 1.333 1.000 0.667 67% 83% Work in Progress

342 1945 Rural Drainage & PCC Scheme UC Mojoki SheikhupuraOn-going

Schemes28.000 23.000 1.667 1.250 0.834 67% 85% Work in Progress

343 1946 Rural Drainage & PCC Scheme UC Warn SheikhupuraOn-going

Schemes25.000 10.510 4.830 3.623 2.415 67% 52% Work in Progress

344 1947Rural Drainage & PCC scheme Union Council Burj

attari, District SheikhupuraSheikhupura

On-going

Schemes99.509 30.000 3.333 2.500 1.667 67% 32% Work in Progress

345 1948Rural Drainage & PCC scheme Union Council Kot

Mehmood, District SheikhupuraSheikhupura

On-going

Schemes91.385 30.000 3.333 2.500 1.667 67% 35% Work in Progress

Page 22: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

346 1949

Rural Drainage Construction of Street Scheme

Chak No 44,45 and Village Jair District

Sheikhupura

SheikhupuraOn-going

Schemes199.486 74.950 3.333 2.500 1.667 67% 38% Work in Progress

347 1950

Rural Drainage Construction Of Street Scheme

Dograi Gill Qadeem Dograi Gill District

Sheikhupura

SheikhupuraOn-going

Schemes195.462 125.646 3.333 2.500 1.667 67% 65% Work in Progress

348 1951Rural Drainage Scheme UC Chapa Minera

SheikhupuraSheikhupura

On-going

Schemes87.910 54.975 3.333 2.500 1.667 67% 64% Work in Progress

349 1952Rural Drainage Scheme UC Chichoki Malian

SheikhupuraSheikhupura

On-going

Schemes85.423 48.694 3.333 2.500 1.667 67% 59% Work in Progress

350 1953 Rural Drainage Scheme UC Jahamke Sheikhupura SheikhupuraOn-going

Schemes94.134 54.999 3.333 2.500 1.667 67% 60% Work in Progress

351 1954Rural Drainage Scheme UC Mallian Kalan

SheikhupuraSheikhupura

On-going

Schemes92.869 50.900 3.333 2.500 1.667 67% 57% Work in Progress

352 1955Rural Drainage Scheme Abdullah Pur Kolar Chak

No 1/RB Tehsil Safdarabad District SheikhupuraSheikhupura

On-going

Schemes50.000 10.000 3.333 2.500 1.667 67% 23% Work in Progress

353 1956

Rural Sewerage Drainage System at Village Kot

Pindi Das Tehsil Ferozewala, Distt. Sheikhupura

(Revised)

SheikhupuraOn-going

Schemes199.993 185.231 4.921 3.691 2.461 67% 94% Work in Progress

354 1957Rural Drainage PCC Scheme UC Dhamkey

Sheikhupura FerozwalaSheikhupura

On-going

Schemes199.308 88.690 3.333 2.500 1.667 67% 45% Work in Progress

355 1958Rural Drainage PCC Scheme UC Mahmood Kot,

Sheikhupura , Sharqpur (Revised)Sheikhupura

On-going

Schemes180.146 78.279 3.333 2.500 1.667 67% 44% Work in Progress

356 1959Rural Drainage PCC Scheme UC Mandain Wala

Sheikhupura , Sharqpur (Revised)Sheikhupura

On-going

Schemes191.008 10.687 3.333 2.500 1.667 67% 6% Work in Progress

357 1960Rural Drainage PCC Scheme UC Mhar

Bhanguwan District Sheikhupura Sheikhupura

On-going

Schemes95.862 83.000 4.287 3.215 2.144 67% 89% Work in Progress

358 1961Rural Drainage PCC Scheme UC Quershian

Sheikhupura , Sharqpur (Revised)Sheikhupura

On-going

Schemes87.395 66.200 3.333 2.500 1.667 67% 78% Work in Progress

359 1962Rural Drainage PCC Scheme, UC Sehjowal

District Sheikhupura (Revised)Sheikhupura

On-going

Schemes93.090 74.136 3.333 2.500 1.667 67% 81% Work in Progress

360 1963Rural Drainage PCC Scheme, Wandala Dial Shah

UC 24 District Sheikhupura (Revised) Sheikhupura

On-going

Schemes144.546 142.456 0.697 0.523 0.349 67% 99% Work in Progress

361 1964Rural Drainage PCC Tuff Tile Scheme UC

Sharqpur, SheikhupuraSheikhupura

On-going

Schemes97.335 72.267 3.333 2.500 1.667 67% 76% Work in Progress

362 1965Rural drainage scheme at UC Bhadro District

SheikhupuraSheikhupura

On-going

Schemes15.110 13.100 0.670 0.503 0.335 67% 89% Scheme Completed

363 1966 RSD Scheme Faizpur Khurd District Sheikhupura SheikhupuraOn-going

Schemes40.000 16.500 3.333 2.500 1.667 67% 45% Work in Progress

364 1967Rural drainage & Const of streets scheme UC

Khan pur Sheikhupura Sheikhupura

On-going

Schemes134.768 81.863 3.333 2.500 1.667 67% 62% Work in Progress

365 1968Rural drainage & Const of streets scheme UC

Mandialy Sheikhupura (Revised)Sheikhupura

On-going

Schemes196.571 57.986 3.333 2.500 1.667 67% 30% Work in Progress

366 1969Rural drainage & Const of streets scheme UC Qila

Sattar Shah Sheikhupura (Revised)Sheikhupura

On-going

Schemes182.244 72.431 3.333 2.500 1.667 67% 41% Work in Progress

367 1970Rural drainage & Const of streets scheme Zia

abad Sheikhupura (Revised)Sheikhupura

On-going

Schemes177.038 45.905 3.333 2.500 1.667 67% 27% Work in Progress

368 1971 Rural Drainage & PCC Scheme U.C. Ajnianwala SheikhupuraOn-going

Schemes75.000 25.595 5.000 3.750 2.500 67% 37% Work in Progress

369 1972 Rural Drainage & PCC Scheme U.C. Buttar SheikhupuraOn-going

Schemes57.000 39.000 1.667 1.250 0.834 67% 70% Work in Progress

370 1973 Rural Drainage & PCC Scheme U.C. Easerkey SheikhupuraOn-going

Schemes38.000 25.000 2.667 2.000 1.334 67% 69% Work in Progress

371 1974Rural Drainage & PCC Scheme U.C. Gujiana Nu

District SheikhupuraSheikhupura

On-going

Schemes55.000 11.629 3.333 2.500 1.667 67% 24% Work in Progress

372 1975 Rural Drainage & PCC Scheme U.C. Harchand SheikhupuraOn-going

Schemes35.000 11.629 2.333 1.750 1.167 67% 37% Work in Progress

Page 23: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

373 1976Rural Drainage Scheme Chak No 8/RB

Sheikhupura Sheikhupura

On-going

Schemes75.000 17.987 3.333 2.500 1.667 67% 26% Work in Progress

374 1977Rural Drainage Scheme Faizpur Khurd IIc abadis,

Tehsil FerozewalaSheikhupura

On-going

Schemes152.400 74.217 3.333 2.500 1.667 67% 50% Work in Progress

375 1978Rural Drainage/PCC Scheme at Moran Wala

District SheikhupuraSheikhupura

On-going

Schemes90.000 80.000 0.667 0.500 0.334 67% 89% Work in Progress

376 1979Rural PCC & Drainage Scheme, UC Bhaiwala

Kalan, District Sheikhupura.Sheikhupura

On-going

Schemes29.000 22.000 2.333 1.750 1.167 67% 80% Work in Progress

377 1980

Beautification of Sharqpur Sharif, Provision of

PCC, Tufftiles, Fountains, Monuments, LED Street

lights and construction of roof of Main Bazar

SheikhupuraOn-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress

378 1981Rural Drainage & PCC Scheme UC Mirza Virkan

District Sheikhupura.Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

379 1982Rural Drainage & PCC Scheme UC Chichoki

Mallian District Sheikhupura.Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

380 1983Rural Drainage & PCC Scheme Village Madar

District Sheikhupura.Sheikhupura

On-going

Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in Progress

381 1984Rural Drainage & PCC Scheme UC Mohallah

Rehman Pura District Sheikhupura.Sheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

382 1985Rural Drainage & PCC Scheme UC kot Ranjeet

District Sheikhupura.Sheikhupura

On-going

Schemes10.000 7.500 0.833 0.625 0.417 67% 79% Work in Progress

383 1986Rural Drainage & PCC Scheme UC Kurlkey

District Sheikhupura.Sheikhupura

On-going

Schemes10.000 5.000 1.667 1.250 0.834 67% 58% Work in Progress

384 1987Rural Drainage & PCC Scheme UC Mallian Kalan

District Sheikhupura.Sheikhupura

On-going

Schemes15.000 7.500 2.500 1.875 1.250 67% 58% Work in Progress

385 1988Rural Water Supply & Drainage Scheme Murady

Kalan, ShiekpuraSheikhupura

On-going

Schemes95.246 20.000 1.121 0.841 0.561 67% 22% Work in Progress

386 1989 Construction of Sewerage and PCC at Bucheki

Town.Nankana Sahib

On-going

Schemes195.998 164.782 3.333 2.500 1.667 67% 85% Work is in progress.

387 1990Provision of Sewerage System at Warburton Town

Nankana Sahib.Nankana Sahib

On-going

Schemes130.000 61.000 3.333 2.500 1.667 67% 48% Work is in progress.

388 1991Provision of Rural Drainage / PCC Scheme for 16

Nos. of Union Councils in , District SheikhupuraNankana Sahib

On-going

Schemes50.000 32.599 3.333 1.500 0.667 44% 67% Work is in progress.

389 1992PCC and drainage scheme Thieng More /Illah

abad, Tehsil Chunian, District KasurKasur

On-going

Schemes256.672 89.991 6.667 5.000 3.334 67% 36% Work in Progress

390 1993 Construction of Sullage Carrier at Chah

Kalalanwala, Tehsil Pattoki, District KasurKasur

On-going

Schemes88.300 36.983 6.667 5.000 3.334 67% 46% Work in Progress

391 1994Const. of Soling Nullah, PCC etc. Union Council

Chirrawan, Tehsil & District Kasur Kasur

On-going

Schemes30.000 27.991 0.669 0.502 0.335 67% 94% Work in Progress

392 1995

Const. of Soling, Nullah PCC etc. Badian, Rai

Kalan, Khurd, Baddar Pur and adjoining abadies,

Tehsil Kasur

KasurOn-going

Schemes30.000 24.991 1.669 1.252 0.835 67% 86% Work in Progress

393 1996Const. of Soling, Nullah, PCC etc. Katlohi, Wadara

and adjoining abadies, Tehsil & District Kasur Kasur

On-going

Schemes30.000 24.999 1.667 1.250 0.834 67% 86% Work in Progress

394 1997 Construction of PCC and Tuff Tile Phoolnagar

Phase-II, Tehsil Pattoki, District Kasur Kasur

On-going

Schemes188.416 30.350 10.000 7.500 5.000 67% 19% Work in Progress

395 1998

Rural Drainage PCC Brick pavement Schemes

Rao Khan wala and Beroon Rao Khan Wala and

Adjoining Abadies Tehsil & District Kasur

KasurOn-going

Schemes77.000 34.995 8.333 6.250 4.167 67% 51% Work in Progress

396 1999Rural Drainage PCC Scheme Dholan District

Kasur.Kasur

On-going

Schemes114.588 99.662 4.975 3.731 2.488 67% 89% Work in Progress

397 2000Rural Drainage Scheme Sarhali Kalan & Adjoining

Abadies, Tehsil & District Kasur.Kasur

On-going

Schemes94.174 66.977 9.063 6.797 4.532 67% 76% Work in Progress

Page 24: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

398 2001

Water Supply & Drainage Scheme Nathey Jagir,

Lakhankay Abadies, Kamogill, Mega Jatt, Sardar

Mill & Choudharian Wala.

KasurOn-going

Schemes101.853 98.860 0.998 0.749 0.499 67% 98% Work in Progress

399 2002Provision of PCC & drainage Scheme Habib ababd

District KasurKasur

On-going

Schemes99.000 20.000 5.000 3.750 2.500 67% 23% Work in Progress

400 2003Rural Drainage Scheme Baggiana, kamogil

Jahuggian, dhinasing & Baroon AbadiesKasur

On-going

Schemes90.000 20.000 3.333 2.500 1.667 67% 24% Work in Progress

401 2004Rural Drainage Scheme Nathay Khasla Sardar

Mill, Garden Adda & Chohdry Jhlar & dhanaKasur

On-going

Schemes90.000 20.000 6.667 5.000 3.334 67% 26% Work in Progress

402 2005Rural Drainage Scheme Khanko more Chakoki

Chak No 04, Madarkhai Kasur

On-going

Schemes95.000 19.995 6.667 5.000 3.334 67% 25% Work in Progress

403 2006Rural Drainage PCC Scheme Theh Shaikham and

Adjoining Abadies District Kasur.Kasur

On-going

Schemes97.400 90.282 2.371 1.778 1.186 67% 94% Work in Progress

404 2007Rural Drainage & PCC Scheme Bhamba Kalan &

Khurd and Adjoining Abadies District Kasur.Kasur

On-going

Schemes95.000 77.499 5.834 4.376 2.917 67% 85% Work in Progress

405 2008Rural Drainage & PCC Scheme Bohar and

Adjoining Abadies District Kasur.Kasur

On-going

Schemes81.000 62.466 6.172 4.629 3.086 67% 81% Work in Progress

406 2009Rural Drainage & PCC Scheme Mudke UC District

Kasur.Kasur

On-going

Schemes97.014 75.826 6.667 5.000 3.334 67% 82% Work in Progress

407 2010Rural Drainage Scheme Baroon Raja Jang &

Adjoining Abadies, Tehsil & District Kasur.Kasur

On-going

Schemes99.998 74.698 3.333 2.500 1.667 67% 76% Work in Progress

408 2011

Rural drainage Scheme Hanjray Kalan & Allied

Abadies, Khudian, Bhaseen, Dello Multani,

Wander, Jagu Wal Tehsil Pattoki District Kasur

KasurOn-going

Schemes67.952 49.988 5.984 2.988 1.492 50% 76% Work in Progress

409 2012Rural drainage scheme Hardo Sahari, District

KasurKasur

On-going

Schemes87.235 60.798 20.000 16.500 11.500 70% 83% Work in Progress

410 2013 Rural Drainage Scheme Qadiwind KasurOn-going

Schemes99.677 61.497 5.000 3.750 2.500 67% 64% Work in Progress

411 2014Rural Drainage Scheme, Lakhankey, Tehsil &

District Kasur.Kasur

On-going

Schemes76.899 67.976 2.974 2.231 1.487 67% 90% Work in Progress

412 2015Rural PCC & Drainage Scheme Green Kot and

Ibrahimabad & Adjoining Abadies District Kasur.Kasur

On-going

Schemes75.000 64.963 3.343 2.507 1.672 67% 89% Work in Progress

413 2016Rural PCC & Drainage Scheme Handal and Rawal

Jhangar & adjoining abadies District Kasur.Kasur

On-going

Schemes69.000 60.768 2.741 0.685 0.000 0% 88% Work in Progress

414 2017Rural PCC & Drainage Scheme Khara and

Wadana & adjoining abadies District Kasur.Kasur

On-going

Schemes50.000 39.406 3.530 2.648 1.765 67% 82% Work in Progress

415 2018Rural PCC & Drainage Scheme Ramthaman and

Matta & adjoining abadies District Kasur.Kasur

On-going

Schemes74.724 65.000 3.241 0.810 0.000 0% 87% Work in Progress

416 2019Rural PCC & Drainage Scheme Zafarkey and

Ghanikey & adjoining abadies District Kasur.Kasur

On-going

Schemes50.000 47.306 0.898 0.674 0.449 67% 96% Work in Progress

417 2020Laying of Tuff Tiles / Sewerage and Sullage Carrier

in Left Over Streets in Ward No.1 to 50 City OkaraOkara

On-going

Schemes47.436 24.999 3.333 2.500 1.667 67% 56%

Date of AA 06.03.2017, Date of TS 11.03.2017,

Date of Invitation of Tender ,01.05.2017, Date of

Receipt of Tender,02.05.2017, Date of work

Order.10.05.2017, Date of completion As per PC-

I.30.06.2018 , Anticipated date of completion,

30.06.2019, Funds Release on 20-07-2018

Projected Population 409924 Person.

Page 25: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

418 2021Drainage schemes and soling work at UC 103

Depalpur District OkaraOkara

On-going

Schemes28.107 12.598 4.836 1.227 0.000 0% 45%

Date of AA 23.03.2016, Date of TS 25.03.2016,

Date of Invitation of Tender 16.05.2016, Date of

Receipt of Tenders 17.05.2016 , ( No Tender

Received), Date of Re-Invitation of Tender

11.06.2016, Date of Receipt of Tenders,13.06.2016,

Date of work Order 24.06.2016, Date of completion

As per PC-I. 18.06.2017, Anticipated date of

completion,30.06.2019,Re-Appropreation (-) 2.400

Projected Population 51130 Person, Work is ini

progress.(TPV Awaited) The scope of work has

been completed in saving due to compitative rates.

419 2022Drainage Schemes and soling work at UC 105

Depalpur District OkaraOkara

On-going

Schemes27.990 21.521 1.080 0.270 0.000 0% 77%

Date of AA 23.03.2016, Date of TS 25.03.2016,

Date of Invitation of Tender 16.05.2016, Date of

Receipt of Tenders 17.05.2016 ,( No Tender

Received), Date of Re-Invitation of Tender

11.06.2016, Date of Receipt of Tenders,13.06.2016,

Date of work Order 18.06.2016, Date of completion

As per PC-I. 18.06.2017, Anticipated date of

completion,30.06.2019, Re-Appropreation (-) 0.540

Projected Population 51398 Person, Work is ini

progress.(TPV Awaited) The scope of work has

been completed in saving due to compitative rates.

420 2023Rural water Supply & Sewerage Drainage

Scheme, Behlolpur, Tehsil Depalpur, Okara.Okara

On-going

Schemes19.075 18.063 0.326 0.245 0.163 67% 96%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work

Order.02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion, 30-06-

2019 Funds Release on 20-07-2018 Projected

Population 24422 Person.

421 2024

Rural water Supply & Sewerage Drainage

Scheme, Arrora Mian Khan, Tehsil Depalpur,

Okara.

OkaraOn-going

Schemes28.303 22.499 1.934 1.451 0.967 67% 83%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work

Order.02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

30.06.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

422 2025Rural water Supply & Sewerage Drainage

Scheme, Bhai Rao Key, Tehsil Depalpur, Okara.Okara

On-going

Schemes15.441 11.056 1.460 1.095 0.730 67% 76%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work Order

02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

31.12.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

423 2026Rural water Supply & Sewerage Drainage

Scheme, Bhukan, Tehsil Depalpur, Okara.Okara

On-going

Schemes25.728 19.496 2.076 1.557 1.038 67% 80%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender,25.05.2017, Date of

Receipt of Tenders, 26.05.2017, Date of work

Order.02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

30.06.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

424 2027Rural water Supply & Sewerage Drainage

Scheme, Jhunjh Kalan, Tehsil Depalpur, Okara.Okara

On-going

Schemes25.728 22.607 1.039 0.779 0.520 67% 90%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work

Order.02.06.2017, Date of completion As per PC-

I.31.12.2017, Aniticipated date of completion, 30-06-

2019 Funds Release on 20-07-2018 Projected

Population 24422 Person.

425 2028

Rural water Supply & Sewerage Drainage

Scheme, Kot Shah Mushtaq, Tehsil Depalpur,

Okara.

OkaraOn-going

Schemes22.049 21.029 0.340 0.255 0.170 67% 96%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work Order

02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion, 30-06-

2019 Funds Release on 20-07-2018 Projected

Population 24422 Person.

426 2029Rural water Supply & Sewerage Drainage

Scheme, Lalay Wala, Tehsil Depalpur, Okara.Okara

On-going

Schemes21.017 18.798 0.398 0.299 0.199 67% 90%

Date of AA- 08.03.2017, Date of TS-20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work

Order.02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

31.12.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

427 2030

Rural water Supply & Sewerage Drainage

Scheme, Phularwa Wazirkey, Tehsil Depalpur,

Okara.

OkaraOn-going

Schemes23.747 18.351 1.797 1.348 0.896 66% 81%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work

Order.02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

31.12.2019 Funds Release on 20-07-2018 Projected

Population 24422 Person.

Page 26: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

428 2031Rural water Supply & Sewerage Drainage

Scheme, Shah Pur, Tehsil Depalpur, Okara.Okara

On-going

Schemes19.862 18.978 0.294 0.221 0.147 67% 96%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work Order

02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

31.12.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

429 2032Rural water Supply & Sewerage Drainage

Scheme, Shinwal, Tehsil Depalpur, Okara.Okara

On-going

Schemes16.746 14.842 0.633 0.475 0.317 67% 91%

Date of AA 08.03.2017, Date of TS 20.03.2017,

Date of Invitation of Tender 25.05.2017, Date of

Receipt of Tenders 26.05.2017, Date of work Order

02.06.2017, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

31.12.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

430 2033Rural water Supply and Drainage Scheme,

Jaithpur DepalpurOkara

On-going

Schemes20.215 19.350 0.288 0.216 0.144 67% 96%

Date of AA 03.08.2016, Date of TS 20.03.2017,

Date of Invitation of Tender 11.10.2016, Date of

Receipt of Tenders 13.10.2016, Date of work Order

17.11.2016, Date of completion As per PC-

I.31.12.2017, Anticipated date of completion,

31.12.2019, Funds Release on 20-07-2018

Projected Population 10309 Person

431 2034

Rural Drainage Scheme Tuff Tiles PCC

Sewerage and Soling, 3SP, 43SP, Khurpy 44SP

Waltoya Matan Wala Amliya Key Suhag, Nihal

Muhar, Mahlo sheikhu, Mahant Darshan Nama

Jindida, District Okara

OkaraOn-going

Schemes97.984 95.372 0.868 0.651 0.433 67% 98%

Date of AA 31.08.2016, Date of TS 22.11.2016,

Date of Invitation of Tender 09.12.2016, Date of

Receipt of Tenders 10.12.2016, Date of work

Order.05.01.2017, Date of completion As per PC-

I.30.06.2018 , Anticipated date of completion,

30.06.2019, Funds Release on 20-07-2018

Projected Population 24422 Person.

432 2035 Sewerage Scheme in Sahiwal City SahiwalOn-going

Schemes27.844 22.271 0.748 0.561 0.500 89% 82%

Date of AA 22.02.2017, Date of TS 24.02.2017,

Date of receipt of tender 20.03.2017, Date of Work

Order 03.04.2017 , Date of completion as per PC-1

30.06.2018 , Anticipated date of completion

30.06.2019 subject to availablity of balance funds,

Work in progress.

433 2036Sewerage Scheme Sahiwal City, City Bund Road,

LBDC, High Street & Girls College RoadSahiwal

On-going

Schemes167.605 74.784 10.000 7.500 7.000 93% 49%

Date of AA 10.01.2017, Date of TS 03.03.2017,

Date of Pre-qualification 11.04.2017 , Date of

receipt of tender 17.04.2017, Date of Work Order

15.05.2017, Date of completion as per PC-1

30.06.2019 , Date of completion as per agreement

30.06.2019, Anticipated date of completion

30.06.2019 subject to availablity of balance funds,

Work in progress.

434 2037

Provision of Sewerage / Drainage / Street

Pavements, etc in Chak No. 147/EB Tehsil

Arifwala District Pakpattn

PakpattanOn-going

Schemes72.933 50.997 4.155 3.116 2.852 92% 74%

Date of A.A= 31.08.2016, Date of T.S= 09.09.2016,

Date of Prequalification = 05.01.2017, Date of

receipt of tenders = 23.01.2017, Date of work

order= 30.01.2017, Date of completion as per PC-

1= 30.06.2018, Date of completion as per

agreement= 30.06.2018, No. of beneficiaries=

14050 persons, Funds released by FD =

03.08.2018,Funds online = 13.08.2018,Disposal

station completed and made functional and handed

over to CBO.Work in progress.

435 2038Provision of Sewerage / Drainage Scheme Chak

No. 64/EB, Arifwala, District Pakpattan.Pakpattan

On-going

Schemes36.218 26.920 3.099 2.324 2.100 90% 80%

Date of A.A= 16.03.2017, Date of T.S= 20.03.2017,

Date of invitation of tenders=16.05.2017, Date of

receipt of tenders = 20.05.2017, Date of work

order= 24.05.2017, Date of completion as per PC-

1= 30.06.2018, Date of completion as per

agreement= 30.06.2018, No. of beneficiaries= 5749

persons, Funds released by FD = 03.08.2018,Funds

online = 13.08.2018,Work in progress.

436 2039 Rural Sewerage/Drainage Scheme 38/EB Arifwala PakpattanOn-going

Schemes32.095 13.986 3.333 2.500 1.667 67% 49%

Date of A.A= 13.10.2016, Date of T.S= 25.10.2016,

Date of invitation of tenders=18.11.2016, Date of

receipt of tenders = 10.12.2016, Date of work

order= 02.01.2017, Date of completion as per PC-

1= 30.06.2018, Date of completion as per

agreement= 30.06.2018, No. of beneficiaries=

14825 persons, Funds released by FD = 03.08.2018

,Funds online = 13.08.2018,Scheme made

functional. Work in progress.

437 2040Rural Drainage Nizam Wala Nawab Pur Road

District Multan Multan

On-going

Schemes19.295 14.295 1.667 0.416 0.000 0% 74%

1. Date of AA 09.03.2015 (16.05.2016) 2. Date of

T.S 15.05.2015 3. Dated of Prequalification __ 4.

Date of invitation of tender 24.03.2015 5. Date of

Receipt of tenders 25.03.2015 6. Date of work order

29.05.2015 7. Date of Completion as per PC-l

08.03.2016 8. Anticipated date of completion

30.06.2019 9. Date of released of funds 03.08.2018.

24.01.2019 10. No. of beneficiaries 2768 persons.

Scheme completed. Rs. 0.416 million proposed for

re-appropriation.

Page 27: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

438 2041Rural Drainage Scheme Sewra Chok Adjoining

Abadies Mouza Mubarak Pur Taj Pur SandilaMultan

On-going

Schemes99.890 89.890 3.333 2.500 1.667 67% 92%

1.Date of AA 09.03.2015 2.Date of T.S 21.04.2015

3.Dated of Prequalification 28.01.2015 4.Date of

invitation of tender 27.04.2015 5.Date of Receipt of

tenders 02.05.2015 6.Date of work order 02.06.2015

7.Date of Completion as per PC-l 08.03.2016 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 46964 persons. Work is in progress

439 2042Sewerage Drainage Scheme Matotli Qaiserpur

ShujabadMultan

On-going

Schemes46.000 35.000 3.667 2.750 1.834 67% 80%

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date

of Pre-Qualification: 30.09.2016 4. Date Invitation of

Tender: 01.11.2016 5. Date of Receipt of Tender:

02.11.2016 6. Date of Award: 10.11.2016 7. Date of

Completion as per PC-I: 09.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

Benificiary= Persons. Work is in progress

440 2043Rural Sewerage Drainage Scheme Chah Rattay

wala Mouza Jangal Barirah District MultanMultan

On-going

Schemes28.800 22.792 1.667 1.250 0.834 67% 82%

1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of

Prequalification 12.03.2016 4.Date of invitation of

tender 07.04.2016 5.Date of Receipt of tenders

09.04.2016 6.Date of work order 27.05.2016 7.Date

of Completion as per PC-l 26.11.2016 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 8253 Persons. Work is in progress

441 2044 Rural Sewerage Drainage Scheme Mill Sadiqabad MultanOn-going

Schemes87.080 75.000 4.027 3.020 3.012 100% 90%

1. Date of A.A: 27.10.2016 2. Date of T.S: - 3. Date

of Pre-Qualification: 30.09.2016 4. Date Invitation of

Tender: 01.11.2016 5. Date of Receipt of Tender:

02.11.2016 6. Date of Award: 18.11.2016 7. Date of

Completion as per PC-I: 17.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 10.No. of Benificiary= 23659

Persons. Work is in progress

442 2045Rural Sewerage Drainage Scheme Mouza

Jahangirabad MultanMultan

On-going

Schemes46.400 41.400 1.667 1.250 0.834 67% 91%

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010

3.Dated of Prequalification - 4.Date of invitation of

tender 30.01.2010 5.Date of Receipt of tenders

15.03.2010 6.Date of work order 20.03.2010 7.Date

of Completion as per PC-l 08.03.2013 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 2250 persons. Work is in progress

443 2046Rural Sewerage Drainage Scheme Pakkay Wala

Anayat Pur Mahota Tehsil and District MultanMultan

On-going

Schemes29.930 25.833 1.167 0.875 0.584 67% 88%

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date

of Pre-Qualification: - 4. Date Invitation of Tender:

09.11.2016 5. Date of Receipt of Tender:

10.11.2016 6. Date of Award: 16.12.2016 7. Date of

Completion as per PC-I: 15.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

Benificiary= Persons. Work is in progress

444 2047Rural Sewerage Drainage Scheme Saddiqabad

Hirawat and Yaray wala District MultanMultan

On-going

Schemes22.840 20.937 0.515 0.386 0.258 67% 93%

1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of

Prequalification 12.03.2016 4.Date of invitation of

tender 07.04.2016 5.Date of Receipt of tenders

09.04.2016 6.Date of work order 01.06.2016 7.Date

of Completion as per PC-l 31.11.2016 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 25285 Persons. Work is in progress

445 2048Rural Sewerage Scheme Chah Sunna Wala

Multan.Multan

On-going

Schemes13.360 8.887 1.490 1.118 0.745 67% 72%

1.Date of AA 25.03.2017 2.Date of T.S 01.04.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 20.04.2017 5.Date of Receipt of tenders

21.04.2017 6.Date of work order 23.05.2017 7.Date

of Completion as per PC-l 22.07.2017 8. Anticipated

date of completion 30.04.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 4648 persons. Work is in progress

446 2049 Rural Sewerage Schemes Ambala MultanOn-going

Schemes50.000 44.336 1.714 1.286 0.857 67% 90%

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date

of Pre-Qualification: 30.09.2016 4. Date Invitation of

Tender: 01.11.2016 5. Date of Receipt of Tender:

02.11.2016 6. Date of Award: 10.11.2016 7. Date of

Completion as per PC-I: 09.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

Benificiary= Persons. Work is in progress

Page 28: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

447 2050

Rural Drainage, Sewerage, Solding and Tuff Tiles

Scheme Gardezpur, Dhandho, Bagrain Ghangi,

Amanullah Shah Wains & Marha, District Multan

MultanOn-going

Schemes7.000 3.635 1.078 0.270 0.000 0% 52%

1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated

of Prequalification - 4. Date of invitation of tender

15.05.2017 5. Date of Receipt of tenders

16.05.2017 6. Date of work order 31.05.2017 7.

Date of Completion as per PC-l 30.07.2017 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018. 24.01.2019 10. No.

of beneficiaries=111527 persons. Scheme

completed in saving. Rs. 0.270 million proposed for

re-appropriation.

448 2051

Rural Drainage, Sewerage Scheme Mithu Shrqi,

Basti Mithu Gharbi, Basti Dad Shah Moosa

Muqeempur, District Multan

MultanOn-going

Schemes7.000 3.921 1.012 0.271 0.018 7% 56%

1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated

of Prequalification - 4. Date of invitation of tender

15.05.2017 5. Date of Receipt of tenders

16.05.2017 6. Date of work order 31.05.2017 7.

Date of Completion as per PC-l 30.07.2017 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018. 24.01.2019 10. No.

of beneficiaries=111527 persons. Scheme

completed in saving. Rs. 0.253 million proposed for

re-appropriation.

449 2052 Rural Drainage, Sewerage Scheme Basti

Dodwpur, Basti Shahpur, District MultanMultan

On-going

Schemes6.000 3.464 0.802 0.201 0.000 0% 58%

1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated

of Prequalification - 4. Date of invitation of tender

15.05.2017 5. Date of Receipt of tenders

16.05.2017 6. Date of work order 31.05.2017 7.

Date of Completion as per PC-l 30.07.2017 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018. 24.01.2019 10. No.

of beneficiaries=111527 persons. Scheme

completed in saving. Rs 0.201 million proposed for

re-appropriation.

450 2053 Rural Sewerage Scheme Basti Laar MultanOn-going

Schemes50.000 35.000 1.000 0.750 0.500 67% 71%

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date

of Pre-Qualification: 30.09.2016 4. Date Invitation of

Tender: 01.11.2016 5. Date of Receipt of Tender:

02.11.2016 6. Date of Award: 12.11.2016 7. Date of

Completion as per PC-I: 11.05.2018 8. Anticipated

Date of Completion: 30.06.2018 9.Date of released

of funds 23.11.2018 24.01.2019 10.No. of

Benificiary= Persons. Work is in progress.

451 2054Sewerage, Tuff Tiles in Remaining Portion of Gaily

Wal City.Lodhran

On-going

Schemes62.170 28.077 6.667 5.000 3.800 76% 51%

1. Date of A.A: 27-08-2016. 2. Date of T.S: 26-09-

2016 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 14-11-2016 5. Date of Receipt

of Tender: 15-11-2016 6. Date of Award: 08-12-

2016 7. Date of Completion as per PC-I: 31-12-2017

8. Anticipated Date of Completion: 10-03-2018

9.Date of released of funds 03.08.2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

32835 Persons. Work is in Progress

452 2055Tuff Tiles & Sewerage Scheme for remaining

portion of Gogran City.Lodhran

On-going

Schemes45.795 32.717 4.359 2.269 1.112 49% 74%

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-

2016 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 14-11-2016 5. Date of Receipt

of Tender: 15-11-2016 6. Date of Award: 24-11-

2016 7. Date of Completion as per PC-I: 30-06-2017

8. Anticipated Date of Completion: 23-01-2018

9.Date of released of funds 03.08.2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

16528 Persons. Scheme is functional & handed

over to the community. Rs. 1.157 million proposed

for re-appropriation

453 2056Provision / Laying of Sewer Lines in Missing Areas

of Khanewal City including new and old Azafi AbadKhanewal

On-going

Schemes100.000 55.895 6.667 5.000 4.769 95% 61%

1. Date of A.A: 27.08.2016 2. Date of T.S:

25.10.2016 3. Date of Pre-Qualification: 22.10.2016

4. Date of Invitation of Tender: 29.11.2016 5. Date

of Receipt of Tender: 05.12.2016 6. Date of Work

order: 15.12.2016 7. Date of Completion as per PC-

I: 30.06.2018 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: --------- 11

No. of beneficiaries 379227 Persons Work is in

progress.

454 2057Provision of Drains, Soling Culverts etc to different

abadies of PP-212, Tehsil Kabirwala, KhanewalKhanewal

On-going

Schemes40.000 22.000 6.000 4.500 4.029 90% 65%

1. Date of A.A: 25.04.2017 2. Date of T.S:

04.05.2017 3. Date of Pre-Qualification: ---------- 4.

Date of Invitation of Tender: 03.06.2017 5. Date of

Receipt of Tender: 05.06.2017 6. Date of Work

order: 07.06.2017 7. Date of Completion as per PC-

I: 30.06.2018 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

10. Reason of Slow Moving: -------- 11 No. of

beneficiaries 7819 Persons Work in progress.

Page 29: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

455 2058Drainage Scheme Chak No.88/10-R District

KhanewalKhanewal

On-going

Schemes10.000 3.000 2.333 1.750 1.319 75% 43%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 09.11.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 5120 Persons Work is in

progress.

456 2059Provision of Tuff Pavement in Gaggo Mandi /

Dharian / Chak No. 187/EB Vehari

On-going

Schemes49.970 28.688 3.333 2.500 1.870 75% 61%

1. Date of A.A: 21.02.2017 2. Date of T.S:

25.02.2017 3. Date of Pre-Qualification: 4. Date of

Invitation of Tender: 20.05.2017 5. Date of Receipt

of Tender: 22.05.2017 6. Date of Work order: 7.

Date of Completion as per PC-I: 21.05.2019 8.

Anticipated Date of completion: 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of beneficiaries

13005 Persons Work is in progress.

457 2060Rehabilitation of Sewerage & Drainage Scheme

Machiwal, Tehsil and District Vehari.Vehari

On-going

Schemes22.396 19.450 0.982 0.737 0.670 91% 90%

1. Date of A.A: 27-08-2016 2. Date of T.S:

02.09.2016 3. Date of Pre-Qualification: ____ 4.

Date Invitation of Tender: 06.12.2016 5. Date of

Receipt of Tender: 07.12.2016 6. Date of Award:

22.12.2016 7. Date of Completion as per PC-I:

21.12.2017 8. Anticipated Date of Completion:

30.06.2018 9.Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: NIL 11 No.

of beneficiaries 11435 Persons Work is in progress.

458 2061Execution of Forty (40) Misc. Development

Schemes in NA-167, District Vehari Vehari

On-going

Schemes27.500 21.681 1.000 0.750 0.570 76% 81%

1. Date of A.A: 21.01.2013 2. Date of T.S:

22..01.2013 3. Date of Pre-Qualification: 4. Date

Invitation of Tender: 14.02.2013 5. Date of Receipt

of Tender: 16.02.2013 6. Date of Award: 26.02.2013

7. Date of Completion as per PC-I: 26.05.2013 8.

Anticipated Date of Completion: 30.06.2013 9.Date

of released of funds 23.11.2018 24.01.2019 10.

Reason of Slow Moving: - 11. No. of Beneficiary=

Persons Work is in progress.

459 2062 Provision of Sewerage & Tuff Tiles for Dajal City RajanpurOn-going

Schemes120.100 34.990 28.367 21.275 14.184 67% 41% "• Date of A.A = 05.11.2016

460 2063

Construction of Drain, Brick Pavement Sullage

Carrier Culverts, Tuff Tile Muhammad Pur Dewan

Rajanpur

RajanpurOn-going

Schemes29.990 25.694 1.000 0.750 0.000 0% 86% "• Date of A.A = 17.12.2014

461 2064Construction of Drain, Brick Pavement Sullage

Carrier Culverts, Tuff Tile Fazilpur RajanpurRajanpur

On-going

Schemes50.000 25.952 1.000 0.750 0.500 67% 53% "• Date of A.A = 17.12.2014

462 2065

Comprehensive Sewerage / Drainage / Soling /

PCC / Tuff Tile scheme at Sanawan Town, District

Muzaffargarh (Remaining Portion)

MuzaffargarhOn-going

Schemes25.000 22.152 0.949 0.712 0.425 60% 90% "• Date of A.A 22-09-2016

463 2066

Construction of Drain Brick Pavement, RCC

Culverts, VR Bridge and Sullage Carrier in UC

Wainse No. 76 Tehsil Jatoi

MuzaffargarhOn-going

Schemes42.270 10.000 10.757 8.068 5.279 65% 36% Date of AA 31.7.2017

464 2067

Construction of Drain Brick Pavement, RCC

Culverts, VR Bridge and Sullage Carrier in UC

Bairband No. 84 Tehsil Jatoi

MuzaffargarhOn-going

Schemes43.350 10.000 11.117 8.338 5.300 64% 35% Date of AA 31.7.2017

465 2068

Construction of Drain Brick Pavement, RCC

Culverts, VR Bridge and Sullage Carrier in UC

Kotla Gamoon No. 77 Tehsil Jatoi

MuzaffargarhOn-going

Schemes43.730 10.000 11.243 8.432 5.400 64% 35% Date of AA 31.7.2017

466 2069Sewerage / Drainage Scheme for Rangpur

MuzaffargarhMuzaffargarh

On-going

Schemes241.100 48.442 56.667 42.500 27.450 65% 31% "• Date of A.A 22.9.2016

467 2070 Rural Sewerage / drainage scheme Shah Jamal MuzaffargarhOn-going

Schemes68.504 63.220 1.000 0.500 0.000 0% 92%

Funds received on 12.11.2018 (Rs.0.500 M)

Balance funds of Rs.4.540 M released on

10.12.2018 for clearance of liabilities of the

contractor as per Court Order which is under

process.

468 2071

Rural Sewerage/Drainage Scheme Dhori Adda &

Adoining Abadies Chak No. 426AB & 438/TDA

(Revised)

LayyahOn-going

Schemes198.000 63.732 25.010 18.758 12.505 67% 39% • Date of AA = 25.10.2014

Page 30: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

469 2072

Rural Drainage/Sewerage & Nallian Mosan Shah,

Mongarh, Ahsin & Waddeh wali UC Wara Sehran

Tehsil Karoor Lal Essen District Layyah

LayyahOn-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% • Date of AA = 29.07.2017

470 2073Sewerage scheme Chak No. 110/TDA, Tehsil

Karor, District LayyahLayyah

On-going

Schemes30.000 20.395 3.202 2.402 1.600 67% 73% • Date of AA = 22-09-2016

471 2074Sewerage scheme Chak No. 229/TDA, Tehsil

Karor, District LayyahLayyah

On-going

Schemes30.000 15.000 5.000 3.750 2.500 67% 58% • Date of AA = 22-09-2016

472 2075Sewerage scheme Chak No. 251/TDA, Tehsil

Karor, District LayyahLayyah

On-going

Schemes30.000 14.952 5.016 3.762 2.505 67% 58% • Date of AA = 22-09-2016

473 2076Construnction of soling & drain/Nallian in UC

Baseera Tehsil Karoor District Layyah NA-181Layyah

On-going

Schemes30.000 17.200 4.267 3.200 2.134 67% 64% • Date of AA = 29.07.2017

474 2077 Construction of Sewerage chak no. 63,DB. BahawalpurOn-going

Schemes18.845 14.803 1.340 1.455 1.100 76% 84%

Date of AA. 08.08.2016. Date of T.S. 13.10.2016.

Tender received on 14-11-2016. Date of award-03-

01-2017. Date of completion=02-12-2017.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Funds Rs.0.450 million provided through re-

appropriation dated 19.10.2018.Work is in progress.

475 2078

Provision of Sewerage / Tuff Tile in Basti Jhangara

Sharqi, Mouza Jhangara Sharqia, Union Council

Bahawalpur Ghalvan, Tehsil Ahmedpur Sharqia,

District Bahawalpur.

BahawalpurOn-going

Schemes29.895 26.878 1.003 0.752 0.500 66% 92%

Date of AA. 08.08.2016. Date of T.S. 13.10.2016.

.Tender received on 14-11-2016. Date of award-03-

01-2017. Date of completion=02-12-2017.

Anticipated date of completion 30.06.2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

476 2079 Sewerage & Tuff Tile Jamalpur BahawalpurOn-going

Schemes29.526 22.718 2.269 1.702 1.130 66% 81%

Date of AA. 08.08.2016. Date of T.S. 13.10.2016.

.Date of receipt of Tender 14.11.2016. Date of

award 30.11.2016. Date of completion 29.10.2017.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

477 2080 Sewerage / Drainage Scheme, Chak No. 110/DB BahawalpurOn-going

Schemes29.725 27.964 0.133 0.100 0.067 67% 94%

Date of A.A= 18-08-2015. Date of T.S= 28-08-2015.

Date of receipt of tenders = 08-03-2016. Date of

work order= 18.04.2016. . Date of completion as per

agreement=17.04.2017. Anticipated date of

completion = 30.06.2019. Date of receipt of funds

by F.D. 20.07.2018 & 11.01.2019. Work is in

progress.

478 2081Sewerage Scheme Chak no. 15/Ford wah, Tehsil

Hasilpur.Bahawalpur

On-going

Schemes15.616 8.287 1.855 0.891 0.428 48% 56%

Date of AA. 08.08.2016. Date of T.S. 13.10.2016.

.Date of receipt of tender 14-11-2016. Date of award

15-12-2016. Date of completion 14-11-2017.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Funds Rs.0.500 million surrendered vide Chief

Engineer(S),PHED Lahore No.72-78/B(4) dated

10.01.2019.Work is in progress.

479 2082 Rural Sewerage Scheme 17/F.W BahawalpurOn-going

Schemes25.000 13.450 3.833 2.075 1.110 53% 58%

Date of AA. 08.08.2016. Date of T.S. 13.10.2016.

Date of Receipt of tender 14.11.2016. Date of award

15.12.2016. Date of completion 14.11.2017.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Funds Rs.0.800 million surrendered vide Chief

Engineer(S),PHED Lahore No.72-78/B(4) dated

10.01.2019.Work is in progress.

480 2083 Rural Sewerage Scheme Basti Chohan BahawalpurOn-going

Schemes21.500 10.625 3.510 2.633 1.750 66% 58%

Date of AA. 08.08.2016. Date of T.S. 13.10.2016.

.Date of Receipt of tender 14.11.2016. Date of

award 15.12.2016. Date of completion 14.11.2017/.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress. . .

481 2084

Construction of Sewerage Drainage Schemes

Abadi Jodheka QasimKa Chak Sarkari Bagar Wala

Khoo Chavek, Toba Balochan Tehsil & Distt.

Bahawalnagar

BahawalnagarOn-going

Schemes99.996 29.990 23.335 17.501 15.000 86% 45%

Date of AA. 21.10.2016. Date of T.S. 26.10.2016.

Date of Tender 12.12.2016. Funds released by FD

04-07-2017 & 06-10-2017.Date of receipt of tender

14-12-2016 . Date of award 19-01-2017. Date of

completion 18-12-2017. Anticipated date of

completion 30-06-2019. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Page 31: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

482 2085Sewererage and Drainage Scheme Maroot Tehsil

Fortabbas District BahawalnagarBahawalnagar

On-going

Schemes120.980 52.857 22.665 16.999 16.990 100% 58%

Date of AA. 15-10-2015 . Date of TS. 22-02-2016.

Prequalification of the contractor=22-03-2016. Date

of invitation of tenders=24-03-2016. Date of receipt

of tenders = 07-04-2016. Date of award= 30-04-

2016. Date of completion as per agreement=29-04-

2018.Expected date of completion 30-06-2019. Date

of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

483 2086Comprehensive Urban / Draiange Sewerage

Scheme Doonga BoongaBahawalnagar

On-going

Schemes72.683 69.236 1.000 0.500 0.500 100% 96%

Date of AA. 08.02.2011. Date of T.S. 08.02.2011.

Date of award. 11.03.2011. Date of completion

30.06.2012. Anticipated date of completion 30-06-

2019. Funds released by FD on 12-11-2018 &

11.01.2019 .Work is in progress.

484 2087Provision of water Supply /Sewerage scheme for

MC Tranda Saway Khan, Tehsil & District RYK

Rahim Yar

Khan

On-going

Schemes121.000 32.590 29.466 22.100 14.700 67% 39%

Date of AA(DDWP)=28-10-2016..Date of T.S.

13.02.2017..Tenders received on 13-03-2017 ..

Date of work awarded .25-04-2017. .Date of

completion 30-06-2019. .Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019..Funds of 3rd Quarter

is not credited/onlined to the District Accounsts

office RYK..Work is in progress.

485 2088 Construction of Sewerage Open Drain in

Chachran Sharif

Rahim Yar

Khan

On-going

Schemes97.240 52.148 14.698 11.024 8.847 80% 63%

Date of A.A= 26-02-2016.Date of T.S= 05-05-

2016.Date of prequalification. 03-08-2016..Date of

tender received on 10-10-2016.Date of award= 16-

11-2016.Date of completion= 15-04-2018.Expected

date of completion 30-06-2019. Date of receipt of

funds by F.D. 20.07.2018 & 11.01.2019. Work is in

progress.

486 2089Urban water Supply / Sewerage Scheme for City

Tranda Muhammad Pannah

Rahim Yar

Khan

On-going

Schemes121.750 49.980 23.917 17.938 13.989 78% 53%

Date of AA =17-09-2016.Date of TS=23-11-

2016.Prequalification of contractors 05-01-2017.

Date op receipt of Tenders 06-02-2017..Date of

work awarded 17.03.2017..Date of completion

16.09.2018..Expected date of completion. 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

487 2090Sewerage & Tuff tiles in UC 36, 37, 38, 40, 41, 42

and 71 under Rahim Yar Khan

Rahim Yar

Khan

On-going

Schemes35.000 20.000 1.000 0.750 0.601 80% 59%

Date of AA. 24.10.2016..Date of T.S. 29.11.2016.

Tenders received on 16-01-2017 .Date of work

awarded 08-02-2017. Date of completion 07-08-

2017. Anticipated date of completion 30-06-

2019.Funds released by FD on 11.01.2019. Work is

in progress.

488 2091

Sewerage Scheme R.Y.Khan City with Treatment

Plant-Construction of Intermediate Pumping

Station Near Niazi Colony & Installation of Force

Main

Rahim Yar

Khan

On-going

Schemes481.825 421.239 2.000 1.500 1.187 79% 88%

Date of A.A= 30-12-2015..Date of RAA= 23-09-

2016.Date of T.S. 30.09.2016..Date of

prequalification= 03-08-2016.Date of tender= 21-10-

2016.Date of work awarded=19-12-2016.Date of

completion=18-05-2017.Anticipated date of

completion: 30.06.2019.Funds released by FD on

11.01.2019. The scheme is completed and

functional. Libility of Contractor is yet to be cleared.

Estimate submitted to Chief Engineer(S), PHED

Lahore for revised A.A from the P&D Department.

489 2092Provision of Sewerage in Chak No 141JB

Khokhran Tehsil & District ChiniotChiniot

On-going

Schemes31.350 25.000 2.117 1.588 1.059 67% 83%

1. Date of AA = 20.10.2016 2. Date of TS =

25.10.2016 3.Date of Award of work 17.12.2016

4.Dated of Released Funds 5. No. of Beneficiaries =

1891 Persons Funds Released upto 24.01.2019 by

the Chief Engineer (South) PHED Lahore and work

is in progress.

490 2093Sewerage Scheme, PCC Slab Soling in Bhowana

city ChiniotChiniot

On-going

Schemes77.000 20.363 8.333 6.250 4.100 66% 32%

1. Date of AA = 19.09.2017 2. Date of TS =

25.10.2017 3. Date of Work Order = 09.12.2017

4.Dated of Released Funds 03.11.2017 Funds

Released upto 24.01.2019 by the Chief Engineer

(South) PHED Lahore and work is in progress.

491 2094Bulk water Supply Project from River Jhelum to

Murree Rawalpindi

On-going

Schemes4,254.770 1,068.566 1.000 0.750 0.000 0% 25% Work in Progress.

492 2095 water Supply Scheme Fazaiya Housing Colony

Turnol Tehsil & District RawalpindiRawalpindi

On-going

Schemes373.073 338.322 11.584 8.688 5.792 67% 92%

Work suspended at site due to change of intake site

by SPD Department, now NOC granted by SPD and

revised estiamte under process of approval.

493 2096

Improvement of Water Supply System in Murree

under PPP Rehabilitate, Operate and Transfer

(ROT Mode).

RawalpindiOn-going

Schemes24.500 14.500 3.333 2.500 0.000 0% 59% Funds Released by FD on 31st July 2018.

494 2097Installation of water Supply scheme for residents

of Fateh Jang attockAttock

On-going

Schemes469.913 400.994 10.000 7.500 5.000 67% 86%

A.A Date 21.10.2014.T.S Date 10.11.2014.Date of

Start of Scheme 22.01.2015.Date of Completion of

Scheme 30.06.2019.Work is in progress.

Page 32: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

495 2098Rehabilitation of Urban water Supply Scheme

Kallar Kahar District ChakwalChakwal

On-going

Schemes73.390 61.987 3.801 2.851 1.901 67% 87%

Date of A.A 17.09.2015. Date of T.S.Date of Start

11.02.2016.Date of completion 30.06.2019.Full

funds utilized. Scheme is short funded.

496 2099 Est. of W.S. Scheme Talagang ChakwalOn-going

Schemes94.580 82.608 3.931 2.948 1.966 67% 89%

Date of A.A 17.09.2015 .Date of T.S

07.10.2015.Date of Start 26.01.2016.Date of

completion 30.06.2019.Full funds utilized. Scheme

is short funded.

497 2100 water Supply Scheme Chakwal Based on Khai

DamChakwal

On-going

Schemes1,018.160 341.465 33.333 9.488 0.506 5% 34%

"Date of A.A 03.04.2014.Date of T.S

16.04.2014.Date of Start 30.05.2014.Date of

completion 30.06.2021.Phase i of the scheme has

been completed. 2 Cusec water from Khai Dam is

being supplied to M.C Chakwal since 01-2018. The

amended A.A has been submitted in P&D for

according approval. The tendering process of Phase-

II will be started after getting amended approval.

498 2101Installation of 02 no. of Tubewells in choa Saiden

Shah, District ChakwalChakwal

On-going

Schemes18.460 17.730 0.730 0.548 0.365 67% 98%

Date of A.A 21.11.2017. Date of T.S

23.11.2017.Date of Start 12.01.2018. Date of

completion 30.06.2018.Work completed. However

further funds are required to clear the liability

against the above rates of awarded work.

499 2102Water Suplly Scheme based on Naroomi Dhan

Spring Phase IIJhelum

On-going

Schemes298.854 286.982 3.953 2.965 1.977 67% 97%

"A.A: 10-04-14.T.S: 16-4-14 .Date of

Commencement 24-10-2014.Work is in Progress.

Scheme is partially operational.

500 2103Lying of water Supply Pipelines in D Block Old

Satellite Town & Millat Abad Sargodha CitySargodha

On-going

Schemes5.386 4.139 0.416 0.312 0.312 100% 83%

Date of A.A 27.08.2016, Date of T.S 04.09.2016,

Date of Award 22.02.2017, Scheduled date of

Completion is 30.06.2018, Date of Commencement,

22.02.2017, Funds released on 30.07.2018, Funds

on-lined on 30.07.2018. R/Main / D-System 9395-

Rft laid. P.C.C Slab 3128-Cft laid. RCC Sewer 12"

i/d 531-Rft laid. Work in progress.

501 2104Augmentation of water Supply Scheme Sargodha

based on Canal water Supply Sargodha Phase ISargodha

On-going

Schemes268.210 197.713 16.667 12.500 9.628 77% 77%

Date of A.A 28.02.2014, Date of T.S 30.04.2014,

Date of Award 28.06.2014, Scheduled date of

Completion is 30.06.2017, Date of Commencement,

28.06.2014, Funds released on 30.07.2018, Funds

on-lined on 30.07.2018. 21-No. tube wells

completed out of provision 22-No. 21-No. Pump

Houses 90% completed out of provision 22-No. 31-

Sets of Pumping machinery arranged. R/Main / D-

System 122534-Rft laid out of provision 125047-Rft.

5-No. GSTs 90% completed out of 05-No. 05-No.

Staff Quarter 85% completed. Work in progress.

502 2105 water Supply Scheme for Farooq Colony,

Imtiazabad Abad Sargodha CitySargodha

On-going

Schemes98.971 65.957 6.667 5.000 5.000 100% 72%

Date of A.A 11.08.2015, Date of T.S 14.10.2015,

Date of Award 16.01.2016, Scheduled date of

Completion on 30.06.2017, Date of

Commencement, 16.01.2016, Funds released on

30.07.2018, Funds on-lined on 30.07.2018. 06-No.

trial bore, tube well bore & pump house completed

out of provision 06-No. 08-Sets of Pumping

machinery arranged. R/Main / D-System 40803-Rft

laid & 360-Rft arranged out of provision 112510-Rft.

02-No. GSTs 90% completed. Work in progress.

503 2106Comprehensive Urban water Supply and

Sewerage Scheme Khushab CityKhushab

On-going

Schemes358.444 342.647 5.261 2.946 2.940 100% 96%

Date of A.A 08.10.2009 Date of T.S 05.11.2009

Date of award 06.01.2010. Date of completion

30.06.2019 Scheme is functional and handed over

to Municipal Committee Khushab.v

504 2107Comprehensiver Urban water Supply and

Sewereage Scheme JauharabadKhushab

On-going

Schemes586.987 462.440 33.333 26.000 19.500 75% 82%

Date of A.A 08.10.2009 Date of T.S 05.11.2009

Date of award 11.08.2010 Date of completion

30.6.2019 All 10 No. Tubewell with pump house,

pumping machinary and GST 800000 Gln

completed. Work of laying of water supply pipe line

is in Progress. All 3 Nos disposal works completed

and functional. Work lying lataral sewer is in

progress.

505 2108Replacement of Old water Supply Pipeline in

Jauharabad.Khushab

On-going

Schemes90.000 21.943 3.333 2.500 1.870 75% 26%

Date of AA 27.08.2016 Date of TS 01.11.2016 Date

of award 06.02.2017 Date of Completion 30.06.2020

Work is in progress.

506 2109Replacement of Old water Supply Pipeline in

Khushab City.Khushab

On-going

Schemes130.000 44.202 16.667 12.500 9.800 78% 42%

Date of AA 27.08.2016 Date of TS 01.11.2016 Date

of award 06.02.2017 Date of Completion.

30.06.2020 Work is in progress.

Page 33: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

507 2110Comprehensive water Supply Sewerage Scheme

MianwaliMianwali

On-going

Schemes494.444 462.274 6.667 4.300 2.634 61% 94%

Revised Date of A.A. 16-01-2014 Date of Revised

T.S.08-08-2014, Date of 2nd Revised A.A. 04-11-

2015, Date of 2nd Revised T.S.10-12-2015, Date of

Start of Work.03-12-2009, Remarks. Tube-

Well=8/8, Pump House=8/8, Pumping

Machinery=9/9, Rising Feeding Main=12"i/d A.C=

921/940, 10" i/d A.C= 11959 /11960, 8" i/d

PVC=26535 /26541, 6"i/d PVC= 30244 /30591,4"i/d

PVC= 40592/40583, 3"i/d PVC= 137262/137106,

OHR = 3/3, Chlorinator = 8/8, T/Line 5/8, RCC

Sewer=42"i/d= 480/480, 36"i/d =8385/8385, 30"i/d

=2159/2159, 27"i/d= 8694/8694, 24"i/d=12415

/12415, 21"i/d= 14020/14020, 18"i/d= 23255/23357,

15"i/d= 28803 /29337, 12"i/d=137955 /137918,

9"i/d=31456/31456, Sullage Carrier=8500/8500,

Oxidation Pond=2/2. Work is in progress.

508 2111Water Supply Scheme Iskandarabad, District

Mianwali.Mianwali

On-going

Schemes4.498 1.509 0.996 0.273 0.024 9% 34%

Date of A.A. 11-08-2015, Date of T.S. 15-08-2015,

Date of Start of Work 28-10-2015, Remarks. Rising

Main=4"i/d PVC= 1960/1960, D/System=4"i/d G.I=

0/50, 3"i/d PVC=6000/6000, 4"i/d PVC= 400/400,

6"i/d PVC 1900/1900, O.H.R=1/1 , Repair of

P/Machinery, R/F Main old=1/1. Scheme completed

in saving Fund proposed to be surrendered.

509 2112Comprehensive water Supply Scheme Kamalia

CityToba Tek Singh

On-going

Schemes426.211 307.725 25.000 18.750 13.450 72% 75%

1-Date of A.A 16.10.2014 2- Date of T.S 28.11.2014

3-Date of Prequalification 08.12.2014 4-Date of

invitation of tenders 07.12.2014 5- Date of Receipt

of tenders 23.12.2014 6- Date of work order

31.12.2014 7- Date of completion as per PC-I

15.10.2017 8- Anticipated date of completion

30.12.2017 9- No. of Beneficiary - 298364 Person

10-Funds Released by F.D 03.08.2018 &

24.01.2019. 11-Re-appropriation of funds (+/-) Work

in progress.

510 2113 Urban water Supply Scheme Gojra Phase II Toba Tek SinghOn-going

Schemes532.942 125.000 33.333 25.000 16.600 66% 27%

1-Date of A.A 01.01.2016 2- Date of T.S 30.03.2016

3-Date of Prequalification -31.03.2016 4-Date of

invitation of tenders 17.04.2016 5- Date of Receipt

of tenders 25.04.2016 6- Date of work order -

18.05.2016 7- Date of completion as per PC-I

11.11.2018 8- Anticipated date of completion

11.11.2018 9- No. of Beneficiary - 393651 Person

10-Funds Released by F.D 03.08.2018 &

24.01.2019. 11- Re-appropriation of funds(+/-)

.Work in progress.

511 2114

Provision of Brick Pavements, Drains, Tuff Tiles,

Water Supply, Play Grounds, Public Parks, etc., in

the Rural and Urban Areas of Tehsil Kamalia and

Tehsil Pir Mehal District T.T. Singh

Toba Tek SinghOn-going

Schemes245.000 120.000 16.667 12.500 8.200 66% 52%

1-Date of A.A 23.10.2017 2- Date of T.S

17.11.2017. 3-Date of Prequalification 4-Date of

invitation of tenders 05.12.2017 5- Date of Receipt

of tenders 07.12.2017 6- Date of work order

12.12.2017 7- Date of completion as per PC-I 8-

Anticipated date of completion 30.06.2018.9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

512 2115Provision of water Supply and Drainage Scheme

for Dinga City Distt Gujrat.Gujrat

On-going

Schemes197.050 138.416 10.000 7.500 5.000 67% 73%

A.A Date =5.9.2014.T/Well installed=4

Nos.functional= 3 Nos .PVC Pipe Laid=170825

Rft.PCC= 156462 Cft. S.C=7719 Rft. Soling=6069

sft, Tuff paver=19570 sft.1 No OHR 50000 Gln

completed.Work in porgress.

513 2116 Construction of water Supply System Gujrat GujratOn-going

Schemes742.379 487.503 33.333 10.000 1.667 17% 66%

A.A Date =10.02.2009.17 Nos Tube wells are

functional and Handed over to M.C Gujrat .3 Nos

OHR's are functional. 763906 Rft pipes laid &

functional.House Connection= 2155 Nos. 2 Nos

contracts are rescinded while 1 No has been

reinstated.

514 2117Extension of Urban water Supply and drainage

scheme Azafi Abadies in Kharian CityGujrat

On-going

Schemes122.416 79.911 5.000 3.750 2.500 67% 67%

A.A Date =23.9.2014.T/Well installed= 3 Nos

Functional= 2 Nos.PVC Pipe Laid=36194

Rft.PCC=104022 Cft. S.C=5986 Rft.Tuff Paver=

74392 Sft Work in porgress.

515 2118Extension of Urban water Supply and drainage

scheme Sarai Alamgir City.Gujrat

On-going

Schemes159.603 122.667 8.432 11.324 9.216 81% 83%

A.A Date =23.9.2014.T/Well installed= 2 Nos.PVC

Pipe Laid=77073 Rft.PCC= 328408 Cft. S.C=550

Rft.Work in porgress.

516 2119 water Supply & Sewerage Scheme in PP 114 GujratOn-going

Schemes47.981 22.984 8.332 6.249 4.166 67% 57%

Drain Type-I=23952 Rft. PCC. 1:2:4=91393

Cft.Work in progress.

517 2120 water Supply scheme Lalamusa and Rural Areas GujratOn-going

Schemes197.321 40.000 5.000 3.750 2.500 67% 22%

A.A Date =23.02.2017.3 T/Well installed.Pipe

8"=400 Rft, 4"=2000 Rft, 3'=1000 rft. Work in

porgress.

Page 34: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

518 2121Improvement / Extension of Urban water Supply

Sewerage & Drainage Scheme M.B.Din City

Mandi

Bahauddin

On-going

Schemes345.995 114.976 16.667 14.700 10.534 72% 36%

* A.A Date. 25.03.2016* T.S Date. 29.03.2016* Start

Date 24.04.2016* Completion date 23.04.2019. *

Work in progress.

519 2122Improvement / Extension of Urban water Supply

Sewerage & Drainage Scheme Malikwal City

Mandi

Bahauddin

On-going

Schemes197.956 102.347 5.000 3.750 2.500 67% 53%

* A.A Date. 07.01.2016* T.S Date. 15.01.2016.*

Start Date 01.03.2016* Completion date

28.02.2019. * Work in progress.

520 2123 water Supply Scheme Chot Dhirian, M.B.DinMandi

Bahauddin

On-going

Schemes75.000 64.263 3.333 1.100 0.267 24% 86%

* A.A Date. 07.09.2015* T.S Date. 10.09.2015* Start

Date 17.12.2015.* Completion date 30.06.2019.*

Work in progress

521 2124Rehabilitation / Augmentation of Urban water

Supply Scheme Narowal City Narowal

On-going

Schemes185.411 98.401 13.333 3.733 0.395 11% 53%

A.A Date.30.9.2014T.S Date.10.11.2014*Start Date

23.12.2014*Completion date 30.06.2019.Work in

progress. Fund not received on spending end yet

522 2125Urban water Supply Scheme Kahna Phase I and

IILahore

On-going

Schemes199.405 126.661 6.667 4.500 2.834 63% 65%

Scheme in nearing completion, 2-Nos. Tube wells

are put operational. Balance funds are required to

complete the scheme

523 2126Provision of Open water Supply Scheme

FerozwalaSheikhupura

On-going

Schemes175.524 125.000 3.333 2.500 1.667 67% 72% Work in Progress

524 2127 Urban water Supply Scheme Muridkey SheikhupuraOn-going

Schemes450.000 219.000 16.667 12.500 8.334 67% 51% Work in Progress

525 2128 water Supply Scheme Chunian Amended KasurOn-going

Schemes228.855 220.454 2.672 1.534 0.866 56% 97% Work in Progress

526 2129Urban water Supply and Sewerage/ Drainage

Scheme Phool NagarKasur

On-going

Schemes475.472 468.331 2.380 1.185 0.590 50% 99% Work in Progress

527 2130 water Supply, Drainage & PCC Scheme Outside

Khudian District KasurKasur

On-going

Schemes176.173 172.172 1.334 1.001 0.667 67% 98% Work in Progress

528 2131Extension / Improvement of water Supply Scheme

Southern City, Okara.Okara

On-going

Schemes864.000 701.498 26.667 20.000 13.334 67% 83%

Date of A.A (Revised) 22.01.2013, Date of T.S

(Revised) 28.01.2013, Date of Prequalification

11.09.2012, Date of invitation of tenders

16.02.2013, Date of Receipt of tenders 16.02.2013,

Date of work order 21.02.2013, Date of completion

as per PC-I 13.05.2015, Anticipated date of

completion 30.06.2019, No. of Beneficiary - 69380

Person, Funds Release on 20-07-2018 Work is in

progress.

529 2132

Provision and Installation of six (06) Water

Purification Plants at Matotli Qaisarpur, Shah Mosa

Shah Pipulwala, Basti Mahram Rukn Hatti, Chak

No.13- Faiz, Chak Sardarpur & Basti Nawan

Shehar, Tehsil Shujabad, District Multan

MultanOn-going

Schemes10.722 4.461 2.087 1.007 0.486 48% 46%

1. Date of AA 05.12.2016 2. Date of T.S - 3. Dated

of Prequalification - 4. Date of invitation of tender

01.02.2017 5. Date of Receipt of tenders

03.02.2017 6. Date of work order 11.02.2017 7.

Date of Completion as per PC-l 10.06.2017 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018. 24.01.2019 10. No.

of beneficiaries=111527 persons. Scheme

completed in saving. Rs 0.521 million proposed for

re-appropriation.

530 2133Rehabilitation of water Supply and Sewerage

Schemes in Tulamba City.Khanewal

On-going

Schemes106.963 68.841 6.667 5.000 4.519 90% 69%

1. Date of A.A: 17.09.2015 2. Date of T.S:

09.11.2015. 3. Date of Pre-Qualification: 18.01.2016

4. Date of Invitation of Tender: 16.02.2016 5. Date

of Receipt of Tender: 17.02-2016 6. Date of Work

order: 05.03.2016 7. Date of Completion as per PC-

I: 16-09-2017 8. Anticipated Date of completion: 30-

06-2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ---- 11 No.

of beneficiaries 53394Persons Work is in progress.

531 2134Urban water Supply & Sewerage Scheme

Khanewal CityKhanewal

On-going

Schemes191.232 147.091 14.714 11.036 10.971 99% 83%

1. Date of A.A: 05.09.2014 2. Date of T.S:

28.10.2014 3. Date of Pre-Qualification: 18.12.2014

4. Date of Invitation of Tender: 19.01.2015 5. Date

of Receipt of Tender: 20.01.2015 6. Date of Work

order: 18-02-2015 7. Date of Completion as per PC-

I: 04-09-2016 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: -------- 11

No. of beneficiaries 358569 Persons Work is in

progress.

Page 35: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

532 2135Comprehensive water Supply & Sewerage

Scheme for Luddan City District Vehari.Vehari

On-going

Schemes99.982 78.470 6.970 5.228 3.885 74% 82%

1. Date of A.A: 11.01.2016. 2. Date of T.S:

25.02.2016 3. Date of Pre-Qualification: 11.04.2015

4. Date of Invitation of Tender: 24.03.2016 5. Date

of Receipt of Tender: 02.04.2016 6. Date of Work

order. 14.04.2016 7. Date of Completion as per PC-

I: 10.01.2018 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ----- 11. No.

of Beneficiary 20316 Persons Work is in progress.

533 2136Comprehensive water Supply & Sewerage

Scheme for Vehari city.Vehari

On-going

Schemes332.198 308.130 8.000 6.000 4.540 76% 94%

1. Date of A.A: 11.04.2016. 2. Date of T.S:

29.04.2016. 3. Date of Pre-Qualification:

11.04.2015. 4. Date of Invitation of Tender:

18.05.2016. 5. Date of Receipt of Tender:

28.05.2016. 6. Date of Award: 15.06.2016 G-I.

17.06.2016 G-II 7. Date of Completion as per PC-I:

14.06.2018 8. Anticipated Date of completion:

30.06.2018 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------ 11.

No. of Beneficiary= 140193 Persons Work is in

progress.

534 2137Comprehensive water Supply Scheme Taunsa

Sharif

Dera Ghazi

Khan

On-going

Schemes195.973 149.673 15.433 11.575 8.218 71% 81% "• Date of A.A = 12.12.2014

535 2138Rehabilitaion of Urban water Supply Scheme Fort

Minroe

Dera Ghazi

Khan

On-going

Schemes257.064 243.790 4.397 3.298 1.154 35% 95% "• Date of A.A =01.04.2015

536 2139Comprehensive Extension/Rehab. of Urban water

Supply Scheme Rojhan and adjoining abadiesRajanpur

On-going

Schemes49.569 25.000 8.190 6.143 4.095 67% 59% "• Date of A.A = 22.09.2016

537 2140Enhancement of Supply of Water for Rojhan City

District RajanpurRajanpur

On-going

Schemes30.000 20.000 3.333 2.500 1.667 67% 72% "• Date of A.A = 22.09.2016

538 2141Urban water Supply

Scheme,Muzaffargarh(Ammended) (PSDP)Muzaffargarh

On-going

Schemes419.689 398.484 4.110 3.083 2.054 67% 95% "• Date of A.A 10.11.2008

539 2142Rehabilitation and Agumentation of water Supply

Scheme, BahawalpurBahawalpur

On-going

Schemes282.533 254.014 3.805 1.654 0.700 42% 90%

Date of AA :29-11-2006. Date of TS :08-01-2007.

Date of RAA: 17-04-2014. Date of RTS. 17-04-

2014. Date of receipt of tender.14-02-2007. Date of

work order:17-03-2007. Date of completion as per

agreement 16-03-2008.Anticipated date of

completion 30-06-2019.Date of receipt of funds by

F.D 20.07.2018 & 11.01.2019.Funds Rs.1.200

million surrendered vide Chief Engineer(S),PHED

Lahore No.72-78/B(4) dated 10.01.2019 Three out

of four portions are completed and handed over to

TMA on 30-04-2014. Balance one portion at trust

colony, Model Town-B is under test operation.

540 2143 Urban water Supply Scheme for Hasilpur BahawalpurOn-going

Schemes100.000 76.466 7.844 5.883 3.900 66% 80%

Date of AA(DDWP)=24-10-2016. Date of TS=19-01-

2017. Prequalification of the contractors=05-01-

2017. Date of receipt of tender 27-02-2017 . Date of

award=03-03-2017. Date of completion. 02-03-2018.

Expected date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

541 2144

water Supply Scheme of Chak Sarkari and

Adjoining Abadies Tehsil Minchinabad District

Bahawalnagar

BahawalnagarOn-going

Schemes10.827 9.283 1.544 1.158 1.060 92% 96%

Date of AA. 08.08.2016. Date of T.S. 27.09.2016.

Date of receipt of tender 02.11.2016. Date of award.

30.11.2016. Date of completion 29.07.2017.

Anticipated date of completion 30-06-2019. Funds

released by FD on 12-11-2018 & 11.01.2019.Work

is in progress.

542 2145Water Supply Scheme Doonga Boonga, District

Bahawalnagar.Bahawalnagar

On-going

Schemes11.168 0.915 3.418 0.891 0.820 92% 16%

Date of AA 09.03.2010. Date of T.S 13.03.2010.

Date of award 14.05.2010. Date of completion

13.05.2011. Anticipated date of completion 30-04-

2019. Scheme remained unfunded during 2011-12.

Funds released on 20-07-2018 & 11.01.2019.

Scheme completed in saving. Excess funds

Rs.1.673 million surrendered dated 19.10.2018.

543 2146Replacement & Up-Gradation of Urban Water

Supply Scheme Bahawalnagr Bahawalnagar

On-going

Schemes214.155 211.310 0.947 0.441 0.441 100% 99%

Date of AA 11.08.2009. Date of T.S 31.10.2009.

Date of award 13.01.2010. Date of completion

30.06.2014. Scheme remained unfunded during

2013.14. Date of receipt of funds by F.D.

20.07.2018 & 11.01.2019. Scheme completed in

saving. Excess funds Rs.0.269 million surrendered

dated 19.10.2018.

Page 36: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

544 2147 water Supply Scheme Sadiqabad, Tehsil

Sadiqabad, District R.Y. Khan.

Rahim Yar

Khan

On-going

Schemes692.527 454.150 67.779 50.834 40.405 79% 71%

A.A issued on 12-05-2014. .Date of T.S. 26-05-

2014. .Date of prequalification=21-07-2014.Date of

receipt of tenders = 22-12-2014. .Date of work

order= 03-01-2015..Date of completion as per

agreement 30.06.17.Anticipated date of completion

30.06.2019.No. of beneficiaries=405864

persons.Date of receipt of funds by F.D. 20.07.2018

& 11.01.2019. Work is in progress.

545 2148

Urban Water Supply Scheme Bismillah Town,

Thalli Road, Near Madrassa Kulyat ul Islam City

Rahim Yaar Khan

Rahim Yar

Khan

On-going

Schemes30.000 9.949 6.667 5.000 3.760 75% 46%

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.

.Date of receipt of Tender: 07.09.2017..Date of

award: 31.10.2017..Date of completion:

31.1.2018..Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

546 2149Const. of Water Supply Scheme Tranda Sway,

R.Y.Khan.

Rahim Yar

Khan

On-going

Schemes2.610 0.603 0.669 0.252 0.252 100% 33%

Date of AA 18.08.2015..Date of T.S 14.09.2015.

.Date of award 07.01.2016..Date of completion

30.06.2016..Scheme remained unfunded during

2016-17..2018. Date of receipt of funds by F.D.

20.07.2018 & 11.01.2019. Scheme completed & put

in to operation.

547 2150Urban Sewerage / Drainage & PCC for Fateh Jang

City, Tehsil Fateh Jhang, District attock.Attock

On-going

Schemes99.948 80.231 5.341 5.006 3.671 73% 84%

A.A Date 09.01.2016.T.S Date 22.01.2016.Date of

Start of Scheme 09.03.2016.Date of Completion of

Scheme 30.06.2019.Work is in progress.

548 2151Urban Sewerage / drainage scheme for Hassan

Abdal City, Hassan Abdal, District attock Attock

On-going

Schemes195.317 167.071 8.336 7.232 5.148 71% 88%

A.A Date 28.08.2014.T.S Date 01.09.2014.Date of

Start of Scheme 26.01.2015.Date of Completion of

Scheme 30.06.2019.ork is in progress.

549 2152

Providing / laying of Sewerage, Construction /

Rehabilitation of storm water channel in Choa

Saiden Shah District Chakwal (Phase-I) (3rd

Revised)

ChakwalOn-going

Schemes239.300 225.507 2.429 1.822 1.215 67% 95%

Date of A.A 29.03.2016 (2nd Rev). Date of T.S

07.04.2016 (Rev).Date of Start 21.02.2014.Date of

completion 30.06.2019.Date of scheme almost

completed only contractor liabilities are to be clear.

550 2153 Urban Sewerage Scheme, Talagang City. ChakwalOn-going

Schemes99.667 80.853 5.067 2.800 1.530 55% 83%

Date of A.A 22.01.2015 (3rd Rev).Date of T.S

06.02.2015.Date of Start 13.04.2015.Date of

completion 30.06.2019.Work is in progress.

551 2154 Construction of Sewerage and Drianage Scheme

Sohawa CityJhelum

On-going

Schemes30.000 17.456 4.167 3.125 2.084 67% 65%

Date of A.A 26-08-2016.Date of T.S 30-09-

2016.Work awarded on 24-01-2017.Work in

progress

552 2155Urban Sewerage Scheme Jhelum with Treatment

Plant District JhelumJhelum

On-going

Schemes539.592 382.102 33.333 25.000 16.667 67% 74%

"Date of A.A .14-09-2009.Date of Revise A.A 29-03-

2016.Date of T.S 24-10-2009.Date of Revis T.S 31-

05-2016.Date of Commencement 17-08-2016.Date

of Completion 15-08-2018.Scheme has been

Revised and Administratively approved vide.

No.SO(PH-S)9-16/2015 (Jhelum)

553 2156Comprehensive Urban Sewerage Scheme Bhalwal

ColoniesSargodha

On-going

Schemes232.641 216.687 4.972 1.757 0.513 29% 93%

Date of A.A 25.06.2009, Revised Date of A.A

31.01.2014, 2nd Revised Date of A.A 19.09.2016,

Date of T.S 29.06.2009, Date of 2nd Revised T.S

30.09.2016, Date of Award 24.11.2009 &

04.12.2009, Scheduled date of Completion on

12.2010, Revised date of Completion 30.06.2018,

Date of Commencement, 24.11.2009 & 04.12.2009,

Funds released on 30.07.2018, Funds on-lined on

30.07.2018.Scheme completed in saving,

operational and handed over to Municipal

Committee Bhalwal.

554 2157Rehabilitation of Sewerage Scheme Kot Momin

District Sargodha Sargodha

On-going

Schemes152.397 32.809 3.333 0.893 0.059 7% 22%

Date of A.A 27.08.2016, Date of Revised A.A

15.06.2017, Date of T.S 10.10.2016, Date of Award

16.11.2016, Scheduled date of Completion is

15.11.2017, Date of Commencement, 16.11.2016,

Funds released on 30.07.2018, Funds on-lined on

30.07.2018. Drain Type-I, II & III 4807-Rft,

constructed. Land acquisition for construction of

disposal works is in process.

555 2158 Construction of Sewerage PCC Soling Resoling

Bashir Colony Sargodha CitySargodha

On-going

Schemes5.177 4.283 0.298 0.224 0.224 100% 87%

Date of A.A 27.08.2016, Date of T.S 04.09.2016,

Date of Award 22.02.2017, Scheduled date of

Completion is 30.06.2018, Date of Commencement,

22.02.2017, Funds released on 30.07.2018, Funds

on-lined on 30.07.2018. RCC Sewer 12" to 24" i/d

1845-Rft laid, PCC Slab 2257-Cft laid. Work in

progress

Page 37: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

556 2159Costruction of Sewerage / PCC / soling / Sullage

Carrier Mulsim Town, Usman Park, Shiraz Park, Sargodha

On-going

Schemes5.927 4.376 0.500 0.375 0.375 100% 80%

Date of A.A 27.08.2016, Date of T.S 04.09.2016,

Date of Award 22.02.2017, Scheduled date of

Completion is 30.06.2018, Date of Commencement,

22.02.2017, Funds released on 30.07.2018, Funds

on-lined on 30.07.2018. Sullage Carrier 1653-Rft

constructed Soling 1639-Cft laid. RCC Sewer 12" i/d

961-Rft laid Work in progress

557 2160 Construction of Sewerage PCC Soling in Nawab

Colony Aziz Colony and Ghani Park Sargodha CitySargodha

On-going

Schemes5.430 4.789 0.214 0.161 0.161 100% 91%

Date of A.A 27.08.2016, Date of T.S 04.09.2016,

Date of Award 22.02.2017, Scheduled date of

Completion is 30.06.2018, Date of Commencement,

22.02.2017, Funds released on 30.07.2018, Funds

on-lined on 30.07.2018. RCC Sewer 12" i/d 1504-Rft

laid, PCC Slab 11550-Cft laid. Work in progress

558 2161Urban Drainage / PCC Flooring Scheme Miani

District SargodhaSargodha

On-going

Schemes93.181 35.964 5.000 3.750 3.750 100% 43%

Date of A.A 27.08.2016, Date of T.S 28.10.2016,

Date of Award 14.02.2017, Scheduled date of

Completion on 13.02.2018, Date of

Commencement, 14.02.2017, Funds released on

30.07.2018, Funds on-lined on 30.07.2018. 01-No.

Collecting tank completed, Sullage Carrier 23424-

Rft & Drain 2546-Rft constructed. P.C.C 27147-Cft

& Tuff Tile 22857-Sft laid Work in progress.

559 2162

Urban Sewerage Scheme for (Islam Pura, Zafar

Colony, Qartaba Town, Jauhar Colony, Sultan

Town, Shirazi park, Mujhid Colony, Ali Town,

Gilwala Including Adjacent Colonies) & Abadies of

(Yousaf park, Aziz Colony, Bashir Colony, Nawab

Colony

SargodhaOn-going

Schemes389.887 213.660 16.667 12.500 12.500 100% 58%

Date of A.A 09.06.2015, Date of T.S 17.06.2015,

Date of Award 31.07.2015, Scheduled date of

Completion is 30.07.2017, Date of Commencement,

31.07.2015, Funds released on 30.07.2018, Funds

on-lined on 30.07.2018.02-No. screening chamber,

collecting tank, pumping chamber 90% completed.

08-Sets Pumping Machinery out of 14-sets & 02-

Sets Generator arranged at site. RCC Sewer 1958-

Rft laid. RCC Box Channel 9139-Rft constructed.

Work in progress.

560 2163Sewerage and Drainage Scheme at Chak No.60

Shamali Khizarabad Ghosia Mehria ColonySargodha

On-going

Schemes60.000 49.976 3.334 2.501 2.500 100% 87%

Date of A.A 25.08.2015, Date of T.S 14.10.2015,

Date of Award 15.01.2016, Scheduled date of

Completion on 30.06.2017, Date of

Commencement, 15.01.2016, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.Drain

34406-Rft & Sullage carrier 8212-Rft constructed,

Soling 4484-Cft & PCC Slab 114865-Cft laid. work

in progress.

561 2164

Rural Drainage Scheme U.C Bhabra, U.C Halal

Pur, U.C Takhat Hazara and Adjoining Abadies

Tehsil Kot Momin District Sargodha

SargodhaOn-going

Schemes10.000 4.985 1.667 1.250 0.968 77% 60%

"Date of A.A 02.01.2018, Date of T.S 13.02.2018,

Date of Award 20.03.2018, Scheduled date of

Completion on 30.06.2019, Date of

Commencement, 20.03.2018, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

562 2165

Rural Drainage Scheme U.C Mouzamabd, U.C

Jalla Makhdoom, U.C Mateela including Adjoining

Abadies Tehsil Kot Momin District Sargodha

SargodhaOn-going

Schemes10.000 5.000 1.667 1.251 0.946 76% 59%

"Date of A.A 02.01.2018, Date of T.S 13.02.2018,

Date of Award 24.03.2018, Scheduled date of

Completion on 30.06.2019, Date of

Commencement, 24.03.2018, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

563 2166

Rural Drainage Scheme U.C Ghula Pur, U.C Chak

No.11/SB, U.C Garhi Kala and Adjoining Abadies

Tehsil Kot Momin District Sargodha

SargodhaOn-going

Schemes10.000 4.989 1.667 1.250 1.021 82% 60%

"Date of A.A 02.01.2018, Date of T.S 13.02.2018,

Date of Award 17.03.2018, Scheduled date of

Completion on 30.06.2019, Date of

Commencement, 17.03.2018, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

564 2167

Rural Drainage Scheme U.C Mela, U.C Naseer

Pur Kalan, U.C Mustafa Abad and Adjoining

Abadies Tehsil Kot Momin District Sargodha

SargodhaOn-going

Schemes10.000 4.957 1.667 1.250 1.159 93% 61%

"Date of A.A 02.01.2018, Date of T.S 13.02.2018,

Date of Award 20.03.2018, Scheduled date of

Completion on 30.06.2019, Date of

Commencement, 20.03.2018, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

565 2168

Rural Drainage Scheme U.C Dodha, U.C Gurna,

U.C Jan Muhammad Wala, U.C Laksian, U.C

Miana Kot and Adjoining Abadies Tehsil Kot

Momin District Sargodha

SargodhaOn-going

Schemes10.000 4.989 1.667 1.251 0.981 78% 60%

"Date of A.A 02.01.2018, Date of T.S 13.02.2018,

Date of Award 20.03.2018, Scheduled date of

Completion on 30.06.2019, Date of

Commencement, 20.03.2018, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

566 2169

Rural Drainage Scheme U.C Bucha Kalan, U.C

Wan Miana, U.C Midh Ranjha and Adjoining

Abadies Tehsil Kot Momin District Sargodha

SargodhaOn-going

Schemes10.000 4.984 1.667 1.250 1.155 92% 61%

"Date of A.A 02.01.2018, Date of T.S 13.02.2018,

Date of Award 20.03.2018, Scheduled date of

Completion on 30.06.2019, Date of

Commencement, 20.03.2018, Funds released on

30.07.2018, Funds on-lined on 30.07.2018.

Page 38: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

567 2170Urban Sewerage / Drainag Scheme, Kamar

Mushani, Mianwali.Mianwali

On-going

Schemes190.611 117.953 16.667 12.500 8.320 67% 66%

Date of A.A. 05-09-2014, Date of T.S.03-10-2014,

Date of Start of Work,08-11-2014, , Remarks. RCC

Sewer=9" i/d=13629 /15205, 12"i/d= 3959/4960,

15"i/d= 8037/8695, 18"i/d= 3678/3675,

21"i/d=184/200, 24"i/d= 485/500, 27"i/d= 585/600,

30"i/d= 1106/1250, 33"i/d= 3232/3330, Screening

Chamber=1/1, Collecting Tank 25'dia= 2/2,

P/Machinery=0/4, Suction Delivery=1/1, Discharge

Sump=1/1, Generator Room=1/1, Staff

Quarter=1/1, Generator Set=1/1, Boundary

Wall=1/1, S/Carrier= 3120/4675, Out fall

Structure=0/1, S/Drain= 14933/51760, PCC Slab=

174131/294164, Electric T/Line=0/1. Work is in

progress.

568 2171Provision of PCC Slab and Sewerage Scheme in

Municipal Committee Dullay wala Bhakkar

On-going

Schemes68.340 48.098 3.333 2.500 2.500 100% 74%

Date of A.A 27.08.2016 Date of T.S 30.09.2016

Date of Commencement 28.11.2016 Date of

completion 30.06.2020

569 2172Urban Sewerage/Drainage scheme, PCC Slab &

Brick Pavement in Bhakkar CityBhakkar

On-going

Schemes833.933 39.633 50.000 37.500 25.000 67% 8%

Date of A.A 15.08.2017 Date of Amended A.A

16.12.2017 Date of T.S 07.02.2018 Date of

commencement 24.03.2018 Date of completion

30.06.2021 Work at Disposal Station is in progress.

Payment for land acquisition has been made. Target

will be acheived in the coming month.

570 2173Provision of Sewerage in Tandlianwala City District

Faisalabad Phase 1Faisalabad

On-going

Schemes100.000 69.988 9.366 7.025 4.683 67% 75%

Date of A.A 20-10-2016. Date of T.S.31-10-2016.

Work order issued on 17-12-2016. Work is in

progress. Funds released on 03.08.2018 & 24.1.19

571 2174Construction of Carpet Road (2200 feet) at Chak

No. 353/GB, District FaisalabadFaisalabad

On-going

Schemes4.000 1.000 1.000 0.750 0.750 100% 44% Funds transfer to xen Highway Divison Faisalabad.

572 2175Construction of Boundary Wall of at Football

Ground at Chak No.144/GB District Faisalabad.Faisalabad

On-going

Schemes1.500 0.500 1.000 0.750 0.750 100% 83% Funds transfer to xen Building Divison Faisalabad.

573 2176

Construction of Boundary Wall of Graveyard at

Chak No. 630/GB Abadi Rairoo, District

Faisalabad.

FaisalabadOn-going

Schemes2.099 0.500 1.000 0.750 0.750 100% 60% Funds transfer to xen Building Divison Faisalabad.

574 2177Provision of Soling /Drainage at Chak No.568/GB

Abadi Ahmad Khan District Faisalabad.Faisalabad

On-going

Schemes2.000 0.485 1.515 1.136 0.700 62% 59%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. work is in

progress.Funds released on 23.11.2018 & 24.1.19

575 2178Provision of Soling /Drainage at Abadi Bahadur

Khan District Faisalabad.Faisalabad

On-going

Schemes3.000 0.997 1.000 0.000 0.000 #DIV/0! 33%

AA issued on 15.11.2017. Tenders received on

28.11.2017. Funds received on 27-01-2018. Work

order issued on 13.12.2017. work is in progress.

Funds not yet been relased uptill now.

576 2179Provision of Soling /Drainage at UC- 51 District

Faisalabad.Faisalabad

On-going

Schemes1.000 0.499 0.501 0.376 0.250 66% 75%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. work is in

progress.Funds released on 23.11.2018 & 24.1.19

577 2180Construction of TST Road 12 feet wide4 at Abadi

Hayyat Ullah, District Faisalabad.Faisalabad

On-going

Schemes5.000 1.000 1.000 0.750 0.750 100% 35% Funds transferred to XEN High Way Division FSD.

578 2181Provision Main Drainage at UC 35 Chak

No.119/GB, District Faisalabad.Faisalabad

On-going

Schemes5.000 0.998 1.000 0.750 0.490 65% 30%

AA issued on 15.11.2017. Funds received on 23-11-

2018. Work order issued on 13.12.2017. work is in

progress.Funds released on 23.11.2018 & 24.1.19

579 2182Repair of Road (4400 feet) 01-KM at Bhagi Dhal to

Purana Wasiran, District Faisalabad.Faisalabad

On-going

Schemes3.000 0.600 1.000 0.750 0.750 100% 45% Funds transfer to xen Highway Divison Faisalabad.

580 2183Construction of TST Road at Chak No.119/GB,

District Faisalabad.Faisalabad

On-going

Schemes6.000 1.000 1.000 0.750 0.750 100% 29% Funds transfer to xen Highway Divison Faisalabad.

581 2184

Rehabilitation / Carpeting of Road (Length 4.00

KM) at Lahore Road Pull Sal to Dulchian Road to

Daand Gali, District Faisalabad.

FaisalabadOn-going

Schemes21.715 5.000 1.000 0.750 0.750 100% 26% Funds transfer to xen Highway Divison Faisalabad.

582 2185Comprehensive Sewerage/ Drainage scheme AP

Sial (Urban)Jhang

On-going

Schemes100.000 30.000 6.667 5.000 4.010 80% 34%

Date of A.A 20.10.2016 Date of T.S 24.11.2016

Date of Invitation of tenders 15.12.2016. Date of

Receipt of tender 24.12.2016 Date of work order

28.12.2016 Date of Completion As per PC-I

19.10.2019 Anticipated date of completion.

27.12.2019 No of Baneficiary 12731-Persons

Agreement Amount 96.709-Million Work is in

progress.

Page 39: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

583 2186

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 1,2,3,4,5&6 and adjoining

abadies urban area Jhang

JhangOn-going

Schemes6.000 4.000 0.667 0.500 0.390 78% 73%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

07.09.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

06.07.2018 No of Baneficiary 12731-Persons

Agreement Amount 4.961-Million Work is in

progress.

584 2187

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 13,14,15,16,17 & 18 and

adjoining abadies urban area Jhang

JhangOn-going

Schemes6.000 3.900 0.667 0.500 0.401 80% 72%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

28.09.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

06.07.2018 No of Baneficiary 12709-Persons

Agreement Amount 5.006-Million Work is in

progress.

585 2188

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 19,20,21,22,23 & 24 and

adjoining abadies urban area Jhang

JhangOn-going

Schemes6.000 4.000 0.667 0.500 0.395 79% 73%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

07.09.2017 Date of work order 07.09.2017 Date of

Completion As per PC-I 19.10.2018 No of

Baneficiary 12709-Persons Agreement Amount

5.491-Million Work is in progress.

586 2189

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 25,26,27,28,29 & 30 and

adjoining abadies urban area Jhang

JhangOn-going

Schemes6.000 3.998 0.667 0.500 0.405 81% 73%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

07.09.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

06.07.2018 No of Baneficiary 112173-Persons

Agreement Amount 5.494-Million Work is in

progress.

587 2190

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 31,32,33,34,35 & 36 and

adjoining abadies urban area Jhang

JhangOn-going

Schemes6.000 3.993 0.667 0.500 0.398 80% 73%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

08.08.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

07.05.2018 No of Baneficiary 11596-Persons

Agreement Amount 4.920-Million Work is in

progress.

588 2191

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 37,38,39,40,41,42, & 43 and

adjoining abadies urban area Jhang

JhangOn-going

Schemes7.000 5.000 0.667 0.500 0.418 84% 77%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

07.09.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

06.07.2018 No of Baneficiary 13260-Persons

Agreement Amount 6.191-Million Work is in

progress.

589 2192

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 44,45,46,47,48,49, & 50 and

adjoining abadies urban area Jhang

JhangOn-going

Schemes7.000 4.963 0.667 0.500 0.412 82% 77%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

08.08.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

07.05.2018 No of Baneficiary 13015-Persons

Agreement Amount 6.084-Million Work is in

progress.

590 2193

Construction of Sewerage, PCC Slab, Drain &

Soling at Ward NO. 7,8,9,10,11&12 and adjoining

abadies urban area Jhang

JhangOn-going

Schemes6.000 3.906 0.667 0.500 0.415 83% 72%

Date of A.A 25.03.2017 Date of T.S 28.03.2017

Date of Invitation of tenders 18.04.2017. Date of

Receipt of tender 20.04.2017 Date of work order

07.09.2017 Date of Completion As per PC-I

19.10.2018 Anticipated date of completion.

06.07.2018 No of Baneficiary 12768-Persons

Agreement Amount 5.416-Million Work is in

progress.

591 2194Extension Rehabilitation of Urban Sewerage

Scheme Karnalia City Phase IIToba Tek Singh

On-going

Schemes488.756 239.700 33.333 25.000 23.000 92% 54%

1-Date of A.A 12.11.20152- Date of T.S

25.02.20163-Date of Prequalification -07.03.20164-

Date of invitation of tenders 18.03.20165- Date of

Receipt of tenders 26.03.20166- Date of work odder

-29.04.20167- Date of completion as per PC-I

11.11.20188- Anticipated date of completion

11.11.2018 9- No. of Beneficiary - 306625 Person10-

Funds Released by F.D 03.08.2018 & 24.01.2019

11-Re-appropriation of funds(+/-) Work in progress.

Page 40: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

592 2195Extension/Rehabilitation of Urban Sewerage

Scheme Gojra Toba Tek Singh

On-going

Schemes400.000 224.900 16.667 12.500 10.000 80% 59%

1-Date of A.A 12.11.20152- Date of T.S

26.02.20163-Date of Prequalification -07.03.20154-

Date of invitation of tenders 18.03.20165- Date of

Receipt of tenders 26.03.20166- Date of work odder

-18.04.20167- Date of completion as per PC-I

11.11.20188- Anticipated date of completion

11.11.20189- No. of Beneficiary -393651 Person 10-

Funds Released by F.D 03.08.2018 & 24.01.2019.

11-Re-appropriation of funds(+/-) Work in progress.

593 2196 Urban Sewerage and Drainage Scheme Pir Mehal Toba Tek SinghOn-going

Schemes290.000 230.000 6.667 5.000 5.000 100% 81%

1-Date of A.A 16.10.20142- Date of T.S

03.12.20143-Date of Prequalification 08.12.20144-

Date of invitation of tenders 08.12.20145- Date of

Receipt of tenders 23.12.20146- Date of work order

31.12.20147- Date of Completion as per PC-I

15.10.20178- Anticipated date of completion

30.12.2018 9- No. of Beneficiary - 139496 Person

10-Funds Released by F.D 03.08.2018 1&

24.01.2019 1-Re-appropriation of funds(+/-) Work in

progress.

594 2197Improvement of Street / Roads of Rajana Town,

District T.T SinghToba Tek Singh

On-going

Schemes25.000 7.939 1.667 1.250 0.900 72% 35%

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

595 2198Provision of Laying Tuff Tile, Sewerage and

Nullahs in Gojra, District T.T.SinghToba Tek Singh

On-going

Schemes150.000 75.000 8.333 6.250 4.167 67% 53%

1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-). Work in progress.

596 2199 Construction of Sewerage Drainage Tuff tiles in

Noshera VirkanGujranwala

On-going

Schemes208.986 25.000 3.333 2.500 1.667 67% 13% Work in progress

597 2200Const of Sewerage Drainage PCC Scheme Sodhra

Talwara Tehsil WazirabadGujranwala

On-going

Schemes120.754 84.455 5.306 3.980 2.653 67% 72% Work in progress

598 2201

Provision of Sewerage & water Supply Scheme at

Ghakhar & Ladhaywala, District Gujranwala

(Revised)

GujranwalaOn-going

Schemes199.871 130.786 30.000 22.500 15.000 67% 73% Work in progress

599 2202

Sewerage / Drainage & PCC / RCC Scheme at

Rahwali including Adjoining Abadies etc,

Gujranwala.

GujranwalaOn-going

Schemes392.400 100.600 20.000 21.218 16.218 76% 30% Work in progress.

600 2203

Provision of Drainage / PCC Scheme at Tehsil

Noshera Virkan & UC Sharan Kalan, District

Gujrnawala

GujranwalaOn-going

Schemes77.000 16.846 3.333 2.500 1.667 67% 24% Work in progress.

601 2204Provision of Sanitation / Drainage in City Pindi

BhattianHafizabad

On-going

Schemes167.781 109.933 10.000 6.300 3.800 60% 68%

A.A 167.781 Date 04/04/2016 T.S. 167.77 date 16-

05-2016 work in progress Fund release but not yet

online.

602 2205Provision of Sanitation facilities in City Sukhike

MandiHafizabad

On-going

Schemes141.332 129.643 3.796 2.847 1.897 67% 93%

The work was alloted to the contractor on dt: 26-11-

2016 and contractor started the work at site .A.A

141.240 Date 06/09/2016 T.S. 142.374 date 30-09-

2016 Drain 140910 Rft, Sullage Carrier /storm water

1.5x1.5=2225 Rft 2.0x2.0=1350 Rft 2.0x2.5=2350

Rft 3.0x3.0=5878 Rft Tuff tile 60mm thick=17292

Sft 80mm thick =3200 Sft Brick Pavement/Soling =

37645 Cft, PCC 3" thick= 69726 Cft,4" thcik=56945

Cft,thick=82872 Cft, work in progress.Fund release

but not yet online.

603 2206 Urban Drainage Scheme Jalapur Bhattian HafizabadOn-going

Schemes96.640 84.870 3.884 2.913 1.940 67% 90%

The work was alloted to the contractor on dt: 26-11-

2016 and contractor started the work at site .A.A

141.240 Date 06/09/2016 T.S. 142.374 date 30-09-

2016 Drain 140910 Rft,Sullage Carrier /storm Fund

release but not yet online.

604 2207Urban Sewerage / Drianage Scheme Eastern Side

Ghari Awan & Allied Abadies Hafizabad CityHafizabad

On-going

Schemes219.535 141.081 10.000 7.500 5.000 67% 67% work in progress Fund release but not yet online.

Page 41: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

605 2208 Construction of Two Pumps Station at Old

G.T.Road Drain Gujrat.Gujrat

On-going

Schemes108.440 66.578 13.928 10.446 6.964 67% 68%

R.A.A Date =3.05.2017R.T.S date=29.9.2017.1 Nos

Screening Chamber, 1 Nos Collecting Tank 20' Dia

6set Machinery, Force main pipe i/d Dia 10"=50

Rft,12"=100 Rft, 16"=3300 Rft, 18"=400 Rft Drain

type-I=2862 Rft Sullage Carrier= 2500 Rft RCC

Sewer 15'=300 Rft,18"=346 Rft, 24"=1664 Rft

PCC=7568 Cft .work in progress

606 2209 Sewerage & water Supply Tank for Bhiki SharifMandi

Bahauddin

On-going

Schemes116.314 90.745 8.522 6.392 4.261 67% 82%

* A.A Date. 09.10.2014* T.S Date. 22.12.2014 *

Start Date 16.02.2015* Completion date

30.06.2019. * Work in progress.

607 2210Sewerage / Drainage Scheme Malikwal City,

Distt.M.B.Din

Mandi

Bahauddin

On-going

Schemes237.200 62.105 8.333 5.350 3.267 61% 28%

* A.A Date. 06.01.2016* T.S Date. 15.01.2016* Start

Date 11.03.2016* Completion date 10.03.2019.*

Work in progress.

608 2211Urban Sewerage/ Drainage PCC and Tuff Tiles in

City Phalia Tehsil Phalia District M.B.Din

Mandi

Bahauddin

On-going

Schemes270.500 27.095 10.000 7.500 5.000 67% 12%

* A.A Date. 06.09.2017* T.S Date. 24.10.2017* Start

Date. 07.01.2018* Completion date

06.01.2021.Work in progress.

609 2212Provision of Sewerage/PCC Streets/ Drain/Tuff

Tiles/Park and Janazgah District M.B.Din

Mandi

Bahauddin

On-going

Schemes75.000 55.000 6.667 5.000 3.337 67% 78%

* A.A Date. 25.08.2017* T.S Date. 06.09.2017* Start

Date. 06.01.2018* Completion date 05.01.2020*

Work in progress.

610 2213

Provision of PCC / Soling / Nullah / Street Scheme

at Adalat Garah Bashamula, Muzaffarpura,

Dhanay, phabarainawala, Gujayanwala, Ravail

pura, Stabgary, Burj / Butter etc.,Teshil & District

Sialkot

SialkotOn-going

Schemes200.000 25.000 3.333 2.500 1.667 67% 13% Work in progress.

611 2214Provision of Sewerage Drainage and and Tuff Tile

at Daska CitySialkot

On-going

Schemes100.000 30.000 3.333 2.500 1.667 67% 32% Work in progress.

612 2215

Construction of Street PCC / Tufff Tiles Drains &

Nullah Fazal Pura & adjoining Streets Sambrial

City

SialkotOn-going

Schemes80.000 49.845 3.333 2.500 1.667 67% 64% Work in progress.

613 2216

Construction of Street PCC / Tufff Tiles Drains &

Nullah in Mandi Samrial and old Sambrial Tehsil

Sambrial

SialkotOn-going

Schemes80.000 44.945 3.333 2.500 1.667 67% 58% Work in progress.

614 2217

Construction of Street PCC/Tuff Tiles Drains &

Nullah in Mohallah Rasoolpur & More Sambrial,

Tehsil Sambrial

SialkotOn-going

Schemes80.000 44.992 3.333 2.500 1.667 67% 58% Work in progress.

615 2218

Construction of Streets (Drains, PCC) Mohallah

Sharif Pur, Habib Pura, Bashir Pura, Nazir Abad

Colony and others.

SialkotOn-going

Schemes90.000 49.918 3.333 2.500 1.667 67% 57% Work in progress.

616 2219 Construction of Urban Drainage Scheme Pasrur

City, Tehsil Pasrur, District Sialkot.Sialkot

On-going

Schemes99.827 24.992 3.333 2.500 1.667 67% 27% Work in progress.

617 2220

Construction of Nallah Around Road from Uggoki

to Rai Pur Abba Baigowala Ganda Nallah Railway

Station etc. Tehsil Sambrial ,District Sialkot

SialkotOn-going

Schemes199.826 69.726 5.000 3.750 2.500 67% 36% Work in progress.

618 2221

Removal of ponds / construction of Pull and

establishment of Park at Moza Bahlor Tehsil

Pasrur, District Sialkot.

SialkotOn-going

Schemes36.043 20.643 5.133 1.283 0.000 0% 57% Scheme completed

619 2222Const of PCC / Tuff tiles of City Package Zafarwal

City Narowal

On-going

Schemes69.569 49.569 6.667 5.000 3.324 66% 76%

*Date of A.A 9.4.2016 *Date of T.S 19.4.2016 *Start

Date 6.6.2016 *Completion date 30.06.2019.Work in

progress.

620 2223Sewerage scheme for Talwandi Bhindran,

Narowal.Narowal

On-going

Schemes109.876 105.797 1.360 1.020 0.677 66% 97%

A.A Date.3.5.2014 T.S Date.23.5.2014 *Start Date

25.08.2014*Completion date 30.06.2019.Work in

progress. Fund not received on spending end yet.

621 2224

Provision of clean drinking water Sewerage system

PCC and allied facilities in Chung Mohlanwal

Manak

LahoreOn-going

Schemes200.742 171.650 9.697 11.073 8.649 78% 90%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

622 2225

Provision of clean drinking water, Sewerage

system, PCC and allied facilities in Babo Mehar

Town, Lidhar, Bedian Road and adjoining abadies

LahoreOn-going

Schemes200.012 171.650 9.454 7.091 4.727 67% 88%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

623 2226

Provision of clean drinking water, Sewerage

system, PCC and allied facilities in Jallo More,

Batapur

LahoreOn-going

Schemes509.268 219.523 26.667 20.000 13.334 67% 46% Work stopped due to awaiting funds.

Page 42: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

624 2227PCC and drainage Scheme in UC 117 Mansoora

Lahore.Lahore

On-going

Schemes202.567 128.019 5.000 3.750 2.500 67% 64% Work stopped due to awaiting funds.

625 2228

Construction of PCC, Nallah at Maraka UC-122,

Shamke Bhattian, Chahram & mal, Manga Mandi

Sunder, Kot Fateh Muahammad Athul, District

Lahore

LahoreOn-going

Schemes24.200 7.634 5.522 2.642 1.261 48% 37%

Physically scheme is completed, balance funds are

required to clear the contractor's liability.

626 2229

Construction of PCC Sewerage & Drainage

System at UC-272 Raiwind Kalan & UC-273

Raiwind City, District Lahore

LahoreOn-going

Schemes8.000 5.581 0.806 0.202 0.000 0% 70% scheme completed

627 2230Katcha Storm / Sullage Water Channel in District

SheikhupuraSheikhupura

On-going

Schemes199.813 139.520 5.000 3.750 2.500 67% 71% Work in Progress

628 2231Provision of Sewerage Scheme Burjwala, Saleem

Kot, Housing Colony, City Sheikhupura Sheikhupura

On-going

Schemes174.527 165.000 3.176 2.382 1.588 67% 95% Work in Progress

629 2232Provision of Sewerage system in mohllah ghareeb

abad etc City Sheikhupura Sheikhupura

On-going

Schemes157.452 155.000 0.817 0.613 0.409 67% 99% Work in Progress

630 2233Provision of Open water Supply Scheme

Ferozwala.Sheikhupura

On-going

Schemes199.210 82.664 3.333 2.500 1.667 67% 42% Work in Progress

631 2234

Provision Of Sewerage and PCC Scheme Pir

Bahar Shah, Qazi Park Ramgarah & Purana

Shehar City Sheikhupura

SheikhupuraOn-going

Schemes175.000 95.000 3.333 2.500 1.667 67% 55% Work in Progress

632 2235Urban Sewerage / Drainage Scheme Sharqpur

Seikhupura , SharqpurSheikhupura

On-going

Schemes183.441 89.027 3.333 2.500 1.667 67% 49% Work in Progress

633 2236Urban Sewerage Scheme Ferozwala New Sewer

Lines District Sheikhupura Sheikhupura

On-going

Schemes199.330 184.330 5.000 3.750 2.500 67% 94% Work in Progress

634 2237Urban Drainage & PCC Scheme Northn Side of

Railway Track City SheikhupraSheikhupura

On-going

Schemes96.319 48.319 5.000 3.750 2.500 67% 53% Work in Progress

635 2238

Providing and laying of sewerage at Ghaloria

Colony Farooq Nagar Shah Colony District

Sheikhupura

SheikhupuraOn-going

Schemes97.683 47.683 5.000 3.750 2.500 67% 51% Work in Progress

636 2239Execution of Sanitation Sector Development

scheme Shah Kot City District Nankana Sahib Nankana Sahib

On-going

Schemes50.000 23.600 3.333 4.500 3.667 81% 55% Work is in progress.

637 2240

Const. of Storm Water Channel / Ext. &

Improvement Urban Sewerage / Drainage Scheme

Shahkot Phase-II

Nankana SahibOn-going

Schemes119.138 99.756 6.461 4.846 3.231 67% 86% Work is in progress.

638 2241Augmentation / Rehabilitation of Urban Sewerage

Scheme, Nankana SahibNankana Sahib

On-going

Schemes264.253 130.000 5.000 3.750 2.500 67% 50% Work is in progress.

639 2242

Construction of Sullage Carrier for Ultimate

Disposal of Phoolnagar City, Tehsil Pattoki, District

Kasur

KasurOn-going

Schemes337.971 18.614 20.000 15.000 10.000 67% 8% Work in Progress

640 2243Provision of Sewerage & Drainage System in

Chunian City, KasurKasur

On-going

Schemes99.011 76.401 20.000 16.520 11.520 70% 89% Work in Progress

641 2244 Urban Drainage Scheme Kasur city District kasur KasurOn-going

Schemes99.827 34.999 20.000 16.389 11.389 69% 46% Work in Progress

642 2245Urban Drainage, PCC & Brick Pavement scheme

Kasur city District KasurKasur

On-going

Schemes457.681 407.681 16.667 12.500 8.334 67% 91% Work in Progress

643 2246Urban PCC & Drainage Scheme Kot Radha

Kishan District Kasur.Kasur

On-going

Schemes112.887 104.597 2.758 0.690 0.000 0% 93% Work in Progress

644 2247Urban Sewerage Drainage Scheme, Pattoki

(Revised)Kasur

On-going

Schemes680.017 657.032 6.294 1.621 0.047 3% 97% Work in Progress

645 2248Sewerage Drainage Scheme Kangan Pur District

Kasur.Kasur

On-going

Schemes161.161 122.346 3.333 2.500 1.667 67% 77% Work in Progress

646 2249Drainage P.C.C. & Brick pavement in Mustafabad,

Kasur.Kasur

On-going

Schemes246.400 196.400 16.667 4.977 0.811 16% 80% Work in Progress

Page 43: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

647 2250

Complete Repair and renovation of Sewerage

system including PCC, Drains, water channels,

soling, tuff tiles etc. in M.C. Mandi Ahmed Abad,

District Okara.

OkaraOn-going

Schemes184.048 172.023 4.006 3.005 1.926 64% 95%

Date of AA 03.03.2014, Date of TS 05.03.2014,

Date of Pre-qualification.05.05.2014, Date of

Receipt of Tenders,20.05.2014, Date of work Order.

30.05.2014, Date of completion As per PC-I.

30.06.2016, Anticipated date of

completion.30.06.2019, Projected Population 66950

Person, Funds Release on 20-07-2018 Release of

Funds 02.08.2017.

648 2251 Construction of Sewerage Scheme Renala Khurd

City, District Okara Okara

On-going

Schemes327.480 296.423 10.352 7.764 5.176 67% 92%

Date of AA 02.04.2014, Date of TS 14.04.2014,

Date of Pre-qualification.10.04.2014, Date of

Invitation of Tender 05.05.2014, Date of Receipt of

Tenders 05.05.2014, Date of work Order

13.05.2014, Date of completion As per PC-I.

30.06.2016., Anticipated date of

completion,30.06.2019, Funds Release on 20-07-

2018 Projected Population 119573 Person, Release

of Funds 02.08.2017.

649 2252 Sewerage Scheme Depal Pur City District Okara OkaraOn-going

Schemes300.355 269.408 3.620 2.715 1.810 67% 90%

Date of AA 09.04.2010 ( Original), Date of Revised

AA 31.10.2014 , Date of TS 18.08.2010 (Phase -I),

Date of Revised TS 05.03.2015 , Date of Pre-

qualification,20.03.2015, Date of Invitation of

Tender 09.05.2015, Date of Receipt of Tenders

10.05.2015, Date of work Order 20.06.2011 &

03.09.2015, Date of completion As per Revised PC-

I. 31.12.2017, Anticipated date of

completion,30.06.2019, Funds Release on 20-07-

2018 Projected Population 229210 Person,

650 2253 Sewerage Scheme Shergarh Renala Khurd Okara OkaraOn-going

Schemes99.224 94.810 1.424 1.068 0.841 79% 96%

Date of AA 16.05.2014, Date of TS 28.06.2014,

Date of Pre-qualification 17.06.2014, Date of

Invitation of Tender 30.06.2014, Date of Receipt of

Tenders 30.06.2014, Date of work Order

17.09.2014, Date of completion As per PC-

I.14.09.2016 , Anticipated date of

completion,30.06.2019, Funds Release on 20-07-

2018 Projected Population 26497 Person.

651 2254

Extension, Improvement Complete Repair,

Renovation of Sewerage and and Water Supply

System alongwith Provision of Strom Water

Channels, Street Lights and Tuff Tiles in Hujrah

Shah Muqeem, District Okara

OkaraOn-going

Schemes398.910 59.545 6.667 5.000 3.587 72% 16%

Date of A.A 30-11-2017 Date of T.S 24-01-2018

Date of Prequalification 13-09-2017 Date of

invitation of tenders 22-02-2018 Date of Receipt of

tenders 22-02-2018 Date of work order 22-03-2018

Date of completion as per PC-I 22-03-2021

Anticipated date of completion 30-06-2021 No. of

Beneficiary 47415 Person Work is in progress.

652 2255Rehabilitation/Augmentation of Sewerage System

at Harrappa CitySahiwal

On-going

Schemes78.583 56.389 7.398 5.549 5.000 90% 78%

Date of AA 13.10.2016 , Date of TS 07.12.2016,

Date of Pre-qualification 08.02.2017, Date of receipt

of tender 18.02.2017 , Date of Work Order

22.03.2017 , Date of completion as per PC-1

30.06.2018 , Date of completion as per agreement

30.06.2018, Anticipated date of completion

30.06.2019, Work in progress.

653 2256

Provision / Rehablitation / Improvement of water

Supply in Urban U/Cs-12 & 13 and Construction of

Drain, Tuff Tiles, Sewerage in Urban U/Cs-

23,24,26 & 41 Multan City

MultanOn-going

Schemes6.000 4.000 0.667 0.166 0.000 0% 67%

1.Date of AA 11.04.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 06.11.2017 7.Date

of Completion as per PC-l 05.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 4648 persons. Scheme completed.Rs

0.166 million proposed for re-appropriation.

654 2257Extension of Urban Sewerage Scheme Jalalpur

Pirwala, District Multan (Revised)Multan

On-going

Schemes196.830 158.627 12.289 9.217 6.145 67% 84%

1. Date of A.A. 15.01.2014 (21.04.2016) 2. Date of

T.S. 22.01.2014 (05.08.2016) 3. Date of

Prequalification 27.01.2014 4. Date of Invitation of

Tender 12.02.2014 5. Date of Receipt of Tenders

24.02.2014 6. Date of work order

10.03.2014/18.11.2016 7. Date of Completion as

per PC-l 14.01.2016 8. Anticipated date of

completion 30.06.2019 9. Date of released of funds

03.08.2018 24.01.2019 10. No. of beneficiaries=

170275 persons. Work is in progress.

Page 44: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

655 2258Sewerage Water Disposal from North South

Shujabad City MultanMultan

On-going

Schemes145.222 118.112 8.989 2.247 0.000 0% 81%

1. Date of AA 26.08.2014. 2. Date of T.S

15.10.2014. 3. Dated of Prequalification 11.08.2014.

4. Date of invitation of tender 23.10.2014. 5. Date of

Receipt of tenders 24.10.2014. 6. Date of work

order 08.11.2014. 7. Date of Completion as per PC-l

25.08.2016 8. Anticipated date of completion

30.06.2019 9. Date of released of funds 03.08.2018.

24.01.2019 10. No. of beneficiaries=111527

persons. Scheme completed in saving and handed

over to TMA Shujabad.Rs 2.247 million proposed

for re-appropriation.

656 2259Rehabilitation / extension of Sewerage / drainage

system of Mian Channu City Khanewal

On-going

Schemes306.616 254.224 17.464 13.098 12.388 95% 87%

1. Date of A.A: 12.02.2015 2. Date of T.S:

05.03.2015. 3. Date of Pre-Qualification:

11.08.2014. 4. Date of Invitation of Tender:

23.10.2014. 5. Date of Receipt of Tender:

24.10.2014 6. Date of Work order: 05.11.2014 7.

Date of Completion as per PC-I: 25.08.2016 8.

Anticipated Date of completion: 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: -------- 11 No. of

beneficiaries 200428 Persons Work is in progress.

657 2260Revamping of Jahanian Sewerage System,

JahanianKhanewal

On-going

Schemes199.359 97.866 16.667 12.500 11.213 90% 55%

1. Date of A.A: 27.08.2016 2. Date of T.S:

25.10.2016 3. Date of Pre-Qualification: 26.10.2016

4. Date of Invitation of Tender: 03.12.2016 5. Date

of Receipt of Tender: 05.12.2016 6. Date of Work

order: 15.12.2016 7. Date of Completion as per PC-

I: 30.09.2019 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: -------- 11

No. of beneficiaries 65206Persons Work is in

progress.

658 2261Provision of Urban sewerage Scheme at Kabirwala

City, District Khanewal.Khanewal

On-going

Schemes99.676 49.676 10.000 7.500 6.719 90% 57%

1. Date of A.A: 18.11.2017 2. Date of T.S:

08.12.2017 3. Date of Pre-Qualification: 06.09.2017

4. Date of Invitation of Tender: 30.01.2018 5. Date

of Receipt of Tender: 31.01.2018 6. Date of Work

order: 10.02.2018 7. Date of Completion as per PC-

I: 31.03.2019 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: --------- 11

No. of beneficiaries 56299 Persons Work is in

progress.

659 2262Provision of drainage / Sewerage, soling & water

Supply in Municipal Area of Burewala City.Vehari

On-going

Schemes358.775 233.686 16.667 12.500 11.250 90% 68%

1. Date of A.A: 29.12.2014. 2. Date of T.S:

12.03.2015 3. Date of Pre-Qualification: 13.03.2015

4. Date of Invitation of Tender: 10.04.2015 5. Date

of receipt of Tender: 11.04.2015 6. Date of Award:

20.04.2015 7. Date of Completion as per PI:

28.12.2016 8. Anticipated Date of Complion:

30.06.2018 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ----- 11. No.

of Beneficiaries 226016 Persons. Work is in

progress.

660 2263

Comprehensive Sewerage / Drainage Scheme

Taunsa Sharif including Tuff Tilling of Streets -

InActive

Dera Ghazi

Khan

On-going

Schemes485.406 214.529 33.333 25.000 6.428 26% 46% • Date of A.A = 12.02.2015

661 2264

Construction of Nali Soling in UC Basti Jaam,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Ara Jafar,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Kotla Ahmad

Khan, District D.G. Khan.

Dera Ghazi

Khan

On-going

Schemes21.500 10.747 3.583 2.687 1.935 72% 59% "• Date of A.A = 04.10.2017

662 2265

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas Muza Chak Masso

U/C Nawan Shumali, Construction Of Nali

Soling,Tough Tiles Drainage,Culverts And Qulabas

U/C Jakhar Imam Shah, District D.G. Khan.

Dera Ghazi

Khan

On-going

Schemes6.000 2.973 1.000 0.750 0.548 73% 59% "• Date of A.A = 04.10.2017

663 2266

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Haji Kamand,

District D.G. Khan.

Dera Ghazi

Khan

On-going

Schemes9.000 4.442 1.500 1.125 0.844 75% 59% "• Date of A.A = 04.10.2017

Page 45: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

664 2267

10930 Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Khan Pur

Janobi, Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Nawan

Shumali, Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C N

Dera Ghazi

Khan

On-going

Schemes33.700 16.843 5.617 4.213 2.991 71% 59% "• Date of A.A = 04.10.2017

665 2268

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Aali Wala,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Jalbani,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Basti Malana,

Dera Ghazi

Khan

On-going

Schemes52.000 25.955 8.667 6.500 4.875 75% 59% "• Date of A.A = 04.10.2017

666 2269

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Tibbi Kharak,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Chabri

Zareen, Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Kot,

Dera Ghazi

Khan

On-going

Schemes130.000 64.993 6.000 4.500 3.375 75% 53% "• Date of A.A = 04.10.2017

667 2270

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Darahma,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Samina,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Chorahatta,

Dist

Dera Ghazi

Khan

On-going

Schemes29.000 14.485 4.833 3.625 2.719 75% 59% "• Date of A.A = 04.10.2017

668 2271

Construction of Nali Soling V/C Aliwala C/O Fateh

Muhammad Bazgir, Construction of Nali Soling,

Tuff Tiles, Drainage, Culverts and Qulabas U/C

Mana Ahmadani, District D.G. Khan.

Dera Ghazi

Khan

On-going

Schemes10.000 4.978 1.667 1.250 0.888 71% 59% "• Date of A.A = 04.10.2017

669 2272

Construction of Nali Soling, Tuff Tiles, Drainage,

Culverts and Qulabas U/C Notak Mahmeed,

District D.G. Khan.

Dera Ghazi

Khan

On-going

Schemes11.000 5.474 1.833 1.375 1.045 76% 59% "• Date of A.A = 04.10.2017

670 2273

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Darkhast

Jamal Khan Darmiani, Construction Of Nali

Soling,Tough Tiles Drainage,Culverts And Qulabas

U/C Darkhast Jamal Khan Janobi, Construction Of

Nali Soling,Tough Tiles Drainage,

Dera Ghazi

Khan

On-going

Schemes10.000 5.000 1.667 1.250 0.938 75% 59% "• Date of A.A = 04.10.2017

671 2274

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Jhoke Utra,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Hazara,

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Haider

Quresh

Dera Ghazi

Khan

On-going

Schemes47.500 23.731 3.333 2.500 1.825 73% 54% "• Date of A.A = 04.10.2017

672 2275

Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Khan Pur

Janobi, Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C Nawan

Shumali, Construction Of Nali Soling,Tough Tiles

Drainage,Culverts And Qulabas U/C N

Dera Ghazi

Khan

On-going

Schemes40.000 20.000 1.000 3.334 2.809 84% 57% "• Date of A.A = 04.10.2017

Page 46: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

673 2276

Construction of Urban Sewerage Drainage Earth

filling brick pavement and Tuff Tile scheme for

Rojhan

RajanpurOn-going

Schemes61.369 55.200 1.000 0.750 0.500 67% 91% " Date of A.A = 24.4.2015

674 2277

Urban drinage/Sewerage/tuff tile scheme in

Jampur City (replacement of outlived sewer and

new sewer system in Faisal Colony, Shah Jamal

Colony and Tattar Wala)

RajanpurOn-going

Schemes365.753 195.169 33.333 25.000 16.667 67% 58% "• Date of A.A = 23.12.2014

675 2278

Rural Drainage Sewerage PCC and Tuff Tile

flooring Rajan Pur City and Adjoining Abadies UC

Rajan Pur

RajanpurOn-going

Schemes40.500 25.600 4.967 3.725 2.484 67% 69% "• Date of A.A = 24.4.2015

676 2279

Construction of drain, brick pavement sullage

carrier culverts & tuff tile flooring scheme of fazilpur

tehsil & district rajanpur

RajanpurOn-going

Schemes50.000 25.000 8.333 6.250 0.000 0% 50% "• Date of A.A = 17.12.2014

677 2280Open Drainage & Tuff Tile Scheme in Remaining

Portion of Kot Addu City Muzaffargarh

On-going

Schemes49.850 32.404 5.815 4.361 2.908 67% 71% "• Date of A.A 22-09--2016

678 2281Sewerage System for Recep Tayyip Erdogan

Hospital Muzaffargarh Expansion ProjectMuzaffargarh

On-going

Schemes191.449 78.700 1.000 0.750 0.000 0% 41% Part-I is Completed

679 2282Comprehensive Sewerage Scheme alongwith Tuff

Tiles in City Chowk AzamLayyah

On-going

Schemes199.995 105.377 16.667 12.500 8.300 66% 57% • Date of AA = 22-09-2016

680 2283 Urban Sewerage / Drainage Scheme Chowk Azam LayyahOn-going

Schemes147.290 138.871 1.000 0.750 0.500 67% 95% "• Date of AA(Original) = 10-09-2007

681 2284 Urban Sewerage Scheme for Kot Sultan LayyahOn-going

Schemes191.440 152.935 6.667 5.000 3.334 67% 82% • Date of AA = 24-02-2009

682 2285Sewer Line from Bahawalpur Victoria Hospital to

Disposal Lal Bagh Tehsil & District Bahawalpur.Bahawalpur

On-going

Schemes172.906 139.513 11.131 8.348 5.560 67% 84%

Date of AA :26-02-2014. Date of TS :05-03-2014.

Date of RAA=12-05-2016. Date of pre-qualification:

07-03-2014. . Date of receipt of tenders. 02-04-

2014. Date of work order :29-04-2014. Date of

completion as per agreement:28.04.2016.

Anticipated date of completion=30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress. Date of AA :26-02-2014. Date

of TS :05-03-2014. Date of RAA=12-05-2016. Date

of pre-qualification: 07-03-2014. . Date of receipt of

tenders. 02-04-2014. Date of work order :29-04-

2014. Date of completion as per

agreement:28.04.2016. Anticipated date of

completion=30-06-2019. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Work is in progress.

683 2286Sewerage / Tuff Tile in Choti Karana Tehsil &

District Bahawalpur.Bahawalpur

On-going

Schemes1.288 0.883 0.135 0.033 0.000 0% 69%

Date of A.A 04.05.2016. Date of T.S 26-05-2016.

Date Awarded 11.06.2016. Date of completion 11-

09-2017. Expected date of completion 30-06-2018.

Funds released by FD 20.07.2018 & 11.01.2019. .

Work completed during 2017-2018. Liability of the

contractor cleared.Excess funds Rs. 0.068 million

surrendered dated 19.10.2018.

684 2287 Construction of Tuff Tile in Main Street Gillani City

Uch Sharif Tehsil Ahmed Pur East, Bahawalpur.Bahawalpur

On-going

Schemes3.089 0.801 0.763 0.190 0.000 0% 26%

Date of AA 19.03.2015. Date of T.S 18.04.2015.

Date of award 18.05.2015. Date of completion

17.09.2015. Expected date of completion 30-06-

2018. Funds released by FD 20.07.2018 &

11.01.2019. . Scheme remained unfunded during

2016-2017. Remaining work has been

executed/completed by Local Government due to

which funds not required. Excess funds Rs. 0.0382

million surrendered dated 19.10.2018.

685 2288Laying of Tuff Paver and provision of water Supply

Pipelines in City Bahawalnagar.Bahawalnagar

On-going

Schemes70.000 49.812 4.922 3.692 3.000 81% 75%

Date of AA: 11.01.2014. Date of TS: 17.01.2014.

Date of RTS 23-11-2016. Date of pre-qualification:

28.02.2014. Date of receipt of tenders = 19-03-

2014. Date of work order=11.04.2014. Date of

completion as per agreement=10.04.16. Anticipated

date of completion=30-06-2019. Date of receipt of

funds by F.D. 20.07.2018 & 11.01.2019. . Original

scope of work is completed. Revised scope of work

is in progress.

Page 47: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

686 2289Provision of Sewerage Scheme Zone A with Tuff

Paver at BahawalnagarBahawalnagar

On-going

Schemes399.587 138.058 50.000 50.000 50.000 100% 47%

Date of AA = 29-09-2016(DDSC). Date of T.S.

08.02.2017. Funds released by FD= 04-07-2017 .

Prequalification of the contractor 26-01-2017.

Tender received on 22.03.2017 . Date of work

awarded.03-05-2017. . Date of completion 02-05-

2019. . Date of receipt of funds by F.D. 20.07.2018

and 19-12-2018. Work is in Progress.

687 2290Sewerage Scheme Chishtian City Uplift Package

ChishtianBahawalnagar

On-going

Schemes916.110 672.765 33.333 25.000 21.500 86% 76%

Date of A.A 25.05.2014 . . Date of T.S. 21-07-2014.

Date of Prequalification. 21-07-2014. Date of receipt

of tenders =12-08-2014. Date of work order= 16-09-

2014. Date of completion as per agreement=

15.09.2017.Anticipated date of completion =

30.06.2019 .No. of beneficiaries=342309 persons.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

688 2291 Mega Sewerage Scheme Liaqatpur CityRahim Yar

Khan

On-going

Schemes500.000 49.996 66.667 50.000 33.200 66% 17%

Date of A.A(PDWP) 19-01-2017.Date of T.S

16.02.2017.. Prequalification of the contractor

15.03.2017..Date of receipt of tender:- 03.04.2017.

.Date of award 24.07.2017 Date of completion. 23-

07-2019.Date of receipt of funds by F.D. 20.07.2018

& 11.01.2019..Funds of 3rd Quarter is not

credited/onlined to the District Accounsts office

RYK..Work is in progress.

689 2292Request for provision of Sewerage Scheme of

Feroza Town, Tehsil Liaqat Pur

Rahim Yar

Khan

On-going

Schemes199.970 160.769 13.063 9.797 8.150 83% 84%

Date of AA. 23-09-2014. Date of TS.. 27-11-2014.

Date of prequalification. 08-12-2014. Date of receipt

of tenders = 31-12-2014. Date of work order=10-2-

15. Date of completion as per agreement 09-8-16.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

690 2293 Rehabilitation of Sewerage City SadiqabadRahim Yar

Khan

On-going

Schemes70.326 52.373 5.984 1.688 0.192 11% 75%

Date of AA. 09-10-2014. .Date of TS. 21-11-

2014.Rev: TS 28.10.2016..Date of prequalification.

08-12-2014..Date of receipt of tenders = 31-12-

2014..Date of work order= 10-01-2015..Date of

completion as per agreement= 09-01-

2016.Anticipated date of completion=30-06-2018.

Scheme completd in saving. Date of receipt of

funds by F.D. 20.07.2018 & 11.01.2019. Funds not

required during 2018-2019. Excess funds Rs. 1.496

million proposed to Re-appropriate.

691 2294Laying of Soling, Water Supply, Sewerage Line

and Tuff Tiles in City Sadiq Abad.

Rahim Yar

Khan

On-going

Schemes40.000 19.958 6.667 5.000 3.888 78% 60%

Date of AA 19-12-2017.Date of T.S 15-02-

2018.Tenders received on 13-03-2018 .Date of

award 18.04.2018..Date of completion

12.04.2019..Date of receipt of funds by F.D.

20.07.2018 & 11.01.2019. Work is in progress.

692 2295Laying of Soling, Water Supply, Sewerage Line

and Tuff Tiles in Rural Area Tehsil Sadiq Abad.

Rahim Yar

Khan

On-going

Schemes35.000 17.468 5.833 4.375 3.501 80% 60%

Date of AA 19-12-2017.Date of T.S 15-02-

2018.Date of receipt of tenders 13-03-2018 .Date of

work awarded 30-03-2018.Date of completion 29-06-

2019..Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

693 2296

Laying of Soling, Water Supply, Sewerage Line

and Tuff Tiles in Chak No. 148/P Tehsil Sadiq

Abad.

Rahim Yar

Khan

On-going

Schemes8.000 3.984 1.333 1.000 0.799 80% 60%

Date of AA 19-12-2017.Date of T.S 16-02-

2018.Date of receipt of tenders 13-03-2018 .Date of

work awarded 07-04-2018.Date of completion 06-06-

2019..Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

694 2297Construction of Sewerage Line and Soling Wahid

Bux Mahar Tehsil Sadiq Abad.

Rahim Yar

Khan

On-going

Schemes5.000 2.471 0.833 0.625 0.493 79% 59%

Date of AA 19-12-2017.Date of T.S 16-02-

2018.Tenders received on 13-03-2018..Dated of

award 11.05.2018..Date of completion

26.06.2018..Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

695 2298

Rehabilitation / Augmentation of Sewerage

scheme Khan Pur city Phase-II District Rahim Yar

Khan

Rahim Yar

Khan

On-going

Schemes452.844 432.844 2.000 1.500 1.211 81% 96%

Date of AA =05.03.2014.Date of

TS=05.03.2014.Date op receipt of Tenders

25.03.2014.Date of work awarded 14.04.2014..Date

of completion 13.04.2016..Scheme remained

unfunded. Funds released by FD on 12-11-2018 &

11.01.2019. Scheme completed. Liability of the

contractor Rs. 20.00 Million is yet to be cleared.

696 2299Comprehensive Sewerage scheme Chenab Nagar

ChiniotChiniot

On-going

Schemes719.952 164.999 66.667 50.000 32.750 66% 27%

1. Date of AA =02.05.2016 2. Date of TS =

19.08.2016 . 3. Date of work order= 22.10.2016. 4.

Date of Completion as per PC-I = 3 Ye.5.

Anticipated Date of Comp = 30.06.2019 6. No. of

Beneficiaries= 116058.Funds Released upto

24.01.2019 by the Chief Engineer (South) PHED

Lahore and work is in progress.

Page 48: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

697 2300

New urban Sewerage scheme for Mohallah Fateh

Abad Rashida Osmanaabad paris road Moazam

Shah Shahbaal

ChiniotOn-going

Schemes199.694 103.971 16.667 12.500 12.500 100% 58%

1. Date of AA =15.09.2014. 2. Date of TS

=28.11.2014 3. Date of Pre-qualification

=06.12.2014 4. Date of inviting Tenders=20.12.2014

5. Date receipt of Tenders= 20.12.2014 6. Date of

work order= 01.01.2015 7.Date of Completion as

per PC-I =2 Year 8. No. of Beneficiaries 94630

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

698 2301Soling / Drain, Pulian Hajiabad, Muradwala,

Sabowala,Colony, Sabowala, District ChiniotChiniot

On-going

Schemes4.998 0.800 1.000 0.750 0.500 67% 26%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

699 2302Construction of PCC / Soling / Drain, in Town

Committee Lalian, District ChiniotChiniot

On-going

Schemes10.000 9.410 0.590 0.443 0.295 67% 97%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

700 2303Extension Rehabilitation Sewerage Scheme

Chiniot City.Chiniot

On-going

Schemes212.366 209.621 1.000 0.750 0.500 67% 99%

1. Date of AA = 24.12.2012 2. Date of TS =

29.10.2013 (Revised) 3.Date of Award of work

31.01.2013. Work completed. Liability of the

contractor is pending.

701 2304

Construction of PCC / Soling / Drain,Pullian Mouza

Colony Mohammad Wala, Muhammad Wala,

Mamola, District Chiniot

ChiniotOn-going

Schemes4.000 2.539 1.461 1.096 0.731 67% 82%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

702 2305Construction of Sewerage Disposal Harsa Sheikh

Lahore road ChiniotChiniot

On-going

Schemes28.493 22.230 1.000 0.750 0.500 67% 80%

1. Date of AA = 31.07.2015 2. Date of TS =

27.08.2015 3.Date of Award of work 31.10.2015.

Work completed. Liability of the contractor is

pending.

703 2306Construction of PCC / Soling / Drain,Mouza Burj

Babal , District ChiniotChiniot

On-going

Schemes4.000 2.957 1.043 0.782 0.522 67% 87%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

704 2307Soling / Drains / Culverts / PCC Slabs / UC No.35

Tehsil Bhowana District Chiniot in PP-76, Chiniot Chiniot

On-going

Schemes5.000 4.729 0.271 0.203 0.136 67% 97%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

705 2308Soling / Drains / Culverts / PCC Slabs / Mc

Bhowana District Chiniot in PP-76, ChiniotChiniot

On-going

Schemes10.000 7.409 1.000 0.750 0.500 67% 79%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

706 2309Soling / Drains / Culverts / PCC Slabs /Uc No.34

Tehsil Bhowana District Chiniot PP- 76, Chiniot Chiniot

On-going

Schemes4.000 3.804 0.196 0.147 0.098 67% 98%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

707 2310Soling / Drains / Culverts / PCC Slabs / UC No.33

Tehsil Bhowana District Chiniot in PP-76, Chiniot Chiniot

On-going

Schemes5.000 2.669 1.000 0.750 0.500 67% 63%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

Work completed. Liability of the contractor is

pending.

708 2311Capacity Strenghthening of Design Cell of

HUD&PHED for projectPunjab

On-going

Schemes180.278 62.397 8.333 25.850 23.767 92% 48% In Progress

709 2312 Construction of Residential Buildings at Lahore

Head Quarter for officers BS 16 to BS 18 PHEDPunjab

On-going

Schemes277.000 81.706 10.000 7.500 5.000 67% 31% In Progress

710 2313Improvement and Extension of the Water Testing

Laboratories Phase IPunjab

On-going

Schemes260.000 19.590 50.000 12.500 0.000 0% 8% In Progress

711 2314 Renovation of PHED Head Quarter Building. PunjabOn-going

Schemes95.000 38.500 0.833 0.625 0.417 67% 41% In Progress

712 2315

Establishment of Management Information System

and Monitoring & Evaluation (MIS & ME) For

Capacity Building

PunjabOn-going

Schemes175.000 30.000 11.667 14.750 10.860 74% 23% In Progress

713 2316Establishment of PMU for WASH (Water,

Sanitataion & Hygiene)Punjab

On-going

Schemes35.000 4.200 3.267 4.850 3.710 76% 23% In Progress

714 2317Establishment of regional design cell at each civil

division / Circle levelPunjab

On-going

Schemes19.043 1.443 3.333 0.900 0.000 0% 8% In Progress

715 2318

Preparation of Water Quality Survey & Sewerage

Master Plan/Development Plan of Districts, Tehsil

and Urban Area

PunjabOn-going

Schemes18.235 12.435 1.650 1.238 0.000 0% 68% In Progress

716 2319 Survey & investigation of water source PunjabOn-going

Schemes9.436 0.456 2.993 0.845 0.000 0% 5% In Progress

Page 49: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

717 2320Third Party Validation for Quality Control of the

New Initiatives through out PunjabPunjab

On-going

Schemes39.847 2.301 4.182 3.137 2.091 67% 11% In Progress

718 2321Upgradation / Strengthening of Existing

Laboratories at District Head QuarterPunjab

On-going

Schemes390.000 93.500 50.000 37.500 20.754 55% 29% In Progress

719 2322

Multi Sectoral Nutrition Strategy for WASH

Including Water Supply, Sanitation, Hygiene,

Waste Water

PunjabOn-going

Schemes1,013.037 100.000 166.667 125.000 75.524 60% 17% Work in Progress

720 2323Rehabilitation of 781 dysfunctional Rural Water

Supply SchemesPunjab

On-going

Schemes9,015.746 0.480 333.333 206.667 0.000 0% 0% Work in Progress

721 2324

Combined PC-II of Water Quality Survey,

Identification of outlived pipes, outsourcing of

water Supply schemes, Rationalization of staff in

WASAs, MC & PHED and pre qualification of

contractors and manufacturers

PunjabOn-going

Schemes327.683 30.600 33.333 25.000 16.667 67% 14% In Progress

722 2325Rehabilitation of need based (identified through

TPV) Dysfunctional Rural water Supply SchemesPunjab

On-going

Schemes1,146.048 707.664 66.667 50.000 14.816 30% 63% In Progress

723 2326Scaling up Pakistan Approach for Total Sanitation

(PATS) in Punjab (ODF)Punjab

On-going

Schemes399.705 287.317 16.667 12.500 7.500 60% 74% In Progress

724 2327Construction of PCC in Different Streets in UC -77

District Faisalabad Faisalabad

On-going

Schemes5.000 3.808 1.192 0.894 0.650 73% 89%

AA issued on 05.08.2017. Funds released on

23.11.2017. Work order issued on 13.12.2017.

Work is in progress.Funds released on 23.11.2018

& 24.1.19

725 2328Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Dheer Bain Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

726 2329Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Kotli Nawab Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

727 2330Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Wando Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

728 2331Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Kali Suba Gujranwala

On-going

Schemes10.000 4.807 1.667 0.416 0.000 0% 48% Scheme completed.

729 2332Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Sohawa Dhalwan Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

730 2333Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Nangal Dona Singh Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

731 2334Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Gona Osar Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

732 2335Construction of Streets and Drainage at Ward No.1

District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.

733 2336Construction of Streets and Drainage at Ward

No.2, District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.

734 2337Construction of Streets and Drainage at Ward

No.3, District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.

735 2338Construction of Streets and Drainage at Ward

No.4, District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.

736 2339Construction of Streets and Drainage at Ward

No.5, District Gujranwala Gujranwala

On-going

Schemes5.650 3.150 0.833 0.208 0.000 0% 56% Scheme completed.

737 2340Construction of Streets and Drainage at Ward

No.6, District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed

738 2341Construction of Streets and Drainage at Ward

No.7, District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.

739 2342Construction of Streets and Drainage at Ward

No.8, District Gujranwala Gujranwala

On-going

Schemes5.000 2.500 0.833 0.208 0.000 0% 50% Scheme completed.

740 2343

Provision of PCC / Sewerage / Drainage / Soling

etc. in Village Jajoki, Teshil Nowsehra Virkan,

District Gujranwala

GujranwalaOn-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

Page 50: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

741 2344Rehabilitatin Improvement of Streets in Village Pir

Kot Tehsil Wazirabad, District GujrnawalaGujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

742 2345Construction of PCC, Sewerage/Drains at UC 63

District GujranwalaGujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

743 2346Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Nadala Sindhowan Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

744 2347Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Mandiala Tabsa Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

745 2348Construction of Gallian Nallian PCC Soling and

Tuff Tile in UC Chak Ram Daas Gujranwala

On-going

Schemes10.000 5.000 1.667 0.416 0.000 0% 50% Scheme completed.

746 2349

Construction of PCC Tuff Tile & Draiange at

Railway Road, Salamat Pura, Kamoki, District

Gujranwala

GujranwalaOn-going

Schemes6.755 3.930 0.942 0.236 0.000 0% 58% Scheme completed.

747 2350

Construction of PCC & Drainage at Street

Nos.13,14,15,16,17 and St. Masjid-E-Shuhda, Ahl-

E-Hadith, Tibba Muhammad Nagar, Kamoki,

District Gujranwala

GujranwalaOn-going

Schemes40.000 10.000 1.126 0.282 0.000 0% 25% Scheme completed.

748 2351Installation of Water Filteration Plant at Village

Class Marri Lahore.Lahore

On-going

Schemes5.350 2.833 0.839 0.229 0.020 9% 53%

Filtration Plant already installed in village Class

Mari during F.Y 2017-18, this is duplicate scheme,

required to be deleted for ADP.

749 2352Installation of Water Filteration Plant at Village

Gallian Khuda Bakhsh Lahore.Lahore

On-going

Schemes5.350 0.886 1.488 0.416 0.044 11% 17%

Filtration Plant already installed in village Gallian

Khuda Bakhsh under IPOR Package NA-130 during

F.Y 2017-18, this is duplicate scheme, required to

be deleted for ADP.

750 2353 Installation of filteration Plant Naseebabad LahoreOn-going

Schemes5.350 0.950 1.466 0.400 0.033 8% 18%

Due to change in political scenario, conflict with

community, site is not available for installation of

filtration plant, scheme need to be dropped from

ADP.

751 2354

Construction of PCC, Soling, Drain and Nallah in

Chak No. 11, 8, 7, 6, 18, 16, 15, 14 GB and Chak

No 01 (Khoti Wala) Nizam Pura District

nankanasahib

Nankana SahibOn-going

Schemes30.000 15.000 3.333 1.700 0.867 51% 53% Work is in progress.

752 2355Water Supply Dera Dogran Bhutta Colony Rukn

Deen Pur, District LodhranLodhran

On-going

Schemes39.263 9.986 9.754 7.316 5.300 72% 39%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 10-02-

2018 7. Date of Completion as per PC-I: 28-02-2018

8. Anticipated Date of Completion: 08-02-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

3821 Persons. Work is in Progress

753 2356Water Supply Scheme Kotli Wajjwah, District

LodhranLodhran

On-going

Schemes37.175 9.977 9.058 6.794 5.200 77% 41%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 07-02-

2018 7. Date of Completion as per PC-I : 28-02-

2018 8. Anticipated Date of Completion: 04-02-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

5367 Persons. Work is in Progress.

754 2357

Water Supply Scheme Haifzaabad Dunyapur

Gharbi Remainig Portion Dunyapur Sharqi, District

Lodhran

LodhranOn-going

Schemes49.805 9.900 13.268 14.322 8.953 63% 38%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 06-02-

2018 7. Date of Completion as per PC-I: 28-02-2018

8. Anticipated Date of Completion: 04-02-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

4731 Persons. Work is in Progress.

755 2358Water Supply Scheme in Chak No.359/Wb District

LodhranLodhran

On-going

Schemes19.309 9.896 3.103 2.327 1.850 80% 61%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 06-02-

2018 7. Date of Completion as per PC-I: 28-02-2018

8. Anticipated Date of Completion: 04-02-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

4235 Persons. Work is in Progress

Page 51: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

756 2359Water Supply Scheme in Chak No.358/Wb District

LodhranLodhran

On-going

Schemes26.334 9.992 5.445 4.084 3.100 76% 50%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 10-02-

2018 7. Date of Completion as per PC-I: 28-02-2018

8. Anticipated Date of Completion: 08-02-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

4881 Persons. Work is in Progress.

757 2360Water Supply Scheme in Chak No.311/Wb District

LodhranLodhran

On-going

Schemes36.605 9.855 8.868 6.651 5.150 77% 41%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 30-03-

2018 7. Date of Completion as per PC- I: 28-02-

2018 8. Anticipated Date of Completion: 28-03-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

2996 Persons. Work is in Progress.

758 2361Water Supply Scheme in Chak No.13/M District

LodhranLodhran

On-going

Schemes28.934 9.927 6.311 4.733 3.650 77% 47%

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-

2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 03-01-2018 5. Date of Receipt

of Tender: 04-01-2018 6. Date of Award: 10-02-

2018 7. Date of Completion as per PC-I: 28-02-2018

8. Anticipated Date of Completion: 08-02-2019

9.Date of released of funds 03-08-2018 24.01.2019

10. Reason of Slow Moving: 11.No. of Benificiary

1934 Persons. Work is in Progress.

759 2362Construction of Nali Soling Tuff Tile & Culverts UC

Shero Dasti Dg Khan

Dera Ghazi

Khan

On-going

Schemes7.000 2.000 1.000 0.750 0.548 73% 36% "• Date of A.A = 13.1.17

760 2363

Construction of Nali Soling Tuff Tiles On The West

of Mana Ahmadani Town Ship + Basti Budhan Dg

Khan

Dera Ghazi

Khan

On-going

Schemes10.000 2.000 1.000 0.750 0.000 0% 20% "• Date of A.A = 13.1.17

761 2364Rehabilitation of Water Supply in Fareed Abad PP-

244 District Dg Khan

Dera Ghazi

Khan

On-going

Schemes10.000 7.000 1.000 0.750 0.548 73% 75% "• Date of A.A = 25.7.2017

762 2365Rehabilitation of Water Supply in Gharib Abad PP-

244 District Dg Khan

Dera Ghazi

Khan

On-going

Schemes10.000 5.000 1.000 0.750 0.555 74% 56% "• Date of A.A = 25.7.2017

763 2366Rehabilitation of 10 Rural Water Supply Schemes

Tehsil Murree & Kotli Sattian, District RawalpindiRawalpindi

On-going

Schemes34.830 9.787 3.333 2.500 1.667 67% 33% Work in Progress.

764 2367

Const. of 02 Nos. Filtration Plants in each Ward of

Chaklala Cantt Ward No.5 to 10& Const. of 0.2 MG

capacity UGT at Sarwar Park LalKurti, District

Rawalpindi

RawalpindiOn-going

Schemes50.000 19.500 4.667 3.500 2.334 67% 44% Work in Progress.

765 2368

Const. of Bridge / Drain at Rawal Town, Tench

Road/Adra Bridge/ Kacha Stop under Railway

Track/Aliabad/Dk. Banaras/ Ahmadabad, District

Rawalpindi

RawalpindiOn-going

Schemes50.000 20.000 6.667 9.000 7.334 81% 55% Work in Progress.

766 2369

Const. of Road / Sewerage at each Ward No.1 to

10 of Rawalpindi Cantt and Ward No.5 to 10 &

Minority Member, District Rawalpindi

RawalpindiOn-going

Schemes50.000 20.909 6.667 7.500 5.834 78% 53% Work in Progress.

767 2370Construction of streets in UCs PP-03 including

Gujar Khan City, District RawalpindiRawalpindi

On-going

Schemes150.000 35.897 6.667 9.329 7.663 82% 29% Work in Progress.

768 2371

Laying of 4’’ Dia Water Supply Pipe Line Ward

No,1 to Ward No,10 Rawalpindi Cantonment

Board ., District Rawalpindi

RawalpindiOn-going

Schemes40.000 10.000 10.000 7.500 5.000 67% 38% Work in Progress.

769 2372

Const. of 02 Nos. Filtration Plants in each Ward of

Rawalpindi Cantt Ward No.1 to 10 and Const. of

0.2 MG capacity UGT at Dk. Gujran Ward No.10,

District Rawalpindi

RawalpindiOn-going

Schemes50.000 20.000 10.000 7.500 5.000 67% 50% Work in Progress.

770 2373Construction of Under Ground Water Tank

Rawalpindi Cantonment Board, District RawalpindiRawalpindi

On-going

Schemes25.000 21.156 1.114 0.836 0.557 67% 87%

Only payment of WAPDA Demand Notice pending

which will be paid after issuance of Demand Notice

by WAPDA.

Page 52: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

771 2374Water Supply Scheme at Dhala, District

RawalpindiRawalpindi

On-going

Schemes10.200 5.000 1.733 1.300 0.867 67% 58% Work is in progress.

772 2375

Construction of PCC link road Wasla to Dhoke

Bhattian, length=2.00 Km UC Sui Chemian, Tehsil

Gujar Khan, District Rawalpindi

RawalpindiOn-going

Schemes12.815 5.000 2.605 0.651 0.000 0% 39% Work is in progress.

773 2376

Construction of PCC link road Sattal to Sabah Sher

and Dhoke Phugoo, length=2.00 Km, Tehsil Gujar

Khan, District Rawalpindi

RawalpindiOn-going

Schemes12.881 5.000 2.627 0.656 0.000 0% 39% Work is in progress.

774 2377

Construction of PCC road Dhoke Khumbail, Phase-

I, length=1.5 Km, UC Sui Chemian, Tehsil Gujar

Khan, District Rawalpindi

RawalpindiOn-going

Schemes10.569 5.000 1.856 0.464 0.000 0% 47% Work is in progress.

775 2378Constt. Of PCC link Road Mohri Barsal uc Jero

Ratial., District RawalpindiRawalpindi

On-going

Schemes14.000 8.969 1.677 1.258 0.839 67% 70% Work is in progress.

776 2379Constt. Of PCC link Road Paka Khanpur UC

Bhadana., District RawalpindiRawalpindi

On-going

Schemes14.000 4.917 3.000 0.750 0.000 0% 35% Work is in progress.

777 2380Constt. Of PCC link Road Dhoke Rajgan UC

Qazian., District RawalpindiRawalpindi

On-going

Schemes12.000 5.000 2.333 1.750 1.167 67% 51% Work is in progress.

778 2381Constt. Of PCC link Road Dhoke fateh Paharian

UC Qazian., District RawalpindiRawalpindi

On-going

Schemes11.000 4.500 2.000 1.500 1.000 67% 50% Work is in progress.

779 2382

Constt. Of PCC link Road Dhoke Channi Dakhali

Sohawa Mirzian, Islam Pura Jabbar / Bewal.,

District Rawalpindi

RawalpindiOn-going

Schemes11.000 5.000 2.000 1.500 1.000 67% 55% Work is in progress.

780 2383

Construction of PCC link road Jhawan to Kountrila

UC Kountrila, length=1.70 Km, Tehsil Gujar Khan,

District Rawalpindi

RawalpindiOn-going

Schemes10.530 4.773 1.843 0.460 0.000 0% 45% Work is in progress.

781 2384

Construction of PCC link road Kanyal to Dhoke

Jeaven, length=1.70 Km UC Mohra Noori, Tehsil

Gujar Khan, District Rawalpindi

RawalpindiOn-going

Schemes10.170 4.995 1.723 0.430 0.000 0% 49% Work is in progress.

782 2385Drainage scheme at Noorpur and Lundi, Tehsil

Hazro, District AttockAttock

On-going

Schemes26.139 9.977 5.380 1.535 1.090 71% 42%

A.A Date 02.08.2017. T.S Date 13.09.2017.Date of

Start of Scheme 29.01.2018.Date of Completion of

Scheme 30.06.19.Work is in progress.

783 2386Drainage scheme at Khudlathi and Sarwana,

Tehsil Hazro, District AttockAttock

On-going

Schemes28.306 9.977 6.102 4.577 3.051 67% 46%

A.A Date 02.08.2017.T.S Date 13.09.2017.Date of

Start of Scheme 07.12.2017.Date of Completion of

Scheme 30.06.19.Work is in progress.

784 2387Drainage scheme at Musa and Sherani, Tehsil

Hazro, District Attock Attock

On-going

Schemes26.931 14.976 3.977 2.983 1.989 67% 63%

A.A Date 02.08.2017.T.S Date 13.09.2017.Date of

Start of Scheme 27.11.2017.Date of Completion of

Scheme30.06.19.Work is in progress.

785 2388Rural drainage scheme in village Shakardara

Phase-II, District AttockAttock

On-going

Schemes32.394 9.980 3.333 2.500 1.667 67% 36%

A.A Date 02.08.2017. T.S Date 13.09.2017.Date of

Start of Scheme 09.12.2017.Date of Completion of

Scheme 30.06.2019.Work is in progress.

786 2389Rural draiange scheme in village Ghourgushti

Phase-II, Tehsil Hazro, District AttockAttock

On-going

Schemes19.313 9.914 3.104 2.328 1.552 67% 59%

A.A Date 02.08.2017. T.S Date 13.09.2017.Date of

Start of Scheme 09.12.2017.Date of Completion of

Scheme 30.06.2019.Work is in progress.

787 2390

Construction of PCC road from Kohat road

Bhandar to Dhok Sanakhi UC Langar Tehsil Jand

District Attock

AttockOn-going

Schemes28.500 9.979 6.167 4.625 3.084 67% 46%

A.A Date 02.08.2017. T.S Date 13.09.2017.Date of

Start of Scheme 06.12.2017.Date of Completion of

Scheme 30.06.19.Work is in progress.

788 2391Water Supply scheme of village Ferozwali UC

Gareebwal Tehsil Pindigheb District AttockAttock

On-going

Schemes22.500 7.961 4.833 3.625 2.417 67% 46%

A.A Date 02.08.2017. T.S Date 13.09.2017.Date of

Start of Scheme 10.01.2018.Date of Completion of

Scheme 30.06.2019.Work is in progress.

789 2392Drainage / sewerage scheme in village Painda,

Daman, Jalalia, District AttockAttock

On-going

Schemes61.838 25.999 3.333 2.500 1.667 67% 45%

A.A Date 16.09.2017.T.S Date 11.10.2017.Date of

Start of Scheme 06.11.2017.Date of Completion of

Scheme 30.06.2019.Dwork is in progress.

790 2393Drainage / sewerage scheme in village Shadi Khan

Phase-II, District AttockAttock

On-going

Schemes54.788 19.972 3.333 3.500 2.667 76% 41%

A.A Date 16.09.2017.T.S Date 10.10.2017. Date of

Start of Scheme 09.12.2017.Date of Completion of

Scheme 30.06.2019.Work is in progress.

791 2394Drainage / Sewerage System in village Barazai,

Tehsil Hazro, District AttockAttock

On-going

Schemes15.450 9.346 1.817 1.363 0.909 67% 66%

A.A Date 16.09.2017.T.S Date 10.10.2017. Date of

Start of Scheme 09.12.2017.Date of Completion of

Scheme 30.06.2019.Work is in progress.

Page 53: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

792 2395Rural drainage scheme and water supply

Oudherwal and Mohallah Islam Pura ChakwalChakwal

On-going

Schemes18.000 10.000 2.667 2.600 1.934 74% 66%

Date of A.A 31.07.2017. Date of T.S 08.08.2017

.Date of Start 18.10.2017.Date of completion

30.06.2019.Work is in progress.

793 2396Rural drainage scheme and Water Supply in UC

Dub, District ChakwalChakwal

On-going

Schemes24.000 10.000 4.667 5.031 3.865 77% 58%

Date of A.A 31.07.2017.Date of T.S

08.08.2017.Date of Start 18.10.2017.Date of

completion 30.06.2019.Full funds utilized. Scheme

is short funded.

794 2397Urban sewerage and drainage scheme in Chakwal

City, Ward No.1 to Ward No.12, District ChakwalChakwal

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39%

"Date of A.A 31.07.2017.Date of T.S

08.08.2017.Date of Start 19.10.2017

795 2398

Urban Drainage & Sewerage scheme of Chakwal

City from Ward No.13 to Ward No.23, District

Chakwal

ChakwalOn-going

Schemes30.000 16.000 4.667 11.900 10.732 90% 89%

Date of A.A 31.07.2017. Date of T.S

08.08.2017.Date of Start 19.10.2017 .Date.of

fcompletion.30.06.2019.Allocated funds were

utilized. utilized. Additional funds Rs.8.4 M provided

through .reappropriation in Dec.2018 and will be

consumed during next month.

796 2399

Urban Drainage & Sewerage scheme of Chakwal

City from Ward No.28 to Ward No.37, District

Chakwal

ChakwalOn-going

Schemes30.000 9.970 3.333 2.500 1.667 67% 39%

Date of A.A 31.07.2017. Date of T.S 08.08.2017.

Date of Start 19.10.2017.Date of completion

30.06.2020.Full funds utilized. Scheme is short

funded.

797 2400Rural drainage scheme and retaining wall and

Cause Way in MC Bhaun, District ChakwalChakwal

On-going

Schemes27.000 13.000 4.667 7.000 5.834 83% 70%

Date of A.A 31.07.2017. Date of T.S

08.08.2017.Date of Start 23.10.2017.Date of

completion 30.06.2019.Allocated funds were

utilized. utilized. Additional funds Rs.3.5 M provided

through reappropriation in Dec.2018 and will be

consumed during next month.

798 2401Rural Drainage Scheme and Retaining wall and

Cause way in UC Mureed, District ChakwalChakwal

On-going

Schemes25.000 13.999 3.667 2.750 1.834 67% 63%

Date of A.A 31.07.2017. Date of T.S

08.08.2017.Date of Start 25.10.2017.Date of

completion 30.06.2019.Full funds utilized. Scheme

is short funded.

799 2402Rural Drainage Scheme and Retaining wall and

Cause way in UC Jand Awan, District ChakwalChakwal

On-going

Schemes20.000 9.997 3.333 2.500 1.667 67% 58%

Date of A.A 31.07.2017.Date of T.S

08.08.2017.Date of Start 26.10.2017.Date of

completion 30.06.2019.Full funds utilized. Scheme

is short funded.

800 2403Rural drainage and water supply village Tatral,

District ChakwalChakwal

On-going

Schemes20.000 10.000 3.333 0.969 0.136 14% 51%

Date of A.A 31.07.2017. Date of T.S

08.08.2017.Date of Start 26.10.2017 ..Date of

completion 30.06.2019.Work is in progress.

801 2404Rural Drainage scheme and Retaining wall in UC

Mulhal Mughllan, District ChakwalChakwal

On-going

Schemes17.000 9.996 2.333 1.150 0.567 49% 62%

Date of A.A 31.07.2017. Date of T.S

08.08.2017.Date of Start 26.10.2017.Date of

completion 30.06.2019.Full funds utilized. Scheme

is short funded.

802 2405Rural draiange scheme & Retaining wall and

causeway in UC Chak Umara, District ChakwalChakwal

On-going

Schemes13.000 8.000 1.667 3.750 3.333 89% 87%

Date of A.A 31.07.2017 .Date of T.S

08.08.2017.Date of Start 26.10.2017 .Date of

completion 30.06.2019.Allocated funds were

utilized. utilized. Additional funds Rs.8.4 M provided

through reappropriationin in Dec.2018 and will be

consumed during next month.

803 2406Rural drainage scheme UC -Jaswal, Tehsil &

District ChakwalChakwal

On-going

Schemes20.000 9.997 3.333 1.900 1.067 56% 55%

Date of A.A 31.07.2017 .Date of T.S 08.08.2017.

Date of Start 26.10.2017 .Date of completion

30.06.2019.Work is in progress.

804 2407Rural drainage scheme Nichandi & Dhapai, Tehsil

& District ChakwalChakwal

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58%

"Date of A.A 31.07.2017 .Date of T.S 08.08.2017

.Date of Start 27.10.2017

805 2408Construction of PCC, Streets, Drain & Water

Supply at Talagang, District ChakwalChakwal

On-going

Schemes147.248 29.998 3.333 2.500 1.667 67% 22%

Date of A.A 09.08.2017. Date of T.S 02.10.2017

.Date of Start 17.11.2017 .Date of completion

30.06.2020.Full funds utilized. Scheme is short

funded.

806 2409Construction of PCC, Streets, Drain & Water

Supply at Tehsil Lawa PP-23, District ChakwalChakwal

On-going

Schemes98.166 24.920 3.333 2.500 1.667 67% 27%

Date of A.A 09.08.2017.Date of T.S 08.08.2017

.Date of Start 21.11.2017 . Date of completion

30.06.2020.Full funds utilized. Scheme is short

funded.

807 2410

Restoration / Flood Rains Damages vented

causeway on Dhermond to Dk. Fateh Shah Road,

Vented causeway Darot & street / drains village

Wanhar, Tehsil Talagang, District Chakwal

ChakwalOn-going

Schemes14.239 10.000 1.413 1.060 0.707 67% 75%

Date of A.A 31.07.2017.Date of T.S

08.08.2017.Date of Start 27.10.2017.Date of

completion 30.06.2019.Scheme completed.

808 2411Provision of sewerage at Ward No.36 Tehsil &

District Jhelum, District JehlumJhelum

On-going

Schemes15.000 4.480 2.333 1.750 1.167 67% 38%

A.A Date 27-07-2017.T.S Date 09-08-2017.Date of

Work Award 09-09-2017.Work in progress

809 2412Provision of Sewerage system at UC Kotla Faqeer,

Tehsil & District JhelumJhelum

On-going

Schemes30.000 10.000 3.333 9.185 4.445 48% 48%

A.A Date 27-07-2017.T.S date 09-08-2017.Date of

Work Award 09-09-2017.Work in progress

810 2413Provision of Water Supply at Pind Sawika, Tehsil &

District JhelumJhelum

On-going

Schemes15.000 7.988 2.333 1.750 1.167 67% 61%

A.A Date 27-07-2017.T.S date 09-08-2017.Date of

Work Award 16-09-2017.Work in progress

811 2414Provision of Water supply at village Kundal, District

JhelumJhelum

On-going

Schemes21.747 9.941 3.916 2.937 1.958 67% 55%

A.A Date 27-07-2017.T.S date 09-08-2017.Date of

Work Award 13-09-2017.Work in progress

Page 54: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

812 2415Water supply scheme at Chak No.165 Shumali,

Sillanwali, District SargodhaSargodha

On-going

Schemes10.673 4.947 1.891 1.418 1.411 100% 60% Work in progress.

813 2416

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No

45/SB Tehsil and District Sargodha

SargodhaOn-going

Schemes20.000 9.979 3.333 2.500 1.899 76% 59% Work in progress.

814 2417

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No

46/Sb tehsil and District Sargodha

SargodhaOn-going

Schemes20.000 9.977 3.333 2.500 2.226 89% 61% Work in progress.

815 2418

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No

107/Sb Tehsil and District Sargodha

SargodhaOn-going

Schemes20.003 9.920 3.334 2.501 2.120 85% 60% Work in progress.

816 2419

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No

85/NB tehsil and District Sargodha

SargodhaOn-going

Schemes10.004 6.036 1.323 0.993 0.993 100% 70% Work in progress.

817 2420

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No

84/NB Tehsil and District Sargodha

SargodhaOn-going

Schemes10.008 4.972 1.669 1.252 1.009 81% 60% Work in progress.

818 2421Water supply scheme at Chak No.129 Janobi,

Sillanwali, District SargodhaSargodha

On-going

Schemes23.594 7.000 4.531 3.398 3.364 99% 44% Work in progress.

819 2422Water supply scheme at Chak No.119 Janobi,

Sillanwali, District SargodhaSargodha

On-going

Schemes17.002 10.000 2.334 1.751 1.671 95% 69% Work in progress.

820 2423Water supply scheme at Chak No.111/107

Shumali, Sillanwali, District SargodhaSargodha

On-going

Schemes17.193 10.000 2.398 1.799 1.624 90% 68% Work in progress.

821 2424Water supply scheme at Chak No.140 Janobi,

Sillanwali, District SargodhaSargodha

On-going

Schemes12.961 5.997 2.320 1.740 1.353 78% 57% Work in progress.

822 2425

Construction of Drain / PCC / Soling / Sullage

Carrier at Midh Pergana Islam Pure More, Tehsil

Bhera. District Sargodha

SargodhaOn-going

Schemes16.130 10.000 2.043 1.532 1.204 79% 69% Work in progress.

823 2426

Construction of PCC / Soling / Sewerage / Nullah

Dera Abdul Sattar jhamat Chak No. 19 Shumali L=

2800 Feet, District Sargodha

SargodhaOn-going

Schemes20.000 9.972 3.333 2.500 1.889 76% 59% Work in progress.

824 2427

Construction of PCC / Soling / Sewerage / Chabar

Balooka Dera Mehar Muhammad Akhtar Lak and

PCC / Soling Mehar Qadir Yat Lak, UC Sakisar

Baar, District Sargodha

SargodhaOn-going

Schemes20.000 10.000 3.333 2.500 1.947 78% 60% Work in progress.

825 2428

Constructio of Soling / Sewerage / PCC, Dera Jaat

via Mehar Shahid Akram Lak, Ghulam Ahmed

Kamrana, Ahmed Yaar Gondal, Haji Muhammad

Sher, UC Mardi Lak, District Sargodha

SargodhaOn-going

Schemes20.000 10.000 3.333 2.500 2.026 81% 60% Work in progress.

826 2429

Construction of Soling / PCC / Nullah / Dera Mahar

Nasar Hayat Lak and Soling Lak More to Bonga

Minhas Colony, Dera Jaat Mahar Muhammad

Bakhsh Lak, Mahar Abdul Rehamn Lak, Salah

Muhammad Sipra, UC Lak More, District Sargodha

SargodhaOn-going

Schemes20.000 10.000 3.333 2.500 1.901 76% 60% Work in progress.

827 2430Construction of Soling / PCC / UC Chak No. 58

Shumali, District SargodhaSargodha

On-going

Schemes20.000 9.978 3.333 2.500 1.977 79% 60% Work in progress.

828 2431

Construciton of Soling Dera Jaat Badle Wala and

PCC / Sewerage and repair of road Chak No. 53

Shumali, District Sargodha

SargodhaOn-going

Schemes20.000 10.000 3.333 2.500 1.898 76% 59% Work in progress.

829 2432Rural Drainage scheme for Chak No 9/SB, District

SargodhaSargodha

On-going

Schemes29.294 11.100 3.333 2.500 2.241 90% 46% Work in progress.

Page 55: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

830 2433Rural Drainage scheme for Chak No.18/SB &

Colonies, District SargodhaSargodha

On-going

Schemes25.885 13.609 3.333 2.500 1.967 79% 60% Work in progress.

831 2434Rural Drainage scheme Chak No.2/NB, District

SargodhaSargodha

On-going

Schemes30.261 9.966 3.333 2.500 2.352 94% 41% Work in progress.

832 2435 Rural Drainage Scheme Abdal, District Sargodha SargodhaOn-going

Schemes25.667 10.885 3.333 2.500 1.923 77% 50% Work in progress.

833 2436

Construciton of Drainage / Soling, Adjoining

Abadies of Mouza Ahmaday wala, District

Sargodha

SargodhaOn-going

Schemes15.000 5.000 3.333 2.500 2.069 83% 47% Work in progress.

834 2437Rural drainage scheme UC No.64, Dharema,

Sargodha, District SargodhaSargodha

On-going

Schemes19.991 8.500 3.330 2.498 1.891 76% 52% Work in progress.

835 2438Rural drainage scheme UC No.77, Hyderabaad

Town, District SargodhaSargodha

On-going

Schemes19.927 9.995 3.309 2.482 1.916 77% 60% Work in progress.

836 2439Rural drainage scheme UC No.76, Chak

No.71/NB, District SargodhaSargodha

On-going

Schemes19.955 10.000 3.318 2.489 2.033 82% 60% Work in progress.

837 2440Rural drainage scheme UC No.74, Chak

No.79/NB, District SargodhaSargodha

On-going

Schemes19.987 10.000 3.329 2.497 1.978 79% 60% Work in progress.

838 2441Drainage scheme at Chak No.132/136, Janobi,

Sillanwali, District Sargodha Sargodha

On-going

Schemes29.657 11.993 3.333 2.500 2.139 86% 48% Work in progress.

839 2442Drainage scheme at Chak No.125/129 Shumali,

Sillanwali, District SargodhaSargodha

On-going

Schemes32.611 10.000 3.333 2.500 2.500 100% 38% Work in progress.

840 2443Drainage scheme at Chak No.128/130 Janobi,

Sillanwali, District SargodhaSargodha

On-going

Schemes33.563 12.999 3.333 2.500 2.252 90% 45% Work in progress.

841 2444

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No 23-

ASB Tehsil and District Sargodha.

SargodhaOn-going

Schemes15.000 10.000 1.667 1.251 1.211 97% 75% Work in progress.

842 2445

Construction of road Drain / Soling / Re-Soling /

PCC / Tuff Pavers / Sullage Carrier in Chak No

73/SB Tehsil and District Sargodha

SargodhaOn-going

Schemes15.002 10.000 1.667 1.251 0.963 77% 73% Work in progress.

843 2446Urban Sewerage & Drainage Scheme in M.C-04

Sargodha City.Sargodha

On-going

Schemes50.000 19.981 3.333 2.500 2.500 100% 45% Work in progress.

844 2447Urban Sewerage & Drainage Scheme in M.C-19

Sargodha City.Sargodha

On-going

Schemes40.000 19.788 3.333 2.500 2.104 84% 55% Work in progress.

845 2448Urban Sewerage & Drainage Scheme in

Cantonment Ward No. 01 to 05 Sargodha City.Sargodha

On-going

Schemes50.000 20.675 3.333 2.500 2.500 100% 46% Work in progress.

846 2449Urban Sewerage & Drainage Scheme in

Cantonment Ward No. 06 to 10 Sargodha City.Sargodha

On-going

Schemes50.000 21.099 3.333 2.500 2.500 100% 47% Work in progress.

847 2450

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline including Disposal Station Gillwala

and Tiwana Park Sargodha City.

SargodhaOn-going

Schemes50.000 19.917 3.333 2.500 1.973 79% 44% Work in progress.

848 2451

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline including Disposal Station M.C No.

07 Street No. 01, 02, 03, 04 & 05 to Rehman Pura

Chowk via Pistool Marka Gali Sargodha City.

SargodhaOn-going

Schemes50.000 22.600 3.333 2.500 1.888 76% 49% Work in progress.

849 2452Urban Sewerage & Drainage Scheme / Water

Supply Pipeline in M.C No. 08 Sargodha City.Sargodha

On-going

Schemes40.000 20.000 3.333 2.500 2.500 100% 56% Work in progress.

850 2453

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline including Renovation of Disposal

Station Eid Gah M.C No. 09 Sargodha City.

SargodhaOn-going

Schemes45.000 19.996 3.333 2.500 2.500 100% 50% Work in progress.

Page 56: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

851 2454

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline M.C No. 11 & M.C No. 13

Sargodha City

SargodhaOn-going

Schemes50.000 21.260 3.333 2.500 2.030 81% 47% Work in progress.

852 2455

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline including Disposal Station Iqbal

Colony and at Girls Degree College to Block No.

16 Sargodha City

SargodhaOn-going

Schemes50.000 13.000 3.333 2.500 2.500 100% 31% Work in progress.

853 2456

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline Madina Town, New Madina Town,

Muhammadi Colony including Disposal Station and

Main Water Works Chowk / Road Sargodha City.

SargodhaOn-going

Schemes50.000 20.309 3.333 2.500 2.500 100% 46% Work in progress.

854 2457

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline M.C No. 22 with Road Election

Commission Sargodha City.

SargodhaOn-going

Schemes50.000 21.488 3.333 2.500 2.500 100% 48% Work in progress.

855 2458

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline M.C No. 20 M.C No. 21 Sargodha

City.

SargodhaOn-going

Schemes40.000 19.969 3.333 2.500 2.142 86% 55% Work in progress.

856 2459

Urban Sewerage & Drainage Scheme / Water

Supply Pipeline Hameed Town, Society Colony

including Renovation of Main Disposal Works

Sillanwali Road Sargodha City.

SargodhaOn-going

Schemes45.000 19.994 3.333 2.500 2.168 87% 49% Work in progress.

857 2460Urban Sewerage & Drainage Scheme in M.C-01

Sargodha City.Sargodha

On-going

Schemes50.000 24.739 3.333 2.500 1.897 76% 53% Work in progress.

858 2461Urban Sewerage & Drainage Scheme in M.C-02

Sargodha City.Sargodha

On-going

Schemes30.000 14.684 3.333 2.500 1.932 77% 55% Work in progress.

859 2462Urban Sewerage & Drainage Scheme in M.C-03

Sargodha City.Sargodha

On-going

Schemes30.000 9.580 3.333 2.500 1.901 76% 38% Work in progress.

860 2463Rehabilitation water supply scheme Bhera Town,

District SargodhaPhase-ISargodha

On-going

Schemes80.000 33.978 3.333 4.472 4.472 100% 48% Work in progress.

861 2464

Urban Water Supply Scheme Distribution System

Factory Area, Essa Nagar, Istaqlalabad, Hameed

Town, Corporation Town, Society Colony and

Nallah including Slab Karkhana Bazar Sargodha

City.

SargodhaOn-going

Schemes30.000 14.911 3.333 2.500 1.986 79% 56% Work in progress.

862 2465

Additional Water Supply pipeline in Cheema

Colony, Kalyar Town, Rehmat Park, Pir

Muhammad Colony & Adjoining Colonies

Sargodha City.

SargodhaOn-going

Schemes30.000 15.000 3.333 2.500 1.893 76% 56% Work in progress.

863 2466Rehabilitation of Water Supply Scheme New

Satellite Town Sargodha CitySargodha

On-going

Schemes50.000 20.000 3.333 2.500 2.003 80% 44% Work in progress.

864 2467Providing / Fixing Ultra Filtration Plants U.F / R.O

in Wards / M.Cs in PP-34 Sargodha City 10-No.Sargodha

On-going

Schemes40.000 25.000 3.333 2.500 1.899 76% 67% Work in progress.

865 2468

Up-gradation of Disposal Works in New Satellite

Town & Ghani Park and laying of Distribution

System in New Satellite Town & adjoining abadies

Sargodha City

SargodhaOn-going

Schemes48.000 27.221 3.333 2.500 2.500 100% 62% Work in progress.

866 2469Water supply scheme at Sobaga, Sillanwali,

District SargodhaSargodha

On-going

Schemes23.195 9.943 3.333 2.500 2.108 84% 52% Work in progress.

867 2470

Construction of PCC Tuff Tiles / Tuff Pever road

Liaqat Shaheed road to Merydal School & Suger

Mil road to Lalazar Colony road & Merydal School

to Sail Nallah & Pathan Wala road, Street Masjid

Wali, Bhalwal, District Sargodha

SargodhaOn-going

Schemes20.000 10.000 3.333 2.500 2.500 100% 63% Work in progress.

Page 57: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

868 2471Construciton of Sewerage Scheme, Tehsil

Sahiwal, District SargodhaSargodha

On-going

Schemes50.000 29.250 3.333 2.500 2.500 100% 64% Work in progress.

869 2472Construciton of Sewerage Scheme Farooqa,

District SargodhaSargodha

On-going

Schemes50.000 20.000 3.333 2.500 1.991 80% 44% Work in progress.

870 2473Construciton of Sewerage Scheme Vijh, Tehsil

Sahiwal, District SargodhaSargodha

On-going

Schemes30.000 8.200 3.333 2.500 1.894 76% 34% Work in progress.

871 2474Construciton of Sewerage Scheme Nehong, Tehsil

Sahiwal, District SargodhaSargodha

On-going

Schemes40.000 14.992 3.333 4.807 4.793 100% 49% Work in progress.

872 2475Extension of Rural Water Supply Scheme, Malwal,

District KhushabKhushab

On-going

Schemes24.530 9.979 4.843 3.632 3.630 100% 55%

Date of AA 29.7.2017 Date of award 09.12.2017

Date of completion 30.06.2019 Tube Well 1 No.

Pump House 1 No. Rising Main 9000/9000 Rft

D/System 5700/7970 Rft Work is in progress.

873 2476Provision of 100 Hand Pumps at Mahar Area,

District Khushab District KhushabKhushab

On-going

Schemes30.000 9.991 3.333 2.500 2.000 80% 40%

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of

award 23.12.2017 Date of completion 30.06.2020

Hand Pump 23/34 Nos. Bore with submersible

pump 13/29 Nos. G.S Tank 500 Glns 5/29 Nos.

874 2477Extension / Improvement of Water Supply Scheme,

Kuradhi UC Uchhali, District KhushabKhushab

On-going

Schemes21.225 3.000 3.333 2.500 2.250 90% 25%

Date of AA 29.07.2017 Date of TS 04.9.2017 Date

of award 18.12.2017 Date of completion 30.06.2020

Tube Well 1 No. Pump House 1 No. Pumping

Machinery 1 No. Rising Main 3240/28525 Rft Work

is in progress.

875 2478

Rehabilitation / Improvement of Water Supply

Scheme, Fateh Pur Maira UC Gunjial Shumali,

District Khushab

KhushabOn-going

Schemes12.400 5.595 2.133 1.600 1.440 90% 57%

Date of AA 29.07.2017 Date of TS 15.8.2015 Date

of award 08.01.2018 Date of completion 30.06.2019

Rising Main 9600/11500 Rft D/System 1800/2355

Rft Work is in progress.

876 2479Rehabilitation of Water Supply Scheme, Warcha

UC Warcha, District KhushabKhushab

On-going

Schemes25.000 9.999 3.333 2.500 2.250 90% 49%

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of

award 23.12.2017 Date of completion 30.06.2020

Tube Well 1 No. Pump House 1 No. Pumping

Machinery 1 No. Rising Main 11880/17875 Rft

D/System 0/1320 Rft Work is in progress.

877 2480Rehabilitation of Water Supply Scheme, Kufri UC

Kufri, District KhushabKhushab

On-going

Schemes15.230 8.750 1.743 1.307 1.180 90% 65%

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of

award 16.12.2017 Date of completion 30.06.2020

Tube Well 1 No. Pump House 1 No. Pumping

Machinery 1 No. Rising Main 12800/12807 Rft Work

is in progress.

878 2481Construciton of Water Supply Scheme of Rehman

Colony MC Hadhali, District KhushabKhushab

On-going

Schemes30.000 15.000 3.333 2.500 2.250 90% 58%

Date of AA 29.07.2017 Date of TS 4.9.2017 Date of

award 11.12.2017 Date of completion 30.06.2020

Tube Well 6/6 Set. Pumping Machinery 6 Nos.

Rising Main 50800/53196 Rft Work is in porgress.

879 2482Construciton of Water Supply Scheme of Zaman

Colony MC Hadhali, District KhushabKhushab

On-going

Schemes30.000 15.999 4.667 3.500 2.980 85% 63%

Date of AA 29.07.2017 Date of TS 4.9.2017 Date of

award 11.12.2017 Date of completion 30.06.2019

Tube Well 6 Nos. Pumping Machinery 6/6 Set.

Rising Main 49480/52184 Rft Work is in progress .

880 2483Provision of sewerage scheme Roda, District

KhushabKhushab

On-going

Schemes100.000 23.486 3.333 2.500 1.870 75% 25%

Date of AA 16.10.2017 Date of TS 15.8.2015 Date

of award 04.01.2018 Date of completion 30.06.2020

RCC Sewer 0/1500 Rft. PCC Slab 28522/293128

Cft Work is in progress.

881 2484Provision of Drainage System in MC Mitha Tiwana,

District KhushabKhushab

On-going

Schemes49.900 14.997 3.333 2.500 1.875 75% 34%

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of

award 08.12.2017 Date of completion 30.06.2020

PCC Slab 60101/89202 Cft Surface Drain 0/19550

Rft Sullage Carrier 0/10715 Rft Work is in progress.

882 2485Provision of Drainage System in MC QuaidaAbad,

District KhushabKhushab

On-going

Schemes49.831 16.993 3.333 2.500 1.880 75% 38%

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of

award 08.12.2017 Date of completion 30.06.2020

RCC Sewer 5786/18305 Rft PCC Slab 40186/76862

Cft Surface Drain 0/3000 Rft work is in progrss .

883 2486Provision of Drainage System in UC Ukhli Mohla,

District KhushabKhushab

On-going

Schemes18.025 9.998 2.675 2.006 1.500 75% 64%

Date of AA 29.07.2017 Date of TS 05.09.2017 Date

of award 09.12.2017 Date of completion 30.06.2019

PCC Slab 27608/54740 Cft work is in progress.

884 2487Construction of Drainage / Sewerage scheme,

Rehman Colony, MC Hadhali, District KhushabKhushab

On-going

Schemes32.000 9.999 3.333 2.500 1.870 75% 37%

Date of AA 29.07.2017 Date of TS 04.09.2017 Date

of award 09.12.2017 Date of completion 30.06.2020

RCC Sewer 7320/8700 Rft PCC Slab 17510/39304

Cft Surface Drain 4401/6000 Rft Work is in

progress.

885 2488Construction of Drainage / Sewerage scheme,

Zaman Colony, MC Hadhali, District KhushabKhushab

On-going

Schemes30.000 10.000 3.333 2.500 1.879 75% 40%

Date of AA 29.07.2017 Date of TS 04.09.2017 Date

of award 09.12.2017 Date of completion 30.06.2020

PCC Slab 24015/27284 Cft Surface Drain 513/5000

Rft Sullage Carrier 1800/15540 Rft Work is in

progress.

Page 58: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

886 2489Construction of PCC Derajat, UC Uttra, District

KhushabKhushab

On-going

Schemes20.000 9.998 3.333 2.500 1.880 75% 59%

Date of AA 29.7.2017 Date of TS 05.09.2017 Date

of award 07.12.2017 Date of completion 30.06.2019

PCC Slab 46175/66532 Cft Surface Drain 0/1470

Rft Work is in progress .

887 2490Construction of PCC Slab, UC Gunjial, District

KhushabKhushab

On-going

Schemes30.000 9.929 3.333 2.500 1.990 80% 40%

Date of AA 29.07.2017 Date of TS 05.09.2017 Date

of award 11.12.2017 Date of completion 30.06.2020

RCC Sewer 0/860 Rft Surface Drain 0/5000 Rft

PCC Slab 25515/63069 Cft Work is in progrss.

888 2491Construction of PCC Slab, UC 14 MB, District

KhushabKhushab

On-going

Schemes20.000 10.000 3.333 2.500 2.020 81% 60%

Date of AA 29.7.2017 Date of TS 05.09.2018 Date

of award 11.12.2017 Date of completion 30.06.2019

PCC Slab 42293/66326 Cft Surface Drain 900/1600

Rft Work is in progress.

889 2492Construction of Sewerage in, MC Mitha Twana,

District KhushabKhushab

On-going

Schemes100.000 15.490 3.333 2.500 1.870 75% 17%

Date of AA 11.08.2015 Date of TS 15.8.2015 Date

of award 28.03.2018 Date of completion 30.06.2020

PCC Slab 16620/78190 Cft Surface Drain

2661/18230 Rft Sullage Carrier 0/29400 Rft work is

in progress.

890 2493Provision of Sewerage and Sanitation at village

Dhoranka City, UC Namal, District MianwaliMianwali

On-going

Schemes20.000 1.996 3.333 2.500 1.667 67% 18%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks.RCC

Pipe Sewer 9"i/d=2900-Arranged/2957, 12"i/d=2800-

Arranged/2878, 15"i/d=1100-Arranged/1175,

18"i/d=800-Arranged/828, 21"i/d= 900-

Arranged/978, 24"i/d=0/942, Surface Drain=0/430,

PCC Slab=0/9035, Sullage Carrier

(1.25'x1.5')=0/100, (1.50'x2')=0/500,

(2.50'x4')=0/1400. Work is in progress.

891 2494Provision of Integrated Sewerage Scheme for Wan

Bhachran Town, District MianwaliMianwali

On-going

Schemes75.000 11.995 3.333 2.974 2.141 72% 19%

Date of A.A. 18-08-2017, Date of T.S. 13-11-2017,

Date of Start of Work 19-01-2018, Remarks. RCC

Sewer=9" i/d=0/6890, 12"i/d= 482-Laid & 5214-

Arranged/23310, 15"i/d= 6416-Arranged /6595,

18"i/d=2536-Arranged/2590, 21"i/d=0/150,

24"i/d=1600-Arranged/1635, 27"i/d=1656-

Arranged/1690, 30"i/d=1704-Arranged/1740,

33"i/d=407/510, Surface Drain= 0460, PCC Slab=

19713/98880, Sullage Carrier= 0/500, 0/150,

Screening Chamber=0/1, P/Machinery=0/1,

T/Line=0/1. Work is in progress.

892 2495Provision of Sewerage and Sanitation at UC Mari,

District MianwaliMianwali

On-going

Schemes20.000 12.997 2.333 1.750 1.165 67% 71%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks.RCC

Pipe Sewer 9"i/d=0/980, 12"i/d=0/2532,

15"i/d=0/1418, 18"i/d=0/930, Surface Drain=0/1040,

PCC Slab= 55632/28106, Sullage Carrier

(1.25'x1.5')=0/430, (1.50'x2') =0/1850, (2.50'x4')

=0/100 Work is in progress.

893 2496Provision of Sewerage and Sanitation at UC Kalon

Wala, District MianwaliMianwali

On-going

Schemes20.000 12.495 2.500 1.875 1.250 67% 69%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks.RCC

Pipe Sewer 12"i/d=372-Arranged/ 2393,

15"i/d=0/868, 18"i/d=0/636, Surface

Drain=700/4535, Sullage Carrier=0/955, PCC Slab=

47095/33241, Brick Pavement=0/51000. Work is in

progress.

894 2497Provision of Sewerage and Sanitation at UC

Manda Khel / Jalal Pur, District MianwaliMianwali

On-going

Schemes20.000 12.495 2.500 1.875 1.247 67% 69%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017-,

Date of Start of Work 29-10-2017, Remarks. RCC

Pipe Sewer 12"i/d=0/536, 24"i/d=0/257, Surface

Drain=491/3130, Sullage Carrier=350/850, PCC

Slab= 40772/56009. Work is in progress.

895 2498Installation of Submersible Pumps in PP-43 ,

District MianwaliMianwali

On-going

Schemes50.000 21.998 3.333 2.500 1.667 67% 47%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks.

ERS=116/116, Trial Bore=06/11, Tube Well =

28/58, Pumping Machinery= 28/58, G.S.Tank 500-

Glns=0/58. Work is in progress.

896 2499PCC Slab / Drainage Scheme UC Kot Chandna,

Tehsil Isa Khel, District MianwaliMianwali

On-going

Schemes20.000 12.499 2.500 1.875 1.250 67% 69%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks. PCC

Slab= 53864/ 59483, Surface Drain=1630/2900,

Sullage Carrier=0/350 Work is in progress.

897 2500Urban sewerage drainage scheme Isa Khel,

District MianwaliMianwali

On-going

Schemes20.000 9.999 3.333 2.500 1.662 66% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks. RCC

Pipe Sewer 12"i/d= 785/1284, 24"i/d =280/330,

Surface Drain= 1261/4540, Sullage Carrier=

540/1335, PCC Slab= 23154/28996, Tuff Tiles=

3238 /3564, Replacement of Rising Main 8"i/d

PE=2000/3335, 6"i/d PVC=0/60, 4"i/d PVC = 0/60,

3"i/d PVC= 0/660. Work is in progress.

Page 59: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

898 2501 PCC Slab at U.C Khaglanwala, District Mianwali MianwaliOn-going

Schemes20.000 10.000 3.333 2.500 1.666 67% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks. PCC

Slab=44695 /53023, Surface Drain=984/9255,

Sullage Carrier=150/150, RCC Sewer 12" =

318/335. Work is in progress.

899 2502 PCC Slab at U.C Vanjari, District Mianwali MianwaliOn-going

Schemes20.000 9.999 3.333 2.500 1.667 67% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks. PCC

Slab= 44443 /63118, Surface Drain=0/1055, Sullage

Carrier=0/120. Work is in progress.

900 2503 PCC Slab at U.C Chapri, District Mianwali MianwaliOn-going

Schemes20.000 9.998 3.333 2.500 1.661 66% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017. Remarks. PCC

Slab= 41949/59804, Surface Drain= 0/4235, Sullage

Carrier=0/600. Work is in progress.

901 2504PCC Slab at U.C Paka Kamar Mushani, District

MianwaliMianwali

On-going

Schemes20.000 6.999 3.333 2.500 1.665 67% 43%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017

Date of Start of Work 29-10-2017, Remarks. RCC

Pipe Sewer 12"i/d=862/1530, Surface

Drain=0/1720, Sullage Carrier=400/400, PCC

Slab=40973/57767. Work is in progress.

902 2505Construction of PCC Slab & Drain Kala Bagh Lari

Adda, District MianwaliMianwali

On-going

Schemes15.250 6.999 2.750 2.063 1.370 66% 55%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks.

Surface Drain=0/7230, Sullage Carrier=0/100, PCC

Slab=24252/35699, Tuff Tiles=0/15800. Work is in

progress.

903 2506Sewerage and Sanitation for Paki Shah Mardan

District MianwaliMianwali

On-going

Schemes30.000 9.991 3.333 2.500 1.661 66% 39%

Date of A.A. 01-08-2017, (Rev)Date of T.S.08-03-

2018, Date of Start of Work 29-10-2017, Remarks.

RCC Pipe Sewer 9"i/d=0/938, 12"i/d=590/4320,

15"i/d=1314/1276, 18"i/d= 2504/3950,

21"i/d=1812/1664, 24"i/d=1291/2062, Surface

Drain=0/120, PCC Slab=0/4600, Sullage

Carrier=350/1060. Work is in progress.

904 2507PCC Slab / Drainage Scheme UC vanjari, Tehsil

Isa Khel, District MianwaliMianwali

On-going

Schemes20.000 9.994 3.333 2.500 1.667 67% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks.RCC

Pipe Sewer 12"i/d=2592-Arranged/2595, 15"i/d=480-

Arranged/480, Surface Drain=0/4535, Sullage

Carrier=0/955, PCC Slab= 35812/44680. Work is in

progress.

905 2508PCC Slab / Drainage Scheme UC Pacca Kama

Mushani, Tehsil Isa Khel, District MianwaliMianwali

On-going

Schemes40.000 20.000 6.667 5.000 3.330 67% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks. RCC

Pipe Sewer 12"i/d=2550/2785, 15"i/d=0/660,

Surface Drain=0/1270, Sullage Carrier=0/350, PCC

Slab= 77311/107505 Work is in progress.

906 2509PCC Slab / Drainage Scheme UC Sultan Khel,

Thesil Isa Khel, District MianwaliMianwali

On-going

Schemes20.000 9.996 3.333 2.500 1.660 66% 58%

Date of A.A. 01-08-2017, Date of T.S. 08-08-2017,

Date of Start of Work 29-10-2017, Remarks. PCC

Slab= 41269/59297, Surface Drain 0/5945, Sullage

Carrier=0/200 Work is in progress.

907 2510

Construction of Sewerage / Drainage scheme i/c

PCC Pavement in Street village Hussasin Shah,

Tehsil Darya Khan District Bhakkar

BhakkarOn-going

Schemes64.920 10.000 3.333 2.500 2.500 100% 19%

"Date of A.A 10.08.2017 Date of T.S 13.09.2017

Date of Commencement 08.12.2017 Date of

completion 30.06.2020

908 2511

Construction of sullage carrier, surface drain, brick

pavement, PCC Slab, RCC Sewer and Disposal

Station in Sara-e-Mohajir, Chak No.250/TDA,

District Bhakkar.

BhakkarOn-going

Schemes48.600 10.500 3.333 2.500 2.500 100% 27%

"Date of A.A 10.08.2017Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

909 2512

Construction of sullage carrier, surface drain, brick

pavement, PCC Slab, RCC Sewer and Disposal

Station in Chak No.67/ML, District Bhakkar.

BhakkarOn-going

Schemes48.600 15.500 3.333 2.500 2.500 100% 37%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 02.11.2017 Date of

completion 30.06.2020

910 2513

Construction of sullage carrier, surface drain, brick

pavement, PCC Slab, RCC Sewer and Disposal

Station in Sara-e-Mohajir Chak No.71/ML, District

Bhakkar.

BhakkarOn-going

Schemes47.255 18.000 3.333 2.500 2.167 87% 43%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

911 2514

Construction of sullage carrier, surface drain, brick

pavement, PCC Slab, RCC Sewer and Disposal

Station at Adda Jahan Khan, Chak No.45/TDA,

District Bhakkar.

BhakkarOn-going

Schemes49.833 18.000 3.333 2.500 2.267 91% 41%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

Page 60: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

912 2515

Rural sewerage, drainage, PCC Slab / brick

pavement scheme in UC Katchi Shahani, Tehsil &

District Bhakkar

BhakkarOn-going

Schemes57.023 17.500 3.333 2.500 2.500 100% 35%

"Date of A.A 10.08.2017 Date of T.S 06.11.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

913 2516

Rural sewerage, drainage, PCC Slab / brick

pavement scheme in UC Sial, Tehsil & District

Bhakkar

BhakkarOn-going

Schemes59.573 20.000 3.333 2.500 2.500 100% 38%

"Date of A.A 10.08.2017 Date of T.S 06.11.2017

Date of Commencement 13.12.2017 Date of

completion 30.06.2020

914 2517

PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian /

and soling scheme UC Fazal, UC Chak No. 40/ML

UC Chak No. 63/DB, Tshil Kallur Kot, District

Bhakkar

BhakkarOn-going

Schemes30.000 10.000 6.667 5.000 3.934 79% 46%

"Date of A.A 10.08.2017 Date of T.S 18.18.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2019

915 2518

PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian /

and soling scheme UC Dali Namdar UC Ghulaman

No.1, UC Ghulaman No.2, Tehsil Kallur Kot,

District Bhakkar

BhakkarOn-going

Schemes40.000 15.000 3.333 2.500 1.667 67% 42%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

916 2519

PCC Slab/ Sewerage / Tuff tiles / RCC / Pullian /

and soling scheme UC Haitthu, UC Kalul, UC

Maibal, UC Kanjan and UC Noon Dagar, Tehsil

Kallur Kot, District Bhakkar

BhakkarOn-going

Schemes50.000 18.000 3.333 2.500 2.500 100% 41%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

917 2520

Provision of PCC Pavement / Slab, Sewerage,

Culverts and Soling in UC Khaawar kala, Majoka,

Lak Kalan, tehsil Darya Khan District Bhakkar

BhakkarOn-going

Schemes46.563 23.500 3.333 2.500 1.667 67% 54%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

918 2521

Provision of PCC Pavement / Slab, Sewerage,

Culverts and Soling in UC Dullaywala Rural,

Jhammat Shumali, Barranga, Tehsil Darya Khan

District Bhakkar

BhakkarOn-going

Schemes46.904 20.000 3.333 2.500 1.661 66% 46%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

919 2522

Provision of PCC Pavement / Slab, Sewerage,

Culverts and Soling in UC Daggar Qureshi,

Wahwara, Barkatwala, Tehsil Darya Khan District

Bhakkar.

BhakkarOn-going

Schemes36.304 15.000 3.333 2.500 1.660 66% 46%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

920 2523

Provision of PCC Pavement / Slab, Sewerage,

Culverts and Soling in UC Angra Daggar, Chak No

6/TDA, Gadai Tehsil Darya Khan District Bhakkar.

BhakkarOn-going

Schemes49.827 10.000 3.333 2.500 1.661 66% 23%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

921 2524

Provision of PCC Pavement / Slab, Sewerage,

Culverts and Soling in UC Punjigrain Daggar and

Nasheb, Tehsil Darya Khan District Bhakkar.

BhakkarOn-going

Schemes32.268 10.000 3.333 2.500 1.667 67% 36%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

922 2525

Construction of Sewerage / Drainage scheme i/c

PCC Pavement in Street village Sukha Shah,

Tehsil Darya Khan District Bhakkar

BhakkarOn-going

Schemes15.040 8.495 2.180 1.635 1.247 76% 65%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 03.11.2017 Date of

completion 30.06.2019

923 2526Construction of Sewerage / Drainage scheme

Baranga Tehsil Darya Khan, District BhakkarBhakkar

On-going

Schemes49.760 15.000 3.333 2.500 2.500 100% 35%

"Date of A.A 10.08.2017 Date of T.S 18.18.2017

Date of Commencement 02.11.2017 Date of

completion 30.06.2020

924 2527

Construction of Sewerage / Drainage scheme i/c

PCC Pavement in Street village Londi Nasheeb,

Tehsil Darya Khan, District Bhakkar

BhakkarOn-going

Schemes27.650 10.000 3.333 2.500 2.500 100% 45%

"Date of A.A 10.08.2017 Date of T.S 18.18.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

925 2528Rural Drainage scheme UC Goharwala and

Khansar., District BhakkarBhakkar

On-going

Schemes28.345 15.000 4.448 3.336 3.336 100% 65%

"Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 03.11.2017 Date of

completion 30.06.2019

926 2529Construction of sewerage / Drainage scheme in

Chak No. 49/TDA Tehsil and District BhakkarBhakkar

On-going

Schemes36.766 10.000 3.333 2.500 2.267 91% 33%

Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 02.11.2017 Date of

completion 30.06.2020

927 2530Construction of sewerage / Drainage scheme in

Chak No. 47/TDA Tehsil and District BhakkarBhakkar

On-going

Schemes45.685 5.000 3.333 2.500 2.500 100% 16%

Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 02.11.2017 Date of

completion 30.06.2020

Page 61: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

928 2531

Extension of Sewerage / Drainage Scheme and

PCC pavement in left over streets Darya Khan

City, Tehsil Darya Khan District Bhakkar.

BhakkarOn-going

Schemes50.000 22.499 3.333 2.500 2.060 82% 49%

Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

929 2532Sewerage scheme Kotla Jam, Tehsil & District

BhakkarBhakkar

On-going

Schemes48.611 4.000 3.333 2.500 1.660 66% 12%

Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

930 2533PCC Slab and Sewerage scheme MC jandanwala,

Tehsil Kallut Kot, District BhakkarBhakkar

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39%

Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

931 2534PCC Slab and Sewerage scheme MC Kallut Kot,

District BhakkarBhakkar

On-going

Schemes50.000 21.500 3.333 2.500 2.500 100% 48%

Date of A.A 10.08.2017 Date of T.S 18.08.2017

Date of Commencement 31.10.2017 Date of

completion 30.06.2020

932 2535

Construction of PCC, Soling & drains schemes in

Chak No.409 GB, 420 GB, 410 GB, 405 GB, 407

GB, 424 GB District Faisalabad

FaisalabadOn-going

Schemes15.500 10.000 1.833 1.375 0.917 67% 70%

Date of A.A 29-09-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

933 2536

Construction of PCC, Soling & drains schemes in

Chak No. 430 GB, 422GB, 423 GB, 427 GB, 428

GB, 425 GB, 404 GB District Faisalabad

FaisalabadOn-going

Schemes12.500 7.000 1.833 1.375 0.917 67% 63%

Date of A.A 29-09-2017. Date of T.S.05-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

934 2537

Construction of PCC, soling & drainage and

boundary walls of graveyards in Pindi Sheikh

Musa, Mobarik Pura, Chak No.451 GB, 429 GB,

400 GB, 408 GB & Nazir Colony District

Faisalabad

FaisalabadOn-going

Schemes17.000 5.889 2.333 1.750 1.167 67% 42%

Date of A.A 29-09-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

935 2538 Rural Drainage Scheme of Villages in NA-76 FaisalabadOn-going

Schemes150.000 39.926 6.667 5.000 3.334 67% 29%

ate of A.A 04-10-2017. Date of T.S.14-12-2017.

Work order issued on 01-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

936 2539Construction of Rural Drainage and PCC Road UC

30, 194/RB, District FaisalabadFaisalabad

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 19-01-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

937 2540Construction of Rural Drainage and PCC Road

,UC 60 District Faisalabad Faisalabad

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44%

ate of A.A 04-10-2017. Date of T.S.14-12-2017.

Work order issued on 01-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

938 2541Construction of Rural Drainage and PCC Road ,

UC 71 District Faisalabad Faisalabad

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44%

ate of A.A 04-10-2017. Date of T.S.14-12-2017.

Work order issued on 01-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

939 2542Construction of Rural Drainage and PCC Road at

U.C. 62 District Faisalabad Faisalabad

On-going

Schemes15.000 3.495 2.667 2.000 1.330 67% 32%

ate of A.A 04-10-2017. Date of T.S.14-12-2017.

Work order issued on 01-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

940 2543Construction of Rural Drainage and PCC Road at

U.C. 65 District Faisalabad Faisalabad

On-going

Schemes15.000 2.049 1.667 1.250 0.834 67% 19%

ate of A.A 04-10-2017. Date of T.S.14-12-2017.

Work order issued on 01-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

941 2544Construction of Rural Drainage and PCC Road at

U.C. 67 District Faisalabad Faisalabad

On-going

Schemes15.000 4.928 1.667 1.250 0.834 67% 38%

ate of A.A 04-10-2017. Date of T.S.14-12-2017.

Work order issued on 01-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

942 2545

Provision of Sewerage/ Drainage Facilities in PP-

57, District Faisalabad FaisalabadOn-going

Schemes50.000 19.297 3.333 2.500 1.667 67% 42%

Date of A.A 27-10-2017. Date of T.S.28-10-2017.

Work order issued on 30-11-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

943 2546Rural Drainage Scheme for Muncipal committee

Samundri District Faisalabad Faisalabad

On-going

Schemes49.888 29.937 3.333 2.500 1.667 67% 63%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 19-01-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

944 2547Rural Drainage Scheme for Samundri District

Faisalabad Faisalabad

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 19-01-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

945 2548Rural Drainage Scheme at Chak No. 263/RB,

Dijkot Town Committee Tehsil ,District Faisalabad Faisalabad

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 19-01-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

Page 62: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

946 2549Rural Water Supply Scheme chak No. 203\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes23.880 10.000 4.627 3.470 2.314 67% 52%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

947 2550Rural Water supply Scheme chak no. 199\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes13.434 10.000 1.145 0.859 0.573 67% 79%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

948 2551Rural Water supply Scheme chak no. 208\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes20.359 10.000 3.453 2.590 1.727 67% 58%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

949 2552PCC / Seewrage etc. Scheme Jaranwala City in

NA-76Faisalabad

On-going

Schemes100.000 20.877 6.667 5.000 3.334 67% 24%

Date of A.A 02-10-2017. Date of T.S.02-11-2017.

Work order issued on 01-03-2018. Work is in

progress.Funds released on 03.08.2018& 24.1.19.

950 2553

Provision of Solling / Nalian / Drainage in

Tandlianwala City , Mamu kanjan City, UC's

76,77,78,79,80,81,82,83,84,85,86,87, 88, 89, 90,

91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102,

103, 104, Tehsil Tandlianwala District Faisalabad

FaisalabadOn-going

Schemes126.000 24.631 6.667 5.000 3.334 67% 22%

Date of A.A 09-10-2017. Date of T.S.02-11-2017.

Work order issued on 01-02-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

951 2554Rural Water supply Scheme chak no. 209\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes19.412 10.000 3.137 2.353 1.569 67% 60%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

952 2555Rural Water supply Scheme chak no. 212\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes12.439 10.000 0.813 0.610 0.407 67% 84%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

953 2556Rural Water supply Scheme chak no. 207\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes26.341 10.000 3.333 2.500 1.667 67% 44%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

954 2557Rural Water supply Scheme chak no. 211\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes11.338 6.000 1.779 1.334 0.890 67% 61%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

955 2558Rural Water supply Scheme chak no. 202\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes12.378 6.000 2.126 1.595 1.063 67% 57%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

956 2559Rural Water supply Scheme chak no. 200\GB

Tehsil Samundari District Faisalabad Faisalabad

On-going

Schemes11.850 6.000 1.950 1.463 0.975 67% 59%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

957 2560

Construction of Soling, Nallian, Pullian, Nallah and

Water Supply at Chak No. 5 GB Kamal Pur UC

168 in District Faisalabad

FaisalabadOn-going

Schemes37.222 15.000 3.333 2.500 1.667 67% 45%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress.Funds released on 03.08.2018 & 24.1.19.

958 2561

Construction of Soling, Nallian, Pullian, Nallah and

Water Supply at Chak No. 52 GB malal Pur UC

166 in District Faisalabad

FaisalabadOn-going

Schemes22.692 10.000 4.231 3.173 2.116 67% 53%

Date of A.A 05-08-2017. Date of T.S.16-09-2017.

Work order issued on 31-10-2017. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

959 2562Construction of PCC different streets UC-4 UC-6

UC-7 UC-8 in District Faisalabad Faisalabad

On-going

Schemes40.000 18.000 1.000 0.750 0.500 67% 46%

AA issued on 05.08.2017. Date of T.S 16.09.2017

Work order issued on 23.11.2018. Work is in

progress. Funds released on 12.06.2018 & 24.1.19.

960 2563Construction of PCC different streets UC-9 UC-10

UC-11UC-12 in District Faisalabad Faisalabad

On-going

Schemes30.000 15.000 1.000 0.750 0.500 67% 52%

AA issued on 05.08.2017. Date of T.S 16.09.2017

Work order issued on 13.06.2018. Work is in

progress. Funds released on 23.11.2018 & 24.1.19.

961 2564Construction of PCC different streets UC-14 UC-15

UC-17 in District Faisalabad Faisalabad

On-going

Schemes20.000 10.000 1.000 0.750 0.500 67% 53%

AA issued on 05.08.2017. Date of T.S 16.09.2017

Work order issued on 12.06.2018. Work is in

progress. Funds released on 23.11.2018 & 24.1.19.

962 2565 Construction of PCC Streets in District Faisalabad FaisalabadOn-going

Schemes75.000 25.000 6.667 5.000 3.334 67% 38%

Date of A.A 02-10-2017. Date of T.S.01-11-2017.

Work order issued on 08-02-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

963 2566Sewerage Sheme in 240GB and additional

AbadiesFaisalabad

On-going

Schemes30.000 20.000 3.333 2.500 1.960 78% 73%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 19-01-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

964 2567Provision of PCC / Sewerage / Drainage / Tuff Tile

and etc in PP-53, District FaisalabadFaisalabad

On-going

Schemes50.000 25.000 3.333 2.500 1.667 67% 53%

Date of A.A 29-08-2017. Date of T.S.05-09-2017.

Work order issued on 19-01-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

Page 63: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

965 2568Water Supply Schemes in Constitutency NA-80,

District Faisalabad Faisalabad

On-going

Schemes122.000 35.000 6.667 5.000 3.334 67% 31%

Date of A.A 19-09-2017. Date of T.S.20-11-2017.

Work order issued on 01-02-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

966 2569Provision of Installation of New Water Plant in

District Faisalabad Faisalabad

On-going

Schemes75.000 34.862 6.667 5.000 3.334 67% 51%

Date of A.A 02-10-2017. Date of T.S.17-11-2017.

Work order issued on 03-03-2018. Work is in

progress. Funds released on 03.08.2018 & 24.1.19.

967 2570Soling / Drains / Culverts / PCC Slabs / UC No.1 to

UC No.8 Tehsil & District Jhang Jhang

On-going

Schemes13.000 6.996 2.000 1.500 1.166 78% 63%

Date of A.A 01.08.2017 Date of T.S 06.09.2017

Work order issued on 31.10.2017 Work is in

progress.

968 2571 Drainage Scheme Chak no. 479/JB District Jhang. JhangOn-going

Schemes16.749 6.991 3.250 2.438 1.935 79% 53%

Date of A.A 01.08.2017 Date of T.S 06.09.2017

Work order issued on 31.10.2017 Work is in

progress.

969 2572 Drainage Scheme Chak no. 482/JB District Jhang. JhangOn-going

Schemes20.489 4.982 3.333 2.500 1.943 78% 34%

Date of A.A 01.08.2017 Date of T.S 06.09.2017

Work order issued on 31.10.2017 Work is in

progress.

970 2573 Drainage Scheme Chak no. 493/JB District Jhang. JhangOn-going

Schemes30.614 11.999 3.333 2.500 1.999 80% 46%

Date of A.A 01.08.2017 Date of T.S 06.09.2017

Work order issued on 31.10.2017 Work is in

progress.

971 2574

Construction of Soling, Drains, PCC and Sullage at

Sammunduana, Tehsil Ahmad Pur Sial District

Jhang.

JhangOn-going

Schemes14.354 9.855 1.451 1.088 0.846 78% 75%

Date of A.A 01.08.2017 Date of T.S 06.09.2017

Work order issued on 31.10.2017 Work is in

progress.

972 2575Rural Drainage Scheme at Different Villages, 18

Hazari, in District JhangJhang

On-going

Schemes40.000 19.996 3.333 2.500 2.010 80% 55%

Date of A.A 01.08.2017 Date of T.S 13.09.2017

Work order issued on 23.12.2017. Work is in

progress.

973 2576

Water Supply Scheme Chak No. 412 Cheemia

Wali, Tehsil Shorkot, District Jhang and

Construction of Tank for Water Supply Scheme

Chak No. 412 Cheemia Wali.

JhangOn-going

Schemes20.303 9.990 3.434 2.576 2.150 83% 60%

Date of A.A 01.08.2017 Date of T.S 13.09.2017

Work order issued on 23.11.2017 Work is in

progress.

974 2577Provision of Water Supply at Chak No. 498 Tehsil

Shorkot, District Jhang.Jhang

On-going

Schemes22.000 9.993 4.000 3.000 2.433 81% 56%

Date of A.A 01.08.2017 Date of T.S 13.09.2017

Work order issued on 23.11.2017 Work is in

progress.

975 2578Provision of Sewerage & drainage At UC-46

Rustam Sargana Tehsil shorkot.Jhang

On-going

Schemes15.000 6.899 2.667 2.000 1.554 78% 56%

Date of A.A 01.08.2017 Date of T.S 06.09.2017

Work order issued on 31.10.2017 Work is in

progress.

976 2579

Sewerage / Drainage Scheme for Tehsil

Headquartar Ahmad Pur Sial District Jhang Phase-

2.

JhangOn-going

Schemes100.000 39.962 6.667 5.000 3.900 78% 44%

Date of A.A 19.09.2017 Date of T.S 09.10.2017

Work order issued on 17.01.2018 Work is in

progress.

977 2580Hazrat Peer Abdur rehman Sewerage Scheme

District Jhang.Jhang

On-going

Schemes70.000 24.580 6.667 5.000 3.886 78% 41%

Date of A.A 19.09.2017 Date of T.S 28.09.2017

Work order issued on 13.01.2018 Work is in

progress.

978 2581Provision of 16 nos. Water Filtration Plants in

Tehsil 18 Hazari, District Jhang.Jhang

On-going

Schemes40.000 0.600 3.333 2.500 2.001 80% 7%

Date of A.A 18.10.2017 Date of T.S 31.10.2017

Work order issued on 13.08.2018. Work is in

progress.

979 2582

Provision of Drainage and Soling and Replacement

/ new Water Supply Pipelines in UC 18 District T.T.

Singh.

Toba Tek SinghOn-going

Schemes13.000 7.465 1.833 1.375 1.200 87% 67%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

980 2583

Provision of Drainage and Soling and Replacement

/ new Water Supply Pipelines in UC 34 District T.T.

Singh.

Toba Tek SinghOn-going

Schemes12.500 6.225 2.083 1.562 1.042 67% 58%

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

981 2584

Laying of Soling, Resoling, Drain, Repair of Roads

and Piplelines Water and Sewerage in District

T.T.Singh.

Toba Tek SinghOn-going

Schemes315.000 65.000 3.333 2.500 1.900 76% 21%

1-Date of A.A 28.09.2017 2- Date of T.S 19.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

Page 64: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

982 2585

Laying of PCC, Tuff Tiles, Soling and Resoling,

Drain, Repair of Roads and Pipelines of water and

Sewerage in District T.T.Singh.

Toba Tek SinghOn-going

Schemes85.000 34.899 1.000 1.667 1.650 99% 43%

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 - 11-Re-appropriation of funds (+/-)

Work in progress.

983 2586

Rehablitation of Rural Water Supply Scheme Chak

# 148/ GB, 149/GB, 151/GB ,153/GB, Balgn,

294/JB, 350/GB, Rural Water Supply Scheme

Chak # 258/GB Noor Mahal and 292/GB Bara

Rasla in District T.T.Singh.

Toba Tek SinghOn-going

Schemes185.086 40.000 3.333 2.500 2.000 80% 23%

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary 7006 Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

984 2587

Rehabalitation of Rural Water Supply Scheme

Chak # 402/JB Virkan348/GB Bajra, 296/GB,

297/GB, 299/GB, 290/GB, 349/GB, and 351/GB in

District T.T.Singh.

Toba Tek SinghOn-going

Schemes178.792 68.399 3.333 3.000 2.167 72% 39%

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -4383 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

985 2588Water Supply Scheme in Chak no. 374/JB, 387/JB,

385/JB, District T.T.Singh.Toba Tek Singh

On-going

Schemes35.000 11.964 3.333 2.500 2.000 80% 40%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -3360 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

986 2589Drainage/Soling and Water Supply and Road

Repair UC No. 26 in District T.T.Singh.Toba Tek Singh

On-going

Schemes12.000 6.000 2.000 1.500 0.980 65% 58%

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

987 2590Drainage/Soling and Water Supply and Road

Repair UC No. 28 in District T.T.Singh.Toba Tek Singh

On-going

Schemes12.000 5.956 2.000 1.500 0.985 66% 58%

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

988 2591Drainage/Soling and Water Supply and Road

Repair UC No. 32 in District T.T.Singh.Toba Tek Singh

On-going

Schemes12.000 6.000 2.000 1.500 0.970 65% 58%

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

989 2592Drainage/Soling and Water Supply and Road

Repair UC No. 30 in District T.T.Singh.Toba Tek Singh

On-going

Schemes12.000 5.984 2.000 1.500 0.967 64% 58%

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

990 2593

Rural Water Supply Scheme Chak No. 321/GB

Khumanwala Tehsil Pirmahal District Toba Tek

Singh, Chak No. 700/42 GB Pir Kadhiana –

Christian Colony Tehsil Pirmahal District Toba Tek

Singh, Chak No. 294/GB azafi abadi Tehsil &

District Toba Tek Singh.

Toba Tek SinghOn-going

Schemes49.970 17.999 5.000 3.750 3.500 93% 43%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -5847 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

Page 65: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

991 2594

Rehabilitation of Rural Water Supply Scheme

Chak No. 301/GB azafi abadi – New Chak Tehsil &

District Toba Tek Singh, Chak No. 303/GB azafi

abadi Tehsil & District Toba Tek Singh, Chak No.

333/GB, District Toba Tek Singh, Chak No.

341/GB Tehsil & District

Toba Tek SinghOn-going

Schemes72.396 20.000 3.333 2.500 1.665 67% 30%

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 22.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

992 2595

Extension / Rehabilitation Rural Water Supply

Scheme Chak No.325 and 326/ GB, District T.T

Singh.

Toba Tek SinghOn-going

Schemes24.600 19.000 1.867 0.600 0.400 67% 79%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - 13647 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

993 2596Rural Water Supply Scheme Chak No. 671/12-

GBDistrict T.T. Singh.Toba Tek Singh

On-going

Schemes21.500 15.000 2.167 2.425 2.000 82% 79%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - 4716 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

994 2597Rural Water Supply Scheme Chak No.711/GB

District T.T. Singh.Toba Tek Singh

On-going

Schemes15.400 7.000 2.800 0.795 0.095 12% 46%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -5309 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work could not be started due to site

problem.

995 2598Rural Water Supply Scheme Chak No.662/3-GB

District T.T. Singh.Toba Tek Singh

On-going

Schemes29.500 10.000 3.333 2.500 1.667 67% 40%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - 8625 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

996 2599Rural Water Supply Scheme Chak No706/GB.

District T.T. SinghToba Tek Singh

On-going

Schemes27.300 11.998 5.100 3.825 2.500 65% 53%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - 6164 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

997 2600Rural Water Supply Scheme Chak No.720/GB

District T.T. Singh.Toba Tek Singh

On-going

Schemes24.750 17.000 2.583 1.937 1.500 77% 75%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -11853 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

998 2601Rural Water Supply Scheme Chak No.721/GB

District T.T. Singh.Toba Tek Singh

On-going

Schemes25.700 14.799 3.633 2.725 1.800 66% 65%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -8765 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work in progress.

999 2602Rural Water Supply Scheme Chak No.722/GB

District T.T. SinghToba Tek Singh

On-going

Schemes23.500 13.999 3.167 0.885 0.094 11% 60%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary -6826 Person 10-Funds Released by

F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation

of funds (+/-) Work could not be started due to site

problem.

Page 66: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1000 2603

Water Supply Scheme Chak No. 317/JB and

Installation of Filtration Plant in Chak No.401/JB

District T.T.Singh

Toba Tek SinghOn-going

Schemes24.587 10.000 4.862 3.647 3.200 88% 54%

1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018

3-Date of Prequalification 4-Date of invitation of

tenders 05.03.2018 5- Date of Receipt of tenders

06.03.2018 6- Date of work order 27.03.2018 7-

Date of completion as per PC-I 8- Anticipated date

of completion 9- No. of Beneficiary -.. Person 10-

Funds Released by F.D 03.08.2018 & 24.01.2019

11-Re-appropriation of funds (+/-) Work in progress.

1001 2604

Rehabilitation / Improvemnet of Rural Draiange

Scheme Chak no. 402/GB Virkan Tehsil and

District T.T.Singh

Toba Tek SinghOn-going

Schemes35.000 3.999 1.667 1.250 0.834 67% 14%

1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018

3-Date of Prequalification 4-Date of invitation of

tenders 05.03.2018 5- Date of Receipt of tenders

06.03.2018 6- Date of work order 03.04.2018 7-

Date of completion as per PC-I 8- Anticipated date

of completion 9- No. of Beneficiary -.. Person 10-

Funds Released by F.D 03.08.2018 & 24.01.2019

11-Re-appropriation of funds (+/-) Work in progress.

1002 2605

Provision of Soling / Re-Soling Nali / Sewerage /

PCC and Tuff Tile Schemes in City Kamalia In

District T.T.Singh

Toba Tek SinghOn-going

Schemes20.000 9.998 3.333 2.500 2.200 88% 61%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1003 2606

Soling Drainage Khalla Nalli and Pullian in UC 57,

58, 59, 60, 61, 62, 63, 66, 68, Chak No. 735/GB in

Tehsil Kamalia District T.T.Singh

Toba Tek SinghOn-going

Schemes60.000 20.000 3.333 2.500 2.000 80% 37%

1-Date of A.A 19.09.2017 2- Date of T.S 12.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 18.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1004 2607Tuff Tile PCC Soling / Drainage / Sewerage in

Kamalia City Tehsil Kamalia District T.T.Singh Toba Tek Singh

On-going

Schemes40.000 13.662 1.667 1.250 0.834 67% 36%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1005 2608Tuff Tile PCC Soling / Re-soling Drainag,

Sewerage etc for Kamalia City Toba Tek Singh

On-going

Schemes40.000 14.999 1.667 1.250 1.000 80% 40%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1006 2609Construction of PCC / Tuff tile/Soling/Resoling

Pirmahal City in District T.Tsingh Toba Tek Singh

On-going

Schemes25.000 10.000 5.000 3.750 3.000 80% 52%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1007 2610

Provision of Drainage and Soling and Replacement

/ new Water Supply Pipelines in UC 17 District T.T.

Singh.

Toba Tek SinghOn-going

Schemes32.000 12.000 1.667 1.250 1.000 80% 41%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-). Work in progress.

1008 2611Provision of Tuff Paver and Drains in Kamalia City,

District T.T.SinghToba Tek Singh

On-going

Schemes40.000 15.000 1.667 9.451 9.451 100% 61%

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 11-Re-appropriation of

funds (+/-) Work in progress.

Page 67: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1009 2612Provision of Tuff Paver and Drains in Pir Mahal

City, District T.T.Singh.Toba Tek Singh

On-going

Schemes40.000 15.000 1.667 0.483 0.300 62% 38%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1010 2613

Provision of Drainage and Soling and Replacement

/ new Water Supply Pipelines in UC 14 District T.T.

Singh.

Toba Tek SinghOn-going

Schemes15.000 7.500 2.500 1.875 1.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1011 2614

Provision of Drainage and Soling and Replacement

/ new Water Supply Pipelines in UC 15 District T.T.

Singh.

Toba Tek SinghOn-going

Schemes31.000 20.000 3.333 2.500 1.667 67% 70%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1012 2615

Provision of Drainage and Soling and Replacement

/ new Water Supply Pipelines in UC 16 District T.T.

Singh.

Toba Tek SinghOn-going

Schemes13.000 7.500 1.833 1.375 0.912 66% 65%

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1013 2616Rural Drainage/Brick Pavement/Resoling Chak No.

672/13 GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.455 0.500 0.375 0.249 66% 57%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1014 2617

Rural Drainage/Brick Pavement/Resoling Chak No.

673/14/GB Harisabad & azafi abadi in District

T.Tsingh

Toba Tek SinghOn-going

Schemes3.000 1.422 0.500 0.375 0.250 67% 56%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1015 2618Rural Drainage/Brick Pavement/Resoling Chak No.

675/16/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) .Work in progress.

1016 2619Rural Drainage/Brick Pavement/Resoling Chak No.

676/17/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.498 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1017 2620Rural Drainage/Brick Pavement/Resoling Mouza

Shahpur & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.000 0.667 0.500 0.334 67% 44%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

Page 68: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1018 2621Rural Drainage/Brick Pavement/Resoling Mouza

Nakrari & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 0.997 0.667 0.500 0.334 67% 44%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1019 2622Rural Drainage/Brick Pavement/Resoling Mouza

Bub & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes2.500 0.952 1.548 1.161 0.700 60% 66%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

23.11.2018 - 11-Re-appropriation of funds (+/-)

Work in progress.

1020 2623Provision of Sewerage / Drainage / Tuff Tiles etc in

District T.T.Singh.Toba Tek Singh

On-going

Schemes199.924 99.996 5.000 3.750 2.500 67% 51%

1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 18.11.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1021 2624Rural Drainage/Brick Pavement/Resoling Plot-A &

azafi abadi in District T.TsinghToba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1022 2625Rural Drainage/Brick Pavement/Resoling Chak No.

718/GB & azafi abadi in District T.TsinghToba Tek Singh

On-going

Schemes3.000 1.499 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1023 2626Rural Drainage/Brick Pavement/Resoling Chak No.

719/GB & azafi abadi in District T.TsinghToba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1024 2627Rural Drainage/Brick Pavement/Resoling Chak No.

720/GB & azafi abadi in District T.TsinghToba Tek Singh

On-going

Schemes3.000 1.478 0.500 0.375 0.247 66% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1025 2628Rural Drainage/Brick Pavement/Resoling Chak No.

722/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.244 65% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1026 2629Rural Drainage/Brick Pavement/Resoling Chak No.

741/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.020 0.500 0.375 0.245 65% 42%

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

Page 69: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1027 2630Rural Drainage/Brick Pavement/Resoling Chak No.

747/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 0.595 0.500 0.375 0.246 66% 28%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1028 2631Rural Drainage/Brick Pavement/Resoling Chak No.

757/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes2.500 1.204 0.417 0.313 0.200 64% 56%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1029 2632Rural Drainage/Brick Pavement/Resoling Chak No.

759/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.248 66% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) .Work in progress.

1030 2633Rural Drainage/Brick Pavement/Resoling Chak No.

760/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes2.500 1.250 0.417 0.313 0.203 65% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1031 2634Rural Drainage/Brick Pavement/Resoling Chak No.

764/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1032 2635Rural Drainage/Brick Pavement/Resoling Chak No.

660/1/GB & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) Work in progress.

1033 2636Rural Drainage/Brick Pavement/Resoling Mouza

Inayat Shah & azafi abadi in District T.Tsingh Toba Tek Singh

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017

3-Date of Prequalification 4-Date of invitation of

tenders 5- Date of Receipt of tenders 6- Date of

work order 31.10.2017 7- Date of completion as per

PC-I 8- Anticipated date of completion 9- No. of

Beneficiary - Person 10-Funds Released by F.D

03.08.2018 & 24.01.2019 - 11-Re-appropriation of

funds (+/-) . Work in progress.

1034 2637Constructoin of Drains PCC / RCC in UC Qila Mian

Singh Uggu Chak District Gujranwala Gujranwala

On-going

Schemes50.000 13.000 5.000 3.750 2.500 67% 31% Work in progress

1035 2638Sewerage PCC Drainage in UC Wahndo / UC

Chak Ramdas in District Gujranwala Gujranwala

On-going

Schemes60.000 19.991 6.667 5.000 3.334 67% 39% Work in progress

1036 2639

Construction of PCC and Sewerage at Y-Block

Peoples Colony, X-Block Behari Colony, Shadman

Town, Green Town Ahsan Town, Hassan Town

District Gujranwala

GujranwalaOn-going

Schemes20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress

1037 2640

Construction of PCC and Sewerage at Kot

Abdullah, Kangni Wala, Rana Colony, Saddique

Colony, Nabi Pura, Illama Iqbal Town in District

Gujranwala

GujranwalaOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress

Page 70: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1038 2641

Provision of Sewerage, PCC, Street, Drain, Tuff

Tile, Water Supply in City Wazirabad, Sodra,

District Gujranwala

GujranwalaOn-going

Schemes200.000 75.000 3.333 2.500 1.667 67% 38% Work in progress

1039 2642

Drainage and PCC Soling in UCs Nokhar,

Pheloke, Udowali, in Saharan Chatha District

Gujranwala

GujranwalaOn-going

Schemes88.947 19.901 3.333 2.500 1.667 67% 24% Work in progress

1040 2643

Drainage and PCC Soling in UCs Noi wala, Jattan

wali, Bheri Shah Rehman, Jhallan in District

Gujranwala

GujranwalaOn-going

Schemes89.034 17.820 3.333 2.500 1.667 67% 22% Work in progress

1041 2644

Drainage and PCC Soling in UCs Phama Sara,

Arghan, Chak Chaudhary, Kot Ladha, in District

Gujranwla

GujranwalaOn-going

Schemes89.776 20.000 3.333 2.500 1.667 67% 24% Work in progress

1042 2645

Construction of PCC Streets and Drainage in

Botala Sharam Singh / Akbarian, Sansera Goraya

and Muslim Chack, Attawa, Therri Sansi and

Chand da Qila, Kotli Dianat Raye and Sheray wala,

Nangray Dadan, Dera Bhaghat Singh and Dera

Hakam Singh, Chddiala Kalan and Khurd, Murali

wala and Khuwasra, Dhillian wali, Chianwall, Kot

Shera and Sahnaya wala

GujranwalaOn-going

Schemes50.000 20.000 30.000 22.500 15.000 67% 70% Work in progress

1043 2646

Construction of PCC and Sewerage at sarfaraz

Colony, Hashimi Colony, Gulshan Adeel, Mumtaz

Colony, Karmabad District Gujranwala

GujranwalaOn-going

Schemes40.000 15.000 1.667 1.250 0.834 67% 40% Work in progress

1044 2647

Construction of PCC and Sewerage at Asghar

Colony, Salamat Pura, Allah Bukhsh Colony,

Nawaz Colony, Faisal Colony District Gujranwala

GujranwalaOn-going

Schemes40.000 15.000 1.667 1.250 0.834 67% 40% Work in progress

1045 2648

Construction of PCC and Sewerage at Jinnah

Colony, Rehman Colony, Ali Pura, Bukhari Colony,

Sanat Road, Jamia Muhammadiya District

Gujranwala

GujranwalaOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress

1046 2649

Construction of PCC and Sewerage at Rasheed

Colony, Ismail Pura, Abdullah Colony, W Block

Peoples Colony District Gujranwala

GujranwalaOn-going

Schemes20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress

1047 2650

Construction of PCC and Sewerage at Z- Block

Peoples Colony, X-Block Peoples Colony District

Gujranwala

GujranwalaOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress

1048 2651

Construction of PCC and Sewerage at Chamra

Mandi, Wahdat Colony, Chaman Shah Road, Taj

Colony, Arfat Colony, Ferozwala Road in District

Gujranwala

GujranwalaOn-going

Schemes20.000 9.910 3.333 2.500 1.667 67% 58% Work in progress

1049 2652

Construction of PCC and Sewerage at Arfat

Colony, Islam Pura, Haidry Road in District

Gujranwala

GujranwalaOn-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress

1050 2653

Construction of PCC and Sewerage at Mujahid

Pura, Camp No. 4, Saithy Palaza, Faisal Colony,

in District Gujranwala

GujranwalaOn-going

Schemes15.000 9.999 1.667 1.250 0.834 67% 72% Work in progress

1051 2654

Construction of PCC and Sewerage at Galla

Ghulam Thakedar Wala, Galla Mehar Noor Wala,

Islam Pura, Muslim Road in District Gujranwala

GujranwalaOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress.

1052 2655Drainage and PCC at UC, 31,40,46 at District

Gujranwala Gujranwala

On-going

Schemes150.000 29.998 5.000 3.750 2.500 67% 22% Work in progress

Page 71: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1053 2656Construction of PCC/ Tuff Tile, Drainage and Allied

Facilities etc in NA-96, District GujranwalaGujranwala

On-going

Schemes50.000 29.987 3.333 2.500 1.667 67% 63% Work in progress

1054 2657Construction of PCC, Sewerage/Drains at UC 48

District Gujranwala Gujranwala

On-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress

1055 2658Construction of PCC, Sewerage/Drains at UC 49

District Gujranwala Gujranwala

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress

1056 2659Construction of PCC, Sewerage/Drains at UC 50

District Gujranwala Gujranwala

On-going

Schemes15.000 9.948 1.667 1.250 0.834 67% 72% Work in progress

1057 2660Construction of PCC, Sewerage/Drains at UC 51

District Gujranwala Gujranwala

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress

1058 2661Construction of PCC, Sewerage/Drains at UC 52

District Gujranwala Gujranwala

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress

1059 2662Construction of PCC, Sewerage/Drains at UC 53

District Gujranwala Gujranwala

On-going

Schemes20.000 9.920 3.333 2.500 1.667 67% 58% Work in progress

1060 2663Construction of PCC, Sewerage/Drains at UC 54

District Gujranwala Gujranwala

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress

1061 2664Construction of PCC, Sewerage/Drains at UC 57

District Gujranwala Gujranwala

On-going

Schemes20.000 9.982 3.333 2.500 1.667 67% 58% Work in progress

1062 2665Construction of PCC, Sewerage/Drains at UC 58

District Gujranwala Gujranwala

On-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress

1063 2666Construction of PCC, Sewerage/Drains at UC 59

District Gujranwala Gujranwala

On-going

Schemes20.000 9.954 3.333 2.500 1.667 67% 58% Work in progress

1064 2667Construction of PCC, Sewerage/Drains at UC 60

District Gujranwala Gujranwala

On-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Work in progress

1065 2668Construction of PCC, Sewerage/Drains at UC 62

District Gujranwala Gujranwala

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress

1066 2669

Provision of Sewerage, Drainage and PCC

Scheme UC Aroop, UC Butteranwali, District

Gujranwala, Phase-I

GujranwalaOn-going

Schemes200.000 40.000 3.333 2.500 1.667 67% 21% Work in progress

1067 2670

Provision of Sewerage, Drainage and PCC

Scheme for Area Rahwali Sharqi, Kot Shahan And

Trigri District Gujranwala

GujranwalaOn-going

Schemes100.000 30.000 3.333 2.500 1.667 67% 32% Work in progress

1068 2671Construction of PCC/RCC/Drainage at

Shaheenabad, Gujranwala Gujranwala

On-going

Schemes30.000 7.992 20.000 15.000 10.000 67% 60% Work in progress

1069 2672Construction of PCC/RCC/Drainage at Pasban

Colony, GujranwalaGujranwala

On-going

Schemes50.000 15.000 3.333 2.500 1.667 67% 33% Work in progress

1070 2673Construction of PCC/RCC/Drainage at Samnabad,

GujranwalaGujranwala

On-going

Schemes50.000 15.000 3.333 2.500 1.667 67% 33% Work in progress

1071 2674Construction of PCC/RCC/Drainage at

Gondalwala, GujranwalaGujranwala

On-going

Schemes30.000 7.000 3.333 2.500 1.667 67% 29% Work in progress

1072 2675Construction of PCC/RCC/Drainage at Aminpur,

GujranwalaGujranwala

On-going

Schemes30.000 7.989 3.333 2.500 1.667 67% 32% Work in progress

1073 2676Construction of PCC/RCC/Drainage at Badoki

Gusaian, GujranwalaGujranwala

On-going

Schemes30.000 8.000 3.333 2.500 1.667 67% 32% Work in progress

1074 2677Construction of PCC/RCC/Drainage at

Dingranwali, GujranwalaGujranwala

On-going

Schemes30.000 8.000 3.333 2.500 1.667 67% 32% Work in progress

1075 2678

Provision of PCC / Sewerage schemes near

Bypass Surrounding Abadies of Timber Market,

District Gujranwala

GujranwalaOn-going

Schemes190.600 40.000 30.000 22.500 15.000 67% 29% Work in progress

1076 2679Constructoin of Drains PCC / RCC in UC Kalaskay,

Banka, Ladheywala Cheema District Gujranwala Gujranwala

On-going

Schemes50.000 13.000 5.000 3.750 2.500 67% 31% Work in progress

1077 2680

Construction of Drains, PCC/RCC and Sullage

Carrier in Villages of U.C Chianwali in District

Gujranwala

GujranwalaOn-going

Schemes30.000 9.848 8.333 6.250 4.167 67% 47% Work in progress

Page 72: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1078 2681

Construction of Drains, PCC/RCC and Sullage

Carrier in Villages of U.C Ladhaywala Goraya in

District Gujranwala

GujranwalaOn-going

Schemes30.000 9.970 20.000 15.000 10.000 67% 67% Work in progress

1079 2682Sewerage PCC Drainage in UC Malkay / UC Mari

Thakran / UC Ghoma in District Gujranwala Gujranwala

On-going

Schemes80.000 23.483 5.000 3.750 2.500 67% 32% Work in progress

1080 2683Sewerage PCC Drainage in UC Talwandi MK / UC

Jandiala in District Gujranwala Gujranwala

On-going

Schemes60.000 29.963 5.000 3.750 2.500 67% 54% Work in progress

1081 2684Water Supply / PCC / Drainage Facility in Sodhrar

Town, Tehsil Wazirabad, District GujranwalaGujranwala

On-going

Schemes134.586 18.000 20.000 26.218 21.218 81% 29% Work in progress

1082 2685Construction of Streets and Drainage at UC Marri

Thakran, District Gujranwala Gujranwala

On-going

Schemes30.000 9.975 3.333 2.500 1.667 67% 39% Work in progress

1083 2686Construction of Streets and Drainage at UC Akbar

Ghanoke, District Gujranwala Gujranwala

On-going

Schemes30.000 9.972 3.333 2.500 1.667 67% 39% Work in progress

1084 2687Construction of Streets and Drainage at UC

Ghaniya District Gujranwala Gujranwala

On-going

Schemes30.000 9.988 3.333 2.500 1.667 67% 39% Work in progress

1085 2688Construction of Streets and Drainage at UC Guna

Aur District Gujranwala Gujranwala

On-going

Schemes30.000 9.947 3.333 2.500 1.667 67% 39% Work in progress

1086 2689Construction of Streets and Drainage at UC

Ghoma/Harpoki District Gujranwala Gujranwala

On-going

Schemes30.000 9.997 6.667 5.000 3.334 67% 44% Work in progress

1087 2690Construction of Streets and Drainage at UC

Machrala District Gujranwala Gujranwala

On-going

Schemes30.000 9.958 3.333 2.500 1.667 67% 39% Work in progress

1088 2691Construction of Streets and Drainage at UC Sadoki

District Gujranwala Gujranwala

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in progress

1089 2692Provision of Clean Water Facility in NA-95, District

GujranwalaGujranwala

On-going

Schemes200.000 66.995 5.000 3.750 2.500 67% 35% Work in progress

1090 2693Constructoin of Drains PCC / RCC in UC Botal

Jhanda Singh District Gujranwala Gujranwala

On-going

Schemes32.000 12.500 1.667 1.250 0.834 67% 42% Work in progress

1091 2694Sewerage PCC Drainage in UC Mokhal / UC

Nadala / UC Feroz wala in District Gujranwala Gujranwala

On-going

Schemes80.000 23.412 3.333 2.500 1.667 67% 31% Work in progress

1092 2695Sewerage PCC Drainage in UC Nangal Dona / UC

Machrala in District Gujranwala Gujranwala

On-going

Schemes80.000 23.345 3.333 2.500 1.667 67% 31% Work in progress

1093 2696Sewerage PCC Drainage in UC Sohawa / UC Kali

Suba in District Gujranwala Gujranwala

On-going

Schemes60.000 19.898 3.333 2.500 1.667 67% 36% Work in progress

1094 2697Sewerage PCC Drainage in UC Sadhoki / UC

Gunaur / UC Mandiala Tega in District Gujranwala Gujranwala

On-going

Schemes80.000 23.473 5.000 3.750 2.500 67% 32% Work in progress

1095 2698

Construction of Drains,PCC Sullage Carrier UC

Budha Graya Tehsil Nowshera Virkan District

Gujranwala

GujranwalaOn-going

Schemes20.000 9.953 3.333 2.500 1.667 67% 58% Work in progress

1096 2699

Construction of Drains,PCC Sullage Carrier UC

Boopra Kalan Tehsil Nowshera Virkan District

Gujranwala

GujranwalaOn-going

Schemes20.000 9.897 3.333 2.500 1.667 67% 58% Work in progress

1097 2700

Construction of Drains,PCC Sullage Carrier UC

Tatlay Aali Tehsil Nowshera Virkan District

Gujranwala

GujranwalaOn-going

Schemes20.000 9.999 3.333 2.500 1.667 67% 58% Work in progress

1098 2701

Construction of Drains,PCC Sullage Carrier UC

Matto Bbajme Tehsil Nowshera Virkan District

Gujranwala

GujranwalaOn-going

Schemes20.000 9.858 3.333 2.500 1.667 67% 58% Work in progress

1099 2702

Construction of Drains,PCC Sullage Carrier UC

Karyl Kalan Tehsil Nowshera Virkan District

Gujranwala

GujranwalaOn-going

Schemes20.000 9.997 3.333 2.500 1.667 67% 58% Work in progress

1100 2703

Provision of PCC / Sewerage / Drainage /Tuff Tiles

and allied facilities etc. in NA-101, District

Gujranwala

GujranwalaOn-going

Schemes100.000 28.000 5.000 3.750 2.500 67% 31% Work in progress

Page 73: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1101 2704

Provision of Water Filtration Plant / Drainage

System Chak Chatha U/C no. 15, District

Hafizabad

HafizabadOn-going

Schemes30.860 10.000 3.333 2.500 1.667 67% 38%

A.A.30.860 (M) T.S. 30.860 (M) work is in progress

Fund release but not yet online.

1102 2705

Constrcutinn of Drain / Nallah / PCC / Soling

Bateray, Kotli Amir Singh, Kallairwala, Muradian

U/C Sagar Khan, no. 12, District Hafizabad

HafizabadOn-going

Schemes50.000 19.999 3.333 2.500 1.667 67% 43%

A.A. 50.000 (M)T.S. 50.000 (M) work is in progress

Fund release but not yet online.

1103 2706Constrcutinn of Drain / Nallah / PCC / Soling U/C

No. 5, District HafizabadHafizabad

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43%

A.A. 50.000 (M) T.S. 50.000 (M) work is in progress

Fund release but not yet online.

1104 2707Constrcutinn of Drain / Nallah / PCC / Soling U/C

No. 14, District HafizabadHafizabad

On-going

Schemes50.000 19.810 3.333 4.167 3.334 80% 46%

A.A. 50.000 (M) T.S. 50.000 (M) work is in progress

Fund release but not yet online.

1105 2708

Constrcutinn of Drain / Nallah / PCC / Soling and

Sewer in village Vanike Tarar U/C No. 3, District

Hafizabad

HafizabadOn-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43%

A.A. 50.000 (M) T.S. 50.000 (M) work is in progress

Fund release but not yet online.

1106 2709

Rural Drainage Scheme Herdo Sagar, Dhnoi

Dogran, Praim Kot, Batairay, Wingay and

Bashmolajat District Hafizabad

HafizabadOn-going

Schemes25.005 10.000 5.002 2.352 1.090 46% 44%

A.A. 25.002 (M) T.S. 25.002 (M) work is in progress

Fund release but not yet online.

1107 2710

Rural Drainage Scheme Dhunni, Jaidkey, Chak

Chatha, Dahranwali, Thatha, Kharian, Peer Koot

and Bashmolajat District Hafizabad

HafizabadOn-going

Schemes25.002 9.999 5.001 3.751 2.490 66% 50%

A.A. 25.002 (M) T.S.25.002 (M) work is in progress

Fund release but not yet online.

1108 2711Construction of Streets Drains PCC/ Soling and

Nallah In Vilaage Kassesy District Hafizabad Hafizabad

On-going

Schemes20.000 10.000 3.333 4.000 1.667 42% 58%

A.A. 20.000 (M) T.S. 20.000 (M)work is in progress

Fund release but not yet online.

1109 2712Construction of Streets Drains PCC/ Soling and

Nalla In Village Tibba Shah Balol District Hafizabad Hafizabad

On-going

Schemes20.000 9.925 3.333 2.500 1.660 66% 58%

A.A. 20.000 (M) T.S. 20.000 (M) work is in progress

Fund release but not yet online.

1110 2713Construction of Streets Drains PCC/ Soling and

Nallah In Village Kot Khush hall District Hafizabad Hafizabad

On-going

Schemes20.000 9.978 3.333 2.500 1.660 66% 58%

A.A. 20.000 (M)T.S.20.000 (M) work is in progress

Fund release but not yet online.

1111 2714

Construction of Streets Drains PCC/ Soling and

Nallah In Village Tali Goraya and Jasso ke District

Hafizabad

HafizabadOn-going

Schemes25.000 9.763 5.000 3.750 2.490 66% 49%

A.A. 25.000 (M) T.S. 25.000 (M) work is in progress

Fund release but not yet online.

1112 2715

Construction of Streets Drains PCC/ Soling and

Nallah In Village Narowal Dera Jaat District

Hafizabad

HafizabadOn-going

Schemes20.000 10.000 3.333 2.500 1.660 66% 58%

A.A. 20.000 (M) T.S. 20.000 (M) work in progress.

Fund release but not yet online.

1113 2716Construction of Streets Drains PCC/ Soling and

Nallah In Village Chak No. 474 District Hafizabad Hafizabad

On-going

Schemes15.000 10.000 1.667 1.250 0.830 66% 72%

A.A. 15.000 (M) T.S. 15.000 (M) work is in progress

Fund release but not yet online.

1114 2717Construction of Streets Drains PCC/ Soling and

Nallah In Village Matay Ke District Hafizabad Hafizabad

On-going

Schemes15.000 9.719 1.667 0.750 0.330 44% 67%

A.A. 15.000 (M) T.S. 15.000 (M) work is in progress

Fund release but not yet online.

1115 2718Construction of Streets Drains PCC/ Soling and

Nallah In Village Badr Ali District Hafizabad Hafizabad

On-going

Schemes15.000 9.942 1.667 1.250 0.830 66% 72%

A.A. 15.000 (M) T.S.15.000 (M) work is in progress

Fund release but not yet online.

1116 2719Construction of Streets Drains PCC/ Soling and

Nallah In Village Mustafa Abad District Hafizabad Hafizabad

On-going

Schemes15.000 9.959 1.667 2.284 1.034 45% 73%

A.A. 15.000 (M) T.S.15.000 (M) work is in progress

Fund release but not yet online.

1117 2720Provision of Water Filtration Plant / Drainage

System Kolo Tarar U/C no. 8, District Hafizabad Hafizabad

On-going

Schemes36.585 11.209 3.333 2.500 1.660 66% 35%

A.A. 36.585 (M) T.S.36.585 (M) work is in progress

Fund release but not yet online.

1118 2721

Provision of Water Filtration Plant / Drainage

System Kot Said Muhammad U/C No. 1, District

Hafizabad

HafizabadOn-going

Schemes31.854 11.999 3.333 2.500 1.667 67% 43%

A.A. 31.854 (M) T.S.31.854 (M) work is in progress

Fund release but not yet online.

1119 2722Provision of Water Filtration Plant / Drainage

System, Kot Ishaq U/C No. 2, District Hafizabad Hafizabad

On-going

Schemes27.539 13.000 4.846 3.635 2.423 67% 56%

A.A. 27.539 (M) T.S.27.539 (M) work is in progress

Fund release but not yet online.

Page 74: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1120 2723Provision of Water Filtration Plant / Drainage

System Vanike Tarar U/C No. 3, District Hafizabad Hafizabad

On-going

Schemes61.830 20.000 6.667 5.000 3.330 67% 38%

A.A. 61.830 (M) T.S.61.830 (M) work is in progress

Fund release but not yet online.

1121 2724Provision of Water Filtration Plant / Drainage

System Alaudinkey U/C no. 4, District Hafizabad Hafizabad

On-going

Schemes38.225 15.920 3.333 2.500 1.660 66% 46%

A.A. 38.225 (M) T.S.38.225 (M) work is in progress

Fund release but not yet online.

1122 2725Provision of Water Filtration Plant / Drainage

System Sooianwala U/C No. 5, District Hafizabad Hafizabad

On-going

Schemes33.136 11.907 3.333 2.500 1.667 67% 41%

A.A. 33.136(M) T.S.33.136 (M) work is in progress

Fund release but not yet online.

1123 2726

Provision of Water Filtration Plant / Drainage

SystemRamke Chatha U/C no. 6, District

Hafizabad

HafizabadOn-going

Schemes31.145 12.000 3.333 2.500 1.667 67% 44%

A.A. 31.145(M) T.S.31.145 (M) work is in progress

Fund release but not yet online.

1124 2727

Provision of Water Filtration Plant / Drainage

System Dhiranke Lalke U/C no. 7, District

Hafizabad

HafizabadOn-going

Schemes42.320 20.000 3.333 2.500 1.667 67% 51%

A.A. 42.320(M) T.S.42.320 (M) work is in progress

Fund release but not yet online.

1125 2728

Provision of Water Filtration Plant / Drainage

System Sandhwan Tarar U/C no. 9, District

Hafizabad

HafizabadOn-going

Schemes32.850 12.000 3.333 2.500 1.667 67% 42%

A.A. 32.850(M) T.S.32.850 (M) work is in progress

Fund release but not yet online.

1126 2729Provision of Water Filtration Plant / Drainage

System Pind Bawray U/C no. 10, District Hafizabad Hafizabad

On-going

Schemes30.049 10.000 3.333 2.500 1.667 67% 39%

A.A. 30.049(M) T.S.30.049 (M) work is in progress

Fund release but not yet online

1127 2730

Provision of Water Filtration Plant / Drainage

System Sagar Kalan U/C No. 12, District

Hafizabad

HafizabadOn-going

Schemes28.414 10.000 6.138 4.604 3.069 67% 46%

A.A. 32.850(M) T.S.32.850 (M) work is in progress

Fund release but not yet online.

1128 2731Provision of Water Filtration Plant / Drainage

System Dhunni U/C No. 14, District Hafizabad Hafizabad

On-going

Schemes34.675 11.996 3.333 0.833 0.000 0% 35%

A.A. 34.675(M) T.S.34.675 (M) work is in progress

Fund release but not yet online.

1129 2732Provision of Water Filtration Plant / Drainage

System Kalianwala U/C no. 11, District Hafizabad Hafizabad

On-going

Schemes29.334 12.000 5.778 2.684 1.280 48% 45%

A.A.29.334(M) T.S.29.334 (M) work is in progress

Fund release but not yet online.

1130 2733Provision of Water Filtration Plant / Drainage

System Karyala U/C no. 19, District Hafizabad Hafizabad

On-going

Schemes28.045 12.000 5.348 7.061 5.724 81% 63%

A.A. 28.045(M) T.S.28.045(M) work is in progress

Fund release but not yet online.

1131 2734Provision of Water Filtration Plant / Drainage

System kassoke U/C no. 20, District Hafizabad Hafizabad

On-going

Schemes34.935 12.000 3.333 2.500 1.660 66% 39%

A.A. 34.935(M) T.S.34.935 (M) work is in progress

Fund release but not yet online.

1132 2735Provision of Water Filtration Plant / Drainage

System Vinni U/C no. 16, District Hafizabad Hafizabad

On-going

Schemes27.257 10.000 5.752 4.314 2.876 67% 47%

A.A. 27.257(M) T.S.27.257 (M) work is in progress

Fund release but not yet online.

1133 2736

Provision of Water Filtration Plant / Drainage

System Solangi Awan U/C no. 17, District

Hafizabad

HafizabadOn-going

Schemes29.376 10.000 3.333 2.500 1.660 66% 40%

A.A. 29.376(M) T.S.29.376 (M) work is in progress

Fund release but not yet online.

1134 2737Provision of Water Filtration Plant / Drainage

System Kot Nakka Hafizabad

On-going

Schemes47.862 19.864 3.333 2.500 1.667 67% 45%

A.A. 47.862(M) T.S.47.862 (M) work is in progress

Fund release but not yet online.

1135 2738Provision of Water Filtration Plant / Drainage

System Khana Bhattian Hafizabad

On-going

Schemes29.486 9.971 3.333 2.500 1.660 66% 39%

A.A. 29.486(M) T.S.29.486 (M) work is in progress

Fund release but not yet online.

1136 2739Provision of Water Filtration Plant / Drainage

System Thata Jhaid Amirwala Hafizabad

On-going

Schemes35.920 14.993 3.333 2.500 1.667 67% 46%

A.A. 35.920(M) T.S.35.920 (M) work is in progress

Fund release but not yet online.

1137 2740Provision of Water Filtration Plant / Drainage

System North Hafizabad

On-going

Schemes32.026 11.910 3.333 2.500 1.660 66% 42%

A.A. 32.026(M) T.S.32.026 (M) work is in progress

Fund release but not yet online.

1138 2741Provision of Water Filtration Plant / Drainage

System Kot Sarwer Hafizabad

On-going

Schemes53.655 20.000 3.333 2.500 1.650 66% 40%

A.A. 53.655(M) T.S.53.655 (M) work is in progress

Fund release but not yet online.

1139 2742Provision of Water Filtration Plant / Drainage

System Mowan Bhattian Hafizabad

On-going

Schemes25.650 10.000 5.217 3.913 2.600 66% 49%

A.A. 25.650(M) T.S.25.650 (M) work is in progress

Fund release but not yet online.

1140 2743Provision of Water Filtration Plant / Drainage

System Jalal Pur Bhattian in District Hafizabad Hafizabad

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39%

A.A. 30.000(M) T.S.30.000 (M) work is in progress

Fund release but not yet online.

Page 75: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1141 2744

Construction of PCC Street/ Drain, Soling and

Nullah in UC Fatta Band Tehsil Kharian District

Gujrat

GujratOn-going

Schemes20.027 10.000 3.342 2.507 1.671 67% 58%

A.A Date =28.7.2017.Drain Type-I=6937 Rft. PCC.

1:2:4=1000 Cft.Soling= 2741sft .Work in progress.

1142 2745

Construction of PCC Street/ Drain, Soling and

Nullah in U.C's Mirza Tahir, Nona Wali, Bumali,

Kolian Shah Hussain, Jora Kamana, Haji

Muhammad, Sikaryali, Chakori Bhailwal,

Warraichanwala, Nagranwala, Ali Chak, Kulewa,

Taplyala, Chak Pind in Tehsil Kharian

GujratOn-going

Schemes69.000 19.985 3.333 2.500 1.667 67% 31%

A.A Date =28.8.2017.Drain Type-I=6359 Rft. PCC.

1:2:4=43123 Cft.Soling= 8900 sft.Nullah 2x2=400

Rft.Work in progress.

1143 2746Provisino of Sewerage / Drainage / Soling etc in

Various UC's in PP-113, District GujratGujrat

On-going

Schemes50.000 25.000 1.667 1.250 0.834 67% 52%

A.A Date =28.8.2017.Drain Type-I=4629 Rft. PCC.

1:2:4=46666 Cft.Soling= 15646 sft .Nullah

2'x2'=100.Work in progress.

1144 2747

Exten: Construction of PCC Street / Drain, Soling,

Nullah and Eten: of Water Supply Scheme Fath

Bhand Tehsil Kharian District Gujrat

GujratOn-going

Schemes81.151 22.000 3.333 2.500 1.667 67% 29%

A.A Date =28.8.2017.1 Nos T/Well installed. Pipe

6"=10384 Rft, 4"=5678 Rft, 3'=14560 rft.

Soling=34508 sft, Nullah 2'x2'=1019 Rft. Work in

porgress.

1145 2748Rural Water Supply and Drainage Scheme Morala

Tehsil Kharian District Gujrat Gujrat

On-going

Schemes30.000 9.748 3.333 2.500 1.667 67% 38%

1 Nos T/Well installed.PVC Pipe of dias 3" =8032

Rft,4"= 5789 Rft,6"= 3074 Rft.PCC 6581 Cft. Work

in porgress.

1146 2749

Construction of PCC Street / Drain, Soling and

Nullah in U.C Gunjah, Thekarian Matwanawala,

Miana Chak, Punjan Khasana, Khawaspur,

Bhaddhar, Kotla Qasim Khan, Chakor Sher Ghazi,

Deona Mandi, 1 & 2 Dinga, Addowal, Saroki,

Machiana in Tehsil Kharian Distric

GujratOn-going

Schemes60.990 20.000 3.333 2.500 1.667 67% 36%

A.A Date =28.8.2017.Drain Type-I=9351 Rft. PCC.

1:2:4=41644 Cft.Soling= 17354 sft .Tuff

paver=4727. Work in progress.

1147 2750

Construction of PCC Street / Drain, Soling and

Nullah in U.C 1 to 4 Lalamusa City Tehsil Kharian

District Gujrat

GujratOn-going

Schemes18.400 10.000 2.800 2.100 1.400 67% 62%

A.A Date =28.7.2017.Drain Type-I= 1919 Rft. PCC.

1:2:4=18061 Cft .Tuff paver=16112. Work in

progress.

1148 2751

Construction of PCC Street/ Drain, Soling and

Nullah in Bagrianwala, Baho Ghaseet Pur, Sheikh

Sukha, Sabowal, Amra Kalan, Chak Jani in Tehsil

Kharian District Gujrat

GujratOn-going

Schemes27.604 15.000 3.333 2.500 1.667 67% 60%

A.A Date =28.7.2017.Drain Type-I=8360 Rft. PCC.

1:2:4=28683 Cft.Work in progress.

1149 2752

Provision of Streets and Drains in UC's Chak

Sada, Mandhiyala, Thatha Musa, Chopala, Bharaj,

Thim Ke, Manju Chak, Ikhlas Garh, Fateh Pur,

Daulta Nagar, Alam Garh, Doga, Chachian, Jaura

Jalalpur and Dhuma Malka District Gujrat

GujratOn-going

Schemes60.000 22.000 3.333 5.000 4.167 83% 44%

A.A Date =28.8.2017.Drain Type-I=11013 Rft. PCC.

1:2:4=52773 Cft.Sullage Carriar=1470 Rft.Work in

progress.

1150 2753Sewerage Scheme Jail Chowk to Bhimber Nullah,

Gujrat City District GujratGujrat

On-going

Schemes249.994 49.952 3.333 2.500 1.667 67% 21% A.A Date =17.3.2018.work in progress

1151 2754Construction of Nallahs in city Sarai Alamgir

District GujratGujrat

On-going

Schemes82.600 22.195 3.333 1.580 0.747 47% 28% PCC.1:2:4=63195 Cft.Work in progress.

1152 2755Provision of Sewerage / Drainage and streets / Tuff

Tiles etc in various UCs, District Gujrat Gujrat

On-going

Schemes480.000 44.979 6.667 13.420 11.754 88% 12%

A.A Date =29.12.2017.Drain Type-I=17111 Rft.

PCC. 1:2:4=95620Cft.Tuff paver= 53179 sft .Nullah

1.5'x1.5'=1078.RCC pavement=13422 cft.Work in

progress.

1153 2756

Sewerage / Drainage / PCC & Brick Pavement

Scheme in villages Adda PharIanwall, HaIgher

Khurd,Haslanwala,pindl Kalu,Loha Tibba ,Chak

Jano Khurd, Thatha Hast, Luk, Thatha Pheray,

Rajoa, Baghanwala,kot Sattar Duborji, Kotli Qazl,

Sandanwala, Charranwala a

Mandi

Bahauddin

On-going

Schemes30.000 11.977 3.333 4.500 3.667 81% 52%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

Page 76: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1154 2757

Sewerage / Drainage / PCC & Brick Pavement

Scheme in villages kailu, tuggal, channi syedian,

Ratoo, bahri, Chak Kamal, Melu Mahi Gheran,

Aghroa, Kotha Bhola, Maseetwali Komokay, Chak

Mitha, Heigherwala, Kot Phollay shah, Chak Zahir,

Bahu, Manga, Arzani, S

Mandi

Bahauddin

On-going

Schemes30.000 9.021 3.333 2.500 1.667 67% 36%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

1155 2758

Construction of Street Drains, Soling and PCC in

Village Gajjan, Slianman, Kot Hamid Shah, Jhanda

Chohan, Rasul Pur, Chicheranwali, Bhinder Kalan,

Bhinder Khurd, Chakora, Thatha Alia and Thatha

Naik District M B Din

Mandi

Bahauddin

On-going

Schemes23.000 8.494 4.333 3.250 2.167 67% 46%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

1156 2759

Construction of Street Drains, Soling and PCC in

Village Bhagat, Thathi Mureed Sahnpal, Channi

Sahnpal, Ranaml, Sharif Channi Mahram, Qila

Attar Singh, Ghagoki and Sarang District M B Din

Mandi

Bahauddin

On-going

Schemes26.500 14.991 3.833 3.375 2.417 72% 66%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

1157 2760

Construction of Street Drains, Soling and PCC in

Village Narrang, Saad Ullah Pur, Kot Pejo,

Karamawala, Dhudra, Long Charrhkey, Khoosar

and Pindi Dotharan District M B Din

Mandi

Bahauddin

On-going

Schemes26.000 9.541 5.333 5.390 4.057 75% 52%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

1158 2761

Construction of Street Drains, Soling and PCC in

Village Dhaul, Kotly Khurd, Khiyyan, Chak Jano

New Abadies, Addu Sarwani, Sheikh Alipur,

Ransikey, Pahrianwali, Sainthal and saida Saghar

District M B Din

Mandi

Bahauddin

On-going

Schemes31.500 9.595 7.167 9.825 8.034 82% 56%

* A.A Date. 28.07.2017* T.S Date. 15.08.2017* Start

Date. 06.01.2018* Completion date 05.01.2019*

Work in progress.

1159 2762Construction of PCC / Drainage, UC Chobara

District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1160 2763Construction of PCC / Drainage, US Kingra District

Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 1.000 0.698 70% 53% Work in progress.

1161 2764Construction of PCC / Drainage, UC Dogri District

Sialkot Sialkot

On-going

Schemes15.000 7.500 2.500 1.875 1.250 67% 58% Work in progress.

1162 2765Construction of PCC / Drainage, UC Balagan

District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1163 2766Construction of PCC / Drainage, UC Malipur

District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 1.500 0.987 66% 55% Work in progress.

1164 2767Construction of PCC / Drainage, UC Talawandi,

District Sialkot Sialkot

On-going

Schemes20.000 9.100 3.333 2.000 1.568 78% 53% Work in progress.

1165 2768Construction of PCC / Drainage, UC Chacharwali

District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1166 2769Construction of PCC / Drainage, UC Klasswala,

District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 1.000 0.689 69% 53% Work in progress.

1167 2770Construction of PCC / Drainage, UC Jodhala,

District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1168 2771

Construction of PCC, Street Drain/ Nullah Village

Kundan Pur Bashmola Tahthi Minderwal, Chan,

Khany Chak, Kajlewal, Mahal Tajer, Ossomata and

Khurra

SialkotOn-going

Schemes48.000 18.000 3.333 2.500 1.667 67% 41% Work in progress.

1169 2772

Construction of PCC, Street Drain/ Nullah Village

Chakrala Bashmula Machrala, Nandpurn Rang

Khokhran, Lalian, Gaiat, Bahadur and Madina

Town.

SialkotOn-going

Schemes49.000 20.000 3.333 2.500 1.667 67% 44% Work in progress.

1170 2773Construction of PCC, Streets Drains, Tuff Tiles and

Soling in UC Marakiwall in District Sialkot.Sialkot

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.

Page 77: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1171 2774Construction of PCC, Streets Drains, Tuff Tiles and

Soling in UC Berth in District Sialkot Sialkot

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.

1172 2775Construction of PCC, Streets Drains, Tuff Tiles and

Soling in UC Booth in District Sialkot Sialkot

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.

1173 2776Construction of PCC, Streets Drains, Tuff Tiles and

Soling in UC Machranal in District Sialkot Sialkot

On-going

Schemes12.000 9.000 1.000 0.750 0.500 67% 79% Work in progress.

1174 2777

Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Dhilum Balagon, District

Sialkot

SialkotOn-going

Schemes25.000 8.000 1.667 1.250 0.834 67% 35% Work in progress.

1175 2778

Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at Fardaus Pura, Nand Garh,

Wan, Dhoop Sarri, Kotli Miani, Malkhanwala,

District Sialkot

SialkotOn-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1176 2779

Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Bhopalwala Tehsil

Sambrial, District Sialkot

SialkotOn-going

Schemes50.000 19.399 3.333 2.500 1.667 67% 42% Work in progress.

1177 2780Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Alleali, District Sialkot Sialkot

On-going

Schemes20.000 7.000 1.667 1.250 0.834 67% 39% Work in progress.

1178 2781

Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at Villages Mundair Syedian,

Mundair Khothay, Roras, Sohowala, Kharolian etc.,

District Sialkot

SialkotOn-going

Schemes25.000 8.000 1.667 1.250 0.834 67% 35% Work in progress.

1179 2782

Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Berowala Tehsil Daska,

District Sialkot

SialkotOn-going

Schemes40.000 12.000 3.333 2.500 1.667 67% 34% Work in progress.

1180 2783Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Bagowala , District SialkotSialkot

On-going

Schemes20.000 7.000 1.667 1.250 0.834 67% 39% Work in progress.

1181 2784Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Ghuinke, District SialkotSialkot

On-going

Schemes149.892 20.000 3.333 2.500 1.667 67% 14% Work in progress.

1182 2785Construction of Streets / Drain / Nullah / Soling /

Tuff Tiles / PCC at UC Bharokey, District SialkotSialkot

On-going

Schemes40.000 12.000 3.333 2.500 1.667 67% 34% Work in progress.

1183 2786Construction of sewerage, Nallah, PCC at UC

Prochak and Alo Mahr District Sialkot.Sialkot

On-going

Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.

1184 2787Construction of Streets / Sewerage / Tuff Tile/

PCC/ Soling in Rural UC's of NA-113Sialkot

On-going

Schemes100.000 29.967 3.333 2.500 1.667 67% 32% Work in progress.

1185 2788Construction of PCC, Soling / Drains in Villages of

UC in Ghutalian District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1186 2789Construction of PCC, Soling / Drains in Villages of

UC in Chichar wali District Sialkot Sialkot

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.

1187 2790Construction of PCC, Soling / Drains in Villages of

UC in Pejoke Qila Kalarwala District Sialkot Sialkot

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.

1188 2791

Construction of Streets, Nullah, PCC, Soling at

villages Jasso Wali Pun, Sahn Gill, pajokay,

Mehmand Wali, Rata jathool, Baso Panu, alawal

Pur, Loharan Wali, Jhangi Shah Khaki, Jhans,

Sodian, Bhuda, Peera Baryar, Charwind, Deehr,

Bhojo, Alkry, Kala Pahar,

SialkotOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1189 2792Construction of PCC, Soling / Drains in Villages of

UC Sokan Wind District Sialkot Sialkot

On-going

Schemes25.000 12.000 1.667 1.250 0.834 67% 51% Work in progress.

Page 78: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1190 2793

Construction of Streets, Drains PCC/ Soling / Tuff

Tiles in Villages of UC's Kanwanlit, Adamkey

Cheema, Raja Gamman, Galotian Kalan, Galotian

Khurd, Goindkey, Banbanwala, Bharokey and

Mitranwali Tehsil Daska District Sialkot

SialkotOn-going

Schemes120.000 45.000 3.333 2.500 1.667 67% 39% Work in progress.

1191 2794

Constructon of Streets / Drain / Nullah / Soling at

UC, Moongar, Baqarpur, Pindi Khokharn etc.,

District Sialkot

SialkotOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1192 2795Constructon of Streets / Drain / Nullah / Soling at,

UC Kapoor Wali and Khamberwala District Sialkot Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1193 2796

Constructon of Streets / Drain / Nullah / Soling at

Village Satab Garah, Butter, Dhanney, Ganjaniwali

etc. District Sialkot

SialkotOn-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in progress.

1194 2797Construction of Street / Swerage / Tuff Tile ETC in

City Daska District Sialkot Sialkot

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress.

1195 2798Construction of PCC/Streets/Nalian at U.C.

Syedanwali District Sialkot Sialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1196 2799Construction of PCC/Streets/Nalian at U.C.Pargpur

District Sialkot Sialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1197 2800Construction of PCC/Streets/Nalian at U.C. Vario

District Sialkot Sialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1198 2801Construction of PCC/Streets/Nalian at U.C

Rasoolpur Balian District Sialkot Sialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1199 2802Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Kotli Barham Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1200 2803Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Paka Garh Sialkot

On-going

Schemes30.000 15.000 1.667 1.250 0.834 67% 53% Work in progress.

1201 2804Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Maina Pura Sialkot

On-going

Schemes30.000 15.000 1.667 1.250 0.834 67% 53% Work in progress.

1202 2805Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Muzafar Pur Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1203 2806Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Fathegarh Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1204 2807Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Haji Pura Ban Sialkot

On-going

Schemes20.000 9.995 3.333 2.500 1.667 67% 58% Work in progress.

1205 2808Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Imam Saheb Sialkot

On-going

Schemes20.000 9.986 3.333 1.000 0.660 66% 53% Work in progress.

1206 2809Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Mubarik Pura Sialkot

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in progress.

1207 2810

Provision of PCC / Sewerage / Tuff Tiles /

Drainage and allied facilities in PP-122, District

Sialkot

SialkotOn-going

Schemes100.000 44.992 3.333 2.500 1.667 67% 47% Work in progress.

1208 2811

Provision of PCC / Sewerage / Tuff Tiles /

Drainage and allied facilities in PP-123, District

Sialkot

SialkotOn-going

Schemes199.950 100.000 3.333 2.500 1.667 67% 51% Work in progress.

1209 2812

Construction of PCC, Street Drain/ Nullah Village

Jallian Wala Bashamula Moma Khurd, Kalan

Virkan, Dulchikay, Lodhary Dogranwala and Rai

Pur.

SialkotOn-going

Schemes47.000 18.000 3.333 2.500 1.667 67% 42% Work in progress.

1210 2813

Construction of PCC, Street Drain/ Nullah Village

Ghari Gondal Bashmula Ahmal Pur, Sarhall,

Hadali, Minal Pathan, Bazpur and Romal Juttan.

SialkotOn-going

Schemes47.000 17.936 1.667 1.250 0.834 67% 40% Work in progress.

1211 2814

Construction of PCC, Street Drain/ Nullah Village

Baghwal Awan Bashmula Harar, Noul, Dumbola

and Dogran.

SialkotOn-going

Schemes46.000 17.956 5.000 1.350 0.903 67% 41% Work in progress.

Page 79: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1212 2815Construction of sewerage, Nallah, PCC at UC

Jaranwala and Barthanwala, District SialkotSialkot

On-going

Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.

1213 2816Construction of sewerage, Nallah, PCC at UC

Salhokay and Bhuda Gorya, District SialkotSialkot

On-going

Schemes20.000 10.938 3.000 2.250 1.500 67% 62% Work in progress.

1214 2817Construction of sewerage, Nallah, PCC at UC

Mundekay Gorya and Malomay, District SialkotSialkot

On-going

Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.

1215 2818Construction of sewerage, Nallah, PCC at UC

Boghray and Seo Ke, District Sialkot.Sialkot

On-going

Schemes20.000 11.000 3.000 2.250 1.500 67% 63% Work in progress.

1216 2819Construction of sewerage, Nallah, PCC at UC

Adha and Sehjo Kala District Sialkot.Sialkot

On-going

Schemes20.000 12.000 2.667 2.000 1.334 67% 67% Work in progress.

1217 2820Construction of sewerage, Nallah, PCC at UC

Ghuainkey and Badoke Cheema, District Sialkot.Sialkot

On-going

Schemes15.000 9.941 1.667 1.250 0.834 67% 72% Work in progress.

1218 2821Construction of sewerage, Nallah, PCC at UC

Jamkay Cheema and Kanwanliq, District Sialkot.Sialkot

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in progress.

1219 2822Construction Street Drain PCC / and Nullah U/C

JaithkeSialkot

On-going

Schemes20.000 10.000 3.333 4.534 3.701 82% 69% Work in progress.

1220 2823Construction of Street Drain PCC / and Nullah U/C

Kopra Sialkot

On-going

Schemes20.000 9.920 3.333 2.500 1.667 67% 58% Work in progress.

1221 2824Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Dalowali Sialkot

On-going

Schemes40.000 14.963 3.333 2.500 1.667 67% 42% Work in progress.

1222 2825Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Talwara Sialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1223 2826Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Pindi Arian Sialkot

On-going

Schemes20.000 9.968 3.333 2.500 1.667 67% 58% Work in progress.

1224 2827Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Hamza Ghous Sialkot

On-going

Schemes30.000 9.920 1.667 1.250 0.834 67% 36% Work in progress.

1225 2828Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Naika Pura Sialkot

On-going

Schemes20.000 9.987 3.333 2.500 1.667 67% 58% Work in progress.

1226 2829Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Duborji Arian Sialkot

On-going

Schemes20.000 9.937 3.333 2.500 1.667 67% 58% Work in progress.

1227 2830Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Ahmed Pura Sialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1228 2831Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Pura Hiran Sialkot

On-going

Schemes20.000 9.970 3.333 2.500 1.667 67% 58% Work in progress.

1229 2832Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Rangpura Sialkot

On-going

Schemes40.000 15.000 3.333 2.500 1.667 67% 42% Work in progress.

1230 2833Providing & Laying of Tuff Tile PCC and Drainge

Lines in UC Islam Abad Sialkot

On-going

Schemes20.000 9.700 3.333 2.500 1.667 67% 57% Work in progress.

1231 2834Construction of Street Drain PCC/ and Nullah UC

Majra KalanSialkot

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in progress.

1232 2835Construction of Street Drain PCC / and Nullah U/C

Village Srankey Sialkot

On-going

Schemes20.000 10.000 3.333 7.500 6.667 89% 83% Work in progress.

1233 2836Construction of Street Drain PCC/ and Nullah

U/C’s Verowala, Halewai, Habibpur Sialkot

On-going

Schemes80.000 30.000 1.667 1.250 0.834 67% 39% Work in progress.

1234 2837Construction of sewerage, PCC, Tuff Tile, District

Sialkot Sialkot

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work in progress.

1235 2838Construction of PCC & Drains in Village Chobara

U/C Chobara District SialkotSialkot

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in progress.

1236 2839

Construction of Drainage System, PCC and Brick

Pavement in Villages of UC Rupo Chak Tehsil

Zafarwal District Narowal

NarowalOn-going

Schemes12.000 4.993 2.000 1.500 0.999 67% 50%

"A.A. dated 07.08.2017 T.S. dated 08.08.2017 Start

Date 28.09.2017 *Completion date 30.06.2019work

in progress. Fund not received on spending end yet.

Page 80: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1237 2840

Provision of Drains/Soling and PCC in UCs,

Datewal, Mangolay, Hallowal, Dhrug Miana and

Ghota Fateh Garh District Narowal

NarowalOn-going

Schemes30.000 12.308 3.333 2.500 1.659 66% 47%

"A.A. dated 03.08.2017 T.S. dated 12.08.2017

*Start Date 27.10.2017 *Completion date

30.06.2019 work in progress. "A.A. dated

03.08.2017 T.S. dated 12.08.2017 *Start Date

27.10.2017 *Completion date 30.06.2019 work in

progress. "A.A. dated 03.08.2017 T.S. dated

12.08.2017 *Start Date 27.10.2017 *Completion

date 30.06.2019 work in progress.Fund not recived

on spending end yet

1238 2841

Provision of Drains/Soling and PCC in UCs,

Talwandi Bhindran, Giddan, Niddokay, Kot Lakha

Singh and Domala, District Narowal

NarowalOn-going

Schemes30.000 9.960 3.333 2.500 1.661 66% 39%

"A.A. dated 03.08.2017 T.S. dated 12.08.2017

*Start Date 27.10.2017 *Completion date

30.06.2019 Work in progress. Fund not receive on

spending end yet.

1239 2842

Provision of Drains/Soling and PCC in UCs, Khan

Kassa, Dongian, Bubak Murali, Sadowala Uncha

and Falezpur District Narowal

NarowalOn-going

Schemes30.000 9.871 3.333 2.500 1.664 67% 38%

"A.A. dated 03.08.2017 T.S. dated 12.08.2017

*Start Date 27.10.2017 *Completion date

30.06.2019 Work in progress. "A.A. dated

03.08.2017 T.S. dated 12.08.2017 *Start Date

27.10.2017 *Completion date 30.06.2019 Work in

progress"A.A. dated 03.08.2017 T.S. dated

12.08.2017 *Start Date 27.10.2017 *Completion

date 30.06.2019 Work in progress. Funds not

received on spending end yet.

1240 2843

Provision of Drains/Soling and PCC in UCs,

Ahmadabad, Depokey, Jestiwala, Uncha, Lala and

Nonar, District Narowal

NarowalOn-going

Schemes30.000 9.940 3.333 2.500 1.659 66% 39%

"A.A. dated 03.08.2017 T.S. dated 12.08.2017

*Start Date 27.10.2017 *Completion date

30.06.2019 Work in progress. Funds not received

on spending end yet

1241 2844

Provision of Drains/Soling and PCC in UCs, Mehlu

Wala, Dhamthal, Langarkay, Tapiala and

Sankhtara District Narowal

NarowalOn-going

Schemes30.000 9.940 3.333 2.500 1.663 67% 39%

"A.A. dated 03.08.2017 T.S. dated 12.08.2017

*Start Date 27.10.2017 *Completion date

30.06.2019 Work in progress. Funds not received

on spending end yet

1242 2845

Provision of PCC/Streets/Nalian at Bado Malihi,

Chandarkay, Ransiwal, Manak, Qayampur, Agrian,

Pungarian, Salukay, Dawod, Chundowal, Klass

Gorya, Muhammad Rana Wala District Narowal

NarowalOn-going

Schemes130.000 34.991 6.667 5.000 3.320 66% 29%

"A.A. dated 19.10.17 T.S. dated*Start Date

18.10.2017 *Completion date 30.06.2019 Work in

progress. Funds not received on spending end yet.

1243 2846Provision of Tuff Tile from Zafarwal bypass to

Chowk Ghas Mandi, District Narowal Narowal

On-going

Schemes22.000 9.965 4.000 3.000 1.994 66% 54%

"A.A Date.03.08.2017 T.S Date*18.09.2017 Start

Date 28.09.2017*Completion date 30.06.2019 Work

in progress. Funds not received on spending end yet

1244 2847

Construction of Drainage System, PCC and Brick

Pavement in Villages of Jandiala Tehsil Zafarwal

District Narowal

NarowalOn-going

Schemes15.000 4.993 3.333 2.500 1.661 66% 44%

"A.A. dated 03.08.17T.S. dated 08.08.2017*Start

Date 18.08.2017*Completion date 30.06.2019 Work

in progress. Fund not received on spending end yet.

1245 2848Provision of PCC / Sewerage / Drainage etc. in PP-

133, District NarowalNarowal

On-going

Schemes25.000 9.812 1.667 1.250 0.831 66% 43%

"A.A. dated 03.08.17 T.S. dated 08.08.2017 *Start

Date 18.08.2017 *Completion date 30.06.2019

Work in progress. Funds not received on spending

end yet.

1246 2849PCC & Drainage & Sewerage System at UC-273,

Raiwind City, LhrLahore

On-going

Schemes50.000 38.992 3.667 5.090 4.174 82% 86% Work stopped due to awaiting funds.

1247 2850PCC & Drainage & Sewerage System at UC-112,

Mustafa Town, Lahore

On-going

Schemes50.000 39.986 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1248 2851Provision of PCC & Drainage Facilities in Attari &

allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed

1249 2852

Provision of PCC & Drainage Facilities in

Youhanabad, Dhullu Kalan & Khurd & allied

abadies.

LahoreOn-going

Schemes50.000 39.987 3.333 3.400 2.567 76% 85% Work stopped due to awaiting funds.

1250 2853Provision of PCC & Drainage Facilities in

Gajjumatta & allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed

1251 2854Provision of PCC & Drainage Facilities in Bhallar &

allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed

1252 2855Provision of PCC & Drainage Facilities in Dhalloki

& allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed

1253 2856Provision of PCC & Drainage Facilities in Jhulkey

& allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed

1254 2857Provision of PCC & Drainage Facilities in Jaman

and Gawind & allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 2.500 1.667 67% 83% Scheme completed

1255 2858Provision of PCC & Drainage Facilities in

Shahzada & allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed

Page 81: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1256 2859Provision of PCC & Drainage Facilities in Jia

Bhagga & allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.900 0.067 7% 80% Scheme completed

1257 2860Provision of PCC & Drainage Facilities in Pandoki

& allied abadies.Lahore

On-going

Schemes50.000 40.000 3.333 0.860 0.027 3% 80% Scheme completed

1258 2861Provision of PCC & Drainage Facilities in Hair &

allied abadies.Lahore

On-going

Schemes73.000 54.100 3.333 0.900 0.067 7% 74%

Work stopped due to awaiting funds. Revised PC-I

is under review with DDWP.

1259 2862Construction of Sewerage and Disposal Manawan

Sky Land & Abadies Lahore

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Work stopped due to awaiting funds.

1260 2863Construction of PCC/Sewerage and Link Streets

UC-147 Lahore.Lahore

On-going

Schemes50.000 34.992 5.000 3.750 2.500 67% 75% Work stopped due to awaiting funds.

1261 2864Construction of PCC/Sewerage and Link Streets

UC-148 Lahore.Lahore

On-going

Schemes50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1262 2865Construction of PCC/Sewerage and Link Streets

UC-149 Lahore.Lahore

On-going

Schemes50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1263 2866Construction of PCC/Sewerage and Link Streets

UC-150 Lahore.Lahore

On-going

Schemes50.000 39.992 3.333 2.300 1.467 64% 83% Work stopped due to awaiting funds.

1264 2867Construction of PCC/Sewerage and Link Streets

UC-151 Lahore.Lahore

On-going

Schemes50.000 39.538 3.333 2.400 1.567 65% 82% Work stopped due to awaiting funds.

1265 2868Construction of PCC/Sewerage and Link Streets

UC-152 Lahore.Lahore

On-going

Schemes50.000 39.992 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1266 2869Construction of PCC/Sewerage and Link Streets

UC-174 Lahore.Lahore

On-going

Schemes50.000 29.984 3.333 2.500 1.667 67% 63% Work stopped due to awaiting funds.

1267 2870Construction of PCC/Sewerage and Link Streets

UC-175 Lahore.Lahore

On-going

Schemes50.000 39.991 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1268 2871Construction of PCC/Sewerage and Link Streets

UC-183 Lahore.Lahore

On-going

Schemes50.000 39.991 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1269 2872Construction of PCC/Sewerage and Link Streets

UC-108 Lahore.Lahore

On-going

Schemes50.000 34.968 5.000 3.750 2.500 67% 75% Work stopped due to awaiting funds.

1270 2873Construction of PCC/Sewerage and Link Streets

Bhangali Lahore.Lahore

On-going

Schemes100.000 75.000 5.000 3.750 2.500 67% 78%

Scheme completed physically, funds are required to

clear the contractor liabilities.

1271 2874PCC & Drainage & Sewerage System at UC-110,

Niaz Baig LahoreLahore

On-going

Schemes50.000 39.977 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1272 2875PCC & Drainage & Sewerage System at UC-111,

Hunjarwal, LahoreLahore

On-going

Schemes50.000 39.273 3.573 2.680 1.787 67% 82% Work stopped due to awaiting funds.

1273 2876PCC & Drainage & Sewerage System at UC-109,

Margzaar Colony, Lahore. Lahore

On-going

Schemes50.000 39.493 3.500 2.625 1.750 67% 82% Work stopped due to awaiting funds.

1274 2877PCC & Drainage & Sewerage System at UC-117,

Shahpur Kanjran, Lahore. Lahore

On-going

Schemes50.000 45.000 1.667 1.250 0.834 67% 92%

Scheme completed physically, funds are required to

clear the contractor liabilities.

1275 2878PCC & Drainage & Sewerage System at UC-262,

Shamke Bhattian, Lahore.Lahore

On-going

Schemes50.000 29.989 1.667 1.050 0.634 60% 61% Work stopped due to awaiting funds.

1276 2879PCC & Drainage & Sewerage System at UC-255,

Sattu Kattla, LahoreLahore

On-going

Schemes50.000 31.995 1.667 5.250 4.834 92% 74% Work stopped due to awaiting funds.

1277 2880PCC & Drainage & Sewerage System at UC-256,

Ali Raza Abad, LahoreLahore

On-going

Schemes50.000 39.556 3.333 2.500 1.667 67% 82% Work stopped due to awaiting funds.

1278 2881PCC & Drainage & Sewerage System at UC-272,

Raiwind Kalan, LahoreLahore

On-going

Schemes50.000 40.000 3.333 5.000 4.167 83% 88%

Physically scheme is completed, balance funds are

required to clear the contractor's liability

1279 2882Provision of PCC & Drainage in Streets UC-176

Awan Dhai Wala Lahore.Lahore

On-going

Schemes50.000 39.800 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1280 2883Provision of PCC & Drainage in Streets UC-190

Hadiara Lahore.Lahore

On-going

Schemes50.000 39.620 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1281 2884Provision of PCC & Drainage in Streets UC-180

Minhala Kallan Lahore.Lahore

On-going

Schemes50.000 39.599 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1282 2885Provision of PCC & Drainage in Streets UC-181

Wahga Lahore.Lahore

On-going

Schemes50.000 39.977 3.333 2.500 1.667 67% 83% Work stopped due to awaiting funds.

1283 2886Provision of PCC & Drainage in Streets UC-194

Lidhar Lahore.Lahore

On-going

Schemes50.000 40.000 3.333 0.870 0.037 4% 80% Scheme completed

Page 82: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1284 2887

Provision of clean drinking water, sewerage

system, PCC and allied facilities in Manga Mandi,

Raiwind Village and adjoining Abadies.

LahoreOn-going

Schemes300.000 137.599 8.333 6.250 4.167 67% 47% Work stopped due to awaiting funds.

1285 2888Construction of PCC, Soling, Drain & Nallah at

Tibbi Humbo, UC 64, District SheikhupuraSheikhupura

On-going

Schemes15.000 2.500 1.667 1.250 0.834 67% 22% Work in Progress

1286 2889Provision of PCC, Drain, Soling, Nallah & culvert at

UC 87 Farooqabad , District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress

1287 2890Provision of PCC, Drain, Soling, Nallah & culvert at

UC Ghung, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress

1288 2891Provision of PCC, Drain, Soling, Nallah & culvert at

UC Nokhar Nau, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress

1289 2892Provision of PCC, Drain, Soling, Nallah & culvert at

UC Sucha Sauda, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress

1290 2893Provision of PCC, Drain, Soling, Nallah & culvert at

UC Hardev, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 1.667 1.250 0.834 67% 54% Work in Progress

1291 2894Construction of soling, PCC, Drain & Nallah UC

Mojoki Mallian, District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1292 2895Construction of soling, PCC, Drain & Nallah UC

Jhamkay, District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1293 2896Construction of soling, PCC, Drain & Nallah UC

Kalokay, District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1294 2897Construction of soling, PCC, Drain & Nallah UC

Rakh Hiran Minara District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1295 2898Construction of soling, PCC, Drain & Nallah UC

Ghang District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1296 2899Construction of soling, PCC, Drain & Nallah UC

Warn Dera Bhikhi Ana District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1297 2900Rural drainage & PCC Scheme UC Jhabran,

District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1298 2901Rural drainage & PCC Scheme UC Ghazi Minara,

District Sheikhupura,Sheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1299 2902Rural drainage & PCC Scheme UC Hardev,

District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1300 2903Construction of PCC, Drain / Soling & Nallah at UC

Kakar Gill, District SheikhupuraSheikhupura

On-going

Schemes11.000 5.000 2.000 1.500 1.000 67% 55% Work in Progress

1301 2904Construction of PCC, Drain / Soling & Nallah at UC

83 Jatri Kohna, District SheikhupuraSheikhupura

On-going

Schemes14.000 5.000 3.000 2.250 1.500 67% 46% Work in Progress

1302 2905Construction of PCC, Drain / Soling & Nallah at UC

79 Harchand, District SheikhupuraSheikhupura

On-going

Schemes12.000 5.000 2.333 1.750 1.167 67% 51% Work in Progress

1303 2906Construction of PCC, Drain / Soling & Nallah at UC

81 Sucha Sauda, District SheikhupuraSheikhupura

On-going

Schemes16.000 5.000 3.667 2.750 1.834 67% 43% Work in Progress

1304 2907Construction of PCC, Drain / Soling & Nallah at UC

80 Esherke, District SheikhupuraSheikhupura

On-going

Schemes14.000 5.000 3.000 2.250 1.500 67% 46% Work in Progress

1305 2908

Construction of PCC, Drain / Soling & Nallah at UC-

85, 86 & 87 Farooqabad City & Muridke village UC-

70, District Sheikhupura

SheikhupuraOn-going

Schemes55.000 20.000 3.333 2.500 1.667 67% 39% Work in Progress

1306 2909Construction of PCC, Drain, Soling & Nallah Kala

Khatai UC-9, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1307 2910Construction of PCC, Drain, Soling & Nallah

Khatiala Virkan UC-18, District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress

1308 2911Construction of PCC, Drain, Soling & Nallah

Sheikhupura Bedad UC-15, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

Page 83: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1309 2912Construction of PCC, Drain, Soling & Nallah

Nangal Kaswala UC-14, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1310 2913Construction of PCC, Drain, Soling & Nallah

Dharor Muslim UC-13, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1311 2914Construction of PCC, Drain, Soling & Nallah

Ahdian UC-7, District SheikhupuraSheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1312 2915Construction of PCC, Drain, Soling & Nallah

Lambray UC-10, District SheikhupuraSheikhupura

On-going

Schemes12.000 5.000 2.333 1.750 1.167 67% 51% Work in Progress

1313 2916Construction of PCC, Drain, Soling & Nallah

Nangal Sahdan UC-11, District SheikhupuraSheikhupura

On-going

Schemes20.000 5.000 1.667 1.250 0.834 67% 29% Work in Progress

1314 2917Rural Drainage and Construction of Streets

Scheme at UC Barth District Sheikhupura.Sheikhupura

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress

1315 2918Rural Drainage and Construction of Streets

Scheme at UC Chak No.22 District Sheikhupura.Sheikhupura

On-going

Schemes30.000 19.000 3.667 2.750 1.834 67% 69% Work in Progress

1316 2919Rural Drainage and Construction of Streets

Scheme at UC Faizpur Khurd District Sheikhupura.Sheikhupura

On-going

Schemes35.000 19.000 1.667 1.250 0.834 67% 57% Work in Progress

1317 2920Rural Drainage and Construction of Streets

Scheme at UC Luban Wala District Sheikhupura.Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1318 2921Rural Drainage and Construction of Streets

Scheme at UC Faizpur Kalan District Sheikhupura.Sheikhupura

On-going

Schemes30.000 19.000 3.667 2.750 1.834 67% 69% Work in Progress

1319 2922Rural Drainage and Construction of Streets

Scheme at UC Buraj Attari District Sheikhupura.Sheikhupura

On-going

Schemes25.000 10.000 1.667 1.250 0.834 67% 43% Work in Progress

1320 2923Rural Drainage and Construction of Streets

Scheme at UC Moran Wala District Sheikhupura.Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1321 2924Rural Drainage and Construction of Streets

Scheme at UC Rana Bhati District Sheikhupura.Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% scheme Completed

1322 2925

Rural Drainage and Construction of Streets

Scheme at UC Kashmir Town/Rana Town/ Galkxy

Block/ Kot Hadayat/ Haider Road District

Sheikhupura.

SheikhupuraOn-going

Schemes50.000 1.750 3.333 2.500 1.667 67% 7% Work in Progress

1323 2926

Rural Drainage and PCC at villages Samolana,

Mada Treda, Pherianwala, Khanni, Jalalpur,

Nizampura, Kukripur, Sikhanwala, Jogiwala and

adjoinging abdies, District Sheikhupura

SheikhupuraOn-going

Schemes30.000 15.000 1.667 1.250 0.834 67% 53% Work in Progress

1324 2927Construction of PCC, Drains and Nallah at UC-37

Chak 575 GB District SheikhupuraSheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1325 2928Construction of Rural Draiange PCC & Tuff tiles

scheme UC 27, District Sheikhupura Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1326 2929Construction of Rural Draiange PCC & Tuff tiles

scheme UC 28, District Sheikhupura Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1327 2930Construction of Rural Draiange PCC & Tuff tiles

scheme UC 29, District Sheikhupura Sheikhupura

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in Progress

1328 2931Construction of Rural Draiange PCC & Tuff tiles

scheme UC 30, District Sheikhupura Sheikhupura

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work in Progress

1329 2932Construction of Rural drainage PCC & Tuff tiles

scheme UC Rana Bhatti, District Sheikhupura Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1330 2933Construction of Rural drainage PCC & Tuff tiles

scheme UC Mandianwala, District Sheikhupura Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

Page 84: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1331 2934Construction of Rural drainage PCC & Tuff tiles

scheme UC Dhamkay, District Sheikhupura Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1332 2935Construction of Rural drainage PCC & Tuff tiles

scheme UC Chak No.22, District Sheikhupura Sheikhupura

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1333 2936Urban Drainage and Sewerage Scheme Narang

Mandi, District SheikhupuraSheikhupura

On-going

Schemes220.000 30.000 1.000 0.750 0.500 67% 14% Work in Progress

1334 2937

Urban Sewerage, Drainage & PCC Scheme MC

Ferozewala, Tehsil Ferozewala, District

Sheikhupura

SheikhupuraOn-going

Schemes160.000 20.000 5.000 3.750 2.500 67% 14% Work in Progress

1335 2938Construction of PCC, Drain & Nallah Muridke City,

District SheikhupuraSheikhupura

On-going

Schemes100.000 25.000 3.333 2.500 1.667 67% 27% Work in Progress

1336 2939Construction of PCC, Drain & Nallah Narang City,

District SheikhupuraSheikhupura

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress

1337 2940Provision of water supply and sewerage / drainage

scheme city SheikhupuraSheikhupura

On-going

Schemes450.000 17.500 16.667 12.500 8.334 67% 6% Work in Progress

1338 2941

Urban Sewerage, Drainage & PCC Scheme MC

Kot Adbul Malik, Tehsil Ferozewala, District

Sheikhupura

SheikhupuraOn-going

Schemes140.000 15.000 3.333 2.500 1.667 67% 12% Work in Progress

1339 2942

Urban Sewerage, Drainage & PCC Scheme UC

Momin Pura, Tehsil Ferozewala, District

Sheikhupura

SheikhupuraOn-going

Schemes20.000 5.427 4.858 3.644 2.429 67% 39% Work in Progress

1340 2943Urban Sewerage, Drainage & PCC Scheme UC

Shamkay, Tehsil Ferozewala, District SheikhupuraSheikhupura

On-going

Schemes100.000 9.254 3.535 2.651 1.768 67% 11% Work in Progress

1341 2944

Urban Sewerage, Drainage & PCC Scheme UC

Qilla Sattar Shah, Tehsil Muridkay, District

Sheikhupura

SheikhupuraOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Scheme completed

1342 2945Provision of PCC and Tuff Tiles in City

Sheikhupura PP-167, District SheikhupuraSheikhupura

On-going

Schemes180.000 140.000 3.333 2.500 1.667 67% 79% Work in Progress

1343 2946Construction of PCC, Drains and Nallah at UC-57

Jevanpura, District SheikhupuraSheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1344 2947Construction of PCC, Drains and Nallah at UC-58

Kadlathi, District SheikhupuraSheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1345 2948Construction of PCC, Drains and Nallah at UC-80

Khariyanwala. District SheikhupuraSheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1346 2949Construction of PCC, Drains and Nallah at UC-81

Bhikhi. District SheikhupuraSheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1347 2950Construction of PCC, Drains and Nallah at UC-82

Tibbi Hambo. District SheikhupuraSheikhupura

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1348 2951

Construction of sewerage, drains, tuff tiles, PCC &

LED Street lights at Wandala Dial Shah & Dhaka

Nizam Pura, District Sheikhupura

SheikhupuraOn-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work in Progress

1349 2952

Construction of drain / soling / PCC / Nullah and

Pulyat at vilalge Rato Ana, Kot Ghulam Rasool and

village Sheedi Kot UC Kot Hussain Khan, District

Nankana Sahib

Nankana SahibOn-going

Schemes29.500 10.000 3.333 2.500 1.667 67% 40% Work is in progress.

1350 2953Construction of PCC / Soling & Nallah at UC

Buchoke Pur Distirct Nankana Sahib Nankana Sahib

On-going

Schemes30.000 10.000 3.333 4.200 3.367 80% 45% Work is in progress.

1351 2954

Construction of Drain / Nullah / Culverts / PCC and

Soling at UC Kari Wala i/c Mashmoola Jat, Tehsil

Shah Kot, District Nankana Sahib

Nankana SahibOn-going

Schemes15.000 10.000 1.667 0.450 0.034 8% 67% Work is in progress.

Page 85: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1352 2955

Construction of drain / soling / PCC / Nullah and

Pulyat at village Nathowala 180/RB, Chak

No.181/RB, Kari Wala and Chak No.182/RB, UC

Nathowala, District Nankana Sahib

Nankana SahibOn-going

Schemes29.700 10.000 3.333 2.500 1.667 67% 39% Work is in progress.

1353 2956

Construction of drain / soling / PCC / Nullah and

Pulyat at village Chak No.184/RB Kot Nizam Din

and Chak No.186/RB Ghandran UC Kot Nizam

Din, District Nankana Sahib

Nankana SahibOn-going

Schemes29.300 10.000 3.333 2.500 1.667 67% 40% Work is in progress.

1354 2957Construction of Drain / Soling / Nallah at UC

Saleem Pur Pakka, District Nankana Sahib Nankana Sahib

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress.

1355 2958Construction of Drain / Soling / Nallah at UC

Mangtanwala, District Nankana Sahib Nankana Sahib

On-going

Schemes30.000 10.000 3.333 4.200 3.367 80% 45% Work is in progress.

1356 2959Construction of Drain / Soling / Nallah at UC

Chachke Gill, District Nankana Sahib Nankana Sahib

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress.

1357 2960Construction of Drain / Soling / Nallah at UC Haft

Madar, District Nankana Sahib Nankana Sahib

On-going

Schemes30.000 10.000 3.333 3.000 2.167 72% 41% Work is in progress.

1358 2961Construction of Drain / Soling / Nallah in left over

area of UC Ganaish Pur, District Nankana SahibNankana Sahib

On-going

Schemes30.000 10.000 3.333 4.100 3.267 80% 44% Work is in progress.

1359 2962Construction of Drain / Soling / Nallah in left over

area of UC Jawahar Pur, Distirct Nankana Sahib Nankana Sahib

On-going

Schemes40.000 13.000 3.333 1.100 0.267 24% 33% Work is in progress.

1360 2963Construction of Drain / Soling / Nallah in left over

area of UC Jogaykot, Distirct Nankana Sahib Nankana Sahib

On-going

Schemes30.000 10.000 3.333 1.100 0.267 24% 34% Work is in progress.

1361 2964Construction of Drain / Soling / Nullah at UC jalal

Nau, District Nankana SahibNankana Sahib

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% Work is in progress.

1362 2965

Construction of Drain / Soling / Nullah at Village

Balaqian, Dodhay, Chora, Mat Kalayian and

Dharian, District Nanakana Sahib

Nankana SahibOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work is in progress.

1363 2966Provision of sewerage, PCC & Nullah at Mouza

Khiyaray Kalan, Tehsil & District Nankana SahibNankana Sahib

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Work is in progress.

1364 2967

Provision of water supply sanitation and drainage

facilities at Chak No.168/RB Machar Wali District

Nankana Sahib

Nankana SahibOn-going

Schemes112.768 23.200 3.333 2.500 1.667 67% 22% Work is in progress.

1365 2968

Construction of Nullah / Drain and PCC at Bucheki

City and at Chak No.22/75, Chak No.18/71, Chak

No.16/69, Chak No.641 Bohty Wala, Lurka Jangly,

District Nankana Sahib

Nankana SahibOn-going

Schemes50.000 40.000 3.333 0.850 0.017 2% 80% Work is in progress.

1366 2969

Construction of PCC / Drain / Nullah at Burala,

Maddo Ladoana, Juggian Nolan, Warra Narain

Singh, Jahana Nool, Peeray Wali, Chak Wattowan,

Nodhan, Sikhanwali, Kawanwali, Nizam Pura,

Baghoor, District Nankana Sahib

Nankana SahibOn-going

Schemes30.000 13.000 3.333 1.400 0.567 41% 45% Work is in progress.

1367 2970

Construction of Soling, Drains & PCC at village

Nathowala, Nizampura, Nodha, Fareedabad,

Kheokay Bhattian, Madu, Purana Syed wala ,

District Nankana Sahib

Nankana SahibOn-going

Schemes50.000 33.000 3.333 2.500 1.667 67% 69% Work is in progress.

1368 2971

Construction of PCC, Soling & Nullah at UC

Machrala i/c Bhagor, Wakeel Wala, Adampura &

Dolatpura, Distirct Nankana Sahib

Nankana SahibOn-going

Schemes30.000 10.000 3.333 4.000 3.167 79% 44% Work is in progress.

Page 86: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1369 2972Construction of PCC, Soling & Nullah at UC

Mustafaabad / Jislani, Distirct Nankana Sahib Nankana Sahib

On-going

Schemes25.000 10.000 3.333 3.150 2.317 74% 49% Work is in progress.

1370 2973Construction of PCC, Soling & Nullah at UC

Meeranpur, Distirct Nankana Sahib Nankana Sahib

On-going

Schemes25.000 10.000 3.333 0.850 0.017 2% 40% Work is in progress.

1371 2974Construction of PCC, Drains and Nallah at UC-51

Khiarraey Kalan District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress.

1372 2975Construction of PCC, Drains and Nallah at UC-52

Chokian Wala District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 0.950 0.117 12% 34% Work is in progress.

1373 2976Construction of PCC, Nallah, Drains at Syed Wala,

District Nankana SahibNankana Sahib

On-going

Schemes50.000 40.000 3.333 0.850 0.017 2% 80% Work is in progress.

1374 2977Construction of PCC, Drains and Nallah at UC-48

Rehanwala District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 0.950 0.117 12% 34% Work is in progress.

1375 2978Construction of PCC, Drains and Nallah at UC-36

Mashrala District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress.

1376 2979Construction of PCC, Drains and Nallah at UC-39

Meeranpur District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work is in progress.

1377 2980Construction of PCC, Drains and Nallah at UC-50

Ganaishpur District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 3.400 2.567 76% 50% Work is in progress.

1378 2981Construction of PCC, Drains and Nallah at UC-38

Warbutton District Nankana Sahib.Nankana Sahib

On-going

Schemes15.000 5.000 3.333 4.500 3.667 81% 58% Work is in progress.

1379 2982Construction of PCC, Drains and Nallah at UC-40

Shareen Jhangaar District SheikhupuraNankana Sahib

On-going

Schemes15.000 5.000 3.333 4.500 3.667 81% 58% Work is in progress.

1380 2983

Rural Drainage PCC Brick pavement Schemes

Beroon Mustafa Abad and Adjoining Abadies,

Tehsil & District Kasur

KasurOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Work in Progress

1381 2984

Rural Drainage PCC Brick pavement Schemes

Weghal and Adjoining Abadies, Tehsil & District

Kasur

KasurOn-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1382 2985

Rural Drainage PCC Brick pavement Schemes

Badar Pur, Ray, Badian and Adjoining Abadies,

Tehsil & District Kasur

KasurOn-going

Schemes15.000 4.966 3.333 2.500 1.667 67% 44% Work in Progress

1383 2986

Rural Drainage PCC Brick pavement Schemes

Matta and Adjoining Abadies, Tehsil & District

Kasur

KasurOn-going

Schemes20.000 9.957 3.333 2.500 1.667 67% 58% Work in Progress

1384 2987

Rural Drainage PCC Brick pavement Schemes

Khara and Adjoining Abadies, Tehsil & District

Kasur

KasurOn-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Work in Progress

1385 2988Const. of Soling Drains, PCC, Culverts U.C

Handal, Tehsil KRK, District KasurKasur

On-going

Schemes30.000 11.467 1.667 3.620 3.204 89% 49% Work in Progress

1386 2989Rural drainage scheme U.C Bhedian, District

KasurKasur

On-going

Schemes30.000 10.000 1.667 1.250 0.834 67% 36% Work in Progress

1387 2990Rural drainage scheme U.C Sheikhum, District

KasurKasur

On-going

Schemes25.000 9.993 5.000 3.750 2.500 67% 50% Work in Progress

1388 2991Rural drainage scheme U.C Fathe Pur, District

KasurKasur

On-going

Schemes30.000 9.981 1.967 1.475 0.984 67% 37% Work in Progress

1389 2992Rural drainage scheme U.C Hussain Khan Wala,

District KasurKasur

On-going

Schemes30.000 10.000 6.667 6.000 4.334 72% 48% Work in Progress

1390 2993Construction of Sewerage / Drainage / PCC

Scheme Kot Radha Kishan City, District KasurKasur

On-going

Schemes199.860 34.999 20.000 26.303 21.303 81% 28% Work in Progress

1391 2994Construction of Soling, Nallah, PCC & Drain at

Satoki, District Kasur.Kasur

On-going

Schemes15.000 4.992 3.333 2.500 1.667 67% 44% Work in Progress

1392 2995Construction of Soling, Nallah, PCC & Drain at UC

Cheena Arla and Nathoki, District KasurKasur

On-going

Schemes15.000 4.996 3.333 2.500 1.667 67% 44% Work in Progress

Page 87: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1393 2996Construction of Soling, Nallah, PCC & Drain at UC

Pemar, District KasurKasur

On-going

Schemes15.000 4.980 3.333 2.500 1.667 67% 44% Work in Progress

1394 2997Construction of soling / drains / PCC roads in Chak

No.38, District KasurKasur

On-going

Schemes3.000 2.500 0.167 0.125 0.084 67% 86% Work in Progress

1395 2998Construction of soling / drains / PCC roads in

village Chugian & Marathiwala, District KasurKasur

On-going

Schemes3.000 2.457 0.167 0.125 0.084 67% 85% Work in Progress

1396 2999Construction of soling / drains / PCC roads in

village Chaku , District KasurKasur

On-going

Schemes3.000 2.500 0.167 0.125 0.084 67% 86% Work in Progress

1397 3000Construction of Urban Sewerage, Drainage, PCC

Scheme Khudian Phase-II, District KasurKasur

On-going

Schemes360.000 35.000 10.090 7.568 5.045 67% 11% Work in Progress

1398 3001Construction of Urban Sewerage, Drainage, PCC

Scheme, Kanganpur, District KasurKasur

On-going

Schemes150.026 29.977 5.000 3.750 2.500 67% 22% Work in Progress

1399 3002Urban Water supply scheme, Kasur City, District

KasurKasur

On-going

Schemes70.526 20.000 5.000 3.750 2.500 67% 32% Work in Progress

1400 3003

Construction of drain, PCC, Tuff Tile, Culverts,

Sullage Carrier and Brick Pavement Sheikham,

Kacha Pakka, Padhana, Bath Kalan and Tara

Garh, Tehsil Pattoki, District Kasur

KasurOn-going

Schemes144.500 27.996 5.000 3.750 2.500 67% 21% Work in Progress

1401 3004

Construction of drain, PCC, Tuff Tile, Culverts,

Sullage Carrier and Brick Pavement Balloki,

Sandhu Kalan, Sarai Mughal, Beharwal and

Bhonikey, Tehsil Pattoki, District Kasur

KasurOn-going

Schemes149.000 28.000 5.000 3.750 2.500 67% 20% Work in Progress

1402 3005Rehabilitation & Re-construction of sullage carrier

at Waan Adhan, District KasurKasur

On-going

Schemes10.451 7.000 1.150 2.363 2.075 88% 87% Work in Progress

1403 3006

Construction of Drain, Brick Pavement & PCC in

Ghummankey and adjoining abadies, Tehsil

Pattoki, District Kasur

KasurOn-going

Schemes69.298 20.000 20.000 15.000 10.000 67% 43% Work in Progress

1404 3007

Construction of Drain, Brick Pavement & PCC in

Bonga Balochan and adjoining abadies, Tehsil

Pattoki, District Kasur

KasurOn-going

Schemes66.879 20.000 20.000 14.500 9.500 66% 44% Work in Progress

1405 3008

Construction of Drainage, Brick Pavement, PCC

and Sullage Carrier Scheme in Blair, Masradass i/c

adjoining abadies, Tehsil Pattoki, District Kasur

KasurOn-going

Schemes50.000 18.000 3.333 2.500 1.667 67% 39% Work in Progress

1406 3009Rural Sewerage / Drainage Scheme Chak

No.18/GD, District OkaraOkara

On-going

Schemes14.330 9.993 1.000 0.750 0.500 67% 73%

Date of A.A 26.07.2017, Date of T.S 01.08.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 26.09.2017, Date of Receipt of

tenders 27.09.2017, Date of work order ,12.10.2017

Date of completion as per PC-I ,30.06.2018

Anticipated date of completion ,30.06.2018 No. of

Beneficiary - 9878 Person,

1407 3010Rural Water Supply & Drainage Scheme, Sahbay

Wala, Depal Pur Okara

On-going

Schemes20.840 9.992 3.613 2.710 1.806 67% 57%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 9822

Person, Work is in progress.

1408 3011Rural Water Supply & Drainage Scheme, Bhakho

Shah, Depal Pur Okara

On-going

Schemes20.510 7.993 4.170 3.128 1.849 59% 48%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 6316

Person, Work is in progress.

Page 88: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1409 3012Rural Water Supply & Drainage Scheme, Dhool

Choor, Depal Pur Okara

On-going

Schemes20.325 7.992 4.108 3.081 0.539 17% 42%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 9804

Person, Work is in progress.

1410 3013Rural Water Supply & Drainage Scheme, Aman

Wala, Depal Pur Okara

On-going

Schemes19.930 9.991 3.310 2.483 1.325 53% 57%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 4246

Person, Work is in progress.

1411 3014Rural Water Supply & Drainage Scheme, Dhol

Gehla, Depal Pur Okara

On-going

Schemes17.400 7.987 3.133 2.350 1.523 65% 55%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 3302

Person Work is in progress.

1412 3015Rural Water Supply & Drainage Scheme, Mehro

Kalan, Depal Pur Okara

On-going

Schemes17.190 7.500 3.230 2.423 1.060 44% 50%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 6277

Person Work is in progress.

1413 3016Rural Water Supply & Drainage Scheme, Somian

Bholon, Depal Pur Okara

On-going

Schemes17.660 9.972 2.553 1.915 1.262 66% 64%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 3678

Person Work is in progress.

1414 3017Rural Water Supply & Drainage Scheme, Roori,

Depal Pur Okara

On-going

Schemes15.520 9.991 1.840 1.380 0.920 67% 70%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 3005

Person Work is in progress.

1415 3018Rural Water Supply & Drainage Scheme, Mali

Singh, Depal Pur Okara

On-going

Schemes17.900 7.912 3.300 2.475 1.613 65% 53%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 3813

Person Work is in progress.

1416 3019Rural Water Supply & Drainage Scheme, Khan

Bahadar, Depal Pur Okara

On-going

Schemes25.790 9.970 5.263 3.947 2.916 74% 50%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 5319

Person Work is in progress.

1417 3020Rural Water Supply & Drainage Scheme, Kalia

Ibrahim, Depal Pur Okara

On-going

Schemes22.970 4.992 5.990 4.493 2.234 50% 31%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 07-12-2017 Date of Receipt of

tenders 08-12-2017 Date of work order 14-12-2017

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 2866

Person Work is in progress.

1418 3021Rural Water Supply & Drainage Scheme,

Shamaskay, Depal Pur Okara

On-going

Schemes19.710 10.000 3.237 2.428 1.615 67% 59%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018, A

nticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 2619

Person Work is in progress.

Page 89: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1419 3022Rural Water Supply & Drainage Scheme, Subhan

Shah, Depal Pur Okara

On-going

Schemes22.450 9.995 4.150 3.113 1.841 59% 53%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 5870

Person Work is in progress.

1420 3023Rural Water Supply & Drainage Scheme, Bothana,

Depal Pur Okara

On-going

Schemes21.110 9.999 3.703 2.777 1.852 67% 56%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 5652

Person Work is in progress.

1421 3024Rural Water Supply & Drainage Scheme,

Sahniwal, Depal Pur Okara

On-going

Schemes21.510 11.000 3.503 2.627 1.774 68% 59%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary 4724

Person Work is in progress.

1422 3025Rural Water Supply & Drainage Scheme, Chak no.

7/D Rakh Dharma, Depal Pur Okara

On-going

Schemes17.270 9.993 2.423 1.817 1.163 64% 65%

Date of A.A 26.07.2017, Date of T.S 01.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 3781

Person, Work is in progress.

1423 3026Rural Water Supply & Drainage Scheme,

Kandowal Sarai, Depal Pur Okara

On-going

Schemes18.500 9.992 2.833 2.125 1.413 66% 62%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 07-12-2017 Date of Receipt of

tenders 08-12-2017 Date of work order 12-12-2017

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 6281

Person, Work is in progress.

1424 3027Rural Water Supply & Drainage Scheme, Chak no.

19/D, Depal Pur Okara

On-going

Schemes18.330 9.997 2.777 2.083 1.923 92% 65%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 4604

Person, Work is in progress.

1425 3028Rural Water Supply & Drainage Scheme, Sarai

Amar Singh, Depal Pur Okara

On-going

Schemes21.320 9.998 3.773 2.830 1.792 63% 55%

Date of A.A 26.07.2017, Date of T.S 01.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 6642

Person, Work is in progress.

1426 3029Rural Water Supply & Drainage Scheme, Chak

Kamboh, Depal Pur Okara

On-going

Schemes21.650 9.999 3.883 2.912 1.907 65% 55%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 5441

Person, Work is in progress.

1427 3030Rural Water Supply & Drainage Scheme, Doola

Mustakim , Depal Pur Okara

On-going

Schemes19.930 9.986 3.310 2.483 1.645 66% 58%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 10.10.2017, Date of Receipt of

tenders 11.10.2017, Date of work order 16-11-2017,

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 3942

Person, Work is in progress.

Page 90: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1428 3031Rural Water Supply & Drainage Scheme, Bonga

Saleh, Depal Pur Okara

On-going

Schemes21.580 9.992 3.860 2.895 1.874 65% 55%

Date of A.A 26.07.2017, Date of T.S 01.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 07-12-2017 Date of Receipt of

tenders 08-12-2017 Date of work order 14-12-2017

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 7909

Person, Work is in progress.

1429 3032

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara Chak no.

38-GD

OkaraOn-going

Schemes64.454 7.800 3.333 2.500 0.735 29% 13%

Date of A.A 11.08.2017, Date of T.S 15.08.2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 08.10.2017, Date of Receipt of

tenders 09.10.2017, Date of work order 18-11-2017,

Date of completion as per PC-I 30.06.2019,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary -14313

Person, Work is in progress.

1430 3033

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara Chak no.

4/GD

OkaraOn-going

Schemes25.000 9.999 3.333 2.500 1.297 52% 45%

Date of A.A 26.07.2017, Date of T.S 31-07-2017,

Date of Prequalification 13-09-2017, Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order ,07-02-2018

Date of completion as per PC-I 30.06.2018,

Anticipated date of completion 30.06.2019, Funds

Release on 20-07-2018 No. of Beneficiary - 10018

Person,

1431 3034Soling / Sewerage and Drainage of Chak No.

53/2L, 54/2L, 55/2L, District OkaraOkara

On-going

Schemes20.000 9.999 3.333 2.500 1.667 67% 58%

Date of A.A 26.07.2017, Date of T.S 31-07-2017,

Date of Prequalification ,13.09.2017 Date of

invitation of tenders 18-12-.2017, Date of Receipt of

tenders 19-12-2017, Date of work order 19-01-2018

Date of completion as per PC-I , Anticipated date of

completion, 30-06-2019 Funds Release on 20-07-

2018 No. of Beneficiary - 51657 Person,

1432 3035Provision of Soling and Drainage Scheme at U.C.

No.42/3R, District Okara Okara

On-going

Schemes14.000 6.986 2.333 1.750 0.875 50% 56%

Date of A.A 08.08.2017, Date of T.S 10.08.2017

Date of Prequalification ,13.09.2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 31-09-2017

Date of completion as per PC-I , Anticipated date of

completion , 30-06-2019 Funds Release on 20-07-

2018 No. of Beneficiary - 49251 Person, Work is in

progress.

1433 3036Provision of Soling and Drainage Scheme at U.C.

No.35/2RA, District Okara Okara

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58%

Date of A.A 26.07.2017, Date of T.S 02-08-2017

Date of Prequalification ,13.09.2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 12-12-2017

Date of completion as per PC-I , Anticipated date of

completion, 30-06-2019 Funds Release on 20-07-

2018 No. of Beneficiary - 33832 Person,

1434 3037Provision of Tuff Tiles Soling, PCC, and Drainage

Schemes at Haveli Lakha and Adjoining Abadies Okara

On-going

Schemes48.940 18.295 3.333 2.500 1.660 66% 41%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification ,13.09.2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 20-11-2017

Date of completion as per PC-I , Anticipated date of

completion, 30-06-2019 Funds Release on 20-07-

2018 No. of Beneficiary 42300 Person, Work is in

progress.

1435 3038

Installation of LED Street Light 120/W, 50/W

including Pools, Construction of Sullage Carrier /

sewerage & Construction of Tuff Paver different

places at Okara City approx. District Okara

OkaraOn-going

Schemes74.312 38.998 3.333 2.500 1.667 67% 55%

Date of A.A 11.08.2017, Date of T.S 27.09.2017,

Date of Prequalification 19-09-2017 Date of

invitation of tenders 03.11.2017, Date of Receipt of

tenders 03.11.2017, Date of work order 09-11-2017

Date of completion as per PC-I , Anticipated date of

completion, 30-06-2019 Funds Release on 20-07-

2018 No. of Beneficiary 215982 Person Work is in

progress.

1436 3039Construction of Tuff Tiles / Sewerage and

Drainage of Ward no. 1 to 50, District Okara Okara

On-going

Schemes40.000 14.957 3.333 2.500 1.762 70% 42%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 17-11-2017

Date of completion as per PC-I , 30-06-2018

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary -640401

Person,

1437 3040

City Package Renala Khurd Tuff Tile and

Sewerage Androon City Gilyat Renala Khurd In

District Okara

OkaraOn-going

Schemes35.000 15.584 3.333 2.500 1.667 67% 49%

Date of A.A 26.07.2017, Date of T.S 01.08.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 07-11-2017

Date of completion as per PC-I 30-06-2018

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - 64595

Person,

Page 91: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1438 3041

Sewerage Scheme at Mohallah Shakoor Abad,

Mohallah Eid Gah, Mohallah Masjid Basharat,

Akhter Town, Haveli Lakha, City.

OkaraOn-going

Schemes49.934 22.496 3.333 2.500 1.665 67% 48%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 18-11-2017

Date of completion as per PC-I ,30-06-2018

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - Person,

1439 3042 Water supply Schemes for NA-145 OkaraOn-going

Schemes300.000 74.642 20.000 20.990 20.990 100% 32%

Date of A.A 28-09-2017 Date of T.S 16-11-2017

Date of Prequalification 18-11-2017 Date of

invitation of tenders 13-12-2017 Date of Receipt of

tenders, 13-12-2017 Date of work order 23-12-2017

Date of completion as per PC-I 23-12-2020

Anticipated date of completion, 30-06-2020Re-

Appropreation (+)5.990 No. of Beneficiary 900043

Person,

1440 3043

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara:in Mouza

Jaboka

OkaraOn-going

Schemes23.299 11.494 3.333 2.500 1.669 67% 56%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 25-01-2018

Date of completion as per PC-I ,25-01-2019

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - 14607

Person,

1441 3044

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara Mouza

Lasharian

OkaraOn-going

Schemes49.895 17.413 3.333 2.500 1.713 69% 38%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 25-01-2018

Date of completion as per PC-I 25-01-2019

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - 17695

Person,

1442 3045

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara Mouza

Kohla

OkaraOn-going

Schemes26.331 4.996 3.333 2.500 1.705 68% 25%

Date of A.A 26.07.2017, Date of T.S 02.08.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 18-12-.2017, Date of Receipt of

tenders 19-12.2017, Date of work order 19-01-2018

Date of completion as per PC-I 19-01-2019

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - 21476

Person,

1443 3046

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara Mouza

Bama Bala

OkaraOn-going

Schemes18.346 13.991 1.282 0.962 0.682 71% 80%

Date of A.A 26.07.2017, Date of T.S 31.07.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 18-11-2017

Date of completion as per PC-I 30-06-2018

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - 12896

Person, Work is in progress.

1444 3047

Construction of Drain, Brick Pavement, Sullage

Carrier, Tuff Tile, PCC in District Okara Mouza

Maroula Sharif

OkaraOn-going

Schemes27.702 14.999 4.234 3.176 2.059 65% 62%

Date of A.A 08.08.2017, Date of T.S 12.08.2017,

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 23-12-2017

Date of completion as per PC-I 30-06-2018

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary - 09561

Person,

1445 3048Provision of Drainage, Sewerage and Tuff Till

Scheme at Civil Area Okara Cantt, District Okara Okara

On-going

Schemes20.000 5.377 4.833 3.625 2.467 68% 39%

Date of A.A 12-09-2017 Date of T.S 16-09-2017

Date of Prequalification 13-09-2017 Date of

invitation of tenders 27.10.2017, Date of Receipt of

tenders 28.10.2017, Date of work order 20-11-2017

Date of completion as per PC-I 30-06-2018

Anticipated date of completion, 30-06-2019 Funds

Release on 20-07-2018 No. of Beneficiary 98441

Person, Work is in progress.

1446 3049

Providing of Tuff Tile & Sewerage / Drainage in

Basirpur and Mandi Ahmad Abad Town, District

Okara

OkaraOn-going

Schemes26.398 9.999 3.333 4.167 0.816 20% 41% Work is in progress.

1447 3050Water Supply / Sewerage / Filtration Plants in 13

UCs of PP-221, SahiwalSahiwal

On-going

Schemes150.000 34.996 16.667 12.500 10.100 81% 30%

Date of AA 06.12.2017 , Date of receipt of tender

28.03.2018 , Work order 18.04.2018 , Work in

progress.

1448 3051 Water Supply Scheme for Chak No. 78/5L Sahiwal SahiwalOn-going

Schemes30.000 10.000 6.667 5.000 5.000 100% 50%

Date of AA 19.08.2017, Date of Pre-qualification ,

Date of Work Order 23.12.2017 , Anticipated date of

completion 30.06.2019 subject to availablity of

balance funds, Work in progress.

1449 3052

Construction of Drain / Soling Sewerage Nala

Chak no. 50/12L, 105/12L, 106/12/L, District

Sahiwal

SahiwalOn-going

Schemes15.000 5.000 3.333 2.500 2.000 80% 47%

Date of AA 01.08.2017 , Date of receipt of tender

20.11.2017 , Date of Work Order 02.12.2017 ,

Anticipated date of completion 30.06.2019 subject

to availablity of balance funds, Work in progress.

Page 92: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1450 3053

Construction of Drain / Soling Sewerage Nala

Chak no.38/14L,39/14L/40/14L, 41/14L , District

Sahiwal

SahiwalOn-going

Schemes15.000 4.998 3.333 2.500 1.660 66% 44%

Date of AA 01.08.2017 , Date of receipt of tender

09.11.2017 , Date of Work Order 24.11.2017 ,

Anticipated date of completion 30.06.2019 subject

to availablity of balance funds, Work in progress.

1451 3054

Construction of Drain / Soling Sewerage Nala

Chak no. 40/12L, 109/12L, Ghulshan Colony,

District Sahiwal

SahiwalOn-going

Schemes15.000 4.977 3.333 2.500 2.000 80% 47%

Date of AA 01.08.2017 , Date of receipt of tenders

09.11.2017 , Date of Work Order 24.11.2017 ,

Anticipated date of completion 30.06.2019 subject

to availablity of balance funds, Work in progress.

1452 3055

Construction of Drain / Soling Sewerage Nala

Chak no. 118/12L, 117/12L, Ada Kassowal, District

Sahiwal

SahiwalOn-going

Schemes15.000 7.488 2.500 1.875 1.500 80% 60%

Date of AA 01.08.2017 , Date of receipt of tender

20.11.2017 , Date of Work Order 02.12.2017 ,

Anticipated date of completion 30.06.2019 subject

to availablity of balance funds, Work in progress.

1453 3056

Contruction of Drain / Soling Sewerage Nala Chak

no. 119/7DR, 120/7ER, 121/7ER, 122/7ER,

117/7DR, District Sahiwal

SahiwalOn-going

Schemes15.000 7.495 2.500 1.875 1.600 85% 61%

Date of AA 01.08.2017, Date of receipt of tender

09.11.2017, Date of Work Order 24.11.2017,

Anticipated date of completion 30.06.2019 subject

to availablity of balance funds, Work in progress.

1454 3057

Construction of Drain / Soling Sewerage Nala

Chak no. 114/7R, 115/7CR, 116/7CR Sahwa,

Dharma, District Sahiwal

SahiwalOn-going

Schemes15.000 7.499 2.500 1.875 1.600 85% 61%

Date of AA 01.08.2017, Date of receipt of tender

09.11.2017, Date of Work Order

24.11.2017,Anticipated date of completion

30.06.2019 subject to availablity of balance funds,

Work in progress.

1455 3058

Construction of Drain / Soling Sewerage Nala

Chak no. 112/7r, 113/7r, Purani Chichawatni,

Sheikh Tayyab, District Sahiwal

SahiwalOn-going

Schemes15.000 7.497 2.500 1.875 1.700 91% 61%

Date of AA 01.08.2017 , Date of receipt of tender

09.11.2017 , Date of Work Order

02.12.2017,Anticipated date of completion

30.06.2019 subject to availablity of balance funds,

Work in progress,

1456 3059Installation of Filtration Plant at 60/5L in District

Sahiwal Sahiwal

On-going

Schemes3.000 1.500 0.500 0.375 0.250 67% 58%

Date of AA 01.08.2017, Date of receipt of tender

11.09.2017, Date of Work Order 31.10.2017, Date

of Completion 30.06.2019 , Scheme completed.

Balance funds will be re-appropriated.

1457 3060Installation of Filtration Plant at 79/5R in District

Sahiwal Sahiwal

On-going

Schemes3.000 1.500 0.500 0.375 0.072 19% 52%

Date of AA 01.08.2017, Date of receipt of tender

11.09.2017, Date of Work Order 31.10.2017, Date

of Completion 30.06.2019 , Scheme completed in

saving. Balance funds will be re-appropriated.

1458 3061Rural Water Supply Scheme ChakNo. 20/SP

Tehsil and District Pakpattan Pakpattan

On-going

Schemes31.190 9.000 7.397 5.548 4.498 81% 43%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 23.09.2017, Funds released by FD =

03.08.2018,Funds online = 13.08.2018,Work in

progress.

1459 3062Rural Water Supply Scheme Kumari Wala Tehsil

and District Pakpattan Pakpattan

On-going

Schemes34.670 14.978 5.223 3.917 2.612 67% 51%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 31.10.2017, Funds released by FD =

03.08.2018,Funds online = 13.08.2018,Work in

progress.

1460 3063Rural Water Supply Scheme Chak No. 67/D Tehsil

and District Pakpattan Pakpattan

On-going

Schemes32.440 8.700 7.813 5.860 4.120 70% 40%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 23.09.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1461 3064Rural Water Supply Scheme Dhupai Tehsil and

District Pakpattan Pakpattan

On-going

Schemes29.980 16.000 4.660 3.495 2.330 67% 61%

Date of A.A= 01.08.2017. Date of T.S= 04.08.2017.

Date of receipt of tenders = 24.08.2017. Date of

work order= 18.09.2017. Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1462 3065Rural Water Supply Scheme Chak No. 29/KB in

District Pakpattan Pakpattan

On-going

Schemes19.978 10.000 3.326 2.495 1.750 70% 59%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 31.10.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1463 3066Rural Water Supply Scheme Chak No. 111/EB in

District Pakpattan Pakpattan

On-going

Schemes29.412 8.000 7.137 5.353 4.270 80% 42%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 31.10.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1464 3067Rural Drainage Scheme Chak No. 74/D Tehsil and

District Pakpattan Pakpattan

On-going

Schemes27.671 15.000 4.224 3.168 2.112 67% 62%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 23.09.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1465 3068Rural Drainage Scheme 8/EB Tehsil and District

Pakpattn Pakpattan

On-going

Schemes23.979 13.979 3.333 2.500 1.667 67% 65%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 31.10.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

Page 93: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1466 3069Rural Drainage Scheme 90/D Tehsil and District

Pakpattan Pakpattan

On-going

Schemes29.303 19.000 3.434 2.576 1.850 72% 71%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 23.09.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1467 3070Rural Drainage scheme in Various UCs of PP-228

District PakpattanPakpattan

On-going

Schemes74.312 25.000 8.333 6.250 4.356 70% 40%

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,

Date of receipt of tenders = 21.10.2017, Date of

work order= 13.11.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1468 3071

Provision of Sewerage/ Tuff Tile / PCC / Soling /

Nallian in Various UC's of PP-228 in District

Pakpattan

PakpattanOn-going

Schemes74.312 25.000 16.437 12.328 8.450 69% 45%

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,

Date of receipt of tenders = 21.10.2017, Date of

work order= 13.11.2017, Funds released by FD =

03.08.2018Funds online = 15.08.2018,Work in

progress.

1469 3072Rural Sewerage / Drainage Scheme Jamman

Shah in District Pakpattan Pakpattan

On-going

Schemes37.413 6.000 10.471 7.853 6.756 86% 34%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 31.10.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1470 3073Rural Sewerage / Drainage Scheme Chak No.

123/EB in District Pakpattan Pakpattan

On-going

Schemes31.582 20.000 1.304 0.978 0.652 67% 65%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 23.09.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1471 3074Rural Sewerage / Drainage Scheme Chak

No.211/EB in District PakpattanPakpattan

On-going

Schemes36.230 27.376 2.610 1.958 1.770 90% 80%

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017,

Date of receipt of tenders = 24.08.2017, Date of

work order= 23.09.2017, Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress.

1472 3075

Provision of Drainage/ Sewerage Schemes at

Chak No. 161/E.B and Union Council NO.35

(Headquarters 13/EB) Tehsil Arifwala District

Pakpattan

PakpattanOn-going

Schemes35.785 12.976 6.762 5.072 0.000 0% 36%

Amended A.A issued on 27.01.2018.Tender

received on 07.02.2018 and Additional performance

security received on 13.02.2018 and Work order

issued on 17.02.2018.Funds released by FD =

03.08.2018Funds online = 13.08.2018,Work in

progress. Contractor liability amounting to Rs.2.500

million stands. The case submitted to P&D

Department Lahore for correction of project code.

1473 3076Provision of PCC / Sewerage / Drainage / Tuff tiles

etc. in PP-227, District PakpattanPakpattan

On-going

Schemes150.000 33.142 8.333 6.250 6.250 100% 26%

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,

Date of receipt of tenders = 21.10.2017, Date of

work order= 13.11.2017,Funds released by FD =

03.08.2018Funds online = 15.08.2018,Work in

progress.

1474 3077Provision of PCC / Sewerage / Drainage / Tuff tiles

etc. in NA-165, District PakpattanPakpattan

On-going

Schemes148.624 34.998 16.667 12.500 9.250 74% 30%

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,

Date of receipt of tenders = 21.10.2017, Date of

work order= 13.11.2017,Funds released by FD =

03.08.2018Funds online = 15.08.2018,Work in

progress.

1475 3078Provision of PCC / Sewerage / Drainage / Tuff

Tiles etc. in PP-231Pakpattan

On-going

Schemes148.624 31.997 8.333 6.250 5.150 82% 25%

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017,

Date of receipt of tenders = 21.10.2017, Date of

work order= 13.11.2017,Funds released by FD =

03.08.2018Funds online = 15.08.2018,Work in

progress.

1476 3079

Rural Water Supply and Drainage Scheme Basti

Nazak Nagar, Tehsil Jalapur Pirwala, District

Multan

MultanOn-going

Schemes49.180 14.982 11.393 8.545 5.697 67% 42%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 10.01.2018

7.Date of Completion as per PC-l 30.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 4578 persons. Work is in progress

1477 3080Rural Drainage / Sewerage Scheme Basti Bahadur

Pur Tehsil Jalalpur Pirwala District MultanMultan

On-going

Schemes48.970 14.960 11.323 8.492 5.652 67% 42%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 22.12.2017

7.Date of Completion as per PC-l 21.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries = persons. Work is in progress

Page 94: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1478 3081Rural Drainage / Sewerage Scheme Shujat Pur

Tehsil Jalalpur Pirwala District MultanMultan

On-going

Schemes49.070 15.000 11.357 8.518 5.657 66% 42%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 23.12.2017

7.Date of Completion as per PC-l 22.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries - persons. Work is in progress

1479 3082Rural Water Supply Scheme Chak No.55/M and

56/M District MultanMultan

On-going

Schemes14.000 4.947 3.000 2.250 1.500 67% 46%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 03.11.2017 7.Date

of Completion as per PC-l 02.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 4572 persons. Work is in progress

1480 3083Rural Water Supply Scheme Chak No.71, 72 &

73/M District MultanMultan

On-going

Schemes21.000 9.834 3.667 2.750 1.832 67% 56%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 27.11.2017 7.Date

of Completion as per PC-l 26.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 6354 persons. Work is in progress

1481 3084Rural Water Supply Scheme Chak No.76, 77 and

78/M District MultanMultan

On-going

Schemes21.000 9.949 3.667 2.750 1.832 67% 56%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 27.11.2017 7.Date

of Completion as per PC-l 26.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 4687 persons. Work is in progress

1482 3085Rural Water Supply Scheme Chak No.79, 80 &

81/M District MultanMultan

On-going

Schemes21.000 9.853 3.667 2.750 1.834 67% 56%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 27.11.2017 7.Date

of Completion as per PC-l 26.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 6554 persons. Work is in progress

1483 3086

Rural Water Supply Scheme Mouza Obvra

Shumali Saray Khara and Jungle Ameer Hussain

District Multan

MultanOn-going

Schemes14.000 6.840 2.333 1.750 1.167 67% 57%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 03.11.2017 7.Date

of Completion as per PC-l 02.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 12354 persons. Work is in progress

1484 3087Rural Sewerage Scheme Basti Nandla North &

South District MultanMultan

On-going

Schemes45.000 14.990 3.333 2.500 2.459 98% 39%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 19.01.2018

7.Date of Completion as per PC-l 18.07.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 11358 persons. Work is in progress

1485 3088Rural Sewerage Scheme Adda band Bosan, Roye

Hatti & Mattay Hatti District MultanMultan

On-going

Schemes40.600 9.919 3.333 2.500 1.667 67% 29%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 01.01.2018

7.Date of Completion as per PC-l 30.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 13474 persons. Work is in progress

Page 95: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1486 3089Rural Sewerage Scheme Ghousabad, District

MultanMultan

On-going

Schemes37.000 8.690 3.333 2.500 1.667 67% 28%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 29.12.2017 7.Date

of Completion as per PC-l 28.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 14879 persons. Work is in progress

1487 3090Rural Drainage / Sewerage Scheme Chah

Bananwala District MultanMultan

On-going

Schemes14.970 9.995 1.657 1.243 0.829 67% 72%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 23.12.2017 7.Date

of Completion as per PC-l 22.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 9476 persons. Work is in progress

1488 3091

Rural Sewerage Scheme Taj Pur Sandila,

Dhareeban Thahti Sandila Faiz Town UC 95

Tehshil & District Multan

MultanOn-going

Schemes49.980 14.980 3.333 2.500 1.667 67% 33%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 29.12.2017

7.Date of Completion as per PC-l 28.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 4658 persons. Work is in progress

1489 3092Rural Sewerage Scheme Qasim Bela, Basti

Langrial Tehsil and District MultanMultan

On-going

Schemes32.410 13.975 3.333 2.500 1.667 67% 48%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.12.2017 7.Date

of Completion as per PC-l 27.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 4789 persons. Work is in progress

1490 3093Rural Sewerage Scheme Mouza Ajwani / Sharif

District MultanMultan

On-going

Schemes96.500 29.998 3.333 2.500 1.667 67% 33%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 05.01.2018

7.Date of Completion as per PC-l 04.07.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 6589 persons. Work is in progress

1491 3094Rural Drainage, Soling and Tuff Tile Scheme in

Union Council Bagrian District MultanMultan

On-going

Schemes50.000 19.949 3.333 2.500 1.667 67% 43%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 17.01.2018

7.Date of Completion as per PC-l 30.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries = persons. Work is in progress

1492 3095Rural Drainage, Soling and Tuff Tile Scheme in

Union Council Hilal Wajah District MultanMultan

On-going

Schemes50.000 19.973 3.333 2.500 1.667 67% 43%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 27.12.2017

7.Date of Completion as per PC-l 26.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries = persons. Work is in progress

1493 3096Rural Drainage, Soling and Tuff Tile Scheme in

Union Council Gardez Pur District MultanMultan

On-going

Schemes50.000 19.981 3.333 2.500 1.667 67% 43%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 23.12.2017

7.Date of Completion as per PC-l 22.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries = persons. Work is in progress

1494 3097Rural Drainage / Sewerage Scheme Kotla Chakar

Jalalpur Pirwala District MultanMultan

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 28.12.2017

7.Date of Completion as per PC-l 27.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 4587 persons. Work is in progress

Page 96: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1495 3098Rural Drainage / Sewerage Scheme Basti Mithu

Gharbi District MultanMultan

On-going

Schemes30.000 9.850 3.333 2.500 1.667 67% 38%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 10.11.2017 7.Date

of Completion as per PC-l 09.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 13254 persons. Work is in progress

1496 3099Rural Drainage / Sewerage Scheme Muqeempur

District MultanMultan

On-going

Schemes33.000 11.974 3.333 2.500 1.667 67% 41%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 21.12.2017 7.Date

of Completion as per PC-l 20.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 13546 persons. Work is in progress

1497 3100Rural Drainage / Sewerage Scheme Munshi Wala

District MultanMultan

On-going

Schemes39.000 11.994 3.333 2.500 1.667 67% 35%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 10.01.2018 7.Date

of Completion as per PC-l 09.07.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 12144 persons. Work is in progress

1498 3101Rural Drainage / Sewerage Scheme Lal Wah

District MultanMultan

On-going

Schemes25.000 9.931 3.333 2.500 1.667 67% 46%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 11.12.2017 7.Date

of Completion as per PC-l 10.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 14456 persons. Work is in progress

1499 3102Rural Drainage / Sewerage Scheme Obara

Shumali District MultanMultan

On-going

Schemes30.000 11.699 3.333 2.500 1.667 67% 45%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 10.11.2017 7.Date

of Completion as per PC-l 09.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 11243 persons. Work is in progress

1500 3103Rural Drainage / Sewerage Scheme Jagoo Wala

District MultanMultan

On-going

Schemes50.000 9.976 3.333 2.500 1.667 67% 23%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 01.02.2018

7.Date of Completion as per PC-l 30.07.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 3547 persons. Work is in progress

1501 3104Rural Sewerage / Drainage Scheme Kotla Abdul

Fateh District MultanMultan

On-going

Schemes20.000 9.990 3.333 2.500 1.667 67% 58%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.12.2017 7.Date

of Completion as per PC-l 27.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 6547 persons. Work is in progress

1502 3105

Rural Drainage Scheme Basti Kothy Wala, New

Kothy Wala, Basti Utar Wali and Haroo Wala

Mouza Kothy Wala District Multan

MultanOn-going

Schemes30.000 9.994 3.333 2.500 1.667 67% 39%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 19.02.2018 7.Date

of Completion as per PC-l 18.08.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries - persons. Work is in progress

Page 97: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1503 3106 Rural Drainage Scheme UC 18/MR, District Multan MultanOn-going

Schemes26.000 9.521 3.333 2.500 1.667 67% 43%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.01.2018 7.Date

of Completion as per PC-l 27.07.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries - persons. Work is in progress

1504 3107Rural Water Supply Scheme Mouza Matotli and

Qaiser Pur District MultanMultan

On-going

Schemes14.000 6.962 2.333 1.750 1.167 67% 58%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 03.11.2017 7.Date

of Completion as per PC-l 02.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 10452 persons. Work is in progress

1505 3108Rural Water Supply Scheme Mouza Sha Musa and

Muqeem Pur District MultanMultan

On-going

Schemes14.000 6.942 2.333 1.750 1.167 67% 58%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 03.11.2017 7.Date

of Completion as per PC-l 02.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 11365 persons. Work is in progress

1506 3109

Rural Water Supply Scheme Mouza Adu Wali,

Inayat Pur, Mochi Panhuwah, Basti Bairar District

Multan

MultanOn-going

Schemes21.000 9.849 3.667 2.750 1.834 67% 56%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 14.12.2017 7.Date

of Completion as per PC-l 13.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 9878 persons. Work is in progress

1507 3110Rural Water Supply Scheme Mouza Obvra Janubi,

Basti Lang and Nauraja Bhutta District MultanMultan

On-going

Schemes15.000 6.844 2.667 2.000 1.334 67% 55%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 03.11.2017 7.Date

of Completion as per PC-l 02.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 7458 persons. Work is in progress

1508 3111

Rural Sewerage/ Drainage scheme Katcha Talla,

ict Munirabad, Kot Shehbaz Pull 18-Kassi Bhdhla

Road Tehsil & district Multan

MultanOn-going

Schemes44.530 15.000 9.843 7.382 4.922 67% 45%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 13.01.2018

7.Date of Completion as per PC-l 30.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 11354 persons. Work is in progress

1509 3112

Rural Sewerage Scheme 18-Kassi Ghareeb Abad

and Adjoining Abadies UC Jhok Lashkar Pur

District Multan

MultanOn-going

Schemes44.470 14.956 9.823 7.367 4.912 67% 45%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 28.12.2017

7.Date of Completion as per PC-l 27.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 4687 persons. Work is in progress

1510 3113Rural Sewerage Scheme Asghar Pur and Munir

Abad, UC Jhok Lashkar Pur District MultanMultan

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 23.12.2017 7.Date

of Completion as per PC-l 22.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 4589 persons. Work is in progress

Page 98: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1511 3114Rural Drainage Scheme UC Kot Rab Nawaz, UC

120 District MultanMultan

On-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 14.12.2017 7.Date

of Completion as per PC-l 13.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries = persons. Work is in progress

1512 3115Rural Drainage Scheme UC 123 Jalal Abad

Shumali District MultanMultan

On-going

Schemes15.000 9.962 1.667 1.250 0.834 67% 72%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.12.2017 7.Date

of Completion as per PC-l 27.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries = persons. Work is in progress

1513 3116Rural Drainage Scheme UC 131 Chatha District

MultanMultan

On-going

Schemes20.000 9.997 3.333 2.500 1.667 67% 58%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 03.11.2017 7.Date

of Completion as per PC-l 02.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries = persons. Work is in progress

1514 3117Rural Drainage Scheme UC 134 Kiri Tamak

District MultanMultan

On-going

Schemes20.000 9.910 3.333 2.500 1.667 67% 58%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 21.11.2017 7.Date

of Completion as per PC-l 20.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries = persons. Work is in progress

1515 3118Rural Sewerage Scheme Basti Beat Wala Ajwain

Sharif Tehsil & District MultanMultan

On-going

Schemes11.540 4.982 2.180 1.635 1.090 67% 53%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.12.2017 7.Date

of Completion as per PC-l 27.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries= 12358 persons. Work is in progress

1516 3119Rural Sewerage Scheme Tiab Masood Pur, Tehsil

& District Multan Multan

On-going

Schemes33.470 12.346 3.333 2.500 1.667 67% 42%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 23.12.2017

7.Date of Completion as per PC-l 22.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries =14356 persons. Work is in

progress

1517 3120Rural Sewerage Scheme Sharif Pura New

Shalimar Tehsil & District MultanMultan

On-going

Schemes38.080 10.625 3.333 2.500 1.662 66% 32%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 19.01.2018 7.Date

of Completion as per PC-l 18.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries =10358 persons. Work is in progress

1518 3121Rural Sewerage Scheme Gareen Town Deen Pur

& Jarran Wala District MultanMultan

On-going

Schemes41.960 7.499 3.333 2.500 1.664 67% 22%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 14.02.2018

7.Date of Completion as per PC-l 13.08.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries =12548 persons. Work is in

progress

Page 99: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1519 3122Sewerage Scheme Zakaria Town Phase-III District

MultanMultan

On-going

Schemes16.500 9.908 2.167 1.625 1.084 67% 67%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 27.11.2017 7.Date

of Completion as per PC-l 26.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries =14225 persons. Work is in progress

1520 3123Main Sewerage Line for Farrukh Town & Raja Pur,

District MultanMultan

On-going

Schemes49.990 25.000 3.333 2.500 1.660 66% 53%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 04.01.2018

7.Date of Completion as per PC-l 03.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries =11658 persons. Work is in

progress

1521 3124 Water Purification Plants 10 District Multan MultanOn-going

Schemes20.000 9.940 3.333 2.500 1.667 67% 58%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 14.12.2017 7.Date

of Completion as per PC-l 13.06.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries =14212 persons. Work is in progress

1522 3125Rural Drainage Scheme UC-Khan Pur maral,

District MultanMultan

On-going

Schemes13.000 9.967 1.000 0.750 0.500 67% 81%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 30.01.2018 7.Date

of Completion as per PC-l 29.07.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries = persons. Work is in progress

1523 3126Funds for drain/sewerage and soling for UC 95 &

96 City Shujabad. District MultanMultan

On-going

Schemes80.000 26.735 3.333 8.884 8.783 99% 44%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 05.01.2018

7.Date of Completion as per PC-l 30.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 10.No. of

beneficiaries 5587 persons. Work is in progress

1524 3127Funds for drain/sewerage, soling from Raja Ram,

Bagrain and Shahpur. District MultanMultan

On-going

Schemes40.000 16.976 3.333 2.500 1.665 67% 47%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 23.12.2017

7.Date of Completion as per PC-l 22.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries= 6987 persons. Work is in progress

1525 3128

Rural Sewerage and Drainage Scheme, Tuff Tile

Pavement in Basti Ado Wali, Basti Adam Wali,

Basti Dhando, Basti Hayat Pur, Basti Balocha,

Wach Sandela, Basti Ali Pur Sadat and Basti Gull

Wala UC Ali Pur Sadat District Multan

MultanOn-going

Schemes28.000 14.999 4.333 3.250 2.167 67% 61%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 21.11.2017 7.Date

of Completion as per PC-l 20.05.2019 8. Anticipated

date of completion 30.06.2018 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries =15325 persons. Work is in progress

1526 3129

Rural Sewerage and Drainage Scheme, Tuff Tile

Pavement in Basti Brar, Basti Pathan Wala, Basti

Ahmad Wali, Basti Daya, Basti Barzawah, Basti

Lohar, Basti Inayat Pur, Basti Sial, Basti Saif Ullah

Shah, Basti Gakhar, Basti Bagh Arain Wali, Basti

Miani, Basti Ranojha, Basti Saich Wali, Basti

Deewan Wali and Basti Mochian Wali UC Inayat

Pur District Multan

MultanOn-going

Schemes30.000 9.972 6.667 5.000 3.334 67% 44%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 29.11.2017 7.Date

of Completion as per PC-l 28.05.2019 8. Anticipated

date of completion 30.06.2018 9. Date of released

of funds 30.08.2018 24.01.2019 10.No. of

beneficiaries 16358 persons. Work is in progress

Page 100: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1527 3130

Rural Sewerage and Drainage Scheme, Tuff Tile

Pavement in Basti Radal Pur, Basti Lutaf Pur,

Chak Numberabad, Molvi Wala, Basti Cut Wala,

Tibbi Qasian, Basti Balochan Wala UC Radal Pur

District Multan

MultanOn-going

Schemes30.000 9.800 3.333 2.500 1.667 67% 38%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.12.2017 7.Date

of Completion as per PC-l 27.06.2019 8. Anticipated

date of completion 30.06.2018 9. Date of released

of funds 30.08.2018 24.01.2019 10.No. of

beneficiaries 14325 persons. Work is in progress

1528 3131

Rural Sewerage and Drainage Scheme, Tuff Tile

Pavement in Basti Mari Noon, Basti Godar, Basti

Dogran, Basti Khokhran, Basti Ghous Pur UC Mari

Noon District Multan

MultanOn-going

Schemes30.000 11.997 3.333 2.500 1.667 67% 46%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 28.12.2017 7.Date

of Completion as per PC-l 27.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 12442 persons. Work is in progress

1529 3132

Rough Cost Estimates for replacement of Old

Sewer Lines at Muhalla Sharif Pura UC 65 Piran

Ghaib II in Sub Division New Multan Sewerage

Central Division WASA Multan

MultanOn-going

Schemes12.450 8.334 0.817 0.613 0.409 67% 70%

1.Date of AA 03.08.2017 2.Date of T.S 09.09.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 20.11.2017 7.Date

of Completion as per PC-l 19.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 13225 persons. Work is in progress

1530 3133

Ext. of Rual Drainage / Sewerage Scheme Chah

Muhammad Hussain wala & Adjoining Ababdies

District Multan

MultanOn-going

Schemes29.510 12.478 3.333 2.500 1.667 67% 48%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Dated of Prequalification - 4.Date of invitation of

tender 27.09.2017 5.Date of Receipt of tenders

18.10.2017 6.Date of work order 22.11.2017 7.Date

of Completion as per PC-l 21.05.2018 8. Anticipated

date of completion 30.06.2019 9. Date of released

of funds 03.08.2018 24.01.2019 10.No. of

beneficiaries 12455 persons. Work is in progress

1531 3134Scheme / Drainage Scheme Kotli Nijabat District

MultanMultan

On-going

Schemes69.500 21.924 3.333 2.500 1.667 67% 34%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 05.01.2018

7.Date of Completion as per PC-l 30.06.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 15654 persons. Work is in progress

1532 3135 Sewerage System in UC-90 District Multan MultanOn-going

Schemes65.000 4.958 3.333 2.500 1.667 67% 10%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 03.03.2018

7.Date of Completion as per PC-l 02.08.2018 8.

Anticipated date of completion 30.06.2019 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 9876 persons. Work is in progress

1533 3136 Sewerage System in UC-82 District Multan MultanOn-going

Schemes65.000 22.996 3.333 2.500 1.667 67% 38%

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017

3.Date of Prequalification 28.08.2017 4.Date of

invitation of tender 02.12.2017 5.Date of Receipt of

tenders 05.12.2017 6.Date of work order 20.02.2018

7.Date of Completion as per PC-l 19.02.2020 8.

Anticipated date of completion 30.06.2020 9. Date

of released of funds 03.08.2018 24.01.2019 10.No.

of beneficiaries 15775 persons. Work is in progress

1534 3137Rural Drainage Scheme Chak No.7/9-R District

KhanewalKhanewal

On-going

Schemes12.000 6.000 2.000 1.500 1.169 78% 60%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2018 3. Date of Pre-Qualification: --------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

31.12.2018 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: -------- 11

No. of beneficiaries 6340 Persons Work is in

progress.

Page 101: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1535 3138Construction of Drainage Scheme Chak No.93/10-

R District KhanewalKhanewal

On-going

Schemes12.000 2.000 3.333 2.500 2.385 95% 37%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 09.11.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 5788Persons Work is in

progress.

1536 3139Rural Drainage Scheme Chak No.92/10-R District

KhanewalKhanewal

On-going

Schemes18.000 10.000 2.667 2.000 1.891 95% 66%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 09.12.2017 7. Date of Completion as per PC-

I: (8) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 8140 Persons Work is in

progress.

1537 3140Rural Drainage Scheme UC No. 48 Tehsil Mian

ChannuKhanewal

On-going

Schemes11.000 5.000 2.000 1.500 1.500 100% 59%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 8265 Persons Work is in

progress.

1538 3141Rural Drainage Scheme UC No. 51 Tehsil Mian

ChannuKhanewal

On-going

Schemes12.000 6.000 2.000 1.500 1.125 75% 59%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 09.12.2017 7. Date of Completion as per PC-

I: (5) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 6568 Persons Work is in

progress.

1539 3142Rural Drainage Scheme UC No. 55 Tehsil Mian

ChannuKhanewal

On-going

Schemes12.000 7.000 1.667 1.250 1.019 82% 67%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 65619 Persons Work is in

progress.

1540 3143Rural Drainage Scheme UC No. 56 Tehsil Mian

ChannuKhanewal

On-going

Schemes11.000 6.000 1.667 1.250 0.937 75% 63%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 17.11.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 5790 Persons Work is in

progress.

1541 3144Rural Drainage Scheme UC No. 62 Tehsil Mian

ChannuKhanewal

On-going

Schemes12.000 6.000 2.000 1.500 1.119 75% 59%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 5689 Persons Work is in

progress.

1542 3145Rural Drainage Scheme Chak No.134/16-L and

Adjoining Abadies Tehsil Mian ChannuKhanewal

On-going

Schemes12.000 6.000 2.000 1.500 1.211 81% 60%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 6132 Persons Work is in

progress.

Page 102: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1543 3146

Rural Drainage Scheme Chak No 20/8-BR, 1/8-R,

2/8-R, 3/8-R, 4/8-R and Adjoining Abadies Tehsil

Mian Channu

KhanewalOn-going

Schemes12.000 7.000 1.667 1.250 0.949 76% 66%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 6443 Persons Work is in

progress.

1544 3147 Drainage & Soling 122/15-L District Khanewal KhanewalOn-going

Schemes3.000 2.385 0.167 0.125 0.100 80% 83%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (6) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1936 Persons Scheme

Completed in saving.

1545 3148 Drainage & Soling 53/15-L District Khanewal KhanewalOn-going

Schemes3.000 2.500 0.167 0.125 0.094 75% 86%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (3) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1876 Persons Scheme

Completed in saving.

1546 3149 Drainage & Soling 58/15-L District Khanewal KhanewalOn-going

Schemes3.000 2.500 0.167 0.125 0.100 80% 87%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (3) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1916 Persons Work is in

Progress.

1547 3150 Drainage & Soling 117/15-L District Khanewal KhanewalOn-going

Schemes3.000 2.500 0.167 0.125 0.106 85% 87%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 19.10.2017 7. Date of Completion as per PC-

I: (3) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 2065 Persons Scheme

Completed in Saving.

1548 3151 Drainage & Soling 42/15-L District Khanewal KhanewalOn-going

Schemes3.000 2.500 0.167 0.125 0.094 75% 86%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (3) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1837 Persons Scheme

Completed in Saving.

1549 3152 Drainage & Soling 135/16-L District Khanewal KhanewalOn-going

Schemes3.000 2.500 0.167 0.125 0.105 84% 87%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (5) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1926 Persons Work is in

Progress.

1550 3153Drainage & Soling Pakka Haji Majeed District

KhanewalKhanewal

On-going

Schemes3.000 1.700 0.433 0.325 0.277 85% 66%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (3) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1966 Persons Work is in

Progress.

Page 103: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1551 3154Rehabilitation of Sewerage Scheme Tulamba City

in missed area Tehsil Mian ChannuKhanewal

On-going

Schemes49.990 15.000 3.333 2.500 2.258 90% 35%

1. Date of A.A: 26.07.2017 2. Date of T.S:

20.09.2017 3. Date of Pre-Qualification: 05.09.2017

4. Date of Invitation of Tender: 09.11.2017 5. Date

of Receipt of Tender: 11.11.2017 6. Date of Work

order: 23.11.2017 7. Date of Completion as per PC-

I: (12)months 8. Anticipated Date of completion:

31.12.2019 9. Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: -------- 11

No. of beneficiaries 2690 Persons Work is in

progress.

1552 3155Drainage & Soling Chak No.8-9/8-AR District

KhanewalKhanewal

On-going

Schemes3.000 2.500 0.167 0.125 0.112 90% 87%

1. Date of A.A: 26.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: -------- 4.

Date of Invitation of Tender: 28.09.2017 5. Date of

Receipt of Tender: 29.09.2017 6. Date of Work

order: 24.10.2017 7. Date of Completion as per PC-

I: (3) months 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 1896 Persons Scheme

Completed in Saving.

1553 3156

Constructino of Soling, Drains, Sullage Carrier,

RCC Culverts in Union Councils Salar Wahan,

Thull Najeeb, Man Kot, Chak Norang Shah, Boota

Singh, Mari Sahu Ibrahim Pur, Mubarak Pur, 5-

Kassi, Mula Pur, Nabi Pur, Chak Haider Abad &

Monga Wala Tehsil Kabirwala in PP-213 District

Khanewal

KhanewalOn-going

Schemes199.990 72.900 16.667 12.500 11.919 95% 42%

1. Date of A.A: 19.08.2017 2. Date of T.S:

22.09.2017 3. Date of Pre-Qualification: 05.09.2017

4. Date of Invitation of Tender: 09.11.2017 5. Date

of Receipt of Tender: 11.11.2017 6. Date of Work

order: 26.12.2017 7. Date of Completion as per PC-

I: 31.12.2018 8. Anticipated Date of completion:

30.06.2019 9. Date of released of funds 03-08-2018

24.01.2019 10. Reason of Slow Moving: ------- 11

No. of beneficiaries 11356 Persons Work is in

Progress. Rs. 118.765 Million are required to

complete the scheme.

1554 3157Water Supply Scheme Chak No.126/WB, 128/WB

District VehariVehari

On-going

Schemes28.966 9.995 6.322 4.742 3.570 75% 47%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 11.12.2017

7. Date of Completion as per PC-I: 10.12.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ------ 11. No. of

Beneficiary= Persons Work is in progress.

1555 3158Rehabiliation of Water Supply Scheme Chak

No.96/WB District VehariVehari

On-going

Schemes15.000 7.443 1.667 1.250 0.930 74% 56%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019+ 10.

Reason of Slow Moving: ----- 11. No. of

Beneficiary= Persons Work is in progress.

1556 3159

Provision of Water Supply / Filtration Plants &

Sewerage Scheme Chak No.233/EB District

Vehari

VehariOn-going

Schemes17.639 3.877 2.546 1.910 1.390 73% 30%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ----- 11. No. of

Beneficiary= Persons Work is in progress.

1557 3160

Provision of Water Supply / Filtration Plants &

Sewerage Scheme Chak No.249/EB District

Vehari

VehariOn-going

Schemes24.842 5.246 4.947 3.710 2.778 75% 32%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ----- 11. No. of

Beneficiary= Persons Work is in progress.

1558 3161

Provision of Water Supply / Filtration Plants &

Sewerage Scheme Chak No.251/EB District

Vehari

VehariOn-going

Schemes23.451 6.682 4.484 3.363 2.450 73% 39%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ----- 11. No. of

Beneficiary= Persons Work is in progress.

Page 104: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1559 3162

Provision of Water Supply / Filtration Plants &

Sewerage Scheme Chak No.243/EB District

Vehari

VehariOn-going

Schemes20.663 3.934 3.554 2.666 1.980 74% 29%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ----- 11. No. of

Beneficiary= Persons Work is in progress.

1560 3163Rural Sewerage / Drainage & Water Supply

Scheme Chak No.65/WB District VehariVehari

On-going

Schemes31.617 9.998 3.333 2.500 1.890 76% 38%

1. Date of A.A: 31.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: NIL 11. No. of Beneficiary=

Persons Work is in progress.

1561 3164

Construction of Water Filtration Plants 16-No in

Chak No.05/WB, 18/WB, 22/WB, 65/WB, 59/WB,

93/WB, 97/WB, 56/Wb, 34/WB, Pull-48, Pull

Mohsin Shah, 63/WB, 24/WB, 26/WB, Noor Shah

Melsi, Shittab Garh Melsi.

VehariOn-going

Schemes48.000 13.853 11.000 8.250 5.990 73% 41%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1562 3165Rural Water Supply Scheme 176/WB

Baghbanpura District VehariVehari

On-going

Schemes25.171 9.833 5.057 3.793 3.450 91% 53%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 20.11.2017

7. Date of Completion as per PC-I: 19.11.2018 8.

Anticipated Date of Completion: 30.06.2019. 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1563 3166Rural Water Supply Scheme Chak No.182/WB

District VehariVehari

On-going

Schemes16.073 9.999 2.024 1.518 1.150 76% 69%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 22.11.2017

7. Date of Completion as per PC-I: 19.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: --- 11. No. of Beneficiary=

Persons Work is in progress.

1564 3167Rural Water Supply Scheme Chak No.184/WB

District VehariVehari

On-going

Schemes28.673 9.991 6.224 4.668 3.388 73% 47%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1565 3168Rural Water Supply Scheme Chak No.161/WB

District VehariVehari

On-going

Schemes18.426 10.000 2.809 2.107 1.560 74% 63%

1. Date of A.A: 31.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 20.11.2017

7. Date of Completion as per PC-I: 19.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1566 3169Rural Water Supply Scheme Chak No.163/WB

District VehariVehari

On-going

Schemes31.485 9.960 7.162 5.372 4.980 93% 47%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 20.11.2017

7. Date of Completion as per PC-I: 19.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

Page 105: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1567 3170Rural Water Supply Scheme Chak No.159/WB

District VehariVehari

On-going

Schemes17.583 9.978 2.528 1.896 1.450 76% 65%

1. Date of A.A: 31.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 23.10.2017 5. Date of Receipt

of Tender: 24.10.2017 6. Date of Award: 20.11.2017

7. Date of Completion as per PC-I: 19.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: --- 11. No. of Beneficiary=

Persons Work is in progress.

1568 3171Rural Water Supply Scheme Chak No.50/WB

Dahlu Hari Chand and 52 Sharqi District VehariVehari

On-going

Schemes123.590 34.755 16.667 12.500 9.370 75% 36%

1. Date of A.A: 21.08.2017 2. Date of T.S:

19.10.2017 3. Date of Pre-Qualification: 27.10.2017

4. Date Invitation of Tender: 29.11.2017 5. Date of

Receipt of Tender: 30.11.2017 6. Date of Award:

27.12.2017 7. Date of Completion as per PC-I:

26.12.2019 8. Anticipated Date of Completion:

30.06.2019 9.Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: --- 11. No.

of Beneficiary= Persons Work is in progress.

1569 3172Sewerage Schemes Chak No.5/WB, 24/WB, 88/

WB and 90/WB. District VehariVehari

On-going

Schemes40.000 8.323 3.333 2.500 1.870 75% 25%

1. Date of A.A: 31.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: NIL 11. No. of Beneficiary=

Persons Work is in progress.

1570 3173Drainage Sewer Scheme Chak No.110/WB District

VehariVehari

On-going

Schemes20.000 9.999 3.333 2.500 1.840 74% 59%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1571 3174Construction of Soling, Drainage & Culverts UC 46-

173/EB District VehariVehari

On-going

Schemes15.000 6.917 2.500 1.875 1.430 76% 56%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: NIL 11. No. of Beneficiary=

Persons Work is in progress.

1572 3175Construction of Soling, Drainage & Culverts UC 53-

275/EB District VehariVehari

On-going

Schemes15.000 7.165 2.500 1.875 1.410 75% 57%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: NIL 11. No. of Beneficiary=

Persons Work is in progress.

1573 3176Construction of Soling, Drainage & Culverts UC 40-

128/EB District VehariVehari

On-going

Schemes15.000 9.807 1.667 1.250 0.945 76% 72%

1. Date of A.A: 31.07.2017. 2. Date of T.S: - 3. Date

of Pre-Qualification: - 4. Date Invitation of Tender:

26.10.2017 5. Date of Receipt of Tender:

28.10.2017 6. Date of Award: 25.11.2017 7. Date of

Completion as per PC-I: 24.11.2018 8. Anticipated

Date of Completion: 30.06.2019 9.Date of released

of funds 03.08.2018 24.01.2019 10. Reason of Slow

Moving: NIL 11. No. of Beneficiary= Persons Work

is in progress.

1574 3177Construction of Soling, Drainage & Culverts UC 44-

199/EB District VehariVehari

On-going

Schemes15.000 9.967 1.667 1.250 0.940 75% 73%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

Page 106: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1575 3178Construction of Soling, Drainage & Culverts UC 45-

175/EB District VehariVehari

On-going

Schemes15.000 7.499 2.500 1.875 1.420 76% 59%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1576 3179Construction of Soling , Drainage & Culverts UC49-

233/EB District VehariVehari

On-going

Schemes25.000 12.285 4.167 3.125 2.341 75% 59%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 26.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1577 3180Construction of Soling , Drainage & Culverts UC47-

215/EB District VehariVehari

On-going

Schemes25.000 12.500 4.167 3.125 2.325 74% 59%

1. Date of A.A: 31.07.2017 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1578 3181Construction of Soling , Drainage & Culverts UC48-

187/EB District VehariVehari

On-going

Schemes15.000 12.499 0.833 0.625 0.460 74% 86%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

07.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1579 3182Rural Sewerage / Drainage Scheme Chak No.

57/WB Tehsil & District VehariVehari

On-going

Schemes15.000 6.915 2.667 2.000 1.740 87% 58%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of Receipt

of Tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1580 3183Rural Sewerage / Drainage Scheme Chak No.

53/WB Tehsil & District VehariVehari

On-going

Schemes16.000 7.999 2.667 2.000 1.780 89% 61%

1. Date of A.A: 31.07.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: - 4. Date

Invitation of Tender: 26.10.2017 5. Date of receipt

of tender: 28.10.2017 6. Date of Award: 25.11.2017

7. Date of Completion as per PC-I: 24.11.2018 8.

Anticipated Date of Completion: 30.06.2019 9.Date

of released of funds 03.08.2018 24.01.2019 10.

Reason of Slow Moving: ---- 11. No. of Beneficiary=

Persons Work is in progress.

1581 3184

Rehabilitation and Extension of Water Supply &

Sewerage Schemes Mailsi and Adjoining Abadies.

District Vehari

VehariOn-going

Schemes279.804 74.459 33.333 25.000 18.570 74% 33%

1. Date of A.A: 06.09.2017. 2. Date of T.S:

08.08.2017 3. Date of Pre-Qualification: 27.10.2017

4. Date Invitation of Tender: 29.11.2017 5. Date of

receipt of tender: 30.11.2017 6. Date of Award:

19.01.2018 7. Date of Completion as per PC-I:

18.01.2021 8. Anticipated Date of Completion:

18.01.2021 9.Date of released of funds 03.08.2018

24.01.2019 10. Reason of Slow Moving: ---- 11. No.

of Beneficiary= Persons Work is in progress.

1582 3185Construction of Nali Soling Tuff Tile & Culverts UC

Kot Mubarak, Shero Satal and Yaroo DG Khan

Dera Ghazi

Khan

On-going

Schemes11.500 4.955 2.167 1.625 1.203 74% 54% "• Date of A.A = 13.1.17

1583 3186Construction of Nali Soling Culverts and Tuff Tile

U/C Palgah Chak NO.3 DG Khan

Dera Ghazi

Khan

On-going

Schemes20.000 9.975 3.333 2.500 1.875 75% 59% "• Date of A.A = 13.1.17

1584 3187Construction of Nali Soling & Culverts UC Dagar

Chitt. DG Khan

Dera Ghazi

Khan

On-going

Schemes13.000 6.999 2.000 1.500 1.140 76% 63% "• Date of A.A = 13.1.17

Page 107: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1585 3188Construction of Nali Soling Tuff Tile of Basti Foja

and Darkhast Jamal Janubi DG Khan

Dera Ghazi

Khan

On-going

Schemes14.000 6.643 2.333 1.750 1.313 75% 57% "• Date of A.A = 13.1.17

1586 3189Construction of Nali Soling Tuff Tiles in UC Basti

Malana DG Khan

Dera Ghazi

Khan

On-going

Schemes13.610 6.617 2.203 1.652 1.206 73% 57% "• Date of A.A = 13.1.17

1587 3190Construction of Sewerage Nali Soling & Culverts /

Bridge UC Khakhi. DG Khan

Dera Ghazi

Khan

On-going

Schemes11.000 4.986 2.000 1.500 1.065 71% 55% "• Date of A.A = 13.1.17

1588 3191Construction of Nali Soling Tuff Tile & Culverts UC

Kala DG Khan

Dera Ghazi

Khan

On-going

Schemes12.000 4.985 2.333 1.750 1.260 72% 52% "• Date of A.A = 13.1.17

1589 3192Construction of Nali Soling Tuff Tile & Culverts UC

Shadan Lund DG Khan

Dera Ghazi

Khan

On-going

Schemes14.000 6.000 2.667 2.000 1.460 73% 53% "• Date of A.A = 13.1.17

1590 3193Construction of Nali / Drainage Tuff Tile Choti City

and Colonies DG Khan

Dera Ghazi

Khan

On-going

Schemes40.000 14.264 8.333 6.250 4.500 72% 47% "• Date of A.A = 13.1.17

1591 3194Water Supply Scheme City Choti Zereen District

DG Khan

Dera Ghazi

Khan

On-going

Schemes50.000 14.999 11.667 8.750 6.388 73% 43% "• Date of A.A = 25.7.2017

1592 3195Rehabilitation and Augmentation of Water Supply

Scheme of Choti Zareen

Dera Ghazi

Khan

On-going

Schemes30.000 4.999 3.333 2.500 1.800 72% 23% "• Date of A.A = 25.7.2017

1593 3196Rural Water Supply Scheme Nutkani District DG

Khan

Dera Ghazi

Khan

On-going

Schemes80.000 29.999 10.000 7.500 5.325 71% 44% "• Date of A.A = 16.09.2017

1594 3197Construction of PCC Drainage / Tuff Tile in NA-171

DG Khan

Dera Ghazi

Khan

On-going

Schemes155.000 26.295 33.333 25.000 18.000 72% 29% "• Date of A.A = 16.09.2017

1595 3198Rehabilitation of Water Supply in Block Churatta

District DG Khan

Dera Ghazi

Khan

On-going

Schemes20.000 9.964 3.333 2.500 1.850 74% 59% "• Date of A.A = 25.7.2017

1596 3199Rehabilitation of Water Supply in Union Gaddai

District DG Khan

Dera Ghazi

Khan

On-going

Schemes20.000 9.999 3.333 2.500 1.825 73% 59% "• Date of A.A = 25.7.2017

1597 3200Construction of Nali Soling Tuff Tiles & Culverts

UC Shero Satai DG Khan

Dera Ghazi

Khan

On-going

Schemes3.000 2.354 0.167 0.125 0.088 70% 81% "• Date of A.A = 25.7.2017

1598 3201Construction of Nali Soling Culverts Jhok,Uttra DG

Khan

Dera Ghazi

Khan

On-going

Schemes3.000 2.438 0.167 0.125 0.091 73% 84% "• Date of A.A = 25.7.2017

1599 3202Construction of Nali Soling in Jukharr Imam &

Sherru Qasbas

Dera Ghazi

Khan

On-going

Schemes3.000 2.474 0.167 0.125 0.093 74% 86% "• Date of A.A = 25.7.2017

1600 3203Sewerage and Tuff Tiles in PP-244 District DG

Khan

Dera Ghazi

Khan

On-going

Schemes90.000 49.000 6.667 5.000 3.500 70% 58% "• Date of A.A = 16.09.2017

1601 3204

Rehabilitation of Rural Water Supply Scheme in

Thul Sirak & Thul Jaman Tehsil Jampur, District

Rajanpur.

RajanpurOn-going

Schemes15.000 10.000 1.667 1.250 0.834 67% 72% "• Date of A.A = 09.01.2018

1602 3205Provision of Sewerage & Tuff Tile Kot Tahir City

District Rajanpur Rajanpur

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017.

1603 3206Installation of 1000 Nos. Deep Hand Pumps at

Pachad Area, District Rajanpur.Rajanpur

On-going

Schemes35.000 12.000 7.667 5.750 3.834 67% 45% "• Date of A.A = 04.08.2017.

1604 3207Rehabilitation of water supply in scheme Basti

Tuski in District Rajan PurRajanpur

On-going

Schemes16.000 8.000 2.667 2.000 1.334 67% 58% "• Date of A.A = 04.08.2017.

1605 3208

Water supply scheme in Veeni Khosa to Hajoo Via

Basti Riaz hambae UC-Wah Lashari in District

Rajanpur

RajanpurOn-going

Schemes13.000 5.993 2.333 1.750 1.167 67% 55% "• Date of A.A = 04.08.2017.

1606 3209 Deep Hand Pump in Pachad Area 200No RajanpurOn-going

Schemes50.000 16.000 11.333 8.500 5.667 67% 43% "• Date of A.A = 04.08.2017.

1607 3210

Rural drainage / sewerage, PCC & Tuff Tile

Flooring Rajanpur City of left over area District

Rajanpur

RajanpurOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017.

1608 3211Construction of Tuff Tile, Soling, Sewerage,

Drainage and Street etc Rajan Pur CityRajanpur

On-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% "• Date of A.A = 04.08.2017.

1609 3212Construction of Street, Soling, Sewerage,

Drainage, Tuff tiles in District Rajan Pur CityRajanpur

On-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% "• Date of A.A = 04.08.2017.

1610 3213Provision of Sewerage & Tuff Tile at Basti Cheena,

Basti Talai Wala U/C Kot Janu. Disrict Rajan PurRajanpur

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% "• Date of A.A = 04.08.2017.

1611 3214Provision of Sewerage & Tuff Tile Noshera Gharbi.

Disrict Rajan PurRajanpur

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% "• Date of A.A = 04.08.2017.

Page 108: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1612 3215Provision of Sewerage and Tuff Tile Kotla

Mughlan. Disrict Rajan PurRajanpur

On-going

Schemes30.000 9.990 6.667 5.000 3.334 67% 44% "• Date of A.A = 04.08.2017.

1613 3216Construction of Soling and Drain UC Jhugi Wala

District MuzaffargarhMuzaffargarh

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 31.7.2017

1614 3217Construction of Soling, Tuff Tiles & Drain UC

Seetpur District MuzaffargarhMuzaffargarh

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 31.7.2017

1615 3218Provision of Soling Tuff Tiles & Drains in Union

Council Alludewall, District Muzaffargarh (Revised)Muzaffargarh

On-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018

1616 3219

Construction of Soling Tuff Tiles & Drains in Union

Council Meeran Pur, District Muzaffargarh

(Revised)

MuzaffargarhOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018

1617 3220

Construction of Soling Tuff Tiles & Drains in Union

Council Usman Koria, District Muzaffargarh

(Revised)

MuzaffargarhOn-going

Schemes20.000 10.000 3.333 2.500 1.667 67% 58% Date of AA 11.01.2018

1618 3221Construction of PCC/ Drainage and Tuff Tiles

District MuzaffargarhMuzaffargarh

On-going

Schemes90.000 25.000 6.667 5.000 3.200 64% 31% Date of A.A 06.9.2017

1619 3222

Provision of Tuff Tile, Sewerage and Drainage in

Urban Area Municipal Committee Chowk Sarwar

Shaheed District Muzaffargarh

MuzaffargarhOn-going

Schemes40.000 10.000 30.000 22.500 10.450 46% 51% • Date of AA 5.8.2017

1620 3223

Construction of Soling and Driange work in UC-

Dammar Wala and Kotla Gmaoon, District

Muzaffargarh

MuzaffargarhOn-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Date of AA 31.7.2017

1621 3224

Construction of Soling and Driange work in Calor

Wali Qadir Pur and Damar Wali, District

Muzaffargarh

MuzaffargarhOn-going

Schemes25.000 10.000 5.000 3.750 2.500 67% 50% Date of AA 31.7.2017

1622 3225

Construction of Soling and Driange work in Janda

Wali Aluda Wali and Mahal Khakhi, District

Muzaffargarh

MuzaffargarhOn-going

Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017

1623 3226Const: of Soling Drain Tuff Tile VR Bridges UC

Kotla Gamon District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1624 3227Const: of Soling Drain Tuff Tile VR Bridges UC

Kotla Lal Shah District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1625 3228Const: of Soling Drain Tuff Tile VR Bridges UC

Shehr Sultan District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 13.250 3.333 2.500 1.667 67% 50% Date of AA 31.7.2017

1626 3229Const: of Soling Drain Tuff Tile VR Bridges UC

Vains District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1627 3230Const: of Soling Drain Tuff Tile VR Bridges UC

Jhalarin District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1628 3231Const: of Soling Drain Tuff Tile VR Bridges UC

Bair Bund District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1629 3232Const: of Soling Drain Tuff Tile VR Bridges UC

Binda Ishaq District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1630 3233Drainange / Soling / Tuff Tile / Culverts Gul Wala,

Khanpur Fazil Kalroo District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 6.667 5.000 3.334 67% 44% Date of AA 31.7.2017

1631 3234Construction of Soling and Driange work in UC-

Vains and Basti Arif Wala, District MuzaffargarhMuzaffargarh

On-going

Schemes15.000 5.000 3.333 2.500 1.667 67% 44% Date of AA 31.7.2017

1632 3235

Construction of Soling and Driange work in Jatoi,

Rampur, Nichrani, Baber, Azam Khan and Kasir

Gazlani, District Muzaffargarh

MuzaffargarhOn-going

Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017

1633 3236

Construction of Soling and Driange work in Rohilan

Wali, Binday Wali and Khakhi, District

Muzaffargarh

MuzaffargarhOn-going

Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017

Page 109: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1634 3237

Construction of Soling and Driange work in Miyan

Sawar Mochi Wala Ganga and Khakhi, District

Muzaffargarh

MuzaffargarhOn-going

Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017

1635 3238

Construction of Soling and Driange work in Baily

Wala and Bait Umar Draz and Bindi Pitafi, District

Muzaffargarh

MuzaffargarhOn-going

Schemes15.000 7.000 2.667 2.000 1.334 67% 56% Date of AA 31.7.2017

1636 3239

Cosntruction of Soling / Drainage and Culverts Tuff

Tiles Municipal Committee Daira Deen Panah

District Muzaffargarh

MuzaffargarhOn-going

Schemes20.000 9.000 3.333 2.500 2.167 87% 56% Date of AA 31.7.2017

1637 3240

Drainage / Soling / UC Thath Gurmani, U/C

Gurmani Sharqi, U/C Sheikh Umar, U/C Daya

Jokha Sharqi, U/C Gujrat U/C Allud District

Muzaffargarh

MuzaffargarhOn-going

Schemes100.000 33.500 6.667 5.000 3.300 66% 37% Date of A.A 06.9.2017

1638 3241Muzaffargarh City Sewerage Scheme Soling /

Drainage, Tuff Tiles District MuzaffargarhMuzaffargarh

On-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Date of AA 31.7.2017

1639 3242Construction of Soling / Drainage Tuff Tiles Union

Council Taleri Doaba District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 3.333 2.500 1.667 67% 39% Date of AA 31.7.2017

1640 3243Construction of Soling / Drainage Tuff Tiles Union

Council Bhutta Pur District MuzaffargarhMuzaffargarh

On-going

Schemes30.000 10.000 3.333 2.500 1.640 66% 39% Date of AA 31.7.2017

1641 3244

Drainage / Soling / Tuff Tiles / Culverts K.D Qurehi,

Gulqaim Mastoi, Budh, Wanpitafi, Sharif Chujra, Ali

Dah, Dawna, Mehmood Kot District Muzaffargarh

MuzaffargarhOn-going

Schemes50.000 20.000 3.333 2.500 1.667 67% 43% Date of AA 31.7.2017

1642 3245

Construction of Soling / Drainage Tuff Tile Culverts

sullage Carrier Pull Pullet PPC Allied Work etc

Qureshi Aabwala Rahim Ali Mulan Walidad

Mazhay wala Tibbi Godar Chowk Sanwai Syed

Hassan Shah Bakhsh Wala Jada Chandai District

Muzaffargarh

MuzaffargarhOn-going

Schemes60.000 20.000 3.333 2.500 1.667 67% 36% Date of AA 31.7.2017

1643 3246

Const: of Soling/ Sewerage Drain UC Jhanday

Wali UC Manikpur UC Darien UC Shahjamal UC

Alludeywali District Muzaffargarh

MuzaffargarhOn-going

Schemes30.000 10.000 3.333 2.500 1.650 66% 39% Date of AA 31.7.2017

1644 3247Construction of PCC/Drainage and Tuff Tile in

NA179 and PP-258 District MuzaffargarhMuzaffargarh

On-going

Schemes65.000 25.000 6.667 5.000 3.334 67% 44% Date of A.A 06.9.2017

1645 3248

Construction of Tuff Tile Drainge Sewerage Soling

PCC Slab and different work PP-262 District

Layyah

LayyahOn-going

Schemes100.000 35.000 6.667 5.000 3.334 67% 38% • Date of AA = 15.08.2017

1646 3249

Construction of Tuff Tile Drainage Sewerage

Soling PCC Slab and different work PP-263 District

Layyah

LayyahOn-going

Schemes120.000 30.000 10.000 7.500 5.000 67% 29% • Date of AA = 15.08.2017

1647 3250

Construction of Tuff Tile Drainage Sewerage

Soling PCC Slab and different work PP-264 District

Layyah

LayyahOn-going

Schemes100.000 30.000 16.667 12.500 8.334 67% 38% • Date of AA = 15.08.2017

1648 3251Comprehensive sewerage / Drainage scheme

along with tuff Tile in Choubara city District Layyah.Layyah

On-going

Schemes100.000 30.000 23.333 17.500 11.667 67% 42% • Date of AA = 15.08.2017

1649 3252 Swerage Drainge / Tuff Tiles for Layyah city LayyahOn-going

Schemes300.000 75.000 50.000 37.500 25.000 67% 33% • Date of AA = 06.09.2017

1650 3253

Construction of Sewerage/Drains and Laying of

Tuff Tiles/Soling in UC, Sirishta Thal District

Layyah

LayyahOn-going

Schemes143.137 10.000 21.297 15.973 10.643 67% 14%

Administrative Approval issued on dated. 08-01-

2018.

1651 3254

Rural Sewerage/ Drainage / Brick Pavement / Tuff

Tiles in Union Council 164-A / TDA and Adjoining

Abadies Tehsil District Layyah

LayyahOn-going

Schemes20.000 10.000 3.333 2.500 1.660 66% 58% • Date of AA = 29.07.2017

Page 110: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1652 3255Const. of Road, Sewerage & tuff Tile Chak

No.5/BC District BahawalpurBahawalpur

On-going

Schemes11.889 5.990 1.963 1.472 0.980 67% 59%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of tender; 12-10-2017. Date of award:-26-10-

2017. Date of completion. 25-10-2018. Anticipated

date of completion 30-06-2019. Date of receipt of

funds by F.D. 20.07.2018 & 11.01.2019. Work is in

progress.

1653 3256Rehabilitation of water supply schemes in Chak

no.5/DNB Tehsil Yazman District BahawalpurBahawalpur

On-going

Schemes20.488 9.994 3.496 2.622 1.740 66% 57%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 12-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1654 3257Rehabilitation of water supply schemes in Chak

no.14/DNB Tehsil Yazman District BahawalpurBahawalpur

On-going

Schemes20.802 14.939 1.934 1.451 0.967 67% 76%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 23-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1655 3258Rehabilitation of water supply schemes in Chak

no.76/DNB Tehsil Yazman District BahawalpurBahawalpur

On-going

Schemes17.490 8.396 2.497 1.873 1.245 66% 55%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 23-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1656 3259Rehabilitation of water supply schemes in Chak

no.24/DNB Tehsil Yazman District BahawalpurBahawalpur

On-going

Schemes21.552 9.997 3.851 2.888 1.925 67% 55%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 23-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1657 3260Rehabilitation of water supply schemes in Chak

No.44/DB Tehsil Yazman, District Bahawalpur.Bahawalpur

On-going

Schemes46.980 25.000 3.333 2.500 1.660 66% 57%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 23-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1658 3261Rehabilitation of water supply schemes in Chak

No.143/DB Tehsil Yazman, District Bahawalpur.Bahawalpur

On-going

Schemes22.680 14.996 2.560 1.920 1.280 67% 72%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 23-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1659 3262Water Supply Scheme in Chak No.115/DB Kachi

Tehsil Yazman District Bahawalpur.Bahawalpur

On-going

Schemes20.000 9.928 3.333 2.500 1.660 66% 58%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of tender; 23-10-2017. Date of award:-31-10-

2017. Date of completion. 30-07-2018. Anticipated

date of completion 30-06-2019. Date of receipt of

funds by F.D. 20.07.2018 & 11.01.2019. Work is in

progress.

1660 3263 Water Supply scheme of Chak No.114/DNB BahawalpurOn-going

Schemes18.000 8.698 2.667 2.000 1.334 67% 56%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 23-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1661 3264Const. of Road, Sewerage & Tuff Tile Basti

Hansarah District BahawalpurBahawalpur

On-going

Schemes15.000 5.954 3.000 2.250 1.500 67% 50%

Date of AA = 27-07-2017. Date of T.S 29.09.2017. .

Date of receipt of tender: 12-10-2017. Date of

award: 31.10.2017. Date of completion: 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1662 3265P/L of Sewerage and Tuff Tile Basti Inayati Tehsil

Khairpur Tamewali District BahawalpurBahawalpur

On-going

Schemes29.000 14.991 4.667 3.500 2.330 67% 60%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1663 3266P/L of Sewerage and Tuff Tile Basti Bohran Tehsil

Khairpur Tamewali District Bahawalpur Bahawalpur

On-going

Schemes15.300 4.974 3.433 2.575 1.710 66% 44%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 12-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1664 3267Sewerage/Drainage/Tuff Tiles/ Sullage in

189/Murad adjoining Abadies District BahawalpurBahawalpur

On-going

Schemes22.000 9.999 4.000 3.000 2.000 67% 55%

Date of AA= 08.08.2017 . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1665 3268

Sewerage/Drainage/Tuff Tiles/ Sullage in

147/Murad and adjoining Abadies District

Bahawalpur

BahawalpurOn-going

Schemes35.000 9.990 3.333 2.500 1.660 66% 33%

Date of AA= 08.08.2017 . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

Page 111: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1666 3269

Sewerage/Drainage/Tuff Tiles/ Sullage in

179/Murad and adjoining Abadies District

Bahawalpur

BahawalpurOn-going

Schemes35.100 14.341 3.333 2.500 1.660 66% 46%

Date of AA= 08.08.2017 . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1667 3270Sewerage/Drainage/Tuff Tiles/ Sullage in

160/Murad Adjoining Abadies, District BahawalpurBahawalpur

On-going

Schemes35.100 14.999 3.333 2.500 1.660 66% 47%

Date of AA= 08.08.2017 . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1668 3271Const. of Sewarage & Tuff Tile Basti Kori Wala,

Hoot Wala District BahawalpurBahawalpur

On-going

Schemes20.000 9.989 3.333 2.500 1.660 66% 58%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1669 3272

Rehabilitation of Sewerage Scheme/Drainage and

Tuff Tiles City Noor Pur Noranga District

Bahawalpur

BahawalpurOn-going

Schemes12.086 8.999 1.029 0.772 0.514 67% 79%

Date of AA= 27-07-2017. . Date of T.S= 31.07-

2017. Date of tender; 12-10-2017. Date of award:-

26-10-2017. Date of completion. 25-09-2018.

Anticipation date of completion.30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1670 3273P/L Sewerage /Tuff Tile City Hathaiji Mouza

Hathaiji Tehsil Ahmadpur East District BahawalpurBahawalpur

On-going

Schemes50.000 19.998 10.000 7.500 5.000 67% 50%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1671 3274P/L Sewerage /Tuff Tile Mubrakpur City Tehsil

Ahmadpur East District BahawalpurBahawalpur

On-going

Schemes40.000 6.903 3.333 2.500 1.659 66% 21%

Date of AA= 27-07-2017. . Date of T.S=09-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

. Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1672 3275Rehabilitation of Sewerage, City Yazman District

BahawalpurBahawalpur

On-going

Schemes300.000 59.999 33.333 25.000 16.500 66% 25%

Date of A.A (DDSC). 28-09-2017. Date of T.S. 17-

10-2017. Prequalification completed on 06-11-2017.

Date of receipt of tender from Prequalified

contractors on 05-12-2017 .Date of award. 01-01-

2018. Date of completion. 31-12-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1673 3276Sewerage Scheme Chak No.86/DB District

BahawalpurBahawalpur

On-going

Schemes19.359 8.000 3.786 2.840 1.890 67% 51%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1674 3277Sewerage Scheme Chak No.53/DB District

BahawalpurBahawalpur

On-going

Schemes20.588 8.999 3.863 2.897 1.927 67% 53%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1675 3278Sewerage Scheme Chak No.68/DB District

BahawalpurBahawalpur

On-going

Schemes16.397 4.998 3.799 2.849 1.900 67% 42%

Date of AA= 27-07-2017. . Date of T.S=08-08-2017.

Date of receipt of tender: 12-10-2017. Date of

award:-31-10-2017. Date of completion. 30.07.2018.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1676 3279Provision of Tuff Tile & Sanitation Scheme in Hatiji

Tehsil Ahmadpur East Ditrict BahawalpurBahawalpur

On-going

Schemes40.000 14.995 3.333 2.500 1.667 67% 42%

Date of AA= 27-07-2017. . Date of T.S=09-08-2017.

Date of receipt of tender: 16-10-2017. Date of

award:-31-10-2017. Date of completion. 30.01.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1677 3280

Provision of Water supply Chak No. 202-206/M,

128-132/M, 133-134/M, 176/M, 60/4/R District

Bahawalnagar

BahawalnagarOn-going

Schemes50.000 14.992 6.667 5.000 5.000 100% 40%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 31-12-

2018. Anticipation date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1678 3281

Provision and laying of water supply schemes

Chak No.53/F alongwith allied basties District

Bahawalnagar

BahawalnagarOn-going

Schemes25.000 10.000 5.000 3.750 3.750 100% 55%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 31-12-

2018. Anticipation date of compltion.30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

Page 112: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1679 3282Rehabilitation of water supply schemes Chak

No.45/F Jattan wali District BahawalnagarBahawalnagar

On-going

Schemes15.000 9.984 1.667 1.250 1.250 100% 75%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 30-09-

2018. Anticipation date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1680 3283

Rehabilitation of Rural Water Supply Scheme

Chak No. 82/5-R &138-139/6-R Including All

Adjoining Abadies Tehsil Haroonabad District

Bahawalnagar

BahawalnagarOn-going

Schemes40.000 14.997 8.333 6.250 5.150 82% 50%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1681 3284

Rehabilitation of Rural Water Supply Scheme

Chak No. 53/4-R & 137/6-R Including All Adjoining

Abadies Tehsil Haroonabad District Bahawalnagar

BahawalnagarOn-going

Schemes44.000 15.652 9.447 7.085 5.750 81% 49%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1682 3285

Rural Water Supply Scheme/ Sewerage/ Drainage

scheme Sri Ram Pura, Khair Shah, Bhaluka, Puna,

Habibka, Allah Buksh Lalika, Bunga Machi Murad

Wala, Musa Bhota Jhulan Arrain, Sanateka,

Jurana Basti, Kup Quraishian, Chak Jodheka,

Bhaluka, Chakmadrass, Distr

BahawalnagarOn-going

Schemes80.000 34.980 8.333 6.250 6.250 100% 52%

Date of A.A 09-08-2017. . Date of T.S. 12.10.2017. .

prequalification of the contractors. 31.10.2017. Date

of receipt of Tender from prequalified contractors on

16-11-2017 .Date of award. 30-12-2017.Date of

completion. 29-12-2018.Anticipated date of

completion 30-06-2019. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Work is in progress.

1683 3286

Construction of Soling / Water Supply in Union

Councils Islam Pura, Fateh Kot, Malik Pura, Sawae

Wala, Muhammad Pur, Koryanwala, Denan,

Sondha, Gulaab Ali, Barah Sajwad Khan, Teko

Raam, Donga Bonga District Bahawalnagar

BahawalnagarOn-going

Schemes100.000 29.963 10.000 7.500 7.496 100% 37%

Date of A.A 09-08-2017. Date of T.S. 12.10.2017.

prequalification of the contractors completed on

31.10.2017. Date of receipt of tender. 16-11-2017 .

Date of work awarded. 11-12-2017. Date of

completion. 10-12-2018. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Work is in progress.

1684 3287Rural Water supply scheme of Khiraaj Pura and

Goband Pur District BahawalnagarBahawalnagar

On-going

Schemes15.000 6.996 2.667 2.000 2.000 100% 60%

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .

Date of receipt of tender 11-09-2017. Date of work

awarded 31.10.2017. Date of completion

30.10.2018. Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1685 3288Rural Water supply scheme of Maakhe wali,

Mohan Pura, Jeeto, Jhugyan District BahawalnagarBahawalnagar

On-going

Schemes15.000 6.960 2.667 2.000 2.000 100% 60%

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .

Date of receipt of tender received 27.11.2017. Date

of work awarded. 30-11-2017. Date of completion

29-12-2018 . Anticipated date of completion 30-06-

2019Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1686 3289Rural water supply scheme of Taalya and Dhaban

District BahawalnagarBahawalnagar

On-going

Schemes15.000 6.886 2.667 2.000 2.000 100% 59%

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .

Date of receipt of tender 11-09-2017. Date of work

awarded 31.10.2017. Date of completion

30.10.2018. Anticipated date of completion 30-06-

2019 Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1687 3290

Rehabilitation of Rural Water Supply Scheme

Chak No. 143/6-R including all Adjoining Abadies

Tehsil Haroonabad District Bahawalnagar

BahawalnagarOn-going

Schemes28.807 9.944 6.269 4.702 3.800 81% 48%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1688 3291Rural Water Supply Scheme Chak No. 196/HB

Tehsil Fortabbas District BahawalnagarBahawalnagar

On-going

Schemes25.000 9.999 5.000 3.750 3.090 82% 52%

Date of A.A 03-08-2017. Date of T.S. 08.08.2017. .

Date of receipt of tender 11-11-2017. Date of work

award. 16-11-2017. Anticipated date of completion

30-06-2019. Date of completion 15-11-2018. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1689 3292

Rehabilitation of Rural Water Supply Scheme

Chak No. 70/4-R & 84/5-R Including All Adjoining

Abadies Tehsil Haroonabad District Bahawalnagar

BahawalnagarOn-going

Schemes50.000 19.949 10.000 7.500 6.300 84% 52%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 22-09-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

Page 113: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1690 3293

Rural Water Supply Scheme Chak No.

237,238,239/9R & 239/HB Including All Adjoining

Abadies Tehsil Fortabbas. District Bahawalnagar

BahawalnagarOn-going

Schemes40.000 14.999 8.333 6.250 5.550 89% 51%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 02-10-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1691 3294

Construction of Sewer Lines and Tuff Tiles in City

Area Haroonabad Tehsil Haroonabad District

Bahawalnagar

BahawalnagarOn-going

Schemes18.000 9.990 2.667 1.400 1.400 100% 63%

Date of A.A 03-08-2017. . Date of T.S 08-08-2017.

Date of tender receipt 11-09-2017. Date of award

31.10.2017. Date of completion 31.10.2018. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress. Excess funds Rs.0.600 million

surrendered dated 19.10.2018.

1692 3295Construction of Tuff Paverment urban area City

Chistian Ward No.1 to 36 District BahawalnagarBahawalnagar

On-going

Schemes100.000 29.999 16.667 12.500 10.000 80% 40%

Date of A.A. 09-08-2017. Date of T.S. 04.10.2017. .

Tender received on 10-01-2018. Date of award:

23.01.2018. Date of completion 30.06.2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1693 3296

Provision of Soling, Drainage system, Erection of

Tuff Tiles in Mandi Sadiq Gunj city. District

Bahawalnagar

BahawalnagarOn-going

Schemes44.000 16.998 3.333 2.500 2.500 100% 44%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 02-10-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1694 3297

Provision of Soling, Drainage System, Erection of

Tuff Tiles in Macloed Gunj city. District

Bahawalnagart

BahawalnagarOn-going

Schemes50.000 19.985 3.333 2.500 2.498 100% 45%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 28-10-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1695 3298Provision of Soling, Drainage System Erection of

Tuff Tiles in Madhaniwal District BahawalnagarBahawalnagar

On-going

Schemes21.000 9.996 3.667 2.750 2.530 92% 60%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 28-10-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1696 3299Provision of Soling, Drainage System, Erection of

Tuff Tiles in Hasil Sarrhu. District BahawalnagarBahawalnagar

On-going

Schemes45.000 21.853 3.333 8.424 8.422 100% 67%

Date of A.A 03-08-2017. . Date of T.S 08-08-2017. .

Date of Tender receipt 11-09-2017. Date of award

31.10.2017. Date of completion 30.01.2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress. Rs.5.924 million provided

through re-appropriation dated 19.10.2018.

1697 3300Provision of Soling, Tuff Tile, Drainage in Mouza

Muharram Cheena. District BahawalnagarBahawalnagar

On-going

Schemes12.000 9.998 0.667 0.500 0.500 100% 87%

Date of A.A 03-08-2017. . Date of T.S 05.08.2017. .

Date of tender receipt 11-09-2017. Date of award

31.10.2017. Date of completion 30.10.2017.

Anticipated date of completion 30-06-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Scheme completed in saving.

1698 3301Provision of Soling, Tuff Tile, Drainage in Mouza

Hassanwala. District BahawalnagarBahawalnagar

On-going

Schemes21.000 9.999 3.667 2.750 2.600 95% 60%

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-

2017. Date of receipt of tender. 11-09-2017. Date of

work award. 02-10-2017. Date of completion. 31-12-

2018. Anticipated date of completion 30-06-2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1699 3302

Sewerage / drainage scheme Sri Ram Pura, Khair

Shah, Bhaluka, Puna, Habibka, Allah buksh Lalika,

Bunga Machi Murad wala, Musa Bhota Jhulan

Arrain, Sanateka, Jattu wal Deen Pure, Chak

Hotyana and Jurana Hafizabad District

Bahawalnagar

BahawalnagarOn-going

Schemes150.000 43.484 6.667 5.000 5.000 100% 32%

Date of A.A 09-08-2017. . Date of T.S. 12.10.2017. .

prequalification of the contractors. 31.10.2017. .

Date of receipt of Tender from prequalified

contractors on 16-11-2017 . Date of award. 30-12-

2017. Date of completion 29-03-2019. Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1700 3303

Providing and laying sewerage schemes Chak

No.98/F, Bakhshan Khan, Chak 54/F, 105/F,

10/FW, 174/M District Bahawalnagar

BahawalnagarOn-going

Schemes100.000 29.859 10.000 7.500 7.500 100% 37%

Date of A.A 09-08-2017. Date of T.S 06-11-2017.

Date of receipt of tender: 10-01-2018. Date of

award: 23.01.2018. Date of completion 30.06.2019.

Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

Page 114: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1701 3304

Provision of Soling, Drainage System Eraction of

Tutt Tiles in BhainiSikandarJassoka and

MouzaShamonJassoka Tehsil Minchanabad

District Bahawalnagar

BahawalnagarOn-going

Schemes3.000 2.500 0.167 0.209 0.125 60% 88%

The scheme Provision of Soiling, Tuff Tile,

Drainage in Mouza Muharram Cheena District

Bahawalnagar reflected in ADP-2017-18 was

substituted by Standing Committee of the Cabinet

on Finance & Development in its meeting held on

20-09-2017 as proposed by Mian Fida Hussain

Watto EX-MPA PP-277 and minutes of meeting

issued vide S&GAD No.SO(CAB-II)1-2/2017(Fin-

170) dated 06-10-2017. Scheme approved on 02-11-

2017 by DDC. . Work awarded on 29-12-2017 but

work not started due to non availability of funds

during 2017-2018. Now funds have been released

by FD on 12-11-2018 & 11.01.2019. Date of

completion dated 28-03-2018. Anticipated dated of

competition 30-06-2019 Amended A.A is issued

from DC, office on 11-12-2018. Work in progress.

1702 3305

Provision of Soling Drainage System Erection of

Tuff Tile in Moti Pur, Qadir Pur, Munshi Other,

Basti Shah Bharamka, Manzoor Kot, Chak Saroo,

Chak Saroo, Chak Tehsil Minchanabad District

Bahawalnagar

BahawalnagarOn-going

Schemes15.000 9.999 1.667 0.900 0.899 100% 73%

Scheme approved on 02-11-2017 by DDC. Tender

received on 27-11-2017 .Date of receipt of funds by

FD.05-03-2018. Date of award. 29-12-2017. Date of

completion 26-06-2018. Anticipated date of

completion. 25.10.2018. Date of receipt of funds by

F.D. 20.07.2018 & 11.01.2019. Scheme completed

in saving. Excess funds Rs.0.350 million

surrendered dated 19.10.2018.

1703 3306Construction of Sewer Lines and Tuff Tiles in Faqir

Wali Tehsil Haroonabad District BahawalnagarBahawalnagar

On-going

Schemes40.000 14.367 3.333 5.000 4.142 83% 46%

Date of A.A(DDC) 03-08-2017. . Date of T.S. 08-08-

2017. . Date of receipt of tender.12-09-2017. Date

of work award. 22-09-2017. Date of completion. 21-

12-2018. Anticipated date of completion 30-06-

2019. Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Funds Rs.2.500 million Provided

through re-appropriation vide Chief

Engineer(S),PHED Lahore No.72-78/B(4) dated

10.01.2019.Work is in progress.

1704 3307Constuction PCC Draiinge / Soling in NA-193

District Rahim Yar Khan

Rahim Yar

Khan

On-going

Schemes40.013 12.987 3.333 2.500 1.951 78% 37%

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.

.Date of receipt of Tender: 07.09.2017..Date of

award: 31.10.2017..Date of completion:

28.02.2018..Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress..

1705 3308Construction of laying Sewerage, Water Supply &

Tuff Tiles City Sadiqabad District Rahim Yar Khan

Rahim Yar

Khan

On-going

Schemes30.000 26.419 1.192 0.894 0.699 78% 90%

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.

.Date of receipt of Tender: 07.09.2017..Date of

award: 31.10.2017..Date of completion:

31.06.2018..Anticipated date of completion 30-06-

2019. Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1706 3309Mega Sewerage Scheme Roads & Tuff Tile

Kotsamaba

Rahim Yar

Khan

On-going

Schemes100.000 14.996 16.667 12.500 9.989 80% 25%

Date of A.A. 09-08-2017. .Date of T.S 26-10-

2017.Date of receipt of Tenders from prequalified

contractors 27-12-2017..Date of award 21-02-

2018..Date of completion 20-10-2019. .Date of

receipt of funds by F.D. 20.07.2018 & 11.01.2019.

Work is in progress.

1707 3310

Providing / Lying of Tuff Tiles Both Sides of Road

from Attock Petrolium to Chowk Din Pur Sharif

Length: 1.50 KM District Rahim Yar Khan

Rahim Yar

Khan

On-going

Schemes31.500 9.999 3.333 2.500 2.156 86% 39%

Date of A.A. 05.08.2017.. Date of T.S. 09.08.2017.

.Date of receipt of Tender: 07.09.2017..Date of

award: 31.10.2017..Date of completion:

31.01.2018..Anticipated date of completion 30-06-

2019.Date of receipt of funds by F.D. 20.07.2018 &

11.01.2019. Work is in progress.

1708 3311Rural Drainage Scheme / PCC Slab For Mouza

Rao Bagh Tehsil and Distt. Chiniot Chiniot

On-going

Schemes29.995 7.498 3.333 2.500 1.550 62% 30%

1. Date of AA = 02.08.2017 2. Date of TS =

26.08.2017 3.Date of Award of work 31.10.2017

4.Dated of Released Funds 30.10.2017 Funds

Released upto 24.01.2019 by the Chief Engineer

(South) PHED Lahore and work is in progress.

1709 3312

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Adda Road Haidry

Chowk Lalian, Baldia Road Al Qaim Medical Store

Afzal Bhatti Mehar Sikandar Lali Chowk, Gala

Mandi Paka Bazar Abadi Bil Muqabil Baldiya office

Aqab Abadi Police

ChiniotOn-going

Schemes14.993 10.000 1.664 1.248 0.832 67% 72%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

4.Dated of Released Funds 30.10.2017 Funds

Released upto 24.01.2019 by the Chief Engineer

(South) PHED Lahore and work is in progress.

Page 115: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1710 3313

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Afzal Bhatti Doctor

Bashir Road Heli Chowk Laliyan, beli Chowk

Laliyan, Beli Chowk to soling/ Sheikh Muhammad

Hussain Airan Store Jhang Road via Hujra Mor,

Beli/ Hujra Road to

ChiniotOn-going

Schemes23.000 8.496 4.333 3.250 2.150 66% 46%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

4.Dated of Released Funds 30.10.2017 Funds

Released on 03.08.2018 by the Chief Engineer

(South) PHED Lahore and work is in progress.

1711 3314

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Ahmadabad Chowk

Bazar Kocha Bandi Ward no. 10, Chongi no. 5 to

Jamia Mosque Chowk Bangla Road,Bangla Road

to Chowk Bazar, Kot Muhammad Yar- Nawab

Chowk Aqeeb Baldiya Office Mo

ChiniotOn-going

Schemes17.907 10.000 2.636 1.977 1.257 64% 63%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

4.Dated of Released Funds 30.10.2017 Funds

Released upto 24.01.2019 by the Chief Engineer

(South) PHED Lahore and work is in progress.

1712 3315

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Jamiya Mosque Bangla

Road Nawab Chowk Imtiaz Lali Chowk, Old Eid

gah Changran - Qadirabad Wark No 3, Ghulam

Mustafabad Ward no 4, Dera Mehar Imtiaz Lali to

Haidery Chowk Police

ChiniotOn-going

Schemes26.900 4.938 3.333 2.500 1.667 67% 25%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1713 3316

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Allah Chowk to

Sargodha Road, Station Noorpur Ward no. 2,

Ward no. 5 Laliyan, Tariqabad Ward no. 6 Lalian

ChiniotOn-going

Schemes25.500 4.420 3.333 2.500 1.667 67% 24%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1714 3317

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Jamia Mosque ward no

7 Laliyan, Imtia Town New Eidgah Umerabad ward

no. 11 Phase I, Imtiaz Town New Eidgah

Umerabad ward no 11 Phase II, including Bangla

Road to Pir Qatbi Shah

ChiniotOn-going

Schemes21.499 4.850 3.333 2.500 1.650 66% 30%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1715 3318

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Dars Colony Bashir

Colony Jaly Dar Dakhli Laliyan, Miana Thatha

Zahoor Colony Dakhli Laliyan, Mouza oilywala

Hujra Hujra Colony Abadi near Petrol Pump Dakhli

Laliyan,Mouza Bhais

ChiniotOn-going

Schemes15.500 4.663 3.500 2.625 1.023 39% 37%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore. Work stopped by

the contractor and Notice issued from this office as

well as S.E PHE Circle Faisalabad Office to the

contractor for restart the work.

1716 3319

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles in Mohallah Pulliyan Abadi Rana

Colony Soling remaining Portion sargodha road to

Rana Colony Dakhli Laliyan, Soling, Mouza Wala,

Mouza Thathi Bala Raja, Mouza Kalu wal.

ChiniotOn-going

Schemes31.100 2.850 3.333 2.500 0.972 39% 12%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore. Work stopped by

the contractor and Notice issued from this office as

well as S.E PHE Circle Faisalabad Office to the

contractor for restart the work.

1717 3320

Construction of PCC / Soling / Drainage / Street

and Tuff Tiles Pullian Mouza Ahmad Nagar,

Carpet City Ladhiyan Phase-I, Carpet City

Ladhiyan Phase-II, and alongwith Road Mouza

Changarwala.

ChiniotOn-going

Schemes32.000 9.816 3.333 2.500 1.562 62% 36%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1718 3321

P/L Tuff Tile, Sewer Line PCC and Street Lights in

Mohallah Rehmanabad, Karamabad, Moqeet Town

and Sagheer Colony in Tehsil and District Chiniot

ChiniotOn-going

Schemes40.827 8.900 3.333 2.500 1.667 67% 26%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1719 3322

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

11, District Chiniot

ChiniotOn-going

Schemes49.988 10.000 3.333 2.500 1.667 67% 23%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

Page 116: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

1720 3323

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

12, District Chiniot

ChiniotOn-going

Schemes49.990 14.200 3.333 2.500 1.667 67% 32%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1721 3324

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

13, District Chiniot

ChiniotOn-going

Schemes49.982 15.000 3.333 2.500 2.500 100% 35%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1722 3325

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

14, District Chiniot

ChiniotOn-going

Schemes49.982 13.000 3.333 2.500 1.650 66% 29%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1723 3326

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

15, District Chiniot

ChiniotOn-going

Schemes49.986 20.000 5.000 3.750 2.500 67% 45%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1724 3327

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

21, District Chiniot

ChiniotOn-going

Schemes49.990 10.000 5.000 3.750 1.789 48% 24%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress. Target progress will be achieved in

coming month.

1725 3328

Provision Drainage/Sewerage/Nallah/PCC/Tuff Tile

/Brick Pavement including all allied works of UC

22, District Chiniot

ChiniotOn-going

Schemes49.980 15.000 5.000 3.750 3.750 100% 38%

1. Date of AA = 02.08.2017 2. Date of TS =

28.08.2017 3.Date of Award of work 31.10.2017

Funds Released upto 24.01.2019 by the Chief

Engineer (South) PHED Lahore and work is in

progress.

1725 Total Ongoing 127182.789 59312.981 8408.757 6297.326 4256.283 68% 50%

New Schemes

1 3329Reheblitiation of Rural Water Supply Scheme

394/JB Tehsil & Distt Toba Tek SinghToba Tek Singh New 28.997 0.000 2.000 0.000 0.000 #DIV/0! 0%

"1-Date of A.A 07.12.2018 2- Date of T.S

12.12.2018 3-Date of Prequalification 4-Date of

invitation of tenders 08.01.2019 5- Date of Receipt

of tenders 09.01.2019 6- Date of work order 7- Date

of completion as per PC-I 8- Anticipated date of

completion 9- No. of Beneficiary -4536-Person 10-

Funds Released by F.D 11-Re-appropriation of

funds (+/-)

2 3330

Rural water supply scheme Saho Chak, Badi Pur &

Gurdanpur U/C Ghurri Tehsil & District Sialkot

(Court Direction)

Sialkot New 27.900 0.000 1.000 1.000 0.000 0% 0% Tender under process

3 3331Rural Drainage Sewerage Scheme of UC Rasulpur

BhallianSialkot New 5.000 0.000 1.000 0.000 0.000 #DIV/0! 0% Tender under process

4 3332

Construction of Sewerage System & Rehabilitation

of Roads, Municipal Committee Zahir Pir Tehsil

Khanpur, Distric R.Y.Khan

Rahim Yar

KhanNew 357.877 0.000 5.000 0.000 0.000 #DIV/0! 0%

Rough Cost Estimate of the scheme is under

preparation by Consultant. Consultant has been

asked for early submission of rough Cost

estimate/PC-1 of the scheme.

5 3333Construction of Waste Water Treatment Plant at

Mianwali.Mianwali New 468.000 0.000 5.000 0.000 0.000 #DIV/0! 0% unapproved

6 3334

Sewerage Drianage Scheme in 05 No. colonies of

chak No. 79/NB including desilting of exisitng

sewer lines, Sargodha (Court Direction)

Sargodha New 69.638 0.000 5.000 0.000 0.000 #DIV/0! 0%Estimate submitted for technical vetting to C.E (N).

Funds yet not released.

7 3335Rehabilitaion / Improvement Sewerage system

Jhang, Phase-IJhang New 700.000 0.000 5.000 0.000 0.000 #DIV/0! 0%

Date of A.A 18.10.2017 Date of T.S 31.10.2017

Work order issued on 13.08.2018. Work is in

progress.

8 3336Sewerage / Drianage scheme adjacent abadies of

ada Mohlanwal Lahore New 150.000 0.000 2.500 0.000 0.000 #DIV/0! 0% AA awaited.

9 3337

Water, Sanitation and Hygiene (WASH)

Programme under stunting reduction programme in

11 Districts of Multan, Bahawalpur and D.G.Khan

Civil Divisions

Punjab New 3,086.564 0.000 8.743 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

10 3338Feasibility Study for provision of surface water and

treatment of waste water across PunjabPunjab New 200.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

Page 117: MONTHLY PROGRESS REPORT UPTO 31.01.19 DEVELOPMENT … · Sr. No. GS. No. New Name of Scheme District Type Approved Cost Exp Upto June 2018 Provision for 2018-19 Funds Released by

11 3339 Funding for Clearance of liablities Punjab New 40.000 0.000 40.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

12 3340

Public Awareness Campaign and strengthening of

communicty development & communication unit of

PHED

Punjab New 100.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

13 3341 Clean Water for Healthy Life Punjab New 5,000.000 0.000 5000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

14 3342 Rural sewerage & drainage schemes Punjab New 3,500.000 0.000 2000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

15 3343Water Quality testing Labortary at Township

Lahore (PPP Mode)Punjab New 395.000 0.000 1.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

16 3344Establishment of Project Support Unit for Clean

Water for Healthy LifePunjab New 500.000 0.000 5.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

17 3345Insaaf Program for Water Supply and Sanitation in

Rural Areas Punjab New 5,000.000 0.000 5000.000 0.000 0.000 #DIV/0! 0% Funds not Released by FD.

17 Total New 19628.976 0.000 12091.243 1.000 0.000 0.000 0%

1742 Total Ongoing + New 146811.765 59312.981 20500.000 6298.326 4256.283 68% 43%