FOLDER 10 1 MONITORING & CONTROL Project Monitoring

Transcript of MONITORING & CONTROL -...

FOLDER 10

1

MONITORING & CONTROL

• Project Monitoring

2

Proses- Proses Pengesanan Kemajuan

Set baseline – open baseline file

Set status - make sure BEFORE current date

Update schedule progress –

set status gridline to see the line

Open tracking table

‘update project’ icon

Prepare ‘tracking summary’ table

Fill in the schedule data

Track actual data

Use actual data

Update it to obtain what has been achieved

Data entry to MSP

Identify variances

Identify variance in tracking summary

Take action 3

Pengesanan Kemajuan

Pengesanan Kemajuan-Menentukan Baseline

4

5

Kenapa Baseline ?

Baseline

...in monitoring

Baseline Start

Date

Baseline

Finish Date

Baseline

Duration

Baseline Cost

Baseline

Resources

1

2

3

4

5

7

Current /Actual

Start

Finish

Duration

Cost

variable

Planned

Baseline Start

Baseline Finish

Baseline Duration

Baseline Cost

static

Variance

Baseline

8

11

Menetapkan Baseline

3

2

1

4

6

5

9

7

10

8

13

12

11

Menetapkan Baseline

Tracking bars with

underlying baseline bars

Menetapkan Baseline

Saving Baseline File

2

1

3

4

Saving & Naming Updated File

2

1

3

4

Pengesanan Kemajuan-Menentukan Tarikh Status

Kemajuan

14

Set Status Date

3

12

4

5

8

6

7

Set Status Date

10

11

12

13

Status date line

Pengesanan Kemajuan- Status Kemajuan Mengikut Jadual

(Update Schedule Progress)

17

Status Kemajuan Mengikut Jadual2

1

3

Default tracking table

Status Kemajuan Mengikut Jadual54

6

8

9

7

20

Baseline :Ref.

ColumnSchd.

ProgressActual

ProgressVariance Actions

Financial Progress

Actual Cost

Physical Progress

% Comp

Project Finish Date

ID

Analisa Kemajuan Projek

Pengesanan Kemajuan- Mengesan Kemajuan Sebenar di Tapak

(Track Actual Progress)

21

22

Yang Perlu disemak

Tarikh mula& siapsetiapaktiviti

% siap

Menilai Kemajuan Sebenar Di Tapak

Create Additional Column For Scheduled Progress

(% Schedule)

1

2

Right click

3

Create Additional Column For Scheduled Progress

(% Schedule)

Create Text 1 column

4

5

Right click

Create Additional Column For Scheduled Progress

(% Schedule)

6 7

8

9

The “% Schedule”

column is created

Type in % Schedule

CREATE ADDITIONAL COLUMN FOR SCHEDULED

PROGRESS (% SCHEDULE)

11

10

Selecting % Comp Data

11

13

Inserting % Schedule

Data

% Schedule Column

Schedule Cost Column

Repeat steps to create new “Schedule Cost” column by using data from Act Cost column. Using Text 2 in the new column property.

Kemajuan Sebenar di Tapak

Baseline: 1

Status date:

30.6.2013

Actual Start Actual Finish

% Schedule

Blok A

Kerja Tanah 15/6 - 20%

Kerja Struktur - - -

Blok B

Kerja Tanah 20/6 - 15%

Kerja Struktur - - -

Contoh: Actual Progress Data pada 30 Jun 2013

30

Cara memasukkan maklumat kemajuan kerjadalam MSP.

Mengikut turutan seperti berikut:

1. Actual Start

2. Actual Finish

3. % complete

Actual Start Dan Actual Finish Mesti Dimasukkan .

Turutan Ini Tidak Terpakai Pada Milestone

Mengemaskini Kemajuan Sebenar Di Tapak

1

3

2

Mengemaskini Kemajuan Sebenar Di Tapak

Finish date milestone has

automatically shifted

Mengemaskini Kemajuan Sebenar Di Tapak

Pengesanan Kemajuan- Mengenalpasti Varian

33

Mengenalpasti Varian

Physical

variances

Financial

variances

PFD Variances

Baseline: 1

Status date:

30.6.2013

Actual

Progress

Schedule

Progress

Variances

Financial (RM) 94,650.00 150,050.00 - 55,400.00

Financial (%) 4.7 9.5 - 4.8

Physical (%) 9 12 - 3

Project Finish

Date

11.11.2013 30.10.2013 +12days

Contoh Varian Projek

Pengesanan Kemajuan- Tindakan Kepada Varian

36

37

Tindakan mengikut keutamaan :

1

2

3

Tindakan Kepada Varian

Baseline: 1

Status date:

30.6.2013

Actual

Progress

Schedule

Progress

Varian Tindakan

(contoh)

Financial (RM) 94,650.00 150,050.00 - 55,400.00 Laksana kerja yang

bernilai tinggiFinancial (%) 4.7 9.5 - 4.8

Physical (%) 9 12 - 3 Fokus kepada

kerja-kerja kritikal

Project Finish

Date

11.11.2013 30.10.2013 +12days Laksana kerja yang

masih belum

bermula

Contoh Tindakan Kepada Varian

39

Contoh template laporan kemajuan kerja yang perlu disediakan olehkontraktor