Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk...

92
Monitoring and Control 15-Apr-2014 1

Transcript of Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk...

Page 1: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Monitoring and Control

15-Apr-2014

1

Page 2: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

...recap::Risk Management

Risk Management begins with Risk Awareness

2

Page 3: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap:: RM Process

Risk Identification Risk Assessment Risk Evaluation Risk Management

3

Page 4: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap:: RM Process

4

Page 5: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap::RM Risk Register

5

Page 6: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap: RM Risk Exposure

6

Page 7: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap: RM Risk Management Chart

7

Page 8: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap::RM Principles of Risk Management Proactive Continuous

MonitoringAssessmentDecision making

Expected result: Continuous risk reduction

8

Page 9: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap::Types of risks

Resource Risks Business Risks Technical Risks Schedule Risks

9

Page 10: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap: Risk Response Strategies (-)

Risk avoidance Risk reduction Risk transfer Risk acceptance

10

Page 11: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap::Risk Response Strategies (+) Exploit Share Enhance Risk acceptance

11

Page 12: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

…recap::Risk Indicators

Total impact of top ten risks Top ten risks mitigation costs Top ten risk variation Top ten risks impact variation

12

Page 13: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Today’s topic

Project Monitoring and Control

13

Page 14: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMC topics for today

Briefly describe monitoring purpose, deliverables, activities, measures

Controlling processes, as described in PMBOK

Some specific metrics examples

14

Page 15: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Definition

The goal of Project Monitoring and Control (PMC) is to provide an understanding of the project's progress so that appropriate corrective actions can be taken when the project's performance deviates significantly from the plan.

15

Page 16: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Project Monitoring & Control

Monitoring – collecting, recording, and reporting information concerning project performance that project manager and others wish to know

Controlling – uses data from monitor activity to bring actual performance to planned performance

16

Page 17: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMC

Why do we monitor? What do we monitor? When do we monitor? How do we monitor?

17

Page 18: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Why do we monitor? Goals Provide project manager and

development team with the following: An accurate assessment of the progress to

date Insight into the quality of the evolving

software productA basis for estimating cost and budgeting

with increased accuracy over time

18

Page 19: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

What do we monitor? Men (human resources) Machines Materials Money Space Time Tasks Quality/Technical Performance

19

Page 20: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Purpose Ensure the team is making progress

Overall objectives:Track accomplishments and compare to

planned valuesRevise the project plan: accomplishments so

far, remaining work (if needed)Detect performance issues as early as

possible, such that corrective action can be taken

20

Page 21: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

What do we obtain?Inputs Time Money Resources Material Usage Tasks Quality/Technical

Performance

Outputs

Progress

Costs

Job starts

Job completion

Engineering / Design changes

Variation order (VO)

21

Page 22: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Deliverables Written status reports Updates to lists of action items, risks,

problems, and issues Updates to plan/schedule, to reflect

actual progress Comparison of actual vs. budgeted

cost, cost/benefit analysis (EVA) Audit/review reports of the activities

and work products under development22

Page 23: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

When do we monitor? Continuously Regularly Logically While there is still time to react As soon as possible At task completion At pre-planned decision points

(milestones) End of the project

23

Page 24: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMC – Activities Continuously monitor progress

Examine progress on all key dimensions of the project; goals likely to be met?

Conduct team reviewsCommunicate status (technical activities); plan

for next activities of the project Conduct formal progress reviews

Monthly basis with senior management and key stakeholders

24

Page 25: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMC – Activities (contd.) Manage changes

Identify, evaluate, prioritize, and control changes to the project

Revise the planSignificant changes need to be reviewed and

agreed to by those who originally approved the plan

Conduct work product reviewsWalkthroughs, technical reviews and

inspections, based on quality goals

25

Page 26: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMC – Example Measures Milestone attainment

Maintain the initial baseline, as well as the most recent update

Report achievement and variance to both

Effort spent Compare initial effort estimates for each major

WBS element with actual effort spent

26

Page 27: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMC – Example Measures (contd.)

Budget/Cost performanceCompare rate of spending on the project by

period (week or month) compared to the planned spending

Requirements change Track requirements change by period (month

usually): total number of requirements, number added in this period, number deleted in this period, and number changed in this period

EVA – Earned Value Analysis

27

Page 28: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

PMBOK Guide

28

Page 29: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Scope Verification Obtain formal acceptance of the project

scope by stakeholders

Review deliverables – correct and satisfactory (not quality check!!)

29

Page 30: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Scope Verification Inputs:

Work results: which deliverables – fully/partially completed

Product documentation: describes project’s products

WBS: used to verify work of the project; defines scope baseline

Scope statement: defines scope in some detail

Project plan

30

Page 31: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Scope Verification Outputs:

Formal acceptance: must be documented; can be conditional

Tools & Techniques: Inspection: measure/examine/test results vs.

requirements

31

Page 32: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Project Control Cycle

32

PLANSpecificationsProject ScheduleProject budgetResource planVendor contracts MONITOR

Record statusReport progressReport cost

COMPAREActual status against plan- Schedule- Cost

ACTION

Correct deviations from plan

RE-PLAN as necessary

Page 33: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Scope Change Control Concerned with: influencing change

factors; determining occurrence of a scope change; managing changes if/when occur

Must be integrated with other control processes

33

Page 34: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Scope Change Control Inputs:

WBSPerformance reports: e.g. which interim

deliverables have been completed, which notChange requests: oral/written, direct/indirect,

external/internal, legally mandated/optionalScope management plan: how scope is

managed; how changes are integrated; assessment of expected stability; how changes are identified/classified

34

Page 35: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Scope Change Control Outputs:

ScopeCorrective changesLessons learnedAdjusted baseline

Tools & Techniques:Scope change controlPerformance measurementAdditional planning: e.g. modification to WBS

35

Page 36: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control Concerned with: influencing change

factors; determining occurrence of a scope change; managing changes if/when occur [same as scope change control]

Must be integrated with other control processes

36

Page 37: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control Inputs:

Project schedule: schedule baselinePerformance reportsChange requestsSchedule management plan

37

Page 38: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control Outputs:

Schedule updatesCorrective actionLessons learned

Tools & Techniques:Schedule change control systemPerformance measurementAdditional planningProject management softwareVariance analysis

38

Page 39: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control – metrics Measurement done at WBS unit level:

CAP – Control Account Plan = work package with extra features:

Assignment of responsibility (organization/individual)

Division (if needed) in lower-level work packages Metrics for measuring performance: milestones,

%complete…

39

Page 40: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control – metrics EVA – Earned Value Analysis

Variance analysis – not full picturePlanned vs. completed work, to

determine if cost, schedule, and work are progressing as planned

40

Page 41: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control – metrics Three key values: used to derive further

schedule/cost indicators:BCWS: budgeted cost of work

scheduled; a.k.a. PV – Planned ValueACWP: actual cost of work performed;

a.k.a. AC – Actual CostBCWP: budgeted cost of work

performed; a.k.a. EV – Earned Value

41

Page 42: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Schedule Control – metrics Schedule indicators

SV: Schedule Variance:SV = BCWP – BCWS< 0 => behind schedule

SPI: Schedule Performance IndexSPI = BCWP/BCWS < 1 => behind schedule

42

Page 43: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Example

5500049000

56000

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWS

BCWP

ACWP

SV = BCWP-BCWS

$49,000 – 55,000

SV = - $ 6,000

SPI: BCWP/BCWS

49,000/55,000 = 0.891

43

Page 44: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Cost Control Concerned with: same as before Must be integrated with other control

processes Includes:

Monitor cost performance, detect and understand variances from plan

Ensure all appropriate changes – recorded accurately in cost baseline

44

Page 45: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Cost Control Includes (contd):

Prevent incorrect/inappropriate/ unauthorized changes to cost baseline

Inform stakeholdersAct to bring expected costs within

acceptable limits

45

Page 46: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Cost Control Inputs:

Cost baselinePerformance reportsChange requestsCost management plan

46

Page 47: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Cost Control Outputs

Revised cost estimatesBudget updatesCorrective actionEstimates at completionProject closeoutLessons learned

47

Page 48: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Cost Control Tools & Techniques

Cost change control systemPerformance measurementEVAAdditional planningSoftware tools (e.g. MSProject)

48

Page 49: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Cost Control – metrics – EVA Cost indicators:

CV: Cost Variance CV = BCWP – ACWP < 0 => over the budget

CPI: Cost Performance Index CPI = BCWP/ACWP < 1 => over the budget

49

Page 50: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Example

5500049000

56000

0

20000

40000

60000

80000

100000

120000

Jan-

03

Feb

-03

Mar

-03

Apr

-03

May

-03

Jun-

03

Jul-0

3

Aug

-03

Sep

-03

Oct

-03

Nov

-03

Dec

-03

BCWS

BCWP

ACWP

CV = BCWP-ACWP

$49,000 – 56,000

CV = - $ 7,000

CPI: BCWP/ACWP

49,000/56,000 = 0.875

50

Page 51: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

EAC – Estimate At Completion Forecast of most likely total project costs

EAC = actuals to date + new estimate for remaining work

EAC = AC + ETC Used when original assumptions – proven

flawed/no longer relevant to a change in conditions

51

Page 52: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

EAC – Estimate At Completion EAC = actuals to date + remaining budget

EAC = AC + (BAC – BCWP); Used when current variances – atypical; not

expected to appear in future

52

Page 53: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

EAC – Estimate At Completion EAC = actual to date + remaining budget

modified by a performance factor (often CPI)

EAC = AC + (BAC – BCWP)/CPIUsed when current variances – typical of

future variancesOnce a project is 20% complete, the CPI does

not vary from its current value by more than 10%.

53

Page 54: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Earned Value Chart

54

Page 55: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

ExampleAssume that operations on a Work Package

cost $1,500 to complete. They were originally scheduled to finish today. At this point, we actually spent $1,350. And we estimate that we have completed two thirds (2/3) of the work. What are the cost and schedule variances?CV = BCWP – ACWP = 1500 (2/3) – 1350 = - 350 SV = BCWP – BCWS = 1500 (2/3) – 1500 = - 500 55

Page 56: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Example continued

CPI = BCWP/ACWP = 1500(2/3)/1350 = 0.74SPI = BCWP/BCWS = 1500(2/3)/1500 = 0.67Spending higher than budget, and given what we have spent, we are not as far along as we should be (have not completed as much work as we should have)

56

Page 57: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Relations between indicators

Possible to have one of indicators to be favorable while the other unfavorable

Might be ahead of schedule and behind costs

Six possibilities (see figure next slide)

57

Page 58: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

6 Possibilities Earned Value Analysis

58

Page 59: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Exercise

A project to develop a software system has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the two indexes.

59

Page 60: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Solution

60

BCWS = 475,000 CV = BCWP – ACWP = -50,000BCWP = 300,000 SV = BCWP – BCWS = -175,000ACWP = 350,000 CPI = BCWP/ACWP = 0.86 SPI = BCWP/BCWS = 0.63

Page 61: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Critical Ratio Sometimes, especially large projects, it may be

worthwhile calculating a set of critical ratios for all project activities

The critical ratio is

actual progress x budgeted cost

scheduled progress actual cost

If ratio is 1 everything is probably on target The further away form 1 the ratio is, the more we

may need to investigate

61

Page 62: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Critical ratio example Which activities are probably on target and

which need to be investigated?

62

Page 63: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Critical ratio example

Can be on schedule and below budget (Act A) Why so good? Cutting corners?

Can be behind schedule but below budget (Act C)

Can be on budget but physical progress lagging (Act E)

Can be on schedule but cost running higher than budget (Act D)

On budget ahead of schedule (Act B)63

Page 64: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control Monitor and evaluate specific results

against relevant quality standards; eliminate causes of unsatisfactory results.

Often performed by a Quality Control Department

64

Page 65: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control Inputs:

Work results: both process and productQuality management planOperational definitions (metrics)Checklists

65

Page 66: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control (contd.) Tools & Techniques:

InspectionControl chartsPareto diagramsStatistical samplingFlowchartingTrend analysis

66

Page 67: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control (contd.) Outputs:

Quality improvementAcceptance decisionsReworkCompleted checklistsProcess adjustments

67

Page 68: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control – metrics Control charts = graphic display of results, over time, of a process. Used to monitor any type of output variable (cost/schedule

variances, scope changes volume/frequency, errors in docs)

Control chart of project schedule performance

68

Page 69: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control – metrics Pareto diagrams = histogram, ordered by

frequency of occurrence, that shows how many results were generated by type of cause

Rank – used to guide corrective actionPareto’s law: 80% of problems are due

to 20% of causes

69

Page 70: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control – metrics Flowcharting = show relations between

system elements.

Cause-and-effect: how various factors may be linked to potential problems/effects

System/process flowcharts

70

Page 71: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control – metrics Trend Analysis = use math techniques to

forecast future based on past:

Technical performance: no. of errors identified; no. corrected

Cost/Schedule performance: no. of activities/period completed with significant variances

71

Page 72: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control – normal trends

Defect density acrosslifecycle

72

Page 73: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Quality Control – normal trends

Rework trends across lifecycle

73

Page 74: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Keep track of identified risks; monitor

residual risks; identify new risks; ensure execution of risk plans & evaluate their effectiveness

Risks change as project matures

74

Page 75: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Provides info that assists with making

effective decisions in advance of the risks appearing

Periodically communicate with stakeholders to agree upon level of risk in project

75

Page 76: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Purpose – check if:

Risk responses have been implemented as planned

Risk responses are effective, or new must be implemented

Project assumptions – still validRisk exposure has changed (trend

analysis)

76

Page 77: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Purpose – check if:

Risk trigger has occurredProper policies and procedures are

followedRisks not previously identified have

occurred

77

Page 78: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Inputs:

Risk management planRisk response planProject communication: issues logs,

action-item lists, jeopardy warnings, escalation notices.

Additional risk identification and analysis

Scope changes

78

Page 79: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Tools & Techniques

Project risk response auditsPeriodic project risk reviewsEarned Value AnalysisTechnical performance measurementAdditional risk response planning

79

Page 80: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control Outputs:

Workaround plansCorrective actionProject change requestsUpdates to the risk response planRisk databaseUpdates to risk identification checklists

80

Page 81: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Risk Monitoring & Control

Typical project risk exposure

81

Page 82: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Performance Reporting Includes:

Status reportingProgress reportingForecasting

Include info on scope, schedule, cost and quality; risk and procurement.

Inputs:Project planWork resultsOther project records (e.g. project context)

82

Page 83: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Performance Reporting Tools & Techniques:

Performance reviewsVariance analysisTrend analysisEVA Information distribution tools and

techniques Outputs:

Performance reportsChange requests

83

Page 84: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control Concerned with: influencing change

factors; determining occurrence of a change; managing changes if/when occur

Original project scope and performance baseline – maintained by continuously managing changes

84

Page 85: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control

Requirements:Maintain integrity of the performance

measurements baselineEnsure changes in product scope –

reflected in project scopeCoordinate changes across knowledge

areas (risk control, time control, schedule control…)

85

Page 86: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control Inputs:

Project planPerformance reportsChange requests

86

Page 87: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control Tools & Techniques:

Change control system Collection of formal, documented procedures that

defines how project performance will be monitored and evaluated

Paperwork, tracking systems, processes, approval levels

Evaluation groups: Configuration Control Board (CCB), Engineering Review Board (ERB), Technical Review Board (TRB), Technical Assessment Board (TAB)

87

Page 88: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control Tools & Techniques (contd.)

Configuration management: any documented procedure used to apply technical/administrative direction and surveillance to

Identify and document the functional and physical characteristics of an item or system

Control any changes to such characteristics Record and report the change and its

implementation status Audit items and system, to verify conformance with

requirements

88

Page 89: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control

Tools & Techniques (contd.)Performance measurementAdditional planningProject management information system

(PMIS)

89

Page 90: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Integrated Change Control

Outputs:Project plan updatesCorrective actionLessons learned

90

Page 91: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Conclusions

The progress towards project goals and the quality of software products must be measurable throughout the software development lifecycle

Metrics values provide an important perspective for managing the process. Metrics trends provide another.

91

Page 92: Monitoring and Control 15-Apr-2014 1. ...recap::Risk Management Risk Management begins with Risk Awareness 2.

Conclusions The most useful metrics are extracted

directly from the evolving artefacts Objective analysis and automated data

collection are crucial for any metrics program.

Subjective assessments and manual data collection are likely to fail.

92