Monitor Placement for Estimation of Voltage Sags in Power ...
Transcript of Monitor Placement for Estimation of Voltage Sags in Power ...
Monitor Placement for Estimation
of Voltage Sags in Power Systems
A thesis submitted to The University of Manchester for the degree of
Doctor of Philosophy
in the Faculty of Engineering and Physical Sciences
2012
José Manuel Avendaño Mora, M. Sc.
School of Electrical and Electronic Engineering
2 |
Contents
Abstract ................................................................................................................... 10
Declaration ................................................................................................................... 11
Copyright Statement .......................................................................................................... 12
Acknowledgments ............................................................................................................. 13
Chapter 1 Introduction .............................................................................................. 15
1.1 Power Quality ............................................................................................ 15
1.2 Voltage sags ............................................................................................... 16
1.2.1 Causes and Characteristics ......................................................................... 17
1.2.2 Consequences ............................................................................................. 20
1.2.3 Indices ........................................................................................................ 21
1.2.4 Monitoring ................................................................................................. 23
1.3 Literature review ........................................................................................ 24
1.3.1 Monitor Placement for Sag Performance Assessment ............................... 24
1.3.2 Sag Performance Estimation ...................................................................... 30
1.3.3 Voltage Sag State Estimation .................................................................... 33
1.3.4 Summary .................................................................................................... 36
1.4 Aims of Research ....................................................................................... 36
1.5 Major Contributions of the Research ......................................................... 37
1.6 Overview of the Thesis .............................................................................. 38
Chapter 2 Modeling and Simulation Tools .............................................................. 40
2.1 Simulation Tools for Voltage Sag Studies ................................................. 40
2.2 Modeling of System Components .............................................................. 42
2.2.1 Cables and Lines ........................................................................................ 42
2.2.2 Generators .................................................................................................. 43
2.2.3 Loads .......................................................................................................... 44
2.2.4 Transformers .............................................................................................. 44
2.3 Bus Impedance Matrix ............................................................................... 47
2.4 Fault Calculation Based on System Impedance Matrix ............................. 50
2.4.1 Three-Phase Faults ..................................................................................... 54
2.4.2 Single Line-to-Ground Faults .................................................................... 55
2.4.3 Line-to-Line Faults .................................................................................... 57
2.4.4 Line-to-Line-to-Ground Faults .................................................................. 58
2.5 Voltage Sag Assessment Software ............................................................ 60
2.6 Test Systems .............................................................................................. 60
2.6.1 10-bus Power System ................................................................................. 60
2.6.2 IEEE Reliability Test System .................................................................... 61
2.6.3 IEEE 118-bus Power Flow Test Case ........................................................ 62
2.6.4 Generic Distribution System ...................................................................... 62
2.7 Summary .................................................................................................... 63
Chapter 3 Optimal Monitor Placement for Voltage Sag Characterization .......... 65
3.1 Monitor Reach Area Method ..................................................................... 65
3.1.1 Formulation of the Optimization Problem ................................................. 68
3 |
3.1.2 Voltage Sag Estimation at Non-Monitored Buses ..................................... 68
3.1.3 Factors Influencing Accuracy of Voltage Sag Detection .......................... 69
3.1.4 Variability in Number of Optimally Placed Monitors ............................... 72
3.2 Enhanced Fault Location Algorithm .......................................................... 75
3.2.1 Fault Location of Three-phase Symmetrical Faults ................................... 75
3.2.2 Fault Location of Line to Line Faults ........................................................ 78
3.2.3 Fault Location of Line to Ground Faults ................................................... 80
3.2.4 Fault Location of Line to Line to Ground Faults ....................................... 80
3.3 Enhanced Monitor Reach Area Algorithm ................................................ 83
3.4 Enhancement of Sag Estimation Accuracy with EMRAA ........................ 85
3.5 Summary .................................................................................................... 88
Chapter 4 Generalized Formulation of the Optimal Monitor Placement Problem
for Fault Location .................................................................................... 89
4.1 Optimal Monitor Placement for Fault Location ........................................ 90
4.2 Generalized Formulation of the Optimal Monitor Placement Problem ..... 93
4.2.1 Definition of new variables ........................................................................ 93
4.2.2 Reduction of Number of Constraints ......................................................... 95
4.2.3 Problem Formulation ................................................................................. 96
4.2.4 Application in the 4-bus Sample System ................................................... 97
4.3 Application in Large Power Networks ...................................................... 97
4.3.1 10-bus 500 kV Power Network ................................................................. 98
4.3.2 IEEE 24-bus Reliability Test System (RTS) ........................................... 100
4.3.3 IEEE 118-bus Test System ...................................................................... 101
4.4 Summary .................................................................................................. 104
Chapter 5 Heuristic Approach for Determining Optimal Monitor Placement for
Voltage Sag Estimation ......................................................................... 105
5.1 Review of Proposed Formulation of Optimal Monitor Placement for Fault
Location ................................................................................................... 106
5.2 The Greedy Search Algorithm ................................................................. 107
5.2.1 Set-Covering Problem .............................................................................. 107
5.2.2 The Greedy Algorithm ............................................................................. 108
5.2.3 Application of the Greedy Algorithm to the Optimal Monitor Placement
Problem .................................................................................................... 109
5.3 Greedy Monitor Placement with Custom Objective Functions ............... 111
5.3.1 Observability Weight Factors .................................................................. 112
5.3.2 Sag Magnitude Estimation Error ............................................................. 116
5.3.3 Sag Event Estimation Error ..................................................................... 122
5.4 Summary .................................................................................................. 130
Chapter 6 Techno-Economic Assessment of Voltage Sags Using Optimal
Monitoring Programs ............................................................................ 131
6.1 Hybrid Methodology for Monitoring and Estimation of Voltage Sags ... 132
6.1.1 Selection of Most Probable Fault Location ............................................. 132
6.1.2 Hybrid Monitor Placement Method ......................................................... 137
6.1.3 Simplified Voltage Sag Estimation .......................................................... 138
4 |
6.2 Case Study 1: Assessment of Voltage Sag Events .................................. 138
6.2.1 Size of Monitoring Programs ................................................................... 139
6.2.2 Sag Event Estimation ............................................................................... 139
6.3 Risk-Based Assessment of Financial Losses due to Voltage Sags .......... 142
6.4 Case Study 2: Assessment of Financial Losses Caused by Voltage Sags 143
6.4.1 Conventional and Optimal Monitoring Schemes ..................................... 143
6.4.2 Assessment of Financial Losses .............................................................. 144
6.5 Summary .................................................................................................. 150
Chapter 7 Conclusions and Future Work.............................................................. 151
7.1 Conclusions .............................................................................................. 151
7.2 Future Work ............................................................................................. 154
Chapter 8 References ............................................................................................... 156
Appendix A Network Data of Test Systems .............................................................. 167
Appendix B Minimization of SMEE by greedy monitor placement ....................... 183
Appendix C Minimization of SEEE by greedy monitor placement ........................ 188
Appendix D Distribution of SNPV from 1000 trials for all customers’ plants at
different locations .................................................................................. 193
Appendix E Distribution of SNPV from 1000 trials at all locations for different
types of customer plants ........................................................................ 201
Appendix F List of Publications ................................................................................. 210
Final word count: 40,101
5 |
List of Figures
Figure 1-1 Basic procedure to evaluate voltage sags, modified from [2] ..................... 17
Figure 1-2 Origin of voltage sags. ................................................................................ 18
Figure 1-3 Measured voltage sag due to a short circuit fault, voltage in three phases in
time domain (reproduced from [1])................................................................................. 19
Figure 1-4 Rms voltages for the sag shown in Figure 1-3 (reproduced from [1]). ....... 19
Figure 1-5 Sag duration as a function of the voltage threshold for the three phases of
the sag shown in Figure 1-3 (reproduced from [1]). ....................................................... 19
Figure 1-6 Types of voltage sags in phasor-diagram form. .......................................... 20
Figure 2-1 Lumped parameters model of cables and lines. .......................................... 43
Figure 2-2 Model of generators..................................................................................... 44
Figure 2-3 Constant impedance load model. ................................................................ 44
Figure 2-4 Transformer representation, (a) equivalent circuit with an ideal transformer
and (b) equivalent circuit with magnetizing current neglected (adopted from [83]). ..... 45
Figure 2-5 Zero-sequence equivalent circuits of five three-phase transformer banks and
their respective symbols and connection diagrams (adopted form [83]). ....................... 46
Figure 2-6 Equivalent circuit for tap changing transformer (adopted from [85]). ........ 47
Figure 2-7 Single line diagram of a three-phase system (a), the three sequence
networks of the system (b-d), and the Thévenin equivalent circuit of each network for a
fault at point P , identified as bus k (e-g) (adopted from [83]). ..................................... 51
Figure 2-8 Three-phase fault through fault impedance fZ , (a) symbolic representation
and (b) connection of the Thévenin equivalent circuit (adopted from [83]). .................. 55
Figure 2-9 Single line-to-ground fault through fault impedance fZ , (a) symbolic
representation and (b) connection of the Thévenin equivalent circuits (adopted from
[83]). ................................................................................................................................ 56
Figure 2-10 Line-to-line fault with fault impedance fZ , (a) symbolic representation
and (b) connection of the Thévenin equivalent circuits (adopted from [83]). ................ 58
Figure 2-11 Double line-to-ground fault with fault impedance fZ , (a) symbolic
representation and (b) connection of the Thévenin equivalent circuits (adopted from
[83]). ................................................................................................................................ 60
Figure 2-12 A sample 10-bus network. ........................................................................ 61
Figure 2-13 IEEE Reliability Test System (RTS). ........................................................ 61
6 |
Figure 2-14 IEEE 118-bus power flow test case. .......................................................... 62
Figure 2-15 Single line diagram of the generic distribution system (GDS). ................ 64
Figure 3-1 Symbolic representation of three monitor reach areas for bus 9 of the IEEE-
RTS. ................................................................................................................................ 66
Figure 3-2 Illustrative power system. ........................................................................... 67
Figure 3-3 Voltage sag magnitude at monitored buses (3, 6, 8, and 17) and bus 5 (one
of the ends of faulted line) as a function of fault impedance. ......................................... 70
Figure 3-4 Voltage sag magnitude at monitored buses (3, 6, 8, and 17) and bus 5 (one
of the ends of faulted line) as a function of fault distance. ............................................. 71
Figure 3-5 Voltage sag magnitude at monitored buses as a function of pre-fault
voltage. ............................................................................................................................ 71
Figure 3-6 Number of voltage sags with a residual voltage of 90% or less (SARFI90).
......................................................................................................................................... 87
Figure 3-7 Number of voltage sags with a residual voltage of 80% or less (SARFI80).
......................................................................................................................................... 87
Figure 3-8 Number of voltage sags with a residual voltage of 70% or less (SARFI70).
......................................................................................................................................... 88
Figure 4-1 Flowchart for generating constrains for fault point F1 (adopted from [53]).
......................................................................................................................................... 91
Figure 4-2 Sample 4-bus system. .................................................................................. 91
Figure 4-3 Line segments (length is labeled) of the system used in [53] where faults
cannot be uniquely located with 2 monitors. .................................................................. 98
Figure 4-4 Observable lines by monitors installed at buses 7 and 8 in the IEEE-RTS.
....................................................................................................................................... 101
Figure 4-5 Optimal monitoring locations that lead to full fault observability of the
IEEE 118-bus system. ................................................................................................... 103
Figure 5-1 Illustration of set-covering problem. ......................................................... 108
Figure 5-2 Flowchart of the greedy approximation algorithm. ................................... 109
Figure 5-3 Flowchart for implementing the weighted greedy algorithm. ................... 113
Figure 5-4 Buses (red numbered) designated by greedy monitor placement algorithms
as optimal locations for voltage measurement devices. ................................................ 115
Figure 5-5 Flowchart detailing the process of building an optimal sag monitoring
program (OSMP) aimed at minimizing the sag magnitude estimation error (SMEE). . 118
7 |
Figure 5-6 Proportions of the GDS network where line to ground faults can be located
by the ordered addition of voltage measurement devices. ............................................ 120
Figure 5-7 Sag Magnitude Estimation Error (SMEE) obtained during each iteration of
the greedy monitor placement procedure. ..................................................................... 121
Figure 5-8 Increase in network’s coverage of different types of faults obtained during
each iteration of the greedy monitor placement procedure. .......................................... 122
Figure 5-9 No Damage Region of the ITIC Curve. .................................................... 125
Figure 5-10 GDS network’s voltage sag profile. ........................................................ 126
Figure 5-11 SEMI F47 Curve – required semiconductor equipment voltage sag
immunity (adopted from [117]). ................................................................................... 127
Figure 6-1 Difference between calculated and real phase residual voltages of line to
line to ground faults on the IEEE-RTS. ........................................................................ 135
Figure 6-2 Difference between calculated and real magnitude of sags caused by line to
line and three-phase faults not correctly localized using the residual voltages from bus
12. .................................................................................................................................. 136
Figure 6-3 Monitoring schemes and customer’s plant locations in the generic
distribution system. Engineering monitoring sites are indicated through color squares
with Roman numerals and uppercase letters; optimal monitoring locations (25) are
numbered with color circles; the eight plant locations analyzed are symbolized and
represented with minuscule letters. ............................................................................... 146
Figure 6-4 Distribution of SNPV from 1000 trials for all customers’ plants at location
h estimated using all monitoring schemes. ................................................................... 147
Figure 6-5 Distribution of SNPV from 1000 trials for a semiconductor factory at all
locations (a-h) estimated using all monitoring schemes. .............................................. 149
8 |
List of Tables
Table 1-1 Transformation of sag type to lower voltage levels (adopted from [1]) ....... 19
Table 1-2 Impact of sag characteristics on equipment immunity (adopted from [19] .. 20
Table 1-3 Economic consequences of voltage sags (adopted from [12]) ..................... 21
Table 1-4 Voltage sag table recommended by IEC 61000-2-8 and range of SARFI80
index ................................................................................................................................ 23
Table 1-5 Number of monitors at different voltage levels in current European
monitoring systems (adopted from [35]) ........................................................................ 27
Table 2-1 Voltage sag calculation methodology (adopted from [11]) .......................... 41
Table 2-2 Overview of voltage sag studies (adopted from [11]) .................................. 42
Table 2-3 Number and characteristics of generic distribution system components ...... 63
Table 3-1 Number of Voltage Measurement Devices Required to Record Voltage Sags
in the GDS ....................................................................................................................... 72
Table 3-2 Number of Voltage Measurement Devices Required for Full Sag-
Observability of the GDS Network Using the MRA Method ......................................... 74
Table 3-3 Number of Fault Location Estimates Determined Using Original MRA
Method and Enhanced MRA Algorithm (EMRAA) ....................................................... 84
Table 3-4 Inputs Randomly Generated During Monte Carlo Simulation (1000 trials)
and their Corresponding Probability Distributions ......................................................... 86
Table 4-1 Single monitors and pairs of monitors required to locate fault α .................. 92
Table 4-2 Compliance of monitoring solutions of the sample system of 4-bus system
(Figure 4-2) with generic linear constraints .................................................................... 97
Table 4-3 Optimal monitoring programs obtained with original and proposed
formulations for the sample system of Figure 4-3 .......................................................... 99
Table 4-4 Fault location estimates [from-bus, to-bus, mile] using voltage at buses 1, 3,
and 6 of the sample system of Figure 4-3 ....................................................................... 99
Table 4-5 Optimal pairs of monitor locations required for full observability of LL,
LLG and LLL faults in the IEEE 118-bus test system .................................................. 102
Table 4-6 Optimal monitor program to locate LG faults in the IEEE 118-bus test
system ............................................................................................................................ 103
Table 4-7 Optimal monitoring programs for locating all types of fault in the IEEE 118-
bus test system. (Complement to monitors fixed at buses 39, 41, 67, 84, 88, 93, 95, 97,
and 117) ......................................................................................................................... 104
9 |
Table 5-1 Number of Voltage Measurement Devices Required for Sag Detection in the
GDS Network ................................................................................................................ 110
Table 5-2 Number of Voltage Measurement Devices Required for Full Fault Location
Observability of the IEEE 118-bus Network ................................................................ 111
Table 5-3 Number of Voltage Measurement Devices Obtained by Three Different
Methods ......................................................................................................................... 114
Table 5-4 Monitor Placement for Fault Location in the 118-bus Network Utilizing
Greedy Algorithms ........................................................................................................ 115
Table 5-5 Minimum Number of Monitors Required for Fault Location in the 295-bus
GDS Network ................................................................................................................ 116
Table 5-6 Sag Magnitude Estimation Error of Each Phase for Line to Ground Faults
Occurring in the GDS Network..................................................................................... 119
Table 5-7 EN 50160 classification of voltage sags according to residual voltage and
duration (adopted from [112]) ....................................................................................... 123
Table 5-8 Fault clearing times in the GDS network ................................................... 124
Table 5-9 SARFI indices for three voltage levels in the GDS network ...................... 127
Table 5-10 Minimization of the Overall Sag Event Estimation Error in the GDS
Network with Greedy Monitor Placement .................................................................... 129
Table 6-1 Percentiles of the Absolute Values of the Imaginary Parts of Fault Location
Estimates ....................................................................................................................... 133
Table 6-2 Fault Location Estimates for a Line to Line to Ground Fault at 0.3636 on
Line 14 of the IEEE-RTS and the Corresponding Residual Voltages at Bus 12 .......... 134
Table 6-3 Ratio between Negative-Sequence and Zero-Sequence Residual Voltages at
Bus 12 for the Fault Location Estimates of Table 6-2 .................................................. 135
Table 6-4 Number of Voltage Measurement Devices Required for Distinct Functions
in the 295-bus GDS ....................................................................................................... 139
Table 6-5 System Fault Statistics (adopted from [90]) ............................................... 140
Table 6-6 Probability of Occurrence of Loading Profiles (adopted from [80]) .......... 140
Table 6-7 Difference between Estimated and Actual Number of Sag Events ............ 141
Table 6-8 Customer Plant Characteristics, adopted from [120] .................................. 144
10 |
Abstract
Title: Monitor Placement for Estimation of Voltage Sags in Power Systems
Mr. José Manuel Avendaño Mora, The University of Manchester, July 5th
2012.
Power quality related problems cause large financial losses in the order of billions
worldwide. The evaluation process aimed at determining effective remedial actions
starts with the correct identification and characterization of power quality disturbances.
Measurements performed in the electrical power network and the corresponding
collection and process of data are the primary method of characterization of the
phenomena. The ideal deployment of monitoring devices would entail a monitor
installed at each node of the network so that the power quality throughout the system
could be directly assessed. In reality, however, technical and mostly economical
constraints limit the number of monitors a network operator can install in the system.
Power quality at non-monitored sites, therefore, has to be estimated by extrapolating the
data from monitored sites. Consequently, it is crucial to identify the sites that provide
the most accurate picture of the system’s overall power quality. Unfortunately, no
recommended practices or guidelines for determining the minimum number and the best
locations for optimal power quality monitoring have been prescribed in standards or
reports. This thesis investigates voltage sag monitoring as part of a larger power quality
monitoring scheme. The aim is to develop a methodology for optimal monitor
placement for fault location and sag estimation. The thesis, divided in four main parts,
focuses on network sag performance estimation and optimal monitor placement for fault
localization and sag estimation. The introductory part of the thesis gives an overview of
power quality surveys conducted around the world in recent years with special emphasis
on the monitor placement criteria used. It also summarizes the main methods for
network sag performance estimation proposed to date. The main part of the thesis firstly
reviews the most referred optimal monitor placement method for sag estimation
proposed in academia, highlighting its limitations. Then a robust fault location
algorithm is proposed to enhance this method and overcome the identified limitations.
The enhanced method is thereafter used as the basis for the generalization of one of the
leading methods for optimal monitor placement for fault location in the second part of
the thesis. The formulation of its optimization problem is extended for application in
large power networks by adapting the modeling approach for the sag monitor placement
problem. To reduce the high computational and memory burden associated with finding
the optimal fault location monitor program, the thesis introduces a less memory
intensive heuristic search algorithm in the third part of the thesis. A series of custom
objective functions are proposed to be used with this algorithm to find optimal fault
location and sag monitoring programs aimed at estimating the most critical events for
customers. In the final part of the thesis, the main concepts and techniques introduced in
the first three sections are combined to develop a synergistic approach to optimal
monitor placement for sag characterization based on fault location. The suitability of the
new method for techno-economic assessment of voltage sags using strategically or
conventionally deployed monitors is established.
11 |
Declaration
No portion of the work referred to in the thesis has been submitted in support of an
application for another degree or qualification of this or any other university or other
institute of learning.
12 |
Copyright Statement
i. The author of this thesis (including any appendices and/or schedules to this
thesis) owns certain copyright or related rights in it (the “Copyright”) and s/he
has given The University of Manchester certain rights to use such Copyright,
including for administrative purposes.
ii. Copies of this thesis, either in full or in extracts and whether in hard or
electronic copy, may be made only in accordance with the Copyright, Designs
and Patents Act 1988 (as amended) and regulations issued under it or, where
appropriate, in accordance with licensing agreements which the University has
from time to time. This page must form part of any such copies made.
iii. The ownership of certain Copyright, patents, designs, trade marks and other
intellectual property (the “Intellectual Property”) and any reproductions of
copyright works in the thesis, for example graphs and tables (“Reproductions”),
which may be described in this thesis, may not be owned by the author and may
be owned by third parties. Such Intellectual Property and Reproductions cannot
and must not be made available for use without the prior written permission of
the owner(s) of the relevant Intellectual Property and/or Reproductions.
iv. Further information on the conditions under which disclosure, publication and
commercialisation of this thesis, the Copyright and any Intellectual Property
and/or Reproductions described in it may take place is available in the
University IP Policy (see http://documents.manchester.ac.uk/DocuInfo.aspx?
DocID=487), in any relevant Thesis restriction declarations deposited in the
University Library, The University Library‟s regulations (see
http://www.manchester.ac.uk/library/aboutus/regulations) and in The
University‟s policy on Presentation of Theses.
13 |
Acknowledgments
Firstly, I would like to acknowledge the financial support provided by the National
Council on Science and Technology (CONACYT), México, without which my research
and this thesis would not have been possible.
My deepest gratitude and recognition goes to my supervisor Prof. Jovica V. Milanović
for his expert technical guidance and encouragement throughout this process. He has
been a very special mentor and an inspiration to pursue professional excellence.
I would like to extend my appreciation to all my friends and colleagues of the Electrical
Energy and Power Systems research group for providing an excellent academic and
social environment for enjoying research. In particular, I wish to thank Mr. Alejandro
Martínez for his continuous help and advice on the issues faced in the research. Special
thanks to Mr. Nick Woolley, our collaboration was very productive and helpful for my
research. Many thanks to Mr. Muhammad Ali for his endless willingness to discuss and
help with my research problems. Special thanks must also go to Mr. Robin Preece who
has selflessly given up countless hours to discuss the research and correct my English.
The help provided by Dr. Jhan Yhee Chan throughout the research and particularly for
the last chapter of the thesis is very much appreciated.
I am very grateful to Dr. Miguel A. Ortega Vázquez and Dr. Ricardo Rubio Barros who
became my true friends and teachers during my time in Manchester.
I would also like to express my gratitude to Dr. Luis (Nando) Ochoa and Dr. Joseph
Mutale for their invaluable comments and discussions, which have contributed to the
enhancement of the work embodied in this thesis.
Lastly, but certainly not least, I am especially appreciative for the crucial mental and
moral support throughout the period of this research of my dear girlfriend, Maria
Kiousi. Σ’ ευχαριστώ πολύ αγάπη μου!
14 |
A mis padres,
Sandra Leticia Mora Robles y José Manuel Avendaño Reyes,
por su infinito amor e incondicional apoyo durante mi
intenso proceso educativo.
A mis abuelos,
Aurora Reyes de Avendaño, Ana Rosa Robles de Mora (†),
José Trinidad Mora Guzmán (†) y Manuel Edgar Avendaño
Sumano (†), cuyas vidas me han inspirado a la búsqueda
constante y permanente por ser un mejor ser humano.
(To my parents,
Sandra Leticia Mora Robles and José Manuel Avendaño
Reyes, for their endless love and unconditional support
during my intense educational process.
To my grandparents,
Aurora Reyes de Avendaño, Ana Rosa Robles de Mora (†),
José Trinidad Mora Guzmán (†) and Manuel Edgar
Avendaño Sumano (†), whose lives have inspired me in my
constant and permanent quest to be a better human being.)
Chapter 1 • Introduction
15 |
Chapter 1
Introduction
1.1 Power Quality
Power quality is the characteristic property that stems from the combination of voltage
quality and current quality. Voltage quality describes the significant deviation of the
actual voltage from a sine wave of statutory frequency and magnitude, whereas current
quality depicts the same for the current. Power quality related issues are of the most
concern for customers, and therefore a power quality problem is any unbalance or
deviation in frequency, current, or voltage that causes customer equipment to fail or
misoperate. The economic impact of power quality problems is the primary reason for
interest in power quality [1, 2].
The interest in power quality has increased from the early 1970’s mainly because the
economic losses from power quality phenomena have also risen steadily. Recent studies
estimate the annual power quality related losses at billions of funds for the European
Union and United States alone [3-5]. The key reason behind the rise in costs has been
the proliferation of electronic and power electronic equipment. Modern converter-driven
equipment (from consumer electronics and computers, up to adjustable-speed drives)
has become much more sensitive to voltage disturbances than their older
electromechanical counterparts and, paradoxically, it is a source of voltage disturbances
itself.
Other factors have contributed to the increase in engagement in power quality as well.
Notable among them are the growing need to agree on adequate standards that clearly
define performance criteria (especially in a deregulated electric industry), the higher
expectations of customers that see electricity as a rightful commodity that must be of
premium quality, and the advancement of monitoring technologies that enable obtaining
a very accurate picture of the power quality performance.
Chapter 1 • Introduction
16 |
The terms power quality phenomenon and power quality disturbance are synonyms of
deviations of the ideal voltage or current from their quasi-ideal waveforms. Power
quality phenomena can be broadly classified into two big groups: variations and events.
Current and voltage variations are moderate deviations of voltage or current from their
nominal or ideal values. Typical examples include variations in current magnitude,
voltage frequency, and voltage magnitude, harmonic current distortion, and harmonic
voltage distortion. Power quality events in contrast, are significant deviations of voltage
or current from their nominal or ideal wave shapes. Interruptions, undervoltages,
overvoltages, and fast voltage events (transients) are the most common events. The
characterization of both power quality events and variations requires monitoring of
current and or voltage signals.
Short-duration undervoltages known as voltage dips or voltage sags are generally
believed to be the most pressing power quality problem. It is the extensive disruption of
industrial processes caused by these disturbances and the corresponding economic
losses which have led to this view [4, 6-8]. This thesis focuses on the monitoring of
voltage sags.
1.2 Voltage sags
A voltage sag or dip is a decrease in root mean square (rms) voltage at the power
frequency for a duration of between half a cycle to one minute [9]. This reduction of the
rms value of the ac voltage is below a specified dip threshold and followed by its
recovery after a brief interval [10]. Several comprehensive power quality surveys
conducted as early as the 1970’s have reported the incidence of voltage sags to be close
to 65% of all recorded power quality phenomena [11]. Electrical equipment in
commercial and industrial facilities, like adjustable speed-drives, computers, contactors,
process-control equipment and relays, is often disrupted by voltage sags. The cost of
each of these disruptions has been estimated as high as €6 million/hour for the financial
sector and €3.8 million per disturbance for a semiconductor factory [12]. It can be seen
therefore that voltage sags are one of the most common and also most costly power
quality problems.
A general procedure to evaluate many power quality problems including voltage sags is
shown in Figure 1-1 [2]. Measurements are essential to characterize the problem at hand
or the overall power quality performance of the system. A range of potential solutions
Chapter 1 • Introduction
17 |
has to be identified at all levels of the system from utility supply to end-use sensitive
equipment. Possible solutions are then evaluated in terms of technical feasibility and
those considered viable are compared on an economic basis to determine the optimal
solution. Figure 1-1 highlights the stage of the power quality evaluation framework in
which this dissertation is concentrated, i.e., measurement/data collection, along with the
major considerations that must be addressed in this step; namely causes, characteristics,
consequences, and indices. All of these are described in the next section with the
emphasis on voltage sags.
Figure 1-1 Basic procedure to evaluate voltage sags, modified from [2]
1.2.1 Causes and Characteristics
Voltage sags are caused by increases in current magnitude mostly happening elsewhere
in the system, as illustrated in Figure 1-2, where a voltage drop occurs at the point of
common coupling (PCC) between the customer and the source of the increase in
current. The main causes for a temporary increase of current are short circuit faults,
starting of induction motors, and energizing of transformers. However, the majority of
power quality literature has focused on voltage sags induced by faults since these sags
lead to most of the equipment malfunctions. In this dissertation too, only sags caused by
faults have been considered.
Voltage magnitude
variation
Voltage sags Interruptions TransientsHarmonic
distortion
Measurements/data collection
Causes and characteristics
Consequences
Utility
transmission
system
Utility
distribution
system
End-use
customer
interface
End-use
customer
system
Equipment
design/
specifications
Modeling/analysis procedures Evaluate technical alternatives
Evaluate economics of possible solutions
Identify problem category
Problem characterization
Identify range of solutions
Evaluate solutions
Optimum solution
Power Quality Problem Evaluation
Indices
Chapter 1 • Introduction
18 |
Figure 1-2 Origin of voltage sags.
The only two sag characteristics defined by IEC 61000-4-30 [13] are residual voltage
and duration. The residual voltage is the lowest rms voltage measured once per cycle in
any of the voltage channels during the event. A voltage channel can be one, two, or
three phase-to-phase, phase-to-neutral or phase-to-ground voltages. The duration is the
time during which the one-cycle rms voltage at any voltage channel is below a voltage
dip (sag) threshold. Although it is not prescribed in the standard the most common
voltage sag threshold is 90% of the nominal voltage.
An example of a voltage sag caused by a fault at 132 kV and measured at 11 kV is
illustrated in Figure 1-3 to Figure 1-5. Figure 1-3 shows the voltage waveforms for the
three phases with voltages in per unit. The rms voltage versus time for the sag is plotted
in Figure 1-4 showing the residual voltage of the event and its duration for a threshold
of 90%. Figure 1-5 plots the duration as a function of the threshold, for the three phases.
Since the residual voltage in one of the phases is 88% any voltage threshold setting
below 88% results in duration of zero cycles for that phase. The sag duration for the
other two phases is approximately 4 cycles using a voltage threshold of 90%.
Residual voltage and duration are the most widely used characteristics to describe
voltage sags but not the only ones. Other characteristics like phase-angle jump, point on
wave, sag energy and three-phase characteristics have been introduced in the literature
to complement the description of load behavior during voltage sags [14]. The phase-
angle jump is the difference in voltage phase angle between the pre-sag voltage and the
voltage during the sag. The point-on-wave of sag initiation and point-on-wave of
voltage recovery are used to identify more accurately the phase angle at which the
voltage sag starts and the phase angle at which the voltage recovers, respectively. The
voltage sag-energy is a measure of the non-delivered energy to an impedance load that
merges both residual voltage and duration.
Transmission system
Customer experiencing
voltage sag
Short circuit faults
Starting of induction motors
Energizing of transformersIncrease
in current
PCC
Chapter 1 • Introduction
19 |
Figure 1-3 Measured voltage sag due to a short circuit fault, voltage in three phases in time domain
(reproduced from [1]).
Figure 1-4 Rms voltages for the sag shown in Figure 1-3 (reproduced from [1]).
Figure 1-5 Sag duration as a function of the voltage threshold for the three phases of the sag shown in
Figure 1-3 (reproduced from [1]).
The three-phase characteristics of voltage sags are described through a classification
method proposed in [15]. This classification is summarized in Figure 1-6. The types A,
C and D are the base of the classification, corresponding to an equal drop in amplitude
in three phases, a drop in two phases, and a drop in one phase only, respectively. The
propagation of all types of sags (7 types) to lower voltage levels through transformers
with different winding connections is summarized in Table 1-1. Detailed description of
all sag characteristics can be found in [1, 16-18].
Table 1-1 Transformation of sag type to lower voltage levels (adopted from [1])
Transformer connection Sag on primary side
Type A Type B Type C Type D Type E Type F Type G
YNyn A B C D E F G
Yy, Dd, Dz A D C D G F G
Yd, Dy, Yz A C D C F G F
0 2 4 6 8 10 12 14 16
-1
-0.8
-0.6
-0.4
-0.2
0
0.2
0.4
0.6
0.8
1
Time in cycles
Voltag
e in p
.u.
4 5 6 7 8 9 10 11 12
0.55
0.6
0.65
0.7
0.75
0.8
0.85
0.9
0.95
1
1.05
Time in cycles
RM
S v
oltag
e in p
u
Sag magnitude or residual voltage
Sag duration
0.8 0.82 0.84 0.86 0.88 0.9 0.92 0.94 0.96 0.98 10
2
4
6
8
10
12
Threshold in p.u.
Estim
ate
d s
ag d
ura
tion (
cycle
s)
Chapter 1 • Introduction
20 |
Figure 1-6 Types of voltage sags in phasor-diagram form.
1.2.2 Consequences
The majority of voltage sags caused by faults have adverse consequences on the utility
system and ultimately on the end–user side. The reduction in voltage experienced
during a voltage sag abates the energy-transfer capability of the system, limits the fault-
clearing time in transmission systems or results in tripping of embedded generation
from the grid [11]. On the customer side, the main consequence of voltage sags is the
misoperation of sensitive equipment. Many modern devices like computers, process
controllers, and adjustable-speed drives experience operational problems when the
voltage drops below 85% for more than 40 ms [11]. Equipment sensitivity to voltage
sags varies according to load type, control settings, and applications. Equipment
immunity to voltage sags is represented by the sag characteristics that influence the
behavior of the equipment (the most commonly used are residual voltage and duration).
The sag characteristics that affect different equipment are shown in Table 1-2.
Table 1-2 Impact of sag characteristics on equipment immunity (adopted from [19]
Equipment Sag
Magnitude
Sag
Duration
Point on
wave
Phase-angle
jump Types A-G
AC Contactors
DC Contactors
Induction Motor
AC Adjustable Speed Drives
DC Adjustable Speed Drives
Personal Computers
Programmable Logic
Controller
Type A
Type B Type C Type D
Type E Type F Type G
Sags caused by three-phase faults
Sags caused by single line-to-ground and line-to-line faults
Sags caused by double line-to-ground faults
Chapter 1 • Introduction
21 |
The trip of equipment at industrial installations can lead to process disruption depending
on process immunity time (PIT). PIT is the maximum time a process could continue
operating after its equipment has tripped due to a sag [20]. When process disruptions do
occur they can entail substantial economic losses as shown in Table 1-3.
Table 1-3 Economic consequences of voltage sags (adopted from [12])
Industry Typical financial loss per event €
Computer centre 750 000
Financial trading 6 000 000 per hour
Glass industry 250 000
Semiconductor production 3 800 000
Steel works 350 000
Telecommunications 30 000 per minute
1.2.3 Indices
The aim of voltage-sag indices is to describe the performance of the power system
through a limited number of parameters [21]. This description is usually given by means
of averages and distributions over time and space. The IEEE 1564 Task Force, currently
working towards the creation of the IEEE Guide for Voltage Sag Indices, proposes the
following five-step procedure to quantify the sag performance of a power system [21]:
1. Obtain sampled voltages with a certain sampling rate and resolution.
2. Calculate characteristics as a function of time from the sampled voltages.
3. Calculate single-event characteristics from the characteristics as a function of
time.
4. Calculate site indices from the single-event characteristics of all events
measured during a certain period of time.
5. Calculate system indices from the site indices for all sites within a certain power
system.
The first step when calculating voltage-sag indices is to obtain sampled voltage
waveforms, typically for the three phases. In most cases the equipment used for
monitoring the harmonic spectrum will also be used for monitoring voltage sags. These
monitoring devices have typical sampling rates of 128 or 256 samples per cycle, which
exceed the sampling requirements for calculating sag indices.
The second step consists of calculating one or more characteristics from the voltages
sampled in step one as a function of time for each event recorded. The event can be
characterized by the rms voltage, the peak voltage or the amplitude of the fundamental
Chapter 1 • Introduction
22 |
voltage component. Most equipment uses the rms voltage as a function of time as the
only event characteristic.
In the third step the retained voltage and the duration of the event are calculated. The
duration is the time the rms voltage stays below the threshold and the retained voltage is
the lowest rms voltage during the event. Recommended threshold values are in the
range 85-90% of the voltage reference for troubleshooting or statistical applications, and
70% for contractual applications [13].
The fourth step is quantifying the sag performance of each monitored site through one
or more site indices. Site indices typically give the frequency for events with given
values of residual voltage and duration. A commonly used method of presenting the
performance is by means of a voltage sag table whose cells are given by the division of
the residual voltage and duration ranges into a small number of intervals. The choice of
the magnitude and duration ranges is a point of discussion and different publications use
different values. Table 1-4 is the voltage sag table proposed in IEC technical report
61000-2-8 [10]. Tables with different resolutions in the duration and residual voltages
ranges are proposed in [22] and used in [23].
An alternative and widely used approach to counting voltage sags is the system average
rms frequency index (SARFI). The SARFI index was originally proposed in [24] and is
recommended by standard-setting organizations (CIGRE, CIRED, IEEE) in [25] and
[26]. The SARFIX index gives the number of events per year with duration of up to 1
minute and a residual voltage less than X%. For instance, SARFI80 gives the number of
events with residual voltage less than 80% as highlighted in Table 1-4. The SARFICURVE
index (where “CURVE” is the name of a predefined immunity curve) gives the annual
number of events below the predefined curve. For example SARFISEMI gives the
number of events more severe than the SEMI curve [27]. Although the index refers to
system average it can be used to quantify the occurrence of sags at a single site.
The fifth and final step of the procedure to quantify the system sag performance is to
calculate the system indices from the site indices from all the monitored sites. The
system indices are usually the same as the site indices but with typically lower level of
detail. System indices can be calculated either from the average of the site indices or
from the value not exceeded by a high-percentile of monitored sites, e.g. 95%.
A full description of the calculation of sag indices and others reporting methods can be
found among others, in [1], [14], [21], [25] and [26].
Chapter 1 • Introduction
23 |
Table 1-4 Voltage sag table recommended by IEC 61000-2-8 and range of SARFI80 index
1 cycle-0.1 s 0.1-0.25 s 0.25-0.5 s 0.5-1 s 1-3 s 3-20 s 20-60 s 1-3 min
80-90%
70-80% SARFI80
60-70%
50-60%
40-50%
30-40%
20-30%
10-20%
<10%
1.2.4 Monitoring
The overview of the main aspects of voltage sags presented above shows that
monitoring plays an absolutely crucial role in the assessment of voltage sags. It is
through monitoring that the causes of sags can be discerned and their characteristics
defined, so that the possible consequences are estimated. Monitoring of voltage sags is
also the main source of data for calculating sag indices. As previously stated, sag
monitoring is the central topic within the scope of this investigation. A general summary
of the monitoring aspects most relevant to this thesis is given next.
First, two types of power quality monitoring should be distinguished [1, 2]:
On-site monitoring, aimed at assessing the power quality at particular sites.
Reasons for this type of monitoring include characterization of specific problems
and verification of compliance of power quality contracts. Only one monitoring
device installed at the site of interest is required.
System-level monitoring, intended to estimate the overall power quality of the
entire system. This approach requires monitoring usually at a large number of
sites and estimating the voltages at sites without monitors, i.e. power quality
state estimation (PQSE).
Monitoring of voltage sags at system level is the factual framework for this research and
therefore only this approach will be discussed further. The main aspects that need to be
considered when executing a system-wide sag monitoring campaign are:
Monitor placement. Ideally, monitors would be placed at all locations
throughout the system to completely understand the overall power quality. Such
deployment of monitors however may be unaffordable and the challenges related
to data management, analysis, and interpretation can be significant.
Nevertheless, full coverage is usually not required since measurements from
several strategic locations can be used to characterize the sag performance of the
Chapter 1 • Introduction
24 |
whole system. Hence careful selection of monitoring locations based on
monitoring objectives is of paramount importance. By recognizing the most
important influencing factors and considering site categorization it should be
possible to install monitors in a targeted way such that full coverage of the
network is achieved. The sag data from monitored sites can then be mapped on
to non-monitored sites and verified based on known faults statistics [2], [25],
[26].
Estimation of sags at non-monitored sites. It was stated before that the main
cause of voltage sags is short-circuit faults. With this in mind, the procedure to
estimate sags at sites without monitors involves finding a fault location that
produces voltages and currents that most closely match the measurements from
the few available monitors [2].
Monitor connection. Voltage sag statistics in three-phase systems can be
collected through monitors connected phase-to-phase or phase-to-ground. Power
quality monitoring standards do not prescribe a monitor connection. However, a
joint report from CIGRE and CIRED recommends the use of phase-to-phase
voltages for system indices derived from monitoring HV and EHV sites because
they give a better indication of the voltage experienced by the end-user
equipment than phase-to-ground voltages [25]. If monitors are connected phase-
to-ground, methods like the one proposed in [28] can be used to estimate the
phase-to-phase rms voltages from phase-to-neutral voltages.
The main facets of the sag monitoring in power systems discussed above are addressed
by this thesis. An overview of these aspects is presented in following sections.
1.3 Literature review
1.3.1 Monitor Placement for Sag Performance Assessment
Monitoring the electrical environment of power systems is the best way to assess
voltage sag performance [1, 2, 29]. Two streams of monitor placement for sag
characterization can be distinguished: the selection of monitoring locations adopted in
practice to undertake power quality surveys, and the optimal monitor placement
proposed in academia. Both approaches are discussed further in this section.
Chapter 1 • Introduction
25 |
1.3.1.1 Power Quality Surveys
In recent years, several monitoring programs have been performed with the main
objective of assessing the overall power quality of power systems at different voltage
levels. The power quality disturbances considered in these surveys include voltage sags.
The results of a four year power quality monitoring program conducted by the National
Power Laboratory (NPL) are analyzed in [30]. The monitored area covered 112
locations in USA and Canada. Single phase, line-to-neutral voltages were recorded at
standard wall receptacles. The wide statistical variation of the data collected hindered
the definition of a typical site representing the overall power quality of the power
system.
The difficulty in utilizing data from monitoring programs to estimate the expected
electrical environment is also reported in [31], where a comparison was carried out
between the monitoring results of the NPL survey and the data from two additional
monitoring programs, one conducted by the Canadian Electrical Association (CEA) and
one by the Electric Power Research Institute (EPRI). The CEA survey was conducted
with the participation of twenty-two utilities throughout Canada. In this survey, 550
sites were monitored for 25 days each. Residential, commercial, and industrial customer
sites were monitored at the PCC. Only line-to-neutral voltages were monitored (120 V
or 347 V). The EPRI survey lasted for more than 2 years, and around 50 GB of power
quality data was obtained. The survey was performed in distribution systems with
voltages ratings from 4.16 kV to 34.5 kV supplying residential, commercial, and
industrial customers. Monitors were placed at substations and along three-phase
sections of feeders.
The data from the power quality surveys conducted in North America by the NPL, the
CEA, and the EPRI showed that voltage sags occur more frequently at the point of use
than at the substation or on the utility distribution feeders. It also demonstrated that
most of the sags had a voltage magnitude between 80% and 90% while the most severe
sags were the fewest recorded. Although the surveys’ data were combined to obtain the
range of sag events that might be expected at the majority of locations, it was pointed
out that there is a difficulty in doing so due to the differences in the recording and
classification of sags by each brand of monitor, the voltage threshold settings used in
each survey, the monitored locations, and the sources and propagation characteristics of
sags.
Chapter 1 • Introduction
26 |
The voltage sag data of the EPRI survey was briefly compared against two European
power quality surveys in [32]. One of the European surveys was performed in nine
countries by the Distribution Study Committee of Eurelectric (formerly UNIPEDE),
which collected statistical data based on over 80 years from 85 monitoring locations on
medium voltage networks. The second survey was performed by the Norwegian Electric
Power Research Institute (EFI) by monitoring 400 sites in Norway. The examination of
the similarities of the data shows that the vast majority of the registered events were less
than 1 second in duration and had magnitude between 70% and 90%.
The need for long monitoring periods is evidenced in [33] and [34], where data from
short-term monitoring programs and for single monitoring points is considered. In [33],
monitoring data from a period of eight months in three locations is presented, while in
[34] the results of voltage sag measurements in two industrial facilities for a period of
17 months are studied. It can be deduced from both, that short monitoring periods are
generally insufficient to obtain accurate sag performance data.
The surveys discussed above are by no means the only ones conducted in recent years
but they were the ones for which detailed results were available and comparable.
Although it is difficult to establish the typical duration of the monitoring surveys
examined since it ranges from few months to several decades, an average duration of
2.4 years is calculated neglecting the 80 year survey performed by Eurelectric.
Significant efforts in surveying power quality are also evidenced in the latest (2011)
Benchmarking Report on the Quality of Electricity Supply of the Council of European
Energy Regulators (CEER) [35]. Table 1-5 shows the number of measurement devices
currently installed at different voltage levels in 14 European countries. It can be seen
from this table that the largest number of monitors is deployed in France whereas Latvia
and The Netherlands report less than 30 monitors installed. In no instance, however, is
an optimal deployment strategy reported in [35].
In summary, it can be said that monitoring programs require significant investment in
measurement equipment and in data collection and processing. The latter must be
automated in order to maintain reliable statistics on voltage sags [36]. Moreover, the
requirement for high accuracy of monitoring data may necessitate long monitoring
periods, typically several years [1].
Chapter 1 • Introduction
27 |
Table 1-5 Number of monitors at different voltage levels in current European monitoring systems
(adopted from [35])
Country Period of
monitoring since
Number of measuring units installed
EHV / HV MV LV Total
Austria April 2011 299 299
Bulgaria June 2010 495 1 372 1 867
Cyprus Distribution: 2000
Transmission: 2010
Czech Republic 2006 160 694 14 525 15 379
France EHV and HV: 1998
MV: not available
LV: March 2010
208 30 000 250 000 280 208
Greece March 2008 500 500
Hungary 2004 157 585 742
Italy 2006 165 600 (Through smart meters) 765
Latvia 1999 20 20
The Netherlands EHV and HV: 2004
For all DSOs: 1996 28 60
† 60
† 28
Norway 2006
Portugal 53 101 166 320
Romania 2008 22 130 152
Slovenia 2004 183 183 366 † Number of measurement periods with duration of one week being performed with several measuring
instruments per year.
Alternatively, the assessment of voltage sag performance can be done stochastically by
computer simulations. This option is more appropriate to estimate the expected voltage
sag performance of systems in planning stage considering different operating scenarios,
generator scheduling and loading profiles [29], [37]. In addition, the accuracy of the
stochastic approaches is not subject to long monitoring periods.
1.3.1.2 Optimal Monitor Placement for Sag Estimation
As stated previously, monitoring of the power supply can provide a direct assessment of
the voltage sag performance of the monitored site. However, since it might be
economically unfeasible to monitor the whole power system, only a limited number of
monitors can be located in a network. Therefore, it is necessary to determine the
minimum number of monitors and their best possible locations that lead to an accurate
description of the system sag performance. Few methods have been published for the
optimal allocation of power quality monitors aimed at maximizing the observability of
voltage sags. These are discussed next.
The monitor reach area (MRA) is defined in [38] as the area of the network for which a
monitor is able to capture voltage sags of a given magnitude. This area includes all the
points where the occurrence of faults will cause sags more severe than a given
threshold. Building the monitor reach area for all buses in the system allow us to find
the minimum number of monitors subject to complete observability of voltage sags. In
Chapter 1 • Introduction
28 |
[39] the optimal set of monitors is used to identify accurately the average sag
performance of the network and multiple solutions for the optimization problem are
explored through a genetic algorithm. However, in reported studies only symmetrical
faults at buses were considered.
The MRA-based method is extended in [40] to consider unsymmetrical faults and faults
along lines. The analytical formulae derived in [41] are used to calculate the residual
voltage caused by any type of fault at both buses and lines. The optimal placement of
monitors is carried out utilizing both analytical expressions and the fault positions
method [41]. The study indicates that only the method based on analytical expressions
assures the complete observability of voltage sags in the network.
Although the algorithm introduced in [42] was not strictly developed for optimal
monitoring of sags it is very similar to the MRA-based method. It incorporates the cost
associated with the monitoring system and ranks the monitoring programs based on data
redundancy.
1.3.1.3 Optimal Monitor Placement for Fault Location
Since the voltage sags caused by short-circuit faults are of the most concern any monitor
placement methods whose objective is the localization of faults could lead to an
improvement in sag estimation accuracy. The most relevant approaches proposed to
date for monitor placement for fault location are discussed separately in the section
reviewing monitor placement for sag estimation.
A technique for optimal allocation of fault indicators on distribution feeders to reduce
the number of potential fault location estimates is proposed in [43]. Two additional
objective functions namely, minimization of the distance between fault location
estimates and prioritization of buses based on critical customers, are incorporated in
[44] to develop a method for optimal placement of fault indicators in distribution
networks. In both approaches the optimization problems are solved using a genetic
algorithm.
In terms of measurement devices, the relatively recent developments and investments in
the synchrophasor technology have influenced investigations on optimal monitor
placement for fault location. A deterministic allocation method is proposed in [45] to
determine optimal sets of phasor measurement units (PMU) that maximize the accuracy
of localization of single line to ground faults. Single line to ground, line to line, and
Chapter 1 • Introduction
29 |
three-phase faults are taken into account in the development of a stochastic model for
optimal PMU placement for fault location in [46]. These two methods obtain optimal
sets of PMUs using metaheuristic search algorithms but require the user to define the
number of PMUs available. The performance of both approaches for faults occurring at
points other than buses is not presented.
A three step PMU placement procedure is described in [47] to achieve fault location
observability in transmission networks. The first step consists of placing PMUs on
buses with the highest number of incident branches. Secondly, PMUs are positioned so
that every two devices are spaced by one bus. During the final step, redundant PMUs
are eliminated until the one-bus-spaced criterion is violated. The deployment strategy is
therefore, pretty involved (“manual” to a certain extent) and might be cumbersome for
application in large systems.
The one-bus-spaced deployment strategy is also implemented in [48] and [49] to
minimize the number of PMUs while preserving fault location observability. In these
two methods the optimization problem is formulated as an integer programming
problem following the modeling approach of [50] and solved using a branch and bound
algorithm [48] and a genetic algorithm [49]. However, it is argued in [51] that the
method proposed in [48] and [49] is not complete and might provide incorrect results.
The optimal PMU placement for fault location is also modeled in [51] as an integer
linear programming problem. The work was extended to include zero injection buses in
the formulation, as it was shown this can reduce the total number of PMUs required.
The requisite of placing PMUs on terminal buses to maintain fault observability under
faulted conditions is demonstrated in [52], where the PMU placement is optimized in
conjunction with the placement of conventional power flow measurements.
The methods proposed in [47]-[49], [51], and [52] determine the optimal placement of
PMUs so that a two-terminal fault location algorithm like the one described in [47] can
be applied to all lines of the network. This algorithm requires synchronized
measurements of the voltage phasor at both ends of the faulted line and the current at
any end of the line to determine the fault location.
An alternative and more comprehensive method is the one proposed in [53]. This
method determines the minimum number of monitors and identifies the best locations
for installing not only PMUs but any other device with voltage measurement
capabilities, such as power quality monitors or digital fault recorders, in order to
Chapter 1 • Introduction
30 |
uniquely locate every fault occurring throughout the network. Since the one-terminal
fault location algorithm employed in [53] relies on only one voltage measurement (that
can be distant from the fault location) and no current measurements, a reduction in the
total number of measurement devices can be expected. This method is similar to, and
uses the same data as, the MRA-based method. In theory, the two methods should
provide the same sag estimation results. The method presented in [53] however has only
been tested in a simple 10-bus system and a generalized formulation applicable to an
arbitrary system is still missing.
1.3.2 Sag Performance Estimation
Stochastic estimation methods calculate the number and characteristics of voltage sags
of a single site or an entire power system based on the network model and the fault
statistics data of the system. The accuracy of these methods relies on the correctness of
the models employed and the knowledge of the number and characteristics of faults in
the system. Several methods have been proposed in the past for the stochastic estimation
of voltage sags. These methods will be reviewed next.
1.3.2.1 The method of critical distances
This method determines the exposed area, or area of vulnerability, for a given voltage
sag magnitude. The exposed area of a sensitive load is the part of the system where a
fault can produce a sag of critical magnitude for the load of interest. The expected
number of voltage sags is obtained by adding the expected number of faults within the
exposed area [54],[55], [56]. Since the expressions used by this method are based on a
simple voltage divider model of a radial feeder, the applicability of the method is
limited to radial systems. Although expressions for non-radial systems have been
derived their implementation is rather complex [54], [57].
1.3.2.2 The method of fault positions
This method determines the voltage sag magnitude at all, or selected, buses in the
network for faults occurring in previously selected fault positions. For each fault
position the sag magnitude at the point of interest is calculated for balanced and
unbalanced faults. Since faults can occur throughout the power system, fault positions
are randomly distributed and a fault rate is assigned to each position. The accuracy of
Chapter 1 • Introduction
31 |
this method is directly proportional to the number of fault positions, i.e., the higher the
number of fault positions, the more accurate the estimation[58], [59], [60],[61].
Monte Carlo based approaches can be seen as a variation of the method of fault
positions [62]. In the Monte Carlo method, random variables such as fault location, fault
resistance, fault duration and fault type are iteratively calculated according to their
statistical distributions every time a simulation is performed [63].
1.3.2.3 Analytical approaches to the method of fault positions
These approaches are based on the algebraic description of the residual voltage at a
given bus when a fault location moves along a line. In other words, the residual voltage
at an observation bus is expressed as a function of the position of a moving fault node
providing a deterministic relation between two stochastic variables: 1) fault position and
2) residual voltage. Firstly, in [64] the probability density function (PDF) of voltage
sags as a function of fault distributions on transmission lines is calculated. Probability
density functions can be used to predict the number of voltage sags, and to analyze the
influence of generation scheduling and fault distributions of lines. The study shows
variations in the sag incidence due to different generation patterns and multiple fault
distributions. The main limit of this method is that it was developed for symmetrical
faults only.
Similarly, in [65] the cumulative frequency function (CFF) of sags of a given voltage
magnitude is determined. The main reason to use cumulative frequency functions of
sags is that for a sensitive load it is necessary to estimate the number of sags with
voltage magnitude below a given threshold. Again only symmetrical faults were
addressed.
In [41] the previous analytical methods are extended for the estimation of voltage sags
due to symmetrical and unsymmetrical faults. The study reveals the better
computational efficiency of the analytical approach over the fault position method for
similar accuracy levels.
A different way to find critical points on lines is proposed in [66], where quadratic
interpolation and the secant method are used to find the exact points on lines where the
occurrence of a fault will lead to sags with a specific voltage magnitude at an
observation bus. The same method is used in [67] to determine the influence of
generation scheduling and time-varying fault rates in the stochastic estimation of
Chapter 1 • Introduction
32 |
voltage sags. The study shows that both factors strongly influence the estimation of
voltage sags.
1.3.2.4 Analytical approaches to the method of critical distances
Slight modifications or additions to the base method reported in [54] and
implementations in radial systems fall into this category. For example, in [68] the basic
principles of the method of critical distances are used to determine the areas of
vulnerability to voltage sags. Then, the reliability of the protection scheme in the
calculation of number of voltage sags is taken into account and finally the estimated
voltage sag performance is compared with tolerance curves of sensitive loads in order to
calculate the expected load trips.
Analytical expressions for the calculation of voltage sag magnitude considering the
effect of power transformers are derived in [69]. A comparison between the method of
critical distances, the method of fault positions, and Monte Carlo simulation shows that
a high number of fault positions and iterations are required to obtain results with
acceptable accuracy.
1.3.2.5 The voltage sag matrix method
The method proposed in [70] is based on a re-formulation of the bus impedance matrix.
Assuming limited phase angle differences among pre-fault voltages, pre-fault voltages
equal to 1 p. u., and neglecting the resistances of the network components, the voltage
sag at bus i, caused by the fault at bus j is given by the quotient of the transfer
impedance between the buses i and j and the driving-point impedance of the faulted
point j. The elements of the “voltage sag matrix” are these quotients for all the buses of
the network. In this way, the voltage sag matrix directly provides voltage drops in
percentage at each bus due to symmetrical faults in each bus of the network. The main
limitation of this method is that it is exclusively suitable under the aforementioned
assumptions.
A common feature of all the stochastic methods analyzed before is the use of fault
statistic data. Fault rates can be obtained from historical records for existing systems or
simply take theoretical values for research purposes. However, since the probability of
fault occurrence is strongly influenced by several factors such as weather conditions,
maintenance, tree trimming, etc., the fault rate for a given system can be considerably
different from one year to another [1], [71]. In this respect, stochastic methods are
Chapter 1 • Introduction
33 |
suitable only for long term estimations because the estimation of voltage sags for a
specific year can differ significantly from the sags measured by power quality monitors
[72]. The estimation of stochastic methods can be improved by tuning them using
monitoring data [73], [74]. The next section discusses voltage sag estimation
approaches that combine power quality monitoring data and statistical prediction
techniques.
1.3.3 Voltage Sag State Estimation
Monitoring of the power supply can provide a direct assessment of the sag performance
of the monitored site. However, since it is economically unfeasible to monitor the whole
power system, only a limited number of monitors can be located in a network. This
leads to the problem of voltage sag estimation at non-monitored buses.
Voltage sag state estimation (VSSE) techniques have been proposed to circumvent this
obstacle. These approaches are based on estimating the voltage sag frequency at non-
monitored buses by using the data collected at a limited number of metering points [72].
In recent years, interest in voltage sag state estimation has emerged, especially on
distribution systems with radial topology.
The power quality state estimation (PQSE) process can be described as follows [75]: the
first step is the selection of a model that will be used to estimate the state of an entire
network based on a limited set of monitoring data. Differently from traditional power
system state estimation, in PQES there is a lack of redundant metering data. Once the
model is selected, the next steps are filtering the measured data, pre-processing the
measurements, and verification of system observability. The final step of PQES is the
model validation which implies testing the fitness of the predicted data to the observed
data. The absence of full state measurement is recognized as the most challenging issue
for PQES.
Two main groups of VSSE methods can be distinguished: methods for radial systems
and statistical methods. Both are discussed next.
1.3.3.1 Methods for Radial Systems
As its name suggest, these methods were specially developed for radial networks. They
take advantage of the monotonic form of the variation of the remaining voltage at an
observation bus with the distance of the fault. In other words, the voltage magnitude
Chapter 1 • Introduction
34 |
curve increases or decreases monotonically with fault distance. In short, these methods
try to fit the monotonic curve.
A voltage sag estimation algorithm for radial distribution feeders is proposed in [76].
This algorithm uses a limited number of voltage measurements to estimate the voltage
profile of a faulted feeder. It utilizes a least-square method to fit the trend followed by
the voltage along the fault path. Linear and 2nd
order equations for the voltage sag
magnitude are derived. These equations relate the sag magnitude at certain point to the
normalized feeder length. The study shows a sag state estimation error of less than
0.35%. However, improvement of the algorithm for robustness and efficiency and
verification with field data is suggested.
The method of disturbance circuit is introduced in [77] as another algorithm to estimate
the voltage sags of radial distribution systems with limited monitoring points. This
algorithm involves substituting the loads at buses along a radial feeder with equivalent
voltage disturbance sources in order to calculate the voltage sags in all the buses of the
feeder. The efficiency of the method was compared against the efficiency of the method
proposed in [76]. The mean square error between simulated and estimated values was
1.76%. Although the error is greater than the error in [76], it is still negligible and the
results were obtained with 70% fewer monitors.
Similar work to that presented in [76] and [77] is performed in [78]. The authors’
approach to voltage sag estimation is based on the distribution system model and the
Kalman filter algorithm. The latter is used as estimation technique to obtain the voltage
profiles of a radial feeder based on limited metering points. The estimation error
between the estimated values and the simulated values is less than 0.0011%, which is
considerably less than those incurred in [79] and [76], although the number of monitors
considered in the study is not specified.
1.3.3.2 Methods Based on Statistical Analysis of Monitoring Data
These methods develop models for the estimation of voltage sags based on statistical
analysis of monitoring data and system parameters. The models derived relate the
number of sags with certain characteristics (duration and magnitude) with system
characteristics such as length of feeders, transformers’ impedance; weather conditions;
and historical records of sags.
Chapter 1 • Introduction
35 |
A methodology to validate the voltage sag data derived from short monitoring periods is
proposed in [80]. The accuracy of the monitoring data is evaluated through a
comparison with simulated data. This involves calculating the confidence intervals for
the sag frequency found in simulation results. The measured sag frequency is
considered valid if it lies within the simulation confidence interval. Then, a sequence of
hypothesis tests is performed for monitoring and simulation data obtaining probability
values for each monitoring point. In order to validate the sag magnitude data of a
measured point, its probability value has to be greater than the adopted significance
level (α%) of the confidence intervals.
A multiple regression analysis is performed in [81] in order to find a relationship
between the expected number of sags at certain low voltage (LV) points and influencing
parameters from medium voltage (MV) and high voltage (HV) in Belgian systems.
Meteorological information and sag statistics collected from 18 HV substations (over 5
years) and from 15 MV substations (over 3 years) were used in the statistical analysis.
Regression models describing the relationship between the expected number of sags and
the aforementioned parameters were obtained. The results showed that for the case of 3
phase sags originating in the HV network, the most influential parameter is the altitude
of the substations. The incidence of 2 phase sags originating in the HV network is
affected by the altitude, the interconnection, and the lightning density. On the other
hand, the number of 3 phase sags in the MV network is mainly influenced by the short
circuit impedance of the substations.
An extensive statistical analysis of data from power quality studies is completed in [82]
to obtain models for the estimation of power quality disturbances. The analyzed data
was collected from 24 utility systems at 276 locations on 100 distribution feeders over a
27 month period. Further analysis of the data shows that the three strongest indicators of
voltage sags are circuit exposure, lightning, and a term involving transformer size and
number of feeders. Similarly to the work presented in [81], the authors employed
regression techniques to find a model to estimate the annual number of sags which will
fall under the lower ITIC curve. The fitness of the model may be considered fair, since
34% of the observed values are within 25% of the prediction intervals, and 60% of the
observed values are within 50% of the prediction intervals.
Chapter 1 • Introduction
36 |
1.3.4 Summary
Review of past research in the field identified several areas that need to be addressed.
These areas are summarized as follows:
The influence of fault impedance, fault location, pre-fault voltage (loading
conditions) on optimal monitor placement methods for sag estimation and fault
location has not been investigated. These factors could affect the number and
locations of monitoring devices deployed in the network.
The possibility of developing a unified approach to monitor placement for sag
estimation and fault location has not been explored. These two objectives have
been mainly treated separately and the synergy of both has not been fully
addressed.
Following the previous point, a monitor placement method for fault location that
could be combined with sag monitor placement lacks a generic formulation
applicable to any power system.
Existing methods proposed for optimal monitor placement for sag estimation
and fault location do not evaluate sub-optimal solutions or provide a ranking of
importance of monitoring locations.
Current monitor placement methods for sag estimation do not take into account
sag indices, immunity curves, or standards when determining optimal
monitoring locations.
The problem of optimal monitor placement for fault location is a non-
deterministic polynomial time-hard (NP-hard) problem, meaning that is not
possible to find an optimal solution in polynomial time. Alternative algorithms
for its solution have not been proposed.
1.4 Aims of Research
This research aims to address some of the issues that have not been satisfactorily
resolved in the past and to provide answers to the problems identified. The ultimate aim
is to establish comprehensive understanding of all relevant aspects involved in efficient
monitor placement for accurate voltage sag estimation at non-monitored sites, and to
propose a methodology for development of optimal sag monitoring programs. The main
aims of the research are therefore:
Chapter 1 • Introduction
37 |
1. To summarize existing methodologies for estimation of sag performance at non-
monitored sites using limited monitoring data.
2. To provide a critical overview of existing methodologies for optimal monitor
placement for voltage sag estimation and investigate potential ways of
improvement.
3. To develop a general approach to monitor placement for fault location in power
systems.
4. To develop a unified approach to monitor placement for estimation of sag
magnitude at all buses in the network and fault location.
5. To develop a methodology for choosing optimal sag monitoring programs in the
network.
6. To develop a flexible methodology for reliable estimation of voltage sags and
strategic monitor placement suitable for assessment of economic losses due to
sags.
1.5 Major Contributions of the Research
The research has contributed to the field of optimal monitor placement for voltage sag
estimation. These contributions are summarized next. (Paper numbers given in the
parentheses indicate that the related results are published or submitted for publication in
international journals or in proceedings of international conferences. A full list of thesis-
based publications is given in Appendix F).
The leading optimal monitor placement for voltage sag characterization, the
monitor reach area (MRA) method, was enhanced by incorporating a recently
proposed fault location algorithm. The limitations of the MRA were overcome
and the accuracy of sag estimation was increased without increasing the number
of monitors (F7, F9).
A generalized formulation for optimal monitor placement for fault location was
developed (F1, F2). The proposed formulation reduces significantly the number
of constraints of the problem.
The monitor location area (MLA) was designed to map the area of a power
network where combinations of monitors can determine the exact location of
faults (F1, F2).
Chapter 1 • Introduction
38 |
A series of heuristic (greedy) algorithms was developed to solve the problem of
optimal monitor placement for fault location and sag estimation with much
lesser computational burden (F7, F9, F11).
Custom objective functions for the monitor placement optimization process were
developed. These functions minimize the sag estimation error and maximize the
fault location observability (F7, F9, F11).
A new methodology for reliable estimation of voltage sags based on hybrid
monitor placement suitable for assessment of economic losses due to sags was
developed (F1).
The feasibility of assessment of financial losses due to voltage sags based on a
limited number of existing monitors in the network and optimally deployed
monitors was established (F6, F13).
1.6 Overview of the Thesis
The thesis is organized into seven chapters. This chapter, Chapter 1 , is the introductory
chapter. An outline of each of the remaining six chapters of the thesis follows.
Chapter 2 Modeling and Simulation Tools
In this chapter a summary of the existing methodology for voltage sag studies is
presented. The simulation and calculation methods along with the power system
component models used throughout this thesis are explained. The bus impedance matrix
building algorithm and the use of this matrix for fault analysis in power systems is
discussed thoroughly. The custom-made software employed to perform sag studies is
briefly commented on. The last part of this chapter introduces all the test systems on
which the thesis’ studies were performed.
Chapter 3 Optimal Monitor Placement for Voltage Sag Characterization
This chapter provides an overview of the first and still the most referred optimal
monitor placement method for voltage sag characterization, the MRA method. The
limitations of this method are highlighted through extensive simulations on IEEE and
generic systems. A recently proposed fault location algorithm that can be used to
overcome these limitations and enhance the robustness of the method is also reviewed
and discussed in this chapter. The improvement of the MRA method by incorporating
the aforesaid fault location algorithm is presented in the last section of this chapter.
Chapter 1 • Introduction
39 |
Chapter 4 Generalized Formulation of the Optimal Monitor Placement for Fault
Location
This chapter reviews an optimal monitor placement for fault location and extends and
generalizes its modeling approach. New sets of generic linear constraints for the
problem of optimal monitor placement are introduced so it can be solved by integer
linear programming. The novel concept of monitor location area is proposed also in this
chapter to facilitate the formulation of generic constraints. Simulation studies performed
in several test systems that validate the proposed formulation are shown in the last
section of the paper.
Chapter 5 Heuristic Approach for Determining Optimal Monitor Placement for
Voltage Sag Estimation
This chapter develops a heuristic methodology that finds optimal monitor placement
solutions with techniques considerably less computationally taxing than integer
programming. The methodology includes three custom objective functions formulated
for greedy monitor placement. Lastly, the proposed approach is used to determine a
range of monitoring programs for estimating sag performance in a generic distribution
network using different sag characteristics and sag benchmarking methodologies.
Chapter 6 Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring
Programs
This chapter develops a new methodology for monitoring and estimation of voltage sags
in power systems. The proposed methodology encompasses a hybrid monitor placement
method and a simplified technique for fault location that allows network sag
characterization. The sag monitoring schemes obtained with the proposed methodology
are then tested in two case studies utilizing Monte Carlo simulation. In the first case
study the characteristics of voltage sags are estimated to quantify the number of ITIC
and SARFI-90 events occurring in the network. In the second case study the financial
losses incurred by different sensitive customers due to voltage sags are assessed using a
risk-based methodology.
Chapter 7 Conclusions and Future Work
In this chapter the main conclusions of the research are discussed and suggestions are given
for future works and potential improvements on the methodologies developed.
Chapter 2 • Modeling and Simulation Tools
40 |
Chapter 2
Modeling and Simulation
Tools
This chapter describes the existing methodology for voltage sag studies including the
different types of simulations tools, calculation methods, sag studies, and solution
techniques. The simulation and calculation framework used throughout the thesis is
chosen from these groups, and the corresponding modeling requirements are discussed.
The models of the main power system components used in the thesis are also presented.
The building of the bus impedance matrix and its use for fault analysis in power systems
is explained in detail. The different test systems employed for all the studies carried out
in the thesis are also presented.
2.1 Simulation Tools for Voltage Sag Studies
Voltage sags can be calculated and analyzed utilizing two main types of simulation
tools: custom-made tools usually developed on commercial software platforms and
general purpose simulation packages, e.g. EMTP-like tools. The selection between these
two instruments depends on many factors including the study objectives, accuracy
required, and the user’s experience [11].
There are three main approaches to calculate the characteristics of voltage sags: fault-
current calculations, time-varying phasors, and time-domain calculations. Table 2-1
summarizes the voltage sag characteristics, modeling guidelines, and software tool
capabilities of each approach. Fault-current calculation is the simplest method but its
only output is residual voltage in steady-state. The method of time-varying phasors can
calculate the duration of sags by incorporating models of protective devices and
dynamic behavior of generators and control systems. Time-domain calculations can
Chapter 2 • Modeling and Simulation Tools
41 |
capture all voltage sag characteristics (magnitude, duration, phase angle jump, point of
wave) at the expense of more detailed models and the requirement for higher simulation
capabilities [11].
Table 2-1 Voltage sag calculation methodology (adopted from [11])
Calculation method Voltage sag
characteristics Modeling guidelines Software tool capabilities
Fault-current
calculations Retained voltage Steady-state models
Three-phase phasor calculations.
Models adequate for steady-state
calculations.
Time-varying
phasors
Retained voltage
and duration Steady-state models
Three-phase phasor calculations.
Models to reproduce the dynamic
behavior and the control systems of
generators.
Protective device models.
Time-domain
calculations All
Time-domain low-
frequency transient
models
Three-phase calculations.
Models to reproduce the transient
behavior of power components,
protective devices, and generators.
Options to capture voltage-sag
characteristics.
Load modeling options.
Frequency-domain and time-domain are the two basic solution techniques applied to
voltage sag calculations. In the frequency-domain, solutions are obtained using either
the bus admittance matrix or the bus impedance matrix. The bus impedance matrix is
preferred due to its suitability for calculating fault currents and residual voltages,
efficiency at determining sag magnitudes, and suitability for voltage sag propagation
studies [11].
Voltage sag studies can be classified according to their goals as: single-event
calculations, statistical simulations, sensitivity studies, or calculations of voltage sag
indices. Single-event calculations aim to characterize sags at particular buses. Statistical
simulations obtain the probability density function (PDF) of the sag characteristics and
the respective rate of occurrence. The goal of sensitivity studies is to determine the
effect of a system or fault parameter on voltage sag performance. Voltage sag indices
are used to quantify the sag performance of a single event, a site or a system. A
summary of the simulation tool capabilities required to obtain the aforesaid goals is
shown in Table 2-2. A fourth column has been included in this table to indicate the type
of voltage sag study performed in each chapter of this thesis. The results presented in
Chapter 3 to Chapter 6 of the thesis involve all types of voltage sag studies.
Chapter 2 • Modeling and Simulation Tools
42 |
Table 2-2 Overview of voltage sag studies (adopted from [11])
Study Goals Required capabilities
Chapters
of this
thesis
Single-event
calculations
Obtain some or all
characteristics of voltage sags
at buses of a power system
See Table 2-1 3,4
Stochastic
predictions
Obtain the PDF of some or all
characteristics of voltage sags
at buses of a power system.
Obtain the rate of occurrence
of different voltage sag
characteristics.
Capabilities shown in Table 2-1 plus
multiple run option (this should include
all options required to perform a Monte
Carlo solution) and post-processing
capabilities (i.e. those capabilities needed
to determine probability density functions
and rates of occurrence).
3,6
Sensitivity
analyses
Deduce the effect that some
system and fault parameter can
have on the voltage sag
performance; e.g. the number
of trips at a given load bus.
Capabilities shown in Table 2-1 plus
multiple run option and post-processing
capabilities. If the analysis is used to
obtain the sensitivity of a stochastic
assessment, then the options to perform
Monte Carlo method are also required.
3
Voltage dip
index
calculations
Obtain index values for either
sites or the entire system
Similar to those required for stochastic
predictions. 3, 5, 6
2.2 Modeling of System Components
The voltage sag characteristic most relevant to this research is the retained voltage at the
bus, i.e., the voltage sag magnitude. It was previously shown that fault-current
calculations in the frequency-domain using the bus impedance matrix are the most
suitable and efficient method when the goal is to obtain the retained voltage. Models
adequate for steady-state calculations are required by fault-current calculations. Steady-
state models can be obtained by converting system components into equivalent
resistance ( )R and reactance ( )X on common bases. The steady-state modeling of the
main system components, i.e. cables and lines, generators, loads, and transformers, is
described in this section.
2.2.1 Cables and Lines
The modeling of lines and cables of short and medium length using lumped parameters
is sufficiently accurate [83]. Shunt capacitance ( )C can be neglected in short lines and
cables and those of medium length can be modeled by the series resistance R and the
series reactance X for the total length of the line or cable, with half of the susceptance
for the total length lumped at each end of the equivalent circuit, as shown in Figure 2-1.
In terms of handling of capacitance, open-wire 60-Hz lines less than 80 km (50 mi) long
Chapter 2 • Modeling and Simulation Tools
43 |
are considered short lines. Lines having length between 80 km (50 mi) and 240 km (150
mi) are of medium length. Lines longer than 240 km (150 mi) require models based on
distributed parameters ( , , )R X C if a high degree of accuracy is required.
Figure 2-1 Lumped parameters model of cables and lines.
The positive- and negative-sequence series-impedance and shunt-capacitances of fully
transposed lines are equal. The zero-sequence impedance of overhead lines depends of
the existence of a return path provided by ground wires, tower footing resistance, and
grounding. The zero-sequence impedance value of lines is usually between two and six
times the value of the positive-sequence impedance [84].
2.2.2 Generators
After a fault occurs in a generator, the subtransient, transient, and steady state periods
are characterized by values in positive-sequence of the subtransient reactance dX , the
transient reactance dX , and the steady-state reactance dX , respectively. These
reactances have increasing values, i.e. d d dX X X and the corresponding fault
currents have decreasing values that is, f f fI I I . Subtransient reactances are
generally used to determine the initial current drawn by a short-circuit fault and
resistance is taken into account if greater accuracy is desired [83]. Values for the
negative- and zero-sequence impedances for synchronous machines are specified by
manufacturers based on test results. The negative-sequence is usually approximated to
half of the sum of the direct and the quadrature axis subtransient reactances [84]. A
practical approximation for short-circuit studies is to use a value for the zero-sequence
reactance of synchronous machines between 15% and 60% of the subtransient reactance
[85]. Generators have been modeled here as a constant driving voltage in series with
corresponding sequence resistances and subtransient reactances [86] as shown in Figure
2-2.
R jX
jB/2 jB/2
Chapter 2 • Modeling and Simulation Tools
44 |
Figure 2-2 Model of generators.
2.2.3 Loads
Several load models have been developed for voltage sag studies including constant
impedance, voltage dependant load, induction motor load, and hybrid load model. Load
modeling can be very important for some calculations, for example the calculation of
energy based voltage sag indices or when the interaction between a load and the system
during the fault that causes the voltage sag is of interest. However, load modeling is not
a critical issue in many other voltage sag studies, like fault-current calculations to
determine the retained voltage. For this application loads can be represented sufficiently
well as constant impedances and hence statics loads can be converted into equivalent
impedances with equal values of positive- and negative-sequence as shown in Figure
2-3.
Figure 2-3 Constant impedance load model.
The resistance R and the reactance X of the load are given by
2
*
VR jX
P jQ
(2.1)
where P , Q , and V are the active power (kW), reactive power (kVAr), and rated
voltage (kV) of the load, respectively, and the symbol *denotes the complex conjugate.
2.2.4 Transformers
Only voltage sags caused by faults are simulated throughout this thesis. Since in most
cases transformers do not saturate during the occurrence of fault-induced voltage sags a
R jXd//
E
Bus n
R jXd Bus n
Chapter 2 • Modeling and Simulation Tools
45 |
linear model can be used [87]. The sequence equivalent circuits of three-phase
transformers are determined by the connections of the primary and secondary windings.
Different connections of delta and wye windings defined the configurations of the zero-
sequence circuits and the phase shift in the positive- and negative-sequence circuits.
The equivalent circuit of an ideal transformer can be reduced to obtain the positive- and
negative-sequence equivalent circuits of the transformer by defining, with reference to
Figure 2-4, the following:
2
1 2R r a r (2.2) 2
1 2X x a x
(2.3)
where
a turns ratio;
1r ,1x winding resistance and leakage reactance of primary side;
2r ,2x winding resistance and leakage reactance of secondary side;
,R X resistance and reactance of equivalent circuit.
The parameters R and X are determined by the short-circuit test, in which impedance is
measured across the terminals of one winding when applying a short-circuit to the other
winding (usually the low-voltage side). Winding resistance is often omitted in the
transformer equivalent circuit since R is typically less than 1% [83]. The values of the
conductance cG and magnetizing susceptancemB can be calculated for the equivalent
circuit by an open-circuit test, which consists of applying rated voltage to the low-
voltage terminals of the transformer to measure the power input and currents. Both
parameters are very small (μS) and thus the exciting current is often neglected [83].
Positive- and negative-sequence impedances of a transformer are equal because it is a
static apparatus and the sequence impedances do not change with the phase sequence
when balanced voltages are applied to the terminals.
Figure 2-4 Transformer representation, (a) equivalent circuit with an ideal transformer and (b)
equivalent circuit with magnetizing current neglected (adopted from [83]).
r1 x1 a2x2 a2r2
Gc Bm
I1I2/a
a:1
V1
+
_
V2
+
_
I2
(a)
R jX
V1
+
_
V2
+
_
I1
(b)
Chapter 2 • Modeling and Simulation Tools
46 |
The zero-sequence impedance of a transformer can vary from a low value to an infinite
value depending on the transformer winding connection, method of neutral grounding
and the core construction [83]. The most common connections of two-winding
transformers and the respective zero-sequence equivalent circuits are summarized in
Figure 2-5. The arrows on the connection diagrams indicate the possible paths for the
flow of zero-sequence current. The absence of an arrow denotes that the transformer
connection lacks a flowing path for the zero-sequence current. The zero-sequence
equivalent circuits are approximations because winding resistance and the magnetizing-
susceptance have been neglected.
Figure 2-5 Zero-sequence equivalent circuits of five three-phase transformer banks and their respective
symbols and connection diagrams (adopted from [83]).
Figure 2-5 shows that delta and ungrounded wye windings impede the flow of zero-
sequence current by means of an open-circuit. In the presence of a path for the zero-
sequence current through at least one grounded wye winding, the total zero-sequence
impedance 0 3 3N nZ R jX Z Z when both the high-voltage and the low-voltage
windings are grounded and 0 3 NZ R jX Z if only the high-voltage side is
grounded.
P Q
P Q
P Q
P Q
P Q
N
ZN
P n
Zn
Q
N
ZN
P n Q
P Q
N
ZN
P Q
NP Q
QP Z0
Reference
QP Z0
Reference
QP Z0
Reference
QP Z0
Reference
QP Z0
Reference
Symbols Connection diagrams Zero-sequence equivalent circuits
Chapter 2 • Modeling and Simulation Tools
47 |
Almost all transformers in power systems feature taps on windings to vary the ratio of
transformation by changing tap position when the transformer in not energized [83].
However, load-tap-changing (LTC) transformers can automatically change taps while
the transformer is energized. The tap changing is operated by motors which respond to
relays responsible for maintaining the voltage within a prescribed band. Transformers
with off-nominal ratios can be represented by a π equivalent circuit according to the tap
ratio [85]. The π equivalent of a transformer connected between buses j and k with tap
ratio n :1 where n is variable, and impedance Z is shown in Figure 2-6.
Figure 2-6 Equivalent circuit for tap changing transformer (adopted from [85]).
Phase shift occurs in delta-wye transformers. Although practical systems are designed
with such phase shifts summing to zero around all loops, the calculation of
unsymmetrical faults might require taking into account the effects of phase shift. This
can be accomplished by advancing all positive-sequence voltages and current by 30°
when stepping up from the low-voltage side to the high-voltage side of a delta-wye or
wye-delta transformer [83].
2.3 Bus Impedance Matrix
The modeling of the main components of the typical power transmission network is
developed in previous sections. In this section a composite representation of the
interconnection and interaction of those components is formulated as a network model.
In the analysis of large power networks, the network model takes on the form of a
network matrix whose elements are determined by the relationship between the current
flow through a network component and the voltage drop across it. There are two types
of network matrices depending on the parameter used to relate the current flows to the
voltage drops: the bus admittance matrix and the bus impedance matrix. Both describe
the steady-state behavior of all the components acting together as a system and can be
obtained by nodal analysis of the network equations. The bus admittance matrix is
widely used for power-flow analysis whereas the bus impedance matrix is preferred for
power system fault analysis [83].
nZ
1
nZ
n
2
1
n Z
nVj
+
_
j
+
_
Vk
k
Chapter 2 • Modeling and Simulation Tools
48 |
By definition the bus impedance matrix is the inverse of the bus admittance matrix, that
is
1
bus bus
Z Y (2.4)
The standard form of the bus impedance matrix is illustrated below for a network with
three independent buses:
11 12 13
21 22 23
31 33 33
bus
Z Z Z
Z Z Z
Z Z Z
Z (2.5)
The bus impedance matrix is symmetrical around the principal diagonal. The elements
of busZ on the principal diagonal are called driving-point impedances of the buses and
the off-diagonal elements are called the transfer impedances of the buses. The bus
impedance matrix and can be obtained directly without inverting the bus admittance
matrix. For instance, starting with the bus equations expressed as
busV Z I (2.6)
where V and I are column vectors of the bus voltages and the currents entering the
buses from current sources. Expanding (2.6) for the network expressed by (2.5) results
in
1 11 1 12 2 13 3V Z I Z I Z I (2.7)
2 21 1 22 2 23 3V Z I Z I Z I
(2.8)
3 31 1 32 2 33 3V Z I Z I Z I
(2.9)
It can be seen from (2.7) that the driving point impedance of bus 1 is determined by
open-circuiting the current sources at buses 2 and 3 and by injecting the source current
1I at bus 1. Thus,
2 3
111
1 0I I
VZ
I
(2.10)
Transfer impedances can be obtained in a similar way. For example, (2.8) indicates that
if current sources 2I and 3I are open-circuited it is possible to determine the transfer
impedance of bus 1 and 2 as in (2.11).
Chapter 2 • Modeling and Simulation Tools
49 |
2 3
221
1 0I I
VZ
I
(2.11)
Equation (2.9) states that injecting a current into bus 3 with current sources at buses 1
and 2 open leaves impedance33Z as the only one through which
3I flows. Under the same
conditions, (2.7) and (2.8) show that 3I causes voltages at buses 1 and 2 expressed by
1 13 3V Z I
(2.12)
2 23 3V Z I
(2.13)
Once the bus impedance matrix has been built the Thévenin impedances at buses can be
readily obtained. The Thévenin impedance at bus k is given by
,th k kkZ Z (2.14)
where kkZ is the diagonal entry in row k and column k of
busZ . The Thévenin impedance
between bus j and bus k can be calculated as:
, 2th jk jj kk jkZ Z Z Z (2.15)
The analysis embodied in equations (2.6)-(2.15) shows that the change in voltage at a
bus can be approximated by the product of the current and the appropriate driving-point
or transfer impedance. A further approximation can be made by adding these estimates
to the original values to obtain the new voltages [83]. These approximations form the
basis for power system fault analysis, which is addressed in the next section.
It was previously stated that the bus impedance matrix can be constructed without
having to invert the bus admittance matrix. This is accomplished by the busZ building
algorithm. It starts by selecting a branch tied to the reference from a bus and adding to
this bus a second branch connected from a new bus. The outcome of the first step is a 2
by 2 bus impedance matrix. In the next step, a third branch connected to one or both of
the already chosen buses is added to expand both the evolving network and its bus
impedance matrix. This procedure is repeated until all branches of the physical network
have been incorporated into busZ [83].
Chapter 2 • Modeling and Simulation Tools
50 |
2.4 Fault Calculation Based on System Impedance
Matrix
Conceptually, a voltage sag is the change in voltage due to a change in current or
resistance as stated by Ohm’s law. Since power systems have non-zero impedances any
increase in current causes a reduction in voltage. In the vast majority of these reductions
however the voltage remains within statuary limits. The voltage reduction is
proportional to the current increment, and therefore short-circuit currents generally
cause a greater voltage drop than the starting current of induction motors, the inrush
current of transformer energizing, and overload currents. In practice, voltage sags
induced by short-circuit faults cause the most equipment trips and accordingly interest
has been focused on this type of sags [1]. The bus voltage changes, i.e., voltage sags or
voltage swells that occur in the system due to a fault are obtained from fault
calculations, which are discussed in this subsection.
The bus impedance matrix is most often used for fault analysis as equivalent circuits
based on its elements can simplify the calculation of currents and voltages throughout
the system upon the occurrence of a fault [83]. Both symmetrical and unsymmetrical
faults can be analyzed with this approach but the method of symmetrical components
must be used to handle the unbalanced currents caused by unsymmetrical faults. The
solution method is based on Thévenin’s theorem, which allows finding the fault current
by replacing the entire system with an equivalent circuit consisting of a single generator
and series impedance.
A simple power system has been used in [83] to derive general equations applicable to
any balanced system regardless of its complexity. The system contains three
synchronous machines, two are grounded through a reactance and the other one is not
grounded. These generators are connected through three-phase transformers to a
transmission line. The single-line diagram of the system, its sequence networks, and the
Thévenin equivalent circuits of the sequence networks are shown in Figure 2-7.
Generators are modeled by their subtransient internal voltages in series with their
subtransient reactances (since subtransient reactances of generators and motors are
generally used to calculate the initial current drawn by a short-circuit fault [83]). It is
assumed that a fault occurs at point P , which is identified as bus k in the single-line
diagram and in the sequence networks.
Chapter 2 • Modeling and Simulation Tools
51 |
Figure 2-7 Single line diagram of a three-phase system (a), the three sequence networks of the system
(b-d), and the Thévenin equivalent circuit of each network for a fault at point P , identified as bus k (e-g)
(adopted from [83]).
The negative-, positive-, and zero-sequence networks can be represented symbolically
by the bus impedance matrix as follows:
( ) ( ) ( ) ( )
11 12 1 1
( ) ( ) ( ) ( )
21 22 2 2
( )
( ) ( ) ( ) ( )
1 2
( ) ( ) ( ) ( )
1 2
s s s s
k N
s s s s
k N
s
bus s s s s
k k kk kN
s s s s
N N Nk NN
Z Z Z Z
Z Z Z Z
Z Z Z Z
Z Z Z Z
Z (2.16)
where s = 0, 1, or 2 indicates zero, positive, or negative sequence impedance values,
respectively.
Alternatively, each of the sequence networks can be also represented by its Thévenin
equivalent between any bus and the Reference node. For example, Figure 2-7 shows the
Thévenin equivalent circuit between the fault point P and the Reference node for each
sequence network. The voltage source in the positive-sequence network and its
k
P
+
_
+
_
+
_
k
P
Vf
+
_ Reference
Ifa(1)
k
P
Reference
Ifa(2)
+
_Vf
Zkk(1)
P
+
_
Ifa(1)
Vka(1)
k
Zkk(2)
P
+
_
Ifa(2)
Vka(2)
k
Zkk(0)
P
+
_
Ifa(0)
Vka(0)
k
(a) Single-line diagram of balanced three-phase system.
(b) Positive-sequence network.
(c) Negative-sequence network.
(d) Zero-sequence network.
(e) Thévenin equivalent of the
positive sequence network.
(f) Thévenin equivalent of the
negative sequence network.
(g) Thévenin equivalent of the
zero sequence network.
k
Reference
Ifa(0)
Chapter 2 • Modeling and Simulation Tools
52 |
Thévenin equivalent circuit is fV , the voltage to neutral at the fault point P (bus k )
before the occurrence of the fault. The absence of voltage sources in the negative- and
zero-sequence networks and their Thévenin equivalent circuits is explained by the
assumption that no negative- or zero-sequence currents flow before the fault occurs. The
Thévenin impedance existing between bus k (fault point P ) and the Reference node of
the negative-, positive-, and zero-sequence networks are (2)
kkZ , (1)
kkZ , and (0)
kkZ (diagonal
elements of (2)
busZ , (1)
busZ , and (0)
busZ ), respectively and their values depend on the values of
the reactances used in the network.
Let faI be the current of phase a flowing out from the original balanced system into the
fault. As can be seen in Figure 2-7 the symmetrical components of faI , that is
(0)
faI , (1)
faI ,
and (2)
faI , are being drawn out of the respective sequence networks and their Thévenin
equivalent circuits at fault point P . The currents flowing out of faulted bus k can be
represented as current injections into bus k as (0)
faI , (1)
faI , and (2)
faI . These current
injections cause voltage changes (sags and swells) at the buses of the zero-, positive,
and negative-sequence networks, respectively. The voltage changes ( ) in the sequence
networks ( s = 0, 1, or 2) of the N-bus network due to the current injections are given in
general terms by
( ) ( ) ( ) ( ) ( )
1 11 12 1 1
( ) ( ) ( ) ( ) ( )
2 21 22 2 2
( )( ) ( ) ( ) ( ) ( )
1 2
( ) ( ) ( ) ( ) ( )
1 2
0
0
0
s s s s s
a k N
s s s s s
a k N
ss s s s s
faka k k kk kN
s s s s s
Na N N Nk NN
V Z Z Z Z
V Z Z Z Z
IV Z Z Z Z
V Z Z Z Z
( ) ( )
1
( ) ( )
2
( ) ( )
( ) ( )
s s
k fa
s s
k fa
s s
kk fa
s s
Nk fa
Z I
Z I
Z I
Z I
(2.17)
It can be seen that only column k , which represents the bus where the faults occurs,
needs to be considered. The total positive-sequence voltage of phase a at each bus
during the fault can be then calculated using the corresponding prefault voltages as:
Chapter 2 • Modeling and Simulation Tools
53 |
(1) (1) (1) (1)(1) (1)1 1 11 1
(1) (1) (1) (1)(1) (1)2 2 22 2
(1) (1)(1) (1)
(1)(1) (1)
af af k faa a
af af k faa a
f f kk faka ka
NafNa Na
V V Z IV V
V V Z IV V
V V Z IV V
VV V
(1) (1) (1)
Naf Nk faV Z I
(2.18)
In industry practice, load currents are usually omitted in fault calculations [83]. This
means that all prefault currents are regarded as being zero and the prefault voltage at all
buses as fV . Both prefault voltages equal to
fV and actual prefault voltages determined
taking into account load currents have been used in this thesis.
Under the assumption that prefault voltages in the negative- and zero-sequence
networks are zero, the voltage changes are equivalent to the total negative- and zero-
sequence voltages during the fault as expressed by
( ) ( )( )11
( ) ( )( )22
( ) ( )( )
( ) ( )( )
s ssk faa
s ssk faa
s sskk faka
s ssNk faNa
Z IV
Z IV
Z IV
Z IV
(2.19)
where s is either 0 or 2, the former representing zero-sequence quantities and the latter
negative-sequence quantities.
A generalization can be made from (2.18) and (2.19) such that once the symmetrical
components of the fault current at any bus are known, the sequence voltages at any
other bus of the system can be determined. That is, during the fault at bus k the
sequence voltages of phase a at any bus j are
(0) (0) (0)
ja jk faV Z I
(1) (1) (1) (1)
ja jaf jk faV V Z I (2.20)
(2) (2) (2)
ja jk faV Z I
From the set of sequence voltages of phase a the set of line-to-neutral voltages of
phases a ( )janV , b ( )jbnV , and c ( )jcnV at bus j can be determined using symmetrical
components as follows:
Chapter 2 • Modeling and Simulation Tools
54 |
(0) (1) (2)
(0) 2 (1) (2)
(0) (1) 2 (2)
jan ja ja ja
jbn ja ja ja
jcn ja ja ja
V V V V
V V V V
V V V V
(2.21)
where = 1 120°is an operator that causes a rotation of 120° in the anticlockwise
direction. The line-to-line voltages at bus j are then given by
jab jan jbn
jbc jbn jcn
jca jcn jan
V V V
V V V
V V V
(2.22)
A voltage measurement device (e.g. a power quality monitor) connected phase-to-
neutral at bus j will measure a voltage sag or swell as defined by (2.21) upon the
occurrence of fault, whereas the same monitor connected phase-to-phase will measure
the event as expressed by (2.22). The magnitude of the sag measured by each monitor
will depend on the type of fault and on the relative location of the fault, i.e., if there is a
delta-wye transformer between the fault location and the monitored bus.
Equation (2.20) states that calculation of the voltages changes caused by a fault requires
knowledge of the values of the symmetrical components (0)
faI ,(1)
faI , and(2)
faI of the
fault current. These values are determined by the type of fault and the fault impedance
fZ . The calculation of the symmetrical components of the fault current for the most
common types of faults is discussed next.
2.4.1 Three-Phase Faults
Faults involving the three phases represent only about 5% of the total but are the most
severe [83]. A symmetrical three-phase fault with the same fault impedance fZ in all
phases and a common point is represented in Figure 2-8. The common point may or
may not be connected to ground. Both of these cases are essentially equal unless the
fault occurs simultaneously with a second unbalanced fault involving ground [88]. The
equation to calculate the fault current can be obtained directly from the Thévenin
equivalent circuit of the system at the fault bus k (see Figure 2-8 (b)) by incorporating
the fault impedance:
Chapter 2 • Modeling and Simulation Tools
55 |
(1)
(1)
f
fa
kk f
VI
Z Z
(2.23)
As can be seen from (2.23) only positive-sequence fault currents are drawn by three-
phase faults. Assuming bolted faults (fZ = 0) equates to a direct short circuit that entails
the highest value of fault current, which can be taken as the most conservative value to
assess the effects of faults. Faults however often involve fault impedances greater than
zero.
Figure 2-8 Three-phase fault through fault impedance fZ , (a) symbolic representation and (b)
connection of the Thévenin equivalent circuit (adopted from [83]).
2.4.2 Single Line-to-Ground Faults
Most of the faults on transmission lines (70% - 80%) are unsymmetrical single line-to-
ground faults caused by insulator flashovers resulting from a lightning strike or by
conductors making contact with grounded structures [83]. Figure 2-9 (a) shows the
representation of a single line-to-ground occurring in phase a (without any loss of
generality) through a fault impedancefZ . The conditions at the faulted bus k are given
by
0fb fcI I (2.24)
ka fa fV I Z (2.25)
Therefore, the symmetrical components of fault currents are
(0)
(1) 2
(0) 2
1 1 11
1 03
1 0
fa fa
fa
fa
I I
I
I
(2.26)
Ifa
Ifb
Ifc
Zf
Zf
Zf
a
b
c
k
k
k
+
_Vf
+
_
Ifa(1)
Vka(1)
k
Zkk(1)
Zf
(a) (b)
Chapter 2 • Modeling and Simulation Tools
56 |
which yields
(0) (1) (2)
3
fa
fa fa fa
II I I (2.27)
Replacing (1)
faI and (2)
faI with (0)
faI shows that (0)3fa faI I , and from (2.20) the following
applies
(0) (0) (0)
(1) (1) (0)
(2) (2) (0)
ka kk fa
ka f kk fa
ka kk fa
V Z I
V V Z I
V Z I
(2.28)
The voltage to neutral in phase a at the fault bus k can be then calculated as
(0) (1) (2) (0) (1) (2) (0) (0)3ka ka ka ka f kk kk kk fa f faV V V V V Z Z Z I Z I (2.29)
Solving for (0)
faI and combining the result with (2.27) gives
(0) (1) (2)
(0) (1) (2) 3
f
fa fa fa
kk kk kk f
VI I I
Z Z Z Z
(2.30)
The symmetrical components of the fault current for a single line-to-ground fault
through fault impedance fZ are determined by (2.29). The series connection of
Thévenin equivalents of the three sequence networks as depicted in Figure 2-9 (b)
simulate a single line-to-ground fault on phase a at bus k of the system. Since the
currents and voltages in this circuit satisfy (2.29) all the required equations for the fault
point can be derived from this sequence-network connection.
Figure 2-9 Single line-to-ground fault through fault impedance fZ , (a) symbolic representation and (b)
connection of the Thévenin equivalent circuits (adopted from [83]).
Ifa
Ifb
Ifc
a
b
c
Zf
k
k
k
+
_Vf
+
_
Ifa(1)
Vka(1)
k
Zkk(1)
Ifa(2) k
Zkk(2) +
_
Vka(2)
Ifa(0) k
Zkk(0) +
_
Vka(0)
3Zf
Ifa(0)
Ifa(1)
= = Ifa(2)
(b)(a)
Chapter 2 • Modeling and Simulation Tools
57 |
2.4.3 Line-to-Line Faults
Faults involving two lines but not ground are also unsymmetrical faults and the rate of
occurrence is similar to three-phase faults [89]. A line-to-line fault on phases b and c
through fault impedance fZ is represented in Figure 2-10 (a) and a schematic model of
the fault is shown in Figure 2-10 (b). The following relations hold at the fault point k :
0faI (2.31)
fb fcI I (2.32)
kb kc fb f fc fV V I Z I Z (2.33)
Therefore, the symmetrical components of the unsymmetrical fault current are
(0)
(1) 2
(0) 2
1 1 1 01
13
1
fa
fa fb
fa fb
I
I I
I I
(2.34)
which results in
(0) 0faI
(2.35)
(1) (2)
fa faI I
(2.36)
Since zero-sequence sources are absent and zero-sequence currents do not flow line-to-
line fault calculations do not require zero-sequence components. From the connection of
negative- and positive-sequence networks shown in Figure 2-10 the following can be
derived:
(1) (2) (1) (2) (1) (1) (2) (1)
2 (1) 2 (2) 2 (1) (2)
kb kc kb kb kc kc kb kc kb kc
ka ka ka ka
V V V V V V V V V V
V V V V
(2.37)
(1) (2) 2 (1) (2)
fb f fb fb f fa fa fI Z I I Z I I Z (2.38)
Since (2.37) and (2.38) are equal and substituting (2.36) the following is obtained:
2 (1) (2) 2 (1)
ka ka fa fV V I Z (2.39)
which is equivalent to the voltage-drop equation for impedance fZ in Figure 2-10 (b):
(1) (2) (1)
ka ka fa fV I I Z (2.40)
Chapter 2 • Modeling and Simulation Tools
58 |
Figure 2-10 Line-to-line fault with fault impedance fZ , (a) symbolic representation and (b) connection
of the Thévenin equivalent circuits (adopted from [83]).
The equations for the negative- and positive-sequence components of the fault current
can be obtained from the connection of the Thévenin equivalent circuits shown in
Figure 2-10 as follows:
(1) (2)
(1) (2)
f
fa fa
kk kk f
VI I
Z Z Z
(2.41)
There are no zero-sequence components in the current of line-to-line faults. The phase
shift of the negative- and positive-sequence caused by delta-wye transformers must be
taken into account in the calculations.
2.4.4 Line-to-Line-to-Ground Faults
Faults involving two phases and ground are another type of unsymmetrical fault that
usually occur more often than line-to-line and three-phase faults [89]. The graphical
representation of a double line-to-ground fault at bus k between phases b and c is
shown in Figure 2-11 (a) and the connection of the Thévenin equivalents of the
sequence networks for the fault is shown in Figure 2-11 (b). The following applies for
the fault at bus k :
0faI
(2.42)
(0)
3
fb fc
fa
I II
(2.43)
(0)3kb kc fb fb f fa fV V I I Z I Z (2.44)
Replacing kcV with
kbV to perform the symmetrical-component transformation yields:
Ifa
Ifb
Ifc
Zf
a
b
c
k
k
k
+
_Vf
+
_
Ifa(1)
Vka(1)
k
Zkk(1)
Ifa(2)Zf
Zkk(2)
k
+
_
Vka(2)
(a) (b)
Chapter 2 • Modeling and Simulation Tools
59 |
(0)
(1) 2
(0) 2
1 1 11
13
1
ka ka
ka kb
ka kb
V V
V V
V V
(2.45)
which results in
(1) (2)
ka kaV V (2.46)
(0) (0) (1) (2) (0)3 2 2 3ka ka kb ka ka ka fa fV V V V V V I Z (2.47)
The characterizing equations of the double line-to-ground fault can then be obtained by
solving for (1)
kaV :
(1) (2) (0) (0)3ka ka ka fa fV V V I Z (2.48)
(0) (1) (2) 0fa fa faI I I (2.49)
The symmetrical components of the fault current can be obtained from the diagram of
sequence network connections as follows:
(1)
(2) (0)
(1)
(0) (2)
3
3
f
fa
kk kk f
kk
kk kk f
VI
Z Z ZZ
Z Z Z
(2.50)
(0)
(2) (1)
(0) (2)
3
3
kk f
fa fa
kk kk f
Z ZI I
Z Z Z
(2.51)
(2)(0) (1)
(0) (2) 3
kkfa fa
kk kk f
ZI I
Z Z Z
(2.52)
As a final observation from the calculation of symmetrical and symmetrical faults,
recall that the symmetrical components (0)
faI , (1)
faI , and (2)
faI of the fault current can be
treated as negative current injections into the sequence networks at the fault bus k to
calculate the voltage changes, i.e., the voltage sags or swells, at all buses of the system
using the bus impedance matrices.
Chapter 2 • Modeling and Simulation Tools
60 |
Figure 2-11 Double line-to-ground fault with fault impedance fZ , (a) symbolic representation and (b)
connection of the Thévenin equivalent circuits (adopted from [83]).
2.5 Voltage Sag Assessment Software
Throughout this thesis a custom-made program developed on MATLAB® named vSAS
(“Voltage Sag Assessment Software”) has been used to calculate the voltage sag
characteristics in several networks. vSAS was developed in [90] to provide an analytical
tool for the techno-economic assessment of voltage sag performance and mitigating
solutions. The numerical results and graphical descriptions generated by vSAS have
been published, among others, in [91-93]. The software calculates all the voltage sag
characteristics required in this thesis by means of fault-current calculations based on the
bus impedance matrix.
2.6 Test Systems
2.6.1 10-bus Power System
The sample 500-kV power network depicted in Figure 2-12 is introduced in [53] to
perform monitor placement studies and is used in Chapter 4 of this thesis. The network
consists of 10 buses, 10 lines, and 5 generators. The network data is given in [53] and is
also provided in Appendix A.
Ifa
Ifb
Ifc
Zf
a
b
c
k
k
k
Ifb + Ifc
+
_Vf
+
_
Ifa(1)
Vka(1)
k
Zkk(1)
3Zf
+
_
Ifa(2)
Vka(2)
k
Zkk(2) +
_
Ifa(0)
Vka(0)
k
Zkk(0)
(a) (b)
Chapter 2 • Modeling and Simulation Tools
61 |
Figure 2-12 A sample 10-bus network.
2.6.2 IEEE Reliability Test System
The IEEE Reliability Test System (RTS) was developed by the IEEE Reliability
subcommittee and publicized in 1978. The purpose of this system is to provide a
benchmark system for testing reliability methods [94]. The system is used in Chapter 3
and Chapter 4 and is depicted in Figure 2-13. The RTS consists of 24 buses, 33 lines, 10
generators, and 5 transformers and it was recently modeled as a 24-substation, breaker-
oriented, three-phase model in [95] for use in research for three-phase power flow
analysis, reliability analysis, fault analysis, and transient stability, among other
applications. The updated system parameters were taken from [96] and are provided in
Appendix A.
Figure 2-13 IEEE Reliability Test System (RTS).
9
1
8
10
6
5
432
7
1 2 7
45
3 9
24 11 12
10
8
6
15
14
16
17
19
13
18
2320
21 22
138 kV 230 kV
Chapter 2 • Modeling and Simulation Tools
62 |
2.6.3 IEEE 118-bus Power Flow Test Case
The IEEE 118-bus test system diagrammed in Figure 2-14 represents a portion of the
electric power system in the Midwestern USA dating back to 1962 [97]. This system is
used in Chapter 4 and it consists of 35 generators, 118 buses, 177 transmission lines,
and 9 transformers. The network data is provided in [97] and reproduced in Appendix
A.
Figure 2-14 IEEE 118-bus power flow test case.
2.6.4 Generic Distribution System
The generic distribution system (GDS) depicted in Figure 2-15 was developed using
typical parameters and configurations present in UK distribution networks [98-100]. It
has been utilized to perform technical and economical studies on voltage sags in [29, 91,
93, 101] among others, and it is used in all the chapters of the thesis. The system
consists of 295 buses and 278 overhead lines and underground cables with lengths
between 0.05 and 11 kilometers. It also comprises a 400-kV/275-kV transmission
system in-feed, a 33-kV predominantly meshed sub-transmission network, and an 11-
kV predominantly radial distribution network. The system supplies 373 MW and 77
1 2
3
4
11733
1211
56 7
13
14
15
19
18
17
30113
16
8
9
10
29
27
32
114
26
25
23
2221
2031
35
34
36
73
7224
74
75
83
84
85
86
88 89
82
90 9187
95 94
93
92
102 101112
111
110103
109
108107
105
106
104100
99
8179
96
80
78
76
77
118
70
71
116
68
69
38
4137
4345
48
46
47
39
40 42 54
5253
56
59
55
58
51 6064
6149
67
6662
65
63
50
115
44
57
9897
28
Chapter 2 • Modeling and Simulation Tools
63 |
MVAR through 39 transformers to 148 load buses at which static loads (constant
impedance) are connected. The system data is provided in Appendix A and summarized
in Table 2-3.
Table 2-3 Number and characteristics of generic distribution system components
400 V 11 kV 33 kV 132 kV 275 kV 400 kV Total
Buses 5 233 25 23 4 5 295
Loads 0 139 6 3 0 0 148
P (MW) 0 47.79 144.88 180.13 0 0 372.8
Q (MVAR) 0 9.44 31.44 35.77 0 0 76.65
Overhead lines 0 136 5 4 0 0 145
Underground cables 0 93 18 22 0 0 133
Average X/R ratio of
lines and cables
N/A 0.6212 2.5816 4.1345 N/A N/A 1.1119
Transformers 0 2 8 13 4 12 39
2.7 Summary
The sag characteristic most relevant to this thesis is the residual voltage. Therefore,
from the range of simulation tools available for voltage sag studies described in section
2.1, the fault-current calculation method was deemed as the most convenient for this
research due to its high suitability for calculating residual voltages, ease of
implementation, and the relatively simple required capabilities of the simulation tool. In
accordance with this selection, steady-state models of the main system components and
the fault calculation method based on bus impedance matrix are utilized throughout the
thesis. Results are obtained from a previously developed program on MATLAB®
named vSAS.
Chapter 2 • Modeling and Simulation Tools
64 |
Figure 2-15 Single line diagram of the generic distribution system (GDS).
28
4
24
46
17
28
16
14
12
26
21
19
23
22
22
2
18
15
54
52
53
22
9
50
75
22
7
74
22
8
20
22
0
51
76
13
26
7
87
48
47
49
22
1
43
42
41
40
39
38
37
26
8
23
42
35
23
0
78
79
80
81
85
88
28
5
82
83
84
28
6
90
91
92
94
93
95
96
97
10
09
8 99
10
1
10
21
03
10
4
10
51
06
10
7
10
8
10
9
11
0
11
1
11
2
11
31
14
11
5
12
0
12
1
12
21
23
12
4
12
5
12
6
12
7
11
6
11
7
11
81
19
86
11
10
8
97654
55
1
65
64
63
57
22
52
26
58
14
8
14
6
15
3
15
4
14
91
52
15
5
14
71
45
14
4
14
0
14
2
14
1
14
3
13
9
13
8
12
8
12
91
32
13
0
13
4
13
61
35
13
7
13
3
15
6
16
0
15
7
18
5
18
3
13
1
15
9
16
4
16
1
16
2
16
3
16
5
16
6
16
71
68
16
9
17
9
18
0
18
11
82
18
4
18
6
18
7
18
8
18
91
90
19
1
19
2
19
3
19
6
19
7
19
91
98
20
0
20
1
20
22
03
20
4
20
5
20
6
20
72
08
15
0
15
1
22
3
23
1
77
15
8
22
4
21
4
21
5
21
0
21
12
09
21
2
21
3
21
6
21
71
70
21
8
21
9
17
1
17
2
17
3
17
4
17
5
17
6
17
7
62
60
59
61
2
3
72
70
17
8
25
27
29
30
32
31
33
34
35
36
71
68
67
69
73
89
45
44
24
82
49
26
52
66
24
1
25
1
25
9
23
6
24
3
26
0
25
0
24
02
44
24
52
42
26
12
71
26
92
52
27
32
70
27
52
74
26
22
63
27
2
23
9
25
32
57
25
52
58
27
6
24
6
27
7
24
7
27
923
3
27
8
23
22
54
25
6
28
82
87
28
92
90
29
22
91
29
42
93
29
5
23
42
37
28
3
23
8
28
22
80
28
1
56
BA
CD
E
F
HI
J/IX
K/X
L
G
13
2k
V
33
kV
11
kV
0.4
kV
27
5k
V
40
0k
V
66
III
IVV
VI
VII
VIII
XI
III
18
2
18
3
18
41
85
18
61
87
18
81
89
190
191
192
19
31
94
19
51
96
19
71
98
199
20
0
20
1
20
2
20
3
20
42
05
206
207
208
209
210
211
212
213
214
215
21
6
21
72
18
21
922
0
221
22
2
22
322
4
225
22
6
22
7
22
82
29
23
023
1
23
2
23
3
23
4
23
523
6
23
723
8
23
924
0
241
242
243
244
24
5
24
6
247
24
8
24
92
50
251
25
2
25
3
25
4
25
5
25
6
25
7
25
82
59
26
0
19
4261
19
5262
26
3
264
26
5
26
62
67
268
269
270
271
27
2
27
4
27
52
78
27
3
27
62
77
1
2 8
33
34
5
5
6
7
9
10
11
12
13
13
13
14
15
16
17
18
1920
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
9394
95
96
96
97
98
99
10
0
10
1
10
2
10
3
10
41
05
10
6
10
7
10
8
10
9
11
0
11
1
11
21
13
11
4
11
51
15
11
6
11
71
18 1
19
12
0
12
1
12
2
12
3
123
12
41
25
12
61
27
12
8
12
9
13
0
13
1
13
2
13
31
34
13
5
13
6
13
7
13
81
39
14
0
14
11
42
14
3
14
41
45
14
6
14
7
14
8
14
9
15
0
15
1
15
21
53
15
4
15
5
15
6
15
71
58
15
9
16
0
16
11
62
16
3
16
4
16
5
16
6
16
7
16
8
16
9
17
0
17
1
17
2
17
3
17
4
17
51
76
17
71
78
17
9
18
01
80
18
0
18
1
+1
21
12
2B
us
nu
mb
er
16
1L
ine
nu
mb
er
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
65 |
Chapter 3
Optimal Monitor
Placement for Voltage Sag
Characterization
This chapter provides an overview of the first and still the most referred optimal
monitor placement method for voltage sag characterization. The monitor reach area
(MRA) method determines minimum monitoring programs that estimate the sag
performance of all non-monitored buses of the system. This method, however, has
important limitations which are highlighted through simulations on the IEEE 24-bus
reliability test system (IEEE-RTS) and on the 295-bus generic distribution system
(GDS). A recently proposed fault location method that can be used to overcome these
limitations and enhance the robustness of the MRA method is also reviewed and
discussed in the chapter. Finally, the chapter presents the improvement of the MRA
method by incorporating the previous fault location method in the MRA algorithm. This
improvement of MRA method presents the first original contribution of the thesis.
3.1 Monitor Reach Area Method
The monitor reach area (MRA) is defined as the region of the network where a monitor
is able to register voltage sags caused by faults [39]. This region encompasses the buses
and lines where the occurrence of faults causes a voltage drop at the bus where the
monitor is installed. The size of the MRA is proportional to the voltage drop, i.e. the
bigger the voltage drop the smaller the size of the MRA, as depicted in Figure 3-1. The
voltage drop, measured as the magnitude of the voltage sag, is determined from short
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
66 |
circuit analysis based on the bus impedance matrix. The classical symmetrical
component method is used to calculate the magnitude of voltage sags, e.g., [1], [91-93].
Figure 3-1 Symbolic representation of three monitor reach areas for bus 9 of the IEEE-RTS.
Consider the illustrative power system shown in Figure 3-2 and assume that a fault takes
place at fault point t on line connecting buses j and k . The fault distance per unit
from bus j is denoted by d and s
z is the total impedance of the line, with s = 0, 1, or
2 indicating zero, positive, or negative sequence impedance values. The sequence
voltages at bus i [83] can be calculated by:
1 1 1 (1)pf
i i it fV V Z I (3.1)
2 2 2
i it fV Z I (3.2)
0 0 0
i it fV Z I (3.3)
where
1 2 0, ,i i iV V V positive, negative, and zero sequence voltage at bus i during the fault;
(1) pf
iV pre-fault positive sequence voltage at bus i ;
1 2 0, ,it it itZ Z Z positive, negative, and zero sequence transfer bus impedance between
bus i and fault point t ;
1 2 0, ,f f fI I I positive, negative, and zero sequence current at fault point t .
1 2 7
45
3 9
24 11 12
10
8
6
15
14
16
17
19
13
18
2320
21 22
S.C.
0.90 p.u. 0.70 p.u. 0.40 p.u.
V
138 kV 230 kV
V Voltage measurement device
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
67 |
And the three-phase voltages at bus i can be calculated as the product of a component
of aV (voltage of phase a ) and some function of operator 1 120 as follows:
0
12
2 2
1 1 1
1
1
aa
b a
c a
VV
V V
V V
(3.4)
Power system network
j k
i
tdz(s) (1-d)z(s)
Figure 3-2 Illustrative power system.
The monitor reach areas of a network’s buses can be modeled as a binary matrix of
order N F , where N is the number of buses, and F is the number of fault positions.
Fault positions can represent potential faults at buses, discrete points on lines, or line
segments. The MRA matrix is built for each type of fault and for a given voltage
threshold thV , using the magnitude of the phase voltages calculated with (3.4) as
follows:
,
,
,
1,if min , ,
0,if min , ,
a b c thx y
x y
a b c thx y
V V V V
V V V V
MRA (3.5)
The value of ,x yMRA equals one only if faults occurring at fault point y produce a
voltage sag with magnitude below or equal to thV at bus x in any of the three phases.
As stated previously, the size of the monitor reach area is proportional to the sag
magnitude and thus the lower the voltage threshold thV used to build MRA the more
monitors are required to cover the entire network.
A single MRA matrix represents the area of the network where a monitor can detect
and capture the voltage sags originated by faults with specific characteristics, such as
type, location, and fault resistance, and taking place under particular system conditions
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
68 |
such as network topology and generation schedule. Therefore, a considerable number of
MRA matrices should be built in order to study a reasonable number of fault scenarios.
3.1.1 Formulation of the Optimization Problem
In order to formulate the optimal monitor placement problem the binary vector M of
length N (number of buses) is defined as a decision variable whose element xM takes
the value 1 if a monitor is placed at bus x and equals 0 in absence of a monitor. The
monitor placement problem has been formulated as an integer linear programming
problem as [39]:
Minimize1
N
x
x
M (3.6)
subject to ,
1
1,N
x x y
x
y
M MRA (3.7)
The solution of the problem described by (3.6) and (3.7) provides an optimal sag
monitoring program (OSMP), i.e. the minimum set of monitors required to capture all
the voltage sags with magnitude equal to or less than thV caused by faults in the
network. There can be more than one OSMP for a network, all of them having the same
number of monitors but indicating different buses for their location.
3.1.2 Voltage Sag Estimation at Non-Monitored Buses
The number and characteristics of voltage sags at non-monitored buses can be estimated
by finding a set of fault positions likely to cause the residual voltages registered by the
OSMP [65, 102]. For every possible fault position identified, the residual voltage at all
non-monitored buses can be determined by simulating the fault at such a position.
Since the method is not designed to pinpoint the exact fault position, the residual
voltage is calculated as a weighted average of all potential residual voltages as in (3.8),
using the per-unit fault rate of potential fault positions as weighing factors.
1
1
1 fp
iu k ikfpk
k
k
V V
(3.8)
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
69 |
where iuV is the estimated residual voltage at bus i caused by a fault at an unknown
position u , fp is the number of possible fault positions, k is the fault rate of fault
position k , and ikV is the residual voltage at bus i caused by a fault at position k .
The effectiveness of sag performance estimation at non-monitored buses obtained from
OSMPs is strictly dependant on the triggering of monitors after the voltage of any phase
has dropped below thV . The voltage measured by a monitor during a fault depends,
among the other factors, on the fault characteristics (type, fault impedance, etc.), the
distance between the monitored bus and the fault location, and the pre-fault conditions
of the networks (loading profile, pre-fault voltages at buses, etc). So far the effects of
these factors on sag detection by OSMPs and consequently on the accuracy of sag
performance estimation at non-monitored buses have not been investigated. The effects
of two of these factors, namely, fault impedance and pre-fault voltages are looked into
in the next section.
3.1.3 Factors Influencing Accuracy of Voltage Sag Detection
The estimation of voltage sags using the OSMPs discussed above is strongly dependent
on detection of sags below a fixed voltage threshold. Therefore, if none of the monitors
captures a sag event no estimation can be done. The OSMPs are designed so that every
sag occurring throughout the network can be recorded by at least one monitor; however
there are situations in which the OSMP can overlook voltage sags. Examples of such
situations are discussed below.
In [72] an OSMP for the IEEE-RTS network is obtained by applying the MRA method
for a voltage threshold of 0.7 p.u. The resulting OSMP comprises four monitors
installed at buses 3, 6, 8, and 17. In theory any three-phase (LLL) fault causing a
voltage sag with magnitude below 0.7 p.u. should be detected and recorded by, at least,
one of the monitors placed at these buses.
Line-to-ground (LG) faults have been simulated in the middle of line between buses 5
and 10 using different values of pre-fault voltages and fault resistance. A total of 21 pre-
fault voltage profiles have been calculated using Matpower [103] varying all loads of
the system from 90% to 110% of base values as stated in [95] in steps of 1%. The fault
resistance values used range from 0 to 20Ω [104].
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
70 |
The voltage sag magnitudes at buses 3, 6, 8, 17 (selected for optimal sag monitoring)
and bus 5 (one end of the faulted line) caused by LG faults and base load (load factor =
100%) are presented in Figure 3-3. It can be seen, for example, that the voltage sag
magnitude at bus 3 is lower than 0.9 p.u. for fault resistance between 0 and 7 Ω and
rises above 0.9 p.u. for greater values of fault resistance. Voltage sag magnitudes at bus
5 lie between 0.32 and 0.74 p.u. The voltage at bus 6 can decrease to 0.71 p.u. but with
a fault resistance of 17 Ω or higher it remains over 0.9 p.u., etc.
Since the most common voltage threshold for which a monitor is set to register voltage
sags is 0.9 p.u. [14], the OSMP determined for the IEEE-RTS network will not capture
LG faults occurring in the middle of line between buses 5 and 10 when the fault
resistance is 17 Ω or higher because the sag magnitude at buses 3, 6, 8, and 17 is greater
than 0.9 p.u. A LG fault with a fault resistance between 17 Ω and 20 Ω however, causes
voltage sags at bus 5 with magnitudes between 0.67 and 0.74 p.u.
Figure 3-3 Voltage sag magnitude at monitored buses (3, 6, 8, and 17) and bus 5 (one of the ends of
faulted line) as a function of fault impedance.
The residual voltage at buses 3, 5, 6, 8, and 17 upon occurrence of a LG fault with fault
impedance of 17 Ω along the line connecting buses 5 and 10 is shown in Figure 3-4. It
is apparent from this figure that none of the monitors at optimal locations would trigger
and therefore record the voltage sag caused by the fault taking place up to 0.57 of the
line because the residual voltage stays above 90% of the nominal voltage (138 kV).
Nevertheless, faults beyond this point generate residual voltages at buses 6 and 8 below
0.9 p.u., as can be observed in the magnified portions of the plot (inset) with an
exception at the very end of the line (length of segment is less than 0.02 p.u.) for bus 6.
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Vo
ltag
e S
ag
Mag
nit
ud
e (
p.u
.)
Fault Impedance (Ohm)
BUS 3 BUS 5 BUS 6 BUS 8 BUS 17
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
71 |
Figure 3-4 Voltage sag magnitude at monitored buses (3, 6, 8, and 17) and bus 5 (one of the ends of
faulted line) as a function of fault distance.
The variation in magnitude of voltage sags at the OSMP buses due to fluctuation in pre-
fault voltages (21 different values) is depicted in Figure 3-5. The same LG fault
(midway between buses 5 and 10) is simulated with fault resistance of 17 Ω. It can be
seen from Figure 3-5 that the sag magnitude at buses 3, 8, and 17 remains above 0.9 p.u.
in all cases. In three cases the voltage sag magnitude at bus 6 drops below 0.9 p.u. The
voltage sag magnitude at bus 5 drops constantly to 0.7 p.u. over the whole range of pre-
fault voltages. Under these conditions the OSMP however, fails to detect the fault
causing a sag at bus 5 for 18 out of 21 loading scenarios.
Figure 3-5 Voltage sag magnitude at monitored buses as a function of pre-fault voltage.
The simple analysis presented above demonstrates that system’s loading conditions (i.e.
pre-fault voltages at buses) and fault resistance can prevent OSMPs from detecting and
recording voltage sags when the typical triggering threshold value of 90% of the
nominal voltage is used. This lack of sag detection could lead to an increase in the
0.6
0.65
0.7
0.75
0.8
0.85
0.9
0.95
1
1.05
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Vo
ltag
e S
ag
Mag
nit
ud
e (
p.u
.)
Fault Distance from Bus 5 (p.u.)
BUS 3 BUS 5 BUS 6 BUS 8 BUS 17
0.88
0.89
0.9
0.57 0.64 0.71 0.78 0.85 0.92 0.99
0.915
0.925
0.935
0.978 0.986 0.993
a) Bus 3
0.890
0.910
0.930
1.075 1.086 1.094
b) Bus 6
0.900
0.907
0.914
0.993 1.000 1.005
c) Bus 8
1.014
1.015
1.016
1.0398 1.0401 1.0403
d) Bus 17
Vo
ltag
e S
ag
Mag
nit
ud
e (p
.u.)
Pre-fault Voltage (p.u.) Pre-fault Voltage (p.u.)
Vo
ltag
e S
ag
Mag
nit
ud
e (p
.u.)
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
72 |
number of monitors required to cover the network. The same problem could arise for
other voltage sag thresholds. The actual effects of these factors, namely, pre-fault
voltages, fault resistance, and voltage thresholds on the size of OSMPs are investigated
further in the next section.
3.1.4 Variability in Number of Optimally Placed Monitors
The variation in number of monitors that must be deployed to detect and register every
voltage sag occurring in the GDS network is shown in Table 3-1. Data shown in this
table has been obtained using a pre-fault voltage profile associated with base loading
profile and is presented according to fault impedance, type of faults, and voltage
thresholds thV . From this it can be seen that for low values of fault impedance (0 Ω
and 5 Ω) and all types of faults, the lower the voltage threshold the greater the number
of monitors required to cover the network, i.e., sags with magnitude lower than 0.9 p.u.
entail the fewest monitors whereas sags with magnitude lower than 0.7 p.u. entail the
most. This finding (lower threshold = more monitors) was also established in [40],
however, when the fault impedance is 10 Ω or higher the relationship only holds for
LLG faults, meaning that the monitor reach areas for this type of fault remain
practically the same despite the increase in fault impedance.
For LG faults with fault impedance of 10 Ω or higher and modeled as showed in Section
2.4.2 (see Figure 2-9), less monitors are needed for sags with magnitude lower than 0.7
p.u. than the monitors needed for shallower sags. This is an indication that the total area
of the network where these faults cause voltage drops below 0.7 p.u. is smaller than the
area where the same faults cause sags with magnitude above 0.7 p.u., and thus fewer
monitors are required. The only exception arises when LG faults have a fault impedance
of 25 Ω since the number of monitors for covering sags with magnitude of 0.8 p.u. and
0.7 p.u. is the same.
Table 3-1 Number of Voltage Measurement Devices Required to Record Voltage Sags in the GDS
Rf
(Ω)
LG LL LLG LLL
thV (p.u.) thV (p.u.) thV (p.u.) thV (p.u.)
0.90 0.80 0.70 0.90 0.80 0.70 0.90 0.80 0.70 0.90 0.80 0.70
0 7 10 16 4 6 8 4 5 8 4 7 8
5 14 24 25 5 15 24 4 5 7 10 13 10
10 16 24 15 8 21 8 4 5 7 14 7 8
25 17 8 8 16 6 15 4 6 8 7 8 0
50 10 6 1 5 9 0 4 6 8 3 0 0
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
73 |
No general relation can be drawn from LL and LLL faults having fault impedance
values of 10 Ω or higher since there is not homogeneous variation in number of
monitors for these cases. In some cases higher voltage threshold entails more monitors
than lower threshold and in other instances the opposite applies. For example, 8
monitors are sufficient to detect both sags with magnitude lower than 0.9 p.u. and sags
with magnitude lower than 0.7 p.u. when these are caused by LL faults having a fault
impedance of 10 Ω, but this number increases to 21 monitors for sags with magnitude
lower than 0.8 p.u. An inverse effect is seen for a fault impedance of 25 Ω. Sags with a
magnitude of 0.9 p.u. and 0.7 p.u. entail 16 and 15 monitors, respectively whereas sags
with magnitude of 0.8 p.u. require only 6 monitors. With regard to LLL faults, the
number of monitors required to register every voltage sag with magnitude of 0.9 p.u.,
0.8 p.u., and 0.7 p.u. is 14, 7, and 8, respectively for fault impedance of 10 Ω. These
numbers change to 7, 8 and 0 in the same order as above when the fault impedance is 25
Ω. LLL faults with fault impedance of 25 Ω and 50 Ω do not cause voltage drops below
0.7 p.u. at any bus and thus no monitors are required for this type of sags. The same
occurs for voltage sags with magnitude of 0.7 p.u. caused by LL faults with fault
impedance of 50 Ω.
Because of these inconsistencies, a new study was performed to determine OSMPs
incorporating all types of faults simultaneously. The three voltage sag thresholds used
previously (0.9, 0.8, and 0.7 p.u.) and the five values of fault impedance (0, 5, 10, 25,
and 50 Ω) were considered in the study. Four different pre-fault voltage profiles were
used to determine the OSMPs. Three pre-fault voltage profiles were determined using
Matpower according to low, base, and high loading profiles, which correspond to
system loading factors of 90%, 100%, and 110%, respectively. Voltages equal to 1 p.u.
at all buses constitute the fourth pre-fault voltage profile.
The minimum number of monitors required to detect all fault-induced voltage sags
occurring throughout the GDS network is shown in Table 3-2. Data from this table can
be compared with the data in Table 3-1 which shows similar results. The principle that
lower sag thresholds entail more monitors does not always hold for faults with fault
impedance greater that 0 Ω. Consider, for example, faults having an impedance of 10 Ω
and occurring during base loading conditions. The number of monitors required to
detect all the voltage sags caused by these faults are shaded in green in Table 3-2. It can
be seen that sags with magnitude lower than or equal to 0.7 p.u. require fewer monitors
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
74 |
than sags with magnitude greater that 0.7 p.u. This is because the total area of the
network where the aforesaid faults cause sags with magnitude lower than 0.7 p.u. is
smaller than the area where the same faults cause sags with magnitude above 0.7 p.u.,
and thus fewer monitors are required.
Table 3-2 Number of Voltage Measurement Devices Required for Full Sag-Observability of the GDS
Network Using the MRA Method
Rf
(Ω)
1 p.u. Low loading profile Base loading profile High loading profile
thV (p.u.) thV (p.u.)
thV (p.u.) thV (p.u.)
0.90 0.80 0.70 0.90 0.80 0.70 0.90 0.80 0.70 0.90 0.80 0.70
0 7 11 18 7 11 17 7 11 16 7 11 16
5 22 36 43 18 30 41 16 30 40 14 30 40
10 32 45 29 27 32 23 24 32 22 21 32 22
25 35 20 25 22 19 22 19 19 21 17 17 23
50 19 18 9 14 17 9 13 14 9 12 14 9
As can be seen from Table 3-1 and Table 3-2, the number of monitors required to
achieve full observability of voltage sags in the GDS network varies between 7 and 45
due to combination of the following four factors: 1) fault impedance, 2) pre-fault
voltage, 3) voltage sag threshold, and 4) fault type. The impact of these factors on the
size of the monitor reach areas causes the variability in number of monitors needed for
OSMPs. The results shown in Table 3-1 and Table 3-2 demonstrate that the variation in
number of sag monitors is not uniform due to a non-uniform expansion and waning of
the MRAs of the network’s buses. This variation in MRAs size is not only given by the
voltage sag threshold but also by a rather complex combination between impedance of
faults and pre-fault voltages.
Two important limitations of the MRA method resulting from the use of voltage sag
triggering thresholds have been demonstrated. The first one, shown in Section 3.1.3, is
the potential loss of sag detection capability of OSMPs when sag magnitude at
monitored buses remains above 90% of nominal voltage but falls below this level at
other (non-monitored) buses. The second one, presented in Section 3.1.4, is the high
variability in the number of monitors that might be required to cover the same network
for faults with different characteristics. The underlying reason behind these limitations
is the susceptibility of the fault detection and fault location algorithms employed by the
MRA method to fault resistance, pre-fault voltage profile, and voltage sag thresholds.
An adequate fault location method that can pinpoint the fault position regardless of
these three parameters is therefore needed. One such method is discussed below.
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
75 |
3.2 Enhanced Fault Location Algorithm
The method proposed in [104] pinpoints the location of faults using the same network
data as the MRA method and solving equations (3.1)-(3.3) for the point t where the
fault occurs (see Figure 3-2). The approach was originally developed to locate faults on
single-circuit transmission lines using voltage measurements that do not have to be from
the ends of the faulted line (no current measurements are involved). The method has
been extended in [105] to locate faults on double-circuit transmission lines using only
limited voltage measurements. The basic assumptions of the method include: the
transmission system is transposed, pre-fault voltages are 1.0 p.u., fault impedance is
purely resistive, and the network data required to build the system’s bus-impedance
matrix of each sequence is available.
The method comprises different fault location algorithms formulated neglecting and
including shunt-capacitance and using measurements from one and two buses (both
synchronized and unsynchronized). Clearly, a one-bus algorithm requires fewer
monitors than a two-bus algorithm at the expense of a decrease in accuracy. Ignoring
shunt capacitance simplifies the algorithm and reduces the use of iterative solution
methods. Iterative solution methods are usually required for distributed-parameter line
models however, they lead to the detriment of accuracy. The maximum difference
between the fault location errors from one-bus and two-bus algorithms, and from
lumped line parameter and distributed line parameter approaches reported in [104] is
8.05%. In line with the objective of optimal monitor placement and given the acceptable
loss of accuracy, the one-bus algorithm that omits shunt capacitance is reviewed in the
next section and subsequently employed to enhance the fault location capability of the
MRA method.
3.2.1 Fault Location of Three-phase Symmetrical Faults
Assume that a three-phase symmetrical fault takes place at fault point t of the sample
power system shown in Figure 3-2 and that the voltage measurement from bus i is
available. For this type of fault only positive-sequence fault current flows and it can be
calculated (ignoring prefault currents) as:
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
76 |
(1)(1)
1
pf
tf
tt f
VI
Z R
(3.9)
Replacing (1)
fI in (3.1) with (3.9) results in
(1)(1) (1) (1)
(1)
pfpf t
i i it
tt f
VV V Z
Z R
(3.10)
where (1) pf
tV is the pre-fault positive-sequence voltage at fault location t , (1)
ttZ is the
positive-sequence driving-point impedance at fault location t , and fR is the fault
resistance.
1
itZ , and 1
ttZ are calculated as:
(1) (1) (1) (1)
it ij ik ijZ Z Z Z d (3.11)
1 1(1) (1) (1) (1) 2 (1) (1) (1)2 2tt jj kk jk jj jk jjZ Z Z Z z d z Z Z d Z
(3.12)
where d is the fault location (fault distance p.u. from bus j ), (1)
ijZ , (1)
ikZ , (1)
jjZ , (1)
jkZ , and
(1)
kkZ are the positive-sequence transfer impedances corresponding to buses i , j and k ,
and 1
z is the total positive-sequence impedance of line j k .
Substituting (3.11) and (3.12) into (3.10) results in
(1) (1) (1) (1)
(1) (1)
1 1(1) (1) (1) 2 (1) (1) (1)2 2
pf
t ij ik ijpf
i i
jj kk jk jj jk jj f
V Z Z Z dV V
Z Z Z z d z Z Z d Z R
(3.13)
The unknowns in (3.13) are fault location, fault resistance, and pre-fault positive-
sequence voltage at the fault location, thus (3.13) is unsolvable. However, the pre-fault
voltage at the fault location can be approximated to 1.0 p.u. and (3.13) can be separated
into real and imaginary parts to formulate two new equations, then the fault location and
fault resistance can be determined. Alternatively, the following exact equation for the
pre-fault voltage at the fault location can be used:
(1) (1) (1) (1)pf pf pf pf
t j k jV V V V d
(3.14)
where (1) pf
jV and (1) pf
kV are the pre-fault positive sequence voltages at buses j and k ,
which can be calculated by a load-flow simulation tool or state estimation. As (3.14)
shows, assuming pre-fault voltages equal to 1.0 p.u. results in pre-fault voltage at the
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
77 |
fault location equal to 1.0 p.u., as in the original approach. Given that with (3.14) it is
possible to handle calculated pre-fault voltages and pre-fault voltages approximated to
1.0 p.u., this new equation will be incorporated in the enhanced method to derive more
accurate fault location equations.
To facilitate the separation of (3.13) into real and imaginary parts, let:
(1) (1)
ik ijA Z Z
(3.15)
(1) (1)pf pf
k jB V V
(3.16)
1(1) (1) (1)2jj kk jkC Z Z Z z (3.17)
1 (1) (1)2 jj jkD z Z Z (3.18)
Substituting (3.11), (3.12), (3.14), and (3.15)-(3.18) to (3.10) leads to:
(1) (1)
(1) (1)
2 (1)
pf
ij jpf
i i
jj f
Z Ad V BdV V
Cd Dd Z R
(3.19)
Defining (1) (1) pf
i iE V V and solving for fault location d we get:
(1) (1) (1) (1)
2 (1) 0
pf pfj ij j ij
f jj
AV BZ V ZABd C d D R Z
E E E
(3.20)
The unknown variables in (3.20) are d and fR and hence this equation is unsolvable.
However, it is possible to decompose (3.20) into real and imaginary parts to formulate
two equations so the fault location can be determined. In order to separate the real and
imaginary parts define the following:
1 2
ABC c jc
E (3.21)
(1) (1)
3 4
pf
j ijAV BZD c jc
E
(3.22)
(1) (1)
(1)
5 6
pf
j ij
jj
V ZZ c jc
E (3.23)
Then (3.20) is separated into:
2
1 3 5 0fc d c d c R (3.24)
2
2 4 6 0c d c d c (3.25)
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
78 |
The solution of (3.25) provides two possible values for d . The value lying between 0
and 1 is the fault location as it is the feasible solution. The other value is an unfeasible
solution (negative value or greater than 1 in the vast majority of cases). As can be seen
from (3.25), fault resistance is not needed to determine the fault location and can be
readily computed once the fault location has been determined. Overall, the quadratic
equation defining the fault location of three-phase symmetrical faults is a function of the
following positive-sequence parameters: 1) the transfer impedance between monitored
bus i and buses j and k , 2) the driving-point impedance of buses j and k , 3) the
impedance of the faulted line, 4) the pre-fault voltages at buses i , j and k and, 5) the
voltage during the fault at monitored bus i .
3.2.2 Fault Location of Line to Line Faults
For a fault between phases b and c, (1) (2) (0), 0f f fI I I holds, and the following applies:
(1)(1)
1 2
pf
tf
f tt tt
VI
R Z Z
(3.26)
(1)(1) (1) (1)
1 2
pfpf t
i i it
f tt tt
VV V Z
R Z Z
(3.27)
where
2 2(2) (2) (2) (2) 2 (2) (2) (2)2 2tt jj kk jk jj jk jjZ Z Z Z z d z Z Z d Z
(3.28)
being (2)
ijZ , (2)
jkZ , (2)
jjZ , (2)
jkZ , and (2)
kkZ the negative-sequence transfer impedance
corresponding to buses i , j and k ; and 2
z the total negative sequence impedance of
line j k .
Let
2(2) (2) (2)2jj kk jkH Z Z Z z (3.29)
2 (2) (2)2 jj jkI z Z Z
(3.30)
Substituting (3.11), (3.12), (3.14), and (3.15)-(3.18), (3.29), and (3.30) into (3.27),
yields:
(1) (1)
(1) (1)
2 (1) (2)
pf
ij jpf
i i
jj jj f
Z Ad V BdV V
C H d D I d Z Z R
(3.31)
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
79 |
Recalling (1) (1) pf
i iE V V and solving for fault location d gives:
(1) (1) (1) (1)
2 (1) (2) 0
pf pfj ij j ij
f jj jj
AV BZ V ZABd C H d D I R Z Z
E E E
(3.32)
Similar to (3.20) for three-phase faults, the unknown variables in (3.32) are the fault
location and the fault resistance and hence the equation is unsolvable. However, it is
also possible to decompose (3.32) into real and imaginary parts to formulate two
equations so the fault location can be determined. In order to separate the real and
imaginary parts define:
7 8
ABC H c jc
E (3.33)
(1) (1)
9 10
pf
j ijAV BZD I c jc
E
(3.34)
(1) (1)
(1) (2)
11 12
pf
j ij
jj jj
V ZZ Z c jc
E (3.35)
Then (3.32) is separated into:
2
7 9 11 0fc d c d c R (3.36)
2
8 10 12 0c d c d c (3.37)
The quadratic equation (3.37) has two solutions for d , and the one lying between 0 and
1 corresponds to the fault location. The other one can also be a feasible solution but this
occurs rarely. Since fR is not included in this equation, the fault location can be
estimated without knowing the fault resistance, which can be readily computed solving
(3.36) once the fault location has been determined. The expression that determines the
fault location of line to line faults is a function of: 1) the positive-sequence transfer
impedance between monitored bus i and buses j and k , 2) the negative- and positive-
sequence driving-point impedance of buses j and k , 3) the negative- and positive-
sequence impedance of the faulted line, 4) the positive-sequence pre-fault voltages at
buses i , j and k and, 5) the positive-sequence voltage during the fault at monitored bus
i .
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
80 |
3.2.3 Fault Location of Line to Ground Faults
For a fault between phase a and ground, (0) (1) (2)
f f fI I I holds. Dividing (3.2) by (3.3)
yields:
(2) (2)
(0) (0)
i it
i it
V Z
V Z (3.38)
where
(0) (0) (0) (0)
it ij ik ijZ Z Z Z d (3.39)
(2) (2) (2) (2)
it ij ik ijZ Z Z Z d
(3.40)
Defining (2) (0)
i iG V V and utilizing (3.39) and (3.40), gives:
(2) (2) (2)
(0) (0) (0)
ij ik ij
ij ik ij
Z Z Z dG
Z Z Z d
(3.41)
The fault location is obtained solving (3.41):
(2) (0)
(0) (0) (2) (2)
ij ij
ik ij ik ij
Z GZd
G Z Z Z Z
(3.42)
As can be seen from (3.42), the linear equation describing the fault location of line to
ground faults is a function of: 1) the negative- and zero-sequence transfer impedance of
buses i , j and k , and 2) the ratio of negative- and zero- sequence voltage at bus i
during the fault.
3.2.4 Fault Location of Line to Line to Ground Faults
For a fault involving phase b and c to ground fault. The following holds:
2
(0) (1)
0 23
ttf f
tt tt f
ZI I
Z Z R
(3.43)
(1)(1)
2 0
1
0 2
pf
tf
tt tt f
tt
tt f tt
VI
Z Z RZ
Z R Z
(3.44)
0
(2) (1)
0 2
3
3
tt f
f f
tt tt f
Z RI I
Z Z R
(3.45)
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
81 |
Dividing (3.45) by (3.43) results in:
0(2)
(0) 2
3f tt f
f tt
I Z R
I Z
(3.46)
Using (3.2), (3.3), and (3.46) leads to:
0(2)(2)
(0) 2(0)
3it tt fi
i it tt
Z Z RV
V Z Z
(3.47)
where
0 0(0) (0) (0) (0) 2 (0) (0) (0)2 2tt jj kk jk jj jk jjZ Z Z Z z d z Z Z d Z
(3.48)
being (0)
ijZ , (0)
jkZ , (0)
jjZ , (0)
jkZ , and (0)
kkZ the zero-sequence transfer impedance
corresponding to buses i , j and k ; and 0
z the total zero sequence impedance of line
j k .
Let
0(0) (0) (0)2jj kk jkJ Z Z Z z (3.49)
0 (0) (0)2 jj jkK z Z Z (3.50)
By employing (3.28)-(3.30), (3.39)-(3.41), and (3.48)-(3.50), (3.47) becomes:
(2) (2) (2) 2 (0)
(0) (0) (0) 2 (2)
3ij ik ij jj f
ij ik ij jj
Z Z Z d Jd Kd Z RG
Z Z Z d Hd Id Z
(3.51)
Define the following two terms:
(0) (0)
ik ijR Z Z (3.52)
(2) (2)
ik ijS Z Z (3.53)
Rearranging (3.51) using (3.52) and (3.53) yields:
2 2 0
0 0 23 2
2 0
0 2
3...
3... 0
ij ij jj f
ij ij jj
ij jj f
ij jj
JZ KS KZ SZ SRJSd HR d HZ IR d IZ RZ
G G G
Z Z RZ Z
G
(3.54)
Then define:
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
82 |
13 14
JSHR c jc
G
(3.55)
2
0
15 16
ij
ij
JZ KSHZ IR c jc
G
(3.56)
2 0
0 2
17 18
ij jj
ij jj
KZ SZIZ RZ c jc
G
(3.57)
19 20
3Sc jc
G (3.58)
0 2
0 2
21 22
jj ij
ij jj
Z ZZ Z c jc
G (3.59)
2
23 24
3 ijZc jc
G
(3.60)
Applying (3.55)-(3.60) and separating (3.54) into real and imaginary part produces:
3 2
13 15 17 21 19 23 0fc d c d c d c c d c R (3.61)
3 2
14 16 18 22 20 24 0fc d c d c d c c d c R (3.62)
Fault resistance can be calculated from (3.61) as:
3 2
13 15 17 21
19 23
f
c d c d c d cR
c d c
(3.63)
Substituting (3.63) into (3.62) results in:
4 3 2
25 26 27 28 29 0c d c d c d c d c (3.64)
where
25 14 19 13 20c c c c c (3.65)
26 14 23 16 19 13 24 15 20c c c c c c c c c (3.66)
27 16 23 18 19 15 24 17 20c c c c c c c c c (3.67)
28 18 23 19 22 17 24 20 21c c c c c c c c c (3.68)
29 22 23 21 24c c c c c (3.69)
From the solutions of (3.64), the one falling between 0 and 1 is chosen as the fault
location estimate. The others are unfeasible solutions (negative values or greater than 1).
In very rare occasions though, a second feasible solution exists. In these cases the
correct fault location can be identified through voltage matching of multiple monitors.
Equation (3.64) shows that the fault location for line to line to ground faults is a bi-
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
83 |
quadratic function relating: 1) the zero- and negative-sequence transfer impedances
between monitored bus i and buses j and k , 2) the zero- and negative-sequence
transfer impedances of buses j and k , 3) the zero- and negative-sequence impedances
of the faulted line and, 4) the quotient of zero- and negative-sequence residual voltages
at bus i during the fault.
3.3 Enhanced Monitor Reach Area Algorithm
Fault location tests have been performed on the IEEE-RTS network using both the
original MRA method recapitulated in Section 3.1, and the enhanced version of the
original obtained by implementing the fault location algorithms reviewed in Section
Chapter 3 . Symmetrical and asymmetrical faults with different values of fault
resistance have been simulated at all buses and at different locations along the lines (i.e.,
0.25, 0.5, and 0.75 p.u. of each line length). The fault resistance values used for line to
line faults and three-phase faults were 0 Ω and 5 Ω, whereas for line to ground and line
to line to ground fault resistance values were 0 Ω, 5 Ω, 25 Ω, and 50 Ω.
The pseudo-measurements of the OSMP determined in [72] for the IEEE-RTS network,
i.e. the residual voltages registered by monitors at buses 3, 6, 8, and 17, were used to
formulate the equations of the fault location algorithm. Fault location equations were
developed for every line and a solution having a value between 0 and 1 was considered
as a possible fault location on the line. The potential fault locations determined by all, or
most of the monitors, constitute the list of fault location estimates of the enhanced
monitor reach area algorithm (EMRAA).
For the original MRA method, nine voltage thresholds were used to build the monitor
reach areas for each monitored bus. The voltage thresholds utilized range from 0.1 p.u.
to 0.9 p.u. in steps of 0.1 p.u. Fault positions on each bus and on ten uniformly
distributed points along every line were considered. Accordingly, the matrix
representing the monitor reach areas of the monitoring program has 4 rows (monitored
buses) and 354 columns (fault positions).
Fault location through the original MRA method was done by intersection of monitor
reach areas, which were selected according to the magnitude of the residual voltages
registered at the monitored buses. The fault positions encompassed by most of the
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
84 |
monitor reach areas were assumed as the most probable fault locations. This set of fault
positions common to all monitors constitutes the list of fault location estimates of the
original MRA method.
The mean, standard deviation, and the largest value of the number of fault location
estimates determined by both methods are compared in Table 3-3. Each row of the
Table pertains to a specific value of fault resistance, which is indicated in the first
column. In addition, the percentage of faults detected by each method is indicated in the
last two columns.
As can be seen from Table 3-3, the EMRAA outperforms the original MRA approach in
all cases. The average number of fault location estimates determined by the EMRAA
remains close to 19 in all instances, whereas the same measure for the original MRA
method ranges from 52 to 81. Moreover, much less variability in the number of
estimates can be expected from the EMRAA than from the original MRA method; the
standard deviation of the EMRAA stays around 4 while it varies between 68 and 88 in
case of the original MRA method.
The data in Table 3-3 also reveals that about 30% and 45% of faults with a value of
fault impedance of 25 Ω and 50 Ω, respectively, are not detected by the monitoring
program when using the original MRA approach. In contrast, the same monitoring
program estimates the location of all faults regardless of fault impedance values if the
EMRAA is employed.
The results of the application of EMRAA and the original MRA method on the IEEE-
RTS network corroborate that the former method is not affected by fault impedance.
Since higher values of fault impedance can cause shallower voltage sags, the use of
fixed voltage thresholds by the original MRA method prevents the detection of some
high-impedance faults.
Table 3-3 Number of Fault Location Estimates Determined Using Original MRA Method and Enhanced
MRA Algorithm (EMRAA)
Rf
(Ω)
Average Std. Dev. Max % Detection
EMRAA MRA EMRAA MRA EMRAA MRA EMRAA MRA
0 19.26 62.16 4.02 68.69 30 336 100 100
5 19.47 81.82 4.08 75.51 29 352 100 100
25 19.45 73.00 3.97 88.30 28 325 100 71.54
50 19.50 52.58 4.13 81.91 28 325 100 55.69
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
85 |
Another important fact is that since the locations along the lines where the faults were
simulated do not match the points used to build the monitor reach areas, none of the
fault location estimates provided by the MRA method can be the actual fault location.
By contrast, the EMRAA can determine the actual fault location without the use of
monitor reach areas.
The results of the fault location tests show that the EMRAA can be used to increase the
overall robustness of optimal sag monitoring programs. Enhanced fault detection and
location capabilities can be achieved implementing the EMRAA while keeping the
same number of monitors. This enhancement can lead to an increase in sag estimation
accuracy of OSMPs.
3.4 Enhancement of Sag Estimation Accuracy with
EMRAA
Additionally, more thorough simulation tests have been carried out on the IEEE-RTS
network to illustrate the accuracy enhancement of sag estimation that can be attained
through the implementation of the EMRAA. A total of 1000 faults obtained from Monte
Carlo simulation has been applied to the IEEE-RTS and the number of sags caused by
these faults has been estimated for all buses using the OSMP (monitors placed at buses
3, 6, 8, and 17). The list of inputs generated randomly from probability distributions
during the Monte Carlo experiment is presented in Table 3-4. It can be seen from this
data that most of the faults simulated were line to ground faults occurring on lines and
having an average fault resistance value of 25 Ω, plus or minus 5 Ω, or an approximate
range of 20 Ω to 30 Ω. As also shown in Table 3-4, the numeric values representing the
faulted lines, i.e. 1 to 33, and the faulted buses, i.e. 1 to 24, were drawn from uniform
distribution on the intervals [1,33] and [1,24], respectively.
The number of voltage sags at the 24 buses of the network was estimated using the
pseudo-measurements at buses 3, 6, 8, and 17 (OSMP) and applying the original MRA
method and the EMRAA. Sag magnitude estimation was performed with both methods
by calculating the average of the residual voltages corresponding to all the possible fault
locations determined following the procedures described in Section 3.3.
For the MRA method, the monitor reach areas of buses 3, 6, 8, and 17 for voltage
thresholds of 0.9 p.u. to 0.1 p.u. (in steps of 0.1 p.u.) were used. Two groups of monitor
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
86 |
reach areas, for 0 Ω and 5 Ω, were utilized for line to line and three-phase faults, and
five groups of monitor reach areas, for 0 Ω, 5 Ω, 10 Ω, 25 Ω, and 50 Ω, were applied
for line to ground and line to line to ground faults. In the MRA approach, the sets of
possible fault locations were defined by the intersection of these groups of monitor
reach areas of the triggered monitors.
With the EMRAA, the fault location algorithms described in Section Chapter 3 were
applied to each line using the voltage measurements at the four monitored buses after
the triggering of at least one monitor. Both fault location and fault resistance were
calculated with the fault location algorithm. The sets of possible fault locations for this
approach were built with the fault location estimates obtained by most of the monitors.
Table 3-4 Inputs Randomly Generated During Monte Carlo Simulation (1000 trials) and their
Corresponding Probability Distributions
Input Probability distribution
Type of fault 0.85 LG faults, 0.08 LL faults, 0.05 LLG faults, and 0.02
LLL faults
Faulted element: line or bus 0.98 line faults and 0.02 bus faults
Faulted line Uniform distribution on the interval [1,33]
Fault point on lines Uniform distribution on the interval [0,1]
Faulted bus Uniform distribution on the interval [1,24]
Fault resistance of LG and LLG faults Normal distribution: = 25 Ω, = 5 Ω
Fault resistance of LL and LLL faults Normal distribution: = 2.5 Ω, = 1 Ω
The System Average Rms-variation Frequency Index (SARFI) has been used to count
the number of voltage sags at every bus of the IEEE-RTS network. The SARFI90 index,
i.e. the number of voltage sags with a residual voltage of 90% or less, is presented in
Figure 3-6. The real number of events and the number of events estimated using the
EMRAA and the original MRA method are indicated with blue diamond, red square,
and green triangle markers, respectively.
As shown in Figure 3-6, the MRA method overestimates the SARFI90 index at all sites
except, of course, the monitored buses (3, 6, 8, and 17). The biggest overestimate is 278
events at bus 13 and the lowest is 6 at bus 22. A different trend is observed for the
EMRAA since sags are underestimated at most sites apart from buses 1, 2, 10 and the
monitored buses. The biggest discrepancy between real and estimated sags with the
EMRAA is 112 for bus 20 and the smallest is 6 for bus 13. This underestimation is
explained by the fact that a triggering threshold of 0.9 p.u. was also used to apply the
EMRAA.
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
87 |
Figure 3-6 Number of voltage sags with a residual voltage of 90% or less (SARFI90).
The better performance of the EMRAA can also be evidenced in Figure 3-7, where the
three SARFI80 indices are shown. It can be seen that the biggest overestimation by the
MRA method occurs at bus 14 where 349 sags are counted in excess of their true value.
The lowest underestimation by the EMRAA consists of 38 sags at bus 20.
Figure 3-7 Number of voltage sags with a residual voltage of 80% or less (SARFI80).
The actual and estimated SARFI70 indices are shown in Figure 3-8. The number of sags
estimated with the MRA method exceeds the actual number at eleven buses (9, 11, 12,
15, 16, 18-21, 23, and 24) and is inferior at nine buses (1, 2, 4, 5, 7, 10, 14, and 22). The
overestimation varies between 7 and 101 events and the underestimation range lies
between 1 and 35 events. The EMRAA overestimates the SARFI70 index at nine sites
(buses 14, 15, 18-24) by as much as 7 events and underestimates the index at nine buses
(1, 4, 5, 7, 9-11, 13, and 16) by 18 or less sags.
0
100
200
300
400
500
600
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
SA
RF
I90
ind
ex
Buses
REAL-SARFI 90 EMRAA-SARFI 90 MRA-SARFI 90
0
100
200
300
400
500
600
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
SA
RF
I80
ind
ex
Buses
REAL-SARFI 80 EMRAA-SARFI 80 MRA-SARFI 80
Chapter 3 • Optimal Monitor Placement for Voltage Sag Characterization
88 |
Figure 3-8 Number of voltage sags with a residual voltage of 70% or less (SARFI70).
3.5 Summary
In this chapter the leading optimal monitor placement method for voltage sag
characterization, the MRA method, was reviewed. Two important limitations of this
method were demonstrated. The first one is the potential loss of sag detection capability
of OSMPs when sag magnitude at monitored buses remains above 90% of nominal
voltage (the most used triggering threshold). The second one is the high variability in
the number of monitors that might be required to cover the same network for faults with
different characteristics. The underlying reason behind these limitations is the
susceptibility of the fault detection and fault location algorithms employed by the MRA
method to fault resistance, pre-fault voltage profile, and voltage sag thresholds. A fault
location method that can of overcome these limitations and enhance the robustness and
sag estimation accuracy of the MRA method was also reviewed. This robust fault
location method is then implemented in the original MRA method resulting in the
enhanced monitor reach area algorithm (EMRAA). The EMRAA will be used to
determine the optimal monitor placement for fault location in the next chapter.
0
20
40
60
80
100
120
140
160
180
200
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
SA
RF
I70
ind
ex
Buses
REAL-SARFI 70 EMRAA-SARFI 70 MRA-SARFI 70
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
89 |
Chapter 4
Generalized Formulation
of the Optimal Monitor
Placement Problem for
Fault Location
A fault location method that enhances the robustness of the MRA method was analyzed
in the previous chapter. The approach was used in [53] to develop a method for optimal
monitor placement for fault location. This method determines the minimum number of
monitors and identifies the best locations for installing power quality monitors, or any
other device with voltage measurement capabilities, in order to uniquely locate every
fault occurring throughout the network. This enables virtually exact voltage sag
estimation at all buses in the network. The method however has only been tested in a
simple 10-bus system and a generalized formulation applicable to an arbitrary system is
still missing.
This chapter reviews the optimal monitor placement for fault location proposed in [53]
and extends and generalizes its modeling approach. The generalized formulation
determines a set of generic linear constraints for the problem of optimal monitor
placement so it can be solved by integer linear programming. The generalization of the
optimal monitor placement for complete fault location observability in the system
represents the second original contribution of this research.
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
90 |
4.1 Optimal Monitor Placement for Fault Location
The problem of optimal monitor placement for fault location is defined as finding the
minimum number and optimal locations for monitors in a system so that the system is
completely observable [53]. It is necessary here to clarify exactly what is meant by
observable. In a fault location sense, a system is fully observable if all faults occurring
anywhere in the system are uniquely localized. A fault that is uniquely localized is one
for which only one fault location estimate is determined. Sets of fault location estimates
are obtained from single monitors or constructed from the intersection of sets of
multiple monitors.
Similar to the monitor placement for voltage sag characterization, the optimal monitor
placement problem for fault location has been formulated as an integer linear
programming problem with the following objective function:
1
MinimizeN
x x
x
r
M (4.1)
where xr is the cost of placing a monitor at bus x , M is a binary-decision-variable
vector of length N indicating the need for a monitor at bus x , and N is the number of
buses in the network. The entries of M are xm as shown below:
1 if a monitor is required at bus ,
0 otherwise x
xm x
(4.2)
The set of linear constraints that guarantee full fault location observability are derived
from a list of pre-defined fault points and the combinations of monitors that can
uniquely determine their location. A six-step procedure to generate the constraints for a
fault point, shown in Figure 4-1, and an example of a set of linear constraints have been
given in [53]. That example is reviewed here for illustration purposes and for a later
comparison.
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
91 |
Figure 4-1 Flowchart for generating constrains for fault point F1 (adopted from [53]).
The fictitious 4-bus network depicted in Figure 4-2 has been built to illustrate the
procedure to formulate the linear constraints. Assume that a fault is simulated at point α
and residual voltages at all buses are calculated. Next, the fault location equations
presented in [104] and reviewed in the previous chapter are solved for every line using
the voltage at each bus, i.e. a total of 16 equations are solved (four equations for each
bus). The solutions of these equations are then used to find the combinations of
monitors that identify point α as the only or most likely fault location. Lastly, the linear
constraints are derived from the combinations of monitors that can uniquely determine
the actual fault point α .
Figure 4-2 Sample 4-bus system.
As Figure 4-2 shows, bus 1 estimates only one fault location whereas the rest of buses
yield two estimates. The fault location estimate from bus 1 corresponds to the actual
fault location. Buses 2, 3, and 4 also locate the fault correctly but not uniquely. Bus 2
estimates an additional fault location at point β while buses 3 and 4 estimate a second
Obtain the residual voltage at each bus
Obtain set S1, the set of fault locations, using voltage at bus i
i = 1,…,N
Identify all the sets with a single element and record the
corresponding bus number
Obtain all the combinations of monitors that can uniquely determine
the fault location and record corresponding bus numbers
Simulate a fault at point F1
Derive the linear constraints based on the sets of recorded bus
numbers
1
2
3
4
α
β
γ
Fault location estimates of :
bus 1 bus 2 bus 3 bus 4
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
92 |
fault location at point γ . Accordingly, the sets of possible fault locations obtained from
buses 1, 2, 3, and 4, respectively are:
1 αS
(4.3)
2 α,βS
(4.4)
3 α,γS
(4.5)
4 α,γS
(4.6)
It is evident from these solution sets that:
1 1 2 1 3 1 4 2 3 2 4 αS S S S S S S S S S S (4.7)
The only element of 1S , the intersection of
1S and any other set, and the intersections of
2S and either 3S or
4S , are equal to α , the actual fault location. Thus, there are six
combinations of monitors that can uniquely determine fault point α and these are listed
in Table 4-1. It can be seen from this table that placing one monitor at bus 1, or two
monitors, the first one at bus 2 and the second one at bus 3 or 4, are sufficient to
uniquely locate fault point α . Mathematically, this constraint can be represented as:
1 2 3 2 4 1M M M M M (4.8)
Logical constraint (4.8) is modeled in [53] with binary variables 2_ 3M and
2_ 4M as:
1 2_3 2_ 4 1M M M (4.9)
2_3 2M M (4.10)
2_3 3M M (4.11)
2_3 2 3 1M M M (4.12)
2_ 4 2M M (4.13)
2_ 4 4M M (4.14)
2_ 4 2 4 1M M M (4.15)
Table 4-1 Single monitors and pairs of monitors required to locate fault α
Combination number First monitored bus Second monitored bus
1 1 1
2 1 2
3 1 3
4 1 4
5 2 3
6 2 4
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
93 |
If linear constraints (4.9)-(4.15) are satisfied fault point α becomes observable. Since
the overall aim of the optimization problem is the minimization of monitoring costs, one
monitor at bus 1 would be chosen as the most economical monitor combination (from
the six analyzed) that ensures observability of fault point α .
A procedure like the one described above should be followed to determine the full set of
linear constraints for all pre-defined fault points and all types of fault. For example, in a
1000-bus system, it is required to determine the fault location observability of almost
half a million of pairs of monitors or more than 166 million sets of three monitors.
Assume that the system has 1500 lines, 10 fault points are posed on each line, and that
all faults (15000) can be uniquely localized by 5 pairs of monitors. For this case 225000
linear constraints like (4.9)-(4.15) are generated for each type of fault. As can be seen,
formulating the linear constraints is the most arduous task of the optimal monitor
placement problem, especially for large systems, since it entails finding pairs of
monitors that can uniquely locate faults. In order to facilitate efficient formulation of
linear constraints the modeling approach proposed in [53] is extended and generalized
in the next section.
4.2 Generalized Formulation of the Optimal Monitor
Placement Problem
The substantial number of linear constraints that can be derived from the optimal
monitor placement problem for fault location can be reduced and integrated into a single
compact array that simplifies the original model. An approach similar to the one used in
[39] (and reviewed in the previous chapter) to formulate the optimal monitor placement
problem for voltage sag monitoring is utilized here. In this section, a new set of
variables is first introduced and then utilized to reformulate the optimal monitor
placement problem. The new formulation is applied first to the aforementioned 4-bus
sample network at the end of this section, and then to a much larger power network to
validate its suitability for application in realistic power systems.
4.2.1 Definition of new variables
Recalling Chapter 3 , the monitor reach area (MRA) of a monitor is defined as the area
of the network where the monitor can detect voltage sags caused by short circuit faults
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
94 |
[39]. In a similar fashion, the monitor location area (MLA) is defined here as the
observable area of a monitor or a combination of monitors, i.e. the area of the network
where a monitor or a combination of monitors can uniquely locate faults. The monitor
location areas of the network’s buses can be modeled as a binary matrix based on the
following conditions:
1, if a fault at is uniquely located by monitor combination 1;
0, otherwise 1ij
j i i Q
j F
MLA (4.16)
where i can represent one monitor or a combination of monitors, and j is a fault
position at a bus or on a line. The order of matrix MLA is Q F , where Q is the
number of combinations of monitors and F is the number of pre-defined fault
positions. The number of combinations having m monitors that can be obtained from a
network with N buses is given by (4.19).
!
! !
NC
m N m
(4.17)
The second variable introduced here is the indexing matrix L of size Q m whose
purpose is to list the buses of each combination of monitors. The monitor location area
and the monitoring indexing matrix corresponding to the 4-bus sample network (see
Figure 4-2) have the following structure (fictitious values have been used for fault β
and γ ):
st nd
1
2
3
4
5
6
7
8
9
10
1 monitor 2 monitor α β γ
1 1 1 0 0
1 2 1 1 1
1 3 1 1 0
1 4 1 0 0
2 2 0 0 1
2 3 1 1 1
2 4 1 0 1
3 3 0 1 0
3 4 0 0 0
4 4 0 1 0
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
L MLA
The indexing matrix has been built for single buses and pairs of buses, i.e. for 2m .
The two values of each row iQ denote the buses where monitors are placed. A
progressive numeration is used to fill the entries of matrix L , so that all pairs of
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
95 |
monitors involving bus 1 are listed first, followed by pairs having bus 2, then bus 3, and
finishing with bus 4. Therefore, the first combination of L , 1Q , represents only one
monitor placed at bus 1. The next pair, 2Q , refers to two monitors, the first one at bus 1
and the second one at bus 2. The last pair of monitors having one monitor at bus 1 is 4Q
in which the second monitor is at bus 4. Since the pair of monitors representing
measurements at buses 1 and 2 is already covered by 2Q , the pseudo-pair
5Q ,
representing one single monitor at bus 2, is the first one starting with bus 2. 6Q is the
pair that places monitors at buses 2 and 3. This numeration continues so that the
penultimate pair 9Q , represents monitors at buses 3 and 4, and the last set,
10Q ,
corresponds to just one monitor at bus 4.
The six combinations of monitors that locate fault point α can be identified readily by
means of the matrix representation of the monitor location area. In addition, the total
number of pairs of monitors that locate fault point α can be determined by adding up
the elements of the first column of the matrix. In general, the sum of a column of the
monitor location area matrix gives the total number of monitor combinations that locate
a given fault, whereas the sum of one of its rows provides the total number of faults that
a specific combination of monitors locates.
The third variable defined here is a binary vector, similar to M , to handle the decision
of placing monitors at the buses of monitor combinations. The entries of this vector take
the following values:
1, if meters are placed at buses of combination
0, if meters are not placed at buses of combination i
i
i
P ; 1i Q (4.18)
A causal relationship between variables M and P must be enforced so that every value
of P causes a change in M . For example, in the 4-bus network 1 1P should entail one
monitor placed at bus 1, that is 1 1M . If 4 1P , 1 1M and 4 1M must be satisfied,
which requires placing monitors at buses 1 and 4.
4.2.2 Reduction of Number of Constraints
It was shown in [104] and [53] and that a single monitor provides a set with more than
one fault location estimate in some cases and thus combinations of two, three or more
monitors must be used to derive a unique fault location estimate. Clearly, a unique fault
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
96 |
location estimate can be obtained when the intersection of no more than two sets of
possible fault locations contains only one fault location estimate, and therefore two
monitors at most are required to derive a unique fault location estimate for every fault in
any network. For this reason the number of monitor combinations to be analyzed is
limited to the number of pairs of monitors in the system. Under this new principle, the
total number of monitor combinations that need to be considered in the formulation of
the optimization problem for a network with N buses is:
!
2! 2 !
NQ N
N
(4.19)
That is, the total number of monitor combinations is given by the sum of the number of
buses of the system and the number of pairs of monitors that can be obtained from the
system. This premise reduces considerably the number of monitor combinations to be
studied and consequently the number of constraints of the optimization problem.
4.2.3 Problem Formulation
The new variables defined in the previous sections i.e. L , MLA , P , and Q provide the
framework for generalizing the formulation of the optimal monitor placement problem.
Objective function (4.1) therefore, has to be optimized subject to the following general
linear constraints:
1
1,C
ij i
i
j
MLA P (4.20)
10,
ii i LP M (4.21)
20,
ii i L
P M (4.22)
1 2
1,i i i i L LM M P
(4.23)
where i represents the i-th combination of monitors and j the j-th pre-defined fault.
Constraint (4.20) ensures that all faults simulated in the system are uniquely located by
at least one monitor or a pair of monitors. Indexing matrix L is used in inequalities
(4.21)-(4.23) to enforce the causal relationship between variables M and P .
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
97 |
4.2.4 Application in the 4-bus Sample System
The generalized formulation of the optimal monitor placement problem has been
applied to the 4-bus sample system. The combinations of monitors that can uniquely
determine fault point α are 1, 1,2, 1,3, 1,4, 2,3, and 2,4. The compliance
of these combinations with constraints (4.20)-(4.23) has been verified. Table 4-2 shows
the values of these constraints solved for the six combinations. The first and second
columns of Table 4-2 show monitored buses and monitor combinations, respectively;
the rest of the columns show the values of the restrictions. It is apparent from this table
that all monitoring solutions satisfy the constraints of the general formulation of the
optimal monitor placement problem. Minimization of monitoring costs guarantees that
the optimal solution is 1. In the next section, the generalized model is further
validated through its implementation on much larger systems.
Table 4-2 Compliance of monitoring solutions of the sample system of 4-bus system (Figure 4-2) with
generic linear constraints
iM iP
Value of constraint
(4.20)
Value of constraint
(4.21)
Value of constraint
(4.22)
Value of constraint
(4.23)
1 1 1 0 0 1
1, 2 2 1 0 0 1
1, 3 3 1 0 0 1
1, 4 4 1 0 0 1
2, 3 6 1 0 0 1
2, 4 7 1 0 0 1
As it has been shown, the proposed generalized formulation for the optimal monitor
placement for fault location yields the same results as the original modeling approach
presented in [53] for the 4-bus sample system. In the next section, the generalized model
is further validated through its implementation on much larger systems.
4.3 Application in Large Power Networks
The generalized model developed in the previous section has been used to determine the
minimum monitoring programs required for full fault observability in three systems, the
10-bus network used in [53], the IEEE reliability test system (RTS) [106], and the IEEE
118-bus power flow test case [97]. The optimal monitoring programs have been
determined employing FICO’s Xpress optimization suite [107].
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
98 |
4.3.1 10-bus 500 kV Power Network
As stated before, the groundwork for the proposed generalization of the optimal monitor
placement problem was established in [53]. There the method was tested in the
transmission network depicted in Figure 4-3. The network consists of 10 buses, 10 lines,
and 5 generators. The network data is also given in [53] and is provided in Appendix A.
Prefault voltages were assumed to be 1 p.u. as in the original study.
Figure 4-3 Line segments (length is labeled) of the system used in [53] where faults cannot be uniquely
located with 2 monitors.
In [53] fault points were defined at every 2 miles on each line and since the length of
lines is not equal, each line had a different number of fault positions. The line
connecting buses 5 and 6 is the longest of the network (86.81 miles) and thus it is the
one having the greatest number of fault positions (44). In order to build a uniform
monitor location area, 44 fault positions were defined on all lines in an equidistant
manner. Since there are 10 single monitor locations and 45 pairs of monitors, the total
number of monitor combinations is 55. Under these considerations the monitor location
area of the network is represented by a 55 × 44 binary matrix.
Table 4-3 shows the optimal monitoring programs determined with both the original and
the enhanced formulation proposed in this thesis. The main difference between the
results obtained with both approaches is the minimum number of required monitors.
The original modeling approach determines that 3 monitors are required to locate all
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
99 |
types of faults while the generalized formulation finds that 2 monitors are sufficient for
the same purpose. The discrepancy between results has been further investigated.
Table 4-3 Optimal monitoring programs obtained with original and proposed formulations for the
sample system of Figure 4-3
Fault
Type
Optimal monitor locations (3)
obtained with original formulation
Optimal monitor locations (2)
obtained with generalized formulation
LG 1,3,6,3,6,7,3,7,8,
3,7,10,1,3,10,1,3,8
1,6,1,8,1,10,6,7,7,8,7,10
LL 1,3,6,3,6,7,3,7,8,
3,7,10,1,3,10,1,3,8
1,6,1,8,1,10,6,7,7,8,7,10
LLG Any single bus 1,3,1,4,1,5,1,6,1,8,1,9,1,10,
3,7,4,7,5,7,6,7,7,8,7,9,7,10
LLL 1,3,6,3,6,7,3,7,8,
3,7,10,1,3,10,1,3,8
1,6,1,8,1,10,6,7,7,8,7,10
All
types
1,3,6,3,6,7,3,7,8,
3,7,10,1,3,10,1,3,8
1,6,1,8,1,10,6,7,7,8,7,10
Examples of LG and LLL faults declared in [53] as observable only through 3 monitors
are shown in Table 4-4. The locations of these faults are in the unobservable segments
depicted in Figure 4-3. The second column of Table 4-4 present the estimated locations
of LG faults previously found in [53], i.e. using voltage at buses 1 and 3. The third
column shows the fault location estimates determined with the generalized formulation
and using voltage from bus 6. Similarly, the last two columns of Table 4-4 list the
estimated locations of LLL faults found in [53], i.e. using voltage at buses 3 and 6, as
well as the fault location estimates determined using voltage at bus 1. The results, as
shown in Table 4-4, confirm that a LG fault at 5 miles from bus 5 on line connecting
bus 5 and bus 8 cannot be uniquely localized using voltage at buses 1 and 3, but that a
unique fault location can be derived based on voltage measurements from bus 1 and bus
6 or from bus 3 and bus 6. The same conclusion can be drawn for a LG fault at 2.68
miles from bus 5 on line connecting buses 5 and 6.
Table 4-4 Fault location estimates [from-bus, to-bus, mile] using voltage at buses 1, 3, and 6 of the
sample system of Figure 4-3
Monitored
bus
Actual location of LG faults Actual location of LLL faults
[5,8,5.0] [5,6,2.68] [1,2,43.95] [2,7,41.0]
1 [5,8,5.0],
[5,6,2.68]
[5,6,2.68],
[5,8,5.01]
[1,2,43.95] [2,7,41.0],
[4,5,11.85]
3 [5,8,5.0],
[5,6,2.68]
[5,6,2.68],
[5,8,5.01]
[1,2,43.95],
[2,7,40.95]
[1,2,8.58],
[2,7,41.0]
6 [4,5,27.20],
[5,8,5.0]
[5,6,2.68] [1,2,43.95],
[2,7,40.95]
[1,2,8.58],
[2,7,41.0]
1, 3 [5,8,5.0],
[5,6,2.68]
[5,6,2.68],
[5,8,5.01]
[1,2,43.95] [2,7,41.0]
1, 6 [5,8,5.0] [5,6,2.68] [1,2,43.95] [2,7,41.0]
3, 6 [5,8,5.0] [5,6,2.68] [1,2,43.95],
[2,7,40.95]
[1,2,8.58],
[2,7,41.0]
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
100 |
The data from Table 4-4 also confirms that voltage measurements from bus 3 and bus 6
are not sufficient to determine uniquely the location of a LLL fault simulated at 43.95
miles from bus 2 on line connecting bus 1 and bus 2. However, monitors placed at buses
1 and 3 or at buses 1 and 6 are able to pinpoint the location of this fault and the location
of a LLL fault at 41 miles from bus 2 on line connecting bus 2 with bus 7. It is stated in
[53] that the four faults analyzed in Table 4-4 (2 LG and 2 LLL) required at least 3
monitors to be uniquely localized. Nevertheless, as Table 4-4 shows, voltage
measurements from bus 1 and bus 6 yield intersects of a unique element for these faults.
Furthermore, it was found that monitors at buses 1 and 6 constitute an optimal solution
for full observability of all types of faults in the 10-bus system, as Table 4-3 shows. The
difference in results from the proposed formulation and [53] can be attributed to
difference in the criteria used to select valid fault location estimates. The solutions of
the fault location equations for LG faults can be complex numbers hence a maximum
tolerance for the imaginary part must be set to validate a fault location estimate. The
maximum tolerance used in this study was 1×10-6
but no information regarding the
criteria to validate fault location estimates is given in [53].
4.3.2 IEEE 24-bus Reliability Test System (RTS)
The optimal monitoring locations for fault location have been determined with the
generalized modeling approach for the IEEE reliability test system. The network
consists of 24 buses, 33 lines, 10 generators, 5 transformers, and 1 synchronous
condenser. The system parameters were taken from [106] and are provided in Appendix
A. Prefault voltages were assumed to be 1 p.u at all buses and 10 fault points were
distributed uniformly on every line and thus the total number of fault positions is 330.
In addition to the 24 single monitoring locations, 276 pairs of monitors can be drawn
from the IEEE-RTS and therefore the total number of monitor combinations is 300. The
resulting monitor location area for each type of fault is a 300 × 330 binary matrix.
The number of monitors was minimized subject to constraints (4.20)-(4.23). It was
found that the minimum number of monitors required to uniquely pinpoint the location
of all simulated faults is 2. Apart from pair 7, 8 any pair of monitors can be used to
determine the location of all types of fault occurring throughout the network. That is,
placing a monitor in any 2 buses other than 7 and 8 makes the IEEE reliability test
system fully observable with respect to fault location. Figure 4-4 depicts the lines where
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
101 |
faults can be uniquely located using the voltage measurements from buses 7 and 8. All
types of faults occurring on the line connecting these two buses can be localized. In
addition, the location of phase-to-phase and three-phase faults can be uniquely
identified if these occur on line connecting buses 17 and 22. Phase-to-phase-to-ground
faults can be pinpointed when they take place on line between buses 21 and 22. For the
rest of the network multiple fault location estimates are derived using the voltage
measurements from buses 7 and 8.
Figure 4-4 Observable lines by monitors installed at buses 7 and 8 in the IEEE-RTS.
4.3.3 IEEE 118-bus Test System
The IEEE 118-bus test system represents a portion of the electric power system in the
Midwestern USA dating back to 1962 [97]. The network consists of 35 generators, 118
buses, 177 transmission lines, and 9 transformers. The system data is provided in [97]
and reproduced in Appendix A. A prefault voltage profile equal to 1 p.u was taken
1 2 7
4 5
3 9
24 11 12
10
8
6
15
14
16
17
19
13
18
23
20
21 22
S.C.
LLG faultsAll types of faultsLL and LLL faults
138 kV 230 kV
V
V
V Voltage measurement
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
102 |
across the network. Three fault points were allocated at 0.25, 0.50, and 0.75 on every
line. The total number of fault positions is 531. Taking into account individual monitor
locations and pairs of monitors, the total number of monitor combinations is 7021. The
binary matrix representing the monitor location area for this case has 7021 rows and 531
columns.
Table 4-5 provides the minimum number of monitors and their optimal position in the
network required to locate all LL, LLG, and LLL faults. It was found that 2 monitors
suffice to determine the exact location of these types of faults. There are 204 pairs of
monitors that can pinpoint both LL and LLL faults. The first monitored bus can be any
of the 102 buses listed in the top row of the second column of Table 4-5, whilst the
second monitored bus can be either bus 111 or bus 112. This means that in order to
achieve full fault location observability of LL and LLL faults, the voltages at bus 111 or
bus 112 should be measured along with the voltages at one of the 102 buses enumerated
accordingly in Table 4-5.
In the case of LLG faults, 989 pairs exist that can locate the 531 LLG faults simulated in
the IEEE 118-bus system. Almost all buses of the system can be an optimal location for
a monitor if they are paired with a second optimal location as indicated in the second to
fifth rows of Table 4-5. The only non-optimal monitoring buses of the system are 70 to
73, 77, 100, and 117 (7 in total). A comparison between the optimal combinations of
monitors presented in Table 4-5 reveals that 192 pairs are common to all sets of
monitors. These pairs of monitors are presented in the last row of Table 4-5.
Table 4-5 Optimal pairs of monitor locations required for full observability of LL, LLG and LLL faults
in the IEEE 118-bus test system
Type of fault Alternative locations for first
monitor
Alternative locations for second
monitor
LL and LLL 1-93, 95, 96, 98,102, 113-116, 118 111, 112
LLG 1-69, 74-76, 78-92, 94-96, 98-99, 102 103-112
LLG 93 104, 105, 107
LLG 97, 101 103, 110, 112
LLG 103-112 113-116, 118
LL, LLG, and
LLL 1-69, 74-76,78-92,95,96,102,113-116, 118 111, 112
The optimal monitoring program to locate LG faults is described in Table 4-6. It was
determined that 13 monitors is the minimum number of voltage measurements required
to ensure complete fault location observability of LG faults. It was also found that it is
mandatory to install monitors at buses 39, 41, 67, 84, 88, 93, 95, 97, and 117, otherwise
the system becomes unobservable. Apart from these nine the remaining four optimal
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
103 |
monitor locations must be selected singly from four different sets of monitors. The tenth
monitored bus should be either 78 or 79; the eleventh measurement has to be at bus 101
or bus 102; the possible locations for the twelfth monitor are buses 111 or 112; and the
buses to place the thirteenth monitor are 114 or 115.
Table 4-6 Optimal monitor program to locate LG faults in the IEEE 118-bus test system
The overall optimal monitoring schemes for fault location are shown in
Table 4-7. Full observability of all types of faults requires 13 monitors. The 16 sets of
13 monitors that locate LG faults also cover LL, LLG, and LLL faults. The deployment
of the optimal monitoring scheme is depicted in Figure 4-5, which can be seen as the
graphical representation of Table 4-6.
Figure 4-5 Optimal monitoring locations that lead to full fault observability of the IEEE 118-bus system.
Required locations for
1st to 9
th monitors
Alternative locations for
10th
monitor 11th
monitor 12th
monitor 13th
monitor
39, 41, 67, 84, 88,
93, 95, 97, 117 78, 79 101, 102 111, 112 114, 115
Chapter 4 • Generalized Formulation of the Optimal Monitor Placement for Fault Location
104 |
Table 4-7 Optimal monitoring programs for locating all types of fault in the IEEE 118-bus test system.
(Complement to monitors fixed at buses 39, 41, 67, 84, 88, 93, 95, 97, and 117)
No. Additional optimal monitor locations No. Additional optimal monitor locations
1 78,101,111,114 9 79,101,111,114
2 78,101,111,115 10 79,101,111,115
3 78,101,112,114 11 79,101,112,114
4 78,101,112,115 12 79,101,112,115
5 78,102,111,114 13 79,102,111,114
6 78,102,111,115 14 79,102,111,115
7 78,102,112,114 15 79,102,112,114
8 78,101,112,115 16 79,101,112,115
4.4 Summary
A generalized formulation for optimal monitor placement for fault location is proposed
in this chapter. This formulation determines a set of generic linear constraints for the
problem of optimal monitor placement so it can be solved by integer linear
programming. This set of linear constraints can be derived for any power system
network from its monitor location area, which is introduced in this chapter to
characterize the overall fault location observability of the system. The principle that a
maximum of two monitors are sufficient in order to correctly locate any fault leads to a
significant reduction of linear constraints in the problem. The generalized formulation
determines the minimum number of voltage measurements and their optimal location
required to pinpoint any type of fault occurring throughout the network. Simulation
studies performed in several test systems validate the proposed formulation. However,
an optimal monitoring program for full fault observability of the 295-bus GDS network
could not be obtained due to high computer memory usage. Therefore a much less
memory intensive metaheuristic method capable of finding a solution in any case has
been developed in the next chapter.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
105 |
Chapter 5
Heuristic Approach for
Determining Optimal
Monitor Placement for
Voltage Sag Estimation
In Chapter 4 a generalized formulation for the optimal monitor placement problem for
fault location was developed. The optimization problem was formulated as an integer
linear programming problem. Although optimal monitoring programs were found for
the IEEE 24-bus reliability test system (RTS) and the IEEE 118-bus power flow test
system using the generalized model, a global optimal solution could not be found in the
295-bus generic distribution system (GDS) due to high computational memory usage.
For this reason a less memory intensive method to determine fault location monitoring
schemes is developed in this chapter. The base of this method is a greedy algorithm that
searches for set of monitors which cover the entire network. Three custom objective
functions have been formulated and incorporated into the greedy algorithm to enhance
its robustness and assess the sag estimation accuracy of limited monitoring programs.
The proposed approach is tested in the IEEE 118-bus test system and in a 295-bus
generic distribution system (GDS). The test results show the practical efficiency of the
developed method. This heuristic approach for monitor placement represents the third
original contribution of this thesis.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
106 |
5.1 Review of Proposed Formulation of Optimal Monitor
Placement for Fault Location
The fundamentals of the method developed in the previous chapter are reviewed briefly
in this chapter for completeness of discussion and as it forms a basis for the
development of the new algorithm. The optimal monitor placement problem for fault
location has been formulated as an integer linear programming problem as follows:
1
1, ; 1, ,C
ij i
i
j j F
MLA P (5.1)
subject to:
10, ; 1, ,
ii i i Q LP M (5.2)
20, ; 1, ,
ii i i Q LP M (5.3)
1 2
1, ; 1, ,i i i i i Q L LM M P
(5.4)
where
F number of pre-defined fault positions;
1iL first monitored bus of pair i ;
2iL second monitored bus of pair i ;
xM binary-decision-variable vector of length N indicating the need for a monitor at
bus x ;
MLA monitor location area of all buses in the network;
N number of buses in the network;
iP binary-decision-variable vector of length Q indicating the need for monitors at
the buses indicated by pair i ;
Q number of pairs of monitors that can be drawn from the system;
xr cost of placing a monitor at bus x .
Although the generalized optimal monitor placement method is proven to yield
satisfactory results, its implementation in large systems can be hampered due to the
existence of a prohibitively great number of monitor combinations to be analyzed. For
example, if during the optimization process a set of 21 monitors is found as the best
current solution in a 300-bus system, an exhaustive search might be necessary to verify
if a set of 20 monitors is a feasible (and better) solution. The upper bound of this search
space would be greater than 7.5×1030
combinations.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
107 |
The memory usage required to solve the optimal monitor placement problem in realistic
size power systems can be so intensive that convergence might not be achieved. This
means that the sets of monitors found are not guaranteed to be an optimal solution. Most
importantly, in some cases no solution can be found at all. For this reason a heuristic
search algorithm, which is faster and less memory intensive, is proposed here to ensure
that a solution is always obtained regardless of the system’s size and, as will be
demonstrated, is also capable of obtaining optimal set of monitors for fault location.
5.2 The Greedy Search Algorithm
Solving the linear integer programming problem of optimal monitor placement utilizing
an enumerative method such as Branch and Bound can lead to computational explosion,
which hinders finding an optimal solution. Therefore a simple, yet effective greedy
search algorithm that requires a much lesser usage of computational resources can be
used. For this purpose, a reconsideration of the optimal monitor placement problem as a
minimum set cover problem is introduced next.
5.2.1 Set-Covering Problem
An instance ,U F of the set-covering problem consists of a finite set U and a family
F of subsets of U , such that every element of U belongs to at least one subset in F :
S
U S
F
(5.5)
Assume that a subset S F covers its elements. The problem is to find a minimum-size
subset F whose members cover all of U :
S
U S
(5.6)
Any subset satisfying equation (5.6) covers U . The size of is the number of sets it
contains, rather than the number of individual elements in these sets, since every subset
that covers U must contain all U individual elements. An example ,U F of the
set-covering problem is illustrated in Figure 5-1, where U consists of 12 black points
and 1 2 3 4 5 6, , , , ,S S S S S SF . The minimum set cover is 3 4 5, ,S S SF , with size 3.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
108 |
Figure 5-1 Illustration of set-covering problem.
The set-covering problem is an optimization problem that models many problems that
require resources to be allocated [108], e.g. monitors in a network [109]. In the decision
version of the set-covering problem, it is determined if a set cover of size n exists,
where n is an integer given in the problem. The decision version of set covering is NP-
complete, and the optimization version of set cover is NP-hard [108], meaning that is
not possible to find an optimal solution in polynomial time. For this reason, polynomial-
time approximation algorithms are required to find near-optimal solutions. The greedy
algorithm is possibly the most used strategy in the set cover problem [110].
5.2.2 The Greedy Algorithm
The greedy algorithm applies naturally to the set cover problem: iteratively pick the set
S that covers the greatest number of remaining elements that are uncovered [108].
Figure 5-2 shows the flowchart of the greedy algorithm. The algorithm work as follows.
The set X contains, at each stage, the set of remaining uncovered elements. The set
contains the cover being constructed. In every iteration a subset S that covers as many
uncovered elements as possible is chosen. After S is selected, the covered elements are
removed from X , and S is placed into . The algorithm terminates (in polynomial
time) when all elements of X have been covered. The outcome is the set that
contains a subfamily of F that covers X .
In the example of Figure 5-1, the greedy algorithm produces a cover of size 4 by
selecting, in order, the sets 1S , 4S , and 5S , followed by either 3S or 6S . As it can be
seen, the greedy algorithm might fail to find the optimal solution, nevertheless this type
of algorithm is essentially the best available for the minimum set cover problem [110].
S3 S5S4
S6
S2
S1
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
109 |
Figure 5-2 Flowchart of the greedy approximation algorithm.
5.2.3 Application of the Greedy Algorithm to the Optimal
Monitor Placement Problem
Recalling the characteristics of both optimal monitor placement problems for fault
location and for sag detection, it can be observed that such problems are equivalent to
the optimization version of the minimum set cover problem. The finite set U can be
seen as the set of fault positions to be located or the faults causing voltage sags below a
given threshold; F can be a collection of subsets of faults positions located/detected by a
monitor or groups of monitors; and would be a minimal set of monitors able to locate
or detect all the fault positions of U . Hence, finding a minimal subset is equivalent
to finding a set of monitors which uses the fewest monitors to either locate all faults or
detect all sags with a given magnitude.
The application of the greedy algorithm to both monitor placement problems is
straightforward: at each stage (see flowchart of Figure 5-2), select the combination of
monitors which contains the largest number of non-located/detected fault positions.
Since the space search is limited to the MRA matrix in the sag detection problem and to
the MLA matrix in the fault location problem, the computational burden is considerably
lower than the one entailed by enumerative methods.
X = U
Γ = Æ
Select an S F that maximizes |S X|
X = X – S; Γ = Γ È S
X ≠ Æ
End
Yes
No
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
110 |
The greedy algorithm has been implemented in the 295-bus GDS network to obtain sets
of monitors that cover all the faults causing voltage sags. The heuristic search has also
been applied to the 118-bus test system to determine groups of monitors required for
full fault location observability. The results of both tests have been compared to the
optimal sag monitoring programs (OSMP) and the optimal fault location monitoring
programs (OFLMP) found in Chapter 3 and Chapter 4 , respectively. Table 5-1 and
Table 5-2 compare the results obtained from a linear programming-based branch-and-
bound algorithm and the greedy algorithm; the former for full sag observability of the
GDS network and the latter for full fault location observability of the IEEE 118-bus
network.
It can be seen from the data in Table 5-1 that the greedy algorithm obtains the optimal
number of voltage measurement devices in 13 out of 15 cases analyzed. The only two
cases where the greedy algorithm does not provide the minimum number of monitors
are for voltage sags having magnitude of 0.8 p.u. and 0.7 p.u. or less and caused by
faults with fault resistance of 5 Ω. In both instances, shaded in green in Table 5-1, the
greedy algorithm determines one monitor in excess of the minimum required, that is 31
monitors for voltage sag threshold of 0.8 p.u. and 41 monitors for threshold of 0.7 p.u.
The results presented in Table 5-1 correspond to base loading profile but similar results
were obtained for the rest of the loading profiles (low, high, and pre-fault voltages equal
to 1 p.u.) since the maximum surplus determined by the greedy algorithm remained at
one monitor.
Table 5-1 Number of Voltage Measurement Devices Required for Sag Detection in the GDS Network
Rf
(Ω)
Linear programming Greedy algorithm
thV (p.u.) thV (p.u.)
0.90 0.80 0.70 0.90 0.80 0.70
0 7 11 16 7 11 16
5 16 30 40 16 31 41
10 24 32 22 24 32 22
25 19 19 21 19 19 21
50 13 14 9 13 14 9
As Table 5-2 shows, a simple greedy algorithm is also capable of yielding the same
results as a linear programming-based algorithm when optimal fault location monitoring
programs are determined. In all instances the heuristic method found the same minimum
number of measurement devices as its analytical counterpart.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
111 |
Table 5-2 Number of Voltage Measurement Devices Required for Full Fault Location Observability of
the IEEE 118-bus Network
Type of fault Linear programming Greedy algorithm
Line to ground 13 13
Line to line 2 2
Line to line to ground 2 2
Three phase 2 2
All types 13 13
The results obtained with the greedy algorithm establish that this less memory intensive
heuristic approach can be used to obtain optimal and near-optimal monitoring programs.
Two inherent characteristics of the greedy algorithm, namely, the simplicity of its
objective function and its iterative procedure have been further exploited to gain insight
into the accuracy of sag estimation trough limited monitoring programs. This
development is shown in the next section.
5.3 Greedy Monitor Placement with Custom Objective
Functions
As has been demonstrated previously, the use of the greedy algorithm to obtain
monitoring programs consists of selecting iteratively the monitor that covers the largest
number of uncovered fault positions until all fault positions have been included. This
procedure, in its simplest form, provides in each iteration only two data: the best bus to
place a voltage measurement device and the percentage of the network covered by the
addition of this device in terms of fault location or voltage sag detection. The network’s
coverage gained by the addition of monitors enables to prioritize the installation of new
monitors in networks where some monitoring already exists; moreover, it can be further
exploited to obtain more information, particularly regarding the estimation of sags
caused by uncovered faults, by means of custom objective functions incorporated into
the greedy search algorithm.
Three new objective functions have been developed to assign different types of values
to the solutions found in each iteration of the greedy algorithm. The aim is to determine
fault location monitoring programs based on the degree of observability of faults and
sag monitoring programs according to sag estimation accuracy.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
112 |
5.3.1 Observability Weight Factors
The first custom objective function has been designed to identify the less observable
sections of the network, i.e. the areas where faults are localized or voltage sags are
detected by only few monitors, based on weighting factors assigned to every fault
position. The observability weight factor of a fault position is defined as in equation
(5.7) for the fault location problem and as in equation (5.8) for the sag detection
problem.
1
1j C
ij
i
w
MLA
(5.7)
1
1j N
ij
i
w
MRA
(5.8)
In the fault location problem, the weight factor of a fault position is given by the inverse
of the sum of the number of monitor combinations that locate such fault position,
whereas in the sag detection problem the weight factor is given by the inverse of the
sum of the number of monitors that detect the voltage sag caused by the fault at this
position. A fault position located by many monitors has lower weight than one located
by few monitors. In the same way, a position where faults cause voltage sags detected
by many monitors has lower weight than a position where faults lead to sags triggering
fewer monitors. The weighting of fault positions represents a measure of the
observability of each fault position and can be readily integrated into the greedy
algorithm.
The flowchart for implementing the proposed weighted search algorithm is
fundamentally the same as the flowchart of the original greedy algorithm with the
addition of the custom objective function, as shown in Figure 5-3. The algorithm work
as follows. The vector X is initialized with all the pre-defined fault positions to be
covered; vector W includes the observability weight factors of all the fault positions in
X . The monitoring program to be built can either be an optimal sag monitoring
program (OSMP) or an optimal fault location monitoring program (OFLMP). In every
iteration the bus that maximizes the sum of the observability weight factors of the
uncovered fault positions S is selected as the best place for a voltage measurement
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
113 |
device. The search terminates when all fault positions are uniquely located or all voltage
sags are detected. The outcome is a monitoring program obtained from MLA or MRA
that covers X .
In summary, with the weighted search algorithm monitors are selected based on both the
number of faults localized or sags detected and the respective degree of observability.
Since the space search is limited to the binary matrices MLA or MRA , the
computational burden is considerably lower than the one entailed by enumerative
methods.
The size of several sag monitoring programs determined for the GDS network by the
proposed weighted greedy algorithm is shown in Table 5-3. The number of
measurements optimized using linear programming and the simple greedy algorithm is
also presented for comparison. In nine of the eleven cases where the simple greedy
algorithm overestimates the size of the monitoring programs, the weighted version of
the algorithm determines correctly the minimum number of monitors required. In the
other two instances, shaded in green in Table 5-3, the weighted algorithm obtained the
same number as the simple greedy algorithm (one more than the minima).
Figure 5-3 Flowchart for implementing the weighted greedy algorithm.
X = 1, 2,…, F;
OSMP = Æ; OFLMP = Æ; W
X = X – S; OSMP = OSMP È i
or OFLMP = OFLMP È i
X ≠ Æ
End
Yes
No
Select bus i whose S MLA or MRA
maximizes W S X
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
114 |
Table 5-3 Number of Voltage Measurement Devices Obtained by Three Different Methods
Loading
profile
Rf
(Ω)
thV
(p.u.)
Linear
programming
Simple greedy
algorithm
Weighted greedy
algorithm
Low 0 0.8 11 12 12
Low 5 0.8 30 31 30
Low 5 0.7 41 42 41
Medium 5 0.8 30 31 30
Medium 5 0.7 40 41 40
High 5 0.8 30 31 30
High 5 0.7 40 41 40
1 p.u. 0 0.7 18 19 18
1 p.u. 5 0.9 22 23 22
1 p.u. 25 0.9 35 36 36
1 p.u. 25 0.7 25 26 25
Table 5-4 compares the measurement placement for the IEEE 118-bus network
performed by simple and weighted greedy algorithms. The bus selection sequence, the
value of the weighted objective function, and the coverage of the network of the two
algorithms are contrasted in this table. Both techniques produce the same optimal fault
location monitoring programs (number and positions of monitors) but they differ in the
monitor placement sequence on account of the objective functions used in each
approach. The simple greedy algorithm finds the buses for monitoring that maximize
the coverage of the whole network while the weighted algorithm determines the buses
that maximize the coverage of the less observable areas of the network. Although
different objective functions were used to select the optimal buses for monitoring, all
the values presented in Table 5-4 correspond to the objective function of the weighted
greedy algorithm, i.e. the sum of the observability weight factors of uncovered faults.
The simple greedy algorithm, as can be seen in Table 5-4, starts by selecting the pair of
buses 78 and 111, where the presence of measurement devices leads to location of faults
in the largest area of the network (95.34%) but a relatively low value of the objective
function at 0.51, meaning that faults occurring in this area can be located by high
number of monitors. The weighted greedy algorithm instead, chooses only bus 117 as
the best initial site for voltage monitoring since its measurements are the only ones that
can be used to locate the faults occurring on the line connecting bus 117 with the rest of
the network (see Figure 5-4). For this reason, each of the three faults simulated on this
line have a weight factor equal to 1 and summed together they add 3 units of the
objective function in the first iteration.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
115 |
Table 5-4 Monitor Placement for Fault Location in the 118-bus Network Utilizing Greedy Algorithms
Order
Simple greedy algorithm Weighted greedy algorithm
Bus Objective
function
Percentage of
network covered Bus
Objective
function
Percentage of
network covered
1 78 and 111 0.51 95.34 117 3.01 4.66
2 101 0.56 95.90 111 3.47 94.55
3 114 0.62 96.46 39 3.55 95.39
4 39 0.69 96.88 41 3.62 95.81
5 41 0.77 97.30 67 3.70 96.23
6 67 0.85 97.72 84 3.79 96.65
7 84 0.92 98.14 88 3.85 97.07
8 88 1.00 98.56 93 3.93 97.49
9 93 1.08 98.98 95 4.01 97.91
10 95 1.15 99.40 97 4.10 98.32
11 97 1.23 99.81 78 4.14 98.88
12 117 4.24 100.00 101 4.19 99.44
13 — — — 114 4.24 100.00
After the first iteration, both heuristic algorithms continue selecting only single buses
until the coverage of the whole network is reached, which is equivalent to the objective
function having a total value of 4.24 units. The simple greedy algorithm terminates the
search one iteration before the weighted algorithm due to the selection of two buses in
the first iteration. The buses selected by the greedy algorithms are shown in Figure 5-4
and these conform to the optimal monitor placement determined in Chapter 4 .
Figure 5-4 Buses (red numbered) designated by greedy monitor placement algorithms as optimal
locations for voltage measurement devices.
117
114
84
88
95
93
101
111
78
4139
67
97
Faults on this line can only be
(uniquely) located by bus 117
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
116 |
Although it is apparent from Table 5-3 that in most cases the proposed weighted greedy
algorithm can obtain better results than the simple greedy algorithm, the main advantage
of the proposed approach resides in its much reduced computer memory usage since it
allows finding sets of monitors when linear programming fails to do so, for example in
the 295-bus GDS network.
The number of monitors required to locate each and all types of faults in the GDS
network is presented in Table 5-5. It can be seen that both approaches found that 8
monitors can locate all line to ground faults in the network. The weighted greedy
algorithm found that 16 monitors are sufficient to determine the location of line to line
and three phase faults. The memory requirements entailed by FICO’s Xpress
optimization suite are so vast that a PC with an Intel® CoreTM
2 Duo processor with a
2.00 GHz clock and with 4.00 GB of RAM ran out of memory while attempting to find
a solution for these two types of fault. With respect to line to line to ground faults, the
branch and bound search tree drawn by the commercial software kept growing after 1
hour of execution (more than 60000 active nodes were defined) and for this reason the
optimization was intentionally stopped after this period having found that 23 monitors
can estimate a unique location for this type of faults. The proposed search algorithm
also found 23 monitors in just few seconds. An optimal fault location monitoring
program for all types of faults was not found using Xpress due to its associated
computational and memory burden. The greedy algorithm determined that 25 monitors
suffice to localize all types of faults.
Table 5-5 Minimum Number of Monitors Required for Fault Location in the 295-bus GDS Network
Type of fault Linear programming Weighted greedy algorithm
Line to ground 8 8
Line to line No solution found 16
Line to line to ground 23 23
Three phase No solution found 16
All types No solution found 25
5.3.2 Sag Magnitude Estimation Error
The second custom objective function is aimed at assessing the sag estimation accuracy
of monitoring programs. It was shown in Chapter 3 that the enhanced MRA algorithm
(EMRAA) can pinpoint a fault or determine multiple estimates of its location, and
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
117 |
therefore the estimated voltage sag magnitude at bus i due to fault at point j can take
one of the following values:
1
1
,
,
,
ij
fpest k
ij ijfpk
pf
i
V
V V
V
if fault at point j is uniquely located
(5.9) if fault at point j has fp estimated locations
if fault at point j is not located
If a fault location can be pinpointed using the voltage measurements from one or more
buses, it is assumed that the estimated sag magnitude is the true value of the voltage sag
caused by the fault. If multiple estimates for the fault location are determined using the
set of voltage measurements available, the estimated sag magnitude is given by the
average of the voltage sags caused by the faults occurring at all the possible locations. If
the fault cannot be located, e.g. in the presence of a delta-wye transformer between the
monitored bus and the location of a single line to ground fault, no fault occurrence is
assumed and the estimated sag magnitude equals the pre-fault voltage.
The sag magnitude estimation error ( )SMEE is introduced here as a measure of the
overall sag estimation accuracy of a monitoring program and it is calculated as the
average percentage difference between the real and estimated magnitude of sags at all
buses:
1
1100,
real estN
ij ij
reali
ij
V VSMEE j
N V
(5.10)
where real
ijV and est
ijV are the real and estimated magnitudes of the sag at bus i caused by
a fault at point j , respectively. This error can be calculated for every phase and for each
type of fault.
The iterative process that builds optimal sag monitoring programs based on
minimization of the SMEE is similar to the greedy monitor placement procedures as
can be seen in Figure 5-5. The aim in each iteration is to determine the bus whose
voltage measurements can be used to reduce the SMEE to minimum. The voltage sag
magnitude at all buses is estimated according to (5.9) based on the location estimates for
all faults derived from a given bus. The SMEE is then calculated using (5.10) for the
three phases and for the four types of faults discussed previously. These operations are
executed using the measurements from each bus of the system. The bus for which the
SMEE results in the minimum is selected as the best voltage monitoring site. The
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
118 |
process is repeated incorporating the selected buses until the number of buses selected
equals the size of an optimal fault location monitoring program; by then all simulated
faults are uniquely located, i.e., the estimated magnitude of all sags are the true values
of the voltage sags and hence the SMEE is zero.
Figure 5-5 Flowchart detailing the process of building an optimal sag monitoring program (OSMP)
aimed at minimizing the sag magnitude estimation error (SMEE).
The results of applying the procedure explained above to the 295-bus GDS network are
presented in Table 5-6. As previously found (see Table 5-5), with eight monitors all
single line to ground faults can be located throughout the network and thus the SMEE is
zero. Over 33% of the network is covered by the first bus chosen for voltage monitoring
and five voltage measurement devices can locate line to ground faults in practically
99% of the network. The low standard deviation and the maximum error of 100%
obtained in every step indicate that the magnitude estimation of sags caused by faults
occurring outside the areas covered by the monitors is due to undetected faults. For
example, while the addition of the first monitor provides a virtually perfect estimation
( 0)SMEE of the sag magnitude in 33.45% of the network, the voltage measurements
of this monitor cannot be used to estimate the location of line to ground faults in the
remaining 66.55% of the network, i.e. faults are undetected leading to a SMEE of
OSMP = Æ;
nm = size of OFLMP
End
Yes
No
Calculate according to (3.9) for all
faults and for all buses.
est
ijV
Calculate SMEE according to (3.10) for
every phase and for all types of faults.
Select bus i that minimizes SMEE
OSMP = OSMP È i
Size of OSMP = nm
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
119 |
almost 100%. The selection of every bus for voltage monitoring is limited by its fault
location capability which is determined by the presence of delta-wye transformers in the
network in the case of line to ground faults.
Table 5-6 Sag Magnitude Estimation Error of Each Phase for Line to Ground Faults Occurring in the
GDS Network
Number
of buses
SMEE (%) Std. dev. (%) Maximum (%) Network
coverage (%) A B C A B C A B C
1 99.47 99.46 99.46 0.04 0.00 0.00 100 99.46 99.46 33.45
2 99.15 99.15 99.15 0.07 0.00 0.00 100 99.15 99.15 57.91
3 98.46 98.44 98.44 0.13 0.00 0.00 100 98.44 98.45 76.98
4 95.88 95.83 95.84 0.35 0.00 0.00 100 95.85 95.86 91.37
5 67.04 66.68 66.69 2.76 0.02 0.04 100 66.82 66.88 98.92
6 50.56 50.01 50.03 4.14 0.03 0.06 100 50.23 50.31 99.28
7 1.13 0.03 0.06 8.29 0.06 0.11 100 0.47 0.63 99.64
8 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.00
The influence of delta-wye transformers in the monitor placement is illustrated in Figure
5-6. The sections of the network covered by each selected bus are confined to the color
meshed areas. The size of the sections, relative to the whole network, and the sequence
in which buses are selected is also shown. A closer examination of the topology of the
network reveals that each section is isolated, in terms of location of single line to ground
faults, by a delta-wye transformer. For this reason, only monitors installed within these
sections can detect and locate single line to ground faults occurring at the buses and on
the lines encompassed by these areas.
The last three buses selected for monitoring are required to locate the faults occurring
on the lines connected to those buses. In the cases of the sixth and seventh monitor both
lines are connecting two buses where delta-wye transformers are attached, forcing the
deployment of a monitor at any end of the line. The last (eighth) monitor is
indispensable at the end of a feeder to obtain only one estimate for the location of line to
ground faults taking place on the line connecting the last two buses of such feeder.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
120 |
Figure 5-6 Proportions of the GDS network where line to ground faults can be located by the ordered
addition of voltage measurement devices.
2n
d:
25
%
4th
: 1
4%
5th
: 8
%
3rd
: 1
9%
8th
: 0
.33
%
1s
t : 3
3%
6th
: 0
.33
%
7th
: 0
.33
%
24
46
17
28
16
14
12
26
21
19
23
22
22
2
18
15
54
52
53
22
9
50
75
22
7
74
22
8
20
22
0
51
76
13
26
7
87
48
47
49
22
1
43
42
41
40
39
38
37
26
8
23
42
35
23
0
78
79
80
81
85
88
28
5
82
83
84
28
6
90
91
92
94
93
95
96
97
10
09
8 99
10
1
10
21
03
10
4
10
51
06
10
7
10
8
10
9
11
0
11
1
11
2
11
31
14
11
5
12
0
12
1
12
21
23
12
4
12
5
12
6
12
7
11
6
11
7
11
81
19
86
11
10
8
97654
55
1
65
64
63
57
22
52
26
58
14
8
14
6
15
3
15
4
14
91
52
15
5
14
71
45
14
4
14
0
14
2
14
1
14
3
13
9
13
8
12
8
12
91
32
13
0
13
4
13
61
35
13
7
13
3
15
6
16
0
15
7
18
5
18
3
13
1
15
9
16
4
16
1
16
2
16
3
16
5
16
6
16
71
68
16
9
17
9
18
0
18
11
82
18
4
18
6
18
7
18
8
18
91
90
19
1
19
2
19
3
19
6
19
7
19
91
98
20
0
20
1
20
22
03
20
4
20
5
20
6
20
72
08
15
0
15
1
22
3
23
1
77
15
8
22
4
21
4
21
5
21
0
21
12
09
21
2
21
3
21
6
21
71
70
21
8
21
9
17
1
17
2
17
3
17
4
17
5
17
6
17
7
62
60
59
61
2
3
72
70
17
8
25
27
29
30
32
31
33
34
35
36
71
68
67
69
73
89
45
44
24
82
49
26
52
66
24
1
25
1
25
9
28
4
23
6
24
3
26
0
25
0
24
02
44
24
52
42
26
12
71
26
92
52
27
32
70
27
52
74
26
22
63
27
2
23
9
25
32
57
25
52
58
27
6
24
6
27
7
24
7
27
923
3
27
8
23
22
54
25
6
28
82
87
28
92
90
29
22
91
29
42
93
29
5
26
42
37
28
3
23
8
28
22
80
28
1
56
13
2k
V
33
kV
11
kV
3.3
kV
27
5k
V
40
0k
V
66
18
2
18
3
18
41
85
18
61
87
18
81
89
19
0
19
1
19
2
19
31
94
19
51
96
19
71
98
19
92
00
20
1
20
2
20
3
20
42
05
20
6
20
7
20
8
20
9
21
0
21
1
21
2
21
3
21
4
21
5
21
6
21
72
18
21
92
20
22
1
22
2
22
32
24
22
5
22
6
22
7
22
82
29
23
02
31
23
2
23
3
23
4
23
52
36
23
72
38
23
92
40
24
1
24
2
24
3
24
42
45
24
6
24
72
48
24
92
50
25
1
25
2
25
3
25
4
25
5
25
6
25
7
25
82
59
26
0
19
426
1
19
526
22
63
26
42
65
26
62
67
26
8
26
9
27
0
27
12
72
27
4
27
52
78
27
3
27
62
77
1
2 8
33
34
5
5
6
7
9
10
11
12
13
13
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
9394
95
96
96
97
98
99
10
0
10
1
10
2
10
3
10
41
05
10
6
10
7
10
8
10
9
11
0
11
1
11
21
13
11
4
11
51
15
11
6
11
71
18 1
19
12
0
12
1
12
2
12
3
12
3
12
41
25
12
61
27
12
8
12
9
13
0
13
1
13
2
13
31
34
13
5
13
6
13
7
13
81
39
14
0
14
11
42
14
3
14
41
45
14
6
14
7
14
8
14
9
15
0
15
1
15
21
53
15
4
15
5
15
6
15
71
58
15
9
16
0
16
11
62
16
3
16
4
16
5
16
6
16
7
16
8
16
9
17
0
17
1
17
2
17
3
17
4
17
51
76
17
71
78
17
9
18
01
80
18
0
18
1
V
V
V
V
V
V
V
V
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
121 |
The overall SMEE calculated for all types of faults during the greedy monitor
placement is shown in Figure 5-7 along with the values of the standard deviation and
the largest errors. An almost constant reduction of the SMEE is achieved with the
addition of every measurement device. The comprehensive detection and estimation of
location of line to line and three-phase faults account for this steady reduction. Although
both the estimation error and the standard deviation remain under 5% from the seventh
monitor chosen, the maximum errors vary between 13% and 42% until the whole
network has been covered with 25 monitors.
Figure 5-7 Sag Magnitude Estimation Error (SMEE) obtained during each iteration of the greedy
monitor placement procedure.
The normalized size of the areas where faults can be located is depicted in Figure 5-8
according to the type of fault. Full fault location observability of line to ground faults,
representing 25% of the total coverage, is attained after the addition of ten monitors,
which can be used to locate 92% (23% of total) of line to line faults, 62% (15% of total)
of line to line to ground faults, and 91% (23% of total) of three-phase faults. All types
of faults can be localized anywhere in the network (each type of fault representing 25%
of the total coverage) once 25 buses have been selected.
The detailed data of Figure 5-7 and Figure 5-8 is presented in tabular form in Appendix
B. Tables containing the results of minimization of SMEE by greedy monitor
placement for each type of fault are also given in Appendix B.
0
10
20
30
40
50
60
70
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Perc
en
tag
e e
rro
r
Number of voltage measurement devices
SMEE Std dev. Maximum
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
122 |
Figure 5-8 Increase in network’s coverage of different types of faults obtained during each iteration of
the greedy monitor placement procedure.
5.3.3 Sag Event Estimation Error
The third custom objective function has been designed to jointly minimize the number
of monitors deployed and the number of sag events estimated at non-monitored buses.
The sag estimation at non-monitored buses is done by counting the number of sag
events based on the average of the residual voltages corresponding to all the possible
fault locations calculated following the procedures described in Section 3.3. The
accuracy of the sag estimation is given by the difference between the real and the
estimated number of sags. Voltage-tolerance curves such as CBEMA, voltage sag
immunity standards like SEMI F47, performance indices like SARFI-X, voltage quality
standards like EN 50160, or voltage-sag tables such as generalized sag table can be used
to specify the type of sags (sag characteristics) that the monitoring program will use for
assessment of the accuracy of the estimation. For example, the sag event estimation
error ( )SEEE for voltage sags specified by SARFI-X indices is calculated as:
1
- -N
rea est
i i
i
SARFI X SARFI X
SEEEN
(5.11)
where - rea
iSARFI X is the real number of voltage sags with magnitude equal to or less
than X at bus i , - est
iSARFI X is the estimated number of sags with the same
characteristics at bus i , and N is the total number of buses.
0
10
20
30
40
50
60
70
80
90
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Perc
en
tag
e o
f n
etw
ork
co
vere
d
Number of voltage measurement devices
LG faults LL faults LLG faults LLLfaults
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
123 |
An iterative search strategy similar to the ones previously described in sections 5.3.1
and 5.3.2 is used to determine sag monitoring programs that minimize (5.11). At every
iteration, the sag event estimation error at each bus is calculated and the bus with the
minimum error is chosen as the monitor location corresponding to that iteration. The
gradual search is run repeatedly increasing the number of monitors and reducing the
estimation error at each stage. The search is terminated when the SEEE has been
reduced to a pre-defined value or a pre-defined number of monitors have been placed.
Voltage sags with characteristics specified by the aforesaid voltage-tolerance and sag
immunity curves, sag performance indices, European standards, and voltage-sag tables
have been analyzed. The next five subsections describe the occurrence of these types of
sags in the GDS network. These descriptions are followed by the results of the greedy
monitor placement aimed at minimizing the SEEE of each of type of event.
5.3.3.1 Occurrence of voltage sags as classified by standard EN 50160
The European standard EN 50160 defines, describes, and specifies the characteristics of
the supply voltage in public electricity networks [111]. The standard classifies voltage
dips (sags) according to Table 5-7 for statistics collection. Typical values of sag
incidence for each cell of the table are not given due to the high spatial and temporal
variability of voltage sags. Nevertheless, the vast majority of voltage sags last less than
1 second and have a residual voltage above 40% [111] and thus most of the events will
typically lie in cells A1, A2, A3, B1, B2, B3, C1, C2, and C3. Moreover, the standard
suggests the use of Table 5-7 to identify the expected performance of the network and to
assess the probable behavior of the equipment connected. It is expected that equipment
tested according to product standards EN 61000-4-11 and EN 610000-4-34 will ride
through sags indicated in the cells A1, A2, B1, and B2 for class 2 equipment and A1,
A2, A3, A4, B1, B2, and C1 for class 3 equipment.
Table 5-7 EN 50160 classification of voltage sags according to residual voltage and duration (adopted
from [111])
Residual
voltage u (%)
Duration t (ms)
10 ≤ t ≤ 200 200 ≤ t ≤ 500 500 ≤ t ≤ 1 000 1 000 ≤ t ≤ 5 000 5 000 ≤ t ≤ 60 000
90 > u ≥ 80 Cell A1 Cell A2 Cell A3 Cell A4 Cell A5
80 > u ≥ 70 Cell B1 Cell B2 Cell B3 Cell B4 Cell B5
70 > u ≥ 40 Cell C1 Cell C2 Cell C3 Cell C4 Cell C5
40 > u ≥ 5 Cell D1 Cell D2 Cell D3 Cell D4 Cell D5
5 > u Cell X1 Cell X2 Cell X3 Cell X4 Cell X5
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
124 |
Faults occurring throughout the network can generally cause residual voltages as low as
0% in at least one bus. The duration of voltage sags, however, is mainly limited by the
fault clearing time of the protection scheme, which depends among other factors, on
voltage level. In the case when there is a significant presence of dynamic loads in the
network, induction motors in particular, sags can last longer than the time determined
by protection settings [112]. The maximum duration of the sag considered in this thesis
is assumed to be equivalent to the fault clearing time, and it can be used to determine if
a certain type of sag, as indicated in the cells of Table 5-7, can occur in the network.
The fault clearing times assumed for the GDS network are listed in Table 5-8. It can be
seen that the maximum duration of a fault is 300 milliseconds (ms) or 15 cycles barring
a protection system failure. Under this assumption most of the sags occurring in the
GDS network would appear in cells A1, A2, B1, B2, C1, and C2 and consequently the
monitoring program should be focused on these types of sags.
Table 5-8 Fault clearing times in the GDS network
Faulted element Voltage level (kV) Fault clearing time (ms) Fault clearing time (cycles)
Line 11 300 15
Line 33 150 7.5
Line 132 80 4
Bus 11, 33, and 132 60 3
5.3.3.2 Occurrence of voltage sags as classified by the ITIC Curve
The Information Technology Industry Council (ITIC), formerly known as the Computer
& Business Equipment Manufacturer’s Association (CBEMA) published the ITIC
Curve, which describes the AC input voltage envelope that can be withstood by most
information technology equipment (ITE) without interruption in their function [113]. In
terms of voltage sags the ITIC Curve describes a region of the composite envelope
where the normal functional state of the ITE can be disrupted but no damage to the ITE
should result. The No Damage Region encompasses events with duration between 20
ms and 500 ms and residual voltage of less than 70% of the nominal voltage. Since the
fastest fault clearing time specified in the GDS network is 60 ms and the longest is 300
ms (see Table 5-8 ) all voltage sags having residual voltage lower than or equal to 70%
lie in the No Damage Region as shown in Figure 5-9. Monitoring programs can also be
determined to minimize the estimation error of these types of sags.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
125 |
Figure 5-9 No Damage Region of the ITIC Curve.
5.3.3.3 Occurrence of voltage sags as classified by the generalized sag
table
The generalized sag table includes information about the three phase residual voltages
individually to provide a more comprehensive assessment of the sag performance
severity. The columns and rows of the table are divided in ten magnitude ranges in steps
of 10% from 0% to 100% of the nominal voltage. Intersections of columns and rows
then determine cells and the figures to be put in the cells refer to the number of
equivalent events with particular combinations of three-phase voltage magnitudes [114].
A sag profile of the GDS network has been constructed by simulating symmetrical and
asymmetrical faults (four types of faults) at 0.25, 0.50, and 0.75 of the length of each of
the 278 lines of the system (3 336 faults in total) and calculating the residual voltages of
the three phases at each of the 295 buses. Every fault simulated then causes sags with
different combinations of three-phase voltage magnitudes at every bus, i.e., every fault
event accounts for 295 sag events (984 120 sags in total). The generalized sag table built
from these results is shown in Figure 5-10. The majority of sags (62.48%) are non-
disruptive since the voltage in the three phases remain between 90% and 100% as can
be seen in the top rightmost cell (614 901 events). The three types of potentially
disruptive sags with the greatest number of occurrences are indicated with red ellipses
and these are:
1) Voltage sags with residual voltage in two phases between 40% and 50% and
residual voltage in third phase between 90% and 100%,
2) Voltage sags with residual voltage in two phases between 50% and 60% and
residual voltage in third phase between 90% and 100% and,
0
10
20
30
40
50
60
70
80
90
100
14-Apr-12 15-Apr-12 16-Apr-12 17-Apr-12 18-Apr-12
Perc
en
t o
f N
om
inal V
olt
ag
e
Duration in miliseconds
20 500 10000300
GDS sag ocurrence
region
No Interruption in Function Region
No Damage Region(but possible interruption)
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
126 |
3) Voltage sags with residual voltage in two phases between 90% and 100% and
residual voltage in third phase between 70% and 80%.
These types of sags constitute nearly 9% of the total number of events and can be
treated as an initial focus of a sag monitoring program.
Figure 5-10 GDS network’s voltage sag profile.
5.3.3.4 Occurrence of voltage sags as classified by SARFI indices
The System Average Rms-variations Frequency Index (SARFI), originally proposed in
[24], is a simple yet widely used approach to counting voltage sags with magnitudes and
durations outside of some specifications. For example, SARFI80 would provide a count
of all voltage sags with a residual voltage less than 80% of nominal (regardless of
duration). SARFIITIC would provide a count of all voltage sags exceeding the ride
through specifications of the ITIC Curve. Although the acronym expresses System
Average, SARFI indices are also used to quantify sag performance at individual sites.
Some selected SARFI indices have been calculated for three voltage levels in the GDS
network based on the fault simulations performed in the previous section. The results,
summarized in Table 5-9 as total and average number of events, show higher incidence
of sags at 11 kV sites than at 33 kV and 132 kV sites for all SARFI indices. Since every
SARFI index includes all the events counted by a lower SARFI index, e.g. SARFI40
includes all the events being counted by SARFI10, SARFI90 will always count the
highest number of events. This index (or any other) can be used to guide the sequential
monitor placement.
0 10 20 30 40 50 60 70 80 90 1000
10
20
30
40
50
60
70
80
90
100
Voltage in two phases (% of nominal)
Voltage in t
he t
hird p
hase (
% o
f nom
inal)
19239
120
126
6
114
0
285
804
282
10695
12
14550
18
24
6
9
51
513
219
5856
0
0
13281
0
363
1929
456
681
339
4080
6
0
0
8166
0
804
7059
4470
864
4653
198
69
0
0
7377
3
48
3180
558
38520
72
585
30
0
3
5193
0
36
900
27453
339
357
423
87
0
6
4338
0
3
7989
243
336
852
948
576
15
27
12846
309
5439
1671
1398
2787
2967
2043
579
384
4815
11538
18288
11367
5916
6357
10824
11265
8676
9954
21636
17316
614901
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
127 |
Table 5-9 SARFI indices for three voltage levels in the GDS network
SARFI index 11 kV (233 sites) 33 kV (25 sites) 132 kV (23 sites)
Total Average Total Average Total Average
SARFI90 334 542 1435.80 19 349 773.96 18 075 785.87
SARFI85 310 084 1330.83 15 999 639.96 15 921 692.22
SARFI70 255 788 1097.80 12 783 511.32 10 660 463.48
SARFI40 134 505 577.27 7 420 296.80 6 413 278.83
SARFI10 46 792 200.82 1 240 49.60 1 076 46.78
5.3.3.5 Occurrence of voltage sags as classified by the SEMI F47 Curve
Semiconductor Equipment and Materials International (SEMI®) is a global industry
association of manufacturers of equipment and materials used in the micro- and nano-
electronics industries, including semiconductors, photovoltaics, and LED, among
others. SEMI developed the SEMI F47 standard to define the voltage sag immunity
required for semiconductor processing, metrology, and automated test equipment [115].
The standard is shown in Figure 5-11. The equipment shut-down region of the SEMI
F47 was determined for the GDS network according to the maximum fault clearing
times presented in Table 5-8. This region is represented in Figure 5-11 as the area below
the SEMI F47 Curve limited by a dashed line, which represents the maximum fault
clearing time of the network (300 ms). The GDS sag occurrence region encompasses all
sags of 50% of nominal voltage occurring throughout the network and sags of 70% of
nominal voltage but caused by faults occurring only on 11 kV buses and lines.
Monitoring programs can be specially design to estimate the incidence of these types of
sags.
Figure 5-11 SEMI F47 Curve – required semiconductor equipment voltage sag immunity (adopted from
[116]).
0
10
20
30
40
50
60
70
80
90
50 200 350 500 650 800 950
Perc
en
t o
f E
qu
ipm
en
t N
om
inal V
olt
ag
e
Duration in milliseconds
GDS sag ocurrence
region
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
128 |
5.3.3.6 Results of monitor placement
Monitor placement aimed at minimizing the SEEE of the sags described above has been
performed in the GDS network. The following types of sags have been considered
individually:
1) Sags with residual voltage between 40% and 90% in any phase (EN 50160).
2) Sags with residual voltage of 70% or less in any phase (ITIC Curve).
3) Sags with residual voltage in two phases between 40% and 60% and residual
voltage in third phase between 90% and 100% and sags with residual voltage in
two phases between 90% and 100% and voltage in third phase between 70% and
80% (Generalized Sag Table).
4) Sags with a residual voltage of 90% or less in any phase (SARFI90 index).
5) Sags with a residual voltage of 50% or less in any phase and sags with a residual
voltage of 70% or less in any phase but caused by faults occurring only on 11
kV buses and lines (SEMI F47).
A total of 25 buses have been selected to reduce the event estimation errors to zero
(when full fault location observability is achieved) but only the results of the first 11 are
summarized in Table 5-10. Less than a third of the full monitoring program, i.e. eight
monitors cut down the SEEE to less that 4 events for all types of sags, being the
SARFI90 index error reduced the furthest (0.63). Adding three more monitors results in
a reduction of the SEEE to less than 0.5 for all types of sags with standard deviation
ranging from 0.25 to 1.16. This means that on average the difference between real and
estimated sags at all buses lies within 0 and less than 1 event for sags described by
standard EN 50160, ITIC Curve, Generalized Sag Table (GST), and SARFI90 index and
within 0 and less than 2 events for sags below the SEMI F47 Curve. Complete results of
the deployment of the full monitoring program and the minimization of SEEE for each
type of sag separately are provided in Appendix C.
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
129 |
Tab
le 5
-10
M
inim
izat
ion o
f th
e O
ver
all
Sag
Ev
ent
Est
imat
ion
Err
or
in t
he
GD
S N
etw
ork
wit
h G
reed
y M
on
itor
Pla
cem
ent
Chapter 5 • Heuristic Approach for Determining Optimal Monitor Placement for Voltage Sag Estimation
130 |
5.4 Summary
An optimal fault location monitoring program can lead to virtually exact sag estimation
at non-monitored buses. However, determining these monitoring programs for large
power systems by integer linear programming can fail due to the computational and
memory usage entailed, and in some instances no set of monitors can be found at all.
A heuristic methodology has been developed that ensures finding fault location and sag
detection monitoring programs where integer programming fails to do so due to
considerably less memory usage. The proposed methodology found optimal monitoring
programs (determined with integer linear programming) in most cases. In the few
instances where the heuristic approach failed to find the minimum number of monitors,
the size of the monitoring programs exceeded only by one the minima.
The methodology developed and presented in this chapter includes three custom
objective functions formulated for greedy monitor placement. The first objective
function is aimed at determining fault location monitoring programs based on the degree
of observability of faults. The second objective function is designed to assess the sag
magnitude estimation accuracy of limited monitoring programs; whereas the third
objective function advances the sag magnitude estimation into sag event estimation and
incorporates a range of sag performance indices that can be used in the design and
specification of monitoring programs.
The heuristic approach proposed for efficient monitor placement can be used to
determine a range of monitoring programs for estimating sag performance in the
network using different sag characteristics and sag benchmarking methodologies. This
feature offers the opportunity to utilities to choose a monitoring program specifically
designed to estimate, not only general sag performance in the network but also number
of sags with characteristics relevant to their customers, while balancing the accuracy
and the cost of the monitoring program.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
131 |
Chapter 6
Techno-Economic
Assessment of Voltage Sags
Using Optimal Monitoring
Programs
In Chapter 5 a heuristic monitor placement method with custom objective functions
aimed at reducing the sag estimation error at non-monitored buses was presented. It was
shown that the proposed method can determine both optimal and sub-optimal
monitoring programs even when linear programming does not achieve finite-time
convergence to a global optimum due to high memory requirements.
In this chapter a hybrid method to facilitate the identification of strategic sites for
voltage sag monitoring and estimation will be developed. The simplified hybrid method
combines the monitor placement methods for sag estimation and for fault location
reviewed in Chapter 3 and Chapter 4 , respectively. The work includes network
simulations to characterize voltage sags at non-monitored sites using the hybrid
monitoring programs and the assessment of the financial losses caused by voltage sags
utilizing a risk-based methodology. This hybrid method for assessing voltage sag
performance in the network using optimal monitoring represents the fourth original
contribution of this research.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
132 |
6.1 Hybrid Methodology for Monitoring and Estimation
of Voltage Sags
In Chapter 3 it was demonstrated that when triggering thresholds are used for monitors
to detect the occurrence of fault-induced voltage sags, high-impedance faults and
changes in the loading condition of the network can cause sag-events that the monitors
might fail to register. However, the enhanced MRA algorithm (EMRAA) also
developed in Chapter 3 can be implemented effectively by the same monitoring
program to overcome this limitation without the need of additional data. This section
describes how both monitor placement methods, for sag estimation and for fault
location, can be combined to determine a more flexible and cost-effective sag
monitoring program.
6.1.1 Selection of Most Probable Fault Location
A drawback common to all impedance-based fault location methods is the existence of
multiple estimates for the fault location due to the presence of laterals and branched
nature of the network. Since in most cases the residual voltages caused by faults
occurring at these multiple locations are very similar and close to the real ones, a safe
approach is to take the average of all the voltages as the expected residual voltage at
non-monitored buses [39]. The proposed approach, instead, select the most likely fault
location (only one) according to the type of fault. The criteria to select the most
probable fault location for each type of fault are described next.
6.1.1.1 Most Probable Fault Location of Line to Ground Faults
The most probable fault location of line to ground faults is selected by verifying the
numeric validity of all the estimates, i.e., they should be a real number between 0 and 1.
For example, equation (6.1), firstly presented in Section 3.2.3, defines the location of
line to ground faults and results in a complex number with a (relatively) significant
imaginary component when solved for lines other than the actual faulted line. A simple
yet sound principle to discard possible fault locations is checking their imaginary
component.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
133 |
(2) (0)
(0) (0) (2) (2)
ij ij
ik ij ik ij
Z GZd
G Z Z Z Z
(6.1)
The value of the imaginary part of the fault location estimates of 1650 line to ground
faults simulated in the IEEE 24-bus reliability test system was assessed. Ten faults
uniformly distributed on each line of the system were applied with fault impedance
values of 0 Ω, 5 Ω, 10 Ω, 25 Ω, and 50 Ω. The distribution of the values of the
imaginary parts corresponding to the actual fault location and the rest of the fault
location estimates is presented in Table 6-1. It can be seen that 99% of the values of the
actual fault locations are lower or equal than 0.5486×10-14
, which can be considered as
machine dependent round-off errors. Fault locations estimated on lines other than the
actual faulted line have considerable much higher imaginary components since 99% of
their values are within 3.58. A comparison of the two results confirms that only the
solutions corresponding to the actual fault locations have a negligible imaginary part.
Table 6-1 Percentiles of the Absolute Values of the Imaginary Parts of Fault Location Estimates
Percentile Actual fault location Rest of fault location estimates
25th 0.0035×10
-14 0.0127
50th 0.0082×10
-14 0.0437
75th 0.0179×10
-14 0.1077
99th 0.5489×10
-14 3.5804
6.1.1.2 Most Probable Fault Location of Line to Line to Ground Faults
The principle of zero imaginary part of fault location estimates cannot be applied to
identify the most probable fault location of line to line to ground faults because their
quartic (fourth-degree) fault location equation can have real roots between 0 and 1 for
lines other than the faulted lines. Probable locations for this type of fault can be ruled
out by comparing the measured voltage at the monitored bus to the calculated residual
voltage caused by simulating each possible fault. For example, the voltages at bus 12
during a line to line to ground fault with fault resistance of 50 Ω at 0.3636 on line
connecting buses 11 and 14 of the IEEE 24-bus reliability test system (RTS), are 1.0134
p.u. for phase a, 0.6237 p.u. for phase b, and 0.7439 p.u. for phase c. Applying the
enhanced fault location method results in 14 possible fault locations.
Table 6-2 lists the possible fault locations along lines and the magnitude of the residual
voltage of each phase at bus 12. The last column indicates the difference between the
calculated and the measured residual voltages at bus 12. It is apparent from this table
that the actual location and fault resistance can be correctly identified (shaded in gray in
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
134 |
Table 6-2) from a group of estimates since the minimum difference between simulated
and measured voltages at bus 12 correspond to the actual fault location.
The significant discrepancy between three-phase residual voltages is explained by the
use of the ratio between negative- and zero-sequence residual voltages in the location of
line to line to ground faults, as can be seen in equation (6.2), which is solved for d to
derive the quartic equation that determines the fault location. Equal values for this ratio
can be obtained with different complex values of negative-and zero-sequence residual
voltages at the monitored bus.
22000
02222
0
2 3
jjijikij
fjjijikij
i
i
ZIdHddZZZ
RZKdJddZZZ
V
V
(6.2)
It can be seen from the data in Table 6-3 that, although different negative- and zero-
sequence voltages are registered at bus 12 for each simulated fault, the ratio between
them is equal in all cases. The results presented in Table 6-2 and Table 6-3 show that
different combinations of fault locations and fault resistance can be determined as
potential fault locations for the same line to line to ground fault but that the actual fault
location can be distinguished from all the fault location estimates based on the
calculated residual voltages at monitored buses.
Table 6-2 Fault Location Estimates for a Line to Line to Ground Fault at 0.3636 on Line 14 of the IEEE-
RTS and the Corresponding Residual Voltages at Bus 12
Estimate Line Point fR
(Ω)
estimated
aV
(p.u.)
estimated
bV
(p.u.)
estimated
cV
(p.u.)
c
ax
estimated
x
real
x VV
(p.u.)
1 2 0.0032 3.92 0.905 0.680 0.827 0.248
2 3 0.0099 4.41 0.914 0.677 0.828 0.237
3 4 0.0056 4.30 0.911 0.676 0.828 0.238
4 5 0.6729 121.83 1.011 0.827 0.891 0.352
5 6 0.5151 94.94 1.012 0.776 0.856 0.266
6 7 0.4371 115.17 1.013 0.787 0.869 0.290
7 8 0.5726 97.68 1.014 0.721 0.834 0.188
8 11 0.6102 116.19 1.013 0.782 0.867 0.282
9 12 0.7213 111.73 1.014 0.741 0.848 0.221
10 13 0.9405 5.91 0.840 0.321 0.546 0.674
11 14 0.3636 50.00 1.013 0.624 0.744 0
12 17 0.9961 1.49 0.693 0.456 0.548 0.684
13 31 0.9856 1.49 0.693 0.456 0.549 0.683
14 32 0.9856 1.49 0.693 0.456 0.549 0.683
Results like the ones presented in Table 6-2 were obtained for 1650 line-to-line-to-
ground faults simulated in the IEEE 24-bus RTS. Ten faults uniformly distributed on
each line of the system were applied with fault impedance values of 0 Ω, 5 Ω, 10 Ω, 25
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
135 |
Ω, and 50 Ω. The difference between calculated and measured phase residual voltages
is shown in Figure 6-1 by means of box plots, one for every bus. On each box, the
central mark represents the median, the lower and upper edges of the box indicate the
25th
and the 75th
percentile, respectively, and the whiskers extend to the most extreme
data points not considered outliers. The calculated residual voltages correspond to faults
simulated at the fault locations estimated by each monitor. Measured voltages are the
ones corresponding to the actual fault location. Results for the 24 buses are included but
outliers have been neglected for the sake of clarity.
Table 6-3 Ratio between Negative-Sequence and Zero-Sequence Residual Voltages at Bus 12 for the
Fault Location Estimates of Table 6-2
Estimate (2)
12V (0)
12V (2) (0)
12 12/V V
1 0.0873 - j0.0763 0.0152 + j0.0038 4.2282 - j6.0791
2 0.0934 - j0.0777 0.0158 + j0.0044 4.2282 - j6.0791
3 0.0920 - j0.0783 0.0158 + j0.0042 4.2282 - j6.0791
4 0.0932 - j0.0284 0.0103 + j0.0081 4.2282 - j6.0791
5 0.1209 - j0.0344 0.0131 + j0.0108 4.2282 - j6.0791
6 0.1130 - j0.0358 0.0127 + j0.0098 4.2282 - j6.0791
7 0.1464 - j0.0487 0.0167 + j0.0125 4.2282 - j6.0791
8 0.1154 - j0.0376 0.0131 + j0.0099 4.2282 - j6.0791
9 0.1354 - j0.0465 0.0156 + j0.0114 4.2282 - j6.0791
10 0.2638 - j0.1212 0.0338 + j0.0199 4.2282 - j6.0791
11 0.2113 - j0.0476 0.0216 + j0.0198 4.2282 - j6.0791
12 0.1101 - j0.0608 0.0152 + j0.0075 4.2282 - j6.0791
13 0.1095 - j0.0607 0.0152 + j0.0075 4.2282 - j6.0791
14 0.1095 - j0.0607 0.0152 + j0.0075 4.2282 - j6.0791
Figure 6-1 Difference between calculated and real phase residual voltages of line to line to ground faults
on the IEEE-RTS.
As can be seen from Figure 6-1, differences between calculated and real residual
voltages occur in all buses of the IEEE-RTS. The highest dispersion in voltage
discrepancy is observed at buses 14 to 17. The voltage difference at these buses can be
higher than 0.45 p.u. For example, the lowest value, the median, the 75th
percentile, and
the highest value of bus 16 is 0.0 p.u., 0.1 p.u., 0.2 p.u., and 0.49 p.u., respectively,
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Buses
0
0.4
0.2
0.1
0.15
0.05
0.3
0.25
0.35
0.45
Dif
fere
nc
e in
vo
lta
ge
s (
p.u
.)
0.5
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
136 |
which means that half of the discrepancies are lie between 0 and 0.1 p.u., an additional
25% of the discrepancies range from 0.1 p.u. to 0.2 p.u., and the remaining differences
are between 0.2 p.u. and 0.49 p.u. The box plots of buses 1, 2, and 7 can be interpreted
in a similar way. It can thus be seen that these buses show the lowest variation in
voltage differences, typically below 0.1 p.u.
6.1.1.3 Most Probable Fault Location of Line to Line and Three-phase
Faults
The absence of the ratio between negative- and zero- sequence residual voltages in the
fault location formulation of line to line and three-phase faults gives rise to the
estimation of potential fault locations with practically equal residual voltages. The
negligible differences among voltages were confirmed by calculations. Therefore, the
selection of the most probable fault location is simply limited to the one presenting the
minimum difference between calculated and measured voltages at all monitors.
The most probable location of 6600 faults (1650 for each type of fault including fault
impedance values of 0, 5, 10, 25, and 50 Ω) was determined using the residual voltages
at bus 12. It was found that with the proposed approach 100% of line to ground and line
to line to ground faults and 62% of line to line and three-phase faults are correctly
localized. Figure 6-2 shows the difference between calculated and real magnitude of the
sags caused by the faults that were not correctly localized (38%). It can be seen that
75% of the errors in sag magnitude estimation lie below 0.08 p.u. and the remaining
estimation errors are less than 0.19 p.u. As stated in Chapter 4 (section 4.3.2), the
addition of one more monitor in the network suffices the correct location of all faults in
the IEEE-RTS and consequently the elimination of sag estimation errors.
Figure 6-2 Difference between calculated and real magnitude of sags caused by line to line and three-
phase faults not correctly localized using the residual voltages from bus 12.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
137 |
6.1.2 Hybrid Monitor Placement Method
The approach proposed in this chapter combines the monitor placement methods for sag
estimation and for fault location reviewed in Chapter 3 and Chapter 4 , respectively.
Given that now the selection of the most probable fault location is based solely on the
attributes of fault location estimates, rather than on triangulation by multiple monitors
(like existing methods for sag estimation and fault location), the only constraint for
determining the proposed monitoring program is to ensure that all faults are detected by
at least one monitor, as an optimal sag monitoring program determined by the MRA
method. However, the detection of faults must be accomplished using the EFL method.
The new and simplified monitor placement problem is an integer linear programming
problem formulated as:
1
MinimizeN
x
x
M
1
Subject to : , 1, ,N
x
x x y x y
M MLA (6.3)
where MLA is the monitor location area defined for the generic formulation of the
optimal fault location monitoring problem in Chapter 4 . In this new formulation
though, MLA has the same size as the monitor reach area MRA defined in Chapter 3
since no combination of monitors are considered.
MLA matrices are built for each type of fault using the respective fault location
equations. There is no need to have a unique fault location estimate in an MLA because
only single monitors are taken into account.
The use of the row-reduced version instead of both, the original MLA matrix and the
MRA matrix, offers significant advantages over the last two; it is not affected by
different voltage thresholds and it indicates the areas of the network where faults can be
located. Both features along with the algorithm for cutting down the number of fault
location estimates can increase the accuracy of sag performance estimation and reduce
the number of monitors required for such purpose.
The sag monitoring program obtained by this approach is the minimum set of monitors
that not only can detect voltage sags throughout the network but can also pinpoint the
location of the faults that cause those sags regardless of their magnitude. Although
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
138 |
faults are not located uniquely, the actual fault location is selected correctly from a list
of possible estimates in the vast majority of cases and when it is not, the sag magnitude
estimation error incurred is negligible.
6.1.3 Simplified Voltage Sag Estimation
The system sag performance is estimated by determining the most probable fault
location from the set of potential fault locations for every fault detected and according
to the type of fault. For line to ground faults, the potential fault location having the
minimum value of the imaginary part is considered as the actual fault location.
For line to line, line to line to ground, and three-phase faults, faults are simulated at the
potential locations and with the estimated fault resistance. The most probable fault
location is the one which has the closest calculated residual voltages to the measured
voltages by all voltage measurement devices of the monitoring program. Although this
can result in the incorrect selection of the fault location, the error incurred in the sag
performance estimation is tolerable in large majority of the cases (as previously shown).
Distinctions should be made at this point between the proposed approach and the fault
location observability analysis and the associated monitor placement for fault location
presented in [53]. Even though both approaches aim to find a unique location estimate
for all faults, the method introduced in [53] chooses the most probable fault location
from the intersection of sets of potential locations of several monitors, whereas with the
proposed method such estimate is selected by evaluating the difference between
calculated voltages and measured voltages and the imaginary component of the fault
location estimate.
The dissimilarity in the procedure of each method leads to the most significant
difference between the two which is the total number of monitors required. The
proposed method utilizes only a fraction of the number of monitors demanded by the
method developed in [53] as it is shown in the next section.
6.2 Case Study 1: Assessment of Voltage Sag Events
The first case study has been performed to corroborate the sag event estimation
accuracy of the hybrid monitor placement method through stochastic simulation. The
cost-effectiveness of the hybrid method is also demonstrated with a comparison of the
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
139 |
number of voltage measurement devices required by the proposed and existing
approaches. The study was carried out in the 295-bus generic distribution system with a
pre-defined set of six fault positions distributed uniformly along all lines and taking into
account all types of faults.
6.2.1 Size of Monitoring Programs
The minimum number of monitors required to estimate the voltage sags caused by the
aforesaid set of faults and the minimum required to locate them was determined in
Chapter 3 and Chapter 5 , respectively. In addition, the number of voltage
measurements for full observability of the system (in the state estimation sense) has
been obtained using the topology-based method proposed in [117].
The size of each monitoring scheme is shown in Table 6-4. It can be seen that full
observability of the system for state estimation requires the greatest number of monitors
(68) followed by the optimal fault location monitoring program (28). As previously
determined in Chapter 3 (see Section 3.1.4), the size of the optimal sag monitoring
programs developed with the MRA method ranges from 7 to 45. The number of
monitors required for sag estimation using the proposed hybrid method is 8, equivalent
to the monitoring scheme required to locate all line to ground faults determined in
Chapter 5 (see Figure 5-6).
Table 6-4 Number of Voltage Measurement Devices Required for Distinct Functions in the 295-bus
GDS
Function Number of monitors
Voltage sag estimation Between 7 and 45
Unique fault location 28
State estimation 68
Sag estimation with non-unique fault location (Hybrid approach) 8
6.2.2 Sag Event Estimation
The sag monitoring program determined with the MRA method for a voltage threshold
of 0.7 p.u., consisting of 16 monitors and the 8 monitors obtained with the proposed
approach have been tested and compared through Monte Carlo simulation. In each
simulation a random number of faults is generated from the Poisson distribution and
based on the system fault statistics shown in Table 6-5. For faults simulated on lines the
fault point along the line is also randomly selected from a uniform distribution. This
ensures that the location of every fault simulated on a line is different from the six fault
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
140 |
positions used to determine the monitoring programs. The fault resistance of each fault
is randomly assigned. It is assumed that the fault resistances follow a normal
distribution with mean μ = 15 Ω and standard deviation δ = 4.5 Ω [90].
Three loading profiles have been considered during the simulations [80]. The
probability distribution and loading factors of these loading profiles are shown in Table
6-6. The pre-fault voltages corresponding to each loading profile were determined using
Matpower. For each simulated fault the loading profile and the associated pre-fault
voltage profile were assigned according to Table 6-6. A fourth loading profile
equivalent to 105% of the base loading profile was used in all calculations to test the
robustness of the method when pre-fault voltages are estimated.
Table 6-5 System Fault Statistics (adopted from [90])
Fault location Fault rate/year Fault distribution according to fault type
LG (73%) LL (6%) LLG (17%) LLL (4%)
Bus 0.08 0.0584 0.0048 0.0136 0.0032
132 kV line 0.6 0.438 0.036 0.102 0.024
33 kV line 3.7 2.701 0.222 0.629 0.148
11 kV line 8.7 6.351 0.522 1.479 0.348
11 kV cable 4.9 3.577 0.294 0.833 0.196
Table 6-6 Probability of Occurrence of Loading Profiles (adopted from [80])
Loading profile Load factor Probability
High load 110% 0.1250
Base load 100% 0.5417
Low load 90% 0.3333
A total of 100 simulations, each representing one year of system performance, were
executed. The residual voltages of all the faults simulated were calculated and the
voltages at monitored buses were used as pseudo-measurements to identify the most
probable fault locations and the number of sags was estimated based on these estimates.
The difference between the actual number of sags at all buses and the number estimated
using the voltage measurements of each monitoring program is shown in Table 6-7 for
two types of sags; voltage sags falling in the region of undervoltage conditions of the
ITIC curve are presented in the second and third columns and sags with magnitude of
0.9 p.u. or less of the nominal voltage (SARFI-90%) are shown in the fourth and fifth
columns. Results are presented in percentiles, each indicating the percent of buses in
which the difference between real and estimated number of sag events falls below a
certain value, for example, the fourth row of Table 6-7 (shaded in green) indicates that
for 80% of the buses the difference between the real sag incidence and the sag incidence
estimated using the MRA method can be as high as 1588 for ITIC events and as high as
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
141 |
1615.5 for SARFI-90 events. With the hybrid approach these differences are 3 and 7
events, respectively.
The data of Table 6-7 illustrate significant improvement in accuracy of sag estimation
when a more robust fault location method is implemented. The monitoring program
determined with the proposed hybrid method estimated correctly the incidence of sags
below the ITIC Curve for half of the buses, whereas the optimal sag monitoring
program (OSMP) failed to register up to 91 events in one single bus over the simulation
period. More importantly, the maximum difference between the actual number of sags
and sags estimated by the new monitoring program was less than 6 for 95% of the
system buses. On the other hand, the OSMP entailed an error of up to 1618 missed sags
over the entire simulation period (100 years), i.e. an average of 16 sags per year
affecting a bus were not identified.
Similar results were obtained for voltage sags with magnitude less than 0.9 p.u. For half
of the buses of the network, the new monitoring program did not overlook any event,
while there were buses where the OSMP failed to detect 1438 events. Considering 95%
of the network, 14 sags at most were not detected by the proposed monitoring program
during the 100 years simulation period, i.e. less than 0.14 per year. In the same portion
of the network, monitors of the OSMP missed up to 1813 sags in a single bus in 100
simulations, an average of 18.13 per year. A moderate impact of the inaccuracy in
estimation of the pre-fault voltage values (introduced by using the aforesaid fourth
loading profile) on the proposed approach is evidenced by the marginal errors in sag
estimation shown in Table 6-7.
Table 6-7 Difference between Estimated and Actual Number of Sag Events
Percentile
ITIC SARFI-90
MRA method
(16 monitors)
Hybrid method
(8 monitors)
MRA method
(16 monitors)
Hybrid method
(8 monitors)
10% 40 0 106 0
20% 68 0 117 1
50% 91 0 1438 4
80% 1588 3 1615.5 7
90% 1595 4 1772 10
95% 1618 5.75 1813.8 14
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
142 |
6.3 Risk-Based Assessment of Financial Losses due to
Voltage Sags
The methodology for analysis of financial losses caused by voltage sags proposed in
[118] is implemented here due to its comprehensive risk-based approach. The
methodology is focused on losses suffered by industrial plants and includes a
probabilistic modeling of the main elements involved in the assessment of process-
disruptive sags and the associated financial losses. The financial loss incurred by an
industrial plant due to each sag event is given by (6.4) [118].
ProcessFinancial Loss due to
failure loss process trip
risk
(6.4)
It can be seen from (6.4) that the two most important factors that determine the
magnitude of financial loss are the failure risk of the industrial process and the losses
incurred due to process trip. The main factors that influence industrial process failure
risk are the sensitivity of customer equipment and processes and number and
characteristics of sags at the customer site. The financial losses entailed by a process
trip depend on the type of the process and the variation in process activity due to the
process cycle and the plant’s load profile.
For voltage sag financial analysis, the stochastic net present value (SNPV) method is
incorporated in the methodology. SNPV is a modification of conventional net present
value (NPV) method that includes risk representation in the analysis. This characteristic
allows taking into account the non-deterministic nature of several components included
in the analysis, such as process sensitivity and voltage sag profile.
The financial losses incurred by the industrial plant due to voltage sags can be
calculated using the following equations [118]:
1
SCFSNPV
1+
Yy
yy
Ir
(6.5)
1
SCFS
y y s s
s
T p L
(6.6)
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
143 |
where
ySCF stochastic net cash flow at year y ;
Y
project lifetime in years;
y year number;
I
initial investment (if applicable);
r
discount rate;
S
total number of sags in year y ;
s
sag number;
p process failure risk, obtained from (6.4)
yT
operation and maintenance cost of investment in year y (if applicable);
L
loss due to process trip, obtained from (6.4).
Although (6.5) and (6.6) were originally formulated to calculate the stochastic net
present value of a sag mitigation option, they can be used to determine how much
money could be lost without mitigation [118].
6.4 Case Study 2: Assessment of Financial Losses
Caused by Voltage Sags
Assessment of financial losses due to sags has been undertaken using various
monitoring schemes. The studies were performed on the 295-bus generic distribution
system (GDS) simulating four types of power system short circuit faults, i.e., line to
ground (LG), line to line (LL), line to line to ground (LLG), and three-phase faults
(LLL).
6.4.1 Conventional and Optimal Monitoring Schemes
Five sag monitoring schemes have been used to perform the financial loss assessment.
Two of them represent the current practice in most parts of the world, where power
quality monitoring takes place at HV/MV substations. These two monitoring schemes
have been termed “eng1” and “eng2”. eng1 consists of 9 monitors placed at 132/33kV
substations and 2 monitors located at 132/11kV substations (11 monitors in total). These
substations are indicated in Figure 6-3 by Roman numerals contained in red squares.
eng2 comprises 8 monitors installed at 33/11kV substations, 2 monitors measuring the
primary and secondary sides of 11/3.3kV transformers, and 2 monitors placed at 132/11
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
144 |
kV substations (12 monitors in total). Green squares with capital letters indicate the
location of these substations in Figure 6-3. The remaining three monitoring schemes,
termed “opt8”, “opt10”, and “opt6”, correspond respectively to the eight monitors
required to cover all line to ground faults plus and minus two monitors taken from the
25 required to pinpoint the location of all types of fault (see Table 5-5 in Chapter 5 ).
These schemes are depicted in Figure 6-3 with encircled Arabic numbers.
6.4.2 Assessment of Financial Losses
The methodology developed in [118] and summarized in Section 6.3 has been used to
calculate the financial losses incurred by 9 different types of customer plants due to
voltage sags. The plants’ characteristics used in the assessment are shown in Table 6-8.
The plants have financial loss specific to business type (ranging from less than £4.4k to
more than £3M), different numbers of sensitive processes in each plant (from 1 to 8),
and different types of sensitive equipment type.
Table 6-8 Customer Plant Characteristics, adopted from [119]
Customer Business Financial loss
(£/event)
Number of
sensitive
processes
Sensitive
equipment
1 Pulp and paper integrated 18300 5 AC contactors, ASD
2 Metal works 152500 4 ASD, PLC
3 Food processing 4366 3 ASD, PLC, AC contactors
4 Textile 15250 4 ASD, PLC, AC contactors
5 Semiconductor fabrication 3344000 8 ASD, PLC
6 Automotive assembly 45750 5 ASD, PLC, AC contactors,
PC
7 Chemical 30500 2 ASD, PLC
8 Equipment manufacturing 61000 4 ASD, AC Contactors
9 Plastic extrusion 18300 1 ASD
Eight different locations of customer plants have been considered in the assessment of
financial losses. Plants are either located close to (locations a, c, f, and g) or far away
from (locations b, d, e, and h) bulk supply substations (33/11kV), as depicted in Figure
6-3. Monte Carlo simulation of 1000 trials has been run for a one-year assessment
period. The steps involved in the simulation are as follows [118]:
Step 1) Generate the annual number of faults using the data of Table 6-5.
Step 2) For each fault, select the most probable fault location applying the
algorithms proposed in Section 6.1.1 and using the five monitoring
schemes described above.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
145 |
Step 3) For each fault located, estimate sag characteristics at locations a – h
according to the simplified approach of Section 6.1.3.
Step 4) Run the sensitivity assessment for the 9 plants with the estimated sags
as input. Obtain process failure for each sag, as required by (6.6).
Step 5) Calculate the loss due to process trip ( )L using (6.4), with the data of
Table 6-8.
Step 6) Calculate SNPV using (6.5) and ignore investment costs.
Step 7) Repeats Steps 1) - 6) for 1000 trials.
The distribution of financial losses due to voltage sags for all customers’ plants attached
to location h is shown in Figure 6-4. Six graphs are plotted in each subfigure, five
corresponding to the losses estimated using the aforesaid monitoring schemes and the
sixth one representing the real losses; i.e., losses calculated assuming that a monitor is
present at the customer busbar (location h).
As the overlapping of the blue (real losses), black (losses estimated using opt10
scheme), and magenta (losses estimated using opt8 scheme) graphs shows, 8 and 10
optimally placed monitors provide the most accurate results. The 10 monitors measuring
voltages at both 33 kV and 11 kV voltage levels (eng2 scheme represented by green
graphs) estimate the real amount of losses fairly accurately although they overestimate
the probability of occurrence in most cases. Less accurate are the estimates derived from
the first 6 monitors of the optimal sag monitoring scheme (opt6 scheme represented by
cyan graphs), since the financial losses determined by this set of monitors tend to be
lower than the real losses.
Finally, the least accurate results, represented by red graphs, came from the set of
monitors installed at the 132 kV and 33 kV levels (eng1 scheme). The financial losses
estimated by this monitoring scheme are practically nil for all customers. This is
explained by the fact that 9 of the 11 monitors of eng1 scheme are situated at
transformers with delta-wye connections, which hinders the location of line to ground
and line to line to ground faults and these two types of fault constitute 90% of the total
as indicated by Table 6-5.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
146 |
Figure 6-3 Monitoring schemes and customer’s plant locations in the generic distribution system.
Engineering monitoring sites are indicated through color squares with Roman numerals and uppercase
letters; optimal monitoring locations (25) are numbered with color circles; the eight plant locations
analyzed are symbolized and represented with minuscule letters.
24
46
17
28
16
14
12
26
21
19
23
22
22
2
18
15
54
52
53
22
9
50
75
22
7
74
22
8
20
22
0
51
76
13
26
7
87
48
47
49
22
1
43
42
41
40
39
38
37
26
8
23
42
35
23
0
78 79
80
81
85
88
28
5
82
83
84
28
6
90
91
92
94
93
95
96
97
10
09
8 99
10
1
10
21
03
10
4
10
51
06
10
7
10
8
10
9
11
0
11
1
11
2
11
31
14
11
5
12
0
12
1
12
21
23
12
4
12
5
12
6
12
7
11
6
11
7
11
81
19
86
11
10
8
97654
55
1
65
64
63
57
22
52
26
58
14
8
14
6
15
3
15
4
14
91
52
15
5
14
71
45
14
4
14
0
14
2
14
1
14
3
13
9
13
8
12
8
12
91
32
13
0
13
4
13
61
35
13
7
13
3
15
6
16
0
15
7
18
5
18
3
13
1
15
9
16
4
16
1
16
2
16
3
16
5
16
6
16
71
68
16
9
17
9
18
0
18
11
82
18
4
18
6
18
7
18
8
18
91
90
19
1
19
2
19
3
19
6
19
7
19
91
98
20
0
20
1
20
22
03
20
4
20
5
20
6
20
72
08
15
0
15
1
22
3
23
1
77
15
8
22
4
21
4
21
5
21
0
21
12
09
21
2
21
3
21
6
21
71
70
21
8
21
9
17
1
17
2
17
3
17
4
17
5
17
6
17
7
62
60
59
61
2
3
72
70
17
8
25
27
29
30
32
31
33
34
35
36
71
68
67
69
73
89
45
44
24
82
49
26
52
66
24
1
25
1
25
9
28
4
23
6
24
3
26
0
25
0
24
02
44
24
52
42
26
12
71
26
92
52
27
32
70
27
52
74
26
22
63
27
2
23
9
25
32
57
25
52
58
27
6
24
6
27
7
24
7
27
923
3
27
8
23
22
54
25
6
28
82
87
28
92
90
29
22
91
29
42
93
29
5
23
42
37
28
3
23
8
28
22
80
28
1
56
13
2k
V
33
kV
11
kV
3.3
kV
27
5k
V
40
0k
V
66
18
2
18
3
18
41
85
18
61
87
18
81
89
19
0
19
1
19
2
19
31
94
19
51
96
19
71
98
19
92
00
20
1
20
2
20
3
20
42
05
20
6
20
7
20
8
20
9
21
0
21
1
21
2
21
3
21
4
21
5
21
6
21
72
18
21
92
20
22
1
22
2
22
32
24
22
5
22
6
22
7
22
82
29
23
02
31
23
2
23
3
23
4
23
52
36
23
72
38
23
92
40
24
1
24
2
24
3
24
42
45
24
6
24
72
48
24
92
50
25
1
25
2
25
3
25
4
25
5
25
6
25
7
25
82
59
26
0
19
426
1
19
526
22
63
26
42
65
26
62
67
26
8
26
9
27
0
27
12
72
27
4
27
52
78
27
3
27
62
77
1
2 8
33
34
5
5
6
7
9
10
11
12
13
13
13
14
15
16
17
18
1920
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
9394
95
96
96
97
98
99
10
0
10
1
10
2
10
3
10
41
05
10
6
10
7
10
8
10
9
11
0
11
1
11
21
13
11
4
11
51
15
11
6
11
71
18 1
19
12
0
12
1
12
2
12
3
12
3
12
41
25
12
61
27
12
8
12
9
13
0
13
1
13
2
13
31
34
13
5
13
6
13
7
13
81
39
14
0
14
11
42
14
3
14
41
45
14
6
14
7
14
8
14
9
15
0
15
1
15
21
53
15
4
15
5
15
6
15
71
58
15
9
16
0
16
11
62
16
3
16
4
16
5
16
6
16
7
16
8
16
9
17
0
17
1
17
2
17
3
17
4
17
51
76
17
71
78
17
9
18
01
80
18
0
18
1
1
2
3
45
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
a
b
c
d
e
fg
h
BA
CD
F
HL
G
III
IVV
VI
VII
VIII
XI
III
JIX
KX
E6
I
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
147 |
Figure 6-4 Distribution of SNPV from 1000 trials for all customers’ plants at location h estimated using
all monitoring schemes.
-20
24
68
10
12
x 1
05
012345678x 1
0-6
Probability Density
-10
12
34
56
78
9
x 1
06
0
0.2
0.4
0.6
0.81
x 1
0-6
-50
510
15
20
x 1
04
0123456789x 1
0-5
-10
12
34
56
78
x 1
04
0
0.51
1.52
2.53
3.5
x 1
0-4
Probability Density
-10
12
34
5
x 1
07
0
0.51
1.52
2.53
x 1
0-7
-20
24
68
10
12
14
x 1
05
01234567x 1
0-6
-20
24
68
10
12
x 1
05
012345678x 1
0-6
Sto
chastic N
et P
resent V
alu
e (
£)
Probability Density
-10
12
34
56
78
x 1
05
0
0.51
1.52
x 1
0-5
Sto
chastic N
et P
resent V
alu
e (
£)
-20
24
68
10
12
x 1
05
01234567x 1
0-6
Sto
chastic N
et P
resent V
alu
e (
£)
0.5
11.5
22.5
33.5 x 1
05
1.82
2.2
2.4
2.6
2.8
x 1
0-6
11.5
22.5
3
x 1
06
2.83
3.2
3.4
3.6
x 1
0-7
12
34
x 1
04
1.2
1.4
1.6
1.8
x 1
0-5
4000
6000
8000
10000
12000
14000
3.54
4.5
x 1
0-5
24
68
10
x 1
06
5
5.56
6.57
x 1
0-8
1.5
22.5
33.5
x 1
05
1.7
1.8
1.9
x 1
0-6
0.5
11.5
22.5
33.5 x
10
5
1.52
2.5
x 1
0-6
1.3
1.4
1.5
1.6
1.7
x 1
05
4.2
4.2
5
4.3
x 1
0-6
11.5
22.5
33.5
x 1
05
2
2.53
x 1
0-6
Cu
sto
me
r 3
Cu
sto
me
r 1
Cu
sto
me
r 2
Cu
sto
me
r 5
Cu
sto
me
r 6
Cu
sto
me
r 4
Cu
sto
me
r 7
Cu
sto
me
r 8
Cu
sto
me
r 9
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
148 |
However, both of the remaining monitors of eng1 scheme are placed at wye-wye
transformers (substations IX and X) and thus they can locate all types of faults
occurring in this zone of the network (downstream of substations IX and X), accounting
for all the losses greater than zero estimated by eng1 scheme. Similar results were found
for the rest of the plant locations and these are presented in Appendix D.
Figure 6-4 also shows that for most of the 1000 trials, the SNPV for customers 1, 2, and
3 is centered around £200k, £150k, and £30k, respectively. This means that these plants
will lose every year an average present worth of £200k, £150k, and £30k, respectively,
due to voltage sags. Similarly, the assessment of financial losses for customers 4, 5, and
6 shows that they will lose an annual average present worth of £9k, £6M, and £275k,
respectively. The annual losses for customers 7 and 9 will average around £200k, and
for customer 8 £160k.
The distribution of financial losses due to voltage sags for customer 5 (semiconductor
factory) at every location (a to h) is shown in Figure 6-5. The first box plot in the
subfigures represents the actual losses and the other five the losses determined using a
specific monitoring scheme. For example, 25%, 50%, and 75% of the calculations of
real losses at location “a” are lower than £1.8M (lower edge of the blue box), £3.8M
(red central mark), and £6M (upper edge of the blue box). All the estimates lie between
£0 (lower whisker) and £13M (upper whisker).
A comparison between monitoring schemes shows that opt6 and eng1 provide the least
accurate financial loss estimation and among the two, eng1 entails the biggest
discrepancy between actual and estimated losses. This is due to the better fault location
observability of the first six optimal sag monitoring locations (three 11kV buses and
three 33 kV buses) than the eleven monitored substations (nine 132/33 kV and two
132/11kV) of scheme eng1.
Regarding the financial losses incurred by the semiconductor fabrication plant, which
suffers the highest financial loss per event, the median annual losses range from less
than £1 M to almost £10 M. It can be seen from Figure 6-5 that locating the plant close
to bulk supply substations (location a, c, f, g) entails lower financial losses than at the
end of feeders (location b, d, e, h). (Please note difference in ordinate scale in Figure
6-5). The estimation of financial losses for the rest of the customers shows similar
results as can be seen in Appendix E.
Chapter 6 • Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
149 |
Figure 6-5 Distribution of SNPV from 1000 trials for a semiconductor factory at all locations (a-h)
estimated using all monitoring schemes.
02468
10
12
14
16
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Stochastic Net Present Value (£)
0
0.51
1.52
x 1
07 Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
0
0.51
1.52
2.5
x 1
07 Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
0
0.51
1.52
2.5
x 1
07 Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
02468
10
12
14
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Stochastic Net Present Value (£)
0123456789x 1
06 Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
0123456789
10
11
x 1
06 Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
0
0.51
1.52
2.53
x 1
07 Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
locati
on
bP
lan
t lo
cati
on
cP
lan
t lo
cati
on
dP
lan
t lo
cati
on
a
Pla
nt
locati
on
eP
lan
t lo
cati
on
fP
lan
t lo
cati
on
gP
lan
t lo
cati
on
h
Chapter 6 •Techno-Economic Assessment of Voltage Sags Using Optimal Monitoring Programs
150 |
6.5 Summary
A new methodology for monitoring and estimation of voltage sags in power systems has
been developed in this chapter. The proposed methodology encompasses a hybrid
monitor placement method and a simplified technique for fault location that allows
network sag characterization. Two optimal monitor placement methods, one for voltage
sag detection and studied in Chapter 3 , and one for fault location and presented in
Chapter 4 , were combined to overcome the main limitations of both, i.e. the use of
triggering thresholds to detect the occurrence of voltage sags and the high
computational memory usage entailed by the optimal monitor placement for fault
location problem. The voltage measurements from the buses selected by this hybrid
monitor placement are used to determine the most probable location of faults and
estimate their impact throughout the network.
The sag monitoring schemes obtained with the proposed methodology were tested in
two case studies utilizing Monte Carlo simulation. First the characteristics of voltage
sags were estimated to quantify the number of ITIC and SARFI-90 events occurring in
the network. Secondly, the financial losses incurred by different sensitive customers due
to voltage sags were assessed using a risk-based methodology. This assessment was
carried out by estimating voltage sag profiles at customer busbars based on the
simplified approach for fault localization. Results of both studies support the following:
High accuracy in both sag event estimation and assessment of financial losses
due to voltage sags can be achieved when monitoring power quality in sites
other that substations and with sag monitoring schemes partly deployed.
The main factor influencing the effectiveness of sag monitoring schemes is the
extent of their fault location observability area, which is greatly determined by
the presence of transformers with delta connections.
The number of voltage measurement devices entailed by the proposed hybrid
methodology is considerably less than the generic formulation of the monitor
placement for fault location (see Chapter 4 ), and can be implemented when
resources are limited or as the first stage of a measurement device deployment,
without significant impact on the accuracy of techno-economic assessment of
voltage sags.
Chapter 7 • Conclusions and Future Work
151 |
Chapter 7
Conclusions and Future
Work
7.1 Conclusions
The thesis developed a methodology for strategical monitor placement for the
estimation of voltage sags in power systems based on robust fault localization.
A review of past literature showed that voltage sags are currently one of the most
critical power quality disturbances. The economic losses entailed by the extensive
disruption of commercial and industrial processes caused by sags have been estimated
in the range of hundreds of millions of funds per year in developed countries alone. The
continuous proliferation of sensitive equipment in households, business and industry
threatens to exacerbate the economic impact of voltage sags.
The evaluation of voltage sags (as any other power quality problem) starts with the
correct identification and accurate characterization by means of measurement and data
collection. While monitoring the power quality at a single site is a relatively simple way
to obtain the data required to quantify and qualify the occurrence of sags at that site, the
sag performance characterization of an entire network becomes increasingly complex
and requires significant investment in measurement equipment and in data collection
and processing. Alternatively limited monitoring programs capable of estimating the
incidence and characteristics of sags at every bus of the network can be developed. A
strategic selection of monitoring locations is required to specify this such a
measurement scheme.
A thorough review of past power quality surveys conducted around the world revealed a
lack of consensus in the criteria for selection of monitoring locations and monitoring
Chapter 7 • Conclusions and Future Work
152 |
periods, as well as great heterogeneity in the monitoring data obtained. Only in very few
instances are monitors placed at locations other than substations and there have been no
major efforts aimed at deploying monitors to estimate the sag performance of an entire
network. Despite the surge in monitoring of power quality in electric power systems in
recent years, there are no specific guidelines prescribed in current standards in power
quality for selecting strategic monitoring locations and for the number of monitors
required to characterize the overall sag performance of the network.
Academic research has not fully addressed the optimal monitor placement for sag
estimation either, and the leading (most cited) method proposed to date has important
limitations. This monitor reach area (MRA) method is particularly sensitive to pre-fault
voltage, fault impedance, fault position, and voltage sag thresholds; so that the
minimum number of monitors required to cover the network varies significantly with
changes in any of these parameters. A recently developed fault location algorithm is
incorporated as a part of this research into the MRA method to enhance its robustness to
variation in pre-fault voltage and to provide virtual immunity to voltage sag thresholds,
fault impedance and fault position. The improvement of the MRA method leads to a
fixed minimum number of monitors regardless of variation in any of the aforesaid
influencing factors and with no additional data requirements. The development of the
enhanced monitor reach area (EMRA) algorithm is the first original contribution of this
thesis.
The vast majority of sags causing process disruptions originate from short-circuit faults.
If these faults are pinpointed, an accurate estimation of the induced sags throughout the
network can be achieved. Therefore, a set of monitors optimally deployed to locate
faults is equivalent to an optimal sag monitoring program. A recently proposed optimal
monitor placement method for fault location is extended and generalized in this thesis
for its implementation in large power networks. Adapting concepts from the MRA
method the monitor location area (MLA) is developed as the centerpiece of this
generalization. The MLA is introduced as the area of the network where up to two
monitors are able to pinpoint a fault to simplify and reduce the number of constraints in
the problem. The formulation of generic framework for the optimal monitor placement
for fault location is the second original contribution of this thesis.
Chapter 7 • Conclusions and Future Work
153 |
In some cases finding optimal fault location monitoring programs using linear
programming can be impeded when an immense number of combinations of monitors
needs to be analyzed. A heuristic search algorithm, which is much less memory
demanding, is developed in this research to find “sub-optimal” monitoring programs as
a trade-off between problem solvability and number of monitors considered. Custom
objective functions are also developed to guide the monitor deployment consistent with
maximization of fault location observability and minimization of sag magnitude
estimation error (SMEE) and sag event estimation error (SEEE); the latter being a user-
defined measure of sag estimation accuracy. In this thesis different benchmarking
criteria, such as sag immunity curves, ITIC and SEMI F47, performance indices,
SARFI, generalized sag table and voltage quality standards, EN 50160, are used to
define the SEEE. The heuristic monitor placement method unifies two monitoring
objectives, namely estimation of sag characteristics and indices and fault localization.
The proposed unified approach to sag and fault monitoring represents the third original
contribution of this thesis.
The use of monitoring data for sag estimation and fault location is intrinsically related.
Sag estimation at non-monitored buses is performed by means of fault location, while
short-circuit faults can be located using the voltage sags measured at monitored buses.
Sag estimation and fault location algorithms are further combined to create a synergistic
method that performs both sag estimation and fault location using fewer monitors than
optimal fault location monitoring programs. With the novel approach, the actual
location of faults is identified from several estimates with the aid of validity analysis of
measured voltages rather than triangulation of multiple monitors. This results in a
reduction of the number of monitors required while preserving the robustness of fault
location and accuracy of sag estimation. Case studies demonstrate that the proposed
technique provides accurate data for techno-economic assessment of voltage sags from
both strategically or conventionally deployed monitors. The flexible, cost-effective, and
scalable methodology for monitor placement and sag estimation constitutes the fourth
original contribution of this thesis.
Chapter 7 • Conclusions and Future Work
154 |
7.2 Future Work
Although all initially defined goals of this research have been fulfilled and its
contributions can help to develop guidelines for the deployment of power quality
monitoring devices and sag performance estimation at non-monitored sites, some
assumptions had to be made throughout the research to ensure that research goals are
met within prescribed time frame, while at the same time providing technically sound
and robust results and conclusions.
The approach taken in this thesis to locate faults utilizes impedance matrix techniques.
A core assumption is that the network data including negative-, positive- and zero-
sequence parameters are known, and thus the bus impedance matrix of the network can
be readily built. The suitability of alternative fault location algorithms that employ local
data, such as superimposed components, travelling waves, and synchronized or
unsynchronized measurements from one or more terminals, needs to be determined in
the future for systems where the bus impedance matrix cannot be constructed.
The considered fault location methods in this thesis include one-terminal and two-
terminal algorithms. Only the former, however, has been pursued since it is better suited
for minimization of monitoring costs. The two-terminal algorithm simplifies greatly the
fault location procedure at expense of an increase in number of monitors. If it is deemed
affordable, the optimal monitor placement problem for fault location and sag estimation
based on the two-terminal algorithm can be performed. The corresponding optimization
problem however has yet to be formulated. The hybrid approach, i.e., combination of
one- and two-terminal algorithms, to solving the monitor placement problem could also
be addressed in the future.
Throughout this thesis it was assumed that all transmission lines in the test systems are
fully transposed and that they can be represented by single circuits with lumped
parameters using π-equivalent model. The fault location algorithms used could be
further extended and adjusted to handle the changes in line impedance introduced by
non-transposed and double-circuit lines. Furthermore, if distributed parameter line
models are to be used, the iterative solution methods would need to be considered.
The impact of measurement errors and errors in network parameters, e.g., line
parameters, transformer parameters, source impedances, etc., on fault location accuracy
Chapter 7 • Conclusions and Future Work
155 |
and thus sag estimation accuracy has not been directly assessed in this research. A
probabilistic tool might be the most suitable approach to handle all these uncertainties.
Some initial work in this area has been carried out though and it showed promising
results [F12].
Since zero-sequence components are required to locate the most common type of faults,
line-to-ground faults, monitors connected phase-to-ground are considered better suited
for estimation of voltage sags based on fault location. If monitors connected phase-to-
phase are to be used, sag estimation can still be completed but not through fault
location. The problem of strategic placement of monitors connected phase-to-phase, or a
combination of these and monitors connected phase-to-ground, needs further research.
This would be very practical extension of present research as it is very likely that in real
networks a mix of monitors would be deployed.
It is proved in this thesis that voltage sag triggering thresholds, like 0.9 p.u. of nominal
voltage, are not required to perform both fault location and sag estimation at non-
monitored buses. Therefore, the occurrence of faults has to be detected even when the
voltage drop measured at monitored locations remains above 0.9 p.u. This can be
achieved using parametric methods, where a signal model is used [120]. The residuals
or models errors are calculated as the difference between the original waveform and the
waveform estimated by the model. Residual values are small as long as the signal is
quasi-stationary but they become large in the presence of sudden changes in the signal.
Residuals can therefore be used to detect the occurrence of short-circuit faults and
voltage sags without the use of sag triggering thresholds. The detailed application of
these methods in power quality monitoring programs requires further research.
Although this research has been focused on the monitoring and estimation of one of the
most pressing power quality problems, i.e. voltage sags, a comprehensive power quality
monitoring scheme needs to be developed in the future. The number and optimal
locations of monitoring devices required for simultaneous detection and estimation of
several, if not all, power quality disturbances (e.g. harmonic distortion, flicker,
unbalance, voltage transients, etc) needs to be determined in the future as this would be
the most cost-effective way of monitoring the power quality of the network.
Chapter 8 • References
156 |
Chapter 8
References
[1] M.H.J. Bollen, Understanding Power Quality Problems: Voltage Sags and
Interruptions, Piscataway, NJ, 1999.
[2] R.C. Dugan, M.F. McGranaghan, S. Santoso, H.W. Beaty, Electrical Power Systems
Quality, 2nd ed., McGraw-Hill, 2003.
[3] R. Targosz, J. Manson, Pan European LPQI power quality survey, in: 19th
International Conference on Electricity Distribution (CIRED), Vienna, 2007.
[4] CIGRE/CIRED C4.107 Economic Framework For Power Quality, in, Paris, 2011.
[5] EPRI, The Cost of Power Disturbances to Industrial & Digital Economy Companies,
in, Madison, WI, 2001.
[6] W.W. Carter, Control of power quality in modern industry, in: IEEE Annual Textile
Industry Technical Conference, 1989, pp. 11/11-11/14.
[7] J. Arrillaga, M.H.J. Bollen, N.R. Watson, Power quality following deregulation,
Proceedings of the IEEE, 88 (2000) 246-261.
[8] M.F. McGranaghan, D.R. Mueller, M.J. Samotyj, Voltage sags in industrial systems,
IEEE Transactions on Industry Applications, 29 (1993) 397-403.
[9] IEEE Recommended Practice for Monitoring Electric Power Quality, IEEE Std
1159-2009 (Revision of IEEE Std 1159-1995), (2009) c1-81.
[10] IEC 61000-2-8, Electromagnetic compatibility (EMC) - Part 2-8: Environment -
Voltage dips and short interruptions on public electric power supply systems with
statistical measurement results (2002).
[11] CIGRE TF C4.102 Voltage dip evaluation and prediction tools, (2009).
[12] D. Chapman, Power Quality Application Guide, Copper Development Association,
2001.
Chapter 8 • References
157 |
[13] IEC 61000-4-30, Electromagnetic Compatibility (EMC) - Part 4-30: Testing and
Measurement Techniques - Power Quality Measurement Methods, (2003).
[14] M.H.J. Bollen, I.Y.H. Gu, Signal Processing of Power Quality Disturbances,
Wiley-IEEE Press 2006.
[15] M.H.J. Bollen, Characterisation of voltage sags experienced by three-phase
adjustable-speed drives, IEEE Transactions on Power Delivery, 12 (1997) 1666-
1671.
[16] M.H.J. Bollen, D.D. Sabin, R.S. Thallam, Voltage-sag indices - recent
developments in IEEE PI564 task force, in: CIGRE/IEEE PES International
Symposium on Quality and Security of Electric Power Delivery Systems, 2003,
pp. 34-41.
[17] S.Z. Djokic, J.V. Milanovic, Advanced voltage sag characterisation. Part I: Phase
shift, IEE Proceedings Generation, Transmission & Distribution, 153 (2006) 423-
430.
[18] S.Z. Djokic, J.V. Milanovic, S.M. Rowland, Advanced voltage sag characterisation
ii: point on wave, IET Generation, Transmission & Distribution, 1 (2007) 146-
154.
[19] M.H.J. Bollen, I. McMichael, M.Stephens, K. Stockman, S. Djokic, F. Zavoda, B.
Brumsickle, A. McEachern, J.R. Gordon, G. Ethier, R. Neumann,
CIGRE/CIRED/UIE JWG C4.110 - Voltage dip immunity of equipment in
installations - status April 2008, in: 13th International Conference on Harmonics
and Quality of Power (ICHQP), Wollongong, 2008.
[20] CIGRE/CIRED/UIE_Joint_Working_Group_C4.110, Voltage dip immunity of
equipment and installation, in, 2010.
[21] M.H.J. Bollen, D.D. Sabin, International coordination for voltage sag indices, in:
IEEE PES Transmission and Distribution Conference and Exhibition, 2006, pp.
229-234.
[22] Electromagnetic Compatibility (EMC), Part 4, Section 11: Voltage dips, short
interruptions and voltage variations inmunity tests, IEC 610000-4-11, 2004.
Chapter 8 • References
158 |
[23] Electricity supply — quality of supply. art 2: Voltage characteristics, compatibility
levels, limits and assessment methods NRS 048-2:2003, 2003.
[24] D.L. Brooks, R.C. Dugan, M. Waclawiak, A. Sundaram, Indices for assessing
utility distribution system RMS variation performance, IEEE Transactions on
Power Delivery, 13 (1998) 254-259.
[25] CIGRE/CIRED Joint Working Group C4.07 Power quality indices and objectives
in, Paris, 2004.
[26] IEEE P1564 Draft Guide for Voltage Sag Indices, in, 2011.
[27] Specification for Semiconductor Processing Equipment Voltage Sag Immunity,
SEMI F47-0706, 2006.
[28] M.H.J. Bollen, P. Goossens, A. Robert, Assessment of voltage dips in HV-
networks: deduction of complex voltages from the measured RMS voltages, IEEE
Transactions on Power Delivery, 19 (2004) 783-790.
[29] M.T. Aung, J.V. Milanovic, C.P. Gupta, Propagation of asymmetrical sags and the
influence of boundary crossing lines on voltage sag prediction, IEEE Transactions
on Power Delivery, 19 (2004) 1819-1827.
[30] D.S. Dorr, Point of utilization power quality study results, in: 29th IEEE Industry
Applications Society Annual Meeting, 1994, pp. 2334-2344.
[31] D.S. Dorr, T.M. Gruzs, M.B. Hughes, R.E. Jurewicz, D. Gurcharn, J.L. McClaine,
Interpreting recent power quality surveys to define the electrical environment, in:
31st IEEE Industry Applications Society Annual Meeting, 1996, pp. 2251-2258
[32] M. Stephens, PQ in continuous manufacturing, in: H.D. Keulenaer (Ed.) Power
Quality and Utilisation Guide, Leonardo ENERGY, 2006.
[33] R.S. Thallam, G.T. Heydt, Power acceptability and voltage sag indices in the three
phase sense, in: IEEE Power Engineering Society Summer Meeting, 2000, pp.
905-910.
[34] H.G. Sarmiento, E. Estrada, A voltage sag study in an industry with adjustable
speed drives, in: IEEE Technical Conference on Industrial and Commercial
Power Systems, 1994, pp. 85-89.
[35] 5th CEER Benchmarking Report on the Quality of Electricity Supply, in, 2011.
Chapter 8 • References
159 |
[36] M.H.J. Bollen, M. Speychal, K. Linden, Estimation of dip frequency from fault
statistics - including three-phase characteristics, in: International Conference on
Probabilistic Methods Applied to Power Systems (PMAPS ), 2006, pp. 1-6.
[37] G. Celli, F. Pilo, G. Pisano, Optimal distribution network planning with stochastic
assessment of voltage dips, in: International Conference on Probabilistic Methods
Applied to Power Systems, 2004, pp. 801-806.
[38] G. Olguin, M.H.J. Bollen, Optimal dips monitoring program for characterization of
transmission system, in: IEEE Power Engineering Society General Meeting,
2003, pp. 2490.
[39] G. Olguin, F. Vuinovich, M.H.J. Bollen, An optimal monitoring program for
obtaining Voltage sag system indexes, IEEE Transactions on Power Delivery, 21
(2006) 378-384.
[40] E. Espinosa-Juarez, A. Hernandez, G. Olguin, An approach based on analytical
expressions for optimal location of voltage sags monitors, IEEE Transactions on
Power Delivery, 24 (2009) 2034-2042.
[41] E. Espinosa-Juarez, A. Hernandez, An analytical approach for stochastic
assessment of balanced and unbalanced voltage sags in large systems, IEEE
Transactions on Power Delivery, 21 (2006) 1493-1500.
[42] M.A. Eldery, E.F. El-Saadany, M.M.A. Salama, A. Vannelli, A novel power
quality monitoring allocation algorithm, IEEE Transactions on Power Delivery,
21 (2006) 768-777.
[43] F. de Santana, L. de Almeida, F.F. Costa, Optimal positioning of geo-referenced
short circuit sensors for faster fault finding using genetic algorithm, in: IEEE
International Symposium on Industrial Electronics (ISIE), 2008, pp. 2236-2241.
[44] M.C. de Almeida, F.F. Costa, S. Xavier-de-Souza, F. Santana, Optimal placement
of faulted circuit indicators in power distribution systems, Electric Power Systems
Research, 81 (2010) 699-706.
[45] R.A.F. Pereira, L.G.W. da Silva, J.R.S. Mantovani, PMUs optimized allocation
using a tabu search algorithm for fault location in electric power distribution
system, in: IEEE/PES Transmission and Distribution Conference and Exposition:
Latin America 2004, pp. 143-148.
Chapter 8 • References
160 |
[46] A.A.P. Bíscaro, R.A.F. Pereira, J.R.S. Mantovani, Optimal phasor measurement
units placement for fault location on overhead electric power distribution feeders,
in: IEEE/PES Transmission and Distribution Conference and Exposition: Latin
America, 2010, pp. 37-43.
[47] L. Kai-Ping, L. Chih-Wen, Y. Chi-Shan, J.A. Jiang, Transmission network fault
location observability with minimal PMU placement, IEEE Transactions on
Power Delivery, 21 (2006) 1128-1136.
[48] K. Mazlumi, H.A. Abyaneh, S.H.H. Sadeghi, S.S. Geramian, Determination of
optimal PMU placement for fault-location observability, in: 3rd International
Conference on Electric Utility Deregulation and Restructuring and Power
Technologies (DRPT), 2008, pp. 1938-1942.
[49] S.S. Geramian, H.A. Abyane, K. Mazlumi, Determination of optimal PMU
placement for fault location using genetic algorithm, in: 13th International
Conference on Harmonics and Quality of Power (ICHQP), 2008, pp. 1-5.
[50] Xu Bei, Y.J. Yoon, A. Abur, Optimal placement and utilization of phasor
measurement for state estimation, in: Power System Computation Conference,
Liege, Belgium, 2005.
[51] S.P. Pokharel, S. Brahma, Optimal PMU placement for fault location in a power
system, in: North American Power Symposium (NAPS), 2009, pp. 1-5.
[52] R. Kavasseri, S.K. Srinivasan, Joint placement of phasor and conventional power
flow measurements for fault observability of power systems, IET Generation,
Transmission & Distribution, 5 (2011) 1019-1024.
[53] Y. Liao, Fault location observability analysis and optimal meter placement based
on voltage measurements, Electric Power Systems Research, 79 (2009) 1062-
1068.
[54] M.H.J. Bollen, Fast assessment methods for voltage sags in distribution systems,
IEEE Transactions on Industry Applications, 32 (1996) 1414-1423.
[55] M.H.J. Bollen, Method of critical distances for stochastic assessment of voltage
sags, Generation, Transmission and Distribution, IEE Proceedings-, 145 (1998)
70-76.
Chapter 8 • References
161 |
[56] IEEE recommended practice for the design of reliable industrial and commercial
power systems, IEEE Std 493-1997 [IEEE Gold Book], (1998).
[57] M.H.J. Bollen, Additions to the method of critical distances for stochastic
assessment of voltage sags, in: IEEE Power Engineering Society Winter Meeting,
1999, pp. 1241-1246.
[58] L. Conrad, C. Grigg, K. Little, Predicting and preventing problems associated with
remote fault clearing voltage dips, in: Technical Conference on Industrial and
Commercial Power Systems 1989, pp. 74-78.
[59] IEEE Recommended Practice for the Design of Reliable Industrial and Commercial
Power Systems - Redline, IEEE Std 493-2007 (Revision of IEEE Std 493-1997) -
Redline, (2007) 1-426.
[60] M.R. Qader, M.H.J. Bollen, R.N. Allan, Stochastic prediction of voltage sags in a
large transmission system, IEEE Transactions on Industry Applications, 35 (1999)
152-162.
[61] C. Becker, W.B. Jr., K. Carrick, T. Diliberti, C. Grigg, J. Groesch, B. Hazen, T.
Imel, D. Koval, D. Mueller, T.S. John, L.E. Conrad, Proposed chapter 9 for
predicting voltage sags (dips) in revision to IEEE Std 493, the Gold Book, IEEE
Transactions on Industry Applications, 30 (1994) 805-821.
[62] J.A. Martínez-Velasco, Computer-based voltage dip assessment in transmission
and distribution networks, Electric Power Quality and Utilisation, XIV (2008) 31-
38.
[63] J.A. Martinez, J. Martin-Arnedo, Voltage sag stochastic prediction using an
electromagnetic transients program, IEEE Transactions on Power Delivery, 19
(2004) 1975-1982.
[64] Y.S.L.a.G. Strbac, Analytical approach to probabilistic prediction of voltage sags
on transmission networks, IEE Proceedings- Generation, Transmission and
Distribution, 149 (2002) 7-14.
[65] G. Olguin, Voltage dip (sag) estimation in power systems based on stochastic
assessment and optimal monitoring, in: Dept. Energy Envir., Chalmers University
of Technology, Göteborg, 2005, pp. 181.
Chapter 8 • References
162 |
[66] C.-H. Park, G. Jang, Stochastic estimation of voltage sags in a large meshed
network, IEEE Transactions on Power Delivery, 22 (2007) 1655-1664.
[67] C.-H. Park, G. Jang, R.J. Thomas, The influence of generator scheduling and time-
varying fault rates on voltage sag prediction, IEEE Transactions on Power
Delivery, 23 (2008) 1243-1250.
[68] J. Wang, S. Chen, T.T. Lie, System voltage sag performance estimation IEEE
Transactions on Power Delivery, 20 (2005) 1738-1747.
[69] M.N. Moschakis, N.D. Hatziargyriou, Analytical calculation and stochastic
assessment of voltage sags, IEEE Transactions on Power Delivery, 21 (2006)
1727-1734.
[70] S. Quaia, F. Tosato, A method for analytical voltage sags prediction, in: IEEE
Power Tech Conference, Bologna, 2003, pp. 6.
[71] J.V. Milanovic, M.T. Aung, C.P. Gupta, The influence of fault distribution on
stochastic prediction of voltage sags, IEEE Transactions on Power Delivery, 20
(2005) 278-285.
[72] E. Espinosa-Juarez, A. Hernandez, A method for voltage sag state estimation in
power systems, IEEE Transactions on Power Delivery, 22 (2007) 2517-2526.
[73] D.L. Sikes, Comparison between power quality monitoring results and predicted
stochastic assessment voltage sags-"real" reliability for the customer, IEEE
Transactions on Industry Applications, 36 (2000) 677-682.
[74] J.M.C. Filho, J.P.G. Abreu, R.C. Leborgne, T.C. Oliveira, D.M. Correia, J.F.d.
Oliveira, Comparative analysis between measurements and simulations of voltage
sags, in: 10th International Conference on Harmonics and Quality of Power,
2002, pp. 435-440.
[75] T.L. Tan, S. Chen, S.S. Choi, An overview of power quality state estimation, in:
7th International Power Engineering Conference (IPEC), 2005, pp. 1-276.
[76] B. Wang, W. Xu, Z. Pan, Voltage sag state estimation for power distribution
systems, in: IEEE Power Engineering Society General Meeting, 2005, pp. 2476
Chapter 8 • References
163 |
[77] Y.R. Gahrooyi, M.A. Golkar, Voltage Sag Estimation in Radial Distribution
Systems with Limited Monitoring Points, in: International Conference on
Electrical Engineering (ICEE), 2007, pp. 1-4.
[78] M. Janabali, S. Meshksar, E. Farjah, M. Zolghadri, Voltage Sag State Estimation
For Power Distribution Systems Using Kalman Filter, in: IEEE International
Symposium on Industrial Electronics (ISIE), 2007, pp. 2449-2453.
[79] Y.R. Gahrooyi, M.A. Golkar, Voltage sag estimation in radial distribution systems
with limited monitoring points, in: International Conference on Electrical
Engineering (ICEE), 2007, pp. 1-4.
[80] T.C. de Oliveira, J.M. de Carvalho Filho, R.C. Leborgne, M. Bollen, Voltage sags:
validating short-term monitoring by using long-term stochastic simulation, IEEE
Transactions on Power Delivery, 24 (2009) 1344-1351.
[81] M. Didden, R. Belmans, W. D'Haeseleer, Geographic generalization of limited
voltage sag monitoring data, in: CIGRE/IEEE PES International Symposium on
Quality and Security of Electric Power Delivery Systems, 2003, pp. 42-47.
[82] T.A. Short, A. Mansoor, W. Sunderman, A. Sundaram, Site variation and
prediction of power quality, IEEE Transactions on Power Delivery, 18 (2003)
1369-1375.
[83] J.J. Grainger, W.D. Stevenson, Power System Analysis, McGraw-Hill, New York,
1994.
[84] C.F. Wagner, R.D. Evans, Symmetrical components as applied to the analysis of
unbalanced electrical circuits, McGraw-Hill, New York ; London, 1933.
[85] P.M. Anderson, Analysis of Faulted Power Systems, IEEE PRESS, Piscataway,
NJ, 1995.
[86] K.R. Padiyar, Power system dynamics: stability and control, John Wiley, New
York, 1995.
[87] J.A. Martinez, J. Martin-Arnedo, Voltage sag studies in distribution Networks-part
I: system modeling, IEEE Transactions on Power Delivery, 21 (2006) 1670-1678.
[88] E. Council, Power System Protection: Principles and components, Peter Peregrinus
Ltd., 1981.
Chapter 8 • References
164 |
[89] P. Heine, M. Lehtonen, Voltage sag distributions caused by power system faults,
IEEE Transactions on Power Systems, 18 (2003) 1367-1373.
[90] Y. Zhang, Techno-economic assessment of voltage sag performance and
mitigation, in: School Elect. Electron. Eng., Univ. of Manchester, Manchester,
2008, pp. 283.
[91] Y. Zhang, J.V. Milanovic, Global voltage sag mitigation with FACTS-based
devices, IEEE Transactions on Power Delivery, 25 (2010) 2842-2850.
[92] J.V. Milanovic, Y. Zhang, Modeling of FACTS devices for voltage sag mitigation
studies in large power systems, IEEE Transactions on Power Delivery, 25 (2010)
3044-3052.
[93] J.V. Milanovic, Y. Zhang, Global minimization of financial losses due to voltage
sags with FACTS based devices, IEEE Transactions on Power Delivery, 25
(2010) 298-306.
[94] P.M. Subcommittee, IEEE Reliability Test System, IEEE Transactions on Power
Apparatus and Systems, PAS-98 (1979) 2047-2054.
[95] Q.B. Dam, A.P. Sakis Meliopoulos, G.T. Heydt, A. Bose, A breaker-oriented,
three-phase IEEE 24-substation test system, IEEE Transactions on Power
Delivery, 25 (2010) 59-67.
[96] Q.B. Dam, A.P.S. Meliopoulos, G.T. Heydt, A. Bose, Three-phase, breaker-
oriented IEEE 24-substation reliability test system, in, Available at:
http://pscal.ece.gatech.edu/testsys/index.html, 2010.
[97] R. Christie, 118-bus Power Flow Test Case, in, University of Washington, College
of Engineering, Electrical Engineering, 1993.
[98] M.T. Aung, Comprehensive probabilistic assessment of voltage sags in distribution
networks, in: School Elect. Electron. Eng., Univ. of Manchester, Manchester,
UK, 2005, pp. 201.
[99] R. Gnativ, J.V. Milanovic, Voltage sag propagation in systems with embedded
generation and induction motors, in: Power Engineering Society Summer
Meeting, 2001, pp. 474-479.
Chapter 8 • References
165 |
[100] J.V. Milanovic, R. Gnativ, K.W.M. Chow, The influence of loading conditions
and network topology on voltage sags, in: 9th International Conference on
Harmonics and Quality of Power, 2000, pp. 757-762.
[101] M.T. Aung, J.V. Milanovic, The influence of transformer winding connections on
the propagation of voltage sags, IEEE Transactions on Power Delivery, 21 (2006)
262-269.
[102] G. Olguin, An optimal trade-off between monitoring and simulation for voltage
dip characterization of transmission systems, in: IEEE/PES Transmission and
Distribution Conference and Exhibition: Asia and Pacific, 2005, pp. 1-6.
[103] R.D. Zimmerman, S. Murillo, C. E., R.J. Thomas, MATPOWER: Steady-state
operations, planning, and analysis tools for power systems research and education,
IEEE Transactions on Power Systems, 26 (2011) 12-19.
[104] Y. Liao, Fault location for single-circuit line based on bus-impedance matrix
utilizing voltage measurements, IEEE Transactions on Power Delivery, 23 (2008)
609-617.
[105] K. Ning, L. Yuan, Double-circuit transmission-line fault location with the
availability of limited voltage measurements, IEEE Transactions on Power
Delivery, 27 (2012) 325-336.
[106] C. Grigg, P. Wong, P. Albrecht, R. Allan, M. Bhavaraju, R. Billinton, Q. Chen, C.
Fong, S. Haddad, S. Kuruganty, W. Li, R. Mukerji, D. Patton, N. Rau, D. Reppen,
A. Schneider, M. Shahidehpour, C. Singh, The IEEE Reliability Test System-
1996. A report prepared by the Reliability Test System Task Force of the
Application of Probability Methods Subcommittee, IEEE Transactions on Power
Systems, 14 (1999) 1010-1020.
[107] F.X.O. Suite, Xpress-Mosel user guide, in, 2009.
[108] T.H. Cormen, C.E. Leiserson, R.L. Rivest, C. Stein, Introduction to Algorithms,
3rd ed., MIT press, 2009.
[109] D.C.S. Reis, P.R.C. Villela, C.A. Duque, P.F. Ribeiro, Transmission systems
power quality monitors allocation, in: IEEE Power and Energy Society General
Meeting - Conversion and Delivery of Electrical Energy in the 21st Century,
2008, pp. 1-7.
Chapter 8 • References
166 |
[110] V.V. Vazirani, Approximation Algorithms, 1st ed., Springer-Verlag, Berlin, 2001.
[111] EN 50160, Voltage characteristics of electricity supplied by public electricity
networks, in, 2010.
[112] G. Yaleinkaya, M.H.J. Bollen, P.A. Crossley, Characterization of voltage sags in
industrial distribution systems, IEEE Transactions on Industry Applications, 34
(1998) 682-688.
[113] ITI (CBEMA) Curve Application Note, Information Technology Industry
Council, in.
[114] S.Z. Djokic, J.V. Milanovic, D.J. Chapman, M.F. McGranaghan, D.S. Kirschen,
A new method for classification and presentation of voltage reduction events,
IEEE Transactions on Power Delivery, 20 (2005) 2576-2584.
[115] S. Gan, SEMI F47: Increased Power Quality Concerns in Chinese Fabs, in, 2009.
[116] Impact of SEMI F47 on Utilities and Their Customers - Abridged Version, in,
EPRI, Palo Alto, CA, 2004.
[117] B. Xu, A. Abur, Optimal placement of phasor measurement units for state
estimation, in, PSERC, Ithaca, NY, Final project report,, 2005.
[118] J.Y. Chan, J.V. Milanovic, A. Delahunty, Risk-based assessment of financial
losses due to voltage sag, IEEE Transactions on Power Delivery, 26 (2011) 492-
500.
[119] J.Y. Chan, Framework for assessment of economic feasibility of voltage sag
mitigation solutions, in: School Elect. Electron. Eng., Univ. of Manchester,
Manchester, UK, 2010, pp. 296.
[120] M.H.J. Bollen, I.Y.H. Gu, S. Santoso, M.F. McGranaghan, P.A. Crossley, M.V.
Ribeiro, P.F. Ribeiro, Bridging the gap between signal and power, IEEE Signal
Processing Magazine, 26 (2009) 12-31.
Appendix A • Network Data of Test Systems
167 |
Appendix A Network Data of Test
Systems
Table A-1 Generator impedances of the 10-bus 500 kV power system
Generator bus number Positive sequence (p.u.) Zero sequence (p.u.)
1 0.001006 + j0.016521 0.0018296 + j0.013763
6 0.00016441 + j0.0046618 0.00017024 + j0.0028855
7 0.0016382 + j0.024301 0.0056571 + j0.03134 9 0.0014553 + j0.023504 0.0026958 + j0.022641
10 0.00020591 + j0.004648 0.00052175 + j0.0047921
Table A-2 Transmission line parameters of the 10-bus 500 kV power system
Line (from bus-to bus) Length (mile) Positive sequence (p.u.) Zero sequence (p.u.)
1-2 52.58 0.0008 + j0.012 0.0087 + j0.0309 2-3 33.20 0.0005 + j0.0076 0.0083 + j0.0252 3-4 47.90 0.0007 + j0.0109 0.012 + j0.0366 4-2 56.88 0.0009 + j0.013 0.0143 + j0.0427 2-7 45.45 0.0007 + j0.0097 0.0106 + j0.031 4-5 27.99 0.0004 + j0.0064 0.0074 + j0.0215 5-8 63.51 0.001 + j0.0142 0.0169 + j0.0498
8-10 62.77 0.001 + j0.0143 0.0166 + j0.0484 5-6 86.81 0.0014 + j0.0197 0.0181 + j0.0555 4-9 27.72 0.0004 + j0.0063 0.0075 + j0.0192
Table A-3 Bus data of the IEEE Reliability Test System (RTS)
Bus number Type Pd Qd Gs Bs Area Vm Va Base kV Zone Vmax Vmin
1 2 108.00 22.00 0 0 1 1.035 -7.2064 138 1 1.06 0.94 2 2 97.00 20.00 0 0 1 1.035 -7.3084 138 1 1.06 0.94 3 1 180.00 37.00 0 0 1 0.9864 -5.431 138 1 1.06 0.94 4 1 74.00 15.00 0 0 1 1.0007 -9.7563 138 1 1.06 0.94 5 1 71.00 14.00 0 0 1 1.0318 -10.021 138 1 1.06 0.94 6 1 136.00 28.00 0 0 1 1.0856 -13.000 138 1 1.06 0.94 7 2 125.00 25.00 0 0 1 1.0250 -7.3282 138 1 1.06 0.94 8 1 171.00 35.00 0 0 1 0.9997 -11.109 138 1 1.06 0.94 9 1 175.00 36.00 0 0 1 1.0064 -7.6215 138 1 1.06 0.94
10 1 195.00 40.00 0 0 1 1.0553 -9.7312 138 1 1.06 0.94 11 1 0.00 0.00 0 0 1 1.0001 -3.0003 230 1 1.06 0.94 12 1 0.00 0.00 0 0 1 1.0089 -1.4634 230 1 1.06 0.94 13 3 265.00 54.00 0 0 1 1.0200 0 230 1 1.06 0.94 14 2 194.00 39.00 0 0 1 0.9881 0.1628 230 1 1.06 0.94 15 2 317.00 64.00 0 0 1 1.0140 11.8605 230 1 1.06 0.94 16 2 100.00 20.00 0 0 1 1.0170 10.9874 230 1 1.06 0.94 17 1 0.00 0.00 0 0 1 1.0401 14.7403 230 1 1.06 0.94 18 2 333.00 68.00 0 0 1 1.0500 16.1978 230 1 1.06 0.94 19 1 181.00 37.00 0 0 1 1.0230 9.7628 230 1 1.06 0.94 20 1 128.00 26.00 0 0 1 1.0381 10.6403 230 1 1.06 0.94 21 2 0.00 0.00 0 0 1 1.0500 17.1449 230 1 1.06 0.94 22 2 0.00 0.00 0 0 1 1.0500 22.7139 230 1 1.06 0.94 23 2 0.00 0.00 0 0 1 1.0500 11.8366 230 1 1.06 0.94 24 1 0.00 0.00 0 0 1 0.9812 5.4794 230 1 1.06 0.94
Appendix A • Network Data of Test Systems
168 |
Table A-4 Generator data of the IEEE Reliability Test System (RTS) Bus Pg Qg Qmax Qmin Vg Rate Status Pmax Pmin R1 X1 R0 X0
1 15 3.31 10 0 1.035 24 1 20 16 0.001 0.32 0.001 0.1406 1 15 3.31 10 0 1.035 24 1 20 16 0.001 0.32 0.001 0.1406
1 75 3.31 30 -25 1.035 89 1 76 15.2 0.001 0.30 0.001 0.0379
1 75 3.31 30 -25 1.035 89 1 76 15.2 0.001 0.30 0.001 0.0379 2 15 0 10 0 1.035 24 1 20 16 0.001 0.32 0.001 0.1406
2 15 0 10 0 1.035 24 1 20 16 0.001 0.32 0.001 0.1406
2 75 -9.02 30 -25 1.035 89 1 76 15.2 0.001 0.30 0.001 0.0379 2 75 -9.03 30 -25 1.035 89 1 76 15.2 0.001 0.30 0.001 0.0379
7 80 14.64 60 0 1.025 118 1 100 25 0.001 0.32 0.001 0.0286
7 80 14.64 60 0 1.025 118 1 100 25 0.001 0.32 0.001 0.0286 7 80 14.64 60 0 1.025 118 1 100 25 0.001 0.32 0.001 0.0286
13 32.44 28.68 80 0 1.02 232 1 197 68.95 0.001 0.32 0.001 0.0145
13 32.44 28.68 80 0 1.02 232 1 197 68.95 0.001 0.32 0.001 0.0145 13 32.44 28.68 80 0 1.02 232 1 197 5 0.001 0.32 0.001 0.0145
15 9 0 6 0 1.014 14 1 12 2.4 0.001 0.32 0.001 0.2411
15 9 0 6 0 1.014 14 1 12 2.4 0.001 0.32 0.001 0.2411 15 9 0 6 0 1.014 14 1 12 2.4 0.001 0.32 0.001 0.2411
15 9 0 6 0 1.014 14 1 12 2.4 0.001 0.32 0.001 0.2411
15 9 0 6 0 1.014 14 1 12 2.4 0.001 0.32 0.001 0.2411 15 155 -14.72 80 -50 1.014 182 1 155 54.25 0.001 0.30 0.001 0.0185
16 155 34.44 80 0.02 1.017 182 1 155 54.25 0.001 0.30 0.001 0.0185
18 400 141.8 200 -50 1.05 471 1 400 100 0.01 0.40 0.01 0.0072 21 400 113.6 200 -50 1.05 471 1 400 100 0.001 0.40 0.001 0.0072
22 50 -6.09 16 -10 1.05 53 1 50 10 0.001 0.28 0.001 0.1061
22 50 -6.09 16 -10 1.05 53 1 50 10 0.001 0.28 0.001 0.1061 22 50 -6.09 16 -10 1.05 53 1 50 10 0.001 0.28 0.001 0.1061
22 50 -6.09 16 -10 1.05 53 1 50 10 0.001 0.28 0.001 0.1061
22 50 -6.09 16 -10 1.05 53 1 50 10 0.001 0.28 0.001 0.1061 22 50 -6.09 16 -10 1.05 53 1 50 10 0.001 0.28 0.001 0.1061
23 149.59 50.14 80 -50 1.05 182 1 155 54.25 0.001 0.30 0.001 0.0185
23 149.59 50.14 80 -50 1.05 182 1 155 54.25 0.001 0.30 0.001 0.0185 23 350 80 150 -25 1.05 412 1 350 140 0.001 0.30 0.001 0.0082
Table A-5 Line data of the IEEE Reliability Test System (RTS)
From
bus
To
bus R1 X1 B1 R0 X0 B0
Rating Length Type Status
A B C (miles)
1 2 0.0007 0.0012 0.0007 0.0026 0.0011 0.0007 175 200 193 0.95 C 1
1 3 0.0542 0.2111 0.0613 0.1595 0.7628 0.0319 175 220 208 55 OL 1 1 5 0.0224 0.0849 0.0244 0.0649 0.3064 0.0127 175 220 208 22 OL 1
2 4 0.0336 0.1273 0.0366 0.0972 0.4593 0.0191 175 220 208 33 OL 1
2 6 0.0506 0.1920 0.0557 0.1466 0.6939 0.0290 175 220 208 50 OL 1 3 9 0.0315 0.1192 0.0343 0.0911 0.4301 0.0179 175 220 208 30.9 OL 1
4 9 0.0269 0.1078 0.0279 0.0767 0.3577 0.0154 175 220 208 26.5 OL 1
5 10 0.0233 0.0884 0.0254 0.0676 0.3189 0.0132 175 220 208 22.9 OL 1 6 10 0.0226 0.0333 0.1303 0.0521 0.0218 0.1303 175 200 193 16 C 1
7 8 0.0161 0.0610 0.0179 0.0471 0.2222 0.0093 175 220 208 16 OL 1
8 9 0.0423 0.1648 0.0478 0.1248 0.5959 0.0249 175 220 208 42.9 OL 1 8 10 0.0423 0.1648 0.0478 0.1248 0.5959 0.0249 175 220 208 42.9 OL 1
11 13 0.0058 0.0475 0.0959 0.0321 0.1483 0.0590 500 625 600 33 OL 1
11 14 0.0051 0.0417 0.0843 0.0282 0.1304 0.0518 500 625 600 29 OL 1 12 13 0.0058 0.0476 0.0959 0.0321 0.1483 0.0590 500 625 600 33 OL 1
12 23 0.0122 0.0964 0.1984 0.0547 0.3131 0.1095 500 625 600 67 OL 1
13 23 0.0106 0.0864 0.1752 0.0581 0.2697 0.1078 500 625 600 60.2 OL 1 14 16 0.0048 0.0388 0.0785 0.0263 0.1241 0.0483 500 625 600 27 OL 1
15 16 0.0021 0.0173 0.0349 0.0117 0.0540 0.0214 500 625 600 12 OL 1
15 21 0.0061 0.0490 0.1006 0.0278 0.1595 0.0555 500 625 600 34 OL 1 15 21 0.0061 0.0490 0.1006 0.0278 0.1595 0.0555 500 625 600 34 OL 1
15 24 0.0064 0.0519 0.1066 0.0295 0.1688 0.0587 500 625 600 36 OL 1
16 17 0.0032 0.0259 0.0523 0.0175 0.0810 0.0322 500 625 600 18 OL 1 16 19 0.0028 0.0230 0.0465 0.0156 0.0720 0.0286 500 625 600 16 OL 1
17 18 0.0018 0.0144 0.0291 0.0097 0.0450 0.0179 500 625 600 10 OL 1
17 22 0.0123 0.1053 0.2116 0.0489 0.3427 0.1110 500 625 600 73 OL 1 18 21 0.0033 0.0260 0.0533 0.0149 0.0845 0.0293 500 625 600 18 OL 1
18 21 0.0033 0.0260 0.0533 0.0149 0.0845 0.0293 500 625 600 18 OL 1
19 20 0.0051 0.0396 0.0814 0.0227 0.1290 0.0448 500 625 600 27.5 OL 1 19 20 0.0051 0.0396 0.0814 0.0227 0.1290 0.0448 500 625 600 27.5 OL 1
20 23 0.0028 0.0216 0.0444 0.0124 0.0704 0.0245 500 625 600 15 OL 1
20 23 0.0028 0.0216 0.0444 0.0124 0.0704 0.0245 500 625 600 15 OL 1 21 22 0.0083 0.0677 0.1367 0.0321 0.2215 0.0715 500 625 600 47.1 OL 1
Appendix A • Network Data of Test Systems
169 |
Table A-6 Transformer data of the IEEE Reliability Test System (RTS)
From bus To bus R1 X1 B1 From winding To winding Tap Shift Rating
Status A B C
3 24 0.0023 0.0839 0.0000 Wye Wye 1 0 400 600 510 1
9 11 0.0023 0.0839 0.0000 Wye Wye 1 0 400 600 510 1
9 12 0.0023 0.0839 0.0000 Wye Wye 1 0 400 600 510 1 10 11 0.0023 0.0839 0.0000 Wye Wye 1 0 400 600 510 1
10 12 0.0023 0.0839 0.0000 Wye Wye 1 0 400 600 510 1
Table A-7 Bus data of the IEEE 118-bus Test System
Bus
number Type Pd Qd Gs Bs Area Vm Va
Base
kV Zone Vmax Vmin
1 2 51.00 27.00 0 0 1 0.955 10.67 138 1 1.06 0.94 2 1 20.00 9.00 0 0 1 0.971 11.22 138 1 1.06 0.94
3 1 39.00 10.00 0 0 1 0.968 11.56 138 1 1.06 0.94
4 2 39.00 12.00 0 0 1 0.998 15.28 138 1 1.06 0.94 5 1 0.00 0.00 0 -40 1 1.002 15.73 138 1 1.06 0.94
6 2 52.00 22.00 0 0 1 0.9900 13 138 1 1.06 0.94 7 1 19.00 2.00 0 0 1 0.9890 12.56 138 1 1.06 0.94
8 2 28.00 0.00 0 0 1 1.0150 20.77 345 1 1.06 0.94
9 1 0.00 0.00 0 0 1 1.0430 28.02 345 1 1.06 0.94 10 2 0.00 0.00 0 0 1 1.0500 35.61 345 1 1.06 0.94
11 1 70.00 23.00 0 0 1 0.9850 12.72 138 1 1.06 0.94
12 2 47.00 10.00 0 0 1 0.9900 12.2 138 1 1.06 0.94 13 1 34.00 16.00 0 0 1 0.9680 11.35 138 1 1.06 0.94
14 1 14.00 1.00 0 0 1 0.9840 11.5 138 1 1.06 0.94
15 2 90.00 30.00 0 0 1 0.9700 11.23 138 1 1.06 0.94 16 1 25.00 10.00 0 0 1 0.9840 11.91 138 1 1.06 0.94
17 1 11.00 3.00 0 0 1 0.9950 13.74 138 1 1.06 0.94
18 2 60.00 34.00 0 0 1 0.9730 11.53 138 1 1.06 0.94 19 2 45.00 25.00 0 0 1 0.9630 11.05 138 1 1.06 0.94
20 1 18.00 3.00 0 0 1 0.9580 11.93 138 1 1.06 0.94
21 1 14.00 8.00 0 0 1 0.9590 13.52 138 1 1.06 0.94 22 1 10.00 5.00 0 0 1 0.9700 16.08 138 1 1.06 0.94
23 1 7.00 3.00 0 0 1 1.0000 21 138 1 1.06 0.94
24 2 13.00 0.00 0 0 1 0.9920 20.89 138 1 1.06 0.94 25 2 0.00 0.00 0 0 1 1.0500 27.93 138 1 1.06 0.94
26 2 0.00 0.00 0 0 1 1.0150 29.71 345 1 1.06 0.94
27 2 71.00 13.00 0 0 1 0.9680 15.35 138 1 1.06 0.94 28 1 17.00 7.00 0 0 1 0.9620 13.62 138 1 1.06 0.94
29 1 24.00 4.00 0 0 1 0.9630 12.63 138 1 1.06 0.94
30 1 0.00 0.00 0 0 1 0.9680 18.79 345 1 1.06 0.94 31 2 43.00 27.00 0 0 1 0.9670 12.75 138 1 1.06 0.94
32 2 59.00 23.00 0 0 1 0.9640 14.8 138 1 1.06 0.94
33 1 23.00 9.00 0 0 1 0.9720 10.63 138 1 1.06 0.94 34 2 59 26 0 14 1 0.986 11.3 138 1 1.06 0.94
35 1 33 9 0 0 1 0.981 10.87 138 1 1.06 0.94
36 2 31 17 0 0 1 0.98 10.87 138 1 1.06 0.94 37 1 0 0 0 -25 1 0.992 11.77 138 1 1.06 0.94
38 1 0 0 0 0 1 0.962 16.91 345 1 1.06 0.94
39 1 27 11 0 0 1 0.97 8.41 138 1 1.06 0.94 40 2 66 23 0 0 1 0.97 7.35 138 1 1.06 0.94
41 1 37 10 0 0 1 0.967 6.92 138 1 1.06 0.94
42 2 96 23 0 0 1 0.985 8.53 138 1 1.06 0.94 43 1 18 7 0 0 1 0.978 11.28 138 1 1.06 0.94
44 1 16 8 0 10 1 0.985 13.82 138 1 1.06 0.94
45 1 53 22 0 10 1 0.987 15.67 138 1 1.06 0.94 46 2 28 10 0 10 1 1.005 18.49 138 1 1.06 0.94
47 1 34 0 0 0 1 1.017 20.73 138 1 1.06 0.94
48 1 20 11 0 15 1 1.021 19.93 138 1 1.06 0.94 49 2 87 30 0 0 1 1.025 20.94 138 1 1.06 0.94
50 1 17 4 0 0 1 1.001 18.9 138 1 1.06 0.94
51 1 17 8 0 0 1 0.967 16.28 138 1 1.06 0.94 52 1 18 5 0 0 1 0.957 15.32 138 1 1.06 0.94
53 1 23 11 0 0 1 0.946 14.35 138 1 1.06 0.94
54 2 113 32 0 0 1 0.955 15.26 138 1 1.06 0.94 55 2 63 22 0 0 1 0.952 14.97 138 1 1.06 0.94
56 2 84 18 0 0 1 0.954 15.16 138 1 1.06 0.94 57 1 12 3 0 0 1 0.971 16.36 138 1 1.06 0.94
58 1 12 3 0 0 1 0.959 15.51 138 1 1.06 0.94
59 2 277 113 0 0 1 0.985 19.37 138 1 1.06 0.94 60 1 78 3 0 0 1 0.993 23.15 138 1 1.06 0.94
Appendix A • Network Data of Test Systems
170 |
61 2 0 0 0 0 1 0.995 24.04 138 1 1.06 0.94
62 2 77 14 0 0 1 0.998 23.43 138 1 1.06 0.94 63 1 0 0 0 0 1 0.969 22.75 345 1 1.06 0.94
64 1 0 0 0 0 1 0.984 24.52 345 1 1.06 0.94 65 2 0 0 0 0 1 1.005 27.65 345 1 1.06 0.94
66 2 39 18 0 0 1 1.05 27.48 138 1 1.06 0.94
67 1 28 7 0 0 1 1.02 24.84 138 1 1.06 0.94 68 1 0 0 0 0 1 1.003 27.55 345 1 1.06 0.94
69 3 0 0 0 0 1 1.035 30 138 1 1.06 0.94
70 2 66 20 0 0 1 0.984 22.58 138 1 1.06 0.94 71 1 0 0 0 0 1 0.987 22.15 138 1 1.06 0.94
72 2 12 0 0 0 1 0.98 20.98 138 1 1.06 0.94
73 2 6 0 0 0 1 0.991 21.94 138 1 1.06 0.94 74 2 68 27 0 12 1 0.958 21.64 138 1 1.06 0.94
75 1 47 11 0 0 1 0.967 22.91 138 1 1.06 0.94
76 2 68 36 0 0 1 0.943 21.77 138 1 1.06 0.94 77 2 61 28 0 0 1 1.006 26.72 138 1 1.06 0.94
78 1 71 26 0 0 1 1.003 26.42 138 1 1.06 0.94
79 1 39 32 0 20 1 1.009 26.72 138 1 1.06 0.94 80 2 130 26 0 0 1 1.04 28.96 138 1 1.06 0.94
81 1 0 0 0 0 1 0.997 28.1 345 1 1.06 0.94
82 1 54 27 0 20 1 0.989 27.24 138 1 1.06 0.94 83 1 20 10 0 10 1 0.985 28.42 138 1 1.06 0.94
84 1 11 7 0 0 1 0.98 30.95 138 1 1.06 0.94
85 2 24 15 0 0 1 0.985 32.51 138 1 1.06 0.94 86 1 21 10 0 0 1 0.987 31.14 138 1 1.06 0.94
87 2 0 0 0 0 1 1.015 31.4 161 1 1.06 0.94
88 1 48 10 0 0 1 0.987 35.64 138 1 1.06 0.94 89 2 0 0 0 0 1 1.005 39.69 138 1 1.06 0.94
90 2 163 42 0 0 1 0.985 33.29 138 1 1.06 0.94
91 2 10 0 0 0 1 0.98 33.31 138 1 1.06 0.94 92 2 65 10 0 0 1 0.993 33.8 138 1 1.06 0.94
93 1 12 7 0 0 1 0.987 30.79 138 1 1.06 0.94
94 1 30 16 0 0 1 0.991 28.64 138 1 1.06 0.94 95 1 42 31 0 0 1 0.981 27.67 138 1 1.06 0.94
96 1 38 15 0 0 1 0.993 27.51 138 1 1.06 0.94
97 1 15 9 0 0 1 1.011 27.88 138 1 1.06 0.94 98 1 34 8 0 0 1 1.024 27.4 138 1 1.06 0.94
99 2 42 0 0 0 1 1.01 27.04 138 1 1.06 0.94
100 2 37 18 0 0 1 1.017 28.03 138 1 1.06 0.94 101 1 22 15 0 0 1 0.993 29.61 138 1 1.06 0.94
102 1 5 3 0 0 1 0.991 32.3 138 1 1.06 0.94
103 2 23 16 0 0 1 1.001 24.44 138 1 1.06 0.94 104 2 38 25 0 0 1 0.971 21.69 138 1 1.06 0.94
105 2 31 26 0 20 1 0.965 20.57 138 1 1.06 0.94
106 1 43 16 0 0 1 0.962 20.32 138 1 1.06 0.94 107 2 50 12 0 6 1 0.952 17.53 138 1 1.06 0.94
108 1 2 1 0 0 1 0.967 19.38 138 1 1.06 0.94
109 1 8 3 0 0 1 0.967 18.93 138 1 1.06 0.94 110 2 39 30 0 6 1 0.973 18.09 138 1 1.06 0.94
111 2 0 0 0 0 1 0.98 19.74 138 1 1.06 0.94
112 2 68 13 0 0 1 0.975 14.99 138 1 1.06 0.94 113 2 6 0 0 0 1 0.993 13.74 138 1 1.06 0.94
114 1 8 3 0 0 1 0.96 14.46 138 1 1.06 0.94 115 1 22 7 0 0 1 0.96 14.46 138 1 1.06 0.94
116 2 184 0 0 0 1 1.005 27.12 138 1 1.06 0.94
117 1 20 8 0 0 1 0.974 10.67 138 1 1.06 0.94 118 1 33 15 0 0 1 0.949 21.92 138 1 1.06 0.94
Table A-8 Generator data of the IEEE 118-bus Test System
Bus Pg Qg Qmax Qmin Vg Rate Status Pmax Pmin R1 X1 R0 X0
1 0 0.00 15 -5 0.955 100 1 100 0 0 0.30 0 0.05
4 0 0.00 300 -300 0.998 100 1 100 0 0 0.30 0 0.05
6 0 0.00 50 -13 0.99 100 1 100 0 0 0.30 0 0.05 8 0 0.00 300 -300 1.015 100 1 100 0 0 0.30 0 0.05
10 450 0.00 200 -147 1.05 100 1 550 0 0 0.30 0 0.05
12 85 0.00 120 -35 0.99 100 1 185 0 0 0.30 0 0.05 15 0 0.00 30 -10 0.97 100 1 100 0 0 0.30 0 0.05
18 0 0.00 50 -16 0.973 100 1 100 0 0 0.30 0 0.05
19 0 0.00 24 -8 0.962 100 1 100 0 0 0.30 0 0.05 24 0 0.00 300 -300 0.992 100 1 100 0 0 0.30 0 0.05
25 220 0.00 140 -47 1.05 100 1 320 0 0 0.30 0 0.05
26 314 0.00 1000 -1000 1.015 100 1 414 0 0 0.30 0 0.05
Appendix A • Network Data of Test Systems
171 |
27 0 0.00 300 -300 0.968 100 1 100 0 0 0.30 0 0.05
31 7 0.00 300 -300 0.967 100 1 107 0 0 0.30 0 0.05 32 0 0.00 42 -14 0.963 100 1 100 0 0 0.30 0 0.05
34 0 0.00 24 -8 0.984 100 1 100 0 0 0.30 0 0.05 36 0 0.00 24 -8 0.98 100 1 100 0 0 0.30 0 0.05
40 0 0.00 300 -300 0.97 100 1 100 0 0 0.30 0 0.05
42 0 0.00 300 -300 0.985 100 1 100 0 0 0.30 0 0.05 46 19 0.00 100 -100 1.005 100 1 119 0 0 0.30 0 0.05
49 204 0.00 210 -85 1.025 100 1 304 0 0 0.30 0 0.05
54 48 0.00 300 -300 0.955 100 1 148 0 0 0.30 0 0.05 55 0 0.00 23 -8 0.952 100 1 100 0 0 0.30 0 0.05
56 0 0.00 15 -8 0.954 100 1 100 0 0 0.30 0 0.05
59 155 0.00 180 -60 0.985 100 1 255 0 0 0.30 0 0.05 61 160 0.00 300 -100 0.995 100 1 260 0 0 0.30 0 0.05
62 0 0.00 20 -20 0.998 100 1 100 0 0 0.30 0 0.05
65 391 0.00 200 -67 1.005 100 1 491 0 0 0.30 0 0.05 66 392 0.00 200 -67 1.05 100 1 492 0 0 0.30 0 0.05
69 516.4 0.00 300 -300 1.035 100 1 805.2 0 0 0.30 0 0.05
70 0 0.00 32 -10 0.984 100 1 100 0 0 0.30 0 0.05 72 0 0.00 100 -100 0.98 100 1 100 0 0 0.30 0 0.05
73 0 0.00 100 -100 0.991 100 1 100 0 0 0.30 0 0.05
74 0 0 9 -6 0.958 100 1 100 0 0 0.30 0 0.05 76 0 0 23 -8 0.943 100 1 100 0 0 0.30 0 0.05
77 0 0 70 -20 1.006 100 1 100 0 0 0.30 0 0.05
80 477 0 280 -165 1.04 100 1 577 0 0 0.30 0 0.05 85 0 0 23 -8 0.985 100 1 100 0 0 0.30 0 0.05
87 4 0 1000 -100 1.015 100 1 104 0 0 0.30 0 0.05
89 607 0 300 -210 1.005 100 1 707 0 0 0.30 0 0.05 90 0 0 300 -300 0.985 100 1 100 0 0 0.30 0 0.05
91 0 0 100 -100 0.98 100 1 100 0 0 0.30 0 0.05
92 0 0 9 -3 0.99 100 1 100 0 0 0.30 0 0.05 99 0 0 100 -100 1.01 100 1 100 0 0 0.30 0 0.05
100 252 0 155 -50 1.017 100 1 352 0 0 0.30 0 0.05
103 40 0 40 -15 1.01 100 1 140 0 0 0.30 0 0.05 104 0 0 23 -8 0.971 100 1 100 0 0 0.30 0 0.05
105 0 0 23 -8 0.965 100 1 100 0 0 0.30 0 0.05
107 0 0 200 -200 0.952 100 1 100 0 0 0.30 0 0.05 110 0 0 23 -8 0.973 100 1 100 0 0 0.30 0 0.05
111 36 0 1000 -100 0.98 100 1 136 0 0 0.30 0 0.05
112 0 0 1000 -100 0.975 100 1 100 0 0 0.30 0 0.05 113 0 0 200 -100 0.993 100 1 100 0 0 0.30 0 0.05
116 0 0 1000 -1000 1.005 100 1 100 0 0 0.30 0 0.05
Table A-9 Line data of the IEEE Reliability the IEEE 118-bus Test System
From
bus
To
bus R1 X1 B1 R0 X0 B0
Rating Status
A B C
1 2 0.0303 0.0999 0.0254 0.0909 0.2997 0.0127 9900 0 0 1
1 3 0.0129 0.0424 0.0108 0.0387 0.1272 0.0054 9900 0 0 1 4 5 0.0018 0.0080 0.0021 0.0053 0.0239 0.0011 9900 0 0 1
3 5 0.0241 0.1080 0.0284 0.0723 0.3240 0.0142 9900 0 0 1
5 6 0.0119 0.0540 0.0143 0.0357 0.1620 0.0071 9900 0 0 1 6 7 0.0046 0.0208 0.0055 0.0138 0.0624 0.0028 9900 0 0 1
8 9 0.0024 0.0305 1.1620 0.0073 0.0915 0.5810 9900 0 0 1
9 10 0.0026 0.0322 1.2300 0.0077 0.0966 0.6150 9900 0 0 1 4 11 0.0209 0.0688 0.0175 0.0627 0.2064 0.0087 9900 0 0 1
5 11 0.0203 0.0682 0.0174 0.0609 0.2046 0.0087 9900 0 0 1
11 12 0.0060 0.0196 0.0050 0.0179 0.0588 0.0025 9900 0 0 1 2 12 0.0187 0.0616 0.0157 0.0561 0.1848 0.0079 9900 0 0 1
3 12 0.0484 0.1600 0.0406 0.1452 0.4800 0.0203 9900 0 0 1
7 12 0.0086 0.0340 0.0087 0.0259 0.1020 0.0044 9900 0 0 1 11 13 0.0223 0.0731 0.0188 0.0668 0.2193 0.0094 9900 0 0 1
12 14 0.0215 0.0707 0.0182 0.0645 0.2121 0.0091 9900 0 0 1
13 15 0.0744 0.2444 0.0627 0.2232 0.7332 0.0313 9900 0 0 1 14 15 0.0595 0.1950 0.0502 0.1785 0.5850 0.0251 9900 0 0 1
12 16 0.0212 0.0834 0.0214 0.0636 0.2502 0.0107 9900 0 0 1
15 17 0.0132 0.0437 0.0444 0.0396 0.1311 0.0222 9900 0 0 1 16 17 0.0454 0.1801 0.0466 0.1362 0.5403 0.0233 9900 0 0 1
17 18 0.0123 0.0505 0.0130 0.0369 0.1515 0.0065 9900 0 0 1 18 19 0.0112 0.0493 0.0114 0.0336 0.1479 0.0057 9900 0 0 1
19 20 0.0252 0.1170 0.0298 0.0756 0.3510 0.0149 9900 0 0 1
15 19 0.0120 0.0394 0.0101 0.0360 0.1182 0.0051 9900 0 0 1 20 21 0.0183 0.0849 0.0216 0.0549 0.2547 0.0108 9900 0 0 1
Appendix A • Network Data of Test Systems
172 |
21 22 0.0209 0.0970 0.0246 0.0627 0.2910 0.0123 9900 0 0 1
22 23 0.0342 0.1590 0.0404 0.1026 0.4770 0.0202 9900 0 0 1 23 24 0.0135 0.0492 0.0498 0.0405 0.1476 0.0249 9900 0 0 1
23 25 0.0156 0.0800 0.0864 0.0468 0.2400 0.0432 9900 0 0 1 25 27 0.0318 0.1630 0.1764 0.0954 0.4890 0.0882 9900 0 0 1
27 28 0.0191 0.0855 0.0216 0.0574 0.2565 0.0108 9900 0 0 1
28 29 0.0237 0.0943 0.0238 0.0711 0.2829 0.0119 9900 0 0 1 8 30 0.0043 0.0504 0.5140 0.0129 0.1512 0.2570 9900 0 0 1
26 30 0.0080 0.0860 0.9080 0.0240 0.2580 0.4540 9900 0 0 1
17 31 0.0474 0.1563 0.0399 0.1422 0.4689 0.0200 9900 0 0 1 29 31 0.0108 0.0331 0.0083 0.0324 0.0993 0.0042 9900 0 0 1
23 32 0.0317 0.1153 0.1173 0.0951 0.3459 0.0587 9900 0 0 1
31 32 0.0298 0.0985 0.0251 0.0894 0.2955 0.0126 9900 0 0 1 27 32 0.0229 0.0755 0.0193 0.0687 0.2265 0.0096 9900 0 0 1
15 33 0.0380 0.1244 0.0319 0.1140 0.3732 0.0160 9900 0 0 1
19 34 0.0752 0.2470 0.0632 0.2256 0.7410 0.0316 9900 0 0 1 35 36 0.0022 0.0102 0.0027 0.0067 0.0306 0.0013 9900 0 0 1
35 37 0.0110 0.0497 0.0132 0.0330 0.1491 0.0066 9900 0 0 1
33 37 0.0415 0.1420 0.0366 0.1245 0.4260 0.0183 9900 0 0 1 34 36 0.0087 0.0268 0.0057 0.0261 0.0804 0.0028 9900 0 0 1
34 37 0.0026 0.0094 0.0098 0.0077 0.0282 0.0049 9900 0 0 1
37 39 0.0321 0.1060 0.0270 0.0963 0.3180 0.0135 9900 0 0 1 37 40 0.0593 0.1680 0.0420 0.1779 0.5040 0.0210 9900 0 0 1
30 38 0.0046 0.0540 0.4220 0.0139 0.1620 0.2110 9900 0 0 1
39 40 0.0184 0.0605 0.0155 0.0552 0.1815 0.0078 9900 0 0 1 40 41 0.0145 0.0487 0.0122 0.0435 0.1461 0.0061 9900 0 0 1
40 42 0.0555 0.1830 0.0466 0.1665 0.5490 0.0233 9900 0 0 1
41 42 0.0410 0.1350 0.0344 0.1230 0.4050 0.0172 9900 0 0 1 43 44 0.0608 0.2454 0.0607 0.1824 0.7362 0.0303 9900 0 0 1
34 43 0.0413 0.1681 0.0423 0.1239 0.5043 0.0211 9900 0 0 1
44 45 0.0224 0.0901 0.0224 0.0672 0.2703 0.0112 9900 0 0 1 45 46 0.0400 0.1356 0.0332 0.1200 0.4068 0.0166 9900 0 0 1
46 47 0.0380 0.1270 0.0316 0.1140 0.3810 0.0158 9900 0 0 1
46 48 0.0601 0.1890 0.0472 0.1803 0.5670 0.0236 9900 0 0 1 47 49 0.0191 0.0625 0.0160 0.0573 0.1875 0.0080 9900 0 0 1
42 49 0.0715 0.3230 0.0860 0.2145 0.9690 0.0430 9900 0 0 1
42 49 0.0715 0.3230 0.0860 0.2145 0.9690 0.0430 9900 0 0 1 45 49 0.0684 0.1860 0.0444 0.2052 0.5580 0.0222 9900 0 0 1
48 49 0.0179 0.0505 0.0126 0.0537 0.1515 0.0063 9900 0 0 1
49 50 0.0267 0.0752 0.0187 0.0801 0.2256 0.0094 9900 0 0 1 49 51 0.0486 0.1370 0.0342 0.1458 0.4110 0.0171 9900 0 0 1
51 52 0.0203 0.0588 0.0140 0.0609 0.1764 0.0070 9900 0 0 1
52 53 0.0405 0.1635 0.0406 0.1215 0.4905 0.0203 9900 0 0 1 53 54 0.0263 0.1220 0.0310 0.0789 0.3660 0.0155 9900 0 0 1
49 54 0.0730 0.2890 0.0738 0.2190 0.8670 0.0369 9900 0 0 1
49 54 0.0869 0.2910 0.0730 0.2607 0.8730 0.0365 9900 0 0 1 54 55 0.0169 0.0707 0.0202 0.0507 0.2121 0.0101 9900 0 0 1
54 56 0.0028 0.0096 0.0073 0.0083 0.0287 0.0037 9900 0 0 1
55 56 0.0049 0.0151 0.0037 0.0146 0.0453 0.0019 9900 0 0 1 56 57 0.0343 0.0966 0.0242 0.1029 0.2898 0.0121 9900 0 0 1
50 57 0.0474 0.1340 0.0332 0.1422 0.4020 0.0166 9900 0 0 1
56 58 0.0343 0.0966 0.0242 0.1029 0.2898 0.0121 9900 0 0 1 51 58 0.0255 0.0719 0.0179 0.0765 0.2157 0.0089 9900 0 0 1
54 59 0.0503 0.2293 0.0598 0.1509 0.6879 0.0299 9900 0 0 1 56 59 0.0825 0.2510 0.0569 0.2475 0.7530 0.0285 9900 0 0 1
56 59 0.0803 0.2390 0.0536 0.2409 0.7170 0.0268 9900 0 0 1
55 59 0.0474 0.2158 0.0565 0.1422 0.6474 0.0282 9900 0 0 1 59 60 0.0317 0.1450 0.0376 0.0951 0.4350 0.0188 9900 0 0 1
59 61 0.0328 0.1500 0.0388 0.0984 0.4500 0.0194 9900 0 0 1
60 61 0.0026 0.0135 0.0146 0.0079 0.0405 0.0073 9900 0 0 1 60 62 0.0123 0.0561 0.0147 0.0369 0.1683 0.0073 9900 0 0 1
61 62 0.0082 0.0376 0.0098 0.0247 0.1128 0.0049 9900 0 0 1
63 64 0.0017 0.0200 0.2160 0.0052 0.0600 0.1080 9900 0 0 1 38 65 0.0090 0.0986 1.0460 0.0270 0.2958 0.5230 9900 0 0 1
64 65 0.0027 0.0302 0.3800 0.0081 0.0906 0.1900 9900 0 0 1
49 66 0.0180 0.0919 0.0248 0.0540 0.2757 0.0124 9900 0 0 1 49 66 0.0180 0.0919 0.0248 0.0540 0.2757 0.0124 9900 0 0 1
62 66 0.0482 0.2180 0.0578 0.1446 0.6540 0.0289 9900 0 0 1
62 67 0.0258 0.1170 0.0310 0.0774 0.3510 0.0155 9900 0 0 1 66 67 0.0224 0.1015 0.0268 0.0672 0.3045 0.0134 9900 0 0 1
65 68 0.0014 0.0160 0.6380 0.0041 0.0480 0.3190 9900 0 0 1
47 69 0.0844 0.2778 0.0709 0.2532 0.8334 0.0355 9900 0 0 1 49 69 0.0985 0.3240 0.0828 0.2955 0.9720 0.0414 9900 0 0 1
69 70 0.0300 0.1270 0.1220 0.0900 0.3810 0.0610 9900 0 0 1
24 70 0.0022 0.4115 0.1020 0.0066 1.2345 0.0510 9900 0 0 1
Appendix A • Network Data of Test Systems
173 |
70 71 0.0088 0.0355 0.0088 0.0265 0.1065 0.0044 9900 0 0 1
24 72 0.0488 0.1960 0.0488 0.1464 0.5880 0.0244 9900 0 0 1 71 72 0.0446 0.1800 0.0444 0.1338 0.5400 0.0222 9900 0 0 1
71 73 0.0087 0.0454 0.0118 0.0260 0.1362 0.0059 9900 0 0 1 70 74 0.0401 0.1323 0.0337 0.1203 0.3969 0.0168 9900 0 0 1
70 75 0.0428 0.1410 0.0360 0.1284 0.4230 0.0180 9900 0 0 1
69 75 0.0405 0.1220 0.1240 0.1215 0.3660 0.0620 9900 0 0 1 74 75 0.0123 0.0406 0.0103 0.0369 0.1218 0.0052 9900 0 0 1
76 77 0.0444 0.1480 0.0368 0.1332 0.4440 0.0184 9900 0 0 1
69 77 0.0309 0.1010 0.1038 0.0927 0.3030 0.0519 9900 0 0 1 75 77 0.0601 0.1999 0.0498 0.1803 0.5997 0.0249 9900 0 0 1
77 78 0.0038 0.0124 0.0126 0.0113 0.0372 0.0063 9900 0 0 1
78 79 0.0055 0.0244 0.0065 0.0164 0.0732 0.0032 9900 0 0 1 77 80 0.0170 0.0485 0.0472 0.0510 0.1455 0.0236 9900 0 0 1
77 80 0.0294 0.1050 0.0228 0.0882 0.3150 0.0114 9900 0 0 1
79 80 0.0156 0.0704 0.0187 0.0468 0.2112 0.0094 9900 0 0 1 68 81 0.0018 0.0202 0.8080 0.0053 0.0606 0.4040 9900 0 0 1
77 82 0.0298 0.0853 0.0817 0.0894 0.2559 0.0409 9900 0 0 1
82 83 0.0112 0.0367 0.0380 0.0336 0.1100 0.0190 9900 0 0 1 83 84 0.0625 0.1320 0.0258 0.1875 0.3960 0.0129 9900 0 0 1
83 85 0.0430 0.1480 0.0348 0.1290 0.4440 0.0174 9900 0 0 1
84 85 0.0302 0.0641 0.0123 0.0906 0.1923 0.0062 9900 0 0 1 85 86 0.0350 0.1230 0.0276 0.1050 0.3690 0.0138 9900 0 0 1
86 87 0.0283 0.2074 0.0445 0.0848 0.6222 0.0223 9900 0 0 1
85 88 0.0200 0.1020 0.0276 0.0600 0.3060 0.0138 9900 0 0 1 85 89 0.0239 0.1730 0.0470 0.0717 0.5190 0.0235 9900 0 0 1
88 89 0.0139 0.0712 0.0193 0.0417 0.2136 0.0097 9900 0 0 1
89 90 0.0518 0.1880 0.0528 0.1554 0.5640 0.0264 9900 0 0 1 89 90 0.0238 0.0997 0.1060 0.0714 0.2991 0.0530 9900 0 0 1
90 91 0.0254 0.0836 0.0214 0.0762 0.2508 0.0107 9900 0 0 1
89 92 0.0099 0.0505 0.0548 0.0297 0.1515 0.0274 9900 0 0 1 89 92 0.0393 0.1581 0.0414 0.1179 0.4743 0.0207 9900 0 0 1
91 92 0.0387 0.1272 0.0327 0.1161 0.3816 0.0163 9900 0 0 1
92 93 0.0258 0.0848 0.0218 0.0774 0.2544 0.0109 9900 0 0 1 92 94 0.0481 0.1580 0.0406 0.1443 0.4740 0.0203 9900 0 0 1
93 94 0.0223 0.0732 0.0188 0.0669 0.2196 0.0094 9900 0 0 1
94 95 0.0132 0.0434 0.0111 0.0396 0.1302 0.0056 9900 0 0 1 80 96 0.0356 0.1820 0.0494 0.1068 0.5460 0.0247 9900 0 0 1
82 96 0.0162 0.0530 0.0544 0.0486 0.1590 0.0272 9900 0 0 1
94 96 0.0269 0.0869 0.0230 0.0807 0.2607 0.0115 9900 0 0 1 80 97 0.0183 0.0934 0.0254 0.0549 0.2802 0.0127 9900 0 0 1
80 98 0.0238 0.1080 0.0286 0.0714 0.3240 0.0143 9900 0 0 1
80 99 0.0454 0.2060 0.0546 0.1362 0.6180 0.0273 9900 0 0 1 92 100 0.0648 0.2950 0.0472 0.1944 0.8850 0.0236 9900 0 0 1
94 100 0.0178 0.0580 0.0604 0.0534 0.1740 0.0302 9900 0 0 1
95 96 0.0171 0.0547 0.0147 0.0513 0.1641 0.0074 9900 0 0 1 96 97 0.0173 0.0885 0.0240 0.0519 0.2655 0.0120 9900 0 0 1
98 100 0.0397 0.1790 0.0476 0.1191 0.5370 0.0238 9900 0 0 1
99 100 0.0180 0.0813 0.0216 0.0540 0.2439 0.0108 9900 0 0 1 100 101 0.0277 0.1262 0.0328 0.0831 0.3786 0.0164 9900 0 0 1
92 102 0.0123 0.0559 0.0146 0.0369 0.1677 0.0073 9900 0 0 1
101 102 0.0246 0.1120 0.0294 0.0738 0.3360 0.0147 9900 0 0 1 100 103 0.0160 0.0525 0.0536 0.0480 0.1575 0.0268 9900 0 0 1
100 104 0.0451 0.2040 0.0541 0.1353 0.6120 0.0271 9900 0 0 1 103 104 0.0466 0.1584 0.0407 0.1398 0.4752 0.0204 9900 0 0 1
103 105 0.0535 0.1625 0.0408 0.1605 0.4875 0.0204 9900 0 0 1
100 106 0.0605 0.2290 0.0620 0.1815 0.6870 0.0310 9900 0 0 1 104 105 0.0099 0.0378 0.0099 0.0298 0.1134 0.0049 9900 0 0 1
105 106 0.0140 0.0547 0.0143 0.0420 0.1641 0.0072 9900 0 0 1
105 107 0.0530 0.1830 0.0472 0.1590 0.5490 0.0236 9900 0 0 1 105 108 0.0261 0.0703 0.0184 0.0783 0.2109 0.0092 9900 0 0 1
106 107 0.0530 0.1830 0.0472 0.1590 0.5490 0.0236 9900 0 0 1
108 109 0.0105 0.0288 0.0076 0.0315 0.0864 0.0038 9900 0 0 1 103 110 0.0391 0.1813 0.0461 0.1172 0.5439 0.0231 9900 0 0 1
109 110 0.0278 0.0762 0.0202 0.0834 0.2286 0.0101 9900 0 0 1
110 111 0.0220 0.0755 0.0200 0.0660 0.2265 0.0100 9900 0 0 1 110 112 0.0247 0.0640 0.0620 0.0741 0.1920 0.0310 9900 0 0 1
17 113 0.0091 0.0301 0.0077 0.0274 0.0903 0.0038 9900 0 0 1
32 113 0.0615 0.2030 0.0518 0.1845 0.6090 0.0259 9900 0 0 1 32 114 0.0135 0.0612 0.0163 0.0405 0.1836 0.0081 9900 0 0 1
27 115 0.0164 0.0741 0.0197 0.0492 0.2223 0.0099 9900 0 0 1
114 115 0.0023 0.0104 0.0028 0.0069 0.0312 0.0014 9900 0 0 1 68 116 0.0003 0.0041 0.1640 0.0010 0.0122 0.0820 9900 0 0 1
12 117 0.0329 0.1400 0.0358 0.0987 0.4200 0.0179 9900 0 0 1
75 118 0.0145 0.0481 0.0120 0.0435 0.1443 0.0060 9900 0 0 1
Appendix A • Network Data of Test Systems
174 |
76 118 0.0164 0.0544 0.0136 0.0492 0.1632 0.0068 9900 0 0 1
Table A-10 Transformer data of the IEEE Reliability the IEEE 118-bus Test System
From bus To bus R1 X1 B1 From winding To winding Tap Shift Rating
Status A B C
8 5 0 0.0267 0 Wye Wye 0.985 0 9900 0 0 1 26 25 0 0.0382 0 Wye Wye 0.960 0 9900 0 0 1
30 17 0 0.0388 0 Wye Wye 0.960 0 9900 0 0 1
38 37 0 0.0375 0 Wye Wye 0.935 0 9900 0 0 1 63 59 0 0.0386 0 Wye Wye 0.960 0 9900 0 0 1
64 61 0 0.0268 0 Wye Wye 0.985 0 9900 0 0 1
65 66 0 0.0370 0 Wye Wye 0.935 0 9900 0 0 1 68 69 0 0.0370 0 Wye Wye 0.935 0 9900 0 0 1
81 80 0 0.0370 0 Wye Wye 0.935 0 9900 0 0 1
Table A-11 Bus data of the 295-bus Generic Distribution System (GDS)
Bus number
Type Pd Qd Gs Bs Area Vm Va Base kV
Zone Vmax Vmin
1 1 0.2407 0.0392 0 0 1 0.9659 -5.49 11 1 1.06 0.94
2 1 0.1033 0.0149 0 0 1 0.9645 -5.52 11 1 1.06 0.94
3 1 0.0000 0.0000 0 0 1 0.9622 -5.55 11 1 1.06 0.94 4 1 0.8932 0.0130 0 0 1 0.9646 -5.51 11 1 1.06 0.94
5 1 0.1699 0.0279 0 0 1 0.9637 -5.52 11 1 1.06 0.94
6 1 0.0473 0.0121 0 0 1 0.9632 -5.53 11 1 1.06 0.94 7 1 0.1474 0.0213 0 0 1 0.9630 -5.53 11 1 1.06 0.94
8 1 0.0000 0.0000 0 0 1 0.9629 -5.53 11 1 1.06 0.94
9 1 0.0111 0.0019 0 0 1 0.9629 -5.53 11 1 1.06 0.94 10 1 0.0000 0.0000 0 0 1 0.9628 -5.53 11 1 1.06 0.94
11 1 0.1066 0.0185 0 0 1 0.9628 -5.53 11 1 1.06 0.94
12 1 0.1020 0.0159 0 0 1 0.9953 -8.58 11 1 1.06 0.94 13 1 0.0872 0.0127 0 0 1 0.9896 -8.63 11 1 1.06 0.94
14 1 0.1731 0.0298 0 0 1 0.9975 -8.56 11 1 1.06 0.94
15 1 0.0000 0.0000 0 0 1 0.9991 -8.55 11 1 1.06 0.94 16 1 0.0299 0.0080 0 0 1 0.9988 -8.55 11 1 1.06 0.94
17 1 0.0160 0.0050 0 0 1 0.9989 -8.55 11 1 1.06 0.94
18 1 0.0000 0.0000 0 0 1 0.9990 -8.55 11 1 1.06 0.94 19 1 0.0361 0.0050 0 0 1 1.0018 -8.52 11 1 1.06 0.94
20 1 0.0000 0.0000 0 0 1 1.0063 -8.48 11 1 1.06 0.94
21 1 0.0152 0.0020 0 0 1 1.0062 -8.49 11 1 1.06 0.94 22 1 0.4105 0.0819 0 0 1 1.0118 -8.43 11 1 1.06 0.94
23 1 0.0000 0.0000 0 0 1 0.9804 -8.70 11 1 1.06 0.94
24 1 0.7024 0.1576 0 0 1 0.9803 -8.70 11 1 1.06 0.94 25 1 0.0000 0.0000 0 0 1 0.9597 -5.57 11 1 1.06 0.94
26 1 0.0000 0.0000 0 0 1 0.9757 -8.76 11 1 1.06 0.94
27 1 0.0000 0.0000 0 0 1 0.9594 -5.58 11 1 1.06 0.94 28 1 0.0000 0.0000 0 0 1 0.9750 -8.77 11 1 1.06 0.94
29 1 0.5936 0.1395 0 0 1 0.9579 -5.58 11 1 1.06 0.94
30 1 0.0786 0.0256 0 0 1 0.9559 -5.58 11 1 1.06 0.94 31 1 0.4062 0.0881 0 0 1 0.9532 -5.57 11 1 1.06 0.94
32 1 0.0000 0.0000 0 0 1 0.9534 -5.57 11 1 1.06 0.94
33 1 0.0000 0.0000 0 0 1 0.9534 -5.57 11 1 1.06 0.94 34 1 0.6605 0.1490 0 0 1 0.9531 -5.57 11 1 1.06 0.94
35 1 0.1326 0.0327 0 0 1 0.9531 -5.57 11 1 1.06 0.94
36 1 0.0391 0.0127 0 0 1 0.9531 -5.57 11 1 1.06 0.94 37 1 0.3897 0.0974 0 0 1 0.9542 -9.20 11 1 1.06 0.94
38 1 0.1095 0.0219 0 0 1 0.9554 -9.21 11 1 1.06 0.94 39 1 0.6730 0.2149 0 0 1 0.9563 -9.21 11 1 1.06 0.94
40 1 0.7774 0.2500 0 0 1 0.9569 -9.18 11 1 1.06 0.94
41 1 0.2059 0.0506 0 0 1 0.9588 -9.18 11 1 1.06 0.94 42 1 0.1184 0.0268 0 0 1 0.9617 -9.19 11 1 1.06 0.94
43 1 0.3977 0.0957 0 0 1 0.9639 -9.19 11 1 1.06 0.94
44 1 0.3127 0.0576 0 0 1 0.9719 -8.77 11 1 1.06 0.94 45 1 0.4198 0.0946 0 0 1 0.9724 -8.77 11 1 1.06 0.94
46 1 0.0000 0.0000 0 0 1 0.9710 -8.82 11 1 1.06 0.94
47 1 0.0000 0.0000 0 0 1 0.9710 -8.82 11 1 1.06 0.94 48 1 0.2733 0.0603 0 0 1 0.9708 -8.82 11 1 1.06 0.94
49 1 0.4437 0.1055 0 0 1 0.9706 -8.82 11 1 1.06 0.94
50 1 0.2681 0.0424 0 0 1 1.0175 -8.39 11 1 1.06 0.94 51 1 0.4793 0.0878 0 0 1 1.0164 -8.42 11 1 1.06 0.94
52 1 0.0000 0.0000 0 0 1 1.0171 -8.43 11 1 1.06 0.94
53 1 0.4992 0.0806 0 0 1 1.0167 -8.44 11 1 1.06 0.94
Appendix A • Network Data of Test Systems
175 |
54 1 0.6236 0.1264 0 0 1 1.0178 -8.34 11 1 1.06 0.94
55 1 0.3901 0.0812 0 0 1 0.9660 -5.49 11 1 1.06 0.94 56 1 0.1188 0.0187 0 0 1 0.9674 -5.47 11 1 1.06 0.94
57 1 0.1646 0.0273 0 0 1 0.9698 -5.42 11 1 1.06 0.94 58 1 0.5276 0.1371 0 0 1 0.9724 -5.38 11 1 1.06 0.94
59 1 0.6552 0.1307 0 0 1 0.9730 -5.48 11 1 1.06 0.94
60 1 0.7942 0.1471 0 0 1 0.9741 -5.33 11 1 1.06 0.94 61 1 0.2830 0.0492 0 0 1 0.9729 -5.48 11 1 1.06 0.94
62 1 0.1565 0.0245 0 0 1 0.9711 -5.40 11 1 1.06 0.94
63 1 0.4096 0.0733 0 0 1 0.9693 -5.43 11 1 1.06 0.94 64 1 0.2411 0.0413 0 0 1 0.9686 -5.44 11 1 1.06 0.94
65 1 0.4400 0.0758 0 0 1 0.9676 -5.44 11 1 1.06 0.94
66 1 0.8287 0.1574 0 0 1 0.9650 -5.43 11 1 1.06 0.94 67 1 0.0000 0.0000 0 0 1 0.9619 -5.56 11 1 1.06 0.94
68 1 0.0000 0.0000 0 0 1 0.9619 -5.56 11 1 1.06 0.94
69 1 0.0167 0.0028 0 0 1 0.9618 -5.56 11 1 1.06 0.94 70 1 0.0000 0.0000 0 0 1 0.9619 -5.56 11 1 1.06 0.94
71 1 0.1628 0.0314 0 0 1 0.9617 -5.56 11 1 1.06 0.94
72 1 0.0000 0.0000 0 0 1 0.9619 -5.56 11 1 1.06 0.94 73 1 0.0231 0.0037 0 0 1 0.9619 -5.56 11 1 1.06 0.94
74 1 0.0000 0.0000 0 0 1 1.0148 -8.46 11 1 1.06 0.94
75 1 0.4166 0.0669 0 0 1 1.0142 -8.47 11 1 1.06 0.94 76 1 0.7046 0.1391 0 0 1 1.0150 -8.45 11 1 1.06 0.94
77 1 0.0000 0.0000 0 0 1 1.0130 -6.64 11 1 1.06 0.94
78 1 0.1007 0.0147 0 0 1 1.0244 -7.60 11 1 1.06 0.94 79 1 0.4065 0.0721 0 0 1 1.0222 -7.64 11 1 1.06 0.94
80 1 0.7890 0.2540 0 0 1 1.0203 -7.67 11 1 1.06 0.94
81 1 0.0000 0.0000 0 0 1 1.0139 -7.61 11 1 1.06 0.94 82 1 0.0000 0.0000 0 0 1 1.0138 -7.62 11 1 1.06 0.94
83 1 0.0370 0.0051 0 0 1 1.0134 -7.63 11 1 1.06 0.94
84 1 0.0308 0.0041 0 0 1 1.0132 -7.63 11 1 1.06 0.94 85 1 0.0000 0.0000 0 0 1 1.0129 -7.64 11 1 1.06 0.94
86 1 0.1251 0.0236 0 0 1 1.0126 -7.65 11 1 1.06 0.94
87 1 0.9032 0.1630 0 0 1 1.0254 -7.66 11 1 1.06 0.94 88 1 0.0000 0.0000 0 0 1 1.0130 -7.62 11 1 1.06 0.94
89 1 1.1915 0.3914 0 0 1 1.0122 -7.63 11 1 1.06 0.94
90 1 0.0000 0.0000 0 0 1 1.0123 -7.64 11 1 1.06 0.94 91 1 0.0000 0.0000 0 0 1 1.0116 -7.68 11 1 1.06 0.94
92 1 0.0440 0.0072 0 0 1 1.0115 -7.68 11 1 1.06 0.94
93 1 0.0000 0.0000 0 0 1 1.0114 -7.70 11 1 1.06 0.94 94 1 0.0082 0.0010 0 0 1 1.0110 -7.70 11 1 1.06 0.94
95 1 0.0000 0.0000 0 0 1 1.0103 -7.71 11 1 1.06 0.94
96 1 0.0367 0.0061 0 0 1 1.0103 -7.72 11 1 1.06 0.94 97 1 0.0000 0.0000 0 0 1 1.0099 -7.72 11 1 1.06 0.94
98 1 0.0163 0.0020 0 0 1 1.0097 -7.72 11 1 1.06 0.94
99 1 0.0825 0.0163 0 0 1 1.0094 -7.73 11 1 1.06 0.94 100 1 0.0734 0.0143 0 0 1 1.0097 -7.73 11 1 1.06 0.94
101 1 0.0000 0.0000 0 0 1 1.0106 -7.74 11 1 1.06 0.94
102 1 0.0663 0.0112 0 0 1 1.0103 -7.74 11 1 1.06 0.94 103 1 0.0092 0.0010 0 0 1 1.0103 -7.75 11 1 1.06 0.94
104 1 0.0000 0.0000 0 0 1 1.0099 -7.77 11 1 1.06 0.94
105 1 0.0235 0.0031 0 0 1 1.0099 -7.77 11 1 1.06 0.94 106 1 0.0387 0.0061 0 0 1 1.0095 -7.78 11 1 1.06 0.94
107 1 0.0183 0.0031 0 0 1 1.0090 -7.80 11 1 1.06 0.94 108 1 0.0000 0.0000 0 0 1 1.0087 -7.81 11 1 1.06 0.94
109 1 0.0000 0.0000 0 0 1 1.0086 -7.81 11 1 1.06 0.94
110 1 0.1291 0.0315 0 0 1 1.0083 -7.81 11 1 1.06 0.94 111 1 0.0203 0.0031 0 0 1 1.0085 -7.82 11 1 1.06 0.94
112 1 0.0000 0.0000 0 0 1 1.0084 -7.82 11 1 1.06 0.94
113 1 0.0061 0.0009 0 0 1 1.0083 -7.82 11 1 1.06 0.94 114 1 0.0102 0.0010 0 0 1 1.0083 -7.83 11 1 1.06 0.94
115 1 0.0000 0.0000 0 0 1 1.0079 -7.84 11 1 1.06 0.94
116 1 0.0061 0.0009 0 0 1 1.0078 -7.84 11 1 1.06 0.94 117 1 0.0000 0.0000 0 0 1 1.0078 -7.84 11 1 1.06 0.94
118 1 0.0051 0.0007 0 0 1 1.0078 -7.84 11 1 1.06 0.94
119 1 0.0081 0.0010 0 0 1 1.0078 -7.84 11 1 1.06 0.94 120 1 0.0000 0.0000 0 0 1 1.0078 -7.84 11 1 1.06 0.94
121 1 0.0000 0.0000 0 0 1 1.0078 -7.84 11 1 1.06 0.94
122 1 0.0000 0.0000 0 0 1 1.0078 -7.84 11 1 1.06 0.94 123 1 0.0000 0.0000 0 0 1 1.0078 -7.84 11 1 1.06 0.94
124 1 0.0091 0.0010 0 0 1 1.0076 -7.84 11 1 1.06 0.94
125 1 0.0233 0.0071 0 0 1 1.0074 -7.84 11 1 1.06 0.94 126 1 0.0071 0.0010 0 0 1 1.0073 -7.84 11 1 1.06 0.94
127 1 0.0203 0.0030 0 0 1 1.0073 -7.85 11 1 1.06 0.94
128 1 0.0000 0.0000 0 0 1 0.9791 -7.67 11 1 1.06 0.94
Appendix A • Network Data of Test Systems
176 |
129 1 0.0431 0.0077 0 0 1 0.9791 -7.67 11 1 1.06 0.94
130 1 0.0000 0.0000 0 0 1 0.9792 -7.67 11 1 1.06 0.94 131 1 0.0353 0.0048 0 0 1 0.9767 -7.71 11 1 1.06 0.94
132 1 0.0180 0.0028 0 0 1 0.9744 -7.75 11 1 1.06 0.94 133 1 0.0170 0.0028 0 0 1 0.9710 -7.81 11 1 1.06 0.94
134 1 0.0000 0.0000 0 0 1 0.9699 -7.84 11 1 1.06 0.94
135 1 0.0094 0.0009 0 0 1 0.9699 -7.84 11 1 1.06 0.94 136 1 0.8682 0.2853 0 0 1 0.9657 -7.96 11 1 1.06 0.94
137 1 0.0000 0.0000 0 0 1 0.9657 -7.96 11 1 1.06 0.94
138 1 0.0000 0.0000 0 0 1 0.9808 -7.64 11 1 1.06 0.94 139 1 0.0096 0.0019 0 0 1 0.9808 -7.64 11 1 1.06 0.94
140 1 0.0000 0.0000 0 0 1 0.9841 -7.58 11 1 1.06 0.94
141 1 0.0213 0.0068 0 0 1 0.9840 -7.58 11 1 1.06 0.94 142 1 0.0000 0.0000 0 0 1 0.9871 -7.53 11 1 1.06 0.94
143 1 0.0029 0.0004 0 0 1 0.9871 -7.53 11 1 1.06 0.94
144 1 0.0029 0.0004 0 0 1 0.9896 -7.48 11 1 1.06 0.94 145 1 0.0000 0.0000 0 0 1 0.9935 -7.42 11 1 1.06 0.94
146 1 0.0000 0.0000 0 0 1 0.9966 -7.35 11 1 1.06 0.94
147 1 0.0189 0.0030 0 0 1 0.9965 -7.35 11 1 1.06 0.94 148 1 0.0000 0.0000 0 0 1 1.0029 -7.21 11 1 1.06 0.94
149 1 0.0201 0.0030 0 0 1 1.0028 -7.21 11 1 1.06 0.94
150 1 0.0000 0.0000 0 0 1 1.0083 -7.03 11 1 1.06 0.94 151 1 0.0091 0.0010 0 0 1 1.0083 -7.03 11 1 1.06 0.94
152 1 0.0000 0.0000 0 0 1 0.9903 -7.48 11 1 1.06 0.94
153 1 0.0206 0.0039 0 0 1 0.9902 -7.48 11 1 1.06 0.94 154 1 0.0000 0.0000 0 0 1 0.9865 -7.55 11 1 1.06 0.94
155 1 0.0127 0.0019 0 0 1 0.9865 -7.55 11 1 1.06 0.94
156 1 0.0000 0.0000 0 0 1 0.9837 -7.59 11 1 1.06 0.94 157 1 0.0348 0.0058 0 0 1 0.9835 -7.59 11 1 1.06 0.94
158 1 0.0203 0.0029 0 0 1 0.9834 -7.59 11 1 1.06 0.94
159 1 0.0183 0.0029 0 0 1 0.9825 -7.62 11 1 1.06 0.94 160 1 0.0000 0.0000 0 0 1 0.9791 -7.70 11 1 1.06 0.94
161 1 0.0345 0.0048 0 0 1 0.9788 -7.71 11 1 1.06 0.94
162 1 0.1312 0.0316 0 0 1 0.9785 -7.71 11 1 1.06 0.94 163 1 0.0048 0.0007 0 0 1 0.9785 -7.71 11 1 1.06 0.94
164 1 0.0076 0.0010 0 0 1 0.9764 -7.78 11 1 1.06 0.94
165 1 0.0000 0.0000 0 0 1 0.9754 -7.81 11 1 1.06 0.94 166 1 0.0000 0.0000 0 0 1 0.9752 -7.81 11 1 1.06 0.94
167 1 0.0200 0.0029 0 0 1 0.9752 -7.81 11 1 1.06 0.94
168 1 0.0390 0.0076 0 0 1 0.9749 -7.81 11 1 1.06 0.94 169 1 0.0000 0.0000 0 0 1 0.9747 -7.81 11 1 1.06 0.94
170 1 0.0000 0.0000 0 0 1 0.9691 -8.01 11 1 1.06 0.94
171 1 0.0000 0.0000 0 0 1 0.9689 -8.01 11 1 1.06 0.94 172 1 0.1116 0.0225 0 0 1 0.9684 -8.02 11 1 1.06 0.94
173 1 0.0000 0.0000 0 0 1 0.9683 -8.02 11 1 1.06 0.94
174 1 0.0347 0.0047 0 0 1 0.9683 -8.02 11 1 1.06 0.94 175 1 0.0000 0.0000 0 0 1 0.9682 -8.02 11 1 1.06 0.94
176 1 0.0356 0.0066 0 0 1 0.9681 -8.03 11 1 1.06 0.94
177 1 0.0000 0.0000 0 0 1 0.9681 -8.03 11 1 1.06 0.94 178 1 0.0000 0.0000 0 0 1 0.9597 -5.57 11 1 1.06 0.94
179 1 0.0000 0.0000 0 0 1 0.9746 -7.81 11 1 1.06 0.94
180 1 0.0000 0.0000 0 0 1 0.9745 -7.82 11 1 1.06 0.94 181 1 0.0085 0.0009 0 0 1 0.9744 -7.82 11 1 1.06 0.94
182 1 0.0000 0.0000 0 0 1 0.9742 -7.82 11 1 1.06 0.94 183 1 0.0114 0.0209 0 0 1 0.9741 -7.81 11 1 1.06 0.94
184 1 0.0000 0.0000 0 0 1 0.9740 -7.82 11 1 1.06 0.94
185 1 0.0190 0.0028 0 0 1 0.9739 -7.82 11 1 1.06 0.94 186 1 0.0398 0.0085 0 0 1 0.9737 -7.82 11 1 1.06 0.94
187 1 0.0000 0.0000 0 0 1 0.9743 -7.84 11 1 1.06 0.94
188 1 0.0000 0.0000 0 0 1 0.9743 -7.84 11 1 1.06 0.94 189 1 0.0047 0.0065 0 0 1 0.9743 -7.84 11 1 1.06 0.94
190 1 0.0047 0.0007 0 0 1 0.9743 -7.84 11 1 1.06 0.94
191 1 0.0047 0.0007 0 0 1 0.9743 -7.84 11 1 1.06 0.94 192 1 0.0180 0.0028 0 0 1 0.9726 -7.90 11 1 1.06 0.94
193 1 0.0000 0.0000 0 0 1 0.9719 -7.91 11 1 1.06 0.94
194 1 0.0085 0.0009 0 0 1 0.9719 -7.91 11 1 1.06 0.94 195 1 0.0085 0.0009 0 0 1 0.9718 -7.91 11 1 1.06 0.94
196 1 0.0151 0.0028 0 0 1 0.9717 -7.91 11 1 1.06 0.94
197 1 0.0000 0.0000 0 0 1 0.9713 -7.92 11 1 1.06 0.94 198 1 0.0160 0.0019 0 0 1 0.9713 -7.92 11 1 1.06 0.94
199 1 0.0170 0.0028 0 0 1 0.9711 -7.93 11 1 1.06 0.94
200 1 0.0226 0.0047 0 0 1 0.9708 -7.93 11 1 1.06 0.94 201 1 0.0000 0.0000 0 0 1 0.9706 -7.94 11 1 1.06 0.94
202 1 0.0198 0.0028 0 0 1 0.9705 -7.94 11 1 1.06 0.94
203 1 0.0075 0.0009 0 0 1 0.9703 -7.94 11 1 1.06 0.94
Appendix A • Network Data of Test Systems
177 |
204 1 0.0000 0.0000 0 0 1 0.9702 -7.95 11 1 1.06 0.94
205 1 0.0000 0.0000 0 0 1 0.9701 -7.95 11 1 1.06 0.94 206 1 0.0000 0.0000 0 0 1 0.9700 -7.95 11 1 1.06 0.94
207 1 0.0075 0.0009 0 0 1 0.9700 -7.95 11 1 1.06 0.94 208 1 0.0442 0.0094 0 0 1 0.9698 -7.95 11 1 1.06 0.94
209 1 0.0000 0.0000 0 0 1 0.9715 -7.93 11 1 1.06 0.94
210 1 0.0000 0.0000 0 0 1 0.9710 -7.95 11 1 1.06 0.94 211 1 0.0000 0.0000 0 0 1 0.9710 -7.95 11 1 1.06 0.94
212 1 0.0000 0.0000 0 0 1 0.9709 -7.95 11 1 1.06 0.94
213 1 0.0320 0.0047 0 0 1 0.9707 -7.95 11 1 1.06 0.94 214 1 0.0000 0.0000 0 0 1 0.9703 -7.97 11 1 1.06 0.94
215 1 0.0000 0.0000 0 0 1 0.9703 -7.97 11 1 1.06 0.94
216 1 0.0000 0.0000 0 0 1 0.9696 -7.99 11 1 1.06 0.94 217 1 0.0789 0.0197 0 0 1 0.9691 -8.00 11 1 1.06 0.94
218 1 0.0000 0.0000 0 0 1 0.9688 -8.01 11 1 1.06 0.94
219 1 0.0619 0.0094 0 0 1 0.9687 -8.01 11 1 1.06 0.94 220 1 0.0000 0.0000 0 0 1 1.0166 -8.41 11 1 1.06 0.94
221 1 0.0000 0.0000 0 0 1 0.9678 -9.19 11 1 1.06 0.94
222 1 0.9151 0.1797 0 0 1 1.0192 -8.36 11 1 1.06 0.94 223 1 0.0000 0.0000 0 0 1 1.0121 -6.66 11 1 1.06 0.94
224 1 0.6706 0.1313 0 0 1 1.0126 -6.68 11 1 1.06 0.94
225 1 17.0941 3.0690 0 0 1 0.9761 -5.30 11 1 1.06 0.94 226 1 0.0000 0.0000 0 0 1 0.9761 -5.30 11 1 1.06 0.94
227 1 2.4472 0.4207 0 0 1 1.0205 -8.32 11 1 1.06 0.94
228 1 0.0000 0.0000 0 0 1 1.0205 -8.32 11 1 1.06 0.94 229 1 0.0000 0.0000 0 0 1 1.0273 -7.53 11 1 1.06 0.94
230 1 1.8787 0.3504 0 0 1 1.0273 -7.53 11 1 1.06 0.94
231 1 0.9612 0.1756 0 0 1 1.0134 -6.62 11 1 1.06 0.94 232 1 68.8649 14.4206 0 0 1 0.9880 -2.12 132 1 1.10 0.90
233 1 0.0000 0.0000 0 0 1 0.9880 -2.12 132 1 1.10 0.90
234 1 0.0000 0.0000 0 0 1 1.0343 23.78 33 1 1.06 0.94 235 1 0.0000 0.0000 0 0 1 1.0343 23.78 33 1 1.06 0.94
236 1 0.0000 0.0000 0 0 1 1.0112 24.49 33 1 1.06 0.94
237 1 0.0000 0.0000 0 0 1 1.0343 23.78 33 1 1.06 0.94 238 1 0.0000 0.0000 0 0 1 1.0343 23.78 33 1 1.06 0.94
239 1 3.4953 0.7065 0 0 1 0.9751 25.45 33 1 1.06 0.94
240 1 0.0000 0.0000 0 0 1 1.0125 25.17 33 1 1.06 0.94 241 1 31.7830 8.8286 0 0 1 1.0323 23.69 33 1 1.06 0.94
242 1 28.0839 5.4088 0 0 1 1.0088 24.62 33 1 1.06 0.94
243 1 0.0000 0.0000 0 0 1 1.0088 24.62 33 1 1.06 0.94 244 1 14.6242 2.3698 0 0 1 1.0144 24.72 33 1 1.06 0.94
245 1 0.0000 0.0000 0 0 1 1.0144 24.72 33 1 1.06 0.94
246 1 40.7015 8.7496 0 0 1 0.9719 24.23 33 1 1.06 0.94 247 1 0.0000 0.0000 0 0 1 0.9719 24.23 33 1 1.06 0.94
248 1 26.1959 5.3742 0 0 1 1.0358 23.82 33 1 1.06 0.94
249 1 0.0000 0.0000 0 0 1 1.0358 23.82 33 1 1.06 0.94 250 1 0.0000 0.0000 0 0 1 1.0157 24.73 33 1 1.06 0.94
251 1 0.0000 0.0000 0 0 1 1.0191 24.35 33 1 1.06 0.94
252 1 0.0000 0.0000 0 0 1 0.9906 -1.92 132 1 1.10 0.90 253 1 68.3597 12.1889 0 0 1 0.9874 -2.30 132 1 1.10 0.90
254 1 0.0000 0.0000 0 0 1 0.9874 -2.30 132 1 1.10 0.90
255 1 0.0000 0.0000 0 0 1 0.9910 -1.86 132 1 1.10 0.90 256 1 0.0000 0.0000 0 0 1 0.9910 -1.86 132 1 1.10 0.90
257 1 42.9038 9.1610 0 0 1 0.9860 -2.10 132 1 1.10 0.90 258 1 0.0000 0.0000 0 0 1 0.9860 -2.10 132 1 1.10 0.90
259 1 0.0000 0.0000 0 0 1 1.0173 24.54 33 1 1.06 0.94
260 1 0.0000 0.0000 0 0 1 1.0173 24.54 33 1 1.06 0.94 261 1 0.0000 0.0000 0 0 1 0.9872 -2.25 132 1 1.10 0.90
262 1 0.0000 0.0000 0 0 1 0.9901 -1.89 132 1 1.10 0.90
263 1 0.0000 0.0000 0 0 1 0.9901 -1.89 132 1 1.10 0.90 264 1 0.0000 0.0000 0 0 1 0.9727 25.20 33 1 1.06 0.94
265 1 0.0000 0.0000 0 0 1 1.0341 23.78 33 1 1.06 0.94
266 1 0.0000 0.0000 0 0 1 1.0341 23.78 33 1 1.06 0.94 267 1 0.0000 0.0000 0 0 1 1.0294 23.68 33 1 1.06 0.94
268 1 0.0000 0.0000 0 0 1 1.0294 23.68 33 1 1.06 0.94
269 1 0.0000 0.0000 0 0 1 0.9814 -2.16 132 1 1.10 0.90 270 1 0.0000 0.0000 0 0 1 0.9865 -2.18 132 1 1.10 0.90
271 1 0.0000 0.0000 0 0 1 0.9812 -2.16 132 1 1.10 0.90
272 1 0.0000 0.0000 0 0 1 0.9850 -2.18 132 1 1.10 0.90 273 1 0.0000 0.0000 0 0 1 0.9907 -1.90 132 1 1.10 0.90
274 1 0.0000 0.0000 0 0 1 0.9909 -2.03 132 1 1.10 0.90
275 1 0.0000 0.0000 0 0 1 0.9864 -2.18 132 1 1.10 0.90 276 1 0.0000 0.0000 0 0 1 0.9892 -2.15 132 1 1.10 0.90
277 1 0.0000 0.0000 0 0 1 0.9892 -2.15 132 1 1.10 0.90
278 1 0.0000 0.0000 0 0 1 0.9900 -2.04 132 1 1.10 0.90
Appendix A • Network Data of Test Systems
178 |
279 1 0.0000 0.0000 0 0 1 0.9900 -2.04 132 1 1.10 0.90
280 1 0.0000 0.0000 0 0 1 1.0126 22.37 0.4 1 1.06 0.94 281 1 0.0000 0.0000 0 0 1 1.0126 22.37 0.4 1 1.06 0.94
282 1 0.0000 0.0000 0 0 1 0.9826 53.78 0.4 1 1.06 0.94 283 1 0.0000 0.0000 0 0 1 0.9826 53.78 0.4 1 1.06 0.94
284 1 0.0000 0.0000 0 0 1 1.0173 54.54 0.4 1 1.06 0.94
285 1 0.0000 0.0000 0 0 1 1.0126 -7.63 11 1 1.06 0.94 286 1 0.0000 0.0000 0 0 1 1.0126 -7.63 11 1 1.06 0.94
287 1 0.0000 0.0000 0 0 1 0.9987 -0.19 400 1 1.10 0.90
288 1 0.0000 0.0000 0 0 1 0.9987 -0.19 400 1 1.10 0.90 289 1 0.0000 0.0000 0 0 1 0.9987 -0.50 275 1 1.10 0.90
290 1 0.0000 0.0000 0 0 1 0.9996 -0.08 275 1 1.10 0.90
291 1 0.0000 0.0000 0 0 1 0.9993 -0.12 275 1 1.10 0.90 292 1 0.0000 0.0000 0 0 1 0.9993 -0.12 275 1 1.10 0.90
293 1 0.0000 0.0000 0 0 1 0.9992 -0.13 400 1 1.10 0.90
294 1 0.0000 0.0000 0 0 1 0.9992 -0.13 400 1 1.10 0.90 295 3 0.0000 0.0000 0 0 1 1.0000 0.00 400 1 1.10 0.90
Table A-12 Generator data of the Generic Distribution System (GDS)
Bus Pg Qg Qmax Qmin Vg Rate Status Pmax Pmin R1 X1 R0 X0
300 0 0 99999 -99999 1 1200 1 99999 0 0.0000 0.0208 0.0006 0.0063
Table A-13 Line data of the Generic Distribution System (GDS)
From bus To
bus R1 X1 B1 R0 X0 B0
Rating Type Status
A B C
232 233 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
232 278 0.00840 0.00598 0.00136 0.05040 0.01794 0.00045 99 0 0 C 1
278 256 0.00103 0.00736 0.00167 0.00167 0.02208 0.00056 99 0 0 C 1 233 279 0.00840 0.00598 0.00136 0.05040 0.01794 0.00045 99 0 0 C 1
279 255 0.00103 0.00736 0.00167 0.00617 0.00221 0.00056 99 0 0 C 1
256 255 0.00001 0.00001 0.00000 0.00006 0.00001 0.00000 99 0 0 OL 1
279 276 0.00139 0.00989 0.00225 0.00834 0.02967 0.00075 99 0 0 C 1
278 277 0.00139 0.00989 0.00225 0.00834 0.02967 0.00075 99 0 0 C 1
247 246 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 253 254 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
233 253 0.00388 0.02760 0.00627 0.02328 0.08280 0.00209 99 0 0 C 1
232 254 0.00388 0.02760 0.00627 0.02328 0.08280 0.00209 99 0 0 C 1 256 263 0.00588 0.00441 0.03391 0.03528 0.01323 0.01130 99 0 0 C 1
255 262 0.00588 0.00441 0.03391 0.03528 0.01323 0.01130 99 0 0 C 1
226 225 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 226 58 0.12491 0.07400 0.00025 0.74946 0.22200 0.00008 99 0 0 C 1
58 62 0.05640 0.02157 0.00005 0.33840 0.06471 0.00002 99 0 0 C 1 62 63 0.08474 0.04121 0.00012 0.50844 0.12363 0.00004 99 0 0 C 1
61 59 0.02940 0.01983 0.00007 0.17640 0.05949 0.00002 99 0 0 C 1
59 60 0.06000 0.27600 0.00008 0.36000 0.82800 0.00003 99 0 0 C 1 60 226 0.10500 0.04831 0.00014 0.63000 0.14493 0.00005 99 0 0 C 1
63 64 0.04237 0.02060 0.00006 0.25422 0.06180 0.00002 99 0 0 C 1
225 57 0.12712 0.06181 0.00019 0.76272 0.18543 0.00006 99 0 0 C 1 57 56 0.04943 0.02404 0.00007 0.29658 0.07212 0.00002 99 0 0 C 1
56 55 0.02825 0.01374 0.00004 0.16950 0.04122 0.00001 99 0 0 C 1
64 65 0.21795 0.03210 0.00005 1.30770 0.09630 0.00002 99 0 0 C 1 64 66 0.40866 0.06019 0.00010 2.45196 0.18057 0.00003 99 0 0 C 1
67 68 0.09174 0.16264 0.00000 0.55044 0.48792 0.00000 99 0 0 OL 1
68 69 0.07521 0.02876 0.00007 0.45126 0.08628 0.00002 99 0 0 C 1 68 70 0.07645 0.13554 0.00000 0.45870 0.40662 0.00000 99 0 0 OL 1
70 71 0.11281 0.04314 0.00011 0.67686 0.12942 0.00004 99 0 0 C 1
70 72 0.03431 0.02314 0.00008 0.20586 0.06942 0.00003 99 0 0 C 1 72 73 0.08405 0.14909 0.00000 0.50430 0.44727 0.00000 99 0 0 OL 1
72 3 0.12000 0.05521 0.00016 0.72000 0.16563 0.00005 99 0 0 C 1
3 2 0.09750 0.04486 0.00013 0.58500 0.13458 0.00004 99 0 0 C 1 2 55 0.06000 0.02760 0.00008 0.36000 0.08280 0.00003 99 0 0 C 1
55 1 0.05449 0.00802 0.00001 0.32694 0.02406 0.00000 99 0 0 C 1
74 75 0.13161 0.05033 0.00130 0.78966 0.15099 0.00043 99 0 0 C 1 74 76 0.05650 0.02747 0.00008 0.33900 0.08241 0.00003 99 0 0 C 1
3 178 0.11281 0.04314 0.00011 0.67686 0.12942 0.00004 99 0 0 C 1
178 25 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
25 27 0.01470 0.00992 0.00004 0.08820 0.02976 0.00001 99 0 0 C 1
26 28 0.01470 0.00992 0.00004 0.08820 0.02976 0.00001 99 0 0 C 1
55 4 0.10248 0.02641 0.00006 0.61488 0.07923 0.00002 99 0 0 C 1 4 5 0.17569 0.04527 0.00009 1.05414 0.13581 0.00003 99 0 0 C 1
Appendix A • Network Data of Test Systems
179 |
5 6 0.14640 0.03773 0.00008 0.87840 0.11319 0.00003 99 0 0 C 1
6 7 0.07521 0.02876 0.00007 0.45126 0.08628 0.00002 99 0 0 C 1 7 8 0.05640 0.02157 0.00005 0.33840 0.06471 0.00002 99 0 0 C 1
8 9 0.07521 0.02876 0.00007 0.45126 0.08628 0.00002 99 0 0 C 1 8 10 0.04700 0.01798 0.00005 0.28200 0.05394 0.00002 99 0 0 C 1
10 11 0.01880 0.00792 0.00002 0.11280 0.02338 0.00001 99 0 0 C 1
12 14 0.03760 0.01438 0.00004 0.22560 0.04314 0.00001 99 0 0 C 1 12 13 0.10341 0.03955 0.00100 0.62046 0.11865 0.00033 99 0 0 C 1
13 23 0.16921 0.06471 0.00016 1.01526 0.19413 0.00005 99 0 0 C 1
24 23 0.01880 0.00719 0.00002 0.11280 0.02157 0.00001 99 0 0 C 1 23 26 0.09887 0.04807 0.00015 0.59322 0.14421 0.00005 99 0 0 C 1
27 29 0.07320 0.01886 0.00004 0.43920 0.05658 0.00001 99 0 0 C 1
29 30 0.13622 0.02006 0.00003 0.81732 0.06018 0.00001 99 0 0 C 1 30 32 0.19071 0.02809 0.00004 1.14426 0.08427 0.00001 99 0 0 C 1
32 31 0.02820 0.01079 0.00003 0.16920 0.06474 0.00001 99 0 0 C 1
32 33 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 33 34 0.02820 0.01079 0.00003 0.16920 0.03237 0.00001 99 0 0 C 1
33 35 0.11712 0.03018 0.00006 0.70272 0.09054 0.00002 99 0 0 C 1
35 36 0.10898 0.01605 0.00003 0.65388 0.04815 0.00001 99 0 0 C 1 37 38 0.27244 0.04012 0.00006 1.63464 0.12036 0.00002 99 0 0 C 1
38 39 0.16346 0.02407 0.00004 0.98076 0.07221 0.00001 99 0 0 C 1
28 46 0.09887 0.04807 0.00015 0.59322 0.14421 0.00005 99 0 0 C 1 46 48 0.08173 0.01204 0.00002 0.49038 0.03612 0.00001 99 0 0 C 1
47 46 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
47 49 0.08173 0.01204 0.00002 0.49038 0.03612 0.00001 99 0 0 C 1 28 45 0.32693 0.04815 0.00008 1.96158 0.14445 0.00003 99 0 0 C 1
45 44 0.14640 0.03773 0.00008 0.87840 0.11319 0.00003 99 0 0 C 1
221 47 0.04943 0.24010 0.00007 0.29658 0.07203 0.00002 99 0 0 C 1 221 43 0.13176 0.03395 0.00007 0.79056 0.10185 0.00002 99 0 0 C 1
43 42 0.08748 0.02264 0.00005 0.52488 0.06792 0.00002 99 0 0 C 1
42 41 0.11712 0.03018 0.00006 0.70272 0.09054 0.00002 99 0 0 C 1 41 40 0.08784 0.02264 0.00005 0.52704 0.06792 0.00002 99 0 0 C 1
40 39 0.03814 0.05617 0.00009 0.22884 0.16851 0.00003 99 0 0 C 1
227 228 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 76 220 0.14124 0.06868 0.00021 0.72744 0.20604 0.00007 99 0 0 C 1
220 50 0.05650 0.02747 0.00008 0.33900 0.08241 0.00003 99 0 0 C 1
50 228 0.15536 0.07555 0.00023 0.93216 0.22665 0.00008 99 0 0 C 1 220 51 0.04411 0.02975 0.00011 0.26466 0.08925 0.00004 99 0 0 C 1
52 53 0.07521 0.02876 0.00007 0.45126 0.08628 0.00002 99 0 0 C 1
52 54 0.09401 0.35950 0.00009 0.56406 1.07850 0.00003 99 0 0 C 1 54 228 0.23425 0.06036 0.00013 1.40550 0.18108 0.00004 99 0 0 C 1
14 15 0.02820 0.01079 0.00003 0.16920 0.03237 0.00001 99 0 0 C 1
15 18 0.27870 0.09107 0.00000 1.24722 0.27321 0.00000 99 0 0 OL 1 18 16 0.55431 0.24284 0.00000 0.32586 0.72856 0.00000 99 0 0 OL 1
18 17 0.48502 0.21249 0.00000 2.91012 0.63747 0.00000 99 0 0 OL 1
15 19 0.04700 0.01798 0.00005 0.28200 0.05394 0.00002 99 0 0 C 1 19 20 0.07521 0.02876 0.00001 0.45126 0.08628 0.00000 99 0 0 C 1
20 21 0.13161 0.05033 0.00013 0.78966 0.15099 0.00004 99 0 0 C 1
20 22 0.09401 0.03595 0.00009 0.56406 0.10785 0.00003 99 0 0 C 1 22 227 0.13500 0.06211 0.00018 0.81000 0.18633 0.00006 99 0 0 C 1
255 273 0.00282 0.00298 0.02927 0.01692 0.00894 0.00976 99 0 0 C 1
256 252 0.00282 0.00298 0.02927 0.01692 0.00894 0.00976 99 0 0 C 1 243 242 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
243 236 0.01274 0.01633 0.00293 0.07644 0.04899 0.00098 99 0 0 C 1 236 251 0.00952 0.05048 0.00006 0.05712 0.15144 0.00002 99 0 0 C 1
251 259 0.00504 0.02673 0.00003 0.03024 0.08019 0.00001 99 0 0 C 1
250 260 0.00585 0.02700 0.00003 0.03510 0.08100 0.00001 99 0 0 C 1 251 241 0.01776 0.06236 0.00007 0.07056 0.18708 0.00002 99 0 0 C 1
240 250 0.01176 0.06236 0.00007 0.07056 0.18708 0.00002 99 0 0 C 1
250 244 0.02414 0.08624 0.00009 0.14484 0.25872 0.00003 99 0 0 C 1 244 245 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
274 252 0.00348 0.01608 0.00350 0.02088 0.04824 0.00117 99 0 0 C 1
258 257 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 255 257 0.00399 0.02622 0.00596 0.02394 0.07866 0.00199 99 0 0 C 1
256 258 0.00399 0.02622 0.05960 0.02394 0.07866 0.01987 99 0 0 C 1
259 260 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 275 257 0.00276 0.01272 0.00277 0.01656 0.03816 0.00092 99 0 0 C 1
270 258 0.00197 0.01104 0.00251 0.01182 0.03312 0.00084 99 0 0 C 1
269 257 0.00197 0.01104 0.00251 0.01182 0.03312 0.00084 99 0 0 C 1 257 261 0.00137 0.00897 0.00204 0.00822 0.02691 0.00068 99 0 0 C 1
258 271 0.00137 0.00897 0.00204 0.00822 0.02691 0.00068 99 0 0 C 1
248 249 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1 248 241 0.02324 0.08624 0.00009 0.13944 0.25872 0.00003 99 0 0 C 1
248 234 0.02324 0.01372 0.00153 0.13944 0.04116 0.00051 99 0 0 C 1
234 267 0.07471 0.04409 0.00493 0.44826 0.13227 0.00164 99 0 0 C 1
Appendix A • Network Data of Test Systems
180 |
249 235 0.02324 0.01372 0.00153 0.13944 0.04116 0.00051 99 0 0 C 1
235 268 0.07471 0.04409 0.00493 0.44826 0.13227 0.00164 99 0 0 C 1 261 253 0.00305 0.02001 0.00455 0.01830 0.06003 0.00152 99 0 0 C 1
248 266 0.05313 0.03135 0.00350 0.31878 0.09405 0.00117 99 0 0 C 1 249 265 0.05313 0.03135 0.00350 0.31878 0.09406 0.00117 99 0 0 C 1
229 230 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
230 78 0.07841 0.05289 0.00190 0.47046 0.15867 0.00063 99 0 0 C 1 78 79 0.05881 0.03967 0.00014 0.35286 0.11901 0.00005 99 0 0 C 1
222 227 0.12742 0.08595 0.00031 0.76452 0.25785 0.00010 99 0 0 C 1
79 80 0.06050 0.03388 0.00011 0.36300 0.10164 0.00004 99 0 0 C 1 80 81 0.30600 0.02760 0.00008 1.83600 0.08280 0.00003 99 0 0 C 1
81 88 0.04500 0.02070 0.00006 0.27000 0.06210 0.00002 99 0 0 C 1
88 89 0.06000 0.02807 0.00008 0.36000 0.84210 0.00003 99 0 0 C 1 88 286 0.06000 0.02807 0.00008 0.36000 0.08421 0.00003 99 0 0 C 1
285 286 0.00001 0.00001 0.00000 0.00006 0.00003 0.00000 99 0 0 OL 1
285 90 0.04500 0.02070 0.00006 0.27000 0.06210 0.00002 99 0 0 C 1 90 91 0.07645 0.13554 0.00000 0.45870 0.40662 0.00000 99 0 0 OL 1
91 92 0.14750 0.07500 0.00000 0.88500 0.22500 0.00000 99 0 0 OL 1
91 93 0.03058 0.05421 0.00000 0.18348 0.16263 0.00000 99 0 0 OL 1 93 101 0.16430 0.19791 0.00000 0.98580 0.59373 0.00000 99 0 0 OL 1
101 102 0.38350 0.19500 0.00000 2.30100 0.58500 0.00000 99 0 0 OL 1
101 103 0.05868 0.07068 0.00000 0.35208 0.21204 0.00000 99 0 0 OL 1 103 104 0.10562 0.12723 0.00000 0.63372 0.38169 0.00000 99 0 0 OL 1
104 105 0.14750 0.07500 0.00000 0.88500 0.22500 0.00000 99 0 0 OL 1
104 106 0.10500 0.10150 0.00000 0.63000 0.30450 0.00000 99 0 0 OL 1 106 107 0.18000 0.17400 0.00000 1.08000 0.52200 0.00000 99 0 0 OL 1
107 108 0.09000 0.08700 0.00000 0.54000 0.26100 0.00000 99 0 0 OL 1
108 109 0.11800 0.06000 0.00000 0.70800 0.06300 0.00000 99 0 0 OL 1 109 110 0.21211 0.02603 0.00003 1.27266 0.07809 0.00001 99 0 0 C 1
108 111 0.15085 0.13090 0.00000 0.90510 0.39270 0.00000 99 0 0 OL 1
111 112 0.17240 0.11782 0.00000 1.03440 0.35346 0.00000 99 0 0 OL 1 112 113 0.14750 0.08120 0.00000 0.88500 0.24360 0.00000 99 0 0 OL 1
112 114 0.08620 0.05891 0.00000 0.51720 0.17673 0.00000 99 0 0 OL 1
114 115 0.38789 0.26509 0.00000 2.32734 0.79527 0.00000 99 0 0 OL 1 115 116 0.47200 0.24000 0.00000 2.83200 0.72000 0.00000 99 0 0 OL 1
116 117 0.23600 0.12000 0.00000 1.41600 0.36000 0.00000 99 0 0 OL 1
117 118 0.23600 0.12000 0.00000 1.41600 0.36000 0.00000 99 0 0 OL 1 117 119 0.17700 0.09000 0.00000 1.06200 0.27000 0.00000 99 0 0 OL 1
115 120 0.17240 0.11782 0.00000 1.03440 0.35346 0.00000 99 0 0 OL 1
120 121 0.05449 0.00802 0.00001 0.32694 0.02406 0.00000 99 0 0 C 1 121 122 0.05449 0.00802 0.00001 0.32694 0.02406 0.00000 99 0 0 C 1
121 123 0.05449 0.00802 0.00001 0.32694 0.02406 0.00000 99 0 0 C 1
123 124 0.20650 0.10500 0.00000 1.23900 0.31500 0.00000 99 0 0 OL 1 124 125 0.41300 0.21000 0.00000 2.47800 0.63000 0.00000 99 0 0 OL 1
125 126 0.17700 0.09000 0.00000 1.06200 0.27000 0.00000 99 0 0 OL 1
126 127 0.20680 0.10500 0.00000 1.23900 0.31500 0.00000 99 0 0 OL 1 81 82 0.03760 0.01438 0.00004 0.22560 0.04314 0.00001 99 0 0 C 1
82 83 0.21550 0.14727 0.00000 1.29300 0.44181 0.00000 99 0 0 OL 1
83 84 0.12930 0.08836 0.00000 0.77580 0.26508 0.00000 99 0 0 OL 1 84 85 0.21550 0.14727 0.00000 1.29300 0.44181 0.00000 99 0 0 OL 1
85 86 0.17240 0.11782 0.00000 1.03440 0.35346 0.00000 99 0 0 OL 1
87 229 0.16818 0.29818 0.00000 1.00908 0.89454 0.00000 99 0 0 OL 1 93 94 0.14750 0.07500 0.00000 0.88500 0.22500 0.00000 99 0 0 OL 1
94 95 0.29500 0.15000 0.00000 1.77000 0.45000 0.00000 99 0 0 OL 1 95 96 0.11800 0.06000 0.00000 0.70800 0.18000 0.00000 99 0 0 OL 1
95 97 0.23600 0.12000 0.00000 1.41600 0.36000 0.00000 99 0 0 OL 1
97 100 0.26550 0.13500 0.00000 1.59300 0.40500 0.00000 99 0 0 OL 1 97 98 0.17700 0.09000 0.00000 1.06200 0.27000 0.00000 99 0 0 OL 1
98 99 0.29500 0.15000 0.00000 1.77000 0.45000 0.00000 99 0 0 OL 1
258 272 0.00879 0.02175 0.00455 0.05274 0.06525 0.00152 99 0 0 C 1 239 264 0.04180 0.11780 0.00120 0.25080 0.35340 0.00040 99 0 0 C 1
231 223 0.04879 0.05058 0.00024 0.29274 0.15174 0.00008 99 0 0 C 1
223 150 0.09755 0.33284 0.00000 0.58530 0.99852 0.00000 99 0 0 OL 1 150 151 0.17322 0.07589 0.00000 1.03932 0.22767 0.00000 99 0 0 OL 1
150 148 0.21000 0.20300 0.00000 1.26000 0.60900 0.00000 99 0 0 OL 1
148 149 0.24510 0.10624 0.00000 1.47060 0.31872 0.00000 99 0 0 OL 1 148 146 0.25860 0.17673 0.00000 1.55160 0.53019 0.00000 99 0 0 OL 1
146 147 0.34645 0.15178 0.00000 2.07870 0.45534 0.00000 99 0 0 OL 1
146 145 0.12930 0.08836 0.00000 0.77580 0.26508 0.00000 99 0 0 OL 1 145 152 0.29500 0.15000 0.00000 1.77000 0.45000 0.00000 99 0 0 OL 1
145 144 0.30169 0.20618 0.00000 1.80140 0.61854 0.00000 99 0 0 OL 1
144 142 0.19395 0.13255 0.00000 1.16370 0.39765 0.00000 99 0 0 OL 1 142 143 0.17322 0.07589 0.00000 1.03932 0.22767 0.00000 99 0 0 OL 1
142 140 0.23705 0.16200 0.00000 1.42230 0.48600 0.00000 99 0 0 OL 1
140 141 0.20787 0.09107 0.00000 1.24722 0.27321 0.00000 99 0 0 OL 1
Appendix A • Network Data of Test Systems
181 |
140 138 0.25860 0.17673 0.00000 1.55160 0.53019 0.00000 99 0 0 OL 1
138 139 0.13858 0.06071 0.00000 0.83148 0.18213 0.00000 99 0 0 OL 1 138 130 0.12930 0.08836 0.00000 0.77580 0.26508 0.00000 99 0 0 OL 1
130 131 0.21550 0.14727 0.00000 1.29300 0.44181 0.00000 99 0 0 OL 1 130 128 0.17240 0.11782 0.00000 1.03440 0.35346 0.00000 99 0 0 OL 1
128 129 0.10775 0.07364 0.00000 0.64650 0.22092 0.00000 99 0 0 OL 1
231 77 0.05489 0.05690 0.00270 0.32934 0.17070 0.00090 99 0 0 C 1 77 224 0.03881 0.10400 0.00000 0.23286 0.31200 0.00000 99 0 0 OL 1
214 215 0.12930 0.08836 0.00000 0.77580 0.26508 0.00000 99 0 0 OL 1
215 216 0.19395 0.13255 0.00000 1.16370 0.39765 0.00000 99 0 0 OL 1 216 170 0.25860 0.17673 0.00000 1.55160 0.53019 0.00000 99 0 0 OL 1
170 171 0.06465 0.04418 0.00000 0.38790 0.13254 0.00000 99 0 0 OL 1
171 172 0.27244 0.04012 0.00006 1.63464 0.12036 0.00002 99 0 0 C 1 172 173 0.16346 0.02407 0.00000 0.98076 0.07221 0.00000 99 0 0 OL 1
173 174 0.08620 0.05891 0.00000 0.51720 0.17673 0.00000 99 0 0 OL 1
174 175 0.15085 0.10309 0.00000 0.90510 0.30927 0.00000 99 0 0 OL 1 175 176 0.27244 0.04012 0.00006 1.63464 0.12036 0.00002 99 0 0 C 1
216 217 0.27716 0.12142 0.00000 1.66296 0.36429 0.00000 99 0 0 OL 1
217 218 0.48502 0.21249 0.00000 2.91012 1.27494 0.00000 99 0 0 OL 1 218 219 0.22621 0.04686 0.00009 1.35726 0.14058 0.00003 99 0 0 C 1
152 153 0.20787 0.09107 0.00000 1.24722 0.27321 0.00000 99 0 0 OL 1
152 154 0.35400 0.18000 0.00000 2.12400 0.54000 0.00000 99 0 0 OL 1 154 155 0.24251 0.10624 0.00000 1.45506 0.31872 0.00000 99 0 0 OL 1
154 156 0.27716 0.12142 0.00000 1.66296 0.36426 0.00000 99 0 0 OL 1
156 157 0.25860 0.17673 0.00000 1.55160 0.53019 0.00000 99 0 0 OL 1 157 158 0.31180 0.13660 0.00000 1.87080 0.40980 0.00000 99 0 0 OL 1
156 159 0.11149 0.07376 0.00000 0.66894 0.22128 0.00000 99 0 0 OL 1
159 160 0.34612 0.20653 0.00000 2.07672 0.61959 0.00000 99 0 0 OL 1 160 161 0.15608 0.10326 0.00000 0.93648 0.30978 0.00000 99 0 0 OL 1
161 162 0.22298 0.14752 0.00000 1.33788 0.44256 0.00000 99 0 0 OL 1
162 163 0.21350 0.09126 0.00000 1.28100 0.27378 0.00000 99 0 0 OL 1 160 164 0.34479 0.23564 0.00000 2.06874 0.70692 0.00000 99 0 0 OL 1
164 165 0.12930 0.08836 0.00000 0.77580 0.26508 0.00000 99 0 0 OL 1
165 166 0.11800 0.06000 0.00000 0.70800 0.18000 0.00000 99 0 0 OL 1 166 167 0.20787 0.09107 0.00000 1.24722 0.27321 0.00000 99 0 0 OL 1
166 168 0.23600 0.12000 0.00000 1.41600 0.36000 0.00000 99 0 0 OL 1
168 169 0.17700 0.09000 0.00000 1.06200 0.27000 0.00000 99 0 0 OL 1 169 179 0.09401 0.03595 0.00009 0.56406 0.10785 0.00003 99 0 0 C 1
179 180 0.17700 0.09000 0.00000 1.06200 0.27000 0.00000 99 0 0 OL 1
180 181 0.23600 0.12000 0.00000 1.41600 0.36000 0.00000 99 0 0 OL 1 180 182 0.35400 0.18000 0.00000 2.12400 0.54000 0.00000 99 0 0 OL 1
182 183 0.35400 0.18000 0.00000 2.12400 0.54000 0.00000 99 0 0 OL 1
182 184 0.27716 0.12142 0.00000 1.66296 0.36426 0.00000 99 0 0 OL 1 184 185 0.21350 0.09126 0.00000 1.28100 0.27378 0.00000 99 0 0 OL 1
184 186 0.53374 0.22816 0.00000 3.20244 0.68448 0.00000 99 0 0 OL 1
131 132 0.19395 0.13255 0.00000 1.16370 0.39765 0.00000 99 0 0 OL 1 132 133 0.30169 0.20618 0.00000 1.81014 0.61854 0.00000 99 0 0 OL 1
133 134 0.09000 0.08700 0.00000 0.54000 0.26100 0.00000 99 0 0 OL 1
134 135 0.13161 0.05033 0.00000 0.78966 0.15099 0.00000 99 0 0 OL 1 134 136 0.36000 0.34800 0.00000 2.16000 1.04400 0.00000 99 0 0 OL 1
136 137 0.12000 0.11600 0.00000 0.72000 0.34800 0.00000 99 0 0 OL 1
165 187 0.17240 0.11782 0.00000 0.03440 0.35346 0.00000 99 0 0 OL 1 187 188 0.20787 0.09107 0.00000 1.24722 0.27321 0.00000 99 0 0 OL 1
188 189 0.27716 0.12142 0.00000 1.66296 0.36426 0.00000 99 0 0 OL 1 188 190 0.41574 0.18213 0.00000 2.49440 0.54639 0.00000 99 0 0 OL 1
190 191 0.27716 0.12142 0.00000 1.66296 0.36426 0.00000 99 0 0 OL 1
187 192 0.30169 0.20618 0.00000 1.81014 0.61854 0.00000 99 0 0 OL 1 192 209 0.25860 0.17673 0.00000 1.55160 0.53019 0.00000 99 0 0 OL 1
209 210 0.12930 0.08836 0.00000 0.77580 0.26508 0.00000 99 0 0 OL 1
210 215 0.21550 0.14727 0.00000 1.29300 0.44181 0.00000 99 0 0 OL 1 210 211 0.18258 0.07622 0.00000 1.09548 0.22866 0.00000 99 0 0 OL 1
211 212 0.29213 0.12195 0.00000 1.75278 0.36585 0.00000 99 0 0 OL 1
212 213 0.43820 0.17673 0.00000 2.62920 0.53019 0.00000 99 0 0 OL 1 192 193 0.36517 0.15244 0.00000 2.19102 0.45732 0.00000 99 0 0 OL 1
193 196 0.14607 0.06098 0.00000 0.87642 0.18294 0.00000 99 0 0 OL 1
193 194 0.17322 0.07589 0.00000 1.03932 0.22767 0.00000 99 0 0 OL 1 194 195 0.31180 0.13660 0.00000 1.87080 0.40980 0.00000 99 0 0 OL 1
196 197 0.25562 0.10671 0.00000 1.53372 0.32013 0.00000 99 0 0 OL 1
197 198 0.20787 0.09107 0.00000 1.24722 0.27321 0.00000 99 0 0 OL 1 197 199 0.18258 0.07622 0.00000 1.09548 0.22866 0.00000 99 0 0 OL 1
201 202 0.09401 0.03595 0.00009 0.56406 0.10785 0.00003 99 0 0 C 1
201 203 0.43820 0.18293 0.00000 2.62920 0.54879 0.00000 99 0 0 OL 1 203 204 0.21910 0.09146 0.00000 1.31460 0.27447 0.00000 99 0 0 OL 1
204 205 0.07521 0.02876 0.00007 0.45126 0.08628 0.00002 99 0 0 C 1
205 206 0.14607 0.06098 0.00000 0.87642 0.18294 0.00000 99 0 0 OL 1
Appendix A • Network Data of Test Systems
182 |
206 207 0.29213 0.12195 0.00000 1.75278 0.36585 0.00000 99 0 0 OL 1
206 208 0.40168 0.16768 0.00000 2.41008 0.50304 0.00000 99 0 0 OL 1 245 249 0.04356 0.20100 0.00022 0.26136 0.60300 0.00007 99 0 0 C 1
199 200 0.29213 0.12195 0.00000 1.75278 0.36585 0.00000 99 0 0 OL 1 200 201 0.25562 0.10671 0.00000 1.53372 0.32013 0.00000 99 0 0 OL 1
234 237 0.03600 0.38510 0.00004 0.21600 1.15530 0.00001 99 0 0 C 1
235 238 0.36300 0.03851 0.00004 0.21780 0.11553 0.00001 99 0 0 C 1 176 177 0.49039 0.07222 0.00012 2.94234 0.21666 0.00004 99 0 0 C 1
Table A-14 Transformer data of the Generic Distribution System (GDS)
From bus To bus R1 X1 B1 From winding To winding Tap Shift Rating
Status A B C
294 295 0.00010 0.01000 0.00000 Wye Wye 1.00 0 99 0 0 1
234 294 0.00330 0.14660 0.00000 Wye Wye 1.00 0 99 0 0 1
293 295 0.00010 0.01000 0.00000 Wye Wye 1.00 0 99 0 0 1 235 293 0.00333 0.14667 0.00000 Wye Wye 1.00 0 99 0 0 1
248 278 0.00833 0.30000 0.00000 Delta Wye 1.00 30 99 0 0 1
249 279 0.00833 0.30000 0.00000 Delta Wye 1.00 30 99 0 0 1 255 292 0.00417 0.18333 0.00000 Wye Wye 1.00 0 99 0 0 1
292 295 0.00010 0.01000 0.00000 Wye Wye 1.00 0 99 0 0 1
256 291 0.00417 0.18333 0.00000 Wye Wye 1.00 0 99 0 0 1 291 295 0.00010 0.01000 0.00000 Wye Wye 1.00 0 99 0 0 1
257 290 0.00556 0.22222 0.00000 Wye Wye 1.00 0 99 0 0 1
290 295 0.00010 0.01000 0.00000 Wye Wye 1.00 0 99 0 0 1 258 289 0.00278 0.01380 0.00000 Wye Wye 1.00 0 99 0 0 1
289 295 0.00005 0.00500 0.00000 Wye Wye 1.00 0 99 0 0 1
228 265 0.01587 0.44440 0.00000 Wye Wye 1.00 0 99 0 0 1 227 264 0.01587 0.44440 0.00000 Wye Wye 1.00 0 99 0 0 1
245 254 0.01250 0.40000 0.00000 Delta Wye 1.00 30 99 0 0 1 244 275 0.01250 0.40000 0.00000 Delta Wye 1.00 30 99 0 0 1
243 271 0.01250 0.40000 0.00000 Delta Wye 1.25 30 99 0 0 1
242 272 0.01250 0.40000 0.00000 Delta Wye 1.00 30 99 0 0 1 246 276 0.02500 0.55000 0.00000 Delta Wye 1.00 30 99 0 0 1
247 277 0.02500 0.55000 0.00000 Delta Wye 1.00 30 99 0 0 1
288 295 0.00010 0.01000 0.00000 Wye Wye 1.00 0 99 0 0 1 259 288 0.00208 0.10000 0.00000 Wye Wye 1.00 0 99 0 0 1
287 295 0.00005 0.00500 0.00000 Wye Wye 1.00 0 99 0 0 1
260 287 0.00104 0.05000 0.00000 Wye Wye 1.00 0 99 0 0 1 250 273 0.00833 0.30000 0.00000 Delta Wye 1.25 30 99 0 0 1
251 263 0.00833 0.30000 0.00000 Delta Wye 1.00 30 99 0 0 1
229 269 0.03333 0.60000 0.00000 Wye Delta 1.00 -30 99 0 0 1 230 270 0.03333 0.60000 0.00000 Wye Delta 1.00 -30 99 0 0 1
232 268 0.06667 0.80000 0.00000 Wye Delta 1.00 -30 99 0 0 1
231 267 0.06667 0.80000 0.00000 Wye Delta 1.00 -30 99 0 0 1 241 274 0.02500 0.55000 0.00000 Delta Wye 1.00 30 99 0 0 1
233 266 0.06667 0.80000 0.00000 Wye Delta 1.05 -30 99 0 0 1
284 261 0.01786 0.28570 0.00000 Delta Wye 1.00 30 99 0 0 1 283 239 0.02142 0.17143 0.00000 Delta Wye 0.95 30 99 0 0 1
282 240 0.02142 0.17143 0.00000 Delta Wye 0.95 30 99 0 0 1
281 286 0.02301 0.14423 0.00000 Delta Wye 1.00 30 99 0 0 1 280 285 0.02301 0.14423 0.00000 Delta Wye 1.00 30 99 0 0 1
Appendix B • Minimization of SMEE by greedy monitor placement
183 |
Appendix B Minimization of SMEE by
greedy monitor placement
Appendix B • Minimization of SMEE by greedy monitor placement
184 |
Nu
m.
Bu
ses
SM
EE
A
SM
EE
B
SM
EE
C
SM
EE
AB
C
Std
. d
ev.
A
Std
. d
ev.
B
Std
. d
ev.
C
Std
. d
ev.
AB
C
Max
.
A
Max
.
B
Max
.
C
Max
.
AB
C
Over
all
net
work
cover
age
(%)
LG
fau
lts
net
work
cover
age
(%)
LL
fau
lts
net
work
cover
age
(%)
LL
G f
ault
s
net
work
cover
age
(%)
LL
L f
ault
s
net
work
cover
age
(%)
1
223
49.0
9
51.7
0
51.8
0
50.8
7
4.9
5
5.4
4
5.9
6
5.4
0
60.2
5
66.4
2
64.9
3
62.8
5
9.5
3
33.0
9
2.2
8
0.4
8
2.2
8
2
229
39.2
9
40.8
8
40.4
6
40.2
1
1.9
5
3.4
2
3.0
3
2.7
8
42.6
3
47.5
9
46.2
3
45.4
5
26.2
0
52.1
6
26.0
2
0.6
0
26.0
2
3
290
32.7
7
35.1
9
34.6
0
34.1
9
2.0
1
3.6
1
3.2
6
2.9
4
36.2
9
41.4
8
40.1
0
39.2
6
32.6
7
76.2
6
26.3
8
1.6
8
26.3
8
4
16
27.2
8
29.8
9
29.2
3
28.8
0
2.3
4
3.8
8
3.5
2
3.2
4
32.0
2
36.7
3
35.2
6
34.6
5
39.6
9
90.6
5
33.2
1
1.6
8
33.2
1
5
238
13.6
5
15.9
6
15.4
2
15.0
1
3.0
6
3.8
6
3.4
7
3.4
1
22.0
6
22.7
8
21.3
4
22.0
4
41.7
6
98.2
0
33.2
1
2.4
0
33.2
1
6
246
9.9
3
12.1
3
11.5
9
11.2
2
3.3
2
3.8
7
3.4
8
3.4
9
19.4
8
18.9
6
17.5
3
18.6
4
41.9
4
98.5
6
33.2
1
2.7
6
33.2
1
7
239
3.7
9
5.8
1
5.2
7
4.9
5
3.7
6
3.8
8
3.4
9
3.6
1
15.2
4
12.6
5
11.2
2
13.0
2
42.1
2
98.9
2
33.2
1
3.1
2
33.2
1
8
214
2.7
3
4.5
4
4.2
2
3.8
3
3.1
2
3.7
6
3.4
3
3.3
3
19.8
6
16.1
1
14.2
7
15.9
5
56.5
9
99.2
8
52.2
8
22.4
2
52.4
0
9
67
1.8
9
2.9
0
2.8
7
2.5
6
2.7
5
2.8
4
2.7
8
2.5
5
26.9
4
11.5
2
11.2
9
11.2
9
65.7
4
99.6
4
61.5
1
40.1
7
61.6
3
10
126
1.3
1
2.2
9
2.4
0
2.0
0
2.4
4
2.2
5
2.1
0
1.9
4
27.8
1
9.1
1
8.5
0
12.5
4
76.3
8
99.6
4
74.3
4
57.0
7
74.4
6
11
75
1.1
7
1.7
5
2.1
2
1.6
8
2.5
0
1.7
0
1.7
0
1.7
3
28.1
0
6.1
5
6.4
3
13.1
0
79.8
3
99.6
4
77.1
0
65.3
5
77.2
2
12
236
1.1
3
1.7
1
1.7
8
1.5
4
2.5
1
1.9
4
1.9
9
1.9
2
28.0
8
6.6
6
6.9
2
13.3
9
81.5
3
99.6
4
77.1
0
72.1
8
77.2
2
13
137
0.8
4
1.6
9
1.7
4
1.4
2
1.0
6
2.0
9
2.1
3
1.7
5
4.2
4
7.5
6
7.8
3
6.5
4
84.1
7
100
.00
80.3
4
75.9
0
80.4
6
14
65
0.7
6
1.5
3
1.6
5
1.3
1
1.1
9
2.3
0
2.3
8
1.9
4
4.8
5
8.5
1
8.8
3
7.3
9
86.1
8
100
.00
83.0
9
78.4
2
83.2
1
15
42
0.7
3
1.3
8
1.4
7
1.1
9
1.3
8
2.6
0
2.7
5
2.2
4
5.7
1
10.7
6
11.2
0
9.2
2
88.9
7
100
.00
85.6
1
84.5
3
85.7
3
16
186
0.6
6
1.2
5
1.3
5
1.0
9
1.4
0
2.6
3
2.7
8
2.2
7
6.2
4
11.8
6
12.2
3
10.1
1
90.8
6
100
.00
88.1
3
87.0
5
88.2
5
17
208
0.5
7
1.1
1
1.2
1
0.9
7
1.3
1
2.5
1
2.6
6
2.1
6
6.5
2
12.5
4
13.4
1
10.7
2
93.2
0
100
.00
91.2
5
90.1
7
91.3
7
18
176
0.5
0
0.9
0
1.0
1
0.8
0
1.2
2
2.2
9
2.4
1
1.9
7
6.2
2
11.8
5
12.4
4
10.1
7
95.8
6
100
.00
94.6
0
94.2
4
94.6
0
19
189
0.4
3
0.8
1
0.8
8
0.7
1
1.3
6
2.5
5
2.6
8
2.2
0
7.0
0
13.2
8
13.9
4
11.4
1
96.3
1
100
.00
95.2
0
94.8
4
95.2
0
20
35
0.4
1
0.7
7
0.8
5
0.6
7
1.3
2
2.4
2
2.5
6
2.1
0
8.2
5
15.7
2
16.4
9
13.4
8
97.2
1
100
.00
96.4
0
96.0
4
96.4
0
21
69
0.4
1
0.7
5
0.8
3
0.6
6
1.3
2
2.4
6
2.6
0
2.1
2
8.2
4
16.1
0
16.8
7
13.7
3
97.2
7
100
.00
96.4
0
96.2
8
96.4
0
22
119
0.4
4
0.7
9
0.8
9
0.7
1
1.5
4
2.8
8
3.0
6
2.4
9
9.8
9
19.6
3
20.5
9
16.7
0
97.7
5
100
.00
97.0
0
97.0
0
97.0
0
23
99
0.6
0
1.0
4
1.2
0
0.9
4
2.3
3
4.3
6
4.7
2
3.8
0
19.0
0
36.4
2
38.1
3
31.1
7
98.8
0
100
.00
98.4
4
98.3
2
98.4
4
24
1
2.8
9
4.6
7
4.6
2
4.0
6
3.4
5
5.4
1
5.5
5
4.7
8
27.8
1
48.6
0
48.3
1
41.5
7
99.0
7
100
.00
98.8
0
98.6
8
98.8
0
25
9
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
100
.00
100
.00
100
.00
100
.00
100
.00
Tab
le B
-1
Gre
edy
mon
ito
r p
lace
men
t w
ith
min
imiz
atio
n o
f sa
g m
agn
itu
de
esti
mat
ion
err
or
(SM
EE
) fo
r al
l ty
pes
of
fau
lts
Appendix B • Minimization of SMEE by greedy monitor placement
185 |
Nu
m.
Buse
s S
ME
E
A
SM
EE
B
SM
EE
C
SM
EE
AB
C
Std
.
dev
.
A
Std
.
dev
.
B
Std
.
dev
.
C
Std
.
dev
.
AB
C
Max
.
A
Max
.
B
Max
.
C
Max
.
AB
C
Net
wo
rk
cover
age
(%)
1
66
0.3
0
9.1
1
10
.08
6.4
9
0.4
7
5.2
4
5.9
6
3.0
5
3.9
6
48
.66
19
.47
18
.17
0.9
6
2
16
0.0
2
1.8
9
0.7
9
0.9
0
0.0
6
1.6
0
0.5
9
0.7
2
0.4
2
5.1
0
1.8
5
2.2
8
34
.53
3
20
7
0.0
2
1.1
7
0.5
4
0.5
8
0.0
8
1.1
9
0.5
1
0.5
5
0.6
2
6.2
3
1.9
3
2.3
9
56
.12
4
35
0.0
2
0.8
2
0.3
4
0.3
9
0.0
8
1.0
9
0.4
0
0.4
9
0.6
7
7.2
0
1.3
7
2.7
4
62
.83
5
98
0.0
1
0.3
5
0.1
9
0.1
8
0.0
2
0.3
5
0.1
9
0.1
8
0.1
5
2.1
7
0.9
3
1.0
0
72
.78
6
74
0.0
0
0.2
4
0.1
3
0.1
2
0.0
1
0.1
9
0.1
0
0.1
0
0.0
7
0.8
7
0.4
4
0.4
2
75
.54
7
39
0.0
0
0.2
0
0.1
1
0.1
0
0.0
1
0.2
1
0.1
1
0.1
1
0.0
7
0.9
4
0.4
9
0.4
4
78
.06
8
17
7
0.0
0
0.1
7
0.0
9
0.0
9
0.0
1
0.2
2
0.1
1
0.1
1
0.1
0
1.2
2
0.5
2
0.5
8
83
.21
9
11
9
0.0
0
0.1
1
0.0
8
0.0
6
0.0
0
0.1
4
0.1
1
0.0
8
0.0
2
0.5
2
0.5
5
0.3
3
89
.57
10
67
0.0
0
0.0
9
0.0
6
0.0
5
0.0
0
0.1
2
0.1
0
0.0
7
0.0
1
0.5
4
0.4
8
0.3
4
91
.37
11
13
5
0.0
0
0.0
6
0.0
5
0.0
4
0.0
0
0.1
0
0.0
9
0.0
6
0.0
1
0.5
5
0.4
9
0.3
5
94
.60
12
19
1
0.0
0
0.0
7
0.0
6
0.0
4
0.0
0
0.1
1
0.1
0
0.0
7
0.0
1
0.6
2
0.5
5
0.3
9
95
.20
13
12
3
0.0
0
0.0
8
0.0
6
0.0
5
0.0
0
0.1
3
0.1
2
0.0
8
0.0
1
0.7
3
0.6
5
0.4
6
95
.92
14
18
6
0.0
0
0.1
2
0.1
1
0.0
8
0.0
0
0.2
9
0.2
8
0.1
9
0.0
3
1.9
1
1.6
9
1.2
0
98
.44
15
1
0.0
9
2.4
0
2.0
7
1.5
2
0.2
9
0.6
8
0.6
7
0.2
5
2.3
3
4.3
7
2.6
0
1.8
9
98
.80
16
11
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
10
0.0
0
Tab
le B
-2
Gre
edy
mon
ito
r p
lace
men
t w
ith
min
imiz
atio
n o
f sa
g m
agn
itu
de
esti
mat
ion
err
or
(SM
EE
) fo
r li
ne
to l
ine
fau
lts
Appendix B • Minimization of SMEE by greedy monitor placement
186 |
Nu
m.
Buse
s S
ME
E
A
SM
EE
B
SM
EE
C
SM
EE
AB
C
Std
.
dev
.
A
Std
.
dev
.
B
Std
.
dev
.
C
Std
.
dev
.
AB
C
Max
.
A
Max
.
B
Max
.
C
Max
.
AB
C
Net
wo
rk
cover
age
(%)
1
13
5
66
.57
69
.73
69
.57
68
.62
0.4
3
5.5
8
5.3
0
3.7
7
67
.54
83
.02
81
.81
77
.42
0.1
2
2
25
7
43
.42
49
.85
49
.13
47
.47
0.4
6
6.5
3
6.0
7
4.3
2
44
.24
64
.53
61
.14
56
.58
0.8
4
3
87
25
.11
32
.22
31
.41
29
.58
1.4
7
6.0
0
5.6
3
4.0
3
29
.12
45
.39
41
.99
37
.44
0.8
4
4
74
10
.84
19
.08
18
.02
15
.98
1.4
8
5.3
8
5.0
9
3.6
0
14
.95
30
.99
27
.56
23
.02
0.8
4
5
23
8
3.3
2
11
.84
11
.23
8.8
0
1.5
1
5.2
6
4.9
8
3.5
4
7.4
9
23
.65
20
.29
15
.63
1.5
6
6
1
2.6
3
9.1
8
9.0
4
6.9
5
1.7
1
5.7
1
5.5
2
4.0
1
7.1
7
20
.54
19
.23
14
.07
13
.43
7
22
4
2.7
0
8.0
5
8.1
3
6.2
9
2.0
5
5.4
4
5.4
1
4.0
4
8.1
0
18
.17
18
.11
14
.26
23
.62
8
98
1.8
1
7.4
0
7.6
2
5.6
1
0.4
9
5.9
6
5.5
6
3.9
6
3.3
5
21
.03
19
.62
14
.59
35
.49
9
24
7
1.2
6
6.8
8
7.1
0
5.0
8
0.4
9
5.9
9
5.5
9
3.9
8
2.8
0
20
.59
19
.17
14
.11
35
.85
10
23
9
0.7
0
6.3
5
6.5
8
4.5
4
0.4
9
6.0
3
5.6
2
4.0
0
2.2
6
20
.14
18
.72
13
.62
36
.21
11
16
0.4
2
5.3
2
6.1
3
3.9
6
0.3
2
5.9
1
5.6
0
3.9
1
1.2
3
20
.28
19
.63
13
.65
44
.48
12
20
8
0.3
9
3.8
6
5.0
2
3.0
9
0.3
1
4.2
2
4.2
0
2.8
2
1.4
5
17
.47
15
.83
11
.42
58
.99
13
24
0
0.2
4
3.8
0
3.8
7
2.6
4
0.3
6
5.1
3
4.7
1
3.3
6
1.6
0
20
.67
17
.87
13
.37
65
.83
14
37
0.2
3
3.6
8
3.5
9
2.5
0
0.4
3
6.0
3
5.4
3
3.9
3
1.9
4
25
.13
21
.69
16
.24
71
.94
15
69
0.3
7
3.2
7
3.4
3
2.3
6
0.2
1
4.7
4
5.0
6
3.3
1
1.3
2
18
.08
19
.80
12
.46
78
.78
16
10
0.1
3
2.9
7
3.1
6
2.0
9
0.2
4
5.0
5
5.3
9
3.5
3
1.2
8
18
.84
20
.67
12
.90
80
.10
17
21
8
0.1
4
2.9
0
2.9
8
2.0
0
0.3
3
5.8
3
5.7
8
3.9
5
1.8
2
26
.73
26
.85
18
.24
85
.97
18
18
6
0.1
6
2.7
8
2.7
3
1.8
9
0.4
0
6.9
3
6.7
7
4.6
7
2.2
2
32
.57
32
.72
22
.23
88
.49
19
12
5
0.1
7
2.3
8
2.3
6
1.6
3
0.7
3
7.5
7
6.4
7
4.8
7
5.0
7
52
.08
38
.21
31
.45
94
.96
20
66
0.0
2
1.8
1
2.2
9
1.3
7
0.0
4
6.7
8
7.0
2
4.5
9
0.1
9
44
.82
45
.36
30
.08
97
.48
21
19
0
0.0
2
1.6
7
1.7
0
1.1
3
0.0
5
8.5
5
8.7
0
5.7
5
0.2
5
58
.83
59
.53
39
.48
98
.08
22
34
0.0
5
1.3
2
1.3
3
0.9
0
0.1
4
8.3
3
8.4
7
5.6
2
0.6
8
88
.34
89
.19
59
.36
99
.28
23
11
8
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
10
0.0
0
Tab
le B
-3
Gre
edy
mon
ito
r p
lace
men
t w
ith
min
imiz
atio
n o
f sa
g m
agn
itu
de
esti
mat
ion
err
or
(SM
EE
) fo
r li
ne
to l
ine
to g
rou
nd
fau
lts
Appendix B • Minimization of SMEE by greedy monitor placement
187 |
Nu
m.
Buse
s S
ME
E
A
SM
EE
B
SM
EE
C
SM
EE
AB
C
Std
.
dev
.
A
Std
.
dev
.
B
Std
.
dev
.
C
Std
.
dev
.
AB
C
Max
.
A
Max
.
B
Max
.
C
Max
.
AB
C
Net
wo
rk
cover
age
(%)
1
98
30
.61
30
.61
30
.61
30
.61
11
.17
11
.17
11
.17
11
.17
5
7.2
4
57
.24
57
.24
57
.24
1.4
4
2
19
0
7.6
2
7.6
2
7.6
2
7.6
2
8.3
0
8.3
0
8.3
0
8.3
0
28
.22
28
.22
2
8.2
2
28
.22
47
.48
3
17
6.0
2
6.0
2
6.0
2
6.0
2
7.9
3
7.9
3
7.9
3
7.9
3
32
.18
32
.18
3
2.1
8
32
.18
54
.32
4
34
3.9
3
3.9
3
3.9
3
3.9
3
4.5
7
4.5
7
4.5
7
4.5
7
16
.39
16
.39
1
6.3
9
16
.39
63
.31
5
20
8
3.3
5
3.3
5
3.3
5
3.3
5
3.7
7
3.7
7
3.7
7
3.7
7
14
.65
14
.65
1
4.6
5
14
.65
70
.62
6
12
4
3.2
4
3.2
4
3.2
4
3.2
4
3.9
5
3.9
5
3.9
5
3.9
5
15
.57
15
.57
1
5.5
7
15
.57
77
.10
7
18
5
3.1
4
3.1
4
3.1
4
3.1
4
4.1
6
4.1
6
4.1
6
4.1
6
15
.83
15
.83
1
5.8
3
15
.83
79
.62
8
17
3
3.0
3
3.0
3
3.0
3
3.0
3
4.6
0
4.6
0
4.6
0
4.6
0
17
.94
17
.94
1
7.9
4
17
.94
84
.77
9
65
2.8
7
2.8
7
2.8
7
2.8
7
5.1
7
5.1
7
5.1
7
5.1
7
21
.78
21
.78
2
1.7
8
21
.78
87
.53
10
76
2.6
5
2.6
5
2.6
5
2.6
5
5.6
9
5.6
9
5.6
9
5.6
9
27
.91
27
.91
2
7.9
1
27
.91
90
.29
11
13
5
2.2
7
2.2
7
2.2
7
2.2
7
5.1
7
5.1
7
5.1
7
5.1
7
21
.77
21
.77
21
.77
21
.77
93
.53
12
49
1.7
5
1.7
5
1.7
5
1.7
5
5.7
0
5.7
0
5.7
0
5.7
0
34
.62
34
.62
3
4.6
2
34
.62
96
.04
13
11
8
1.9
0
1.9
0
1.9
0
1.9
0
6.6
0
6.6
0
6.6
0
6.6
0
40
.80
40
.80
4
0.8
0
40
.80
96
.64
14
67
2.3
6
2.3
6
2.3
6
2.3
6
9.2
2
9.2
2
9.2
2
9.2
2
74
.99
74
.99
7
4.9
9
74
.99
98
.44
15
1
6.1
9
6.1
9
6.1
9
6.1
9
9.6
7
9.6
7
9.6
7
9.6
7
89
.24
89
.24
8
9.2
4
89
.24
98
.80
16
10
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
0.0
0
10
0.0
0
Tab
le B
-4
Gre
edy
mon
ito
r p
lace
men
t w
ith
min
imiz
atio
n o
f sa
g m
agn
itu
de
esti
mat
ion
err
or
(SM
EE
) fo
r th
ree-p
has
e fa
ult
s
Appendix C • Minimization of SEEE by greedy monitor placement
188 |
Appendix C Minimization of SEEE by
greedy monitor placement
Appendix C • Minimization of SEEE by greedy monitor placement
189 |
Tab
le C
-1
Min
imiz
atio
n o
f th
e O
ver
all
Sag
Ev
ent
Est
imat
ion
Err
or
(SE
EE
) in
th
e G
DS
Net
wo
rk w
ith
Gre
edy
Mo
nit
or
Pla
cem
ent
N
um
ber
of
buse
s
EN
50
160
ITI
Curv
e
Gen
eral
ized
Sag
Tab
le
SA
RF
I-9
0
SE
MI
F4
7 C
urv
e
SE
EE
S
td.
dev
.
Co
ver
age
(%)
SE
EE
S
td.
dev
.
Co
ver
age
(%)
SE
EE
S
td.
dev
.
Co
ver
age
(%)
SE
EE
S
td.
dev
.
Co
ver
age
(%)
SE
EE
S
td.
dev
.
Co
ver
age
(%)
1
12
3.0
3
57
.53
3.0
0
16
4.7
6
24
.35
9.5
3
26
.11
10
.38
9
.53
18
4.3
9
43
.06
9.5
3
16
2.0
6
22
.31
9.5
3
2
53
.51
28
.51
19
.24
9
5.2
6
5.9
6
26
.20
13
.38
6.4
1
27
.34
92
.93
5.0
1
26
.20
91
.08
8
.17
26
.20
3
36
.78
19
.75
32
.40
4
9.3
1
6.8
4
32
.67
8.2
4
7.2
3
44
.39
46
.81
4.3
7
32
.67
50
.16
7
.68
32
.67
4
25
.04
18
.69
38
.70
2
0.0
0
5.2
0
39
.69
6.1
9
5.7
7
54
.98
19
.56
6.2
0
38
.49
20
.74
6
.10
39
.69
5
16
.16
19
.12
47
.75
8
.09
4.7
1
41
.67
4.6
9
3.8
6
67
.18
6.2
2
4.2
1
40
.47
10
.13
5
.30
41
.76
6
8.6
1
7.6
1
53
.63
3
.60
4.2
4
50
.72
3.6
9
3.5
3
71
.43
2.4
7
3.4
9
46
.22
3.8
9
4.4
8
50
.81
7
5.6
2
4.0
5
64
.21
2
.52
2.8
1
61
.36
2.9
7
3.4
4
75
.96
1.4
7
2.1
8
56
.80
2.8
2
3.0
2
61
.45
8
3.7
4
2.8
3
66
.01
1
.77
2.8
1
61
.54
2.3
3
2.8
3
78
.03
0.6
3
0.6
2
63
.70
2.0
7
3.0
2
61
.63
9
2.1
2
1.9
9
72
.90
1.1
8
1.0
5
65
.14
1.2
1
2.6
8
79
.74
0.1
3
0.4
6
63
.88
1.4
7
1.2
7
65
.23
10
1.0
5
0.6
8
87
.65
0
.67
1.1
2
65
.32
0.6
0
1.1
3
83
.33
0.0
8
0.4
4
65
.68
0.9
6
1.1
4
66
.94
11
0.3
4
0.6
5
87
.83
0
.41
0.5
0
82
.37
0.1
3
0.2
5
85
.97
0.0
5
0.4
2
65
.86
0.4
5
1.1
6
67
.12
12
0.1
0
0.3
1
89
.84
0
.19
0.4
9
84
.17
0.0
5
0.1
2
87
.23
0.0
2
0.1
4
82
.91
0.1
9
0.4
9
84
.17
13
0.0
7
0.2
9
90
.38
0
.01
0.0
9
86
.18
0.0
2
0.0
9
89
.12
0.0
0
0.0
1
88
.31
0.0
1
0.0
9
86
.18
14
0.0
4
0.2
6
90
.53
0
.00
0.0
4
88
.82
0.0
1
0.0
6
91
.76
0.0
0
0.0
1
88
.85
0.0
0
0.0
4
88
.82
15
0.0
1
0.0
5
91
.37
0
.00
0.0
2
89
.72
0.0
0
0.0
2
91
.94
0.0
0
0.0
1
88
.91
0.0
0
0.0
2
89
.72
16
0.0
0
0.0
3
93
.71
0
.00
0.0
0
91
.61
0.0
0
0.0
1
94
.00
0.0
0
0.0
1
89
.36
0.0
0
0.0
0
91
.61
17
0.0
0
0.0
1
94
.60
0
.00
0.0
0
92
.06
0.0
0
0.0
0
96
.34
0.0
0
0.0
1
90
.26
0.0
0
0.0
0
92
.06
18
0.0
0
0.0
1
95
.14
0
.00
0.0
0
94
.39
0.0
0
0.0
0
96
.88
0.0
0
0.0
1
92
.60
0.0
0
0.0
0
94
.39
19
0.0
0
0.0
1
95
.59
0
.00
0.0
0
95
.44
0.0
0
0.0
0
97
.33
0.0
0
0.0
1
93
.65
0.0
0
0.0
0
95
.44
20
0.0
0
0.0
1
96
.64
0
.00
0.0
0
95
.92
0.0
0
0.0
0
98
.38
0.0
0
0.0
1
95
.53
0.0
0
0.0
0
95
.92
21
0.0
0
0.0
1
98
.53
0
.00
0.0
0
98
.56
0.0
0
0.0
0
98
.56
0.0
0
0.0
1
96
.07
0.0
0
0.0
0
98
.56
22
0.0
0
0.0
1
98
.71
0
.00
0.0
0
98
.65
0.0
0
0.0
0
98
.65
0.0
0
0.0
1
98
.71
0.0
0
0.0
0
98
.65
23
0.0
0
0.0
1
98
.80
0
.00
0.0
0
98
.80
0.0
0
0.0
0
98
.80
0.0
0
0.0
1
98
.80
0.0
0
0.0
0
98
.80
24
0.8
6
0.2
9
99
.07
0
.67
0.3
0
99
.07
0.0
3
0.0
8
99
.07
0.8
5
0.3
5
99
.07
0.4
0
0.2
9
99
.07
25
0.0
0
0.0
0
10
0.0
0
0.0
0
0.0
0
10
0.0
0
0.0
0
0.0
0
10
0.0
0
0.0
0
0.0
0
10
0.0
0
0.0
0
0.0
0
10
0.0
0
Appendix C • Minimization of SEEE by greedy monitor placement
190 |
Table C-2 Minimization of the Sag Event Estimation Error (SEEE)for Sags as Classified by EN 50160
Num. Buses SEEE Std.
dev. Max.
Network coverage (%)
LG LL LLG LLL All
1 236 123.03 57.53 232.75 7.55 2.04 0.36 2.04 3.00
2 75 53.51 28.51 138.25 21.94 27.10 0.84 27.10 19.24
3 137 36.78 19.75 82.25 55.40 36.57 0.96 36.69 32.40
4 290 25.04 18.69 74.25 79.50 36.57 2.04 36.69 38.70
5 69 16.16 19.12 66.00 79.50 45.68 20.02 45.80 47.75
6 229 8.61 7.61 27.00 98.56 47.84 20.14 47.96 53.63
7 119 5.62 4.05 22.00 98.56 60.55 37.05 60.67 64.21
8 238 3.74 2.83 18.00 98.56 60.55 44.24 60.67 66.01
9 42 2.12 1.99 9.00 98.56 67.75 57.43 67.87 72.90
10 176 1.05 0.68 4.75 98.56 85.25 81.53 85.25 87.65
11 246 0.34 0.65 4.00 98.92 85.25 81.89 85.25 87.83
12 65 0.10 0.31 2.25 98.92 88.01 84.41 88.01 89.84
13 16 0.07 0.29 2.25 98.92 88.73 85.13 88.73 90.38
14 67 0.04 0.26 2.25 99.28 88.85 85.13 88.85 90.53
15 223 0.01 0.05 0.50 99.28 88.85 88.49 88.85 91.37
16 208 0.00 0.03 0.25 99.28 91.97 91.61 91.97 93.71
17 35 0.00 0.01 0.25 99.28 93.17 92.81 93.17 94.60
18 126 0.00 0.01 0.25 99.28 93.88 93.53 93.88 95.14
19 189 0.00 0.01 0.25 99.28 94.48 94.12 94.48 95.59
20 99 0.00 0.01 0.25 99.28 95.92 95.44 95.92 96.64
21 186 0.00 0.01 0.25 99.28 98.44 97.96 98.44 98.53
22 239 0.00 0.01 0.25 99.64 98.44 98.32 98.44 98.71
23 214 0.00 0.01 0.25 100.00 98.44 98.32 98.44 98.80
24 1 0.86 0.29 1.00 100.00 98.80 98.68 98.80 99.07
25 9 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00
Table C-3 Minimization of the Sag Event Estimation Error (SEEE) for Sags as Classified by ITIC Curve
Num. Buses SEEE Std.
dev. Max.
Network coverage (%)
LG LL LLG LLL All
1 223 164.76 24.35 217.75 33.09 2.28 0.48 2.28 9.53
2 229 95.26 5.96 112.25 52.16 26.02 0.60 26.02 26.20
3 290 49.31 6.84 70.75 76.26 26.38 1.68 26.38 32.67
4 16 20.00 5.20 40.00 90.65 33.21 1.68 33.21 39.69
5 236 8.09 4.71 24.25 98.20 33.21 2.04 33.21 41.67
6 69 3.60 4.24 18.50 98.20 42.33 20.02 42.33 50.72
7 126 2.52 2.81 15.25 98.20 55.16 36.93 55.16 61.36
8 246 1.77 2.81 14.50 98.56 55.16 37.29 55.16 61.54
9 42 1.18 1.05 8.25 98.56 57.67 46.64 57.67 65.14
10 239 0.67 1.12 8.25 98.92 57.67 47.00 57.67 65.32
11 176 0.41 0.50 2.00 98.92 80.10 70.38 80.10 82.37
12 238 0.19 0.49 2.00 98.92 80.10 77.58 80.10 84.17
13 65 0.01 0.09 1.00 98.92 82.85 80.10 82.85 86.18
14 75 0.00 0.04 0.50 98.92 85.61 85.13 85.61 88.82
15 35 0.00 0.02 0.25 98.92 86.81 86.33 86.81 89.72
16 186 0.00 0.00 0.00 98.92 89.33 88.85 89.33 91.61
17 189 0.00 0.00 0.00 98.92 89.93 89.45 89.93 92.06
18 208 0.00 0.00 0.00 98.92 93.05 92.57 93.05 94.39
19 99 0.00 0.00 0.00 98.92 94.48 93.88 94.48 95.44
20 119 0.00 0.00 0.00 98.92 95.08 94.60 95.08 95.92
21 137 0.00 0.00 0.00 99.28 98.32 98.32 98.32 98.56
22 214 0.00 0.00 0.00 99.64 98.32 98.32 98.32 98.65
23 67 0.00 0.00 0.00 100.00 98.44 98.32 98.44 98.80
24 1 0.67 0.30 1.00 100.00 98.80 98.68 98.80 99.07
25 9 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00
Appendix C • Minimization of SEEE by greedy monitor placement
191 |
Table C-4 Minimization of the Sag Event Estimation Error (SEEE) for Sags as Classified by Generalized Sag Table
Num. Buses SEEE Std.
dev. Max.
Network coverage (%)
LG LL LLG LLL All
1 223 26.11 10.38 63.50 33.09 2.28 0.48 2.28 9.53
2 16 13.38 6.41 25.50 47.48 30.70 0.48 30.70 27.34
3 176 8.24 7.23 25.50 47.48 53.12 23.86 53.12 44.39
4 35 6.19 5.77 25.50 71.58 62.11 24.10 62.11 54.98
5 119 4.69 3.86 17.75 90.65 76.98 24.10 76.98 67.18
6 229 3.69 3.53 17.75 90.65 76.98 41.13 76.98 71.43
7 65 2.97 3.44 17.75 90.65 79.74 53.72 79.74 75.96
8 238 2.33 2.83 10.75 98.20 79.74 54.44 79.74 78.03
9 236 1.21 2.68 10.75 98.20 79.74 61.27 79.74 79.74
10 42 0.60 1.13 5.75 98.20 82.25 70.62 82.25 83.33
11 75 0.13 0.25 1.00 98.20 85.01 75.66 85.01 85.97
12 69 0.05 0.12 0.75 98.20 86.69 77.34 86.69 87.23
13 186 0.02 0.09 0.75 98.20 89.21 79.86 89.21 89.12
14 137 0.01 0.06 0.75 98.56 92.45 83.57 92.45 91.76
15 246 0.00 0.02 0.25 98.92 92.45 83.93 92.45 91.94
16 290 0.00 0.01 0.25 98.92 92.45 92.21 92.45 94.00
17 208 0.00 0.00 0.00 98.92 95.56 95.32 95.56 96.34
18 126 0.00 0.00 0.00 98.92 96.28 96.04 96.28 96.88
19 189 0.00 0.00 0.00 98.92 96.88 96.64 96.88 97.33
20 99 0.00 0.00 0.00 98.92 98.32 97.96 98.32 98.38
21 239 0.00 0.00 0.00 99.28 98.32 98.32 98.32 98.56
22 214 0.00 0.00 0.00 99.64 98.32 98.32 98.32 98.65
23 67 0.00 0.00 0.00 100.00 98.44 98.32 98.44 98.80
24 1 0.03 0.08 0.25 100.00 98.80 98.68 98.80 99.07
25 9 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00
Table C-5 Minimization of the Sag Event Estimation Error (SEEE) for Sags as Classified by SARFI90
Num. Buses SEEE Std.
dev. Max.
Network coverage (%)
LG LL LLG LLL All
1 223 184.39 43.06 247.00 33.09 2.28 0.48 2.28 9.53
2 229 92.93 5.01 111.50 52.16 26.02 0.60 26.02 26.20
3 290 46.81 4.37 64.25 76.26 26.38 1.68 26.38 32.67
4 75 19.56 6.20 40.50 90.65 30.58 2.16 30.58 38.49
5 236 6.22 4.21 24.75 98.20 30.58 2.52 30.58 40.47
6 65 2.47 3.49 19.50 98.20 35.25 16.19 35.25 46.22
7 119 1.47 2.18 16.25 98.20 47.96 33.09 47.96 56.80
8 42 0.63 0.62 7.50 98.20 55.16 46.28 55.16 63.70
9 239 0.13 0.46 6.75 98.56 55.16 46.64 55.16 63.88
10 238 0.08 0.44 6.75 98.56 55.16 53.84 55.16 65.68
11 246 0.05 0.42 6.75 98.92 55.16 54.20 55.16 65.86
12 176 0.02 0.14 1.25 98.92 77.58 77.58 77.58 82.91
13 67 0.00 0.01 0.25 99.28 84.89 84.17 84.89 88.31
14 126 0.00 0.01 0.25 99.28 85.61 84.89 85.61 88.85
15 69 0.00 0.01 0.25 99.28 85.61 85.13 85.61 88.91
16 189 0.00 0.01 0.25 99.28 86.21 85.73 86.21 89.36
17 35 0.00 0.01 0.25 99.28 87.41 86.93 87.41 90.26
18 208 0.00 0.01 0.25 99.28 90.53 90.05 90.53 92.60
19 99 0.00 0.01 0.25 99.28 91.97 91.37 91.97 93.65
20 186 0.00 0.01 0.25 99.28 94.48 93.88 94.48 95.53
21 16 0.00 0.01 0.25 99.28 95.20 94.60 95.20 96.07
22 137 0.00 0.01 0.25 99.64 98.44 98.32 98.44 98.71
23 214 0.00 0.01 0.25 100.00 98.44 98.32 98.44 98.80
24 1 0.85 0.35 1.00 100.00 98.80 98.68 98.80 99.07
25 9 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00
Appendix C • Minimization of SEEE by greedy monitor placement
192 |
Table C-6 Minimization of the Sag Event Estimation Error (SEEE) for Sags as Classified by SEMI F47 Curve
Num. Buses SEEE Std.
dev. Max.
Network coverage (%)
LG LL LLG LLL All
1 223 162.06 22.31 212.50 33.09 2.28 0.48 2.28 9.53
2 229 91.08 8.17 111.50 52.16 26.02 0.60 26.02 26.20
3 290 50.16 7.68 71.00 76.26 26.38 1.68 26.38 32.67
4 16 20.74 6.10 40.25 90.65 33.21 1.68 33.21 39.69
5 238 10.13 5.30 25.75 98.20 33.21 2.40 33.21 41.76
6 69 3.89 4.48 19.00 98.20 42.33 20.38 42.33 50.81
7 126 2.82 3.02 16.00 98.20 55.16 37.29 55.16 61.45
8 246 2.07 3.02 15.25 98.56 55.16 37.65 55.16 61.63
9 42 1.47 1.27 8.25 98.56 57.67 47.00 57.67 65.23
10 236 0.96 1.14 8.25 98.56 57.67 53.84 57.67 66.94
11 239 0.45 1.16 8.25 98.92 57.67 54.20 57.67 67.12
12 176 0.19 0.49 2.00 98.92 80.10 77.58 80.10 84.17
13 65 0.01 0.09 1.00 98.92 82.85 80.10 82.85 86.18
14 75 0.00 0.04 0.50 98.92 85.61 85.13 85.61 88.82
15 35 0.00 0.02 0.25 98.92 86.81 86.33 86.81 89.72
16 186 0.00 0.00 0.00 98.92 89.33 88.85 89.33 91.61
17 189 0.00 0.00 0.00 98.92 89.93 89.45 89.93 92.06
18 208 0.00 0.00 0.00 98.92 93.05 92.57 93.05 94.39
19 99 0.00 0.00 0.00 98.92 94.48 93.88 94.48 95.44
20 119 0.00 0.00 0.00 98.92 95.08 94.60 95.08 95.92
21 137 0.00 0.00 0.00 99.28 98.32 98.32 98.32 98.56
22 214 0.00 0.00 0.00 99.64 98.32 98.32 98.32 98.65
23 67 0.00 0.00 0.00 100.00 98.44 98.32 98.44 98.80
24 1 0.40 0.29 1.00 100.00 98.80 98.68 98.80 99.07
25 9 0.00 0.00 0.00 100.00 100.00 100.00 100.00 100.00
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
193 |
Appendix D Distribution of SNPV from
1000 trials for all
customers’ plants at
different locations
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
194 |
Figure D-1 Distribution of SNPV from 1000 trials for all customers’ plants at location a estimated using
all monitoring schemes.
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
-20
24
68
10
x 1
05
0123456x 1
0-6
Pulp
and p
aper
inte
gra
ted
Probability Density
-10
12
34
56
7
x 1
06
01234567x 1
0-7
Meta
l m
anufa
ctu
ring
-20
24
68
10
12
14
16
x 1
04
0
0.51
1.52
2.53
x 1
0-5
Food p
rocessin
g
-0.5
00
.51
1.5
22
.53
x 1
04
0123456x 1
0-4
Textile
Probability Density
-0.5
00
.51
1.5
22
.5
x 1
07
0
0.51
1.52
x 1
0-7
Sem
iconducto
r fa
brication
-20
24
68
10
x 1
05
01234x 1
0-6
Auto
motive a
ssem
bly
-10
12
34
56
78
x 1
05
0123456x 1
0-6
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-0.5
00
.51
1.5
22
.53
3.5
x 1
05
0
0.2
0.4
0.6
0.81
1.2
1.4
x 1
0-5
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-20
24
68
10
x 1
05
012345x 1
0-6
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
195 |
Figure D-2 Distribution of SNPV from 1000 trials for all customers’ plants at location b estimated using
all monitoring schemes.
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
-20
24
68
10
12
x 1
05
01234x 1
0-6
Pulp
and p
aper
inte
gra
ted
Probability Density
-20
24
68
10
x 1
06
012345x 1
0-7
Meta
l m
anufa
ctu
ring
-50
51
01
52
0
x 1
04
0
0.51
1.52
2.53
x 1
0-5
Food p
rocessin
g
-10
12
34
5
x 1
04
012
x 1
0-4
Textile
Probability Density
-0.5
00
.51
1.5
22
.53
3.5
4
x 1
07
0
0.51
1.52
x 1
0-7
Sem
iconducto
r fa
brication
-20
24
68
10
12
14
x 1
05
0
0.51
1.52
2.53
3.5
x 1
0-6
Auto
motive a
ssem
bly
-20
24
68
10
x 1
05
012345x 1
0-6
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-0.5
00
.51
1.5
22
.53
3.5
4
x 1
05
0
0.2
0.4
0.6
0.81
1.2
x 1
0-5
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-20
24
68
10
12
x 1
05
0
0.51
1.52
2.53
3.5
x 1
0-6
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
196 |
Figure D-3 Distribution of SNPV from 1000 trials for all customers’ plants at location c estimated using
all monitoring schemes.
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
-20
24
68
10
12
x 1
05
01234x 1
0-6
Pulp
and p
aper
inte
gra
ted
Probability Density
-20
24
68
10
x 1
06
012345x 1
0-7
Meta
l m
anufa
ctu
ring
-50
51
01
52
0
x 1
04
0
0.51
1.52
2.5
x 1
0-5
Food p
rocessin
g
-10
12
34
56
78
x 1
04
0123456x 1
0-4
Textile
Probability Density
-10
12
34
5
x 1
07
0
0.2
0.4
0.6
0.81
1.2
1.4
x 1
0-7
Sem
iconducto
r fa
brication
-20
24
68
10
12
14
16
x 1
05
0
0.51
1.52
2.53
x 1
0-6
Auto
motive a
ssem
bly
-20
24
68
10
12
x 1
05
01234x 1
0-6
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-0.5
00
.51
1.5
22
.53
3.5
4
x 1
05
0
0.2
0.4
0.6
0.81
1.2
x 1
0-5
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-20
24
68
10
12
x 1
05
0
0.51
1.52
2.53
3.5
x 1
0-6
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
197 |
Figure D-4 Distribution of SNPV from 1000 trials for all customers’ plants at location d estimated using
all monitoring schemes.
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
-20
24
68
10
12
x 1
05
0
0.51
1.52
2.53
3.5
x 1
0-6
Pulp
and p
aper
inte
gra
ted
Probability Density
-20
24
68
10
x 1
06
012345x 1
0-7
Meta
l m
anufa
ctu
ring
-0.5
00
.51
1.5
22
.5
x 1
05
0
0.51
1.52
x 1
0-5
Food p
rocessin
g
-10
12
34
56
78
x 1
04
0
0.2
0.4
0.6
0.81
1.2
1.4
x 1
0-4
Textile
Probability Density
-10
12
34
5
x 1
07
0
0.2
0.4
0.6
0.81
x 1
0-7
Sem
iconducto
r fa
brication
-20
24
68
10
12
14
16
x 1
05
0
0.51
1.52
2.5
x 1
0-6
Auto
motive a
ssem
bly
-20
24
68
10
12
x 1
05
0
0.51
1.52
2.53
3.5
x 1
0-6
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-10
12
34
5
x 1
05
02468x 1
0-6
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-20
24
68
10
12
14
x 1
05
0
0.51
1.52
2.53
x 1
0-6
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
198 |
Figure D-5 Distribution of SNPV from 1000 trials for all customers’ plants at location e estimated using
all monitoring schemes.
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
-10
12
34
56
7
x 1
05
0
0.2
0.4
0.6
0.81
1.2
x 1
0-5
Pulp
and p
aper
inte
gra
ted
Probability Density
-10
12
34
5
x 1
06
0
0.2
0.4
0.6
0.81
1.2
1.4
x 1
0-6
Meta
l m
anufa
ctu
ring
-20
24
68
10
12
x 1
04
0
0.2
0.4
0.6
0.81
1.2
1.4
x 1
0-4
Food p
rocessin
g
-10
12
34
5
x 1
04
01234x 1
0-4
Textile
Probability Density
-0.5
00
.51
1.5
22
.53
x 1
07
012345x 1
0-7
Sem
iconducto
r fa
brication
-20
24
68
10
x 1
05
0
0.2
0.4
0.6
0.81
x 1
0-5
Auto
motive a
ssem
bly
-10
12
34
56
7
x 1
05
0
0.2
0.4
0.6
0.81
1.2
x 1
0-5
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-0.5
00
.51
1.5
22
.5
x 1
05
0
0.51
1.52
2.53
x 1
0-5
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-10
12
34
56
7
x 1
05
0
0.2
0.4
0.6
0.81
x 1
0-5
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
199 |
Figure D-6 Distribution of SNPV from 1000 trials for all customers’ plants at location f estimated using
all monitoring schemes.
-10
12
34
5
x 1
05
0
0.51
1.52
x 1
0-5
Pulp
and p
aper
inte
gra
ted
Probability Density
-0.5
00
.51
1.5
22
.53
3.5
4
x 1
06
0
0.51
1.52
2.5
x 1
0-6
Meta
l m
anufa
ctu
ring
-20
24
68
10
x 1
04
012
x 1
0-4
Food p
rocessin
g
-0.5
00
.51
1.5
22
.53
3.5
x 1
04
01234x 1
0-4
Textile
Probability Density
-50
51
01
52
0
x 1
06
02468x 1
0-7
Sem
iconducto
r fa
brication
-10
12
34
56
7
x 1
05
0
0.51
1.52
x 1
0-5
Auto
motive a
ssem
bly
-10
12
34
5
x 1
05
0
0.51
1.52
2.5
x 1
0-5
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-0.5
00
.51
1.5
22
.5
x 1
05
0123456x 1
0-5
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-10
12
34
56
x 1
05
0
0.51
1.52
x 1
0-5
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
Appendix D • Distribution of SNPV from 1000 trials for all customer’s plants at different locations
200 |
Figure D-7 Distribution of SNPV from 1000 trials for all customers’ plants at location g estimated using
all monitoring schemes.
-50
510
15
x 1
05
02468x 1
0-6
Real
Eng1
Eng2
Opt1
0O
pt8
Opt6
-10
12
34
56
x 1
05
0
0.51
1.52
2.53
x 1
0-5
Pulp
and p
aper
inte
gra
ted
Probability Density
-0.5
00
.51
1.5
22
.53
3.5
4
x 1
06
0
0.51
1.52
2.53
3.5
x 1
0-6
Meta
l m
anufa
ctu
ring
-10
12
34
56
78
x 1
04
01234x 1
0-4
Food p
rocessin
g
-0.5
00
.51
1.5
22
.53
3.5
4
x 1
04
012
x 1
0-4
Textile
Probability Density
-0.5
00
.51
1.5
22
.5
x 1
07
0
0.2
0.4
0.6
0.81
1.2
x 1
0-6
Sem
iconducto
r fa
brication
-10
12
34
56
x 1
05
0
0.51
1.52
2.5
x 1
0-5
Auto
motive a
ssem
bly
-10
12
34
5
x 1
05
0
0.51
1.52
2.53
x 1
0-5
Chem
ical
Probability Density
Sto
ch
astic N
et P
rese
nt V
alu
e
-0.5
00
.51
1.5
22
.5
x 1
05
02468x 1
0-5
Equip
ment
manufa
ctu
ring
Sto
ch
astic N
et P
rese
nt V
alu
e
-10
12
34
56
x 1
05
0
0.51
1.52
2.5
x 1
0-5
Pla
stic e
xtr
usio
n
Sto
ch
astic N
et P
rese
nt V
alu
e
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
201 |
Appendix E Distribution of SNPV from
1000 trials at all locations
for different types of
customer plants
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
202 |
Figure E-1 Distribution of SNPV from 1000 trials for an integrated pulp and paper mill at all locations
(a-h) estimated using all monitoring schemes.
01234567
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
0123456789
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
0123456789
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
0123456789
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
0
0.51
1.52
2.53
3.54
4.55
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Monitori
ng S
chem
e
Pla
nt
location e
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
3.54
4.5
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Monitori
ng S
chem
e
Pla
nt
location f
0
0.51
1.52
2.53
3.54
4.5
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Monitori
ng S
chem
e
Pla
nt
location g
0123456789
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Monitori
ng S
chem
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
203 |
Figure E-2 Distribution of SNPV from 1000 trials for a metal manufacturing plant at all locations (a-h)
estimated using all monitoring schemes.
0123456
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
01234567
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
01234567
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
012345678x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
0
0.51
1.52
2.53
3.54
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
3.5
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
0
0.51
1.52
2.53
3.5
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
01234567
x 1
06
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
204 |
Figure E-3 Distribution of SNPV from 1000 trials for a food processing plant at all locations (a-h)
estimated using all monitoring schemes.
02468
10
12
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
02468
10
12
14
16
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
02468
10
12
14
16
18
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
02468
10
12
14
16
18
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
0123456789
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
012345678
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
01234567
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
05
10
15
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
205 |
Figure E-4 Distribution of SNPV from 1000 trials for a textile mill at all locations (a-h) estimated using
all monitoring schemes.
0
0.51
1.52
2.5
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
3.54
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
0123456
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
01234567
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
0
0.51
1.52
2.53
3.54
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
0
0.51
1.52
2.53
3.5
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
01234567
x 1
04
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
206 |
Figure E-5 Distribution of SNPV from 1000 trials for an automotive assembly plant at all locations (a-h)
estimated using all monitoring schemes.
0123456789x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
02468
10
12
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
02468
10
12
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
02468
10
12
14
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
01234567
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
0123456
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
012345
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
02468
10
12
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
207 |
Figure E-6 Distribution of SNPV from 1000 trials for a chemical plant at all locations (a-h) estimated
using all monitoring schemes.
01234567
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
012345678
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
0123456789
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
0123456789
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
012345
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
3.54
4.5
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
0
0.51
1.52
2.53
3.54
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
0123456789
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
208 |
Figure E-7 Distribution of SNPV from 1000 trials for an equipment manufacturing plant at all locations
(a-h) estimated using all monitoring schemes.
0
0.51
1.52
2.53
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
3.5
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
0
0.51
1.52
2.53
3.5
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
0
0.51
1.52
2.53
3.54
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
0
0.51
1.52
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
0
0.2
0.4
0.6
0.81
1.2
1.4
1.6
1.82
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
0
0.51
1.52
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
01234567
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix E • Distribution of SNPV from 1000 trials at all locations for different types of customer plants
209 |
Figure E-8 Distribution of SNPV from 1000 trials for a plastic extrusion plant at all locations (a-h)
estimated using all monitoring schemes.
012345678
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location a
Stochastic Net Present Value (£)
0123456789
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location b
0123456789
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location c
02468
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Pla
nt
location d
0123456x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location e
Stochastic Net Present Value (£)
0
0.51
1.52
2.53
3.54
4.55
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location f
0
0.51
1.52
2.53
3.54
4.55
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location g
0123456789
10
x 1
05
Real
Eng1
Eng2
Opt6
Opt8
Opt1
0
Mo
nito
rin
g S
ch
em
e
Pla
nt
location h
Appendix F • List of Publications
210 |
Appendix F
List of Publications
Journal Papers
[F1] J. M. Avendano-Mora and J. V. Milanović, “Monitor Placement for Reliable
Estimation of Voltage Sags in Power Networks,” IEEE Transactions on Power
Delivery, Vol. 27, No 2, 2012, pp. 936-944.
[F2] J. M. Avendano-Mora and J. V. Milanović, “Generalized Formulation of the
Optimal Monitor Placement Problem for Fault Location," accepted for
publication in Elsevier Electric Power Systems Research, 2012.
[F3] N. C. Woolley, J. M. Avendano-Mora, J. V. Milanović, “Immune System
Inspired Methodology for Robust Monitoring of Voltage Sags Based on
Equipment Trip Probabilities,” accepted for publication in Elsevier Electric
Power Systems Research, 2012.
Submitted Journal Papers
[F4] N. C. Woolley, J. M. Avendano-Mora, J. V. Milanović, “Probabilistic voltage
sag performance estimation part I: localisation and voltage magnitude
estimation,” submitted to IEEE Transactions on Power Systems in 2012.
[F5] N. C. Woolley, J. M. Avendano-Mora, J. V. Milanović, “Probabilistic voltage
sag performance estimation part II: estimation of impacts on end users,”
submitted to IEEE Transactions on Power Systems in 2012.
Appendix F • List of Publications
211 |
International Conference Papers
[F6] J. M. Avendano-Mora, Y. Zhang, J. V. Milanović and B. Patel, "The influence
of model parameters and uncertainties on assessment of network wide costs of
voltage sags," 10th
IEEE International Conference Electric Power Quality and
Utilisation (EPQU), 15-17 September 2009.
[F7] J. M. Avendano-Mora, N. C. Woolley and J. V. Milanović, "On improvement
of accuracy of optimal voltage sag monitoring programmes," 14th
IEEE
International Conference on Harmonics and Quality of Power (ICHQP), 26-29
September 2010.
[F8] N. C. Woolley, J. M. Avendano-Mora, J. V. Milanović, “A Comparison of
Voltage Sag Estimation Algorithms Using Optimal Monitoring Locations”,
International Conference on Harmonics and Quality of Power (ICHQP), 26-29
September 2010.
[F9] J. M. Avendano-Mora and J.V. Milanović, "Methodology for flexible, cost-
effective monitoring of voltage sags," 21st International Conference on
Electricity Distribution CIRED 2011, 6-9 June 2011.
[F10] N. C. Woolley, J. M. Avendano-Mora, and J. V. Milanović, “Integration of
cost effective bus profiling in distribution networks”, International Federation
of Automatic Control (IFAC), 28 Aug – 02 Sept. 2011, Invited Conference
Paper
[F11] J. M. Avendano-Mora and J.V. Milanović, "A Heuristic Approach for Optimal
Monitor Placement for Fault Location," IEEE International Conference on
Smart Measurements for Future Grids (SMFG), 14-16 November 2011.
[F12] N. C. Woolley, J. M. Avendano-Mora, J. V. Milanović, “Probabilistic Fault
Location Using Erroneous Measurement Devices”, Smart Metering for Future
Grids (SMFG), 14-16 November 2011
[F13] J. M. Avendano-Mora, J.V. Milanović and M. Madrigal, “Assessment of
Financial Losses Due to Voltage Sags Using Optimal Monitoring Schemes,”
International Conference on Renewable Energies and Power Quality
(ICREPQ), 28-30 March 2012.
N.B.: Only publications F1, F2, F6, F7, F9, F11, and F13 are cited in the list of
contributions as they are directly based on the work embodied in this thesis.