MONDARRA PL23 INTERCONNECT INFRASTRUCTURE …

19

Transcript of MONDARRA PL23 INTERCONNECT INFRASTRUCTURE …

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 2 of 19

REVISION RECORD Revision No. Description of Revision

A Document drafted, reviewed and issued

0 Document finalised and issued for submission

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 3 of 19

TABLE OF CONTENTS 1 INTRODUCTION .......................................................................................... 4

1.1 Purpose and Scope........................................................................................................ 4

1.2 Objectives ..................................................................................................................... 4

1.3 Definitions and Abbreviations ....................................................................................... 5

2 PROJECT BACKGROUND ............................................................................. 6

3 PROJECT ACTIVITIES ................................................................................... 8

3.1.1 Earthworks (ECR) ....................................................................................................... 8

3.1.2 Electrical System ........................................................................................................ 8

3.1.3 Hydro Testing ............................................................................................................. 8

3.1.4 Finishing Works .......................................................................................................... 8

4 DESCRIPTION OF THE ENVIRONMENT ...................................................... 11

5 ENVIRONMENTAL RISK ASSESSMENT AND MANAGEMENT ...................... 11

6 STAKEHOLDER CONSULATION .................................................................. 13

7 APA GROUP CONTACT DETAILS ................................................................ 19

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 4 of 19

1 INTRODUCTION This ‘Environmental Plan Bridging Document - Summary – Parmelia Gas Pipeline System - RUSSELL ROAD INTERCONNECT PROJECT’ (RRI Project E-BD Summary) (RRI-PL-HS-0006) provides an overview of the environmental management requirements for the design and build of a connection between the Parmelia Gas Pipeline System (PGPS) and the ATCO Gas Australia (ATCO) South Metro reticulation system.

This is a summary document of the ‘Environmental Plan Bridging Document - Parmelia Gas Pipeline System - RUSSELL ROAD INTERCONNECT PROJECT’ (RRI Project E-BD) (RRI-PL-HS-0005) which bridges the environmental requirements and management techniques of the Operations Environment Plan Parmelia Gas Pipeline System (PAR-EMP-457; Rev 1.2; 26/06/2013) (PGPS OEMP) to the RRI Project.

1.1 Purpose and Scope

The purpose of the RRI Project E-BD Summary is to provide information to the general public regarding environmental considerations and management requirements. The scope of this RRI Project E-BD Summary is limited to the environmental management techniques applicable to the RRI Project which control environmental risks additional to normal Parmelia Gas Pipeline operations.

1.2 Objectives

The overall environmental objective of the RRI Project E-BD is as follows:

To describe the work to be undertaken to design and build a connection between the PGPS and the ATCO South Metro reticulation system;

To provide management techniques to minimise environmental impacts resulting from project activities;

To mitigate all identified environmental risks to ALARP;

To comply with all relevant legal and regulatory environmental requirements; and

To minimise disturbance to surrounding landholders.

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 5 of 19

1.3 Definitions and Abbreviations

ALARP As Low As Reasonably Practicable

APA APA Group, also incorporating APT Parmelia Pty Ltd, a wholly owned subsidiary of APA

Contractor A supplier in a contractual situation

DBP Dampier to Bunbury Natural Gas Pipeline (PL40)

DFES Department of Fire and Emergency Services

DMP Department of Mines and Petroleum or its successor

E-BD Environment Plan Bridging Document

ECR Energy Commission Russell Road - Primary site for RRI Project

ERA Environmental Risk Assessment

HSE Health, Safety and Environment

Incident An undesired event or set of circumstances that did result in an undesired outcome through injury to people, harm to the environment, damage to property, equipment or materials or loss of process.

KNR Kwinana Nickle Refinery - Secondary Project site for RRI Project

NATA National Association of Testing Authorities

OEMP Operations Environmental Management Plan

PGPS OEMP Operations Environment Plan Parmelia Gas Pipeline System (PAR-EMP-457; Rev 1.2; 26/06/2013) (PGPS OEMP)

PGPS Parmelia Gas Pipeline System (PL 1, 2, 3, 5, 23, 32, 44, 45, 46, 52, 53 and 61)

Relevant Authorities Either one or all of DMP, DER, DPAW, EPA as the case may be

Risk Assessment The process used to determine risk priorities by evaluating and comparing the level of risk against program standards, pre-determined risk levels or other

RRI Russell Road Interconnect Project

SDS Safety Data Sheet (previously Material Safety Data Sheet – MSDS)

SECWA State Energy Commission of Western Australia

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 6 of 19

2 PROJECT BACKGROUND The PGPS comprises the Parmelia Gas Pipeline mainline (PGP) and numerous lateral pipelines. The PGPS is owned and operated by APT Parmelia Pty Ltd (APA). The primary function of the PGPS is to transport gas from the Dampier to Bunbury Natural Gas Pipeline (DBNGP) and Mondarra Storage Facility (MSF) to customers located throughout in the south west of WA as far south as Pinjarra.

A growth opportunity exists for APA to supply natural gas to ATCO Gas Australia’s (ATCO) Metro South Reticulation Network with the PGP identified as ideally situated to provide transport of the gas. This project is called the RRI Project.

The RRI Project provides for the relocation of the existing filtration, metering and pressure reduction equipment located at the Kwinana Nickel Refinery (KNR) to the APA controlled Energy Commission Russell Road (ECR) compound.

The existing Russell Road Sales Tap (RST) (See ‘Russell Road Compound’ - Figure 1) has been chosen as the viable location for the new metering station. The RST is situated on the PGPS Mainline at KP356.1 which adjoins the ECR compound. The ECR is APA owned and currently unused. APA has an access agreement for the ECR with the Department of Lands (Infrastructure Corridors) who are the land owners.

Existing pipework is installed at the KNR site (Figure 2). Under the RRI Project scope, these materials will be removed and transported to the ECR site for the project.

As the RRI Project operations are being staged out of the PGPS Mainline, environmental aspects associated with the project fall within the scope of the accepted PGPS OEMP. The Operations Environment Plan Parmelia Gas Pipeline System (PAR-EMP-457; Rev 1.2; 26/06/2013) (PGPS OEMP) is the document being bridged to.

A Bridging Document is adequate to cover the proposed activities given that the project:

Pertains to new activities that are within the scope of the PGPS OEMP, for which the environment risks are covered; or

Will result in changed operational details from the scope of the PGPS OEMP, but do not result in any major additional or modified environment risks.

This is consistent with advice given in the DMP Guidelines for the Preparation and Submission of an Environment Plan (DMP, 2012).

Table 1 provides a summary of the scope of work associated with the RRI Project.

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 7 of 19

Table 1 - Summary of RRI Project

Item Detail

Company / Licence APT Parmelia Pty Ltd; Pipeline License No.’s 1, 2, 3, 5, 23, 32, 44, 46, 52, 53 and 61 (a member of APA Group of companies)

Project name Russell Road Interconnect Project (RRI Project)

Location ECR - The site (Figure 1) is located at 448 Russell Road, Wattleup, on the corner of Russell Road and Power Avenue, approximately 24 km south-southwest of Perth (50H) (387929.00 m E, 6441442.00 m S). The ECR is located on Lot 582 of Deposited Plan 187902. The lot is divided into two parcels of land with the western portion in use by DBP.

KNR – The site (Figure 2) is located off Patterson Road, straddling the boundaries of Rockingham and Kwinana, approximately 34km south-southwest of Perth (50H) (384117.67 m E, 6431177.24 m S). The Lot is owned by BHP to which APT Parmelia Pty Ltd (APA Group) has been granted an easement for the purposed of the pipeline and delivery station.

Existing infrastructure Energy Commission Russell Road (ECR) - The site currently contains a decommissioned SECWA building and buried concrete footings from its previous use as a substation.

Infrastructure and

equipment operated and

stored in project area.

Diesel generator(s), light vehicles, excavator/bobcat, crane, water trailer, waste oil trailer, contaminated and inert waste management areas (skip bins), fuel trailer.

Hours of operation 10 hours per day, Monday - Friday.

The work is scheduled to commence at the beginning of September 2015 and last up to 105 days. An indicative break down of project phases is provided in Table 2, below.

Table 2 Indicative project schedule

Aspect Date Duration

RRI Project EBD Preparation and ERA July 2015 31 days

Approval of RRI Project E-BD Aug-Sept 2015 Up to 30 days

Project mobilisation and activities

conducted as per scope

Sept-Dec 2015 110 days

Demobilisation December 2015 3 days

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 8 of 19

3 PROJECT ACTIVITIES The project work phases which present significant environmental hazards are outlined below.

3.1.1 Earthworks (ECR)

Clearing and grubbing – Removal of rubble, asphalt, site levelling (approximately 0.0016ha area

– ECR Site);

Stripping and stockpiling of topsoil (approximately 0.0016ha area – ECR Site);

Excavation, screening and stockpiling of in‐situ materials;

Disposal of in‐situ material which is unsuitable for reuse (to approved spoil locations);

Loading and hauling of imported fill material; and

Site finishing - Blue metal / crushed rock / gravel.

3.1.2 Electrical System Civil works (trenching, excavation, bedding, backfill) for installation of buried services;

Main earth grid and earth rods;

Electrical conduits and pits; and

Underground connections to earth grid for future bonding.

3.1.3 Hydro Testing

Provision of water supplies;

Filling and testing;

Dewatering, cleaning and drying;

Facilities for water disposal, storage and re‐use of water; and

Provision of NATA accredited test records, chart record and test report.

3.1.4 Finishing Works

Create hardstands, grading and compaction/rolling of any areas disturbed during the project

works to APA’s Technical Specifications and Standard Details;

Clean‐up and disposal of all rubbish; and

Removal of all tools, shipping containers and temporary construction offices and amenities.

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 9 of 19

Figure 1 - Location of ECR Site and RST (Russell Road Compound)

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006

Page 10 of 19

Figure 2 - Location of KNR Site Facilities, Boundary and Existing Infrastructure

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 11 of 19

4 DESCRIPTION OF THE ENVIRONMENT A detailed description of the environment surrounding the PGPS is provided in the PGPS OEMP.

Specific to the ECR Site (Figure 1), the site contains no vegetation, soils generally consist of Spearwood Sands with varying amounts of organic material and gravel. Soils are very loose with no clay content. The site is relatively flat and is surrounded by bushland.

A desktop investigation of the ECR site and surrounding area found no known area of aboriginal or European heritage.

The majority of land surrounding the site has been developed for rural business practices or residences and consequently contains limited environmental value. Residual native bushland in proximity to the site has been heavily disturbed and also contains limited environmental value.

The ECR site lies on the northern slope of the Jandakot Mound system which extends from the Swan River in the north to the Serpentine River in the south. The RRI Project works will not exceed 1500mm below the existing ground surface. Interaction with groundwater systems is not anticipated and unlikely.

5 ENVIRONMENTAL RISK ASSESSMENT AND MANAGEMENT

The environmental risks associated with all activities conducted on the PGPS are addressed in the PGPS OEMP. A review of these risks under the scope of the RRI Project was undertaken in July 2015.

The objective was to ensure that all aspects, impacts and risks associated with the project were adequately assessed and control measures identified in the PGPS OEMP were adequate for the activities. Any new risks (or risks where the associated hazard was markedly different that of normal operations) are addressed in the RRI Project E-BD.

A total of 15 additional or changed risks were assessed as part of the ERA process and management measures and mitigation factors were identified to ensure risks were managed ALARP.

The APA standard risk methodology (WI-4.21.8 Risk Management (FIRM) Work Instruction) and matrix were used for the ERA. These have been previously developed by APA as per regulatory requirements and are consistent with AS/NZS ISO 31000:2009 (Risk Management – Principles and Guidelines) requirements.

The ERA was attended by the following APA project personnel:

APA Environmental Officer

APA Project Manager (RRI Project Manager)

APA Project Approvals Manager

APA Project Engineer

APA Team Leader (PGPS South)

A summary of the key environmental risks assessed during the workshop are below (Table 3). The corresponding control measures and mitigating factors for the RRI Project are included in Table 4 - 9.

Note: The below Tables are indicative of major hazards and controls and are not comprehensive of all commitments made by APA in the RRI Project E-BD or PGPS OEMP.

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 12 of 19

Table 3 Summary Environmental Risks and Hazards

Risk (Environmental Aspect) Hazard (Activity/Cause)

Uncontrolled release of substance which is potentially harmful to the environment

*Largest potential release 50L

SMALL *Chemical (storage and) handling

*Predominantly brought to site as required *All fuels, oils, hazardous or other potentially harmful substances

*Stored in individual containers of <50L *e.g. Oils/lubricants (excluding bulk oils); degreasers; corrosion inhibitors;

diesel etc.

Uncontrolled release of substance which is potentially harmful to the environment

*maximum credible release <1000 L

MEDIUM *Storage, handling and general utilisation of (odorant) turbine oil

*Max storage <1000 L *Potential causes of spills: -

- Rupture of storage vessel (i.e. due to integrity failure or mechanical impact) - Spill during container handling (i.e. crane drop/ 3monthly)

-Transfers (i.e. bulky to storage tank) *Refuelling of equipment

*Servicing and maintenance of plant, vehicles and equipment

Incorrect disposal of chemical waste resulting in uncontrolled release

*max credible release <50L Chemical waste disposal - All

Vehicle accident during chemical transport resulting in uncontrolled

release *maximum credible spill <1000L

Transport of fuels and chemicals (inc equipment) to and from site <1000 L - Diesel

- assorted paints etc. - Solvents

Incorrect inert/putrescible waste storage and disposal methods

*Inert and putrescible waste generation (non-industrial i.e. general household, organic waste, plastics etc.)

Dust Generation

*Site Access *Operation of heavy construction equipment

*Clearing and grubbing/site levelling *Site excavations

Traffic - disturbance to landholders - Noise

- Volume Site access, construction operations

Erosion of soil *Obstruction and redirection natural drainage, lack of vegetation coverage/

soil

Weeds: Export and/or spread *Site Access

*Road maintenance *Site levelling and civil works (removal of topsoil from site)

Disturbance to Indigenous and/or European heritage areas and/or artefacts

*Site access *Excavation

Ignition source for fire *Operation of plant and equipment

*Sources of ignition (e.g. welding and grinding)

Exposure or movement of existing contaminated soil

Excavation, waste disposal, vehicle movement

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 13 of 19

Risk (Environmental Aspect) Hazard (Activity/Cause)

Ground and soil contamination Grey water and Effluent Waste Disposal/Overflow

Noise, fire, environmental, disruption to community

Controlled release - Venting odorised gas

Uncontrolled/controlled release of natural gas into atmosphere, excessive

noise from vent. Introduction of natural gas and pressure up to 5600kPa

6 STAKEHOLDER CONSULATION The following stakeholders have been identified as having an interest in activities associated with the RRI Project and were engaged as part of the consultation process.

• APA Operations Group, who will be responsible for the operation of the off-take and pipeline infrastructure at the RRI Project interconnect;

• WA Department of Mines and Petroleum (DMP); • Department of Environment Regulation (DER); • Dampier to Bunbury Pipeline (DBP); • Department of Lands (Infrastructure Corridors); • Western Power; • City of Cockburn; • ATCO Gas.

All Stakeholders have indicated their agreement with the RRI Project scope, timing and all associated characteristics and impacts of the Project. Insofar as there would be an effect on a stakeholder, they will be kept up to date on progress; and any unforeseen changes to the proposal including delays to the commencement/completion of the activity. Stakeholder Consultation will be managed as per of the PGPS OEMP.

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 14 of 19

Table 4 - Chemical Transport, Handling and Storage

Management Requirements

Office/Management requirements

1) Inductions addressing storage and handling of hazardous substances

2) SDS available for all liquid hazardous substances onsite

3) Procedures for chemical handling

4) Hazard and incident reporting via APA reporting system

5) SWMS/JHA

6) DMP reporting

7) Procedures for servicing of vehicles, plant and equipment

Site-based requirements

8) Minimal storage at sites - substances brought in as required

9) Spill response equipment, including containment and recovery equipment, available on site which caters for release of both liquids and solids

10) All storage of hazardous chemicals in containers <50L

11) Storage of hazardous liquids within storage area which is; enclosed, ventilated and bunded

12) Regular housekeeping checks

13) SDS register/ chemical register (list of chemicals onsite)

14) Trained and competent operators

15) Use of drip trays or alike (absorbent material) when handling fuels, oils and hazardous substances outside of bunded areas

16) Compliance with AS1940-2004 The storage and handling of flammable and combustible liquids

17) Speed limit 80km/hr on unsealed roads; unless otherwise marked; Appropriate vehicle use

18) Emergency service available for response - police, DFES, air traffic control

19) Adequate Securing and/or tie down of chemical containers during transport

20) Vehicle maintenance as per manufactures recommendation

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 15 of 19

Table 5 - Waste Disposal

Management Requirements

Office/Management requirements

1) Inductions addressing chemical disposal

2) Hazard and incident reporting via APA reporting system

3) Operations waste management procedure

4) Hazard and incident reporting via APA reporting system

Site-based requirements

5) Licenced contractors to remove all hazardous waste

6) SDS available for hazardous chemicals

7) Procedures for disposal of chemical waste - check/ safeguard

8) Spill response equipment onsite

9) Chemical (controlled) waste removed from site for disposal by contractors licensed by DER under Environmental Protection (Controlled Waste) Regulations 2004

10) Chemical waste disposal methods in compliance with DER Environmental Protection (Controlled Waste) Regulations 2004 AND DER Landfill Waste Classification and Waste Definitions 2009

11) Inert and putrescible wastes to be removed from site and disposed of at a licensed landfill facility

12) Segregated, labelled covered bins (Hazardous substance skip bin and general waste skip bin on site)

13) Site fenced to prevent spread of windblown rubbish offsite

14) Housekeeping to assess waste disposal methods and clean up litter

15) Regular emptying of rubbish bins to prevent overfilling and spillage

16) Site toilets and crib hut waste bins emptied regularly and as required by licenced contractor

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 16 of 19

Table 6 – Site Access

Management Requirements

Office/Management requirements

1) Hazard and incident reporting via APA reporting system

2) RRI Project Traffic Management Plan

Site-based requirements

3) Speed limit on unsealed road 80km/hr unless otherwise marked - drive to conditions

4) Low traffic volumes

5) Trained and competent drivers

6) Provision to wet down site for dust suppression available

7) No parking verges outside site compound

8) Vehicles are required to remain on designated roads and tracks at all times

9) Declared weeds found onsite to be reported - to APA environmental staff to report to DAFWA

10) Timely response to declared weed occurrences as per DAFWA recommendations

11) Consult with surrounding landholders regarding weed management if required

12) Ground disturbing equipment to be clean of soil clumps upon leaving site

13) Spraying or manual removal of identified weeds

14) Civil works in dry conditions

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 17 of 19

Table 7 – Soil Conservation, Excavations and Spoil Management

Management Requirements

Office/Management requirements

1) Desktop investigation of site history

2) Engagement of Contaminated Sites Consultant to conduct PSI

3) Soil Analysis Plan and targeted Soil Testing Analysis conducted

4) Hazard and incident reporting via APA reporting system

Site-based requirements

5) Vehicles to remain on existing roads/tracks or within designated areas at all times

6) Stabilisation and monitoring of soil in high risk areas

7) Hazard ID via APA incident reporting system to identify repair strategy

8) Rectify erosion where impacts to the surrounding environment exist

9) No earthworks >1000mm

10) All works confined to the construction area

11) Personnel to stop work and notify Environmental Officer if suspected heritage remains are uncovered

12) Fencing installed around existing structure (SECWA Building)

13) No entry to existing structure (SECWA Building)

14) No excavation beyond previously tested soil depth

15) Awareness of site personnel in induction - historical site use/soil testing already complete

16) Excavated soil to remain on site

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 18 of 19

Table 8 – Plant, Equipment and Fire

Management Requirements

Office/Management requirements

1) Fire emergency response covered in ERP

2) Hazard and incident reporting via APA reporting system

3) APA smoking policy

Site-based requirements

4) Maintenance of fire response equipment - fire extinguishers

5) Maintenance of fire breaks around site; minimum 3 metres

6) Inductions and training which address fire management, fire response and use of fire response equipment (fire extinguisher training)

7) PTW system to be used during hot works

8) SWMS/JHAs

9) Fire awareness to be reinforced at toolbox meetings

10) Fire machinery bans communicated via toolbox

11) All equipment to be certified and maintained as per machinery and equipment specification

12) Flammable materials to be removed from areas around ignition sources i.e. welding bays

13) Any rubbish, debris or oil refuse that could constitute a fire hazard shall securely store for later removal/ or removed immediately

14) Vehicles to be equipped with firefighting equipment and signed

15) Emergency contact details available to all site personnel

16) Flammable chemicals to be stored as per SDS

17) Site to be kept neat and tidy and as much as possible free of combustible material

18) Equipment operated as intended by competent operators

RUSSELL ROAD INTERCONNECT Environmental Plan Bridging Document - Summary

RRI-PL-HS-0006 Page 19 of 19

Table 9 – Commissioning - Gas Introduction and Venting

Management Requirements

Office/Management requirements

1) Communications: Notify all personnel in the vicinity of the blowdown to evacuate the area until the blowdown activity has been completed

2) Communications: Notify immediate business owners and stakeholders

3) Design: Gas blowdown stacks to be above head height

4) Documentation: Commissioning plan and relevant work instructions

5) Design: Piping specifications exceed maximum shut-in pressure

Site-based requirements

Venting Odorised Gas

6) Log all gas emissions to record the amount of gas emitted into the atmosphere

7) Fire extinguishers available

8) Plan the job to limit the number of times blowdowns need to occur

9) Limitations: anticipated to be <500 cubic metres

10) Restrictions: Keep ignition sources away from work area

11) Permit to work to be in place prior to venting

12) Traffic Management Plan

13) Barricading: Prohibited/barricaded areas

14) Design: Piping specifications exceed maximum shut-in pressure

15) Design: Open area at ground level

16) Testing: Piping, valves and flanges pressure tested prior to pre-commissioning

Commissioning

17) Barricading: Prohibited/barricaded areas

18) Design: Open area at ground level

19) Testing: Piping, valves and flanges pressure tested prior to pre-commissioning

7 APA GROUP CONTACT DETAILS

For further queries regarding the RRI Project E-BD please contact Mr. Sean Helbig on:

Ph.: (08) 6189 4569; or

Email: [email protected]