MANUFACTURING RESOURCE PLANNING (MRP II) Presented By - MOHSIN DALVI 13MT07IND014 M. Tech (Indl. Engg), Sem-II MANUFACTURING RESOURCE PLANNING (MRP II)

Transcript of mohsin dalvi mrp ii presentation

MANUFACTURING RESOURCE PLANNING (MRP II)

Presented By - MOHSIN DALVI13MT07IND014M. Tech (Indl. Engg), Sem-II

MANUFACTURING RESOURCE PLANNING (MRP II)

2

Manufacturing Resource Planning(MRP II)

Evolution of MRP II

3

• Manufacturing processes are at the centre of all value addition activities.

• In 1962, in response to Toyota Manufacturing Program, Joseph Orlicky developed Material Requirements Planning (MRP).

MRP

MATERIAL B

MATERIAL A

MATERIAL C

MANUFACTURING PROCESSMATERIALS FINISHED

GOODS

Manufacturing Operations ControlThe Future of MRP II

4

Material Requirements Planning

• Black & Decker was first the company to use MRP in 1964. • MRP systems help to better manage material

procurement for supporting manufacturing operations • MRP translates the master production schedule into

component level demand using a bill of materials and direct the purchasing group when to procure based on the component lead times loaded into the MRP system and the current inventory levels.

Evolution of MRP II

5

MRP Process FlowEvolution of MRP II

6

Problems With MRP

• The user has to specify how long it takes a factory to make a product from its component parts.• The system design assumes that manufacturing lead

time will be constant every time.• It takes no account of capacity in its calculations. Thus

it will give results that are impossible to implement due to manpower or machine or supplier capacity constraints.

Evolution of MRP II

7

Opportunities Beyond MRP

• Once an MRP system is in place, inventory data can be augmented by other useful information• Labor hours• Material costs• Capital costs• Virtually any resource

Evolution of MRP II

8

MRP

II

MRP

MATERIAL B

MATERIAL A

MATERIAL C

MATERIALS MANUFACTURING PROCESS

FINISHED GOODS

OPERATOR A

OPERATOR BOPERATORS

EQUIPMENT A

EQUIPMENT BEQUIPMENTS MACHINE

HOURS

MAN HOURS

Expanded Scope of Operational ControlThe Future of MRP II

9

Introducing MRP II

• In 1983 Oliver Wight along with Walter Goddard developed Manufacturing Resource Planning (MRP II) from MRP and also led the evolution of Production Planning into Operations Planning.• MRP II systems deal with resource capacities and consist

of the basic MRP I modules plus the RCCP (Rough Cut Capacity Planning), CRP (Capacity Requirement Planning) and SFC (Shop Floor Control) modules.

Evolution of MRP II

10

Why MRP II?

• While MRP stops at the receiving dock, MRP II incorporates the value stream all the way through the manufacturing unit up to the shipping dock.• The value stream includes demand forecasting , machine

capacity scheduling, labor planning and quality tracking.• MRP II extends the Just in Time concept beyond

inventory and expands it into labor availability, raw material arrival, machine availability and so on.

Evolution of MRP II

11

Manufacturing Resource Planning(MRP II)

Definition and Features of MRP II

12

Definition of MRP IIDefinition and

Features of MRP II

• Manufacturing Resource Planning (MRP II) is defined by APICS (American Production and Inventory Control Society, estd. 1957) as a method for the effective planning of all resources of a manufacturing company.• It addresses operational planning in units, financial

planning in dollars, and has a simulation capability to answer "what-if" questions and extension of closed-loop MRP.

13

Definition of MRP II

• MRP II is an incremental information integration business process strategy implemented using hardware and modular software applications linked to a central database that stores and delivers business data and information. • The goal of MRP II is to provide consistent data to all

players in the manufacturing process as the product moves through the production line.

Definition and Features of

MRP II

14

Features of MRP II

• MRP II concentrates on the resources, i.e. material, man and machine for detailed production scheduling. • Loading by resource means that capacity is taken into

account , which offers tighter control over the plant.• The Rough Cut Capacity Planning attempts to match the

order load to the capacity available, by identifying resource overloads and moving orders to achieve a balance (knocking the mountains into the valleys).

Definition and Features of

MRP II

15

Features of MRP II

• It builds on closed-loop MRP by adopting the feedback principle and extending it to additional areas of the enterprise such as purchasing, marketing and finance.• It integrates all aspects of the manufacturing process,

including materials, finance and human relations, for planning and control purposes. • This integration extends from strategic to operational

levels and encompasses long term planning up to short term control.

Definition and Features of

MRP II

16

Features of MRP II

• Fluctuations in forecast data are taken into account by including simulation of the master production schedule, thus creating a long-term control.• MRP II is a total company management concept for

using human resources more productively.• The MRP II process is carried out by a synergistic

combination of computer and human resources.

Definition and Features of

MRP II

17

Manufacturing Resource Planning(MRP II)

Structure and Working of MRP II

18

Working of an MRP II System

• MRP II systems begin with MRP, which inputs the sales forecasts from sales and marketing and determines the demand of raw materials by analyzing the forecasts. • The company’s strategic plans for the future are

translated into a Master Production Schedule (MPS).• MRP II assures that the production facility is capable of

accomplishing the MPS otherwise all these plans will result in inability to meet the promised delivery dates.

Structure and Working of

MRP II

19

Working of an MRP II System

• This is performed in an iterative manner.• MRP schedules are constructed to support this MPS.• Then Capacity Requirements Planning (CRP) is

performed which tells what equipment, personnel, and materials would be needed to meet the MRP schedules.• If this capacity is not available, then the MPS and

possibly the strategic plans must be revised until the MRP schedules are consistent with the plant capacity.

Structure and Working of

MRP II

20

Working of an MRP II System

• This revision process facilitates the development of a detailed production schedule that accounts for labor and machine capacity. • The schedules are released to the departments which

perform production and/or purchasing operations.• The MRP II system draws on the revised MPS and

provides output in the form of a final labor and machine schedule and schedules the production runs according to the arrival of materials.

Structure and Working of

MRP II

21

Working of an MRP II System

• The MRP II systems continuously provide production data to accounting and finance about the production costs in terms of machine time, labor time and materials, as well as the final production numbers.• The feed back of this information to the MRP/MPS

elements allow plans to be updated thereby creating a closed loop planning and execution system.

Structure and Working of

MRP II

22

Structure and Working of

MRP IIMRP II Process Flow

Problem:To schedule the resources for enabling uninterrupted production of 100 units of product P 9 weeks from now.

A Typical Resource Planning ProblemWHAT ARE

NEURAL NETWORKS?

MATL - A1 UNIT

MATL – PI UNIT

MATL - C3 UNITS

MATL - B2 UNITS

Resource Requirement Matl A Matl B Matl C

Lead time (Wks) 1 2 4

Raw Matl Cost (Rs) 2 5 5

Labor Reqd (Hrs) 10 10 2

Machine Reqd (Hrs) 2 2 1

Bill Of Materials

24

Week5 6 7 8

A. Units (lead time 1 week) 100Labor: 10 hours each 1,000Machine: 2 hours each 200Payable: Rs 2 each 200

B. Units (lead time 2 weeks, 2 each required) 200Labor: 10 hours each 2,000Machine: 2 hours each 400Payable: Raw material at Rs 5 each 1,000

C. Units (lead time 4 weeks, 3 each required) 300Labor: 2 hours each600Machine: 1 hour each 300Payable: Raw material at Rs 10 each 3,000

Structure and Working of

MRP IIResource Estimation

25

Softwares for MRP II

• A typical MRP II software system employs a modular construction.• The modules keep track of and regulate specific

characteristics and functions of the entire organization.• The MRP II differs fundamentally from point contact

planning, in which individual characteristics and functions have their own dedicated systems.

Definition and Features of

MRP II

26

Primary Modules in an MRP II Software

• Master Production Scheduling (MPS)• Item Master Data (Technical Data)• Bill of Materials (BOM) (Technical Data)• Production Resources Data (Manufacturing Technical Data) • Inventories & Orders (Inventory Control)• Purchasing Management• Material Requirements Planning (MRP)• Shop Floor Control (SFC)• Capacity planning or Capacity Requirements Planning (CRP) • Standard Costing (Cost Control)• Cost Reporting / Management (Cost Control)

Structure and Working of

MRP II

27

Ancillary Modules in a MRP II Software

• Business Planning • Lot Traceability • Contract Management • Tool Management • Engineering Change Control • Configuration Management • Shop Floor Data Collection • Sales Analysis and Forecasting• Finite Capacity Scheduling (FCS) • General Ledger• Accounts Payable (Purchase Ledger) • Accounts Receivable (Sales Ledger)• Sales Order Management

Structure and Working of

MRP II

• Distribution Requirements Planning• Distribution Resource Planning (DRP)• [Automated] Warehouse Management• Project Management• Employee attendance• Labour productivity• Quality tracking tools• Technical Records• Estimating• Computer-aided design/Computer-

aided manufacturing (CAD/CAM)• Computer Aided Process Planning

(CAPP)

28

Softwares for MRP II

• The MRP II system integrates these modules together so that they use common data and freely exchange information, in a model of how a manufacturing enterprise should and can operate.• MRP II is not exclusively a software function, but a

marriage of people skills, dedication to data base accuracy, and computer resources.

Definition and Features of

MRP II

29

Manufacturing Resource Planning(MRP II)

Benefits and Limitations of MRP II

30

Benefits From MRP II

• Increased direct labor productivity• High accuracy of inventory and manufacturing capacity• Effective interaction between different functions due to

common databases and improved information flow• Quicker implementation of engineering changes• Simulation capability to test what-if scenarios in a risk

free environment• Company focus shifts from crisis management to

process control

Benefits and Limitations of

MRP II

31

Benefits of MRP II to Business Functions

• For Manufacturing Functions: • Better control of inventories • Improved scheduling • Productive relationships with suppliers

• For Financial and Costing Functions : • Reduced working capital for inventory • Improved cash flow through quicker deliveries • Accurate inventory records • Timely and valid cost and profitability information

• For Design / Engineering Functions : • Improved design control • Better quality and quality control

Benefits and Limitations of

MRP II

32

Limitations of MRP II

• Capacity can be considered only after the MRP schedule has been prepared. • It may happen that insufficient time was allowed within

the MRP schedule for the individual operations to be completed, thus leading to erroneous data.• All the planning, if done on the basis of misleading data,

will slow down the production process.• If unexpected input changes occur, the planning process

has to be recalculated from start.

Benefits and Limitations of

MRP II

33

Limitations of MRP II

• Inefficiencies will be built up in the system if feedback about problems is not supplied on a timely, regular basis.• MRP II is mostly run in batch environments, as it enables

rapid lot to lot course corrections to meet real world conditions. In long production runs, corrections take time.• MRP II softwares are costly and have a learning curve.• MRP II does not integrate all aspects of development,

finance, marketing, human resources and information technology operations .

Benefits and Limitations of

MRP II

34

Keys to MRP II Success

• Commitment to change and improvement• Serious evaluation of current situation and future goals• Active support from top management• Full time dedicated project implementation manager• Implementation of cross functional teams• Methodical implementation plan• Implementation schedule that is long enough to be

thorough but short enough to sustain momentum

Benefits and Limitations of

MRP II

35

Keys to MRP II Success

• Unmodified off-the-shelf software package• Database integrity before beginning implementation• Pilot program before gradual but complete changeover• Company wide training and education (focus on people,

not computers)• Minimal reliance on consultants once system is

operational• Perseverance to overcome cultural barrier

Benefits and Limitations of

MRP II

36

Manufacturing Resource Planning(MRP II)

The Future of MRP II

37

ERP

MRP

II

MRP

MATERIAL B

MATERIAL A

MATERIAL C

MATERIALS MANUFACTURING PROCESS

FINISHED GOODS

OPERATOR A

OPERATOR BOPERATORS

EQUIPMENT A

EQUIPMENT BEQUIPMENTS MACHINE

HOURS

MAN HOURS

INFRASTRUCTURECUSTOMER RELATIONS

MANAGEMENT

FINANCES HUMAN RESOURCES

Extending MRP II Over The EnterpriseThe Future of MRP II

38

Enterprise Resource Planning

• ERP is the next evolution of the MRP system.• It attempts to integrate the information flow from all

departments of the company: finance, marketing, production, logistics and human resources.• A properly set up ERP system allows all departments to

intercommunicate and monitor a customer order at any point in time.

The Future of MRP II

39

Enterprise Resource PlanningThe Future of MRP II

40

Manufacturing Resource Planning(MRP II)

End of Presentation