MoE Priorities for the Next 5 Years

Presentation No 2 - Dtd (2nd June 2009)

Page 2: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

Iraqi Electricity Sector:

• The electricity sector in Iraq requires large investments to fulfill the increasing demand on electrical power.

• The below table shows the expected peak demand for electricity from 2009 to 2015.

• The below table shows the situation of the electricity network for the first five months in 2007 and 2008.

Year 2009 2010 2011 2012 2013 2014 2015

Peak Demand MW 12500 13800 15200 16700 18400 20300 22300

Months2007 2008

Production MW

Demand MW

Shortage MW

Production MW

Demand MW

Shortage MW

Jan. 3366 7865 4499 3746 8586 4840

Feb. 3733 7784 4051 4115 8399 4284

Mar 3637 6631 2994 4252 6887 2635

Apr. 3909 6693 2784 4460 7318 2858

May 3699 7786 4087 4200 8025 4009

Average 3668 7351 3683 4154 7843 3725

Page 3: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

• The required investment is estimated to be $16 Billion US Dollars from the period 2007 – 2010 according to the National Development Strategy issued by the Ministry of Planning and Development Cooperation and these estimates include government and private investments.

• MoE have plans to increase the production capacity and improve the performance of their transmission and distribution to cover the full demand gradually till 2012 by:

First: Rehabilitation of the existing power plants to produce electric power to their existing access design capacity. This will have a low cost effectiveness as well as short time for

implementation.

Second: Establishment of new production plants (Thermal & Gas) according to the central plan to

cover the entire requirement of electricity power till 2012.

Page 4: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

REHABLITATION OF GAS STATIONS FOR 2009 & 2010

Page 5: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

GAS TURBINE REHABILITATION PROGRAM (2009)No Station Expected Capacity to be added Remarks

YEAR 20091 Al-Dura ( 4x 37.5 ) 100 MW Rehabilitate Units ( 4)

2 Al-Hilla ( 5x25 ) 20 MW Rehabilitate Unit 5 Type FT8

3 Al- NAJAF ( 3x63 ) 40 MW Rehabilitate unit No (1)

4 DIBIS ( 3x37.5 ) 15 MW Rehabilitate Units (3 )

5 MULLA ABDULLAH old(12x20 ) 30 MW Rehabilitate Units (1 and 2)

6 BAIJI ( 4x159 ) 40 MW Rehabilitate 2 units

7 BAIJI MOBILE ( 7x 23 45 MW Rehabilitate 3 units Type TM2500

8 BAZERGAN ( 1x43 ) 15 MW Rehabilitate unit (1)

9 MOUSIL ( 12x20 ) 15 MW Rehabilitate Units (1)

10 Al-QUDS ( 4x43 ) 100 MW Rehabilitate Units (1)

Total Expected Capacity to be added 460 MW

Page 6: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

GAS TURBINE REHABILITATION PROGRAM (2010)No Station Expected Capacity to be added Remarks

1 Al- NAJAF ( 3x63 ) 10 MW Rehabilitate Units (2)

2 MULLA ABDULLAH old(12x20 ) 45 MW Rehabilitate Unit (5)

3 SHOAIBA MOBILE (2x13) 5 MW Rehabilitate one unit

4 TAJI MOBILE(3x20) 45 MW Rehabilitate 3 units Type TM2500

5 BAIJI MOBILE ( 7x 23) 45 MW Rehabilitate 3 units Type TM2500

Total Expected Capacity to be added 150 MW

Page 7: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

REHABLITATION THERMAL POWER STATIONS 2009 - 2014

Page 8: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

THERMAL UNITS REHABILITATION PROGRAM (2009)

No Station Expected Capacity to be added Remarks

1 SOUTH BAGHDAD (2x67.5 + 4x45 ) 50 MW Rehabilitate unit No : 3 Execution %70

2 SOUTH BAGHDAD (2x67.5 + 4x45 ) 50 MW Rehabilitate units 1&2 contract signed with Ag Inrgos

Total Expected Capacity to be added 100 MW

Page 9: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

THERMAL UNITS REHABILITATION PROGRAM (2010)No Station Expected Capacity to be added Remarks

1 AL-DURA( 4x160) 120 MW Rehabilitate units 3 & 4

2 AL-HARTHA( 4x200 ) 400 MW Rehabilitate units 2 & 3 W.B

3 BAIJI ( 6x 220 ) 200 MW Rehabilitate units 5

4 AL-MUSSAIB (4x300) 100 MW Rehabilitate unit 3 : Japanese Loan

Total Expected Capacity to be added 820 MW

Page 10: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

THERMAL UNITS REHABILITATION PROGRAM (2011)No Station Expected Capacity to be added Remarks

1 AL-MUSSAIB (4x300) 100 MW Rehabilitate Unit (1)

2 BAIJI ( 6x 220 100 MW Rehabilitate 3 Units

3 AL-HARTHA( 4x200 ) 400 MW Rehabilitate Units 2 & 3 W.B

Total Expected Capacity to be added 600 MW

Page 11: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

THERMAL UNITS REHABILITATION PROGRAM (2012)No Station Expected Capacity to be added Remarks

1 BAIJI ( 6x 220 ) 100 MW Rehabilitate Unit (1)

2 AL-HARTHA( 4x200 ) 50 MW Rehabilitate Unit (1)

3 AL- NASSIRIYAH ( 4 x210 ) 50 MW Rehabilitate Unit (1)

Total Expected Capacity to be added 200 MW

Page 12: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

THERMAL UNITS REHABILITATION PROGRAM (2013)No Station Expected Capacity to be added Remarks

1 AL-MUSSAIB (4x300) 100 MW Rehabilitate unit No : 2

2 AL- NASSIRIYAH ( 4 x210 ) 50 MW Rehabilitate unit No : 2

3 AL-HARTHA( 4x200 ) 50 MW Rehabilitate unit No : 4

Total Expected Capacity to be added 200 MW

Page 13: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

THERMAL UNITS REHABILITATION PROGRAM (2014)No Station Expected Capacity to be added Remarks

1 AL-MUSSAIB (4x300) 100 MW Rehabilitate unit No : 4

2 AL- NASSIRIYAH ( 4 x210 ) 50 MW Rehabilitate unit No: 3

3 BAIJI ( 6x 220 ) 100 MW Rehabilitate unit No: 2

Total Expected Capacity to be added 200 MW

Page 14: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

NEW THERMAL POWER STATIONS FOR2009 - 2015

Page 15: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

NEW THERMAL POWER STATTION PLAN (2009 2014)

No Station DESIGNE OUTPUT MW EXPECTED OPERATION DATE

1 AL-KHAYRAT 4x300 = 1200 MW 2013-2014

2 AL-Youssifya 3X210 = 630 MW 2012

3 Al-Shemal Station 4x350 = 1,400 MW 2012-2013

4 Salah Al-Deen 4x300 = 1,200 MW 2013-2014

5 Al-Anbar 4 x 300 = 1,200 MW 2013-2014

6 HARTHA EXTENSION 2x300 = 600 MW 2013

7 NAJIBIYAH EXTENSION 1x150 = 150 MW 2012-2013

8 South Baghdad Expansion 1 x 150 = 150 MW 2012-2013

9 Al-Nasiriya Expansion 2 x 350 = 700 MW 2013

Total Expected Capacity to be added 7730 MW

Page 16: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

NEW GAS STATIONS 2009 - 2015

Page 17: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

NEW GAS TURBINE PROJECTS 2009 – 2014 The MoE’s plan includes the establishment of Gas Turbineprojects units as follows :

1) 60 Units 125 MW each (GE).

2) 4 units 40 MW each (GE).

3) 6 units 260 MW each (SIEMENS).

4) 10 units 160 MW each (SIEMENS).

Page 18: MoE Priorities for the Next 5 Years Presentation No 2 - Dtd (2 nd June 2009)

NEW GAS POWER STATTION PLAN (2009 - 2014)

No Station Designed Capacity in MW EXPECTED OPERATION DATE

1 SHAT AL-BASRAH 6x125 = 750 MW 2011-20122 AL-NASSIRIYAH 4x125 = 500 MW 2011 3 AL- KHAYRAT 6x125 = 750 MW 2011-2012

4 AL- ANBAR 4x125 = 500 MW 2012

5 NAYNAWA 6x125 = 750 MW 2011-2012

6 AL-NAJAF 4x125 = 500 MW 2010-2011

7 AL - QUDS 2X125 = 250 MW 2011

8 WASSIT 2X125 = 250 MW 2011-2012

9 AL- MANSOURIA 2X125 = 250 MW 2011-2012

10 DURA SITE 3 6X125 = 750 MW 2011-201211 AL- DEWANIAYAH 4X125 = 500 MW 2011-2012 12 OMARAA 2X125 = 250 MW 2011-2012 13 AL-SADIR CITY 2X160 =320 MW 2011-201214 BAIJI 6X160 = 960 MW 2011-201215 DIBIS 2X160 = 320 MW 2011-201216 KARKUK TAZA 1X260 = 260 MW 210-201117 RUMAILA NORTH 5X260 = 1300 MW 2011-201218 KARBALA’A 2X125 = 250 MW 2009-2010 19 HILLA ABU GARAQ 2X125 = 250 MW 2009-201020 TAJI 4X40 =160 MW 2009-2010

Total Expected Capacity to be added 9820 MW

No. 18, 19 & 20 are under prequalification