Module 4 - Pier Rehabilitation Design and Construction

15
Travis Butz, PE, Burgess & Niple Module 4: Pier Rehabilitation Design and Construction ABC-UTC In-Depth Web Training Milton Madison Bridge Replacement: the Mega-Lateral Slide Existing Bridge 2 Milton, KY Madison, IN Proposed Bridge Pier 2 Pier 3 Pier 4 Pier 5 Pier 6 600’ 600’ 727’-3” 500’ New Pier Cap Strengthen Existing Pier New Pier 254’ 150’ Pier 9 Pier 8 Pier 7 Pier 6 Pier 4 600’ 600’ 727’-3” Pier 5 Typical Existing River Piers 3 20’ Water 60’ Soil Un-reinforced Caisson Un-reinforced Rock Socket 1.7’-6.7’ deep Existing Pier stem reinforcing extends 12’ into caisson Boulders

Transcript of Module 4 - Pier Rehabilitation Design and Construction

Travis Butz, PE, Burgess & Niple

Module 4: Pier Rehabilitation

Design and Construction

ABC-UTC In-Depth Web TrainingMilton Madison Bridge Replacement: the Mega-Lateral Slide

Existing Bridge

2

Milton, KY Madison, IN

Proposed Bridge

Pier 2

Pier 3

Pier 4

Pier 5

Pier 6

600’ 600’ 727’-3” 500’

New Pier Cap

Strengthen Existing Pier

New Pier

254’ 150’

Pier 9

Pier 8

Pier 7

Pier 6

Pier 4

600’ 600’ 727’-3” Pier 5

Typical Existing River Piers

3

20’ Water

60’ Soil

Un-reinforced Caisson

Un-reinforced Rock Socket 1.7’-6.7’ deep

Existing Pier stem reinforcing extends 12’ into caisson

Boulders

4

Proposed Pier Strengthening

1. Drill holes into existing

unreinforced caisson

2. Grout Rebar into Caisson

3. Add Stem Reinforcement

4. 2’ thick encapsulation

5. Pier Cap Reinforcement

6. Form and Cast new Pier

cap

Existing Pier and Caisson

SECTION A-A

A A

Design Concept:

5

6

Pier Construction Sequence

7

Pier Construction Sequence

8

Pier Construction Sequence

9

Pier Construction Sequence

10

Pier Construction Sequence

11/10/201511

Sliding

Truss Sliding

Pulling

Truss Sliding

Truss Sliding

Truss Sliding

Truss Sliding

FE Analysis of Pier Foundations

FE Analysis of Pier Foundations

FE Analysis of Pier Foundations

FE Analysis of Pier Foundations

FE Analysis of Pier Foundations

Strength Analysis of Caissons & Stem

Pier Cofferdams Installed

Exposed Caisson

Exposed Caisson

Coring Operation

Holes extended up to 71’-7” below the top surface of the caisson

Coring Operation

Caisson Reinforcement

Bundles of 3-#14 Bars

Grouting:

Grout tubes installed with bars. Grout injected from the bottom up.

Grouting:

- Revealed that holes were interconnected

- Raised concerns about voids within the caissons

Pier Construction Method:

Caisson Voids:

Caisson Voids:

Caisson Void Resolution:

- Grouting procedure altered in an attempt to assure all connected voids are filled.

- Test holes were cored after grouting was complete to verify that no voids were discovered.

Pier Stem Shear Connectors:

Stem Reinforcement

Sliding GirderPedestal Bars

Tighter spacingnear top of stem

Stem Complete

TemporaryPier in Place

Sliding Girder PedestalReinforcement:

New Pier Caps

New Pier Caps

Truss Sliding

Final Condition

• Expect the unexpected when you are rehabilitating an existing bridge.

• Anticipating potential problems during design can make things easier during construction.

• Be flexible in finding solutions for problems in the field.

Lessons Learned:

Questions?

Thanks to the following for photos and other material included in this presentation :