Page 1: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Module 1-2

Introduction to Preventive Maintenance

1-2.1

Page 2: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.2

Learning Outcomes1. Explain the concept of preventive

maintenance2. Discuss the importance of treatment

timing3. List the benefits of a preventive

maintenance program4. Describe a good candidate pavement

for preventive maintenance

Page 3: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.3

Failing to Learn

... or learning from failure

Over-applied band-aid crack sealant leads to moratorium in New York

Cracked windshield claims lead to bans (many agencies)

Claims in Michigan lead to restrictions on double chip seals and microsurfacing

Page 4: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.4

Planned strategy Cost effective treatments Maintains or improves functional

condition Does not increase structural capacity

Defining Preventive Maintenance

Page 5: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Preventive Maintenance Concept

Keeping good roads in good condition!Keeping good roads in good condition!

1-2.5

Page 6: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.6

Preventive Maintenance and Safety

1. Treatments are excellent opportunity to improve safety characteristics

2. Potentially more frequent work zones present challenges to both workers and drivers

3. Safe practices should always be followed

Page 7: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

How do preventive treatments differ from routine/reactive treatments?

Similar treatments…different TIMING!

1-2.7

Page 8: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.8

Age of pavement or surface Condition of pavement Next scheduled treatment

Preventive Maintenance Timing

Page 9: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Pav

emen

t C

ondi

tion

(Fun

ctio

nal o

rS

truc

tura

l)

Time (Years)

Preventive Maintenance

Reconstruction

Good

Poor Rehabilitation

DeferAction

Preventive Maintenance Timing

1-2.9

Page 10: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Time or Traffic

Pav

emen

t C

ondi

tion

PreventiveMaintenancePreventiveMaintenance

ReactiveMaintenanceReactiveMaintenance

RehabilitationRehabilitation

Importance of Treatment Timing

1-2.10

Page 11: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.11

Expected Benefits Preserve investment

Improved pavement performance Long term cost savings/leveling

High level of service Increased safety Greater customer satisfaction

Page 12: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.12

Preserving the Investment Keep water out! Reduce debris infiltration into joints or

cracks Slow aging effects of bituminous

pavements Minimize dynamic loads

Page 13: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.13

Maintain good rideability Maintain good surface friction Minimize potentially dangerous

surface characteristics

Maintaining High Level of Service

Page 14: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.14

Impact on Distress Prevent or slow some distresses from

occurring Correct minor surface deterioration

Page 15: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.15

HMA Problems Reduced/Slowed with Preventive Maintenance Oxidation/raveling Block cracking Edge cracking Crack deterioration Roughness Potholes

Page 16: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.16

Minor rutting Raveling Bleeding/flushing Surface friction loss Roughness

HMA Problems Corrected with Preventive Maintenance

Page 17: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.17

PCC Problems Reduced/Slowed with Preventive Maintenance Loss of fines (pumping) Corner breaks Joint faulting Joint spalling Crack deterioration Roughness Blow-ups

Page 18: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.18

PCC Problems Corrected with Preventive Maintenance Joint seal damage Map cracking and scaling Surface friction loss Roughness

Page 19: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.19

Evaluating Pavements for Preventive Maintenance

What you don’t see may be more important than what you do see!

Condition Friction Roughness Ability to carry loads

Page 20: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.20

Good Candidate Pavements for Preventive Maintenance No structural failures Minimal distress (extent and severity) Relatively young in age Minor functional problems Few historical problems with similar

projects

Page 21: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.21

When is it too late for preventive maintenance?

HMA Problems PCC Problems Potholes Severely

deteriorated cracks Delamination Unstable rutting

Blow-ups Corner breaks Severely

deteriorated cracks

Page 22: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

1-2.22

Review: Learning Outcomes1. Explain the concept of preventive

maintenance2. Discuss importance of treatment

timing3. List the benefits of a preventive

maintenance program4. Describe a good candidate pavement

for preventive maintenance

Page 23: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

JEOPARDJEOPARDY!Y!

1-2.23

Page 24: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Preventive Maintenance (PM) Jeopardy

Intro to Preventive

Maintenance

$100

$200

$300

$400

$500

1-2.24

Page 25: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Introduction to PM - $100 Keeping good roads in good condition

1-2.25

Page 26: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Introduction to PM - $200 Improved performance Greater customer satisfaction Cost savings Increased safety

1-2.26

Page 27: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Introduction to PM - $300 Potholes Severely deteriorated cracks Delamination Unstable rutting

1-2.27

Page 28: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Introduction to PM - $400 Age of pavement or surface Condition of pavement Next scheduled treatment

1-2.28

Page 29: Module 1-2 Introduction to Preventive Maintenance 1-2.1.

Introduction to PM - $500 Minor rutting Raveling Bleeding/flushing Surface friction loss Roughness