Page 1: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

MODIFICATION OF AIR PREHEATERS IN BOILERS OF

THERMAL POWER STATION-1

NLC LIMITED,NEYVELI.

Page 2: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

PROJECT MEMBERS

A.JANARTHANAN (80106114012)

S.K.KRISHNAKUMAR (80106114019) N.SARAVANAPRASATH (80106114032) T.SATHISHKUMAR (80106114034)

PROJECT GUIDES

INTERNAL GUIDE EXTERNAL GUIDE

Mr.S.RAJKUMAR Mr.K.GANESAN ASSISTANT PROFESSOR, Chief Manager(FHS)

DEPT.OF MECHANICAL ENGINEERING, TPS-I, NLC

A.V.C COLLEGE OF ENGINEERING.

Page 3: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

FLOW OF THE PRESENTATION

TITLE OF THE PROJECT.PROJECT MEMBERS &PROJECT GUIDES.COMPANY PROFILE.OBJECTIVE OF THE PROJECT.

REASON FOR CHOOSING THE TOPIC.METHODOLOGY.PROBLEM DEFINITION.LITERATURE REVIEW.SPEPCIFICATIONS.MODEL CALCULATIONS.HEATING ELEMENTS.RESULTS &CONCLUSIONS.

Page 4: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

COMPANY PROFILEABOUT US• Biggest open-cast Mechanised Lignite Mines in India.

VISION:• To emerge as a leading mining and power company, continue to be a socially

responsible company and strive for Operational excellence in mining and exploration.

 MISSION: • Strive towards greater cost competitiveness and work towards continued

financial strength.• Continually imbibe best practices from the best Indian and International

Organisations engaged in Power Generation and Mining. Be a preferred employer by offering attractive avenues of career growth and excellent work environment and by developing human resources to match international standards.

• Play an active role in society and be sensitive to emerging environmental issues.

Page 5: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

POWER GENERATION

TPS-1 600MW

                       TPS-1 EXPANSION

420 MW

TPS-2 1470 MW

TPS-2 EXPANSION

500MW (to be commissioned)

Page 6: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

Thermal Power Station I

TPS -I is one of the four power stations of a NLC LIMITED its capacity is 600 MW ,12 BOILERS each having a capacity of 220 tonnes/hr, supply steam at 540°C and 90ksc to 6 * 50 Mw turbogenerator and 3 * 100 MW units.

ALLOTED TO %

TNEB Export 80%

Station Consumption 12%

NLC schemes(Mines, Township & others)

8%

Page 7: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

Some of the special features of this TPS-1 are:

•  First Lignite Power Station in south East Asia .

•  First pit head power station in India .

•  First Power Station in India with Soviet Collaboration .

• First largest Thermal Power Station in South India.

• The power generated from the Thermal Power Station is fed to the grid of

Tamil Nadu Electricity Board, the sole beneficiary.

Page 8: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

OBJECTIVE OF THE PROJECT

Improving the efficiency of the boiler at TPS-1 The design value of exit gas temperature in TPS-1 boilers is 160°C.

In our study, we found that the actual exit gas temperature is around 185°C in some boilers. This high gas temperature leads to enormous heat loss through exit gas and ultimately reducing the efficiency of boiler.

Modification of heat recovery system ( i.e.) Air preheaters will utilize temperature of exit flue gas so that there is an improvement in efficiency.

So, we planned to study and analyze the arrangement of air preheaters and suitably modify them so that exit flue gas temperature will be around 160°C which is a designed value

Page 9: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

REASON FOR CHOOSING THE TOPIC

•The purpose of the air preheater is to recover the heat from the boiler flue gas which increases the thermal efficiency of the boiler by reducing the useful heat lost in the flue gas.

•As a consequence, the flue gases are also sent to the flue gas stack (or chimney) at a lower temperature, allowing simplified design of the ducting and the flue gas stack.

•It also allows control over the temperature of gases leaving the stack (to meet emissions regulations).

•Use highly Efficient Air PreHeaters Save Money, Save Energy!

Page 10: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.
Page 11: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

STUDY OF OVERALL PLANT OPERATIONS

IDENTIFICATION OF MAJOR HEAT LOSS OCCURRING IN AIR PREHEATERS

RESULTS:1.Flue gas temperature high &wasted 2. Low efficiency of boilers

DECISION1.To improve the heat balance 2.To recover the waste heat 3.To reduce the moisture

PERFORMANCE OF HEAT EXCHANGERS ANALYZED

CAST-IRON AIRPREHEATER FOUND TO HAVE LOW EFFECTIVENESS

REDESIGN OF CAST-IRON AIR PREHEATER

CALCULATIONS & COST ANALYSIS

Page 12: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

PROBLEM DEFINITION

Initially a complete study is conducted on the 5th boiler in thermal power station -1 at NLC and we collected data about exit flue gas temperature of the boilers.

These data are collected from electronic display unit automatically and as per the standard procedure.

The exit flue gas temperature coming out of the chimney was found to be around 185°C.

The overall efficiency of boiler was reduced due to the high heat loss in the exit flue gas .

There is also insufficient heat transfer area between the exit flue gas and the air that enters the combustion chamber.

Page 13: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

LITERATURE REVIEW

Literature regarding designing of heat exchangers were studied for re designing the existing heat exchanger.

Timo Eirola et al published a paper titled based on “mathematical modeling for a single pass cross flow heat exchangers.”

Basic idea of heat exchanger is to be transfer heat from hot fluid to cold

one.

The modeling of heat exchanger needs simultaneous modeling of energy and mass transfer.

For re-designing the existing heat exchanger we are using minimum

air required and quantity of flue gas formed. For increasing number of elements the heat transfer per unit area of cast iron preheater is considered.

Page 14: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

CONTINUED Ashish V.Pattekar et al (1999) published a titled “synthesis of

optimum controllable heat exchanger “.process integration has paved the way for designs that are optimal from the point of view of energy recovery.

The modern heat exchangers synthesis problem can therefore be stated as the simultaneous optimization of a heat exchanger design from the point of view of energy area and control.

A novel procedure ,genetic algorithms (GA) is used for optimal model of heat exchanger.

Page 15: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

SPECIFICATIONS:

DESCRIPTION UNIT VALUE

Material of the tubes Cast iron

length mm 3560

Heating surface of one element m² 4.45

Number of elements in one row 74

Total number of tubes 888

Heating surface of cast iron tubes m² 3950

Flow characteristics Single pass cross flow

Page 16: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

EXIT GAS TEMPERATURE

TEMPERATURE

DATE MAX(°c) MIN(°c)

25.12.2009 191 187

26.12.2009 195 188

27.12.2009 189 185

28.12.2009 188 184

29.12.2009 188 183

30.12.2009 191 186

31.12.2009 184 179

01.01.2010 185 180

02.01.2010 189 177

03.01.2010 185 185

Page 17: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

MODEL CALCULATIONS:

•FORMULA TO FIND THE NUMBER OF HEATING ELEMENT TO BE ADDED:

 

1) Designed value of heat transfer expected per unit area of cast iron air preheater per kg of flue gas

 

= 1×Cp×dT

= 1×0.25× (523-431)

= 23 Kcal

Where

Cp = 0.25kcal/kg.k

 

Dt= t1 –t2

 

t2 = 158°c

t1 = 250°c

Page 18: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

2) Actual value of heat transfer expected per unit area of cast iron air preheater per kg of flue gas

=1×Cp×dT

= 1×0.25× (523-458)

= 16.25 k.cal

3) Difference in heat transfer expected per unit area of cast iron air preheater per kg of flue gas

                                   =designed value –actual value

=23-16.25

= 6.75 k.cal

Page 19: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

4) Increase in percentage of heat transfer per unit area of cast iron air preheater

                           = 6.75/23

=29%

 

5) Heating surface of actual cast iron air preheater =3950sq.m

For 29%  increase  in heat  transfer,  the  increased heating  surface of  cast  iron air preheater is

                = (29/100) ×3950

=1145.5                                        ≈ 1146 sq.m

Page 20: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

6) Heating surface of re-designed cast iron air preheater

                                 =3950+1146                                =5096 sq.m7) Heating surface of one element in cast iron air preheater

                                                                   =4.45sq.m   8) Total number of additional elements to be added to increase the heat

transfer area in cast iron airpreheater  =       Increase in heating surface of CIAPH 

Heating surface of one element = 1146/4.45

=258 elements .

Hence 258 additional elements are to be added in cast iron air preheater to increase its heating surface or heat transfer area.

Page 21: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

FORMULAS TO FIND THE OVER ALL INCREASE IN EFFICIENCY OF BOILERS :

Steps to be followed:  1) Minimum air required/kg of fuel.

2) Quantity of flue gas formed (mflue)

=minimum air required/kg of fuel+29% (Increase in percentage of heat transfer per unit area of cast iron air preheater)

3) Heat absorbed in cast iron air preheater  a)Design value: mflue × Cp× ((Temperature of inlet flue gas in °k-(158+273)) b) Actual value: mflue × Cp×((Temperature of inlet flue gas in °k-(185+273)) Where Cp=0.24 kcal/kg.k

Page 22: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

4) Percentage of heat loss :

= [(design value –actual value)/ design value]

This much of percentage area to be increased.

 

5) To find efficiency improvement

Efficiency of boiler =100-various losses in percentage

Losses are calculated separately

Efficiency before modification =100-(2.52+%loss in flue gas before modification) ……. (A)

Efficiency after modification =100-(2.52+% losses in flue gas after modification) ……. (B)

Therefore overall increase in efficiency of boiler = (B)-(A) in %.

Page 23: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

CALCULATION :( Data from NLC manual, Boiler operation and maintenance)  

• Minimum air required/kg of fuel. = (100/23) × {(8/3)C+8[H2-(O2/8)]+S} Where C=carbon, H2=hydrogen, O2 =oxygen s=sulphur  =11.6C+34.8[H2-(O2/8)]+4.35S  • From operation and maintenance manual, [C=31%, H2=2.2%, O2=9%, S=0.3%] =(11.6×0.31)+34.8[0.022-(0.09/8)+(4.35×0.03)  =3.596+0.3741+0.1305  =4.1006 kg/kg of fuel.

Page 24: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Therefore minimum air required per kg of fuel

=4.1006 kg/kg of fuel.

 

• For 29% excess air to be passed through CIAPH

 

           = 4.1006×1.29

 

=5.28977 kg/kg of fuel

 

• Total gas per hour =61900×5.28977

 

=327437 kg/hr

Page 25: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Total flue gas generated                              =61900×5.28977  =327437 kg/hr 

• Heat absorbed by cast iron air preheater from flue gas (design condition)                       =327437×0.24×[(245+273)-(158+273)]  =327437×0.24×(518-431)  = 6836884.7 kcal/hr 

• Heat absorbed /transformed in CIAPH from flue gas (actual condition)                   = 327437×0.24× [(245+273)-(185+273)]  = 327437×0.24× [(518)-(458)]  =4715092.8 kcal/hr  

Page 26: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Percentage decrease in heat absorption    = (6836884.7- 4715092.8)/ 6836884.7  =0.3103  =31.03% ≈31% • Therefore 31% more heating area is to be added. 

Page 27: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Total heating area already available =3950sq.m  Therefore 3950×1.31=5174.5sq.m • Each is divided by heating surface of one element in CIAPH given by

(5174.5/4.45) =1162.80 ≈1163 tubes. • Therefore 1163 elements are required for new heat transfer area of CIAPH  • Additional elements required to increase the total heating area  =1163-888(already provided)  =275 elements.

Hence 275 new elements are to added to increaser the heat transfer area of CIAPH

Page 28: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Various losses in boilers:

 

Assuming the following percentage of losses are constant as referring to NLC, operation and maintenance manual

– Losses due to mechanical under burning =1.5%

– Losses due to chemical under burning=0.5%

– Losses due to radiation effect=0.52%

Therefore,

Total loss=1.5%+0.5%+0.52%

= 2.52%

Page 29: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• To find difference in efficiency:

  8) Heat lost in flue gas before modification                                =327437×0.24×185                                   =14538202kcal • Total heat input =quantity of fuel used ×calorific value of fuel                                    =61900×2450                                     =151655000kcal.

Page 30: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

•  

9) Percentage loss in flue gas before modification,                         Heat lost in flue gas before modification ×100       =                             Total heat input            =   (14538202  /151655000)×100        =9.58%   

10) Heat lost in flue gas after modification  =327437×0.24×158                   =12416411kcal  •  

Page 31: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

11) Percentage loss in flue gas after modification  Heat lost in flue gas after modification ×100 = Total heat input  = (12416411/151655000) ×100  =8.1875%

 

Page 32: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• To find efficiency: Efficiency of boiler =100-losses in percentage  a)Efficiency before modification =100-(2.52+9.58) =87.9%   b)Efficiency after modification =100-(2.52+8.1875) = 89.29%   Therefore overall increase in efficiency of boiler =89.29-87.9  =1.393%  

Page 33: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

FORMULA TO SOLVE FUEL SAVINGS:

1) Fuel savings=61900×% increase in efficiency

 

=61900×1.393 

=86226.7kg of lignite

 

) In terms of rupees One tonne of lignite =Rs.900  Total fuel savings     =86226.7/1000                                           =86.2267tonnes

Total fuel savings in Rs = 86.2267×900                                        =Rs.77604.03

COST ANALYSIS

Page 34: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

3) Cost of one heating element =Rs.10000

• Total expense =no. of elements added ×cost of one heating element =275×10000  =Rs.2750000

4) To find payback period  Fuel savings in tonnes /hr =61900×1.393                                            =86226.7 kg of lignite                                               =86.2267 tonnes of lignite

Page 35: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

•Fuel savings in tonnes /day =86.2267×24

 

=2069.44 tonnes/day

 

•We know that fuel savings α increase in % of efficiency

 

Fuel savings α 1.393η

 

•Saved fuel consumption per day= (1.393/100)×2069.44

 

=28.827 tonnes /day

 

 

 

Page 36: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Cost of fuel per tonne=Rs.900

 

• Total fuel savings/day=28.827×900

 

=Rs.25944.5

 

• Total fuel savings/month =25944.5×30

 

=Rs.778337.07

 

• Pay back period = (total expense)/( Total fuel savings/day)

 

=2750000/25944.5

 

=106 days

 

Page 37: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

• Total fuel savings per year for one boiler=778337.07×12  =Rs.9340044.8 • Since we are considering about 12 boilers  • Therefore fuel savings per year for 12 boilers =9340044.8×12  =Rs.112080537.6 11.2Crores(approx.) 

Page 38: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

HEATING ELEMENTS

Page 39: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

RESULTS

•The detailed study of all the 12 boilers was conducted in thermal power station -1 at NLC limited

•The exit flue gas temperature of boiler-5 was found to be 185°c as against designed value of 158°c contributing to the loss of boiler efficiency

•The efficiency of boiler before the modification of CIAPH is 87.9%

•The overall heat transfer coefficient of CIAPH was found to be lower of the order of 14.54W/m²k when compared to other air pre heater

•Effectiveness of CIAPH was also lower of the order of 0.40

Page 40: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

•The redesign of existing CIAPH was proposed.

•The additional elements required to increase the heat transfer surface of CIAPH is 275 elements

•The efficiency of boiler after the modification of CIAPH is 89.29%.

•The overall increases in efficiency of boiler due to redesign of CIAPH is 1.393%

 

•The estimated cost required for the re design 27.50 lakhs.

 

•The pay back period for the proposed design is 106 days

 

•The expected savings per year using the re design was found to Rs.11.2 crores for total of 12 boilers.

Page 41: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

CONCLUSION

•In this project effectiveness of recovery system was observed, performance analyzed based on careful feasibity analysis, modification of cast iron air preheater was recommended.

•The possible improvements in performance was calculated and submitted for consideration.

 

• In addition the following suggestions are put forward for follow up and implementation in order to achieve better efficiency of boiler units.

Page 42: MODIFICATION OF AIR PREHEATERS IN  BOILERS  OF THERMAL  POWER STATION-1 NLC  LIMITED,NEYVELI.

1. It is strongly recommended to replace the sector of elements to achieve design effectiveness when the defective elements exceed 1%

 2. Periodic inspection of heat recovery system is to be carried out to

assess insulation fall, ash deposition &general condition of heat transfer area.

 3. Energy audit of the boiler is to be carried regularly to trace out the

specific area of energy loss.  