Modeling Schedule- 2013 Alternatives Adopted February 5, 2004 Steering Committee Meeting
-
Upload
rashad-morin -
Category
Documents
-
view
25 -
download
2
description
Transcript of Modeling Schedule- 2013 Alternatives Adopted February 5, 2004 Steering Committee Meeting
1
RMATS
Modeling Schedule- 2013 AlternativesAdopted February 5, 2004 Steering Committee Meeting
Week 1
(Feb 16- 20)
Week 2
(Feb 23- 27)
Week 3
(Mar 1- 5)
Week 4
(Mar 8- 12)
Week 5
(Mar 15- 19)
Week 6
(Mar 22- 26)
Week 7
(Mar 29- 2)
Modelers input the resource information into model
Run model is run for Alternatives 1 and 2
TAWG convenes group to decide transmission cases that modelers should model for Alternatives 1 and 2
Modelers begin running model to determine congestion/LMPs implications of alternatives 1 and 2 with transmission cases
RAWG begins process of quantifying capital costs of new resources
Modelers initiate runs for Alternatives 3 and 4
TAWG and modelers iterate on alternatives 1 and 2
Joint TAWG and modeling team meeting
Modelers provide alternatives 3 and 4 results to TAWG (without transmission adds)
TAWG finalizes transmission solution for alternative 1
TAWG begins process of quantifying capital costs of transmission additions
TAWG decides transmission solutions to be modeled for Alternatives 3 and 4
Modelers initiate additional sensitivities ($4 gas, hydro, carbon limitations, DSM, target export markets, high load)
TAWG and modelers iterate on alternatives 2, 3 and 4
Joint TAWG and modeling team meeting
TAWG finalizes transmission solution for alternative 2
Preparation for the Public Meeting
TAWG and modelers iterate on alternatives 3 and 4
Joint TAWG and modeling team meeting
TAWG finalizes transmission solution for alternatives 3 and 4
RAWG and TAWG complete quantification of capital costs for resource and transmission additions
Modelers complete additional sensitivities
Tie up loose ends
Consolidate results
Validate results
Package packaging results
TAWG m
eetin
g sch
edule
d
for M
ar 8th at
PDX
Red indicates completed