Part Four How projects under the Model achieve most of the Millennium goals in project areas.
Model Project-Part 2
-
Upload
khusbu-sarathkumar -
Category
Documents
-
view
219 -
download
0
Transcript of Model Project-Part 2
-
8/8/2019 Model Project-Part 2
1/32
o Per shift 30 rolls are made and kept in the bias-cutting room which
is air-conditioned
3.1.2 Building
o There are three machines available.
Activities done are:
o Fitting the mould in the building machine;
o Silicon application on mould;
o Putting next layer Jacket;
o Cord is rolled above this layer;
o Rubber sheet is rolled in required numbers as per the width
required for a specification.
o Mould of different diameter is used as per the requirement.
3.1.3 Vulcanizing (or Pot Curing)
o There are three machines available.
o It follows differential pressure curing method.
o Mould should be kept for 30 minutes inside the pot.
o Defect in this process may be that, the operator will take the mould
before 30 minutes itself.
3.1.4 Cooling
o Tank of water at a particular cool temperature is maintained.
o Mould is immersed inside this water for cooling for ten mins.
o Process starting from building stage up to the present stage must be
completed within a day so that the rubber quality is maintained.
o Defect in this process is that, the operator may take the mould
before the stipulated ten minutes period.
3.1.5 Stripping
o A single machine is available.
o Rubber and the mould are separated at this process using a machine.
3.1.6 Strip/Square Cutting
o A single machine is available.
-
8/8/2019 Model Project-Part 2
2/32
o Cuts the rubber which looks like hollow cylinder into belts of
different sizes as per the requirement.
3.1.7 Grinding
o There are six machines available.
o Two machines are imported from China. The belts are grinded a
single time in these machines, whereas in the rest four machines the
grinding is done in two machines for neat finish. i.e., once the grooves
are made in one machine as rough finish and final touch is done by
another machine.
o Grooves are created at this process.
o Specification of the belt varies as per the diameter and the no. of
grooves.
3.1.8 Single-belt cutting
o A single machine is available.
o Same mechanism as Strip cutting is applied here.
o Difference is that, in strip cutting, for conveniences of grinding the
belt are cut in twos or threes.
o Here, the belts are cut into individual pieces. [E.g.: if 4 groove
belts are required, then it will be cut into 24 groove belts in the strip-
cutting process, which will be comfortable in grinding instead of 6*4
belts.]
o Final step is done by the single-belt cutting machine.
3.1.9 Dust-cleaning machine
o A single machine is available.
o It cleans the dust in the belt completely.
3.1.10 Visual inspection
o Three staff does the inspection work manually.
o They will visually see for flaws in the belt and will reject if they
find any.
3.1.11 Coding
-
8/8/2019 Model Project-Part 2
3/32
o A single machine is available.
o It is similar to inspection, but performed with a machine.
o It checks the length of each belt with respect to the specification.
3.1.12 Taken to finished goods warehouse for dispatch to customers
oThe finished products after the production process will be transferred to
the finished goods department for dispatching to the customers.
-
8/8/2019 Model Project-Part 2
4/32
-
8/8/2019 Model Project-Part 2
5/32
4 Analysis & interpretation
The following section analyses the data collected through secondary sources in the form
of tables and provides interpretations for the same.
Table 4.1 Standards Vs Actuals for the month of October 2009
Machinery
Machine
hours
available
Rated
production
(in units)
Actual
hours
utilized
Actual
production
(in units)
Bias Cutting 504 2160 489.33 2086
Building 1 504 2880 469.50 2664
Building 2 504 2160 460.75 2030
Building 3 504 2160 452.60 2006Pot curing 504 7200 443.52 6700
Stripping 504 5040 501.40 5213
Strip cutting 504 5040 502.42 5616
Grinding 504 100800 425.83 88315
DRO cutting 504 115200 501.31 123651
Dust cleaning 504 96000 409.99 69975
Coding 504 120000 492.64 108000
Table 4.1 shows the comparison between the machine hours available and actual hours
utilized and the rated production from each machine Vs actual production for the period
of October 2009.
Available machine hours are computed as follows:
No. of working days in October 2009 = 24
Time available for production per day = 21 hours
Time available for production in Oct 2009 = 21 hours*24 days = 504 hours
Actual hours utilized in each machine is computed by deducting the breakdown time of
each machine.
-
8/8/2019 Model Project-Part 2
6/32
Table 4.2 Productivity during October 2009
MachineryProductivity
%
Actual
Hours %
Bias cutting 96.57 97.09
Building 1 92.50 93.15
Building 2 93.98 91.42
Building 3 92.87 89.80
Pot curing 93.06 88.00
Stripping 103.43 99.48
Strip cutting 111.43 99.69Grinding 87.61 84.49
DRO cutting 107.34 99.47
Dust cleaning 72.89 81.35
Coding 90.00 97.75
Computation of productivity for Table 4.2
Productivity (in terms of output) = Actual Production * 100
Rated Production
Actual Hours % = Actual hours utilized * 100
Available time
From Table 4.2 it is evident that, Dust cleaning machine has the lowest productivity and
highest downtime.
-
8/8/2019 Model Project-Part 2
7/32
Table 4.3 Standards Vs Actuals for the month of November 2009
Table 4.3 shows the comparison between the machine hours available and actual hours
utilized and the rated production from each machine Vs actual production for the period
of November 2009.
Machinery
Machine
hours
available
Rated
production
(in units)
Actual
hours
utilized
Actual
production
(in units)
Bias Cutting 546 2340 521.33 2184
Building 1 546 3120 499.32 2879
Building 2 546 2340 511.45 2128
Building 3 546 2340 479.81 1983
Pot curing 546 7800 500.74 6990
Stripping 546 5460 543.68 6084
Strip cutting 546 5460 545.67 6084
Grinding 546 109200 425.49 80286
DRO cutting 546 124800 545.33 140400
Dust cleaning 546 104000 501.62 92134
Coding 546 130000 482.9 117000
-
8/8/2019 Model Project-Part 2
8/32
Available machine hours are computed as follows:
No. of working days in November 2009 = 26
Standard time available for production per day = 21 hours
Standard time available for production in Nov 2009 = 21 hours*26 days = 546 hours
Actual time taken in each machine is computed by deducting the breakdown time of each
machine.
Table 4.4 Productivity during November 2009
MachineryProductivit
y %
Actual
Hours %
Bias cutting 93.33 95.48
Building 1 92.28 91.45Building 2 90.94 93.67
Building 3 84.74 87.88
Pot curing 89.62 91.71
Stripping 111.43 99.58
Strip cutting 111.43 99.94
Grinding 73.52 77.93
DRO cutting 112.50 99.88
Dust cleaning 88.59 91.87
Coding 90.00 88.44
Computation of productivity for Table 4.4
Productivity (in terms of output) = Actual Production * 100
Rated Production
Actual Hours % = Actual hours utilized * 100
Available time
-
8/8/2019 Model Project-Part 2
9/32
From Table 4.4 it is evident that, Grinding machine has the lowest productivity and
highest downtime.
Table 4.5 Standards Vs Actuals for the month of December 2009
Machinery
Machine
hours
available
Rated
production
(in units)
Actual
hours
utilized
Actual
production
(in units)
Bias Cutting 546 2340 532.61 2300
Building 1 546 3120 512.33 2885
Building 2 546 2340 520.40 2220Building 3 546 2340 525.67 2283
Pot curing 546 7800 499.09 7388
Stripping 546 5460 543.08 5850
Strip cutting 546 5460 539.75 5850
Grinding 546 109200 470.51 95413
DRO cutting 546 124800 545.42 135000
Dust cleaning 546 104000 455.54 82976
Coding 546 130000 462.36 112500
Table 4.5 shows the comparison between the machine hours available and actual hours
utilized and the rated production from each machine Vs actual production for the period
of December 2009.
Available machine hours are computed as follows:
No. of working days in December 2009 = 26
-
8/8/2019 Model Project-Part 2
10/32
Standard time available for production per day = 21 hours
Standard time available for production in Dec 2009 = 21 hours*26 days = 546 hours
Actual time taken in each machine is computed by deducting the breakdown time of each
machine.
Table 4.6 Productivity during December 2009
MachineryProductivity %
(output)
Actual
Hours %
Bias cutting 98.29 97.55
Building 1 92.47 93.83Building 2 94.87 95.31
Building 3 97.56 96.28
Pot curing 94.72 91.41
Stripping 107.14 99.47
Strip cutting 107.14 98.86
Grinding 87.37 86.17
DRO cutting 108.17 99.89
Dust cleaning 79.78 83.43
Coding 86.54 84.68
Computation of productivity for Table 4.6
Productivity (in terms of output) = Actual Production * 100
Rated Production
Actual Hours % = Actual hours utilized * 100
Available time
-
8/8/2019 Model Project-Part 2
11/32
From Table 4.6 it is evident that, Dust cleaning machine has the lowest productivity and
highest downtime.
Maintenance cost of each machinery along with percentage analysis
Table 4.7 October 2009 Maintenance cost
This table shows the maintenance cost incurred for each machine during October 2009.
Table 4.7 shows that 50% of the total maintenance cost has been incurred for Grinding
machine during October 2009.
Figure 4.1 Maintenance Cost incurred during October 2009:
Machinery Cost (Rs) %
Bias Cutting 405 1.34
Building 1 1841 6.10
Building 2 4386 14.53
Building 3 2829 9.37Pot curing 3020 10.00
Stripping 648 2.15
Strip cutting 703 2.33
Grinding 15093 50.00
DRO cutting 507 1.68
Dust cleaning 388 1.29
Coding 366 1.21
Total cost 30186 100
-
8/8/2019 Model Project-Part 2
12/32
Figure 4.1 shows the total maintenance cost that has been incurred for machinery during
October 2009. It is evident from the above chart that, Grinding machine has incurred the
highest maintenance cost of 51% during October 2009.
Table 4.8 November 2009 Maintenance cost
This table shows the maintenance cost incurred for each machine during November 2009.
MachineryCost
(Rs)%
Bias Cutting 1624 1.92Building 1 8006 9.48
Building 2 5523 6.54
Building 3 7105 8.42
Pot curing 8232 9.75
Stripping 2367 2.80
Strip cutting 3694 4.38
Grinding 42109 49.88
DRO cutting 2108 2.50
Dust cleaning 1791 2.12
Coding 1867 2.21
Total cost 84426 100
Table 4.8 shows that 49.88% of the total maintenance cost has been incurred for Grinding
machine during November 2009.
Figure 4.2 Maintenance Cost incurred during November 2009
Maintenance Cost
1% 6%15%
9%
10%
2%
2%
51%
2%
1%
1%
Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
-
8/8/2019 Model Project-Part 2
13/32
Maintenance cost
2% 9% 7%
8%
10%
3%
4%
51%
2%
2%
2%
Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
Figure 4.2 shows the total maintenance cost that has been incurred for machinery duringNovember 2009. It is evident from the above chart that, Grinding machine has incurred
the highest maintenance cost of 51% during November 2009.
Table 4.9 December 2009 Maintenance cost
This table shows the maintenance cost incurred for each machine during December 2009.
Machinery
Cost
(Rs) %Bias Cutting 1798 1.41
Building 1 13210 10.36
Building 2 12065 9.46
Building 3 12977 10.18
Pot curing 12751 10.00
Stripping 3003 2.36
Strip cutting 2135 1.67
Grinding 63692 49.95
DRO cutting 3484 2.73
Dust cleaning 955 0.75
Coding 1436 1.13
TOTAL COST 127506 100
Table 4.9 shows that 49.95% of the total maintenance cost has been incurred for Grinding
machine in December 2009.
Figure 4.3 Maintenance Cost incurred during December 2009
-
8/8/2019 Model Project-Part 2
14/32
Figure 4.3 shows the total maintenance cost that has been incurred for machinery during
December 2009. It is evident from the above chart that, Grinding machine has incurred
the highest maintenance cost of 51% during December 2009.
Table 4.10 Computation of downtime for October 2009
Machinery
Machine
hoursavailable
Actual
hoursutilized
Downtime
Bias Cutting 504 489.33 14.67
Building 1 504 469.50 34.50
Building 2 504 460.75 43.25
Building 3 504 452.60 51.40
Pot curing 504 443.52 60.48
Stripping 504 501.40 2.60
Strip cutting 504 502.42 1.58
Grinding 504 425.83 78.17DRO cutting 504 501.31 2.69
Dust cleaning 504 409.99 94.01
Coding 504 492.64 11.36
Maintenance cost
1% 10%9%
10%
10%
2%
2%
51%
3%
1%
1%
Bias cutting
Building 1
Building 2Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
-
8/8/2019 Model Project-Part 2
15/32
Downtime of each machine is the difference between machine hours available and the
actual hours utilized. From Table 4.10, it is evident that Dust cleaning machine suffers
from the highest downtime and Grinding machine stands next.
Table 4.11 Computation of downtime for November 2009
MachineryMachine
hours
available
Actualhours
utilized
Downtime
Bias Cutting 546 521.33 24.67
Building 1 546 499.32 46.68
Building 2 546 511.45 34.55
Building 3 546 479.81 66.19
Pot curing 546 500.74 45.26
Stripping 546 543.68 2.32
Strip cutting 546 545.67 0.33Grinding 546 425.49 120.51
DRO cutting 546 545.33 0.67
Dust cleaning 546 501.62 44.38
Coding 546 482.90 63.10
-
8/8/2019 Model Project-Part 2
16/32
Downtime of each machine is the difference between machine hours available and the
actual hours utilized. From Table 4.11 it is evident that, Grinding machine suffers from
the highest downtime and Building machine 3 has the second highest downtime.
Table 4.12 Computation of downtime for December 2009
Machinery
Machine
hours
available
Actual
hours
utilized
Downtime
Bias Cutting 546 532.61 13.39
Building 1 546 512.33 33.67
Building 2 546 520.4 25.60
Building 3 546 525.67 20.33
Pot curing 546 499.09 46.91
Stripping 546 543.08 2.92Strip cutting 546 539.75 6.25
Grinding 546 470.51 75.49
DRO cutting 546 545.42 0.58
Dust cleaning 546 455.54 90.46
Coding 546 462.36 83.64
-
8/8/2019 Model Project-Part 2
17/32
Downtime of each machine is the difference between machine hours available and the
actual hours utilized. From Table 4.12 it is evident that, Dust cleaning machine suffers
from the highest downtime and Coding machine stands next.
Table 4.13 Loss of production (in units) due to under utilization for October 2009
Machinery DowntimeProductivit
y (%)
Loss of
production
Contributionto total loss
(%)
Bias cutting 14.67 96.57 1417 4.10
Building 1 34.50 92.50 3191 9.24
Building 2 43.25 93.98 4065 11.77
Building 3 51.40 92.87 4774 13.82
Pot curing 60.48 93.06 5628 16.30
Stripping 2.60 103.43 269 0.78
Strip cutting 1.58 111.43 176 0.51
Grinding 78.17 87.61 6848 19.83
DRO cutting 2.69 107.34 289 0.84
Dust cleaning 94.01 72.89 6852 19.84
Coding 11.36 90.00 1022 2.96
The loss of production is computed as follows:
-
8/8/2019 Model Project-Part 2
18/32
Loss of production (in units) = Downtime * Productivity
The contribution to total loss refers to the contribution of loss of each machine in %.
From Table 4.13 it is evident that, Grinding machine and Dust cleaning machine
contributes the highest loss in production.
Figure 4.4 Loss of production from each machine during October 2009
Loss of Productio
0
2000
4000
6000
8000
loss of production
Machine
Units
lost
Bias cutting
Building 1
Building 2
Building 3
Pot curing
StrippingStrip cutting
Grinding
DRO cutting
Dust cleaning
Coding
From Figure 4.4 it is evident that, Grinding machine and Dust cleaning machine have the
highest loss of production during October 2009.
Figure 4.5 Contribution to Total Loss for October 2009
-
8/8/2019 Model Project-Part 2
19/32
Contribution to Total Loss
4%9%
12%
14%
16%1%1%
19%
1%
20%
3%Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
From Figure 4.5 it is evident that, Grinding machine and Dust cleaning machine
contribute maximum to the total loss during October 2009.
Table 4.14 Loss of production (in units) due to under utilization for November 2009
Machinery DowntimeProductivit
y (%)
Loss of
production
Contribution
to total loss
(%)
Bias cutting 24.67 93.33 2302 6.02
Building 1 46.68 92.28 4308 11.26
Building 2 34.55 90.94 3142 8.21
Building 3 66.19 84.74 5609 14.66
Pot curing 45.26 89.62 4056 10.60
Stripping 2.32 111.43 259 0.68
Strip cutting 0.33 111.43 37 0.10
Grinding 120.51 73.52 8860 23.16
DRO cutting 0.67 112.50 75 0.20
-
8/8/2019 Model Project-Part 2
20/32
Dust cleaning 44.38 88.59 3932 10.28
Coding 63.10 90.00 5679 14.84
The loss of production is computed as follows:
Loss of production (in units) = Downtime * Productivity
The contribution to total loss refers to the contribution of loss of each machine in %.
From Table 4.14 it is evident that, Grinding machine contributes the highest loss in
production.
Figure 4.6 Loss of production from each machine during November 2009
Loss of production
0
2000
4000
6000
8000
10000
loss of production
Machine
Units
lost
Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
From Figure 4.6 it is evident that, Grinding machine has the highest loss of production
during November 2009.
Figure 4.7 Contribution to Total Loss for November 2009
-
8/8/2019 Model Project-Part 2
21/32
Contribution to Total Loss
6%
11%
8%
15%
11%1%0%
23%
0%
10%
15%
Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
From Figure 4.7 it is evident that, Grinding machine contributes maximum to the total
loss during November 2009.
Table 4.15 Loss of production (in units) due to under utilization for December 2009
Machinery DowntimeProductivit
y (%)
Loss of
production
Contribution
to total loss
(%)
Bias cutting 13.39 98.29 1316 3.72
Building 1 33.67 92.47 3113 8.80
Building 2 25.60 94.87 2429 6.86
Building 3 20.33 97.56 1983 5.61
Pot curing 46.91 94.72 4443 12.56
Stripping 2.92 107.14 313 0.88
Strip cutting 6.25 107.14 670 1.89
Grinding 75.49 87.37 6596 18.64
DRO cutting 0.58 108.17 63 0.18
Dust cleaning 90.46 79.78 7217 20.40
-
8/8/2019 Model Project-Part 2
22/32
Coding 83.64 86.54 7238 20.46
The loss of production is computed as follows:
Loss of production (in units) = Downtime * Productivity
The contribution to total loss refers to the contribution of loss of each machine in %.
From Table 4.15 it is evident that, Dust cleaning machine and Coding machine
contributes the highest loss in production.
Figure 4.8 Loss of production from each machine during December 2009
Loss of Production
0
2000
4000
6000
8000
loss of production
Machine
Units
lost
Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
From Figure 4.8 it is evident that, Dust cleaning machine and Coding machine have the
highest loss of production during December 2009.
Figure 4.9 Contribution to Total Loss for December 2009
-
8/8/2019 Model Project-Part 2
23/32
Contribution to Total Los
4%9%
7%
6%
13%
1%2%19%
0%
19%
20%
Bias cutting
Building 1
Building 2
Building 3
Pot curing
Stripping
Strip cutting
Grinding
DRO cutting
Dust cleaning
Coding
From Figure 4.9 it is evident that, Dust cleaning machine and Coding machine contribute
maximum to the total loss during December 2009.
Table 4.16 Correlation between Maintenance cost and Loss in production for
October 2009
Machinery Cost
Loss of
production
Bias cutting 405 1417
Building 1 1841 3191
Building 2 4386 4065
Building 3 2829 4774
Pot curing 3020 5628
Stripping 648 269
Strip cutting 703 176
-
8/8/2019 Model Project-Part 2
24/32
Grinding
1509
3 6848
DRO cutting 507 289
Dust cleaning 388 6852
Coding 366 1022
The correlation coefficient between Maintenance cost incurred during October 2009 and
the Loss of Production is 0.58599. This denotes the strength of relationship between the
two variables is strong.
Table 4.17 Correlation between Maintenance cost and Loss in production for
November 2009
Machinery Cost
Loss ofproduction
Bias cutting 1624 2302.45
Building 1 8006 4307.63
Building 2 5523 3141.98
Building 3 7105 5608.94
Pot curing 8232 4056.20
-
8/8/2019 Model Project-Part 2
25/32
Stripping 2367 258.52
Strip cutting 3694 36.77
Grinding 42109 8859.90
DRO cutting 2108 75.37
Dust cleaning 1791 3931.62
Coding 1867 5679.00
The correlation coefficient between Maintenance cost incurred during November 2009
and the Loss of Production is 0.70799. This denotes the strength of relationship between
the two variables is strong.
Table 4.18 Correlation between Maintenance cost and Loss in production for
December 2009
Machinery Cost
Loss ofproduction
Bias cutting 1798 1316.10
Building 1 13210 3113.46
Building 2 12065 2428.67
Building 3 12977 1983.39
Pot curing 12751 4443.32
-
8/8/2019 Model Project-Part 2
26/32
Stripping 3003 312.85
Strip cutting 2135 669.63
Grinding 63692 6595.56
DRO cutting 3484 62.74
Dust cleaning 955 7216.90
Coding 1436 7238.21
The correlation coefficient between Maintenance cost incurred during December 2009
and the Loss of Production is 0.87231. This denotes the strength of relationship between
the two variables is strong.
-
8/8/2019 Model Project-Part 2
27/32
5.1 Findings
There is consistency in the levels of
productivity of each machine from October 2009 to December 2009.
There is consistency in downtime of each
machine during October 2009 till December 2009.
On an average 50% of the maintenance cost
is incurred for Grinding machine during these months.
Dust cleaning machine and Grinding
machine are prone to breakdown the highest number of times during these three
months.
-
8/8/2019 Model Project-Part 2
28/32
Dust cleaning machine and Grinding
machine contribute to the highest loss of production during two of the three
months.
There exist high positive correlation
between Maintenance cost and Loss of Production consistently during the three
months. This implies, higher the maintenance cost, higher the loss in
production.
5.2 Reasons
Grinding machine and Dust cleaning machine suffer from the productivity
problems when compared to other machines. The reasons are:
Breakdown time for Grinding machine and Dust cleaning machine
are the highest than for other machinery. This makes the maintenance
expensive.
The number of trainees engaged in October 2009 was 36, in
November 2009 were 38 and in December 2009 it was 47. There is clear
evidence that absenteeism and attrition during this period has been high.
The trainees are not provided with formal training for machinery
operation, thus leading to reduced output from every machine, affecting
the productivity considerably.
5.3 Suggestions
The increased expenditure on maintenance will have an impact on the profitability
of Poly-V department. In order to reduce such increased expenditure on
maintenance, the organization can even consider capital budgeting decisions by
investing in new machinery for Grinding and Dust cleaning, as 50% of the total
expenditure is spent for Grinding machine.
-
8/8/2019 Model Project-Part 2
29/32
Standardized Training shall be provided to the trainees to help them acquire
knowledge in operating the machinery in the right manner.
The production in Poly-V department is based on orders. It has only 16 permanent
employees. The production department must take due care that at least one person
operating each machine is a permanent employee and is an experienced person.
This increases the morale of permanent employee as well as helps in increasing
the productivity.
A well trained employee with at least 1 year of operating experience can be
placed in the machinery which faces repeated breakdowns, and on bottleneck
equipments.
Automation of processes for important tasks like Curing (by setting the time for
curing), Grinding (the duration to be grinded), etc., will reduce the possibility of
mishandling of machinery by the trainees, thereby reducing the chances of
breakdown to an extent.
By utilizing the excess labor to replace absentee workers and training them by
adding a production shift during weekends for the purpose of on the job training
can be done.
-
8/8/2019 Model Project-Part 2
30/32
6.1 Conclusion
From the study undertaken at Fenner India Limited, it is evident that:
Excepting Stripping, Strip cutting and DRO cutting machinery, the
productivity levels of machinery are not up to the standard.
-
8/8/2019 Model Project-Part 2
31/32
As Dust cleaning and Grinding machine are contributing the most to loss in
production, capital budgeting decisions regarding the same is recommended
to the organization in order to improve productivity and reducing loss in
production to an extent.
Bibliography:
-
8/8/2019 Model Project-Part 2
32/32
1. Raj. K. Wadhwa, Jimmy Davar and P. Bhaskara Rao, Production management and
inventory control.
2. The ICFAI University Journal of Operations Management, Vol. VII, No.4, 2008.
3. Analyzing machine efficiency, National Public Accountant, The, Dec, 1994 by Cindy
D. Edmonds, Bor Yl Tsay, Wen-Wei Lin
4. www.measureproductivty.com
http://findarticles.com/p/articles/mi_m4325/http://findarticles.com/p/articles/mi_m4325/is_n12_v39/http://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Bor%20Yl%20Tsayhttp://findarticles.com/p/search/?qa=Wen-Wei%20Linhttp://findarticles.com/p/articles/mi_m4325/http://findarticles.com/p/articles/mi_m4325/is_n12_v39/http://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Bor%20Yl%20Tsayhttp://findarticles.com/p/search/?qa=Wen-Wei%20Lin