Model Project-Part 2

download Model Project-Part 2

of 32

Transcript of Model Project-Part 2

  • 8/8/2019 Model Project-Part 2

    1/32

    o Per shift 30 rolls are made and kept in the bias-cutting room which

    is air-conditioned

    3.1.2 Building

    o There are three machines available.

    Activities done are:

    o Fitting the mould in the building machine;

    o Silicon application on mould;

    o Putting next layer Jacket;

    o Cord is rolled above this layer;

    o Rubber sheet is rolled in required numbers as per the width

    required for a specification.

    o Mould of different diameter is used as per the requirement.

    3.1.3 Vulcanizing (or Pot Curing)

    o There are three machines available.

    o It follows differential pressure curing method.

    o Mould should be kept for 30 minutes inside the pot.

    o Defect in this process may be that, the operator will take the mould

    before 30 minutes itself.

    3.1.4 Cooling

    o Tank of water at a particular cool temperature is maintained.

    o Mould is immersed inside this water for cooling for ten mins.

    o Process starting from building stage up to the present stage must be

    completed within a day so that the rubber quality is maintained.

    o Defect in this process is that, the operator may take the mould

    before the stipulated ten minutes period.

    3.1.5 Stripping

    o A single machine is available.

    o Rubber and the mould are separated at this process using a machine.

    3.1.6 Strip/Square Cutting

    o A single machine is available.

  • 8/8/2019 Model Project-Part 2

    2/32

    o Cuts the rubber which looks like hollow cylinder into belts of

    different sizes as per the requirement.

    3.1.7 Grinding

    o There are six machines available.

    o Two machines are imported from China. The belts are grinded a

    single time in these machines, whereas in the rest four machines the

    grinding is done in two machines for neat finish. i.e., once the grooves

    are made in one machine as rough finish and final touch is done by

    another machine.

    o Grooves are created at this process.

    o Specification of the belt varies as per the diameter and the no. of

    grooves.

    3.1.8 Single-belt cutting

    o A single machine is available.

    o Same mechanism as Strip cutting is applied here.

    o Difference is that, in strip cutting, for conveniences of grinding the

    belt are cut in twos or threes.

    o Here, the belts are cut into individual pieces. [E.g.: if 4 groove

    belts are required, then it will be cut into 24 groove belts in the strip-

    cutting process, which will be comfortable in grinding instead of 6*4

    belts.]

    o Final step is done by the single-belt cutting machine.

    3.1.9 Dust-cleaning machine

    o A single machine is available.

    o It cleans the dust in the belt completely.

    3.1.10 Visual inspection

    o Three staff does the inspection work manually.

    o They will visually see for flaws in the belt and will reject if they

    find any.

    3.1.11 Coding

  • 8/8/2019 Model Project-Part 2

    3/32

    o A single machine is available.

    o It is similar to inspection, but performed with a machine.

    o It checks the length of each belt with respect to the specification.

    3.1.12 Taken to finished goods warehouse for dispatch to customers

    oThe finished products after the production process will be transferred to

    the finished goods department for dispatching to the customers.

  • 8/8/2019 Model Project-Part 2

    4/32

  • 8/8/2019 Model Project-Part 2

    5/32

    4 Analysis & interpretation

    The following section analyses the data collected through secondary sources in the form

    of tables and provides interpretations for the same.

    Table 4.1 Standards Vs Actuals for the month of October 2009

    Machinery

    Machine

    hours

    available

    Rated

    production

    (in units)

    Actual

    hours

    utilized

    Actual

    production

    (in units)

    Bias Cutting 504 2160 489.33 2086

    Building 1 504 2880 469.50 2664

    Building 2 504 2160 460.75 2030

    Building 3 504 2160 452.60 2006Pot curing 504 7200 443.52 6700

    Stripping 504 5040 501.40 5213

    Strip cutting 504 5040 502.42 5616

    Grinding 504 100800 425.83 88315

    DRO cutting 504 115200 501.31 123651

    Dust cleaning 504 96000 409.99 69975

    Coding 504 120000 492.64 108000

    Table 4.1 shows the comparison between the machine hours available and actual hours

    utilized and the rated production from each machine Vs actual production for the period

    of October 2009.

    Available machine hours are computed as follows:

    No. of working days in October 2009 = 24

    Time available for production per day = 21 hours

    Time available for production in Oct 2009 = 21 hours*24 days = 504 hours

    Actual hours utilized in each machine is computed by deducting the breakdown time of

    each machine.

  • 8/8/2019 Model Project-Part 2

    6/32

    Table 4.2 Productivity during October 2009

    MachineryProductivity

    %

    Actual

    Hours %

    Bias cutting 96.57 97.09

    Building 1 92.50 93.15

    Building 2 93.98 91.42

    Building 3 92.87 89.80

    Pot curing 93.06 88.00

    Stripping 103.43 99.48

    Strip cutting 111.43 99.69Grinding 87.61 84.49

    DRO cutting 107.34 99.47

    Dust cleaning 72.89 81.35

    Coding 90.00 97.75

    Computation of productivity for Table 4.2

    Productivity (in terms of output) = Actual Production * 100

    Rated Production

    Actual Hours % = Actual hours utilized * 100

    Available time

    From Table 4.2 it is evident that, Dust cleaning machine has the lowest productivity and

    highest downtime.

  • 8/8/2019 Model Project-Part 2

    7/32

    Table 4.3 Standards Vs Actuals for the month of November 2009

    Table 4.3 shows the comparison between the machine hours available and actual hours

    utilized and the rated production from each machine Vs actual production for the period

    of November 2009.

    Machinery

    Machine

    hours

    available

    Rated

    production

    (in units)

    Actual

    hours

    utilized

    Actual

    production

    (in units)

    Bias Cutting 546 2340 521.33 2184

    Building 1 546 3120 499.32 2879

    Building 2 546 2340 511.45 2128

    Building 3 546 2340 479.81 1983

    Pot curing 546 7800 500.74 6990

    Stripping 546 5460 543.68 6084

    Strip cutting 546 5460 545.67 6084

    Grinding 546 109200 425.49 80286

    DRO cutting 546 124800 545.33 140400

    Dust cleaning 546 104000 501.62 92134

    Coding 546 130000 482.9 117000

  • 8/8/2019 Model Project-Part 2

    8/32

    Available machine hours are computed as follows:

    No. of working days in November 2009 = 26

    Standard time available for production per day = 21 hours

    Standard time available for production in Nov 2009 = 21 hours*26 days = 546 hours

    Actual time taken in each machine is computed by deducting the breakdown time of each

    machine.

    Table 4.4 Productivity during November 2009

    MachineryProductivit

    y %

    Actual

    Hours %

    Bias cutting 93.33 95.48

    Building 1 92.28 91.45Building 2 90.94 93.67

    Building 3 84.74 87.88

    Pot curing 89.62 91.71

    Stripping 111.43 99.58

    Strip cutting 111.43 99.94

    Grinding 73.52 77.93

    DRO cutting 112.50 99.88

    Dust cleaning 88.59 91.87

    Coding 90.00 88.44

    Computation of productivity for Table 4.4

    Productivity (in terms of output) = Actual Production * 100

    Rated Production

    Actual Hours % = Actual hours utilized * 100

    Available time

  • 8/8/2019 Model Project-Part 2

    9/32

    From Table 4.4 it is evident that, Grinding machine has the lowest productivity and

    highest downtime.

    Table 4.5 Standards Vs Actuals for the month of December 2009

    Machinery

    Machine

    hours

    available

    Rated

    production

    (in units)

    Actual

    hours

    utilized

    Actual

    production

    (in units)

    Bias Cutting 546 2340 532.61 2300

    Building 1 546 3120 512.33 2885

    Building 2 546 2340 520.40 2220Building 3 546 2340 525.67 2283

    Pot curing 546 7800 499.09 7388

    Stripping 546 5460 543.08 5850

    Strip cutting 546 5460 539.75 5850

    Grinding 546 109200 470.51 95413

    DRO cutting 546 124800 545.42 135000

    Dust cleaning 546 104000 455.54 82976

    Coding 546 130000 462.36 112500

    Table 4.5 shows the comparison between the machine hours available and actual hours

    utilized and the rated production from each machine Vs actual production for the period

    of December 2009.

    Available machine hours are computed as follows:

    No. of working days in December 2009 = 26

  • 8/8/2019 Model Project-Part 2

    10/32

    Standard time available for production per day = 21 hours

    Standard time available for production in Dec 2009 = 21 hours*26 days = 546 hours

    Actual time taken in each machine is computed by deducting the breakdown time of each

    machine.

    Table 4.6 Productivity during December 2009

    MachineryProductivity %

    (output)

    Actual

    Hours %

    Bias cutting 98.29 97.55

    Building 1 92.47 93.83Building 2 94.87 95.31

    Building 3 97.56 96.28

    Pot curing 94.72 91.41

    Stripping 107.14 99.47

    Strip cutting 107.14 98.86

    Grinding 87.37 86.17

    DRO cutting 108.17 99.89

    Dust cleaning 79.78 83.43

    Coding 86.54 84.68

    Computation of productivity for Table 4.6

    Productivity (in terms of output) = Actual Production * 100

    Rated Production

    Actual Hours % = Actual hours utilized * 100

    Available time

  • 8/8/2019 Model Project-Part 2

    11/32

    From Table 4.6 it is evident that, Dust cleaning machine has the lowest productivity and

    highest downtime.

    Maintenance cost of each machinery along with percentage analysis

    Table 4.7 October 2009 Maintenance cost

    This table shows the maintenance cost incurred for each machine during October 2009.

    Table 4.7 shows that 50% of the total maintenance cost has been incurred for Grinding

    machine during October 2009.

    Figure 4.1 Maintenance Cost incurred during October 2009:

    Machinery Cost (Rs) %

    Bias Cutting 405 1.34

    Building 1 1841 6.10

    Building 2 4386 14.53

    Building 3 2829 9.37Pot curing 3020 10.00

    Stripping 648 2.15

    Strip cutting 703 2.33

    Grinding 15093 50.00

    DRO cutting 507 1.68

    Dust cleaning 388 1.29

    Coding 366 1.21

    Total cost 30186 100

  • 8/8/2019 Model Project-Part 2

    12/32

    Figure 4.1 shows the total maintenance cost that has been incurred for machinery during

    October 2009. It is evident from the above chart that, Grinding machine has incurred the

    highest maintenance cost of 51% during October 2009.

    Table 4.8 November 2009 Maintenance cost

    This table shows the maintenance cost incurred for each machine during November 2009.

    MachineryCost

    (Rs)%

    Bias Cutting 1624 1.92Building 1 8006 9.48

    Building 2 5523 6.54

    Building 3 7105 8.42

    Pot curing 8232 9.75

    Stripping 2367 2.80

    Strip cutting 3694 4.38

    Grinding 42109 49.88

    DRO cutting 2108 2.50

    Dust cleaning 1791 2.12

    Coding 1867 2.21

    Total cost 84426 100

    Table 4.8 shows that 49.88% of the total maintenance cost has been incurred for Grinding

    machine during November 2009.

    Figure 4.2 Maintenance Cost incurred during November 2009

    Maintenance Cost

    1% 6%15%

    9%

    10%

    2%

    2%

    51%

    2%

    1%

    1%

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

  • 8/8/2019 Model Project-Part 2

    13/32

    Maintenance cost

    2% 9% 7%

    8%

    10%

    3%

    4%

    51%

    2%

    2%

    2%

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    Figure 4.2 shows the total maintenance cost that has been incurred for machinery duringNovember 2009. It is evident from the above chart that, Grinding machine has incurred

    the highest maintenance cost of 51% during November 2009.

    Table 4.9 December 2009 Maintenance cost

    This table shows the maintenance cost incurred for each machine during December 2009.

    Machinery

    Cost

    (Rs) %Bias Cutting 1798 1.41

    Building 1 13210 10.36

    Building 2 12065 9.46

    Building 3 12977 10.18

    Pot curing 12751 10.00

    Stripping 3003 2.36

    Strip cutting 2135 1.67

    Grinding 63692 49.95

    DRO cutting 3484 2.73

    Dust cleaning 955 0.75

    Coding 1436 1.13

    TOTAL COST 127506 100

    Table 4.9 shows that 49.95% of the total maintenance cost has been incurred for Grinding

    machine in December 2009.

    Figure 4.3 Maintenance Cost incurred during December 2009

  • 8/8/2019 Model Project-Part 2

    14/32

    Figure 4.3 shows the total maintenance cost that has been incurred for machinery during

    December 2009. It is evident from the above chart that, Grinding machine has incurred

    the highest maintenance cost of 51% during December 2009.

    Table 4.10 Computation of downtime for October 2009

    Machinery

    Machine

    hoursavailable

    Actual

    hoursutilized

    Downtime

    Bias Cutting 504 489.33 14.67

    Building 1 504 469.50 34.50

    Building 2 504 460.75 43.25

    Building 3 504 452.60 51.40

    Pot curing 504 443.52 60.48

    Stripping 504 501.40 2.60

    Strip cutting 504 502.42 1.58

    Grinding 504 425.83 78.17DRO cutting 504 501.31 2.69

    Dust cleaning 504 409.99 94.01

    Coding 504 492.64 11.36

    Maintenance cost

    1% 10%9%

    10%

    10%

    2%

    2%

    51%

    3%

    1%

    1%

    Bias cutting

    Building 1

    Building 2Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

  • 8/8/2019 Model Project-Part 2

    15/32

    Downtime of each machine is the difference between machine hours available and the

    actual hours utilized. From Table 4.10, it is evident that Dust cleaning machine suffers

    from the highest downtime and Grinding machine stands next.

    Table 4.11 Computation of downtime for November 2009

    MachineryMachine

    hours

    available

    Actualhours

    utilized

    Downtime

    Bias Cutting 546 521.33 24.67

    Building 1 546 499.32 46.68

    Building 2 546 511.45 34.55

    Building 3 546 479.81 66.19

    Pot curing 546 500.74 45.26

    Stripping 546 543.68 2.32

    Strip cutting 546 545.67 0.33Grinding 546 425.49 120.51

    DRO cutting 546 545.33 0.67

    Dust cleaning 546 501.62 44.38

    Coding 546 482.90 63.10

  • 8/8/2019 Model Project-Part 2

    16/32

    Downtime of each machine is the difference between machine hours available and the

    actual hours utilized. From Table 4.11 it is evident that, Grinding machine suffers from

    the highest downtime and Building machine 3 has the second highest downtime.

    Table 4.12 Computation of downtime for December 2009

    Machinery

    Machine

    hours

    available

    Actual

    hours

    utilized

    Downtime

    Bias Cutting 546 532.61 13.39

    Building 1 546 512.33 33.67

    Building 2 546 520.4 25.60

    Building 3 546 525.67 20.33

    Pot curing 546 499.09 46.91

    Stripping 546 543.08 2.92Strip cutting 546 539.75 6.25

    Grinding 546 470.51 75.49

    DRO cutting 546 545.42 0.58

    Dust cleaning 546 455.54 90.46

    Coding 546 462.36 83.64

  • 8/8/2019 Model Project-Part 2

    17/32

    Downtime of each machine is the difference between machine hours available and the

    actual hours utilized. From Table 4.12 it is evident that, Dust cleaning machine suffers

    from the highest downtime and Coding machine stands next.

    Table 4.13 Loss of production (in units) due to under utilization for October 2009

    Machinery DowntimeProductivit

    y (%)

    Loss of

    production

    Contributionto total loss

    (%)

    Bias cutting 14.67 96.57 1417 4.10

    Building 1 34.50 92.50 3191 9.24

    Building 2 43.25 93.98 4065 11.77

    Building 3 51.40 92.87 4774 13.82

    Pot curing 60.48 93.06 5628 16.30

    Stripping 2.60 103.43 269 0.78

    Strip cutting 1.58 111.43 176 0.51

    Grinding 78.17 87.61 6848 19.83

    DRO cutting 2.69 107.34 289 0.84

    Dust cleaning 94.01 72.89 6852 19.84

    Coding 11.36 90.00 1022 2.96

    The loss of production is computed as follows:

  • 8/8/2019 Model Project-Part 2

    18/32

    Loss of production (in units) = Downtime * Productivity

    The contribution to total loss refers to the contribution of loss of each machine in %.

    From Table 4.13 it is evident that, Grinding machine and Dust cleaning machine

    contributes the highest loss in production.

    Figure 4.4 Loss of production from each machine during October 2009

    Loss of Productio

    0

    2000

    4000

    6000

    8000

    loss of production

    Machine

    Units

    lost

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    StrippingStrip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    From Figure 4.4 it is evident that, Grinding machine and Dust cleaning machine have the

    highest loss of production during October 2009.

    Figure 4.5 Contribution to Total Loss for October 2009

  • 8/8/2019 Model Project-Part 2

    19/32

    Contribution to Total Loss

    4%9%

    12%

    14%

    16%1%1%

    19%

    1%

    20%

    3%Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    From Figure 4.5 it is evident that, Grinding machine and Dust cleaning machine

    contribute maximum to the total loss during October 2009.

    Table 4.14 Loss of production (in units) due to under utilization for November 2009

    Machinery DowntimeProductivit

    y (%)

    Loss of

    production

    Contribution

    to total loss

    (%)

    Bias cutting 24.67 93.33 2302 6.02

    Building 1 46.68 92.28 4308 11.26

    Building 2 34.55 90.94 3142 8.21

    Building 3 66.19 84.74 5609 14.66

    Pot curing 45.26 89.62 4056 10.60

    Stripping 2.32 111.43 259 0.68

    Strip cutting 0.33 111.43 37 0.10

    Grinding 120.51 73.52 8860 23.16

    DRO cutting 0.67 112.50 75 0.20

  • 8/8/2019 Model Project-Part 2

    20/32

    Dust cleaning 44.38 88.59 3932 10.28

    Coding 63.10 90.00 5679 14.84

    The loss of production is computed as follows:

    Loss of production (in units) = Downtime * Productivity

    The contribution to total loss refers to the contribution of loss of each machine in %.

    From Table 4.14 it is evident that, Grinding machine contributes the highest loss in

    production.

    Figure 4.6 Loss of production from each machine during November 2009

    Loss of production

    0

    2000

    4000

    6000

    8000

    10000

    loss of production

    Machine

    Units

    lost

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    From Figure 4.6 it is evident that, Grinding machine has the highest loss of production

    during November 2009.

    Figure 4.7 Contribution to Total Loss for November 2009

  • 8/8/2019 Model Project-Part 2

    21/32

    Contribution to Total Loss

    6%

    11%

    8%

    15%

    11%1%0%

    23%

    0%

    10%

    15%

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    From Figure 4.7 it is evident that, Grinding machine contributes maximum to the total

    loss during November 2009.

    Table 4.15 Loss of production (in units) due to under utilization for December 2009

    Machinery DowntimeProductivit

    y (%)

    Loss of

    production

    Contribution

    to total loss

    (%)

    Bias cutting 13.39 98.29 1316 3.72

    Building 1 33.67 92.47 3113 8.80

    Building 2 25.60 94.87 2429 6.86

    Building 3 20.33 97.56 1983 5.61

    Pot curing 46.91 94.72 4443 12.56

    Stripping 2.92 107.14 313 0.88

    Strip cutting 6.25 107.14 670 1.89

    Grinding 75.49 87.37 6596 18.64

    DRO cutting 0.58 108.17 63 0.18

    Dust cleaning 90.46 79.78 7217 20.40

  • 8/8/2019 Model Project-Part 2

    22/32

    Coding 83.64 86.54 7238 20.46

    The loss of production is computed as follows:

    Loss of production (in units) = Downtime * Productivity

    The contribution to total loss refers to the contribution of loss of each machine in %.

    From Table 4.15 it is evident that, Dust cleaning machine and Coding machine

    contributes the highest loss in production.

    Figure 4.8 Loss of production from each machine during December 2009

    Loss of Production

    0

    2000

    4000

    6000

    8000

    loss of production

    Machine

    Units

    lost

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    From Figure 4.8 it is evident that, Dust cleaning machine and Coding machine have the

    highest loss of production during December 2009.

    Figure 4.9 Contribution to Total Loss for December 2009

  • 8/8/2019 Model Project-Part 2

    23/32

    Contribution to Total Los

    4%9%

    7%

    6%

    13%

    1%2%19%

    0%

    19%

    20%

    Bias cutting

    Building 1

    Building 2

    Building 3

    Pot curing

    Stripping

    Strip cutting

    Grinding

    DRO cutting

    Dust cleaning

    Coding

    From Figure 4.9 it is evident that, Dust cleaning machine and Coding machine contribute

    maximum to the total loss during December 2009.

    Table 4.16 Correlation between Maintenance cost and Loss in production for

    October 2009

    Machinery Cost

    Loss of

    production

    Bias cutting 405 1417

    Building 1 1841 3191

    Building 2 4386 4065

    Building 3 2829 4774

    Pot curing 3020 5628

    Stripping 648 269

    Strip cutting 703 176

  • 8/8/2019 Model Project-Part 2

    24/32

    Grinding

    1509

    3 6848

    DRO cutting 507 289

    Dust cleaning 388 6852

    Coding 366 1022

    The correlation coefficient between Maintenance cost incurred during October 2009 and

    the Loss of Production is 0.58599. This denotes the strength of relationship between the

    two variables is strong.

    Table 4.17 Correlation between Maintenance cost and Loss in production for

    November 2009

    Machinery Cost

    Loss ofproduction

    Bias cutting 1624 2302.45

    Building 1 8006 4307.63

    Building 2 5523 3141.98

    Building 3 7105 5608.94

    Pot curing 8232 4056.20

  • 8/8/2019 Model Project-Part 2

    25/32

    Stripping 2367 258.52

    Strip cutting 3694 36.77

    Grinding 42109 8859.90

    DRO cutting 2108 75.37

    Dust cleaning 1791 3931.62

    Coding 1867 5679.00

    The correlation coefficient between Maintenance cost incurred during November 2009

    and the Loss of Production is 0.70799. This denotes the strength of relationship between

    the two variables is strong.

    Table 4.18 Correlation between Maintenance cost and Loss in production for

    December 2009

    Machinery Cost

    Loss ofproduction

    Bias cutting 1798 1316.10

    Building 1 13210 3113.46

    Building 2 12065 2428.67

    Building 3 12977 1983.39

    Pot curing 12751 4443.32

  • 8/8/2019 Model Project-Part 2

    26/32

    Stripping 3003 312.85

    Strip cutting 2135 669.63

    Grinding 63692 6595.56

    DRO cutting 3484 62.74

    Dust cleaning 955 7216.90

    Coding 1436 7238.21

    The correlation coefficient between Maintenance cost incurred during December 2009

    and the Loss of Production is 0.87231. This denotes the strength of relationship between

    the two variables is strong.

  • 8/8/2019 Model Project-Part 2

    27/32

    5.1 Findings

    There is consistency in the levels of

    productivity of each machine from October 2009 to December 2009.

    There is consistency in downtime of each

    machine during October 2009 till December 2009.

    On an average 50% of the maintenance cost

    is incurred for Grinding machine during these months.

    Dust cleaning machine and Grinding

    machine are prone to breakdown the highest number of times during these three

    months.

  • 8/8/2019 Model Project-Part 2

    28/32

    Dust cleaning machine and Grinding

    machine contribute to the highest loss of production during two of the three

    months.

    There exist high positive correlation

    between Maintenance cost and Loss of Production consistently during the three

    months. This implies, higher the maintenance cost, higher the loss in

    production.

    5.2 Reasons

    Grinding machine and Dust cleaning machine suffer from the productivity

    problems when compared to other machines. The reasons are:

    Breakdown time for Grinding machine and Dust cleaning machine

    are the highest than for other machinery. This makes the maintenance

    expensive.

    The number of trainees engaged in October 2009 was 36, in

    November 2009 were 38 and in December 2009 it was 47. There is clear

    evidence that absenteeism and attrition during this period has been high.

    The trainees are not provided with formal training for machinery

    operation, thus leading to reduced output from every machine, affecting

    the productivity considerably.

    5.3 Suggestions

    The increased expenditure on maintenance will have an impact on the profitability

    of Poly-V department. In order to reduce such increased expenditure on

    maintenance, the organization can even consider capital budgeting decisions by

    investing in new machinery for Grinding and Dust cleaning, as 50% of the total

    expenditure is spent for Grinding machine.

  • 8/8/2019 Model Project-Part 2

    29/32

    Standardized Training shall be provided to the trainees to help them acquire

    knowledge in operating the machinery in the right manner.

    The production in Poly-V department is based on orders. It has only 16 permanent

    employees. The production department must take due care that at least one person

    operating each machine is a permanent employee and is an experienced person.

    This increases the morale of permanent employee as well as helps in increasing

    the productivity.

    A well trained employee with at least 1 year of operating experience can be

    placed in the machinery which faces repeated breakdowns, and on bottleneck

    equipments.

    Automation of processes for important tasks like Curing (by setting the time for

    curing), Grinding (the duration to be grinded), etc., will reduce the possibility of

    mishandling of machinery by the trainees, thereby reducing the chances of

    breakdown to an extent.

    By utilizing the excess labor to replace absentee workers and training them by

    adding a production shift during weekends for the purpose of on the job training

    can be done.

  • 8/8/2019 Model Project-Part 2

    30/32

    6.1 Conclusion

    From the study undertaken at Fenner India Limited, it is evident that:

    Excepting Stripping, Strip cutting and DRO cutting machinery, the

    productivity levels of machinery are not up to the standard.

  • 8/8/2019 Model Project-Part 2

    31/32

    As Dust cleaning and Grinding machine are contributing the most to loss in

    production, capital budgeting decisions regarding the same is recommended

    to the organization in order to improve productivity and reducing loss in

    production to an extent.

    Bibliography:

  • 8/8/2019 Model Project-Part 2

    32/32

    1. Raj. K. Wadhwa, Jimmy Davar and P. Bhaskara Rao, Production management and

    inventory control.

    2. The ICFAI University Journal of Operations Management, Vol. VII, No.4, 2008.

    3. Analyzing machine efficiency, National Public Accountant, The, Dec, 1994 by Cindy

    D. Edmonds, Bor Yl Tsay, Wen-Wei Lin

    4. www.measureproductivty.com

    http://findarticles.com/p/articles/mi_m4325/http://findarticles.com/p/articles/mi_m4325/is_n12_v39/http://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Bor%20Yl%20Tsayhttp://findarticles.com/p/search/?qa=Wen-Wei%20Linhttp://findarticles.com/p/articles/mi_m4325/http://findarticles.com/p/articles/mi_m4325/is_n12_v39/http://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Cindy%20D.%20Edmondshttp://findarticles.com/p/search/?qa=Bor%20Yl%20Tsayhttp://findarticles.com/p/search/?qa=Wen-Wei%20Lin