Model Project for replacement of fine aggregate

download Model Project for replacement of fine aggregate

of 72

description

civil

Transcript of Model Project for replacement of fine aggregate

  • ANALYSIS AND DESIGN OF MULTICOMPLEX

    BUILDING AT TIRUNELVELI

    A DESIGN PROJECT REPORT

    Submitted by

    NAME REG . NO

    NAME REG . NO

    NAME REG . NO

    NAME REG . NO

    in partial fulfilment for the award of the degree

    of

    BACHELOR OF ENGINEERING

    IN

    CIVIL ENGINEERING

    XXXXX COLLEGE OF ENGINEERING,

    CHENNAI - 6

    ANNA UNIVERSITY: CHENNAI 6

    ANNA UNIVERSITY: CHENNAI

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • BONAFIDE CERTIFICATE

    Certified that this project report DESIGN OF MULTICOMPLEX

    BUILDING is the bonafide work of NAMES who carried out the project under my supervision.

    SIGNATURE SIGNATURE

    HEAD OF THE DEPARTMENT SUPERVISOR

    Civil Engineering Civil Engineering

    XXXXXXXXXXX XXXXXXXXXXXX

    College of Engineering College of Engineering

    Submitted to the viva voce held at XXXXXXXXXXXXX COLLEGE OF

    ENGINEERING on..............................

    INTERNAL EXAMINER EXTERNAL EXAMINER

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • CONTENTS

    PAGE NO

    1 INTRODUCTION

    1.1 Objectives 1.2 Analysis of framed structure 1.3 Design of structures 1.4 Slab 1.5 Beam 1.6 Column 1.7 Footing

    2 PLAN, ELEVATION AND SECTION

    2.1 Ground floor plan 2.2 First floor plan 2.3 Second floor plan 2.4 Third floor plan 2.5 Fourth floor plan 2.6 Fifth floor plan 2.7 Sixth floor plan 2.8 Seventh floor plan

    3 ANALYSIS OF MULTISTOREY FRAME

    3.1 Frame analysis

    4 DESIGN

    4.1 Design of slab

    4.2 Design of beams

    4.3 Design of column

    4.4 Design of footing

    5 CONCLUSION

    6 REFERENCE

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 19 35 40 54 61 62

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • LIST OF DRAWING

    I. Plan II. Elevation III. Section IV. Slab detailing V. Beam detailing VI. Column detailing VII. Footing detailing

    LIST OF TABLES

    I. Beam maximum bending moments

    II. Beam maximum shear forces

    III. Column maximum axial forces

    IV. Column maximum bending moments

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • ACKNOWLEDGEMENT

    We thank the almighty for his kind guidance all throughout the tenure of this work

    We take this opportunity to express our thanks to our beloved principal

    Dr.S.Joseph Sekhar M.E., Ph.D and our correspondent Rev.Fr.Jesu Marian for

    their co-operative guidance and encouragement.

    We are extremely grateful to our beloved H.O.D, civil Engg, and Dr.S.Carmel Jawahar M.E., Ph.D for his help and encouragement.

    We owe greatest debt of gratitude to our beloved guide Er.J.Sherin Nisha M.E

    for her technical idea for the well completion of this project.

    We sincerely acknowledgement thanks to our entire teaching and non-

    teaching staff members.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • ABSTRACT

    This report discusses on the Design of a Multicomplex building. This project

    mainly includes the analysis and design of the building. The load conditions as

    per code IS456 are assumed. The slab and beams are designed for bending,

    shear and deflection limit.

    The plan, Elevation, Section and Reinforcement retails are drawn in AutoCAD.

    The analysis made in STADD Pro. Designs are made manually by using IS 456:

    2000.

    Design is carried out manually and it is based on IS 456- 2000. And detailing

    was done for the structural elements as per SP 3.

    Concrete grade of M20 and steel HYSD bars of grade Fe415 are used. Safe

    Bearing Capacity of soil is taken as 180KN/m2. Footing is designed as Circular.

    Plan and detailing are enclosed in this report.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • SYMBOLS

    A - Total area

    Ast - Area of tensile reinforcement

    Asc - Area of compression reinforcement

    D - Overall depth of beam or slab

    d - Effective depth of beam or slab

    Leff - Effective span of beam, slab or column

    B.M - Bending moment

    R.M - Resisting moment

    m - Modular ratio

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • fy - Characteristic strength of steel

    V - Shear force

    Z - Modules of section

    cbc - Permissble stress in concrete in bending compression

    st - Permissble stress in tensile steel

    fck - Chracteristic strength of concrete

    B - Breadth of footing

    L - Length of footing

    Pu - Ultimate load

    W - Total load

    v - Normal shear stress

    c - Permissble shear stress

    Ac - Area of concrete

    d - Diameter of steel

    DL - Dead load

    LL - Live load

    WL - Wind load

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 1

    CHAPTER 1

    INTRODUCTION

    1.1. GENERAL Soils having low bearing capacity are found in several parts of the world.

    In Tamilnadu also low bearing capacity soil occur in many parts. The

    basic problems associated with these types of deposits are low shear

    strength and high compressibility. Whenever poor soil conditions are at

    site such as, loose sand, soft clay, highly organic deposit or dumped

    heterogeneous material are encountered the following are the alternatives

    to overcome the problems.

    i. Avoid the site by relocating the proposed structure at a site with

    better soil conditions.

    ii. Adopt a foundation system that recognizes the inadequacies of the

    soil and transfers load to it in a manner that the inadequacies are

    unable to cause any harm to the superstructure

    iii. Adopt a foundation system that by-passes the poor soil and

    transfers the load from the superstructure to better soil located from

    below the poor soil.

    iv. Improve or modify the properties of the soil either by excavating

    the poor quality soil and replacing it with soil having better

    engineering properties or by in-situ treatment without excavation

    these processes are known as ground improvement or ground

    modification.

    Due to growth of population and scarcity of land, construction of

    structures in poor soil is unavoidable.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 2

    1.2. GROUND IMPROVEMENT AND MODIFICATION

    The terms ground improvement and modification refer to the

    improvement or modification to the engineering properties of the soil so

    that soil posses properties that are acceptable to us for the proposed civil

    engineering activity. The improved or modified soil exhibits satisfactory

    performance when foundations, earth retaining structures are constructed

    on within or using the soil.

    The term Ground improvement means a permanent or long term

    improvement and the term Ground modification means a temporary or

    short term modification effected for the construction stage only.

    Improvements in soil behaviour required are listed below.

    i. An increase in the bearing capacity.

    ii. A reduction in the amount of settlement and on the time in which it

    occurs.

    iii. An increase in the capacity to retard seepage.

    iv. Acceleration in the rate at which drainage occurs.

    v. Elimination of the possibility of liquefaction.

    vi. An increase in the suitability of a slope or a vertical cut or an

    underground opening.

    1.3. IMPROVEMEND BY MIXING WITH ADDITIVES There are various methods of modification that are possible to

    achieve improvement in soil properties. Of all the available

    methods, improving the properties by mixing with additives such

    as

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 3

    1.1 OBJECTIVES

    The objectives of project are

    To prepare drawings for the building.

    To analyse and Design a multi-storeyed building of eight storey.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 4

    1.2 ANALYSIS OF FRAMED STRUCTURE

    The method by which multicomplex building frames resist horizontal

    or lateral forces depends on how the structures has be laid down or planned to

    bear these loads.

    1.2.1 METHODS OF ANALYSIS

    Analysis of the whole frame by using STADD Pro.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 5

    1.2.1 a. MAXIMUM BENDING MOMENTS IN BEAMS

    The magnitude of bending moments in beams and columns respectively depend upon their relative rigidity. Generally the beams are made of the same

    dimensions in all the floors, while the dimensions of column vary from storey to

    storey. Columns have smallest dimensions at the top and largest dimensions at

    bottom, due to this the ratio of the rigidity of the beam to that of the column is

    larger in the upper floors than in lower floors. Beam in all floors are made of the

    same dimensions and provided with same amount of steel, only one substitute

    frame may be sufficient when placed in a position in the structure for which the

    B.M is largest.

    1.2.1 b. MAXIMUM BENDING MOMENT IN COLUMNS

    The bending moment in columns increases with increase in their rigidity. Hence they are largest in the lower storeys, and smallest in upper

    storey. The maximum compressive stress in columns is found by combining

    maximum vertical loads with the maximum bending moments.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 6

    1.3. DESIGN OF RCC STRUCTURES

    Reinforced cement concrete members can be designed by one of the following methods.

    a) Working Stress method

    b) Limit state method

    1.3.1 LIMIT STATE DESIGN

    Limit state method of design is based on the plastic theory.

    Partial safety factors are used in this method to determine the design

    loads and design strength of materials from their characteristic values.

    The design aids to IS: 456 published by the Bureau of Indian Standards

    made by the design by limit state method very simple and hence this

    method is being widely used in practice.

    This method gives economical results when compared with the

    conventional working stress method.

    1.3.2. WORKING STRESS METHOD

    This is conventional method adopted in the past in the design of

    R.C structures.

    It is based on the elastic theory in which the materials, concrete and

    steel, are assumed to be stressed well above their elastic limit under

    the load.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 7

    1.4. SLABS

    Slabs are the primary members of a structure, which support the imposed loads directly on them and transfer the same safely to the

    supporting elements such as beams, walls, columns etc.

    A slab is a thin flexural member used in floors and roofs of structures to support the imposed loads.

    CLASSFICATION OF SLAB

    Solid slab

    Hollow slab or voided slab

    Ribbed slabs

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 8

    1.5. BEAM

    A beam has to be generally designed for the actions such as bending moments, shear forces and twisting moments developed

    by the lateral loads.

    The size of a beam is designed considering the maximum B.M in it and generally kept uniform throughout its length.

    IS 456:2000 recommends that minimum grade of concrete should not be less than M20 in R.C works.

    1.5.1. BREADTH OF BEAM

    It shall not exceed the size of the supports. Generally the breadth of a beam is kept as 1/3 to 2/3 of its depth.

    1.5.2. DEPTH OF BEAMS

    The depth of the beam is to be designed to satisfy the strength and stiffness requirement.

    It also satisfy sufficient M.R. and deflection check as recommended in IS456:2000

    For preliminary analysis purpose over all depth of beam may assumed 1/10 to 1/12 of clear span for simply support 1/7 to 1/5

    for continuous and cantilever beam.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 9

    1.6. COLUMN

    Members in compression are called column and struts.

    The term column is reserved for members who transfer loads to the ground. Classification of column, depending slenderness

    a. Short column

    b. Slender column

    a. Short column

    IS 456:2000 classifying rectangular columns as short when ratio of

    the effective length (Le) to the least dimensions less than 12. This

    ratio is called slenderness ratio of the column.

    b. Slender column

    The ratio of Le to the least dimensions is greater than 12 is called

    slender column.

    End conditions Effective length factor

    1. Both end fixed - 0.65L

    2. One end fixed-one end hinged - 0.80L

    3. Both end hinged - 1.00L

    4. One end fixed one end free - 2.00L

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 10

    1.7. FOOTING

    Foundation is the bottom most but the most important component

    of a structure.

    It should be well planned and carefully to ensure the safety and

    stability of the structure.

    Foundation provide for R.C columns are called column base.

    1.7.1. BASIC REQUIREMENT OF FOOTING

    a. It should withstand applied load moments and induced reactions.

    b. Sufficient area should be providing according to soil pressure.

    Footings carry two different loads then it should plan carefully.

    1.7.2. TYPES OF FOOTING

    a. Isolated base/footing

    b. Combined footing

    c. Strap footing

    d. Solid raft footing

    e. Annular raft footing

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 11

    2.1. GROUND FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 12

    2.2. FIRST FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 13

    2.3. SECOND FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 14

    2.4. THIRD FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 15

    2.5. FOURTH FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 16

    2.6. FIFTH FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 17

    2.7. SIXTH FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 18

    2.8. SEVENTH FLOOR PLAN

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 19

    ELEVATION

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 20

    SECTION X-X

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 21

    ANALYSIS OF MULTISTOREY FRAME

    3.1 FRAME ANALYSIS

    STAAD.Pro Report

    To: From:

    Copy to:

    Date: 02/11/2011 12:11:00

    Ref: ca/ Document1

    Job Information

    Engineer Checked Approved

    Name: Date: 23-Oct-11

    Structure Type SPACE FRAME

    Number of Nodes 1674 Highest Node 1676

    Number of Elements 4158 Highest Beam 4158

    Number of Basic Load Cases 4

    Number of Combination Load Cases 10

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 22

    Included in this printout are data for: Included in this printout are results for load cases:

    Type L/C Name

    Combination 5 combination load case 5 Basic Load Cases

    Number Name

    1 seismic load 2 wind load 3 dead load 4 live load

    Combination Load Cases

    Comb. Combination L/C Name Primary Primary L/C Name Factor

    5 combination load case 5 1 seismic load 1.50 dead load 1.50 live load 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 23

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 24

    My 889.644kN-m:1m Mz 889.644kN-m:1m 1 SEISMIC LOAD

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 25

    BEAM Beam Maximum Moments Distances to maxima are given from beam end A.

    Beam Node A Length

    (m) L/C d

    (m) Max My (kN-m)

    d (m)

    Max Mz (kN-m)

    3930 1491 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.979 10.000 425.281

    Max +ve 10.000 -1.615 5.000 -215.180

    3931 1492 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 2.319 10.000 436.108

    Max +ve 10.000 -2.414 5.000 -199.390

    3932 1493 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 0.346 10.000 407.302

    Max +ve 10.000 -0.484 5.000 -200.438

    3933 1494 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.062 10.000 413.841

    Max +ve 10.000 -0.936 5.000 -200.359

    3934 1495 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.461 10.000 409.856

    Max +ve 10.000 -1.350 5.000 -200.002

    3935 1496 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.781 10.000 406.231

    Max +ve 10.000 -1.755 5.000 -200.051

    3936 1497 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.502 10.000 401.913

    Max +ve 10.000 -1.548 5.000 -200.180

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 26

    3937 1498 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.301 0.000 399.014

    Max +ve 10.000 -1.305 5.000 -200.352

    3938 1499 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.429 0.000 403.629

    Max +ve 10.000 -1.627 5.000 -214.118

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 27

    Beam Maximum Shear Forces Distances to maxima are given from beam end A.

    Beam Node A Length

    (m) L/C d

    (m) Max Fz

    (kN) d

    (m) Max Fy

    (kN)

    3930 1491 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 230.857

    Max +ve 0.000 -0.359 10.000 -247.742

    3931 1492 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 231.850

    Max +ve 0.000 -0.473 10.000 -246.749

    3932 1493 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 237.406

    Max +ve 0.000 -0.083 10.000 -241.198

    3933 1494 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 236.109

    Max +ve 0.000 -0.200 10.000 -242.490

    3934 1495 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 236.978

    Max +ve 0.000 -0.281 10.000 -241.621

    3935 1496 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 237.693

    Max +ve 0.000 -0.354 10.000 -240.906

    3936 1497 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 238.530

    Max +ve 0.000 -0.305 10.000 -240.069

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 28

    3937 1498 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 239.523

    Max +ve 0.000 -0.261 10.000 -239.081

    3938 1499 10.000 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 243.199

    Max +ve 0.000 -0.306 10.000 -235.400

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 29

    COLUMN

    Beam Maximum Moments Distances to maxima are given from beam end A .

    Beam Node A Length

    (m) L/C d

    (m) Max My (kN-m)

    d (m)

    Max Mz (kN-m)

    1 1 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 45.798 3.500 187.455

    Max +ve 0.000 -25.159

    3 3 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 39.379 0.000 97.025

    Max +ve 0.000 -21.942 3.500 -4.218

    43 43 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 1.359 0.000 107.504

    Max +ve 0.000 -3.188 3.500 -5.854

    520 189 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 53.052 3.500 168.181

    Max +ve 0.000 -53.491 0.000 -152.967

    522 191 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 35.748 0.000 73.210

    Max +ve 0.000 -46.405 3.500 -39.973

    562 231 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 2.081 0.000 79.087

    Max +ve 0.000 -1.714 3.500 -51.438

    1039 375 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 56.325 3.500 166.002

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 30

    Max +ve 0.000 -54.858 0.000 -169.227

    1041 377 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 27.518 0.000 32.105

    Max +ve 0.000 -24.766 3.500 -31.219

    1081 417 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 1.473 0.000 57.030

    Max +ve 0.000 -0.394 3.500 -59.893

    1225 377 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 27.518 0.000 32.105

    Max +ve 0.000 -24.766 3.500 -31.219

    1559 561 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 59.396 3.500 166.500

    Max +ve 0.000 -58.365 0.000 -177.914

    1561 563 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 32.583 0.000 20.869

    Max +ve 0.000 -28.549 3.500 -32.916

    1601 603 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 0.740 0.000 46.108

    Max +ve 3.500 -58.906

    1745 563 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 32.583 0.000 20.869

    Max +ve 0.000 -28.549 3.500 -32.916

    2079 747 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 61.939 3.500 168.501

    Max +ve 0.000 -60.918 0.000 -186.126

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 31

    2081 749 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 37.176 0.000 14.355

    Max +ve 0.000 -34.141 3.500 -32.551

    2121 789 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 1.547 0.000 36.501

    Max +ve 3.500 -0.418 3.500 -55.096

    2265 749 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 37.176 0.000 14.355

    Max +ve 0.000 -34.141 3.500 -32.551

    2599 933 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 64.558 3.500 174.454

    Max +ve 0.000 -62.687 0.000 -194.580

    2601 935 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 41.438 0.000 7.323

    Max +ve 0.000 -38.002 3.500 -26.356

    2641 975 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 2.644 0.000 24.854

    Max +ve 3.500 -0.398 3.500 -44.675

    2785 935 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 41.438 0.000 7.323

    Max +ve 0.000 -38.002 3.500 -26.356

    3119 1119 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 64.685 3.500 184.871

    Max +ve 0.000 -62.594 0.000 -199.406

    3121 1121 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 47.700 0.000 5.545

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 32

    Max +ve 0.000 -39.571 3.500 -14.102

    3161 1161 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 6.338 0.000 18.375

    Max +ve 3.500 -1.343 3.500 -26.546

    3305 1121 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 47.700 0.000 5.545

    Max +ve 0.000 -39.571 3.500 -14.102

    3639 1305 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 103.950 3.500 340.859

    Max +ve 0.000 -62.252 0.000 -193.960

    3641 1307 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 72.529 0.000 14.721

    Max +ve 0.000 -34.631 3.500 -24.154

    3681 1347 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 0.000 13.873 0.000 30.317

    Max +ve 3.500 -14.354 3.500 -44.532

    3825 1307 3.500 5:COMBINATION LOAD CASE 5

    Max -ve 3.500 72.529 0.000 14.721

    Max +ve 0.000 -34.631 3.500 -24.154

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 33

    Beam Maximum Axial Forces Distances to maxima are given from beam end A.

    Beam Node A Length (m) L/C d

    (m) Max Fx

    (kN)

    1 1 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 4.44E 3

    Max +ve

    3 3 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 7.65E 3

    Max +ve

    43 43 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 7.32E 3

    Max +ve

    520 189 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 3.9E 3

    Max +ve

    522 191 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 6.86E 3

    Max +ve

    562 231 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 6.4E 3

    Max +ve

    1039 375 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 3.35E 3

    Max +ve

    1041 377 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 3.04E 3

    Max +ve

    1081 417 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 5.49E 3

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 34

    Max +ve

    1225 377 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 3.04E 3

    Max +ve

    1559 561 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.79E 3

    Max +ve

    1561 563 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.54E 3

    Max +ve

    1601 603 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 4.57E 3

    Max +ve

    1745 563 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.54E 3

    Max +ve

    2079 747 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.24E 3

    Max +ve

    2081 749 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.04E 3

    Max +ve

    2121 789 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 3.66E 3

    Max +ve

    2265 749 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.04E 3

    Max +ve

    2599 933 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.68E 3

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 35

    Max +ve

    2601 935 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.53E 3

    Max +ve

    2641 975 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 2.75E 3

    Max +ve

    2785 935 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.53E 3

    Max +ve

    3119 1119 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.12E 3

    Max +ve

    3121 1121 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.02E 3

    Max +ve

    3161 1161 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.83E 3

    Max +ve

    3305 1121 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 1.02E 3

    Max +ve

    3639 1305 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 551.286

    Max +ve

    3641 1307 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 507.947

    Max +ve

    3681 1347 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 915.875

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 36

    Max +ve

    3825 1307 3.500 5:COMBINATION LOAD CASE 5 Max -ve 0.000 507.947

    Max +ve

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 37

    DESIGN

    4.1. DESIGN OF SLAB

    DATA:

    SLAB - B C1, C12,C B2

    Size of floor = 5m x 10m

    Materials M20 concrete and Fe415 HYSD bars

    PERMISSIBLE STRESSES

    cbc = 7 N/mm2 (from IS456:2000 table 21)

    st = 230 N/mm2(from table 22)

    For M20 concrete;

    Q = 0.91

    j = 0.90

    m = 13.33

    TYPE OF SLAB

    LY / Lx = 10 / 5 = 2

    Two-way slab

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 38

    DEPTH OF SLAB

    (from IS456:2000 page no.39 cl.24.1)

    Span / overall depth = L/D = 35 x 0.8 = 28

    5000 / 28 = 178 mm

    Adopt Overall depth = 180 mm

    D = 180 mm

    Effective depth, d = D C /2

    Adopt , d = 155 mm

    EFFECTIVE SPAN

    Effective span is the least of;

    (i) Centre to centre of supports = 5 + 0.23 = 5.23m

    (ii) Clear span + effective depth = 5 + 0.155 = 5.155 m

    (iii) Le = 5.155 m

    LOAD CALCULATION

    Self weight = 0.18 x 1 x 25 = 4.5 KN/m2

    Live load = 1.5 KN/m2

    Floor finishes = 0.75 KN/m2

    Total load = 6.75 KN/m2

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 39

    BENDING MOMENT

    Ly/Lx = 10 / 5 = 2

    x = 0.118

    y = 0.029 (from IS456:2000 table 27)

    Mx = x x W x lx2

    = 0.118 x 6.75 x 5.1552

    = 21.13 KN.m

    My = y x W x lx2

    = 0.029 x 6.75 x 5.1552

    = 5.19 KN.m

    CHECK FOR DEPTH

    Effective depth required, de = M/Qb

    = 21.13 x 106 / 0.91 x 1000

    = 152 mm

    Depth provided Depth required

    Hence safe

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 40

    REINFORCEMENT

    Reinforcement in shorter span;

    Ast = Mx / st jd

    = 21.13 x 106 / 230 x 0.9 x 155

    = 658.56 mm2

    Spacing = 1000 x ast / Ast

    = 1000 x (10/2) / 658.56

    = 119 mm

    Adopt 10mm dia. Bars @ 120 mm spacing

    Reinforcement in longer span

    Ast = My / st jd

    = 5.19 x 106 / 230 x 0.9 x 155

    = 161.75 mm2

    Spacing = 1000 x ast / Ast

    = 1000 x (10/2) / 161.75

    = 485 mm

    Adopt 10mm dia. Bars @ 300 mm spacing

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 41

    Reinforcement detailing

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 42

    4.2. DESIGN OF BEAMS

    DATA:

    BEAM - A 12 =10 m

    Effective Span = 10m

    fy = 415 N/mm2

    fck = 20N/mm2

    Thickness of Beam = 450mm

    STAAD OUTPUT

    Maximum positive BM Mu(+ive) = 215 KNm

    Maximum negative BM Mu(-ive) = 425 KNm

    Maximum Shear force Vu = 247 KN

    DEPTH

    Mu lim = 0.138fckb.d2

    d = 425106(0.13825300)

    d = 585 600mm

    D = 600+50 =650mm

    REINFORCEMENT AT TOP

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 43

    Mu = 0.87 Ast fy d 1 styck 425 106 = 0.87 Ast 415 600 1 st 41545060020 425 106 = 216630Ast 16.65 Ast2

    Ast=2407mm2

    Using 2 layers of 5 nos of 25mm dia bars on compression face

    Ast pro = 2418.1mm2

    REINFORCEMENT AT BOTTOM

    Mu = 0.87 Astfy d 1 styck 215 106 = 0.87 Ast 415 600 1 st 415 45060020 215 106 =216630Ast 16.65 Ast2

    Ast=1082.5mm2

    Using 4nos of 25mm dia bars on the Tension face

    Ast pro = 1081.2mm2

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 44

    SHEAR REINFORCEMENT

    CHECK FOR SHEAR STRESS

    v =

    = 247103 450600 = 0.91 N/mm2

    Pt = 100Ast = 1002418

    450600 = 0.89N/mm2

    Ref. table 19 from IS456

    c = 0.59

    c < v

    Then shear reinforcement are to be designed to resist the balance shear

    compute as

    Vus = (v c) bd

    Vus = (0.91 0.59)45060010-3

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 45

    Vus = 86.4 KN

    Using 8 mm dia 2 legged stirrups

    Sv =0.87

    Sv = 251mm

    Adopt 8 mm dia 2 legged stirrups at 251mm spacing

    CHECK FOR DEFLECTION CONTROL

    max =

    basicKtKcKf

    fs = 0.58fy

    fs = 0.584152407

    2418.1 = 239.6 Pt = 0.89 , fs =239.6, Fig 4 IS 456-2000 kt= 1.0

    max = 26111 = 26

    actual = 5000

    600 = 8.3

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 46

    max >

    actual

    Hence safe

    REINFORCEMENT DETAILING

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 47

    DESIGN OF SECONDARY BEAM

    DATA:

    BEAM AB1 = 5m

    Effective Span = 5m

    fy = 415 N/mm2

    fck = 20N/mm2

    Thickness of Beam = 450mm

    STAAD OUTPUT

    Maximum positive BM Mu(+ive) = 215 KNm

    Maximum negative BM Mu(-ive) = 425 KNm

    Maximum Shear force Vu = 247 KN

    DEPTH

    Mu lim = 0.138fckb.d2

    d= 425106(0.13825300)

    d = 585 600mm

    D = 600+50 =650mm

    REINFORCEMENT AT TOP

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 48

    Mu = 0.87 Ast fy d 1 styck 425 106 = 0.87 Ast 415 600 1 st 41545060020 425 106 =216630Ast 16.65 Ast2

    Ast=2407mm2

    Using 2 layers of 5 nos of 25mm dia bars on compression face

    Ast pro = 2418.1mm2

    REINFORCEMENT AT BOTTOM

    Mu = 0.87 Astfy d 1 styck 215 106 = 0.87 Ast 415 600 1 st 415 45060020 215 106 =216630Ast 16.65 Ast2

    Ast=1082.5mm2

    Using 4nos of 25mm dia bars on the Tension face

    Ast pro = 1081.2mm2

    SHEAR REINFORCEMENT

    CHECK FOR SHEAR STRESS

    v =

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 49

    = 247103 450600 = 0.91 N/mm2

    Pt = 100Ast = 1002418

    450600 = 0.89N/mm2

    Ref. table 19 from IS456

    c = 0.59

    c < v

    Then shear reinforcement are to be designed to resist the balance shear

    compute as

    Vus = (v c) bd

    Vus = (0.91 0.59)45060010-3

    Vus = 86.4 KN

    Using 8 mm dia 2 legged stirrups

    Sv = 0.87 Sv = 251mm

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 50

    Adopt 8 mm dia 2 legged stirrups at 251mm spacing

    CHECK FOR DEFLECTION CONTROL

    max =

    basicKtKcKf

    fs = 0.58fy

    fs = 0.584152407

    2418.1 = 239.6

    Pt=0.89, fs =239.6, Fig 4 IS 456-2000 Kt= 1.0

    max = 26111 = 26

    actual= 10000

    600 = 16.67

    max >

    actual

    Hence safe

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 51

    REINFORCEMENT DETAILING

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 52

    4.3. DESIGN OF COLUMN

    DATA:

    COLUMN A1

    Pu = 915.875 KN

    fck = 20 N/mm2

    fy = 415 N/mm2

    Strength of compression members with helical reinforcement is 1.05 times the

    strength similar members with lateral ties (IS456:2000 cl. 39.4)

    Pu = 915.875 / 1.05 = 873 KN

    MINIMUM ECCENTRICITY

    Assume; emin = 20mm ; (IS456:2000 CL 25.4)

    emin < 0.05D

    20mm < 40mm

    Pu = 0.4 fck + 0.67 fy Asc (IS456:2000 cl 39.3)

    Assume 1 % of steel

    Asc = 1/100 x Ag

    Pu = 0.4 x 20 x(Ag Asc) + 0.67 x 415 x Ag / 100

    Ag = 85591mm2

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 53

    CHECK FOR ECCENTRICITY

    0.05D = 0.05 x 800 = 40 mm

    emin < 0.05D

    Hence ok

    REINFORCEMENT

    Provide 18 mm dia. Bars

    Asc = Ag / 100 = 85591 / 100 = 855.91mm2

    No. Of bars = 855.91 / x (18 / 2)2 = 3.4

    Adopt 5 nos. of 18mm dia. Bars

    HELICAL REINFORCEMENT

    Use 8 mm dia bars mild steel for helical reinforcement

    fy = 250 N/mm2

    Core dia. = Dc = 800 (2 X29.5) = 740mm

    Area of core = Ac = x (Dc)2 / 4 = x 7402 / 4 = 430084mm2

    0.36(Ag/Ac 1 )fck / fy = 0.36 ((800/2)2 1/430084 - 1) x 20/250= 4.859 x 10-3

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 54

    dn = 800 (2 x 33.5) = 733mm

    Let, S = Pitch of spiral

    Vu = dn / S x ( x s / 4)

    Vu = 115750.7204 S

    Vc = Ac x 1 = 430084 x 1 = 430084

    115750.7204S /430084 = 4.8596x 10-3

    S = 55mm

    PITCH SCHEDULE

    (i) < 75mm

    (ii) 1/ 6 Dc = 1 /6 x 740 = 123.33mm

    (iii) >3s = 3 x 8 =24mm

    (iv) S = 55mm

    Hence ok

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 55

    REINFORCEMENT DETAILING

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 56

    4.4. DESIGN OF FOOTING

    DATA:

    Pu = 915.875 KN

    D = 800mm

    P = 180 KN/m2

    fck= 20 N/mm2

    fy = 415 N/mm2

    pu = (1.5 x 180) = 270 KN/m2

    DIMENSIONS OF FOOTING

    Load on column = 915.875 KN

    Self weight of footing = (10%) = 91.6 KN

    Total load on soil = wu = 1007.5 KN

    Let, Df = diameter of the circular footing

    Af = area of the footing

    Af = ( Df2 / 4) = (wu / pu) = (1007.5 / 800) = 1.26 m2

    Df = (4 x 1.26) / = 1.27 m

    Adopt diameter of footing = Df = 2m

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 57

    Upward soil pressure = pu = (915.875 x 4 / x 22) = 291.5 KN/m2 < 300 KN/m2

    Hence, the diameter of the footing is adequate to resist the loads.

    Rx = 0.6 [R2 + r2 + Rr / R +r ] = 0.6[10002 + 4002 +(1000 x 400) /(1000 + 400)]

    = 668mm

    Upward load on area (b b c c) is expressed as Wq and computed as,

    Wq =[ (1 0.42) 291.5 / 4 ] = 192 KN

    BENDING MOMENT

    Maximum bending moment at the face of the column quadrant is computed as,

    Mu = 192 (0.668 0.4) = 51.5 KN.m

    Breadth of footing = rc / 2 = x 0.4 / 2 = 0.63m = 630 mm

    Depth of footing = d = Mu / 0.138 fck b =1.72 m

    Depths required from shear considerations will nearly 1.5 times that for moment

    computations.

    Hence adopt effective depth = d = 250 mm = and overall depth = 300 mm

    REINFORCEMENTS

    Mu = [0.87fyAstd][1-{(Ast fy)/(bdfck)}]

    = [0.87 x 415 Ast x 250][1 {(Ast 415) / (172 x 250 x 20]

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 58

    = 1100mm2

    Ast min = (0.0012 x 172 x 300) = 61.92 mm2

    Provide 10 mm diameter bars at 150 mm spacing.

    CHECK FOR SHEAR STRESS

    Ultimate shear force at a distance of 0.25m from the face of column is given by,

    Vu = 291.5(22 1.352) (/4) = 498.5 KN

    Shear per metre width of perimeter = (498.5 / x 1.35) = 110 KN

    v = (Vu / bd ) = (110 x 103 / 1000 x 250 ) = 0.44 N/mm2

    (100 Ast / bd) = (100 x 1100 / 1000 x 250) = 0.44 N/mm2

    Refer table 19 of IS 456:2000 and read out the permissible shear stress in concrete

    (ks c) = (1 x 0.45) = 0.45 N/mm2 > 0.44 N/mm2

    Hence, the shear stresses are within safe permissible limits.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 59

    REINFORCEMENT DETAILING

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 60

    ESTIMATION

    ITEM

    NO

    PARTICULARS

    NO LENGTH m

    BREADTH m

    HEIGHT OR DEPTH

    M

    QTY

    1 EARTH WORK EXCAVATION

    190 3 3 1.5 2565m3

    2 PLAIN CEMENT

    CONCRETE

    190 3 3 0.05 85.5m3

    3 RCC FOR FOUNDATION

    190 3 3 0.6 1026m3

    4 BACKFILL 1453.5m3

    5 DISPOSAL 1111.5m3

    6 RCC FOR COLUMN

    190 DIA=0.8 AREA=0.5027m2

    30.5 2913.14m2

    7 RCC FOR BEAM1

    1022

    5 0.45 0.6 1379.7m3

    8 RCC FOR BEAM2

    1106

    10 0.45 0.6 2986.2m3

    9 RCC FOR SLAB 1008

    10 5 0.18 9072m3

    10 BRICK WORK1 4 75.6 0.2 28 1693.44m3

    11 BRICKWORK2 2 82.8 0.2 28 927.36m3

    12 BRICKWORK3 10 36.8 0.2 28 2060.8m3

    13 BRICKWORK4 2 65.2 0.2 28 730.24m3

    14 PLASTERING 2 1020 28 57120m2

    15 WHITE WASH 2 1020 28 57120m2

    16 PAINTING 2 1020 28 57120m2

    17 REINFORCEMENT FOR

    FOOTING(10mmDIA)

    11 3m 33X190=6270m 3870.kg

    18 REINFORCEMENT FOR

    FOOTING(6mm DIA)

    16 3m 48X190=9120m 2026.7kg

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 61

    19 REINFORCEME

    NT FOR COLUMN(18m

    m DIA)

    5 30.5m 152.5X190=28975m

    57950kg

    20 REINFORCEMENT FOR

    COLUMN(10mm DIA)

    102 0.8m 81.6X190=15504m

    9570.4kg

    21 REINFORCEMENT FOR

    BEAM1(25mm DIA)

    8 10m 80X1022=81760m

    315432.02kg

    22 REINFORCEMNT FOR

    BEAM1(8mm DIA)

    34 2.1m 71.4X1022=72970.8m

    28828kg

    23 REINFORCEMENT FOR

    BEAM2(25mm DIA)

    8 5m 40X1106=44240m

    170679.0kg

    24 REINFORCEMENT FOR

    BEAM2(8mm DIA)

    17 2.1m 35.7X1106=39484.2m

    15598.7kg

    25 REINFORCEMENT FOR

    SLAB(10mm)

    11 5m 55X1008=55440m

    34222.2kg

    26 REINFORCEMENT FOR

    SLAB(10mm DIA)

    17 10m 170X1008=17136m

    10577.7kg

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 62

    ITEM NO PARTICULARS QUANTITY RATE AMOUNT

    1 EARTH WORK EXCAVATION

    2565m3 175.00 448875 /-

    2 PLAIN CEMENT CONCRETE

    85.5m3 3000 256500 /-

    3 RCC FOR FOUNDATION

    1026m3 5500 5643000 /-

    4 BACKFILL 1453.5m3 50 72675 / - 5 DISPOSAL 1111.5m3 50 55575 / - 6 RCC FOR COLUMN 2913.14m2 5500 16022270 / -

    7 RCC FOR BEAM1 1379.7m3 5500 7588350 / -

    8 RCC FOR BEAM2 2986.2m3 5500 16424100 / -

    9 RCC FOR SLAB 9072m3 5500 49896000 / -

    10 BRICK WORK1 1693.44m3 2750 4656960 / -

    11 BRICKWORK2 927.36m3 2750 2550240 / - 12 BRICKWORK3 2060.8m3 2750 5667200 /- 13 BRICKWORK4 730.24m3 2750 2008160 /- 14 PLASTERING 57120m2 135 7711200 /- 15 WHITE WASH 57120m2 10 571200 /- 16 PAINTING 57120m2 115 6568800/- 17 REINFORCEMENT 648754.72kg 51 33086490 / - 18 ELECTRIFICATION 500000/-

    TOTAL 309727595/-

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 63

    CONCLUSION

    The multicomplex building of eight storey height is designed to be

    located at Tirunelveli. The limit state and working stress method was

    adopted. The design for slabs, beams, columns, footing has been

    done.

    It is concluded that the design by manual method satisfies the

    entire requirement and it would be sufficient for the construction of

    building.

    In this work a eight storey multicomplex with all the facilities for

    a comfortable working has been properly analysed and designed as

    per IS456-2000.

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

  • 64

    REFERENCES

    1. P.C.Varghese, Limit state design of reinforced concrete

    2. N.Krishna Raju, R.N.Pranesh, Reinforced concrete design

    3. B.C.Punmia, Theory of structures

    4. B.N.Dutta, Estimating and Costing in Civil Engg.

    5. Code IS456:2000

    6. Code Sp:16

    7. Code IS 875:1986

    DOWNLOADED FROM http://annacivil.blogspot.com

    http://annacivil.blogspot.in

    DESGIN AND ANALYSIS OF MULTICOMPLEX BUILDING.pdfDATA:STAAD OUTPUTDEPTHREINFORCEMENT AT TOPREINFORCEMENT AT BOTTOMSHEAR REINFORCEMENTCHECK FOR SHEAR STRESSCHECK FOR DEFLECTION CONTROLDATA:STAAD OUTPUTDEPTHREINFORCEMENT AT TOPREINFORCEMENT AT BOTTOMSHEAR REINFORCEMENTCHECK FOR SHEAR STRESSCHECK FOR DEFLECTION CONTROL