Model Persediaan yang tergantung permintaan Master Production ...
Transcript of Model Persediaan yang tergantung permintaan Master Production ...
PERT 06 Material Requirement Planning (MRP)
� Model Persediaan yang tergantung
permintaan
� Master Production Schedule
� Bills of Materials
� Accurate Inventory records
� Purchase Orders Outstanding
� Lead Times for Each Component
Requirements for Effective Use of
Dependent Demand Inventory Models
Effective use of dependent demand
inventory models requires that the
operations manager know the:
– master production schedule
– specifications or bills-of-material
– inventory availability
– purchase orders outstanding
– lead times
Demand Characteristics
11 22 33 44 55
WeekWeek
400 400 –
300 300 –
200 200 –
100 100 –No. of tables
No. of tables
Continuous demandContinuous demand
M T W Th F M T W Th FM T W Th F M T W Th F
400 400 –
300 300 –
200 200 –
100 100 –No. of tables
No. of tables
Discrete demandDiscrete demand
Independent demandIndependent demand
100 tables100 tables
Dependent demandDependent demand
100 x 1 = 100 x 1 = 100 100 tabletopstabletops
100 x 4 = 400 table legs100 x 4 = 400 table legs
� Shows items to be produced
– End item, customer order, module
� Derived from aggregate plan
Master Production Schedule
Master Production Schedule
� Drives MRP process with a schedule of finished products
� Quantities represent production not demand
� Quantities may consist of a combination of customer orders and demand forecasts
� Quantities represent what needs to be produced, not what can be produced
� Quantities represent end items that may or may not be finished products
�Shows items to be produced
– End item, customer order, module
�Derived from aggregate plan
Master Production Schedule
Item/Week Oct 3 Oct 10 Oct 17 Oct 24
Drills 300 200 310 300
Saws 300 450 310 330
Example
Master Production Schedule
PERIODPERIOD
MPS ITEMMPS ITEM 11 22 33 44 55
Pencil CasePencil Case 125125 125125 125125 125125 125125
ClipboardClipboard 8585 9595 120120 100100 100100
LapboardLapboard 7575 120120 4747 2020 1717
LapdeskLapdesk 00 5050 00 5050 00
Inputs to theProduction Plan
Procurement
Supplier
Performance
Aggregate
Production Plan
Marketing
Customer
Demand
Engineering
Design
Completion
Management
Return on
Investment
Capital
Human
Resources
Manpower
Planning
Finance
Cash Flow
ProductionCapacity
Inventory
The Planning Process
Production Plan
Execute MaterialPlans
Master ProductionSchedule
MaterialRequirements
Plan
CapacityRequirements
Plan
Execute CapacityPlans
Realistic??No
Yes
Inventory
Process
stage
Demand
Type
Number
& ValueOther
Raw Material
WIP Finished
Goods
Independent
Dependent
A Items
B Items
C Items
Maintenance
Dependent
Operating
Inventory Classifications
Item Materials WithIndependent Demand
Materials WithDependent Demand
DemandSource
Company Customers Parent Items
MaterialType
Finished Goods WIP & Raw Materials
Method ofEstimatingDemand
Forecast & BookedCustomer Orders
Calculated
PlanningMethod
EOQ & ROP MRP
Dependent versus Independent Demand
Inputs to theProduction Plan
Procurement
Supplier
Performance
Aggregate
Production Plan
Marketing
Customer
Demand
Engineering
Design
Completion
Management
Return on
Investment
Capital
Human
Resources
Manpower
Planning
Finance
Cash Flow
ProductionCapacity
Inventory
The Planning Process
Production Plan
Execute MaterialPlans
Master ProductionSchedule
MaterialRequirements
Plan
CapacityRequirements
Plan
Execute CapacityPlans
Realistic??No
Yes
Typical Focus of the Master Production Schedule
Make to Order
(Process Focus)
Assemble to Order or Forecast
(Repetitive)
Stock to Forecast
(Product Focus)
Schedule finished
product
Steel, Beer, Bread Light bulbs, Paper
Print shopMachine shop
Fine dining restaurant
Examples:
Number of end
items
Number of
inputs
Typical focus of the
master production
schedule Schedule
orders
Schedule
modules
Motorcycles, autos,
TVs, fast-food
restaurant
� List of components & quantities needed
to make product
� Provides product structure (tree)
– Parents: Items above given level
– Children: Items below given level
� Shows low-level coding
– Lowest level in structure item occurs
– Top level is 0; next level is 1 etc.
Bill-of-Material
Figure from Example 1
� Modular bills
– Modules are final components used to make
assemble-to-stock end items
� Planning bills
– Used to assign artificial parent
– Reduces number of items scheduled
� Phantom bills
– Used for subassemblies that exist temporarily
Special Bills-of-Material
Bicycle(1)P/N 1000
Handle Bars (1)P/N 1001
Frame Assembly (1)
P/N 1002
Wheels (2)P/N 1003
Frame (1)P/N 1004
Bill-of-MaterialProduct Structure Tree
Time-Phased Product Structure
1 2 3 4 5 6 7 8
D
G2 weeks
1 weekF
E
3 weeks
2 weeks
A1 week
C1 week
B
2 weeks to produce
E
D
Must have D and E
completed here so
production can begin on B
2 weeks
1 week
Start production
of D
1 2 3 4 5
Gross Requirements 2 20 25 15
Scheduled Receipts 5 30
Available 25 23 33 33 8
Net Requirements 7
Planned Order Receipts 7
Planned Order Releases 7
� Manufacturing computer information
system
� Determines quantity & timing of
dependent demand items
© 1995
Corel
Corp.
Material Requirements Planning (MRP)
� Computer system
� Mainly discrete products
� Accurate bill-of-material
� Accurate inventory status
– 99% inventory accuracy
� Stable lead times
© 1984-1994 T/Maker Co.
MRP Requirements
Material Requirements, Planning (MRP)
� Computerized inventory control and
production planning system
� When to use MRP?
– Dependent demand items
– Discrete demand items
– Complex products
– Job shop production
– Assemble-to-order environments
� Increased customer satisfaction due to
meeting delivery schedules
� Faster response to market changes
� Improved labor & equipment utilization
� Better inventory planning & scheduling
� Reduced inventory levels without reduced
customer service
MRP Benefits
Material Requirements Planning
Materialrequirementsplanning
Planned order
releases
Work orders
Purchase orders
Rescheduling notices
Itemmaster file
Productstructure
file
Master production schedule
Structure of the MRP System
MRP by period report
MRP by date report
Planned orders report
Purchase requirements
Exception reports
MRP
Programs
Master Production
ScheduleBOM
Lead Times
(Item Master File)
(Bill-of-Material)
Inventory Data
Purchasing data
Table 14.3
Derivation of Master Schedule
Therefore, these are the gross
requirements for B1040+10
= 50 40 50 2015+30
= 45
1 2 3 4 5 6 7 8Periods
Gross requirements: B
Periods
10 10
1 2 3
Master schedule for S sold directly
40 50 15
A
CB
5 6 7 8 9 10 11
Lead time = 4 for AMaster schedule for A
40 20 30
S
B C
8 9 10 1211 13
Lead time = 6 for SMaster schedule for S
MRP Systems - Input and Output
MasterProductionScheduleBill of
MaterialsMaterial
RequirementsPlanning System
InventoryStatus
Planned Order& OtherReports
Item MasterPurchasingData
Lot-Sizing Techniques
�Lot-for-lot
�Economic Order Quantity
�Part Period Balancing
�Wagner-Whitin Algorithm
Figure from Example 4
Figure from Example 5
Figure from Example 6
Extensions of MRP
�Closed loop MRP
�Capacity planning - load reports
�MRP II - Material Resource Planning
�Enterprise Resource Planning
Figure 14.8: Closed-Loop MR
Extensions of MRPCapacity Planning
� Tactics for smoothing the load and minimizing the impact
of changed lead time include:
– Overlapping - reduces the lead time, entails sending
pieces to the second operation before the entire lot has
completed the first operation
– Operations splitting - sends the lot to two different
machines for the same operation
– Lot splitting - breaking up the order and running part
of it ahead of the schedule