Mobo Aroroy

download Mobo Aroroy

of 28

Transcript of Mobo Aroroy

  • 7/23/2019 Mobo Aroroy

    1/28

    A CONCEPTUAL DESIGN OF A

    TRANSIMISSION LINE SITUATED

    IN THE ISLAND OF MASBATE

    Proposed Old

    Masbate-Aror

    oy

    Transmission

    LineDesign 1 ELEN 3254

    Submitted By:

    Moris I. Mascarias, BSEE V-1

    Submitted To:

    Engr. Jesus Bien

  • 7/23/2019 Mobo Aroroy

    2/28

    i

    SUMMARY

    This document specifies the requirements for the construction of overhead transmission line

    connecting the Old Masbate Diesel Power Plant and a proposed load end station situated at the

    municipality of Aroroy in Masbate Province.

    DISCLAIMER

    This entire documentation is primarily intended for academic presentation. Calculations

    presented herewith are based on data gathered as general facts in relation to the subject of its

    study. Surveys that may be presented on foregoing parts of this document are mainly gathered

    via research in various websites and in no way intended to be presented as absolute facts. -

    Hence, the researcher is open to the possibility of conflict between the data to be presented and

    the actual status of the case being posed in this study.

  • 7/23/2019 Mobo Aroroy

    3/28

    ii

    Documentation of the Proposed

    Old Masbate- Aroroy Overhead Transmission Line

    CONTENTS

    SCOPE ................................................................................................. 1

    INTRODUCTION .................................................................................. 1

    REFERENCES ....................................................................................... 2

    DEFINITIONS ...................................................................................... 3

    ROUTE SELECTION ............................................................................. 5

    EASEMENTS .......................................................................................... 8

    STRUCTURES ........................................................................................ 9

    CONDUCTORS ..................................................................................... 16

    STRUCTURE SPOTTING ...................................................................... 17

    CORONA .............................................................................................. 22

    EMF ....................................................................................................... 2

  • 7/23/2019 Mobo Aroroy

    4/28

    1

    SCOPE

    For the construction of the proposed Old Masbate- Aroroy transmission line to be designed

    having a 220 KV operating voltage, this document intends to make use of standard parameters

    under the guidance of various accredited references and manuals to come up with an

    appropriate and credible construct calculated for its specification. Whenever non-standard

    parameters may be presented on the concluding parts, those are not contended as a certain

    specification and its modification may be regarded appropriate.

    INTRODUCTION

    The project documented in this report is the Masbates220 kV Transmission Line that starts from

    the Masbate Diesel Power Plant located at Barangay Tugbo in the municipality of Mobo, Masbate

    and ends at municipality of Aroroy. The line traverses several barangays along the municipalities

    of Mobo, Masbate City, Baleno, and Aroroy. The project would be consisted of five phases. The

    phase I connects the line from Masbate Diesel Power Plant, the source of power, and Phase Vjoins to the load-end at its farthest point in Aroroy Town. The Transmission Line construction of

    Phases II-IV would be consisted of segments of line of transmission poles situated in various

    locations. The construction shall conform to the standards of the criteria as required by the listed

    references. Drawings and supporting documents are provided as part of the Design Information.

  • 7/23/2019 Mobo Aroroy

    5/28

    2

    REFERENCES

    The following documents are used to meet the standard criteria for the proposed construction of

    the project featured in this study. These documents are presumed to be the latest guidelines

    governing the codes and considerations in transmission line construction.

    ENA EG-0 Power System Earthing Guide Part 1: Management Principles ENA

    EG1 Substation Earthing Guide Energized Line Working with Polymer

    Insulators for Voltages 60kV and AboveIEEE ESMOL

    HB 102 Co-ordination of power HB 331 HandbookOverhead Line DesignIEEE Std 987 IEEE Guide for Application Of Composite Insulators

    NS 167 Pole PositioningNS220 Guide for Overhead Transmission

    ASCE Guidelines for Electrical Transmission Line Structural Loading (Manual No. 74)

    1724E-204 Guide Specifications for Steel Single Pole and H-Frame Structures

    McGrawHill, Steel Poles and Towers

    1724E-214 Guide Specification for Standard Class Steel Transmission Poles

    1724E-206 Guide Specification for Spun, Prestressed Concrete Poles and Concrete

    Pole Structures

    1724E-216 Guide Specification for Standard Class Spun, Prestressed Concrete

    Transmission Poles

    CL&Ps Transmission line route / configuration alternatives

    McGrawHill The Linemans and Cable mansHandbook,

    REA Design Manual for High Voltage Transmission Lines (REA

    Bulletin 621)

    BULLETIN 1724E-200 Designmanual for high voltage transmission lines

  • 7/23/2019 Mobo Aroroy

    6/28

    3

    DEFINITIONS

    ACSR- Aluminum conductor steel-reinforced (ACSR) is a specific type of high-capacity,high-strength stranded conductor typically used in overhead power lines. The outer strands arehigh-purity 1350 or 1370 aluminum alloy, chosen for its excellent conductivity, low weight andlow cost.

    Conductivity- Measure of a material's ability to conduct an electric current.

    Corona- An electrical discharge brought on by the ionization of a fluid surrounding a conductorthat is electrically energized. The discharge will occur when the strength (potential gradient) ofthe electric field around the conductor is high enough to form a conductive region, but not highenough to cause electrical breakdown or arcing to nearby objects.

    Easements- An easement is a non-possessory right of use or enters onto the real property ofanother without possessing it.

    Efficiency - The useful power output divided by the total electrical power consumed a fractionalexpression

    NESCNational Electrical Safety Code,published exclusively by IEEE, the NESC sets theground rules for practical safeguarding of persons during the installation, operation, ormaintenance of electric supply & communication lines & associated equipment. It contains thebasic provisions that are considered necessary for the safety of employees & the public under thespecified conditions.

    Right of Way- Describes the legal right, established by usage or grant, to pass along a specificroute through grounds or property belonging to another, or a path or thoroughfare subject tosuch a right.

    SagAn act of drooping as an effect of elevation.

    Truss- A structure that "consists of two-force members only, where the members are organizedso that the assemblage as a whole behaves as a single object.

    Mechanical Load -The force exerted on a body on surface while the force is a vector quantitythat possesses magnitude.

    Tension- Describes the pulling force exerted by each end of a string, cable, chain, or similarone-dimensional continuous object, or by each end of a rod, truss member, or similar threedimensional objects.

    Wind Loading- Analyzes effects of wind in the natural and the built environment and studiesthe possible damage, inconvenience or benefits which may result from wind.

    ClearanceOpen space between two elements of a structure to aid in proper placement, tocompensate for minor inaccuracies in modification, or to allow unobstructed movement betweenparts.

    ToleranceStructures potential to cope with changes in the following elements of its

    surroundings such as a physical dimension, a measured value or physical property of a material,such as temperature, humidity, etc., and remain functioning.

  • 7/23/2019 Mobo Aroroy

    7/28

    4

    DESIGN BRIEF

    A design brief is prepared to outline each section of the transmission line construction. It includes

    the following information.

    Project scope and description

    Proposed route or end points

    System loading requirements

    Operating voltage

    Line capacity (or in some cases, conductor size and material type for phase conductors)

    Maximum design operating temperature of the conductors

    Maximum design temperature under wind loading conditions

    Minimum design operating temperature of the conductors

    Permissible tower material, (e.g. concrete, wood, steel)

    Permissible construction type, (e.g. H-pole, standoff insulators, etc.)

    Allowance for additional circuits, if applicable

    Conductor size and material type for overhead earth wire, where require whether the

    overhead earth wire is not required for the full length of line whether an OPGW (optical

    pilot ground wire) is required

    Required Earthing of structures including maximum pole earth resistance and allowable

    Earthing construction (for contestable projects the Client is generally responsible for the

    Earthing study)

    Protection requirements, where relevant to the scope of works

    Any special conditions or arrangements already made for easements, right-of-way and

    access to private land

    Any special conditions or arrangements already made with the local council or roads

    authority for lines on public roads.

  • 7/23/2019 Mobo Aroroy

    8/28

    5

    ROUTE SELECTION

    In The process of analysis of the routing selection of the 69 KV transmission line from Mobo,Masbate up to its load end station at Aroroy Town, Several objectives are listed which areprimary considerations that advise the erection of the structure. These are;

    Cost effectiveness and reliable system of transmission that interconnects to specified

    substations and switching stations.

    Maximization of the efficiency of the project

    Minimization of adverse effects to sensitive environmental resources

    Minimization of adverse effects to significant cultural resources

    Minimization of adverse effects on designated scenic resources and heritage sites.

    Minimization off conflicts with local and national land resource policies Minimization of the need to acquire property by eminent domain

    Maintenance of public health and safety

    In compliance with the aforesaid criteria, the project route is decided to be as shown below.

    Line Route

  • 7/23/2019 Mobo Aroroy

    9/28

    6

    Proposed Project Area

    The route is identified by avoiding, to such extent possible and applicable, areas where a

    transmission line could create significant impacts such as:

    Existing high-density residential areas.

    Agricultural areas where center pivot irrigation systems are used.

    Areas where horizontal clearances are limited because of trees or nearby structures.

    Environmentally sensitive sites such as areas with threatened or endangered species of

    Animals

    Areas of Cultural Significance

    Line Route

  • 7/23/2019 Mobo Aroroy

    10/28

    7

    The proposed project area is the most reasonable option concluded by the following

    considerations.

    Public and Social considerations

    Distance of transmission centerline to homes and businesses

    Distance and impact to public facilities, parks, and trails

    Extent of tree and vegetation removal which should be minimized

    Distance and to historical sites in the area

    Environmental/Cultural considerations

    Adherence to national and local regulations

    Adherence to sound environmental principles

    Avoidance of areas such as burial sites, wildlife protected areas, protected wetlands, andscientific research areas of threatened and endangered species of animals.

    Engineering/Construction considerations

    Adherence to sound engineering/construction principles

    Safety

    Reliability

    Accessibility

    Engineering Considerations

    Suitable soil conditions

    Required angle structures

    Structure size

    Span lengths

    Potential total line length due to the proposed location

    Special construction requirements

    Cost effectiveness

  • 7/23/2019 Mobo Aroroy

    11/28

    8

    EASEMENTS

    Pole positioning and location shall be in accordance with the regulation of Electric Power

    research Institute. In this documentation, citation in Ausgrids NS 167, Pole Positioningalso

    serves as a basis. Where possible, line routes shall follow existing roads, and be contained within

    the reserved area for pole erection.

    In the case of the proposed location, savings or other advantages due to reduction of distances

    may be obtained by traversing private property or other land not dedicated as public roads. In

    this case, negotiations with property owner shall be coordinated.

    Several routes where vehicle access is not appropriate to conduct maintenance and repairs shall

    be established a right of way.

    Re-routing of small segments may be applied in instances of impossibility to establish a

    right-of-way due to the unsatisfiable demands of the property owner.

    Below are lists of easements permits and authorizations that are meant to be secured;

    Private properties Easement from owner and permission to cutdanger trees and for traversing the respectiveproperties

    Highways Permit or Agreement with National and localGovernment for the utilization of CentralNautical Highway

    Other public bodies Authorization for each respective concerns

    City and National Government Building Permits

    Instances of joint and common use of poles ofother organizations

    Permit or agreement

    Wire crossing Permission of utility

  • 7/23/2019 Mobo Aroroy

    12/28

    9

    STRUCTURES

    Cited references for the contents of the structure analysis are the ASCE Guidelines for Electrical

    Transmission Line Structural Loading (Manual No. 74) and the 1724E-204, Guide Specifications

    for Steel Single Pole and H-Frame Structures. The aforesaid manuals provide the major criteria

    for the design consideration employed in this documentation.

    In economic considerations for transmission lines 230 KV and below, wood structures is

    apprehended as a more economic choice. However in the case of the Mobo-Aroroy project, in

    which longer spans between pole structures should be employed from which heavier loading

    situation would occur, steel structures may be considered more economical considering the long

    term maintenance cost associated with wood structures.

    Economic studies are conducted to determine by comparison, the structure configuration that

    may be best employed. - Or materials to be used such as base pole class of wood, steel or

    prestressed concrete. Similarly, such studies are also employed to determine efficiency in terms

    of material costs, cost of foundations and erection and different structural heights that defines

    the structures reliability.

    Factors that define the structure reliability are defined as follows:

    Strength: Horizontal spans are limited by cross brace, poles, etc. Vertical spans are

    limited by cross arms structure strength. For H-frame structures, horizontal and vertical

    spans are also limited by pullout resistance for H-frame structures.

    Conductor Separation: Conductor separation is intended to provide adequate space

    for line crew personnel on poles, prevention of contact and flashover between

    conductors.

    Clearances-to-Ground: Limits on spans are directly related to height of structures.

    Insulator Swing: The ratio of horizontal to vertical span will be limited by insulator

    swing and clearance to structure.

  • 7/23/2019 Mobo Aroroy

    13/28

    10

    For the purpose of the design featured in this study, which are subjected into various

    parameters, primarily defined by the climate condition of the proposed location of the structure,

    as well as the environmental concerns posed by the regulating bodies of forest preservation, the

    use of steel structures shall be employed.

    DESIGN CALCULATIONS:

    For a 69 KV, steel transmission tower, the following preliminary values are assumed by

    considering NESC heavy loading standards.

    DESIGN OF STEEL TOWER

    Conductor: ACSR galvanized stranded-steel ground wire. Three no. 1, hard-drawn strandedcopper, 120,000 volts.

    Span = 400 ft.Nor. sag = 9 ft. 0 in. Nor. tension (60F.) = 570 lb.Max. Sag = 10 ft. 6 in. Max. Tension (0F., %-in. ice, 8 lb. Wind) =1960 lb.

    Elastic limit, No. 1 wire = 2180 lb.

  • 7/23/2019 Mobo Aroroy

    14/28

    11

    Wind pressure on wires (%-in. ice, 8 lb. per square foot wind):

    %-in. ground wire = 0.917 X 400 = 367 lb.No. 1 conductor = 0.885 X 400 = 354 lb.Wind on pole = 13 lb. per square foot X 1 times exposed area of windward side = 20 lb. perlineal foot.

    With the above transverse loading and no broken wires, the compressive stress in the leg abovethe foundation is obtained by taking moments of the forces about the panel point 2 ft. 1 in. abovethe foundation.

    Ground wire 367 lb. X 42.4 = 15,560 ft.-lb.Power wires 354 lb. X 39.9 = 14,120 ft.-lb.Power wires 354 lb. X 2 X 37.4 = 26,480 ft.-lb.

    Wind on pole = 20 lb. X = 17,980 ft.-lb.

    Total bending moment =15,560 ft.-lb. + 14,120 ft.-lb. + 26,480 ft.-lb. + 17,980 ft.-lb.= 74,140 ft.-lb.

    Since the lever arm of the resisting forces = 1.9 ft.:

    7 4,140 ft.-lb. (1.9 ft. X 2 legs) = 19,500 lb.

    Vertical load-steel = 1700 lb.

    Vertical load-wires and insulators = 1500 lb.

    3200 lb. 4 legs = 800 lb.

    Total compressive stress in each leg = 19,500 lb. + 800 lb. = 20,300 lb.

    Since 1 L 3 X 3 X M = 1.44 sq. in,

    Maximum unit stress in each leg = 20,300 1.44 = 14,100 lb. per square inch.

    The transmission tower is to be designed with identical faces on its sides. - Hence, the leg is

    restrained from buckling in one direction by the intersecting diagonals, so the maximum l/r will

    be computed as follows;

    l r = 44in. 0.92 = 48 or;

    l r = 22in 0.59 = 37

    The ultimate strength of the angle based on the greater value of l/r in the curve in Fig. 33 of

    422

    2

  • 7/23/2019 Mobo Aroroy

    15/28

    12

    McGrawHill, Steel Poles and Towersis 14,100 lb. per square foot; therefore;

    Safety Factor = 35,000 14100 = 2.5

    STRESS IN DIAGONALS

    Assumptions are;

    Ground wire = 367 lb. X 1 = 367

    Conductors = 354 lb. X 3 = 1062

    Wind on pole = 201b. X 6 = 120

    Total = 1549 lb.

    By web systems of two faces of McGraw Hills transmission poles and towers, the configurationof the tower design, will yield a shear stress of 775 lb. per face. The stress in the diagonal just

    below the arm is to equal the shear multiplied by the secant of the slope.

    Assuming a 45 slope for the diagonals;

    Stress = 775 lb. X (1 cos 45) =1100 lb.

    STRESS IN CROSSARMS

    The cross arms should be designed for maximum wind loads on both spans or for the maximum

    ice and wind loads on one span combined with a longitudinal load due to the breaking of the wire

    in the other span. Ice loads are of minimal effect on the project location.- However, still included

    in the calculation as set by standards.

    CONDITION No. 1

    Vertical load (%-in. ice on wires) - 0.770 lb. per foot X 400 ft. = 308 lb.

    Insulator and pin = 25 lb. 333 lb.

    = 333 lb.

    333 lb. X 35 in = 11,660 in.-lb.

    Weight of arm = 15 lb. per foot X X 12 = 860 in.-lb.

    312

    2

  • 7/23/2019 Mobo Aroroy

    16/28

    13

    Horizontal load (8 lb. per square foot wind on wire 0.885 lb. per foot X 400 ft.)

    = 354 lb. X 12 in = 4,250 in.-lb.

    Total bending moment = 16,770 in.-lb.

    3in. X 3 in. X 5/16in. X i/c = 2 X 0.95 = 1.90.

    Max. Unit stress in cross arm = 16,770 1.90 =8800 lb. per square inch.

    CONDITION No. 2

    Vertical load (3-in. ice on wires) - 0.770 lb. per foot X 200 ft. = 154 lb.

    Insulator and pin = 25 lb.

    179 lb.

    179 lb. X 35 in =6270 in.-lb.

    Weight of arm = 15 lb. per foot X X 12 =860 in.-lb.

    Horizontal load (8 lb. per square foot wind on wire -0.885 lb. per foot X 200 ft.) =

    177 lb. X 12 in =2120 in.-lb.

    Total Bending Moment = 9250 in.-lb.

    9250 1.90 = 4900 lb. per square inch,

    Longitudinal load:

    1960 lb. X X 1.50 = 3720 lb.

    3720 1.94 = 1900 lb. per square inch,

    3.1

    2

    2.85

    1.50

  • 7/23/2019 Mobo Aroroy

    17/28

    14

    Maximum unit stress in cross arm = 4900 + 1900 = 6800 lb. per square inch.

    The four legged Pratt Braced towers, designed for a 220 KV transmission line tower will be

    employed in this in this project.

    TOWER HEIGHT

    For Minimum Permissible Ground Clearance (h1) for 220kV;

    h1 = 7.01m

    Maximum Sag (h2):

    For the sag tension calculation for the conductor and earth wire, citation will be made with

    provisions of IS: 5613:1985For the following combinations;

    -100% design wind pressure after accounting for drag coefficient and gust response factor

    at every day temperature

    -36% design wind pressure after accounting for drag coefficient and gust response factor

    at minimum temperature.

  • 7/23/2019 Mobo Aroroy

    18/28

    15

    For the conductors with higher aluminum content normally used for 220kV lines, increased sag

    of 2 to 4% of the maximum sag value is allowed.

    T22 [T2 + A E (t2- t1) - t1] =

    From the above equation, we get sag tension of the conductor (T2).

    Sag =

    The following combinations of factors will be considered:No Wind, t2 = 00 C

    No Wind, t2 = 750 C

    No Wind, t2 = 320 C

    Full Wind, t2 = 320 C

    75% Full Wind, t2 = 320 C

    Sag value for different temperatures and for different wind conditions are calculated and the

    maximum value of the above combinations + 4% extra will gives the h2 of the conductor.

    Vertical Clearance between Ground Wire and Top Conductor (h4): The same procedure isrepeated as done in finding sag of the conductor (h2) but only difference is instead of conductorproperties substitute earth wire properties.

    H = h1 + h2 + h3 +h4 = 33.52 m.

    FOUNDATION DESIGN

    Tower foundations shall be capable of withstanding loadsspecified strength limit state and

    serviceability limit state conditions. Pole embedment depths shall be is indicated in NS220,

    Ausgrids Overhead Design Manual, and Sections 6.2 Foundations as cited.

    AL P E

    24T

    AL P E

    24T

    PL

    8T

  • 7/23/2019 Mobo Aroroy

    19/28

    16

    CONDUCTORS

    Conductor materials which used for Mobo-Aroroy overhead transmission lines shall have the

    following electrical and physical properties.

    The conductor shall have a high conductivity for minimal losses

    It should have tensile strength.

    It should have a high melting point and thermal stability.

    It should be flexible to permit us to handle easily and to transport to the site easily.

    It should be corrosion resistance.

    As cited in ACSR Manual, Aluminum Wires and Cables, conductor data sheet shall be the

    following;

    ACSR Code Name Zebra

    No. of Conductor/Phase One

    Stranding/ Wire Diameter 54/3.18mm AL + 7/3.18mm steel

    Total Sectional Area 484.5 mm2

    Overall Diameter 28.62 mm

    Approximate Weight 1621 Kg/ Km

    Calculated D.C Resistance at 20 0C 0.06915 ohm/Km

    Minimum Ultimate Tensile Strength 130.32 KN

    Modulus of Elasticity 7034 Kg/mm2

    Coefficient of Linear Expansion 19.30 x 10-6/ 0C

    Max. Allowable Temperature 750C

    EARTHWIRE

    By NESC Standard for Transmission Conductors, earth wires to be employed as lightning and

    high voltage surge arresters for 220 KV line transmission towers shall have the properties as

    summarized below.

    Material of Earth wire Galvanized steel

    No. of Earth Wire One or two *depending on the shielding angle as

    required by the location

    Stranding/ Wire Diameter 7- 3.15mm

    Total Sectional Area 54.55 mm2

  • 7/23/2019 Mobo Aroroy

    20/28

    17

    Overall Diameter 9.45 mm

    Approximate Weight 428 Kg/ Km

    Calculated D.C resistance at 200C 3.375 ohm/Km

    Min. Ultimate Tensile Strength 5710 Kg

    Modulus of Elasticity 19361 Kg/mm2

    STRUCTURE SPOTTING

    The specifications of the route alignment of tower structures are profiled through the use of the

    Google map imagery of the Masbate province. The output documentation shall be in the form of

    digitized route alignment drawing by the utilization of the PLS-CADD, providing the digital

    imagery of the terrain modeling along the selected route.

    Following considerations are employed in the spotting of locations for the transmission towers

    featured in this document;

    The alignment of the transmission line shall be economical upon its construction and

    access for its maintenance.

    Routing of transmission line in protected /reserved forest area should be avoided. In case

    that as such is not possible, the cutting down trees shal be kept at minimum.

    The number of angle points shall be kept to a minimum.

    The distance between the terminal points specified shall be kept shortest possible, and

    consistent with the encountered terrain.

    Low lying areas, river beds and earth slip zones shall be avoided to minimize risk to the

    foundations and towers.

    Ground level alignment shall be utilized.

    Crossing of communication line shall be minimized and it shall be at right angle. Proximity

    and parallel alignment with telecommunication lines shall be eliminated to avoid danger

    of induction.

    Areas subjected to flooding shall be avoided.

    As provided by the REA, Design Manual for High Voltage Transmission Lines, clearances for

    220 KV lines shall be of 7 meters at minimum. The ground clearance curve should not touch or

    cross the ground line. Besides normal ground clearance, the clearance between power

    conductor and objects like other power or telecommunication lines, houses, roads etc., shall also

    be checked.

  • 7/23/2019 Mobo Aroroy

    21/28

    18

    While crossing over existing power lines, one of the crossing span of the new line is preferably

    located near the existing power line, to take advantage of the higher height of the conductors

    near the tower. This reduces the necessity of increasing the height of the towers of the new line

    for obtaining the requisite clearance. Double suspension tension insulator strings, depending on

    the type of the towers shall to be used in the new line on such crossings. Minimum clearances in

    meters between lines crossing each other, specified for 220KV shall be 4.58 meters.

    A tower schedule is prepared which contains all the information such as location numbers, type

    of tower, span length, section length, sum of adjacent spans, weight spans as affected by of one

    side as well as both sides under maximum and minimum sag conditions and angle of deviations.

    SAG TEMPLATE CALCULATIONS

    When calculating maximum sags for new conductors, allowances shall be made for conductorcreep and for minor errors in construction. This additional creep allowance does not have to be

    applied to existing conductors which are being diverted or reconstructed.

    Conductor: ACSR Zebra (420 mm2)

    Construction: 54 Aluminums / 7 Steels / 3.18 mm

    PARAMETERS:

    Basic Span () : 350 meters

    Ultimate Tensile Strength of Conductor (U.T.S.) : 13290 Kg

    Overall diameter of the Conductor (d) : 28.62 mm

    Weight of the Conductor (w) : 1.621 kg / m

    Wind Pressure (P) : 83.38 Kg /m2

    Coefficient of linear Expansion () : 19.3 106 per C

    Youngs Modulus of elasticity (Final) (Ef) : 0.686 10 6 Kg / cm2

    Youngs Modulus of elasticity (Initial) (Ei) : 0.4675 10 6 Kg / cm2

    Maximum temperature (Ambient) : 50 C

    Maximum temperature (Conductor) : 75 C

    Minimum Temperature (Ambient) : (-) 2.5 C

    Minimum Temperature (Conductor) : (-) 2.5 C

    Normal Temperature : 32.2 C

    Area of Cross section of Conductor (A) : 4.845 cm2

    Factor of Safety (F.O.S.) (at 32.2 C) : 4

    Factor of Safety (F.O.S.) (Otherwise) : 2

  • 7/23/2019 Mobo Aroroy

    22/28

    19

    Weight of Conductor per unit area () : = w = 1.621

    A 4.845

    = 0.334571723 Kg /m / cm2

    Minimum Ground Clearance : 7.01 meters

    CONDITION: I

    Temperature = 32.2 CWind = NILFactor of Safety = 4

    Working tension; T1 = U.T.S = 13290F.O.S 4

    T1 = 3322.5 Kg

    Working Stress; f1 = T1 = 3322.50A 4.845

    f1 = 685.75851 Kg / cm2

    Loading factor; q1 = P2 + w2 =1 (for no wind; P = 0)W

    The working stress is determined by the following formula:

    f12(f1k) = 22q12Ef24

    k = f122q12Ef24 f12

    k= 685.75851(350)2 (0.334571723)2 (1)2 (0.686 106)24 (685.75851)2

    = 685.75851833.46049

    k = (-) 147.70198

    CONDITION: II

    Temperature = 75 CWind = NILFactor of Safety = 4

    Working tension; T1 = U.T.S = 13290F.O.S 4

  • 7/23/2019 Mobo Aroroy

    23/28

    20

    T1 = 3322.5 Kg

    Working Stress; f1 = T1 = 3322.50A 4.845

    f1 = 685.75851 Kg / cm2

    Loading factor; q1 = P2 + w2 =1 (for no wind; P = 0)W

    The working stress is determined by the following formula:

    f12(f2(k- t Ef) = 22q12Ef24

    f22[f2{147.70198(19.3 106) 42.8 (0.686 106)}]

    = (350)2 (0.334571723)2 (1)2 (0.686 106)24

    f22(f2+ 714.36542) = 3.919470757 108

    f22= 555.553321 Kg / cm2

    Working tension; T2= f2 A = 555.553321 4.84 = 2691.656 Kg / cm2

    Maximum Sag; s = 2 q28 f2

    = (350)2 (0.334571723) (1)8 555.553321

    = 9.22 meters

    CONDITION: III

    Temperature = (-) 2.5 CWind = NILLoading factor; q3 = P2 + w2 = 1 (for no wind; P = 0)

    W

    Difference of temperature; t =2.532.2 =34.7 C

    The working stress is determined by the following formula:

    f32[f3(k t E f) = 22q32E f24

    f32[f3{147.70198(19.3 10 6) (34.7) (0.686 106)}]

  • 7/23/2019 Mobo Aroroy

    24/28

    21

    = (350)2 (0.334571723)2 (1)2 (0.686 106)24

    f32(f3+ 311.71908) = 3.919470757 108

    f3= 851.8511701 Kg / cm2

    Working tension; T3 = f3 A

    = 851.8511701 4.845

    = 4127.219 Kg / cm2

    Factor of Safety = 13290 = 3.22, hence O. K.4127.2

    Maximum Sag; s = 2

    q38 f3

    = (350)2 (0.334571723) (1)8 851.8511701

    = 6.01 meters

    For Sag calculation at any span, the following formula can be used.

    Sag at any Span = Sag at Basic Span (Span Length)

    2

    (Basic Span) 2

  • 7/23/2019 Mobo Aroroy

    25/28

    22

    CORONA

    Corona is defined as a self-sustained electric discharge in which the field intensified ionization islocalized only over a portion of the distance between the electrodes.

    During unusual situations in the overhead transmission line when the intensity of the electric

    field exceeds the dielectric strength of air, the area around the conductor experiences electricdrilling, which causes increased losses and apparent conductivity.

    Corona phenomenon initiates as a hissing noise and is heard and ozone gas is formed which canbe detected and characterized by its color.

    The object of this documentation was to obtain data for the choice of conductor to be used ona 220-kv. 60- Cycle line. The results show the effect of weathering of conductors, the type ofconductors of two different diameters, the effect of size of conductor strands and the method ofstranding.

    Corona activity on the 220 kV transmission line can generate a small amount of sound energy.Corona also results in a small amount of power loss to the transmission line. The audible noiselevel can increase during foul weather conditions. Water drops may collect on the surface of theconductors and increase corona activity so that a crackling or humming sound may be heardnear a transmission line. Audible noise decreases with distance away from a transmission line.Corona is affected by the voltage of the line, the diameter of the conductor, and thecondition of the conductor and suspension hardware. The electric field gradient is therate at which the electric field changes and is directly related to the line voltage. Theelectric field gradient is greatest at the surface of the conductor. Large-diameterconductors have lower electric field gradients at the conductor surface and, hence,lower corona than smaller conductors, everything else being equal.

    In this document the following solutions are proposed to be employed;

    Minimize the voltage stress and electric field gradient. This is accomplished bymaximizing the distance between conductors that have large voltagedifferentials, using conductors with large radius, and avoiding parts that havesharp points or sharp edges.

    Surface Treatments: Corona inception voltage can sometimes be increased byusing a surface treatment, such as a semiconductor layer, high voltage putty orcorona dope.

    Employ proper geometric configuration of the conductors.

    Eliminate unwanted voltage transients in the line, which can cause corona tostart.

    By increasing the diameter of the conductor: Diameter of the conductor can beincreased to reduce the corona discharge effect.

    Using Bundled Conductors, multiple conductors per phase are used in the 220 KV

    line. This is a common way of increasing the effective diameter of the conductor,which in turn results in less resistance, which in turn reduces losses.

  • 7/23/2019 Mobo Aroroy

    26/28

    23

    MAGNETIC FIELDS

    A double circuit 220kV transmission lines crosses several plane land surfaces in Masbateprovince and connects the Aroroy Substation and the Old Masbate diesel power plant inthe province. Each line is on one side of the tower and consist of three phase with eachphase consisting of a bundle of two conductors. The lines also have two conductors onthe top of the towers (called earth wires) that do not carry current but act as to shield

    the line from lightning current surges.

    Considering the EMF-Effect associated with the proposed design, the followingmeasures are conducted.

    - The undergrounding of the power lines with the required transition enclosures: and

    - Retaining the power lines above ground mounted on poles, with the slight realignmentof the easement.

    Electric fields are created by the electric charges on high voltage equipment. They

    diminish rapidly with distance and are shielded by common materials such as trees orbuildings. Electric fields have not been identified as a source of major safety issues.However, they can potentially cause a number of effects such as audible noise, RF noiseinterference and visible spark.Electric field strengths associated with 220 KV transmission lines typically are in therange of 1 - 3 kV/m under the power lines - contact shocks to occur. At the edge of thetransmission line easement, typically 20 to 30 meters from the power line poles, theelectric fields are typically in the range of 0.1 - 1.0 kV/m.

    It is also possible for voltages to be induced in long metallic structures that are alignedso that they run parallel to the transmission lines. However, the induction is significantly

    small; running through lengthy structures that makes it becomes dissipated andgenerally wontreach the bottom part that would affect the public.

    There are a number of ways to reduce EMF effects: F irstly, as the magnitude of the EMFis inversely proportional to the distance from the current carrying elements, one canincrease the distance of the public from the conductors. Hence by increasing the widthof an easement, increasing the height of a transmission line or increasing the distanceto the boundary of the terminal station will reduce the magnetic field strengthmagnitude. Higher transmission poles will produce a lower EMF, so there is a potentialtrade-off between the height of a transmission pole and its effect on visual amenity andthe reduction in EMF. There are practical limits to the physical height of poles and sizeof the easements and substation sites so this solution, whilst generally practical, doesnot suit every situation.

    More compact structures have lower EMF as better cancellation of the fields occurs if theconductors are close together but there are engineering limits to how close conductorscan be place to each other.

    EMF shielding is possible using materials of high magnetic permeability. However, thissolution is expensive and usually only used to solve specific local problems.

    Other solutions, such as current cancellat ion loops may offer alternative, but less provenoptions for addressing magnetic field problems.

  • 7/23/2019 Mobo Aroroy

    27/28

    24

    The various solutions are applied during detailed design. Generally speaking physicalseparation will provide appropriate EMF levels and this particularly applies totransmission lines through rural areas where the lines are well away from areas desedwith people.

  • 7/23/2019 Mobo Aroroy

    28/28