MMX: CREATING CHOICES IN SEABORNE IRON ORE SUPPLY Rio de Janeiro | September 2012

Transcript of Mmx setembro 2012 - ingles v. final

Page 1: Mmx   setembro 2012 - ingles v. final

MMX: CREATING CHOICES IN SEABORNE IRON ORE SUPPLY

Rio de Janeiro | September 2012

Page 2: Mmx   setembro 2012 - ingles v. final

This presentation relating to MMX Mineração e Metálicos S.A. (“MMX”) includes “forward-looking statements”, as that term

is defined in the Private Securities Litigation Reform Act of 1995, in Section 27A of the Securities Act of 1933 and Section

21E of the U.S. Securities Exchange Act of 1934. All statements other than statements of historical facts are statements

that could be deemed forward-looking statements and are often characterized by the use of words such as “projects”,

“expects”, “anticipates”, “intends”, “plans”, “believes”, “estimates”, “may”, “will”, or “intends”, or by discussions or

comments about our objectives, strategy, plans or intentions and results of operations. Forward-looking statements include

projections regarding our operating capacity, operating expenditures, capital expenditures and start-up dates.

By their nature, these forward-looking statements involve numerous assumptions, uncertainties and opportunities, both

general and specific. The risk exists that these statements may not be fulfilled or, even if they are fulfilled, the results or

developments described in such statements may not be indicative of results or developments in future periods. We caution

participants of this presentation not to place undue reliance on these forward-looking statements as a number of factors

could cause future results to differ materially from these statements.

Forward-looking statements may be influenced in particular by factors such as the ability to obtain all required regulatory

approvals on a timely basis or at all, exploration for mineral resources and reserves, difficulty in converting geological

resources into mineral reserves, and changes in economic, political and regulatory conditions. We caution that the

foregoing list is not exhaustive. When relying on forward-looking statements to make decisions, investors should carefully

consider these factors as well as other uncertainties and events.

MMX does not undertake to update our forward-looking statements unless required by law. This presentation is neither an

offer to sell (which can only be made pursuant to definitive offering documents) nor a solicitation of an offer to buy any

securities in the United States, or any other jurisdiction. The securities referred to herein have not been registered in any

jurisdiction, and in particular, will not be registered under the U.S. Securities Act of 1933, as amended, or any applicable

state securities laws and may not be offered or sold in the United States absent registration or an applicable exemption

from such registration requirements.

This presentation and its contents are proprietary information and may not be reproduced or otherwise disseminated in

whole or in part without MMX’s prior written consent.

DISCLAIMER

Page 3: Mmx   setembro 2012 - ingles v. final

MMX INTRODUCTION

1

Page 4: Mmx   setembro 2012 - ingles v. final

HIGH QUALITY MINING ASSETS IN TRADITIONAL

MINING DISTRICTS

Sudeste SystemSerra Azul Unit

Bom Sucesso UnitCorumbá System

Sudeste Superport

Chile System

Mining rights in traditional iron ore districts:

Brazil – Minas Gerais and Chile

Production committed with strategic consumers

– China and South Korea – through long-term

contracts

Brownfield start up in Brazil

Expanding beyond 40 Mtpy in Brazil and Chile,

through fully integrated systems: with private

ports in Brazil

Unique port location

4

Page 5: Mmx   setembro 2012 - ingles v. final

42% ControllingShareholders

16% Wisco

14% SK Networks

28% Free Float

MMX Corumbá Mineração

MMX SudesteMinera MMX

do Chile

Superporto Sudeste

Serra Azul

Bom Sucesso

100% 100% 99%70%

5,48% EBX

MMXM3: SOLID CONTROLLING SHAREHOLDERS

5

Page 6: Mmx   setembro 2012 - ingles v. final

SRK certification: 3,1 billion tons of mineral resources, and further mineral

potential of up to 1,4 billion tons. Reserves of 1 billion tons in Serra Azul.

64% of future production already committed through long-term contracts

Experience management team with implementation and operational expertise

Installed Capacity of 10 Mtpy (Serra Azul and Corumbá sites)

Sudeste Superport at 50 Mtpy, expandable to 100 Mtpy, provides gateway to

seaborne markets

Long Term Railway Contract with MRS

Low stripping ratio

Competitive scale – New beneficiation plant

Energy supply contract with MPX

Integrated infrastructure with the existing MRS railway

Resource Base

Secured Off-take

Operational Track Record

GuaranteedLogistics

Competitive Production Cost

Structure

INGREDIENTS FOR A SUCCESSFUL IRON ORE

BUSINESS

6

Page 7: Mmx   setembro 2012 - ingles v. final

Beginning of construction of the Serra Azul Unit expansion

Installation License authorizing the Serra Azul Unit expansion

MMX signs contract for railway services with MRS through 2026

SRK certified 997,4 million tons of mineral reserves at Serra Azul Unit

EIA-RIMA filed for Sudeste Superport expansion to 100 Mtpa

Orders for long lead equipment for Serra Azul expansion

EPCM contract with CNEC Worley Parsons for Serra Azul expansion

Contract with MPX for energy supply for expansion of Serra Azul

Preliminary license of the Serra Azul expansion

Financial advisory contract with Itaú BBA and Bradesco

Acquisition of 99,1% of PortX shares

Deal with Usiminas

May2012

February2011

A LOT HAS BEEN DELIVERED

7

Page 8: Mmx   setembro 2012 - ingles v. final

FINANCIAL HIGHLIGHTS

37% 32% 33%

63% 68% 67%

0%

20%

40%

60%

80%

100%

2Q11 1Q12 2Q12

Debt profile

Short Term Long Term

61%53% 56%

0%

15%

30%

45%

60%

2Q11 1Q12 2Q12

Gross Margin (%)

75.2

4.2 13.9

0

15

30

45

60

75

90

2Q11 1Q12 2Q12

EBITDA (R$ million)

90,9 49,3

-391,6

-400

-300

-200

-100

0

100

200

2Q11 1Q12 2Q12

Net Profit (R$ million)

Page 9: Mmx   setembro 2012 - ingles v. final

SUDESTE SYSTEM

2

Page 10: Mmx   setembro 2012 - ingles v. final

SERRA AZUL UNIT

2.1

Page 11: Mmx   setembro 2012 - ingles v. final

UNIQUE INTEGRATED LOGISTICS

Since Iron ore is a bulk commodity, an integrated logistic (mine railway port) is the key factor for a successful operation

Mine SuperportRailway

Serra Azul unit is near to theMRS railway - 10 km from themine, a distance currentlytraversed by trucks.

MMX has a long term contractwith MRS railway, which connectsthe mine with the CSN’s Itaguaíport and to the SudesteSuperport.

Sudeste Superport is located inItaguaí and will have 50Mtpy ironore shipping capacity. The Superportwill have a depth of 20 meters,enough to handle Capesize vessels.

Offtakers (Shareholders)

Long-Term contract (20 years) to trade ironore. SK will take-off part of the SudesteSystem yearly production equivalent to itsparticipation in MMX Capital (14%).

SK and Wisco will togetherofftake 64% of total production

Long-Term contract (20 years). Wisco willoff-take at least 50% of MMX Sudesteproduction.

11

Page 12: Mmx   setembro 2012 - ingles v. final

QUADRILÁTERO FERRÍFEROIron ore Quadrangle

12

Page 13: Mmx   setembro 2012 - ingles v. final

RAILWAY

Railway access conecting MRS to the Sudeste Superport

13

Page 14: Mmx   setembro 2012 - ingles v. final

Contract signed on December 28th 2011.

Long term contract through 2026.

Provides for a volume of up to 36 million tons of iron ore per year.

Tariff: R$ 26.463/ton , net of tax, readjusted annually by a parametric

formula the variation in IGP-DI and in diesel oil.

MRS CONTRACT

MMX signed a long term contract for railway services

14

Page 15: Mmx   setembro 2012 - ingles v. final

SERRA AZUL

Expansion project with integrated logistic and pellet feed iron ore

Highlights

Production target: 29 Mtpy

64% of production already committed through long-term

contracts

997.4 million tons of reserves already secured by SRK

Execution Update

Beginning of construction of Serra Azul Unit expansion

Construction license issued in April, 2012

Acquisiion of gyratory crushers, ball mills, SAG mills and

vertical mills for the new beneficiation plant

Contract with CNEC WorleyParsons

Contract with MPX to supply power for 15 years at a

base-price of R$125/MWh

Expected Quality – Ouro Preto pilot plant test work

Fe: 67.0% P: 0.03%

SiO2: 3.5% Mn: 0.5%

AL2O3: 0.5% LOI: 0.25%

15

Page 16: Mmx   setembro 2012 - ingles v. final

SERRA AZUL

Growth through consolidation while leveraging existing infrastructure

16

Page 17: Mmx   setembro 2012 - ingles v. final

SERRA AZUL

Serra Azul Unit Expansion Project

New Beneficiation Plant, transmission line and water pipelines, Stockyard and Loading Terminal

Pit

17

Page 18: Mmx   setembro 2012 - ingles v. final

Serra Azul Expansion

Beneficiation Plant18

Page 19: Mmx   setembro 2012 - ingles v. final

Earthwork

19

ConstructionSite and

Warehouse

Maintenanceworkshop

Benefic. substation

Sump andThickners

AdministrativeBuildings

PrimaryCrushing

Grind

Pile

ConstructionSite

Processing

SERRA AZUL

Page 20: Mmx   setembro 2012 - ingles v. final

SUDESTE SUPERPORT

2.2

Page 21: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Location

21

Page 22: Mmx   setembro 2012 - ingles v. final

Nautical Access

Offshore

Tunnel

Stockyard 32

Stockyard 06

Railway Access

Sudeste Superport

Artistic View

22

Page 23: Mmx   setembro 2012 - ingles v. final

SUDESTE SUPERPORT

Overview

Sudeste Superport - Itaguaí

Highlights

50 mtpy capacity, expandable to 100 mtpy

Capesizes handling

Loading: 2 ship loaders of 25 Mtpy each

Fully funded (BNDES)

Start-up forecast: 2Q13

100% of equipment already ordered

Licensing for 100 Mtpy underway

23

Page 24: Mmx   setembro 2012 - ingles v. final

SUDESTE SUPERPORT

Overview

Sudeste Superport - Itaguaí

Highlights

Public hearing for 100 Mtpy held on May, 2012

Tunnel: Meeting of the two excavation fronts as

of September 2011

EIA-RIMA for 100 Mtpy filed with Inea in

September 2011

Licensed to 50 Mtpy

Navy Approval to 100 Mtpy

24

Page 25: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Railway access

25

Page 26: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Stockyard Elevation 6 m

26

Page 27: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Car Dumpers Elevation 6 m

27

Page 28: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Mariquita Hill

28

Page 29: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Stockyard Elevation 32 m

29

Page 30: Mmx   setembro 2012 - ingles v. final

11 m

20.5 m

Sudeste Superport

Tunnel entrance

30

Page 31: Mmx   setembro 2012 - ingles v. final

Sudeste Superport

Tunnel exit

31

Page 32: Mmx   setembro 2012 - ingles v. final

Bridge

450 m

3232

Superporto Sudeste

Offshore Structure - Bridge

Page 33: Mmx   setembro 2012 - ingles v. final

33

Superporto Sudeste

Offshore Structure

Page 34: Mmx   setembro 2012 - ingles v. final

SUDESTE SUPERPORT

34

Shiploader (China)

Page 35: Mmx   setembro 2012 - ingles v. final

SUDESTE SUPERPORT

Shiploader (China)

35

Page 36: Mmx   setembro 2012 - ingles v. final

Assembly of car dumpers

SUDESTE SUPERPORT

Page 37: Mmx   setembro 2012 - ingles v. final

SUDESTE SUPERPORT

Assembly of car dumpers

37

Page 38: Mmx   setembro 2012 - ingles v. final

USIMINAS AGREEMENT

SRK resources audit : 810 million tons

plus a potential 75 million tons

Pau de Vinho target production: 8 Mtpy

Significant synergies with current

mining operations at Serra Azul

13.5% of production at Pau de Vinho

will be delivered to Usiminas

MMX will be responsible for the

licensing, CAPEX and operation for 30

years

Handling fee: USD 12.63/ton adjusted

by US-PPI

Volumes:

■ 12 Mtpy

80% Take-or-Pay

Usiminas can renew the contract for 1

to 5 years

Pau de Vinho Joint Mining Sudeste Superport Handling

38

Page 39: Mmx   setembro 2012 - ingles v. final

BOM SUCESSO

2.3

Page 40: Mmx   setembro 2012 - ingles v. final

BOM SUCESSO

High-quality iron ore with high magnetite content

Highlights

Production target: 10 Mtpy

64% of production already committed through long-term

contracts

Execution Update

Conceptual engineering

SRK resources audit update: 365 million tons plus a

potential of 741 million tons

Expected Quality – Ouro Preto pilot plant test work

Fe: 67.2% P: 0.033%

SiO2: 2.5% PPC: 0.6%

AL2O3: 0.5% FeO: 8.8%

40

Page 41: Mmx   setembro 2012 - ingles v. final

CHILE

3

Page 42: Mmx   setembro 2012 - ingles v. final

CHILE

Highlights

High-quality iron ore with magnetite content

Production target: 10 Mtpy

50% of production already committed through

long-term contracts

460 Mt of iron ore potential

Execution Update

Castilla Port fully licensed

Drilling performed 2011: approximately 43

thousand meters

Water permits

Expected Quality – Ouro Preto pilot plant test work

Fe: 67.50% SiO2: 2.5%

Al2O3: 0.85% P: 0.015%

42

Page 43: Mmx   setembro 2012 - ingles v. final

CHILE

Castilha Port

BERTH N° 1 – COAL

BERTH N° 2 – IRON ORE

BERTH N° 3 – COPPER

Fully Licensed Port

Deep water port – 28 meter draft: Chinamax vessels

Shared construction with MPX (Sister Company)

43

Page 44: Mmx   setembro 2012 - ingles v. final

CORUMBÁ

4

Page 45: Mmx   setembro 2012 - ingles v. final

CORUMBÁ

Highlights

Current Capacity: 2.1 Mtpy

Long-term contracts signed with local and international

barge operators

77% of production already committed through long-term

contracts

SRK audit resources report: 192 million tons plus a

potential of an additional 123 million tons

45

Page 46: Mmx   setembro 2012 - ingles v. final

Investor RelationsGuilherme Escalhão – CEO and IRO

Adriana Marques – ManagerDaniella Maia - Analyst

Phone + 55 21 2555-6197+55 21 2163-4366

[email protected]