MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

download MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

of 34

Transcript of MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    1/34

    Class: MMS (2010-2012)

    Sub : Legal aspects of business

    Topic: 1) RIL-RNRL Dispute

    2) JET-SAHARA Dispute

    Group No: 5

    Submitted to: Prof. Anant Amdekar

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    2/34

    No. NAME ROLL NO.

    1 Mayuri Rathod M1041

    2 Bhakti Redij M1043

    3 Mayuresh Sardesai M10454 Shallot Paul M1047

    5 Rohan Shinde M1049

    6 Tejas Shirodkar M1051

    7 Govind Surwase M1053

    8 Kranti Tondvalkar M1055

    9 Raj Malkan M1057

    10 Vineeta Raju M1059

    Sr. No. Table of Contents

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    3/34

    1) Introduction2) RIL & RNRL3) New Exploration & Licensing Policy I4) Memorandum of Understanding5) Supreme Court Verdict6) Gas Supply Master Agreement7) Conclusion8) Jet-Sahara Deal9) The Deal Falls Apart

    10) The New Deal Strikes11) Tax Liability Dispute12) Legal Issues Involved13) Conclusion14) Bibliography

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    4/34

    Introduction

    While studying these two corporate cases, we have following objectives:

    To understand perspectives of all the parties involved

    To find out and study the legal issues involved in the case

    To study the purpose of law applicable to the case

    To provide suggestions for amendments in law if it has any flaws

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    5/34

    RIL-RNRL Dispute

    Reliance Industries Limited (RIL)

    The Reliance Group was founded by Dhirubhai H. Ambani in 1966 as a polyester firm. The

    Group's activities span exploration and production of oil and gas, petroleum refining and

    marketing, petrochemicals, textiles, retail and special economic zones. The flagship company,

    Reliance Industries Limited, is a Fortune Global 500 company and is the largest private sector

    company in India.

    Reliance enjoys global leadership in its businesses, being the largest polyester yarn and fiber

    producer in the world and among the top five to ten producers in the world in major

    petrochemical products.

    Major Group Companies are Reliance Industries Limited (including main subsidiary Reliance

    Retail limited) and Reliance Industrial Infrastructure Limited.

    Reliance Natural Resources Limited (RNRL)

    Reliance Natural Resources Limited was originally incorporated on the March 24, 2000, under the Companies Act, 1956 as Reliance Platforms Communications.Com Private Limited. The

    status of the Company changed from private limited to public limited on July 25, 2005. The

    name has since been changed to its present name, viz. Reliance Natural Resources Limited.

    Reliance Natural Resources Limited (RNRL) is engaged in the business of sourcing, supply and

    transportation of gas, coal and liquid fuels. The company is concentrating on building a strong

    foundation for the business of fuel management and has already established itself as a contending

    player in the Indian market.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    6/34

    RIL-RNRL dispute- Background

    On 6th

    June, 2002, Mr. Dhirubhai Ambani passed away. Sometime thereafter, differences started between Mukesh Ambani and Anil Ambani over the management and control of the group

    companies. Both the brothers, at the relevant time, were looking after the affairs of RIL in all

    respects, including the group companies. In June 2005, Reliance Group finally got split up. Elder

    brother, Mukesh Ambani managed to receive businesses of petrochemicals and retail whereas

    Anil got telecommunications, financial services, electricity and some more verticals. They signed

    non-compete agreement in each others fields. Moreover, they signed MoU (Memorandum of

    Understanding) stating that RIL would provide RNRL 80 mmscmd (million standard cubic

    meters per day) of gas from the Krishna-Godavari Basin for 17 years at $2.34 per mmbtu

    (Million Metric British Thermal Unit) - for its Dadri power plant. With RIL not supplying the

    gas, RNRL went to court against it for not implementing this part of a family MoU signed when

    the empire was being separated between the two brothers.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    7/34

    What is NELP?

    In 1999, the Government of India announced a New Exploration and Licensing Policy ( NELP I ),1999. This policy provided that various petroleum blocks could be awarded for exploration,

    development, and production of petroleum and gas to private entities. It is the policy of the

    Government that Petroleum Resources which may exist in the territorial waters and the exclusive

    economic zone of India be discovered and exploited with in the overall interest of India and in

    accordance with good international petroleum industry practice.

    RIL-NIKO bids for KG basin

    Krishna-Godavari basin is a basin in India and it is spread across more than 50,000 square

    kilometers in the Krishna River and Godavari River basins in Andhra Pradesh. The site is known

    for the D-6 block where Reliance Industries discovered the biggest natural gas reserves in India

    in 2002. It was also the world's largest gas discovery of 2002.

    In the same year, i.e. 1999, RIL has formed a consortium with the Canadian company-NIKO.

    Their consortium was the successful bidder for Block KG-D6 and was called the Contractor as

    their consortium went into contract with the Indian Government for extracting Natural Gas from

    allotted D-6 block. This contract is further called a Production Sharing Contract (PSC) . Niko has

    a 10 percent interest in the D6 block.

    What was there in PSC under NELP I?

    On 12 th April, 2000, A Production Sharing Contract was entered into between the Government of

    India and the Contractor. As per the PSC, RIL got Block D6 in KG basin as its exploration

    block. The exploration in such areas requires employment of highly skilled and experienced

    technical personnel and an extremely expensive and time-consuming exercise. As per PSC, all

    exploration expenses required to locate petroleum resources have to be borne by the Contractor.

    Therefore, RIL is bound to incur huge cost and resources for discovery of reserves in the area at

    its risk. As per the PSC, all the expenses relating to the exploration, development and production

    of cost incurred by the Contractor could only be recovered from the petroleum/gas actually

    produced and sold by the Contractor. As per PSC under NELP I, the Contractor had freedom

    http://en.wikipedia.org/wiki/Reliance_Industrieshttp://en.wikipedia.org/wiki/Reliance_Industries
  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    8/34

    to sell the gas produced from the block subject to the terms of profit sharing between the

    Government and the RIL as mentioned in the PSC.

    What is MoU?

    A memorandum of understanding (MOU) is a document describing a bilateral or multilateral

    agreement between parties. It expresses a convergence of will between the parties, indicating an

    intended common line of action. It is often used in cases where parties either do not imply a legal

    commitment or in situations where the parties cannot create a legally enforceable agreement.

    What was the MoU between Ambani brothers?

    In 2005, RNRL and RIL signed a memorandum of understanding on the terms under which gas

    would be supplied for the RNRLs Dadri power project in UP.This MoU specified that the price

    at which the gas would be supplied would be the same as the price at which RIL would supply

    gas to an NTPC project. In 2004, RIL made successful bid for NTPC to supply gas at a price of

    2.34 per mmbtu.

    Was the MoU between Ambanis a valid contract?

    MoU was signed by Ambani brothers only in the presence of their mother, Kokilaben Ambani

    and shareholders were not taken into consideration although terms in the deal had capacity toaffect their wealth indirectly.

    Was MoU Limited to only brothers or also binding on their companies?

    MoU was not binding on the company, as it had never been shown to its board of directors. But

    even if it was, RIL would be unable to supply 28 mmscmd of gas to RNRL at $2.34 per mmBtu

    as it contradicted the governments gas pricing and utilization policy.

    Gas Utilization Policy decides the tenure, quantity and receiving parties while providing

    guidelines to all contractors. Policy also gives preference to sectors such as electricity, fertilizers,

    etc.

    Rejection by Oil Ministry for RIL-RNRL deal

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    9/34

    To proceed the deal, RIL sent a pro forma the gas supply master agreement (GSMA) and a gas

    sale and purchase agreement (GSPA). According to which, RIL was to supply 28 million cubic

    meters of gas a day at $2.34 per million units to RNRL for 17 years. RIL sent copy to oil

    ministry for approval of the price. However, Oil ministry refused to approve the price of gas

    agreed to between RNRL and RIL under GSMA saying that natural gas belongs to government

    of India and none of the parties have right to decide the price at which it will be offered.

    Changes in NELP VII

    In 2007, the government changed the model PSC and the changes first came about in NELP VII

    terms around the same time when the RIL RNRL fight was heating up. As per new policy, no

    one other than government can decide the price of Natural Gas. Thus, RIL could not provide gas

    to RNRL at pre-determined price and it also said that it would be totally governments decision

    to fix up pricing. It further asked the companies to whom RIL had planned to supply gas to quote

    rate at which they would prefer to buy. Moreover, it came up with a price on basis of prices

    provided by the concerned companies. This price was later approved by the Oil Ministry of

    India.

    Role of RIL-NTPC deal as a basis for MoU

    NTPC had removed a global tender for supply of gas to its Power projects. RIL succeeded to win

    this bid and NTPC became the first buyer of RIL. According to this bid RIL had to supply 12

    mmscmd (million standard cubic meters per day) of gas to NTPC at $ 2.34/ mmbtu annually for

    a period of 17 years to NTPCs 1,300 MW Kawas and Gandhar projects in Gujarat. NTPC had

    gone for a transparent competitive bidding after which the letter of intent was given to RIL, the

    receipt of which was acknowledged. But the contract could never materialize and NTPC went to

    court against RIL. The lawsuit between NTPC and RIL dates back to December 2005, with the

    point of contention being the existence and terms of a valid contract between the two. The

    royalty loss is expected to be around Rs 25,000 crore over 15 years. RIL had offered to deliver natural gas to NTPC at $3.18 per million British thermal units exclusive of taxes. Under article

    21 of the PSC (Production Sharing Contract), gas sold to the government or any other

    government nominee, is to be valued on terms and conditions, including pricing formula and

    delivery, approved by the government. According to this NTPC can claim gas at $2.34 per

    million British thermal unit, a price RIL had quoted in its tender way back in 2004.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    10/34

    Considering the price of the RIL - NTPC deal and the demand of NTPC that RIL should supply

    gas at $2.34/mmbtu RNRL also demanded gas at the same price from RILs KG D6 block which

    was fixed in the family MOU by the two brothers in its appeal in the court.

    RNRL moved the Bombay High Court

    Due to this approval, RNRL alleged that Oil Ministry favored the RIL while deciding on pricing

    policy and filed petition in Bombay High Court. In June, 2009, The Bombay High Court ruled

    that RIL should supply gas to RNRL at $ 2.34 per mmbtu which was nearly half the $ 4.20 price

    it had set in January, 2009.

    RIL moved the Supreme Court

    The dispute between the Ambani brothers over the gas supply moved the Supreme Court in 2009

    challenging Bombay High Court verdict on the row. The Bombay High Court ordered RIL to

    supply 28 million cubic meters per day of gas from its Krishna-Godavari basin fields at USD

    2.34 per mmBtu-- 44 per cent lower than the government-approved rate-- for 17 years to Anil

    Ambani group firm Reliance Natural Resources Ltd.

    The court gave the two companies a month's time to work out firm gas volumes, price, timelines

    and other commercial details for sourcing the fuel from K-G basin fields.

    Three days after the HC verdict, RNRL on June 19, 2009, filed a caveat before the Supreme

    Court to preclude the chances of an ex parte order (in the interests of one side only) is being

    passed against it on the gas-sharing deal.

    RNRL submitted that it should be given an opportunity to defend the matter before the apex

    court and it moved the Supreme Court seeking modification in the Bombay High Court order to

    make binding the gas supply from Reliance Industries. It alleged that the high court erred indeciding the three terms as to quantity, tenure and price of gas supply to power plants of RNRL

    affiliate.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    11/34

    In the PSC, the government gets a share of RIL's KG profits. Since profits were related to the

    price, the government said that it had the right to vet each contract RIL signs to sell gas. The

    ministry used this to reject the RIL-RNRL contract, saying it was not an arms-length one.

    Oil ministry filed petition in the Supreme Court

    Oil and petroleum ministry also filed a petition in court claiming that KG basin and its natural

    assets are public property .The petroleum ministry said that the Ambani family pact be declared

    null and void. The ministry told the Supreme Court that the Indian government had the sovereign

    ownership over natural gas and its distribution, and RIL was just a contractor on behalf of the

    government. The ministry also stated that the family agreement between the Ambanis could not

    be binding upon the government.

    Petroleum Minister Murli Deora said that the KG basin gas belongs to the government and not to

    either of the Ambani brothers, Mukesh and Anil, who have taken the battle to court.

    The Supreme Court gave verdict

    The Supreme Court judgment on 7 th May, 2010 ruled in favor of Reliance Industries in the RIL-

    RNRL Case that the government was the legal owner of the gas in the RIL-RNRL gas dispute

    and said Government has right to decide price and utilization of fuel, which is a natural asset.

    The government contract overrides any private deal, the court ruled. The apex court also toldRIL and RNRL to renegotiate their deal within a period of six weeks or else the matter could be

    taken to the Company Law Board.

    Gas Supply Master Agreement (GSMA)

    On 25 th June, 2010, RIL and RNRL signed new Gas Supply Master Agreement which was made

    on the basis of directions given by judgment of an apex court. GSMA was compliant with the

    Gas Utilization Policy of the Government and the decisions of the Empowered Group of Ministers. GSMA mentioned that RNRL will get gas from RIL's Krishna-Godavari (KG)-D6

    block, but at prices set by the Government, which will be much higher than the $ 2.34 per

    mmBtu that it had hoped to pay under the terms of an agreement between the two brothers when

    they signed an MoU. The Government will also decide the quantity and the tenure of supply.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    12/34

    Before GSMA, on May 23, both brothers signed an agreement cancelling all existing non-

    compete arrangements between them. Mukesh Ambani also said that his company looked

    forward to a harmonious and constructive relationship with ADAG (Anil Dhirubhai Ambani

    Group) and would provide them gas once RNRLs plants are ready to receive it.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    13/34

    CONCLUSION

    We can say, in early 2000, there were some shortcomings in production sharing contract (PSC)

    and policy-makers had some kind of myopia as government could not foresee consequences of

    terms and conditions of NELP and it seems that some provisions in contract were made

    arbitrarily.

    Besides this, governments attempt to amend law as per its requirement can make people lose

    believe in the judicial system. As government allowed contractors (extracting companies) to

    decide their own price earlier in 2000 and it suddenly changed the pricing policy to protect

    interests of the society. In spite of capital expenditure borne by contractor, law does not have any

    provision by which these companies can fix up the price to required extent.

    As a group, we think that after meeting market demand, government should allow contractors to

    set up price for excessive quantity. Before revising pricing policy, government should inform

    this change to all extracting companies and other concerned entities and should also seek their

    views on such changes before taking final decision.

    However, we also appreciate the way government controls the pricing of Natural Gas which has

    considerable effect on inflation. Government does this in the interest of general public but shouldnot exercise its control at the expense of contractor companies projected earnings at the time of

    getting into PSC.

    As RNRL signed MoU with RIL in 2005, they must have projected their earnings in upcoming

    years. However, government suddenly changed the pricing policy which forced RNRL to revise

    their projected profits because this was going to have a direct impact on the revenue which they

    were expecting. According to changes made by government, RNRL have to depend upon policy

    for the quantity which they would receive from RIL and the tenure in which they would receiveit. It has major consequences on long-term planning/corporate planning of RNRL.

    According to our group, RNRL should have received gas supply from RIL as per the MoU,

    subjected to its validity. But, supplying gas which is a scarce resource to particular company

    probably below market price for 17 years could not have been in the interest of the government

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    14/34

    as well as of general public. But government should not have denied the supply to RNRL and

    could have found out a mid-way solution by which they could have right to regulate the price of

    electricity produced at Dadri plant if RNRL had not charged their customers in the proportion of

    their production cost. But, restricting right to RNRL was harsh decision as it mainly affected

    ADAG. It will make them suffer huge financial loss.

    Moreover, as MoU was signed in 2005 and NELP VII was made in 2007; changes made in

    policy should not be applicable to the contracts which were signed before 2007 as giving

    retrospective legal effect is unfair to the parties involved.

    In case of RIL-NTPC deal, it is already questionable as matter is still in the court of law. RNRL

    considered this deal as a basis for deciding pricing for Natural Gas in MoU. However, while

    taking this basis, it was not aware of legality of the deal. As RIL was a successful bidder in this

    deal, it can be understood that government was aware of fact that RIL would provide gas to

    NTPC at $ 2.34 per mmbtu. Knowing this government did not take any objection on this deal but

    kept RNRL away from deal with RIL i.e. MoU. This was a unfair treatment on the part of

    government. Such approach can hamper relations between government and private players

    especially when government policy is responsible for financial loss suffered by these companies.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    15/34

    JET-SAHARA CASE

    Jet Airways

    Jet Airways is an airline based in Mumbai, India. It is Indias third largest airline after Air India

    and Kingfisher airlines. It operates over 400 daily flights to 64 destinations worldwide. Its

    primary base is Mumbais Chatrapati Shivaji International Airport with secondary hubs at

    Brussels, Chennai, Delhi and Ahmadabad, Bangalore, Hyderabad, Kolkata, Pune as focus cities.

    Jet Airways also operates two low-cost airlines, namely Jet lite (formerly Air Sahara) and Jet

    Airways Konnect. Jet Airways was incorporated as an air taxi operator on 1 April 1992. It started

    Indian commercial airline operations on 5 May 1993 with a fleet of four leased Boeing 737-300

    aircraft. In January 1994, a change in the law enabled Jet Airways to apply for scheduled airline

    status, which was granted on 4 January 1995. It began international operations to Sri Lanka in

    March 2004. While the company is listed on the BSE, 80% of its stock is controlled by Naresh

    Goyal.

    Air Sahara

    The airline was established on 20 September 1991 and began operations on 3 December

    1993 with two Boeing 737-200 aircraft as Sahara Airlines. Initially services were primarily

    concentrated in the northern sectors of India, keeping Delhi as its base, and then operations were

    extended to cover all the country. Sahara Airlines was rebranded as Air Sahara on 2 October

    2000, although Sahara Airlines remains the carrier's registered name. On 22 March 2004 it

    became an international carrier with the start of flights from Chennai to Colombo. It is part of the

    major Sahara India Pariwar business conglomerate. The uncertainty over the airline's fate has

    caused its share of the domestic Indian air transport market go down from approximately 11% in

    January 2006 to a reported 8.5% in April.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    16/34

    The Background

    In 2005 Sahara group got in touch with management consultants to chalk out a road map for the

    airline component of its business. There was a clear feeling amongst the management that the

    airline could not remain at the existing size and it either needed to grow or consolidate.

    In the beginning the option of bringing in private equity was examined. But, Ernst and Young,

    the consultants to Air Sahara felt that this model would not work here due to infrastructure

    bottlenecks. Also, according to one of the airline official money could have been raised through

    an IPO, but, the utilization of money would not have been that fast. Eventually, however, the top

    management of the Sahara Group veered around to the view that it would be best to exit the

    airline business and instead focus more on areas such as Para banking and real estate

    development.

    The management of Air Sahara then got into talks with Jet Airways. When asked why the airline

    was in talks only with Jet Airways, the then Exec VP Mr. Sharma said that there was a lot of

    commonality between the two airlines. Both were full service airlines, and the kind of aircraft

    that both operated were similar.

    A couple of glitches cropped up during the negotiations. One was the sponsorship deal of the

    Indian cricket team by Sahara. In the previous month, Air Sahara won the right to sponsor the

    Indian cricket team for the next four years for Rs 313.80 crore. Sources said that the balance

    sheet of the airline company was submitted during the bidding process and this could turn into a

    liability for the acquiring company.

    Officials in investment banking circles said that since Jet was not very keen on sponsoring

    cricket, it was unlikely to pick up the cricket tab. But the sale of the airline would not create

    problems for the team sponsorship. Officials of the Board of Control for Cricket in India

    maintained that the logo of any other Sahara group company could be used, and the deal was notrestricted to Air Sahara alone.

    Another hitch in the buyout negotiations is said to be indications from Government sources that

    any sale would not mean an automatic transfer of flying rights.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    17/34

    The Deal

    Due Diligence

    Before signing on the deal, detailed due diligence was done. A complete report on the balance

    sheet and the operations of the airline was available. This was also discussed at a board meeting

    attended by the entire board in late January, 2006. Moreover, the indemnification clause in the

    SPA provided for indemnification of liability not disclosed in vendor due diligence. The report

    was based on a joint certification by Ernst &Young and Chaturvedi and Shah (the auditors of

    Sahara and Jet Airways, respectively). After that anything more that shows up was a subject

    matter of indemnification, which means that Air Sahara would have to pay for any other

    liabilities that arise. So, there was no the question of suddenly discovering huge liabilities.

    Contingent contract

    Finally, signing of the largest deal in Indian aviation between Air Sahara and Jet Airways on

    January 19, 2006 brought to an end a process that had started around July 2005. Under the

    agreement signed for the buyout on January 19, Jet had put an enterprise value of $500 million

    (Rs 2,217 crore) on Air Sahara. This amount took into account all the liabilities of Sahara. The

    contract signed was a contingent contract which states that certain pre-requisites (like obtaining

    all necessary approvals from government) need to be filled to have a deal in place. And it wasdrafted in such a way that Jet Airways could walk out of the deal without any liabilities if the

    deal doesnt materialize.

    Legal Clearances

    The first step towards the integration of Air Sahara with Jet Airways had been initiated with

    documents seeking formal clearance for the buyout being submitted to the authorities. Several

    approvals from different departments like the Aircraft Acquisition Committee (AAC), MRTPC,

    civil aviation, government approval and security clearances were necessary for the deal to go

    through.

    In March 30, 2006, after a detailed review, the Aircraft Acquisition Committee cleared the 100%

    transfer of Saharas assets to Jet, including the transfer of properties as well as rights to parking

    bays and slots. The Ministry of Company Affairs also gave its green signal to the merger under

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    18/34

    section 108A of the Companies Act, 1956, under which the Central Governments prior approval

    has to be taken if a corporate body acquires more than 25% of the paid-up equity share capital of

    a public company, and either the acquirer or the target is a dominant undertaking (i.e., it controls

    25% or more of any services that are rendered in India).

    MRTPC approval

    BJP MP, Uday Singh, was responsible for deal being probed by MRTP Commission as he

    complained of the deal and then PMO (Prime Ministers Office) had to intervene the matter. On

    22nd May, 2006, MRTPC gave its go ahead after the Director General of Investigation and

    Registration (DGIR) found that the merger between the two entities did not violate the

    provisions of the Monopolies and Restrictive Trade Practices Act, 1969 (MRTP Act) .

    Experts view

    Mr. Prem Chand Gupta, then Minister of State for Company Affairs said " being large or in a

    dominant position per se is not a problem, unless an entity indulges in abuse of dominant

    position. And there are provisions in the MRTP Act where the Ministry can take action if abuse

    of dominance is found ."

    Evidence of abuse of dominant position

    If the firm is charging excessively high prices; However, this might be difficult to judge but if they are making high profits then this is an indication.

    Predatory Pricing. This involves cutting prices and selling below average cost to forcerivals out of business.

    As merged entity had not started functioning then, abuse of dominance was not applicable tothe deal.

    An Escrow Account

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    19/34

    An escrow account was then set up with the ICICI bank to facilitate the deal and deposited Rs

    500 crores against the banks guarantee. Escrow generally refers to money held by a third-party

    on behalf of transacting parties. An escrow account is an account established by a broker (third

    party), for the purpose of holding funds on behalf of the broker's principal or some other person

    until the completion or termination of a transaction. There was a 65 day deadline (March 24 th

    2006) for the acquisition to be completed.

    Share Purchase Agreement crosses the deadline

    The agreement, signed on January 19 th 2006, created a mental picture that Air Sahara's entire

    aviation business, including some aircraft leases, real estate and assets such as auxiliary power

    units and engines, being acquired by Jet Airways. The deal seemed almost through before reports

    started coming in about Jet Airways having second thoughts on the buyout. This was reportedly

    because the Government might not be likely to allot all the landing and parking rights of Sahara

    to Jet, said to be one of the main considerations behind the Jet acquisition move. Other

    unconfirmed reports suggested that on inspection, Jet had found the quality of Sahara assets

    below expectations.

    Despite all this, Jet Airways has agreed to pay an advance of Rs 500 crore to Air Sahara as part-

    payment for buying out the latter , thereby, putting at rest speculation that the deal had run into

    rough weather. The airline then announced that it has reached an understanding with Sahara

    Airlines and its shareholders to extend the share purchase agreement just before the 65 day

    deadline expired on March 24 th 2006. The two airlines have also agreed to extend the term of the

    Escrow Arrangement by 90 days.

    According to revised period, Jet was told to get an approval for share purchase agreement (SPA)

    from government by 21 st June, 2006. Failing to do so was to be led by cancellation of the deal.

    Jet awaited Government approval for the share purchase agreement and security clearance of the board of directors as the deadline approached. However, Home Ministry gave its approval on

    22nd June, 2006. This led to cancellation of the deal.

    Why Ministry failed to meet deadline?

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    20/34

    In Indian Aviation Industry, when the new company is being created and whenever that happens,

    clearances from the Directorate-General of Civil Aviation (DGCA) are required. Generally, the

    DGCA gives clearances to the Board after the names have been given security clearance by the

    Home Ministry. However, reports came out that Mr. Naresh Goyal, Owner of Jet Airways, has

    links with Al Qaida and Lashkar-e-Taiba. Due to this, ministry could not give security clearance

    to Mr. Goyal as director on the Board of merged entity.

    The Deal falls apart

    Unclear Guidelines

    The policy related to mergers and acquisition in the aircraft industry did not clearly specify the

    terms of transfer for airport infrastructure. The guidelines though clear on parking bays and

    landing slots, did not specify the status of aircraft hangars, check-in counters, cargo warehouses,

    passenger lounges and other such airport facilities.

    However, on 11 th May, 2006, the Minister for Civil Aviation, Mr. Praful Patel told the Lok Sabha

    that the Government had accepted the recommendations of the Ministry's AAC and the policy on

    the use of airport infrastructure in the case of merger or takeover of airlines and sale or transfer

    of aircraft approved by the competent authority.

    Difference of opinions

    International flying rights was probably the single most valuable asset of Air Sahara that

    attracted Jet Airways to buy the airline. However, the regulatory body i.e. Director General of

    Civil Aviation and the Civil Aviation Minister had different opinions on the automatic transfer of

    Sahara's flying rights to Jet Airways. DGCA officials opined that Jet would have to re-apply for

    such rights and the re-allocation would be done based on Jet's requirements. However, the Civil

    Aviation Minister, Praful Patel was clear that rights were considered the asset of an organization

    and like other assets; it would get transferred to the buyer.

    Overvaluation

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    21/34

    Also, Jet Airways enthusiastically overvalued Air Sahara, and later wanted a discount on the

    original price (20 to 25 percent). This is typically a case of overvaluing a company whose

    business model was not that profitable.

    Non-cooperation by parties involved

    The collapse of the deal for Jet Airways to acquire Air Sahara could have been avoided if both

    the airlines had sent a letter to the Directorate-General of Civil Aviation (DGCA) agreeing to

    constitute the board with four persons.

    Consequently, Government could not approve Share Purchase Agreement before the deadline of

    21st June, 2006. After haggling for a price discount, Jet finally walked out of the deal in June

    2006, after operating Air Sahara for about three months in which Jet had infused 160 crores as

    operating expenses. This was possible because the agreement between the two parties was

    drafted such that if the necessary conditions precedent the deal (like obtaining government

    approvals etc) were not met, then the party (Jet Airways) would walk out of the deal without anyliability. Consequently, both the airlines moved the court.

    Both the sides hired the best legal brains Mr. Harish Salve by Jet Airways and Mr. Fali

    Nariman by Air Sahara.

    Contrived Breach of Contract

    Unfortunately, in most cases, conditions precedent are not met because one or the other party did

    not want them met and this opens the door on several challenges that lawyers must meet.

    First, there is the problem of inaction. If a seller is to achieve the conditions precedent, and the

    market is bullish, he can easily make a deal with the buyer and then wait for a better deal to

    come along. If it does, the seller makes sure that conditions precedent under the first deal are not

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    22/34

    met, waits for the deadline to pass and then goes and makes a new deal with a new buyer on

    better terms. Conditions precedent sometimes make an options contract out of a binding one and

    the legal challenge is not only to compel all contracting parties to make a reasonable bona fide

    effort to achieve the condition precedent but to also penalize anyone who tries to profit from

    failing to do so. This is never simple because it is never easy to prove.

    Thus inaction, if any, on the part of Jet Airways was the reason perceived to be the cause for the

    delay as per the legal experts. However, as we have seen above, this is very tough to prove and

    hence cannot be categorically stated.

    The Battle reaches court

    Freezing an escrow account

    Each of the private carriers took recourse to legal action. Developments took a surprising turn

    when Air Sahara moved a Lucknow court and got an interim order restraining Jet from

    withdrawing Rs. 500 crore from the escrow account. Jet moved to the Bombay High Court

    seeking a similar restraint on Air Sahara, saying the conditions agreed upon such as transfer of

    infrastructure by June 21 had not been met. Hence, Air Sahara should not be allowed to operate

    the escrow account.

    Mr. Goyal had taken the legal battle with Sahara chief Mr. Subrata Roy a few notches higher by

    filing a petition with the Bombay High Court, holding Mr. Roy personally liable for refunding

    Rs 500 crore by July 4. According to the Jet petition, Mr. Roy had stood as a personal guarantor

    to the deal. Sahara was to refund Rs 500 crore paid as guarantee money within seven days of the

    termination of the agreement.

    Air Sahara petitioned the Lucknow court, saying that Jet Airways terminated the takeover

    agreement and secured an interim stay on operation of escrow account till June 23, 2006. District

    and Sessions Judge Shiv Charan Singh also restrained ICICI Bank, where the account has been

    opened, not to make any payment to Jet Airways.

    In his interim order Mr. Singh said: " It has been alleged on behalf of the petitioner that the

    opposite party (Jet Airways) has terminated the contract, hence there is a dispute, for which

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    23/34

    arbitrator is to be appointed in due course. " The court gave Jet Airways time till June 23 to file

    objections to Sahara's contention on the deal.

    The order came on a petition filed by Sahara India Commercial Corporation Ltd, holding

    company of Air Sahara, under Section 9 of the Arbitration and Conciliation Act.

    While parking the entire money for the deal in the account, Jet had paid Rs. 500 crore against

    guarantees to Air Sahara in March and given an advance of Rs. 100 crore to Sahara without

    guarantees. Under the agreement, Air Sahara was entitled to claim Rs. 500 crore from the escrow

    agent only on completion of the takeover. According to the deal, Jet maintained that Sahara

    had to repay Rs. 500 crore within seven days of termination of the agreement without any

    dispute.

    Set-up of Arbitration Tribunal

    In August, 2006, the Supreme Court transferred two petitions filed by Sahara in a Lucknow court

    to the Bombay High Court for hearing. An arbitration panel was set up to deal with the case

    under Bombay high court jurisdiction. The three-member tribunal consisted of retired Supreme

    Court chief justices S P Bharucha, Jeevan Reddy and Lord Stein.

    On November 26, Air Sahara claimed an amount of Rs. 3020 crore before the Arbitration

    Tribunal.

    New Deal Strikes

    External Pressure

    During this period (Jan 2006-April 2007), many low-cost carriers captured the more market

    share. Air Deccan managed to get almost 33% market share. Air Saharas market share dropped

    from 12% to 8%. Dispute led to a sharp decline in the stock market valuations for Jet Airways

    over this period. The market capitalization of Jet Airways got shrunk from Rs 9,200 crore to Rs

    5,400 crore a 41 per cent drop. Deal created almost negative environment in aviation industry.

    Both the parties started realizing that legal procedure is not taking them anywhere but to a loss of

    opportunity cost.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    24/34

    Out-of-court settlement

    It is also understood that both the parties were in constant touch with each other and were trying

    to reach deal in some or other way. It was also reported that the legal working draft of the

    agreement was exchanged at the meeting which happened in Oberoi hotel and representatives of

    both the parties were present for the same . Finally, parties submitted a revised Share Purchase

    Agreement to Arbitration panel and on April 17, 2007, a new deal was signed. As per the new

    deal, Jet Airways agreed to buy out Air Sahara for Rs 1,450 crore, which was about 40 per cent

    less than the Rs 2,217 crore that Jet had agreed to pay for the acquisition in January 2006.

    An all-cash deal was struck between the two parties with Jet Airways paying Air Sahara Rs 400

    crore immediately to seal the deal. In addition, from March 2008, Jet Airways would pay

    interest-free installments Rs 137.50 crore annually for the next four years to Air Sahara.

    Air Sahara was further rebranded as JetLite.

    Is Jet Airways a real winner?

    Benefits

    The buyout made the merged entity the largest domestic private carrier, with a market share of about 42 per cent and a fleet of 88 aircraft, including the 27 operated by Air Sahara. The buyout

    not only allowed Jet Airways to operate on Air Saharas routes but also helped Jet in its plans to

    go international.

    While reacting to the development, the Jet Airways stock increased by 3.24 per cent to close at

    Rs 628.65 on the BSE on 12 th April, 2007.

    Still long way to go

    If we look at total sale consideration of 1450 crore, it represents almost 34 per cent discount to

    the original acquisition price of Rs 2,217 crore agreed to by the two companies in January 2006.

    However, Air Saharas market share dropped from 12% to 8% when aviation industry was

    growing at considerable rate.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    25/34

    Deal did not mention anything about the cash invested by Jet in Air Sahara as an operational

    expense. Jet also allowed Sahara to retain some tangible as well as intangible assets. Jet also

    decided to retain the entire staff of the acquired operations, as opposed to its earlier plan of

    absorbing only the pilots and technical staff.

    Default in payment of installment (2008)

    In March 2008, the income-tax department demanded pending taxes of Rs 37 crore from Sahara,

    then owned by Jet. Jet Airways argued that since the amount was due from Sahara before the

    deal, it was not responsible for the liability. Jet cleared the income-tax demand but deducted

    Rs37 crore while paying its March 2008 installment to Sahara.

    Failure to Out-of-court settlement

    In June, 2009, court asked them to settle the matter on their own. It was also reported that Jet

    Airways proposed to pay around Rs300 crore to Sahara as an advance payment to settle.

    In December 2009, both the parties informed High Court that they failed to reach an out-of-court

    settlement.

    Sahara claimed that Jet had defaulted on its payment commitment and filed an application in

    Bombay High Court. However, Jet Airways maintained that it deducted Rs 87.50 crore from the

    two installments after a tax demand of 107 crore was raised by the IT department which was for

    the period prior to the takeover. It deducted Rs 37.50 crore from the first installment and Rs 50

    crore from the second installment as the airline claimed that it had deposited the amount.

    According to the buy-out agreement , Jet Airways was to pay the Sahara Group Rs 550 crore in

    four installments of Rs 137.50 crore each from March 2008.

    Claiming that Jet had defaulted on payment of the installment, SICCL (Sahara India Commercial

    Corporation Limited) sought court direction for attachment of some of the carriers movable

    properties. In the course of successive Court hearings, Jet claimed that there was an IT demand

    of Rs 1,032 crore on Air Sahara which Jet is now liable to pay. The Rs 87.50 crore deductions

    were made on the grounds that as per the share purchase agreement, any tax liability arising in

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    26/34

    excess of Rs 50 crore would have to be reimbursed by Sahara . Jet is now seeking

    reimbursement of the balance Rs 821 crore while defending its decision to deduct a part of the IT

    dues from the installments.

    Sahara, on the other hand, has accused Jet of breaching a clause of the agreement which

    stipulated that it had to pay the four installments in full without any setoff or deduction . As a

    result, Sahara argued the negotiated price of Rs 1,450 crore would be revoked and Jet would

    have to pay the originally agreed Rs 2,000 crore.

    Ernst and Young report is the Key

    On 15 th July, 2010, after hearing arguments from counsels of Jet Airways and Sahara India

    Commercial Corporation the Bombay High Court asked both counsels to furnish details on thetax liabilities stated in the due diligence report by Ernst & Young. The report was prepared in

    2006 by E&Y on Sahara Airlines, prior to its takeover by Jet.

    The E&Y report came under the scanner as Sahara claimed in the Court that the report did

    disclose the disputed tax liability.

    Jet, however, said that the tax liability had not been disclosed, and was merely mentioned as

    other income'. Of this, disclosed liability was Rs 124.35 crore and undisclosed liability was Rs908 crore.

    Jet further argued that even after deducting Rs 87 crore from the undisclosed liability', which it

    claimed to have paid to the I-T department there is still a tax liability demand of Rs 821 crore

    from Sahara Airlines.

    On December 20, 2010, Bombay High Court reserved the order in this case. The order was

    reserved by Justice Dhananjay Chandrachud but did not disclose about when the verdict wouldhappen.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    27/34

    Legal issues in Jet-Sahara deal

    The MRTP Act, 1969

    The MRTP Act 1969 came into existence on 1 st June 1970. The Monopolies and Restrictive

    Trade Practices Act, 1969, aims to prevent concentration of economic power to the common

    detriment, provide for control of monopolies and probation of monopolistic, restrictive and

    unfair trade practice, and protect interest.

    The Monopolistic and Restrictive Trade Practices Act, 1969, was enacted1. To ensure that the operation of the economic system does not result in the concentration

    of economic power in hands of few,

    2. To provide for the control of monopolies, and

    3. To prohibit monopolistic and restrictive trade practices.

    The MRTP Act extends to the whole of India except Jammu and Kashmir. Unless the

    Central Government otherwise directs, this act shall not apply to:

    1. Any undertaking owned or controlled by the Government Company,

    2. Any undertaking owned or controlled by the Government,

    3. Any undertaking owned or controlled by a corporation (not being a company established

    by or under any Central, Provincial or State Act),

    4. Any trade union or other association of workmen or employees formed for their own

    reasonable protection as such workmen or employees,

    5. Any undertaking engaged in an industry, the management of which has been taken over

    by any person or body of persons under powers by the Central Government,6. Any undertaking owned by a co-operative society formed and registered under any

    Central, Provincial or state Act,

    7. Any financial institution.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    28/34

    The Competition Act, 2002

    The Competition Act, 2002, which still hasnt been completely enforced as yet, was devised as a

    replacement of the Monopolies and Restrictive Trade Practices (MRTP) Act, 1969. This act

    moved away from the earlier emphasis of curbing monopolies in particular industries, to a more

    particular and directed approach towards promoting competition and thereby increasing the size

    and scope of industry. Better competition is believed to lead to higher efficiency in competing

    companies, thereby leading to a better allocation of given resources.

    Contingent Contract

    Section 31 of the Indian contract act defines contingent contract as A contract to do or not to

    do something if some event, collateral to such contract, does or does not happen.

    So in simple word, it may be defined as a conditional contract.

    Essential elements of valid contingent contract

    1. There must be valid contract.

    2. The performance of the contract must be conditional.

    3. The event must be future uncertain.

    4. The event must be collateral to the contract.

    Rules regarding the enforcement of the contingent contract

    Section 32 - It depends on the happening of the future uncertain event. So the contract will be

    enforced only if the uncertain event has happened.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    29/34

    In other words, the law says that if I agreed to fly you to Malaysia as soon as I get my license,

    you will have to wait for me to die because only then would you be sure I can't fulfill a contract

    to personally fly you to Malaysia. The converse is equally true.

    Section 33 - It depends on the Non-happening of the future uncertain event. So the contract will

    be enforced only if the happening of that uncertain event becomes impossible as that event

    cannot happen.

    This means that if you agreed to pay me to never fly to Malaysia, you won't have to pay me till I

    die because so long as I am alive, I can always fly to Malaysia.

    Section 35 - It depends on the happening of the specified uncertain event within the fixed time.

    So the contract will be enforced only if the uncertain event happens with in the fixed time.

    Section 35 (second Para) It depends on the Non-Happening of the specified uncertain event

    within the fixed time. So the contract will be enforced only if the happening of that uncertain

    event becomes impossible within the fixed time as that event cannot happen.

    Contingent contract dependent on the impossible event is void and cannot be enforced by law as

    the impossible event will never happen. This will be void whether the impossibility of the event

    is known or not to the parties at that time of making the contract.

    The buyout Agreement

    A Buyout Agreement is a legal agreement between the owners of a business that sets out how the

    future sale or buyout of an owner's interest in the business will be handled. A buyout agreement

    may also stipulate whether or not a departing partner has to be bought out and what specific

    events will trigger a buyout.

    If you are entering a business partnership, you should set up a buyout agreement when you create

    your partnership agreement. It can be part of your partnership agreement itself or stand alone as a

    separate legal document.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    30/34

    The buyout agreement ensures that when one partner wants to quit, becomes bankrupt, divorced,

    incapacitated or dies, the other partners will be able to continue to carry on the business. Without

    a buyout agreement, when one partner wants or has to leave, your partnership may be forced to

    dissolve and/or you could end up in court.

    Indemnification Clause

    An indemnification clause is a clause in a contract which states that a party to the contract agrees

    to compensate the other party for any losses incurred as a result of the performance of the

    contract or in association with the contract. Many times an indemnification clause is brought up

    in the case of third-party claims. In this case, IT department is a third-Party who asked Jet

    Airways to Air Saharas taxes.

    However, an indemnification clause should have clarity and contain legal subject matter.

    Otherwise, court can limit its interpretation and make it unenforceable.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    31/34

    CONCLUSION

    According to our group, this case is one of the complex matters in Indian corporate history which

    has unavoidable impact on aviation industry.

    MRTP act has no role to play in this deal. This is because a merged entity had not started

    functioning when MRTPC scrutinized the deal. To be dominant player in market cannot be an

    offence under any law. Thus, provisions in MRTP act were not applicable to Jet-Sahara deal.

    Although it is understood that the involved parties settled the case outside the court due to

    cumbersome legal procedures, Air Sahara was also allegedly responsible for hiding its liabilities

    in due diligence procedure. Moreover, the collapse of the deal could have been avoided if both

    the airlines had sent a letter to the Directorate-General of Civil Aviation (DGCA) agreeing to

    constitute the board with four persons before the deadline. Thus, partys non-cooperation to

    government is also responsible for failure of deal.

    According to our group, a failure to do a detailed scrutiny of liabilities of Air Sahara was mainly

    responsible for failure of deal in May, 2006.

    The crucial factor which brought both the parties together to settle the issue outside the court was

    opportunity cost due to delay in legal procedure. Although one party could have benefitted by

    continuing the help from the court of law but it was still unclear that how much monetary and

    strategic benefit the winning party could have got in actual terms.

    A vague policy related to mergers and acquisition in the aircraft industry could not clearly

    specify the terms of transfer for airport infrastructure. This was also one of the reasons due to

    which concerned parties always doubted about valuation of deal.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    32/34

    Government is also not able to strike a balance between the pace at which Indian Aviation

    industry is growing and the pace at which laws related to merger and acquisitions in the industry

    are being modified.

    According our group, it is difficult to mention winner in this deal before all the legal issues are

    sorted out. Moreover, it depends upon how efficiently Jet will use JetLites resources in order to

    improve its profitability. Hence, only upcoming period can decide who has ultimately won the

    battle.

    Furthermore, we can say that verdict on tax liability issue will be largely dependent upon Ernst

    and Youngs report and Indemnification clause in Share Purchase Agreement.

    At the end, as a group, we also cannot deny occurrence of financial fraud in this much-awaited

    case.

  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    33/34

    BIBLIOGRPHY

    Newspapers:

    Economic Times

    Mint

    Hindu

    Websites:

    www.law4india.com

    www.petroleum.nic.in

    www.mca.gov.in

    Books:

    Business law (S. S. Gulshan)

    The Indian Contract Act, 1872 (Bare Act)

    http://www.law4india.com/http://www.petroleum.nic.in/http://www.mca.gov.in/http://www.law4india.com/http://www.petroleum.nic.in/http://www.mca.gov.in/
  • 8/4/2019 MMS_Group_5 Law (Ril Rnrl & Jet Sahara)Final

    34/34