MITIGATION PLAN AND MONITORING PLAN · PDF fileE2417 v2 MITIGATION PLAN AND MONITORING PLAN...

35
E2417 v2 MITIGATION PLAN AND MONITORING PLAN for Feasibility Study “Introduction of Energy-Saving Technologies in Railroad Traffic on the Znamianka –Vadym Track Section of the Znamianka–Dolynska–Mykolaiv–Kherson–Djankoi Route” Odessa Railroad 2009 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized closure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized closure Authorized

Transcript of MITIGATION PLAN AND MONITORING PLAN · PDF fileE2417 v2 MITIGATION PLAN AND MONITORING PLAN...

E2417 v2

MITIGATION PLAN AND MONITORING PLAN

for Feasibility Study “Introduction of Energy-Saving Technologies in Railroad Trafficon the Znamianka –Vadym Track Section

of the Znamianka–Dolynska–Mykolaiv–Kherson–Djankoi Route”

Odessa Railroad

2009

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

2

Introduction

The project development objective (PDO) is to :

− substantially increase thecapacity of the railway related to transport of goodsand passengers

− to improve traffic conditions, road-service qualities and technical standards.

This project includes2 main components:

Component A: electrification of the track section Znamianka – Vadym

Component B: construction of the second rail track

The proposed FS ''Introduction of Energy-Saving Technologies in Railroad Traffic on the Znamianka –Vadym Track Section of the Znamianka–Dolynska–Mykolaiv–Kherson–Djankoi Route” is in full compliance with all environmental requirements of the Government of Ukraine and theWorld Bank. In accordance with the World Bank Environmental Assessment (EA) safeguard policy and procedures (OP/BP/GP 4.01) the projecthas been assigned Category B and an Environmental Management Plan is required.Environmental Management Plan includes following chapters:

• Part A – Project Description• Part B – Mitigation Plan• Part C – Monitoring Plan• Part D – Description of Institutional Arrangements• Part E – Results of Public Consultations with all interested parties

3

.1. PROJECT DESCRIPTION

Chapter ’’Environmental Impact Assessment’’ to FS ’’ Introduction of Energy-Saving Technologies in Railroad Traffic on theZnamianka –VadymTrack Section of the Znamianka – Dolynska – Mykolaiv – Kherson – Djankoi Route’’

The Feasibility study provides for:

− Construction of the second track 328,43 km long including upgrading of the existing track – 13,45 km long;

− Construction of a contact network 860,7 km long.

In view of electrification of the track construction of new ESTs is foreseen at all stations and junctions, traction substations and duty postsbuildings of the contact network at stations Mykolaiv, Novopoltavka, Kherson and Brylivka; locomotive maintenance points at stations Mykolaivand Kherson.

Construction of the second track and its operation facilities is foreseen in the roadbed of the railway so there is no need for extra land.

Introduction of energy saving technologies in railroad traffic on the Znamianka – Vadym track section resulted in the improvement ofenvironmental conditions at the expense of exclusion of emmisions into the air of diesel fuel combastion products with total amount of 9375,3t/year.

For the disposal of wastewater from the service and technical buildings at stations Velyki Kopani, Radenske, Novokyivka, junctions Chehovychi,Kotlyareve, Horokhivka, Hreyhove, Lotskyne, Horozhene, and junctions Dobrovilsky, Kazanka, Novodanylivka, Kutsivka, Maderove, Tsukrovapurification installations of the Biotal type will the built with a productivity of 2 m3/day and the treated wastewater will be discharged into filtrationyards.

At stations Vadym, Kalanchak, Brylivks, Tsiuryupynsk, Novopoltavka, Sharivka, junction 5 km - purification installations of the Biotal type with aproductivity of 7 m3/day.

To purify surface flows at the CDAP of stations Kherosn, Brylivka, Mykolaiv and Novopoltavka purification plants with a regulating holdingcapacity will be built.

In the process of construction and operation of facilities construction and domestic waste is disposed, the removal of waste is carried out accordingto the concluded agreements.

The introduction of energy-saving technologies will reduce to a minimum the impact on the environment, agricultural output, landscape, as well asthe flora and fauna. The elimination of emissions of diesel fuel combustion into the atmosphere (carbon monoxide, sulfurous anhydride, nitrogendioxide and soot) will reduce the area’s background pollution, all of which will have a positive effect on the environment.

Since the estimated noise levels in the buffer area will not increase, the FS does not foresee any additional measures.

4

Measures – namely safety, technological and planning measures – have been developed to assure a standard status of the environment.

Measures have been undertaken to protect line-cable communication facilities from electromagnetic impact.

Measures are also foreseen in a scope that is necessary to protect warehouses and structures against sparking of highly inflammable liquid fuels andgases.

Ionizing radiation and ultrasound are absent.

In the course of introduction of energy saving technologies in railroad traffic on the route Znamianka – Dolynska – Mykolaiv – Kherson – Djankoi –Vadym and electrification of the route along with construction of the second track the environment will be impacted.

The environment will be impacted in the following way during the construction process:

− Traffic comlications

− Increased noise level

− Pollution of adjecent areas with dust

− Air pollution by the used gases from the construction equipment.

During operation the impact will be as follows:

− Traffic noise

− Electromagnetic radiation

− Vibrations from railway traffic

− Gas emissions from heating equipment

− Gas emissions from welding equipment

− Water consumption and water discharge.

The public has been informed about the FS '' Introduction of Energy-Saving Technologies in Railroad Traffic on the Znamianka –Vadym TrackSection of the Znamianka – Dolynska – Mykolaiv – Kherson – Djankoi Route’’, its purpose and ways of implementation through media and publicconsultations in Kirovohrad, Mykolaiv and Kherson oblasts.

5

Part B: Mitigation Plan

B. MITIGATION PLANCost Institutional responsibility

Phase Issue Mitigating measureInstall Operate Install Operate

Comments(e.g. secondary impacts)

Construction • Material supplya)Asphalt plant

dust, fumes, workershealth and safety,ecosystem disturbance

a) useexisting asphalt plants;requirement for official approval orvalid operating license

a) NA a) NA a)-Asphalt plant a)-Asphalt plant a)-c) to be specified in biddocuments-Conditions forselection of subcontractorsfor material supply

b)Stone quarrydust, workers healthand safety, ecosystemdisturbance

b) useexisting stone quarries;requirement for official approval orvalid operating license

b) NA b) NA b) Stone quarry b) Stone quarry

c) Sand and gravelborrow pitdisturbance of riverbed, water quality,ecosystem disturbance

c) useexisting borrow pits or buymaterial at licensed separations;requirement for official approval orvalid operating license

c) NA c) NA c) Supplier of sand orgravel or licensedseparation

c) Supplier of sandor gravel orlicensed separation

• Material transporta)Asphalt

dust, fumesa) cover truck load a) mini

mala) mini

mala) Truck operator a) Truck operator a)-d) to bespecified in bid

documents-Technicalb)Stone

Dustb) wet or cover truck load b) mini

malb) mini

malb) Truck operator b) Truck operator Specifications for realization

of worksc) Sand and gravel

Dustc) wet or cover truck load c) mini

malc) mini

malc) Truck operator c) Truck operator

d)Traffic managementnoise, vehicle exhaust,road congestion

d) haul material at off peak traffichours; use alternative routes tominimizemajor traffic sites

d) NA d) minimal

d) Transportmanager; Truckoperator

d) Transportmanager; Truckoperator

• Construction sitea) Noise disturbance to

human and animalpopulation andworkers

a) limit activities to daylight workinghours (not between 8 p.m. and 7a.m. or as agreed with public andauthorities); equipment operatingwith noise mufflers

a) NA;minimal

a) NA;minimal

a) ConstructionContractor

a) ConstructionContractor

a)-k) to be specified in biddocuments-TechnicalSpecifications forrealization of works

6

Cost Institutional responsibilityPhase Issue Mitigating measure

Install Operate Install Operate

Comments(e.g. secondary impacts)

b) Dust b) water construction siteandmaterial storage sites asappropriate

b)minimal

b)minimal

b) ConstructionContractor

b) ConstructionContractor

c) Vibrations resultingfrom equipment work

c) limit work activities to daylightworking hours (not between 8 p.m.and7 a.m. or as agreed with public andauthorities)

c)NA c)NA c) ConstructionContractor

c) ConstructionContractor

d) Traffic disruptionduring constructionactivity

d) traffic management plan withappropriate measures to redirecttraffic that are easily seen or easyto follow; include traffic police

d)minimal

d)minimal

d) ConstructionContractor

d) ConstructionContractor

e) Vehicle and pedestriansafety when there is noconstruction activity

e)- appropriate lighting and well

defined safety signs- when carrying out construction

activities in populated places it isnecessary to fence the jobsiteand set direction signs forvehiclesand pedestrians

- strict compliancewith right ofway: marking permanent andtemporary right of way withranging poles is recommended

e)minimal

e)minimal

e) ConstructionContractor

e) ConstructionContractor

f) Air, water and soilpollution fromimproper materialstorage, managementand usage

f)- prevention of inadmissible

pollution of the soil and airwith waste by keepingconcrete aggregates (roadmetal, sand) in specialstoragesat theconstructionsite

- undertaking measures toprevent wash-out ofconstruction materials bystreams of rain and meltwaters. This is achieved bystoring the materials at theraised yards with condensedor protected with cover

f)minimal f)minimal

f) ConstructionContractor

f) ConstructionContractor

7

surface, vertical planning ofthe territory, attachment ofupland and drainagepits allaround thestorage yard

- in order to reduceenvironmental pollutiontemporary constructionfacilitiesand amenities arelocated in the singlecomplex. Amenitiesarelocated on the windwardside. Industrial amenitycomplex is provided withdrinking-water reservoirsand a toilet facility; domesticwastewater comes into a pit-type tank.

- Storage of unused, written-off or subject to maintenancein normal conditionsmachines or their parts isnotallowed at construction sitesfor temporary use

- Refueling of cars, tractorsand other mechanicallypropelled vehicles should bedone at immovable ormovable fuelling stations inspecially assigned placeslocated far away from waterfacilities. Fuelling ofimmovable machines andmechanisms with limitedmoving capacity (diggersetc.) isdoneby refuelingtrucks. At each sitewheremachines areused aprocedure for collection ofused and replaceablelubricants should beestablished, which alsoshould imply further sendingof lubricants for

8

regeneration. Discharge ofoil into the vegetation, soilor water is prohibited.

Cost Institutional responsibilityPhase Issue Mitigating measure

Install Operate Install Operate

Comments(e.g. secondary impacts)

h) Water and soil pollutionfrom improper disposalof waste materials

h)− cleaning surface runoff

from the CDAP yards− cleaning runoffs from

washing motor vehicles− storage of waste

materials in the assignedplaces/licensed landfillssecured from wastewashing into the water

− installation of containersfor storage of domesticwaste is foreseen at theassigned yards.

h)dependson location

h)minimal h) ConstructionContractor

h) ConstructionContractor

Handling of wastes bylicensed transportationcompany and delivered tolicensed landfill

i) Potential contaminationof soil and water fromimproper maintenanceand fueling of equipment

i) proper handling oflubricants, fuel and solventsby secured storage; ensureproper loading of fuel andmaintenance of equipment;collect all waste and disposeto permitted waste recoveryfacility/licensed landfill site

i)minimal i)minimal i) ConstructionContractor

i) ConstructionContractor

j) Destruction of crops,trees, meadows, etc.

j) ensure control of workingzone and land acquisition;compensate damage

j) NA j)dependson quantityof damage

j) ConstructionContractor; RoadAdministration

j) ConstructionContractor; RoadAdministration

k)Workers safety k)provide workers with safetyinstructionsand protectiveequipment (glasses, masks,helmets, boots, etc); safe

k)minimal k)minimal k) ConstructionContractor

k) ConstructionContractor

9

organization of bypassingtraffic

Operation • Maintenancea) water and blowing

erosion of the roadbeda)− strengthening of cuts by

sowing grass on rich soil− in order to secure the

reliability of the roadbedconstruction a layer bylayer condensing of soilis foreseen on therailroad embankment(layers 20-30 cm wide)ensuring densityaccording to thestandards (minimumdensity index 0,95) toavoid subsidence

− to avoid saturation andwash away ofexcavations constructionof cells and collectorditches which will takerainfall run-off awayfrom the roadbed of therailway lines is foreseen

− installation of artificialfacilities in the body ofthe embankment

a) a) NA;minimal

RoadAdministration

b) Water and soil pollution b) construction of treatmentfacilities for surface run-off at st. Kherson,Brylivka, Mykolayiv andNovopoltavka

b)

10

Cost Institutional responsibilityPhase Issue Mitigating measure

Install Operate Install Operate

Comments(e.g. secondary impacts)

• Exploitationa) Exploitation of designed

facilitiestraction substations

a)

at traction substations for eachitem of equipment filled with oil asystem for oil drain from thesinkssituated under transformers inspecial pipelines into undergroundreservoirs is foreseen which willprevent spreading and penetrationof oil into the soil.

a) a) minimal RoadAdministration

sewage drainages

• Road safety

sewage drainage treatment atbiological treatment facilitiesat st.Velyki Kopani, Radenske,Novokyivka, Chehovychi,Kotlyareve, Horokhivka,Hreyhove, Lotskyne, Horozhene,junctions Dobrovilskyy, Kazanka,Novodanylivka, Kutsivka,Maderove, Tsukrova, Vadym,Kalanchak, Brylivka,Tsyuryupynsk, Novopoltavka,Sharivka, 5 km

a)− installation of automatic

devices with constant dutycycleat all crossings

− use of modern automaticdevices and automaticblocking for regulating trainoperation

a) a) minimal RoadAdministration

11

− construction of alternatingcurrent network 27,5 kilovolt,contact suspension bracketwith reinforcing and screeningwires

12

Part C: Monitoring Plan

C. MONITORING PLAN

Cost Institutional responsibility

PhaseWhat

parameter is tobe monitored?

Where is theparameter to be

monitored?

How is theparameter to be

monitored?/type of

monitoringequipment

When is theparameter to be

monitored?(frequency of

measurement orcontinuous)

Why is theparameter to bemonitored?(optional)

Install Operate Install Operate

Construction• Material supply

a) Asphalt plant a) possessionof officialapproval orvalidoperatinglicense

a) asphaltplant

a) spotinspection

a) beforeworkbegins

a)-c) assureplantcompliance withenvironment,health andsafety

a) NA a) NA a) PlantManager

a) PlantManager

b) Stone quarry b) possessionof officialapproval orvalidoperatinglicense

b) stonequarry

b) spotinspection

b) beforeworkbegins

requirements b) NA b) NA b) QuarryManager

b) QuarryManager

c) Sand and gravelborrow pit

c) possessionof officialapproval orvalidoperatinglicense bytransport. org

c) sand andgravelborrow pit orseparation

c) spotinspection byOblastEnvironmental Authorities

c) beforeworkbegins/occasionalmonitoring

c) NA c) NA c) Borrow Pitor SeparationPlantManager

c) Borrow Pitor SeparationPlantManager

• Materialtransporta) Asphalt a) truck load

covereda) job site a) supervision a) unannounced

inspectionsduring work

a)-d) assurecompliance ofperformancewithenvironment,health and

a) NA a) minimal a) NA a) SupervisionContractor

13

Cost Institutional responsibility

PhaseWhat

parameter is tobe monitored?

Where is theparameter to be

monitored?

How is theparameter to be

monitored?/type of

monitoringequipment

When is theparameter to be

monitored?(frequency of

measurement orcontinuous)

Why is theparameter to bemonitored?(optional)

Install Operate Install Operate

b)Stone b) truck loadcovered orwetted

b) job site b) supervision a) unannouncedinspectionsduring work

safetyrequirementsand enableas

b) NA b) minimal b) NA b) SupervisionContractor

c) Sand and gravel c) truck loadcovered orwetted

c) job site c) supervision a) unannouncedinspectionsduring work

littledisruptionto traffic as it ispossible

c) NA c) minimal c) NA c) SupervisionContractor

d)Trafficmanagement

d) hours androutesselected

d) job site d) supervision a) unannouncedinspectionsduring work

d) NA d) minimal d) NA d) SupervisionContractor

• Construction sitea) Noise disturbanceto human and animalpopulation andworkers

a) noise levels;equivalent noiselevel, equipment

a) job site;nearest homes

a) noise meterand analyzer,

inspection

a) once for eachmachineandequipment whenworks start andon complain

a)-k) assurecompliance ofperformancewithenvironment,health and

a) NA a) NA a) MonitoringContractor

a) MonitoringContractor

b) Air pollution b) dust (solidparticles),

b) at and nearjob site

b) visual b) duringmaterialdelivery andconstruction

safetyrequirementsand enableaslittledisruptionto traffic as it ispossible

b) NA b) NA b) MonitoringContractor

b) MonitoringContractor

14

Cost Institutional responsibility

PhaseWhat

parameter is tobe monitored?

Where is theparameter to be

monitored?

How is theparameter to be

monitored?/type of

monitoringequipment

When is theparameter to be

monitored?(frequency of

measurement orcontinuous)

Why is theparameter to be

monitored?(optional)

Install Operate Install Operate

c) Vibrationsresulting fromequipment work

c) limited timeof activities

c) job site c) supervision c) unannouncedinspectionsduring workand oncomplain

c) NA c) minimal c) NA c) SupervisionContractor

d) Traffic disruptionduring constructionactivity

d) existence oftrafficmanagementplan; trafficpatterns

d) at and nearjob site

d) inspection;observation

d) before worksstart; onceperweek at peakand non peakperiods

d) NA d) minimal d) NA d) SupervisionContractor

e) Reduced access toroadside activities

e) providedalternativeaccess

e) job site e) supervision e) duringconstruction

e) NA e) minimal e) NA e) SupervisionContractor

f) Vehicle andpedestrian safetywhen there is noconstruction activity

f) visibility andappropriateness

f) at and nearjob site

f) observation f) onceperweek in theevening

f) NA f) minimal f) NA f) SupervisionContractor

g) Water and soilpollution frommaterial storage,management andusage

g) water andsoil quality(suspendedsolids, oil andgrease)

g) runoff fromsite, materialstorageareas;wash downareas ofequipment

g) gravity;observation;mobilelaboratory withnecessaryequipment(wateranalyzer);

g) duringmaterialdelivery andconstruction,especiallyduringprecipitation(rain, snow, etc)

g) NA g) NA g) MonitoringContractor

g) MonitoringContractor

15

Cost Institutional responsibility

PhaseWhat

parameter is tobe monitored?

Where is theparameter to be

monitored?

How is theparameter to be

monitored?/type of

monitoringequipment

When is theparameter to be

monitored?(frequency of

measurement orcontinuous)

Why is theparameter to bemonitored?(optional)

Install Operate Install Operate

h) Water and soilpollution fromdisposal of wastematerials

h) water andsoil quality(suspendedsolids, oil andgrease)

h) depositorysite/landfill

h) mobilelaboratory withnecessaryequipment(wateranalyzers);observation

h) in case ofprovisionaldisposal ofwaste atconstruction siteand on complain

h) NA h) NA h) MonitoringContractor/Inspections byOblastEnvironmentalAuthorities

h) MonitoringContractor /Inspections byOblastEnvironmentalAuthoritiesandoccasionalmonitoring byRoad Authority

i) Potentialcontamination of soiland water frommaintenance andfueling of equipment

i) water and soilquality(suspendedsolids, oil andgrease);procedures ofwork

i) job site;equipmentmaintenancefacilities

i) mobilelaboratory withnecessaryequipment(wateranalyzers);observation

i) in case offueling ofequipment atconstruction siteand on complain

i) NA i) NA i) MonitoringContractor

i) MonitoringContractor

j) Destruction of crops,trees, meadows, etc.

j) landacquisition

j) job site j) supervision j) duringmaterialdelivery andconstruction

j) NA j) minimal j) NA j) SupervisionContractor

k) Workers safety k) protectiveequipment(glasses, masks,helmets, boots,etc);organization ofbypassingtraffic

k) job site k) inspection k) unannouncedinspectionsduring work

k) NA k) minimal k) NA k) SupervisionContractor

16

D. DESCRIPTION OF INSTITUTIONAL MEASURES

Institutional Measures

Function Responsible Party (parties) Frequency

Datacollection on monitoring ofenvironmental conditions duringconstruction (reconstruction) andduring exploitation

Contractor / Chief Engineer See monitoring programabove

Analysis of data duringconstruction (reconstruction) periodand during exploitation

- Ukrzaliznitsya DevelopmentDepartment

Oncea month

Preparation of report duringconstruction (reconstruction) periodand during exploitation

- Ukrzaliznitsya DevelopmentDepartment

Every second month

Dissemination of report to theUkrzaliznitsya management andBank Project Manager

Ukrzaliznitsya Project ManagementDepartment sends report to the BankProject Manager

Project Manager receives report

Once in two months toUkrzaliznitsyamanagement and once insix months to World Bank

Measuresaimed at environmentalprotection

- Ukrzaliznitsya DevelopmentDepartment

As necessary

17

E. RESULTS OF PUBLIC CONSULTATIONS WITH ALL INTERESTED PARTIES (SEE ATTACHMENT)

Information about Public Consultationswaspublished in the media in newspapers “Naddnipryanska Pravda” No 15 as of February 27, 2009,“Yuzhnaya Pravda” as of February 28, 2009 and “Narodne Slovo” as of March 3, 2009.

Public Consultations were carried out on March 24, 2009 in Kherson, on March 24, 2009 in Dolynska and on March 14, 2009 in Mykolaiv(See attachment)

Special invitations were distributed to (list of governmental, non-governmental, and other interested parties etc.):

First Name andSurname

Organization / position Address Telephone/Fax

Following were present at Public Consultation event in the city of Kherson:

First Name andSurname

Organization / position Address Telephone/Fax

1 Vasylyev Ye. Yu. Head, industry and InfrastructureDevelopment Department, KhersonOblast Administration

2 Topalov S. V. Chief Engineer of the KhersonOffice for Railroad Shipments

3 Skvirskiy S. M. Chief Engineer of the OJSCDniproDiproTrans Institute

4 Gribkov S. M. Head of the Department forE i t I t A t

18

Environment Impact Assessment,OJSC DniproDiproTrans Institute

5 Residentsof the city

Following questionswere given and answers received:

List of main questionsand answers:

Question Questionfrom

Answers Answered

1. Will thenoise level be reducedduring operation of electrictrains?

Residentsof the city

1. The noise level resulting from the transfer of railroadtracks to electric traction will not change. It is planned tobuild noise suppression structures along the tracks in thevicinity of residential buildings near the tracks.

S. M. Skvirskiy, ChiefEngineer of the OJSCDniproDiproTrans Institute

2. What impact will the transferto electric traction have on theenvironment after itsimplementation?

Residentsof the city

2. The introduction of energy saving technology willreduce the negative impact on the environment,agriculture, production, landscape, natural floraand faunato a minimum. Theelimination of theemission of dieselfuel combustion products (carbonic oxide, sulfuricanhydride, nitrogen dioxide and soot) into theatmospherewill lessen background pollution in the region, which willhavea positive impact on theenvironment.

S. M. Skvirskiy, ChiefEngineer of the OJSCDniproDiproTrans Institute

3. What amount of earth is itplanned to removeduring thebuilding of the track?

Residentsof the city

3. The removal of earth is planned during theconstructionprocess

S. M. Skvirskiy, ChiefEngineer of the OJSCDniproDiproTrans Institute

19

Following were present at Public Consultation event in the city of Dolynska:

First Name andSurname

Organization / position Address Telephone/Fax

1 H. V. Danyliuk Head of Dolynska Regional StateAdministration

2 V. I. Sybirtsev Deputy Head of Oblast StateAdministration

3 M. O. Sukhomlyn Head of Oblast Rada

4 A. I. Olkhovyk OJSC DniproDiproTrans Institute

5 Representatives See the Minutes

6 Residentsof the city

Following questionswere given and answers received:

List of main questionsand answers:

Question Questionfrom

Answers Answered

1. How will the disassembledequipment bedisposed?

Residentsofthe city

In the process of building and operation of the facilities,construction and household wastes will be utilized, andremoval will be carried out in accordance with concludedagreement.

V. I. Sybirtsev, Deputy Headof Oblast StateAdministration

2. Are there any plans to conductan ecological examination ofthe construction project?

Residentsofthe city

The complex examination includes also ecologicalexamination and is being carried out at theUkrDerzhBudExpertiza in Kyiv

V. I. Sybirtsev, Deputy Headof Oblast StateAdministration

20

Following were present at Public Consultation event in the city of Mykolaiv:

First Name andSurname

Organization / position Address Telephone/Fax

1 M. M. Maksymchuk Head of the Administration forIndustry and InfrastructureDevelopment, Mykolaiv Oblast StateAdministration

2 V. A. Zdorovets Deputy Chairman of theCouncil ofIndustrialistsand Entrepreneurs,Mykolaiv Oblast

3 M. O. Stasiuk Director of the StateOwned EnterpriseMykolaivAvtoTransService

4 A. I. Olkhovyk Representative, OJSCDniproDiproTrans Institute

5 S. M. Gribkov Representative, OJSCDniproDiproTrans Institute

6 Representatives See the Minutes

7 Residentsof the city

Following questionswere given and answers received:

List of main questionsand answers:

Question Question from

1. Is the construction of therailroad track to Bashtankapossible?

I. V. Rubskiy, Head of Bashtanka RegionState Administration

1. Proposals from the Head of Bashtanka Region StateAdministration are looked into by Odessa Railway

21

possible?

2. Is the construction ofpedestrian crossing possible atthe Mykolaiv - Khorokhiv openline?

O. V. Boichenko, Head of thePolihonVillageRada

2. Proposals regarding theconstruction of a pedestriancrossing hasbeen taken into account in the FS.

22

RESULTS OF PUBLIC CONSULTATIONS WITH ALL STAKEHOLDERS

Approved: Ye. . Yu. Vasylyev, Head of Administration for Industry and Infrastructure Development, Kherson Oblast State Administration

MINUTES of Public Consultations on Impact of Transferring Railroad Traffic to Electric Traction with

Simultaneous Building of Second Track and Reconstruction of Track Development of Stations Along the Mykolaiv – Kherson - Dzhankoi Route

47 Ushakov Prospect March 24, 2009 Kherson Present were:

1. Ye. Yu. Vasylyev - Head of Administration for Industry and Infrastructure Development, Kherson Oblast State Administration

2. S. M. Skvirskiy – Chief Engineer and S. M. Gribkov –Department Head from the OJSC DniproDiproTrans Institute

3. S. V. Topalov – Chief Engineer of the Kherson Office for Railroad Shipments. 4. Representatives: List included Chairman of Meeting: Ye.Yu. Vasylyev - Head of Administration for Industry and Infrastructure

Development, Kherson Oblast State Administration Secretary of the Meeting: L. V. Starovyerova Agenda:

1. Transferring railroad traffic to electric traction with simultaneous building of second track and reconstruction of track development of stations along Mykolaiv – Kherson - Dzhankoi route. Report by S. M. Skvirskiy – Chief Engineer of the OJSC DniproDiproTrans Institute

2. Impact on natural environment during transfer of trains to electric traction Report by S. M. Gribkov –Head of the Department for Environment Impact Assessment, OJSC DniproDiproTrans Institute

3. Draft decision of Public Consultations on mentioned issues Report by S. V. Topalov, Chief Engineer of the Kherson Office for Railroad Shipments

4. Answers to questions of those present

Main theses of First Speaker The ecological component of the present project is improving the ecological state at the

expense of the elimination of emission of diesel fuel combustion products into the atmosphere, which will allows to lower hothouse gas ejection into the atmosphere and significant reduce noise level. The effective feasibility study for performance of works for ensuring the transfer of railroad traffic to electric traction with simultaneous building of second track and reconstruction of track development of stations determines main technical decisions for introducing energy saving technology during railroad shipments along Znamianka – Dolynska – Mykolaiv – Kherson - Dzhankoi route, on the Znamianka - Vadym run, their value assessment and the expediency of their implementation.

The feasibility study envisages the laying of second track 328.43 km long, including the

reconstruction of the existing track network – 13.45 km, and electrification of route – 385 kilometers.

23

An additional 1232 persons will be employed to operate the network, estimate assessment of construction makes up UAH 6 883 465.48 thousand. The project structures shall be equipped with water supply and sewerage networks with local purification facilities.

The fulfillment of the building of a second track and servicing-technical facilities pose additional requirements:

- mounding ordinary earth on embankment – 602.1 thousand m3

- mounding draining earth on embankment – 522.1 thousand m3

- trimming tracks – crushed stone – 681.34 thousand m3

- sand – 370.50 thousand m3

In the course of the building and operation of facilities, construction and household waste will be utilized, and its removal carried out in accordance with concluded agreements.

The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape and natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products into the atmosphere (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) will lessen background pollution in the region, which will have a positive impact on the environment.

The noise level resulting from the transfer of railroad tracks to electric traction will not change. It is planned to build noise suppression structures along the tracks in the vicinity of residential buildings near the tracks.

Measures have been worked out that will ensure normative state of the environment, namely:

protective, technological and planned.

Measures have been adopted for protection against electromagnetic impact of linear cable communication structures.

Envisaged is the fulfillment of measures in volumes, necessary for protecting storehouses and structures with highly inflammable and fuel liquids and gases from sparking.

Ionizing radiation and ultrasound are nonexistent.

Taking into account to the carrying out of feasibility study measures we can make a conclusion

on safety, from the viewpoint of the ecology, and thus, on the possibility to carry out the introduction of energy saving technology during railroad shipments along the Znamianka - Vadym run.

2. Main thesis of the report by S. V. Topalov, Chief Engineer, Kherson Office for Railroad

Shipments.

Railroad traffic is one of the basic branches of the economy of Ukraine, which ensure its internal and foreign transport and economic ties and requirements of the population in shipments. However the state of the production and technical base requires renewal and modernization. Problem issues, which today complicate the operation of railroads, include limited carrying capacity on Crimean routes. In connection with the introduction high speed passenger train traffic and separation of freight and passenger train routes for more effective use, increase in the volume of cargo shipments to ports in Mykolaiv, Kherson, Zhovtneva and the development of deep water ports in the Crimea, which envisage an increase in the workability capacity of ports, it is extremely necessary to strengthen the carrying capacity of the parallel run. The Dolynska – Mykolaiv – Kherson - Dzhankoi route is overloaded at the present time and is unable to meet shipment requirements. The project envisages the building of a second track and electrification of railroad traffic with the construction of traction substations, electric-traction networks and supply lines for automatic blocking devices,

24

electric centralization and communication and high-voltage internal electricity supply lines for servicing them.

The electrification of railroads will be carried out on alternating current, the advantage of

which has been confirmed by many years of operating respective sections. Capital expenditures for electrification on alternating current are 15-18% lower than that on direct current. The laying of a second track, electrification and modernization of signaling and communication systems, telecommunication systems are a package of measures, necessary for strengthening the carrying capacity of the route.

3. Answers to questions: 3.1. Question: What amount of earth is it planned to remove during the building of the track?

Answer: There will be no removal of earth during the building. 3.2. Question: How will the disassembled equipment be utilized?

Answer: In the process of building and operation of the facilities, construction and household wastes will be utilized, and removal will be carried out in accordance with the signed agreements.

3.3. Question: Will the noise level be reduced during the operation of electric trains? Answer: There will be no change in the noise level resulting from the transfer of railroad tracks to electric traction. It is planned to erect noise suppression structures in the vicinity of residential buildings near the tracks. 3.3. Question: What impact will the transfer to electric traction have on the environment after its implementation? Answer: The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape, natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) into the atmosphere will lessen background pollution in the region, which will have a positive impact on the environment. Decision taken at the meeting: Having heard and discussed the issue pertaining to the impact of transferring train traffic to

electric traction with simultaneous building of a second track and reconstruction of track development of stations, and taking into account that the introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production and natural flora and fauna to a minimum, at the expense of eliminating the emission of diesel fuel combustion products into the atmosphere and significantly reduce noise level from railroad transport,

1. To agree to the transfer of train traffic to electric traction with simultaneous building of a second track and reconstruction of track development of stations.

2. To support and render assistance at all levels of coordination and construction of this project.

The chairman of the meeting thanked those present for their active participation in discussing

this issue. The discussion lasted 2 hours.

Ye. Yu. Vasylyev Chairman of the Meeting

L. V. Starovyerova Secretary of the Meeting

25

APPROVED: H. V. Danyliuk, Head of Dolynska Region State Administration March 24, 2009

MINUTES of Public Consultations on Impact of Transferring Railroad Traffic to Electric Traction with

Simultaneous Building of Second Track and Reconstruction of Track Development of Stations

March 24, 2009 Dolynska Present were: 1. H. V. Danyliuk, Head of Dolynska Region State Administration - V. I, Sybirtsev, Deputy Head of Oblast State Administration - M. O. Sukhomlyn, Head of Oblast Rada 2. A. I. Olkhovyk, OJSC DniproDiproTrans Institute 3. V. V. Matviyenko, Chief Engineer, Znamianka Office for Railroad Shipments 4. Representatives: - L. B. Vareniuk, Malovodiane Village Chairman - R. Ya. Verdiyeva – Road Master of Permanent Way Inspection =23 - M. V. Dobrovolskiy, Director, Marfivka Quarry Ltd., Power Engineering Group - S. I. Zelenokorinniy, Mayor of Dolynska - O. V. Klimovskiy, Head of Inspectorate for State Architecture and Construction Control - V. H. Kuzmenko, Chief Architect of Dolynska Region - N. M. Kuzmina, Department Head, State Committee of Ukraine for Land Resources in Dolynska Region - O. O. Liashenko, First Deputy Head of Dolynska Region State Administration - V. A. Mushyk, Vasylivka Village Chairman - V. H. Panchenko, Bohdanivka Village Chairman - S. P. Omelchenko, Pershotravneve Village Chairman - L. H. Tykha, Sukhodil Village Chairman 5. Participants of the Meeting: - S. O. Balanenko, Moshoryne Village Chairmen, Znamianka Region - M. A. Bondar, Mytrofanivka Village Chairman, Novhorodka Region - B. O. Yeromenko, Land Management Engineer, Protective Forest Planting -3 - M. Ya. Zalizko, Head of the Motor Road Service, Kirovograd Oblast - H. M. Koval, Economist, Dolynska Maintenance Section - K. V. Komyatiy, Deputy Station Master of Dolynska Station - V. I. Koniushenko, Head of Oleksandria Region State Administration - M. P. Korohovskiy, Head of Department for State Land Management Examination and Assessment of Land Market, Main Administration of the State Committee of Ukraine for Land Resources in Kirovograd Oblast - M. V. Lebed, Deputy Editor-in-Chief, Oblast State Television and Radio Broadcasting Company - V. V. Medvid, Head of the Kirovograd Region State Administration - O. I. Mulenkov, Volodymyrivka Village Chairman, Znamianka Region - S. M. Slutskiy, Deputy Head of Dolynska Power Supply Service - A. H. Stoian, First Deputy Head of Znamianka Region State Administration - O. O. Shkola, Kutsivska Village Chairman, Novohoroska Region

26

6. City Residents Hrihoriy Vasylyovych Danyliuk - Chairman of the Meeting Kateryna Viktorivna Komiatiy – Secretary of the Meeting Agenda:

1. Reports by A. I. Olkhovyk, representative of the OJSC DniproDiproTrans Institute. 2. Report by V.V. Matviyenko, Chief Engineer, Znamianka Office for Railroad Shipments 3. Answers to questions posed by residents

Main theses of First Speaker

The ecological component of the present project is improving the ecological state at the expense of eliminating the emission of diesel fuel combustion products into the atmosphere, which will allow to lower hothouse gas ejection into the atmosphere and significant reduce noise level. The effective feasibility study for performance of works for ensuring the transfer of railroad traffic to electric traction with simultaneous building of second track and reconstruction of track development of stations determines main technical decisions for introducing energy saving technology during railroad shipments along Znamianka – Dolynska – Mykolaiv – Kherson - Dzhankoi route, on the Znamianka - Vadym run, their value assessment and the expediency of their implementation.

The feasibility study includes the laying of a 328.43 kilometer second track including the

reconstruction of the existing track network – 13.45 kilometers, and electrification of route – 385 kilometers. An additional 1232 persons will be required for operating the network, estimate assessment of construction – UAH 6 883 465.48. The project structures shall be equipped with water supply and sewerage networks with local purification facilities.

The fulfillment of the building of a second track and servicing-technical facilities pose additional requirements:

- mounding ordinary earth on embankment – 602.1 thousand m3

- mounding draining earth on embankment – 522.1 thousand m3

- trimming tracks – crushed stone – 681.34 thousand m3

- sand – 370.50 thousand m3

In the course of the building and operation of facilities, building and household waste will be utilized, and the removal of these wastes carried out in accordance with concluded agreements.

The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape and natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products into the atmosphere (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) will lessen background pollution in the region, which will have a positive impact on the environment.

The noise level resulting from the transfer of railroad tracks to electric traction will remain the same. It is planned to build noise suppression structures along the tracks near residential buildings.

Measures have been worked out that will ensure normative state of the environment, namely:

protective, technological and planned.

Measures have been adopted for protection against electromagnetic impact of linear cable communication structures.

Envisaged is the fulfillment of measures in volumes, necessary for protecting storehouses and structures with highly inflammable and fuel liquids and gases from sparking.

27

Ionizing radiation and ultrasound are nonexistent.

Taking into account the carrying out of measures in the feasibility study we can make a

conclusion on safety, from the viewpoint of the ecology, and thus, on the possibility to carry out the introduction of energy saving technology during railroad shipments along the Znamianka - Vadym run.

2. Main theses and report by V.V. Matviyenko, Chief Engineer of the Znamianka Office for

Railroad Shipments Railroad traffic is one of the basic branches of the economy of Ukraine, which ensure its

internal and foreign transport and economic ties and requirements of the population in shipments. However the state of the production and technical base requires renewal and modernization. Problem issues, which today complicate the operation of railroads, include limited traffic carrying capacity on Crimean routes. In connection with the introduction high speed passenger train traffic and separation of freight and passenger train routes for more effective use, increase in the volume of cargo shipments to ports in Mykolaiv, Kherson, Zhovtneva and the development of deep water ports in the Crimea, which envisage an increase in the workability capacity of ports, it is extremely necessary to strengthen the carrying capacity of the parallel run. The Dolynska – Mykolaiv – Kherson - Dzhankoi route is overloaded at the present time and is unable to meet shipment requirements. The project envisages the building of a second track and electrification of railroad traffic with the construction of traction substations, electric-traction networks and supply lines for automatic blocking devices, electric centralization and communication and high-voltage internal electricity supply lines for servicing them

The electrification of railroads will be carried out on alternating current, the advantage of

which has been confirmed by many years of operating respective sections. Capital expenditures for electrification on alternating current are 15-18% lower than that on direct current. The laying of a second track, electrification and modernization of the signaling and communication systems, telecommunication systems are complex measures, necessary for strengthening the carrying capacity of the route.

3. Answers to questions: 3.1. V. I. Sybirtsev. Question: What amount of earth is it planned to remove during the building

of the track? Answer: There will be no removal of earth during the building.

3.2. M. O. Sukhomlyn. Question: How will the disassembled equipment be utilized? Answer: In the process of building and operation of the facilities, construction and

household wastes will be utilized, and removal will be carried out in accordance with concluded agreement.

3.3. V. I. Sybirtsev. Question: Is an ecological examination planned of the construction project? Answer: The complex examination includes both ecological examination and is being carried out at the UkrDerzhBudExpertiza in Kyiv.

3.4. S. I. Zelenokorinniy. Question: Will the noise level be reduced during the operation of electric trains?

Answer: There will be no change in the noise level resulting from the transfer of railroad tracks to electric traction. It is planned to erect noise suppression structures in the vicinity of residential buildings near the tracks. 3.5. H. V. Danyliuk. Question: What impact will the transfer to electric traction have on the environment after its implementation? Answer: The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape, natural flora and fauna to a minimum. The

28

elimination of the emission of diesel fuel combustion products (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) into the atmosphere will lessen background pollution in the region, which will have a positive impact on the environment.

Proposals: 1. S. I. Zelenokorinniy, Mayor of Dolynska – to plan the building of 2 pedestrian

crossings through the Dolynska Station. 2. Support the intension of UkrZalisnytsia and Odesa Railroad to develop and strengthen

the carrying capacity along Znamianka – Dolynska – Mykolaiv route, electrification, modernization of the signaling and communication systems, telecommunication system.

3. Take into account opportunities in the Oblast for enlisting contracting organization and quarries to mounding railroad bed.

The Chairman of the Meeting thanked those present for their active discussion of issues. The discussion lasted for 1 and a half hours.

Chairman of the Meeting (Signature)

Secretary of the Meeting

(Signature)

Approved: M. M. Maksymchuk, Head of the Administration for Industry and Infrastructure Development, Mykolaiv Oblast State Administration 14.03.09

MINUTES

of Public Consultations on Impact of Transferring Railroad Traffic to Electric Traction with Simultaneous Building of Second Track and Reconstruction of Track Development of Stations

Mykolaiv 14.03.09 Present were:

1. M. M. Maksymchuk, Head of the Administration for Industry and Infrastructure Development,

Mykolaiv Oblast State Administration 2. V. V. Prytulenko, Deputy Chairman of the Council of Industrialists and Entrepreneurs,

Mykolaiv Oblast; V. A. Zdorovets, Director General of the Association of Haulers , Mykolaiv Oblast; M. O. Stasiuk, Director of the State Owned Enterprise MykolaivAvtoTransService.

3. A. I. Olkhovyk and S. M. Gribkov, department heads, OJSC DniproDiproTrans Institute S. V. Topalov, Chief Engineer of the Kherson Office for Railroad Shipments

4. Representatives: - I.V. Rubskiy, Head of the Bashtanka Region State Administration

29

- V. P. Bulakh, Head of the Department for Industry and Infrastructure Development, Zhovtneviy Region State Administration

- L. P. Tymoshuk, Head of the Department of Economy, Kazanka Region State Administration

- I. O. Kozhushko, Head of the Novoserhiivka Village Rada - N. V. Orlova, Head of the Marivka Village Rada - O. V. Boichenko, Head of the Polihon Village Rada - L. H. Kukhtyk, Secretary of the Voznesensk Village Rada - O. H. Zaporozets, Director of the Housing and Municipal Services - L. V. Herun, Secretary of the Polihon Village Rada - V. F. Rybachenko, Mayor of Bashtanka - M. V. Bordachov, Public Organization of Bashtanka Region. Chairman of the Meeting - M. M. Maksymchuk, Head of the Administration for Industry and

Infrastructure Development, Mykolaiv Oblast State Administration Secretary of the Meeting – Yu. O. Leontiyeva

Agenda: 1. Report by representative of the OJSC DniproDiproTrans Institute 2. Report by S. V. Topalov, Chief Engineer of the Kherson Office for Railroad Shipments 3. Answers to Questions

Main theses of Speaker 1 The ecological component of the present project is improving the ecological state at the

expense of eliminating the emission of diesel fuel combustion products into the atmosphere allowing the lowering of hothouse gas ejection into the atmosphere and significant reduction of noise level. The effective feasibility study for the performance of works for ensuring the transfer of railroad traffic to electric traction with simultaneous building of second tracks and reconstruction of track extension at stations are determined by main technical decisions on introduction of energy saving technology during railroad shipments along Znamianka – Dolynska – Mykolaiv - Kherson – Dzhankoi route, on the Znamianka - Vadym run, their value assessment and the expediency of their implementation.

The feasibility study includes the laying of a 328.43 kilometer second track including the

reconstruction of the existing track network – 13.45 kilometers, and electrification of the route – 385 kilometers. An additional 1232 persons will be required for operating the network, estimate assessment of construction – UAH 6 883465.48. The project structures shall be equipped with water supply and sewerage networks with local purification facilities.

The fulfillment of the building of a second track and servicing-technical facilities pose additional requirements:

- mounding ordinary earth on embankment – 602.1 thousand m3

- mounding draining earth on embankment – 522.1 thousand m3

- trimming tracks – crushed stone – 681.34 thousand m3

- sand – 370.50 thousand m3

In the course of the building and operation of facilities, building and household waste will be utilized, and removal carried out in accordance with concluded agreements.

The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape and natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products into the atmosphere (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) will lessen background pollution in the region, which will have a positive impact on the environment.

30

The noise level resulting from the transfer of railroad tracks to electric traction will not change.

It is planned to build noise suppression structures along the tracks in the vicinity of residential buildings.

Measures have been worked out that will ensure normative state of the environment, namely:

protective, technological and planned.

Measures have been adopted for protection against electromagnetic impact of linear cable communication structures.

Envisaged is the fulfillment of measures in volumes, necessary for protecting storehouses and structures with highly inflammable and fuel liquids and gases from sparking.

Ionizing radiation and ultrasound are nonexistent.

Taking into account the carrying out of measures in the feasibility study we can make a

conclusion on safety, from the viewpoint of the ecology, and thus, on the possibility to carry out the introduction of energy saving technology during railroad shipments along the Znamianka - Vadym run.

Railroad traffic is one of the basic branches of the economy of Ukraine, which ensure its

internal and foreign transport and economic ties and requirements of the population in shipments. However the state of the production and technical base requires renewal and modernization. Problem issues, which today complicate the operation of railroads, include limited carrying capacity on Crimean routes. In connection with the introduction high speed passenger train traffic and separation of freight and passenger train routes for more effective use, increase in the volume of cargo shipments to ports in Mykolaiv, Kherson, Zhovtneva and development of deep water ports in the Crimea, which envisage an increase in the workability capacity of ports, it is extremely necessary to strengthen the carrying capacity of the parallel run. The Dolynska – Mykolaiv – Kherson - Dzhankoi route is overloaded at the present time and is unable to meet shipment requirements. The project envisages the building of a second track and electrification of railroad traffic with the construction of traction substations, electric-traction networks and supply lines for automatic blocking devices, electric centralization and communication and high-voltage internal electricity supply lines for servicing them

The electrification of railroads will be carried out on alternating current, the advantage of

which has been confirmed by many years of operating respective sections. Capital expenditures for electrification on alternating current are 15-18% lower than that on direct current. The laying of a second track, electrification and modernization of the signaling and communication systems, telecommunication systems are complex measures, necessary for strengthening the carrying capacity of the route.

3. Answers to questions: 3.1. Question: What amount of earth is it planned to remove during the building of the track?

Answer: There will be no removal of earth during the building. 3.2. Question: How will the disassembled equipment be utilized?

Answer: In the process of building and operation of the facilities, construction and household wastes will be utilized, and removal will be carried out in accordance with concluded agreement.

3.3. Question: Is an ecological examination of the construction project planned? Answer: A complex examination together with ecological examination

3.4. Question: Will the noise level be reduced during the operation of electric trains?

31

Answer: There will be no change in the noise level resulting from the transfer of railroad tracks to electric traction. It is planned to erect noise suppression structures in the vicinity of residential buildings near the tracks.

3.5. Question: What impact will the transfer to electric traction have on the environment after its implementation?

Answer: The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape, natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) into the atmosphere will lessen background pollution in the region, which will have a positive impact on the environment.

3.6. I. V. Rubskiy, Head of the Bashtanka Region State Administration. Question: Is the construction of the railroad track to Bashtanka possible?

3.7. O. V. Boichenko, Head of the Polihon Village Rada. Is the construction of pedestrian crossing possible at the Mykolaiv - Khorokhiv open line?

Proposals: 1. To include into the plan the construction of a railroad station near the 167 km crossing in

Bashtanka (possible closure of the station Horozhani). Land issues are being solved. Land resources of the Bashtanka City Council will be included in this project. The city authorities guarantee repair of roads and access routes for people to the station.

2. Transfer traction substation and contact network duty post from Novopoltavka to Bashtanka.

The Chairman of the Meeting thanked those present for their active discussion of issues. The discussion lasted for 1 and a half hours.

Chairman of the Meeting

(Signature)

Secretary of the Meeting (Signature)

Signatures of Meeting participants

32

Article from newspaper Yuzhnaya Pravda dated February 28, 2009

INFORMATION ON ELABORATION OF FEASIBILITY STUDY

The effective feasibility study determines the basic technical decisions for introduction of energy saving technology during railroad shipments on Znamianka – Dolynska – Mykolaiv – Kherson – Dzhankoi route, Znamianka – Dolynska –Vadym run, their value assessment and expediency of their implementation, as well as performance of work for ensuring the transfer of train traffic to electric traction with simultaneous building of a second track and reconstruction of the track development of stations.

The feasibility study envisages the laying of a second track 328.43 km long, including the reconstruction of the existing track network – 13.45 km, electrification of the route – 385 km. Envisaged for operation is the construction of a traction substation, duty contact network posts, and electrical centralization posts. An additional 1232 persons will be employed for operating, estimate cost of building – UAH 6 883 465.48 thousand. Project structures will be equipped with water supply and sewerage networks with local purification facilities.

Additional requirements have appeared for the building of a second track and service and technical structures

- mounting of ordinary earth - 603.1 thousand m3- mounting of draining earth – 522.1 thousand m3

- trimming tracks - crushed stone – 681.34 thousand m3

- sand – 370.50 thousand m3

In the course of the building and operation of facilities, building and household waste will be utilized, and removal will be carried out in accordance with concluded agreement.

The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape and natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products into the atmosphere (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) will lessen background pollution in the region, which will have a positive impact on the environment.

The noise level resulting from the transfer of railroad tracks to electric traction will not change. It is planned to build noise suppression structures along the tracks near residential buildings.

Measures have been worked out that will ensure normative state of the environment, namely:

protective, technological and planned.

Measures have been adopted for protection against electromagnetic impact of linear cable communication structures.

Envisaged is the fulfillment of measures in volumes, necessary for protecting storehouses and structures with highly inflammable and fuel liquids and gases from sparking.

Ionizing radiation and ultrasound are nonexistent.

Taking into account the carrying out of measures in the feasibility study we can make a conclusion on safety, from the viewpoint of the ecology, and thus, on the possibility to carry out the introduction of energy saving technology during railroad shipments along the Znamianka - Vadym run.

Kherson Office for Railroad Shipments

33

Article from Nordne Slovo dated

Information on Elaboration of Feasibility Study

The effective feasibility study determines the basic technical decisions for introduction of energy saving technology during railroad shipments on Znamianka – Dolynska – Mykolaiv – Kherson – Dzhankoi route, Znamianka – Dolynska –Vadym run, their value assessment and expediency of their implementation, as well as performance of work for ensuring the transfer of train traffic to electric traction with simultaneous building of a second track and reconstruction of the track development of stations.

The feasibility study envisages the laying of a second track 328.43 km long, including the reconstruction of the existing track network – 13.45 km, electrification of route – 385 km. Envisaged for operation is the construction of a traction substation, duty contact network posts, and electrical centralization posts. An additional 1232 persons will be employed for operating, estimate cost of building – UAH 6 883 465.48 thousand. Project structures will be equipped with water supply and sewerage networks with local purification facilities.

Additional requirements have appeared for the building of a second track and service and technical structures

- mounting of ordinary earth - 603.1 thousand m3- mounting of draining earth – 522.1 thousand m3

- trimming tracks - crushed stone – 681.34 thousand m3

- sand – 370.50 thousand m3

In the course of the building and operation of facilities, building and household waste will be utilized, and removal will be carried out in accordance with concluded agreement.

The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape and natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products into the atmosphere (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) will lessen background pollution in the region, which will have a positive impact on the environment.

The noise level resulting from the transfer of railroad tracks to electric traction will not change. It is planned to build noise suppression structures along the tracks near residential buildings.

Measures have been worked out that will ensure normative state of the environment, namely:

protective, technological and planned.

Measures have been adopted for protection against electromagnetic impact of linear cable communication structures.

Envisaged is the fulfillment of measures in volumes, necessary for protecting storehouses and structures with highly inflammable and fuel liquids and gases from sparking.

Ionizing radiation and ultrasound are nonexistent.

Taking into account the carrying out of measures in the feasibility study we can make a

conclusion on safety, from the viewpoint of the ecology, and thus, on the possibility to carry out the introduction of energy saving technology during railroad shipments along the Znamianka - Vadym run.

Znamianka Office for Railroad Shipments

34

Article from Naddniprianska PRAVDA 15 dated February 27, 2009

Information on Elaboration of Feasibility Study

The effective feasibility study determines the basic technical decisions for introduction of energy saving technology during railroad shipments on Znamianka – Dolynska – Mykolaiv – Kherson – Dzhankoi route, Znamianka – Dolynska –Vadym run, their value assessment and expediency of their implementation, as well as performance of work for ensuring the transfer of train traffic to electric traction with simultaneous building of a second track and reconstruction of the track development of stations.

The feasibility study envisages the laying of a second track 328.43 km long, including the reconstruction of the existing track network – 13.45 km, electrification of the route – 385 km. Envisaged for operation is the construction of a traction substation, duty contact network posts, and electrical centralization posts. An additional 1232 persons will be employed for operating, estimate cost of building – UAH 6 883 465.48 thousand. Project structures will be equipped with water supply and sewerage networks with local purification facilities.

Additional requirements have appeared for the building of a second track and service and technical structures

- mounting of ordinary earth - 603.1 thousand m3- mounting of draining earth – 522.1 thousand m3

- trimming tracks - crushed stone – 681.34 thousand m3

- sand – 370.50 thousand m3

In the course of the building and operation of facilities, building and household waste will be utilized, and removal will be carried out in accordance with concluded agreement.

The introduction of energy saving technology will reduce the negative impact on the environment, agriculture, production, landscape and natural flora and fauna to a minimum. The elimination of the emission of diesel fuel combustion products into the atmosphere (carbonic oxide, sulfuric anhydride, nitrogen dioxide and soot) will lessen background pollution in the region, which will have a positive impact on the environment.

The noise level resulting from the transfer of railroad tracks to electric traction will not change. It is planned to build noise suppression structures along the tracks near residential buildings.

Measures have been worked out that will ensure normative state of the environment, namely:

protective, technological and planned.

Measures have been adopted for protection against electromagnetic impact of linear cable communication structures.

Envisaged is the fulfillment of measures in volumes, necessary for protecting storehouses and structures with highly inflammable and fuel liquids and gases from sparking.

Ionizing radiation and ultrasound are nonexistent.

Taking into account the carrying out of measures in the feasibility study we can make a

conclusion on safety, from the viewpoint of the ecology, and thus, on the possibility to carry out the introduction of energy saving technology during railroad shipments along the Znamianka - Vadym run.

Kherson Office for Railroad Shipments, Odessa Railroad

35