MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE ... B108023.pdf · The Transmission...
Transcript of MISO MODULE B FERC Electric Tariff TRANSMISSION SERVICE ... B108023.pdf · The Transmission...
MISO MODULE B
FERC Electric Tariff TRANSMISSION SERVICE
MODULES 30.0.0
Effective On: November 19, 2013
MISO I
FERC Electric Tariff INTRODUCTION
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall provide Point-To-Point and Network Integration
Transmission Service pursuant to the applicable terms and conditions of this Tariff. Point-To-
Point Transmission Service is for the receipt of Capacity and Energy at designated Point(s) of
Receipt and the transmission of such Capacity and Energy to designated Point(s) of Delivery.
Network Integration Transmission Service allows the Network Customer to integrate,
economically dispatch and regulate its current and planned Network Resources to serve its
Network Load in a manner comparable to that in which Transmission Owners utilize the
Transmission System to serve their Native Load or other Network Customers.
Any Eligible Customer requesting Transmission Service under this Module B (other than
an Eligible Customer requesting HVDC Service) may be eligible to request and receive FTRs
associated with such request pursuant to the provisions of Module C of this Tariff. Any Eligible
Customer seeking to request or receive FTRs must be a Market Participant.
MISO II
FERC Electric Tariff POINT-TO-POINT TRANSMISSION SERVICE
MODULES 31.0.0
Effective On: December 31, 9998
Preamble
The Transmission Provider will provide Firm and Non-Firm Point-To-Point Transmission
Service pursuant to the applicable terms and conditions of this Tariff. An ITC may provide Firm
and Non-Firm Point-To-Point Transmission Service pursuant to the ITC Rate Schedule under
this Tariff where both the Point of Receipt and the Point of Delivery are on the ITC System,
provided that the Transmission Customer has executed an appropriate Service Agreement with
the Transmission Provider. Point-To-Point Transmission Service is for the receipt of Energy at
designated Point(s) of Receipt and the transmission of such Energy to designated Point(s) of
Delivery. Point-to-Point Transmission Service customers are not required to obtain
Transmission Service for the receipt of Energy and transmission of such Energy associated with
Electric Storage Resources when withdrawing Energy while providing Regulating Service or
Down Ramp Capability. Point-To-Point Transmission Service customers with Point(s) of
Receipt and Point(s) of Delivery located within the Transmission System (Michigan) may obtain
Point-To-Point Transmission Service under Schedule 7 – Michigan and Schedule 8 - Michigan
of this Tariff.
MISO 13
FERC Electric Tariff Nature of Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 13.1
FERC Electric Tariff Term
MODULES 30.0.0
Effective On: November 19, 2013
The minimum term of Firm Point-To-Point Transmission Service shall be
one (1) day and the maximum term shall be specified in the Service Agreement.
MISO 13.2
FERC Electric Tariff Reservation Priority
MODULES 30.0.0
Effective On: November 19, 2013
(i)Long-Term Firm Point-To-Point Transmission Service shall be
available on a first-come, first-served basis, i.e., in the chronological sequence in
which each Transmission Customer has reserved service.
(ii)Reservations for Short-Term Firm Point-To-Point Transmission Service
will be conditional based upon the length of the requested transaction or
reservation. However, Pre-Confirmed Applications for Short-Term Point-To-
Point Transmission Service will receive priority over earlier-submitted requests
that are not Pre-Confirmed and that have equal or shorter duration. Among
requests or reservations with the same duration and, as relevant, pre-confirmation
status (pre-confirmed, confirmed, or not confirmed), priority will be given to an
Eligible Customer’s request or reservation based on the earliest date and time of
the request or reservation.
(iii)If the Transmission System becomes oversubscribed, requests for
service may preempt competing requests or reservations that involve the same
flowgate or up to the following conditional reservation deadlines: one day before
the commencement of daily service; one week before the commencement of
weekly service; and one month before the commencement of monthly service.
Before the conditional reservation deadline, if Available Transfer Capability is
insufficient to satisfy all requests and reservations, an Eligible Customer with a
reservation for shorter-term service or equal duration service has the right of first
refusal to match any longer-term request or equal duration service before losing
its reservation priority. A longer-term competing request for Short-Term Firm
MISO 13.2
FERC Electric Tariff Reservation Priority
MODULES 30.0.0
Effective On: November 19, 2013
Point-To-Point Transmission Service will be granted if the Eligible Customer with
the right of first refusal does not agree to match the competing request within
twenty-four (24) hours (or earlier if necessary to comply with the scheduling
deadlines provided in Section 13.8) from being notified by the Transmission
Provider of a longer-term competing request for Short-Term Firm Point-To-Point
Transmission Service. When a longer duration request preempts multiple shorter
duration reservations, the shorter duration reservations shall have simultaneous
opportunities to exercise the right of first refusal. Time of match confirmation
will be used to determine the order by which the multiple shorter duration
reservations will be able to exercise the right of first refusal. In the event the
match confirmations are submitted simultaneously, the original OASIS queue time
will be utilized to determine the order by which the multiple shorter duration
reservations will be able to exercise the right of first refusal. After the conditional
reservation deadline, service will commence pursuant to the terms of this Tariff.
(iv)Firm Point-To-Point Transmission Service will always have a reservation
priority over Non-Firm Point-To-Point Transmission Service under the Tariff. All
Long-Term Firm Point-To-Point Transmission Service will have equal reservation
priority with Native Load Customers and Network Customers. Reservation
priorities for existing firm service customers are provided in Section 2.2.
MISO 13.3
FERC Electric Tariff [RESERVED]
MODULES 30.0.0
Effective On: November 19, 2013
MISO 13.4
FERC Electric Tariff Service Agreements
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall offer a standard form Firm
Point-To-Point Transmission Service Agreement to an Eligible Customer when it
submits a Completed Application for Long-Term Firm Point-To-Point
Transmission Service pursuant to this Tariff (Attachment A-1). The Transmission
Provider shall offer a standard form Firm Point-To-Point Transmission Service
Agreement to an Eligible Customer when it first submits a Completed Application
for Short-Term Firm Point-To-Point Transmission Service pursuant to this Tariff
(Attachment A). Executed Service Agreements that contain the information
required under the Tariff shall be filed with the Commission in compliance with
applicable Commission regulations. An Eligible Customer that uses Transmission
Service at a Point of Receipt or Point of Delivery that it has not reserved and that
has not executed a Service Agreement will be deemed, for purposes of assessing
any appropriate charges and penalties, to have executed the appropriate Service
Agreement.
MISO 13.5
FERC Electric Tariff Obligations for Facility Additions or Redispatch Costs
MODULES 31.0.0
Effective On: August 2, 2017
In cases where the Transmission Provider or ITC determines that the
Transmission System is not capable of providing Firm Point-To-Point
Transmission Service without: (1) degrading or impairing the reliability of service
to Native Load Customers, Network Customers and other Transmission
Customers taking Firm Point-To-Point Transmission Service; or (2) interfering
with the Transmission Provider’s or ITC’s ability to meet prior firm contractual
commitments to others, the relevant Transmission Owner(s) or ITC will be
obligated to expand or upgrade its (their) Transmission System(s) pursuant to the
terms of Section 15.4. The Transmission Customer must agree to pay the
Transmission Provider or ITC for any necessary transmission facility additions
pursuant to the terms of Section 27.
MISO 13.6
FERC Electric Tariff Curtailment of Firm Transmission Service
MODULES 31.0.0
Effective On: January 2, 2019
In the event that a Curtailment on the Transmission System, or a portion
thereof, is required to maintain reliable operation of such system, and the systems
directly and indirectly interconnected with the Transmission System, Curtailments
will be made on a non-discriminatory basis to the transaction(s) that effectively
relieve the constraint. The Transmission Provider may elect to implement such
Curtailments pursuant to the Transmission Loading Relief Procedures specified in
NERC Reliability Standards and NAESB WEQ Business Practice Standards. If
multiple transactions require Curtailment, to the extent practicable and consistent
with Good Utility Practice, the Transmission Provider will curtail service to
Network Customers and Transmission Customers taking Firm Point-To-Point
Transmission Service on a non-discriminatory basis. If any Transmission Owners
have Native Load Customers, then the Transmission Provider will curtail service
on a comparable basis to Native Load Customers.
All Curtailments will be made on a non-discriminatory basis; however, Non-Firm
Point-To-Point Transmission Service shall be subordinate to Firm Transmission
Service. When the Transmission Provider determines that an electrical
Emergency exists on its Transmission System and implements Emergency
procedures to curtail Firm Transmission Service, the Transmission Customer shall
make the required reductions upon request of the Transmission Provider.
However, the Transmission Provider reserves the right to curtail, in whole or in
part, any Firm Transmission Service provided under the Tariff when, in the
Transmission Provider’s sole discretion, an Emergency or other unforeseen
MISO 13.6
FERC Electric Tariff Curtailment of Firm Transmission Service
MODULES 31.0.0
Effective On: January 2, 2019
condition impairs or degrades the reliability of its Transmission System. The
Transmission Provider will notify all affected Transmission Customers in a timely
manner of any scheduled Curtailments. In the event that the Transmission
Customer fails to cease or reduce service in response to a directive by the
Transmission Provider, the Transmission Customer shall pay the following
penalties in addition to any other applicable changes: $10 per kW if the customer
fails to curtail service within ten (10) minutes of a directive by the Transmission
Provider; or $20 per kW if the customer fails to curtail service within twenty (20)
minutes of a directive by the Transmission Provider.
These charges shall apply only to the portion of the service that the
Transmission Customer fails to curtail in response to a Transmission Provider or
ITC directive. The Transmission Provider or ITC, where applicable, shall
compensate any affected Local Balancing Authority Areas or Generation
Resources for their actual costs up to the amount recovered by the Transmission
Provider or ITC, as applicable. Any revenues in excess of actual costs shall be
used to reduce the Transmission Provider’s costs (for other than the penalized
Transmission Customer) in Schedule 10 or, in the case of ITC Service, any
revenues in excess of actual costs shall be applied as specified in the ITC Rate
Schedule.
MISO 13.7
FERC Electric Tariff Classification of Firm Transmission Service
MODULES 31.0.0
Effective On: May 1, 2015
a. The Transmission Customer taking Firm Point-To-Point Transmission Service
may (1) change its Receipt and Delivery Points to obtain service on a non-firm
basis consistent with the terms of Section 22.1 or (2) request a modification of the
Points of Receipt or Delivery on a firm basis pursuant to the terms of
Section 22.3.
b. The Transmission Customer may purchase Transmission Service to make sales of
Capacity and Energy from multiple Generation Resources that are interconnected
to the Transmission System. For such a purchase of Transmission Service, the
Generation Resource will be designated as multiple Points of Receipt, except that
multiple Generation Resources interconnected to the Transmission System and
Interface points designated as Points of Receipt shall be treated as a single Point
of Receipt.
c. The Transmission Provider or ITC, as applicable, shall provide firm deliveries of
Capacity and Energy from the Point(s) of Receipt to the Point(s) of Delivery.
Each Point of Receipt at which firm transmission capacity is reserved by the
Transmission Customer shall be set forth in the Firm Point-To-Point Service
Agreement for Long-Term Firm Transmission Service along with a corresponding
capacity reservation associated with each Point of Receipt. Points of Receipt and
corresponding capacity reservations shall be as mutually agreed upon by the
Parties for Short-Term Firm Transmission. Each Point of Delivery at which firm
transfer capability is reserved by the Transmission Customer shall be set forth in
the Firm Point-To-Point Service Agreement for Long-Term Firm Transmission
MISO 13.7
FERC Electric Tariff Classification of Firm Transmission Service
MODULES 31.0.0
Effective On: May 1, 2015
Service along with a corresponding capacity reservation associated with each
Point of Delivery.
d. Points of Delivery and corresponding capacity reservations shall be as mutually
agreed upon by the Parties for Short-Term Firm Transmission. The greater of
either (1) the sum of the capacity reservations at the Point(s) of Receipt, or (2) the
sum of the capacity reservations at the Point(s) of Delivery shall be the
Transmission Customer’s Reserved Capacity. The Transmission Customer will
be billed for its Reserved Capacity under the terms of the applicable Schedule 7.
The Transmission Customer may not exceed its firm capacity reserved at each
Point of Receipt and each Point of Delivery except as otherwise specified in
Section 22. In the event that MISO identifies that a Transmission Customer’s
delivered energy exceeds its firm reserved capacity at any Point of Receipt or
Point of Delivery, the Transmission Customer shall pay unreserved use penalties
as follows: (1) the unreserved use penalties shall be based on the period of
unreserved use; (2) the unreserved use penalty for a single hour of unreserved use
shall be the applicable rate for daily firm Point-to-Point Transmission Service, as
set forth in Schedule 7 of the Tariff; and (3) more than one assessment for a given
duration (e.g., daily) shall result in an increase of the penalty period to the next
longest duration (e.g., weekly).
e. Unreserved use penalties assessed using daily firm Point-to-Point Transmission
Service rates shall account for off-peak and on-peak usage, as set forth in
MISO 13.7
FERC Electric Tariff Classification of Firm Transmission Service
MODULES 31.0.0
Effective On: May 1, 2015
Schedule 7 of the Tariff. A 200% multiplier shall be applied to all assessed
penalties.
i. Unreserved use penalties will be calculated on a monthly basis, and
allocated to all Tariff Customers and/or Transmission Owners that were
not assessed any unreserved use penalties during the applicable month.
Unreserved use penalties will be allocated to all such non-penalized Tariff
Customers and/or Transmission Owners on a pro rata basis using their
total Network Load for the month and their total Reserved Capacity for
Point-to-Point Transmission Service for the month. Specifically, the
Transmission Provider will allocate unreserved use revenues as follows:
Each Customer’s “Unreserved Use Determinant” is determined by adding
the total Network Load for the month for each Tariff Customer or
Transmission Owner not charged with unreserved use during that month to
that Tariff Customer’s or Transmission Owner’s total Reserved Capacity
for Point-to-Point Transmission Service for the month.
The “Aggregate Unreserved Use Determinant” is determined by adding
the total Network Load for the month of all Tariff Customers and
Transmission Owners not charged with unreserved use during that month
and the total Reserved Capacity for Point-to-Point Transmission Service
MISO 13.7
FERC Electric Tariff Classification of Firm Transmission Service
MODULES 31.0.0
Effective On: May 1, 2015
for the month for all Tariff Customers and Transmission Owners not
charged with unreserved use during the month.
MISO will divide each Customer’s Unreserved Use Determinant by the
Aggregate Unreserved Use Determinant, and will multiply that quotient by
the aggregate unreserved use revenues for the month in order to determine
the share of such unreserved use revenues to be allocated to each such
Tariff Customer or Transmission Owner not charged with unreserved use
for the month.
f. For interchange transactions, evaluation of Interchange Schedules (including
Third-Party Sales by a Transmission Owner) against firm reserved capacity will
be utilized to identify instances of unreserved use. For transactions internal to the
MISO footprint, MISO shall implement monitoring as described in detail in
Business Practice Manual 013, Module B, Transmission Service, to identify
instances of unreserved use.
MISO 13.8
FERC Electric Tariff Scheduling of Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
Interchange Schedules for the Transmission Customer’s Firm Point-To-Point Transmission
Service must be submitted in accordance with the terms in Attachment J. Interchange Schedules
submitted after the applicable time specified in Attachment J will be accommodated, if
practicable. Transmission Customers shall submit all hour-to-hour and intra-hour (four intervals
consisting of fifteen minutes) Interchange Schedules electronically in a form specified by the
Transmission Provider. Hour-to-hour Interchange Schedules of any capacity and energy that is
to be delivered must be stated in increments of 1,000 kW per hour. Transmission Customers
within a Transmission Owner’s service area (or Local Balancing Authority Area) with multiple
requests for Transmission Service at a Point of Receipt, each of which is under 1,000 kW per
hour, may consolidate their service requests at a common Point of Receipt into units of 1,000 kW
per hour for scheduling and billing purposes. Scheduling changes will be permitted in
accordance with Attachment J. However, in the event of a system contingency such as a
generation or an unplanned Transmission Outage, or Curtailment or Interruption of Transmission
Service, scheduling changes will be implemented as soon as practicable.
The Transmission Provider, or if ITC Service is taken, the ITC, will furnish to the
Delivering Party’s system operator, hour-to-hour Interchange Schedules and intra-hour
Interchange Schedules equal to those furnished by the Receiving Party (unless reduced for
losses) and shall deliver the Capacity and Energy provided by such schedules. Should the
Transmission Customer, Delivering Party or Receiving Party revise or terminate any Interchange
Schedule, such party shall immediately notify the Transmission Provider or, if appropriate, the
ITC, and the Transmission Provider shall have the right to adjust accordingly the schedule for
Capacity and Energy to be received and to be delivered.
MISO 13.8
FERC Electric Tariff Scheduling of Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 14
FERC Electric Tariff Nature of Non-Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 14.1
FERC Electric Tariff Term
MODULES 30.0.0
Effective On: November 19, 2013
Non-Firm Point-To-Point Transmission Service will be available for
periods ranging from one (1) hour to one (1) month. However, a Purchaser of
Non-Firm Point-To-Point Transmission Service will be entitled to reserve a
sequential term of service (such as a sequential monthly term without having to
wait for the initial term to expire before requesting another monthly term) so that
the total time period for which the reservation applies is greater than one month,
subject to the requirements of Attachment J.
MISO 14.2
FERC Electric Tariff Reservation Priority
MODULES 30.0.0
Effective On: November 19, 2013
Non-Firm Point-To-Point Transmission Service shall be available from
transfer capability in excess of that needed for reliable service to Native Load
Customers, Network Customers and other Transmission Customers taking Long-
Term and Short-Term Firm Point-To-Point Transmission Service. A higher
priority will be assigned first to requests or reservations with a longer duration of
service and second to Pre-Confirmed Applications. Eligible Customers that have
already reserved shorter-term service have the right of first refusal to match any
longer-term request before being preempted. A longer-term competing request
for Non-Firm Point-To-Point Transmission Service will be granted if the Eligible
Customer with the right of first refusal does not agree to match the competing
request: (i) immediately for hourly Non-Firm Point-To-Point Transmission
Service after notification by the Transmission Provider; and, (ii) within
twenty-four (24) hours (or earlier if necessary to comply with the scheduling
deadlines provided in Attachment J) for Non-Firm Point-To-Point Transmission
Service other than hourly transactions after notification by the Transmission
Provider. When a longer duration request preempts multiple shorter duration
reservations, the shorter duration reservations shall have simultaneous
opportunities to exercise the right of first refusal. Time of match confirmation
will be used to determine the order by which the multiple shorter duration
reservations will be able to exercise the right of first refusal. In the event the
match confirmations are submitted simultaneously, the original OASIS queue
time will be utilized to determine the order by which the multiple shorter duration
MISO 14.2
FERC Electric Tariff Reservation Priority
MODULES 30.0.0
Effective On: November 19, 2013
reservations will be able to exercise the right of first refusal. Transmission Service
for Network Customers from Generation Resources other than designated
Network Resources will have a higher priority than any Non-Firm Point-To-Point
Transmission Service. Non-Firm Point-To-Point Transmission Service over
secondary Point(s) of Receipt and Point(s) of Delivery will have the second
lowest reservation priority under this Tariff, and Non-Firm Point-To-Point
Transmission Service used for Next-Hour-Transmission Service will have the
lowest reservation priority under this Tariff.
MISO 14.3
FERC Electric Tariff [RESERVED]
MODULES 30.0.0
Effective On: November 19, 2013
MISO 14.4
FERC Electric Tariff Service Agreements
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall offer a standard form Non-Firm Point-To-Point Transmission
Service Agreement (Attachment B to this Tariff) to an Eligible Customer when it first submits a
Completed Application for Non-Firm Point-To-Point Transmission Service pursuant to this
Tariff. Executed Service Agreements that contain the information required under this Tariff
shall be filed with the Commission in compliance with applicable Commission regulations.
MISO 14.5
FERC Electric Tariff Classification of Non-Firm Point-To-Point Transmission
MODULES 31.0.0
Effective On: May 1, 2015
Non-Firm Point-To-Point Transmission Service shall be offered under terms and
conditions contained in Module B of this Tariff and any applicable ITC Rate Schedule for ITC
Service offered within an ITC System. The Transmission Provider, Transmission Owners, ITC,
and ITC Participants undertake no obligation under this Tariff to plan the Transmission System
in order to have sufficient capacity for Non-Firm Point-To-Point Transmission Service. Parties
requesting Non-Firm Point-To-Point Transmission Service for the transmission of firm power do
so with the full realization that such service is subject to availability and to Curtailment or
Interruption under the terms of this Tariff. In the event that MISO identifies that a Transmission
Customer’s delivered energy exceeds its non-firm reserved capacity at any Point of Receipt or
Point of Delivery , the Transmission Customer shall pay unreserved use penalties as follows: (1)
the unreserved use penalties shall be based on the period of unreserved use; (2) the unreserved
use penalty for a single hour of unreserved use shall be the applicable rate for daily firm Point-
to-Point Transmission Service, as set forth in Schedule 7 of the Tariff; and (3) more than one
assessment for a given duration (e.g., daily) shall result in an increase of the penalty period to the
next longest duration (e.g., weekly). Unreserved use penalties assessed using daily firm Point-
to-Point Transmission Service rates shall account for off-peak and on-peak usage, as set forth in
Schedule 7 of the Tariff. A 200% multiplier shall be applied to all assessed penalties.
These penalty revenues shall be allocated in the manner set forth in Section 13.7 of the
Tariff except, when ITC Service is taken, the penalty revenues shall be used as set forth in the
applicable ITC Rate Schedule. Non-Firm Point-To-Point Transmission Service shall include
transmission of Energy on an hourly basis and transmission of scheduled short-term capacity and
MISO 14.5
FERC Electric Tariff Classification of Non-Firm Point-To-Point Transmission
MODULES 31.0.0
Effective On: May 1, 2015
Energy on a daily, weekly or monthly basis, but not to exceed one month’s reservation for any
one Application, under the applicable Schedule 8 or the applicable ITC Rate Schedule.
For interchange transactions, evaluation of Interchange Schedules (including Third-Party
Sales by a Transmission Owner) against non-firm reserved capacity will be utilized to identify
instances of unreserved use. For transactions internal to the MISO footprint, MISO shall
implement monitoring as described in detail in Business Practice Manual 013, Module B,
Transmission Service, to identify instances of unreserved use.
MISO 14.6
FERC Electric Tariff Scheduling Non-Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
Interchange Schedules for Non-Firm Point-To-Point Transmission Service, other than for Next-
Hour-Transmission Service, must be submitted to the Transmission Provider or, when
appropriate, the ITC, in accordance with the terms in Attachment J. Interchange Schedules
submitted after the time specified in Attachment J will be accommodated, if practicable.
Transmission Customers shall submit all Interchange Schedules electronically in a form
specified by the Transmission Provider or ITC, if applicable. Hour-to-hour and intra-hour (four
intervals consisting of fifteen minutes) Interchange Schedules of Energy that are to be delivered
must be stated in increments of 1,000 kW per hour. Transmission Customers within the
Transmission Owner’s service (or control) area with multiple requests for Transmission Service
at a Point of Receipt, each of which is under 1,000 kW per hour [MWh], may consolidate their
Interchange Schedules at a common Point of Receipt into units of 1,000 kW per hour [MWh].
Scheduling changes will be permitted in accordance with Attachment J. The Transmission
Provider or, when appropriate the ITC, will furnish to the Delivering Party’s system operator,
hour-to-hour and intra-hour Interchange Schedules equal to those furnished by the Receiving
Party (unless reduced for losses) and shall deliver the Capacity and Energy provided by such
schedules. Should the Transmission Customer, Delivering Party or Receiving Party revise or
terminate any Interchange Schedule, such party shall immediately notify the Transmission
Provider or, where appropriate the ITC, and the Transmission Provider or the ITC shall have the
right to adjust accordingly the schedule for Capacity and Energy to be received and to be
delivered. Schedules for Non-Firm Point-To-Point Transmission Service for Next-Hour
Transmission Service must be in accordance with Attachment J. Schedules submitted less than
twenty (20) minutes prior to the start of the schedule will be accommodated, if practicable.
MISO 14.6
FERC Electric Tariff Scheduling Non-Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 14.7
FERC Electric Tariff Curtailment or Interruption of Service
MODULES 31.0.0
Effective On: January 2, 2019
The Transmission Provider reserves the right to curtail, in whole or in part, Non-Firm
Point-To-Point Transmission Service provided under this Tariff for reliability reasons when, an
Emergency or other unforeseen condition threatens to impair or degrade the reliability of the
Transmission System or the systems directly and indirectly interconnected with the Transmission
System. The Transmission Provider may elect to implement such Curtailments pursuant to the
Transmission Loading Relief Procedures specified in NERC Reliability Standards and NAESB
WEQ Business Practice Standards. The Transmission Provider reserves the right to interrupt, in
whole or in part, Non-Firm Point-To-Point Transmission Service provided under this Tariff for
economic reasons in order to accommodate (i) a request for Firm Transmission Service; (ii) a
request for Non-Firm Point-To-Point Transmission Service of greater duration; (iii) a request for
Non-Firm Point-To-Point Transmission Service of equal duration with a higher price; or (iv)
Transmission Service for Network Customers from non-designated Resources. Point-To-Point
Transmission Service for Next-Hour-Transmission Service will always have the lowest priority.
The Transmission Provider also will discontinue or reduce service to the Transmission Customer
to the extent that deliveries for transmission are discontinued or reduced at the Point(s) of
Receipt. Where required, Curtailments or Interruptions will be made on a non-discriminatory
basis to the transaction(s) that effectively relieve the constraint; however, Non-Firm
Point-To-Point Transmission Service shall be subordinate to Firm Transmission Service. If
multiple transactions require Curtailment or Interruption, to the extent practicable and consistent
with Good Utility Practice, Curtailments or Interruptions will be made first to
Next-Hour-Transmission Service and then to remaining transactions beginning with those
transactions of the shortest term (e.g., hourly non-firm transactions will be curtailed or
MISO 14.7
FERC Electric Tariff Curtailment or Interruption of Service
MODULES 31.0.0
Effective On: January 2, 2019
interrupted before daily non-firm transactions and daily non-firm transactions will be curtailed or
interrupted before weekly non-firm transactions). Transmission Service for Network Customers
from Resources other than designated Network Resources will have a higher priority than any
Non-Firm Point-To-Point Transmission Service under this Tariff. Non-Firm Point-To-Point
Transmission Service over secondary Point(s) of Receipt and Point(s) of Delivery will have a
higher priority than Next-Hour Transmission Service, but will have a lower priority than any
other Non-Firm Point-To-Point Transmission Service under the Tariff. The Transmission
Provider will provide advance notice of Curtailment or Interruption where such notice can be
provided consistent with Good Utility Practice. In the event that the Transmission Customer
fails to cease or reduce service in response to a directive by the Transmission Provider, the
Transmission Customer shall pay the following penalties in addition to any other applicable
charges:
a. $10 per kW if the Customer fails to curtail service within ten (10) minutes of a directive
by the Transmission Provider;
b. $20 per kW if the Customer fails to curtail service within twenty (20) minutes of a
directive by the Transmission Provider; or
c. $20 per kW if the customer fails to interrupt service at the beginning of the Hour for
which the Interruption is requested; provided that the customer is given a minimum of
forty (40) minutes notice before the beginning of such Hour; and provided further that the
customer may retain its service and avoid the penalty by agreeing pursuant to
Section 14.2 of this Tariff to match any longer-term reservation and/or higher price in a
competing request before being Interrupted.
MISO 14.7
FERC Electric Tariff Curtailment or Interruption of Service
MODULES 31.0.0
Effective On: January 2, 2019
These charges shall apply only to the portion of the service that the Transmission
Customer fails to curtail or interrupt in response to a Curtailment or Interruption directive. The
Transmission Provider or ITC where applicable, shall compensate any affected Local Balancing
Authority Areas or generators for their actual costs up to the amount recovered by the
Transmission Provider or ITC, as applicable. Any revenues in excess of actual costs shall be
used to reduce the Transmission Provider costs (for other than the penalized Transmission
Customer) in Schedule 10 or, in the case of ITC Service, any revenues in excess of actual costs
shall be applied as specified in an ITC Rate Schedule.
MISO 15
FERC Electric Tariff Service Availability
MODULES 30.0.0
Effective On: November 19, 2013
MISO 15.1
FERC Electric Tariff General Conditions
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider will provide Firm and Non-Firm Point-To-
Point Transmission Service over, on or across its Transmission System to any
Transmission Customer that has met the requirements of Section 16.1.
MISO 15.2
FERC Electric Tariff Determination of Available Transfer Capability
MODULES 30.0.0
Effective On: November 19, 2013
A description of the Transmission Provider’s specific methodology for
assessing available transfer capability posted on the Transmission Provider’s
OASIS (Section 4) is contained in Attachment C of the Tariff. In the event
sufficient transfer capability may not exist to accommodate a service request, the
Transmission Provider or as appropriate, the ITC, will respond by performing a
System Impact Study in accordance with Attachment D to this Tariff.
MISO 15.3
FERC Electric Tariff Initiating Service in Absence of Executed Agreement
MODULES 30.0.0
Effective On: November 19, 2013
If the Transmission Provider and the Transmission Customer requesting Firm or Non-Firm
Point-To-Point Transmission Service cannot agree on all the terms and conditions of the Point-
To-Point Transmission Service Agreement, the Transmission Provider shall file with the
Commission, within thirty (30) days after the date the Transmission Customer provides written
notification directing the Transmission Provider to file, an unexecuted Point-To-Point Service
Agreement containing terms and conditions deemed appropriate by the Transmission Provider
for such requested Transmission Service.
The Transmission Provider shall commence providing Transmission Service subject to the
Transmission Customer agreeing to: (i) compensate the Transmission Provider at whatever rate
the Commission ultimately determines to be just and reasonable and (ii) comply with the terms
and conditions of the Tariff including posting appropriate security deposits in accordance with
the terms of Section 17.4.
MISO 15.4
FERC Electric Tariff Obligation to Provide Service Requiring Expansion
MODULES 31.0.0
Effective On: August 2, 2017
If the Transmission Provider determines that it cannot accommodate a
Completed Application for Firm Point-To-Point Transmission Service because of
insufficient capability on the Transmission System, the Transmission Provider
and the affected Transmission Owner(s) and ITC(s) will use due diligence to
expand or modify the Transmission System to provide the requested Firm
Transmission Service, consistent with its planning obligations in Attachment FF,
provided the Transmission Customer agrees to compensate the Transmission
Provider and ITC for such costs pursuant to the terms of Section 27. The
Transmission Provider and the affected Transmission Owner(s), ITC(s), and ITC
Participant(s), if applicable, will conform to Good Utility Practice and its
planning obligations in Attachment FF, in determining the need for new facilities
and in the design and construction of such facilities. The obligation applies only
to those facilities that the affected Transmission Owner(s), ITC(s), and ITC
Participant(s) have the right to expand or modify.
MISO 15.5
FERC Electric Tariff Deferral of Service
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider may defer providing service until construction
is completed of new transmission facilities or upgrades needed to provide Firm
Point-To-Point Transmission Service whenever the Transmission Provider
determines that providing the requested service would, without such new facilities
or upgrades, impair or degrade reliability to any existing firm services.
MISO 15.6
FERC Electric Tariff Other Transmission Service Schedules
MODULES 30.0.0
Effective On: November 19, 2013
Eligible Customers receiving Transmission Service under Grandfathered
Agreements and ITC Grandfathered Agreements may continue to receive
Transmission Service under those agreements until such time as those agreements
may be modified by the Commission.
MISO 15.7
FERC Electric Tariff Marginal Losses
MODULES 32.0.0
Effective On: March 1, 2015
System Losses are associated with all Transmission Service including
Transmission Service associated with Grandfathered Agreements. The
Transmission Provider shall assess to Market Participants the Marginal Losses
Component of Ex Post LMP, as specified in Sections 39.2.9, 39.3.3.c.ii, 40.2.11,
and 40.4.1.
MISO 16
FERC Electric Tariff Transmission Customer Responsibilities
MODULES 30.0.0
Effective On: November 19, 2013
MISO 16.1
FERC Electric Tariff Conditions Required of Transmission Customers
MODULES 30.0.0
Effective On: November 19, 2013
Point-To-Point Transmission Service shall be provided by the Transmission Provider, or,
as applicable, the ITC only if the following conditions are satisfied by the Transmission
Customer:
a. The Transmission Customer has pending a Completed Application for service;
b. The Transmission Customer meets the creditworthiness criteria set forth in Attachment L;
c. The Transmission Customer will have arrangements in place for any other Transmission
Service necessary to effect the delivery from the Generating Source to the Transmission
Provider prior to the time service under Module B of this Tariff commences;
d. The Transmission Customer agrees to pay for any facilities constructed and chargeable to
such Transmission Customer under Module B of this Tariff, whether or not the
Transmission Customer takes service for the full term of its reservation;
e. The Transmission Customer provides the information required by the Transmission
Provider’s planning process established in Attachment FF; and
f. The Transmission Customer has executed a Point-To-Point Service Agreement or has
agreed to receive service pursuant to Section 15.3.
MISO 16.2
FERC Electric Tariff Customer Responsibility for Third-Party Arrangements
MODULES 30.0.0
Effective On: November 19, 2013
Any scheduling arrangements that may be required by other electric
systems shall be the responsibility of the Transmission Customer requesting
service. The Transmission Customer shall provide, unless waived by the
Transmission Provider, notification to the Transmission Provider identifying such
systems and authorizing them to schedule the Capacity and Energy to be
transmitted by the Transmission Provider pursuant to Module B of this Tariff on
behalf of the Receiving Party at the Point of Delivery or the Delivering Party at
the Point of Receipt. However, the Transmission Provider will undertake
reasonable efforts to assist the Transmission Customer in making such
arrangements, including without limitation, providing any information or data
required by such other electric system pursuant to Good Utility Practice.
MISO 17
FERC Electric Tariff Arranging Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 17.1
FERC Electric Tariff Application
MODULES 30.0.0
Effective On: November 19, 2013
A request for Firm Point-To-Point Transmission Service for
periods of one year or longer must contain a written Application to the
Transmission Provider submitted in accordance with the timelines set
forth in Attachment J. All Firm Point-To-Point Transmission Service
requests should be submitted by entering the information listed below on
the Transmission Provider’s OASIS.
MISO 17.2
FERC Electric Tariff Time Requirements
MODULES 30.0.0
Effective On: November 19, 2013
Attachment J lists the time requirements applicable to when the
requests must be made, the evaluation of the requests, and the
Transmission Customer response. Requests for Firm Point-To-Point
Service that are subject to no earlier than submission timelines and that are
submitted during the first five minutes after the time when Firm Point-To-
Point Service can first be requested on the OASIS in accordance with
Attachment J, will be considered as if they were submitted simultaneously
during such window as set forth in Section 17.6 of this Tariff.
MISO 17.3
FERC Electric Tariff Completed Application
MODULES 30.0.0
Effective On: November 19, 2013
A Completed Application shall provide all of the information
included in 18 C.F.R. § 2.20 including but not limited to the following:
(i) The identity, address, email address, telephone number and
facsimile number of the entity requesting service;
(ii) A statement that the entity requesting service is, or will be upon
commencement of service, an Eligible Customer under this Tariff;
(iii) The location of the Point(s) of Receipt and Point(s) of Delivery
and the identities of the Delivering Parties and the Receiving
Parties;
(iv) The location of the Generation Resource(s) supplying the capacity
and Energy and the location of the Load ultimately served by the
capacity and energy transmitted. The Transmission Provider will
treat this information as confidential except to the extent that
disclosure of this information is required by this Tariff, by
regulatory or judicial order, for reliability purposes pursuant to
Good Utility Practice or pursuant to RTG transmission information
sharing agreements. The Transmission Provider shall treat this
information consistent with the standards of conduct contained in
Part 37 of the Commission’s regulations;
(v) A description of the supply characteristics of the capacity and
Energy to be delivered;
(vi) An estimate of the Capacity and Energy expected to be delivered
to the Receiving Party;
(vii) The service commencement date and the term of the requested
Transmission Service; and
(viii) The transmission capacity requested for each Point of Receipt and
each Point of Delivery on the Transmission Provider’s
Transmission System; customers may combine their requests for
service in order to satisfy the minimum transmission capacity
requirement. The Transmission Provider and, when ITC Service is
MISO 17.3
FERC Electric Tariff Completed Application
MODULES 30.0.0
Effective On: November 19, 2013
requested, ITC shall treat this information consistent with the
standards of conduct contained in Part 37 of the Commission’s
regulations.
(ix) A statement indicating that, if the Eligible Customer submits a pre-
confirmed Application, the Eligible Customer will execute a
Service Agreement upon receipt of notification that the
Transmission Provider can provide the requested Transmission
Service; and
(x) Any additional information required by the Transmission
Provider’s planning process established in Attachment FF.
MISO 17.4
FERC Electric Tariff Deposit
MODULES 30.0.0
Effective On: November 19, 2013
A Completed Application for Firm Point-To-Point Transmission Service
also shall include, at the discretion of Transmission Provider, a deposit of either
one month’s charge for Reserved Capacity, the full charge for Reserved Capacity
for service requests of less than one month, or a request for waiver of such
deposit, which request shall be accepted if the Eligible Customer is found by the
Transmission Provider to be creditworthy.
If the Application is rejected by the Transmission Provider because it does
not meet the conditions for service as set forth herein, or in the case of requests
for service arising in connection with losing bidders in a Request For Proposals
(“RFP”), said deposit shall be returned with interest less any reasonable costs
incurred by the Transmission Provider in connection with the review of the losing
bidder’s Application. The deposit also will be returned with interest less any
reasonable costs incurred by the Transmission Provider if the Transmission
Provider is unable to complete new facilities needed to provide the service.
If an Application is withdrawn or the Eligible Customer decides not to
enter into a Service Agreement for Firm Point-To-Point Transmission Service,
any deposit shall be refunded in full, with interest, less reasonable costs incurred
by the Transmission Provider to the extent such costs have not already been
recovered by the Transmission Provider from the Eligible Customer. The
Transmission Provider will provide to the Eligible Customer a complete
accounting of all costs deducted from any refunded deposit, which the Eligible
Customer may contest if there is a dispute concerning the deducted costs.
MISO 17.4
FERC Electric Tariff Deposit
MODULES 30.0.0
Effective On: November 19, 2013
Deposits associated with construction of new facilities are subject to the
provisions of Section 19. If a Service Agreement for Firm Point-To-Point
Transmission Service is executed, any deposit, with interest, will be returned to
the Transmission Customer upon expiration or termination of the Service
Agreement for Firm Point-To-Point Transmission Service. Applicable interest
shall be computed in accordance with the Commission’s regulations at 18 C.F.R.
§ 35.19a(a)(2)(iii) and shall be calculated from the day the deposit check is
credited to the Transmission Provider’s account.
MISO 17.5
FERC Electric Tariff Notice of Deficient Application
MODULES 30.0.0
Effective On: November 19, 2013
If an Application fails to meet the requirements of this Tariff, the
Transmission Provider shall notify the entity requesting service within the
applicable time period set forth in Attachment J for responding to Applications.
The Transmission Provider will attempt to remedy minor deficiencies in the
Application through informal communications with the Eligible Customer. If
such efforts are unsuccessful, the Transmission Provider shall return the
Application, along with any deposit, with interest. Upon receipt of a new or
revised Application that fully complies with the requirements of Module B of this
Tariff, the Eligible Customer shall be assigned a new priority consistent with the
date of the new or revised Application.
MISO 17.6
FERC Electric Tariff Response to a Completed Application
MODULES 30.0.0
Effective On: November 19, 2013
Following receipt of a Completed Application for Firm Point-To-Point
Transmission Service, the Transmission Provider shall make a determination of
available transfer capability as required in Section 15.2. If sufficient
transmission capacity is not available to meet requests submitted during the five
minute window described in Section 17.2 of this Tariff, the system(s) will
implement a Customer Allocation Lottery methodology for awarding of
transmission capacity to the TSRs submitted. The Customer Allocation Lottery is
conducted for all TSRs submitted during the five minute window and establishes
the relative order for evaluation of SSW TSRs within the overall queue of
pending requests being processed within the system. The Customer Allocation
Lottery will sort the impacted TSRs by priority based on NERC curtailment
priority, request duration, and pre-confirmation status. TSRs within the tiers will
then be assigned a random queue position and responses to Completed
Applications (including AFC evaluations and grants of service) will occur in
accordance with this Tariff in the numerical order established using the queue
position assigned via the Customer Allocation Lottery. Transmission Customers
will not be allocated transmission capacity in excess of the capacity requested in
the TSR submitted; however, based on the queue position and the amount of
available AFC, each TSR shall be awarded the full amount of capacity requested,
a portion thereof or no capacity. During the conduct of each lottery, all of the
requested AFC will be allocated.
MISO 17.6
FERC Electric Tariff Response to a Completed Application
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall notify the Eligible Customer in
accordance with the times in Attachment J either (i) if it will be able to provide
service without performing a System Impact Study or (ii) if such a study is needed
to evaluate the impact of the Application pursuant to Section 19.1. Responses by
the Transmission Provider must be made as soon as practicable to all completed
applications on a non-discriminatory basis.
MISO 17.7
FERC Electric Tariff Execution of Service Agreement
MODULES 30.0.0
Effective On: November 19, 2013
Whenever the Transmission Provider or, as applicable, ITC determines
that a System Impact Study is not required and that the service can be provided,
Transmission Provider shall notify the Eligible Customer consistent with the
applicable time period set forth in Attachment J. Where a System Impact Study is
required, the provisions of Section 19 will govern the execution of a Service
Agreement. Failure of an Eligible Customer to execute and return the Service
Agreement or request the filing of an unexecuted service agreement pursuant to
Section 15.3, within the times in Attachment J will be deemed a withdrawal and
termination of the Application and any deposit submitted shall be refunded with
interest. Nothing herein limits the right of an Eligible Customer to file another
Application after such withdrawal and termination.
MISO 17.8
FERC Electric Tariff Extensions for Commencement of Service
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Customer can obtain, subject to availability, up to five
(5) one-year extensions for the commencement of service. The Transmission
Customer may postpone service by notifying the Transmission Provider or, as
applicable, ITC, 31 days prior to the commencement date of the service as
initially requested and paying a non-refundable annual reservation fee equal to
one (1) month’s charge for Firm Point-To-Point Transmission Service for each
year or fraction thereof within fifteen (15) days of notification to the Transmission
Provider of its intent to extend the commencement of service. If during any
extension for the commencement of service an Eligible Customer submits a
Completed Application for Firm Point-To-Point Transmission Service, and such
request can be satisfied only by releasing all or part of the Transmission
Customer’s Reserved Capacity, the original Reserved Capacity will be released
unless the following condition is satisfied. Within thirty (30) days, the original
Transmission Customer agrees to pay the Firm Point-To-Point transmission rate
for its Reserved Capacity concurrent with the new Service Commencement Date.
In the event the Transmission Customer elects to release the Reserved Capacity,
the reservation fees or portions thereof previously paid will be forfeited.
MISO 18
FERC Electric Tariff Arranging Non-Firm Point-To-Point Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 18.1
FERC Electric Tariff Application
MODULES 30.0.0
Effective On: November 19, 2013
Eligible Customers seeking Non-Firm Point-To-Point Transmission
Service must submit a Completed Application to the Transmission Provider.
Applications should be submitted by entering the information listed below on the
Transmission Provider’s OASIS.
MISO 18.2
FERC Electric Tariff Completed Application
MODULES 30.0.0
Effective On: November 19, 2013
A Completed Application shall provide all of the information included in
18 C.F.R. § 2.20 including but not limited to the following:
i. The identity, address, email address, telephone number and facsimile
number of the entity requesting service;
ii. A statement that the entity requesting service is, or will be upon
commencement of service, an Eligible Customer under the Tariff;
iii. The Point(s) of Receipt and the Point(s) of Delivery;
iv. The maximum amount of capacity requested at each Point of Receipt and
Point of Delivery; and
v. The proposed dates and hours for initiating and terminating Transmission
Service hereunder. In addition to the information specified above, when
required to properly evaluate system conditions, the Transmission
Provider also may ask the Transmission Customer to provide the
information indicated in (vi) and (vii) below.
vi. The electrical location of the initial source of the power to be transmitted
pursuant to the Transmission Customer’s request for service; and
vii. The electrical location of the ultimate Load. The Transmission Provider
and, when ITC Service is requested, the ITC will treat this information in
(vi) and (vii) as confidential at the request of the Transmission Customer
except to the extent that disclosure of this information is required by this
Tariff, by regulatory or judicial order, for reliability purposes pursuant to
Good Utility Practice, or pursuant to RTG transmission information
sharing agreements. The Transmission Provider and, as applicable, the
ITC shall treat this information consistent with the standards of conduct
MISO 18.2
FERC Electric Tariff Completed Application
MODULES 30.0.0
Effective On: November 19, 2013
contained in Part 37 of the Commission’s regulations.
viii. A statement indicating that, if the Eligible Customer submits a pre-
confirmed Application, the Eligible Customer will execute a Service
Agreement upon receipt of notification that the Transmission Provider can
provide the requested Transmission Service.
MISO 18.3
FERC Electric Tariff Requests and Responses for Non-Firm Point-to-Point Service
MODULES 30.0.0
Effective On: November 19, 2013
Attachment J lists the time requirements applicable to when the requests
must be made, the evaluation of the requests, and the Transmission Customer
response. Requests for service received later than the applicable time prior to the
day service is scheduled to commence will be accommodated if practicable.
MISO 18.4
FERC Electric Tariff Determination of Available Transfer Capability
MODULES 30.0.0
Effective On: November 19, 2013
Following receipt of a tendered schedule the Transmission Provider will
make a determination on a non-discriminatory basis of available transfer
capability pursuant to Section 15.2. Such determination shall be made as soon as
reasonably practicable after receipt, but not later than the time periods specified in
Attachment J.
MISO 19
FERC Electric Tariff Additional Study Procedures For Firm Point-To-Point TSRs
MODULES 30.0.0
Effective On: November 19, 2013
MISO 19.1
FERC Electric Tariff Notice of Need for System Impact Study
MODULES 31.0.0
Effective On: August 2, 2017
After receiving a request for service, the Transmission Provider or ITC, as
applicable, shall determine on a non-discriminatory basis whether a System
Impact Study is needed. Such review, to the extent reasonably feasible, shall rely
upon existing planning studies and System Impact Studies. A description of the
Transmission Provider’s and, as applicable, ITC’s methodology for completing a
System Impact Study is provided in Attachment D.
If the Transmission Provider or ITC, as applicable, determines that a
System Impact Study is necessary to accommodate the requested service, the
Transmission Provider shall so inform the Eligible Customer within the times
specified in Attachment J. The Transmission Provider shall within thirty (30)
days of receipt of a Completed Application tender a System Impact Study
Agreement in the form of Attachment D-1 of this Tariff, pursuant to which the
Eligible Customer shall agree to reimburse the Transmission Provider or ITC, as
applicable, for performing the required System Impact Study including any costs
of the Transmission Owner(s) and ITC Participant(s) where applicable. For a
service request to remain a Completed Application, the Eligible Customer shall
execute the System Impact Study agreement and return it to the Transmission
Provider within the time provided for in Attachment J. If the Eligible Customer
elects not to execute the System Impact Study agreement, its application shall be
deemed withdrawn and any deposit, pursuant to Section 17.4, shall be returned
with interest.
MISO 19.1
FERC Electric Tariff Notice of Need for System Impact Study
MODULES 31.0.0
Effective On: August 2, 2017
MISO 19.1.1
FERC Electric Tariff Exception to Need for System Impact Study
MODULES 31.0.0
Effective On: February 1, 2016
Generally, a System Impact Study is required to approve requests for Firm Point-to-Point
Service with a duration of one year or longer. There is one instance where a request can be
approved without an individualized System Impact Study.
MISO 19.1.1.1
FERC Electric Tariff Withdrawal of Higher Queued Request on Same Path
MODULES 30.0.0
Effective On: November 19, 2013
If a request for long term Firm Point-to-Point service is studied in a System Impact
Study, but ultimately does not result in service being taken by the Transmission Customer, and
there is another request of equal or fewer MW next in queue, then the subsequent request can
utilize the higher queued request’s System Impact Study results and proceed with one of the
following two steps.
i) If there are no constraints identified in the System Impact Study, then the Eligible
Customer will be required to execute the Service Agreement within the
Attachment J timeline.
ii) If there are constraints that need to be mitigated by the transmission customer,
then the Transmission Provider will proceed with a Facilities Study, if that
Facilities Study was not completed by the higher queued request, and notify and
send a Facilities Study agreement within the Attachment J timeline.
MISO 19.1.1.2
FERC Electric Tariff Pre-Certified Point to Point Transmission Drive-Out Paths
MODULES 32.0.0
Effective On: February 1, 2016
MISO 19.2
FERC Electric Tariff System Impact Study Agreement and Cost Reimbursement
MODULES 30.0.0
Effective On: November 19, 2013
(i) The System Impact Study agreement will clearly specify the
Transmission Provider’s or, as applicable, ITC’s estimate of the
actual cost, and time for completion of the System Impact Study.
The charge shall not exceed the actual cost of the study. In
performing the System Impact Study, the Transmission Provider
or, as applicable, ITC shall rely, to the extent reasonably
practicable, on existing transmission planning studies. The
Eligible Customer will not be assessed a charge for such existing
studies; however, the Eligible Customer will be responsible for
charges associated with any modifications to existing planning
studies that are reasonably necessary to evaluate the impact of the
Eligible Customer’s request for service on the Transmission
System.
(ii) If in response to multiple Eligible Customers requesting service in
relation to the same competitive solicitation, a single System
Impact Study is sufficient for the Transmission Provider or ITC, as
applicable, to accommodate the requests for service, the costs of
that study shall be pro-rated among the Eligible Customers.
(iii) Each Transmission Owner shall pay the Transmission Provider for
System Impact Studies that the Transmission Provider conducts on
the Transmission Owner’s behalf in instances where merchant
employees of the Transmission Owner, or as applicable the ITC,
MISO 19.2
FERC Electric Tariff System Impact Study Agreement and Cost Reimbursement
MODULES 30.0.0
Effective On: November 19, 2013
have requested Transmission Service, the same as any non-
transmission owning customer.
MISO 19.3
FERC Electric Tariff System Impact Study Procedures
MODULES 31.0.0
Effective On: August 2, 2017
Upon receipt of an executed System Impact Study Agreement in the form
of Attachment D-1 of this Tariff, the Transmission Provider or ITC, as applicable,
will use due diligence to complete the required System Impact Study in
coordination with the relevant Transmission Owners within sixty (60) days or as
soon as practicable. The System Impact Study shall identify (1) any system
constraints, identified with specificity by transmission element or flowgate, and
(2) additional Direct Assignment Facilities or Network Upgrades required to
provide the requested service.
In the event that the Transmission Provider or ITC is unable to complete
the required System Impact Study within such time period, it shall so notify the
Eligible Customer and provide an estimated completion date along with an
explanation of the reasons why additional time is required to complete the
required studies. A copy of the completed System Impact Study and related work
papers shall be made available to the Eligible Customer as soon as the System
Impact Study is complete. The Transmission Provider or ITC will use the same
due diligence in completing the System Impact Study for an Eligible Customer as
it uses when completing studies for Transmission Owners or ITC Participants.
The Transmission Provider or ITC, as applicable, shall notify the Eligible
Customer immediately upon completion of the System Impact Study if the
Transmission System will be adequate to accommodate all or part of a request for
service or that no costs are likely to be incurred for new transmission facilities or
upgrades. In order for a request to remain a Completed Application, within the
MISO 19.3
FERC Electric Tariff System Impact Study Procedures
MODULES 31.0.0
Effective On: August 2, 2017
time period set forth in Attachment J for a customer response from the date of
completion of the System Impact Study the Eligible Customer must execute a
Service Agreement or request the filing of an unexecuted Service Agreement
pursuant to Section 15.3 or the Application shall be deemed terminated and
withdrawn.
MISO 19.4
FERC Electric Tariff Facilities Study Procedures
MODULES 30.0.0
Effective On: November 19, 2013
If a System Impact Study indicates that additions or upgrades to the Transmission System
are needed to supply the Eligible Customer’s service request, the Transmission Provider, within
thirty (30) days of the completion of the System Impact Study, shall tender to the Eligible
Customer a Facilities Study Agreement pursuant to which the Eligible Customer shall agree to
reimburse the Transmission Provider or, as applicable, ITC and any affected Transmission
Owner(s) for performing the required Facilities Study. For a service request to remain a
Completed Application, the Eligible Customer shall execute the Facilities Study Agreement in
the form of Attachment D-2 of this Tariff and return it to the Transmission Provider within
fifteen (15) days. If the Eligible Customer elects not to execute the Facilities Study Agreement,
its application shall be deemed withdrawn and any deposit, pursuant to Section 17.4, shall be
returned with interest. Upon receipt of an executed Facilities Study Agreement, the
Transmission Provider or ITC, as applicable, in coordination with the appropriate Transmission
Owner(s) and ITC Participant(s) will use due diligence to complete the required Facilities Study
within a one hundred and twenty (120) day period.
If the Transmission Provider or ITC, as applicable, together with the affected
Transmission Owner(s) and ITC Participant(s) are unable to complete the Facilities Study in the
allotted time period, the Transmission Provider or ITC, as applicable, shall notify the
Transmission Customer and provide an estimate of the time needed to reach a final determination
along with an explanation of the reasons that additional time is required to complete the study.
When completed, the Facilities Study will include a good faith estimate of: (i) the cost of Direct
Assignment Facilities to be charged to the Transmission Customer; (ii) the Transmission
Customer’s appropriate share of the cost of any required Network Upgrades as determined
MISO 19.4
FERC Electric Tariff Facilities Study Procedures
MODULES 30.0.0
Effective On: November 19, 2013
pursuant to the provisions of Module B of this Tariff; and (iii) the time required to complete such
construction and initiate the requested service. Unless the Transmission Provider determines that
the Transmission Customer already has a letter(s) of credit or other form(s) of security on file
with the Transmission Provider that is sufficient to cover its existing and proposed obligations,
the Transmission Customer shall be requested to provide the Transmission Provider with a letter
of credit or other reasonable form of security acceptable to the Transmission Provider or ITC, as
applicable, equivalent to the costs of new facilities or upgrades consistent with commercial
practices as established by the Uniform Commercial Code. Within the time set out on
Attachment J, the Transmission Customer shall execute a Service Agreement or request the filing
of an unexecuted Service Agreement and provide the required letter of credit or other form of
security or the request will no longer be a Completed Application and shall be deemed
terminated and withdrawn.
MISO 19.4.1
FERC Electric Tariff Changes in Facilities Study Assumptions
MODULES 30.0.0
Effective On: November 19, 2013
Any changes to the original assumptions, considered during the
System Impact Study, that arise during the Facilities Study, that can
materially impact the results of the Facilities Study, may require the
Transmission Provider to re-evaluate the results of the original System
Impact Study. If the Transmission Provider ascertains that the changes in
assumptions are material modifications to the original scope of the study,
that could change the outcome of the Facilities Study, then the
Transmission Provider shall temporarily stop work on the Facilities Study
until the results from the re-evaluation are available. After the re-
evaluation results are available, the Transmission Provider will make the
final determination whether the initial Facilities Study should proceed
based on the original scope or based on the revised scope. If the scope of
the initial Facilities Study needs to be revised, then the Transmission
Provider will reset the one hundred and twenty (120) day clock to perform
the revised Facilities Study. The Transmission Provider will take
appropriate steps to communicate to the customer the revised scope and
schedule the revised Facilities Study.
MISO 19.4.1
FERC Electric Tariff Changes in Facilities Study Assumptions
MODULES 30.0.0
Effective On: November 19, 2013
MISO 19.5
FERC Electric Tariff Facilities Study Modifications
MODULES 30.0.0
Effective On: November 19, 2013
Any change in design arising from inability to site or construct facilities as
proposed will require development of a revised good faith estimate. New good
faith estimates also will be required in the event of new statutory or regulatory
requirements that are effective before the completion of construction or other
circumstances beyond the control of the Transmission Provider, ITC, ITC
Participant(s), or the affected Transmission Owner(s) that significantly affect the
final cost of new facilities or upgrades to be charged to the Transmission
Customer pursuant to the provisions of Module B of this Tariff.
MISO 19.6
FERC Electric Tariff Due Diligence in Completing New Facilities
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider or the ITC, as applicable, and the affected
Transmission Owner(s) shall use due diligence to add necessary facilities or
upgrade the Transmission System within a reasonable time. The Transmission
Provider will not allow the upgrade to the existing or planned Transmission
System in order to provide the requested Firm Point-To-Point Transmission
Service if doing so would impair system reliability or otherwise impair or degrade
existing firm service.
MISO 19.7
FERC Electric Tariff Partial Interim Service
MODULES 31.0.0
Effective On: August 2, 2017
If the Transmission Provider or ITC determines that it will not have
adequate transfer capability to satisfy the full amount of a Completed Application
for Firm Point-To-Point Transmission Service, the Transmission Provider
nonetheless shall be obligated to offer and provide the portion of the requested
Firm Point-To-Point Transmission Service that can be accommodated without
addition of any facilities. However, the Transmission Provider shall not be
obligated to provide the incremental amount of requested Firm Point-To-Point
Transmission Service that requires the addition of facilities or upgrades to the
Transmission System until such facilities or upgrades have been placed in service.
MISO 19.8
FERC Electric Tariff Expedited Procedures for New Facilities
MODULES 30.0.0
Effective On: November 19, 2013
In lieu of the procedures set forth above, the Eligible Customer shall have
the option to expedite the process by requesting the Transmission Provider to
tender at one time, together with the results of required studies, an expedited
Service Agreement pursuant to which the Eligible Customer would agree to
compensate the Transmission Provider or ITC and the affected Transmission
Owner(s) for all costs incurred pursuant to the terms of this Tariff. In order to
exercise this option, the Eligible Customer shall request in writing an expedited
Service Agreement covering all of the above-specified items within the time
limits set forth in Attachment J from the time it receives the results of the System
Impact Study identifying needed facility additions or upgrades or costs incurred in
providing the requested service.
While the Transmission Provider, ITC, as applicable, and the affected
Transmission Owner(s) agree to provide the Eligible Customer with their best
estimate of the new facility costs and other charges that may be incurred, such
estimate shall not be binding and the Eligible Customer must agree in writing to
compensate the Transmission Provider, ITC, and the affected Transmission
Owner(s) for all costs incurred pursuant to the provisions of the Tariff. The
Eligible Customer shall execute and return such an Expedited Service Agreement
within fifteen (15) days of its receipt or the Eligible Customer’s request for
service will cease to be a Completed Application and will be deemed terminated
and withdrawn.
MISO 19.8
FERC Electric Tariff Expedited Procedures for New Facilities
MODULES 30.0.0
Effective On: November 19, 2013
MISO 19.9
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines:
MODULES 30.0.0
Effective On: November 19, 2013
Sections 19.3 and 19.4 of this Tariff require a Transmission Provider to use due
diligence to meet sixty (60) day study completion deadlines for System Impact
Studies and a one hundred and twenty (120) day completion deadline for Facilities
Studies.
(i) The Transmission Provider is required to file a notice with the Commission in the
event that more than twenty percent (20%) of non-Affiliates’ System Impact
Studies and Facilities Studies completed by the Transmission Provider in any two
(2) consecutive calendar quarters are not completed within the sixty (60) day
study completion deadlines for System Impact Study, and a one hundred and
twenty (120) day study completion deadline for and Facilities Study. Such notice
must be filed within thirty (30) days of the end of the calendar quarter triggering
the notice requirement.
(ii) For the purposes of calculating the percent of non-Affiliates’ System Impact
Studies and Facilities Studies processed outside of the sixty (60) and one hundred
and twenty (120) day study completion deadlines, respectively, the Transmission
Provider shall consider all System Impact Studies and Facilities Studies that it
completes for non-Affiliates during the calendar quarter. The percentage should
be calculated by dividing the number of those studies which are completed on
time by the total number of completed studies. The Transmission Provider may
provide an explanation in its notification filing to the Commission if it believes
there are extenuating circumstances that prevented it from meeting the sixty (60)
day study completion deadlines for System Impact Studies and the one hundred
MISO 19.9
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines:
MODULES 30.0.0
Effective On: November 19, 2013
and twenty (120) day study completion times for the facilities study.
(iii)The Transmission Provider is subject to an operational penalty if it completes ten
percent (10%) or more of non-Affiliates’ System Impact Studies and Facilities
Studies outside of the sixty (60) and one hundred and twenty (120) day study
completion deadlines, respectively, for each of the two (2) calendar quarters
immediately following the quarter that triggered its notification filing to the
Commission. The operational penalty will be assessed for each calendar quarter
for which an operational penalty applies, starting with the calendar quarter
immediately following the quarter that triggered the Transmission Provider’s
notification filing to the Commission. The operational penalty will continue to be
assessed each quarter until the Transmission Provider completes at least ninety
percent (90%) of all non-Affiliates’ System Impact Studies and Facilities Studies
within the sixty (60) and one hundred and twenty (120) day deadline,
respectively.
(iv) For penalties assessed in accordance with subsection (iii) above, the penalty amount for
each System Impact Study or Facilities Study shall be equal to $500 for each day the
Transmission Provider takes to complete that study beyond the sixty (60) and one hundred and
twenty (120) day deadline, respectively.
MISO 19.9
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines:
MODULES 30.0.0
Effective On: November 19, 2013
MISO 20
FERC Electric Tariff Procedures if Unable to Complete New Facilities for Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 20.1
FERC Electric Tariff Delays in Construction of New Facilities
MODULES 30.0.0
Effective On: November 19, 2013
If any event occurs that will materially affect the time for completion of
new facilities, or the ability to complete them, the Transmission Provider shall
promptly notify the Transmission Customer. In such circumstances, the
Transmission Provider shall within thirty (30) days of notifying the Transmission
Customer of such delays, convene a technical meeting with the Transmission
Customer and the affected Transmission Owner(s) and ITC to evaluate the
alternatives available to the Transmission Customer. The Transmission Provider
also shall make available to the Transmission Customer studies and work papers
related to the delay, including all information that is in the possession of the
Transmission Provider and affected Transmission Owner(s) and ITC that is
reasonably needed by the Transmission Customer to evaluate any alternatives.
MISO 20.2
FERC Electric Tariff Alternatives to the Original Facility Additions
MODULES 30.0.0
Effective On: November 19, 2013
When the review process of Section 20.1 determines that one or more
alternatives exist to the originally planned construction project, the Transmission
Provider together with the affected Transmission Owner(s) and ITC shall present
such alternatives for consideration by the Transmission Customer. If, upon
review of any alternatives, the Transmission Customer desires to maintain its
Completed Application subject to construction of the alternative facilities, it may
request the Transmission Provider to submit a revised Service Agreement for
Firm Point-To-Point Transmission Service. If the alternative approach solely
involves Non-Firm Point-To-Point Transmission Service, the Transmission
Provider shall promptly tender a Service Agreement for Non-Firm Point-To-Point
Transmission Service providing for the service. In the event the Transmission
Provider concludes that no reasonable alternative exists and the Transmission
Customer disagrees, the Transmission Customer may seek relief under the dispute
resolution procedures pursuant to Section 12 or it may refer the dispute to the
Commission for resolution.
MISO 20.3
FERC Electric Tariff Refund Obligation for Unfinished Facility Additions
MODULES 30.0.0
Effective On: November 19, 2013
If the Transmission Provider and the Transmission Customer mutually
agree that no other reasonable alternatives exist and the requested service cannot
be provided out of existing capability under the conditions of Module B of this
Tariff, the obligation to provide the requested Firm Point-To-Point Transmission
Service shall terminate and any deposit made by the Transmission Customer shall
be returned with interest pursuant to Commission regulations at 18 C.F.R. §
35.19a(a)(2)(iii). However, the Transmission Customer shall be responsible for
all prudently incurred costs by the Transmission Provider and the affected ITC
and Transmission Owner(s) through the time construction was suspended.
MISO 21
FERC Electric Tariff Transmission Construction and Service on Other Utilities
MODULES 30.0.0
Effective On: November 19, 2013
MISO 21.1
FERC Electric Tariff Responsibility for Third-Party System Additions
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider, Transmission Owners, ITC, and ITC
Participants shall not be responsible for making arrangements for any necessary
engineering, permitting, and construction of transmission or Distribution Facilities
on the system(s) of any other entity or for obtaining any regulatory approval for
such facilities. The Transmission Provider and the affected ITC and Transmission
Owner(s) will undertake reasonable efforts to assist the Transmission Customer in
obtaining such arrangements, including without limitation, providing any
information or data required by such other electric system pursuant to Good
Utility Practice.
MISO 21.2
FERC Electric Tariff Coordination of Third-Party System Additions
MODULES 30.0.0
Effective On: November 19, 2013
In circumstances where the need for transmission facilities or upgrades is
identified pursuant to the provisions of Module B of this Tariff, and if such
upgrades further require the addition of transmission facilities on other systems,
the affected Transmission Owner(s) and ITC in coordination with the
Transmission Provider shall have the right to coordinate construction on its (their)
own system(s) with the construction required by others. The Transmission
Provider together with the affected Transmission Owner(s), and ITC after
consultation with the Transmission Customer and representatives of such other
systems, may defer construction of new transmission facilities, if the new
transmission facilities on another system cannot be completed in a timely manner.
The Transmission Provider shall notify the Transmission Customer in writing of
the basis for any decision to defer construction and the specific problems which
must be resolved before construction of new facilities will be initiated or resumed.
Within sixty (60) days of receiving written notification by the Transmission
Provider of the intent to defer construction pursuant to this section, the
Transmission Customer may challenge the decision in accordance with the
dispute resolution procedures pursuant to Section 12 or it may refer the dispute to
the Commission for resolution.
MISO 22
FERC Electric Tariff Changes in Service Specifications
MODULES 30.0.0
Effective On: November 19, 2013
All changes in service specifications shall be subject to reservation priority set forth in Sections
13.2 and 14.2 of this Tariff as if each change was an original request for transmission service.
MISO 22.1
FERC Electric Tariff Modifications on a Non-Firm Basis
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Customer taking Firm Point-To-Point Transmission
Service may request the Transmission Provider to provide Transmission Service
on a non-firm basis over Receipt and Delivery Points other than those specified in
the Service Agreement (“Secondary Receipt and Delivery Points”), in amounts
not to exceed its firm capacity reservation, without incurring an additional Non-
Firm Point-To-Point Transmission Service charge (except as provided in Section
22.2) or executing a new Service Agreement, subject to the following conditions.
a. Service provided over secondary Receipt and Delivery Points will be non-
firm only, on an as-available basis and will not displace any firm or non-
firm service reserved or scheduled by third-parties under this Tariff or by
the Transmission Owner on behalf of its Native Load Customers.
b. The sum of all Firm and Non-Firm Point-To-Point Transmission Service
provided to the Transmission Customer at any time pursuant to this
section shall not exceed the Reserved Capacity in the relevant Service
Agreement under which such services are provided.
c. The Transmission Customer shall retain its right to schedule Firm Point-
To-Point Transmission Service at the Receipt and Delivery Points
specified in the relevant Service Agreement in the amount of its original
capacity reservation.
d. Service over secondary Receipt and Delivery Points on a non-firm basis
shall not require the filing of an Application for Non-Firm Point-To-Point
Transmission Service under this Tariff. However, all other requirements
MISO 22.1
FERC Electric Tariff Modifications on a Non-Firm Basis
MODULES 30.0.0
Effective On: November 19, 2013
of Module B of this Tariff (except as to transmission rates) shall apply to
Transmission Service on a non-firm basis over secondary Receipt and
Delivery Points.
MISO 22.2
FERC Electric Tariff Additional Charge to Prevent Abuse
MODULES 30.0.0
Effective On: November 19, 2013
If a Transmission Customer making the modifications in Section 22.1
takes service over a transmission path that costs more than the path the
Transmission Customer initially reserved, then for the service the Transmission
Customer schedules, the Transmission Customer shall pay in addition to the
amounts based on its initial reservation the additional costs (i.e., the difference
between the zonal rates) associated with the new path. Such additional charge
shall be prorated to apply only for the period of time during which service is
scheduled over the secondary path. In addition, the Market Participant shall pay
for Marginal Losses and any congestion relief costs based on the actual
transmission path for which service is scheduled according to the provisions in
Module C.
MISO 22.3
FERC Electric Tariff Modification on a Firm Basis
MODULES 30.0.0
Effective On: November 19, 2013
Any request by a Transmission Customer taking Firm Point-To-Point
Transmission Service to modify Receipt and Delivery Points on a firm basis shall
be treated as a new request for service in accordance with Section 17 hereof,
except that such Transmission Customer shall not be obligated to pay any
additional deposit if the capacity reservation does not exceed the amount reserved
in the existing Service Agreement. While such new request is pending, the
Transmission Customer shall retain its priority for service at the existing firm
Receipt and Delivery Points specified in its Service Agreement.
a. Notwithstanding the foregoing, if a Receipt or Delivery Point is
modified on a short-term basis (i.e., daily, weekly or monthly for a
term less than 12 full months) resulting in a transmission path
(“redirect path”) for which the applicable transmission rate is lower
than the transmission rate in effect between the original Receipt and
Delivery Points (“original path”), the Transmission Customer shall
pay, in addition to the amounts associated with the redirect path, an
additional charge reflecting the difference in the firm transmission and
applicable ancillary services rates between the original path and the
redirect path for the duration its service is redirected pursuant to this
Section 22.3. The term “original Receipt and Delivery Points,” as
used in this subsection (a), shall mean the initial set of Receipt and
Delivery Points rather than any Receipt or Delivery Point modified
under Section 22.3.
MISO 22.3
FERC Electric Tariff Modification on a Firm Basis
MODULES 30.0.0
Effective On: November 19, 2013
Crediting Procedure
For purposes of this Crediting Procedure, the term “constrained path”
shall mean instances where a path between a Point of Receipt and a
Point of Delivery is comprised of a single or multi-element interface
for which transmission service is administered to the interface limit
and a single flowgate has been defined and which is fully subscribed
with firm Transmission Service at the time service is redirected
pursuant to this Section 22.3. If all or part of the transmission capacity
on the constrained path that becomes available as a result of a firm
redirect originating on that path is subsequently resold as new firm
service, the redirecting customer(s) will receive a credit on a pro-rata
MWh basis. The credit shall be for the same number of MWhs that
were resold on the original path and shall represent the per MWh
incremental charge that was collected from the redirecting customer
pursuant to this paragraph (a) of Section 22.3 of the Tariff.
MISO 23
FERC Electric Tariff Sale or Assignment of Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 23.1
FERC Electric Tariff Procedures for Assignment or Transfer of Service
MODULES 30.0.0
Effective On: November 19, 2013
(a) A Transmission Customer may sell, assign, or transfer all or a portion of
its rights under its Service Agreement, but only to another Eligible Customer (the
“Assignee”). The Transmission Customer that sells, assigns or transfers its rights
under its Service Agreement is hereafter referred to as the “Reseller.”
Compensation to Resellers shall be at rates established by agreement between the
Reseller and the Assignee.
(b) The Assignee must execute a service agreement with the Transmission
Provider governing reassignments of transmission service prior to the date on
which the reassigned service commences. The Transmission Provider shall
charge the Reseller, as appropriate, at the rate stated in the Reseller’s Service
Agreement with the Transmission Provider or the associated OASIS schedule and
credit the Reseller with the price reflected in the Assignee’s Service Agreement
with the Transmission Provider or the associated OASIS schedule; provided that,
such credit shall be reversed in the event of non-payment by the Assignee. If the
Assignee does not request any change in the Point(s) of Receipt or the Point(s) of
Delivery, or a change in any other term or condition set forth in the original
Service Agreement, the Assignee will receive the same services as did the
Reseller and the priority of service for the Assignee will be the same as that of the
Reseller. The Assignee will be subject to all terms and conditions of this Tariff.
If the Assignee requests a change in service, the reservation priority of service
will be determined by the Transmission Provider pursuant to Section 13.2.
MISO 23.1
FERC Electric Tariff Procedures for Assignment or Transfer of Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 23.2
FERC Electric Tariff Limitations on Assignment or Transfer of Service
MODULES 30.0.0
Effective On: November 19, 2013
If the Assignee requests a change in the Point(s) of Receipt or Point(s) of
Delivery, or a change in any other specifications set forth in the original Service
Agreement, the Transmission Provider will consent to such change subject to the
provisions of the Tariff, provided that the change will not impair the operation
and reliability of the Transmission Owners’, ITC’s, or ITC Participant’s
generation, transmission, or distribution systems. The Assignee also will pay
additional charges, if any, provided for by Section 22.2, and for any additional
charges, including Ancillary Services, or other Transmission Provider charges. In
addition, the Market Participant shall be financially responsible for any Energy,
Marginal Congestion Charge, and Marginal Losses associated with related Market
Participant’s transactions as set forth in Sections 39.3.1, 39.3.3, 40.3 and 40.4.
The Assignee shall compensate the Transmission Provider or ITC, as
applicable, for performing any System Impact Study needed to evaluate the
capability of the Transmission System to accommodate the proposed change and
any additional costs resulting from such change. The Reseller shall remain liable
for the performance of all obligations under the Service Agreement, except as
specifically agreed to by the Transmission Provider and the Reseller through an
amendment to the Service Agreement.
MISO 23.3
FERC Electric Tariff Information on Assignment or Transfer of Service
MODULES 30.0.0
Effective On: November 19, 2013
In accordance with Section 4, all sales or assignments of capacity must be
conducted through or otherwise posted on the Transmission Provider’s OASIS on
or before the date the reassigned service commences and are subject to Section
23.l. Resellers may also use the Transmission Provider’s OASIS to post
transmission capacity available for resale.
MISO 24
FERC Electric Tariff Metering and Power Factor Correction
MODULES 30.0.0
Effective On: November 19, 2013
MISO 24.1
FERC Electric Tariff Transmission Customer Obligations
MODULES 30.0.0
Effective On: November 19, 2013
Unless otherwise agreed, the Transmission Customer shall be responsible
for the cost of installing and maintaining compatible metering and communications
equipment to accurately account for the Energy being transmitted under this Tariff
and to communicate the information to the Transmission Provider. Such equipment
installed on the Transmission Customer’s system shall remain the property of the
Transmission Customer. Such equipment installed on the Transmission Owner’s or
ITC’s system shall remain the property of the Transmission Owner or ITC.
MISO 24.2
FERC Electric Tariff Transmission Provider Access to Metering Data
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider or its agent or, as applicable, ITC shall have
access to metering data, which may reasonably be required to facilitate
measurements and billing under the Service Agreement.
MISO 24.3
FERC Electric Tariff Power Factor
MODULES 30.0.0
Effective On: November 19, 2013
Unless otherwise agreed, the Transmission Customer is required to
maintain a power factor within the same range specified by the Transmission
Provider, in consultation with the appropriate Transmission Owners and ITC,
pursuant to Good Utility Practices. The power factor requirements are specified
in the Service Agreement where applicable.
MISO 25
FERC Electric Tariff Compensation for Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
Rates for Firm and Non-Firm Point-To-Point Transmission Service are provided
in the Schedules appended to this Tariff: Firm Point-To-Point Transmission Service
(Schedule 7); and Non-Firm Point-To-Point Transmission Service (Schedule 8). In
addition to paying any applicable Operating Reserve costs and Other Ancillary Service
costs, the Transmission Customer also shall pay: (i) the Transmission Provider’s costs in
accordance with Schedule 10 and/or, if applicable; (ii) the ITC administrative fee plus
any other applicable charges in accordance with the applicable ITC Rate Schedule.
MISO 26
FERC Electric Tariff Stranded Cost Recovery
MODULES 30.0.0
Effective On: November 19, 2013
This Tariff, including any ITC Rate Schedule, does not affect in any way the right
of any Transmission Owner or ITC Participant to seek and receive stranded cost recovery
or the right of anyone to oppose such stranded cost recovery. Thus, the Transmission
Owner(s) or ITC Participant(s) may seek to recover stranded costs from the User(s) in
accordance with the terms, conditions and procedures set forth in FERC Order No. 888.
However, the Transmission Owner(s) or ITC Participant(s) must separately file any
specific proposed stranded cost charge under Section 205 of the Federal Power Act. If
the Commission approves stranded cost charges to be recovered through schedules to be
implemented by the Transmission Provider, the Transmission Provider as agent shall
charge and collect the appropriate charge(s) from the relevant User(s) and distribute the
appropriate amounts directly to the relevant Transmission Owner(s) or ITC Participant(s).
MISO 27
FERC Electric Tariff Compensation for New Facilities and Redispatch Costs
MODULES 31.0.0
Effective On: August 2, 2017
Whenever a System Impact Study performed by the Transmission Provider in
connection with the provision of Firm Point-To-Point Transmission Service identifies the
need for new facilities, the recovery of such costs shall be governed by Attachment N.
MISO 27A
FERC Electric TariffPOINT-TO-POINT TRANSMISSION SERVICE ON HIGH-VOLTAGE DIRECT C
MODULES 30.0.0
Effective On: November 19, 2013
POINT-TO-POINT TRANSMISSION SERVICE ON HIGH-VOLTAGE DIRECT
CURRENT FACILITIES
This Section 27A applies in lieu of Sections 13-27 of the Tariff to govern Point-
To-Point Transmission Service on HVDC Facilities (HVDC Service). The Transmission
Provider shall provide Firm and Non-Firm HVDC Service pursuant to the applicable
terms and conditions of this Section 27A and other applicable provisions of the Tariff for
Transmission Customers that have executed an HVDC Service Agreement with the
Transmission Provider. Service under this Section 27A is conditioned on the
Transmission Provider and the owner or operator of an HVDC Facility executing an
Agency Agreement or other suitable contractual arrangement permitting the
Transmission Provider to provide HVDC Service on such HVDC Facility, and such
HVDC Service shall be provided as long as such Agency Agreement or other contractual
arrangement remains in effect, unless otherwise provided by the parties thereto. All
requests for eligible HVDC Service during the first five minutes after the time when Firm
HVDC Service can first be requested on the OASIS in accordance with Attachment J
(except for hourly service to which this sentence does not apply), will be considered as if
they were submitted at the same time.
MISO 27A.1
FERC Electric Tariff Nature of Firm High-Voltage Direct Current Service
MODULES 31.0.0
Effective On: December 20, 2013
MISO 27A.1.1
FERC Electric Tariff Term of Firm High-Voltage Direct Current Service:
MODULES 32.0.0
Effective On: December 20, 2013
The minimum term of Firm HVDC Service shall be one (1) day and the maximum term shall be
that specified in the relevant Transmission Customer’s HVDC Service Agreement.
MISO 27A.1.2
FERC Electric Tariff Reservation Priority for Firm High-Voltage Direct Current Se
MODULES 30.0.0
Effective On: November 19, 2013
Reservation Priority for Firm High-Voltage Direct Current Service:
(i) Long-Term Firm HVDC Service shall be determined on a first-come, first-served basis,
i.e., in the chronological sequence in which each Transmission customer has reserved
service.
(ii) Reservations for Short-Term Firm HVDC Service will be conditional based upon the
length of the requested transaction or reservation. However, Pre-Confirmed Requests for
Short-Term Firm HVDC Service will receive priority over earlier-submitted requests that
are not Pre-Confirmed and that have equal or shorter duration. Among requests with the
same duration and, as relevant, pre-confirmation status (pre-confirmed, confirmed, or not
pre-confirmed), priority will be given to an Eligible Customer’s request or reservation
based on the earliest date and time of the request or reservation.
(iii) If the HVDC Facilities become oversubscribed, requests for service may preempt
competing requests or reservations up to the following conditional reservation deadlines:
one day before the commencement of daily service, one week before the commencement
of weekly service, and one month before the commencement of monthly service. Before
the conditional reservation deadline, if Available Transfer Capability is insufficient to
satisfy all requests and reservations, an Eligible Customer with a reservation for shorter
term service or equal duration service has the right of first refusal to match any longer
term request or equal duration service before losing its reservation priority. A longer
term competing request for Short-Term Firm HVDC Service will be granted if the
Eligible Customer with the right of first refusal does not agree to match the competing
request within 24 hours (or earlier if necessary to comply with the scheduling deadlines
MISO 27A.1.2
FERC Electric Tariff Reservation Priority for Firm High-Voltage Direct Current Se
MODULES 30.0.0
Effective On: November 19, 2013
provided in Section 27A.1.7) from being notified by the Transmission Provider of a
longer-term competing request for Short-Term Firm HVDC Service. When a longer
duration request preempts multiple shorter duration reservations, the shorter duration
reservations shall have simultaneous opportunities to exercise the right of first refusal.
Time of match confirmation will be used to determine the order by which the multiple
shorter duration reservations will be able to exercise the right of first refusal. In the event
the match confirmations are submitted simultaneously, the original OASIS queue time will be
utilized to determine the order by which the multiple shorter duration reservations will be
able to exercise the right of first refusal. After the conditional reservation deadline, service
will commence pursuant to the terms of this Section 27A.
(iv) Firm HVDC Service will always have a reservation priority over Non-Firm HVDC
Service under this Section 27A. Reservation priorities for existing firm service
customers are provided in Section 2.2 of this Tariff.
MISO 27A.1.3
FERC Electric Tariff Firm High-Voltage Direct Current Service Agreements:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall offer a standard form Firm
HVDC Service Agreement to an Eligible Customer when it submits a
Completed Application for Long-Term HVDC Service pursuant to this
Tariff. The Transmission Provider shall offer a standard form Firm
HVDC Service Agreement to an Eligible Customer when it first submits a
Completed Application for Short-Term Firm HVDC Service pursuant to
this Tariff. Executed HVDC Service Agreements that contain the
information required under this Tariff will be reported and/or filed by the
Transmission Provider with the Commission in compliance with
applicable Commission regulations. The standard form of Service
Agreements for Firm HVDC Service is provided in Attachment A-3 of the
Tariff. An Eligible Customer that uses HVDC Service at a Point of
Receipt or Point of Delivery that it has not reserved and that has not
executed a HVDC Service Agreement will be deemed, for purposes of
assessing any appropriate charges and penalties, to have executed the
appropriate Service Agreement.
If offered pursuant to an Agency Agreement, a Service Agreement
shall be executed by the Transmission Provider as agent for the relevant
Transmission Owner. In the event that the relevant Agency Agreement
terminates, the Transmission Provider will make a filing under section 205
of the Federal Power Act requesting that any HVDC Service offered by
the Transmission Provider under such a Service Agreement revert to the
MISO 27A.1.3
FERC Electric Tariff Firm High-Voltage Direct Current Service Agreements:
MODULES 30.0.0
Effective On: November 19, 2013
relevant Transmission Owner and the Transmission Provider be released
from all obligations and responsibilities under such Service Agreement.
MISO 27A.1.4
FERC Electric Tariff Obligations for Facility Additions or Redispatch Costs
MODULES 31.0.0
Effective On: August 2, 2017
In cases where the Transmission Provider determines that the
HVDC Facilities are not capable of providing Firm HVDC Service
without: (1) degrading or impairing the reliability of service to
Transmission Customers taking Firm HVDC Service; or (2) interfering
with the Transmission Provider’s ability to meet prior firm contractual
commitments to others, the relevant Transmission Owner(s) will be
obligated to expand or upgrade its (their) HVDC Facilities pursuant to the
terms of Section 27A.3.4 of this Tariff.
The Transmission Customer must agree to pay the Transmission
Provider for any necessary transmission facility additions pursuant to the
terms of Section 27A.15 of this Tariff.
Any HVDC Facility Upgrades or Direct Assignment Facilities
costs to be charged to the Transmission Customer on an incremental basis
under this Tariff will be specified in the HVDC Service Agreement prior
to initiating service.
MISO 27A.1.5
FERC Electric Tariff Curtailment of Firm High-Voltage Direct Current Service
MODULES 32.0.0
Effective On: January 2, 2019
In the event that a Curtailment on the HVDC Facilities, or a portion thereof, is required to
maintain reliable operation of such system, and the systems directly and indirectly
interconnected with the HVDC Facilities, Curtailments will be made on a non-discriminatory
basis to the transaction(s) that effectively relieve the constraint. The Transmission Provider may
elect to implement such Curtailments pursuant to the Transmission Loading Relief Procedures
specified in NERC Reliability Standards and NAESB WEQ Business Practice Standards. If
multiple transactions require Curtailment, to the extent practicable and consistent with Good
Utility Practice, the Transmission Provider will curtail service on a non-discriminatory basis.
All Curtailments will be made on a non-discriminatory basis; however, Non-Firm HVDC
Service shall be subordinate to Firm HVDC Service. Long-Term Firm HVDC Service subject to
conditions described in Section 27A.3.4 shall be curtailed with secondary service in cases where
the conditions apply, but otherwise will be curtailed on a pro rata basis with other Firm HVDC
Service.
When the Transmission Provider determines that an electrical Emergency exists on its
Transmission System or the HVDC Facilities and implements Emergency procedures to curtail
Firm HVDC Service, the Transmission Customer shall make the required reductions upon
request of the Transmission Provider. However, the Transmission Provider reserves the right to
curtail, in whole or in part, any Firm HVDC Service provided under the Tariff when, in the
Transmission Provider’s sole discretion, an Emergency or other unforeseen condition impairs or
degrades the reliability of its Transmission System or the HVDC Facilities. The Transmission
Provider will notify all affected Transmission Customers in a timely manner of any scheduled
Curtailments. In the event that the Transmission Customer fails to cease or reduce service in
MISO 27A.1.5
FERC Electric Tariff Curtailment of Firm High-Voltage Direct Current Service
MODULES 32.0.0
Effective On: January 2, 2019
response to a directive by the Transmission Provider, the Transmission Customer shall pay the
following penalties in addition to any other applicable charges: $10 per kW if the customer fails
to curtail service within ten (10) minutes of a directive by the Transmission Provider; or $20 per
kW if the customer fails to curtail service within twenty (20) minutes of a directive by the
Transmission Provider.
These charges shall apply only to the portion of the service that the Transmission
Customer fails to curtail in response to a Transmission Provider directive. The Transmission
Provider, where applicable, shall compensate any affected Control Areas or Generation
Resources for their actual costs up to the amount recovered by the Transmission Provider, as
applicable. Any revenues in excess of actual costs shall be used to reduce the Transmission
Provider’s costs (for other than the penalized Transmission Customer) in Schedule 35.
MISO 27A.1.6
FERC Electric Tariff Classification of Firm High-Voltage Direct Current Service
MODULES 31.0.0
Effective On: May 1, 2015
i. The Transmission Customer taking Firm HVDC Service may (1) change its Receipt and
Delivery Points to obtain service on a non-firm basis consistent with the terms of Section
27A.10.1 or (2) request a modification of the Points of Receipt or Delivery on a firm
basis pursuant to the terms of Section 27A.10.2.
ii. The Transmission Provider shall provide firm deliveries of capacity and energy from the
Point(s) of Receipt to the Point(s) of Delivery. Each Point of Receipt at which firm
transmission capacity is reserved by the Transmission Customer shall be set forth in the
Firm HVDC Service Agreement for Long-Term Firm HVDC Service along with a
corresponding capacity reservation associated with each Point of Receipt.
Points of Receipt and corresponding capacity reservations shall be as mutually agreed
upon by the Parties for Short-Term Firm HVDC Service. Each Point of Delivery at
which firm transfer capability is reserved by the Transmission Customer shall be set forth
in the Firm HVDC Service Agreement for Long-Term Firm HVDC Service along with a
corresponding capacity reservation associated with each Point of Delivery. Points of
Delivery and corresponding capacity reservations shall be as mutually agreed upon by the
Parties for Short-Term Firm HVDC Service. The greater of either (1) the sum of the
capacity reservations at the Point(s) of Receipt or (2) the sum of the capacity reservations
at the Point(s) of Delivery shall be the Transmission Customer’s Reserved Capacity.
The Transmission Customer will be billed for its Reserved Capacity under the terms of
the Schedule 7. The Transmission Customer may not exceed its firm capacity reserved at
each Point of Receipt and each Point of Delivery.
MISO 27A.1.6
FERC Electric Tariff Classification of Firm High-Voltage Direct Current Service
MODULES 31.0.0
Effective On: May 1, 2015
In the event that MISO identifies that a Transmission Customer’s delivered energy
exceeds its firm reserved capacity at any Point of Receipt or Point of Delivery, the
Transmission Customer shall pay unreserved use penalties as follows: (1) the unreserved
use penalties shall be based on the period of unreserved use; (2) the unreserved use
penalty for a single hour of unreserved use shall be the applicable rate for daily Firm
HVDC Service, as set forth in Schedule 7 of the Tariff; and (3) more than one assessment
for a given duration (e.g., daily) shall result in an increase of the penalty period to the
next longest duration (e.g., weekly). Unreserved use penalties assessed using daily Firm
HVDC Service rates shall account for off-peak and on-peak usage, as set forth in
Schedule 7 of the Tariff. A 200% multiplier shall be applied to all assessed penalties.
These penalty revenues shall be allocated in the manner set forth in Section 13.7 of the
Tariff.
iii. Evaluation of Interchange Schedules (including Third-Party Sales by a Transmission
Owner) against firm reserved capacity will be utilized to identify instances of unreserved
use.
MISO 27A.1.7
FERC Electric Tariff Scheduling Associated with Firm High-Voltage Direct Current
MODULES 30.0.0
Effective On: November 19, 2013
Scheduling Associated with Firm High-Voltage Direct
Current Service
Interchange Schedules for the Transmission Customer’s
Firm HVDC Service must be submitted in accordance with the
terms in Attachment J.
Interchange Schedules submitted after the time
specified in Attachment J will be accommodated, if practicable.
Transmission Customers shall submit all Interchange
Schedules electronically in a form specified by the
Transmission Provider. Hour-to-hour Interchange Schedules of
any capacity and energy that is to be delivered must be stated
in increments of 1,000 kW per hour and shall be subject to the
minimum scheduling requirements of the relevant HVDC
Facilities. Transmission Customers within a Transmission
Owner’s service (or control) area with multiple requests for
HVDC Service at a Point of Receipt, each of which is under
1,000 kW per hour, may consolidate their service requests at a
common Point of Receipt into units of 1,000 kW per hour for
scheduling and billing purposes.
Scheduling changes will be permitted in accordance
with Attachment J. However, in the event of a system
contingency such as a generation or an unplanned
MISO 27A.1.7
FERC Electric Tariff Scheduling Associated with Firm High-Voltage Direct Current
MODULES 30.0.0
Effective On: November 19, 2013
Transmission Outage, or Curtailment or Interruption of
Transmission Service, scheduling changes will be implemented
as soon as practicable.
The Transmission Provider will furnish to the
Delivering Party’s system operator, hour-to-hour Interchange
Schedules equal to those furnished by the Receiving Party and
shall deliver the capacity and energy provided by the
Delivering Party. Should the Transmission Customer,
Delivering Party or Receiving Party revise or terminate any
Interchange Schedule, such party shall immediately notify the
Transmission Provider, and the Transmission Provider shall
have the right to adjust accordingly the schedule for capacity
and Energy to be received and to be delivered.
MISO 27A.2
FERC Electric Tariff Nature of Non-Firm High-Voltage Direct Current Service
MODULES 31.0.0
Effective On: December 20, 2013
MISO 27A.2.1
FERC Electric Tariff Term
MODULES 30.0.0
Effective On: November 19, 2013
Non-Firm HVDC Service will be available for periods ranging
from one (1) hour to one (1) month. However, a Purchaser of Non-Firm
HVDC Service will be entitled to reserve a sequential term of service
(such as a sequential monthly term without having to wait for the initial
term to expire before requesting another monthly term) so that the total
time period for which the reservation applies may be greater than one
month, subject to the requirements of Attachment J.
MISO 27A.2.2
FERC Electric Tariff Reservation Priority
MODULES 30.0.0
Effective On: November 19, 2013
Non-Firm HVDC Service shall be available from transfer
capability in excess of that needed for reliable service to Transmission
Customers taking Long-Term and Short-Term Firm HVDC Service.
A higher reservation priority will be assigned first to Non-Firm
HVDC Service requests or reservations with a longer duration of service
than those reservations with a shorter duration and second to Pre-
Confirmed Requests.
Eligible Customers that have already reserved shorter-term service
have the right of first refusal to match any longer-term request before
being preempted. A longer-term competing request for Non-Firm HVDC
Service will be granted if the Eligible Customer with the right of first
refusal does not agree to match the competing request: (i) immediately for
hourly Non-Firm HVDC Service after notification by the Transmission
Provider; and, (ii) within twenty-four (24) hours (or earlier if necessary to
comply with the scheduling deadlines provided in Attachment J) for Non-
Firm HVDC Service other than hourly transactions after notification by
the Transmission Provider. When a longer duration request preempts
multiple shorter duration reservations, the shorter duration reservations
shall have simultaneous opportunities to exercise the right of first refusal.
Time of match confirmation will be used to determine the order by which
the multiple shorter duration reservations will be able to exercise the right
of first refusal. In the event the match confirmations are submitted
MISO 27A.2.2
FERC Electric Tariff Reservation Priority
MODULES 30.0.0
Effective On: November 19, 2013
simultaneously, the original OASIS queue time will be utilized to
determine the order by which the multiple shorter duration reservations
will be able to exercise the right of first refusal. After the conditional
reservation deadline, service will commence pursuant to the terms of this
Tariff.
MISO 27A.2.3
FERC Electric Tariff Non-Firm High-Voltage Direct Current Service Agreements
MODULES 31.0.0
Effective On: December 20, 2013
The Transmission Provider shall offer a standard form Non-Firm HVDC Service
Agreement (Attachment B-1 of this Tariff) to an Eligible Customer when it first submits a
Completed Application for Non-Firm HVDC Service pursuant to this Tariff. Executed HVDC
Service Agreements that contain the information required under this Tariff shall be filed with the
Commission in compliance with applicable Commission regulations.
MISO 27A.2.4
FERC Electric Tariff Classification of Non-Firm High-Voltage Direct Current Servi
MODULES 31.0.0
Effective On: May 1, 2015
Classification of Non-Firm High-Voltage Direct Current Service:
Non-Firm HVDC Service shall be offered under terms and conditions contained in
Section 27A and other applicable provisions of this Tariff. The Transmission Provider and
Transmission Owners undertake no obligation under this Tariff to plan the HVDC Facilities in
order to have sufficient capacity for Non-Firm HVDC Service. Parties requesting Non-Firm
HVDC Service for the transmission of firm power do so with the full realization that such service
is subject to availability and to Curtailment or Interruption under the terms of this Tariff. In the
event that MISO identifies that a Transmission Customer’s delivered energy exceeds its non-firm
reserved capacity at any Point of Receipt or Point of Delivery, the Transmission Customer shall
pay unreserved use penalties as follows: (1) the unreserved use penalties shall be based on the
period of unreserved use; (2) the unreserved use penalty for a single hour of unreserved use shall
be the applicable rate for daily Firm HVDC Service, as set forth in Schedule 7 of the Tariff; and
(3) more than one assessment for a given duration (e.g., daily) shall result in an increase of the
penalty period to the next longest duration (e.g., weekly).
Unreserved use penalties assessed using daily Firm HVDC Service rates shall account for
off-peak and on-peak usage, as set forth in Schedule 7 of the Tariff. A 200% multiplier shall be
applied to all assessed penalties. These penalty revenues shall be allocated in the manner set
forth in Section 13.7 of the Tariff. Non-Firm HVDC Service shall include transmission of
Energy on an hourly basis and transmission of scheduled short-term capacity and Energy on a
daily, weekly or monthly basis, but not to exceed one month’s reservation for any one
Application, under Schedule 8.
MISO 27A.2.4
FERC Electric Tariff Classification of Non-Firm High-Voltage Direct Current Servi
MODULES 31.0.0
Effective On: May 1, 2015
Evaluation of Interchange Schedules (including Third-Party Sales by a Transmission
Owner) against non-firm reserved capacity will be utilized to identify instances of unreserved
use.
MISO 27A.2.5
FERC Electric Tariff Scheduling of Non-Firm High-Voltage Direct Current Service:
MODULES 30.0.0
Effective On: November 19, 2013
Interchange Schedules for Non-Firm HVDC Service must be
submitted to the Transmission Provider in accordance with the terms in
Attachment J.
Interchange Schedules submitted after the time specified in
Attachment J will be accommodated, if practicable. Transmission
Customers shall submit all Interchange Schedules electronically in a form
specified by the Transmission Provider. Hour-to-hour Interchange
Schedules of Energy that is to be delivered must be stated in increments of
1,000 kW per hour and shall be subject to the minimum scheduling
requirements of the relevant HVDC Facilities. Transmission Customers
within the Transmission Owner’s service (or control) area with multiple
requests for HVDC Service at a Point of Receipt, each of which is under
1,000 kW per hour [MWh], may consolidate their schedules at a common
Point of Receipt into units of 1,000 kW per hour [MWh]. Scheduling
changes will be permitted in accordance with Attachment J.
The Transmission Provider will furnish to the Delivering Party’s
system operator, hour-to-hour Interchange Schedules equal to those
furnished by the Receiving Party (unless reduced for losses) and shall
deliver the Energy provided by the Delivering Party. Should the
Transmission Customer, Delivering Party or Receiving Party revise or
terminate any Interchange Schedule, such party shall immediately notify
the Transmission Provider, and the Transmission Provider shall have the
MISO 27A.2.5
FERC Electric Tariff Scheduling of Non-Firm High-Voltage Direct Current Service:
MODULES 30.0.0
Effective On: November 19, 2013
right to adjust accordingly the schedule for Energy to be received and to
be delivered. Schedules for Non-Firm HVDC Service for Next-Hour
Transmission Service must be submitted to the Transmission Provider no
later than twenty (20) minutes and no earlier than sixty (60) minutes
before the start of the schedule. Schedules submitted less than twenty (20)
minutes prior to the start of the schedule will be accommodated, if
practicable.
MISO 27A.2.6
FERC Electric Tariff Curtailment or Interruption of Non-Firm High-Voltage Direct
MODULES 31.0.0
Effective On: January 2, 2019
Curtailment or Interruption of Non-Firm High-Voltage Direct
Current Service:
The Transmission Provider reserves the right to curtail, in whole or
in part, Non-Firm HVDC Service provided under this Tariff for reliability
reasons when, an Emergency or other unforeseen condition threatens to
impair or degrade the reliability of the HVDC Facilities or the systems
directly and indirectly interconnected with the HVDC Facilities. The
Transmission Provider may elect to implement such Curtailments pursuant
to the Transmission Loading Relief Procedures specified in NERC
Reliability Standards and NAESB WEQ Business Practice Standards. The
Transmission Provider reserves the right to interrupt, in whole or in part,
Non-Firm HVDC Service provided under this Tariff for economic reasons
in order to accommodate (i) a request for Firm HVDC Service; (ii) a
request for Non-Firm HVDC Service of greater duration; (iii) a request
for Non-Firm HVDC Service of equal duration with a higher price; or (iv)
transmission service for Firm HVDC Service during conditional
curtailment periods as described in Section 27A.3.4.
The Transmission Provider also will discontinue or reduce service to the
Transmission Customer to the extent that deliveries for transmission are
discontinued or reduced at the Point(s) of Receipt.
Where required, Curtailments or Interruptions will be made on a
nondiscriminatory basis to the transaction(s) that effectively relieve the
MISO 27A.2.6
FERC Electric Tariff Curtailment or Interruption of Non-Firm High-Voltage Direct
MODULES 31.0.0
Effective On: January 2, 2019
constraint; however, Non-Firm HVDC Service shall be subordinate to
Firm HVDC Service. If multiple transactions require Curtailment or
Interruption, to the extent practicable and consistent with Good Utility
Practice, Curtailments or Interruptions will be made to transactions
beginning with those transactions of the shortest term (e.g., hourly non-
firm transactions will be curtailed or interrupted before daily non-firm
transactions and daily non-firm transactions will be curtailed or
interrupted before weekly non-firm transactions).
The Transmission Provider will provide advance notice of Curtailment or
Interruption where such notice can be provided consistent with Good
Utility Practice. In the event that the Transmission Customer fails to cease
or reduce service in response to a directive by the Transmission Provider,
the Transmission Customer shall pay the following penalties in addition to
any other applicable charges:
i. $10 per kW if the Customer fails to curtail service
within ten (10) minutes of a directive by the
Transmission Provider;
ii. $20 per kW if the Customer fails to curtail service
within twenty (20) minutes of a directive by the
Transmission Provider; or
iii. $20 per kW if the customer fails to interrupt service
at the beginning of the Hour for which the
MISO 27A.2.6
FERC Electric Tariff Curtailment or Interruption of Non-Firm High-Voltage Direct
MODULES 31.0.0
Effective On: January 2, 2019
Interruption is requested; provided that the customer
is given a minimum of forty (40) minutes notice
before the beginning of such Hour; and provided
further that the customer may retain its service and
avoid the penalty by agreeing pursuant to Section
27A.2.2 of this Tariff to match any longer-term
reservation and/or higher price in a competing
request before being Interrupted.
These charges shall apply only to the portion of the service
that the Transmission Customer fails to curtail or
interrupt in response to a Curtailment or Interruption
directive. The Transmission Provider shall
compensate any affected Control Areas or generators
for their actual costs up to the amount recovered by
the Transmission Provider. Any revenues in excess
of actual costs shall be used to reduce the
Transmission Provider costs (for other than the
penalized Transmission Customer) in Schedule 35.
MISO 27A.3
FERC Electric Tariff Service Availability
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.3.1
FERC Electric Tariff General Conditions
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider will provide HVDC Service over, on or
across its HVDC Facilities to any Transmission Customer that has met the
requirements of Section 27.A.4.1.
MISO 27A.3.2
FERC Electric Tariff Determination of Available Transfer Capability
MODULES 30.0.0
Effective On: November 19, 2013
A description of the Transmission Provider’s specific methodology for assessing
ATC posted on the Transmission Provider’s OASIS is contained in
Attachment C of the Tariff. In the event sufficient transfer capability may
not exist to accommodate a service request, the Transmission Provider
will respond by performing a System Impact Study.
MISO 27A.3.3
FERC Electric Tariff Initiating Service in Absence of an Executed Agreement
MODULES 30.0.0
Effective On: November 19, 2013
If the Transmission Provider and the Transmission Customer
requesting HVDC Service cannot agree on all the terms and conditions of
the HVDC Service Agreement, the Transmission Provider shall file with
the Commission, within thirty (30) days after the date the Transmission
Customer provides written notification directing the HVDC Service
Provider to file, an unexecuted HVDC Service Agreement containing
terms and conditions deemed appropriate by the Transmission Provider for
such requested HVDC Service. The Transmission Provider shall
commence providing HVDC Service subject to the Transmission
Customer agreeing to (i) compensate the Transmission Provider at
whatever rate the Commission ultimately determines to be just and
reasonable, and (ii) comply with the terms and conditions of the Tariff
including posting appropriate security deposits in accordance with the
terms of Section 27A.5.4.
MISO 27A.3.4
FERC Electric Tariff Obligation to Provide High-Voltage Direct Current Service
MODULES 30.0.0
Effective On: November 19, 2013
If the Transmission Provider determines that it cannot
accommodate a Completed Application for Firm HVDC
Service because of insufficient capability on the HVDC
Facilities, the Transmission Provider and the affected
Transmission Owner(s) will use due diligence to expand or
modify the HVDC Facilities to provide the requested Firm
HVDC Service, consistent with its planning obligations in
Attachment FF of this Tariff, provided the Transmission
Customer agrees to compensate the Transmission Provider and
Transmission Owner(s) for such costs pursuant to the terms of
Section 27A.14 of this Tariff. The Transmission Provider and
the affected Transmission Owner(s) will conform to Good
Utility Practice and its planning obligations in Attachment FF
of this Tariff, in determining the need for new facilities and in
the design and construction of such facilities. The obligation
applies only to those facilities that the affected Transmission
Owner(s) have the right to expand or modify.
MISO 27A.3.5
FERC Electric Tariff Deferral of Service:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider may defer providing service until it
completes construction of new transmission facilities or upgrades needed
to provide HVDC Service whenever the Transmission Provider determines
that providing the requested service would, without such new facilities or
upgrades, impair or degrade reliability to any existing firm services.
MISO 27A.3.6
FERC Electric Tariff Transmission Losses on High-Voltage Direct Current Facilitie
MODULES 30.0.0
Effective On: November 19, 2013
Transmission Losses on High-Voltage Direct Current Facilities:
Transmission losses are associated with HVDC Service. The
Transmission Provider is not obligated to provide transmission losses.
Transmission Customers taking HVDC Service are responsible for losses
associated with that service, as calculated by the Transmission Provider
in accordance with applicable business practices and procedures and
agreements with the applicable owner or operator of HVDC Facilities.
Such losses shall be apportioned to all Transmission Customers taking
service over HVDC Facilities in accordance with procedures developed
by the Transmission Provider and the owner or operator of those HVDC
Facilities.
MISO 27A.4
FERC Electric Tariff Responsibilities of Customers Taking High-Voltage Direct Cur
MODULES 30.0.0
Effective On: November 19, 2013
Responsibilities of Customers Taking High-Voltage Direct Current Service
MISO 27A.4.1
FERC Electric Tariff Conditions Required of Customers Taking High-Voltage Direct
MODULES 30.0.0
Effective On: November 19, 2013
Conditions Required of Customers Taking High-Voltage Direct Current
Service
HVDC Service will be provided by the Transmission Provider under this
Section 27A and other applicable provisions of the Tariff only if the following
conditions are satisfied by the Transmission Customer:
i. The Transmission Customer has submitted a Completed
Application for HVDC Service in accordance with this Section
27A;
ii. The Transmission Customer meets the creditworthiness criteria set
forth in Attachment L of this Tariff;
iii. The Transmission Customer agrees to have arrangements in place
for any other transmission service necessary to effect the delivery
from the generating source to the Transmission Provider prior to
the time service commences;
iv. The Transmission Customer agrees to pay for HVDC Service
Charges, and for any facilities constructed and chargeable to such a
Transmission Customer under this Section 27A, and the Tariff,
whether or not the Transmission Customer takes service for the full
term of its HVDC Service reservation;
v. The Transmission Customer provides the information required by
the Transmission Provider’s planning process established in
Attachment FF; and
vi. The Transmission Customer and the Transmission Provider have
MISO 27A.4.1
FERC Electric Tariff Conditions Required of Customers Taking High-Voltage Direct
MODULES 30.0.0
Effective On: November 19, 2013
executed a HVDC Service Agreement pursuant to this Section
27A.
MISO 27A.4.2
FERC Electric Tariff Customer Responsibility for Third-Party Arrangements
MODULES 30.0.0
Effective On: November 19, 2013
Any scheduling arrangements that may be required by other
electric systems shall be the responsibility of the Transmission Customer
requesting HVDC Service. The Transmission Customer shall provide,
unless waived by the Transmission Provider, notification to the
Transmission Provider identifying such systems, and authorizing them to
schedule the capacity and energy to be transmitted by the Transmission
Provider pursuant to Module B of this Tariff on behalf of the Receiving
Party at the Point of Delivery or the Delivering Party at the Point of
Receipt. The Transmission Provider will undertake reasonable efforts to
assist the Transmission Customer in making such arrangements, including
without limitation, providing any information or data required by such
other electric system pursuant to Good Utility Practice.
MISO 27A.5
FERC Electric Tariff Procedures for Arranging Firm High-Voltage Direct Current Se
MODULES 30.0.0
Effective On: November 19, 2013
Procedures for Arranging Firm High-Voltage Direct Current Service
MISO 27A.5.1
FERC Electric Tariff Application:
MODULES 30.0.0
Effective On: November 19, 2013
A request for Firm HVDC Service for periods of one year or
longer must contain a written Application to the Transmission Provider
pursuant to the schedule contained in Attachment J. All Firm HVDC
Service requests should be submitted by entering the information listed
below on the Transmission Provider’s OASIS.
MISO 27A.5.2
FERC Electric Tariff Time Requirements:
MODULES 30.0.0
Effective On: November 19, 2013
Attachment J lists the time requirements applicable to when the
requests must be made, the evaluation of the requests, and the
Transmission Customer response. Requests for service received later than
the applicable time prior to the day service is scheduled to commence will
be accommodated if practicable. Requests for Firm HVDC Service that
are subject to no earlier than submission timelines and that are submitted
during the first five minutes after the time when Firm HVDC Service can
first be requested on the OASIS in accordance with Attachment J, will be
considered as if they were submitted at the same time as provided for in
Section 17.6 of this Tariff.
MISO 27A.5.3
FERC Electric Tariff Completed Application:
MODULES 30.0.0
Effective On: November 19, 2013
A Completed Application for Firm HVDC Service shall provide all
of the information included at 18 C.F.R. § 2.20 of the Commission’s
regulations, including but not limited to the following:
i. The identity, address, email address, telephone number and
facsimile number of the entity requesting service;
ii. A statement that the entity requesting service is, or will be upon
commencement of service, an Eligible Customer under this Tariff;
iii. The location of the Point(s) of Receipt and Point(s) of Delivery
and the identities of the Delivering Parties and the Receiving
Parties;
iv The location of the Generation Resource(s) supplying the capacity
and Energy and the location of the Load ultimately served by the
capacity and energy transmitted. The Transmission Provider will
treat this information as confidential except to the extent that
disclosure of this information is required by this Tariff, by
regulatory or judicial order, for reliability purposes pursuant to
Good Utility Practice or pursuant to RTG transmission information
sharing agreements. The Transmission Provider shall treat this
information consistent with the standards of conduct contained in
Part 37 of the Commission’s regulations;
v. A description of the supply characteristics of the capacity and
Energy to be delivered;
MISO 27A.5.3
FERC Electric Tariff Completed Application:
MODULES 30.0.0
Effective On: November 19, 2013
vi. An estimate of the capacity and Energy expected to be delivered to
the Receiving Party;
vii. The service commencement date and the term of the requested
HVDC Service;
viii. The transmission capacity requested for each Point of Receipt and
each Point of Delivery on the HVDC Facilities. Customers may
combine their requests for HVDC Service in order to satisfy the
minimum transmission capacity requirement. The Transmission
Provider shall treat this information consistent with the standards
of conduct contained in part 37 of the Commission’s regulations;
ix. A statement indicating that if the Eligible Customer submits a pre-
confirmed Application, then the Eligible Customer will execute a
HVDC Service Agreement upon receipt of notification that the
Transmission Provider can provide the requested HVDC Service;
and
x. Any additional information required by the Transmission
Provider’s planning process established in Attachment FF.
MISO 27A.5.4
FERC Electric Tariff Deposit:
MODULES 30.0.0
Effective On: November 19, 2013
A Completed Application for HVDC Service by a Transmission
Customer shall also include, at the discretion of the Transmission
Provider, a deposit of either one (1) month’s charge for Reserved Capacity
over the relevant HVDC Facilities for service requests of one (1) month or
greater, the full charge for Reserved Capacity over the relevant HVDC
Facilities for service requests of less than one (1) month, or a request for
waiver of such deposit, which request shall be accepted if the Eligible
Customer is found by the Transmission Provider to be creditworthy.
If the Application for HVDC Service is rejected by the
Transmission Provider because it does not meet the conditions for service
as set forth herein, or in the case of requests for service arising in
connection with losing bidders in a request for proposals (RFP), the
deposit will be returned with interest, less any reasonable costs incurred by
the relevant Transmission Provider in connection with the review of the
Application for HVDC Service. The deposit also will be returned with
interest less any reasonable costs incurred by the Transmission provider if
the Transmission Provider is unable to complete new facilities needed to
provide the service.
If an Application for HVDC Service is withdrawn or the Eligible
Customer decides not to enter into a HVDC Service Agreement, the
deposit will be refunded in full, with interest, less reasonable costs
incurred by the Transmission Provider, to the extent such costs have not
MISO 27A.5.4
FERC Electric Tariff Deposit:
MODULES 30.0.0
Effective On: November 19, 2013
already been recovered from the Eligible Customer. The Transmission
Provider will provide to the Eligible Customer a complete accounting of
all costs deducted from the refunded deposit, which the Eligible Customer
may contest if there is a dispute concerning the deducted costs. If an
HVDC Service Agreement is executed, any deposit, with interest, will be
returned to the Transmission Customer upon expiration or termination of
the HVDC Service Agreement. Applicable interest will be calculated in
accordance with Commission regulations at 18 C.F.R. § 35.19a(a)(2)(iii)
and shall be calculated from the day the deposit is credited to the
Transmission Provider’s account.
MISO 27A.5.5
FERC Electric Tariff Notice of Deficient Application:
MODULES 30.0.0
Effective On: November 19, 2013
If an Application for HVDC Service fails to meet the requirements
of this Tariff, the Transmission Provider will notify the entity requesting
service within the applicable time frame set forth in Attachment J for
responding to Applications. The Transmission Provider will attempt to
remedy minor deficiencies in the Application for HVDC Service through
informal communications with the Eligible Customer. If such efforts are
unsuccessful, the Transmission Provider will return the Application for
HVDC Service, along with any deposit (less the reasonable costs incurred
by the HVDC Service Provider, in connection with the Application for
HVDC Service), with interest, to the Eligible Customer. Upon receipt of a
new or revised Application for HVDC Service that fully complies with the
requirements of this Tariff, the Eligible Customer will be assigned a new
reservation priority consistent with the date of the new or revised
Application.
MISO 27A.5.6
FERC Electric Tariff Response to a Completed Application:
MODULES 30.0.0
Effective On: November 19, 2013
Following receipt of a Completed Application for Firm HVDC
Service, the Transmission Provider shall make a determination of
available transfer capability as required in Section 27A.3.2 of this Tariff.
The Transmission Provider shall notify the Eligible Customer in
accordance with the time periods set forth in Attachment J either (i) if it
will be able to provide service without performing a System Impact Study
or (ii) if such a study is needed to evaluate the impact of the Application
pursuant to Section 27A.7.1. Responses by the Transmission Provider
must be made as soon as practicable to all completed applications on a
non-discriminatory basis.
MISO 27A.5.7
FERC Electric Tariff Execution of High-Voltage Direct Current Service Agreement:
MODULES 30.0.0
Effective On: November 19, 2013
Whenever the Transmission Provider determines that a System
Impact Study is not required and that the requested service can be
provided, the Transmission Provider will notify the Eligible Customer
consistent with the applicable time period set forth in Attachment J.
Where a System Impact Study is required, the provisions of Section 27A.7
will govern the execution of a HVDC Service Agreement. Failure of an
Eligible Customer to execute and return the HVDC Service Agreement or
request the filing of an unexecuted HVDC Service Agreement pursuant to
Section 27A.3.3, within the time periods set forth in Attachment J shall be
deemed a withdrawal and termination of the Application for HVDC
Service and any deposit (less the reasonable costs incurred by the
Transmission Provider, in connection with the Application for HVDC
Service) submitted will be refunded with interest. Nothing herein limits
the right of an Eligible Customer to file another Completed Application
for HVDC Service after such withdrawal and termination.
MISO 27A.5.8
FERC Electric Tariff Extensions for Commencement of Firm High-Voltage Direct Curr
MODULES 30.0.0
Effective On: November 19, 2013
Extensions for Commencement of Firm High-Voltage Direct Current
Service:
The Transmission Customer can obtain, subject to availability, up
to five one-year extensions for the commencement of service. The
Transmission Customer may postpone service by notifying the
Transmission Provider or, as applicable, ITC, 31 days prior to the
commencement date of the service as initially requested and paying a non-
refundable annual reservation fee equal to one-month’s charge for Firm
HVDC Service for each year or fraction thereof within 15 days of
notifying the Transmission Provider it intends to extend the
commencement of service. If during any extension for the
commencement of service an Eligible Customer submits a Completed
Application for Firm HVDC Service, and such request can be satisfied
only by releasing all or part of the Transmission Customer’s Reserved
Capacity over the HVDC Facilities, the original Reserved Capacity over
the HVDC Facilities will be released unless the following condition is
satisfied: within thirty (30) days, the original Transmission Customer
agrees to pay the applicable rate for Firm HVDC Service for its Reserved
Capacity over the HVDC Facilities concurrent with the new HVDC
Service Commencement Date. In the event the Transmission Customer
elects to release the Reserved Capacity over the HVDC Facilities, the
reservation fees or portions thereof previously paid will be forfeited.
MISO 27A.5.8
FERC Electric Tariff Extensions for Commencement of Firm High-Voltage Direct Curr
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.6
FERC Electric Tariff Procedures for Arranging Non-Firm High-Voltage Direct Curren
MODULES 30.0.0
Effective On: November 19, 2013
Procedures for Arranging Non-Firm High-Voltage Direct Current Service
MISO 27A.6.1
FERC Electric Tariff Application:
MODULES 30.0.0
Effective On: November 19, 2013
Eligible Customers seeking Non-Firm HVDC Service must submit
a Completed Application for HVDC Service to the Transmission Provider.
Applications should be submitted by entering the information on the
Transmission Provider’s OASIS.
MISO 27A.6.2
FERC Electric Tariff Completed Application:
MODULES 30.0.0
Effective On: November 19, 2013
A Completed Application for Non-Firm HVDC Service shall
provide all of the information included at 18 C.F.R. § 2.20 of the
Commission’s regulations, including but not limited to the following:
i. The identity, address, email address, telephone number and
facsimile number of the entity requesting service;
ii. A statement that the entity requesting service is, or will be upon
commencement of service, an Eligible Customer under this Tariff;
iii. The Point(s) of Receipt and Point(s) of Delivery;
iv. The maximum amount of capacity requested at each Point of
Receipt and Point of Delivery;
v. The proposed dates and hours for initiating and terminating HVDC
Service hereunder;
vi. The electrical location of the initial source of the power to be
transmitted pursuant to the Transmission customer’s request for
service, and
vii. The electrical location of the ultimate Load. The Transmission
Provider will treat this information as confidential except to the
extent that disclosure of this information is required by this Tariff,
by regulatory or judicial order, for reliability purposes pursuant to
Good Utility Practice or pursuant to RTG transmission information
sharing agreements. The Transmission Provider shall treat this
information consistent with the standards of conduct contained in
MISO 27A.6.2
FERC Electric Tariff Completed Application:
MODULES 30.0.0
Effective On: November 19, 2013
Part 37 of the Commission’s regulations;
viii. A statement indicating that if the Transmission Customer submits a
pre-confirmed Application, then the Eligible Customer will
execute a HVDC Service Agreement upon receipt of notification
that the Transmission Provider can provide the requested HVDC
Service.
MISO 27A.6.3
FERC Electric Tariff Requests and Responses for Reservation of Non-Firm High-Volt
MODULES 30.0.0
Effective On: November 19, 2013
Requests and Responses for Reservation of Non-Firm High-Voltage
Direct Current Service
Attachment J lists the time requirements applicable to when the
requests must be made, the evaluation of the requests, and the
Transmission Customer response. Requests for service received later than
the applicable time prior to the day service is scheduled to commence will
be accommodated if practicable.
MISO 27A.6.4
FERC Electric Tariff Determination of Available Transfer Capability:
MODULES 30.0.0
Effective On: November 19, 2013
Following receipt of a tendered schedule the Transmission
Provider will make a determination on a non-discriminatory basis of
available transfer capability pursuant to Section 27A.3.2. Such
determination shall be made as soon as reasonably practicable after
receipt, but not later than the time periods specified in Attachment J.
MISO 27A.7
FERC Electric Tariff Additional Study Procedures for Firm High-Voltage Direct Cur
MODULES 30.0.0
Effective On: November 19, 2013
Additional Study Procedures for Firm High-Voltage Direct Current Service Requests
MISO 27A.7.1
FERC Electric Tariff Notice of Need for System Impact Study:
MODULES 30.0.0
Effective On: November 19, 2013
After receiving a request for HVDC Service, the Transmission
Provider shall determine on a non-discriminatory basis whether a System
Impact Study is needed. A description of the Transmission Provider’s
methodology for completing a System Impact Study is provided in
Attachment D. If the Transmission Provider determines that a System
Impact Study is necessary to accommodate the requested service, the
Transmission Provider shall so inform the Eligible Customer within the
times specified in Attachment J. The Transmission Provider shall within
thirty (30) days of receipt of a Completed Application, tender a System
Impact Study Agreement in the form of Attachment D-1 of this Tariff,
pursuant to which the Eligible Customer shall agree to reimburse the
Transmission Provider for performing the required System Impact Study
including any costs of the Transmission Owner. For a service request to
remain a Completed Application, the Eligible Customer shall execute the
System Impact Study Agreement and return it to the Transmission
Provider within the time provided for in Attachment J. If the Eligible
Customer elects not to execute the System Impact Study Agreement, its
application shall be deemed withdrawn and any deposit shall be returned
with interest.
MISO 27A.7.1
FERC Electric Tariff Notice of Need for System Impact Study:
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.7.2
FERC Electric Tariff System Impact Study Agreement and Cost Reimbursement
MODULES 31.0.0
Effective On: December 20, 2013
i. The System Impact Study Agreement will clearly specify the
Transmission Provider’s estimate of the actual cost, and time for
completion of the System Impact Study. The charge shall not exceed the
actual cost of the study. In performing the System Impact Study, the
Transmission Provider shall rely, to the extent reasonably practicable, on
existing transmission planning studies. The Eligible Customer will not be
assessed a charge for such existing studies; however, the Eligible
Customer will be responsible for charges associated with any
modifications to existing planning studies that are reasonably necessary to
evaluate the impact of the Eligible Customer’s request for service on the
relevant HVDC Facilities.
ii. If in response to multiple Eligible Customers requesting service in relation
to the same competitive solicitation, a single System Impact Study is
sufficient for the Transmission Provider to accommodate the requests for
service, the costs of that study shall be pro-rated among the Eligible
Customers.
iii. Each Transmission owner shall pay the Transmission Provider for System
Impact Studies that the Transmission Provider conducts on the
Transmission Owner’s behalf in instances where merchant employees of
the Transmission Owner have requested transmission service, the same as
any non-transmission owning customer.
MISO 27A.7.2
FERC Electric Tariff System Impact Study Agreement and Cost Reimbursement
MODULES 31.0.0
Effective On: December 20, 2013
MISO 27A.7.3
FERC Electric Tariff System Impact Study Procedures:
MODULES 31.0.0
Effective On: August 2, 2017
Upon receipt of an executed System Impact Study Agreement in the form
of Attachment D-1 of this Tariff, the Transmission Provider will use due diligence
to complete the required System Impact Study in coordination with the relevant
Transmission Owners within sixty (60) days or as soon as practicable. The
System Impact Study shall identify (1) any system constraints, identified with
specificity by transmission element or flowgate, and (2) additional Direct
Assignment Facilities or Network Upgrades required to provide the requested
service.
In the event that the Transmission Provider is unable to complete the
required System Impact Study within such time period, it shall so notify the
Eligible Customer and provide an estimated completion date along with an
explanation of the reasons why additional time is required to complete the
required studies. A copy of the completed System Impact Study and related work
papers shall be made available to the Eligible Customer as soon as the System
Impact Study is complete. The Transmission Provider will use the same due
diligence in completing the System Impact Study for an Eligible Customer as it
uses when completing studies for Transmission Owners.
The Transmission Provider shall notify the Eligible Customer immediately
upon completion of the System Impact Study if the HVDC Facilities will be
adequate to accommodate all or part of a request for service or that no costs are
likely to be incurred for new transmission facilities or upgrades. In order for a
request to remain a Completed Application, within fifteen (15) days of completion
MISO 27A.7.3
FERC Electric Tariff System Impact Study Procedures:
MODULES 31.0.0
Effective On: August 2, 2017
of the System Impact Study the Eligible Customer must execute an HVDC
Service Agreement or request the filing of an unexecuted HVDC Service
Agreement pursuant to Section 27A.3.3, or the Application shall be deemed
terminated and withdrawn.
MISO 27A.7.4
FERC Electric Tariff Facilities Study Procedures:
MODULES 30.0.0
Effective On: November 19, 2013
If a System Impact Study indicates that additions or upgrades to
certain HVDC Facilities are needed to supply the Eligible Customer's
service request, the Transmission Provider, within thirty (30) days of the
completion of the System Impact Study, shall tender to the Eligible
Customer a Facilities Study Agreement pursuant to which the Eligible
Customer shall agree to reimburse the Transmission Provider and any
affected Transmission Owner(s) for performing the required Facilities
Study. For a service request to remain a Completed Application, the
Eligible Customer shall execute the Facilities Study Agreement in the
form of Attachment D-2 of this Tariff and return it to the Transmission
Provider within fifteen (15) days. If the Eligible Customer elects not to
execute the Facilities Study Agreement, its application shall be deemed
withdrawn and any deposit shall be returned with interest. Upon receipt of
an executed Facilities Study Agreement, the Transmission Provider, in
coordination with the appropriate Transmission Owner(s) will use due
diligence to complete the required Facilities Study within a one hundred
and twenty (120) day period.
If the Transmission Provider, together with the affected
Transmission Owner(s) is unable to complete the Facilities Study in the
allotted time period, the Transmission Provider shall notify the Eligible
Customer and provide an estimate of the time needed to reach a final
determination along with an explanation of the reasons that additional time
MISO 27A.7.4
FERC Electric Tariff Facilities Study Procedures:
MODULES 30.0.0
Effective On: November 19, 2013
is required to complete the study. When completed, the Facilities Study
will include a good faith estimate of (i) the cost of Direct Assignment
Facilities to be charged to the Transmission Customer, (ii) the
Transmission Customer’s appropriate share of the cost of any required
Network Upgrades as determined pursuant to Module B of this Tariff and
cost of HVDC Facility Upgrades to be charged to the Transmission
Customer, and (iii) the time required to complete such construction and
initiate the requested service. The Eligible Customer shall be requested to
provide the Transmission Provider with a letter of credit or other
reasonable form of security acceptable to the Transmission Provider
equivalent to the costs of new facilities or upgrades consistent with
commercial practices as established by the Uniform Commercial Code
unless the Transmission Provider determines that the Eligible Customer
already has a letter(s) of credit or other form(s) of security on file with the
Transmission Provider that is sufficient to cover its existing and proposed
obligations. Within the time set out in Attachment J, the Transmission
Customer shall execute a Service Agreement or request the filing of an
unexecuted Service Agreement and provide the required letter of credit or
other form of security or the request will no longer be a Completed
Application and shall be deemed terminated and withdrawn.
MISO 27A.7.4.1
FERC Electric Tariff Changes in Facilities Study Assumptions
MODULES 30.0.0
Effective On: November 19, 2013
Any changes to the original assumptions, considered during the
System Impact Study, that arise during the Facilities Study, that can
materially impact the results of the Facilities Study, may require the
Transmission Provider to re-evaluate the results of the original System
Impact Study. If the Transmission Provider ascertains that the changes in
assumptions are material modifications to the original scope of the study,
that could change the outcome of the Facilities Study, then the
Transmission Provider shall temporarily stop work on the Facilities Study
until the results from the re-evaluation are available. After the re-
evaluation results are available, the Transmission Provider will make the
final determination whether the initial Facilities Study should proceed
based on the original scope or based on the revised scope. If the scope of
the initial Facilities Study needs to be revised, then the Transmission
Provider will reset the one hundred and twenty (120) day clock to perform
the revised Facilities Study. The Transmission Provider will take
appropriate steps to communicate to the customer the revised scope and
schedule the revised Facilities Study.
MISO 27A.7.4.1
FERC Electric Tariff Changes in Facilities Study Assumptions
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.7.5
FERC Electric Tariff Facilities Study Modifications:
MODULES 30.0.0
Effective On: November 19, 2013
Any change in design arising from inability to site or construct
facilities as proposed will require development of a revised good faith
estimate. New good faith estimates also will be required in the event of
new statutory or regulatory requirements that are effective before the
completion of construction or other circumstances beyond the control of
the Transmission Provider or the affected Transmission Owner(s) that
significantly affect the final cost of new facilities or upgrades to be
charged to the Transmission Customer pursuant to the provisions of
Module B of this Tariff.
MISO 27A.7.6
FERC Electric Tariff Due Diligence in Completing New Facilities:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider and, as applicable, the affected
Transmission Owner(s) shall use due diligence to add necessary facilities
or upgrade the HVDC Facilities within a reasonable time. The
Transmission Provider will not upgrade its existing or planned HVDC
Facilities in order to provide the requested HVDC Service if doing so
would impair system reliability or otherwise impair or degrade existing
firm service.
MISO 27A.7.7
FERC Electric Tariff Partial Interim Service:
MODULES 30.0.0
Effective On: November 19, 2013
If the Transmission Provider determines that it will not have
adequate transfer capability to satisfy the full amount of a Completed
Application for HVDC Service, the Transmission Provider nonetheless
shall be obligated to offer and provide the portion of the requested Firm
HVDC Service that can be accommodated without addition of any
facilities. However, the Transmission Provider shall not be obligated to
provide the incremental amount of requested Firm HVDC Service that
requires the addition of facilities or upgrades to the HVDC Facilities until
such facilities or upgrades have been placed in service.
MISO 27A.7.8
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines:
MODULES 30.0.0
Effective On: November 19, 2013
Sections 27A.7.3 and 27A.7.4 of this Tariff require a Transmission
Provider to use due diligence to meet study completion deadlines for
System Impact Studies and Facilities Studies.
i. The Transmission Provider is required to file a notice with
the Commission in the event that more than twenty (20) percent of
non-Affiliates’ System Impact Studies and Facilities Studies
completed by the Transmission Provider in any two consecutive
calendar quarters are not completed within the 60-day or 120-day
study completion deadlines. Such notice must be filed within
thirty (30) days of the end of the calendar quarter triggering the
notice requirement.
ii. For the purposes of calculating the percent of non-
Affiliates’ System Impact Studies and Facilities Studies processed
outside of the 60-day or 120-day study completion deadlines, the
Transmission Provider shall consider all System Impact Studies
and Facilities Studies that it completes for non-Affiliates during
the calendar quarter. The percentage should be calculated by
dividing the number of those studies which are completed on time
by the total number of completed studies. The Transmission
Provider may provide an explanation in its notification filing to the
Commission if it believes there are extenuating circumstances that
prevented it from meeting the 60-day or 120-day study completion
MISO 27A.7.8
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines:
MODULES 30.0.0
Effective On: November 19, 2013
deadlines.
iii. The Transmission Provider is subject to an operational
penalty if it completes ten (10) percent or more of non-Affiliates’
System Impact Studies and Facilities Studies outside of the 60-day
or 120-day study completion deadlines for each of the two calendar
quarters immediately following the quarter that triggered its
notification filing to the Commission. The operational penalty will
be assessed for each calendar quarter for which an operational
penalty applies, starting with the calendar quarter immediately
following the quarter that triggered the Transmission Provider’s
notification filing to the Commission. The operational penalty will
continue to be assessed each quarter until the Transmission
Provider completes at least ninety (90) percent of all non-
Affiliates’ System Impact Studies and Facilities Studies within the
60-day or 120-day deadline.
iv. For penalties assessed in accordance with subsection (iii)
above, the penalty amount for each System Impact Study or
Facilities Study shall be equal to $500 for each day the
Transmission Provider takes to complete that study beyond the 60-
day or 120-day deadline.
MISO 27A.7.8
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines:
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.8
FERC Electric Tariff Procedures if Unable to Complete New Facilities for Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.8.1
FERC Electric Tariff Delays in Construction of New Facilities:
MODULES 30.0.0
Effective On: November 19, 2013
If any event occurs that will materially affect the time for
completion of new facilities, or the ability to complete them, the
Transmission Provider shall promptly notify the Transmission Customer.
In such circumstances, the Transmission Provider shall within thirty (30)
days of notifying the Transmission Customer of such delays, convene a
technical meeting with the Transmission Customer and the affected
Transmission Owner(s) to evaluate the alternatives available to the
Transmission Customer. The Transmission Provider also shall make
available to the Transmission Customer studies and work papers related to
the delay, including all information that is in the possession of the
Transmission Provider and affected Transmission Owner(s) that is
reasonably needed by the Transmission Customer to evaluate any
alternatives.
MISO 27A.8.2
FERC Electric Tariff Alternatives to the Original Facility Additions:
MODULES 30.0.0
Effective On: November 19, 2013
When the review process of Section 27A.8.1 determines that one
or more alternatives exist to the originally planned construction project,
the Transmission Provider together with the affected Transmission
Owner(s) shall present such alternatives for consideration by the
Transmission Customer. If, upon review of any alternatives, the
Transmission Customer desires to maintain its Completed Application
subject to construction of the alternative facilities, it may request the
Transmission Provider to submit a revised HVDC Service Agreement for
Firm HVDC Service. If the alternative approach solely involves Non-
Firm HVDC Service, the Transmission Provider shall promptly tender a
Service Agreement for Non-Firm HVDC Service providing for the
service. In the event the Transmission Provider concludes that no
reasonable alternative exists and the Transmission Customer disagrees, the
Transmission Customer may seek relief under the dispute resolution
procedures pursuant to Section 12 or it may refer the dispute to the
Commission for resolution.
MISO 27A.8.3
FERC Electric Tariff Refund Obligation for Unfinished Facility Additions
MODULES 30.0.0
Effective On: November 19, 2013
If the Transmission Provider and the Transmission Customer
mutually agree that no other reasonable alternatives exist and the
requested service cannot be provided out of existing capability under the
conditions of Module B of this Tariff, the obligation to provide the
requested Firm HVDC Service shall terminate and any deposit made by
the Transmission Customer shall be returned with interest pursuant to
Commission regulations 35.19a(a)(2)(iii). However, the Transmission
Customer shall be responsible for all prudently incurred costs by the
Transmission Provider through the time construction was suspended.
MISO 27A.9
FERC Electric Tariff Transmission Construction and Service on Other Utilities
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.9.1
FERC Electric Tariff Responsibility for Third-Party System Additions:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall not be responsible for making
arrangements for any necessary engineering, permitting, and construction
of transmission or Distribution Facilities on the system(s) of any other
entity or for obtaining any regulatory approval for such facilities. The
Transmission Provider will undertake reasonable efforts to assist the
Transmission Customer in obtaining such arrangements, including without
limitation, providing any information or data required by such other
electric system pursuant to Good Utility Practice.
MISO 27A.9.2
FERC Electric Tariff Coordination of Third-Party System Additions:
MODULES 30.0.0
Effective On: November 19, 2013
In circumstances where the need for transmission facilities or
upgrades is identified pursuant to the provisions of this Section 27A, and
if such upgrades further require the addition of transmission facilities on
other systems, the affected Transmission Owner(s) in coordination with
the Transmission Provider shall have the right to coordinate construction
on its own HVDC Facilities with the construction required by others. The
Transmission Provider together with affected Transmission Owner(s),
after consultation with the Transmission Customer and representatives of
such other systems, may defer construction of its new transmission
facilities, if the new transmission facilities on another system cannot be
completed in a timely manner. The Transmission Provider shall notify the
Transmission Customer in writing of the basis for any decision to defer
construction and the specific problems which must be resolved before it
will initiate or resume construction of new facilities. Within sixty (60)
days of receiving written notification by the Transmission Provider of its
intent to defer construction pursuant to this section, the Transmission
Customer may challenge the decision in accordance with the dispute
resolution procedures pursuant to Section 12 or it may refer the dispute to
the Commission for resolution.
MISO 27A.10
FERC Electric Tariff Changes in Service Specifications
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.10.1
FERC Electric Tariff Modifications On a Non-Firm Basis:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Customer taking Firm HVDC Service may
request the Transmission Provider to provide transmission service on a
non-firm basis over Receipt and Delivery Points on HVDC Facilities other
than those specified in the HVDC Service Agreement ("Secondary Receipt
and Delivery Points"), in amounts not to exceed its firm capacity
reservation, without incurring an additional Non-Firm HVDC Service
charge or executing a new HVDC Service Agreement, subject to the
following conditions.
i. Service provided over Secondary Receipt and Delivery Points will
be non-firm only, on an as-available basis, will not displace any firm or
non-firm service reserved or scheduled by third-parties under the Tariff or
by the Transmission Provider on behalf of its Native Load Customers, and
will be provided only on HVDC Facilities.
ii. The sum of all Firm and non-firm HVDC Service provided to the
Transmission Customer at any time pursuant to this section shall not
exceed the Reserved Capacity in the relevant HVDC Service Agreement
under which such services are provided.
iii. The Transmission Customer shall retain its right to schedule Firm
HVDC Service at the Receipt and Delivery Points specified in the relevant
HVDC Service Agreement in the amount of its original capacity
reservation.
iv. Service over Secondary Receipt and Delivery Points on a non-firm
MISO 27A.10.1
FERC Electric Tariff Modifications On a Non-Firm Basis:
MODULES 30.0.0
Effective On: November 19, 2013
basis shall not require the filing of an Application for Non-Firm HVDC
Service under the Tariff. However, all other requirements of Section 27A
of the Tariff (except as to transmission rates) shall apply to transmission
service on a non-firm basis over Secondary Receipt and Delivery Points.
MISO 27A.10.2
FERC Electric Tariff Modification On a Firm Basis:
MODULES 30.0.0
Effective On: November 19, 2013
Any request by a Transmission Customer taking Firm HVDC
Service to modify Receipt and Delivery Points on a firm basis shall be
treated as a new request for service on HVDC Facilities in accordance
with Section 27A.6 hereof, except that such Transmission Customer shall
not be obligated to pay any additional deposit if the capacity reservation
does not exceed the amount reserved in the existing HVDC Service
Agreement. While such new request is pending, the Transmission
Customer shall retain its priority for service at the existing firm Receipt
and Delivery Points specified in its HVDC Service Agreement. Service
under this Section 27A.10.2 will be provided only on HVDC Facilities.
MISO 27A.11
FERC Electric Tariff Sale, Assignment, or Transfer of High-Voltage Direct Current
MODULES 30.0.0
Effective On: November 19, 2013
Sale, Assignment, or Transfer of High-Voltage Direct Current Service
MISO 27A.11.1
FERC Electric Tariff Procedures for Sale, Assignment or Transfer of Service:
MODULES 30.0.0
Effective On: November 19, 2013
Subject to Commission approval of any necessary filings, a
Transmission Customer may sell, assign, or transfer all or a portion of its
rights under its HVDC Service Agreement, but only to another Eligible
Customer (the “Assignee”). The Transmission Customer that sells,
assigns, or transfers its rights under its HVDC Service Agreement is
hereafter referred to as the “Reseller.” Compensation to the Reseller shall
be at rates established by agreement between the Reseller and the
Assignee.
The Assignee must execute a service agreement with the
Transmission Provider governing reassignments of transmission service
prior to the date on which the reassigned service commences. The
Transmission Provider shall charge the Reseller, as appropriate, at the rate
stated in the Reseller’s Service Agreement with the Transmission Provider
or the associated OASIS schedule and credit the Reseller with the price
reflected in the Assignee’s Service Agreement with the Transmission
Provider or the associated OASIS schedule; provided that such credit shall
be reversed in the event of non-payment by the Assignee. If the Assignee
does not request any change in the Point(s) of Receipt or the Point(s) of
Delivery, or a change in any other term or condition set forth in the
original HVDC Service Agreement, the Assignee shall receive the same
services as did the Reseller and the transmission priority of service for the
Assignee shall be the same as that of the Reseller. The Assignee shall be
MISO 27A.11.1
FERC Electric Tariff Procedures for Sale, Assignment or Transfer of Service:
MODULES 30.0.0
Effective On: November 19, 2013
subject to all terms and conditions of this Tariff. If the Assignee requests
a change in service, the reservation priority of service will be determined
by the Transmission Provider pursuant to section 27A.1.2 of this Tariff.
MISO 27A.11.2
FERC Electric Tariff Information on Resale of Service:
MODULES 30.0.0
Effective On: November 19, 2013
In accordance with Section 4 of this Tariff, all sales or assignments of capacity must be
conducted through or otherwise posted on the Transmission Provider’s OASIS on or before the
date the reassigned service commences and are subject to Section 27A.12.1. Resellers may also
use the Transmission Provider's OASIS to post transmission capacity available for resale.
MISO 27A.12
FERC Electric Tariff Metering and Power Factor Correction:
MODULES 30.0.0
Effective On: November 19, 2013
MISO 27A.12.1
FERC Electric Tariff Transmission Customer Obligations:
MODULES 30.0.0
Effective On: November 19, 2013
Unless otherwise agreed, the Transmission Customer shall be
responsible for the cost of installing and maintaining compatible metering
and communications equipment to accurately account for the Energy
being transmitted under this Tariff and to communicate the information to
the Transmission Provider. Such equipment installed on the Transmission
Customer’s system shall remain the property of the Transmission
Customer. Such equipment installed on the Transmission Owner’s system
shall remain the property of the Transmission Owner.
MISO 27A.12.2
FERC Electric Tariff Transmission Provider Access to Metering Data:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider or its agent shall have access to
metering data, which may reasonably be required to facilitate
measurements and billing under the Service Agreement.
MISO 27A.13
FERC Electric Tariff Compensation for High-Voltage Direct Current Service:
MODULES 30.0.0
Effective On: November 19, 2013
Rates for Firm and Non-Firm HVDC Service are provided in the
Schedules appended to this Tariff: Firm Point-To-Point Transmission Service
(Schedule 7); and Non-Firm Point-To-Point Transmission Service (Schedule 8).
In addition to paying any applicable Ancillary Service costs, the Transmission
Customer also shall pay applicable charges under Schedule 35.
MISO 27A.14
FERC Electric Tariff Stranded Cost Recovery:
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider may seek to recover stranded costs from the
Transmission Customer pursuant to this Tariff in accordance with the terms,
conditions and procedures set forth in FERC Order No. 888. However, the
Transmission Provider must separately file any specific proposed stranded cost
charge under Section 205 of the Federal Power Act.
MISO 27A.15
FERC Electric Tariff Compensation for New Facilities Costs
MODULES 31.0.0
Effective On: August 2, 2017
Whenever a System Impact Study performed by the Transmission
Provider in connection with the provision of Firm HVDC Service identifies the
need for new facilities, the costs of such facilities shall be recovered from the
Transmission Customer, as provided in the appropriate section of Attachment FF.
MISO 27A.16
FERC Electric Tariff [RESERVED]
MODULES 30.0.0
Effective On: November 19, 2013
[RESERVED]
MISO III
FERC Electric Tariff NETWORK INTEGRATION TRANSMISSION SERVICE
MODULES 30.0.0
Effective On: November 19, 2013
Preamble
The Transmission Provider will provide Network Integration Transmission Service pursuant to
the applicable terms and conditions contained in the Tariff and Service Agreement. Network
Integration Transmission Service allows the Network Customer to integrate, economically
dispatch and regulate its current and planned Network Resources to serve its Network Load in a
manner comparable to that in which the Transmission Owners utilize the Transmission System to
serve their Native Load or other Network Customers. Network Integration Transmission Service
also may be used by the Network Customer to deliver economy Energy purchases to its Network
Load from non-designated Resources on an as-available basis without additional charge.
Transmission Service for sales to non-designated Loads will be provided pursuant to the
applicable terms and conditions of Module B of this Tariff and/or any applicable ITC Rate
Schedule.
An ITC may provide Network Integration Transmission Service pursuant to an ITC Rate
Schedule to the extent both the Network Loads and the Network Resources are within the ITC
System, provided that the Network Customer has an appropriate Service Agreement with the
Transmission Provider. Network Resources located outside of the Transmission System
(Michigan) will be required to obtain services under Schedule 9 of this Tariff in order to import
such Network Resource(s) to the Transmission System (Michigan). Network Customers with
Loads and Resources physically and directly interconnected with the Transmission System
(Michigan) may also obtain Network Integration Transmission Service under Schedule 9 -
Michigan of this Tariff. Network Customers with Loads and Resources located both inside and
outside (and vice versa) of the Transmission System (Michigan) may also obtain Network
MISO III
FERC Electric Tariff NETWORK INTEGRATION TRANSMISSION SERVICE
MODULES 30.0.0
Effective On: November 19, 2013
Integration Transmission Service under Schedule 9 of this Tariff. In addition, Transmission
Service for sales to non-designated Loads that are not on the Transmission System (Michigan)
will be provided pursuant to the applicable terms and conditions of Module B of this Tariff.
MISO 28
FERC Electric Tariff Nature of Network Integration Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 28.1
FERC Electric Tariff Scope of Service
MODULES 30.0.0
Effective On: November 19, 2013
Network Integration Transmission Service is a Transmission Service that allows Network
Customers to efficiently and economically utilize their Network Resources (as well as other non-
designated Generation Resources) to serve their Network Load located in a Transmission
Owner’s, ITC, or ITC Participant(s) Local Balancing Authority Area or pricing zone and any
additional Load that may be designated pursuant to Section 31 of this Tariff. The Network
Customer taking Network Integration Transmission Service must obtain or provide Ancillary
Services pursuant to Section 3 or any applicable ITC Rate Schedule.
MISO 28.2
FERC Electric Tariff Transmission Provider Responsibilities
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider will plan, operate, and cause to be maintained
the Transmission System in accordance with Good Utility Practice and its
planning obligations in Attachment FF in order to provide the Network Customer
with Network Integration Transmission Service over the Transmission System.
The Transmission Owners and ITC Participants, on behalf of Native Load
Customers, shall be required to designate Resources and Loads in the same
manner as any Network Customer under Module B of this Tariff. This
information must be consistent with the information used by the Transmission
Provider to calculate available transfer capability. The Transmission Provider and
ITC shall include the Network Customer’s Network Load in Transmission System
planning and shall, consistent with Good Utility Practice and Attachment FF,
endeavor to cause to be constructed and placed into service sufficient transfer
capability to deliver the Network Customer’s Network Resources to serve its
Network Load on a basis comparable to the Transmission Owner(s’) and ITC
Participant(s’) delivery of electric generating and purchased Resources to Native
Load Customers.
MISO 28.3
FERC Electric Tariff Network Integration Transmission Service
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider and, as applicable, ITC will provide Firm
Transmission Service over the Transmission System to the Network Customer for
the delivery of Capacity and Energy from its designated Network Resources to
service its Network Loads on a basis that is comparable to the Transmission
Owner(s’) and ITC Participant(s’) use of the Transmission System to reliably
serve Native Load Customers.
MISO 28.4
FERC Electric Tariff Secondary Service
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer may use the Transmission System to deliver
energy to its Network Loads from Generation Resources that have not been
designated as Network Resources. Such Energy shall be transmitted, on an as-
available basis, with no additional charges imposed under Schedules 7, 8, or 9, or
the applicable ITC Rate Schedule. Secondary service shall not require the filing
of an Application for Network Integration Transmission Service under this Tariff.
However, all other requirements of Part III of this Tariff (except for transmission
rates) shall apply to secondary service. Deliveries from Generation Resources
other than Network Resources will have a higher priority than any Non-Firm
Point-To-Point Transmission Service under Module B of this Tariff or under any
applicable ITC Rate Schedule.
MISO 28.5
FERC Electric Tariff Marginal Losses
MODULES 32.0.0
Effective On: March 1, 2015
System Losses are associated with all Transmission Service including
Transmission Service associated with Grandfathered Agreements. The
Transmission Provider shall assess to Market Participants the Marginal Losses
Component of Ex Post LMP in Sections 39.2.9, 39.3.3.c.ii, 40.2.11, and 40.4.1.
The Transmission Provider, ITC, Transmission Owners, and ITC Participant(s)
are not obligated to provide Marginal Losses.
MISO 28.6
FERC Electric Tariff Restrictions on Use of Service
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall not use Network Integration Transmission
Service for (i) sales of Capacity and Energy to non-designated Loads, or (ii) direct
or indirect provision of Transmission Service by the Network Customer to third
parties. All Network Customers taking Network Integration Transmission Service
shall use Point-To-Point Transmission Service under Module B of this Tariff for
any Third-Party Sale which requires use of the Transmission Provider’s
Transmission System except for service where the purchaser is a Network
Customer of the Transmission Provider.
MISO 29
FERC Electric Tariff Initiating Service
MODULES 30.0.0
Effective On: November 19, 2013
MISO 29.1
FERC Electric Tariff Condition Precedent for Receiving Service
MODULES 30.0.0
Effective On: November 19, 2013
Subject to the terms and conditions of Module B of this Tariff, the
Transmission Provider or ITC will provide Network Integration Transmission
Service to any Eligible Customer, provided that (i) the Eligible Customer
completes an Application for service as provided under Module B of this Tariff,
(ii) the Eligible Customer and the Transmission Provider in coordination with the
affected Transmission Owner(s), and ITC complete(s) the technical arrangements
set forth in Module B, Sections 29.3 and 29.4, (iii) the Eligible Customer executes
a Service Agreement pursuant to Attachment F for service under Module B of this
Tariff or requests in writing that the Transmission Provider file a proposed
unexecuted Service Agreement with the Commission, and (iv) the Eligible
Customer executes a Network Operating Agreement with the Transmission
Provider pursuant to Attachment G, or requests in writing that the Transmission
Provider file a proposed unexecuted Network Operating Agreement.
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
An Eligible Customer requesting service under Module B of this Tariff must
submit an Application, and at the discretion of Transmission Provider, a deposit
approximating the charge for one month of service or a request for waiver of such
deposit, to the Transmission Provider as far as possible in advance of the month in
which service is to commence. The Transmission Provider shall accept the request
for waiver of the deposit if the Eligible Customer is creditworthy. Unless subject to
the procedures in Section 2, Completed Applications for Network Integration
Transmission Service will be assigned a priority according to the date and time the
Application is received, with the earliest Application receiving the highest priority.
Applications should be submitted by entering the information listed below on the
Transmission Provider’s OASIS; however, any additional supplemental information
may also be requested to be provided by the Transmission Provider pursuant to the
Transmission Provider’s Business Practices Manuals. A Completed Application
shall provide all of the information included in 18 C.F.R. § 2.20 including but not
limited to the following:
(i) The identity, address, email address, telephone number and
facsimile number of the party requesting service;
(ii) A statement that the party requesting service is, or will be upon
commencement of service, an Eligible Customer under this Tariff;
(iii) A description of the Network Load at each delivery point. This
description should separately identify and provide the Eligible
Customer’s best estimate of the total Loads to be served at each
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
transmission voltage level, and the Loads to be served from each
Transmission Provider substation at the same transmission voltage
level. The description should include a ten (10) year forecast of
summer and winter Load and Generation Resource requirements
beginning with the first year after the service is scheduled to
commence;
(iv) The amount and location of any Interruptible Loads included in the
Network Load. This shall include the summer and winter Capacity
requirements for each interruptible Load (had such Load not been
interruptible), that portion of the Load subject to Interruption, the
conditions under which an Interruption can be implemented and
any limitations on the amount and frequency of interruptions. An
Eligible Customer should identify the amount of interruptible
customer Load (if any) included in the ten (10)-year Load Forecast
provided in response to (iii) above;
(v) A description of Network Resources (current and 10-year
projection). For each on-system Network Resource, such
description shall include:
- Unit size, location and amount of Capacity from that unit to
be designated as Network Resource
- Whether the unit is or will be an internal Resource
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
- Whether the unit is capable of receiving or responding to
AGC signals
- Whether the unit is capable of providing Regulation
- Whether the unit is capable of becoming a Spin
Qualified Resource
- VAR capability (both leading and lagging) of all
Generators
- Operating restrictions
- Any periods of restricted operations throughout the
year
- Maintenance schedules
- Minimum loading level of unit
- Normal operating level of unit
- Any must-run unit designations required for system
reliability or contract reasons
- Approximate variable generating cost ($/MWH) for
redispatch computations
- Arrangements governing sale and delivery of power to third
parties from generating facilities located in the MISO
Balancing Authority Area, where only a portion of unit
output is designated as a Network Resource;
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
For each off-system Network Resource, such description
shall include:
- Identification of the Network Resource as an off-system
Resource
- Amount of power to which the customer has rights
- Identification of the Control Area from which the power
will originate
- Delivery point(s) to the Transmission Provider’s
Transmission System
- Transmission arrangements on the external transmission
system(s)
- Operating restrictions, if any
- Any periods of restricted operations throughout the
year
- Maintenance Schedules
- Minimum loading level of unit
- Normal operating level of unit
- Any must-run unit designations required for system
reliability or contract reasons
- Approximate variable generating cost ($/MWH) for
redispatch computations;
(vi) Description of Eligible Customer’s transmission system:
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
- Load flow and stability data, such as real and reactive parts
of the Load, lines, transformers, reactive devices and Load
type, including normal and Emergency ratings of all
transmission equipment in a Load flow format compatible
with that used by the Transmission Provider
- Operating restrictions needed for reliability
- Operating guides employed by system operators
- Contractual restrictions or committed uses of the Eligible
Customer’s transmission system, other than the Eligible
Customer’s Network Loads and Resources
- Location of Network Resources described in subsection (v)
above
- 10-year projection of system expansions or upgrades
- Transmission System maps that include any proposed
expansions or upgrades
- Thermal ratings of Eligible Customer’s Local Balancing
Authority Area ties with other Local Balancing Authority
Areas or Balancing Authority Areas; and
(vii) Service Commencement Date and the term of the requested
Network Integration Transmission Service. The minimum term for
Network Integration Transmission Service is one year.
(viii) A statement signed by an authorized officer from or agent of the
Network Customer attesting that all of the Network Resources
listed pursuant to Section 29.2(v) satisfy the following conditions:
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
(1) the Network Customer owns the Resource, has committed to
purchase generation pursuant to an executed contract, or has
committed to purchase generation where execution of a contract is
contingent upon the availability of Transmission Service under
Part III of the Tariff; and (2) the Network Resources do not include
any Resources, or any portion thereof, that are committed for sale
to non-designated third party load or otherwise cannot be called
upon to meet the Network Customer's Network Load on a non-
interruptible basis, except for purposes of fulfilling obligations
under a reserve sharing program; and
(ix) Any additional information required of the Transmission Customer
as specified in the Transmission Provider’s planning process
established in Attachment FF.
Unless the Parties agree to a different time frame, the Transmission Provider must
acknowledge the request within ten (10) days of receipt. The acknowledgment must include a
date by which a response, including a Service Agreement, will be sent to the Eligible Customer.
If an Application fails to meet the requirements of this section, the Transmission Provider shall
notify the Eligible Customer requesting service within fifteen (15) days of receipt and specify the
reasons for such failure. Wherever possible, the Transmission Provider will attempt to remedy
deficiencies in the Application through informal communications with the Eligible Customer. If
such efforts are unsuccessful, the Transmission Provider shall return the Application without
prejudice to the Eligible Customer filing a new or revised Application that fully complies with
MISO 29.2
FERC Electric Tariff Application Procedures
MODULES 30.0.0
Effective On: November 19, 2013
the requirements of this section. The Eligible Customer will be assigned a new priority
consistent with the date of the new or revised Application. The Transmission Provider shall treat
this information consistent with the standards of conduct contained in Part 37 of the
Commission’s regulations.
MISO 29.3
FERC Electric Tariff Arrangements to be Completed Prior to Service
MODULES 30.0.0
Effective On: November 19, 2013
Network Integration Transmission Service shall not commence until the
Transmission Provider, the affected Transmission Owner, ITC, and the Network
Customer, or a third party, have completed installation of all equipment specified
under the Network Operating Agreement consistent with Good Utility Practice
and any additional requirements reasonably and consistently imposed to ensure
the reliable operation of the Transmission System. The Transmission Provider
and the affected Transmission Owner(s) and ITC shall exercise reasonable efforts,
in coordination with the Network Customer, to complete such arrangements as
soon as practicable taking into consideration the Service Commencement Date.
MISO 29.4
FERC Electric Tariff Network Customer Facilities
MODULES 30.0.0
Effective On: November 19, 2013
The provision of Network Integration Transmission Service shall be
conditioned upon the Network Customer’s constructing, maintaining and
operating the facilities on its side of each Delivery Point or interconnection
necessary to reliably deliver Capacity and Energy from the Transmission System
to the Network Customer. The Network Customer shall be solely responsible for
constructing or installing all facilities on the Network Customer’s side of each
such delivery point or interconnection.
MISO 29.5
FERC Electric Tariff Filing of Service Agreement
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider will file Service Agreements with the
Commission in compliance with applicable Commission regulations.
MISO 30
FERC Electric Tariff Network Resources
MODULES 30.0.0
Effective On: November 19, 2013
MISO 30.1
FERC Electric Tariff Designation of Network Resources
MODULES 30.0.0
Effective On: November 19, 2013
Network Resources shall include all generation owned, purchased or
leased by the Network Customer designated to serve Network Load under the
Tariff. Network Resources may not include Generation Resources, or any portion
thereof, that are committed for sale to non-designated third party Load or
otherwise cannot be called upon to meet the Network Customer’s Network Load
on a non-interruptible basis, except for purposes of fulfilling obligations under a
reserve sharing program. Any owned or purchased Generation Resources that
were serving the Network Customer’s Loads under firm agreements entered into
on or before the Service Commencement Date shall initially be designated as
Network Resources until the Network Customer terminates the designation of
such Generation Resources.
MISO 30.2
FERC Electric Tariff Designation of New Network Resources
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer may designate a new Network Resource by
providing the Transmission Provider with as much advance notice as practicable
and under any procedures established by the Transmission Provider. A
designation of a new Network Resource must be made through the Transmission
Provider’s OASIS by a request for modification of service pursuant to an
Application under Section 29. This request must include a statement that the new
Network Resource satisfies the following conditions: (1) the Network Customer
owns the Resource, has committed to purchase generation pursuant to an executed
contract, or has committed to purchase generation where execution of a contract is
contingent upon the availability of Transmission Service under Part III of this Tariff;
and (2) the Network Resources do not include any Resources, or any portion thereof,
that are committed for sale to non-designated third party Load or otherwise cannot
be called upon to meet the Network Customer's Network Load on a non-interruptible
basis, except for purposes of fulfilling obligations under a reserve sharing program.
The Network Customer’s request will be deemed deficient if it does not include this
statement and the Transmission Provider will follow the procedures for a deficient
application as described in Section 29.2 of this Tariff.
MISO 30.3
FERC Electric Tariff Termination of Network Resources
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer may terminate the designation of all or part of a Generation
Resource as a Network Resource by providing notification to the Transmission
Provider through OASIS and, as appropriate, the ITC as soon as reasonably
practicable, but not later than the firm scheduling deadline for the period of
termination. Any request for termination of Network Resource status must be
submitted on OASIS, and should indicate whether the request is for indefinite or
temporary termination. A request for indefinite termination of Network Resource
status must indicate the date and time that the termination is to be effective, and the
identification and Capacity of the Resource(s) or portions thereof to be indefinitely
terminated. A request for temporary termination of Network Resource status must
include the following:
i. Effective date and time of temporary termination;
ii. Effective date and time of redesignation, following period of temporary
termination;
iii. Identification and Capacity of Resource(s) or portions thereof to be
temporarily terminated;
iv. Resource description and attestation for redesignating the Network
Resource following the temporary termination, in accordance with
Section 30.2; and
v. Identification of any related Transmission Service requests to be
evaluated concomitantly with the request for temporary termination,
such that the requests for undesignation and the request for these
MISO 30.3
FERC Electric Tariff Termination of Network Resources
MODULES 30.0.0
Effective On: November 19, 2013
related Transmission Service requests must be approved or denied as a
single request. The evaluation of these related Transmission Service
requests must take into account the termination of the Network
Resources identified in (iii) above, as well as all competing
Transmission Service requests of higher priority.
As part of a temporary termination, a Network Customer may only
redesignate the same Resource that was originally designated, or a portion
thereof. Requests to redesignate a different Resource and/or a Resource with
increased Capacity will be deemed deficient and the Transmission Provider will
follow the procedures for a deficient application as described in Section 29.2 of
the Tariff.
MISO 30.4
FERC Electric Tariff Operation of Network Resources
MODULES 31.0.0
Effective On: May 1, 2015
The Network Customer shall not operate its designated Network Resources located
within the Midwest ISO Balancing Authority Area(s) such that the output of those facilities
exceeds its designated Network Load, plus Non-Firm Sales delivered pursuant to Module B of
this Tariff, plus net sales of Energy into the Energy Markets under this Tariff, plus Marginal
Losses, plus power sales under a reserve sharing program, plus sales that permit curtailment
without penalty to serve its designated Network Load. This limitation shall not apply to changes
in the operation of a Transmission Customer’s Network Resources at the request of the
Transmission Provider to respond to an Emergency or other unforeseen condition which may
impair or degrade the reliability of the Transmission System. For all Network Resources not
physically connected with the Transmission System, the Network Customer may not schedule
delivery of Energy in excess of the Network Resource’s capacity, as specified in the Network
Customer’s Application pursuant to Section 29, unless the Network Customer supports such
delivery within the Transmission System by either obtaining Point-to-Point Transmission Service
or utilizing secondary service pursuant to Section 28.4.
In the event that a Network Customer’s schedule at the delivery point for a Network
Resource not physically connected with the Transmission System exceeds the Network
Resource’s designated capacity, excluding Energy delivered using secondary service or Point-to-
Point Transmission Service, the Transmission Provider will assess unreserved use penalties as
follows: (1) the unreserved use penalties shall be based on the period of unreserved use; (2) the
unreserved use penalty for a single hour of unreserved use shall be the applicable rate for daily
firm Point-to-Point Transmission Service, as set forth in Schedule 7 of the Tariff; and (3) more
than one assessment for a given duration (e.g., daily) shall result in an increase of the penalty
MISO 30.4
FERC Electric Tariff Operation of Network Resources
MODULES 31.0.0
Effective On: May 1, 2015
period to the next longest duration (e.g., weekly). Unreserved use penalties assessed using daily
firm Point-to-Point Transmission Service rates shall account for off-peak and on-peak usage, as
set forth in Schedule 7 of the Tariff. A 200% multiplier shall be applied to all assessed penalties.
These penalty revenues shall be allocated in the manner set forth in Section 13.7 of the Tariff.
MISO 30.5
FERC Electric Tariff [RESERVED]
MODULES 30.0.0
Effective On: November 19, 2013
MISO 30.6
FERC Electric Tariff Arrangements for Network Resources Not Interconnected
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall be responsible for any arrangements
necessary to deliver Capacity and Energy from a Network Resource not
physically interconnected with the Transmission System. The Transmission
Provider and ITC, if applicable, will undertake reasonable efforts to assist the
Network Customer in obtaining such arrangements, including without limitation,
providing any information or data required by such other entity pursuant to Good
Utility Practice.
MISO 30.7
FERC Electric Tariff Limitation on Designation of Network Resources
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer must demonstrate that it owns or has committed to
purchase generation pursuant to an executed contract in order to designate a
Generation Resource as a Network Resource. Alternatively, the Network
Customer may establish that execution of a contract is contingent upon the
availability of Transmission Service under Module B of this Tariff.
MISO 30.8
FERC Electric Tariff Use of Interface Capacity by the Network Customer
MODULES 30.0.0
Effective On: November 19, 2013
There is no specific limitation upon a Network Customer’s use of the
Transmission System at the Interface(s) to the MISO Balancing Authority Area
(where the Network Customer’s Load is located) to integrate the Network
Customer’s Network Resources (or substitute economy purchases) with its
Network Loads. However, a Network Customer’s use of the Transmission
Provider’s or ITC’s total Interface capacity with other transmission systems may
not exceed the Network Customer’s Load or the applicable Interface capacity;
provided, however, that the usage restriction related to Load shall not limit an
entity's ability to use Interface capacity to schedule a quantity of Energy in excess
of Load to the extent such Energy is scheduled to meet the Network Customer's
must offer requirements set forth in RAR of this Tariff. The Transmission
Provider shall post on its OASIS or otherwise no later than sixty days before the
date this Tariff becomes effective and thereafter (1) the process Network
Customers will use to reach Generation Resources that are located in other
Balancing Authority Areas beyond the boundaries of the Transmission System,
and (2) how competing requests among Network Customers and between
Network Customers and Transmission Customers taking Point-To-Point
Transmission Service will be resolved. Before implementing or changing its
procedures, the Transmission Provider shall submit a filing to the Commission.
MISO 30.8
FERC Electric Tariff Use of Interface Capacity by the Network Customer
MODULES 30.0.0
Effective On: November 19, 2013
MISO 30.9
FERC Electric Tariff Network Customer Owned Transmission Facilities
MODULES 31.0.0
Effective On: March 1, 2016
The Network Customer that owns existing transmission facilities that are integrated with
the Transmission System may be eligible to receive consideration either through a billing credit
or some other mechanism. In order to receive such consideration the Network Customer must
demonstrate that its transmission facilities are integrated into the plans or operations of the
Transmission Provider or ITC to serve its power and transmission customers. For facilities
added by the Network Customer subsequent to July 13, 2007, the Network Customer shall
receive credit for such transmission facilities added if such facilities are integrated into the
operations of the Transmission Provider’s facilities; provided however, the Network Customer’s
transmission facilities shall be presumed to be integrated if such transmission facilities, if owned
by the Transmission Provider, would be eligible for inclusion in the Transmission Provider’s
annual transmission revenue requirement as specified in Attachment O. Calculation of any credit
under this subsection shall be addressed in either the Network Customer’s Service Agreement or
any other agreement between the Parties. This crediting provision does not apply to Network
Customer transmission facilities that are reflected in the rates for service under this Tariff.
MISO 31
FERC Electric Tariff Designation of Network Load
MODULES 30.0.0
Effective On: November 19, 2013
MISO 31.1
FERC Electric Tariff Network Load
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer must designate the individual Network Loads on
whose behalf the Transmission Provider or ITC will provide Network Integration
Transmission Service. The Network Loads shall be specified in the Service
Agreement. Network Loads taking service under Schedule 9 – Michigan must be
directly interconnected with the Transmission System (Michigan) or through
Distribution Facilities in the Transmission System (Michigan).
MISO 31.2
FERC Electric Tariff New Network Loads
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall provide the Transmission Provider or ITC
with as much advance notice as reasonably practicable of the designation of new
Network Load that will be added to its Transmission System. A designation of
new Network Load must be made through a modification of service pursuant to a
new Application submitted using the Transmission Provider’s OASIS. The
Transmission Provider together with affected Transmission Owner(s) or ITC will
use due diligence to install any transmission facilities required to interconnect a
new Network Load designated by the Network Customer. The costs of new
facilities required to interconnect a new Network Load shall be determined in
accordance with the procedures provided in Module B, Section 32.4 and shall be
charged to the Network Customer in accordance with Commission policies.
MISO 31.3
FERC Electric Tariff Location of Network Loads
MODULES 31.0.0
Effective On: July 19, 2015
All Network Load must meet at least one of the following location requirements:
(a) Network Load is physically interconnected with a Transmission Owner or ITC
within the geographic area in which facilities subject to this Tariff are located. All Network
Load taking service pursuant to Schedule 9 – Michigan must be physically and directly
interconnected with the Transmission System (Michigan) or through Distribution Facilities in the
Transmission System (Michigan).
(b) Network Load is not physically interconnected with a Transmission Owner or
ITC within the geographic area in which facilities subject to this Tariff are located but meets all
of the following conditions:
(i) Non-interconnected Network Load must have been either: (1) part of a
Transmission Owner’s bundled or native load prior to that Transmission Owner joining MISO, or
(2) a network customer’s network load under a Transmission Owner’s or ITC’s open access
transmission tariff in effect prior to that Transmission Owner or ITC joining MISO. The non-
interconnected Network Load must be part of the pricing zone of that MISO Transmission Owner
or ITC and the Network Customer must have coordinating arrangements in place with the host
Transmission Owner or ITC for reporting of the Network Load;
(ii) The non-interconnected Network Load is reported in a MISO Local
Balancing Authority Area;
(iii) The Network Customer takes Network Integration Transmission Service
for delivery of its Network Resources or other non-designated Generation Resources to the
Transmission Provider’s geographic area border to serve the non-interconnected Network Load;
and
MISO 31.3
FERC Electric Tariff Location of Network Loads
MODULES 31.0.0
Effective On: July 19, 2015
(iv) The non-interconnected Network Load is served by firm transmission
service on the adjacent non-MISO transmission provider’s system.
(c) Network Load is not physically interconnected with a Transmission Owner or ITC
within the geographic area in which facilities subject to this Tariff are located, but is physically
located within the boundaries of the MISO Balancing Authority Area and balanced by the MISO
Balancing Authority. This does not include load that is Pseudo Tied into MISO Balancing
Authority.
MISO 31.4
FERC Electric Tariff New Interconnection Points
MODULES 30.0.0
Effective On: November 19, 2013
To the extent the Network Customer desires to add a new Delivery Point
or interconnection point between the Transmission System and a Network Load,
the Network Customer shall provide the Transmission Provider and ITC with as
much advance notice as reasonably practicable.
MISO 31.5
FERC Electric Tariff Changes in Service Requests
MODULES 30.0.0
Effective On: November 19, 2013
Under no circumstances shall the Network Customer’s decision to cancel
or delay a requested change in Network Integration Transmission Service (e.g.,
the addition of a new Network Resource or designation of a new Network Load)
in any way relieve the Network Customer of its obligation to pay the costs of
transmission facilities caused to be constructed by the Transmission Provider or
ITC and charged to the Network Customer as reflected in the Service Agreement.
The Network Customer must provide to the Transmission Provider, via the
OASIS, any request to defer the start of the long term service at least 31 days
prior to the beginning of service. The Transmission Provider must treat any
requested change in Network Integration Transmission Service in a non-
discriminatory manner.
MISO 31.6
FERC Electric Tariff Annual Load and Resource Information Updates
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall provide the Transmission Provider and ITC
with annual updates of Network Load and Network Resource forecasts consistent
with those included in its Application for Network Integration Transmission
Service under Module B of this Tariff including, but not limited to, any
information provided under Section 29.2(ix) pursuant to the Transmission
Provider’s planning processes in Attachment FF. The Network Customer also
shall provide the Transmission Provider and ITC with timely written notice of
material changes in any other information provided in its Application relating to
the Network Customer’s Network Load, Network Resources, its transmission
system or other aspects of its facilities or operations affecting the Transmission
Provider’s or ITC’s ability to provide reliable service.
MISO 32
FERC Electric Tariff Additional Study Procedures for Network Integration Transmis
MODULES 30.0.0
Effective On: November 19, 2013
Additional Study Procedures for Network Integration Transmission Service Requests
MISO 32.1
FERC Electric Tariff Notice of Need for System Impact Study
MODULES 30.0.0
Effective On: November 19, 2013
After receiving a request for service, the Transmission Provider or ITC, as
applicable, shall determine on a non-discriminatory basis whether a System
Impact Study is needed. A description of the Transmission Provider’s
methodology for completing a System Impact Study is provided in Attachment D.
If the Transmission Provider or ITC determines that a System Impact Study is
necessary to accommodate the requested service, it shall so inform the Eligible
Customer, as soon as practicable. In such cases, the Transmission Provider shall
within thirty (30) days of receipt of a Completed Application, tender a System
Impact Study agreement pursuant to which the Eligible Customer shall agree to
reimburse the Transmission Provider or ITC, as applicable, for performing the
required System Impact Study. For a service request to remain a Completed
Application, the Eligible Customer shall execute the System Impact Study
agreement in the form of Attachment D-1 of this Tariff and return it to the
Transmission Provider within fifteen (15) days. If the Eligible Customer elects
not to execute the System Impact Study agreement, its Application shall be
deemed withdrawn and any deposit shall be returned with interest.
MISO 32.2
FERC Electric Tariff System Impact Study Agreement and Cost Reimbursement
MODULES 30.0.0
Effective On: November 19, 2013
(i) The System Impact Study agreement will clearly specify the
Transmission Provider’s or, as applicable, ITC’s estimate of the
actual cost, and time for completion of the System Impact Study.
The charge shall not exceed the actual cost of the study. In
performing the System Impact Study, the Transmission Provider
or, as applicable, ITC shall rely, to the extent reasonably
practicable, on existing transmission planning studies. The
Eligible Customer will not be assessed a charge for such existing
studies; however, the Eligible Customer will be responsible for
charges associated with any modifications to existing planning
studies that are reasonably necessary to evaluate the impact of the
Eligible Customer’s request for service on the Transmission
System.
(ii) If in response to multiple Eligible Customers requesting service in
relation to the same competitive solicitation, a single System
Impact Study is sufficient for the Transmission Provider or, as
applicable, ITC to accommodate the service requests, the costs of
that study shall be pro-rated among the Eligible Customers.
(iii) Each Transmission Owner shall pay the Transmission Provider for
System Impact Studies that the Transmission Provider conducts on
the Transmission Owner’s behalf, the same as any non-
Transmission Owner.
MISO 32.2
FERC Electric Tariff System Impact Study Agreement and Cost Reimbursement
MODULES 30.0.0
Effective On: November 19, 2013
MISO 32.3
FERC Electric Tariff System Impact Study Procedures
MODULES 31.0.0
Effective On: August 2, 2017
Upon receipt of an executed System Impact Study agreement, the
Transmission Provider or ITC, as applicable, will use due diligence to complete
the required System Impact Study within a sixty (60)-day period. The System
Impact Study shall identify (i) any system constraints, identified with specificity
by transmission element or flowgate, (ii) available options for installation of
automatic devices to curtail service (when requested by an Eligible Customer),
and (iii) additional Direct Assignment Facilities or Network Upgrades required to
provide the requested service. In the event that the Transmission Provider or ITC
is unable to complete the required System Impact Study within such time period,
it shall so notify the Eligible Customer and provide an estimated completion date
along with an explanation of the reasons why additional time is required to
complete the required studies. A copy of the completed System Impact Study and
related work papers shall be made available to the Eligible Customer as soon as
the System Impact Study is complete.
The Transmission Provider and ITC, as applicable, will use the same due
diligence in completing the System Impact Study for an Eligible Customer as it
uses when completing studies for Transmission Owners or ITC Participants.
The Transmission Provider, or ITC, as applicable, shall notify the Eligible
Customer immediately upon completion of the System Impact Study if the
Transmission System will be adequate to accommodate all or part of a request for
service or that no costs are likely to be incurred for new transmission facilities or
upgrades. In order for a request to remain a Completed Application, within
MISO 32.3
FERC Electric Tariff System Impact Study Procedures
MODULES 31.0.0
Effective On: August 2, 2017
fifteen (15) days of completion of the System Impact Study the Eligible Customer
must execute a Service Agreement or request the filing of an unexecuted Service
Agreement, or the Application shall be deemed terminated and withdrawn.
MISO 32.4
FERC Electric Tariff Facilities Study Procedures
MODULES 30.0.0
Effective On: November 19, 2013
If a System Impact Study indicates that additions or upgrades to the
Transmission System are needed to supply the Eligible Customer’s service
request, the Transmission Provider, within thirty (30) days of the completion of
the System Impact Study, shall tender to the Eligible Customer a Facilities Study
agreement pursuant to which the Eligible Customer shall agree to reimburse the
Transmission Provider or ITC, as applicable, and any affected Transmission
Owner(s) for performing the required Facilities Study. For a service request to
remain a Completed Application, the Eligible Customer shall execute the
Facilities Study agreement in the form of Attachment D-2 of this Tariff and return
it to the Transmission Provider within fifteen (15) days. If the Eligible Customer
elects not to execute the Facilities Study agreement, its Application shall be
deemed withdrawn and any deposit shall be returned with interest.
Upon receipt of an executed Facilities Study agreement, the Transmission
Provider or ITC, as applicable, in coordination with the affected Transmission
Owner(s) will use due diligence to complete the required Facilities Study within a
one hundred and twenty (120) day period. If the Transmission Provider or, as
applicable, ITC together with the affected Transmission Owner(s) are unable to
complete the Facilities Study in the allotted time period, the Transmission
Provider or ITC, as applicable, shall notify the Eligible Customer and provide an
estimate of the time needed to reach a final determination along with an
explanation of the reasons that additional time is required to complete the study.
When completed, the Facilities Study will include a good faith estimate of (i) the
MISO 32.4
FERC Electric Tariff Facilities Study Procedures
MODULES 30.0.0
Effective On: November 19, 2013
cost of Direct Assignment Facilities to be charged to the Eligible Customer, (ii)
the Eligible Customer’s appropriate share of the cost of any required Network
Upgrades, and (iii) the time required to complete such construction and initiate
the requested service.
The Eligible Customer shall be requested to provide the Transmission
Provider with a letter of credit or other reasonable form of security acceptable to
the Transmission Provider, and ITC, as applicable, equivalent to the costs of new
facilities or upgrades consistent with commercial practices as established by the
Uniform Commercial Code unless the Transmission Provider determines that the
Eligible Customer already has a letter(s) of credit or other form(s) of security on
file with the Transmission Provider that is sufficient to cover its existing and
proposed obligations. The Eligible Customer shall have thirty (30) days to
execute a Service Agreement or request the filing of an unexecuted Service
Agreement and provide the required letter of credit or other form of security or
the request no longer will be a Completed Application and shall be deemed
terminated and withdrawn.
MISO 32.4.1
FERC Electric Tariff Changes in Facilities Study Assumptions
MODULES 30.0.0
Effective On: November 19, 2013
Any changes to the original assumptions, considered during the
System Impact Study, that arise during the Facilities Study, that can
materially impact the results of the Facilities Study, may require the
Transmission Provider to re-evaluate the results of the original System
Impact Study. If the Transmission Provider ascertains that the changes in
assumptions are material modifications to the original scope of the study,
that could change the outcome of the Facilities Study, then the
Transmission Provider shall temporarily stop work on the Facilities Study
until the results from the re-evaluation are available. After the re-
evaluation results are available, the Transmission Provider will make the
final determination whether the initial Facilities Study should proceed
based on the original scope or based on the revised scope. If the scope of
the initial Facilities Study needs to be revised, then the Transmission
Provider will reset the one hundred and twenty (120) day clock to perform
the revised Facilities Study. The Transmission Provider will take
appropriate steps to communicate to the customer the revised scope and
schedule the revised Facilities Study.
MISO 32.4.1
FERC Electric Tariff Changes in Facilities Study Assumptions
MODULES 30.0.0
Effective On: November 19, 2013
MISO 32.5
FERC Electric Tariff Penalties for Failure to Meet Study Deadlines
MODULES 30.0.0
Effective On: November 19, 2013
Section 19.9 defines penalties that apply for failure to meet the sixty (60) day study
completion due diligence deadlines for System Impact Studies and one hundred and twenty (120)
day study completion deadlines for Facilities Studies under Part II of this Tariff. These same
requirements and penalties apply to service under Part III of this Tariff.
MISO 33
FERC Electric Tariff Load Shedding, Curtailments and Manual Redispatch
MODULES 30.0.0
Effective On: November 19, 2013
MISO 33.1
FERC Electric Tariff Procedures
MODULES 30.0.0
Effective On: November 19, 2013
Prior to the Service Commencement Date, the Transmission Provider, in
coordination with the affected Transmission Owner(s) and ITC, and the Network
Customer shall establish Load Shedding and Curtailment procedures pursuant to
the Network Operating Agreement with the objective of responding to
contingencies on the Transmission System and on systems directly and indirectly
interconnected with the Transmission Provider’s Transmission System. The
Parties, including the affected Transmission Owner(s) and ITC, will implement
such programs during any period when the Transmission Provider or the ITC
determines that a system contingency exists and such procedures are necessary to
alleviate such contingency. The Transmission Provider will notify all affected
Network Customers, and affected Transmission Owners, and ITCs in a timely
manner of any scheduled Curtailment.
MISO 33.2
FERC Electric Tariff Transmission Constraints
MODULES 30.0.0
Effective On: November 19, 2013
During any period when the Transmission Provider determines that a
transmission constraint exists on the Transmission System, and such constraint
may impair the reliability of the Transmission Provider’s system, the
Transmission Provider or ITC, as applicable, will take whatever actions,
consistent with Good Utility Practice, that are reasonably necessary to maintain
the reliability of the Transmission Provider’s or the ITC system. To the extent the
Transmission Provider or ITC determines that the reliability of the Transmission
System can be maintained by redispatching Resources, the procedures in Module
C shall apply.
MISO 33.3
FERC Electric Tariff Cost Responsibility for Relieving Transmission Constraints
MODULES 30.0.0
Effective On: November 19, 2013
The cost of relieving transmission constraint is the cost of redispatch of
Resources pursuant to the provisions of Module C. The cost of redispatch is the
responsibility of Market Participants and is assessed to each Market Participant’s
transactions pursuant to Sections 39.3.1, 39.3.3, 40.3 and 40.4.
MISO 33.4
FERC Electric Tariff Curtailments of Scheduled Deliveries
MODULES 31.0.0
Effective On: January 2, 2019
If the Transmission Provider or ITC, as applicable, determines that it is
necessary to curtail scheduled deliveries, the Parties and the affected
Transmission Owner(s) and ITC shall curtail such schedules in accordance with
the Network Operating Agreement and any applicable ITC Rate Schedule or this
Tariff, or pursuant to the Transmission Loading Relief Procedures specified in
NERC Reliability Standards and NAESB WEQ Business Practice Standards .
MISO 33.5
FERC Electric Tariff Allocation of Curtailments
MODULES 30.0.0
Effective On: November 19, 2013
The Transmission Provider shall, on a non-discriminatory basis, identify
and curtail transaction(s) in order to effectively relieve the constraint. However,
to the extent practicable and consistent with Good Utility Practice, any
Curtailment will be shared by the affected Transmission Owner(s), or ITC
Participant(s), and Network Customer in proportion to their respective Load Ratio
Shares. The Transmission Provider shall not direct the Network Customer to
curtail schedules to an extent greater than the Transmission Provider would curtail
the Transmission Owner’s, or ITC Participant schedules under similar
circumstances.
MISO 33.6
FERC Electric Tariff Load Shedding
MODULES 30.0.0
Effective On: November 19, 2013
To the extent that a system contingency exists on the Transmission System
and the Transmission Provider or ITC determines that it is necessary for the
affected Transmission Owner(s), ITC Participant(s) and the Network Customer to
shed Load, the Parties shall shed Load in accordance with previously established
procedures under the Network Operating Agreement, and any applicable ITC
Rate Schedule or tariff, or the ISO Agreement whichever is applicable.
MISO 33.7
FERC Electric Tariff System Reliability
MODULES 30.0.0
Effective On: November 19, 2013
Notwithstanding any other provisions of this Tariff, the Transmission
Provider reserves the right, consistent with Good Utility Practice and on a not
unduly discriminatory basis, to curtail Network Integration Transmission Service
without liability on the Transmission Provider’s or Transmission Owner’s, ITC’s,
or ITC Participant’s part for the purpose of making necessary adjustments to,
changes in, or repairs on the Transmission Owner’s and ITC’s lines, substations
and facilities, and in cases where the continuance of Network Integration
Transmission Service would endanger persons or property. In the event of any
adverse condition(s) or disturbance(s) on the Transmission System or on any
other system(s) directly or indirectly interconnected with the Transmission
System, the Transmission Provider, consistent with Good Utility Practice, also
may curtail Network Integration Transmission Service in order to (i) limit the
extent or damage of the adverse condition(s) or disturbance(s), (ii) prevent
damage to generating or transmission facilities, or (iii) expedite restoration of
service. The Transmission Provider will give the Network Customer as much
advance notice as is practicable in the event of such Curtailment.
a) $10 per kW if the customer fails to respond within the required
response period set forth in the Network Operating Agreement; or
b) $20 per KW if the customer fails to respond within a period of
time equal to two times the response period set forth in the
Network Operating Agreement. These charges shall apply only to
the portion of the service that the Transmission Customer fails to
MISO 33.7
FERC Electric Tariff System Reliability
MODULES 30.0.0
Effective On: November 19, 2013
curtail in response to a directive. The Transmission Provider shall
compensate any affected Local Balancing Authority Areas or
Generators for their actual costs up to the amount recovered by the
Transmission Provider. Any revenues in excess of actual costs
shall be used to reduce the Transmission Provider’s costs (for other
than the penalized Transmission Customer) in Schedule 10, or, in
the case of ITC Service, any revenues in excess of actual costs
shall be applied as specified in the ITC Rate Schedule.
MISO 33.8
FERC Electric Tariff Manual Redispatch
MODULES 31.0.0
Effective On: December 20, 2013
MISO 33.8.1
FERC Electric Tariff Circumstances Requiring Manual Redispatch
MODULES 31.0.0
Effective On: December 31, 9998
Generation Resources, Demand Response Resources-Type II, or Electric Storage
Resources may be manually redispatched by the Transmission Provider in order to maintain the
reliability of the Transmission System only in circumstances where automated Real-Time
Energy and Operating Reserve Market generation dispatch procedures set forth in Module C are
inadequate to maintain reliability. Such circumstances arise when the five-minute dispatch
process utilized in Real-Time Energy and Operating Reserve Market operations is unable to
respond.
During these situations, the Transmission Provider may manually redispatch Generation
Resources, Demand Response Resources-Type II, or Electric Storage Resources until such time
as the automated Real-Time Energy and Operating Reserve Market generation dispatch
procedures set forth in Module C of this Tariff are deemed adequate to maintain reliable
operations of the Transmission System. The circumstances that may require Manual Redispatch
include, but are not limited to, any Transmission System condition that requires immediate
action to avoid or mitigate system operating limit violations, or to avoid exceeding an
interconnection reliability operational limit.
If operational factors permit, the Transmission Provider will attempt to inform the Market
Participant and provide it an opportunity to cure behavior that can lead to Manual Redispatch.
Manual Redispatch may be ordered irrespective of any TLR level prevailing at the time. In the
event that the Transmission System is experiencing conditions that exceed an interconnection
reliability operating limit or other conditions that could lead to cascading outages of the
Transmission System, the Transmission Provider shall implement Emergency procedures,
pursuant to Section 40.2.20 of this Tariff.
MISO 33.8.2
FERC Electric Tariff Manual Redispatch Compensation and Eligibility
MODULES 42.0.0
Effective On: December 31, 9998
As a result of following Manual Redispatch instructions, Generation Resources, Demand
Response Resources–Type II, or Electric Storage Resources that are manually redispatched by
the Transmission Provider, either directly or as a Transmission Provider instruction
communicated through a Local Balancing Authority, may not fully recover their real-time
Incremental Energy Cost from the Hourly Real-Time Ex Post LMP during the period the
Transmission Provider has directed the Generation Resources, Demand Response Resources–
Type II, or Electric Storage Resources to operate at Energy levels above the Resource’s Day-
Ahead Schedule for Energy, or may have Day-Ahead Margins eroded during the period the
Transmission Provider has directed the Generation Resource, Demand Response Resource-
Type II, or Electric Storage Resource to operate at Energy levels below the Resource’s Day-
Ahead Schedule for Energy. In such circumstances, the Market Participant owning the
Generation Resource, Demand Response Resource– Type II, or Electric Storage Resource shall
be compensated pursuant to Schedule 27 of this Tariff only if the following eligibility criteria
and requirements are satisfied.
a. A Generation Resource, Demand Response Resource-Type II, or Electric Storage
Resource manually redispatched pursuant to this Section of this Tariff, is only eligible for Real-
Time Offer Revenue Sufficiency Guarantee Payments (“RTORSGP”) under Schedule 27 in
Hours in which it has been committed by the Transmission Provider in the Day-Ahead Energy
and Operating Reserve Market, or received a commitment from the Transmission Provider in the
Real-Time Energy and Operating Reserve Market as must-run. In addition, the following
requirements must be met for a Generation Resource, Demand Response Resource-Type II, or
Electric Storage Resource to be eligible for RTORSGP under Schedule 27:
MISO 33.8.2
FERC Electric Tariff Manual Redispatch Compensation and Eligibility
MODULES 42.0.0
Effective On: December 31, 9998
1) Day-Ahead committed Hours must comply with the following requirements:
(a) The Generation Resource, Demand Response Resource-Type II, or Electric
Storage Resource must offer flexibly for the Hour pursuant to the following
criteria:
i. All ramp rates used in the Real-Time Energy and Operating Reserve
Market within the Dispatch Interval must be greater than one-half MW per
minute;
ii. The Up and Down Ramp Capability Dispatch Status must be submitted as
Economic in the Real-Time Energy and Operating Reserve Market; and
iii. If four or more consecutive Dispatch Intervals fail eligibility, the Resource
will be ineligible for compensation.
(b) The as-committed day-ahead Offers must remain unchanged when submitted as
Real-Time Offers pursuant to the following criteria:
i. For a given day-ahead committed Hour, the following Offers must be the
same as the Offers that the day-ahead commitment was based on, and the
Real-Time Offers at the close of the Real-Time Energy and Operating
Reserve Market Hour as submitted by the Market Participant:
1. Hourly Economic Minimum Limit, Hourly Emergency Minimum
Limit and Hourly Regulation Minimum Limit must be equal to the
day-ahead Hourly Economic Minimum Limit, Hourly Emergency
Minimum Limit and Hourly Regulation Minimum Limit, respectively.
MISO 33.8.2
FERC Electric Tariff Manual Redispatch Compensation and Eligibility
MODULES 42.0.0
Effective On: December 31, 9998
For Electric Storage Resources, applicable real-time hourly minimum
limits must be equal to the hourly day-ahead minimum limits.
2. The real-time Regulating Capacity Offer must be equal to the day-
ahead Regulating Capacity Offer, the real-time Regulating Mileage
Offer must be equal to the day-ahead Regulating Mileage Offer, the
real-time Spinning Reserve Offer must be equal to the day-ahead
Spinning Reserve Offer, and the real-time Supplemental Reserve Offer
must be equal to the day-ahead Supplemental Reserve Offer.
3. The real-time Up and Down Ramp Capability Dispatch Status must be
equal to the day-ahead Up and Down Ramp Capability Dispatch
Status.
2) Real-time must-run committed Hours must meet the following requirements:
(a) The Generation Resource, Demand Response Resource-Type II, or Electric
Storage Resource must offer flexibly for the Hour, pursuant to the following
criteria:
i. All ramp rates used in the Real-Time Energy and Operating Reserve
Market within the Dispatch Interval must be greater than one-half MW per
minute;
ii. The Up and Down Ramp Capability Dispatch Status must be submitted as
Economic in the Real-Time Energy and Operating Reserve Market; and
iii. If four or more consecutive Dispatch Intervals fail eligibility, the Resource
will be ineligible for compensation.
MISO 33.8.2
FERC Electric Tariff Manual Redispatch Compensation and Eligibility
MODULES 42.0.0
Effective On: December 31, 9998
(b) All Offers must be the same for each consecutive real-time must-run Hour within
the Manual Redispatch period and the first Hour of the Manual Redispatch period
must be the same as the previous Hour, if committed, pursuant to the following
criteria:
i. The following Offer parameters must be the same for each consecutive
real-time must-run committed Hour in the Manual Redispatch period:
1. Regulating Capacity, Regulating Mileage, Spinning Reserve and
Supplemental Reserve Offers;
2. Hourly Economic Minimum Limit, Hourly Emergency Minimum
Limit and Hourly Regulation Minimum Limit or applicable hourly
minimum limits for Electric Storage Resources; and
3. Up and Down Ramp Capability Dispatch Status.
ii. The following Offer parameters must be the same for the first Hour of the
real-time must-run committed Hour in the Manual Redispatch period, and
the previous Hour, if committed:
1. Regulating Capacity, Regulating Mileage, Spinning Reserve and
Supplemental Reserve Offers;
2. Hourly Economic Minimum Limit, Hourly Emergency Minimum
Limit and Hourly Regulation Minimum Limit or applicable hourly
minimum limits for Electric Storage Resources; and
3. Up and Down Ramp Capability Dispatch Status.
MISO 33.8.2
FERC Electric Tariff Manual Redispatch Compensation and Eligibility
MODULES 42.0.0
Effective On: December 31, 9998
Failure to meet any of these requirements will result in the Generation Resource,
Demand Response Resource-Type II, or Electric Storage Resource being
disqualified for RTORSGP in the Hour during which such failure occurs and each
subsequent Hour of the Manual Redispatch period.
b. A Generation Resource, Demand Response Resource-Type II, or Electric Storage
Resource manually redispatched pursuant to this Section 33.8 is only eligible for DAMAP under
Schedule 27 in Hours in which its Day-Ahead Margin has been eroded.
1) In addition, the following requirements must be met for a Generation Resource,
Demand Response Resource-Type II, or Electric Storage Resource to be eligible
for DAMAP under Schedule 27:
The Generation Resource must offer flexibly for the Hour, pursuant to the
following criteria:
a. All ramp rates used in the Real-Time Energy and Operating Reserve
Market within the Dispatch Interval must be greater than one-half MW per
minute; and
b. The Up and Down Ramp Capability Dispatch Status must be submitted as
Economic in the Day-Ahead and Real-Time Energy and Operating
Reserve Market.
If four or more consecutive Dispatch Intervals fail eligibility, the Resource will be
ineligible for compensation.
MISO 33.8.2
FERC Electric Tariff Manual Redispatch Compensation and Eligibility
MODULES 42.0.0
Effective On: December 31, 9998
Failure to meet any of these requirements will result in the Generation Resource,
Demand Response Resource-Type II, or Electric Storage Resource being
disqualified for DAMAP in the Hour during which such failure occurs.
2) A Generation Resource, Demand Response Resource-Type II, or Electric Storage
Resource manually redispatched to zero is only eligible for DAMAP under
Schedule 27 in the Hours in which the resource is manually redispatched plus the
Hours for any applicable Minimum Down Time requirement.
3) A Generation Resource will also be reimbursed any start-up costs incurred to
return to online status after being manually redispatched to zero only to the extent
such costs have not been recovered through the clearing and commitment of the
Generation Resource in the Day-Ahead Energy and Operating Reserve Market
and/or the Real-Time Energy and Operating Reserve Market. The reimbursed
start-up costs shall be funded through an assessment of debits on all Market
Participants on a pro rata basis, based on their Market Load Ratio Share.
c. During any period in which a Generation Resource and Electric Storage Resource is
Manually Redispatched, the Generation Resource and Electric Storage Resource shall be exempt
from paying Revenue Sufficiency Guarantee Distribution charges and shall be exempt from
Excessive/Deficient Energy Deployment Charges under Section 40.3.4. If the period of Manual
Redispatch includes any partial Hour, then that entire Hour will be exempt from paying Revenue
Sufficiency Guarantee Charges and shall be exempt from Excessive/Deficient Energy
Deployment Charges under Section 40.3.4.
MISO 33.8.3
FERC Electric Tariff Manual Redispatch Cost Recovery
MODULES 31.0.0
Effective On: December 31, 9998
Payments associated with Manual Redispatch will be allocated based upon the methods specified
in Sections 40.3.5.8 and 40.3.6.6 of this Tariff.
Payments relating to Manual Redispatch may be directly assigned to an individual Transmission
Customer(s), or a Market Participant(s) owning any Generation Resource(s), Demand Response
Resource(s)-Type II, or Electric Storage Resource(s), where circumstances conclusively
demonstrate that the action or inaction of one or more such Transmission Customer(s) or Market
Participant(s), in violation of a Transmission Provider directive and in contravention of Good
Utility Practices, proximately caused the circumstances necessitating Manual Redispatch,
provided that, prior to any such direct assignment of costs, the Transmission Provider must
receive approval from the Commission pursuant to a filing under Section 205 of the Federal
Power Act. The cost allocation set forth in the preceding paragraph shall not apply to any costs
directly assigned hereunder.
MISO 33.8.4
FERC Electric Tariff Notice and Posting
MODULES 31.0.0
Effective On: December 31, 9998
The Transmission Provider will notify the appropriate Local Balancing Authority(ies)
and Market Participant(s) and provide the appropriate Generation Resource(s), Demand
Response Resource(s)-Type II, or Electric Storage Resource(s) with Manual Redispatch
instructions to return the Transmission System within operating limits. Such notice will specify
the nature of the occurrence giving rise to the need for the Manual Redispatch instruction, the
times at which the Manual Redispatch is to commence and cease, and the MW level at which the
Generation Resource, Demand Response Resource(s)-Type II, or Electric Storage Resource shall
operate during the period of Manual Redispatch. Each time a Generation Resource, Demand
Response Resource(s)-Type II, or Electric Storage Resource is manually redispatched, the
Transmission Provider shall promptly post afterwards on its OASIS the existence and nature of
the conditions requiring the Manual Redispatch and the period of time that the Generation
Resource, Demand Response Resource(s)-Type II, or Electric Storage Resource was manually
redispatched. When the Transmission Provider directly assigns Incremental Energy Costs
pursuant to Section 33.8.3 above and with appropriate Commission approval, the Transmission
Provider shall post on its OASIS the entity being directly allocated Incremental Energy Costs
associated with Manual Redispatch of a Generation Resource, Demand Response Resource(s)-
Type II, or Electric Storage Resource.
MISO 34
FERC Electric Tariff Rates and Charges
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall pay the Transmission Provider for any Direct Assignment
Facilities, Ancillary Services, and applicable study costs, consistent with Commission
policy, along with the following:
MISO 34.1
FERC Electric Tariff Monthly Demand Charge
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer, shall pay a monthly demand charge pursuant to
the applicable Schedule 9 which reflects its Load Ratio Share calculated on a
calendar year basis. The charge will be calculated by multiplying the
Transmission Customer’s monthly Network Load determined in accordance with
Module B, Section 34.2 by the applicable firm monthly zonal rate except for
Transmission Customer’s taking service pursuant to the provisions specified
under Schedule 9 – ATC.
MISO 34.2
FERC Electric Tariff Determination of Network Customer’s Monthly Network Load
MODULES 33.0.0
Effective On: December 31, 9998
A Network Customer’s monthly Network Load is its hourly Load (60 minute, Hour);
provided, however, the Network Customer’s monthly Network Load will be its hourly Load
coincident with the monthly peak of the pricing zone where the Network Customer’s Load is
physically located or as otherwise located as defined in Section 31.3 (b) or (c). A Network
Customer’s monthly Network Load shall exclude any withdrawals of Energy by Electric Storage
Resources while providing Regulating Service or Down Ramp Capability.
Transmission losses refer to the loss of energy during the transmission of electricity from
generation resources to Load, which is dissipated as heat through transformers, transmission
lines, and other transmission facilities that are under the functional control of the Transmission
Provider. When reporting monthly network coincident peak loads to MISO for billing purposes,
load reporting entities will adjust Network Load to account for Transmission losses in
accordance with MISO Business Practice Manual – 012.
MISO 34.3
FERC Electric Tariff [RESERVED]
MODULES 30.0.0
Effective On: November 19, 2013
MISO 34.4
FERC Electric Tariff Redispatch Charge
MODULES 30.0.0
Effective On: November 19, 2013
The Market Participant shall pay redispatch costs for their transactions in
accordance with Module C.
MISO 34.5
FERC Electric Tariff Stranded Cost Recovery
MODULES 30.0.0
Effective On: November 19, 2013
This Tariff, including any ITC Rate Schedule, does not affect in any way
the right of any Transmission Owner or ITC Participant to seek and receive
stranded cost recovery or the right of anyone to oppose such stranded cost
recovery. Thus, the Transmission Owner(s) and ITC Participant(s) may seek to
recover stranded costs from the User(s) in accordance with the terms, conditions
and procedures set forth in FERC Order No. 888. However, the Transmission
Owner(s) and ITC Participant(s) must separately file any specific proposed
stranded cost charge under Section 205 of the Federal Power Act. If the
Commission approves stranded cost charges to be recovered through schedules to
be implemented by the Transmission Provider and ITC, the Transmission
Provider and ITC, as agreed, shall charge and collect the appropriate charge(s)
from the relevant User(s) and distribute the appropriate amounts directly to the
relevant Transmission Owner(s) and ITC Participant(s).
MISO 34.6
FERC Electric Tariff ISO Costs
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall pay ISO costs in accordance with Schedule
10 or, where applicable, ITC costs pursuant to the ITC Rate Schedule.
MISO 35
FERC Electric Tariff Operating Arrangements
MODULES 30.0.0
Effective On: November 19, 2013
MISO 35.1
FERC Electric Tariff Operation Under The Network Operating Agreement
MODULES 30.0.0
Effective On: November 19, 2013
The Network Customer shall plan, construct, operate and maintain its
facilities in accordance with Good Utility Practice and in conformance with the
Network Operating Agreement, or, if applicable, the ITC transmission operating
requirements specified in the ITC Rate Schedule.
MISO 35.2
FERC Electric Tariff Network Operating Agreement
MODULES 30.0.0
Effective On: November 19, 2013
The terms and conditions under which the Network Customer shall
operate its facilities and the technical and operational matters associated with the
implementation of Module B of the Tariff shall be specified in the Network
Operating Agreement. For ITC, the ITC transmission operating requirements as
specified in the ITC Rate Schedule shall apply. The Network Operating
Agreement shall provide for the Parties, including the affected Transmission
Owner(s), to (i) operate and maintain equipment necessary for integrating the
Network Customer within the Transmission System (including, but not limited to,
remote terminal units, metering, communications equipment and relaying
equipment),
(ii) transfer data between the Transmission Provider and the Network
Customer (including, but not limited to, heat rates and operational characteristics
of Network Resources, generation schedules for units outside the Transmission
System, Interchange Schedules, unit outputs for redispatch required under Section
33, voltage schedules, loss factors and other real time data), (iii) use software
programs required for data links and constraint dispatching, (iv) exchange data on
Load Forecasts and Resources necessary for long-term planning, and (v) address
any other technical and operational considerations required for implementation of
Module B of this Tariff, including scheduling protocols.
The Network Operating Agreement will recognize that the Network
Customer shall either (i) operate as a Local Balancing Authority Area under the
Applicable Reliability Standard, (ii) satisfy its Local Balancing Authority Area
MISO 35.2
FERC Electric Tariff Network Operating Agreement
MODULES 30.0.0
Effective On: November 19, 2013
requirements, including all necessary Operating Reserve and Other Ancillary
Services, by contracting with the Transmission Provider and/or participating in
the Energy and Operating Reserve Markets, or (iii) satisfy its Local Balancing
Authority Area requirements, including all necessary Operating Reserves and
Other Ancillary Services by contracting with another entity, consistent with Good
Utility Practice, which satisfies the Applicable Reliability Standard. The
Transmission Provider shall not unreasonably refuse to accept contractual
arrangements with another entity for Operating Reserves or Other Ancillary
Services; provided however, that any Operating Reserve not purchased from the
Energy and Operating Reserve Markets shall be self-scheduled through that
market consistent with the terms of Module C. The Network Operating
Agreement is included in Attachment G.
MISO 35.3
FERC Electric Tariff [RESERVED]
MODULES 30.0.0
Effective On: November 19, 2013
MISO 36
FERC Electric Tariff Scheduling
MODULES 30.0.0
Effective On: November 19, 2013
Each Network Customer and/or Market Participant shall submit an Interchange Schedule
daily for flows consistent with the times for Energy scheduling for Firm Point-To-Point
Transmission Service shown on Attachment J and the applicable scheduling provisions
set forth in Module C when the associated Transmission Service Request is an
Interchange Transaction.
MISO IV
FERC Electric Tariff APPLICABILITY TO ALL LOAD
MODULES 30.0.0
Effective On: November 19, 2013
MISO 37
FERC Electric Tariff Applicability
MODULES 30.0.0
Effective On: November 19, 2013
MISO 37.1
FERC Electric Tariff Applicability to Transmission Owner Load
MODULES 30.0.0
Effective On: November 19, 2013
Each Transmission Owner and ITC Participant, to the extent it is a Load
Serving Entity, shall take Network Integration Transmission Service or Point-To-
Point Transmission Service from the Transmission Provider or ITC, as applicable,
in accordance with this Tariff, subject to the limitations in Section 37.3, for (1)
Bundled Load served by a Load Serving Entity; and (2) Load being served at
wholesale under a Grandfathered Agreement. Each Transmission Owner and ITC
Participant that is a Load Serving Entity shall enter into a service agreement(s)
under this Tariff with the Transmission Provider for such Transmission Service.
A Transmission Owner or ITC Participant, making contractual arrangements to
act as agent on behalf of another Transmission Owner(s) or ITC Participant with
Load located in the same pricing zone subject to Grandfathered Agreements, will
be permitted to make arrangements for Network Integration Transmission Service
or Point-To-Point Transmission Service with the Transmission Provider for Load
served by the other Transmission Owner(s) or ITC Participant.
MISO 37.2
FERC Electric Tariff Applicability to Other Load Serving Entities
MODULES 30.0.0
Effective On: November 19, 2013
All other Load Serving Entities not covered under Section 37.1 shall take Network Integration
Transmission Service or Point-To-Point Transmission Service from the Transmission Provider in
accordance with this Tariff and shall enter into a service agreement(s) under this Tariff with the
Transmission Provider for such Transmission Service Any Load Serving Entity serving Load in
the Real-Time Energy and Operating Reserve that is found to have exceeded its capacity
reservations under Sections 13.7, 14.5, 27A.1.6 and/or 27A.2.4 shall pay unreserved use
penalties in accordance with Sections 13.7, 14.5, 27A.1.6 and/or 27A.2.4 as applicable.
MISO 37.3
FERC Electric Tariff Limitations on Charges and Cost Responsibilities
MODULES 32.0.0
Effective On: March 1, 2015
a. Bundled Load: Transmission Owners and ITC Participants taking
Network Integration Transmission Service to serve their Bundled
Load shall not pay charges pursuant to Schedules 1, 3 through 6
and Schedule 9. After the Transition Period ends, beginning
February 1, 2008, the total Schedule 9 revenues to be distributed to
Transmission Owners and ITC Participants under the ISO
Agreement shall include the Schedule 9 charges that would be
payable by any Transmission Owners and ITC Participants covered
by the above exclusion or by a similar exclusion in a Service
Agreement with the Transmission Provider (“imputed revenues”).
In distributing Schedule 9 revenues to Transmission Owners and
ITC Participants, the Transmission Provider shall deduct the
imputed revenues attributed to each such Transmission Owner and
ITC Participant from the total Schedule 9 revenues that are due to
that Transmission Owner or ITC Participant. Notwithstanding the
first sentence of this section, Ameren Service Company, acting as a
Transmission Customer taking Transmission Service to serve
Ameren Energy, Inc., as agent for and on behalf of Union Electric
Company (d/b/a AmerenUE and Ameren Energy Generating
Company), for serving their Bundled Load in the State of Missouri
shall not pay charges pursuant to Schedule 2.1
MISO 37.3
FERC Electric Tariff Limitations on Charges and Cost Responsibilities
MODULES 32.0.0
Effective On: March 1, 2015
The Market Participant shall be financially responsible for
payment of the Marginal Congestion Component of Ex Post LMP
and Marginal Loss Component of Ex Post LMP related to their
transactions as specified in Sections 39.2.9, 39.3.3.c, 40.2.11, and
40.4.1 for those Transmission Owners and ITC Participants taking
Network Integration Service to serve their Bundled Load.
Notwithstanding the foregoing in this Section 37.3.a, the following
rules apply in instances in which there are multiple Transmission
Owners within a pricing zone or Local Balancing Authority Area.
Specifically, a Transmission Owner located in a pricing zone or
Local Balancing Authority Area with one or more other
Transmission Owners shall remain obligated to pay for
Transmission and/or Other Ancillary Services it receives within
that pricing zone or Local Balancing Authority Area that it does
not provide itself unless the transmission and/or ancillary services
are provided pursuant to a Grandfathered Agreement. Any
disputes as to the amount to be paid, or the services to be provided
or received shall be resolved through the ADR process set forth in
Section 12 of this Tariff.
b. Grandfathered Agreements for Load Inside of the ISO: For the
Transmission Service provided as a result of or pursuant to
Grandfathered Agreements for Load inside of the ISO, each GFA
MISO 37.3
FERC Electric Tariff Limitations on Charges and Cost Responsibilities
MODULES 32.0.0
Effective On: March 1, 2015
Responsible Entity which is a party to that Grandfathered
Agreement shall not be obligated to pay charges under Schedules 1
through 9, but it shall be responsible for Transmission Usage
Charges as specified in Sections 40.2.11 and 40.4.1. Each GFA
Responsible Entity shall remain responsible for payment of the
applicable Schedule 10 charges for the services taken pursuant to
Section 37.1 for its Load, which may include wholesale Loads
under Grandfathered Agreements.
c. Grandfathered Agreements for Load Outside of the ISO: For
the Transmission Service provided as a result of or pursuant to
Grandfathered Agreements for Load outside of the ISO, the GFA
Responsible Entity shall be exempt from rates under this Tariff for
services provided pursuant to the existing agreements, except for
charges under Schedule 10, and the Transmission Usage Charge as
specified in Sections 40.2.11 and 40.4.1 to the Interface at the
boundary of the Transmission System.
d. Exception to Section 37.3 (b) and (c): Notwithstanding the
provisions of Section 37.3(b) and (c), (i) if ancillary services are
not taken or provided under the Grandfathered Agreement, in
whole or in part, then such Ancillary Services which are not
provided under such Grandfathered Agreement shall be provided
and charged for under this Tariff; and (ii) if Marginal Losses are
MISO 37.3
FERC Electric Tariff Limitations on Charges and Cost Responsibilities
MODULES 32.0.0
Effective On: March 1, 2015
not provided or paid for under the Grandfathered Agreement, then
the Market Participant will be financially responsible for the
charges attributable to Marginal Losses as assessed for these
related transactions in accordance with the provisions of
Module C, Sections 39.3.1, 39.3.3, 40.3 and 40.5.
e. Imputed Revenues Associated with Grandfathered
Agreements. After the Transition Period ends, beginning
February 1, 2008, the total Schedule 7, 8, and 9 revenues to be
distributed to Transmission Owners and ITC Participants under the
ISO Agreement shall include the Schedule 7, 8, and 9 charges that
would otherwise be payable by any GFA Responsible Entity
covered by the exclusions in Section 37.3(b) or Section 37.3(c)
(“GFA imputed revenues”), provided, however, that GFA imputed
revenues shall not include any Schedule 7, 8, and 9 charges
associated with a Grandfathered Agreement with respect to which
the revenues are reflected as a credit in the calculation of the
Transmission Owner’s or ITC Participant’s revenue requirement
pursuant to Attachment O. In distributing Schedule 7, 8, and 9
revenues to those Transmission Owners and ITC Participants, the
Transmission Provider shall deduct the GFA imputed revenues
attributed to each such Transmission Owner or ITC Participant
MISO 37.3
FERC Electric Tariff Limitations on Charges and Cost Responsibilities
MODULES 32.0.0
Effective On: March 1, 2015
from the total Schedule 7, 8, and 9 revenues that are due to that
Transmission Owner or ITC Participant.
1 Midwest Independent Transmission System Operator, Inc., 106 FERC ¶ 61,293
(2004).
MISO 37.4
FERC Electric Tariff Grandfathered Agreements
MODULES 30.0.0
Effective On: November 19, 2013
Transmission provided pursuant to Grandfathered Agreements shall
continue according to their terms. The Grandfathered Agreements are listed in
Attachment P.