Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3....

27

Transcript of Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3....

Page 1: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …
Page 2: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 1

MINUTES OF THE SPECIAL MEETING WITH KPTCL ON PENDING ISSUES

1. INTRODUCTION

A Special Meeting with KPTCL on pending issues was held at SRPC, Bengaluru on 17th June 2016.

The list of participants is given at Annexure-I.

Sri S.R.Bhat, Member Secretary, SRPC welcomed all the participants to the Meeting. He informed

that it was very heartening to note that A/R feature had been implemented recently in Chikkodi –

Talangde line. He stated that this meeting had been necessitated keeping in view time constraints

experienced in the OCC Meetings. Certain issues involved regulatory compliance, technical

requirements etc and it would thus be apt to take stock of the situation and identify the way forward

to rectify the issues.

2. LOW VOLTAGES

A Meeting with SLDCs/system study groups to discuss the low voltage and an ATC/TTC issue was

held at SRPC on 26.04.2016 and many recommendations/action points had been finalized. The

Minutes of the Meeting are available at SRPC website. The following had been highlighted:

Physical Regulatory Procedure as enumerated was agreed for implementation. Step 4 was a

critical step and thus SLDCs needed to take action to avoid any situation which would compel

SRLDC to take such step.

In case Specific instructions for opening 220/230 kV and below lines were not adhered by

SLDCs it would be deemed as violation of provisions of IEGC/EA 2003.

SLDCs to take action proactively by observing falling trend/pattern of voltages even before

receipt of SRLDC messages. SLDCs to also furnish the physical regulatory measures to be

taken up at low voltage nodes in their system. It was felt that physical regulatory measures at

220 kV and below would give optimum results than physical regulatory measures by SRLDC.

SRLDC real time messages/instructions to be adhered within 15 minutes of issuance and the

action taken report should be furnished within 30 minutes.

As a drive, faulty capacitor banks to be rectified immediately.

Chairperson, SRPC would be kindly requested to take up the issue with the concerned since it

was threat to system integrity.

Constituents were requested to revert back on utilization (operational/commercial limitations &

possibilities) of reactive support from wind/solar units even when they are not generating.

States to furnish data of load management actions taken to overcome low voltage conditions.

Deliberations in the Meeting

SRLDC pointed out that on many instances the voltage profile around Bangalore remained

critically low (ie. below 380kV) and MVAR drawal was 800 MVAR to 1300 MVAR. Even during

such instances, SRLDC instructions for opening specific lines had not been complied. This

amounts to non-compliance of SRLDC’s directions and violation of Grid Code.

KPTCL pointed out that though specific lines may not have been opened, but downstream lines

were opened. Low voltage issues were more in the month of February and March 2016 due to

reconfiguration of loads necessitated due to fire accident in Sharavathi.

Page 3: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 2

SRLDC clarified that low voltage (high MVAR drawal) was due to the loads in Bengaluru area and

MVAR drawal in & around Bangalore. Sharavathi generation does not support Bengaluru in

reactive energy and thereby non-availability of Sharavathi generation could not significantly

attributed for low voltage scenario at Somanahalli, etc.

It was noted that BESCOM needs to be appraised of the high MVAR drawal and low voltages.

Reactive support both by KPTCL and BESCOM are required to address this issue

comprehensively.

Over loading of lines, weak sub transmission system, no generator in Bengaluru area for reactive

support, inadequate reactive support at transmission and distribution levels were the major causes

for high MVAR drawal and low voltages. This could seriously hamper drawal capability of

Bengaluru area unless concrete steps are taken now.

Recommendations finalized

Real time messages/instructions of SRLDC to be adhered within 15 minutes of issuance and

action taken report should be furnished within 30 minutes.

Retrofitting of Somanahalli and Hoody Capacitor Bank of 30 MVAR each to be expedited. KPTCL

to furnish the action plan within 2 weeks.

Faulty Capacitor Banks to be rectified in Bengaluru adjoining areas of KPTCL system. KPTCL to

furnish the details of faulty capacitor banks and action plan for rectification within 2 weeks.

KPTCL /SLDC would call for a meeting with BESCOM with participation at appropriate level

within 2 weeks and following issues would be taken up:

Special drive on rectifying the faulty capacitors in BESCOM in a time bound manner with

the details of status of capacitor banks.

Tap optimization in the distribution transformers of BESCOM (to reduce drawal of VAR)

Study of additional capacitor requirements. This needs to be taken up by BESCOM on

urgent basis.

Discom wise or location wise limitation on MW drawal due to low voltages and high

MVAR drawal.

Extending scope of maintaining power factor by other consumers (presently being limited

to HT Consumers).

BESCOM to identify feeders for Physical Regulatory Procedure based on the MVAR

drawal by the respective feeders

Senior Managements of KPTCL and BESCOM to be appraised that MW drawal capacity had

reached saturation and could be curtailed unless voltage profile is improved and also if sub--

transmission system is not strengthened on war footing basis. Future increase in loads and even

share from Yeramarus, Bellary, LTA etc., would be difficult to meet keeping in view the voltage

profile.

SLDC could envisage taking up the issue with Hon’ble KERC to ensure that BESCOM takes

appropriate steps to improve the voltage profile.

A Task Force could be set up on urgent basis to identifying the issues (Low voltages, high MVAR

drawal, strengthening of transmission & distribution system, drawal capability of Bengaluru area ,

reactive requirement at DISCOMs etc) and to finalize the action plan to resolve these issues in a

time bound manner.

Page 4: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 3

3. UV RELAYS

In the Special Meeting held on 26.04.20116, KPTCL had informed that the UV relay scheme had not

been implemented.The following locations and logics for UVR had been finalized the meeting:

KPTCL: (@ Nelamangala, Somanahalli, Hoody and Bidadi)

Stage 1: When voltage < 380 kV for 10 minutes then the identified loads has to be

disconnected.

Stage 2: When voltage < 370 kV for 5 minutes then at least 25% of additional ICT load has

to be disconnected.

In the 120thOCCM, KPTCL had informed that only for 25 MW automated scheme had been

implemented. Subsequently through manual action the voltages were being controlled. Following

were instances of logic being satisfied during the month of May 2016.

Station No of Times V<380kV for> 10

minutes

Neelamangala 2

Bidadi 2

Somanahalli 20

Recommendations finalized

KPTCL agreed to implement automated scheme of 25 MW each at intervals of 3 minutes, 6

minutes, 9 minutes and 12 minutes (Total 100 MW) whenever the voltage remained below 380

kV at Somanahalli by June 2016. Second stage of automated stage would get triggered at 371

kV after 3 minutes for 50 MW and at 370 kV after 3 minutes for another 50 MW. The second

stage would be implemented by June 2016.

KPTCL agreed to implement automated schemes of UV at Nelamangala, Hoody and Bidadi in

two stages by July 2016 end. The scheme would be finalized in the meeting with BESCOM.

4. SHUNT CAPACITORS REQUIREMENT

In the Special Meeting held on 26.04.2016, based on SRLDCStudy, the following Capacitor

requirement had been arrived as given below:

Sub-Station Capacitor –

Requirement in MVAR

Constituent wise

requirement

Nelamangala 160 Karnataka-505 MVAR

Hoody 185

Somanahalli 160

Deliberations in the Meeting

Page 5: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 4

KPTCL informed that 708.8 MW of Capacitors were being tendered for Bengaluru Transmission

Zone and this was in excess of the requirement of SRLDC of 505 MVAR.

It was requested to expedite the tendering process and ensure installation &

commissioning before Dec’16. It was clarified that 505 MVAR had been worked out for

the March 2016 condition and KPTCL needed to work out the requirement for upcoming

years (considering load growth, power tie ups etc). Accordingly, the present tender may

have a provision for repeat order for additional quantity so as to avoid further tendering

time.

5. DATA FOR TAP OPTIMIZATION

SRLDC informed that Data for Tap optimization had not been furnished by Karnataka SLDC.

SLDC agreed to furnish the requisite details within a week’s time.

6. REACTOR STATUS

Deliberations in the Meeting

KPTCL informed that reactors at Nelamangala and Hoody had been received at site. The

Nelamangala reactor had been erected and is likely to be commissioned by August 2016

end. Hoody reactor may take another six months.

KPTCL was requested to kindly initiate steps for taking up works of Davanagere and

Talguppa reactors as finalized in the 39thMeeting of Standing Committee.

7. REACTIVE POWER PLANNING

In the 4th NPC Meeting held on 10.12.2015 (MoM dated 01.01.2016), the following had been noted:

All States to carry out reactive power planning not only at transmission level but also at

distribution level and prepare schemes to maintain voltage profile as per relevant

Regulations / Standards.

NPC agreed that states should adopt a proactive approach in the matter of reactive power

Entity Bus Name Status REMARKS

KPTCL

Hoody By December 2016 As identified in the 22nd

Standing Committee Meeting on Power System Planning of SR and as approved in the 4

th SRPC Meeting

held on 7th

June 2007

Nelamangala

By August 2016

Davangere

125 MVAR

39th

SC

Talguppa

125 MVAR

39th

SC

Page 6: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 5

planning, and that the provisions regarding reactive power planning similar to those

mandated in the IEGC for the CTU should be included in the respective State Grid codes. It

had beendecided that RPCs would follow up the matter further with states.

Deliberations in the Meeting

Utility Reactive power Planning Voltage

Level

Remarks

Karnataka

(Total 1544

MVAR

Planned)

Bengaluru Tr. Zone:708.8 MVAR 12.1 Retendered on 19.05.2016. PO likely in July 2016. Commissioned by Aug 2017

Bagalkot Tr. Zone :258.1 MVAR

12.1 39 Capacitor Bank supplied- to be erected. 35 nos/ 15 nos inspection raised/ to be raised.11 KV switchgear placed on M/s MEI – delivery from last week of July 2016

Hassan Tr. Zone :136.3 MVAR

12.1 13 Capacitor Bank supplied- to be erected. 16 nos partially supplied. Balance 11 Nos to be supplied. 7 nos Capacitor cell installed. Foundation completed 22 nos.

Mysore Tr. Zone :60.9 MVAR

12.1 All 21 nos (2.9 MVAR) Capacitor Bank supplied. 11 KV switchgear placed on M/s MEI on 28.01.2016 18 Nos Capacitor Banks & 18 Nos DP Structure started

Gulbarga Tr. Zone :98.60 MVAR

12.1 17 nos (2.9 MVAR) Capacitor Bank supplied. 17 Nos to be supplied.

Tumkur Tr. Zone :281.3 MVAR 12.1

KPTCL took note of the deliberations of 4th NPC Meeting.

KPTCL was suggested to take up reactive power planning of BESCOM and other

Discoms as STU regularly.

KPTCL informed that since earlier quote was high, Bengaluru zone Capacitors had been

retendered in May 2016. PO could be placed in July 2016 with likely schedule of

commissioning in August 2017.

For other five transmission zones, the PO has been placed and was moving ahead as

per schedule.

8. SCADA/COMMUNICATION

8.1. OPGW stringing works on the following KPTCL lines was pending to be completed:

Hoody - LILO point of Hoody – Nelamangala

Hoody – HSR

Hoody – HAL

NRS – Peenya- Hebbal

Hassan – Shantigram

Page 7: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 6

MS, SRPC letter dated 13.06.2016 to MD, KPTCL is at Annexure-II.

Deliberations in the Meeting

CE(LD), KPTCL informed that the issue would be resolved by 20/21.6.2016.

MS, SRPC stated that the issue was needed to be resolved at the earliest in the common

interest of SR grid.

PGCIL stated that they would expedite the balance works.

8.2. VC facility from SLDC to SRLDC

PGCIL informed that end equipment had been supplied to SLDC. OFC terminations would be

made through at SLDC and SRLDC in couple of days.

It was agreed that the VC facility would be tested on 27.6.2016 and PGCIL & SLDC were

requested to complete the works.

8.3. Reporting of Non-availability/intermittency of SCADA Data

SRLDC pointed that non-availability / intermittency of SCADA data (Analog and Digital) for the

State Control Area was required to be furnished by SLDCs to SRLDC. NLDC would consolidate

status for the entire country and communicate it to Hon’ble CERC. As agreed in the 120th CC

meeting, they would be furnishing the format and the guidelines for furnishing this data.

SLDC agreed to furnish the details in time bound manner.

9. AUTO RECLOSE

KPTCL informed that A/R feature for Chikkodi –Talagande line had been commissioned. A/R on

Chikkodi - Mudshingi would be commissioned within two to three days.

Regarding Ambewadi - Ponda, KPTCL informed that R&M works were going on for this line and

A/R would be covered in R&M works. In the Meeting, KPTCL informed that there were some

contractor issues and the works were being assigned to M/s Alstom and it may take some time.

Regarding Kaiga - Guttur, KPTCL informed that they were ready to enable the A/R at Guttur end

and once Kaiga agrees, they would enable the A/R.

Regarding lines from Nagjhari, KPTCL would enable the A/R once KPCL is ready. KPCL had

earlier informed that they would be ready by July 2016.

10. UFR & DF/DT RELIEF

For the period 16.05.2016 to 31.05.2016, the following was the relief available vs relief expected:

Expected Relief

as per SRPC

Monitoring Relief Max Min Avg

3539 3557 3090 1491 2454

87 % 42 % 69 %

KPTCL agreed to improve the average relief by September 2016.

Page 8: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 7

11. OUTAGE COORDINATION

As per the Outage Procedure, utilities are to submit the S/D proposals for the subsequent month by

3rd

of the current month. Non-availing the OCC approved shut down was a matter of concern.

Percentage of non-availed shut downs of ICTs and lines (common outages not considered) is given

below:

Approved Availed Non Availed Availed %

May 16 13 6 7 46

Apr 16 5 0 5 0

Mar-16 11 1 10 9

Feb-16 5 0 5 0

Jan-16 5 0 5 0

Deliberations in the Meeting

SRPC pointed that shut down requests were not being received in time. Many times shut down

proposals for the current month were being requested which needs to be avoided.

SRPC/SRLDC also expressed concern over non-availing of planned shut downs. Reasons for

non-availing the shut downs was also not being furnished. Better planning and execution was

required by all utilities of SR. Number of shut downs were also being taken on emergency.

SLDC agreed to look into the issues and improve the availing percentage and agreed to furnish

the shut down proposals in a timely manner.

12. TRANSFER CAPABILITY DETERMINATION BY STATES

As per 4th NPC Meeting, all states were required to compute monthly ATC/TTC limits for their control

area. Monthly TTC/ATC would be uploaded by SLDCs in their respective websites and also

communicated to concerned RLDC & NLDC subsequently. A workshop had been conducted on

ATC/TTC computations was held on31st March and 1

st April 2016. However, no official from KPTCL,

LD had attended. Dedicated Reliability Group (Study Group) at SLDC was very much required.

Deliberations in the Meeting

SRLDC/SRPC pointed out that dedicated Reliability Group was essential at SLDC to carry out

ATC/TTC computations for the Control Area, day to day contingency analysis, Outage

coordination, PoC computations, Reactive power in STU/DISCOMs/embedded generators etc. It

would be useful in providing operational feedback to STU/CTU/CEA, feedback would be useful in

Planning Process.

Page 9: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 8

SLDC pointed about manpower crunch to take up these activities.

It was suggested that SLDC could take up this issue with Management. SRPC/SRLDC stated that

the Higher Management would once again be apprised of the importance of dedicated reliability

Group.

13. REASONS FOR DEMAND -SUPPLY GAP AND ITS VARIATION

This issue of furnishing the load shedding details in different heads along with the reasons by states

had been taken up in the NPC Meetings. MoP/CEA specifically needed reasons for load shedding like

transmission constraints, distribution constraints, and regulatory constraints viz the power purchase

not allowed beyond an agreed cost or quantum, natural calamities, tripping of some of major

transmission lines etc.

Deliberations in the Meeting

SRPC pointed out that reasons of load shedding under various heads as elaborated above were

required by MoP/CEA. The requirement was informed in earlier OCC Meetings but information in

requisite format was not forthcoming. The exact reason for deficit was to be elicited.

SLDC agreed to furnish the details as required.

14. PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS

In recent times, insulator tracking has been observed in Transmission lines and Substations located

in the coastal and polluted areas. It is pertinent that Patrolling and Maintenance needs to be carried

out for the critical lines as per Patrolling Guidelines. It is also imperative that switchyards of the

generators located in coastal areas need to be maintained stringently. SRPC vide letter dated

05.05.2016 had communicated to the concerned in this regard. Following lines require special

attention and patrolling and maintenance schedule/carried out needs to be furnished regularly:

400 kV Kaiga-Guttur D/C 400 kV Guttur-JSWEL S/C

400 KV Guttur-HiriyurS/C

400 kV Hiriyur- Nelmanagala 400 kV BTPS- JSWEL S/C 400 kV RTPS-BTPS S/C

400 kV UPClL-Hassan D/C

220 kV Nagjhari- Kodasalli D/C

220 kV Nagjhari- Ambewadi D/C

220 kV Nagjhari- Hubli D/C 220 kV Nagjhari- Bidna/Hublil D/C

220 kV Kadakola-Kanianmpetta S/C

Deliberations in the Meeting

SRLDC/SRPC highlighted significance of timely Patrolling/Maintenance. The Patrolling

Guidelines were required to be followed. This was evident from recent disturbance at Gazuwaka,

Tuticorin, Vallur, Outages in Western Ghats in Karnataka (Kaiga, Nagjhari, Sharavathy, UPCL)

etc. Important elements in Karnataka Control Area which require specific attention had been

brought out and details as sought were required to be furnished.

KPTCL agreed to pass on specific instructions to the field for periodical Patrolling/Maintenance

and regular updates would be furnished. KPTCL will furnish advance maintenance schedule for

the above elementsand appraise the deviation details, if any, in every OCC Meeting.

Page 10: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 9

15. RESTRICTED GOVERNOR MODE OF OPERATION (RGMO)/FGMO OF GENERATING UNITS

15.1 RGMO response was being analyzed in the OCC meetings and inadequate response was an

area of concern and there was no noticeable improvement. SLDCs were to analyze RGMO

instances posted by SRLDC for generators in their control area and initiate suitable action

as per orders in respect of 84/MP/2015. Inadequate Response was to be taken up with

SERC (Petition No.302/MP/2013).

15.2 SLDCs/RLDCs to analyse response of generators during major frequency excursions and submit

report on quarterly basis to SERCs and POSOCO. The following also needed to be taken

note of

Oil support, if required, for grid security needs to be resorted

Taking out RGMO/FGMO, without informing SLDC/SRLDC may be liable to action under

Section 142 of Act.

Units should not be allowed to operate with their valves wide open and ensure RGMO

performance at all levels of generation.

Any willful locking of the Governors, poor and reverse response, introduction of more than

mandated dead band or any other activity to curtail the primary response, will be viewed

seriously and action under Section 142 of Act shall be taken against such generators for

non-compliance of the provisions of the Grid Code

15.3 RLDCs/SLDCs have inherent powers to restrict schedule corresponding to 100% of installed

capacity without wide valve open condition, even at part loads ensuring primary governor

response at all stages. It was reiterated that unit should not be scheduled beyond 100% of MCR

rating. In view of CERC Order w.r.t Petition No.302/MP/2013, SLDCs need to restrict the state

generators schedule suitably.

15.4 RGMO status of State generating station to SRLDC through ICCP for RTPS, UPCL and JSWEL

not mapped.

Deliberations in the Meeting

SRLDC/SRPC informed that TSSLDC had taken up the non-performance of embedded

generators with their SERC. IEGC and CERC Orders provides for significant steps to be taken by

SLDC in achieving RGMO compliance.

SLDC, KPTCL shall ensure mapping of RGMO status of all eligible generating units in the state

within this month.

SLDC KPTCL will initiate action for appraising on past performance of RGMO of Generating units

in the state to KERC. Also will ensure RGMO performance analysis of future instances and take

suitable action as required.

Page 11: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 10

16. LOW VOLTAGE RIDE THROUGH (LVRT)/PROVISIONS OF CEA REGULATIONS IN RESPECT OF

RENEWABLES

The 3rd

meeting ha been scheduled for 5th July 2016 in Chennai. Nodal officer nomination was

pending from SLDC. Information sought as per Format A& B has not been furnished. There

was on reported update on other issues also.

Deliberations in the Meeting

SLDC agreed to furnish the Nodal Officers details within a weeks’ time. Details sought as per

Format A& B were being compiled in discussion with Wind Developers.

SRPC/SRLDC pointed out that there were number of actionable points to be taken to comply

CERC Order and as finalized in the two special meetings and requested KPTCL to take concrete

steps. Participation of SLDC in 3rd

meeting at Chennai was vital. Ensuring strict implementation

of LVRT feature and other CEA/CERC requirements in all upcoming / newly getting connected

Wind / Solar generators was to followed diligently. Same may be certified while furnishing the

monthly RE generation addition report.

KPTCL informed that they were ensuring LVRT provision and only temporary connectivity was

being granted along-with some penal clauses. Subsequently, after meeting technical specification

specified, permanent connectivity was granted. SRLDC/SRPC suggested for ensuing all the

technical requirements before issuing any type of connectivity.

17. DEMAND ESTIMATION FOR OPERATIONAL PURPOSE (CLAUSE 5.3 OF IEGC)

Each SLDC was to create a mechanism and facilities to facilitate on-line demand estimation of

demandfor daily operational purpose for each 15 minutes block by 01.01.2011. It was required for

Ancillary Services (AS4), RSD/TM schedules etc also.

Deliberations in the Meeting

SRLDC/SRPC enumerated the need for the Requirement and Availability forecast, which was

also a Regulatory requirement.

SLDC agreed to further streamline the process with immediate effect

18. SPS LOADS FOR KKNPP UNIT II

174 MW of loads to be identified and implemented.

Deliberations in the Meeting

KPTCL informed that they had identified the loads in Hassan area and exact details would be

furnished.

PGCIL stated that they would coordinate with the state utilities for extension of the signal to the

STUs.

Synchronisation of KKNP # 2 is expected by July’16 and thereby KPTCL& PGCIL shall ensure

implementation of SPS well on time.

19. INSTANTANEOUS SCHEME FOR SUDDEN WITHDRAWAL OF WIND

Page 12: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 11

Like Tamil Nadu, KPTCL also needs to firm up a scheme for sudden withdrawal of Wind generation.

Deliberations in the Meeting

SRLDC /SRPC explained need for Instantaneous Scheme to take care of sudden withdrawal of

wind generation and it assumed significance as Karnataka was having around 3,000 MW of wind

generation. KPTCL need to focus on Substations having maximum ingress of wind generation.

KPTCL informed that a Consultant has been selected to look into various aspects of

Wind/Renewable integration. They would endeavor to include this aspect if already not covered in

the scope and would come with a scheme. KPTCL will revert back with the details of action /

status by next month

20. PHASE-I & PHASE-II ACTIVITIES IDENTIFIED IN PROTECTION AUDIT

Phase- I& Phase-II activities identified in Protection Audit need to be completed in a time bound

manner. As per Order dated 18.08.2015 on Petition No. 374/MP/2014 extension up to 15.01.2016

had been allowed. KPTCL filed a separate application before CERC on 07.01.2016 seeking time

extension up to 31.05.2017, and the same is under consideration by CERC.

Deliberations in the Meeting

KPTCL informed that LOI had been placed on M/s Alstom after necessary approvals for PSDF

funding with the completion schedule of March 2017. The Tripartite agreement has been signed

by MD, KPTCL and has been put up to Energy Department, GoK for necessary signatures.

Extension from Hon’ble CERC upto May 2017 was awaited.

21. UPDATE ON ACTIONABLE POINTS IN RESPECT OF BMRCL

To expedite on actionable points of KPTCL/BMRCL which were finalized in the special meeting: Report of BMRCL on 17

th& 21

st December 2015 incidents

Relays and settings at BMRCL needed to be reviewed, tested and verified

Welcast SS connectivity to Yelhanka SS

Mock Blackstart Exercise at BMRCL and through KPTCL -quarterly

Deliberations in the Meeting

KPTCL informed that details (Report/relay testing report/mock Blackstart at BMRCL) were yet

to be received from BMRCL. Welcast SS was now being fed from Yelahanka SS.

SRPC/SRLDC observed that SLDC needs to follow up with BMRCL. SLDC agreed for the

same and revert back with status / details.

Page 13: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 12

22. TAP POSITION STATUS

Station Units Present

Tap

Recommend

ed Tap

Remarks

Kadra All units 7 & 225.5 8 & 222.75

Kodasahlli All units 7 & 225.5 8 & 222.75

Sharavathy 9 2 & 231 4 & 220 KPCL informed that tap could not be changed due to technical problems.

UPCL 1 & 2 4 & 409.5 5 & 400 Outage clearance awaited from KPTCL

JSWEL 1,2, 3 & 4 10 & 412 11 & 400 JSWEL agreed for tap change.

SLDC stated they would follow up the recommendations. SRLDC clarified that the tap changing is reviewed

periodically and there by timely implementation is very relevant and requested to SLDC, KPTCL to co-

ordinate accordingly.

23. OVERLOADING OF THE TRANSMISSION ELEMENTS

Line loading on 400 kV Gooty – Nelamangala, Gooty –Somanahalli & Hiriyur-Nelamangala lines

had gone very high failing to satisfy N-1 criteria

N-1 violation of MysoreICTs

Rectification of Hoody ICT and maintenance of healthy spares.

Deliberations in the Meeting

KPTCL informed that the 3rd

ICT at Mysore would come up shortly. One phase (R ph) of 167

MVA capacity of ICT- II (Failed) would come by July 2016 and the ICT was planned to be

restored by August 2016. ICT-I issue of foot insulation have been temporarily taken care, and the

rectification works would be taken up after ICT-II comes back (after monsoon).

SRLDC/SRPC suggested SLDC to take appropriate steps to avoid overloading of the lines and

ICTs as given above. SLDC proactively needs to control the loading and specific instructions by

SRLDC need to complied immediately. Action on maintaining the spares specifically at important

nodes (like Hoody) needs to be given utmost importance.

24. ISSUES TO BE TAKEN UP WITH SERC

24.1. Roadmap to Operationalize Reserves in the Country

Hon’ble CERC vide Order dated 13.10.2015 on Petition No. 11/SM/2015 in the matter of Roadmap

Page 14: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 13

to operationalize Reserves in the country had directed as follows:

(b) The Commission reiterates the need for mandating Primary Reserves as well as Automatic

Generation Control (AGC) for enabling Secondary Reserves.

(i) All generating stations that are regional entities must plan to operationalize AGC along with

reliable telemetry and communication by 1st

April, 2017. This would entail a one-time expense for

the generators to install requisite software and firmware, which could be compensated for.

Communication infrastructure must be planned by the CTU and developed in parallel, in a cost-

effective manner.

(ii) On the other hand, National/Regional/State Load Dispatch Centres (NLDC/RLDCs/SLDCs)

would need technical upgrades as well as operational procedures to be able to send

automated signals to these generators. NLDC /RLDCs and SLDCs should plan to be ready

with requisite software and procedures by the same date.

(iii) The Central Commission advises the State Commissions to issue orders for intra-state

generators in line with this timeline as AGC is essential for reliable operation of India’s large

inter-connected grid.

(c) To start with, a regulated framework in line with the Ancillary Services Regulations would need

be evolved for identification and utilizing of spinning reserves and implemented with effect from 1st

April, 2016. This framework may continue till 31st

March, 2017.

……………

(d) In the long term, however, a market based framework is required for efficient provision of

secondary reserves from all generators across the country. For this, NLDC/POSOCO is directed to

commission a detailed study through a consultant and suggest a proposal to the Commission for

implementation by 1st April, 2017, giving due consideration to the experience gained in the

implementation of Spinning Reserves w.e.f. 1st April, 2016.

24.2. Framework on Scheduling and Imbalance Handling for Variable Renewable Energy Sources (Wind and Solar)

24.3. Compliance of the Central Electricity Authority (Technical Standards for Grid Connectivity) (Amendment) Regulations, 2013 by new generating units being commissioned and getting connected to the grid.

Para 63 of Order in Petition No. 420/MP/2014 66

63. As the Central Electricity Authority (Technical Standards for Grid Connectivity)(Amendment) Regulations, 2013 is applicable for wind generating stations and generating stations using inverters and are connecting at voltage level 66 kV and above to the grid after 15.4.2014. Therefore, all the wind generating stations are directed to comply with the provisions of CEA Technical Standards for Connectivity Regulations. We further direct CTU and STUs to make provisions in this regard in their Connection Agreements to ensure that wind energy generators comply with the provisions of CEA Technical Standards for Connectivity Regulations for grid connectivity before granting connectivity to the grid.

Deliberations in the meeting

KPTCL/SLDC took note of the Regulatory/Technical mandatory requirements.

KPTCL/SLDC informed that Framework on Scheduling and Imbalance Handling for Variable

Renewable Energy Sources has been notified by KERC few days back, which was to be

implemented within 3 months. SRPC/SRLDC requested SLDC to share the highlights in the next

OCCM.

Page 15: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 14

25. UPCOMING TRANSMISSION SYSTEM

Sl.

No

Name of

Transmission

Element

Exe.

Agency Sch. CoD Expected

date

Remarks

1 400 kV Tumkur-

Yelahanka D/C line

PGCIL June 2014 Severe RoW problem.

400 kV Yelahanka S/S is

ready.

2 LILO of 400 kV

Nelamangala –

Hoody at Yelahanka

PGCIL Severe RoW problem.

400 kV Yelahanka S/S is

ready.

3 400 kV Somanahalli –

Dharmapuri D/C

PGCIL 2 months

once ROW

issues are

resolved

DC (Urban) had ordered

compensation of 100 % of

fair value for tower footing

and 55 % for line corridor.

With this, cost of 30 kM

line was working out to as

high as Rs 90 crore.

Hon’ble Power Minister of

Karnataka was scheduled

to make a site visit shortly

to look into compensation

issues etc

3 220 kV Yelahanka

PG- Yelahanka Cable

KPTCL Max Jan

2017

6/7 months’ time (5 kM)

once the award was in

place (max 10 Months)

Meeting Update:

Retendered. Evaluation

under process.

4 400/220 kV Yelahanka S/S – 220 kV BIAL S/S D/C

KPTCL Meeting Update: DPR to

be prepared.

5 220 kV Tumkur –

AntharasanaHalli D/C

KPTCL Sep 2016

Tenders had

been placed

on

18.03.2015

and it would

take 18

months for

completion.

Meeting Update:

Total Locations : 96 Nos

Excavated : 93/96

Stubs concreted : 93/96

Towers erected: 91/96

Stringing : 4.1/18.8 kM

6 400 kV Tumkur S/S –

220 kV Tumkur S/S

D/C

October

2016

Tenders

had been

placed on

Meeting Update:

Total Locations : 209

Nos

Excavated : 146/209

Stubs concreted :

Page 16: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 15

26. Transmission system of KPTCL for evacuation of power from Yermarus TPS (2x800 MW)

18.03.2015

and it would

take 18

months for

completion

146/209

Towers erected: 94/209

Stringing : Nil

Transmission elements Imp. Agency

Line Length (ckm)/ MVA cap.

Sch. COD Constraints/ Remarks

Bellary 400 kV PS near ‘BTPS’

JSWEL (KPTCL)

Jul’16(As informed by JSWEL)

Works under progress

Gulbarga 400/220 kV substation

KPTCL 2x500 Land acquired. Geo tech survey work will be awarded within a week. Bill of Materials prepared and within 15 days estimate will be prepared.

Yermarus TPS - Gulbarga 400 kV D/C line (QM)

KPTCL Detailed survey completed. Estimate is being prepared.

400 kV SS at Chikkanayakanahalli (C.N Halli) near “Loop in Loop Out” (LILO) point on the Nelamangala – Talaguppa 400 kV lines to Hassan.

KPTCL 2x500 MVA

In 39th

SCPSPSR a step down SS with 2 x 500 MVA, 400/220 kV ICTs was agreed.

Land Acquisition is under progress. The proposal is submitted from AC Tiptur to DC Tumkur on 28.03.2016

LILO of both the circuits of Nelamangala – Talaguppa 400 kV lines to the proposed pooling station near CN Halli.

KPTCL Linked with CN Hally station

Termination of 400 kV D/C line feeding 400/220 KV station at Hassan from Nelamangala – Talaguppa line at CN Halli 400 kV pooling station.

KPTCL After CN Halli land identification, survey would be taken up.

Yermarus TPS - Bellary Pooling Station 400 kV D/C line with quad moose conductor

KPTCL 300 (400 kV MC Line (5.138 Kms) and 400 kV DC line (137.355

Aug 2017 (2 years from the award) DPR approved on 26.02.2015. Tendered on 09.03.2015. Techno

Meeting Update:

Total Locations : 399 Nos

Excavated : 209/399

Stubs concreted : 193/399

Towers erected: 14/399

Stringing : Nil

Page 17: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 16

Km) totally for a route length of 142.493 Kms)

Commercial bids opened on 21.05.2015. Price bids opened on 01.07.2015. The works have been awarded in October 2015.

Bellary Pooling Station - C.N.Hally 400 kV D/C line with quad moose conductor

KPTCL 360 Survey using MST conducted and reports submitted to zonal office vide ltr no:1682-83 Dt:30.06.15 and the same is submitted for approval to CEE(P&C) vide ltr.no.2504-06 dt 7.7.2015

To be tendered

Bellary PS to Madhugiri line (765/400kV V.N.pura substation (PGCIL)

a) Madhugiri to Rampura limits): 400kV DC line with Quad Moose ACSR (188.74 Kms)

b) Bellary pooling Stn 400 kV to Rampura limits (KelaginaKanavi): (43.018 Kms)

KPTCL Under Execution by KECIL

By

Kalpataru PTL

380 22-Dec-16 29

th SRPC

March 2017 24-Apr-17 29

th SRPC

March 2017

Out of 512 locations, 470 excavations over, 463 stubs concreted, 445 towers erected &125.9/188.74 km stringing completed Out of 125 locations, 105 excavations over, 96 stubs concreted& 58 towers erected

Bellary TPS – Bellary Pooling Station 400 kV D/C line with quad moose conductor

KPTCL 10 In 39th SCPSPSR it was

agreed to drop the proposal. Dropped

De-link 400 kV S/C line running between RTPS-BTPS-JSW-Guttur with JSW Bus

KPTCL

Agreed in 39th SCPSPSR

400 kV M/C line from JSW to BPS is under progress, once this is commissioned the link between JSW & BPS will be delinked.

Page 18: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 17

27. TRANSMISSION SYSTEM ASSOCIATED FOR TUMKUR ULTRA MEGA SOLAR PARK(2000 MW)

Transmission Elements Line Length

(ckm)/ MVA

Capacity

Impleme

nting

Agency

Sch COD Ant COD/

Act COD

Constraints/ Remarks

Phase-I : Transmission system for Tumkur Ultra Mega Solar Park (1000 MW) April 2017

400/220 KV Tumkur PS Bus Reactor

3 x 500 MVA 1 x 125 MVAR

LILO of 400kV Gooty – Tumkur (Vasantnarsapur) D/C at Tumkur (Pavagada) PS

5

400 kV Tumkur P S - Hiriyur D/C

110

For 400kV Tumkur –Mysore line section routed via Hiryur S/s

LILO of 400kV Bellary Pool – Tumkur (Vasantnarsapur) D/C (Quad)(both circuits)[KPTCL line] at Tumkur (Pavagada) Pooling station*

*KPTCL would complete Bellary pooling station – Tumkur (Vasantnarsapur) line D/c (Quad) by December- 2016

Phase-II : Transmission system for Tumkur Ultra Mega Solar Park (1000 MW) Sep 2017

Augmentation of 400/220KV Tumkur PS 2

nd Bus Reactor

2 x 500 MVA 1 x 125 MVAR

Hiriyur–Mysore 400 kV D/C line Switchable Line Reactor at Mysore

190 1 x 80 MVAR

Tumkur PS – Mysore – De LILOed at Hiriyur

400 kV Tumkur PS- Devanhally (KPTCL) D/C (Quad)

125

KPTCL would complete establishment of 400/220 kV substation at Devanahally including inter-linking 400 kV and

JSW TPS – Bellary Pooling Station 400 kV D/C line with quad moose conductor

KPTCL Jul’16(As informed by JSWEL)

Only after all other Transmission Elements under Stage I are commissioned. KPTCL/JSW to discuss to take up this work as dedicated transmission line by the generator. Works to be carried by JSW.

Additional JSW TPS – Bellary Pooling Station 400 kV D/C line with quad moose conductor

Agreed in 39th SCPSPSR

400 kV BTPS-Guttur D/C line (QM)

Agreed in 39th SCPSPSR

Page 19: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 18

220 kV lines before Phase-II at Ultra Mega Solar Power Park.

Third 400/220 kVMVA transformer at Tumkur (Vasantnarsapur)

1 x 500 MVA

Deliberations in the Meeting

PGCIL/KPTCL were requested to complete their scope of works to avoid any evacuation

constraint since project was scheduled for April 2017.

Nodal agency of Karnataka to initiate actions to facilitate scheduling, accounting etc of Pavagada

Solar generation before it attains UMPP status (500MW).

PGCIL/KPTCL took note of above.

29. MARKET OPERATION RELATED ISSUES

29.1.Non-intimation of Nodal officer for SEM data co-ordination • Nodal officer of KPTCL for SEM data co-ordination is not responding to the issues.

• KPTCL yet to re-nominate another person.

• Issue brought to the notice of KPTCL in various meetings.

o 30th CSCM held on 04.02.2016

o 2nd

Nodal officers meeting held on 29.03.2016

o 31st CSCM held on 02.06.2016

KPTCL agreed to nominate Nodal Officer. Details would be communicated within a

week.

29.2 Issues in receipt of weekly SEM data at SRLDC

• Non-receipt of weekly SEM data from

o Nelamangala – since 21.03.2016

o Kadra – since 13.04.2015

o Yerandahalli – since 25.04.2016

• Delay in receipt of SEM data from RTPS, Sedam&Bellary

29.3.Non-installation of SEMs as per CEA Metering Regulations

Station Element No. of SEMs to be installed

UPCL 400 kV Hassan lines 1 & 2 2

Nelamangala 400 kV Hassan lines 1 & 2 4

Hoody 400 kV Kolar lines 1 & 2 2

Talaguppa 400 kV Hassan line 1

Guttur 400 kV Hiriyur lines 1 & 2 2

BTPS 400 kV Hiriyur lines 1 & 2 2

Total No. of SEMs to be installed 10

Page 20: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 19

29.4. Non-receipt of time drift statements • Time drift of SEMs to be maintained at <45sec wrt GPS time by promptly correcting the SEM

time.

• Time drift /corrections done statements to be sent to SRLDC on the first Monday of every month

without fail.

• Time drift statements never received from any of the Karnataka stations :

Ambewadi RTPS Nelamangala Konaje BTPS

Sedam Guttur Kadra Hoody Kodsally

Kadakola Yerandahalli Bellary

29.5. Sample of Suspected Time Drift at Guttur on 400kV Kaiga Line 1

Sample is given at Annexure -III

29.6.LC for delayed payment to DSM pool • KPTCL delayed payment of Rs. 4,83,13,752/- to the DSM pool for week 51 (14.03.2016-

20.03.2016).

• In line with the clause 10(4) of the DSM regulations, KPTCL had to open an LC for 110% of the

defaulted amount within a fortnight.

• Previous LC of Rs. 5.7 crore has expired on 30.10.2013.

• On KPTCL’s request, the original has been returned on 01.06.2016.

• LC for Rs. 5.32 crore is yet to be received.

29.7.PoC data for 2016-17 • Karnataka had attended the validation committee meeting for Q2, held on 30/05/2016.

• Network data, Node-wise MW/MVAR drawl and Load-Generation data to be submitted to

NLDC/SRLDC on quarterly basis.

• Data for Q3 yet to be furnished.

KPTCL/SLDC agreed to look into all the above issues and assured of corrective/necessary

action.

30. SCHEDULING RELATED - DVC TO BESCOM LTA

30.1 SRLDC stated the following: • Mutually agreed quantum of seller and buyer of LTA/MTOA transactions to be entered in

SRLDC web based scheduling program by the applicant. If the transaction is inter-regional

then SRLDC will communicate the mutually agreed value to other RLDC.

• In normal case, if no objection by buyer, seller and applicant on mutually agreed figure,

respective RLDC's will schedule the agreed quantum

• In this particular case DVC vide letter dated 20.05.16 addressed to ERLDC and SLDC,

Karnataka/BESCOM regarding non-intimation of the share surrender for both LTA and

requesting BESCOM to inform DVC first before intimating to SRLDC/ERLDC.

• In the absence of mutually agreed quantum, SRLDC is unable to reconcile with ERLDC /DVC.

Page 21: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …

Minutes of the Special Meeting with KPTCL-17.06.2016 Page 20

• Applicant viz BESCOM requested and reiterated to resolve the discrepancy and convey the

quantum to be corrected in the implemented schedule by both RLDCs.

30.2 KPTCL informed that as Applicant, they had intimated reduced schedules much in advance,

SRLDC/ERLDC needed to implement the Applicant’s request. During that period the loads had

reduced considerably and they were heavily under drawing and any post facto revisions needed to

be justified.

30.2 SRLDC pointed out that it was for the buyer/seller/applicant to come out with mutually agreed

figure.

30.3 It was noted that more clarity on the issue was required. SRLDC was requested to get in touch with

ERLDC on the injection schedule (breakup) to DVC for that period.

30.4 It was agreed that a separate Meeting would be held on this issue on 21st June 2016.

31. CONCLUSION

MS, SRPC thanked the participants for their valuable inputs and active participation. He expressed

hope that KPTCL & KAR SLDC would take necessary steps to expedite and close the pending points.

****************************

Page 22: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …
Page 23: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …
Page 24: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …
Page 25: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …
Page 26: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …
Page 27: Minutes of the Special Meeting with KPTCL … of the Special Meeting with KPTCL-17.06.2016 Page 3 3. UV RELAYS In the Special Meeting held on 26.04.20116, KPTCL had …