MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys...

10
MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Status of the Proton Source Haud ignota loquor* Haud ignota loquor* Eric Prebys *I say things that are known

Transcript of MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys...

Page 1: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 1

Status of the Proton SourceStatus of the Proton Source

Haud ignota loquor*Haud ignota loquor*

Eric Prebys

*I say things that are known

Page 2: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 2

Fortitudine VincimusFortitudine Vincimus11

• Booster performance has been steady and consistent with the Proton Plan since the shutdown.

• We were anticipating significant beam lost to NuMI by this time, but Diis aliter visum2 , and Malum quidem nullum esse sine aliquo bono3

• As of April 3, habemus VeXX4

• Ergo bibamus5

1By endurance we conquer2The gods decided otherwise3There is, to be sure, no evil without some good4We have 5e205Therefore, let us drink.

Page 3: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 3

Initial NuMI ProgressInitial NuMI Progress

NuMI PoT per Hour (E14)

0

50

100

150

200

250

300

350

400

450

500

3/14

/200

5

3/28

/200

5

4/11

/200

5

4/25

/200

5

5/9/

2005

5/23

/200

5

6/6/

2005

6/20

/200

5

7/4/

2005

7/18

/200

5

8/1/

2005

8/15

/200

5

8/29

/200

5

9/12

/200

5

9/26

/200

5

Design

Base

Actual

Target Failure

PoT per Week (E16)

0

50

100

150

200

250

300

350

400

450

500

3/14

/200

5

3/28

/200

5

4/11

/200

5

4/25

/200

5

5/9/

2005

5/23

/200

5

6/6/

2005

6/20

/200

5

7/4/

2005

7/18

/200

5

8/1/

2005

8/15

/200

5

8/29

/200

5

9/12

/200

5

9/26

/200

5

Desig

Base

Actual

Page 4: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 4

NuMI Target StatusNuMI Target Status

• After two weeks of running, water was found in the oil of the vacuum pump which pumps out the target pipe.

• A scan confirmed that the volume was full of water.

• The target was removed and the water pumped out, but they have been unable to reproduce the leak.

• They have returned the target with a “water letter outer” added.

• Will attempt to run with a Helium overpressure in the target volume.

• Probably begin to take beam early next week.

Page 5: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 5

Hourly Proton RateHourly Proton Rate

Total Peak Hourly Rate (BNB+NuMI+pbar)

0

2

4

6

8

10

12

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

p/h

r (E

16

)

Design

Fallback

Actual

Average Hourly Rate (BNB+NuMI+pbar, while up)

0

2

4

6

8

10

12

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

p/h

r (E

16

)

Design

Fallback

Actual

Improved cogging stability

Page 6: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 6

EfficienciesEfficiencies

Uptime

0

10

20

30

40

50

60

70

80

90

100

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

%

Design

Actual

Average to Peak Efficiency (during uptime)

0

10

20

30

40

50

60

70

80

90

100

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

%

Design

Actual

Page 7: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 7

Overall “Peak to Week” EfficiencyOverall “Peak to Week” EfficiencyOverall "Peak to Week" Efficiency

0

10

20

30

40

50

60

70

80

90

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

% Design

Actual

Includes 5% additional downtime for Ecool access

Page 8: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 8

Integrated Delivery (BNB)Integrated Delivery (BNB)

Weekly Proton Totals (BNB+NuMI)

0

2

4

6

8

10

12

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

To

tal P

roto

ns

(E

18)

Design

Fallback

Actual

Cumulative Proton Totals (BNB+NuMI)

0

50

100

150

200

250

300

350

400

12/1/2004 1/30/2005 4/1/2005 6/1/2005 8/1/2005 10/1/2005 12/1/2005

Date

To

tal P

roto

ns

(E18

)

Design

Fallback

Actual

MiniBooNE hits 5E20 protons!

Page 9: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 9

IssuesIssues

• In terms of beam loss, we are doing very well Loss limit frequenty > 1E17 pph!

• However, we have not been able to hit high batch intensities Typically 4-4.5E12 MB intensity limited by 5Hz rate

• This will become a bigger issue when NuMI comes back online

• Now that cogging is working, reaching high batch intensities is a priority. Almost certainly related to our present slip stacking

problems.

Page 10: MiniBooNE Meeting 4/22/05 Eric Prebys 1 Status of the Proton Source Haud ignota loquor* Eric Prebys *I say things that are known.

MiniBooNE Meeting 4/22/05 Eric Prebys 10

Major Ongoing ProjectsMajor Ongoing Projects

• ORBUMP system Major redesign of injection scheme

• 3 magnets versus 4• Eliminates problematic injection element (DCSEP)

Magnet and power supply will be ready for the 2005 shutdown (likely to start Nov 1)

• Dump reloction Booster dump will be relocated from Long 13 to the

MI-8 line. This will eliminate one of the two extraction regions

and should reduce loss significantly.