Milwaukee’s Best Brew Stand

10
Milwaukee’s Best Brew Stand Ben Caya Carl Czajka 4th Update

description

Milwaukee’s Best Brew Stand. 4th Update. Ben Caya Carl Czajka. Parts. (3) 6” Cast Iron Burner- $18ea 55,000 BTU. (3) 15gal Kettle - $220ea 1mm walls Best Kettle Money Can Buy. (1) Propane Regulator - $28ea. Parts. Heat Exchanger - $40 Aluminum shell - PowerPoint PPT Presentation

Transcript of Milwaukee’s Best Brew Stand

Page 1: Milwaukee’s Best  Brew Stand

Milwaukee’s Best Brew Stand

Ben CayaCarl Czajka

4th Update

Page 2: Milwaukee’s Best  Brew Stand

Parts

(3) 6” Cast Iron Burner-$18ea• 55,000 BTU

(1) Propane Regulator - $28ea

(3) 15gal Kettle - $220ea• 1mm walls• Best Kettle Money Can Buy

Page 3: Milwaukee’s Best  Brew Stand

Parts

(2) March Pumps - 815-PL - $150ea• 8 GPM• .04 HP• 110V

(4) 6” Pneumatic Castor - $19ea• 300lb capacity

(1)Heat Exchanger - $40• Aluminum shell• Inner Copper Spiral

Page 4: Milwaukee’s Best  Brew Stand

PartsName Quantity Price Ea Total

Steel for Frame 1 Donate -

Burners 3 $18 $54.00

Regulators 1 $26 $26.00

Pumps 2 $150 $300.00

Castors 4 $19 $76.00

Kettles 3 $175 $525.00

Thermometers 3 $26 $78.00

Valves 3 $20 $60.00

Piping 1 $40 $40.00

Heat Exchanger 1 $40 $40.00

Total: $1,058.80

Page 5: Milwaukee’s Best  Brew Stand

Frame – Shearing Material

Page 6: Milwaukee’s Best  Brew Stand

Frame – Forming Angles

Page 7: Milwaukee’s Best  Brew Stand

Frame – Sub Frame

Page 8: Milwaukee’s Best  Brew Stand

Frame - Welded

Page 9: Milwaukee’s Best  Brew Stand

Frame - Welded

Page 10: Milwaukee’s Best  Brew Stand

Gantt Chart

WBS TasksTaskLead Start End

Duration (Days)

% Complete

Working Days

Days Compl

ete

Days Remaining  

23 - Jan - 12 30 - Jan - 12 06 - Feb - 12 13 - Feb - 12 20 - Feb - 12 27 - Feb - 12 05 - Mar - 12 12 - Mar - 12 19 - Mar - 12 26 - Mar - 12 02 - Apr - 12

1 Initialize Project   1/23/12 2/15/12 3 100% 18 3 0                                                                                                                                                            

1.1 Partner Assign   1/23/12 1/24/12 2 100% 2 2 0                                                                                                                                                            

1.2 Choose Project   1/23/12 1/25/12 3 100% 3 3 0                                                                                                                                                            

2 VOC and Design Requirments   2/16/12 2/29/12 14 100% 10 14 0                                                                                                                                                            

2.1 HBT Design Pole   2/16/12 2/22/12 7 100% 5 7 0                                                                                                                                                            

2.2 Design Requirments   2/16/12 2/18/12 3 100% 2 3 0                                                                                                                                                            

2.3 Bi-Weekly Report #1   2/25/12 2/29/12 5 100% 3 5 0                                                                                                                                                            

2.4 Oral Presentation #1   2/25/12 2/29/12 5 100% 3 5 0                                                                                                                                                            

3 VOC and Design Requirments   2/16/12 2/29/12 14 100% 10 14 0                                                                                                                                                            

3.1 HBT Design Pole   2/16/12 2/22/12 7 100% 5 7 0                                                                                                                                                            

3.2 Design Requirments   2/16/12 2/18/12 3 100% 2 3 0                                                                                                                                                            

3.3 Bi-Weekly Report #2   2/25/12 2/29/12 5 100% 3 5 0                                                                                                                                                            

3.4 Oral Presentation #2   2/25/12 2/29/12 5 100% 3 5 0                                                                                                                                                            

4 Design Selection   3/01/12 3/14/12 14 77% 10 10 4                                                                                                                                                            

4.1 Select Design   3/01/12 3/04/12 4 100% 2 4 0                                                                                                                                                            

4.2 CAD Models   3/04/12 3/10/12 7 100% 5 7 0                                                                                                                                                            

4.3 FEA Analysis   3/10/12 3/14/12 5 0% 3 0 5                                                                                                                                                            

4.4 Bi-Weekly Report #3   3/12/12 3/14/12 3 100% 3 3 0                                                                                                                                                            

4.5 Oral Presentation #3   3/12/12 3/14/12 3 100% 3 3 0                                                                                                                                                            

5 Manufacturing Design   3/15/12 4/04/12 21 36% 15 7 14                                                                                                                                                            

5.1 Parts List   3/15/12 3/19/12 5 90% 3 4 1                                                                                                                                                            

5.2 Order Parts   3/19/12 3/21/12 3 30% 3 0 3                                                                                                                                                            

5.2.1 Steel for Frame   3/19/12 3/25/12 7 100% 5 7 0                                                                                                                                                            

5.2.2 Heating   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.2.2.1 Burners   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.2.2.2 Piping   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.2.2.3 Pilot Lighting   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.2.3 Pumps (2)   2/27/12 3/27/12 30 25% 22 7 23                                                                                                                                                            

5.2.4 Hoses for Pumps   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.2.5 Valves   3/19/12 3/25/12 7 100% 5 7 0                                                                                                                                                            

5.2.6 Kettles   3/19/12 3/25/12 7 100% 5 7 0                                                                                                                                                            

5.2.7 Thermometers   3/19/12 3/25/12 7 100% 5 7 0                                                                                                                                                            

5.2.8 Heat Exhanger   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.2.9 Castors   3/19/12 3/25/12 7 0% 5 0 7                                                                                                                                                            

5.3 Frame and Accessory Assembly   4/01/12 4/04/12 4 30% 3 1 3                                                                                                                                                            

5.4 Bi-Weekly Report #4   4/02/12 4/04/12 3 100% 3 3 0                                                                                                                                                            

5.5 Oral Presentation #4   4/02/12 4/04/12 3 100% 3 3 0