Millennium Pipeline Company, L.L.C. Northeast Gas Association Regional Market Trends Forum April 21, 2016 Rick Gardner Sr. Vice President, Business Development 1

Transcript of Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2....

Page 1: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Millennium Pipeline Company, L.L.C.

Northeast Gas Association

Regional Market Trends Forum

April 21, 2016

Rick Gardner

Sr. Vice President, Business Development

1

Page 2: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Today’s Discussion

Millennium Pipeline Overview

Millennium Pipeline Growth

Millennium Pipeline Project Updates

2

Page 3: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Millennium Changes

Increased our customer support team

Management changes

– Michelle Hook – Director – Public Relations

– Georgia Carter – Vice President & General Counsel

– Rick Gardner – Sr. Vice President – Business

Development

TransCanada’s pending acquisition of

Columbia Pipeline Group

3

Page 4: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Millennium Pipeline

Millennium Pipeline is owned by the partnership of:

• Columbia Pipeline Group

• National Grid

• DTE Energy

• Empire Pipeline

• Dominion Transmission

• National Fuel

• Columbia Gas

Transmission

Millennium Pipeline interconnects with:• Algonquin

• Stagecoach Storage

• Laser

• Bluestone

Largest % of

Supply

4

RamapoWagoner

Holding Point

& Corning

Page 5: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Steady Supply Growth in Northeast PA has led to Increased Market Deliveries

0

100,000,000

200,000,000

300,000,000

400,000,000

500,000,000

600,000,000

2013Receipts 2013Deliveries

2014Receipts 2014Deliveries

2015Receipts

2015Deliveries

MPC Throughput

Local Markets

National Fuel

AGT

TCO

Empire

Dominion

National Fuel

Stagecoach

Laser

Bluestone

(Dth)

5

Page 6: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Winter 2015/16 Flow ( last year)

Independence

31 MM Avg. (0)

57 MM Peak (-37)

Ramapo

713 MM Avg. (-12)

842 MM Peak (+142)

Wagoner

163 MM Avg. (+115)

170 MM Peak (+71)Stagecoach

532 MM Avg. (-95)

705 MM Peak (-50)

Corning

151 MM Avg. (-57)

256 MM Peak (-95)

Laser

285 MM Avg. (-13)

308 MM Peak (-17)

Bluestone

573 MM Avg. (+127)

621 MM Peak (+219)

Holding Point

225 MM Avg. (+56)

235 MM Peak

6

Page 7: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Eastern System Upgrade –Project Drivers

Increases Capacity between Corning and

Ramapo by approximately 200,000 Dth/day

Customers are all Northeast Utilities

Customers are seeking diversity of supply

Ramapo is a major supply point for New York

State utilities and power plants

Increased supply at Ramapo benefits both

New York and New England energy

consumers

7

Page 8: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Eastern System Upgrade Project Overview

8

Page 9: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Eastern System Upgrade Project Highland Compressor Station

9

Page 10: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

Eastern System UpgradeProposed Schedule

Began Outreach Program October 2015

Began Environmental Surveys November 2015

Submitted Pre-Filing Application January 2016

Submit FERC 7c Application July 2016

FERC Certificate Order July 2017

Start Construction September 2017

In-Service October 2018

10

Page 11: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

CPV Lateral –Project Description / Costs

7.9 Mile 16” Lateral to CPV’s Proposed 650 MW

Combined Cycle Power Plant

Reduces regional dependency on older less

efficient power plants

Competitive Power Ventures is the sole

customer

11

Page 12: Millennium Pipeline Company, L.L.C. Northeast Gas ... · Millennium Pipeline Project Updates 2. Millennium Changes Increased our customer support team ... Eastern System Upgrade Proposed

CPV LateralProposed Schedule

Began Outreach Program January 2015

Began Environmental Surveys February 2015

Submitted Pre-Filing Application April 2015

Submit FERC 7c Application November 2015

FERC Certificate Order October 2016

Start Construction September 2016

In-Service April 2017