Mill Rd Corridor Project Boards April 2015

download Mill Rd Corridor Project Boards April 2015

of 6

Transcript of Mill Rd Corridor Project Boards April 2015

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    1/11

    Redoubt Road – Mill Road corridor project

    Project overview

    • Covers the 8.9km section of the Redoubt

    Road-Mill Road corridor

    • Starting at the State Highway One (SH1)

    on and off ramps on Redoubt Road running

    east then south along Redoubt Road to theRedoubt Road-Mill Road intersection

    • The corridor continues south along Mill Road,

    concluding south of Alfriston Road near the

    intersection of Mill Road and Popes Road

    • It also includes a short section along Hollyford

    Drive to the north of Redoubt Road and

    a portion of Murphys Road from a newintersection on Redoubt Road to Flat Bush

    School Road.

    Why is the project required?

    • Changing land use, population growth

    and planned housing developments will

    increase pressure on local infrastructure

    in south Auckland

    • Significant crash hotspots along the route

    make it necessary to improve the road’s safety

     Improvements to the Mill Road corridor between

    Manukau, Papakura and Drury are identified as

    a priority in the Auckland Long Term Plan (LTP).

    Mill Road approaching new proposed Redoubt / Murphys Road intersection.

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    2/11

    Manukau Harbour

    Pararekau

    Island

        W   a  o  k

     a u r i 

     C r e  e    k 

    P     u    k     

    a             k  i    

     C     r    e   e   k  

     

        D    r    u

       r       y 

           C          r      e      e         k

     

    Pah u r  e h  u  r  e 

     I nle t

    20A

    20A

    20

    20

    20 1

    1

    1

    1

    Puhinui

    Takanini

    Middlemore

    Homai

    Papatoetoe

    Manurewa

    Te Mahia

    Papakura

    ara

    Flat Bush

    ManukauHeights

    Takanini

    ManurewaEast

    RandwickPark

    Manurewa

    GoodwoodHeights

    TotaraHeights

    WattleDowns

    MangereAscot Industrial

    MangereEast

    Puhinui

    Wiri

    HillPark

    Clover Park

    ChapelDowns

    Weymouth

    Clendon

    ConiferGrove

    Papakura

    Opaheke

    Red HillPahurehure

    The Gardens

    DonegalPark

    Papatoetoe

    Kingseat

    Waiau Pa

    agrove

    Karaka

    Hingaia

    Runciman

    Ramarama

    Drury

    Homai

    Te Hihi

    Wesley

    Ardmore

    10,000 new houses inspecial housing areas

    6000 jobs in newindustrial areas

      Redoubt Road-Mill Road corridor route

    Future urban zone

      Special housing area

      New industrial areas

    Special Housing Areas

    announced for the

    area provide for 10,000

    new homes – placing

    pressure on the currenttransport network

    • An estimated 10,000 new houses will be fast tracked in special

    housing areas under the Housing Accord in southern parts of

    Auckland, this includes 4470 houses in Flat Bush, and 1770

    houses in Takanini

    • A further 12,000 – 14,000 houses are anticipated to be

    constructed in the Takanini, Opaheke, Drury and Karaka futureurban zone as indicated in the Proposed Auckland Unitary Plan

    • New industrial areas in Takanini and Drury south will create

    6,000 new jobs

    • Traffic volumes will increase to a level more than the current

    Redoubt and Mill Roads can cope with

    • Congestion is already affecting parts of Redoubt Road andMill Road and traffic will almost double in 10 to 15 years.

    Growth map for the Mill Road –Redoubt Road area

    South Auckland is growing

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    3/11

    Features and benefits

    • A safer and more efficient route that can support future

    growth in the area

    • More reliable journeys by providing a four lane road with

    more capacity and upgraded intersections

    • Improved public transport infrastructure and services

    • More reliable bus journey times, the ability to move

    more people and remove constraints on the public

    transport network by creating bus priority lanes through

    Hollyford Drive and Redoubt Road intersections

    • Improved travel time and safety for drivers, pedestrians and

    cyclists

    • New footpaths on both sides of Redoubt and Murphys Roadimproving pedestrian connectivity

    • Safe pedestrian crossing opportunities at all traffic signals

    • An alternative north-south corridor in case of major disruption

    or emergencies on the other southern arterial routes

    Safety

    • Improves safety and provides for increases in traffic that

    will come with significantly more people living in the area

    and using this route

    • Significant crash hot spots at a number of dangerous

     junctions and curves along the route make it necessary

    to improve the road alignment

    • 283 vehicle crashes and four fatalities (2009-2013)• Without the upgrades there are expected to be further

    safety issues and more traffic than the existing road can

    cope with by 2026.

    Safety

    Accident hotspots along the Redoubt Road – Mill Road Corridor.

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    4/11

    Key project features

    Features and benefits

    • Redoubt Road widened to four lanes (two in

    each direction) between SH1 and Murphys Road

    • Westbound bus lane along Hollyford Drive

    and Redoubt Road towards Manukau

    • Replacement of the existing Mill Road with

    a new four lane arterial (two in each direction)

    between Murphys Road and Popes Road

    • New roundabouts at Ranfurly Road and Alfriston

    Road with pedestrian facilities including safe

    crossing facilities in the medians

    • New and improved signalised intersections at

    Diorella Drive, Hollyford Drive, Santa MonicaPlace and Murphys Road. These intersections

    will have pedestrian crossings and stop boxes

    for cyclists

    • Widening of Murphys Road to four lanes (two in

    each direction) between Flat Bush School Road

    and Redoubt Road

    • Murphys Road-Redoubt Road intersection

    realigned and traffic lights added to improve

    safety

    • On road cycle lanes on both sides for the length

    of the upgrade

    • Off-road cycle and foot paths (shared path) for

    the length of the upgrade

    Proposed Viaduct over Puhinui Creek.

    • Widened footpaths on both sides of Redoubt

    Road, Mill Road and Murphys Road with

    pedestrian crossings at key intersections

    • Improved access to local community

    services and facilities such as Totara Park

    and Murphys Bush

    • Replacement planting and stream restoration

    • Improved stormwater facilities for the entire

    corridor which includes wetlands areas for

    stormwater treatment and retention

    • Landscaping of the new road corridor

    Towards Flat Bush / Manukau

    Proposed Mill Road

    Towards Papakura

       E   x   i  s

       t    i   n  g 

        M   i   l   l

        R  o  a

      d

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    5/11

    S  a  n  t  a   

    M   o n  i   c  a   P  l   

    H   o  l   l    y  f   o  r       d     

    D     r     

    D     i           o    r  e l l a D r   

     R edo u  b   t

        R  o  a d 

    Mill RdProposed Route - 4 Lanes

    Murphys RdProposed Route - 4 Lanes

    AlfristonSchool

       R  a  n  f  u  r   l  y    R  d

      A    l   f  r

       i  s   t  o

      n    R

      d

       H   i   l   l    R

      d

       P  o  p  e

      s    R  d

         S   o    u     t      h       M      i      l      l

           R     d 

         G    u      l      l    y 

           V      i    a     d    u

       c     t      P    u

          h      i    n    u      i      C

        r   e   e      k

     

         G    u      l      l    y 

           V      i    a     d    u

       c     t

    H  i  l  l  t  o  p  R  d  

      R e d o

     u  b  t   R d

     F l a t  B u s h  S

    c hoo l  Rd

    T ho mas  R d 

    EquestrianCentre

    Murphys Bush -scenic reserve

    Auckland RegionalBotanical Gardens

    WatercareReservoir

        M

       u  r  p   h   y  s   R    d

     P h i l l ip  RdS t ratf or d 

     R d  

    St JohnsRedoubt

    E   v  e  

    r       g    l          a   d       e     

      D       r  

       T  e   I  r   i  r  a  n   g   i   D  r

    M  i  l  l   R  d   

     

    Key

    Bus lane

    On Road Cycle Lane

    Off Road Shared Path

    New roundabout

    New signalised intersection

    Existing signal remains*

    E   x  i   s  t  i   n   g   s  i    g  n  

    a  l   -  

    i   s  e  d    i   n  t  e  r  s  e  c  t  i   o  n   

    r  e  m  a  i   n  s   

    Redoubt Rd Proposed route -4 lanes + bus lane

    otaraPark

    S   

    t  a  t  e   H   i    g  h  w  

    a   y   1  

    G   o  o  d   w  

    o   o   d      D   

    r  *

    Mill Road corridor map

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    6/11

    Background and milestones

    2009

    Consultation on theNorthern section beganin 2009 with ManukauCity Council asking thepublic for feedback onoptions for sections ofthe corridor.

    2015 / 2016

    Southern section:Progress work toidentify a routealignment.

    2012

    Auckland Transport

    consulted with directlyaffected landowners andthe wider communityin October andNovember 2012 withsix information days.Responses from thepublic were evaluatedand incorporated inplanning the project.

    2015 / 2016

    Northern section:Notice of requirementdecision to confirmdesignation.

    October 2014

    Northern section: Routeidentified and Noticesof Requirement lodged.

    2020+

    Northern section:Phased constructionalong Redoubt Road,Mill Road and MurphysRoad driven by growth.

    2015

    Northern section:Public submissions andhearing on Notices ofRequirement.

    2025+

    Southern section:Finalisation of routeand constructiondependent on growth.

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    7/11

    Road runoff Filterstrip

    Swales(vegetation)

    Riparian buffer(vegetation)

    Wetlands

    Environmental considerations and ecology

    • Implementing a noise and vibration management plan

    • Managing any soil contamination, stormwater runoff and dust

    • Replacement planting and stream restoration

    • Creating new wetland areas and habitats for local birdlife

    • A pest eradication programme

    • Monitoring environmental issues during construction

    • On-going environmental monitoring after works are completed

    • The route was selected at Puhinui Creek to avoid mature forest

    • It crosses two areas of native forest via 17m and 23m high viaducts.

    These will be built at Puhinui Creek gully and South Mill Road gully

    • At least 22,000 sq. m of native planting

    • Environmental monitoring during and after construction

    • Mitigating effects by planting native trees adjoining to existing

    bush areas• Monitoring mature trees for bat habitation before felling

    • Minimise road lighting and where lights are necessary use

    downward facing low pressure sodium lamps

    • Rescue and relocate native geckos and skinks

    • Provide fish passage and appropriate stream restoration where

    culverts are built

    • Retain a habit linkage beneath the Puhinui Creek Gully viaduct

    during construction of piers which will remain after completion

    A large number of routes were investigated and potential effects assessed before the final route was selected.A number of conditions are proposed to reduce or mitigate any long-term impacts:

    Secondary and tertiary treatment

    eg: raingardens, wetlandsand riparian buffers

    Primary treatment

    eg: filterstrips and swales

    Stormwater treatment removes contaminants through an evironmentally friendly staged design.

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    8/11

    Noise and vibration

    Construction noise and vibration

    • Noise and vibration will be produced from construction activities, laydown

    areas and worksites.

    What will be done about it?

    • The team will comply with procedures set out in the New Zealand standards

    6803:1999, Acoustics – Construction Noise

    • This standard sets out limits and provides methods of predicting and

    managing noise

    • Before commencing any work, Auckland Transport will prepare a detailed

    plan to show how the project will comply with the standards

    Operational noise and vibration

    • Once operational, the project will comply with procedures set out in the

    New Zealand standards 6806:2010, Acoustics – Road Traffic Noise – Newand Altered Roads

    • This is the accepted method in New Zealand to address road-traffic noise

    • It provides performance targets and requires assessment of a number of

    different options for noise mitigation

    Mitigation options include

    • Acoustic barriers

    • Landscaping

    • Use of low noise road surfaces (for example open graded porous asphalt)

    • Dwelling modifications including double glazing and insulation

    • The mitigation processes will change as the design progresses and

    decisions are made on detailed design

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    9/11

    Cycling and walking improvements

    • On road cycle lanes for the length of the upgrade, varying between

    1.5 and 2 metres wide

    • Off road shared use paths for less confident cyclists and pedestrians

    on one side of the length of the upgrade

    • Advanced stop boxes for cyclists at intersections with traffic lights.

    • Two metre wide footpath on both sides of Redoubt Road betweenSH1 and Hollyford Drive intersections

    • A mix of footpaths and the shared use path will be provided for the

    rest of Redoubt Road, Mill Road and Murphys Road

    • Pedestrian crossings on all legs of intersections with traffic lights

    (Hollyford/Redoubt, Diorella/Redoubt, Murphys/Redoubt)

    • Safe crossing refuges in medians at Ranfurly Road and Alfriston Roadroundabouts

    FootpathBerm Berm Cyclepath2m 1m 1.6m

    Lane Lane7m2.7m

    Berm1.7m

       M  e   d   i  a  n

    Lane Lane7m

    BermCyclepath1m1.6m

    Shared path3m

       S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

       S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

    Redoubt Road typical cross section

    Footpath Berm Cyclepath

    2.2m 1.2m 1.8m

    Lane Lane

    6.4   M  e   d   i  a  n

    Lane Lane

    6.4m

    BermCyclepath

    1.2m1.8m

    Shared path

    3m   S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

       S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

    Murphy’s Road typical cross section

    CyclepathBerm2m

    Lane Lane7m5.2m

    Berm1.m

       M  e   d   i  a  n

    Lane Lane7m

    BermCyclepath1m2m

    Shared path3m5.2m

      S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

       S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

    Mill Road typical cross section

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    10/11

    Public transport improvements

    • Public transport improvements to the Mill Road Corridor will provide more

    frequent and more reliable public transport services

    • Bus priority facilities will be provided at the Hollyford Drive/Redoubt Road

    intersection, including a dedicated right turn lane for buses turning out of

    Hollyford Drive into Redoubt Road

    • A new westbound bus lane is proposed between Hollyford Drive and SH1

    intersection

    • The proposed bus lane will allow buses to travel unimpeded between Hollyford

    Drive and Diorella Drive, and between Diorella Drive and the motorway

    • The frequency of bus services will increase which will provide a better level of

    service for public transport users

    • Improvements to bus priority facilities and frequency will enable a strong

    integration with connector routes and local services

    • Bus priority facilities will be provided at the Hollyford Drive/Redoubt Road

    intersection, including a dedicated right turn lane for buses turning out of

    Hollyford Drive into Redoubt Road

    Redoubt Road bus lane cross section

    FootpathBerm Berm Cyclepath

    2m 1.5m1.5mBerm

    1.5mLane Lane

    6.6m1mBerm

    0.9m   M  e   d   i  a  n

    Lane Lane Bus lane

    6.6mCyclepath

    1.6mFootpath

    2m3.4m   S  e  p  a  r  a   t   i  o  n  m  e   d   i  a  n

  • 8/9/2019 Mill Rd Corridor Project Boards April 2015

    11/11

    Planning process and how to get involved

    • Auckland Transport has lodged three separate Notices of Requirement (NoR)

    with Auckland Council

    • The intention is for Auckland Council to publicly notify the NoRs in April 2015

    • The NoR process provides an opportunity for you to provide comment

    (make a submission)

    • If you wish to make a submission on these documents and be involved in

    the process you will be able to find the notified documents and submission

    instructions at the following Auckland Council website location:

    tinyurl.com/o65z5yr

    Lodged late 2014

    Resource Consent applications and alteration for designation

    January 2014

    Council asks for further information

    April – May

    Public notification – 17 April 2015

    Submisssions close – 19 May 2015

    May – June

    Submissions received and reviewed

    June

    Council will ask for further information (if required)

    June – July

    Resolving of pre-hearing issues

    August (to be confirmed)

    Council hearing

    width of road minimised

    opportunity to reinforce bush edge

    Murphys Road widening, adjacent to Murphys Bush.