MIDTOWN CONNECTOR PROJECT Urban Construction Initiative Annual Meeting 21 & 22 May 2014

Transcript of MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 –...

Page 1: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

MIDTOWN CONNECTOR

PROJECT Urban Construction Initiative

Annual Meeting

21 & 22 May 2014

Page 2: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Agenda

2

• Purpose & Goals

• Historical Milestones

• Engineering

• Facts & Figures

• Right of Way

• Utility Relocations

• Sequence of Construction

• Questions

Page 3: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Purpose & Goals

3

• Revitalize the corridor

• Rebuild aging infrastructure

• Provide a safe and efficient route to access the City’s Medical Arts District

• Enhance multimodal transportation opportunities

Page 4: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Historic Milestones

4

• March 1986 – Cross-town Connector initiated

• January 1990 – City begins dedicating Right-of-Way

• August 2006 – Midtown Connector concept adopted

• July 2007 City joins the UCI initiative

• February 2008 – Location and design public hearing

• March 2008 – Council approves L&D public hearing

• June 2008 – City begins Right of Way, Final Design, & Utility Relocation phases

• May 2012 – Construction contract executed

Page 5: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Engineering

5

• Significant updates to base mapping

• Substantial design elements required completion

• Staffing

– Seven consulting firms

– 15 to 25 individuals

• Plans & Specifications

– 465 Plan Sheets

– Drainage Profiles in lieu of VDOT drainage descriptions

– Over 400 pay items (unit price)

– Hybrid document – City & VDOT specifications

Page 6: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Facts & Figures

6

Description Quantity

Project Length 1 ¼ Miles

Storm Sewers 12,760 l. f.

Curb Inlets 134

Asphalt Pavement & Stone 48,515 tons

New Sanitary Sewer 1455 l. f.

Sanitary Sewer Rehabilitation 5837 l. f.

New Water Line 7270 l. f.

Decorative Street Lights 141

Construction Budget $18,071,957.55

Current Completion Date Spring 2015

Page 7: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Right of Way

7

• Four consulting firms

• 101 parcels Identified

– 77 Negotiated acquisitions

– 10 Condemnations

• Relocations Complete

– 4 Residential relocations completed

– 5 Business / nonprofit relocations completed

• 16 Demolitions

• Norfolk Southern – Permits & Acquisitions

Page 8: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Utility Relocations

8

• AEP – Transmission & Distribution

• Verizon

• nTelos

• Comcast

• Zayo Bandwidth

• Columbia Gas

Page 9: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Sequence of Construction

9

Page 10: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Phase I Improvements

Pre Construction Post Construction

10

Page 11: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

Phase I Improvements

Pre Construction Post Construction

11

Page 12: MIDTOWN CONNECTOR PROJECT€¦ · •July 2007 City joins the UCI initiative •February 2008 – Location and design public hearing •March 2008 – Council approves L&D public

MIDTOWN CONNECTOR

PROJECT

QUESTIONS?