Midlothian Esks Barrier Easement Project Phase...
Transcript of Midlothian Esks Barrier Easement Project Phase...
Midlothian Esks Barrier Easement
Project Phase 2a
Project Report
Client: River Forth Fisheries Trust
Reference: WATPB4209R001F01
Revision: 01/Final
Date: 10/05/2016
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 1
HASKONINGDHV UK LTD.
36 Park Row
Leeds
LS1 5JL
36 Park Row
Leeds
LS1 5JL
Water
VAT registration number: 792428892
+44 113 360 0533
royalhaskoningdhv.com+44 113 360 0533
royalhaskoningdhv.com
T
W
T
W
Document title: Midlothian Esks Barrier Easement Project Phase 2a
Document short title: Esk Phase 2a
Reference: WATPB4209R001F01
Revision: 01/Final
Date: 10/05/2016
Project name: Midlothian Esks Barrier Easement Project Phase 2a
Project number: PB4209
Author(s): James Davill, Carina Agnew and Clare Rodgers
Drafted by: James Davill and Clare Rodgers
Checked by: Carina Agnew
Date / initials: 10/05/16
Approved by: Edward Sorfleet
Date / initials: 12/05/2016
Classification
Open
No part of these specifications/printed matter may be reproduced and/or published by print, photocopy, microfilm or by
any other means, without the prior written permission of HaskoningDHV UK Ltd.; nor may they be used, without such
permission, for any purposes other than that for which they were produced. HaskoningDHV UK Ltd. accepts no
responsibility or liability for these specifications/printed matter to any party other than the persons by whom it was
commissioned and as concluded under that Appointment. The quality management system of HaskoningDHV UK Ltd.
has been certified in accordance with ISO 9001, ISO 14001 and OHSAS 18001.
No part of these specifications/printed matter may be reproduced and/or published by print, photocopy, microfilm or
by any other means, without the prior written permission of HaskoningDHV UK Ltd. or our client; nor may they be
used, without such permission, for any purposes other than that for which they were produced. HaskoningDHV UK
Ltd. accepts no responsibility or liability for these specifications/printed matter to any party other than the persons by
whom it was commissioned and as concluded under that Appointment. The quality management system of
HaskoningDHV UK Ltd. has been certified in accordance with ISO 9001, ISO 14001 and OHSAS 18001.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 2
Executive Summary
The North Esk and South Esk are rivers with excellent areas of upstream habitat for fish and
other species, where the use of these habitats is limited by historic weir structures which act as a
barrier to fish migration and impedes the movement of sediment downstream. The River Forth
Fisheries Trust and the Scottish Environment Protection Agency (SEPA) have prioritised two
weir structures for mitigation in this catchment. Montagu Bridge Weir and Dalkeith Weir are
considered to be the most downstream impassable barriers on the North and South Esk rivers
respectively. Enabling fish migration upstream of these sites was identified as the first step to
helping fish access upstream reaches of the Midlothian Esks system.
The design stage followed an initial feasibility and optioneering study which identified a preferred
option to address fish migration and sediment movement issues at these two impassable weirs.
These options were consulted on widely through a series of public engagement events across
the local area. The design stage has built upon the work undertaken during the feasibility and
optioneering study to develop the preferred option for each site into feasible and effective
engineering designs, accompanied by supporting assessments and licences that will be needed
to deliver each option on the ground.
A series of desk and site-based surveys and investigations were undertaken to inform the design
process for each site. These included topographic surveys, ecological surveys, sediment
sampling, assessment of utilities records and ground conditions, at each site. This information
was used to model the existing conditions at each site and then conditions following
implementation of the proposed designs to ensure that the most appropriate design for each site
is progressed.
Dalkeith Weir
Dalkeith Weir (Figure 1) has been in place at this location for over 100 years, associated with a
former saw mill (the mill lade is still evident). The preferred option identified for this weir was full
weir removal as this would restore the full range of natural ecological, hydrological and
geomorphological processes at this site.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 3
Figure 1 - Dalkeith Weir
The final design for Dalkeith Weir is to remove the weir down to bedrock across the majority of
the channel width, with the ends of the weir left in place to become the river bank retaining wall.
The channel walls immediately downstream and adjacent to the weir will be repaired to ensure
that they are in good condition. The river will also be re-profiled for 200m upstream of the weir
to ensure a smooth gradient. An artist’s impression (see Figure 2) has been produced to show
the removal of Dalkeith Weir.
Figure 2 - Dalkeith Weir Removal Visualisation
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 4
Montagu Bridge Weir
Montagu Bridge Weir (Figure 3) has been in place at this location for over 200 years,
constructed as part of the Montagu Bridge structure and landscaping of the grounds of Dalkeith
Palace. The listed building “Dalkeith Park, Montagu Bridge including Cauld” (Category A)
includes the weir (this is the cauld). Heritage considerations have therefore been a significant
factor in developing the design of an appropriate solution at this weir that is acceptable to the
main stakeholders (including the landowner, Buccleuch Estates, and Historic Environment
Scotland). The preferred option identified for this weir was to retain the weir structure and modify
the weir in a way that is sensitive to the surrounding landscape in order to enable fish to travel
upstream. This could be done by either creating a shallow gradient ramp made from rock
downstream (a rock ramp), or by installing a series of smaller weirs to raise water levels in a
series of steps downstream (pre-barrages).
Figure 3 - - Montagu Bridge Weir
The final design for Montagu Bridge Weir is a rock ramp, of width 4m, to be built on the left bank
(looking downstream) of the North Esk from Montagu Bridge Weir for 65m downstream. The
ramp will contain carefully arranged boulders that will break up the flow, creating a diverse range
of flow depths and velocities that different fish native species can use to migrate upstream. Due
to its length, a pool will be built into the rock ramp for fish to rest in as they navigate the ramp.
Scour protection to the banks will be placed downstream made from large boulders, and a
resting pool will be created at the toe of the ramp. An artist’s impression (see Figure 4) has
been produced to show the implementation of the rock ramp to facilitate fish passage over the
Montagu Bridge Weir.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 5
Figure 4 - Montagu Bridge Rock Ramp Visualisation
This design report will be used to support the River Forth Fisheries Trust during the consenting
and funding application process for these sites in the Midlothian Esks catchment and during the
build phase of work.
Building these designs at Dalkeith Weir and Montagu Bridge Weir is an important step towards
addressing the issues of fish migration and sediment movement at these barriers in order to
create a healthier and more resilient river ecosystem for the future in the Midlothian Esks.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 6
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 7
Table of Contents
1 Introduction 11
1.1 Purpose of this report 11
1.2 Background to the project 11
1.3 Proposed designs 12
1.3.1 Dalkeith Weir 12
1.3.2 Montagu Bridge Weir 13
2 Dalkeith Weir Site Conditions and Constraints 15
2.1 Surveys Undertaken 15
2.2 Topography of the site 15
2.3 Utilities Service Search 16
2.4 Geotechnical investigations 17
2.5 Sediment Characterisation 18
2.5.1 Sediment Sampling 18
2.5.2 Wolman Walk (Pebble Count) 19
2.6 Ecological Survey 19
2.7 Initial Heritage Assessment and Consultation 21
2.8 Early Contractor Involvement 23
2.9 Hydraulic Modelling 24
2.10 Aquatic Ecology 26
2.11 Licences and Permits 26
2.11.1 CAR Licence Application 26
2.11.2 Planning and EIA 26
2.11.3 Listed Building Consent 27
2.11.4 Conservation Area Consent 27
3 Montagu Bridge Site Conditions and Constraints 28
3.1 Surveys Undertaken 28
3.2 Topography of the site 28
3.3 Utilities Service Search 29
3.4 Geotechnical investigations 30
3.5 Sediment Characterisation 32
3.5.1 Sediment Sampling 32
3.5.2 Wolman Walk (Pebble Count) 34
3.6 Ecological Survey 35
3.7 Initial Heritage Assessment and Consultation 36
3.8 Early Contractor Involvement 37
3.9 Hydraulic Modelling 38
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 8
3.10 Aquatic ecology 39
3.11 Licences and Permits 39
3.11.1 CAR Licence Application 39
3.11.2 Planning Permission 40
3.11.3 EIA Screening Request 41
3.11.4 Listed Building Consent 41
4 Dalkeith Weir Design 42
4.1 Design approach 42
4.2 Final Design Hydraulic Model Results 43
4.2.1 Hydraulic Modelling 43
4.2.2 Sediment Transport Modelling 45
4.2.3 Flood Risk 48
4.3 Final Design 50
4.3.1 Downstream channel wall 50
4.3.2 Upstream Channel 52
4.3.3 Weir Removal 52
4.3.4 Construction Approach 53
4.3.5 Finishes and reinstatement 53
4.4 Summary of Option 54
4.5 Key Risks 54
5 Montagu Bridge Weir Design 55
5.1 Option Refinement 55
5.2 Design Approach 58
5.2.1 Operational Window 59
5.2.2 Hydraulic Criteria 60
5.2.3 Rock Ramp 60
5.2.4 Resting Pool 61
5.3 Hydraulic Modelling 62
5.3.1 Hydraulic Performance 62
5.3.2 Flood Risk 65
5.4 Final Design 67
5.4.1 Rock Ramp 67
5.4.2 Resting Pool 67
5.4.3 Retaining Wall 68
5.4.4 Notch in the Weir 68
5.4.5 Downstream Channel Works 68
5.4.6 Finishes and reinstatement 69
5.4.7 Safety Considerations 70
5.5 Sediment Management Plan 70
5.6 Summary of Design 71
5.7 Key Assumptions 71
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 9
5.8 Key Risks 71
6 Information to support the contractor 72
7 Conclusion and Recommendations 73
7.1 Conclusion 73
7.1.1 Dalkeith Weir 73
7.1.2 Montagu Bridge Weir 73
7.2 Recommended Next Steps 73
7.2.1 Licences and Permits 73
7.2.2 Vegetation Clearance 74
7.2.3 Photographic Weir Surveys 74
7.2.4 Appointing a Contractor 74
7.2.5 Construction Stage 75
7.2.6 Future Monitoring of Montagu Bridge Weir Fish Pass 75
Appendix A – Site Investigation Data A
A1 – Topographic survey A
A2 – Ecology Survey A
A3 – Sediment Sampling A
A4 – Geophysical Survey A
A5 – Historic Borehole logs A
A6 – Sections and utilities A
Appendix B – Desgin Technical Notes B
B1 – APEM Design Note B
B2 – Montagu Bridge Weir Design Note B
Appendix C – Hydrualic Modelling C
C1 – Hydraulic Modelling C
Appendix D – Outline Design D
D1 – Outline Design D
D2 – Cost Estimate D
Appendix E – Licences and Permits E
E1 – Heritage Report E
E2 – Draft CAR Licence Applications E
E3 – Draft Planning Application (Montagu Bridge Weir) E
E4 – Visualisations E
E5 – Draft Listed Building Consent (Montagu Bridge Weir) E
E6 – Draft Conservation Area Consent (Dalkeith Weir) E
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 10
Appendix F – Construction Drawings F
F1 - Construction Drawings F
F2 - CDM Hazard Log F
Appendix G – Pre-construction information G
G1 - Pre-construction information G
Appendix H – CDM 2015 Letters H
H1 – CDM 2015 Appointment Letters H
Appendix I – Sediment Manegment Plan I
I1 – Sediment Management Plan I
Appendix J – Communications Log J
J1 – Communications Log J
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 11
1 Introduction
1.1 Purpose of this report
The purpose of this project report is to summarise the main design considerations and
assumptions made during the development of the barrier easement designs for Dalkeith Weir
and Montagu1 Bridge Weir on the Midlothian Esks. The supporting information gathered during
the course of the project that has been used to develop the design has been summarised within
this report; the technical reports have been provided in full in the relevant appendices. This
report is to be used to support the River Forth Fisheries Trust during the consenting and funding
application process for these weirs in the Midlothian Esks catchment.
1.2 Background to the project
The River Forth Fisheries Trust and SEPA have identified a need to address issues caused by
historic weir structures along the North and South Esks. To date, thirteen weirs on the main
stems of the North and South Esks have been prioritised where action is needed to make the
structures passable to fish, restore river sediment processes and improve the health of water
bodies under the Water Framework Directive (WFD). A Feasibility and Optioneering Study
(Royal HaskoningDHV - Midlothian Esks Barrier Easement Project FINAL_220715) was
undertaken in 2015 for Phase 1 of the Midlothian Esks Barrier Easement Project to understand
the opportunities and constraints at each site and recommend appropriate solutions. A recent
walkover survey by the River Forth Fisheries Trust has identified further barriers in the wider
Esks catchment that are impassable to migratory fish.
The Feasibility and Optioneering study appraised these thirteen weirs and advised on the
preferred option to be implemented at each site. A combination of site and desk-based activities
were undertaken to develop a strong understanding of each barrier individually and within the
context of the river catchment as a whole. This included detailed geomorphological appraisal of
the historic changes at each site and likely responses to barrier removal/ modification, alongside
a series of stakeholder events held to raise public awareness and gather feedback on potential
options.
This comprehensive understanding of baseline site conditions, opportunities and constraints for
barrier removal or modification was then used to discuss, prioritise and provide cost estimates
for the options available to improve fish passage and restore channel connectivity for each weir.
In discussion with over 50 local stakeholders, the full range of potential options were evaluated
for each site and preferred options identified which provide the most complete restoration of
hydrological, geomorphological and ecological processes feasible for each barrier.
Two weirs were identified as high priority for barrier easement works in this catchment: Dalkeith
Weir, the most downstream impassable barrier on the South Esk, and Montagu Bridge Weir, the
most downstream impassable barrier on the North Esk. Enabling fish migration upstream of
1 Also spelled Montague in some sources, but for the purposes of this report we will use Montagu.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 12
these sites was identified as the first step to helping fish access upstream reaches of the
Midlothian Esks system.
This design stage is an important part of the work to address the issues of fish migration and
sediment movement at these barriers, in order to create a healthier and more resilient river
ecosystem for the future in the Midlothian Esks. SEPA is a key project partner and funder in
delivering this Water Environment Fund (WEF) project to improve WFD status.
1.3 Proposed designs
1.3.1 Dalkeith Weir
Dalkeith Weir is located on the South Esk a short distance upstream of the A6106 Newmills
Road bridge in Dalkeith, near Edinburgh in Scotland. Dalkeith Weir has been in place at this
location for over 100 years, associated with a former saw mill (the mill lade is still evident).
Dalkeith Weir is the most downstream weir impassable to fish on the South Esk and has been
prioritised for mitigation. Although the weir has a baulk fish pass, visible in Figure 5, it is not
effective and the weir is a significant barrier to most fish. Eels and lamprey may find a route over
a shallow section of the weir at low flows, although most would be delayed below the weir for
much of the time.
Figure 5 - Dalkeith Weir in November 2015.
For Dalkeith Weir, the proposed solution identified through the options appraisal process was full
weir removal as this would restore the full range of natural ecological, hydrological and
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 13
geomorphological processes at this site. The main limiting factors identified were the potential
for upstream bank erosion and downstream risk to the road bridge, both of which required
further investigation during the design phase.
1.3.2 Montagu Bridge Weir
Montagu Bridge Weir is located on the North Esk in Dalkeith Park, to the north of Dalkeith, near
Edinburgh in Scotland. Montagu Bridge Weir has been in place at this location for over 200
years, constructed as part of the Montagu Bridge structure and landscaping of the grounds of
Dalkeith Palace.
Montagu Bridge Weir is the most downstream weir impassable to fish on the North Esk and has
therefore been prioritised for mitigation. The weir is considered a complete barrier to all fish as
the head drop is too great for fish to jump the weir and the vertical drop could not be ascended
by eel or lamprey.
Figure 6 - Montagu Bridge Weir.
The listed building “Dalkeith Park, Montagu Bridge including Cauld” (Category A) includes the
weir (this is the cauld). This was the biggest factor governing selection and design of an
appropriate solution to improving fish passage at this weir that is acceptable to the main
stakeholders (including the landowner, Buccleuch Estates and Historic Environment Scotland).
For Montagu Bridge Weir, the proposed solution identified through the options appraisal process
was some form of visually sympathetic modification of the weir structure. The two options
identified for modification were either the use of pre-barrages, or a rock ramp (see Figure 7 for
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 14
examples of these types of fish pass). It is noted that neither of these options would address
sediment transfer issues, for which a Sediment Management Plan may be required. Weir
removal was not considered acceptable at Montagu Bridge Weir as the weir is a Category A
listed structure and important part of the national and local heritage. These options were refined
further following site survey work during the design phase, as discussed in Section 3.
Figure 7 – Examples of preferred options: series of stone pre-barrages (left) and a rock ramp (right).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 15
2 Dalkeith Weir Site Conditions and Constraints
This section of the report details site conditions and constraints that were evaluated during the
design phase for Dalkeith Weir.
2.1 Surveys Undertaken
A range of surveys were undertaken to inform the design development which define the site
parameters, conditions and constraints. The following surveys were undertaken at Dalkeith Weir
and have been summarised in the following sections, with the technical reports provided in the
appendices of this report:
• Topographic survey (Appendix A1 and A6);
• Ecological Survey (Appendix A2);
• Sediment Sampling and Pebble Count (Appendix A3);
• Assessment of borehole records (Appendix A5);
• Site Walkover by project team and Contractor (Early Contractor Involvement); and
• Statutory undertaker utilities records (Appendix A6).
2.2 Topography of the site
Royal HaskoningDHV procured a topographic survey that was used to produce a tailored
hydraulic model and inform the detailed design. The topographic survey was undertaken
(November 2015) by our sub-consultant cbec eco engineering. The survey provided ground
levels around the weirs as well as the profile of the river bed to give confidence to the modelling
results. Topographic survey information can be seen in Appendix A1 and Appendix A6.
Appendix A6 contains a long and cross sections through the river.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 16
Figure 8 - Topographic survey point data locations at Dalkeith Weir. Full image available in Appendix A1.
The following key information for the design was gathered through the topographic survey at
Dalkeith Weir:
• Weir crest level 34.67mAOD.
• Scour hole downstream of weir 30.442mAOD.
• Downstream of weir river bed is approx. 31.8mAOD.
• 100m upstream of the weir the channel bed level is approx. 33.8mAOD.
• 200m upstream of the weir the channel bed level is approx. 34.2mAOD.
• 300m upstream of the weir the channel bed level is approx. 34.3mAOD.
2.3 Utilities Service Search
A desk based utilities search was carried out for this design stage of the project by requesting
records from statutory undertakers. These services have been marked on the topographic
survey, outline design and construction drawings (see Appendix A6, Appendix D1 and
Appendix F1). Prior to commencing any site work it is recommended the contractor review this
information and re-request the data if more than six months has passed.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 17
There were limited services in this area; the services that will provide a restriction on
construction activities are those located in the entrance to the site. These will require protection
during the construction phase, as marked on the design drawings (see Appendix F1).
2.4 Geotechnical investigations
The British Geological Survey collates data on the geology of Great Britain. We used their
website to see if there was existing information that would give us confidence to design the
works without undertaking any geotechnical testing. Figure 9 below shows that existing
boreholes from the 1970’s are available in the vicinity of the weir.
Figure 9 - Historic Boreholes near Dalkeith Weir from the British Geological Society.
The borehole logs are available in Appendix A5. The borehole logs showed that the bedrock
levels varied between 31mAOD and 32mAOD in the area adjacent to the river.
The access to the weir and adjacent banks is very restricted. The banks are steep and
vegetated with mature trees, which within a Conservation Area, would require agreement with
Midlothian council before they could be removed. The river channel upstream is heavily silted
and our topographic surveys had difficulty undertaking a safe survey of the crest . Further, there
is a significant scour pool downstream of the weir, which makes access and inspection difficult.
With the information from the existing boreholes, it was decided that the significant cost and
risks associated with undertaking new boreholes or coring of the weir would not be possible until
the construction stage.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 18
2.5 Sediment Characterisation
2.5.1 Sediment Sampling
To assess the quality of the River Esks shallow sediment, samples were collected from three
sites in the vicinity of the barrier from a depth between 0 – 0.45m (see Table 1 for further
details). The laboratory results can be seen in Appendix A3. Sediment coring was undertaken
on the 2nd December 2015. Due to high flows, coring was limited to the right bank with two
individual sampling locations selected upstream of the weir, and a further sample location
downstream of the weir (as a control). A total of 8 jars of sediment (2 x 500ml, 2 x 250ml and 4 x
60ml) were collected from each location, at varying depths.
Location description Alcontrol
Reference
Co-ordinates Date Time Depth range
X Y
South Esk - upstream of
Dalkeith Weir 4 33555 67042 02.12.15 09.00 0-20cm
South Esk - upstream of
Dalkeith Weir 5 33578 67036 02.12.15 10.30 0-30cm
South Esk - downstream
of Dalkeith Weir &
Bridge 6 33673 67215 02.12.15 13.15 0-45cm
Table 1 - Details of samples taken
The samples were analysed by Alcontrol laboratories. In the absence of accepted local sediment
quality standards, the results were reviewed using the LQM/CIEH S4ULs for Human Health Risk
Assessment standards (Land Quality Press, 2015).
Land Quality Management (LQM) and the Chartered Institute of Environmental Health (CIEH)
developed Suitable For Use Levels (S4ULs) to support the assessment of potential risks posed
to human health by contaminants in soil. The benchmark concentrations have been derived in
accordance with UK legislation and national policy and are based on the concept of minimal or
tolerable risk. For each contaminant, LQM/ CIEH S4Uls have been calculated for six land use
scenarios. It was assumed that the Public Parks land use values will be most appropriate for
purpose of this assessment. Soil Organic Matter (SOM) content was calculated using Fraction
Organic Carbon (FOC). A summary of the findings is presented in Table 2.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 19
Site Alcontrol
Reference SOM [%}
Petroleum
Hydrocarbons
(BTEX)
Total Petroleum
Hydrocarbons
(PAHs)
Metals
4 (Dalkeith) 4 1% Not exceeded Not exceeded Not exceeded
5 (Dalkeith) 5 2.5% Not exceeded Not exceeded Not exceeded
6 (Dalkeith) 6 1% Not exceeded Not exceeded Not exceeded
Table 2 - Sediment Sample analysis for Dalkeith Weir.
2.5.2 Wolman Walk (Pebble Count)
A Wolman Walk survey was carried out to characterise particle size distribution within the river at
Dalkeith Weir. This information was used as an input into the hydraulic model.
The Wolman-walk pebble count methodology (Wolman, 1954) was used to characterise the
sediment. This involved the random sampling of a minimum of 100 substrate particles, each
sample in a grid across a discrete sedimentary unit (e.g. bar features or uniform section of
channel bed). The size of the particles are measured using a ‘gravelometer’ sediment sampler,
consisting of a handheld template with different sized square apertures ranging from sand (<2
mm) to boulders (>256 mm).
The results of the survey are shown in spatial data in Appendix A3, showing the data as D-
values and a substrate map. The findings of this survey are summarised in Table 3 below.
River Sample D50 D84 x y
South Esk 9 27.3 55.36 333660 666559
South Esk 10 35.79 66.89 333679 666713
South Esk 11 30.96 72.67 333647 666828
South Esk 12 62.35 115.33 333617 666869
South Esk 13 32.65 58.57 333554 666920
South Esk 14 43.3 77.87 333502 666953
South Esk 15 81.73 161.43 333703 667249
Table 3 - D50 and D84 values recorded in the river around Dalkeith Weir.
2.6 Ecological Survey
Royal HaskoningDHV procured ecological services from Practecology who undertook an
ecological assessment to inform designs for improvements to fish passage and ease of
sediment transfer at Dalkeith Weir. This incorporated a desk-based review of available data
sources and a field survey. The ecological field assessment was carried out in November 2015
and covered 250m upstream and 500m downstream of Dalkeith weir and across a 100m wide
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 20
riparian corridor centred on the mid channel of the river. An extended survey length downstream
was considered in the event the proposed works led to an increase in water levels. The findings
of the ecological assessment are summarised in the sections below and provided in full in the
report Practecology (2015) Midlothian Esks Barrier Easement Project – Phase 2a: Ecological
Assessment of Dalkeith Weir in Appendix A2.
Protected habitats and species
Two statutory designated sites where identified, Dalkeith Oakwood SSSI and the Firth of Forth
SPA, 1.16km and 6.2km from site respectively. The removal of Dalkeith Weir is not considered
to have any impact on these statutory protected habitats.
Records obtained from online sources and The Wildlife Information Centre indicated the
presence of a number of protected and notable species within 1.5km of Dalkeith Weir. However,
weir removal will be limited in scale and likely to affect only those habitats and species which
occupy the river and its riparian corridor close to the works area.
Dalkeith Bridge and a small culvert close to a private access road have some potential to
support roosting bats. It is considered unlikely that bats will occupy gaps in the retaining walls
adjacent to the weir due to their proximity to the waterline and the presence of overhanging
vegetation. However, if gaps are to be filled to stabilise the wall or remove opportunities for
nesting birds then it is advised that an assessment with an endoscope should be carried out first.
If signs suggest bats could be present then a specific bat survey would be required.
Figure 10 - Dalkeith Bridge
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 21
An otter holt was identified 270m downstream of the weir and will require further monitoring if the
removal of the weir leads to an increase in water level such that it is no longer usable. (Note
modelling shows no change in velocities and depths downstream of the weir once it is removed).
Trees and shrubs must be removed from the works area and route of access ahead of the bird
breeding season to ensure that works are not delayed as a result of finding nesting birds on site.
Blocking gaps in the stonework of the retaining walls, provided no signs of bats are present, is
also recommended, particularly as kingfisher have been observed in the area. Monitoring the
river prior to the commencement of works may also inform the likely location of kingfisher nests
and allow for more targeted mitigation. It is advised that ecological surveys are repeated if more
than six months passes before works commence.
Invasive Species
Both Himalayan balsam and Giant hogweed were found within the survey area along the River
South Esk. During the construction phase a Construction Environmental Management Plan
(CEMP) detailing biosecurity measures should be provided by the main contractor and
implemented during works to stop the spread of these plants and contaminated soil.
Pollution Prevention
The CEMP should also cover what pollution prevention and control measures will be adopted
given the need for in-stream works. Avoiding the refuelling of plant on site, keeping all fuels in a
securely bunded area and having a spill kit on hand for the duration of works is also
recommended.
2.7 Initial Heritage Assessment and Consultation
There are significant heritage considerations and constraints within this project and Midlothian
Council confirmed that Conservation Area Consent would be required for the removal of Dalkeith
Weir. A Heritage Statement was prepared to support the Conservation Area Consent and this
report can be found in Appendix E1.
Dalkeith Weir lies within the northern limits of Newbattle Conservation Area, and although
complete removal of the structure will impact the existing historical and functional associations
with Woodburn Saw Mill Lade and the industrial setting along this part of the river, it is not
considered to impact the character or importance of the Conservation Area. However, in
consideration of the alteration to the industrial setting of this part of the river, it is recommended
that a photographic survey is undertaken of Dalkeith Weir and its surroundings prior to any
demolition works, to provide a record.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 22
Figure 11 – Mill Lade at Dalkeith Weir
The proposed works also include re-profiling the river channel upstream of the weir, topsoil
stripping and removal of some vegetation along the east/south bank of the river. These works
may have an impact on any buried archaeological remains, which are at present unknown, and
therefore it is recommended that an archaeological watching brief is undertaken during any
topsoil stripping required for the siting of the compound and bank stability works, and a finds
protocol is put in place in the event that artefacts are recovered during the excavation of the river
bed. We are advising a precautionary approach and the need for a watching brief will be
confirmed with Midlothian Council following their consideration of the Conservation Area
Consent application. Further detail can be found in the Heritage Statement in Appendix E1.
The removal of some vegetation along the east/south river bank may also have some localised
impact on the formal garden setting of Old Mill House and therefore it is recommended that
these trees are replaced with similar species, of a similar size where possible.
Other mitigation measures prior to and during construction include toolbox talks conducted at the
start of construction in order to highlight the location and significance of the designated and non-
designated built heritage assets, and exclusion zones are clearly demarcated around the Old
Mill House and Woodburn Saw Mill Lade in order to prevent any accidental damage during
construction.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 23
2.8 Early Contractor Involvement
Royal HaskoningDHV partnered with Lumsden and Carroll Civil Engineering (L&C) to provide
early contractor involvement (ECI) on this project. ECI gives a contractor’s view of the site and
identifies access, buildability and site restraints at an early stage.
L&C noted there was limited access to the site, with the only access through the driveway to the
Old Mill House (see 12). This would require the site compound to be located within the grounds
of the Old Mill House. L&C recommended traffic management controls for exit/entry to the site
and protection for services in the private access road.
L&C highlighted that to access the weir and river, there would have to be vegetation and tree
removal. It was proposed access to the river channel should be from upstream of weir where
there were less mature trees and vegetation.
Figure 12 - Driveway to the Old Mill House.
When removing the weir, the retaining walls adjacent to the weir will be affected as they are
connected to the weir structure. Removing the weir will require work to be undertaken on the
channel walls immediately downstream of the weir. L&C suggested the repairs to the
downstream channel walls could be done using a new piled wall and face the piles with cladding
stone. Due to the high bedrock level this was not considered feasible.
L&C input was used to develop an outline construction methodology for the CAR licence and
undertook a pricing exercise creating a bill of quantities for the proposed construction work (see
Appendix D2, note this appendix should be considered as Commercially Sensitive).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 24
2.9 Hydraulic Modelling
The project team assessed the river hydrology to develop an understanding of the river flows.
River gauge data was requested from SEPA and used to calculate flows at Dalkeith Weir.
The closest gauge to the Dalkeith Weir study site is the SEPA gauge at Cowbridge (333881E,
667615N), only 500m downstream of the downstream survey boundary. This gauge has only a
short flow record however, and so peak flow estimates from the gauge data are not reliable for
long term predictions. However, the gauge is suitable for providing low flow estimates, and the
Q95%, Q50% and Q10% daily flows are all available.
For flood flows, the ReFH2 software and FEH web service was used to provide flow peaks and
flow hydrographs for hydraulic modelling and sediment transport/bed mobility modelling. The
flows are shown in Table 4.
Flow statistic Flow [m3/s] Hydraulic significance
50% daily 1.54 Fish passage
10% daily 4.91 Fish passage
2 year return 34.81 Channel forming
200 year return 109.30 Design flood
Table 4 - Hydrology from the Cowbridge Gauge (low flows) and ReFH2
After completion of the topographic survey, a 2D surface Digital Elevation Model (DEM) of the
existing weir and surrounding land was built in AutoCAD. The DEM was used to input into a
hydraulic model of the existing river situation. This provided a baseline to compare the weir
removal against, to understand the impact of the changes. A report on the modelling is located in
Appendix C1.
The design stage of this project required an iterative process between the engineering team and
the hydraulic modellers to ensure that the design details were added to the model and used to
calculate the effect on the river. Model runs were undertaken at a range of flows that can be
seen in detail in the modelling report. Further detail of the design process can be seen in
Section 4 of this report.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 25
Figure 13 - Dalkeith Weir bed stress for the existing situation. Full image available in Appendix C1.
The modelling work was undertaken by sub-consultants cbec eco engineering with Royal
HaskoningDHV’s principal hydraulic modeller providing expert reviews. Also, our project
geomorphology expert worked with cbec during the geomorphology assessment of the effect of
removing the weir. The modelling data and reports can be found in Appendix C1.
The models produced during the design phase included:
• A 1D hydraulic model of the existing conditions;
o 1D HEC-RAS model of existing condition South Esk at Dalkeith Weir- this model
is used to act as a baseline for eventual sediment transport and flood risk
modelling;
• A 2D detailed model of the structure and design condition;
• 2D (SRH-2D) low flow (Q95%, Q50% and Q10%) and flood model (2-200 year) of South
Esk at Dalkeith Weir used for design work and as a baseline for flood risk modelling; and
• A 2D, mobile bed, sediment transport model to aid the design work by showing potential
erosion and deposition following the weir removal.
The 2D model for Dalkeith weir existing conditions, and a design condition without the weir, has
been used in the re-design of the channel upstream of the weir. Importantly, 2D hydraulic
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 26
modelling results have shown that a simple weir removal results in excessive velocities and
shear, which could lead to an unstable channel upstream. Design iterations have reduced this
high velocity proximal to the weir location, and further design iterations and modelling were
required to produce a stable channel. Further information on the model development and
resulting iterative design is provided in Section 4.
2.10 Aquatic Ecology
Royal HaskoningDHV appointed APEM to provide aquatic ecology support to the design
process. The APEM specialist visited the site and reviewed species data available from the
River Forth Fisheries Trust. APEM produced a technical design note to support the design
which can be found in Appendix B1.
River Forth Fisheries Trust provided fish catch data from various locations on the North and
South Esk. This identified that the main native migratory fish species present in the watercourse,
and of concern for fish passage, are:
• Atlantic salmon (Salmo salar);
• Sea and brown trout (Salmo trutta);
• Sea lamprey (Petromyzon marinus);
• River lamprey (Lampetra fluviatilis); and
• European eel (Anguilla anguilla).
It was considered that after the removal of the weir down to bedrock, the river would be in a
natural state. This will allow the migration of native species that would have existed within the
river before the weir was built. It is noted that due to the natural bedrock of the river this may not
result in fish passage at all river flows.
2.11 Licences and Permits
2.11.1 CAR Licence Application
SEPA has confirmed that Controlled Activities Regulations (CAR) authorisation is required for
the physical engineering works within the channel at Dalkeith Weir. The draft CAR licence
application (Forms A and E) has been provided in Appendix E2.
2.11.2 Planning and EIA
Royal HaskoningDHV sought pre-planning advice from Midlothian Council (21/10/2015). The
response was that Dalkeith Weir removal would not require a planning application, unless the
construction of any new structures in the channel would be required to mitigate the removal of
the weir. The design works require the removal of the weir, repair of existing walls, re-profiling of
the river channel, so we do not consider that planning permission is needed.
Royal HaskoningDHV also submitted an EIA Screening Request Letter (25/11/2015) to
Midlothian Council to confirm whether the proposed works will require a statutory Environmental
Impact Assessment to be undertaken. Midlothian Council confirmed (02/12/2015) that the
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 27
removal of Dalkeith Weir would not require a statutory EIA. See Appendix E3 for the screening
letter responses and pre-application advice.
2.11.3 Listed Building Consent
It should be noted that from assessing available records, Dalkeith Weir is not listed and therefore
we have not included any provision for a Listed Building Consent application for the removal of
this structure.
2.11.4 Conservation Area Consent
As identified in Section 2.7, Conservation Area Consent is required for the removal of Dalkeith
Weir. See Appendix E6 for the draft application that will be submitted to Midlothian Council for
consideration.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 28
3 Montagu Bridge Site Conditions and Constraints
This section of the report details site conditions and constraints that were evaluated during the
design phase for Montagu Bridge Weir.
3.1 Surveys Undertaken
A range of surveys were undertaken which define the site parameters, conditions and
constraints. At Montagu Bridge Weir the following surveys were undertaken and can be found in
the appendices of this report:
• Topographic survey (Appendix A1 and A6);
• Ecological Survey (Appendix A2);
• Sediment Sampling and Pebble Count (Appendix A3);
• Geophysical Survey (Appendix A4);
• Site Walkover by project team and Contractor (Early Contractor Involvement); and
• Statutory undertake utilities records (Appendix A6).
Figure 14 - Topographic survey underway at upstream of Montagu Bridge. Photo from upstream of Montagu Bridge Weir,
3.2 Topography of the site
Royal HaskoningDHV procured a topographic survey that was used to produce a tailored
hydraulic model and inform the detailed design. The topographic survey was undertaken by our
sub-consultant cbec eco engineering. The survey provided ground levels around the weirs as
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 29
well as the profile of the river bed to give confidence to the modelling results. Topographic
survey information can be seen in Appendix A1 and Appendix A6.
Figure 15 - Topographic survey points taken at Montagu Bridge Weir. A full version of this image is available in Appendix A1.
The topographic survey revealed three important aspects compared to the estimations made
during the feasibility stage of the project:
1. The height of the weir was greater than the 1.8m estimated at the feasibility stage;
2. The downstream river channel was wider than expected; and
3. The river bed level downstream of the weir had a steeper gradient than expected.
3.3 Utilities Service Search
A desk based utilities search was carried out for this stage of the project by obtaining records
from statutory undertakers. These services have been marked on the topographic survey,
outline design and construction drawings (See Appendix A6, Appendix D1 and Appendix F1).
Prior to commencing any site work it is recommended the contractor review this information and
re-request the data if more than six months has passed.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 30
Figure 16 - Water service at Montagu Bridge.
The obtained records show limited services in this area, with the only service running along the
access road that crosses over Montagu Bridge. However, it is suggested that the contractor
consult with the landowner to determine if they have any site records that should be considered
before breaking ground in the construction phase.
3.4 Geotechnical investigations
At Montagu Bridge Weir, geotechnical information was required for the design of the foundation
of the fish pass structure. A review of the published mapping indicates alluvial and river terrace
deposits overlying Scottish Coal Measures sandstones and mudstones. In addition the initial site
visits showed evidence of rock close to the ground surface. A scoured pool is present
immediately downstream of the weir with an ‘island’ of accreted sand, gravel and cobbles further
downstream.
A review of the British Geological Society (BGS) borehole records showed that historic data is
not available for this site. Therefore, it was decided that further geotechnical information was
required to inform the design at this weir. However, access is extremely difficult with steep sided
river banks making intrusive investigation difficult. In addition, the cost of mobilising suitable
equipment to the location of the fish pass was likely to be significant and environmental
constraints were likely to impede any works in the river bed due to it being conducted during a
sensitive period for migratory fish.
A site walkover was undertaken by a Principal Geotechnical engineer to determine the need for
further geotechnical investigation. The recommendation from this walkover was to use a
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 31
geophysical survey to determine the bedrock depth at the site. This method is non-intrusive and
requires light weight equipment to mitigate the difficult access to the site and negate the need for
intrusive in-channel working.
A geophysical survey was carried out at the location of the proposed fish pass by TerraDat in
January and March 2016 (see Appendix A4) to determine the nature of the ground at the
location of the fish pass. The geophysical survey consisted of both seismic refraction and
resistivity survey techniques, as explained in the Terradat report (Appendix A4).
The geophysical survey indicated that the ground profile in the riverbed at the location of the
proposed fish pass consisted of the following profile in order of superposition:
• A thin layer (<0.5m) of soil/organic material; which is locally absent.
• A layer of compact/dense soil or highly weathered rock which varies in thickness from
approximately 2m to 5m.
• A basal layer of competent rock; the base of which was not proven by the survey.
The ground profiles revealed by the geophysical survey techniques (P wave, S wave and
resistivity) correlated very well at the location of the fish pass. In addition it is considered that the
nature of the ground revealed by the geophysical survey was in accordance with the anticipated
ground profile from the earlier desk study research carried out at the site. Consequently it is
considered that the results of the geophysical survey are sufficiently accurate to enable an
assessment of the required excavation level for the fish pass.
The results of the geophysical survey have indicated that the nature of the ground at the
presumed level of excavation will be either dense soil or weathered rock. It is considered that the
construction of the fish pass in either of these two types of ground would be adequate in terms of
bearing capacity and settlement of the structures.
However, it is possible that the dense soil, which may be alluvial soil, may not be stable during a
significant flood event. Consequently it is recommended that the fish pass is founded at least
0.3m below the top of the weathered rock.
Figure 17 - Extract from TerraDat report (full image in AppendixA4).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 32
The geophysical survey has indicated that the top of the weathered rock is likely to be variable
and may occur at or even above the presumed excavation level of 25mOD. However it is also
possible that locally the top of the weathered rock may be deeper than 25mOD. Figure 17
shows a dashed line (top of the S4 layer) which is the estimated to be the depth of weathered
rock. The weathered rock is around the 25mAOD mark on the left hand side of the river channel;
however this drops down to 22.5mAOD on the right hand side. As a worst case scenario the
foundation of the rock ramp would have to be built at 22.5mAOD. It is noted that the fish pass
will be designed on the left hand side of the channel where the weathered rock is closer to the
existing river bed surface.
The design will require the foundation of the fish pass to be built 0.5m into the weathered rock. It
was agreed to set the invert of the fish pass structure at 25mAOD. A further layer of mass
concrete will be placed below 25mAOD to form the foundation of the structure. In general this
will be a foundation level of 24.5mAOD; however there will be localised areas that will require a
deeper mass concrete fill.
It is recommended that the suitability of the ground at the foundation excavation level should be
confirmed by a site inspection carried out by an engineer during the works.
The full geophysical survey results can be found in Appendix A4.
3.5 Sediment Characterisation
3.5.1 Sediment Sampling
To assess the quality of the North Esks shallow sediment, samples were collected from three
sites in the vicinity of the weir from a depth between 0 – 0.45 m and further details of the survey
locations are provided in Table 5. The laboratory results can be seen in Appendix A3. Sediment
coring was undertaken on the 1st December 2015. Due to the high river flows, coring was limited
to the right bank with two individual sampling locations selected upstream of the weir, and a
further sample location downstream of the weir (as a control). A total of 8 jars of sediment (2 x
500ml, 2 x 250ml and 4 x 60ml) were collected from each location, at varying depths.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 33
Location description Alcontrol
Reference
Co-ordinates Date Time Depth range
X Y
North Esk - upstream
of Montague Bridge 1 33350 68096 01.12.15 10.00 0-20cm
North Esk - directly
underneath Montague
Bridge 2 33368 68105 01.12.15 10.55 0-30cm
North Esk -
downstream of
Montague Bridge &
Weir
3 33371 68164 01.12.15 13.00 0-20cm
Table 5 - Details of samples taken
The makeup of sediment and lack of coarse material in the bed resulted in a maximum of
approximately 30cm of core being produced each time (sediment of a slightly coarse size acts
as a plug and limits the loss of fine sediment and silt from the instrument when it is being
extracted from the bed).
Further downstream, the nature of the bed was found to be considerably more coarse and also
consisted of bedrock, limiting the depth that the corer was able to penetrate. Organic matter was
also evident within many of the cores at this site due to proximity of the sample locations to the
river banks (constrained by high flows). This limited the size of the cores obtained as the caps
which are used to collect fine sediment cores often became clogged with leaf matter.
The samples were analysed by Alcontrol laboratories. In the absence of accepted local sediment
quality standards, the results were reviewed using the LQM/CIEH S4ULs for Human Health Risk
Assessment standards (Land Quality Press, 2015).
Land Quality Management (LQM) and the Chartered Institute of Environmental Health (CIEH)
developed Suitable For Use Levels (S4ULs) to support the assessment of potential risks posed
to human health by contaminants in soil. The benchmark concentrations have been derived in
accordance with UK legislation and national policy and are based on the concept of minimal or
tolerable risk. For each contaminant, LQM/ CIEH S4Uls have been calculated for six land use
scenarios. It was assumed that the Public Parks land use values will be most appropriate for
purpose of this assessment. Soil Organic Matter (SOM) content was calculated using Fraction
Organic Carbon (FOC). A summary of the findings is presented in Table 6 - Sediment Sample
analysis for Montagu Bridge Weir.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 34
Site Al Control
Reference SOM [%}
Petroleum
Hydrocarbons
(BTEX)
Total Petroleum
Hydrocarbons
(PAHs)
Metals
1 (Montagu) 1 1% Not exceeded Not exceeded Not exceeded
2 (Montagu) 2 6% Not exceeded Not exceeded Not exceeded
3 (Montagu) 3 6% Not exceeded Not exceeded Not exceeded
Table 6 - Sediment Sample analysis for Montagu Bridge Weir.
3.5.2 Wolman Walk (Pebble Count)
The project work included a survey to characterise particle size distribution within the river at
Montagu Bridge Weir. This information would be used as an input into the hydraulic model.
The Wolman-walk pebble count methodology (Wolman, 1954) was used to characterise the
sediment. This involved the random sampling of a minimum of 100 substrate particles, each
sample in a grid across a discrete sedimentary unit (e.g. bar features or uniform section of
channel bed). The size of the particles are measured using a ‘gravelometer’ sediment sampler,
consisting of a handheld template with different sized square apertures ranging from sand (<2
mm) to boulders (>256 mm).
The results of the survey are shown in spatial data in Appendix A3, showing the data as D-
values and a site substrate map and a summary is provided in Table 7.
River Sample D50 D84 x y
North Esk 1 39.58 111.71 333124 667599
North Esk 2 61.63 128 333170 667580
North Esk 3 55.96 122.15 333240 667593
North Esk 4 117.64 176.53 333285 667628
North Esk 5 59.71 118.5 333300 667805
North Esk 6 42.74 88.27 333258 667909
North Esk 7 40.89 65.86 333254 668002
North Esk 8 47.79 71.65 333369 668162
Table 7 - D-value for samples on the North Esk near Montagu Bridge Weir.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 35
3.6 Ecological Survey
Ecologists were procured from Practecology to undertake an ecological assessment to inform
designs for improvements to fish passage and ease of sediment transfer at Montagu Bridge
Weir. This incorporated a desk based review of available data sources and a field survey. The
ecological field assessment was carried out in November 2015 and covered 250m upstream and
500m downstream of the weir and across a 100m wide riparian corridor centred on the mid
channel of the river. The findings of the ecological assessment are summarised in the sections
below and provided in full in the report Practecology (2015) Midlothian Esks Barrier Easement
Project – Phase 2a: Ecological Assessment of Montagu Bridge Weir in Appendix A2.
Protected habitats and species
Two statutory designated sites were identified, Dalkeith Oakwood SSSI which is immediately
adjacent to the downstream section of the survey area, and the Firth of Forth SPA, 5km
downstream of the weir. The weir modification within the river immediately downstream of
Montagu Bridge Weir is not considered to have any impact on statutory protected habitats.
Records obtained from online sources and The Wildlife Information Centre indicated the
presence of a number of protected and notable species within 1.5km of Montagu Bridge Weir.
However, the proposed weir easement will be limited in scale and likely to affect only those
habitats and species which occupy the river and its riparian corridor close to the works area.
The proposed works are unlikely to have significant impacts to habitats and species along the
River North Esk. Nevertheless, it will be necessary to remove trees and shrubs from the works
area and the route of access and it is recommended that this is undertaken ahead of the bird
breeding season to ensure nests do not delay works. It is also recommended that a tree close to
the proposed route of access should be retained and protected from both damage and
disturbance due to the potential for it to be used by bats. Although it is unlikely to be required,
should any retaining walls in the vicinity of the weir be affected by the works it is also
recommended that gaps and holes are blocked up to avoid nesting birds e.g. kingfisher utilising
this habitat. It would be necessary to confirm that any gaps in the retaining walls are not
occupied by roosting bats before they are blocked.
Invasive Species
There are a number of invasive non-native species of plant within the survey area, including
Himalayan balsam, Japanese knotweed, giant hogweed, cherry laurel and rhododendron. A
Construction Environmental Management Plan (CEMP) detailing biosecurity measures should
be provided by the main contractor and implemented during works to stop the spread of these
plants and contaminated soil.
Pollution Prevention
The CEMP should also cover what pollution prevention and control measures will be adopted
given the need for in-stream works. Avoiding the refuelling of plant on site, keeping all fuels in a
securely bunded area and having a spill kit on hand for the duration of works is also
recommended.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 36
3.7 Initial Heritage Assessment and Consultation
Royal HaskoningDHV identified during Phase 1 of the project that consultation with Midlothian
Council and Historic Environment Scotland would be key to the successful implementation of
this project, due to the planning and heritage constraints. The development of the design in
consultation with Midlothian Council and Historic Environment Scotland is covered in Section
3.12.1 and Section 5 of this report.
The site is located within the grounds of Dalkeith Palace which is also within the ‘Dalkeith House
& Park Conservation Area’. The weir forms part of the Montagu Bridge (Grade A) Listing which
was identified as a significant project consideration and constraint. A Heritage Statement was
prepared to support the Planning Application and Listed Building Consent applications
necessary for the implementation of this project. This report is appended in Appendix E1.
The final design is considered to result in minimal alteration to the setting of Montagu Bridge
Weir as the existing contrast between the formal ‘romantic’ landscape setting upstream and the
‘wild’ landscape downstream will remain largely unaltered. The noise created by the water as it
flows over the weir will also remain unchanged which is considered an important aspect of the
heritage designation and ‘quality’ of the area. Although it is acknowledged that the construction
of the rock ramp and associated access will temporarily impact upon the tranquil and
picturesque setting of Montagu Bridge Weir, as well as the Garden and Design Landscape and
Conservation Area.
The use of boulders within the rock ramp to vary the flow of water and to create a resting pool is
considered to be in-keeping with the surrounding landscape downstream of the weir. It has been
recommended that a rock cladding is used along the retaining wall of the rock ramp as this is
considered to be more sympathetic to the designed ‘wild’ landscape downstream of the weir,
and will not misrepresent the original design of the listed building. The rock will create
additional habitat and may also facilitate the passage of eels.
In order to mitigate the impacts to Montagu Bridge and Weir, it is recommended that prior to
construction a condition survey of the listed building is undertaken. It is also recommended that
toolbox talks are conducted at the start of construction in order to highlight the location and
significance of the designated features, and exclusion zones are clearly demarcated around any
parts of the listed building which do not require works in order to prevent any accidental damage
during construction.
With respect to buried archaeology, which is at present unknown, it is recommended that an
archaeological watching brief is undertaken during the topsoil strip and a finds protocol is put in
place in the event that artefacts are recovered during the excavation of the river bed.
On completion of the works, the rock ramp will provide a range of flow depths and velocities to
account for a wide range of fish species that migrate up the River North Esk, whilst being
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 37
sympathetic to the designed ‘wild’ landscape setting which adds great value to the significance
of Montagu Bridge and Weir, and the surrounding designated landscape.
3.8 Early Contractor Involvement
We partnered with Lumsden and Carroll Civil Engineering (L&C) to provide early contractor
involvement (ECI) on this project. ECI gives a contractor’s view of the site and identifies access,
buildability and site restraints at an early stage.
L&C noted there was restricted access to the river, though access to the general area was good.
It was proposed to situate a compound in Steel Park, a grass field to the east of the river for
which a temporary haul road to the compound would be needed. A further access route would
then be put along an existing pedestrian access from the field down to the river (see Figure 18).
Figure 18 – Existing pedestrian access from the river to Steel Park.
L&C advised that the fish pass would be best built from the right bank, however it was noted by
our aquatic ecologist that the fish pass would be best built on the left bank where there were
preferential flows (attraction flows).
L&C input was used to develop an outline methodology for the CAR licence and undertook a
pricing exercise creating a bill of quantities for the proposed construction work, these are
appended in Appendix D2 (Note the contractor has provide commercial rates and this appendix
should be considered as Commercially Sensitive).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 38
3.9 Hydraulic Modelling
The first stage of the hydraulic modelling was to assess the site hydrology to determine river
flows at the weir. The gauge at Dalkeith Palace has been subject to vandalism over the years
and is not a reliable indicator of flood flows. The nearest flood gauge is at Dalmore, significantly
upstream of the study site and so can only be used as a rough guide to flood estimates.
The ReFH2 methodology was instead used to determine flood peaks and hydrographs for the
site. Catchment area was calculated as 133.89km2 and this area was checked manually in GIS.
As a check, the results were compared to the Dalmore gauge recommended by SEPA. These
flood flow estimates are tabulated in Table 8.
Return Period [y] Default ReFH2 [m3/s]
2 27.25
10 40.12
100 67.94
200 81.12
Table 8 - Flood flows for Montagu Weir.
However, to provide low flows for the analysis of fish pass, the gauge at Dalkeith Palace, close
to the study site is suitable. The gauged daily Q10%, Q50% and Q95% are tabulated in Table 9
and used for analysis of fish passage for the design at Montagu weir.
Daily Flow Dalkeith Palace Gauge [m3/s]
Q95% 0.577
Q50% 1.45
Q10% 4.67
Table 9 - Gauged daily flows at Dalkeith Palace.
After completion of the topographic survey, a 2D surface called a Digital Elevation Model (DEM)
of the existing weir and surrounding land was built in AutoCAD. The DEM was used to input into
a hydraulic model of the existing river. This provided a baseline to compare the weir removal
against, to see the impact of the changes. A report on the modelling can be found in Appendix
C1.
The design stage of the project required an iterative process with the hydraulic modellers to
ensure that the design details were added to the model, to calculate the effect on the river. A
crucial aspect of this design was in the sizing of the notch in the existing weir at the top of the
rock ramp. This would determine the flow into the rock ramp and thus the pass-ability of the
structure. Further information on the design development can be found in Section 5 of this
report.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 39
The modelling work was undertaken by sub-consultants cbec eco engineering with Royal
HaskoningDHV’s principal hydraulic modeller providing expert reviews. The project
geomorphology expert worked with cbec during the geomorphology assessment. The modelling
data and reports can be found in Appendix C1.
The models produced included:
• A 1D hydraulic model of the existing conditions;
o 1D HEC-RAS model of existing condition North Esk at Montagu weir- this model
is used for design work and to act as a baseline for eventual sediment transport
and flood risk modelling;
• A 2D detailed model of the structure and design conditions;
o 2D (SRH-2D) low flow and bankfull flood model of North Esk at Montagu weir- this
model is used for design work;
• A 2D, mobile bed, sediment transport model using SRH-2D software.
o This model was used to consider if a sediment management plan could be put in
place at Montagu Bridge Weir. Further details are in Appendix I1 and Section 5
of this report.
3.10 Aquatic ecology
Royal HaskoningDHV appointed APEM to provide aquatic ecology support to the design
process. The aquatic ecologist visited the site and reviewed species data available from the
River Forth Fisheries Trust. APEM were involved in the iterative design process, advising on the
parameters for passage of different fish species under different flows. The aquatic ecologist
produced a technical design note that identifies the design criteria in relation to fish species and
supports the design evolution and this is provided in Appendix B1.
River Forth Fisheries Trust provided electrofishing data from various locations on the North Esk.
This identified that the main native migratory fish species present in the watercourse, and of
concern for fish passage, are:
• Atlantic salmon (Salmo salar);
• Sea and brown trout (Salmo trutta);
• Sea lamprey (Petromyzon marinus);
• River lamprey (Lampetra fluviatilis); and
• European eel (Anguilla anguilla).
3.11 Licences and Permits
3.11.1 CAR Licence Application
SEPA confirmed that Controlled Activities Regulations (CAR) authorisation is required for the
existing impoundment at Montagu Bridge Weir. The draft CAR licence application forms (Forms
A and D) have been provided in Appendix E2.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 40
3.11.2 Planning Permission
A request for pre-planning advice was issued to Midlothian Council in October (21/10/2015) and
the following statement was provided by the Senior Planning Officer as part of the formal
response:
“Montagu Bridge was designed by the celebrated Scottish architect Robert Adam, and
completed by his brother James Adam following his death. For reasons of picturesque variety
Adam constructed small cauld, or weir, downstream. Water tumbles over the cauld and the
noise is amplified by the echo of the underside of the bridge; upstream the other side of the
bridge is reflected in the calm waters held back by the cauld. The noise and reflective qualities
of the water contribute to the setting of the bridge.”
It was confirmed by Midlothian Council that planning permission would be required for the
proposed works at Montagu Bridge Weir to create a fish pass at this location.
A meeting was held on site and in the Midlothian Council offices, with Historic Environment
Scotland and the Senior Planning Officer (Adam Thomson) from Midlothian Council on the 10th
December 2015. During the meeting the sketches for both the pre-barrage option and rock
ramp (see Appendix B3) were presented and the development process behind each design
was explained. The planning and heritage stakeholders consulted were broadly supportive of the
fish passage project and its aims. However, the pre-barrage option was not favoured due to the
following issues:
1. The pre-barrages would extend across the whole channel width and therefore the
existing weir will no longer be visible as it was intended to be viewed i.e. a cascading
waterfall.
2. The noise of the water passing over the existing weir, which is part of the setting, will be
altered due to the reduced head loss.
3. The pre-barrages, even if made to individually look natural with rock, will make very
man-made pools and will be regular in their layout.
4. The area downstream of the bridge is seen as a ‘wild designed landscape’ as opposed
to the more formal landscaped area upstream of the bridge. The pre-barrages would not
fit with these characteristics.
The rock ramp option was generally viewed more positively as:
1. The weir was not fully obscured by raised water level across the whole width of the
channel;
2. The noise from the weir will be similar to the existing situation; and
3. The rock ramp is less regular than the pre-barrages which is more befitting of the
‘designed wild landscape’ setting downstream of the bridge.
Further details on the decision to design a rock ramp instead of the originally preferred option of
a pre-barrage system have been provided in Section 5.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 41
3.11.3 EIA Screening Request
Royal HaskoningDHV submitted an EIA Screening Request Letter (25/11/2015) to Midlothian
Council to confirm whether the proposed works will require a statutory Environmental Statement
to be prepared. Midlothian Council confirmed (02/12/2015) that the modification of Montagu
Bridge Weir will not require a statutory EIA. See Appendix E3 for the screening letter
responses.
3.11.4 Listed Building Consent
Listed Building Consent is the mechanism to ensure that any changes to listed buildings are
appropriate and sympathetic to their character. Listed Building Consent, specific to Montagu
Bridge, will be required for the proposed works to install a rock ramp to facilitate fish passage.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 42
4 Dalkeith Weir Design
4.1 Design approach
The first phase of the Midlothian Esk project produced a feasibility and optioneering report
(Royal HaskoningDHV, 2015) that recommended the removal of Dalkeith Weir. The design work
undertaken in this second phase of the project developed the preferred option selected at the
feasibility stage into a detailed design fit for construction. It was confirmed with the River Forth
Fisheries Trust that the weir will be removed down to bed rock level, restoring the river to its
natural condition.
The aim of the work was to remove the weir, while not significantly increasing the flow depths,
velocities or bed shear upstream or downstream of the site which could destabilise the channel.
The design was undertaken to avoid any changes to the flow regime at the Newmills Road
bridge, situated downstream of the weir, as changes to the flow regime could cause potential
instability to the structure. Another key consideration during this phase was that as the weir is
located within a Conservation Area and the design was progressed to ensure the works were
sympathetic to its local character and setting.
A detailed topographic survey (see Appendix A1 and Appendix A6) was used to create long
sections and cross sections of the reach of the South Esk under the current conditions. A 2D
surface called a Digital Elevation Model (DEM) of the existing weir and surrounding land was
built from the data gathered during the topographic survey. The DEM was used as an input to
the hydraulic model of the river which assisted in the design development. This provided a
baseline to determine the impact of the weir removal. A report on the modelling that was
undertaken is located in Appendix C1.
An iterative design process was used to determine the design solution. The design team created
designs of the weir removal and river re-profiling and detailed them onto long sections and cross
sections. These were developed into a 2D hydraulic model. The design model outputs were
compared to the existing case model outputs to see the effects of removing the weir on average
water velocity, depth and bed shear.
The design aimed to move any increased velocities and bed stresses to areas where potential
bed erosion could be tolerated, and indeed used to improve the sediment supply through the
system, and to avoid the outside of the 90 degree bend in the river. The design went through a
range of iterations to develop the preferred channel alignment.
A sediment transport model was used as an additional tool to aid the prediction of erosion and
deposition within the river channel. Further information on the modelling process and findings
can be seen in Appendix C1 and the outline design drawings are provided in Appendix D1 and
final drawings are in Appendix F1.
During the development of the design, the ECI contractor priced the outline design drawings to
support the River Forth Fisheries Trust WEF application in January. The estimated costs from
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 43
the outline design stage can be found in Appendix D2, please note this appendix contains
materials that are commercially sensitive.
4.2 Final Design Hydraulic Model Results
The final design, seen in Appendix F1, was modelled using SRH-2D and the results of the
modelling are described below.
It is noted that the design aimed to reduce the immediate impact of weir removal as far as
possible, however, the river channel is a natural system, and the river will still continue to
develop with some natural erosion and deposition.
4.2.1 Hydraulic Modelling
This section describes the hydraulic modelling undertaken for the final design. Further detail on
the hydraulic modelling and sediment transport modelling can be found in Appendix C1.
The final design was run in a 2D hydraulic model to show the velocities, depth and bed shear.
The outputs from the model runs were displayed graphically. As expected, there is an increase
in both velocity and bed shear across the channel. The largest area of scour is on a steep
naturally occurring section of the river bed, upstream of the bend in the river. This means that
the higher stresses are away from the outside bend of the river, where the banks are also the
steepest. The shear stress areas are shown in Figure 17, and would lead to some localised
erosion. Elsewhere in the design the shear stresses are reasonable and not out of character for
the available sediments.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 44
Figure 19 - Bed shears for the 2 year flow (for design).
It is important to compare the shear stresses between existing and design conditions. The
design increases stress in the section upstream of the weir as expected. The following figure,
Figure 19, compares the change in bed shear within the river channel Areas of blue indicate
where there is an increase in bed shear and so the potential (if high enough for erosion),
whereas red/yellow areas are reduced bed shear with the potential for accretion.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 45
Figure 20 - Stress difference between design and existing conditions. Cold colours are excess design stress; Hot colours are excess
existing stress. The design increases stress upstream of the weir.
The figure shows that there is a general increase in bed shear upstream of the weir location,
which is to have been expected, with the highest increase to the shear stress upstream of the
bend in the river where the slope in the river bed appears to naturally steepen and which is now
exposed to shallow water flow whereas before it was submerged in the back water effects of the
weir.
4.2.2 Sediment Transport Modelling
A sediment transport hydraulic model was used to model the proposed design. This helped
improve the understanding of the implications of the design on the river system. Further details
on the specifics of the modelling can be seen in Appendix C1. This modelling was also used as
an aid during the design process.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 46
The hydraulic modelling showed that the 2 year bank full flow presented a worst case for excess
shear in the steep sloped section upstream of the bend. The final design provides reasonable
stresses and velocities upstream of the weir: In the design area between the bend and the weir
the shear stresses peak at 120Pa on riffle crests, which would mobilize particles around 150mm
in diameter or less. However, there is a steep naturally occurring section of the design
immediately upstream of the bend. This area experiences significant shear stress (150-200Pa),
i.e. it would mobilise larger particles of up to 300mm in diameter.
The distribution of sediments is also calculated by the model and is not expected to change too
much: in the reach upstream of the weir the median particle diameter changes on average from
44mm to 41mm. Downstream of the weir there is limited deposition of sediment except in the
weir pool, and the reach d50 changes from 83mm to 70mm. Local to the largest area of erosion,
at the point of high shear, finer material (d50 20mm) is deposited on the inside of the bend and
the deepened pool is expected to have sediments of d50 60-70mm in it. It should be noted that
the weir will have collected finer material over time and so may not be representative of the
natural grading of the river bed, or what may be achieved in the future.
Results are presented for 12h and 24h into the 24h bankfull flow event to show a prediction of
how erosion and deposition of sediments may progress for the design condition with the weir
removed.
The effects of sediment transport and mobile bed materials were found to rapidly reduce the
shear stress hotspot in the steep area upstream of the bend by reducing the height of the riffle
crest upstream of the bend and reducing the slope of the steep section upstream of the bend.
The pool on the left bank downstream of the bend apex (colloquially known as Bowman’s pool)
was seen to deepen, with deposition of finer sediments on the inside of the bend.
The pool downstream of the current weir experiences deposition in the model also. Figure 21
and Figure 22 show predicted erosional and depositional areas during and after the 24h bankfull
event. Erosion is distinguished by ‘hot’ colours and deposition by ‘cold’ colours. The pattern is
broadly the same at 12h and 24h into the model run which indicates that the river rapidly
reaches a sediment equilibrium and that future events would have a much lesser impact on bed
levels. There is relatively little deposition of sediments downstream of the bridge.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 47
Figure 21 Predicted erosion (hot) and deposition (cool) after 12h bankfull flow
Figure 22 Predicted erosion (hot) and deposition (cool) after 24h banfull flow.
The hydraulic modelling work summarised that the erosional effects of the removal of the weir,
replaced by the final design, are predicted to be limited to the riffle crest upstream of the river
bend, and a deepening of Bowman’s pool on the bend. Deposition occurs mainly in the old weir
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 48
pool (which we have planned to fill with material from upstream), but also continues downstream
slightly, and in reality beyond the downstream end of the model. The model assumes an infinite
depth of sediment and as such there is no limit to erosion. In reality in the region of Bowman’s
Pool, bedrock will rapidly be reached which will limit the depth of erosion in this location.
The design has used hydraulic modelling and sediment transport modelling to show that the
removal of the weir and the designed river bed does not cause an undue risk of channel
instability or risk to other structures on the river.
4.2.3 Flood Risk
The South Esk floodplain is generally constrained, with high tops of banks, and little flood
storage, other than the flat garden area on the right, upstream of the weir. 1D modelling is
relatively well suited to represent the site because of the small amounts of flood storage in the
area. 1D models produce depth and cross section averaged hydraulic variables: water level,
energy grade 2 , velocity magnitude and bed shear stress. Further details of the flood risk
modelling are available in Appendix C1.
To determine changes to flood risk, the 1D model was run for the 2, 10, 200 and 200+ climate
change year events (which is the 200 year event plus 20% discharge). Both water level and
energy grade were compared for existing and design conditions for each flow. For all cases the
flood levels and energy grades for the design were lower than those for the existing conditions.
The design therefore does not increase flood risk. Flood risk maps are included with the
modelling reports in Appendix C1, with the 200 year flood event outline shown in the Figure 23
below.
2 Energy grade is water level plus the level that it would increase by should the flow come to rest.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 49
Figure 23 - 1 in 200 year flood map derived from 1D model levels and GIS. Design inundation is lower upstream of the weir.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 50
4.3 Final Design
4.3.1 Downstream channel wall
Data obtained from the walkovers and surveys showed that the wall which forms the
downstream sides of the weir and the section immediately downstream adjacent to the scour
pool is in a poor state of repair. It has been noted in Section 4.1 that the weir removal has been
designed to avoid changes to the flow regime downstream of the weir. However, any weir
removal works undertaken will require consideration of how the adjacent weir wing
walls/retaining walls impact on the stability of the bank when the weir is removed and as such
may need to be repaired (see Figure 244 and Figure 255).
The channel walls immediately downstream (within 10m of the weir) and adjacent to the weir act
to retain the river bank and the slope above. These walls are tied into the existing weir structure
and may be structurally integral to the weir. Removal of the weir may adversely affect these
walls causing them to degrade further and compromise the stability of the river bank and upper
slope. As a minimum the walls should be repointed and repaired, and the relationship with the
weir structure investigated at the time of the weir removal (as described in Section 4.3.3)
It should be noted that the walls of Newmills Road bridge and just downstream will not be
repaired as part of this scheme because the modelling shows that these will not be affected by
any flow regime change (see Figure 2626). It is therefore the responsibility of the riparian owner
to maintain and repair these walls.
Figure 24 - Photo looking upstream towards Dalkeith Weir. Note the open joints and missing blockwork on the wall on the right hand
side. This wall ties into the existing weir in the centre of the picture.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 51
Figure 25 - Photo looking towards Dalkeith Weir from the right bank. Note the far bank wall clad in vegetation (left bank) ties into the
existing weir.
Figure 26 - Photo looking at the downstream left-hand bank, downstream of road bridge, note the gaps in the existing bank retaining
wall. This wall is outside of the scope of works but is noted as already damaged prior to work commencing.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 52
4.3.2 Upstream Channel
The upstream channel has been designed to be re-profiled for a 200m length upstream of
Dalkeith Weir. The sides of the river banks will be re-profiled to match the adjacent river bank
gradients, which are between 1 in 1 and 1 in 2, together with deepening of the watercourse in
places.
The re-profiling of the river channel will require removal of material from site. It was discussed
with the Trust that there is potential for efficiency if the material could be used on another
construction site, such as Montagu Bridge Weir. This would require a waste permit or exemption.
Some of the material that will be removed would have been transported downstream if it had not
been impounded by the weir. This has led to sediment starvation of the downstream catchment.
The re-use of some of the excavated material elsewhere in the downstream catchment for
channel nourishment is a potential, but would need careful consideration as the size of material
excavated may not match with the requirements in lower reaches. This additional sediment
would create additional habitat downstream for spawning fish, however a plan is needed to use
this in controlled releases.
There is an expectation within the design approach that some sediment movement will occur
following the schemes completion as the channel fully develops over time. This will release
material in to the system at a faster rate to start with and will help in addressing the long term
sediment starvation, but using natural processes to transport the material rather than man made
means.
The design drawing includes setting out points for a contractor to re-profile the river based on
the design. It is noted that no works will be undertaken to the left bank around the bend in the
river, where the banks are very steep and comprised of exposed rock.
4.3.3 Weir Removal
The works involve the removal of Dalkeith Weir. The weir removal will be one of the most
complicated parts of the construction works.
Due to the highly constricted access at the site, the steep banks, deep scour hole at downstream
of the weir and protected trees on the bank, it was not considered feasible to mobilise an
intrusive survey of the weir or trial holes on the adjacent river bank. The most effective way of
doing this will be during the construction stage, when Conservation Area consent is in place and
tree removal has been approved by Midlothian Council. This will allow access to the river bank
and the weir for construction plant. This has led to assumptions been made during the design
phase. As stated in Section 2.4, historic borehole logs were used to provide limited ground
information for the design.
The design requires the removal of the weir, which will create a 3m height difference between
the new river bed level and adjacent river banks. Downstream the banks have been supported
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 53
by vertical retaining walls. Slackening of the bank at the weir is not feasible as it would
undermine the existing walls downstream and potentially extend the scale of works downstream
towards Newmills Road Bridge. Our approach has been to remove the majority of the weir in a
trapezoidal cut, which will create a 12m wide river opening at the weir location and to use the
remaining weir sections to act as a retaining wall for the banks. The remaining sections of the
weir will be grouted to form a mass concrete wall and will be faced with recycled blockstone from
the existing weir face, to keep in character with the local area and protect it from future erosion.
In addition ground anchors will be required to connect the concrete block back to the existing
ground to resist the potential for the walls to slide into the channel which could lead to the slope
above slipping.
When the contractor starts work on site they are required to perform some initial investigation to
ascertain the composition of the weir and the surrounding banks, together with a structural
condition survey of the original weir, wing walls and any weir fill material. As the weir is
demolished, records to show the constitution of the weir and depth of any encountered bed rock
must be taken by the contractor. As early as possible during the construction, but after the
results of the investigations, the contractor must consult with the client and the client’s designer
to confirm the design approach and to agree if any changes in the design are required.
4.3.4 Construction Approach
The construction approach is estimated to take 8 weeks and will require working in lower flow
conditions to make the work safer. The River Forth Fisheries Trust have stipulated that
construction works should be carried out between May and August to avoid the sensitive periods
for native migratory fish species. A construction methodology was outlined in the supporting
information with the Controlled Activities Regulations (CAR) licence and can be found in
Appendix E2. This methodology was developed in conjunction with our ECI contractor to
provide a realistic programme and construction approach that minimises the risks to the South
Esk and surrounding habitats.
As mentioned in the section above the contractor will have to liaise with the client regarding the
findings from their own investigation works on weir once the construction phase begins. This
information will help the contractor form there demolition plan for the weir and have the potential
to reduce the need for the ground anchors.
4.3.5 Finishes and reinstatement
The design was undertaken with an aim to minimise the vegetation loss at the site. To remove
any trees within the Conservation Area requires a request to Midlothian Council. The Council
has the option to place a Tree Preservation Order on any of the trees due to their presence
within the Conservation Area.
Prior to the Planning Application / Conservation Area Consent Applications being submitted, a
tree survey must be completed. Following the tree survey the information will need to be
considered in conjunction with the design and drawings updated to reflect what trees will be
affected by the proposals. The drawings will indicate what trees will not be affected, those that
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 54
will be felled and those that require protection during the works. This information will be
presented in a format appropriate for submission with the planning application.
Any tree loss should be replaced with new tree planting of similar species and where possible
size Grass removed during the construction phase should be re-seeded within the first growing
season.
4.4 Summary of Option
• The weir will be removed down to bedrock to provide a shallower gradient across the
weir site. The ends of the weir will be left in place and faced with existing weir stone to
become the river bank retaining wall.
• The river will be re-profiled for 200m upstream of the weir.
• The channel walls immediately downstream of the weir are integral to the weir will be
repaired..
• The lade will remain intact but will be above the normal water level so that river water
cannot enter unless under very high flows.
4.5 Key Risks
• There is a risk that the landowner adjacent to Dalkeith Weir objects to the proposed
works as the only access to the site will be shared with the Old Mill House.
• There is a risk that local councillors or community groups are opposed to the works
within the Conservation Area and it is advised that consultation with the landowner and
other key stakeholders is carried out prior to the works.
• Due to the difficulty and cost of undertaking investigations on the weir during the design
stage there is limited information on the weir composition.
• Historic boreholes logs were used to show the retaining wall will need ground anchors.
• The Contractor must work with the client to consider if the design is appropriate once the
weir has been exposed. The ground conditions and composition of the weir should be
recorded during the demolition.
• There is a risk that the works do not receive approval from SEPA under the Controlled
Activities Regulations.
• There is a risk that the works do not receive Conservation Area Consent from Midlothian
Council.
• Midlothian Council could decide that Planning Permission is necessary for the proposed
works.
• Trees that need to be removed to undertake the works could be given Tree Preservation
Orders due to their location within the Conservation Area.
• High river flows could delay construction works on site and cause additional costs.
• An otter licence may be required for disturbance to the holt located downstream of the
weir.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 55
5 Montagu Bridge Weir Design
5.1 Option Refinement
Following the Phase 1 work (see Section 1.2) on the Midlothian Esks the project team started
work on designing a pre-barrage structure downstream of Montagu Bridge weir. The detail of the
initial design work is presented in Appendix B2 in the Montagu Bridge Weir design note and
drawings, and a brief summary is provided below.
The findings of the topography surveys, combined with design recommendations from the
ecological survey (see Section 3 and Appendices A1 and A2) were used to inform the initial
design. A pre-barrage design based on 0.3m hydraulic head between pre-barrages was
created. The Figure 27 below shows the indicative layout of the pre-barrages.
Figure 27 - Pre-barrage arrangement (extract from Appendix B2).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 56
On review of this initial design work a number of additional practical constraints were identified.
These constraints included the views of Midlothian Council and Historic Environment Scotland in
terms of the impact on the historic environment, ecological risks associated with the potential for
nesting birds and roosting bats in the right hand retaining wall and greater construction costs
than estimated during the feasibility phase of works due to the steeper gradient and wider
channel. Further detail on these constraints and the reasoning behind altering the design can be
seen in Appendix B2 in the Montagu Bridge Weir design note.
The alternative considered to the pre-barrages was a rock ramp. This rock ramp option was
preferred for the following reasons:
1. It can provide a range of flow depths and velocities to account for all native migratory
fish species; and
2. It provides a more natural bed slope, takes up less of the channel and leaves a
significant portion of the existing weir in existing condition.
3. It does not require work near the right hand bank wall where there is a high potential for
bird nesting and bat roosting.
4. It requires less intrusive construction work, as work would only take place on one side of
the river.
5. The retaining wall would be smaller in size than the pre-barrages, therefore potentially
reducing the construction costs and the construction programme.
6. The rock ramp was confirmed as the preferred option by Historic Environment Scotland
and Midlothian Council who are key project stakeholders.
This design change received approval from the River Forth Fisheries Trust in January 2016.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 57
Figure 28 – Rock Ramp arrangement at Outline Design Stage (extract from Appendix B2).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 58
Figure 29 - Example rock ramp from FAO, Fish Passes, Design, Dimensions and Monitoring
There were some outstanding design issues to be resolved with the rock ramp:
1. Managing sufficient attraction flow away from the weir to encourage native migratory fish
species to access the rock ramp.
2. Works to the existing weir in order to control the flow into the rock ramp i.e. cutting a
notch into the weir.
3. Future monitoring of the ramp’s performance over a range of flows to check its
effectiveness for passage of fish.
5.2 Design Approach
Following the design change the project team commenced work on the rock ramp design. The
design was informed by an aquatic ecologist design note (Appendix B1) which set the fisheries
criteria required for the design. A summary of all of the criteria can be found in Section 2 of this
report.
The topographic survey was used to create long sections and cross sections of the study area,
which in turn were used to create 1D and 2D hydraulic models, to provide river flows, depths and
velocities within the study area.
The fish pass design was developed in conjunction with the criteria set by the aquatic ecologist
and the design was then added to the hydraulic model. The modelled flows in the rock ramp
were assessed against fish species data to make sure the ramp was passable to a range of
species at a range of flows.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 59
In addition during the development of the design, the ECI contractor priced the outline design
drawings to support the River Forth Fisheries Trust WEF application in January. The estimated
costs from the outline design stage can be found in Appendix D2.
The following sub-sections describe the detailed requirements of the design.
5.2.1 Operational Window
To provide the correct conditions for migration the ramp needs to provide different ranges of flow
and depth for different species at different periods in the year. In the absence of specific fish
migration data, the Environment Agency Fish Pass Manual (Armstrong et al, 2010) recommends
that a fish pass facility for upstream migration should be designed to operate across a flow range
from Q90 to Q10 for salmon, Q95 to Q10 for sea and brown trout and Q99 to Q70 for eel. There
is limited literature on Lamprey passage, however the EA Fish Pass Manual indicates sea
lamprey require passage at Q50 to Q20 and river lamprey low flows to Q30.
The operational flow window should therefore ideally be between Q99 and Q103. The figure
below gives a visualisation of the required operational window.
Figure 30 - Fish passage requirements for various species at a range if daily flows.
3 i.e. between the flow that occurs 99% of the time (a low flow) and one which occurs only 10% of the time (a higher flow).
Salmonids Trout Lamprey Eel
Q10%
Q20%
Q30%
Q40%
Q50%
Q60%
Q70%
Q80%
Q90%
Q95%
Required
Not Required
Daily Flow
Species
Required Passability
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 60
5.2.2 Hydraulic Criteria
The APEM Design note in Appendix B1 provides fish passage criteria and the table below
highlights the key criteria.
Species Max velocity (m/s) Minimum Depth (m)
Atlantic Salmon 2 0.15
Sea Trout 2 0.15
Brown Trout 2 0.1
Lamprey Species 0.5 0.08
European Eel 0.3 0.05
Figure 31 - Summary of hydraulic criteria from the APEM Design Note (Appendix B1).
5.2.3 Rock Ramp
The rock ramp was designed using the EA Fish Pass Manual (2010) and the United Nations
Food and Agricultural Organisation 2002 guidance for Fish passage (FAO, 2002), Fish Passes –
Design, dimensioning and monitoring. The EA Fish Pass Manual (2010) provided good detail on
fish pass selection and pass-ability criteria, the FAO (2002) provided specific detail about rock
ramp construction. Throughout this design phase APEM provided aquatic ecology design
support for the design of the rock ramp.
The preferred rock ramp gradient is 1 vertical in 20 horizontal.
The rock ramp maximum width could be effectively the width of the channel. However, in this
case there is a need for the existing weir to remain visible (due to heritage requirements) and for
water to pass over the weir and rock ramp simultaneously. The recommended minimum width is
2m (FAO, 2002).
Section 4 of the FAO 2002, contains information on ‘Close to Nature’ fish passes. The approach
is to use a rock ramp consisting of boulder sills perpendicular to the channel with perturbation
boulders between the sills. The boulders are aligned to slow water flow and increase depth,
however in-between each row of boulders there is a gap of least 0.4m to provide a path for all
species
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 61
Figure 32 - FAO 2002, Figure 4.20, boulder sills to break up flow in channels
.
Consideration was given to eel passage through the rock ramp, the design note produced by
aquatic ecologist, APEM, provided the following comments (full report available in Appendix
B1):
Eels are capable of locomotion both in water and on land using undulations of the body axis
(Ellerby et al., 2001), and therefore can pass very shallow features that may be impassable to
other fish species including salmonids, providing there is a suitable roughened substrate through
which they could crawl. Given that a rock ramp has a roughened bed substrate by design, such
a solution should be suitable throughout the range of flows required. In comparison to eels,
migratory river and sea lamprey do not seem to demonstrate the ability to move over land, and
there is no evidence that they can climb during their upstream migration (Russon et al., 2011;
Reinhardt et al., 2009). Notwithstanding, if suitable substrate is provided for them to crawl
through, such as that present in a rock ramp, upstream passage success of lamprey is likely to
be increased (Tummers et al., 2016), although potentially to a lesser extent than eel (Kerr et al.,
2015).
5.2.4 Resting Pool
For rock ramps longer than 30m, it is recommended that the pass has a gentle slope and deep
resting pools (FAO, 2002) to maximise its passability.
The Environment Agency Fish Pass Manual (2010), page 156, also recommends resting pools
for rock ramps that exceed a 2m head difference.
If a resting pool is used it should be a minimum of 1m deep for salmonids and a minimum length
of 3m. These design criteria have been taken into account during the design phase to maximise
the effectiveness of the rock ramp fish pass at Montagu Bridge weir.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 62
5.3 Hydraulic Modelling
5.3.1 Hydraulic Performance
The 2D hydraulic modelling undertaken by cbec eco engineering demonstrates that the rock
ramp fish pass is likely to function as a fish passable structure, with velocities in the pass largely
lower than 1m/s and water depths greater than 0.1m for flows between the Q95% and Q10%
daily flows. The full modelling report is available in Appendix C1.
The figure below shows the Q10% daily flow for the fish pass and existing river bed and
indicates a consistent water level within the fish pass of between 0.2m and 0.25m. This provides
greater than the minimum depth of 0.15m for salmonids recommend in the APEM design report
(Appendix B1).
Figure 33 - Comparison of existing impassable condition and passable condition down rock ramp at Q10% daily flow.
The modelling also produced results for Q10%, Q50% and Q95% - Figures 33, 34 and 35.
Further detail is available in the modelling report in Appendix C1.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 63
Figure 34 - Depth along rock ramp fish pass at Q95% to Q10%. Resting pool is in the middle of the ramp at around 35-40m, the
downstream end of the ramp is around chainage 68m. (Full image in the Hydraulic Modelling report in Appendix C1).
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 64
Figure 35 - Velocity magnitude along rock ramp fish pass at Q95% to Q10%. R Resting pool is in the middle of the ramp at around
35-40m, the downstream end of the ramp is around chainage 68m. (Full image in the Hydraulic Modelling report in Appendix C1).
Figure 366 compares the ideal matrix of flow frequency passability for each species with the
results obtained from the modelling. For the majority of species the water depths and velocities
at the required flow frequencies provide passable conditions.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 65
The notable exceptions are for salmonids and trout in the lower (more frequent) flows (Q60%
and below). This could be improved by increasing the depth of the notch in the weir and
narrowing the fish pass channel. However, creating a deeper notch in the weir would reduce the
water spilling over the rest of the weir, and at times there would be no flow over the weir crest.
The project team believed this would not be acceptable to the weir owner or meet heritage
requirements. Narrowing the fish pass width, would create deeper flows at low daily flows,
however this would increase the velocities at high daily flows to a point potentially too high for
lamprey passage and possibly too high even for trout and salmonids. The design has been
aimed at providing fish passage to salmonids and trout during higher flows, when migration runs
are more likely to occur.
Figure 36 - Summary of desired passability from the APEM report and achieved passability based on the hydraulic modelling.
5.3.2 Flood Risk
The 1D HEC-RAS hydraulic modelling showed that for all the design conditions in the main
channel the resulting water levels and energy grades were lower than the existing conditions.
The notch in the existing weir causes a slight reduction in water levels over the weir crest but
does not appear to increase levels downstream. It can be concluded that the design does not
increase flood risk. Further details are available in the modelling report found in Appendix C1,
including long sections comparing water depth along the model chainage. The 200 year flood
outline is shown in Figure 377.
Salmonids Trout Lamprey Eel Salmonids Trout Lamprey Eel
Q10% Q10%
Q20% Q20%
Q30% Q30%
Q40% Q40%
Q50% Q50%
Q60% Q60%
Q70% Q70%
Q80% Q80%
Q90% Q90%
Q95% Q95%
Required Achieved
Not Required Not Achieved
Not Required
Achieved Passability
Daily Flow
Species
Daily Flow
Species
Required Passability
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 66
Figure 37 - 200 year flood map. Existing conditions lower layer, design conditions upper layer. For no point is design condition
greater in extent than existing.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 67
5.4 Final Design
5.4.1 Rock Ramp
A rock ramp along the left bank was designed to account for the 2m head drop of the weir. The
end of the rock ramp ties into the existing river bed, and as a result the rock ramp is 65m in
length.
To improve the chances of successful negotiation of the ramp a resting pool has been
introduced into the ramp.
The rock ramp was designed with the following parameters:
• The weir crest is 28mAOD;
• The downstream channel level is 25mAOD;
• The gradient of the rock ramp is 1 in 20;
• The rock ramp is 65m long;
• A resting pool is positioned at the half way along the rock ramp;
• The resting pool is 3m wide, 3m long and 1.2m deep;
• Boulder sills run parallel to the river flow; and
• Perturbation boulders are used between boulder sills to break up the flow.
5.4.2 Resting Pool
Royal HaskoningDHV have been made aware that poaching of fish within this reach of the North
Esk is a potential risk.
In the current situation fish migrating upstream reach the scour pool downstream of the weir and
attempt to pass the weir. The fish collect in the pool as they are unable to pass the barrier and
are at risk of poaching during this time.
With the rock ramp in place, the passability of the weir is greatly increased, but there remains a
risk that migrating fish will be poached as they navigate through the rock ramp and resting pool.
It is considered that with the rock ramp in place the passage of fish upstream will be an
improvement to the current situation, albeit some risk of poaching remains.
The resting pool within the rock ramp is required to maximise its effectiveness and the following
were considered during the design process:
• The rock ramp is designed on the left bank of the river furthest from the access paths
increasing the difficulty of getting to the site.
• Although a grating or mesh could be used to cover the fish pass/resting pool to reduce
the risk of poaching, it was discounted due to the implications on both the appearance
(heritage impact) and maintenance (debris collection).
• A resting pool in the rock ramp is recommended by the literature to maximise the
efficiency of the fish pass and removing it would reduce this greatly.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 68
Additional mitigation to minimise the impact of poaching on the number of fish migrating
upstream should be considered, such as the planting of thorny vegetation species along the left
hand bank to inhibit access to the resting pool. However this would make future maintenance
more difficult. The potential for planting should be discussed with the landowner.
The design of the resting pool also incorporates boulders and cobbles to provide features that
fish can use as shelter when they are within the resting pool.
5.4.3 Retaining Wall
The rock ramp is supported by a U-shaped concrete wall which varies between 0.5 and 3.5m
tall.
The ‘Concrete Specification’ has been provided in the specification document alongside the
construction drawings (Appendix F1).
The retaining wall extends around 1m onto the crest of the existing weir to control the flow of
water into the rock ramp and surround the notch (see below) to maintain the ramp’s passability.
This extended wall will not be physically attached to the weir so that it can be removed in the
future if required without damaging the underlying structure.
5.4.4 Notch in the Weir
The size of the notch in the existing weir has been designed to control the volume, depth and
velocity of water in the rock ramp. In order to notch the weir, permission is needed from Historic
Environment Scotland and Midlothian Council, as part of the Listed Building Consent. Initial
consultation, as part of the pre-planning advice, was that this approach was acceptable if the fish
pass could demonstrate that it fit with the character and setting of the site.
A stop log slot has been built into the fish pass notch, to allow for the potential future regulation
of flow. This recess will allow the placement of a stop log in low flow conditions to reduce the
volume of water going into the fish pass if required.
5.4.5 Downstream Channel Works
There was concern that directing flows from the rock ramp towards the left hand side of the river
could cause scour to the bank. The design incorporates placement of roughly 2 tonne boulders,
1-2 deep within the river bank to protect it from scour. The boulders will be positioned on the
curve of the river. Small cobbles can be used to infill between the larger boulders if required.
As recommended in the APEM design report, larger boulders will also be spread across the
width of the remaining channel at the outlet of the rock ramp. This will help break up the flow
from the rest of the river and encourage fish to enter the rock ramp. An analysis of boulder size
was undertaken to calculate the mass required to resist movement during high flows, these
boulders will be 3-5T.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 69
5.4.6 Finishes and reinstatement
The finishes at the site were designed to be sympathetic with the ‘wild landscape’ downstream of
Montagu Bridge. Two options were discussed, that of a wall clad with blockwork from matching
stone as shown in Figure 388 or by a more rugged approach of boulder stone piled against the
retaining wall shown in Figure 399.
Figure 38 - Rock ramp cladding option using stone to match existing site.
The options were discussed as part of the pre-planning advice with Midlothian Council and
Historic Environment Scotland; however no preference was given at that stage but advice that
whichever option is chosen it should fit with the setting of the ‘wild designed landscape’
downstream of the weir. The project team have decided to use the boulder cladding. The
concrete walls of the rock ramp will be clad using boulders along the riverward edge to blend
with the gravel river and visible bed rock. The rock ramp itself contains boulders and gravels that
will also mimic the river channel.
Figure 39 - Rock ramp cladding option using boulders.
Any tree loss will be replaced with new tree planting. Grass removed will be re-seeded.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 70
5.4.7 Safety Considerations
During the design stage considerations were given to health and safety of the site to members of
the public and those who might undertake future maintenance on the site.
The proposed ‘rock ramp’ solution creates a fish pass structure that has a diverse range of flows
and velocities, suitable for passage of many aquatic species. The proposed solution is designed
to have minimal maintenance therefore requirements to access the rock ramp in future are
minimised.
The site is located on the left bank of the river, and access to the fish pass is through a wooded
sloping bank. A post and rail timber fence adjacent to the fish pass has been included to restrict
free public access, together with the possibly of a safety ring and signage to further discourage
access to the site. It is acknowledged that this will require consultation with the landowners and
the planning authority to ensure that the safety of the site is ensured while maintaining the
heritage of the site.
Stop log for sealing off the pass have not been included due to issues relating to safe access
and manual handling of any stop logs.
It was considered that a structure such as this fish pass should not be constructed without
consideration of appropriate access for future works or maintenance. During the works a
temporary access track will be constructed down to the river from the right bank (opposite side to
the fish pass). The River Forth Fisheries Trust should discuss the possibility of keeping this as a
permanent track down to the river with the landowner, which would facilitate a safe access route
to bring people and plant to the site. Only a small amount of temporary works would then be
required to perform any possible maintenance operations in the future.
5.5 Sediment Management Plan
The issue of sediment transport downstream of Montagu Bridge Weir is considered an important
aspect in the development of a good ecological status for the North Esk. It is noted that it is not
possible to remove Montagu Bridge Weir due to its listed status. This causes an issue in trying to
achieve sediment movement past the weir. As part of this project, a sediment management plan
was developed to consider an approach to management sediment in the North Esk downstream
of Montagu Bridge Weir. The full Sediment Management Plan report is provided in Appendix I1.
The report provided an assessment of the role of the Montagu Bridge weir in the context of
sedimentary processes of the North Esk in its entirety, concluding that the current disruption to
sediment transport associated with the structure has only a limited impact on the sedimentary
regime of the river.
The report, therefore, suggests that sediment management measures at this site are not likely to
be cost-effective and will be unlikely to deliver substantial benefits to the morphological
dynamics and associated quality of in-channel habitats at this site and the river system
downstream.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 71
5.6 Summary of Design
A rock ramp, of width 4m, will be built on the left bank of the North Esk from Montagu Bridge
weir for a 65m length downstream. The ramp will contain boulder sills and perturbation boulders
that will break up the flow creating a diverse range of flow depths and velocities that fish can use
to migrate upstream. Due to the length a resting pool will be built into the rock ramp. Scour
protection to the banks will be placed downstream from large boulders and a resting pool at the
toe of the ramp.
5.7 Key Assumptions
• The bedrock downstream of the weir is 32mAOD and excavation will be too 31.5mAOD.
• The existing river banks are stable.
• The Q95 river flow is 0.577m3/s.
• The Q10 river flow is 4.67m3/s.
5.8 Key Risks
• There is a risk that the landowner objects to the proposed works, despite their
engagement in the process to date.
• There is a risk that the works do not receive Planning Consent or Listed Building Consent
due to stakeholders being opposed to the works.
• There is a risk that the works do not receive approval from SEPA under the Controlled
Activities Regulations.
• There is a risk that planning conditions imposed by Midlothian Council require different
and potentially more expensive finishes than the cost estimate includes.
• High river flows could delay works on site and cause additional costs.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 72
6 Information to support the contractor
Additional design information to support the contractor can be found in the Construction Design
and Management Regulations 2015 (CDM) hazard log, Specification and Pre-Construction
Information documents in Appendix F2 and Appendix G1.
The CDM hazard log provides a list of risks and decisions undertaken at the design stage that a
contractor should review during the construction stage.
The Specification is for the works at for both sites and contains additional information for the
contractor that was not appropriate to place on the construction drawings.
The pre-construction information is a document the client can provide to the contractor to
discharge one of their duties under the Construction Design and Management Regulations 2015.
The document provides all the information the client understands about the site and the
constraints to the contractor to help them plan and manage the construction phase of the
project.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 73
7 Conclusion and Recommendations
7.1 Conclusion
7.1.1 Dalkeith Weir
At Dalkeith Weir, the removal of the weir has been designed and modelled by a team of
engineers, geomorphologists, ecologists and heritage consultants. The removal of this weir will
open up the river to sediment transport and facilitate the passage of migratory fish, meeting the
project objectives set out by the River Forth Fisheries Trust to reinstate natural processes. The
design drawings are appended to this report in Appendix F1.
In accompaniment of the design the following applications have been completed, as far as
possible. These consents must be in place prior to the commencement of any construction
works. These draft applications are found in the appendices within Appendix E.
• CAR Authorisation (4 month determination period); and
• Conservation Area Consent (2 month determination period).
7.1.2 Montagu Bridge Weir
At Montagu Bridge Weir, a solution to allow migratory fish to pass the barrier has been designed
and modelled by a team of engineers, geomorphologists, ecologists and heritage consultants. A
fish pass has been designed to allow the upstream migration of the range of native migratory
fish species present in the North Esk across a range of flows. The design was sympathetic to
the local character and setting of the site to allow fish migration without detracting from the listed
structure and its setting. The design drawings are in appended to this report in Appendix F1.
In accompaniment of the design the following applications have been completed, as far as
possible. These consents must be in place prior to the commencement of any construction
works. These draft applications are found in the appendices within Appendix E.
• Planning Application (2 months determination period);
• Listed Building Consent (2 months determination period);and
• CAR Authorisation (4 months determination period).
7.2 Recommended Next Steps
7.2.1 Licences and Permits
As stated in Sections 7.1.1 and 7.1.2 above, the required consents and licences must be in
place prior to works commencing. There are a number of outstanding issues to be resolved by
the River Forth Fisheries Trust before these applications can be submitted with regard to liability.
A note has been provided alongside the draft applications on the outstanding requriments.
It should also be noted that a tree survey must be completed, for both sites, to accompany these
consent applications. The tree survey will need to be processed to reflect what trees will be
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 74
affected by the proposals i.e. not affected, felled or require protection. This information will be
presented in a format appropriate for the Planning Application (Montagu Bridge
Weir)/Conservation Area Consent application (Dalkeith Weir). The work required will include the
survey, GIS time, engineer input and time to present to planning authority. Once this is
completed the applications can be submitted.
Once the planning application is submitted the River Forth Fisheries Trust will have to support
and answer any queries that occur from the planning process. It is also likely that planning
conditions will accompany the consent and will need to be discharged prior to the
commencement of work.
7.2.2 Vegetation Clearance
The construction works are proposed for summer working (May to September), to ensure that
the most sensitive periods for in-river working are avoided. It is recommended that prior to the
bird breeding period, specialist vegetation clearance is undertaken to remove potential bird
nesting habitat, which could prevent the construction works from occurring within that season.
This would be best done in the winter months prior to the construction. It is advisable to have an
ecologist on site during this vegetation clearance.
While vegetation management is being undertaken it is also advisable that the River Forth
Fisheries Trust consider the clearance of invasive species noted in the ecology survey. This
would reduce the risk of the spread of invasive species during the construction works.
7.2.3 Photographic Weir Surveys
It is expected that a photographic record of the weir structures before construction work will need
to be undertaken, and this is likely to be enforced as a condition for the Conservation Area
Consent (Dalkeith Weir) and potentially a Planning condition/Listed Building Consent condition
(Montagu Bridge Weir). These surveys will need to be undertaken by a heritage specialist.
7.2.4 Appointing a Contractor
The River Forth Fisheries Trust will need to appoint a contractor to undertake the works. The
Trust will need to decide on the type of contract for the work and prepare tender documents. The
Trust will need to issue the tender to interested contractor and give a period of 6-8 weeks to
tender for the works. During this time the Trust will have to answer questions on the tender from
the bidding contractors. It is recommended that the trust take the tendering contractors to the
site to undertake a site walkover to familiarise themselves with the site and the access
constraints.
While the contract documents are being developed it is advisable that the River Forth Fisheries
Trust update the Pre-Construction Information document, produced as part of the design stage,
with any latest developments, for example planning conditions or landowner constraints.
This process of appointing a contractor could take 3-4 months, so it is recommended that the
compilation of tender documents starts in January/February of the year the construction will
occur so that the contractor is appointed in time to start construction in the summer months.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 75
7.2.5 Construction Stage
Royal HaskoningDHV recommend that the work is undertaken in the summer months to avoid
sensitive periods for in-river working and also have a greater potential of lower river flows. At
both sites the construction period is estimated to be 8 weeks in duration. Starting at the end of
May or beginning of June would be preferred. If any delays were to occur to the programme,
there would still be summer working allowed in August.
The Trust should consider the Construction, Design and Management Regulations 2015 (CDM
2015) in the work they are doing, the Trust will undertake the CDM role of a Client. Information is
available from the Health and Safety Executives website on the duties of all parties involved in
construction projects.
The HSE website states that Client duties include:
Make suitable arrangements for managing a project, including making sure:
• other duty-holders are appointed as appropriate;
• sufficient time and resources are allocated.
Make sure:
• relevant information is prepared and provided to other duty holders;
• the principal designer and principal contractor carry out their duties; and
• welfare facilities are provided.
7.2.6 Future Monitoring of Montagu Bridge Weir Fish Pass
Fish pass guidance recommends future monitoring of rock ramps to assess their passability and
provide evidence if adjustments to the boulder positions are needed. We have consulted with
APEM, our aquatic ecologist, to develop a price for monitoring the rock ramp over a period of
high and low flows for one year. Ideally this will be to monitor for 2 months (1 month in summer
and another month in winter). In additional a visual inspection of the pass under a range of flows
could be undertaken to determine where flows may be too high, or depths too shallow,
throughout the pass, and thus where adaptations may be required. We have provided cost
estimates for a consultant to undertake the work, but note that the Trust may be able to
undertake the work themselves at considerably reduced cost. We recommend that this would be
undertaken in the year after construction.
Following the monitoring, the rock ramp may need amendments to the boulder positions to alter
the flows if it is believed the flow regime is sub-optimal for fish migration during some flow
conditions. This item should be considered a risk item as it may not be needed. However,
current literature suggests that it is prudent to plan for minor modifications. It is noted that this is
not a change to the fish pass super-structure and would likely consist of the following
construction activities:
• Re-position of boulders.
• Placing additional boulders.
• Changing the size of the weir notch.
A cost estimate for this is provided in Appendix D2.
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 A
Appendix A – Site Investigation Data
Appendix A contains the following information, split into information about each weir:
A1 – Topographic survey
A2 – Ecology Survey
A3 – Sediment Sampling
A4 – Geophysical Survey
A5 – Historic Borehole logs
A6 – Sections and utilities
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 B
Appendix B – Desgin Technical Notes
Appendix B contains the following:
B1 – APEM Design Note
B2 – Montagu Bridge Weir Design Note
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 C
Appendix C – Hydrualic Modelling
Appendix C contains the following:
C1 – Hydraulic Modelling
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 D
Appendix D – Outline Design
Appendix D contains the following:
D1 – Outline Design
D2 – Cost Estimate
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 E
Appendix E – Licences and Permits
Appendix E contains the following:
E1 – Heritage Report
E2 – Draft CAR Licence Applications
E3 – Draft Planning Application (Montagu Bridge Weir)
E4 – Visualisations
E5 – Draft Listed Building Consent (Montagu Bridge Weir)
E6 – Draft Conservation Area Consent (Dalkeith Weir)
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 F
Appendix F – Construction Drawings
Appendix F contains the following:
F1 - Construction Drawings
F2 - CDM Hazard Log
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 G
Appendix G – Pre-construction information
Appendix F contains the following:
G1 - Pre-construction information
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 H
Appendix H – CDM 2015 Letters
Appendix F contains the following:
H1 – CDM 2015 Appointment Letters
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 I
Appendix I – Sediment Manegment Plan
Appendix I contains the following:
I1 – Sediment Management Plan
10/05/201610/05/2016 ESK PHASE 2A WATPB4209R001F01 J
Appendix J – Communications Log
Appendix J contains the following:
J1 – Communications Log