Transcript of Midi's Free ITTO Spreadsheet
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
506 506 0 506 506 506 506Title Type Knowledge area Process group CAT Activity
Accepted Deliverable Result/Product Scope Management Monitoring & Controlling Output Verify ScopeAccepted Deliverables Result/Product Project Integration Management Closing Input Close Project or Phase
Acquisition Technique HR Management Executing T&T Acquire Project TeamActivity Attributes Artifact/Document Time Management Planning Output Define ActivitiesActivity Attributes Artifact/Document Time Management Planning Input Sequence ActivitiesActivity Attributes Artifact/Document Time Management Planning Input Estimate Activity ResourcesActivity Attributes Artifact/Document Time Management Planning Input Estimate Activity DurationsActivity Attributes Artifact/Document Time Management Planning Input Develop Schedule
Activity Cost Estimate Artifact/Document Cost Management Planning Output Estimate CostsActivity Cost Estimate Artifact/Document Cost Management Planning Input Determine BudgetActivity Cost Estimate Artifact/Document Risk Management Planning Input Plan Risk managementActivity Cost Estimate Artifact/Document Procurement Management Planning Input Plan Procurements
Activity Duration Estimates Artifact/Document Time Management Planning Output Estimate Activity DurationsActivity Duration Estimates Artifact/Document Time Management Planning Input Develop ScheduleActivity Duration Estimates Artifact/Document Risk Management Planning Input Identify Risks
Activity List Artifact/Document Time Management Planning Output Define ActivitiesActivity List Artifact/Document Time Management Planning Input Sequence ActivitiesActivity List Artifact/Document Time Management Planning Input Estimate Activity ResourcesActivity List Artifact/Document Time Management Planning Input Estimate Activity DurationsActivity List Artifact/Document Time Management Planning Input Develop Schedule
Activity Resource Requirements Artifact/Document Time Management Planning Output Estimate Activity ResourcesActivity Resource Requirements Artifact/Document Time Management Planning Input Estimate Activity DurationsActivity Resource Requirements Artifact/Document Time Management Planning Input Develop ScheduleActivity Resource Requirements Artifact/Document HR Management Planning Input Develop HR PlanActivity Resource Requirements Artifact/Document Procurement Management Planning Input Plan ProcurementsAdditional Quality Planning Tools Technique Quality Management Planning T&T Plan Quality
Adjusting Leads and Lags Technique Time Management Monitoring & Controlling T&T Control ScheduleAdvertising Technique Procurement Management Executing T&T Conduct Procurements
Alternative Analysis Technique Time Management Planning T&T Estimate Activity ResourcesAlternative Identification Technique Scope Management Planning T&T Define ScopeAnalogous Estimating Technique Time Management Planning T&T Estimate Activity Durations
Applying Leads and Lags Technique Time Management Planning T&T Sequence ActivitiesApplying Leads and Lags Technique Time Management Planning T&T Develop Schedule
Approved Change Requests Artifact/Document Project Integration Management Executing Input Direct and Manage Project ExecutionApproved Change Requests Artifact/Document Quality Management Monitoring & Controlling Input Perform Quality ControlApproved Change Requests Artifact/Document Procurement Management Monitoring & Controlling Input Administer Procurements
Approved Change Requests Review Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality ControlAssumptions Analysis Technique Risk Management Planning T&T Identify Risks
Basis of Estimates Artifact/Document Cost Management Planning Output Estimate CostsBasis of Estimates Artifact/Document Cost Management Planning Input Determine Budget
Benchmarking Technique Quality Management Planning T&T Plan QualityBidder Conferences Technique Procurement Management Executing T&T Conduct Procurements
Bottom-Up Estimating Technique Time Management Planning T&T Estimate Activity ResourcesBudget Forecast Artifact/Document Cost Management Monitoring & Controlling Output Control CostsBudget Forecasts Artifact/Document Communication Management Monitoring & Controlling Input Report Performance
Business Case Artifact/Document Project Integration Management Initiation Input Create Project CharterCause and Effect Diagram Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality ControlChange Control Meetings Technique Project Integration Management Monitoring & Controlling T&T Change Control Meetings
Change Log Artifact/Document Communication Management Executing Input Manage Stakeholder ExpectationsChange Request Status Updates Artifact/Document Project Integration Management Monitoring & Controlling Output Monitor and Control Project Work
Change Requests Artifact/Document Project Integration Management Executing Input Direct and Manage Project ExecutionChange Requests Artifact/Document Project Integration Management Monitoring & Controlling Input Perform Integrated Change ControlChange Requests Artifact/Document Scope Management Monitoring & Controlling Output Verify ScopeChange Requests Artifact/Document Scope Management Monitoring & Controlling Output Control ScopeChange Requests Artifact/Document Time Management Monitoring & Controlling Output Control ScheduleChange Requests Artifact/Document Quality Management Executing Output Perform Quality AssuranceChange Requests Artifact/Document Quality Management Monitoring & Controlling Output Perform Quality ControlChange Requests Artifact/Document HR Management Executing Output Manage Project TeamChange Requests Artifact/Document Communication Management Executing Output Distribute InformationChange Requests Artifact/Document Communication Management Monitoring & Controlling Output Report PerformanceChange Requests Artifact/Document Risk Management Monitoring & Controlling Output Monitor & Control RisksChange Requests Artifact/Document Procurement Management Planning Output Plan ProcurementsChange Requests Artifact/Document Procurement Management Executing Output Conduct ProcurementsChange Requests Artifact/Document Procurement Management Monitoring & Controlling Output Administer ProcurementsChecklist Analysis Technique Risk Management Planning T&T Identify RisksChecklist Analysis Technique Risk Management Planning T&T Identify Risks
Claims Administration Technique Procurement Management Monitoring & Controlling T&T Administer ProcurementsClosed Procurements Artifact/Document Procurement Management Closing Input Close Procurements
Co-location Technique HR Management Executing T&T Develop Project TeamCommunications Management Plan Artifact/Document Communication Management Planning Output Plan Communications
Communications Methods Technique Communication Management Planning T&T Plan CommunicationsCommunications Methods Technique Communication Management Executing T&T Distribute InformationCommunications Methods Technique Communication Management Executing T&T Manage Stakeholder ExpectationsCommunications Methods Technique Communication Management Monitoring & Controlling T&T Report PerformanceCommunications Models Technique Communication Management Planning T&T Plan Communications
Communications Requirements Analysis Technique Communication Management Planning T&T Plan CommunicationsCommunications Technology Technique Communication Management Planning T&T Plan Communications
Conflict Management Artifact/Document HR Management Executing T&T Manage Project TeamContingent Response Strategies Technique Risk Management Planning T&T Plan Risk Responses
Contract Artifact/Document Project Integration Management Initiation Input Create Project CharterContract Change Control System Technique Procurement Management Monitoring & Controlling T&T Administer Procurements
Contract Types Technique Procurement Management Planning T&T Plan ProcurementsContracts Artifact/Document Cost Management Planning Input Determine Budget
Control Charts Artifact/Document Quality Management Planning T&T Plan QualityControl Charts Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality Control
Cost Aggregation Technique Cost Management Planning T&T Determine BudgetCost Management Plan Artifact/Document Risk Management Planning Input Plan Risk Management
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Cost Management Plan Artifact/Document Risk Management Planning Input Identify RisksCost Management Plan Artifact/Document Risk Management Planning Input Perform Quantitative Risk Management
Cost of Quality Influence Cost Management Planning T&T Estimate CostsCost of Quality Influence Quality Management Planning T&T Plan Quality
Cost Performance Baseline Artifact/Document Cost Management Planning Output Determine BudgetCost Performance Baseline Artifact/Document Quality Management Planning Input Plan QualityCost Performance Baseline Artifact/Document Procurement Management Planning Input Plan Procurements
Cost-Benefit Analysis Technique Quality Management Planning T&T Plan QualityCritical Chain Method Technique Time Management Planning T&T Develop ScheduleCritical Path Method Technique Time Management Planning T&T Develop Schedule
Technique Risk Management Planning T&T Perform Quantitative Risk ManagementDecomposition Technique Scope Management Planning T&T Create WBS
Deliverable Result/Product Project Integration Management Executing Output Direct and Manage Project ExecutionDependency Determination Technique Time Management Planning T&T Sequence Activities
Design of Experiments Technique Quality Management Planning T&T Plan QualityDiagramming Techniques Technique Risk Management Planning T&T Identify RisksDocumentation Reviews Technique Risk Management Planning T&T Identify Risks
Earned Value Management Technique Cost Management Monitoring & Controlling T&T Control CostsEnterprise Environmental Factors Group of influences Project Integration Management Initiation Input Create Project CharterEnterprise Environmental Factors Group of influences Project Integration Management Planning Input Develop Project Management PlanEnterprise Environmental Factors Group of influences Project Integration Management Executing Input Direct and Manage Project ExecutionEnterprise Environmental Factors Group of influences Project Integration Management Monitoring & Controlling Input Monitor and Control Project WorkEnterprise Environmental Factors Group of influences Project Integration Management Monitoring & Controlling Input Perform Integrated Change ControlEnterprise Environmental Factors Group of influences Time Management Planning Input Define ActivitiesEnterprise Environmental Factors Group of influences Time Management Planning Input Estimate Activity ResourcesEnterprise Environmental Factors Group of influences Time Management Planning Input Estimate Activity DurationsEnterprise Environmental Factors Group of influences Time Management Planning Input Develop ScheduleEnterprise Environmental Factors Group of influences Cost Management Planning Input Estimate CostsEnterprise Environmental Factors Group of influences Quality Management Planning Input Plan QualityEnterprise Environmental Factors Group of influences HR Management Planning Input Develop HR PlanEnterprise Environmental Factors Group of influences HR Management Executing Input Acquire Project TeamEnterprise Environmental Factors Group of influences HR Management Executing Input Develop Project TeamEnterprise Environmental Factors Group of influences Communication Management Initiation Input Identify StakeholdersEnterprise Environmental Factors Group of influences Communication Management Planning Input Plan CommunicationsEnterprise Environmental Factors Group of influences Risk Management Planning Input Plan Risk ManagementEnterprise Environmental Factors Group of influences Risk Management Planning Input Identify RisksEnterprise Environmental Factors Group of influences Procurement Management Planning Input Plan Procurements
Group of influences HR Management Executing Output Develop Project Team
Group of influences HR Management Executing Output Manage Project TeamExpert Judgment Technique Project Integration Management Initiation T&T Create Project CharterExpert Judgment Technique Project Integration Management Planning T&T Develop Project Management PlanExpert Judgment Technique Project Integration Management Executing T&T Direct and Manage Project ExecutionExpert Judgment Technique Project Integration Management Monitoring & Controlling T&T Monitor and Control Project WorkExpert Judgment Technique Project Integration Management Monitoring & Controlling T&T Perform Integrated Change ControlExpert Judgment Technique Project Integration Management Closing T&T Close Project or PhaseExpert Judgment Technique Scope Management Planning T&T Define ScopeExpert Judgment Technique Time Management Planning T&T Define ActivitiesExpert Judgment Technique Time Management Planning T&T Estimate Activity ResourcesExpert Judgment Technique Time Management Planning T&T Estimate Activity DurationsExpert Judgment Technique Cost Management Planning T&T Estimate CostsExpert Judgment Technique Cost Management Planning T&T Determine BudgetExpert Judgment Technique Communication Management Initiation T&T Identify StakeholdersExpert Judgment Technique Risk Management Planning T&T Identify RisksExpert Judgment Technique Risk Management Planning T&T Perform Qualitative Risk ManagementExpert Judgment Technique Risk Management Planning T&T Perform Quantitative Risk ManagementExpert Judgment Technique Risk Management Planning T&T Plan Risk ResponsesExpert Judgment Technique Procurement Management Planning T&T Plan ProcurementsExpert Judgment Technique Procurement Management Executing T&T Conduct Procurements
Facilitated Workshops Technique Scope Management Planning T&T Collect RequirementsFacilitated Workshops Technique Scope Management Planning T&T Define Scope
Artifact/Product Project Integration Management Closing Output Close Project or PhaseFlow Charting Technique Quality Management Planning T&T Plan QualityFlow Charting Technique Quality Management Monitoring & Controlling T&T Perform Quality ControlFocus Groups Technique Scope Management Planning T&T Collect RequirementsForecasting Technique Cost Management Monitoring & Controlling T&T Control CostsForecasting Technique Communication Management Monitoring & Controlling T&T Report Performance
Funding Limit Reconciliation Technique Cost Management Planning T&T Determine BudgetGround Rules Technique HR Management Executing T&T Develop Project Team
Group Decision making Techniques Technique Scope Management Planning T&T Collect RequirementsHistogram Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality Control
Historical Relationships Technique Cost Management Planning T&T Determine BudgetHR Plan Artifact/Document Cost Management Planning Input Estimate CostsHR Plan Artifact/Document HR Management Planning Output Develop HR Plan
Independent Estimates Technique Procurement Management Executing T&T Conduct ProcurementsInformation Distribution Tools Tools Communication Management Executing T&T Distribute Information
Information Gathering Techniques Technique Risk Management Planning T&T Identify RisksInspection Technique Scope Management Monitoring & Controlling T&T Verify ScopeInspection Technique Quality Management Monitoring & Controlling T&T Perform Quality Control
Inspections & Audits Technique Procurement Management Monitoring & Controlling T&T Administer ProcurementsInternet Search Technique Procurement Management Executing T&T Conduct Procurements
Interpersonal Skills Technique HR Management Executing T&T Develop Project TeamInterpersonal Skills Technique HR Management Executing T&T Manage Project TeamInterpersonal Skills Technique Communication Management Executing T&T Manage Stakeholder Expectations
Interviews Technique Scope Management Planning T&T Collect RequirementsIssue Log Artifact/Document HR Management Executing T&T Manage Project TeamIssue Log Artifact/Document Communication Management Executing Input Manage Stakeholder Expectations
Data Gathering & Representative Techniques
Enterprise Environmental Factors Updates
Enterprise Environmental Factors Updates
Final Product, Service, or Result Transition
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Make or Buy Analysis Technique Procurement Management Planning T&T Plan ProcurementsMake or Buy Decisions Artifact/Document Procurement Management Planning Output Plan ProcurementsMake or Buy Decisions Artifact/Document Procurement Management Executing Input Conduct Procurements
Management Skills Artifact/Document Communication Management Executing T&T Manage Stakeholder ExpectationsMilestone List Artifact/Product Time Management Planning Output Define ActivitiesMilestone List Artifact/Product Time Management Planning Input Sequence Activities
Negotiated Settlements Technique Procurement Management Closing T&T Close ProcurementsNegotiation Technique HR Management Executing T&T Acquire Project TeamNetworking Artifact/Product HR Management Planning T&T Develop HR Plan
Observations Technique Scope Management Planning T&T Collect Requirements
Artifact/Product HR Management Planning T&T Develop HR PlanOrganizational Process Assets Group of assets Project Integration Management Initiation Input Create Project CharterOrganizational Process Assets Group of assets Project Integration Management Planning Input Develop Project Management PlanOrganizational Process Assets Group of assets Project Integration Management Executing Input Direct and Manage Project ExecutionOrganizational Process Assets Group of assets Project Integration Management Monitoring & Controlling Input Monitor and Control Project WorkOrganizational Process Assets Group of assets Project Integration Management Monitoring & Controlling Input Perform Integrated Change ControlOrganizational Process Assets Group of assets Scope Management Planning Input Create WBSOrganizational Process Assets Group of assets Scope Management Planning Input Define ScopeOrganizational Process Assets Group of assets Scope Management Monitoring & Controlling Input Control ScopeOrganizational Process Assets Group of assets Time Management Planning Input Define ActivitiesOrganizational Process Assets Group of assets Time Management Planning Input Sequence ActivitiesOrganizational Process Assets Group of assets Time Management Planning Input Estimate Activity ResourcesOrganizational Process Assets Group of assets Time Management Planning Input Estimate Activity DurationsOrganizational Process Assets Group of assets Time Management Planning Input Develop ScheduleOrganizational Process Assets Group of assets Time Management Monitoring & Controlling Input Control ScheduleOrganizational Process Assets Group of assets Cost Management Planning Input Estimate CostsOrganizational Process Assets Group of assets Cost Management Planning Input Determine BudgetOrganizational Process Assets Group of assets Cost Management Monitoring & Controlling Input Control CostsOrganizational Process Assets Group of assets Quality Management Planning Input Plan QualityOrganizational Process Assets Group of assets Cost Management Monitoring & Controlling Input Perform Quality ControlOrganizational Process Assets Group of assets HR Management Planning Input Develop HR PlanOrganizational Process Assets Group of assets HR Management Executing Input Acquire Project TeamOrganizational Process Assets Group of assets HR Management Executing Input Manage Project TeamOrganizational Process Assets Group of assets Communication Management Initiation Input Identify StakeholdersOrganizational Process Assets Group of assets Communication Management Planning Input Plan CommunicationsOrganizational Process Assets Group of assets Communication Management Executing Input Distribute InformationOrganizational Process Assets Group of assets Communication Management Executing Input Manage Stakeholder ExpectationsOrganizational Process Assets Group of assets Communication Management Monitoring & Controlling Input Report PerformanceOrganizational Process Assets Group of assets Risk Management Planning Input Plan Risk ManagementOrganizational Process Assets Group of assets Risk Management Planning Input Identify RisksOrganizational Process Assets Group of assets Risk Management Planning Input Perform Qualitative Risk ManagementOrganizational Process Assets Group of assets Risk Management Planning Input Perform Quantitative Risk ManagementOrganizational Process Assets Group of assets Procurement Management Planning Input Plan ProcurementsOrganizational Process Assets Group of assets Procurement Management Executing Input Conduct Procurements
Organizational Process Assets Updates Group of assets Project Integration Management Closing Output Close Project or Phase
Organizational Process Assets Updates Group of assets Scope Management Monitoring & Controlling Output Control Scope
Organizational Process Assets Updates Group of assets Time Management Monitoring & Controlling Output Control Schedule
Organizational Process Assets Updates Group of assets Time Management Monitoring & Controlling Output Control Costs
Organizational Process Assets Updates Group of assets Cost Management Monitoring & Controlling Output Perform Quality Control
Organizational Process Assets Updates Group of assets HR Management Executing Output Manage Project Team
Organizational Process Assets Updates Group of assets Communication Management Executing Output Distribute Information
Organizational Process Assets Updates Group of assets Communication Management Executing Output Manage Stakeholder Expectations
Organizational Process Assets Updates Group of assets Communication Management Monitoring & Controlling Output Monitor and Control Project Work
Organizational Process Assets Updates Group of assets Risk Management Monitoring & Controlling Output Monitor & Control Risks
Organizational Process Assets Updates Group of assets Procurement Management Monitoring & Controlling Output Administer ProcurementsOrganizational Theory Artifact/Product HR Management Planning T&T Develop HR Plan
Outputs from Planning Process Artifact/Document Project Integration Management Planning Input Develop Project Management PlanParametric Estimating Technique Time Management Planning T&T Estimate Activity Durations
Pareto Chart Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality ControlPayment Systems Artifact/Document Procurement Management Monitoring & Controlling T&T Administer Procurements
Performance Reporting Artifact/Document Procurement Management Monitoring & Controlling T&T Administer ProcurementsPerformance Reports Artifact/Document Project Integration Management Monitoring & Controlling Input Monitor and Control Project WorkPerformance Reports Artifact/Document HR Management Executing Input Manage Project TeamPerformance Reports Artifact/Document Communication Management Executing Input Distribute InformationPerformance Reports Artifact/Document Communication Management Monitoring & Controlling Output Report PerformancePerformance Reports Artifact/Document Risk Management Monitoring & Controlling Input Monitor & Control RisksPerformance Reports Artifact/Document Project Integration Management Monitoring & Controlling Input Administer ProcurementsPerformance Reviews Artifact/Document Time Management Monitoring & Controlling T&T Control SchedulePerformance Reviews Artifact/Document Cost Management Monitoring & Controlling T&T Control CostsPerformance Reviews Artifact/Document Procurement Management Monitoring & Controlling T&T Administer Procurements
Technique Quality Management Executing T&T Perform Quality AssurancePre-assignment Technique HR Management Executing T&T Acquire Project Team
Precedence Diagramming Method Technique Time Management Planning T&T Sequence ActivitiesProbability & Impact Assessment Technique Risk Management Planning T&T Perform Qualitative Risk Management
Process Analysis Technique Quality Management Executing T&T Perform Quality AssuranceProcess Improvement Plan Artifact/Document Quality Management Planning Output Plan Quality
Organization Charts &Position Descriptions
Plan Quality and Perform Quality Control tools and techniques
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Procurement Audits Technique Procurement Management Closing T&T Close ProcurementsProcurement Contract Award Artifact/Document Procurement Management Executing Output Conduct ProcurementsProcurement Documentation Artifact/Document Procurement Management Monitoring & Controlling Output Administer ProcurementsProcurement Documentation Artifact/Document Procurement Management Monitoring & Controlling Input Close Procurements
Procurement Documents Artifact/Document Communication Management Initiation Input Identify StakeholdersProcurement Documents Artifact/Document Procurement Management Planning Output Plan ProcurementsProcurement Documents Artifact/Document Procurement Management Executing Input Conduct ProcurementsProcurement Documents Artifact/Document Procurement Management Monitoring & Controlling Input Administer Procurements
Procurement Management Plan Artifact/Document Procurement Management Planning Output Plan ProcurementsProcurement Negotiations Technique Procurement Management Executing T&T Conduct Procurements
Procurement Performance Reviews Technique Procurement Management Monitoring & Controlling T&T Administer ProcurementsProcurement Statement of Work Artifact/Document Procurement Management Planning Output Plan Procurements
Product Analysis Technique Scope Management Planning T&T Define ScopeProject Charter Artifact/Document Project Integration Management Initiation Input Develop Project Management PlanProject Charter Artifact/Document Project Integration Management Initiation Output Create Project CharterProject Charter Artifact/Document Scope Management Planning Input Collect RequirementsProject Charter Artifact/Document Scope Management Planning Input Define Scope
Project Document Updates Artifact/Document Project Integration Management Executing Output Direct and Manage Project ExecutionProject Document Updates Artifact/Document Project Integration Management Monitoring & Controlling Output Monitor and Control Project WorkProject Document Updates Artifact/Document Project Integration Management Monitoring & Controlling Output Perform Integrated Change ControlProject Document Updates Artifact/Document Scope Management Planning Output Collect RequirementsProject Document Updates Artifact/Document Scope Management Planning Output Define ScopeProject Document Updates Artifact/Document Scope Management Monitoring & Controlling Output Verify ScopeProject Document Updates Artifact/Document Scope Management Monitoring & Controlling Output Control ScopeProject Document Updates Artifact/Document Time Management Planning Output Sequence ActivitiesProject Document Updates Artifact/Document Time Management Planning Output Estimate Activity ResourcesProject Document Updates Artifact/Document Time Management Planning Output Estimate Activity DurationsProject Document Updates Artifact/Document Time Management Planning Output Develop ScheduleProject Document Updates Artifact/Document Time Management Monitoring & Controlling Output Monitor and Control ScheduleProject Document Updates Artifact/Document Cost Management Planning Output Estimate CostsProject Document Updates Artifact/Document Cost Management Planning Output Determine BudgetProject Document Updates Artifact/Document Cost Management Monitoring & Controlling Output Control CostsProject Document Updates Artifact/Document Quality Management Planning Output Plan QualityProject Document Updates Artifact/Document Quality Management Executing Output Perform Quality AssuranceProject Document Updates Artifact/Document Quality Management Monitoring & Controlling Output Perform Quality ControlProject Document Updates Artifact/Document Communication Management Planning Output Plan CommunicationsProject Document Updates Artifact/Document Communication Management Executing Output Manage Stakeholder ExpectationsProject Document Updates Artifact/Document Risk Management Planning Output Plan Risk ResponsesProject Document Updates Artifact/Document Risk Management Monitoring & Controlling Output Monitor & Control RisksProject Document Updates Artifact/Document Procurement Management Executing Output Conduct Procurements
Project Documents Artifact/Document Risk Management Planning Input Identify RisksProject Documents Artifact/Document Procurement Management Executing Input Conduct Procurements
Project Funding Requirements Artifact/Document Cost Management Monitoring & Controlling Output Determine BudgetProject Funding Requirements Artifact/Document Cost Management Monitoring & Controlling Input Control Costs
Artifact/Document Cost Management Planning T&T Estimate Costs
Group of Tools Project Integration Management Executing T&T Direct and Manage Project ExecutionProject Management Plan Artifact/Document Project Integration Management Planning Output Develop Project Management PlanProject Management Plan Artifact/Document Project Integration Management Executing Input Direct and Manage Project ExecutionProject Management Plan Artifact/Document Project Integration Management Monitoring & Controlling Input Perform Integrated Change ControlProject Management Plan Artifact/Document Project Integration Management Closing Input Close Project or PhaseProject Management Plan Artifact/Document Scope Management Monitoring & Controlling Input Verify ScopeProject Management Plan Artifact/Document Scope Management Monitoring & Controlling Input Control ScopeProject Management Plan Artifact/Document Time Management Monitoring & Controlling Input Control ScheduleProject Management Plan Artifact/Document Cost Management Monitoring & Controlling Input Control CostsProject Management Plan Artifact/Document Quality Management Executing Input Perform Quality AssuranceProject Management Plan Artifact/Document Quality Management Monitoring & Controlling Input Perform Quality ControlProject Management Plan Artifact/Document HR Management Executing Input Acquire Project TeamProject Management Plan Artifact/Document HR Management Executing Input Develop Project TeamProject Management Plan Artifact/Document HR Management Executing Input Manage Project TeamProject Management Plan Artifact/Document Communication Management Executing Input Distribute InformationProject Management Plan Artifact/Document Communication Management Executing Input Manage Stakeholder ExpectationsProject Management Plan Artifact/Document Communication Management Monitoring & Controlling Input Report PerformanceProject Management Plan Artifact/Document Risk Management Monitoring & Controlling Input Monitor & Control RisksProject Management Plan Artifact/Document Procurement Management Executing Input Conduct ProcurementsProject Management Plan Artifact/Document Procurement Management Monitoring & Controlling Input Administer ProcurementsProject Management Plan Artifact/Document Procurement Management Closing Input Close Procurements
Project Management Plan Updates Artifact/Document Project Integration Management Executing Output Direct and Manage Project ExecutionProject Management Plan Updates Artifact/Document Project Integration Management Monitoring & Controlling Input Monitor and Control Project WorkProject Management Plan Updates Artifact/Document Project Integration Management Monitoring & Controlling Output Monitor and Control Project WorkProject Management Plan Updates Artifact/Document Project Integration Management Monitoring & Controlling Output Perform Integrated Change ControlProject Management Plan Updates Artifact/Document Project Integration Management Closing Output Close Project or PhaseProject Management Plan Updates Artifact/Document Scope Management Monitoring & Controlling Output Control ScopeProject Management Plan Updates Artifact/Document Time Management Monitoring & Controlling Output Control ScheduleProject Management Plan Updates Artifact/Document Cost Management Monitoring & Controlling Output Control CostsProject Management Plan Updates Artifact/Document Quality Management Executing Output Perform Quality AssuranceProject Management Plan Updates Artifact/Document Quality Management Monitoring & Controlling Output Perform Quality ControlProject Management Plan Updates Artifact/Document HR Management Executing Output Acquire Project TeamProject Management Plan Updates Artifact/Document HR Management Executing Output Manage Project TeamProject Management Plan Updates Artifact/Document Communication Management Executing Output Manage Stakeholder ExpectationsProject Management Plan Updates Artifact/Document Risk Management Planning Output Plan Risk ResponsesProject Management Plan Updates Artifact/Document Risk Management Monitoring & Controlling Output Monitor & Control RisksProject Management Plan Updates Artifact/Document Procurement Management Executing Output Conduct ProcurementsProject Management Plan Updates Artifact/Document Procurement Management Monitoring & Controlling Output Administer Procurements
Project Management Software Technique Time Management Planning T&T Estimate Activity ResourcesProject Management Software Technique Time Management Monitoring & Controlling T&T Control ScheduleProject Management Software Technique Cost Management Monitoring & Controlling T&T Control Costs
Project Performance Appraisals Artifact/Document HR Management Executing T&T Manage Project TeamProject Schedule Artifact/Document Time Management Planning Output Develop Schedule
Project Management Estimating Software
Project Management Information System
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Project Schedule Artifact/Document Time Management Monitoring & Controlling Input Control ScheduleProject Schedule Artifact/Document Cost Management Planning Input Estimate CostsProject Schedule Artifact/Document Cost Management Planning Input Determine BudgetProject Schedule Artifact/Document Procurement Management Planning Input Plan Procurements
Project Schedule Network Diagrams Artifact/Document Time Management Planning Output Sequence ActivitiesProject Scope Management Artifact/Document Risk Management Planning Input Plan Risk Management
Project Scope Statement Artifact/Document Scope Management Planning Input Create WBSProject Scope Statement Artifact/Document Scope Management Planning Output Define ScopeProject Scope Statement Artifact/Document Time Management Planning Input Sequence ActivitiesProject Scope Statement Artifact/Document Time Management Planning Input Estimate Activity DurationsProject Scope Statement Artifact/Document Time Management Planning Input Develop ScheduleProject Scope Statement Artifact/Document Risk Management Planning Input Perform Qualitative Risk ManagementProject Staff Assignments Artifact/Document HR Management Executing Output Acquire Project TeamProject Staff Assignments Artifact/Document HR Management Executing Input Develop Project TeamProject Statement of Work Artifact/Document Project Integration Management Initiation Input Create Project Charter
Proposal Evaluation Techniques Technique Procurement Management Executing T&T Conduct Procurements
Technique Quality Management Planning T&T Plan QualityPrototypes Tools Scope Management Planning T&T Collect Requirements
Published Estimating Data Technique Time Management Planning T&T Estimate Activity ResourcesQualified Seller List Artifact/Document Procurement Management Executing Input Conduct Procurements
Quality Audits Technique Quality Management Executing T&T Perform Quality AssuranceQuality Checklists Artifact/Document Quality Management Planning Output Plan QualityQuality Checklists Artifact/Document Quality Management Monitoring & Controlling Input Perform Quality Control
Quality Control Measurements Artifact/Document Quality Management Executing Input Perform Quality AssuranceQuality Control Measurements Artifact/Document Quality Management Monitoring & Controlling Output Perform Quality Control
Quality Management Plan Artifact/Document Quality Management Planning Output Plan QualityQuality Management Plan Artifact/Document Risk Management Planning Input Identify Risks
Quality Metrics Artifact/Document Quality Management Planning Output Plan QualityQuality Metrics Artifact/Document Quality Management Executing Input Perform Quality AssuranceQuality Metrics Artifact/Document Quality Management Monitoring & Controlling Input Perform Quality Control
Technique Risk Management Planning T&T Perform Quantitative Risk ManagementQuestionnaires and Surveys Tools Scope Management Planning T&T Collect Requirements
Recognition & Rewards Technique HR Management Executing T&T Develop Project TeamRecords Management System Technique Procurement Management Monitoring & Controlling T&T Administer ProcurementsRecords Management System Technique Procurement Management Closing T&T Close Procurements
Reporting Systems Tools Communication Management Monitoring & Controlling T&T Report PerformanceRequirements Documentation Artifact/Document Scope Management Planning Output Collect RequirementsRequirements Documentation Artifact/Document Scope Management Planning Input Define ScopeRequirements Documentation Artifact/Document Scope Management Planning Input Create WBSRequirements Documentation Artifact/Document Scope Management Monitoring & Controlling Input Verify ScopeRequirements Documentation Artifact/Document Scope Management Monitoring & Controlling Input Control ScopeRequirements Documentation Artifact/Document Procurement Management Planning Input Plan Procurements
Requirements Management Plan Artifact/Document Scope Management Planning Output Collect Requirements
Requirements Traceability Matrix Artifact/Document Scope Management Planning Output Collect RequirementsRequirements Traceability Matrix Artifact/Document Scope Management Monitoring & Controlling Input Verify ScopeRequirements Traceability Matrix Artifact/Document Scope Management Monitoring & Controlling Input Control Scope
Reserve Analysis Technique Time Management Planning T&T Estimate Activity DurationsReserve Analysis Technique Cost Management Planning T&T Determine BudgetReserve Analysis Technique Cost Management Planning T&T Estimate CostsReserve Analysis Technique Risk Management Monitoring & Controlling T&T Monitor & Control Risks
Resource Breakdown Structure Artifact/Document Time Management Planning Output Estimate Activity ResourcesResource Calendars Artifact/Document Time Management Planning Input Estimate Activity ResourcesResource Calendars Artifact/Document Time Management Planning Input Estimate Activity DurationsResource Calendars Artifact/Document Time Management Planning Input Develop ScheduleResource Calendars Artifact/Document Cost Management Planning Input Determine BudgetResource Calendars Artifact/Document HR Management Executing Output Acquire Project TeamResource Calendars Artifact/Document HR Management Executing Input Develop Project TeamResource Calendars Artifact/Document Procurement Management Executing Output Conduct ProcurementsResource Leveling Technique Time Management Planning T&T Develop ScheduleResource Leveling Technique Time Management Monitoring & Controlling T&T Control ScheduleRisk Assessments Technique Risk Management Monitoring & Controlling T&T Monitor & Control RisksRisk Assessments Technique Risk Management Monitoring & Controlling T&T Monitor & Control Risks
Risk Audits Technique Risk Management Monitoring & Controlling T&T Monitor & Control RisksRisk Categorization Technique Risk Management Planning T&T Perform Qualitative Risk Management
Risk Data Quality Assessment Technique Risk Management Planning T&T Perform Qualitative Risk ManagementRisk Management Plan Artifact/Document Risk Management Planning Output Plan Risk ManagementRisk Management Plan Artifact/Document Risk Management Planning Input Identify RisksRisk Management Plan Artifact/Document Risk Management Planning Input Perform Quantitative Risk ManagementRisk Management Plan Artifact/Document Risk Management Planning Input Perform Qualitative Risk ManagementRisk Management Plan Artifact/Document Risk Management Planning Input Plan Risk Responses
Risk Probability & Impact Assessment Technique Risk Management Planning T&T Perform Qualitative Risk ManagementRisk Register Artifact/Document Cost Management Planning Input Estimate CostsRisk Register Artifact/Document Quality Management Planning Input Plan QualityRisk Register Artifact/Document Risk Management Planning Output Identify RisksRisk Register Artifact/Document Risk Management Planning Input Perform Qualitative Risk ManagementRisk Register Artifact/Document Risk Management Planning Input Perform Quantitative Risk ManagementRisk Register Artifact/Document Risk Management Planning Input Plan Risk ResponsesRisk Register Artifact/Document Risk Management Monitoring & Controlling Input Monitor & Control RisksRisk Register Artifact/Document Procurement Management Planning Input Plan Procurements
Risk Register Updates Artifact/Document Risk Management Planning Output Perform Qualitative Risk ManagementRisk Register Updates Artifact/Document Risk Management Planning Output Perform Quantitative Risk ManagementRisk Register Updates Artifact/Document Risk Management Planning Output Plan Risk ResponsesRisk Register Updates Artifact/Document Risk Management Monitoring & Controlling Output Monitor & Control Risks
Risk Related Contract Decisions Technique Risk Management Planning Output Plan Risk ResponsesRisk Related Contract Decisions Technique Procurement Management Planning Input Plan Procurements
Risk urgency Assessment Technique Risk Management Planning T&T Perform Qualitative Risk Management
Proprietary Quality Management methodology
Quantitative Risk Analysis & Modeling Techniques
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Rolling Way Planning Technique Time Management Planning T&T Define ActivitiesRun Chart Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality Control
Scatter Diagram Artifact/Document Quality Management Monitoring & Controlling T&T Perform Quality ControlSchedule Baseline Artifact/Document Time Management Planning Output Develop ScheduleSchedule Baseline Artifact/Document Time Management Planning Output Develop Schedule
Schedule Compression Technique Time Management Planning T&T Develop ScheduleSchedule Compression Technique Time Management Monitoring & Controlling T&T Control Schedule
Schedule Data Artifact/Document Time Management Planning Output Develop ScheduleSchedule Management Plan Artifact/Document Risk Management Planning Input Plan Risk ManagementSchedule Management Plan Artifact/Document Risk Management Planning Input Identify RisksSchedule Management Plan Artifact/Document Risk Management Planning Input Perform Quantitative Risk ManagementSchedule Network Analysis Technique Time Management Planning T&T Develop Schedule
Schedule Network Templates Artifact/Document Time Management Planning T&T Sequence ActivitiesScheduling Tool Artifact/Document Time Management Planning T&T Develop ScheduleScheduling Tool Artifact/Document Time Management Monitoring & Controlling T&T Control ScheduleScope Baseline Artifact/Document Scope Management Planning Output Create WBSScope Baseline Artifact/Document Time Management Planning Input Define ActivitiesScope Baseline Artifact/Document Cost Management Planning Input Estimate CostsScope Baseline Artifact/Document Cost Management Planning Input Determine BudgetScope Baseline Artifact/Document Quality Management Planning Input Plan QualityScope Baseline Artifact/Document Risk Management Planning Input Identify RisksScope Baseline Artifact/Document Procurement Management Planning Input Plan ProcurementsSelected Sellers Artifact/Document Procurement Management Executing Output Conduct ProcurementsSeller Proposals Artifact/Document Procurement Management Executing Input Conduct Procurements
Source Selection Criteria Artifact/Document Procurement Management Planning Output Plan ProcurementsSource Selection Criteria Artifact/Document Procurement Management Executing Input Conduct Procurements
Stakeholder Analysis Technique Communication Management Planning T&T Identify StakeholdersStakeholder Management Strategy Technique Communication Management Initiation Output Identify StakeholdersStakeholder Management Strategy Technique Communication Management Planning Input Plan CommunicationsStakeholder Management Strategy Technique Communication Management Executing Input Manage Stakeholder Expectations
Stakeholder Register Artifact/Document Scope Management Planning Input Collect RequirementsStakeholder Register Artifact/Document Quality Management Planning Input Plan QualityStakeholder Register Artifact/Document Communication Management Initiation Output Identify StakeholdersStakeholder Register Artifact/Document Communication Management Planning Input Plan CommunicationsStakeholder Register Artifact/Document Communication Management Executing Input Manage Stakeholder ExpectationsStakeholder Register Artifact/Document Risk Management Planning Input Identify RisksStakeholder Registers Artifact/Document communication Management Initiation Output Identify StakeholdersStakeholder Registers Artifact/Document communication Management Planning Input Plan CommunicationsStatistical Sampling Technique Quality Management Planning T&T Plan QualityStatistical Sampling Technique Quality Management Monitoring & Controlling T&T Perform Quality Control
Status Meetings Technique Risk Management Monitoring & Controlling T&T Monitor & Control Risks
Strategies for Negative Risks or Threats Technique Risk Management Planning T&T Plan Risk Responses
Technique Risk Management Planning T&T Plan Risk ResponsesSWOT Analysis Technique Risk Management Planning T&T Identify RisksTeam Building Technique HR Management Executing T&T Develop Project Team
Team Performance Assessments Technique HR Management Executing Output Develop Project TeamTeam Performance Assets Artifact/Document HR Management Executing Input Manage Project Team
Teaming Agreements Artifact/Document Procurement Management Planning Input Plan ProcurementsTeaming Agreements Artifact/Document Procurement Management Executing Input Conduct Procurements
Technical Performance Measurements Technique Risk Management Monitoring & Controlling T&T Monitor & Control RisksTemplates Artifact/Document Time Management Planning T&T Define ActivitiesTemplates Artifact/Document Time Management Planning T&T Sequence Activities
Three-Point Estimates Technique Time Management Planning T&T Estimate Activity Durations
To Complete Performance Index TCPI Artifact/Document Cost Management Monitoring & Controlling T&T Control CostsTraining Technique HR Management Executing T&T Develop Project Team
Validated changes Artifact/Document Quality Management Monitoring & Controlling Output Perform Quality ControlValidated Deliverables Result/Product Scope Management Monitoring & Controlling Input Verify ScopeValidated Deliverables Result/Product Quality Management Monitoring & Controlling Output Perform Quality Control
Variance & Trend Analysis Technique Risk Management Monitoring & Controlling T&T Monitor & Control RisksVariance Analysis Technique Scope Management Monitoring & Controlling T&T Control ScopeVariance Analysis Technique Communication Management Monitoring & Controlling T&T Report PerformanceVariance Analysis Technique Time Management Monitoring & Controlling T&T Control ScheduleVariance Analysis Technique Cost Management Monitoring & Controlling T&T Control Costs
Vendor Bid Analysis Technique Cost Management Planning T&T Estimate CostsVirtual Teams Technique HR Management Executing T&T Acquire Project Team
WBS Artifact/Document Scope Management Planning Output Create WBSWBS Dictionary Artifact/Document Scope Management Planning Output Create WBS
What-If Scenario Analysis Technique Time Management Planning T&T Develop ScheduleWhat-If Scenario Analysis Technique Time Management Monitoring & Controlling T&T Control Schedule
Work Performance Information Artifact/Document Project Integration Management Executing Output Direct and Manage Project ExecutionWork Performance Information Artifact/Document Project Integration Management Executing Input Perform Integrated Change ControlWork Performance Information Artifact/Document Scope Management Monitoring & Controlling Input Control ScopeWork Performance Information Artifact/Document Time Management Monitoring & Controlling Input Control ScheduleWork Performance Information Artifact/Document Cost Management Monitoring & Controlling Input Control CostsWork Performance Information Artifact/Document Quality Management Executing Input Perform Quality AssuranceWork Performance Information Artifact/Document Communication Management Monitoring & Controlling Input Report PerformanceWork Performance Information Artifact/Document Risk Management Monitoring & Controlling Input Monitor & Control RisksWork Performance Information Artifact/Document Procurement Management Monitoring & Controlling Input Administer Procurements
Work Performance Measurements Artifact/Document Scope Management Monitoring & Controlling Output Control ScopeWork Performance Measurements Artifact/Document Time Management Monitoring & Controlling Output Control ScheduleWork Performance Measurements Artifact/Document Cost Management Monitoring & Controlling Output Control CostsWork Performance Measurements Artifact/Document Quality Management Monitoring & Controlling Input Perform Quality ControlWork Performance Measurements Artifact/Document Communication Management Monitoring & Controlling Input Report Performance
Strategies for Positive Risks or Opportunities
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Totals
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Midi's ITTO spreadsheet Property of www.thepreparedpm.com
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Column A Column F Column G (empty)Accepted Deliverable
OutputVerify Scope
Accepted DeliverablesInput
Close Project or PhaseAcquisition
T&TAcquire Project Team
Activity AttributesInput
Develop ScheduleEstimate Activity DurationsEstimate Activity ResourcesSequence Activities
OutputDefine Activities
Activity Cost EstimateInput
Determine BudgetPlan ProcurementsPlan Risk management
OutputEstimate Costs
Activity Duration EstimatesInput
Develop ScheduleIdentify Risks
OutputEstimate Activity Durations
Activity ListInput
Develop ScheduleEstimate Activity DurationsEstimate Activity ResourcesSequence Activities
OutputDefine Activities
Activity Resource RequirementsInput
Develop HR PlanDevelop ScheduleEstimate Activity DurationsPlan Procurements
OutputEstimate Activity Resources
Additional Quality Planning ToolsT&T
Plan QualityAdjusting Leads and Lags
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
T&TControl Schedule
AdvertisingT&T
Conduct ProcurementsAlternative Analysis
T&TEstimate Activity Resources
Alternative IdentificationT&T
Define ScopeAnalogous Estimating
T&TEstimate Activity Durations
Applying Leads and LagsT&T
Develop ScheduleSequence Activities
Approved Change RequestsInput
Administer ProcurementsDirect and Manage Project ExecutionPerform Quality Control
Approved Change Requests ReviewT&T
Perform Quality ControlAssumptions Analysis
T&TIdentify Risks
Basis of EstimatesInput
Determine BudgetOutput
Estimate CostsBenchmarking
T&TPlan Quality
Bidder ConferencesT&T
Conduct ProcurementsBottom-Up Estimating
T&TEstimate Activity Resources
Budget ForecastOutput
Control CostsBudget Forecasts
InputReport Performance
Business CaseInput
Create Project CharterCause and Effect Diagram
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
T&TPerform Quality Control
Change Control MeetingsT&T
Change Control MeetingsChange Log
InputManage Stakeholder Expectations
Change Request Status UpdatesOutput
Monitor and Control Project WorkChange Requests
InputDirect and Manage Project ExecutionPerform Integrated Change Control
OutputAdminister ProcurementsConduct ProcurementsControl ScheduleControl ScopeDistribute InformationManage Project TeamMonitor & Control RisksPerform Quality AssurancePerform Quality ControlPlan ProcurementsReport PerformanceVerify Scope
Checklist AnalysisT&T
Identify RisksClaims Administration
T&TAdminister Procurements
Closed ProcurementsInput
Close ProcurementsCo-location
T&TDevelop Project Team
Communications Management PlanOutput
Plan CommunicationsCommunications Methods
T&TDistribute InformationManage Stakeholder ExpectationsPlan CommunicationsReport Performance
Communications ModelsT&T
Plan CommunicationsCommunications Requirements Analysis
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
T&TPlan Communications
Communications TechnologyT&T
Plan CommunicationsConflict Management
T&TManage Project Team
Contingent Response StrategiesT&T
Plan Risk ResponsesContract
InputCreate Project Charter
Contract Change Control SystemT&T
Administer ProcurementsContract Types
T&TPlan Procurements
ContractsInput
Determine BudgetControl Charts
T&TPerform Quality ControlPlan Quality
Cost AggregationT&T
Determine BudgetCost Management Plan
InputIdentify RisksPerform Quantitative Risk ManagementPlan Risk management
Cost of QualityT&T
Estimate CostsPlan Quality
Cost Performance BaselineInput
Plan ProcurementsPlan Quality
OutputDetermine Budget
Cost-Benefit AnalysisT&T
Plan QualityCritical Chain Method
T&TDevelop Schedule
Critical Path MethodT&T
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Develop ScheduleData Gathering & Representative Techniques
T&TPerform Quantitative Risk Management
DecompositionT&T
Create WBSDeliverable
OutputDirect and Manage Project Execution
Dependency DeterminationT&T
Sequence ActivitiesDesign of Experiments
T&TPlan Quality
Diagramming TechniquesT&T
Identify RisksDocumentation Reviews
T&TIdentify Risks
Earned Value ManagementT&T
Control CostsEnterprise Environmental Factors
InputAcquire Project TeamCreate Project CharterDefine ActivitiesDevelop HR PlanDevelop Project Management PlanDevelop Project TeamDevelop ScheduleDirect and Manage Project ExecutionEstimate Activity DurationsEstimate Activity ResourcesEstimate CostsIdentify RisksIdentify StakeholdersMonitor and Control Project WorkPerform Integrated Change ControlPlan CommunicationsPlan ProcurementsPlan QualityPlan Risk management
Enterprise Environmental Factors UpdatesOutput
Develop Project TeamManage Project Team
Expert JudgmentT&T
Close Project or Phase
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Conduct ProcurementsCreate Project CharterDefine ActivitiesDefine ScopeDetermine BudgetDevelop Project Management PlanDirect and Manage Project ExecutionEstimate Activity DurationsEstimate Activity ResourcesEstimate CostsIdentify RisksIdentify StakeholdersMonitor and Control Project WorkPerform Integrated Change ControlPerform Qualitative Risk ManagementPerform Quantitative Risk ManagementPlan ProcurementsPlan Risk Responses
Facilitated WorkshopsT&T
Collect RequirementsDefine Scope
Final Product, Service, or Result TransitionOutput
Close Project or PhaseFlow Charting
T&TPerform Quality ControlPlan Quality
Focus GroupsT&T
Collect RequirementsForecasting
T&TControl CostsReport Performance
Funding Limit ReconciliationT&T
Determine BudgetGround Rules
T&TDevelop Project Team
Group Decision making TechniquesT&T
Collect RequirementsHistogram
T&TPerform Quality Control
Historical RelationshipsT&T
Determine BudgetHR Plan
Input
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Estimate CostsOutput
Develop HR PlanIndependent Estimates
T&TConduct Procurements
Information Distribution ToolsT&T
Distribute InformationInformation Gathering Techniques
T&TIdentify Risks
InspectionT&T
Perform Quality ControlVerify Scope
Inspections & AuditsT&T
Administer ProcurementsInternet Search
T&TConduct Procurements
Interpersonal SkillsT&T
Develop Project TeamManage Project TeamManage Stakeholder Expectations
InterviewsT&T
Collect RequirementsIssue Log
InputManage Stakeholder Expectations
T&TManage Project Team
Make or Buy AnalysisT&T
Plan ProcurementsMake or Buy Decisions
InputConduct Procurements
OutputPlan Procurements
Management SkillsT&T
Manage Stakeholder ExpectationsMilestone List
InputSequence Activities
OutputDefine Activities
Negotiated SettlementsT&T
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Close ProcurementsNegotiation
T&TAcquire Project Team
NetworkingT&T
Develop HR PlanObservations
T&TCollect Requirements
Organization Charts &Position DescriptionsT&T
Develop HR PlanOrganizational Process Assets
InputAcquire Project TeamConduct ProcurementsControl CostsControl ScheduleControl ScopeCreate Project CharterCreate WBSDefine ActivitiesDefine ScopeDetermine BudgetDevelop HR PlanDevelop Project Management PlanDevelop ScheduleDirect and Manage Project ExecutionDistribute InformationEstimate Activity DurationsEstimate Activity ResourcesEstimate CostsIdentify RisksIdentify StakeholdersManage Project TeamManage Stakeholder ExpectationsMonitor and Control Project WorkPerform Integrated Change ControlPerform Qualitative Risk ManagementPerform Quality ControlPerform Quantitative Risk ManagementPlan CommunicationsPlan ProcurementsPlan QualityPlan Risk managementReport PerformanceSequence Activities
Organizational Process Assets UpdatesOutput
Administer ProcurementsClose Project or PhaseControl Costs
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Control ScheduleControl ScopeDistribute InformationManage Project TeamManage Stakeholder ExpectationsMonitor & Control RisksMonitor and Control Project WorkPerform Quality Control
Organizational TheoryT&T
Develop HR PlanOutputs from Planning Process
InputDevelop Project Management Plan
Parametric EstimatingT&T
Estimate Activity DurationsPareto Chart
T&TPerform Quality Control
Payment SystemsT&T
Administer ProcurementsPerformance Reporting
T&TAdminister Procurements
Performance ReportsInput
Administer ProcurementsDistribute InformationManage Project TeamMonitor & Control RisksMonitor and Control Project Work
OutputReport Performance
Performance ReviewsT&T
Administer ProcurementsControl CostsControl Schedule
Plan Quality and Perform Quality Control tools and techniquesT&T
Perform Quality AssurancePre-assignment
T&TAcquire Project Team
Precedence Diagramming MethodT&T
Sequence ActivitiesProbability & Impact Assessment
T&TPerform Qualitative Risk Management
Process Analysis
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
T&TPerform Quality Assurance
Process Improvement PlanOutput
Plan QualityProcurement Audits
T&TClose Procurements
Procurement Contract AwardOutput
Conduct ProcurementsProcurement Documentation
InputClose Procurements
OutputAdminister Procurements
Procurement DocumentsInput
Administer ProcurementsConduct ProcurementsIdentify Stakeholders
OutputPlan Procurements
Procurement Management PlanOutput
Plan ProcurementsProcurement Negotiations
T&TConduct Procurements
Procurement Performance ReviewsT&T
Administer ProcurementsProcurement Statement of Work
OutputPlan Procurements
Product AnalysisT&T
Define ScopeProject Charter
InputCollect RequirementsDefine ScopeDevelop Project Management Plan
OutputCreate Project Charter
Project Document UpdatesOutput
Collect RequirementsConduct ProcurementsControl CostsControl ScopeDefine ScopeDetermine Budget
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Develop ScheduleDirect and Manage Project ExecutionEstimate Activity DurationsEstimate Activity ResourcesEstimate CostsManage Stakeholder ExpectationsMonitor & Control RisksMonitor and Control Project WorkMonitor and Control SchedulePerform Integrated Change ControlPerform Quality AssurancePerform Quality ControlPlan CommunicationsPlan QualityPlan Risk ResponsesSequence ActivitiesVerify Scope
Project DocumentsInput
Conduct ProcurementsIdentify Risks
Project Funding RequirementsInput
Control CostsOutput
Determine BudgetProject Management Estimating Software
T&TEstimate Costs
Project Management Information SystemT&T
Direct and Manage Project ExecutionProject Management Plan
InputAcquire Project TeamAdminister ProcurementsClose ProcurementsClose Project or PhaseConduct ProcurementsControl CostsControl ScheduleControl ScopeDevelop Project TeamDirect and Manage Project ExecutionDistribute InformationManage Project TeamManage Stakeholder ExpectationsMonitor & Control RisksPerform Integrated Change ControlPerform Quality AssurancePerform Quality ControlReport PerformanceVerify Scope
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
OutputDevelop Project Management Plan
Project Management Plan UpdatesInput
Monitor and Control Project WorkOutput
Acquire Project TeamAdminister ProcurementsClose Project or PhaseConduct ProcurementsControl CostsControl ScheduleControl ScopeDirect and Manage Project ExecutionManage Project TeamManage Stakeholder ExpectationsMonitor & Control RisksMonitor and Control Project WorkPerform Integrated Change ControlPerform Quality AssurancePerform Quality ControlPlan Risk Responses
Project Management SoftwareT&T
Control CostsControl ScheduleEstimate Activity Resources
Project Performance AppraisalsT&T
Manage Project TeamProject Schedule
InputControl ScheduleDetermine BudgetEstimate CostsPlan Procurements
OutputDevelop Schedule
Project Schedule Network DiagramsOutput
Sequence ActivitiesProject Scope Management
InputPlan Risk management
Project Scope StatementInput
Create WBSDevelop ScheduleEstimate Activity DurationsPerform Qualitative Risk ManagementSequence Activities
OutputDefine Scope
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Project Staff AssignmentsInput
Develop Project TeamOutput
Acquire Project TeamProject Statement of Work
InputCreate Project Charter
Proposal Evaluation TechniquesT&T
Conduct ProcurementsProprietary Quality Management methodology
T&TPlan Quality
PrototypesT&T
Collect RequirementsPublished Estimating Data
T&TEstimate Activity Resources
Qualified Seller ListInput
Conduct ProcurementsQuality Audits
T&TPerform Quality Assurance
Quality ChecklistsInput
Perform Quality ControlOutput
Plan QualityQuality Control Measurements
InputPerform Quality Assurance
OutputPerform Quality Control
Quality Management PlanInput
Identify RisksOutput
Plan QualityQuality Metrics
InputPerform Quality AssurancePerform Quality Control
OutputPlan Quality
Quantitative Risk Analysis & Modeling TechniquesT&T
Perform Quantitative Risk ManagementQuestionnaires and Surveys
T&TCollect Requirements
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Recognition & RewardsT&T
Develop Project TeamRecords Management System
T&TAdminister ProcurementsClose Procurements
Reporting SystemsT&T
Report PerformanceRequirements Documentation
InputControl ScopeCreate WBSDefine ScopePlan ProcurementsVerify Scope
OutputCollect Requirements
Requirements Management PlanOutput
Collect RequirementsRequirements Traceability Matrix
InputControl ScopeVerify Scope
OutputCollect Requirements
Reserve AnalysisT&T
Determine BudgetEstimate Activity DurationsEstimate CostsMonitor & Control Risks
Resource Breakdown StructureOutput
Estimate Activity ResourcesResource Calendars
InputDetermine BudgetDevelop Project TeamDevelop ScheduleEstimate Activity DurationsEstimate Activity Resources
OutputAcquire Project TeamConduct Procurements
Resource LevelingT&T
Control ScheduleDevelop Schedule
Risk AssessmentsT&T
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Monitor & Control RisksRisk Audits
T&TMonitor & Control Risks
Risk CategorizationT&T
Perform Qualitative Risk ManagementRisk Data Quality Assessment
T&TPerform Qualitative Risk Management
Risk Management PlanInput
Identify RisksPerform Qualitative Risk ManagementPerform Quantitative Risk ManagementPlan Risk Responses
OutputPlan Risk management
Risk Probability & Impact AssessmentT&T
Perform Qualitative Risk ManagementRisk Register
InputEstimate CostsMonitor & Control RisksPerform Qualitative Risk ManagementPerform Quantitative Risk ManagementPlan ProcurementsPlan QualityPlan Risk Responses
OutputIdentify Risks
Risk Register UpdatesOutput
Monitor & Control RisksPerform Qualitative Risk ManagementPerform Quantitative Risk ManagementPlan Risk Responses
Risk Related Contract DecisionsInput
Plan ProcurementsOutput
Plan Risk ResponsesRisk urgency Assessment
T&TPerform Qualitative Risk Management
Rolling Way PlanningT&T
Define ActivitiesRun Chart
T&TPerform Quality Control
Scatter Diagram
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
T&TPerform Quality Control
Schedule BaselineOutput
Develop ScheduleSchedule Compression
T&TControl ScheduleDevelop Schedule
Schedule DataOutput
Develop ScheduleSchedule Management Plan
InputIdentify RisksPerform Quantitative Risk ManagementPlan Risk management
Schedule Network AnalysisT&T
Develop ScheduleSchedule Network Templates
T&TSequence Activities
Scheduling ToolT&T
Control ScheduleDevelop Schedule
Scope BaselineInput
Define ActivitiesDetermine BudgetEstimate CostsIdentify RisksPlan ProcurementsPlan Quality
OutputCreate WBS
Selected SellersOutput
Conduct ProcurementsSeller Proposals
InputConduct Procurements
Source Selection CriteriaInput
Conduct ProcurementsOutput
Plan ProcurementsStakeholder Analysis
T&TIdentify Stakeholders
Stakeholder Management StrategyInput
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Manage Stakeholder ExpectationsPlan Communications
OutputIdentify Stakeholders
Stakeholder RegisterInput
Collect RequirementsIdentify RisksManage Stakeholder ExpectationsPlan CommunicationsPlan Quality
OutputIdentify Stakeholders
Stakeholder RegistersInput
Plan CommunicationsOutput
Identify StakeholdersStatistical Sampling
T&TPerform Quality ControlPlan Quality
Status MeetingsT&T
Monitor & Control RisksStrategies for Negative Risks or Threats
T&TPlan Risk Responses
Strategies for Positive Risks or OpportunitiesT&T
Plan Risk ResponsesSWOT Analysis
T&TIdentify Risks
Team BuildingT&T
Develop Project TeamTeam Performance Assessments
OutputDevelop Project Team
Team Performance AssetsInput
Manage Project TeamTeaming Agreements
InputConduct ProcurementsPlan Procurements
Technical Performance MeasurementsT&T
Monitor & Control RisksTemplates
T&TDefine Activities
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Sequence ActivitiesThree-Point Estimates
T&TEstimate Activity Durations
TitleCAT
ActivityTo Complete Performance Index TCPI
T&TControl Costs
TrainingT&T
Develop Project TeamValidated changes
OutputPerform Quality Control
Validated DeliverablesInput
Verify ScopeOutput
Perform Quality ControlVariance & Trend Analysis
T&TMonitor & Control Risks
Variance AnalysisT&T
Control CostsControl ScheduleControl ScopeReport Performance
Vendor Bid AnalysisT&T
Estimate CostsVirtual Teams
T&TAcquire Project Team
WBSOutput
Create WBSWBS Dictionary
OutputCreate WBS
What-If Scenario AnalysisT&T
Control ScheduleDevelop Schedule
Work Performance InformationInput
Administer ProcurementsControl CostsControl ScheduleControl ScopeMonitor & Control Risks
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Perform Integrated Change ControlPerform Quality AssuranceReport Performance
OutputDirect and Manage Project Execution
Work Performance MeasurementsInput
Perform Quality ControlReport Performance
OutputControl CostsControl ScheduleControl Scope
Total Result
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Close Project or Phase
Acquire Project Team
Estimate Activity DurationsEstimate Activity Resources
Plan Risk management
Estimate Activity Durations
Estimate Activity DurationsEstimate Activity Resources
Estimate Activity Durations
Estimate Activity Resources
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Conduct Procurements
Estimate Activity Resources
Estimate Activity Durations
Administer ProcurementsDirect and Manage Project ExecutionPerform Quality Control
Perform Quality Control
Conduct Procurements
Estimate Activity Resources
Create Project Charter
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Perform Quality Control
Change Control Meetings
Manage Stakeholder Expectations
Monitor and Control Project Work
Direct and Manage Project ExecutionPerform Integrated Change Control
Administer ProcurementsConduct Procurements
Distribute InformationManage Project TeamMonitor & Control RisksPerform Quality AssurancePerform Quality Control
Administer Procurements
Develop Project Team
Plan Communications
Distribute InformationManage Stakeholder ExpectationsPlan Communications
Plan Communications
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Plan Communications
Plan Communications
Manage Project Team
Plan Risk Responses
Create Project Charter
Administer Procurements
Perform Quality Control
Perform Quantitative Risk ManagementPlan Risk management
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Perform Quantitative Risk Management
Direct and Manage Project Execution
Acquire Project TeamCreate Project Charter
Develop Project Management PlanDevelop Project Team
Direct and Manage Project ExecutionEstimate Activity DurationsEstimate Activity Resources
Monitor and Control Project WorkPerform Integrated Change ControlPlan Communications
Plan Risk management
Develop Project TeamManage Project Team
Close Project or Phase
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Conduct ProcurementsCreate Project Charter
Develop Project Management PlanDirect and Manage Project ExecutionEstimate Activity DurationsEstimate Activity Resources
Monitor and Control Project WorkPerform Integrated Change ControlPerform Qualitative Risk ManagementPerform Quantitative Risk Management
Plan Risk Responses
Collect Requirements
Close Project or Phase
Perform Quality Control
Collect Requirements
Develop Project Team
Collect Requirements
Perform Quality Control
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Conduct Procurements
Distribute Information
Perform Quality Control
Administer Procurements
Conduct Procurements
Develop Project TeamManage Project TeamManage Stakeholder Expectations
Collect Requirements
Manage Stakeholder Expectations
Manage Project Team
Conduct Procurements
Manage Stakeholder Expectations
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Acquire Project Team
Collect Requirements
Acquire Project TeamConduct Procurements
Create Project Charter
Develop Project Management Plan
Direct and Manage Project ExecutionDistribute InformationEstimate Activity DurationsEstimate Activity Resources
Manage Project TeamManage Stakeholder ExpectationsMonitor and Control Project WorkPerform Integrated Change ControlPerform Qualitative Risk ManagementPerform Quality ControlPerform Quantitative Risk ManagementPlan Communications
Plan Risk management
Administer ProcurementsClose Project or Phase
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Distribute InformationManage Project TeamManage Stakeholder ExpectationsMonitor & Control RisksMonitor and Control Project WorkPerform Quality Control
Develop Project Management Plan
Estimate Activity Durations
Perform Quality Control
Administer Procurements
Administer Procurements
Administer ProcurementsDistribute InformationManage Project TeamMonitor & Control RisksMonitor and Control Project Work
Administer Procurements
Perform Quality Assurance
Acquire Project Team
Perform Qualitative Risk Management
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Perform Quality Assurance
Conduct Procurements
Administer Procurements
Administer ProcurementsConduct Procurements
Conduct Procurements
Administer Procurements
Collect Requirements
Develop Project Management Plan
Create Project Charter
Collect RequirementsConduct Procurements
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Direct and Manage Project ExecutionEstimate Activity DurationsEstimate Activity Resources
Manage Stakeholder ExpectationsMonitor & Control RisksMonitor and Control Project WorkMonitor and Control SchedulePerform Integrated Change ControlPerform Quality AssurancePerform Quality ControlPlan Communications
Plan Risk Responses
Conduct Procurements
Direct and Manage Project Execution
Acquire Project TeamAdminister Procurements
Close Project or PhaseConduct Procurements
Develop Project TeamDirect and Manage Project ExecutionDistribute InformationManage Project TeamManage Stakeholder ExpectationsMonitor & Control RisksPerform Integrated Change ControlPerform Quality AssurancePerform Quality Control
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Develop Project Management Plan
Monitor and Control Project Work
Acquire Project TeamAdminister ProcurementsClose Project or PhaseConduct Procurements
Direct and Manage Project ExecutionManage Project TeamManage Stakeholder ExpectationsMonitor & Control RisksMonitor and Control Project WorkPerform Integrated Change ControlPerform Quality AssurancePerform Quality ControlPlan Risk Responses
Estimate Activity Resources
Manage Project Team
Plan Risk management
Estimate Activity DurationsPerform Qualitative Risk Management
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Develop Project Team
Acquire Project Team
Create Project Charter
Conduct Procurements
Collect Requirements
Estimate Activity Resources
Conduct Procurements
Perform Quality Assurance
Perform Quality Control
Perform Quality Assurance
Perform Quality Control
Perform Quality AssurancePerform Quality Control
Perform Quantitative Risk Management
Collect Requirements
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Develop Project Team
Administer Procurements
Collect Requirements
Collect Requirements
Collect Requirements
Estimate Activity Durations
Monitor & Control Risks
Estimate Activity Resources
Develop Project Team
Estimate Activity DurationsEstimate Activity Resources
Acquire Project TeamConduct Procurements
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Monitor & Control Risks
Monitor & Control Risks
Perform Qualitative Risk Management
Perform Qualitative Risk Management
Perform Qualitative Risk ManagementPerform Quantitative Risk ManagementPlan Risk Responses
Plan Risk management
Perform Qualitative Risk Management
Monitor & Control RisksPerform Qualitative Risk ManagementPerform Quantitative Risk Management
Plan Risk Responses
Monitor & Control RisksPerform Qualitative Risk ManagementPerform Quantitative Risk ManagementPlan Risk Responses
Plan Risk Responses
Perform Qualitative Risk Management
Perform Quality Control
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Perform Quality Control
Perform Quantitative Risk ManagementPlan Risk management
Conduct Procurements
Conduct Procurements
Conduct Procurements
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Manage Stakeholder ExpectationsPlan Communications
Collect Requirements
Manage Stakeholder ExpectationsPlan Communications
Plan Communications
Perform Quality Control
Monitor & Control Risks
Plan Risk Responses
Plan Risk Responses
Develop Project Team
Develop Project Team
Manage Project Team
Conduct Procurements
Monitor & Control Risks
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Estimate Activity Durations
Develop Project Team
Perform Quality Control
Perform Quality Control
Monitor & Control Risks
Acquire Project Team
Administer Procurements
Monitor & Control Risks
Free alphabetical Listing of all the ITTO's Property of www.thepreparedpm.com
Perform Integrated Change ControlPerform Quality Assurance
Direct and Manage Project Execution
Perform Quality Control