December 2017
MID-PACIFIC CONSTRUCTION OFFICE Willows, California
Construction Progress Report L-29
(This Page Intentionally Left Blank)
CONSTRUCTION PROGRESS REPORT (L-29) MID-PACIFIC CONSTRUCTION OFFICE MID-PACIFIC REGION December 2017
TABLE OF CONTENTS TITLE PAGE LOCATION MAP i STAFFING ii GLOSSARY OF TERMS iii CONTRACT/SPECS OR P.O. NO., CONTRACTOR, AND CONTRACT NAME PAGE MAP NO. NO. Central California Area Office 1 R10PC20019 20-C0689 Andritz Hydro 3 1 Folsom Power Plant Generators U1, U2, and U3 Rewind and Excitation System Replacement – Folsom Unit, American River Division, Central Valley Project, California
R14PC00096 20-C0816 Alltech Engineering Corporation 4 1
Nimbus Dam Radial Gate Repairs, Phase III - Nimbus Dam, American River Division,
Central Valley Project, California
R16PC00075 20-C0838 Cal Electro, Inc. 5 1
Folsom UHA Switchgear Replacement – Folsom Unit, American River Division,
Central Valley Project, California
R16PC00113 20-C0858 Sapper West, Inc. 7 1
Folsom Dam Municipal and Industrial Temperature Control Device Safety Measures -
Folsom Unit, American River Division, Central Valley Project, California
R17PC00100 None Harrison Western Construction Corporation 12 1
Folsom Dam Auxiliary Spillway American River Phase V – Right Bank Stabilization,
Folsom Unit, American River Division, Central Valley Project, California
R17PC00139 None Site Work Solutions Inc. 19 1
Folsom Aggregate Structure Demolition, Removal & Disposal - Folsom Unit,
American River Division, Central Valley Project, California
Klamath Basin Area Office 23
R17PC00083 None Coleman Environmental Engineering, Inc. 25 2
Tule Lake Road Improvement Phase 2- Klamath Project, Oregon - California
Lahontan Basin Area Office 31
R16PC00062 20-C0850 NW Constructors, Inc. 33 3
Stampede Dam, Dam Safety Modifications - Stampede Division, Washoe Project,
Nevada-California
(This Page Intentionally Left Blank)
R17PC00063 20-C0860 Diana Prince Construction, Inc. 34 4
Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation – Washoe Project,
Nevada-California
R17PC00067 None Sentinel Builders LLC 36 5
Lahontan Dam Rated Vehicle Barrier System - Lahontan Basin Area Office,
Newlands Project, Fallon, Nevada
Northern California Area Office 37 R15PC00089 20-C0831 Contractor Services Group, Inc. 39 7
Intake 3 Screen Extension, Coleman National Fish Hatchery - Shasta Division, Central Valley
Project, California
R16PC00006 20-C0841 Voith Hydro, Inc. 40 6
Trinity Powerplant Generator Rewinds - Trinity River Division, Central Valley Project,
California
R17PC00029 20-C0847 Gardner Zemke 46 6
Trinity River Division Powerplants Replacement of Station Service Transformers
and Low Voltage Bus System – Trinity River Division, Central Valley Project, California
R16PC00134 20-C0852 BCI Construction USA, Inc. 47 8
Whiskeytown Lake, Spring Creek Temperature Control Curtain - Trinity River Division,
Central Valley Project, California
R17PC00103 20-C0866 Air-O-Service 48 6
Keswick & Shasta Powerplant Weldshop Ventilation System Procurement & Installation –
Shasta and Keswick Powerplant - Central Valley Project, California
R17PC00091 20-C0869 Tompco-Triton 49 7
Intake 3 Trash Rake, Coleman National Fish Hatchery, Shasta Division, Central Valley Project,
California
R17PC00092 None Purgatory Fence Company, Inc. 50 6
Install K12 Rated Vehicle Barriers at Keswick, Shasta and Trinity Power Plants
Shasta and Trinity Division, Central Valley Project, California
South-Central California Area Office 51
San Joaquin River Restoration Program 55
Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial Contractors, Inc. 61 9
North Fork Screens and Ladders Completion Contract - Battle Creek Salmon and
Steelhead Restoration Project, California
(This Page Intentionally Left Blank)
Contracts in Warranty Status 67
R11PC20185 20-C0778 69 Tracy 13.8kV Switchgear/Breaker Replacement – Tracy Pumping Plant and Substation, Delta Division, Central Valley Project, California
R13PC20159 20-C0819 GD Nielson Construction, Inc. 69
Lake Berryessa Concessions Areas Improvements – Lake Berryessa, Solano Project,
California
R16PC00079 20-C0851 E.C. Smith, Inc. 69
Red Bluff Flap Gate Retrofit - Sacramento Canals Unit, Sacramento River Division,
Central Valley Project, California
R17PC00022 20-C0857 Salter and Sons Construction 69
Western Tracy Switchyard, Chain Link Fence Project - Tracy Pumping Plant and Substation,
Delta Division, Central Valley Project, California
R11PC2023S None Tehama Environmental Solutions, Inc. 69
Red Bluff Diversion Dam, Fish Passage Improvement Project Terrestrial Mitigation,
Sacramento River Division, Central Valley Project, California
R16PC00099 None Chigosi Company 69
Folsom Resource Building – Folsom Unit, American River Division,
Central Valley Project, California
R16PC00100 None Construction Solutions Group, LLC 69
Lake Woollomes Recreation Area Asphalt Replacement - Central Valley Project, California
R15PC00080 20-C0836 Andrews Contracting Services, LLC 69
Klamath Basin Area Office Sewer Lift Station - Klamath Basin Area Office, Klamath Falls,
Oregon
R16PC00111 20-C0855 BCI Construction USA, Inc. 69
San Joaquin Hatchery Water Supply Pipeline – San Joaquin River Restoration Program,
Friant Division, Central Valley Project, California
R16PC00110 20-C0853 BCI Construction USA, Inc. 70
Madera Canal Headworks Low-Flow Valve – San Joaquin River Restoration Program,
Friant Division, Central Valley Project, California
Lab Reports 71
Stampede Safety of Dams Project Lab Reports 73
North Fork Screens and Ladders Completion Contract Lab Reports 75
(This Page Intentionally Left Blank)
i
Areas in the Mid-Pacific Region Where Work was Performed
4
5 3
7
2
9
1
6 8
(This Page Intentionally Left Blank)
ii
STAFFING MID-PACIFIC CONSTRUCTION OFFICE
The Mid-Pacific Construction Office had 32 construction and administrative employees at the close of this month as follows: Construction Engineer's Office 1 Preaward and Project Management Group 3 Administrative Management 4 Division of Field Engineering 17 Division of Office Engineering 4 Materials Lab Branch 3
(This Page Intentionally Left Blank)
iii
GLOSSARY ACRONYMS AND ABBREVIATIONS
ACRONYM MEANING CCAO Central California Area Office CVP Central Valley Project KBAO Klamath Basin Area Office LBAO Lahontan Basin Area Office MP Mid-Pacific Regional Office MPCO Mid-Pacific Construction Office NCAO Northern California Area Office SCCAO South Central California Area Office SJRRP San Joaquin River Restoration Program TO Tracy Office
(This Page Intentionally Left Blank)
1 | P a g e
Central California Area Office
2 | P a g e
(This Page Intentionally Left Blank)
3 | P a g e
Contract No. R10PC20019 Specification No. 20-C0689 Folsom Power Plant Generators U1, U2, and U3 Rewind and Excitation System Replacement - Folsom Unit, American River Division, Central Valley Project, California Andritz Hydro, Charlotte, NC
Work Performed December 0.0%
Time Elapsed 100.0%
Work Completed 100.0%
Contractor Earnings December $0.00
Previous $20,610,792.74
Total to Date $20,610,792.74
MPCO Noncontract Costs 1st Quarter Expenditures $12,328.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $12,328.00
FY18 Budgeted $25,680.00
Amount Remaining $13,352.00
Percent Remaining 51.99%
Area Office Project Management Project Manager: Jonathan Rogado, MP-250
Office Engineering Contract Administrator: Larry Bowman, MPCO-240
Before contract completion the following work will be performed:
Acceptance testing for Unit 3.
Remaining warranty inspections for Units 1, 2, and 3.
Final submittals (including As-built Drawings and O&M Manuals).
Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310
Construction Representative: Todd Dooley, MPCO-314.
Number of Contractor Employees: 1
Work Performed No onsite work was performed during this period.
4 | P a g e
Contract No. R14PC00096 Specification No. 20-C0816 Nimbus Dam Radial Gate Repairs, Phase III – Nimbus Dam, American River Division, Central Valley Project, California Alltech Engineering Corporation, Mendota Heights, MN
Work Performed December 2.1%
Time Elapsed 58.0%
Work Completed 62.9%
Contractor Earnings December $358,576.85
Previous $10,556,025.46
Total to Date $10,914,602.31
MPCO Noncontract Costs 1st Quarter Expenditures $68,661.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $68,661.00
FY18 Budgeted $377,180.00
Amount Remaining $308,519.00
Percent Remaining 81.80%
Area Office Project Management Project Manager: Jonathan Rogado, CC-611
Office Engineering Contract Administrator: Larry Bowman, MPCO-240
Invoice number 29 was received this reporting period, in the amount of $358,576.85, for work
performed from November 1, 2017 to November 30, 2017.
Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310
Construction Representative: Michael Manlick, MPCO-313
Number of Contractor Employees: 14
Work Performed No onsite work was performed during this period.
5 | P a g e
Contract No. R16PC00075 Specification No. 20-C0838 Folsom UHA Switchgear Replacement – Folsom Unit, American River Division, Central Valley Project, California Cal Electro, Inc., Redding, CA
Work Performed December 0.0%
Time Elapsed 100%
Work Completed 84.5%
Contractor Earnings December $0.00
Previous $2,996,939.22
Total to Date $2,996,939.22
MPCO Noncontract Costs 1st Quarter Expenditures $46,805.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $46,805.00
FY18 Budgeted $57,060.00
Amount Remaining $10,255.00
Percent Remaining 17.97%
Area Office Project Management Project Manager: Vanhue Ly, CC-614
Office Engineering Contract Administrator: Larry Bowman, MPCO-240
Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310
Construction Representative: Sean Frische, MPCO-317
Number of Contractor Employees: 4
Work Performed Installation of new switchgear (UHA) completed. All punch list items have been addressed.
Formal training has not yet been rescheduled. Contractor has completed demobilization and
final site cleanup.
6 | P a g e
Syblon Reid performed the final work on the safety door and hatch, drilling and epoxy-setting an
eye-bolt into the concrete wall. This will be used to latch the hatch in the open position when
accessing the upper ladder.
The clamps securing the grating onto the platform frame had been ordered incorrectly (for 2-inch
deep grates). With the correct 1-inch clamps obtained, Syblon-Reid installed them on each of the
two grates, securely attaching them to the platform frames.
Wire Rope
Syblon-Reid completed the wire rope installation that was started November 30, 2017. The
existing bolts used to temporarily hold the new rope clamps on the drum were replaced with the
correctly sized, new bolts. The bolts were torqued to the manufacturer’s recommended 360 ft. lbs.
The rope drum was operated to tension the new cables and the gate was raised to its original full-
up position, releasing the tension on the temporary rigging which was then removed.
The mechanical counter was reset to 422.4 simultaneously with resetting the electronic counter to
422.1. CCAO’s operator then reinstalled the drive sprocket and belt that operates the upper and
lower limit switch component. The gate was then lowered to the bottom limit, and then cycled to
the upper limit.
The bonnet was reset over the rope drum, where workers re-bolted it into place.
Coatings
Mason Painting applied an epoxy coating to the maintenance pad eyes, including the welded
connection between the maintenance pad eyes and the control gate. Using a Bristol Blaster, he
prepared the bare steel surfaces on the maintenance pad eyes. He also performed two surface
profile tests and checked environmental conditions prior to applying coatings.
After a 24-hour cure of the epoxy coating, Mason Painting applied the UV Resistant Polyurethane
top coat to the new maintenance pad eyes. It took only a few minutes to hand-brush the coating
on each of the two new maintenance pad eyes. The material is very thin; and it was applied with
a wet thickness that will cure to a dry thickness of 2 mils or better.
Syblon Reid marked damaged galvanized surfaces in the galvanized ladders, cages, landings, and
railings. Mason Painting then prepared these surfaces for re-coating with sand paper and thinner.
A single coat of AllPro 11106 Cold Galvanizing was then spray-applied to prepared surfaces.
7 | P a g e
;Contract No. R16PC00113 Specification No. 20-C0858 Folsom Dam Municipal and Industrial Temperature Control Device Safety Measures, Folsom Unit, American River Division, Central Valley Project, California Sapper West, Inc., Sacramento, CA
Work Performed December 0%
Time Elapsed 100%
Work Completed 21%
Contractor Earnings December $0.00
Previous $63,021.24
Total to Date $63,021.24
MPCO Noncontract Costs 1st Quarter Expenditures $17,481.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $17,481.00
FY18 Budgeted $64,670.00
Amount Remaining $47,189.00
Percent Remaining 72.97%
Area Office Project Management Project Manager: Brian Zewe, CC-612
Office Engineering Contract Manager: Kent Perkes, MPCO-225
The work was substantially complete as of December 12, 2017.
The work was transferred to the Bureau of Reclamation Central California Area Office for
operation and maintenance as of December 14, 2017.
The period of performance ended December 29, 2017.
Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310
Construction Representative: Michael Manlick, MPCO-312
Number of Contractor Employees: 6
Work Performed
8 | P a g e
The substantial completion walk-through/inspection was conducted on December 12, 2017. Aside
from a small punch-list, CCAO and MPCO personnel agreed that the project was substantially
complete as of this day.
The project was inspected and transferred to the Central California Area Office for operation and
maintenance on December 14, 2017.
Miscellaneous Metals
Syblon Reid performed the final work on the safety door and hatch, drilling and epoxy-setting an
eye-bolt into the concrete wall. This will be used to latch the hatch in the open position when
accessing the upper ladder.
The clamps securing the grating onto the platform frame had been ordered incorrectly (for 2-inch
deep grates). With the correct 1-inch clamps obtained, Syblon-Reid installed them on each of the
two grates, securely attaching them to the platform frames.
Wire Rope
Syblon-Reid completed the wire rope installation that was started November 30, 2017. The
existing bolts used to temporarily hold the new rope clamps on the drum were replaced with the
correctly sized, new bolts. The bolts were torqued to the manufacturer’s recommended 360 ft. lbs.
The rope drum was operated to tension the new cables and the gate was raised to its original full-
up position, releasing the tension on the temporary rigging which was then removed.
The mechanical counter was reset to 422.4 simultaneously with resetting the electronic counter to
422.1. CCAO’s operator then reinstalled the drive sprocket and belt that operates the upper and
lower limit switch component. The gate was then lowered to the bottom limit, and then cycled to
the upper limit.
The bonnet was reset over the rope drum, where workers re-bolted it into place.
Coatings
Mason Painting applied an epoxy coating to the maintenance pad eyes, including the welded
connection between the maintenance pad eyes and the control gate. Using a Bristol Blaster, he
prepared the bare steel surfaces on the maintenance pad eyes. He also performed two surface
profile tests and checked environmental conditions prior to applying coatings.
After a 24-hour cure of the epoxy coating, Mason Painting applied the UV Resistant Polyurethane
top coat to the new maintenance pad eyes. It took only a few minutes to hand-brush the coating
on each of the two new maintenance pad eyes. The material is very thin; and it was applied with
a wet thickness that will cure to a dry thickness of 2 mils or better.
Syblon Reid marked damaged galvanized surfaces in the galvanized ladders, cages, landings, and
railings. Mason Painting then prepared these surfaces for re-coating with sand paper and thinner.
A single coat of AllPro 11106 Cold Galvanizing was then spray-applied to prepared surfaces
9 | P a g e
The workers are torqueing the rope clamp bolts to 360 foot-pounds.
10 | P a g e
The worker is injecting epoxy into a predrilled hole to set the ladder hatch latch
eye bolt.
11 | P a g e
The crane resets the protective bonnet over the gate hoist’s rope drum.
12 | P a g e
Contract No. R17PC00100 Specification No. None Folsom Dam Auxiliary Spillway American River Phase V – Right Bank Stabilization, Folsom Unit, American River Division, Central Valley Project, California Harrison Western Construction Corporation, Lakewood, CO
Work Performed December 44.5%
Time Elapsed 87%
Work Completed 66.5%
Contractor Earnings December $596,600.00
Previous $289,500.00
Total to Date $886,100.00
MPCO Noncontract Costs 1st Quarter Expenditures $106,860.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $106,860.00
FY18 Budgeted $179,160.00
Amount Remaining $72,300.00
Percent Remaining 40.35%
Area Office Project Management Project Manager: Kyle Keer, CC-108
Office Engineering Contract Manager: Kent Perkes, MPCO-225
Invoice No. 3, received December 13, 2017, in the amount of $596,600.00, for work performed
through December 10, 2017.
The work was substantially completed as of December 8, 2017.
Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310
Construction Representative: Ben Richburg, MPCO-318
Number of Contractor Employees: 11
Work Performed De-mobilization
13 | P a g e
Contractor completed demobilization offsite, removing project equipment/materials necessary to
complete field activities. The contractors’ main staging and auxiliary staging areas were
restored. The 330 ton Liebherr Crane was safely removed offsite. Environmental and
Hazardous Energy Control Programs were terminated with dam releases monitored. All contract
personnel returned CCAO security badges. An environmental assessment of the main staging
area was performed.
Stressing Installed Rock Bolts
The Contractor completed grouting of all rock bolts. The contractor successfully stressed all
rock bolts and completed the bolt disposition with grouted and bolted rock bolt caps.
Concrete Entrants
The contractor repaired concrete surfaces and voids.
Concrete strength testing successfully met contract requirements.
14 | P a g e
Testing rock bolts
15 | P a g e
Concrete repair at the bottom of entrant 1
16 | P a g e
Concrete repair at the bottom of entrant 3
17 | P a g e
Finished rock bolts
18 | P a g e
Completed Right Bank Stabilization Project before crane removal
19 | P a g e
Contract No. R17PC00139 Specification No. None Folsom Aggregate Structure Demolition, Removal & Disposal - Folsom Unit, American River Division, Central Valley Project, California Site Work Solutions Inc., Redding, CA
Work Performed December 13.5%
Time Elapsed 100.0%
Work Completed 100.0%
Contractor Earnings December $0.00
Previous $349,221.55
Total to Date $349,221.55
MPCO Noncontract Costs 1st Quarter Expenditures $54,422.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $54,422.00
FY18 Budgeted $64,800.00
Amount Remaining $10,378.00
Percent Remaining 16.02%
Area Office Project Management Project Manager: Mark Lewis, CC-641
Office Engineering Contract Manager: Madelyn Giles, MPCO-230
Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310
Construction Representative: Sean Frische, MPCO-317
Number of Contractor Employees: 6
Work Performed The remaining concrete debris was removed from the site this month to a local recycling facility.
The Contractor completed placing and compacting fill on the slope where the concrete aggregate
processing structure was previously located. Quality assurance and quality control soil testing
confirmed adequate compaction on the slope. The Contractor tracked walked the entire
20 | P a g e
embankment prior to applying a coating of hydro-seed with fertilizer, mulch, and tackifier. The
entire embankment was then covered with a straw erosion control blankets with fiber rolls
installed on top of the blankets. Site restoration and installation of final BMPs was completed
this month. The Contractor began and completed demobilization this shift.
21 | P a g e
Photo of Contractor installing the straw erosion control blankets on the hydro-
seeded embankment.
22 | P a g e
(This Page Intentionally Left Blank)
23 | P a g e
Klamath Basin Area Office
24 | P a g e
(This Page Intentionally Left Blank)
25 | P a g e
Contract No. R17PC00083 Specification No. None Tule Lake Road Improvement Phase 2- Klamath Project, Oregon - California Coleman Environmental Engineering, Inc., Upper Lake, CA
Work Performed December 24.8%
Time Elapsed 45.4%
Work Completed 24.8%
Contractor Earnings December $167,400.00
Previous $0.00
Total to Date $167,400.00
MPCO Noncontract Costs 1st Quarter Expenditures $44,972.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $44,972.00
FY18 Budgeted $72,345.00
Amount Remaining $27,373.00
Percent Remaining 37.84%
Area Office Project Management Project Manager: Mike Green, KO-400
Office Engineering Contract Management: Amber Pierce, MPCO-205
Invoice No. 1 was received during this period, in the amount of $167,400.00, for work performed
during the months of September through part of December.
Field Engineering Field Engineer: Brian Wagner, MPCO-300
Onsite Government Representative: Dennis Schuenemann, MPCO-338.
Number of Contractor Employees: 4
Work Performed The contractor, Coleman Environmental Engineering, Inc. (CEE) continues to prepare the road
foundations for 4” minus gravel placement. A grader was used to strike off top layer of wet soil
and blading it back over onto the existing road after all material had a chance to dry. A CAT 563
vibratory steel wheel roller (VSWR) was utilized to proof roll the foundation prior to placing 4”
minus base. The roadway widths were prepared to receive gravel from the belly dump trucks for
26 | P a g e
4” minus base rock form the O’Connor pit. 22 belly dump trucks were utilized each day to
deliver gravels to each roadway section. 6” lifts were placed along the various roadways to
achieve the required gravel placement thicknesses. A CAT 140H grader was utilized to spread
the gravels to the required thicknesses. Grading was them followed by VSWR to compact and
proof roll each lift. CEE’s personnel were onsite performing work for 20 days during this
period.
Approximately 18,500 tons of 4” minus gravels were placed this month to complete the
construction of the seven following roadways: A Middle Dike Rd., Pump 10 East Rd., East Rd.,
and N. 13 Rd. Roads that remain to be completed for the 4” minus placement are Pump 10,
Pump 11 and N. 13. About 90 tons remain to be placed to complete the 4” minus placement for
all remaining roadways. Approximately 5000 tons of ¾” minus gravels were placed atop the 4”
minus material base gravels.
The monthly joint safety policy meeting was held during this period in addition to two weekly
safety meetings which were also held by the contractor.
27 | P a g e
Belly Dump Trucks delivering 4” minus to Middle A Dike Road.
28 | P a g e
Cat 140G grader after placement of 4” minus along Middle A Dike Road.
29 | P a g e
Belly dump trucks deliver 4” minus followed by Cat 140G grader which leveled
the rock
30 | P a g e
East Rd receiving a lift of 4” minus Base Rock
31 | P a g e
Lahontan Basin Area Office
32 | P a g e
(This Page Intentionally Left Blank)
33 | P a g e
Contract No. R16PC00062 Specification No. 20-C0850 Stampede Dam, Dam Safety Modifications - Stampede Division, Washoe Project, Nevada-California NW Constructors, Inc., Bozeman, MT
Work Performed December 4%
Time Elapsed 65.9%
Work Completed 74.9%
Contractor Earnings December $1,527,503.00
Previous $15,748,808.42
Total to Date $17,276,311.56
MPCO Noncontract Costs 1st Quarter Expenditures $209,955.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $209,955.00
FY18 Budgeted $925,520.00
Amount Remaining $715,565.00
Percent Remaining 77.31%
Area Office Project Management Project Manager: Todd Hill, MP-240
Office Engineering Contract Manager: Kent Perkes, MPCO-225
Processed Pay Application No. 13, received December 7, 2017, in the amount of $1,527,503.14
for work performed through December 1, 2017.
Field Engineering Construction Manager: Kyle Hughes, MPCO-324
Construction Representative: Zahid Wazid, MPCO-349; Sean Hill, MPCO-328
Number of Contractor Employees: 0
Work Performed No onsite work performed during this period. The project is closed for the winter.
34 | P a g e
Contract No. R17PC00063 Specification No. 20-C0860 Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation - Washoe Project, Nevada-California Diana Prince Construction, Inc., Irvine, CA
Work Performed December 22.2%
Time Elapsed 80.0%
Work Completed 51.2%
Contractor Earnings December $197,739.83
Previous $257,883.77
Total to Date $455,623.60
MPCO Noncontract Costs 1st Quarter Expenditures $128,281.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $128,281.00
FY18 Budgeted $186,040.00
Amount Remaining $57,759.00
Percent Remaining 31.05%
Area Office Project Management Project Manager: Steven Sprague, LO-470
Office Engineering Contract Administrator: Madelyn Giles, MPCO-230
Invoice 04 was received this reporting period, in the amount of $197,739.83, for work performed
from November 1, 2017 to November 30, 2017.
No Modifications were executed this reporting period.
Field Engineering Construction Engineer: Reynaldo Garcia, MPCO-310
Construction Representative: Todd Dooley, MPCO-314, Bill Linder, MPCO-312
Number of Contractor Employees: 7
Work Performed
DPC removed the bulkhead gate installed upstream of Marble Bluff Dam’s radial gate.
DPC with ASI completed the installation of new guardrails on the Marble Bluff Dam’s left
abutment and the installation of new guardrail gates. They also completed the application of
35 | P a g e
Pro-Cryl Universal primer and Pro Industrial Acrylic Topcoat to new guardrails and new
guardrail gates. DPC with ASI completed coating existing guardrails. They also completed the
installation of fence fabric to new and existing guardrails. They also completed applying
DynaTrol-I-XL-DS polyurethane sealant to the bottom of new and existing guardrail posts.
DPC with ASI completed surface preparation for radial gate hoist machinery and the application
of a topcoat of Pro-Industrial Acrylic Topcoat. DPC removed all pumps and equipment from the
entry channel and removed the cover plate installed on the downstream side of the entry
channel’s 24-inch drain pipe. DPC with ASI installed the fish lock brush assemblies. They also
removed both the containment and the scaffolding surrounding the fish lock elevator. DPC with
PEC installed the fish lock hoist. Reclamation operated the hoist with the attached fish lock
elevator through a few cycles without incident. DPC staged equipment no longer in use at
Marble Bluff Dam’s staging area west of the Fish Facility Building. PEC removed existing
panels DFBA and LFBP. They also removed motor starters for Marble Bluff Dam’s Dope Tank,
Turbine Pump, Auxiliary Turbine Pump and the Air Compressor. PEC installed new panels
DFBA and LFBP and motor starter panels for the Dope Tank, Turbine Pump, and Auxiliary
Turbine Pump to replace existing. They also installed a 15-kVA transformer panel between
panels DFBA and LFBP. They also installed new stainless-steel raceways and new ¾-inch rigid
conduit. PEC completed insulation resistance tests of wires between new panels and existing
equipment. They also confirmed the correct phase rotation for each of the existing motors fed
from new panels.
36 | P a g e
Contract No. R17PC00067 Specification No. None Lahontan Dam Rated Vehicle Barrier System - Newlands Project, Fallon, Nevada Sentinel Builders LCC, Sparks NV
Work Performed December 0.0%
Time Elapsed 100%
Work Completed 100%
Contractor Earnings December $0.00
Previous $146,535.00
Total to Date $146,535.00
MPCO Noncontract Costs 1st Quarter Expenditures $18,548.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $18,548.00
FY18 Budgeted $16,605.00
Amount Remaining $0.00
Percent Remaining 0.0%
Area Office Project Management Project Manager: Scott Schoenfeld, LO-410
Office Engineering Contract Administrator: Lawrence Bowman, MPCO-240
This contract was awarded on June 1, 2017 in the amount of $146,535.00.
Field Engineering Construction Engineer: Reynaldo Garcia, MPCO-310
Construction Representative: Reynaldo Garcia, MPCO-310
Number of Contractor Employees: 0
Work Performed No onsite work was performed during this period.
37 | P a g e
Northern California Area Office
38 | P a g e
(This Page Intentionally Left Blank)
39 | P a g e
Contract No. R15PC00089 Specification No. 20-C0831 Intake 3 Screen Extension, Coleman National Fish Hatchery, Shasta Division, Central Valley Project, California Contractor Services Group, Inc., West Sacramento, CA
Work Performed December 3.8%
Time Elapsed 100.0%
Work Completed 90.3%
Contractor Earnings December $0.00
Previous $1,815,088.05
Total to Date $1,815,088.05
MPCO Noncontract Costs 1st Quarter Expenditures $20,270.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $20,270.00
FY18 Budgeted $67,235.00
Amount Remaining $46,965.00
Percent Remaining 69.85%
Area Office Project Management Project Manager: Hank Harrington, NC-210
Office Engineering Contract Manager: Kent Perkes, MPCO-225
The work was substantially completed as of December 12, 2017.
The work was transferred to the Bureau of Reclamation Northern California Area Office for
operation and maintenance as of November 2, 2017.
Field Engineering Construction Manager: Brian Wagner, MPCO-300
Construction Representative: Fernando Pavone, MPCO-333
Number of Contractor Employees: 0
Work Performed No onsite work performed during this period.
40 | P a g e
Contract No. R16PC00006 Specification No. 20-C0841 Trinity Powerplant Generator Rewinds - Trinity River Division, Central Valley Project, California Voith Hydro, Inc., York, PA
Work Performed December 4.6%
Time Elapsed 76.7%
Work Completed 77.7%
Contractor Earnings December $611,483.00
Previous $9,768,798.06
Total to Date $10,380,281.06
MPCO Noncontract Costs 1st Quarter Expenditures $106,542.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $106,542.00
FY18 Budgeted $442,535.00
Amount Remaining $335,993.00
Percent Remaining 75.92%
Area Office Project Management Project Manager: Joe Ascoli, NC-650
Office Engineering Contract Administrator: Madelyn Giles, MPCO-230
Invoice 07 was received this reporting period, in the amount of $611,483.00, for work performed
from November 1, 2017 to November 30, 2017.
No Modifications were received this reporting period.
Field Engineering Construction Manager: Brian Wagner, MPCO-300
Construction Representative: Stephen Holmes, MPCO-320
Number of Contractor Employees: 14
Work Performed Subcontractor Metrology Services was on site checking verticality and roundness of the stator
core. Using a FARO laser, the technician programed unit centerline coordinates from previously
established monuments beneath the core. Once programed the technician shot the core in 24
41 | P a g e
locations equally spaced around the circumference. One shot was taken at the top and bottom of
the core slots.
With acceptance of the roundness and verticality of the stator core the Voith crew began
installation of the armature winding, completing installation of all 432 bottom Roebel bars and
approximately 300 of 432 top bars prior to Christmas break. Each of the bars installed were
wrapped with conductive paper with a layer of conductive putty on the inside of the paper as it is
wrapped around each bar on three sides. The putty is applied with a grooved trowel. The bars
are inserting into their slots by hand and temporarily wedged in place until secured with lashing
to the surge rings on the upper and lower ends.
The crew was able to secure the bottom bars to the rings with epoxy saturated fiberglass cord as
they were tested and accepted and installed before the top bars were started.
During the early part of the month as fill in work, Voith crew members cleaned rotor fan
components with a mild household cleaner removing built-up oil and break dust.
The thrust bearing high pressure lift pump was mounted on the exterior of the unit air housing
and electrical conduits run from the pump’s starter to the Generator ‘A’ box.
A unilateral modification was issued to Voith in November for their rotor pole refurbishment
contractor to investigate obvious arc burns on the amortisseur windings. Representatives from
Voith engineering and the Bureau’s Denver Technical Service Center met at the refurbishment
facility (Delstar) in Montreal, Canada.
The result from dissecting the windings showed the through rods were loose and may have
contributed to the issue.
Unilateral direction was then issued in December for the facility to replace 30 top and 30 bottom
laminations on each of the 36 rotor poles and to peen the five rods connecting the top and bottom
shorting bars of the amortisseur winding.
42 | P a g e
Preparing conductive paper with putty.
43 | P a g e
Crew wrapping Roebel bar with the conductive paper.
44 | P a g e
Crew members inserting bar in the core slot.
45 | P a g e
Thrust bearing high pressure lift pump and starter
46 | P a g e
Contract No. R17PC00029 Specification No. 20-C0847 Trinity River Division Powerplants Replacement of Station Service Transformers and Low Voltage Bus System – Trinity River Division, Central Valley Project, Trinity and Shasta Counties, California Gardner Zemke, Albuquerque, NM
Work Performed December 1.5%
Time Elapsed 35.6%
Work Completed 7.0%
Contractor Earnings December $42,928.00
Previous $155,144.00
Total to Date $198,072.00
MPCO Noncontract Costs 1st Quarter Expenditures $28,553.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $28,553.00
FY18 Budgeted $135,905.00
Amount Remaining $107,353.00
Percent Remaining 78.99%
Area Office Project Management Project Manager: Laurie Larson, NC-211
Office Engineering Contract Administrator: Madelyn Giles, MPCO-230
Invoice No. 04, in the amount of $42,928.00, was received this reporting period for work
performed November 21, 2017 to December 18, 2017.
No Modifications were received this reporting period.
Field Engineering Construction Engineer: Brian Wagner, MPCO-300
Construction Representative: Stephen Holmes, MPCO-320
Number of Contractor Employees: 0
Work Performed: No onsite work was performed during this reporting period.
47 | P a g e
Contract No. R16PC00134 Specification No. 20-C0852 Whiskeytown Lake, Spring Creek Temperature Control Curtain - Trinity River Division, Central Valley Project, California BCI Construction USA, Inc., Belleville IL
Work Performed December 18.3%
Time Elapsed 99.3%
Work Completed 99.5%
Contractor Earnings December $356,169.88
Previous $1,579,325.13
Total to Date $1,935,495.01
MPCO Noncontract Costs 1st Quarter Expenditures $53,464.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $53,464.00
FY18 Budgeted $150,525.00
Amount Remaining $97,061.00
Percent Remaining 64.48%
Area Office Project Management Project Manager: Robert Gee, NC-230
Office Engineering Contract Manager: Amber Pierce, MPCO-205
Invoice No. 05, in the amount of $356,169.88, was received this reporting period, for work
performed during the month of November.
Field Engineering Construction Manager: Brian Wagner, MPCO-300
Construction Representative: Stephen M. Holmes, MPCO-320, Russell Davies, MPCO-341
Number of Contractors Employees: 0
Work performed No onsite work was performed during this period. The contractor demobilized from the site on
November 20, 2017. This work was determined to be substantially complete as of November 16,
2017
48 | P a g e
Contract No. R17PC00103 Specification No. 20-C0866 Keswick & Shasta Powerplant Weldshop Ventilation System Procurement & Installation - Shasta and Keswick Powerplant - Central Valley Project - California Air-O-Service, Redding, CA
Work Performed December 0.00%
Time Elapsed 56.7%
Work Completed 0.00%
Contractor Earnings December $0.00
Previous $0.00
Total to Date $0.00
MPCO Noncontract Costs 1st Quarter Expenditures $10,970.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $10,970.00
FY18 Budgeted $123,045.00
Amount Remaining $84,460.00
Percent Remaining 68.64%
Area Office Project Management Project Manager: Thomas Darlington, NC-232
Office Engineering Contract Administrator: Casandra Arthur, MPCO-111
Field Engineering Construction Manager: Stephen Holmes, MPCO-320
Construction Representative: David Derk, MPCO-334
Number of Contractor Employees: 0
Work Performed No onsite work was performed during this period.
49 | P a g e
Contract No. R17PC00091 Specification No. 20-C0869 Intake 3 Trash Rake, Coleman National Fish Hatchery, Shasta Division, Central Valley Project, California Tompco-Triton, Seabeck, WA
Work Performed December 0.0%
Time Elapsed 22.0%
Work Completed 1.1%
Contractor Earnings December $0.00
Previous $16,143.00
Total to Date $16,143.00
MPCO Noncontract Costs 1st Quarter Expenditures $0.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $0.00
FY18 Budgeted $0.00
Amount Remaining $0.00
Percent Remaining 0.0%
Area Office Project Management Project Manager: Hank Harrington, NC-210
Office Engineering Contract Manager: Kent Perkes, MPCO-225
Approved Request for Change No. 001, Festoon Location, on December 12, 2017, as a no cost
change.
Field Engineering Construction Manager: Brian Wagner, MPCO-300
Construction Representative:
Number of Contractor Employees: 0
Work Performed No onsite work was performed during this period.
50 | P a g e
Contract No. R17PC00092 Specification None Install K12 Rated Vehicle Barriers at Keswick, Shasta and Trinity Power Plants Shasta and Trinity Division, Central Valley Project, California Purgatory Fence Company, Inc., Boise, ID
Work Performed December 0.0%
Time Elapsed 10.1%
Work Completed 6.1%
Contractor Earnings December $0.00
Previous $29,700.00
Total to Date $29,700.00
MPCO Noncontract Costs 1st Quarter Expenditures $19,352.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $19,352.00
FY18 Budgeted $123,045.00
Amount Remaining $103,693.00
Percent Remaining 84.27%
Area Office Project Management Project Manager: Robert Gee, NC-230
Office Engineering Contract Manager: Amber Pierce, MPCO-205
Field Engineering Field Engineer: Brian Wagner, MPCO-300
Construction Manager: Stephen Holmes, MPCO-320.
Number of Contractor Employees: 0
Work Performed No onsite work was performed during this period.
51 | P a g e
South Central California Area
Office
52 | P a g e
(This Page Intentionally Left Blank)
53 | P a g e
There was no work performed during this period for the South Central California Area Office.
54 | P a g e
(This Page Intentionally Left Blank)
55 | P a g e
San Joaquin River Restoration
Program
56 | P a g e
(This Page Intentionally Left Blank)
57 | P a g e
There was no work performed during this period for the South Central California Area Office.
58 | P a g e
(This Page Intentionally Left Blank)
59 | P a g e
Mid-Pacific Regional Office
60 | P a g e
(This Page Intentionally Left Blank)
61 | P a g e
Contract No. R16PC00091 Specification No. 20-C0843 North Fork Screens and Ladder Completion Contract - Battle Creek Salmon and Steelhead Restoration Project, California TNT Industrial Contractors, Inc., Sacramento, CA
Work Performed December 0.00%
Time Elapsed 81.0%
Work Completed 77.5%
Contractor Earnings December $0.00
Previous $4,260,023.10
Total to Date $4,260,023.10
MPCO Noncontract Costs 1st Quarter Expenditures $141,104.00
2nd Quarter Expenditures $0.00
3rd Quarter Expenditures $0.00
4th Quarter Expenditures $0.00
FY18 Cumulative Total $141,104.00
FY18 Budgeted $414,120.00
Amount Remaining $273,016.00
Percent Remaining 65.93%
Area Office Project Management Project Manager: Mary Marshall, MP-203
Office Engineering Contract Administrator: Casandra Arthur, MPCO-111
No invoices were received during this reporting period.
Two modifications were executed during this reporting period; Unilateral Modification 006 in
the amount of $195,000 and Bilateral Modification 007 in the amount of $7,296.04.
Field Engineering Construction Manager: Brian Wagner, MPCO-300
Construction Representative: Jason Foust, MPCO-325
Number of Contractor Employees: 12
Work Performed The following work took place at the North Battle Creek Feeder Diversion Dam (NBCFDD) site;
Subcontractor Syblon Reid (SRCO) finished installing the fish screens and associated parts
including the upper and lower channels for the louvers, the louvers, the upper and lower fish
screen support brackets, the fish screen panels and blanking plates at the fish screen structure.
62 | P a g e
All the connections between the dissimilar metals were isolated. Also at the fish screen
structure, the brush motor and counterweight assemblies were aligned, the electrical for the brush
cleaners was connected and the flashboards were installed in the guide vanes.
SRCO continued work under unilateral modification 006 and installed the transition step on the
downstream of the fish screen structure.
SRCO began demobilizing equipment from the NBCFDD project site. No work occurred at Eagle
Canyon during this reporting period.
63 | P a g e
North Fork Screens and Ladders Completion Contract
Installation of the NBCFDD lower louver channel supports at the fish screen structure
64 | P a g e
North Fork Screens and Ladders Completion Contract
Installation of Fish Screen Louvers
65 | P a g e
North Fork Screens and Ladders Completion Contract
Electrical connections for the Fish Screen Brush Cleaner
66 | P a g e
(This Page Intentionally Left Blank
67 | P a g e
Contracts in Warranty Status
68 | P a g e
(This Page Intentionally Left Blank)
69 | P a g e
R11PC20185 No. 20-C0778 Tracy 13.8kV Switchgear/Breaker Replacement – Tracy Pumping Plant and Substation - Delta Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The warranty work for the
B15 DFR will extend the 1-year warranty from June 29, 2017 through June 28, 2018.
R13PC20159 No. 20-C0819 Lake Berryessa Concessions Areas Improvements – Lake Berryessa, Solano Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began on March 31, 2017 and will end March 30, 2018.
R16PC00079 No. 20-C0851 Red Bluff Flap Gate Retrofit - Sacramento Canals Unit, Sacramento River Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began March 16, 2017 and will end March 15, 2018.
R17PC00022 No. 20-C0857 Western Tracy Switchyard - Chain Link Fence Project Tracy Pumping Plant and Substation - Delta Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began May 11, 2017 and will end May 10, 2018.
R11PC2023S None Red Bluff Diversion Dam, Fish Passage Improvement Project Terrestrial Mitigation - Sacramento River Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began December 31, 2016 and will end December 30, 2017.
R16PC00099 None Folsom Dam Resource Building Replacement - Folsom Unit, American River Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began February 14, 2017 and will end February 13, 2018.
R16PC00100 None Lake Woollomes Recreation Area Asphalt Replacement - Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began April 26, 2017 and will end April 25, 2018.
R15PC00080 20-C0836 Klamath Basin Area Office Sewer Lift Station, Klamath Basin Area Office, Klamath Falls, Oregon Office Engineering is reviewing required submittals. The 1-year warranty period began January
20, 2017 and will end January 19, 2018.
R16PC00111 20-C0855 San Joaquin Hatchery Water Supply Pipeline - Friant Division, Central Valley Project, California Invoice No. 09 was received this reporting period for work performed in August. The 1-year
warranty period began June 29, 2017 and will end June 28, 2018.
70 | P a g e
R16PC00110 20-C0853 Madera Canal Headworks Low-Flow Valve - Friant Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty
period began June 29, 2017 and will end June 28, 2018
71 | P a g e
Lab Reports
72 | P a g e
(This Page Intentionally Left Blank)
73 | P a g e
Stampede Safety of Dams Project
There was no laboratory information provided from the Materials Lab for this
project during this period.
74 | P a g e
(This Page Intentionally Left Blank)
75 | P a g e
North Fork Screens and Ladders Completion Contract
There was no laboratory information provided from the Materials Lab for this project during this period.
76 | P a g e
(This Page Intentionally Left Blank)