Microsoft Project 2010 Demo Part 3

9
1 Microsoft Project 2010 Demo Part 3

description

Microsoft Project 2010 Demo Part 3 . Problem 1.2. - PowerPoint PPT Presentation

Transcript of Microsoft Project 2010 Demo Part 3

Page 1: Microsoft Project 2010 Demo Part 3

1

Microsoft Project 2010 Demo Part 3

Page 2: Microsoft Project 2010 Demo Part 3

2

Problem 1.2Enter tasks, times, and sequence requirements for problem 1.2. Be sure to click Project/Project Information to set project starting date. Calculate mean task times by hand, using a spreadsheet, or using http://www.had2know.com/business/pert-estimation-formula-calculator.html. Find critical path.

Page 3: Microsoft Project 2010 Demo Part 3

3

Insert Rows for More TasksTo insert rows for summary tasks or subtasks, hold cursor on task that will go below new task and right click Insert Task.

Page 4: Microsoft Project 2010 Demo Part 3

4

Indenting TasksTo create subtasks or summary tasks click Task and then the green arrow icons. This will create indented tasks.

Page 5: Microsoft Project 2010 Demo Part 3

5

Cost and Material ResourcesTo add costs, material resources, or additional labor resources, you can go to View/Resource Sheet. You can define resources and fill in information as seen below.

Page 6: Microsoft Project 2010 Demo Part 3

6

Add Cost Column(s)To add a column of data go to a blank column (labeled Add New Column), scroll down the menu and choose the appropriate item such as Cost.

Page 7: Microsoft Project 2010 Demo Part 3

7

Printing ResultsFirst be sure results show on computer screen nicely. Then go to File/Print. See print screen below. Please conserve on pages printed. Be green!

Page 8: Microsoft Project 2010 Demo Part 3

8

Beware of Indicator IconTo remove indicator, double click task with icon. Open the Advanced tab. Set constraint type to “as soon as possible”.

Page 9: Microsoft Project 2010 Demo Part 3

9

Beware of Indicator IconCompleted removal step is shown below.