Microsoft Office Project - Hhsjb Emer-uci Gantt-pert Cpm Final

3
Id Descripción Partida Duración Inicio 1 MEJORAMIENTO DE LA CAPACIDAD RESOLUTIVA DE LOS SERVICIOS DE SALU 210 días jue 01/03/12 2 ESTRUCTURAS 203 días jue 01/03/12 3 OBRAS PROVISIONALES 12 días dom 04/03/12 4 CONSTRUCCIONES PROVISIONALES 8 días dom 04/03/12 5 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M 2 días dom 04/03/12 6 OFICINA DE OBRA 3 días mar 06/03/12 7 ALMACEN DE OBRA 3 días vie 09/03/12 8 CASETA PARA GUARDIANIA 3.00 x 2.40m 3 días vie 09/03/12 9 VESTUARIO PARA EL PERSONAL DE OBRA 3.00 x 3.00 m 3 días vie 09/03/12 10 SERVICIOS HIGIÉNICOS PARA EL PERSONAL DE OBRA 2.40 x 1 3 días mar 06/03/12 11 CERCO PERIMETRICO PROVISIONAL, MALLA CON POSTES DE 4 días dom 04/03/12 12 INSTALACIONES PROVISIONALES 4 días lun 12/03/12 13 INSTALACIÓN PROVISIONAL DE AGUA 2 días mié 14/03/12 14 INSTALACIÓN PROVISIONAL DE DESAGUE 2 días lun 12/03/12 15 INSTALACIÓN PROVISIONAL DE SERVICIO ELÉCTRICO 2 días lun 12/03/12 16 INSTALACIÓN PROVISIONAL DE LÍNEA TELEFÓNICA 2 días mié 14/03/12 17 TRABAJOS PRELIMINARES 184 días jue 01/03/12 18 TRAZO, NIVELES Y REPLANTEO 154 días jue 01/03/12 19 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 3 días jue 01/03/12 20 TRAZO, NIVELES Y REPLANTEO PERMANENTE 10 días lun 02/04/12 21 MOVILIZACIÓN DESMOVILIZACIÓN DE EQUIPOS 184 días jue 01/03/12 22 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO 14 días jue 01/03/12 23 MOVIMIENTO DE TIERRAS 27 días jue 08/03/12 24 NIVELACIÓN DEL TERRENO 2 días vie 16/03/12 25 PERFILADO, NIVELACIÓN Y COMPACTADO DE TERRENO C/EQ 2 días vie 16/03/12 26 EXCAVACIONES 9 días dom 11/03/12 27 EXCAVACIÓN MASIVA O COMGLOMERADO 3 días dom 11/03/12 28 EXCAVACIÓN DE ZANJA PARA CIMIENTO CORRIDO 6 días mié 14/03/12 29 CORTES 3 días jue 08/03/12 30 CORTE MANUAL DE TERRENO NORMAL 3 días jue 08/03/12 31 RELLENOS 3 días sáb 31/03/12 32 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO 3 días sáb 31/03/12 33 ELIMINACIÓN DE MATERIAL EXCEDENTE 2 días lun 02/04/12 34 ELIMINACIÓN DE MATERIAL EXCEDENTE C/EQUIPO 2 días lun 02/04/12 35 NIVELACIÓN INTERIOR Y APISONADO 4 días mar 20/03/12 36 NIVELACIÓN Y COMPACTACIÓN DE TERRENO CON COMPACT 4 días mar 20/03/12 37 CONCRETO SIMPLE 118 días mar 20/03/12 38 SOLADOS 4 días mar 20/03/12 39 CONCRETO C.H. 1:10 E=4" - SOLADOS 4 días mar 20/03/12 40 CIMIENTOS CORRIDOS 8 días sáb 24/03/12 41 CONCRETO CICLOPEO Fc=100 Kg/Cm2 + 30% P.G. - CIMIENTOS 3 días jue 29/03/12 42 ENCOFRADO Y DESENCOFRADO NORMAL CIMIENTOS CORRI 6 días sáb 24/03/12 43 SOBRECIMIENTOS 10 días dom 01/04/12 44 CONCRETO CICLOPEO Fc=140 Kg/Cm2 +25% P.M. SOBRECIMIE 4 días sáb 07/04/12 45 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTOS 6 días dom 01/04/12 46 FALSO PISO 4 días lun 30/04/12 47 FALSO PISO DE 4" CON MEZCLA C:H 1:8 INC. BASE GRANULAR 4 días lun 30/04/12 48 VEREDAS Y SARDINELES 10 días lun 25/06/12 49 VEREDAS DE CONCRETO Fc=140 Kg/Cm2 E=4" 6 días mié 27/06/12 50 SARDINEL PERALTADO DE CONCRETO Fc=140 Kg/Cm2 H=0.20 3 días lun 25/06/12 51 JUNTAS ASFALTICAS 2 días mar 03/07/12 52 RAMPA 10 días vie 06/07/12 53 RAMPA DE CONCRETO PEATONAL Fc=140 Kg/Cm2 4 días vie 06/07/12 54 RAMPA DE CONCRETO VEHICULAR Fc=175 Kg/Cm2 4 días mar 10/07/12 55 JUNTAS ASFALTICAS 2 días sáb 14/07/12 56 ESTACIONAMIENTO 7 días dom 29/04/12 57 LOSA DE CONCRETO Fc=210 Kg/Cm2 E=8" ACABADOS FROTAC 5 días dom 29/04/12 58 JUNTAS ASFALTICAS 2 días vie 04/05/12 59 CONCRETO ARMADO 202 días vie 02/03/12 60 ZAPATAS 11 días sáb 24/03/12 61 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 4 días sáb 31/03/12 62 ACERO CORRUGADO FY=4200 Kg/Cm2 7 días sáb 24/03/12 63 COLUMNAS 51 días sáb 31/03/12 64 CONCRETO EN COLUMNAS F'C=210 KG/CM2 6 días vie 20/04/12 65 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 12 días jue 12/04/12 66 ACERO CORRUGADO FY=4200 Kg/Cm2 8 días sáb 31/03/12 67 VIGAS 58 días lun 21/05/12 68 CONCRETO EN VIGAS F'C=210 KG/CM2 2 días mar 26/06/12 69 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 8 días lun 18/06/12 70 ACERO CORRUGADO FY=4200 Kg/Cm2 8 días lun 21/05/12 71 CISTERNA SUBTERRANEA 21 días mié 11/04/12 72 CONCRETO Fc=245 Kg/Cm2 LOSA ALIGERADA 2 días lun 30/04/12 73 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA SUB 6 días mar 24/04/12 74 ACERO CORRUGADO Fy=4200 Kg/Cm2 4 días mié 11/04/12 75 LOSAS ALIGERADAS 54 días lun 21/05/12 76 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 2 días vie 25/05/12 77 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERA 10 días lun 18/06/12 78 ACERO CORRUGADO FY=4200 Kg/Cm2 8 días lun 21/05/12 79 LADRILLO HUECO DE ARCILLA 20X30X30 CM PARA TECHO ALI 2 días lun 18/06/12 80 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALI 2 días mié 20/06/12 81 VARIOS 202 días vie 02/03/12 82 JUNTA DE DILATACION SISMICA E=2" 3 días vie 22/06/12 83 SEGURIDAD E HIGIENE DE OBRA 20 días vie 02/03/12 84 MITIGACION DEL IMPACTO AMBIENTAL 6 días dom 04/03/12 85 ARQUITECTURA 202 días vie 02/03/12 86 MUROS Y TABIQUES DE ALBAÑILERIA 36 días mar 10/04/12 87 MURO DE LADRILLO K.K. DE CABEZA MEZCLA C:A 1:4 TIPO IV P. TA 10 días sáb 14/04/12 88 MURO DE LADRILLO K.K. DE SOGA MEZCLA C:A 1:4 TIPO IV P. TAR 16 días mar 10/04/12 89 REVOQUES ENLUCIDOS Y MOLDURAS 63 días mié 16/05/12 90 TARRAJEO PRIMARIO Y RAYADO MEZCLA C:A 1:5 4 días mié 16/05/12 91 TARRAJEO FROTACHADO DE MUROS INTERIORES MEZCLA C:A 1: 16 días dom 20/05/12 92 TARRAJEO FROTACHADO DE MUROS EXTERIORES MEZCLA C:A 1 4 días mar 26/06/12 93 TARRAJEO DE COLUMNAS, C:A 1:5, E=1.5 CM 5 días mar 03/07/12 94 TARRAJEO DE VIGAS C:A 1:5, E=1.5 CM 5 días jue 28/06/12 95 TARRAJEO CON IMPERMEABILIZANTE MEZCLA C:A 1:4 E=1.5cm. 3 días dom 15/07/12 96 VESTIDURA DE DERRAMES, ANCHO =0.15m. 5 días dom 08/07/12 97 BRUÑAS DE 1Cm. X 1Cm. 2 días vie 13/07/12 98 CIELORRASOS 16 días vie 01/06/12 99 CIELORRASO CON MEZCLA C:A 1:5 E=1.5 Cm. 8 días vie 01/06/12 100 FALSO CIELO DE DRYWALL 8 días sáb 09/06/12 101 PISOS Y PAVIMENTOS 55 días dom 13/05/12 102 CONTRAPISOS 6 días dom 13/05/12 103 CONTRAPISO DE 4 CM, BASE 3 CM MEZ. 1:5, ACAB. 1 CM. PAS 4 días dom 13/05/12 104 CONTRAPISO DE 48 MM. 4 días mar 15/05/12 105 PISOS 20 días dom 17/06/12 106 PISO DE POLIETILENO VINILICO 1.6MM. EN ROLLO 6 días vie 29/06/12 107 PISO DE CERAMICO DE COLOR CLARO DE 50X50 CM. 8 días jue 21/06/12 108 PISO DE CERAMICO DE COLOR CLARO DE 30X30 CM. 12 días dom 17/06/12 109 PISO DE CEMENTO SEMI PULIDO Y BRUÑADO E=2" 2 días vie 29/06/12 110 VEREDAS (FROTACHADO) C/MORTERO 1:2 X 1.5 CM. DE ESPE 4 días dom 01/07/12 111 BASE DE CONCRETO DE 10cm. 2 días jue 05/07/12 112 CONTRAZOCALOS 16 días vie 01/06/12 113 CONTRAZOCALO SANITARIO DE TERRAZO PULIDO, H=0.10M. 8 días lun 04/06/12 114 CONTRAZOCALO DE CERAMICA 30X10 COLOR CLARO 5 días mar 12/06/12 115 CONTRAZOCALO DE CEMENTO S/COLOREAR (H=10CM.) 3 días vie 01/06/12 116 ZOCALOS 12 días vie 01/06/12 117 ZOCALO DE CERAMICA 20X30 CM 8 días vie 01/06/12 118 ZOCALO DE CEMENTO PULIDO CON IMPERMEABILIZANTE (H=0.50 4 días sáb 09/06/12 119 REVESTIMIENTOS 4 días mar 19/06/12 120 REVESTIMIENTO DE LAMINADO VINILICO DE PISO A TECHO 4 días mar 19/06/12 121 COBERTURAS 6 días jue 02/08/12 122 COBERTURA LADRILLO PASTELERO ASENTADO C/MEZCLA 4 días jue 02/08/12 123 COBERTURA LIGERA CON POLICARBONATO TRANSLUCIDO 4 días sáb 04/08/12 124 CARPINTERIA DE MADERA 45 días vie 29/06/12 125 PUERTAS DE MADERA 9 días jue 02/08/12 126 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5m 5 días jue 02/08/12 127 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5m 4 días mar 07/08/12 128 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5m 2 días dom 05/08/12 129 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5m 2 días mar 07/08/12 130 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5m 2 días jue 09/08/12 131 PANEL DIVISORIO PARA SH (INCL. PUERTA) 2 días mar 07/08/12 132 VENTANAS DE MADERA 2 días jue 09/08/12 133 VENTANA CON MARCO DE MADERA 2 días jue 09/08/12 134 BARRA DE PROTECCIÓN 2 días sáb 11/08/12 135 BARRA DE PROTECCION CONTRAIMPACTO DE CAMILLAS 2 días sáb 11/08/12 136 MUEBLES DE MELANINA 20 días vie 29/06/12 137 MUEBLE FIJO TIPO M-3 3 días vie 29/06/12 138 MUEBLE FIJO TIPO M-6 4 días lun 02/07/12 139 MUEBLE FIJO TIPO M-11 4 días lun 02/07/12 140 MUEBLE FIJO TIPO M-30 2 días vie 06/07/12 141 MUEBLE FIJO TIPO M-38 2 días dom 08/07/12 142 MUEBLE FIJO TIPO M-40 2 días mar 10/07/12 143 MUEBLE FIJO TIPO M-41 2 días jue 12/07/12 144 MUEBLE FIJO DE ADMISION 2 días sáb 14/07/12 145 MUEBLE FIJO DE CONTROL / ESTACION DE ENFERMERAS 3 días lun 16/07/12 146 CARPINTERIA METALICA Y DE ALUMINIO 30 días lun 30/07/12 147 VENTANAS DE ALUMINIO 6 días lun 30/07/12 148 ESTRUCTURA DE ALUMINIO PARA VENTANA CON SISTEMA FI 4 días lun 30/07/12 149 ESTRUCTURA DE ALUMINIO PARA VENTANA CON SISTEMA CO 2 días vie 03/08/12 150 MAMPARAS DE ALUMINIO 4 días lun 30/07/12 151 ESTRUCTURA DE ALUMINIO PARA MAMPARA 4 días lun 30/07/12 152 PUERTAS DE ALUMINIO 2 días vie 03/08/12 153 ESTRUCTURA DE ALUMINIO PARA PUERTA-VENTANA 2 días vie 03/08/12 154 CARPINTERIA METALICA Y HERRERIA 16 días lun 13/08/12 155 BARANDA METALICA DE Ø1.1/2" 4 días lun 13/08/12 156 BARRA DE APOYO PARA DISCAPACITADO 2 días vie 17/08/12 157 TAPA METALICA DE INSPECCION (0.70 x 0.70m.) 3 días jue 16/08/12 158 REJA METALICA BATIENTE 1 HOJA PARA INGRESO PEATONAL 2 días dom 19/08/12 159 REJA METALICA BATIENTE 2 HOJAS PARA INGRESO VEHICUL 2 días mar 21/08/12 160 REJA METALICA BATIENTE 2 HOJAS CON MALLA (1.60X2.20) 2 días jue 23/08/12 161 PASOS METALICOS AISLADOS TIPO GRAPA 2 días sáb 25/08/12 162 MUEBLE METALICO TIPO M - 8 2 días lun 27/08/12 163 CERRAJERIA 31 días mar 07/08/12 164 BISAGRAS 4 días mar 07/08/12 165 BISAGRA CAPUCHINA 31/2" x 31/2" 3 días mar 07/08/12 166 BISAGRA CAPUCHINA 4" x 4" 1 día vie 10/08/12 167 CERRADURAS 17 días sáb 11/08/12 168 CERRADURA TIPO B 3 días sáb 11/08/12 169 CERRADURA TIPO C 2 días mar 14/08/12 170 CERRADURA TIPO D 2 días mar 14/08/12 171 CERRADURA TIPO E 3 días jue 16/08/12 172 CERRADURA TIPO G 3 días dom 19/08/12 173 CERRADURA TIPO H 2 días mié 22/08/12 174 CERRADURA TIPO I 2 días vie 24/08/12 175 CERRADURA TIPO K 2 días dom 26/08/12 176 CIERRA PUERTAS Y OTROS 9 días dom 19/08/12 177 CERROJO SIMPLE TIPO N 1 día dom 19/08/12 178 CIERRAPUERTAS TIPO Q 1 día lun 20/08/12 179 CIERRAPUERTAS TIPO P (Aérea) 1 día mié 22/08/12 180 TOPES 2" 4 días jue 23/08/12 181 PICAPORTE DE ALUMINIO DE 13" 1 día lun 27/08/12 182 VIDRIOS, CRISTALES Y SIMILARES 10 días mar 28/08/12 183 VIDRIO LAMINADO E=4.5mm. 6 días mar 28/08/12 184 VIDRIO LAMINADO E=6mm. 2 días lun 03/09/12 185 VIDRIO TEMPLADO E=10mm. 3 días vie 31/08/12 186 ESPEJO DE CRISTAL (SUMINIST. E INSTALAC.) 2 días lun 03/09/12 187 MURO CORTINA CON CRISTAL TEMPLADO INCOLORO E=10 m 2 días mié 05/09/12 188 PINTURA 30 días mié 08/08/12 189 PINTURA DE CIELORRASOS C/LATEX - 2 MANOS C/ IMPRIMAN 8 días mié 08/08/12 S 1,002.06 S 2,466.68 S 1,213.85 S 495.42 S 856.48 S 501.26 S 6,512.23 S 313.29 S 375.95 S 626.58 S 313.29 S 3,708.68 S 3,884.24 S 3,132.90 S 4,147.57 S 9,408.20 S 15,181.02 S 949.07 S 27,031.41 S 24,224.34 S 12,386.58 S 5,939.18 S 82,723.22 S 28,460.87 S 9,828.58 S 4,258.16 S 90,064.43 S 35,198.02 S 415.42 S 471.89 S 3,819.42 S 2,626.52 S 491.55 S 45,671.48 S 1,114.51 S 53,427.43 S 20,033.94 S 68,163.42 S 61,335.25 S 128,325.26 S 78,901.03 S 82,305.43 S 140,317.72 S 29,716.34 S 8,085.90 S 12,880.92 S 38,135.86 S 67,000.67 S 60,947.46 S 18,295.13 S 21,884.37 S 3,382.00 S 25,063.20 S 28,822.68 S 45,974.73 S 73,384.33 S 18,824.65 S 47,214.57 S 18,365.69 S 14,691.02 S 24,972.87 S 6,816.13 S 15,268.62 S 1,239.44 S 58,487.79 S 18,217.56 S 29,884.89 S 10,953.57 S 60,897.23 S 36,616.72 S 66,138.51 S 1,109.03 S 8,231.14 S 1,063.84 S 15,910.84 S 10,557.91 S 334.95 S 67,479.49 S 1,360.65 S 7,187.62 S 87,984.06 S 6,202.31 S 25,795.48 S 19,095.75 S 3,917.10 S 26,373.46 S 1,126.79 S 10,275.69 S 497.66 S 29,991.53 S 8,006.15 S 17,368.80 S 7,628.14 S 299.24 S 393.12 S 1,490.72 S 3,923.00 S 8,255.01 S 12,335.85 S 8,573.49 S 2,590.86 S 11,839.03 S 3,829.49 S 6,528.32 S 4,195.58 S 969.83 S 814.09 S 1,441.03 S 2,125.56 S 277.81 S 24,478.87 S 4,439.12 S 154.59 S 3,848.30 S 724.49 S 731.34 S 1,377.22 S 2,568.23 S 914.43 S 244.25 S 147.10 S 123.99 S 1,730.68 S 655.59 S 1,617.33 S 57.63 S 13,471.94 S 3,516.16 S 13,857.54 S 986.30 S 15,097.96 S 14,691.74 26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 30 mar '12 abr '12 may '12 jun '12 jul '12 ago '12 sep '12 oct '12 Tarea Tarea crítica Progreso Hito Resumen Tarea resumida Tarea crítica resumida Hito resumido Progreso resumido División Tareas externas Resumen del proyecto Agrupar por síntesis Fecha límite CAPACIDAD RESOLUTIVA DE LOS SERVICIOS DE SALUD DE LA UNIDAD DE EMERGENCIA Y DE UCI DEL HOSPITAL SAN JUAN BAUTISTA DE HUARAL Página 1 Proyecto: Cronograma Fecha: jue 23/02/12

Transcript of Microsoft Office Project - Hhsjb Emer-uci Gantt-pert Cpm Final

Page 1: Microsoft Office Project - Hhsjb Emer-uci Gantt-pert Cpm Final

Id Descripción Partida Duración Inicio

1 MEJORAMIENTO DE LA CAPACIDAD RESOLUTIVA DE LOS SERVICIOS DE SALUD DE LA UNIDAD DE EMERGENCIA Y DE UCI DEL HOSPITAL SAN JUAN BAUTISTA DE HUARAL210 días jue 01/03/12

2 ESTRUCTURAS 203 días jue 01/03/12

3 OBRAS PROVISIONALES 12 días dom 04/03/12

4 CONSTRUCCIONES PROVISIONALES 8 días dom 04/03/12

5 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M 2 días dom 04/03/12

6 OFICINA DE OBRA 3 días mar 06/03/12

7 ALMACEN DE OBRA 3 días vie 09/03/12

8 CASETA PARA GUARDIANIA 3.00 x 2.40m 3 días vie 09/03/12

9 VESTUARIO PARA EL PERSONAL DE OBRA 3.00 x 3.00 m 3 días vie 09/03/12

10 SERVICIOS HIGIÉNICOS PARA EL PERSONAL DE OBRA 2.40 x 1.25 m3 días mar 06/03/12

11 CERCO PERIMETRICO PROVISIONAL, MALLA CON POSTES DE MADERA DE 4" x 4"4 días dom 04/03/12

12 INSTALACIONES PROVISIONALES 4 días lun 12/03/12

13 INSTALACIÓN PROVISIONAL DE AGUA 2 días mié 14/03/12

14 INSTALACIÓN PROVISIONAL DE DESAGUE 2 días lun 12/03/12

15 INSTALACIÓN PROVISIONAL DE SERVICIO ELÉCTRICO 2 días lun 12/03/12

16 INSTALACIÓN PROVISIONAL DE LÍNEA TELEFÓNICA 2 días mié 14/03/12

17 TRABAJOS PRELIMINARES 184 días jue 01/03/12

18 TRAZO, NIVELES Y REPLANTEO 154 días jue 01/03/12

19 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 3 días jue 01/03/12

20 TRAZO, NIVELES Y REPLANTEO PERMANENTE 10 días lun 02/04/12

21 MOVILIZACIÓN DESMOVILIZACIÓN DE EQUIPOS 184 días jue 01/03/12

22 MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO 14 días jue 01/03/12

23 MOVIMIENTO DE TIERRAS 27 días jue 08/03/12

24 NIVELACIÓN DEL TERRENO 2 días vie 16/03/12

25 PERFILADO, NIVELACIÓN Y COMPACTADO DE TERRENO C/EQUIPO2 días vie 16/03/12

26 EXCAVACIONES 9 días dom 11/03/12

27 EXCAVACIÓN MASIVA O COMGLOMERADO 3 días dom 11/03/12

28 EXCAVACIÓN DE ZANJA PARA CIMIENTO CORRIDO 6 días mié 14/03/12

29 CORTES 3 días jue 08/03/12

30 CORTE MANUAL DE TERRENO NORMAL 3 días jue 08/03/12

31 RELLENOS 3 días sáb 31/03/12

32 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO 3 días sáb 31/03/12

33 ELIMINACIÓN DE MATERIAL EXCEDENTE 2 días lun 02/04/12

34 ELIMINACIÓN DE MATERIAL EXCEDENTE C/EQUIPO 2 días lun 02/04/12

35 NIVELACIÓN INTERIOR Y APISONADO 4 días mar 20/03/12

36 NIVELACIÓN Y COMPACTACIÓN DE TERRENO CON COMPACTADORA4 días mar 20/03/12

37 CONCRETO SIMPLE 118 días mar 20/03/12

38 SOLADOS 4 días mar 20/03/12

39 CONCRETO C.H. 1:10 E=4" - SOLADOS 4 días mar 20/03/12

40 CIMIENTOS CORRIDOS 8 días sáb 24/03/12

41 CONCRETO CICLOPEO Fc=100 Kg/Cm2 + 30% P.G. - CIMIENTOS CORRIDOS3 días jue 29/03/12

42 ENCOFRADO Y DESENCOFRADO NORMAL CIMIENTOS CORRIDOS6 días sáb 24/03/12

43 SOBRECIMIENTOS 10 días dom 01/04/12

44 CONCRETO CICLOPEO Fc=140 Kg/Cm2 +25% P.M. SOBRECIMIENTOS4 días sáb 07/04/12

45 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTOS 6 días dom 01/04/12

46 FALSO PISO 4 días lun 30/04/12

47 FALSO PISO DE 4" CON MEZCLA C:H 1:8 INC. BASE GRANULAR 4 días lun 30/04/12

48 VEREDAS Y SARDINELES 10 días lun 25/06/12

49 VEREDAS DE CONCRETO Fc=140 Kg/Cm2 E=4" 6 días mié 27/06/12

50 SARDINEL PERALTADO DE CONCRETO Fc=140 Kg/Cm2 H=0.20m. ANCHO =0.075m.3 días lun 25/06/12

51 JUNTAS ASFALTICAS 2 días mar 03/07/12

52 RAMPA 10 días vie 06/07/12

53 RAMPA DE CONCRETO PEATONAL Fc=140 Kg/Cm2 4 días vie 06/07/12

54 RAMPA DE CONCRETO VEHICULAR Fc=175 Kg/Cm2 4 días mar 10/07/12

55 JUNTAS ASFALTICAS 2 días sáb 14/07/12

56 ESTACIONAMIENTO 7 días dom 29/04/12

57 LOSA DE CONCRETO Fc=210 Kg/Cm2 E=8" ACABADOS FROTACHADO, INC. BASE GRANULAR5 días dom 29/04/12

58 JUNTAS ASFALTICAS 2 días vie 04/05/12

59 CONCRETO ARMADO 202 días vie 02/03/12

60 ZAPATAS 11 días sáb 24/03/12

61 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 4 días sáb 31/03/12

62 ACERO CORRUGADO FY=4200 Kg/Cm2 7 días sáb 24/03/12

63 COLUMNAS 51 días sáb 31/03/12

64 CONCRETO EN COLUMNAS F'C=210 KG/CM2 6 días vie 20/04/12

65 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 12 días jue 12/04/12

66 ACERO CORRUGADO FY=4200 Kg/Cm2 8 días sáb 31/03/12

67 VIGAS 58 días lun 21/05/12

68 CONCRETO EN VIGAS F'C=210 KG/CM2 2 días mar 26/06/12

69 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 8 días lun 18/06/12

70 ACERO CORRUGADO FY=4200 Kg/Cm2 8 días lun 21/05/12

71 CISTERNA SUBTERRANEA 21 días mié 11/04/12

72 CONCRETO Fc=245 Kg/Cm2 LOSA ALIGERADA 2 días lun 30/04/12

73 ENCOFRADO Y DESENCOFRADO NORMAL EN CISTERNA SUBTERRANEA6 días mar 24/04/12

74 ACERO CORRUGADO Fy=4200 Kg/Cm2 4 días mié 11/04/12

75 LOSAS ALIGERADAS 54 días lun 21/05/12

76 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 2 días vie 25/05/12

77 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS10 días lun 18/06/12

78 ACERO CORRUGADO FY=4200 Kg/Cm2 8 días lun 21/05/12

79 LADRILLO HUECO DE ARCILLA 20X30X30 CM PARA TECHO ALIGERADO2 días lun 18/06/12

80 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO2 días mié 20/06/12

81 VARIOS 202 días vie 02/03/12

82 JUNTA DE DILATACION SISMICA E=2" 3 días vie 22/06/12

83 SEGURIDAD E HIGIENE DE OBRA 20 días vie 02/03/12

84 MITIGACION DEL IMPACTO AMBIENTAL 6 días dom 04/03/12

85 ARQUITECTURA 202 días vie 02/03/12

86 MUROS Y TABIQUES DE ALBAÑILERIA 36 días mar 10/04/12

87 MURO DE LADRILLO K.K. DE CABEZA MEZCLA C:A 1:4 TIPO IV P. TARRAJ.10 días sáb 14/04/12

88 MURO DE LADRILLO K.K. DE SOGA MEZCLA C:A 1:4 TIPO IV P. TARRAJ.16 días mar 10/04/12

89 REVOQUES ENLUCIDOS Y MOLDURAS 63 días mié 16/05/12

90 TARRAJEO PRIMARIO Y RAYADO MEZCLA C:A 1:5 4 días mié 16/05/12

91 TARRAJEO FROTACHADO DE MUROS INTERIORES MEZCLA C:A 1:5 E=1.5Cm.16 días dom 20/05/12

92 TARRAJEO FROTACHADO DE MUROS EXTERIORES MEZCLA C:A 1:5 E=1.5cm.4 días mar 26/06/12

93 TARRAJEO DE COLUMNAS, C:A 1:5, E=1.5 CM 5 días mar 03/07/12

94 TARRAJEO DE VIGAS C:A 1:5, E=1.5 CM 5 días jue 28/06/12

95 TARRAJEO CON IMPERMEABILIZANTE MEZCLA C:A 1:4 E=1.5cm. 3 días dom 15/07/12

96 VESTIDURA DE DERRAMES, ANCHO =0.15m. 5 días dom 08/07/12

97 BRUÑAS DE 1Cm. X 1Cm. 2 días vie 13/07/12

98 CIELORRASOS 16 días vie 01/06/12

99 CIELORRASO CON MEZCLA C:A 1:5 E=1.5 Cm. 8 días vie 01/06/12

100 FALSO CIELO DE DRYWALL 8 días sáb 09/06/12

101 PISOS Y PAVIMENTOS 55 días dom 13/05/12

102 CONTRAPISOS 6 días dom 13/05/12

103 CONTRAPISO DE 4 CM, BASE 3 CM MEZ. 1:5, ACAB. 1 CM. PASTA 1:24 días dom 13/05/12

104 CONTRAPISO DE 48 MM. 4 días mar 15/05/12

105 PISOS 20 días dom 17/06/12

106 PISO DE POLIETILENO VINILICO 1.6MM. EN ROLLO 6 días vie 29/06/12

107 PISO DE CERAMICO DE COLOR CLARO DE 50X50 CM. 8 días jue 21/06/12

108 PISO DE CERAMICO DE COLOR CLARO DE 30X30 CM. 12 días dom 17/06/12

109 PISO DE CEMENTO SEMI PULIDO Y BRUÑADO E=2" 2 días vie 29/06/12

110 VEREDAS (FROTACHADO) C/MORTERO 1:2 X 1.5 CM. DE ESPESOR4 días dom 01/07/12

111 BASE DE CONCRETO DE 10cm. 2 días jue 05/07/12

112 CONTRAZOCALOS 16 días vie 01/06/12

113 CONTRAZOCALO SANITARIO DE TERRAZO PULIDO, H=0.10M. 8 días lun 04/06/12

114 CONTRAZOCALO DE CERAMICA 30X10 COLOR CLARO 5 días mar 12/06/12

115 CONTRAZOCALO DE CEMENTO S/COLOREAR (H=10CM.) 3 días vie 01/06/12

116 ZOCALOS 12 días vie 01/06/12

117 ZOCALO DE CERAMICA 20X30 CM 8 días vie 01/06/12

118 ZOCALO DE CEMENTO PULIDO CON IMPERMEABILIZANTE (H=0.50m.) 4 días sáb 09/06/12

119 REVESTIMIENTOS 4 días mar 19/06/12

120 REVESTIMIENTO DE LAMINADO VINILICO DE PISO A TECHO 4 días mar 19/06/12

121 COBERTURAS 6 días jue 02/08/12

122 COBERTURA LADRILLO PASTELERO ASENTADO C/MEZCLA 4 días jue 02/08/12

123 COBERTURA LIGERA CON POLICARBONATO TRANSLUCIDO 4 días sáb 04/08/12

124 CARPINTERIA DE MADERA 45 días vie 29/06/12

125 PUERTAS DE MADERA 9 días jue 02/08/12

126 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5mm 5 días jue 02/08/12

127 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5mm. Y REJILLA4 días mar 07/08/12

128 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5mm., REJILLA Y SOBRELUZ2 días dom 05/08/12

129 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5mm., REFUERZO DE A.I. Y REGISTRO2 días mar 07/08/12

130 PUERTA CONTRAPLACADA E=50mm, CON MDF LAMINADO 5.5mm. Y REGISTRO2 días jue 09/08/12

131 PANEL DIVISORIO PARA SH (INCL. PUERTA) 2 días mar 07/08/12

132 VENTANAS DE MADERA 2 días jue 09/08/12

133 VENTANA CON MARCO DE MADERA 2 días jue 09/08/12

134 BARRA DE PROTECCIÓN 2 días sáb 11/08/12

135 BARRA DE PROTECCION CONTRAIMPACTO DE CAMILLAS 2 días sáb 11/08/12

136 MUEBLES DE MELANINA 20 días vie 29/06/12

137 MUEBLE FIJO TIPO M-3 3 días vie 29/06/12

138 MUEBLE FIJO TIPO M-6 4 días lun 02/07/12

139 MUEBLE FIJO TIPO M-11 4 días lun 02/07/12

140 MUEBLE FIJO TIPO M-30 2 días vie 06/07/12

141 MUEBLE FIJO TIPO M-38 2 días dom 08/07/12

142 MUEBLE FIJO TIPO M-40 2 días mar 10/07/12

143 MUEBLE FIJO TIPO M-41 2 días jue 12/07/12

144 MUEBLE FIJO DE ADMISION 2 días sáb 14/07/12

145 MUEBLE FIJO DE CONTROL / ESTACION DE ENFERMERAS 3 días lun 16/07/12

146 CARPINTERIA METALICA Y DE ALUMINIO 30 días lun 30/07/12

147 VENTANAS DE ALUMINIO 6 días lun 30/07/12

148 ESTRUCTURA DE ALUMINIO PARA VENTANA CON SISTEMA FIJO 4 días lun 30/07/12

149 ESTRUCTURA DE ALUMINIO PARA VENTANA CON SISTEMA CORREDIZO2 días vie 03/08/12

150 MAMPARAS DE ALUMINIO 4 días lun 30/07/12

151 ESTRUCTURA DE ALUMINIO PARA MAMPARA 4 días lun 30/07/12

152 PUERTAS DE ALUMINIO 2 días vie 03/08/12

153 ESTRUCTURA DE ALUMINIO PARA PUERTA-VENTANA 2 días vie 03/08/12

154 CARPINTERIA METALICA Y HERRERIA 16 días lun 13/08/12

155 BARANDA METALICA DE Ø1.1/2" 4 días lun 13/08/12

156 BARRA DE APOYO PARA DISCAPACITADO 2 días vie 17/08/12

157 TAPA METALICA DE INSPECCION (0.70 x 0.70m.) 3 días jue 16/08/12

158 REJA METALICA BATIENTE 1 HOJA PARA INGRESO PEATONAL (1.20X2.40)2 días dom 19/08/12

159 REJA METALICA BATIENTE 2 HOJAS PARA INGRESO VEHICULAR (3.00X2.40)2 días mar 21/08/12

160 REJA METALICA BATIENTE 2 HOJAS CON MALLA (1.60X2.20) 2 días jue 23/08/12

161 PASOS METALICOS AISLADOS TIPO GRAPA 2 días sáb 25/08/12

162 MUEBLE METALICO TIPO M - 8 2 días lun 27/08/12

163 CERRAJERIA 31 días mar 07/08/12

164 BISAGRAS 4 días mar 07/08/12

165 BISAGRA CAPUCHINA 31/2" x 31/2" 3 días mar 07/08/12

166 BISAGRA CAPUCHINA 4" x 4" 1 día vie 10/08/12

167 CERRADURAS 17 días sáb 11/08/12

168 CERRADURA TIPO B 3 días sáb 11/08/12

169 CERRADURA TIPO C 2 días mar 14/08/12

170 CERRADURA TIPO D 2 días mar 14/08/12

171 CERRADURA TIPO E 3 días jue 16/08/12

172 CERRADURA TIPO G 3 días dom 19/08/12

173 CERRADURA TIPO H 2 días mié 22/08/12

174 CERRADURA TIPO I 2 días vie 24/08/12

175 CERRADURA TIPO K 2 días dom 26/08/12

176 CIERRA PUERTAS Y OTROS 9 días dom 19/08/12

177 CERROJO SIMPLE TIPO N 1 día dom 19/08/12

178 CIERRAPUERTAS TIPO Q 1 día lun 20/08/12

179 CIERRAPUERTAS TIPO P (Aérea) 1 día mié 22/08/12

180 TOPES 2" 4 días jue 23/08/12

181 PICAPORTE DE ALUMINIO DE 13" 1 día lun 27/08/12

182 VIDRIOS, CRISTALES Y SIMILARES 10 días mar 28/08/12

183 VIDRIO LAMINADO E=4.5mm. 6 días mar 28/08/12

184 VIDRIO LAMINADO E=6mm. 2 días lun 03/09/12

185 VIDRIO TEMPLADO E=10mm. 3 días vie 31/08/12

186 ESPEJO DE CRISTAL (SUMINIST. E INSTALAC.) 2 días lun 03/09/12

187 MURO CORTINA CON CRISTAL TEMPLADO INCOLORO E=10 mm. CON ZOCALO DE ALUMINIO (INC. ACCESORIOS)2 días mié 05/09/12

188 PINTURA 30 días mié 08/08/12

189 PINTURA DE CIELORRASOS C/LATEX - 2 MANOS C/ IMPRIMANTE 8 días mié 08/08/12

S 1,002.06

S 2,466.68

S 1,213.85

S 495.42

S 856.48

S 501.26

S 6,512.23

S 313.29

S 375.95

S 626.58

S 313.29

S 3,708.68

S 3,884.24

S 3,132.90

S 4,147.57

S 9,408.20

S 15,181.02

S 949.07

S 27,031.41

S 24,224.34

S 12,386.58

S 5,939.18

S 82,723.22

S 28,460.87

S 9,828.58

S 4,258.16

S 90,064.43

S 35,198.02

S 415.42

S 471.89

S 3,819.42

S 2,626.52

S 491.55

S 45,671.48

S 1,114.51

S 53,427.43

S 20,033.94

S 68,163.42

S 61,335.25

S 128,325.26

S 78,901.03

S 82,305.43

S 140,317.72

S 29,716.34

S 8,085.90

S 12,880.92

S 38,135.86

S 67,000.67

S 60,947.46

S 18,295.13

S 21,884.37

S 3,382.00

S 25,063.20

S 28,822.68

S 45,974.73

S 73,384.33

S 18,824.65

S 47,214.57

S 18,365.69

S 14,691.02

S 24,972.87

S 6,816.13

S 15,268.62

S 1,239.44

S 58,487.79

S 18,217.56

S 29,884.89

S 10,953.57

S 60,897.23

S 36,616.72

S 66,138.51

S 1,109.03

S 8,231.14

S 1,063.84

S 15,910.84

S 10,557.91

S 334.95

S 67,479.49

S 1,360.65

S 7,187.62

S 87,984.06

S 6,202.31

S 25,795.48

S 19,095.75

S 3,917.10

S 26,373.46

S 1,126.79

S 10,275.69

S 497.66

S 29,991.53

S 8,006.15

S 17,368.80

S 7,628.14

S 299.24

S 393.12

S 1,490.72

S 3,923.00

S 8,255.01

S 12,335.85

S 8,573.49

S 2,590.86

S 11,839.03

S 3,829.49

S 6,528.32

S 4,195.58

S 969.83

S 814.09

S 1,441.03

S 2,125.56

S 277.81

S 24,478.87

S 4,439.12

S 154.59

S 3,848.30

S 724.49

S 731.34

S 1,377.22

S 2,568.23

S 914.43

S 244.25

S 147.10

S 123.99

S 1,730.68

S 655.59

S 1,617.33

S 57.63

S 13,471.94

S 3,516.16

S 13,857.54

S 986.30

S 15,097.96

S 14,691.74

26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 30mar '12 abr '12 may '12 jun '12 jul '12 ago '12 sep '12 oct '12

Tarea Tarea crítica Progreso Hito Resumen Tarea resumida Tarea crítica resumida Hito resumido Progreso resumido División Tareas externas Resumen del proyecto Agrupar por síntesis Fecha límite

CAPACIDAD RESOLUTIVA DE LOS SERVICIOS DE SALUD DE LA UNIDAD DE EMERGENCIA Y DE UCI DEL HOSPITAL SAN JUAN BAUTISTA DE HUARAL

Página 1

Proyecto: CronogramaFecha: jue 23/02/12

Page 2: Microsoft Office Project - Hhsjb Emer-uci Gantt-pert Cpm Final

Id Descripción Partida Duración Inicio

190 PINTURA DE MUROS INTERIORES C/LATEX - 2 MANOS C/IMPRIMANTE12 días jue 16/08/12

191 PINTURA DE MUROS EXTERIORES C/LATEX - 2 MANOS C/IMPRIMANTE6 días dom 19/08/12

192 PINTURA DE MARCO DE PUERTAS C/BARNIZ NATURAL 8 días sáb 25/08/12

193 PINTURA ANTICORROSIVA Y ESMALTE EN CARPINTERIA METALICA2 días dom 02/09/12

194 PINTURA DE CONTRAZOCALO C/ESMALTE - 2 MANOS 3 días mar 04/09/12

195 VARIOS 202 días vie 02/03/12

196 VARIOS, LIMPIEZA Y JAERDINERIA 202 días vie 02/03/12

197 LIMPIEZA PERMANENTE DE OBRA 20 días vie 02/03/12

198 LIMPIEZA FINAL DE OBRA 4 días dom 02/09/12

199 BOTADERO DE LIMPIEZA DE MAMPOSTERIA DE 2 POZAS B-68 2 días mié 15/08/12

200 TUBO CROMADO PARA CORTINA SUJETA A TECHO 3 días dom 12/08/12

201 PORTASUEROS MOVIL METALICO COLGANTE 3 días jue 09/08/12

202 CORTINA PLEGABLE DE VINIL CORROFAN P-1a 2 días mar 07/08/12

203 TABLERO DE CONCRETO C/REVESTIMIENTO CERAMICO DE 20x30CM. PARA OVALIN2 días dom 05/08/12

204 BANQUETA DE CONCRETO F´C=175Kg/cm2 2 días dom 29/07/12

205 JARDINERA DE CONCRETO (H=60cm.) 9 días lun 25/06/12

206 PROVISION Y SEMBRIO DE GRASS 6 días mar 28/08/12

207 JUNTAS Y TAPAJUNTAS 8 días vie 13/07/12

208 TAPAJUNTAS DE CONSTRUCCION E=2" EN MUROS 2 días vie 13/07/12

209 TAPAJUNTAS DE CONSTRUCCION E=2" EN PISOS 4 días dom 15/07/12

210 TAPAJUNTAS DE CONSTRUCCION E=2" EN TECHOS 2 días lun 16/07/12

211 JUNTA DE DILATACION EN TECHOS CON MORTERO ASFALTICO 3 días mié 18/07/12

212 APARATOS Y ACCESORIOS SANITARIOS 13 días vie 07/09/12

213 LAVATORIOS Y LAVADEROS 11 días vie 07/09/12

214 LAVATORIO DE LOSA VITRIFICADA CONTROL DE CODO O MUÑECA A-2, A-3, A-3a (INCL. ACCESORIOS)2 días vie 07/09/12

215 LAVATORIO EMPOTRADO DE LOSA VITRIFICADA TIPO OVALIN A-5 (INCL. ACCESORIOS)2 días dom 09/09/12

216 LAVADERO DE ACERO INOXIDABLE DE UNA POZA B-1 (INCL. GRIFERIA Y ACCESORIOS)2 días lun 10/09/12

217 LAVADERO DE ACERO INOXIDABLE DE UNA POZA Y ESCURRIDERA B-9 (INCL. GRIFERIA Y ACCESORIOS)2 días mié 12/09/12

218 LAVADERO DE LOSA VITRIFICADA CIRUJANO B-43 (INCL. GRIFERIA Y ACCESORIOS)2 días vie 14/09/12

219 LAVADERO DE LOSA VITRIFICADA CON TRAMPA DE YESO B-45 (INCL. GRIFERIA Y ACCESORIOS)2 días dom 16/09/12

220 BOTADEROS 2 días dom 09/09/12

221 BOTADERO CLINICO DE LOSA VITRIFICADA Y LIMPIADOR DE CHATAS B-50 (INCL. GRIFERIA Y ACCESORIOS)2 días dom 09/09/12

222 INODOROS 4 días mar 11/09/12

223 INODORO DE LOSA VITRIFICADA CON VALVULA FLUXOMETRICA C-1 / C-1a (INCL. GRIFERIA Y ACCESORIOS)4 días mar 11/09/12

224 URINARIOS 3 días sáb 15/09/12

225 URINARIOS DE LOZA CON VALVULA FLUXOMETRICA C-9 (INCL. GRIFERIA Y ACCESORIOS)3 días sáb 15/09/12

226 GRIFERIAS 9 días mar 11/09/12

227 GRIFERIA SIMPLE PARA CONTROL MANUAL DE LAVATORIO A-3, A-3a, A-54 días mar 11/09/12

228 GRIFERIA MEZCLADORA PARA CONTROL MANUAL DE LAVATORIO A-3, A-3a, A-53 días sáb 15/09/12

229 GRIFERIA PARA CONTROL DE CODO O MUÑECA DE LAVADERO B-432 días vie 14/09/12

230 GRIFERIA MEZCLADORA PARA SALIDA DE DUCHA F-1 2 días dom 16/09/12

231 GRIFERIA EXTENSIBLE PARA CONTROL MANUAL TIPO TELEFONO F-42 días mar 18/09/12

232 APARATOS SANITARIOS 9 días mar 11/09/12

233 TOALLERO DE GANCHO DE LOSA H-3 3 días mar 11/09/12

234 DISPENSADOR METALICO PARA JABON LIQUIDO H-4 4 días vie 14/09/12

235 JABONERA DE LOSA EMPOTRADA PARA DUCHA H-5 3 días vie 14/09/12

236 PORTARROLLO DE LOZA EMPOTRADO PARA PAPEL HIGIENICO H-62 días lun 17/09/12

237 BARRA CROMADA PARA CORTINA H-7 1 día mié 19/09/12

238 PORTARROLLO ACRILICO DE SOBREPONER PARA PAPEL HIGIENICO H-213 días lun 17/09/12

239 SEÑALIZACIÓN DE SEGURIDAD 13 días vie 07/09/12

240 DIRECCION DE SALIDA HACIA EL EXTERIOR 2 días vie 07/09/12

241 SALIDA DE EMERGENCIA 1 día sáb 08/09/12

242 ZONA SEGURA EN CASO DE SISMOS 2 días dom 09/09/12

243 PLANOS DE FLUJOGRAMA CON LAS RUTAS DE EVACUACION 1 día dom 09/09/12

244 LUCES DE EMERGENCIA 2 días dom 09/09/12

245 SERVICIOS HIGIENICOS - HOMBRES 1 día mar 11/09/12

246 SERVICIOS HIGIENICOS - MUJERES 1 día mar 11/09/12

247 NOMBRES DE AMBIENTES 3 días mar 11/09/12

248 RIESGO ELECTRICO 1 día vie 14/09/12

249 PROHIBIDO FUMAR 1 día vie 14/09/12

250 SEÑAL DE EXTINTOR CO2, 12 KG 2 días vie 14/09/12

251 SEÑAL DE GABINETE CONTRA INCENDIO 1 día dom 16/09/12

252 DETECTOR DEHUMO 3 días dom 16/09/12

253 COLOCACION DE SEÑALES 3 días lun 17/09/12

254 SEÑALIZACION DE NORMATIVIDAD 12 días dom 02/09/12

255 LETREROS 2 días dom 02/09/12

256 LETRERO 2 días dom 02/09/12

257 SEÑAL ORIENTATIVA 3 días dom 02/09/12

258 SEÑAL OI 1 (PANEL PARED) 2 días dom 02/09/12

259 OI 4 - COLGANTE 2 días lun 03/09/12

260 SEÑAL INDICATIVA 5 días mar 04/09/12

261 IN 2A - PARED 2 días mar 04/09/12

262 IN 3A - PARED 4 días mié 05/09/12

263 IN 3B - PARED 2 días mié 05/09/12

264 IN 6B - PARED 2 días jue 06/09/12

265 IN 8 - PARED 2 días jue 06/09/12

266 SEÑAL REGLAMENTARIA 2 días jue 06/09/12

267 SR 1 - PARED 2 días jue 06/09/12

268 COLOCACION DE SEÑALES 7 días vie 07/09/12

269 COLOCACION DE SEÑAL ORIENTATIVA 2 días vie 07/09/12

270 COLOCACION DE SEÑAL INDICATIVA 3 días dom 09/09/12

271 COLOCACION DE SEÑAL REGLAMENTARIA 2 días mié 12/09/12

272 INSTALACIONES ELECTRICAS 201 días sáb 10/03/12

273 TRABAJOS PRELIMINARES 16 días sáb 10/03/12

274 EXCAVACION MANUAL PARA REDES ELECTRICAS H=0.60m. 3 días sáb 10/03/12

275 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO 2 días sáb 24/03/12

276 CINTA SEÑALIZADORA 2 días sáb 10/03/12

277 SALIDA PARA ALUMBRADO 42 días sáb 07/04/12

278 SALIDA PARA ALUMBRADO EN TECHO DE PVC P20mm (PTO LSOH 4mm2)7 días jue 26/04/12

279 SALIDA PARA ALUMBRADO EN PARED DE PVC P 20mm LSOH 4mm2) 4 días sáb 07/04/12

280 SALIDA PARA TOMACORRIENTE 21 días lun 09/04/12

281 TOMACORRIENTES BIPOLAR DOBLE C/LINEA A TIERRA PVC P-20 mm EN PARED9 días lun 09/04/12

282 TOMACORRIENTE BIPOLAR DOBLE A PRUEBA DE AGUA C/LINEA A TIERRA PVC P 20mm EN PARED3 días mié 18/04/12

283 TOMACORRIENTE BIPOLAR DOBLE C/LINEA A TIERRA PVC P 20mm PARA LUCES DE EMERGENCIA3 días sáb 21/04/12

284 TOMACORRIENTE ESTABILIZADO DOBLE C/LINEA A TIERRA PVC P 20 mm EN PARED6 días mar 24/04/12

285 SALIDA DE FUERZA 8 días vie 30/03/12

286 SALIDA DE FUERZA DE 2.5 HP PVC - P 25 mm ( 4 x 4 mm2 LSOH) 2 días jue 05/04/12

287 SALIDA DE FUERZA 10 HP PVC - P40mm (4X16 mm2 LSOH) 2 días mar 03/04/12

288 SALIDA DE FUERZA DE 1.0 HP PVC - P 25 mm ( 4 x 4 mm2 LSOH) 2 días dom 01/04/12

289 SALIDA PARA SECADORA DE MANO PVC - P20mm (3 x 4 mm2 LSOH) 2 días vie 30/03/12

290 SALIDA VARIOS 3 días mar 27/03/12

291 SALIDA PARA CALENTADOR ELECTRICO (PVC - P20mm) 3 días mar 27/03/12

292 SALIDA PARA SISTEMA DE COMPUTO 8 días sáb 07/04/12

293 SALIDA PARA VOZ Y DATA PVC - P 20 MM EN PARED 3 días sáb 07/04/12

294 SALIDA PARA VOZ PVC - P 20 mm EN PARED 3 días mar 10/04/12

295 SALIDA PARA TRANSFORMADOR 1 día vie 13/04/12

296 SALIDA PARA UPS 1 día sáb 14/04/12

297 CAJA DE PASE 300 x 300 x 100mm 2 días mar 10/04/12

298 CAJA DE PASE 200 x 200 x 100 mm 1 día jue 12/04/12

299 SALIDA PARA PARLANTES 6 días sáb 28/04/12

300 SALIDA PARA PARLANTES EN TECHO 2 días mié 02/05/12

301 SALIDA PARA CONTROL DE PERIFONEO 2 días lun 30/04/12

302 SALIDA PARA CENTRAL DE MUSICA Y PERIFONEO 2 días sáb 28/04/12

303 SALIDA PARA ALARMAS 8 días vie 04/05/12

304 SALIDA PARA DETECTOR DE HUMO IONICO (INC. APARATO) 2 días jue 10/05/12

305 SALIDA PARA PULSADOR DE ALARMA CONTRA INCENDIO 2 días mar 08/05/12

306 SALIDA PARA CENTRAL DE ALARMAS CONTRA INCENDIO 2 días dom 06/05/12

307 SALIDA PARA SIRENA DE ALARMA CONTRA INCENDIO 2 días vie 04/05/12

308 SALIDA PARA LLAMADO DE ENFERMERAS 6 días mié 06/06/12

309 PULSADOR DE LLAMADO DE ENFERMERAS EN PARED 4 días mié 06/06/12

310 SALIDA PARA CENTRAL DE LLAMADA DE ENFERMERAS 2 días dom 10/06/12

311 SALIDAS ESPECIALES 2 días lun 04/06/12

312 TOMACORRIENTE 60 A- 1 FASE 3 CONDUCTORES PARA EQUIPO PORTATIL DE RAYOS X2 días lun 04/06/12

313 CAJA DE PASE 6 días mar 29/05/12

314 CAJA DE PASE 300 x 300 x 100 mm 2 días mar 29/05/12

315 CAJA DE PASE 700 x 700 x 100 MM 4 días jue 31/05/12

316 TUBERIAS 22 días sáb 07/04/12

317 TUBERIA PVC SAP (ELECTRICAS) D=50mm 4 días dom 15/04/12

318 TUBERIA PVC SAP (ELECTRICAS) D=40 mm 3 días jue 19/04/12

319 TUBERIA PVC SAP (ELECTRICAS) D=35 mm 3 días dom 22/04/12

320 TUBERIA PVC SAP (ELECTRICA) D=25 mm 4 días lun 23/04/12

321 TUBERIA PVC SAP (ELECTRICAS) D=20 mm 2 días vie 27/04/12

322 TUBERIA PVC SAP (ELECTRICAS) D=105 mm 8 días sáb 07/04/12

323 CABLES Y CONDUCTORES 30 días dom 26/08/12

324 CABLE ELECTRICO N2XH 50 mm2 4 días mar 04/09/12

325 CABLE ELECTRICO N2XH 35 mm2 2 días sáb 08/09/12

326 CABLE ELECTRICO N2XH 16 mm2 9 días lun 10/09/12

327 CABLE ELECTRICO N2XH 10 mm2 2 días mié 19/09/12

328 CABLE ELECTRICO N2XH 6 mm2 4 días vie 21/09/12

329 CABLE ELECTRICO N2XH 300 mm2 9 días dom 26/08/12

330 TABLERO DE DISTRIBUCION 54 días jue 03/05/12

331 TABLERO DE TRANSFERENCIA AUTOMATICA -TTA 3 días jue 03/05/12

332 TABLERO GENERAL - TG - 1 3 días dom 06/05/12

333 SUB TABLERO DISTRIBUCION 1 - STD-1 3 días mié 09/05/12

334 SUB TABLERO DISTRIBUCION 2 STD-2 3 días sáb 12/05/12

335 SUB TABLERO DISTRIBUCION 3 - STD -3 3 días mar 15/05/12

336 SUB TABLERO DISTRIBUCION 4 - STD - 4 3 días vie 18/05/12

337 SUB TABLERO DE DISTRIBUCION 5 - STD- 5 3 días lun 21/05/12

338 SUB TABLERO DISTRIBUCION AIRE ACONDICIONADO STD -AA 3 días dom 03/06/12

339 TABLERO GENERAL ESTABILIZADO - TGES 3 días jue 07/06/12

340 SUB TABLERO ESTABILIZADO 1 - TDE-1 3 días lun 11/06/12

341 SUB TABLERO ESTABILIZADO 2 - TDE - 2 3 días jue 14/06/12

342 SUB TABLERO ESTABILIZADO 3 - TDE - 3 3 días dom 17/06/12

343 SUB TABLERO BOMBA DE AGUA - TC- BA 3 días mié 20/06/12

344 SUB TABLERO AGUA CONTRA INCENDIO - ST- ACI 3 días sáb 23/06/12

345 ARTEFACTOS 19 días sáb 08/09/12

346 ARTEFACTO TIPO 1 ADOSADO A TECHO C/2 LAMP. FLUORESCENTES 36W8 días sáb 08/09/12

347 ARTEFACTO TIPO 2 ADOSADO A TECHO C/2 LAMP. FLUORESCENTES 18W2 días sáb 08/09/12

348 ARTEFACTO TIPO 3 ADOSADO A TECHO C/2 LAMP. FLUORESCENTES 36W3 días lun 10/09/12

349 ARTEFACTO TIPO 4 PARA EXTERIORES C/1 LAMP. HM 70W 3 días jue 13/09/12

350 ARTEFACTO TIPO 5 ADOSADO C/1LAMP FLUORESCENTE 32W 4 días dom 16/09/12

351 ARTEFACTO TIPO 6 C/DIFUSOR ACRILICO C/1 LAMP FLUORESCENTE 36W3 días jue 20/09/12

352 ARTEFACTO TIPO 7 C/PORTALAMPARAS TIPO E40 C/1LAMP. VS 70W 3 días dom 23/09/12

353 ARTEFACTO TIPO 8 C/REJILLA AL C/1 LAMP. FLUORESCENTE 36W 1 día mié 26/09/12

354 SEÑALETICA SALIDA CON LED 2 días lun 17/09/12

355 LUZ DE EMERGENCIA C/2 LAMP. COMPACTA 18W 3 días mié 19/09/12

356 DETECTOR DE HUMO 5 días sáb 22/09/12

357 EQUIPOS ELECTRICOS Y MECANICOS 57 días lun 23/07/12

358 TRANSFORMADOR DE AISLAMIENTO 7 KVA, 3 Ø 220/220V, 60 HZ 2 días lun 23/07/12

359 TRANSFORMADOR DE AISLAMIENTO 10 KVA, 3 Ø 220/220 V, 60HZ 2 días mié 25/07/12

360 UPS 7 KVA, 220/220V, 60 HZ, 3Ø 2 días vie 27/07/12

361 UPS 10 KVA, 220/220 V, 60 HZ, 3Ø 2 días mié 25/07/12

362 GRUPO ELECTROGENO 140KVA 3 Ø, 60 HZ 2 días dom 16/09/12

363 VARIOS 7 días mar 26/06/12

364 POZO DE TIERRA (PARA EQUIPOS DE FUERZA) R<5 OHMS 3 días sáb 30/06/12

365 BUZON ELECTRICO 1.40 x 1.40 x 1.60 M. 2 días mar 26/06/12

366 PRUEBAS ELECTRICAS 2 días dom 23/09/12

367 PRUEBAS DE AISLAMIENTO Y RESISTIVIDAD 2 días dom 23/09/12

368 SISTEMA DE OXIGENO 20 días lun 30/04/12

369 SALIDA DE OXIGENO 4 días lun 30/04/12

370 SALIDA DE OXIGENO CON TUBERIA DE COBRE TIPO K 1/2" 4 días lun 30/04/12

371 REDES DE DISTRIBUCION 16 días lun 30/04/12

372 TUBERIA DE COBRE TIPO K PARA OXIGENO DE 11/2" 4 días lun 30/04/12

373 TUBERIA DE COBRE TIPO K PARA OXIGENO DE 1" 4 días vie 04/05/12

374 TUBERIA DE COBRE TIPO K PARA VACIO DE 3/4" 4 días mar 08/05/12

375 TUBERIA DE COBRE TIPO K PARA OXIGENO DE 1/2" 4 días sáb 12/05/12

376 LLAVES Y VALVULAS 4 días mié 16/05/12

377 VALVULA ESFERICA 1/2" 2 días mié 16/05/12

378 VALVULA ESFERICA 11/2" 2 días vie 18/05/12

S 41,936.91

S 12,771.33

S 12,238.94

S 388.21

S 401.63

S 3,759.48

S 375.95

S 1,503.49

S 5,252.99

S 4,419.11

S 567.12

S 376.59

S 1,150.55

S 134,764.66

S 23,604.88

S 790.00

S 3,297.55

S 841.51

S 1,846.41

S 6,039.43

S 3,966.06

S 3,209.84

S 10,182.36

S 22,386.15

S 3,321.55

S 12,570.55

S 20,760.68

S 1,344.84

S 2,818.11

S 3,368.83

S 907.09

S 2,019.43

S 155.84

S 1,527.23

S 1,220.70

S 247.99

S 182.21

S 1,379.96

S 1,662.59

S 781.97

S 81.46

S 146.62

S 60.15

S 374.69

S 100.25

S 100.25

S 2,105.31

S 146.62

S 120.30

S 360.91

S 97.75

S 1,971.22

S 518.06

S 1,148.27

S 3,819.63

S 7,639.26

S 4,541.45

S 4,154.23

S 532.59

S 852.15

S 213.04

S 213.04

S 639.49

S 2,354.21

S 47.37

S 719.94

S 288.23

S 899.77

S 27,397.96

S 7,768.39

S 18,551.98

S 2,287.77

S 3,407.99

S 6,845.26

S 360.61

S 786.95

S 176.53

S 1,203.43

S 377.64

S 1,781.24

S 1,154.71

S 198.22

S 229.70

S 289.18

S 96.39

S 1,584.40

S 288.05

S 288.05

S 8,264.09

S 650.34

S 230.81

S 727.23

S 2,268.82

S 706.33

S 367.55

S 289.18

S 1,011.93

S 1,544.90

S 917.31

S 813.35

S 1,092.96

S 434.78

S 7,690.02

S 5,069.66

S 5,825.13

S 12,105.11

S 1,662.32

S 4,030.91

S 198,714.83

S 497.79

S 3,827.66

S 3,236.24

S 4,655.61

S 1,135.56

S 5,960.27

S 1,203.71

S 664.16

S 551.09

S 2,745.80

S 2,146.49

S 2,146.49

S 688.94

S 863.84

S 52,891.67

S 3,961.66

S 2,188.47

S 2,775.85

S 7,181.21

S 7,950.62

S 12,424.33

S 220.00

S 1,008.42

S 5,523.58

S 33,900.21

S 3,011.33

S 4,076.52

S 40,771.34

S 42,358.68

S 121,231.88

S 5,214.71

S 1,282.65

S 1,879.74

S 11,727.66

S 10,737.69

S 2,322.62

S 3,810.27

S 461.11

S 453.27

S 453.67

26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 30mar '12 abr '12 may '12 jun '12 jul '12 ago '12 sep '12 oct '12

Tarea Tarea crítica Progreso Hito Resumen Tarea resumida Tarea crítica resumida Hito resumido Progreso resumido División Tareas externas Resumen del proyecto Agrupar por síntesis Fecha límite

CAPACIDAD RESOLUTIVA DE LOS SERVICIOS DE SALUD DE LA UNIDAD DE EMERGENCIA Y DE UCI DEL HOSPITAL SAN JUAN BAUTISTA DE HUARAL

Página 2

Proyecto: CronogramaFecha: jue 23/02/12

Page 3: Microsoft Office Project - Hhsjb Emer-uci Gantt-pert Cpm Final

Id Descripción Partida Duración Inicio

379 SISTEMA DE VACIO 28 días lun 21/05/12

380 SALIDA DE VACIO 4 días lun 21/05/12

381 SALIDA DE VACIO CON TUBERIA DE COBRE TIPO K 1/2" 4 días lun 21/05/12

382 REDES DE DISTRIBUCION 16 días mar 29/05/12

383 TUBERIA DE COBRE TIPO K PARA VACIO DE 11/2" 4 días mar 29/05/12

384 TUBERIA DE COBRE TIPO K PARA VACIO DE 1" 4 días sáb 02/06/12

385 TUBERIA DE COBRE TIPO K PARA VACIO DE 3/4" 4 días mié 06/06/12

386 TUBERIA DE COBRE TIPO K PARA VACIO DE 1/2" 4 días dom 10/06/12

387 LLAVES Y VALVULAS 4 días jue 14/06/12

388 VALVULA ESFERICA 11/2" 2 días jue 14/06/12

389 VALVULA ESFERICA 1/2" 2 días sáb 16/06/12

390 SISTEMA DE AIRE ACONDICIONADO 16 días dom 01/07/12

391 EQUIPOS MECÁNICOS DE AIRE ACONDICIONADO 8 días dom 01/07/12

392 VENTILADOR CENTRIFUGO VCG - 1 4 días dom 01/07/12

393 EXTRACTOR CENTRIFUGO EN GABINETE ECG - 1 4 días jue 05/07/12

394 DUCTOS DE F°G° 4 días dom 01/07/12

395 DUCTOS DE PLANCHA DE F°G° 4 días dom 01/07/12

396 DIFUSORES 2 días jue 05/07/12

397 DIFUSOR DE 4 VIAS 2 días jue 05/07/12

398 FILTROS Y PREFILTROS 6 días sáb 07/07/12

399 FILTRO ABSOLUTO 4 días sáb 07/07/12

400 PREFILTRO Y FILTRO DE AIRE 4 días lun 09/07/12

401 REJILLAS 2 días vie 13/07/12

402 REJILLA DE SUMINISTRO Y EXTRACCIÓN 2 días vie 13/07/12

403 AISLAMIENTO ACUSTICO 2 días dom 15/07/12

404 AISLAMIENTO ACUSTICO PARA DUCTOS 2 días dom 15/07/12

405 INSTALACIONES SANITARIAS 103 días vie 23/03/12

406 TRABAJOS PRELIMINARES 34 días vie 23/03/12

407 MOVIMIENTO DE TIERRAS 34 días vie 23/03/12

408 EXCAVACIÓN MANUAL P/INTERCEPTOR DESAGUE 1.0<h<0.5 M 4 días vie 23/03/12

409 EXCAVACIÓN MANUAL P/INTERCEPTOR DESAGUE 1.5<h<1.0 M 4 días mar 27/03/12

410 EXCAVACION MANUAL P/INTERCEPTOR DESAGUE 2.0<H<1.5 M 2 días sáb 31/03/12

411 EXCAVACION MANUAL P/RED DE DESAGUE H<0.5 M 3 días lun 02/04/12

412 EXCAVACION MANUAL P/RED DE AGUA H=0.50 M 5 días jue 05/04/12

413 REFINE Y NIVELACION ZANJA TERR.NORMAL"C" PARA TUB. 4"-6" 8 días vie 06/04/12

414 REFINE Y NIVELACION DE ZANJAS T. NORMAL P/TUB. D=1" a 4" 6 días lun 09/04/12

415 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO P/TUB 4"-6"5 días mar 17/04/12

416 RELLENO COMPACTADO A MANO CON MATERIAL PROPIO P/TUB 1"-4"5 días jue 19/04/12

417 ELIMINACION DE MATERIAL, CARGADOR 125 HP/VOLQUETE 6M3 D=5kM.2 días mar 24/04/12

418 SISTEMA DE DESAGUE 50 días sáb 14/04/12

419 SALIDAS DE DESAGUE Y VENTILACION 8 días dom 22/04/12

420 SALIDA DE DESAGUE PVC SAL 2" 4 días dom 22/04/12

421 SALIDA DE DESAGUE PVC SAL 3" 6 días lun 23/04/12

422 SALIDA DE DESAGUE PVC SAL 4" 4 días mié 25/04/12

423 SALIDA DE VENTILACION PVC SAL 2" 4 días jue 26/04/12

424 DESCARGA FINAL 8 días sáb 14/04/12

425 TUBERIA PVC SAL D=6" 5 días mar 17/04/12

426 TUBERIA PVC SAL D=4" 4 días sáb 14/04/12

427 REDES COLECTORAS 10 días dom 22/04/12

428 TUBERIA PVC SAL D=4" 5 días mié 25/04/12

429 TUBERIA PVC SAL D=3" 3 días lun 23/04/12

430 TUBERIA PVC SAL D=2" 2 días dom 22/04/12

431 TUBERIA PVC SAL 2" - VENTILACIÓN 2 días lun 30/04/12

432 ADITAMIENTOS VARIOS 10 días mar 22/05/12

433 SUMIDERO DE BRONCE 2" 2 días mar 22/05/12

434 SUMIDERO DE BRONCE 4" 1 día jue 24/05/12

435 REGISTRO DE BRONCE 4" 4 días vie 25/05/12

436 SOMBRERO DE VENTILACION PVC SAL DE 2" 3 días mar 29/05/12

437 CAMARAS DE INSPECCION 11 días mié 02/05/12

438 CAJA DE REG. ALB - 12" x 24" TAPA DE CONCRETO 6 días lun 07/05/12

439 CAJA DE REG. ALB. 24" x 24" TAPA DE CONCRETO 3 días vie 04/05/12

440 BUZON H=1.60 M 2 días mié 02/05/12

441 INSTALACIONES ESPECIALES 4 días sáb 19/05/12

442 CAJA DE REBOSE 2 días sáb 19/05/12

443 TRAMPA DE GRASA 2 días lun 21/05/12

444 PRUEBAS HIDRAULICAS 2 días vie 01/06/12

445 PRUEBA HIDRAULICA DE DESAGUE 2 días vie 01/06/12

446 SISTEMA DE AGUA FRIA 52 días sáb 14/04/12

447 SALIDA DE AGUA FRIA 11 días sáb 14/04/12

448 SALIDA DE AGUA FRIA CON TUBERIA DE PVC CLASE 10 C/ROSCA 1/2"3 días sáb 14/04/12

449 SALIDA AGUA FRIA CON TUBERIA DE PVC CLASE 10 C/ROSCA 3/4"6 días lun 16/04/12

450 SALIDA AGUA FRIA CON TUBERIA DE PVC CLASE 10 C/ROSCA 11/4"3 días dom 22/04/12

451 RED DE ALIMENTACION Y DISTRIBUCION 12 días sáb 14/04/12

452 TUBERIA PVC CLASE 10 C/ROSCA 2" 2 días mar 24/04/12

453 TUBERIA PVC CLASE 10 C/ROSCA 11/2" 5 días sáb 21/04/12

454 TUBERIA PVC CLASE 10 C/ROSCA 11/4" 7 días jue 19/04/12

455 TUBERIA PVC CLASE 10 C/ROSCA 1" 3 días lun 16/04/12

456 TUBERIA PVC CLASE 10 C/ROSCA 3/4" 2 días sáb 14/04/12

457 LLAVES Y VALVULAS 13 días jue 26/04/12

458 VALVULA DE COMPUERTA DE BRONCE DE 11/4" 3 días mié 02/05/12

459 VALVULA DE COMPUERTA DE BRONCE DE 3/4" 4 días vie 04/05/12

460 VALVULA COMPUERTA DE BRONCE DE 1/2" 1 día mar 08/05/12

461 CAJA PARA VÁLVULAS 6 días jue 26/04/12

462 ALMACENAMIENTO DE AGUA Y OTRAS INSTALACIONES 11 días mié 23/05/12

463 CISTERNA AF - ACCESORIOS 2 días mié 23/05/12

464 CUARTO DE BOMBAS A.F. 2 días vie 01/06/12

465 PRUEBAS HIDRAULICAS 2 días dom 03/06/12

466 PRUEBA HIDRÁULICA AGUA FRIA 2 días dom 03/06/12

467 SISTEMA DE AGUA CALIENTE 18 días mar 05/06/12

468 SALIDA DE AGUA CALIENTE 4 días mar 05/06/12

469 SALIDA AGUA CALIENTE C/TUB. CPVC 1/2" 3 días mar 05/06/12

470 SALIDA AGUA CALIENTE C/TUB. CPVC 3/4" 1 día vie 08/06/12

471 REDES DE DISTRIBUCION 6 días vie 08/06/12

472 TUBERIA CPVC P/AGUA CALIENTE 3/4" 3 días vie 08/06/12

473 TUBERIA CPVC P/AGUA CALIENTE 1/2" 3 días lun 11/06/12

474 LLAVES Y VALVULAS 6 días jue 14/06/12

475 VALVULA DE COMPUERTA DE BRONCE DE 3/4" 3 días jue 14/06/12

476 VALVULA DE COMPUERTA DE BRONCE 1/2" 3 días dom 17/06/12

477 INSTALACIONES ESPECIALES 2 días mié 20/06/12

478 CALENTADOR ELECTRICO 50 LT 2 días mié 20/06/12

479 PRUEBAS HIDRAULICAS 1 día vie 22/06/12

480 PRUEBA HIDRAULICA DE AGUA CALIENTE 1 día vie 22/06/12

481 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 11 días sáb 23/06/12

482 SALIDAS 2 días sáb 23/06/12

483 SALIDA C/TUBERIA SCH-40 DN 80 MM - 3" 2 días sáb 23/06/12

484 REDES DE DISTRIBUCION 2 días lun 25/06/12

485 TUBERIA ACERO SCH-40 DN 80 MM (Ø 3") 2 días lun 25/06/12

486 INSTALACIONES ESPECIALES 6 días mié 27/06/12

487 CISTERNA ACI - ACCESORIOS 2 días mié 27/06/12

488 CUARTO DE BOMBAS ACI 2 días vie 29/06/12

489 GABINETE CONTRA INCENDIO 2 días dom 01/07/12

490 PRUEBAS HIDRAULICAS 1 día mar 03/07/12

491 PRUEBA HIDRAULICA DE AGUA CONTRA INCENDIO 1 día mar 03/07/12

S 14,020.76

S 12,166.23

S 2,289.06

S 2,144.68

S 586.18

S 226.83

S 90.65

S 6,582.15

S 6,582.15

S 5,709.01

S 1,201.83

S 2,132.08

S 755.83

S 1,576.70

S 28,094.59

S 2,342.53

S 2,373.83

S 986.65

S 1,000.90

S 3,020.38

S 832.87

S 1,222.34

S 5,212.95

S 4,499.38

S 1,154.74

S 2,096.27

S 3,601.88

S 2,096.85

S 1,377.17

S 1,823.67

S 2,329.29

S 1,913.43

S 1,097.78

S 382.73

S 793.22

S 289.22

S 188.16

S 1,287.85

S 300.23

S 3,750.56

S 1,788.31

S 1,521.49

S 1,196.99

S 3,566.22

S 730.37

S 1,130.85

S 4,806.06

S 2,115.23

S 443.95

S 4,485.05

S 3,218.40

S 666.41

S 398.32

S 3,215.98

S 2,257.94

S 1,137.17

S 3,794.26

S 1,424.53

S 10,182.65

S 1,310.46

S 673.10

S 157.56

S 753.48

S 769.46

S 155.92

S 436.10

S 6,077.76

S 376.98

S 8,404.25

S 42,659.87

S 1,424.53

S 22,450.06

S 5,274.36

S 1,565.81

26 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 30mar '12 abr '12 may '12 jun '12 jul '12 ago '12 sep '12 oct '12

Tarea Tarea crítica Progreso Hito Resumen Tarea resumida Tarea crítica resumida Hito resumido Progreso resumido División Tareas externas Resumen del proyecto Agrupar por síntesis Fecha límite

CAPACIDAD RESOLUTIVA DE LOS SERVICIOS DE SALUD DE LA UNIDAD DE EMERGENCIA Y DE UCI DEL HOSPITAL SAN JUAN BAUTISTA DE HUARAL

Página 3

Proyecto: CronogramaFecha: jue 23/02/12