MI CHELLE HAW RYLUKMINI STRY OF ENVIR ONMENT
29 OCTOBER 2015
Progress Report on Remediation Options in Elk/Beaver Lake
The Background
2013 steering committee MOE, FLNRO, CRD, District of Saanich, R. Nordin (BCLSS)2014-2015 Comprehensive sampling
(GRR, District of Saanich, R. Nordin, MOE, FLNRO, PSS)2015 Reports:
Overview, status & P budget - Dr. R. Nordin
Evaluation of remediation options - Freshwater Research
Updated Water Quality Objectives….- MOE
Keep in Mind….
1) There are no cheap, easy, one-size-fits-all fixes
2) Lake remediation has to be a two-pronged approach
The immediate problem Watershed management
The Draft Evaluation
Review & update external P load vs. internal P load
Potential remediation techniques
Data gaps & limitations
The Draft Evaluation - [P Load]
Review & update external P vs. internal P
224 kg/yr + 1,585 kg/yr = All P (external) (internal)
O’Donnel Creek
Ephemeral Creeks Atmosphere
Septic systemsBirds
Agriculture
Sediment BankAquatic Vegetation
The Draft Evaluation - Remediation Techniques
Physical treatment destratification, artificial mixingaeration & oxygenation
Flow Managementhypolimnetic withdrawal
P PrecipitationPhoslock
Next Steps
ID gaps & limitationsRevised remediation report December 2015Steering committee review of the
recommended optionsProcess of approvalStakeholder consultationFundraising and approvalsImplementation
Please don’t shoot the messenger