MICE VC 107 10 Jan 2008 MICE news

12
1 MICE VC Alain Blondel 10 January 2008 MICE VC 107 10 Jan 2008 MICE news -- BEST WISHES TO ALL FOR 2008 -- main outcomes of MICO meeting 9 January -- running MICE safely in 2008 -- MOMs for 2008 -- collaboration meeting 10-13 February 2008

description

MICE VC 107 10 Jan 2008 MICE news. -- BEST WISHES TO ALL FOR 2008 -- main outcomes of MICO meeting 9 January -- running MICE safely in 2008 -- MOMs for 2008 -- collaboration meeting 10-13 February 2008. MICO 9 January 2008. 1. Summary of beamline & hall installations (Richard Apsimon) - PowerPoint PPT Presentation

Transcript of MICE VC 107 10 Jan 2008 MICE news

Page 1: MICE VC 107 10 Jan 2008 MICE news

1MICE VC Alain Blondel 10 January 2008

MICE VC 10710 Jan 2008MICE news

-- BEST WISHES TO ALL FOR 2008 -- main outcomes of MICO meeting 9 January-- running MICE safely in 2008-- MOMs for 2008-- collaboration meeting 10-13 February 2008

Page 2: MICE VC 107 10 Jan 2008 MICE news

2MICE VC Alain Blondel 10 January 2008

MICO 9 January 2008

1. Summary of beamline & hall installations (Richard Apsimon) 2. January shutdown status (Tim Hayler) 3. Target status (Chris Booth) 4. ToF & KL (Maurizio Bonesini, Ludovico Tortora) 5. Beam Profile Monitors (Alan Bross) 6. Tracker status (Ken Long) 7. DAQ report (Jean-Sebastien Graulich) 8. Controls & PPS (Brian Martlew, John Alexander) 9. Running plans (Kevin Tilley) 10. Discussion 11. Next meeting --> Thursday 24 January 2008 12. AoB

Page 3: MICE VC 107 10 Jan 2008 MICE news

3MICE VC Alain Blondel 10 January 2008

Main conclusion:EVERYBODY is trying hard to be on time according to end-of-shutdown/ISIS run on 21 January/4 Feb

-- ISIS has two major problems: ISIS dipole 2 needs changing, ISIS target has problems

-- 21 January: ISIS must be closed (there may be a small delay in this date)

21-jan--> 4 Feb running in period We have requested three times 2-3 shifts with MICE control: early, mid, late in this period + any available nights. It is still possible to install reliably a detector that would arrive at RAL in the early part of that period DSA or even in vault (CKOV, TOF0, MBLM)

5 Feb--> production run of ISIS until 13 March Installation opportunities in the DSA will be limited and random

Page 4: MICE VC 107 10 Jan 2008 MICE news

4MICE VC Alain Blondel 10 January 2008

0.- (basic radiation levels - no target in) - doesn't need any specific shifts

1. - 2x8-hour shifts for target tests at the middle of the startup period - to establish target running requirements.

- target position, loss volts, isis activation- increase dip to 0.05V.- radiation levels ~ MICE hall etc.

2. - 3x 8-hour shifts for beamline installation/commissioning work @ 0.05V- 'flushing through': first functional tests where entry synch/DSA poss. to fix- radiation levels~ MICE hall etc.- measure of *early* rates- standardisation checks.

Plan to proceed: 1shift negatives w/o proton absorber: 1shift negatives with proton absorber: 1 shift positives with proton absorber.

3. - 2x 8-hour shifts for target tests at the end of the start up period- continued target shifts if problems.- or to aim to above 0.05V, measure stability, loss, activiation etc, MICE rad. levels.

4. Any available night shiftsChris Rogers

Page 5: MICE VC 107 10 Jan 2008 MICE news

5MICE VC Alain Blondel 10 January 2008

Main conclusions from MICO

++ beam line installation

2 major hickups, scrambling to recover:

-- ISIS personnel not available for upstream beamline work (alignment etc) -- New Target stand not ready

++ MICE detectors

-- Ckov ready to install (stands?) before 20 Jan.

-- TOF0 to arrive last week of January (preferred) or first week of Feb.

-- Mice BeamLineMonitor from Fermilab will arrive for step II. An array of scintillator is being prepared at ICL for the MBLM1.

==> we would like to know more about this.

-- TOF1, KL to arrive second half of February (stand in absence of Spectrometer solenoid?)

-- Jean S. Graulich and Paul Soler has been approached to provide scintillator to measure integrated particle rate at ‘tof0 and tof1’ until these detectors have arrrived. (These scintillators will remain useful)

-- tracker: cryomodules have been repaired. Could be shipped to RAL by end January. Tracker operational first half of February. (meeting Friday 11 to decide: cosmic test or put in beamline? Should be able to do either depending on circumstances

Page 6: MICE VC 107 10 Jan 2008 MICE news

6MICE VC Alain Blondel 10 January 2008

Run Plan

Determine sequence of events to running in the beam lineFlexibility will be required and order of events may change

Plan does include radiation monitoring (2 monitors needed) and radiation surveys at four specific configurations to determine possibility of Hall construction while taking data(tracker TOF1,2 KL installations, Mag. Shielding, Spectro Solenoid) Target commissionning

Pion beam line dipoles, quads, DK solenoid, proton absorber in/out, + and -Vary momentum to measure part. prod.

If possible muon beam and vary optics towards end of period

Controls and monitoring: no report

Action: produce descriptive note.

Page 7: MICE VC 107 10 Jan 2008 MICE news

7MICE VC Alain Blondel 10 January 2008

Running MICE safely

Regular safety-coordination meetings are run by David Findlay with relevant MICE Management. Aim is to ensure safe operation of MICE

Ground rules for operation of MICE at ISIS shall be as follows.

1. MICE shall be set up with its own management structure, and shall operate largely as a “tenant” of the ISIS “landlord”.[Need this because MICE is an international collaboration — ISIS is not in control of everyone in the MICE collaboration.]

• A suitable person shall be appointed by the Director of the Particle Physics Department to take overall responsibility for MICE operations. The appointment is subject to approval by ISIS, and the approval process shall include an assessment of the competence of the person.[At the time of writing, and with the approval of ISIS, Richard Apsimon has been provisionally appointed as MICE Project Manager. Richard Apsimon and Andy Nichols jointly fill the “MICE Technical Coordinator / Project Manager” rôle identified in “Technical coordination of the MICE experiment”, Revision 1: CMPB 14(01), MICE-Note 175, 6th August 2007, but Richard Apsimon has agreed to take the lead in project management matters.]

Richard Apsimon is the MICE person responsible for safety matters

Page 8: MICE VC 107 10 Jan 2008 MICE news

8MICE VC Alain Blondel 10 January 2008

3. The person with overall responsibility for MICE operations shall ensure that MICE is operated safely to the satisfaction of both the Facilities Development and Operations Director and the ISIS Director. At the time of writing, these two directors are one and the same person, Andrew Taylor.

While MICE is operated the MICE operation Managers will be in charge by delegation of R. Apsimon.

3. The ISIS Crew shall not be responsible for running operations in the MICE Hall.

4. MICE shall comply with the STFC safety management system and, with the agreement of ISIS, appoint competent persons as required.

Such persons to include Electrical Authorised Person, Radiation Protection Supervisor (RPS) (who could be Tim Durkin, the PPD RPS, or Paul Flower who has RPS experience), COSHH Responsible Officer (who could be the PPD COSHH officer), and Building Warden (likely to be the Hall Foremen).Except for the Decay Solenoid Area (DSA), the ISIS Duty Officer shall not formally act as the Radiation Protection Supervisor (RPS) for MICE.

The shielded area in R5.2 located up against the synchrotron shielding wall and containing the decay solenoid, one dipole and three quadrupoles. Because of radiation shine through from accelerated beam in the synchrotron room this area has to be treated as an operational ISIS interlocked machine area

Page 9: MICE VC 107 10 Jan 2008 MICE news

9MICE VC Alain Blondel 10 January 2008

6. The ISIS Crew and other approved ISIS staff members must always be able to have access to equipment in R5.2 associated with ISIS operations.[For example, something might go wrong in the DSA and in order to restore beam the ISIS Crew would have to be able to go in at short notice. Or something might go wrong with the HEDS beam chopper and people from the Controls and/or Synchrotron Groups would have to go in to fix it.]

7 The MICE pion target in Straight 7 of the ISIS synchrotron shall ultimately be under the control of the ISIS Crew.[In practice, MICE should be able to operate the target as they see fit within beam loss limits previously shown to be acceptable for ISIS running, but it would be the ISIS DO who granted the initial permission to operate.]

8 Unless otherwise agreed, scheduling ISIS for neutron and muon users shall take precedence over scheduling for MICE if conflicting scheduling issues arise.[Not clear at this stage exactly what these conflicting issues might be, but it would be unfortunate to have all the many users of the two target stations and the muon experiments held off unnecessarily by what is essentially a parasitic activity.]

David Findlay30 November 2007

Page 10: MICE VC 107 10 Jan 2008 MICE news

10MICE VC Alain Blondel 10 January 2008

Qu

ickTim

e™

an

d a

TIF

F (

LZ

W)

decom

pre

sso

rare

nee

de

d t

o s

ee t

his

pic

ture

.

Qu

ickTim

e™

an

d a

TIF

F (

LZ

W)

decom

pre

sso

rare

nee

de

d t

o s

ee t

his

pic

ture

.

MICE run and MOMs

Page 11: MICE VC 107 10 Jan 2008 MICE news

11MICE VC Alain Blondel 10 January 2008

Important aspects of running MICE

The Technical Coordinator/Project Manager is responsible for the safe implementation of the experiment and for its safe operation. Day-to-day responsibility for safety during the build phase of the experiment is delegated to the Hall Manager and Principal contractor. During running, the safe operation of the experiment is delegated to the MICE Operations Manager(MOM) .

For each MICE step a set of safety reviews will be organized by the MICE project manager, before installation (safety design review), before commissioning (authorization to operate) and before regular operation. The critical subsystems of MICE will be reviewed either collectively or one by one as will be seen fit by the MICE project manager in agreement with the spokesperson and in presence of one or several designated ISIS representatives as required.

A fool-proof operations manual, including safety aspects, will have to be ready for each MICE subsystem before regular operation. The documentation is the responsibility of each MICE subsystem.

Page 12: MICE VC 107 10 Jan 2008 MICE news

12MICE VC Alain Blondel 10 January 2008

MEETING CALENDAR

Next Scheduled MICO meeting Thursday 24 January:

Next collaboration meeting:

Sunday 10- Wed 13 February 2008organisers: Kyberd/Blondel/LoaderRegistration page will be posted imminently. Please register.

parallel meetings on Sunday: tracker PID, software, beam linePlenary monday morning in auditorium with WomersleyParallel meeting in the afternoon (software--> analysis) Collaboration dinner monday eveningPlenary on Tuesday morning and Wednesday morningEB on Wednesday afternoon. parallel in R12 R13 or plenary in R12+13 monday aft to wedn. morning.

MICE will be running-in ==> meeting at RAL, Accomodation has been booked  on site at the Ridgeway House(20) and R70(10).Because ISIS will be running there will be food at the RAL in the evening, entertainement in the evening will be conditional to having a car or friends with one.