Step-by-Step Oracle11gR2 two Node RAC running Solaris10 with ISCSI
MICE Project Board 28-08-2011 Alain Blondel 1 MICE running Preamble ISIS running Step I Step(s) IV...
-
date post
21-Dec-2015 -
Category
Documents
-
view
215 -
download
0
Transcript of MICE Project Board 28-08-2011 Alain Blondel 1 MICE running Preamble ISIS running Step I Step(s) IV...
1MICE Project Board 28-08-2011 Alain Blondel
MICE running
Preamble
ISIS running
Step I
Step(s) IV
Step V (and VI)
2MICE Project Board 28-08-2011 Alain Blondel
0. 0.04 0.08 0.12 0.16 0.20 sin2 213
90% C.L.
new results from T2K (13 June) and MINOS (24 June) on e appearance indications that sin2213 is >0
old fit
T2K
MINOSnote:different CP
axes!
3MICE Project Board 28-08-2011 Alain Blondel
Needs confirmation but this is exciting for neutrino long baseline physics!
Large values of sin2213 would give a chance for superbeams to have a shot at CP violation,
but Neutrino Factory remains most precise and only device able to test oscillations very precisely -- precision measurements of angles and mass differences, -- tau appearance and unitarity tests-- detailed study of matter effects-- etc…
Physics is moving forward, no time to waste, Ionization cooling must be demonstrated
4MICE Project Board 28-08-2011 Alain Blondel
Incoming muon beam
VariableDiffuser
Beam PIDTOF 0
CherenkovTOF 1
Trackers 1 & 2 measurement of emittance in and out
Liquid Hydrogen absorbers 1,2,3
Downstreamparticle ID:
TOF 2 KL, EMR
RF cavities 1 RF cavities 2
Spectrometer solenoid 1
Matching coils 1&2
Focus coils 1 Spectrometer solenoid 2
Coupling Coils 1&2
Focus coils 2 Focus coils 3Matching coils 1&2
10% cooling of 200 MeV/c muons requires ~ 20 MV of RF single particle measurements =>
measurement precision can be as good as out/ in ) = 10-3
never done before either…
5MICE Project Board 28-08-2011 Alain Blondel
Quantities to be measured in a cooling experiment
equilibrium emittance = 2.5 mm
cooling effect at nominal inputemittance ~10%
curves for 23 MV, 3 full absorbers, particles on crest
Measurements of
TRANSMISSIONEMITTANCE REDUCTIONEQUILIBRIUM EMITTANCE
for the standard Study II optics
are the main deliverables
beam line can deliver 3,,6,,10 mm(see Mark’s talk)other values can be reached byoffline culling or reweighting
6MICE Project Board 28-08-2011 Alain Blondel
MICE Steps
STEP I
STEP II
STEP IV
STEP Vaim: April 2014
STEP VI
STEP III/III.1
October 2012- March 2013
-- skip --
-- skip --
-- complete -- EMR comm.
7MICE Project Board 28-08-2011 Alain Blondel
MICE RUNNING
8MICE Project Board 28-08-2011 Alain Blondel
MICE Target
-- Linear motor dips target at 80g -- in beam since Sept’09 571k dips-- reproducibility excellent-- tested regularly for reproducibilityto test possible degradation. -- not-so-easy to build a second one that works that well!
9MICE Project Board 28-08-2011 Alain Blondel
T2.X = linear motor 2, target mech. X motor 2 presumed inferior to motor 1nevertheless almost there! Building two new linear motors with improved tolerances. Aim at having T3 and T4 targetsto install in ISIS & Spare by end 2011
10MICE Project Board 28-08-2011 Alain Blondel
MICE STEP I Superb data taking end 2009 and summer 2010!
GOALS ACHIEVED See presentation by M. Rayner at FAC in Jan 2011Rates limited by beam loss induced in ISIS.
11MICE Project Board 28-08-2011 Alain Blondel
-- required muon rate is ~50/200 per pulse without (stepI-IV)/with (StepV-VI) RF
-- limitation is irradiation in ISIS due to beam losses induced by MICE target measured in Volts on Beam Line Monitors -- observed rates in MICE 2010 (6mm beam)
5 TOF1/ms/V_BLM for - beam,
30 TOF1/ms/V_BLM for + beam
following a series of dedicated irradiation runs and measurements of activationISIS allowed us to run routinely at 2V and even tried up to 10V.
We are within range for STEPS I-IV
further studies on how to get more muons per losses are ongoing (beam bump, timing, faster dip, etc..)
muon rates
12MICE Project Board 28-08-2011 Alain Blondel
High beam loss (up to 10 V) tests (14 Aug.)
https://micewww.pp.rl.ac.uk/elog/MICE+Log/1449 https://micewww.pp.rl.ac.uk/elog/MICE+Log/1447
13MICE Project Board 28-08-2011 Alain Blondel
How MICE Measures in Step 1
(t0,x0,y0)
(t1,x1,y1)
TOF0 TOF1
Beam profile at TOF0
Use TOF0 and TOF1 to determine phase space parameters of the muon beam
Tof-0
0.40 m
10 x 4cm scintillator barsx = 1.15 cmt = 50 ps
Tof-1
0.42 m
7 x 6cm barsx = 1.73 cmt = 50 ps
Momentum-dependent matrix relates
(t0,x0,y0,t1,x1,y1)
(t1,p,x1,x’1,y1,y’1)
solved by iteration
14MICE Project Board 28-08-2011 Alain Blondel
Measurement Result: Data vs MC
Reconstructed transverse phase space of the baseline MICE beam (6-200) at TOF1
Data
MC
M.Rayner OxfordU
y (mm) vs x (mm) x (mrad) vs x (mm) y (mrad) vs y (mm)
15MICE Project Board 28-08-2011 Alain Blondel
STATISTICS
See John Cobb MICE note 268: Statistical error on relative change of emittance is 1% with 105 muons
Presently allowed running with beam loss of 2-3 V (assume 50 + /Spill)
for STEP IV: 1 measurement = 2 103 spills ~ 2 hours. (full matrix in 3 days)
for step V and VI need 12 times more statistics (match RF phase!) 1 measurement = 2 104 spills ~ 20 hours.
We would aim at higher rates for step V, rate is sufficient for step IV
16MICE Project Board 28-08-2011 Alain Blondel
ISIS running periods, MOM Rota and MICE runs in 2011
First semester
Second semester
17MICE Project Board 28-08-2011 Alain Blondel
EMR installed in MICE hall
First 3 modules, running cosmics now. Start run on 30 June. Full detector to run in Feb 2012
18MICE Project Board 28-08-2011 Alain Blondel
ISIS running
Typical year consists of 5 ISIS ‘user runs’ of ~35 days each + run-ups, MP.
5 periods April 2013 to April 2014 priority to Step V installation Some additional step IV running not ruled out but lower priorityNext Long Shut Down envisaged: Aug. 2014 to February 2015
new target,full EMR
LiH wedge+ reserve
no running
Step IVInstallation
Step IV: empty/LH2/(LHe)
no absorberflat LiH
19MICE Project Board 28-08-2011 Alain Blondel
MICE Steps
STEP I
STEP II
STEP IV
STEP V
STEP VI
STEP III/III.1
20MICE Project Board 28-08-2011 Alain Blondel
The point was raised (Cobb) that
1.. The optics of step III is not easy to match for conservation of emittance
2. The logistics of changing from Step III to step IV is not trivial.
3. we can execute the physics program of step III and step III.1 with the magnetic channel of step IV
effect on Schedule is a balance =
time gained by suppressing specific installation of step II and step III
time lost by required push-pull operations in replacing solid absorbers
>4 mo
--vs--
3 to 6 x8 days
= Winner!
Skipping steps
21MICE Project Board 28-08-2011 Alain Blondel
Amplitude Cooling... in empty channel
Step 3 empty Step 4 empty
Amp OUT
Amp IN
Amp OUT
Amp IN
6mm beam, SigPz = 1 MeV/c, 100k muons
140
120
100
80
60
40
20
140
120
100
80
60
40
20
0 20 40 60 80 100 120 140
0 20 40 60 80 100 120 140
(T.Carlisle)
22MICE Project Board 28-08-2011 Alain Blondel
Clearly the optics of step III leads to ‘heating’ up to 5% (mis-beaviour of dispersive beam?)
Step IV is much cleaner from this point of view (~0.2%)
23MICE Project Board 28-08-2011 Alain Blondel
23
Step IV
Time to install Step IV – 168 days (about six months)Step IV running time – ~10 daysTime to substitute solid absorber in FC – 8 days
Important assumptions at this stage:• AFC module is ready and tested• LH2 infrastructure in MICE Hall is ready
Hayler, Nichols
24MICE Project Board 28-08-2011 Alain Blondel
STEP IV
in out
1.liquid H2 absorber, emptycommission system, tracker, detectors, optics compare in / out
for various values of momentum, emittance and beta function
systematic errors
2.liquid H2 absorber, full
measure cooling properties of liquid HydrogenAt that point will have measured ionization cooling!
can also measure LHe (lower priority)
STEP IV configurations
25MICE Project Board 28-08-2011 Alain Blondel
STEP IV configurations
3.Vacuum (only He and window for trackers)
execute STEP III program; compare in / out
information on systematic error of final experiment information on effect of windows by comparison with
STEP IV
in out
26MICE Project Board 28-08-2011 Alain Blondel
STEP IV configurations
4.Solid absorbers execute STEP III.1 program; compare trackin /trackout
compare in / out
for various values of momentum, emittance and beta function
information on emittance generating properties of materials
STEP IV
in out
2727
The MICE Energy Absorber
New Hanger Arrangement
3 SS straps 1 Machined SS
clamp 45 cm, t= 65 mm
Y12 is producing the LiHProduced by Hot Isostatic
Pressing (150 oC, 30,000 psi)
Final parts will beTested for Chemical
composition and purity
Radio-graphed to ensure no voids
Machined to sizeDimensional inspectionCoated with epoxy
completely
28MICE Project Board 28-08-2011 Alain Blondel
Absorber measurements thickness 10 MeV energy losswill measure: Liq H2 330 mmLiH 65 mm
Also possible (used in NuFACT beams)Liq He 410 mmBe 34 mmAl 23 mm
with low priority: Plastic 50 mmFe 9 mm Cu 8 mm
Will study wedge absorbers (change 6D emittance)
29MICE Project Board 28-08-2011 Alain Blondel
Step V
STEP V
“sustainable” cooling:cooling happens in the absorbers but production of cool beam requires acceleration with RF cavities
old simulation (at 88MHz)
RF phase
Eout-Ein
-1- running with shutters to commission RF cavities (no beam needed) -1’- running with LH2 and RF first with no beam to check RF noise-2- running with beam with no RF and no LH2 to check optics -3- running with beam with LH2 no RF-4- running with beam with LH2 and RF -5- or running 2-3-4- with solid absorbers?
limited in optics and performance step VI!
09.9.2010 Slide 30
FINAL COMMENTS
Steady progress towards demonstration of Ionization Cooling
Already demonstrated validity of beam line principle and emittance measurements with particle detectors
On daily basis: LHe test of LH2 system, 1MW in RF unit, EMR prototype, SS repair plan, etc…
Progress on global MICE Project management (Thanks Andy!)
On solid ground for running step IV in Oct. 2012, aiming to start step V in 2014 before long shutdown (tough but everyone on board!)
Looking forward to significant cooling measurement results!
09.9.2010 Slide 31
T2KK: T2K 1.66 MW beam to 270 kton fid volume Water Cherenkov detectors in Japan (295km) and in Korea (1050 km); DUSEL: a WBB from Fermilab to a 300 kton WC in Dusel (1300km); SPL 4 GeV, EU-BB and BB+SPL: CERN to Fréjus (130km) project; NF bl is the Neutrino Factory baseline (4000km and 7000km baselines) and NF Py+INO represents the concrete baseline from CERN to Pyhasalmi mine in Finland (2285 km) and to INO in India (7152 km); PS2-Slanic is a preliminary superbeam study at 1500km based on an upgrade of PS2 to 1.66MW and a 100kton Liquid Argon TPC
CERN – SPC panel report , SPC meeting, 16.03.2010
Figure 2 A representative compilation of sensitivities of some future long baseline projects. Here the fraction of CP where CP violation can be observed at 3 standard deviations is plotted as a function of 13.
09.9.2010 Slide 32
From IDS-NF IntermediateDesign Report IDR
09.9.2010 Slide 33
High-power target . 4MW . good transmissionMERIT experiment (CERN)
Major challenges tackled by R&D expts
Fast muon cooling MICE experiment (RAL)
Fast, large aperture accelerator (FFAG)EMMA (Daresbury)