MICE Operations Manager Report Linda Coney University of California, Riverside UKNF Meeting June 8,...
-
Upload
amos-terry -
Category
Documents
-
view
218 -
download
0
Transcript of MICE Operations Manager Report Linda Coney University of California, Riverside UKNF Meeting June 8,...
MICE Operations Manager Report
Linda ConeyUniversity of California, Riverside
UKNF Meeting
June 8, 2010
2June 8, 2010 MOM Report-Coney
Outline
Overview of MICE motivation and beam line layout MICE Schedule Target & Beamline Detector Commissioning
, e, p, and beams Supporting infrastructure Beam studies Upcoming Production Running Conclusions
3June 8, 2010 MOM Report-Coney
MICE Motivation
The muon beam after the front end of a Neutrino Factory is: Wide – x ~ 10(+) cm Divergent – ~ 150(+) mr
Need to cool the beam: Increases number of muons in the acceptance of the accelerator by factor of 2-10
Ionization cooling is the only good option: Muon lifetime is short ~2 s Cannot use stochastic cooling – slow, iterative process Muons pass through absorber material followed by RF cavities Lose transverse and longitudinal momentum in absorber – restore longitudinal with RF g
reduction in transverse emittance Competition between cooling (dE/dx) and heating (multiple scattering)
Optimal results with: Low Z, large X0 material Tightly focused beam H2 most promising absorber material
Simple premise; however, the reality is not simple need a test
Muon Ionisation Cooling Experiment
MICE: Design, build, commission and operate a
realistic section of cooling channel Measure its performance in a variety of modes
of operation and beam conditions …
… i.e. results will be used to optimize the
Neutrino Factory design
5
Layout of MICE:
Target
Upstreambeam line
MICE Local Control Room
Decay solenoid
Downstream beam line
Linde refrigerator
Instrumentation in place:Beam profile monitorsTrigger/rate scintillatorsCKOVs, TOF0,1&2, KL
6June 8, 2010 MOM Report-Coney
MICE Schedule
Current focus is on Step I: Beamline commissioning Detector comissioning and calibration
7June 8, 2010 MOM Report-Coney
Target Operations
50,000 pulses of redesigned target in test stand in R78 Current target installed in ISIS August 2009
Run at base rate (50 Hz/32) and with ISIS at 50 Hz (Normal User Run)
Inspected regularly – PASSED Target is working beautifully – NO problems Target stability checked every 10,000 pulses
Process to monitor target behavior agreed upon with ISIS
Target timing wrt ISIS MS signal monitored Coordinating Beam Loss measured by MICE with that
measured by ISIS Target Operation: 233,000 pulses to date
February/March User Run – 10 days April/May User Run – 15 days
See target update during this session
MICE target path
ISIS cycles
MS marker
ISIS losses
8June 8, 2010 MOM Report-Coney
Upstream Beamline
9June 8, 2010 MOM Report-Coney
Beamline
Conventional magnets Controls software improved
Automatic gradual ramp up/down implemented (DL) Eases burden on electrical infrastructure & on shift crew
Faulty water flow gauges in all magnet power supplies replaced
Removes cause of most magnet trips during running Water flow through magnets increased to recommended
level Monitored in Alarm Handler, archived
New pressure valves installed on magnets Water pressure reduced from 8 to 4 bar
Field monitoring with Hall probe Configuration Database in the works
Polarity detection scheme implemented Proton Absorber installed in February downstream of
Decay Solenoid -see talk this session – Chris Rogers (RAL)
10June 8, 2010 MOM Report-Coney
Beamline: Decay Solenoid Running well during data-taking September – December 2009 Linde Fridge serviced in January developed problems
Cooldown failed end of January Fridge developed fault – N2 contamination in DS cold box Blockage in cold trap?
Linde engineer to RAL late March changed charcoal in gas panel absorber, cycled through processes, no leaks But when compressor isolated from cold box and cold trap back into operation N2 levels rose again
Leak in compressor shaft seal? Easter Engineer back to RAL mid April new shaft seal stuck & would not move
Compressor removed & taken to Linde contractor Back April 20th with completely new compressor Stuck seal suspected of being root cause of the problem
Still not solved Wrong seal from manufacturer – designed for air not He Ordered new seal – sent wrong one again Finally got correct seal for compressor
Vacuum gauges also needed to be replace Scroll pumps needed servicing as well (now done)
Cooldown (re)started mid-May – record time of 5 days Liquid He level probe not working - Problem with old electronics? Debugged – replaced suspected chip – end May determined sensor had gone bad
Friday – cold swapped for new sensor – now working Magnet cold – undergoing current testing
11June 8, 2010 MOM Report-Coney
Data Taking Program: Positive Particles
Detector Calibration: 300 MeV/c pions - used for calibrating the TOF system 290 MeV/c pions – TOF, KL 270 MeV/c pions – TOF, KL 250 MeV/c pions – TOF, KL 200 MeV/c pions – TOF, KL
300 MeV/c positrons - CKOV and KL calorimeter 250 MeV/c positrons - CKOV and KL calorimeter 200 MeV/c positrons - CKOV and KL calorimeter 150 MeV/c positrons - CKOV and KL calorimeter
Beam Studies:
Luminosity monitor studies Particle Rate vs Losses in ISIS Study Muon beam configurations to study proton absorber(s)
Muon Beams: pi+ to mu+ beam (6-200, 3-200, 10-200) - 3500 pulses
17
12June 8, 2010 MOM Report-Coney
Detector Commissioning: Time of Flight Counters
TOF0, TOF1 installed for September & Nov/Dec User Runs TOF2 installed in late November Horizontal and vertical bars Have proven to be essential in beamline commissioning
Tof-0
0.48 m
10 x 4cm scintillator barsx = 1.15 cmt = 50 ps
Tof-1
0.48 m
7 x 6cm scintillator barsx = 1.73 cmt = 50 ps
13June 8, 2010 MOM Report-Coney
Detector Commissioning: Time of Flight Counters
Time resolution after the calibration:
• TOF0 – 51ps;• TOF1 – 62ps;• TOF2 – 52ps.
14June 8, 2010 MOM Report-Coney
Detector Commissioning: TOFs
Time of flight distributions for different data sets:
--
300 MeV/c - beam
e-
--
300 MeV/c - beam
e-
e-
--
300 MeV/c e- beame-
--
300 MeV/c e- beam
-
e-
400 MeV/c - 225 MeV/c -
-
e-
400 MeV/c - 225 MeV/c -
15June 8, 2010 MOM Report-Coney
Detector Commissioning: e/ Identifier
KL lead/scintillating fiber calorimeter module Calibration in progress 50% of electrons 240 MeV/c at target, and 80%
of electrons 360 MeV/c at target release energy in KL tag counter
Muons with 220 MeV/c at target reach EMR Muons with < 80 MeV/c at KL will die in KL (170
at target) More data needed:
170 < p <200 MeV/c at target 195 < p < 230 MeV/c at target
27
Energy Response
16June 8, 2010 MOM Report-Coney
Beam Studies Particle rate vs beam loss – Adam Dobbs - Imperial
Hold target timing steady – vary depth into beam to increase losses
Measure particle rate in MICE beamline
Luminosity Monitors – see talk this session – David Forrest - Glasgow
Determine particle rate close to target & find protons on target as function of depth
Validate particle production in target and beamline simulations
Emittance measurement with TOFs – see talk this session – Mark Rayner - Oxford
Purpose: generate the elements of the “emittance-momentum matrix” Study performance at every portion of a full cooling channel
17June 8, 2010 MOM Report-Coney
Infrastructure: Access, DB, & Data Analysis
New ssh bastion is working Successfully connected through from outside to
computers in the MLCR X-forwarding is working
Two areas of disk space are set up on PPD cluster for MICE
G4MICE will be installed and available on the PPD system
Database Configuration Database is installed on new
database server & web services server at RAL Database interface is visible from control room EPICs client now in place to read/write values set in
a run Tested EPICs client with database – successful NEXT: run in parallel with spreadsheet during
Machine Physics runs Monitoring
environmental conditions, ISIS loss monitors AC units, magnet PS water flow
18June 8, 2010 MOM Report-Coney
Computing Infrastructure
SSH
EPICS Gateway
DB API
DB
Outside World Micenet / MLCR
DB API
eLog
SSH Bastion
Config Database
“Web” services
EPICS archiver web interface
ssh
SSH / web services
EPICS
Spare node
Grid clientsGrid Transfer Box
18
PPD-Grid managed
SSH+ analysis
code
Analysis Node/Farmssh
MICE managed
PPD-IT supervised
19June 8, 2010 MOM Report-Coney
Next: Finish Step I
Moving into Intense data-taking period to finish Step I before long shutdown
Production Running - User Run in June/July/August: Run 5 days/week – M-F 10-12 hours/day (8am-8pm) Personnel needed: MOM, BeamLine Expert, Shift Leader, Shifter
Shift leader has more experience and trains up new person Novices need 1 week training shifts before official shifter
Experts/those doing the study are also there to guide & monitor progress
Data-taking Run: 12 hours
shifter1
shifter2
MOM & BLOC MOM & BLOC
June 8, 2010 MOM Report-Coney 20
June/July/August Run
•Developing Global Run Plan:— User Run JUNE 22-AUGUST 12— Machine Physics Aug 13-15— SHUTDOWN August 16 – January 30, 2011
— Machine Physics studieso Activation Study at 4V beam losso Beam Loss vs Rateo Beam Bump Study
— User Runo Week1: Tues June 22-Fri June25
– 3 days TOF calibration– 1 day KL data
o Week2: June 28-July 2: Emittance/Momentum matrix with muon beams
o Week3 more emittance/momentum matrix data
24/3/2010 CM26 - Riverside 212124/3/2010 CM26 - Riverside 21(*) 700mV ~ 20 mu-/spill
3,1403,140 3,2003,200 3,2403,240
6,1406,140 6,2006,200 6,2406,240
10,14010,140 10,20010,200 10,24010,240
P (MeV/c)
eN
(m
m r
ad
)
- finding the element (3,240) means to find the BL optics that matches the MICE optics for a beam of 3 mm rad at a P=240 MeV/c
- the element (10,200) is the BL optics matching a MICE beam with 10 mm rad at P=200 MeV/c
This pair is our goal: how do we get it?
Fill in -p matrix data
22June 8, 2010 MOM Report-Coney
Conclusions
Beamline is (mostly) working! – negative or positive particles New target operating smoothly - Systematic monitoring of performance Decay Solenoid needed for operation – factor 5 increase muon rate Major increase in loss limits 50 mV (2008) 1V (2009/10) 2V? soon DAQ increase in efficiency: <50 particles/spill (2008) ≤ 200 part/spill (2009) Beam loss vs particle rate shows linear dependence
Detectors are working! TOF0, TOF1, TOF2 calibrated Need more data for KL but progressing Tracker works – nearing dual-readout stage
Muon beam physics happening again soon! Initial measurement of muon beam emittance More (,P) matrix data in June/July/Aug
23June 8, 2010 MOM Report-Coney
24June 8, 2010 MOM Report-Coney
Muon Beam Studies at MICE!
The MICE experiment takes 17000 target pulses of muon beam data!
~170,000 at TOF1 Muon beam studies begin!
Worldwide celebrations
ensue!
Locals in Britain express strong support for the experiment
BlimeBlimey!y!
MuonsMuons!!
35
Extra!
Extra
!
Extra! Extra!
25June 8, 2010 MOM Report-Coney
Detector Commissioning: Cherenkovs
Two aerogel Cherenkov counters Installed downstream of Q6 and TOF0 Used to separate e// 220-350 MeV/c e// calibration data taken Sample electron data shown
26
June 8, 2010 MOM Report-Coney 26
Run Summary
•May 27-28: 10,700 target pulses — Target count is at 233,750
— 300 MeV/c e+ beam TOF calibration – TOF0 triggero Th/Fri – 6,4000 pulses with ~45 particle triggers/spill
— Muon beam: 6-200 point on emittance-momentum matrix – TOF1 trigger
o Fri – 1250 pulses ~6 particle triggers/spill
— Muon beam: 10-200 point on emittance-momentum matrix – TOF1 trigger
o Fri – 1000 pulses ~6 particle triggers/spill
— Muon beam: 3-200 point on emittance-momentum matrix – TOF1 trigger
o Fri – 1000 pulses ~4 particle triggers/spill