Building resilience to climate change: costs and benefits ...
Mgmt study material created/ compiled by - Commander … Costs are the costs which change in direct...
Transcript of Mgmt study material created/ compiled by - Commander … Costs are the costs which change in direct...
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 1 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
COST ACCOUNTING AND COST MANAGEMENT By Mr RS Sardesai
Syllabus
1. Cost analysis and preparation of cost statement
2. Marginal costing and decision making
3. Standard costing calculation and variances
4. Budgetary control and various functional budgets
5. Job costing and apportionment of service dept’s cost
6. Contract costing
7. Process costing
1. Cost Analysis and Preparation of Cost Statement.
(a) Cost. Cost is all expenditure incurred to bring the goods or services in
the present condition or location.
- Implies that all expenditure is not cost
- Cost to be calculated with some reference point
- There is a change in location or condition or change in both.
(i) Raw Material Stock Cost (to be valued at cost)
- Supplier’s price
- Loading Charges
- Transportation
- Transit insurance
- Import duty or octroi etc
- Unloading charges
- Godown charges - X
(a) Godown charges are some times not considered as
cost as there is no change in location or condition
(b) Godown charges are considered only after the item
is shifted from godown. In case of using godown during the
transit, the charges are to be included.
(ii) Finished Goods Stock
- Raw material cost
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 2 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
- Wages
- Factory expenses
(a) Water
(b) Electricity
(c) Shed rent
(d) Depreciation on asset for production
(e) Factory taxes
- Packing
- Excise duty
- Sales tax X (not to be included)
- Advertising X
(iii) Semi finished goods
- Raw material
- Wages On proportionate basis
- Factory expenses
Analysis of Costs. There are three methods adopted for cost analysis.
1. Direct and Indirect Costs method.
2. Variable, Fixed and Semi Variable Costs method
3. Production, Admin, Sales & Finance Costs method
Direct Cost is the cost which is directly related to a particular activity. In
converse way, it is the expenditure which can be avoided if the particular activity
is not undertaken. Eg. The raw material used for manufacturing an item. If a
particular item is not manufactured, the raw material and consequential cost of
raw material is saved/not spent. It is mostly on proportionate basis to the activity
level.
Indirect Cost is that cost which does not have one to one relation with the
activity. It is not directly related to activity. In other words it is the cost which has
to be incurred irrespective of activity progressing or not. Such costs normally
cover much wider range of activities like Administrative costs. These costs do not
have one to one relationship with activity level.
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 3 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Variable Costs are the costs which change in direct proportion with the
quantum of activity. In such cases there is direct fixed relation between quantum
of activity and the cost incurred. Eg. Fuel expenditure of your car which is
directly proportional to the usage of the car.
Fixed Costs are the costs which remain constant (subject to a pre-specified
maximum limit of activity, after which it will change) irrespective of the quantum
of activity. Eg. Depreciation cost of Machinery, Insurance and finance costs of
your vehicle which remain constant irrespective whether the machinery/vehicle is
run or not.
Semi Variable Costs are the costs which do change as the activity level changes
but the variation is not in direct proportion to the activity level variation. These
costs have a fixed component as well as a variable component. Eg. Hiring of a car
which has a fixed daily hiring charges and in addition, per kilometre running
charges applicable. Same is the case of mobile post paid charges. Rental charges
are fixed costs while per unit call charge is the variable cost.
Mathematical Model of Fixed and Variable Costs
Sl Item 2000 Units 5000 Units 3000 units Remarks
(a) Depreciation Rs 10000/- Rs 10000/- Rs 10000/- Fixed Cost
(b) Raw Material
@ Rs25/-per
unit
Rs 50000/- Rs 125000/- Rs 75000/- Variable Cost
(c) Advertisement Rs 20000/- Rs 26000/- Rs 22000/- Semi Variable
Fixed Compo Rs 16000/- Rs 16000/- Rs 16000/-
Variable Comp
@Rs2/-per unit
Rs 4000/- Rs 10000/- Rs 6000/-
In case of Fixed costs, unit rate is constant.
In case of Variable costs, amount is constant.
Example.
A factory can produce 15000 units per month. The following is their data
for Apr and May: -
Sl Item Apr (Units) May (Units)
(a) Total Production 9000 12000
(b) Direct Material Cost Rs 108000/- Rs 144000/-
(c) Direct Labour Cost Rs 81000/- Rs 108000/-
(d) Depreciation Rs 20000/- Rs 20000/-
(e) Production Overheads Rs 35000/- Rs 44000/-
(f) Admin Overhead Rs 15000/- Rs 16500/-
(g) Sales Overhead RS 30000/- Rs 36000/-
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 4 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
The factory is expecting to produce and sell 10000 units in Jun at a selling price to
earn a profit of 20% on the cost. Prepare a cost statement and selling price for Jun.
Cost Analysis Statement
Sl Item Apr May Jun
(a) Total Production 9000(Units) 12000(Units) 10000(Units)
(b) Direct Material Cost Rs 108000/- Rs 144000/- Rs 120000/-
(c) Direct Labour Cost Rs 81000/- Rs 108000/- Rs 90000/-
(d) Depreciation Rs 20000/- Rs 20000/- Rs 20000/-
(e) Production Overheads Rs 35000/- Rs 44000/- Rs 38000/-
Fixed cost Rs 8000/- Rs 8000/- Rs 8000/-
Variable Cost @ 3/- Rs 27000/- Rs 36000/- Rs 30000/-
(f) Admin Overhead Rs 15000/- Rs 16500/- Rs 15500/-
Fixed Cost Rs 10500/- Rs 10500/- Rs 10500/-
Variable Cost @0.50 Rs 4500/- Rs 6000/- Rs 5000/-
(g) Sales Overhead RS 30000/- Rs 36000/- Rs 32000/-
Fixed Cost Rs 12000/- Rs 12000/- Rs 12000/-
Variable Cost @2/- Rs 18000/- Rs 24000/- Rs 20000/-
Cost Statement for Jun
Sl Item Jun Unit Cost
(a) Total Production 10000(Units)
(b) Direct Material Cost Rs 120000/- Rs 12/-
(c) Direct Labour Cost Rs 90000/- Rs 9.00
(d) Depreciation Rs 20000/- Rs 2.00
(e) Production Overheads Rs 38000/- Rs 3.80
(f) Admin Overhead Rs 15500/- Rs 1.55
(g) Sales Overhead Rs 32000/- Rs 3.2
(h) Total Production Cost Rs 315500/- Rs31.55
(j) Profit 20% Rs63100/- Rs 6.31
(k) Selling Price Rs 37.86
Cost Sheet of a Product
1. Production Cost (a) Direct Cost (Also called Prime Cost)
(b) Indirect Cost (Also called Prodn
O/H)
includes indirect material, indirect labour,
power, fuel and depreciation on machinery
etc.
2. Admin Cost is also called Admin O/H.
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 5 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
3. Selling and Distribution Cost called Selling and Distribution O/H.
4. Financial Costs are called Financial O/H. (Not included in cost sheet as this cost
varies between project to project and it is difficult to arrive at a proper figure). But this cost is
fully adjusted/factored while calculating selling price of an article or service.
Purpose of Preparing a Cost Sheet.
1. To plan cost of a new product
2. To fix selling price
3. To control cost of an existing product
4. To find profitability of a product
Cost sheet is a profit and loss account of a product.
Principles of a Profit and Loss Account
1. Relate to a period (an account is applicable for a specified period only).
2. Relate to a product (for every individual and specific product)
3. Relate to a level of activity (Production rate).
While preparing Cost Sheet of a product, it is necessary to have opening stock of: -
(a) Raw Material
(b) Work in progress (ie, Stock of semi finished products)
(c) Finished products
Cost Sheet Model of a Product X
Period: _____________
Production = 1000 units Sale = 9500 units
Sl Item Total Per Unit
(a) Direct Material Cost
(i) Opening Raw Material stock xx
(ii) Add: Purchased during period xx
(iii) Less: Closing stock xx Xxxx x
(b) Direct Wages Xxxx x
1. Prime Cost Xxxx x
Production Overhead Xxxx
2. Factory Cost = production cost of the period Xxxx
Add: Opening WIP Stock Xxxx
Less: Closing WIP Stock Xxxx
3. Works Cost (Prodn
cost of finished product) Xxxx x
Admin O/H = Cost of production of 10000 Xxxx x
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 6 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
units`
Add: Opening finished goods stock Xxxx x
Less: Closing finished goods stock Xxxx x
4. Cost of Goods Sold – Xxxx
Selling O/H (Selling & Distribution Expenses) Xxxx x
5. Cost of Sales Xxxx x
Profit or Loss Xxxx x
6. Sales (Money realised through sales) Xxxx x
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 7 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Practice Problems – Cost Sheet
Q1. When the selling price of a product ‘P’ for the year 2003 was Rs 10/-, the total
sales were Rs 1,00,000/-. For the year 2004, the selling price has been increased by 10%.
The total sales are expected to increase by 21%.
For the year 2003, the materials cost was 40%, labour cost was 30% and total
overheads were 20% of sales.
For the year 2004, the material rates have increased by 10%, labour rates by 5%
and total overheads by Rs 3100/-
Prepare the cost sheet for the year 2003 and 2004 and find out the profitability.
Solution: -
COST SHEET 2003 2004
SL NO ITEM TOTAL PER UNIT INCREASE
PER UNIT TOTAL
Derived Information
Sales 100000 10 10% 11 121000
Units produced 10000 11000
(a) Material Cost Variable Cost 40000 4 10% 4.40 48400
(b) Labour Cost Variable Cost 30000 3 5% 3.15 34650
Prime Cost Variable Cost 70000 7 7.55 83050
(c) Over Heads Semi Variable 20000 2 ???? 2.1 23100
Cost of Sales 90000 9 9.65 106150
Selling Price 100000 10 11 121000
Profit 10000 1 1.35 14850
Q2. A Ltd company manufactures and sells electrical ovens. The selling price of the
same for the year 2003 was Rs 2500. For the year 2003, the material was 40%, labour
30% and total overheads were 30% of the cost of sales.
For the year 2004, the material rates have increased by 5 %, labour rates by 10%
but no change in overheads.
If the management fixes the same selling price of Rs 2500 for the year 2004, there
shall be a reduction in the profit of 2004 by 20% of such profits. The management wants
you to suggest such a price for 2004 so that same percentage of profit shall be
maintained.
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 8 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Sol: -
COST SHEET 2003 2004
SL NO ITEM % Rs % Rs
Material 40 800 42 840
Labour 30 600 33 660
Prime Cost 70 1400 75 1500
Overheads 30 600 30 600
Cost of Sales 100 2000 105 2100
Profits 25 500 25 525
Selling Price 125 2500 130 2625 (See comments on attached excel sheet for sequence of putting the figures in the table)
It is seen from above table that cost of sales in 2004 is 5% more than the cost of sales in
2003.
But it is given that if the selling price is kept same as 2003,
Selling price remaining same, increase in cost = Reduction in profits
That means 5% of the cost of sales = 20 % Profits.
ie Cost of sales = 4 x profits
But cost of sales + profit = selling price = 2500
Therefore 4x profits + profit = 2500
5 profits = 2500
Profit = 500
Cost of sales = 4 x 500 = 2000
Percentage of profits = 25%
Cost of sales in 2004 = 2100
Therefore Selling price for having same level of profit = 2625
Q3. X Ltd has a capacity to manufacture 25000 units per annum. For the year 2003,
they produced and sold 20000 units in domestic market and the data for same is as
under:-
Material Rs 600000
Labour Rs 360000
Production Overheads
(50% fixed)
Rs 200000
Adm Overheads
(50% variable)
Rs 50000
Sales Overhead
(75% variable)
Rs 100000
Cost of sales Rs 1310000
Profit Rs 190000
Sales Rs 1500000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 9 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Additional information is as follows: -
(a) For 2004, the domestic demand shall reduce by 10%, but the company is
expected to utilise 100% of capacity by exporting the units of balance
capacity.
(b) The rates of all the variable costs shall increase by 10% but the fixed costs
are not expected to change.
(c) The variable sales overheads rate for the export is expected to be 50% of
the similar rate for domestic sale.
(d) The company is expected to maintain same level of profit also for 2004.
(e) Prepare the cost sheet for 2004 and find out what selling price shall be
charged for exports if domestic selling price is not expected to change for
2004.
Sol: -
Prepare a work sheet as follows: -
ITEM TOTAL COST UNIT RATE
2003 2003 2004
CHANGE
Material 600000 30 10% 33
Labour 360000 18 10% 19.8
Production O/H
Fixed 100000 -- NIL 100000
Variable 100000 5 10% 5.50
Adm O/H
Fixed 25000 -- NIL 25000
Variable 25000 1.25 10% 1.375
Sales O/H
Fixed 25000 NIL 25000
Variable Domestic 75000 3.75 10% 4.125
Variable Export --- 2.062
Now Prepare a cost sheet
SL ITEM DOMESTIC
18000
EXPORT
7000
TOTAL
25000
1 Material 33 594000 33 231000 33 825000
2 Labour 19.8 356400 19.8 138600 19.8 495000
Prime Cost 52.8 950400 52.8 369600 52.8 1320000
Production O/H
Fixed 4 72000 4 28000 4 100000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 10 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Variable 5.5 99000 5.5 385000 5.5 137500
Works cost 62.3 1121400 62.3 4361000 62.3 1557500
Adm O/H
Fixed 1 18000 1 7000 1 25000
Variable 1.375 24750 1.375 9625 1.375 34375
Cost of Prodn 64.675 1164150 64.675 452725 64.675 1616895
Sales O/H
Fixed 1 18000 1 7000 1 25000
Variable 4.125 74250 2.062 14434 3.547 88684
Cost of sales 69.8 1256400 67.737 47415 69.222 1730559
Profit 5.2 93600 13.771 96400 190000
Sales 75 1350000 81.508 570559 1920559
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 11 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
MARGINAL COSTING
Marginal Costing is an important tool for decision making.
While arithmetically it is correct to say that if profit on one unit is Rs 10/- then profit on
100 units would be Rs 1000/-, in actual business environment, it is not so. The profit
earned on 100 units would rarely be arithmetic calculation of one unit in actual
conditions. It could be Rs 500 or Rs 2000.
Def. Marginal cost is the change in total cost for the change in activity by one unit.
In actual scenario, Marginal cost = Variable cost.
Therefore, Marginal Costing is a decision making technique by use of calculation of
marginal costs.
Marginal Cost Table (Very Very Important Table – Should be remembered
by heart)
Per Unit Total
Sales X XX
(-) Variable Cost X XX
Contribution X XX
(-) Fixed Costs X XX
Profits/Loss X XX
Per Unit Total
Sales 100 100000
(-) Variable Cost 60 60000
Contribution 40 40000
(-) Fixed Costs 30 30000
Profits/Loss 10 10000
Contribution = Difference in sales and variable cost at any level.
= Sales – variable cost
= Qty x (SP) – Qty (Variable cost per unit)
= Qty x (SP – variable cost per unit)
PV Ratio = Profit Volume Ratio
= Contribution/Sales
Note – Contribution and sales should always be taken for the same activity
level.
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 12 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
PV Ratio does not change due to change in
(a) Qty
(b) Fixed Costs
(c) Change in both in same proportion
PV Ratio changes when
(a) Selling Price is Changed (Total Sales Revenue is affected due to change in
SP. Thus denominator in the ratio changes)
(b) Variable Cost changes (Numerator changes due to change in Variable
cost)
(c) Change in both at differential proportion.
Break Even Point – The production level at which there is no profit or loss.
Contribution at BEP = Fixed Costs
Qty = Fixed cost/Contribution per unit
Qty = 30000/40 = 750 units
(Contribution)BEP = Fixed Costs
(Divide both sides by (Sales)BEP)
(Contribution)BEP = Fixed Costs
(Sales)BEP = (Sales)BEP
PV Ratio = Fixed Costs
(Sales)BEP
(Sales)BEP = Fixed Costs
PV Ratio
= 30000
0.4
= 75000
Margin of Safety = Actual level – BEP
= 1000 – 750
= 250 UNITS
Level does not mean only quantity. It could also mean sales
= 100000 – 75000
= 25000 (Sales Value)
Q1. X Ltd sells product P having SP of Rs 150 and variable cost/per unit of Rs 60. The
fixed cost for year 2004 is 3,60,000 and the total sales Rs 12 lakhs.
(a) Calculate
(i) PV Ratio
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 13 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
(ii) BEP (in Qty and Sales Value)
(iii) Margin of Safety
(iv) Profit at present level
(b) Calculate profit or loss if activity is 950 units
(c) Find out how the activity for
(i) How many units to be sold for a profit of Rs 90000
(ii) What would be the sales value
Sol: - (a)
Sales = 1200000/150 = 8000 Units
Fixed Cost per unit = 360000/8000 = 45
Contribution = SP – Variable Cost
= 150 – 60 = 90
Table Per Unit Total
Sales 150 1200000
(-) Variable cost 60 480000
Contribution 90 720000
(-) Fixed Costs 45 360000
Profits 45 360000
(i) PV Ratio = Contribution /Sales
= 90/150
= 0.60
(ii) BEP Contribution = Fixed Cost
(90 x BEP) = 360000
BEP = 360000/90
BEP = 4000 units
= 150x4000 = Rs 600000
(iii) Margin of Safety Actual Level – BEP
8000 – 4000 = 4000
1200000 – 600000 = 600000
(iv) Profit at present level Profit = (SP-Fixed Cost – Var Costs)x Qty
= (150 – 45 – 60) x 8000
= 45 x 8000
= 360000
(b) Profit or loss if activity is 950 units
Contribution per unit = 90
Total contribution = Contribution per unit x total units
90 x 950 = 85500
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 14 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Loss = Fixed cost – contribution
= 360000 – 85500= 274500
Profit or loss for sales of Rs 450000 Total Contribution = PV Ratio x Sales
= 0.60 x 450000
= 270000
Loss = Fixed cost – contribution
Loss = 360000 – 270000
= 90000
(c) (i) Activity for profit of Rs 90000
Total Contribution = Profit + Fixed Costs
= 90000 + 360000
= 450000
Contribution per unit = 90
Total contribution = No of units x contribution per unit
450000 = 90 x X
X = 5000
(ii) Contribution = Fixed Cost – Loss
= 360000 – 60000
= 300000
PV Ratio = Contribution / Sales
0.6 = 300000/X
X = 500000
Q. With above basic data, the management is expecting an increase of Rs 60000 in
fixed costs with the decrease in selling price by 20% and decrease in Variable cost/unit
by 10%. Calculate what would be change in profit/loss.
Sol: -
The new Selling Price = 150 – 20% = Rs 120
The new Variable Cost = 60 – 10% = Rs 54
New fixed cost = 360000 +60000 = 420000
Sales (unit SP) = 120
(-) Var Costs = 54
Contribution = 66 528000
(-) Fixed Costs= 420000
Profit (New) 108000
Profit (Old) 360000
Change in profit = 252000
New contribution per unit = New SP – New Variable Cost
= 150 – 54 = 66
No of units sold earlier = Earlier Sales/Earlier SP
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 15 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
= 1200000/150 = 8000
Total Contribution = 8000 x 66 = 528000
New profit = New contribution – New Fixed Cost
= 528000 – 420000
= 108000
Reduction in profit = Earlier profit – new profit
= 360000 – 108000
= 252000
Q. Under the new circumstances the management wants to achieve same sales value.
How much would be the effect on profits?
Sol. Sales Qty = Sales Value/SP per unit
= 1200000/120 = 10000 Units
Total Contribution = Contribution per unit x no of units
= 66 x 10000
= 660000
New Profit = New Contribution – New fixed costs
= 660000 – 420000
= 240000
Reduction in profits = Old Profit – New Profit
= 360000 – 240000
= 120000
Q. How much should be the sales level under the changed circumstances to earn the
same profit as before?
Desired Contribution = Desired Profit + New fixed cost
= 360000 + 420000
= 780000
Contribution per unit = 66
No of units = 780000/66
= 11819
Sales Value = No of units x SP
= 11810 x 120
= 1418280
Q. The following are the financial results of X Ltd for the years 2002 and 2003: -
2002 2003
Sales 20,00,000 25,00,000
Profits 5,00,000 6,50,000
The fixed costs for the year 2003 were higher than that for 2002 by 50000.
Calculate for both years
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 16 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
(a) PV Ratio
(b) Fixed Costs
(c) Break Even Point
(d) Margin of safety
Sol.
2002 2003 Change
Sales 20,00,000 25,00,000 5,00,000
- Variable Costs 12,00,000 15,00,000 3,00,000
= Contribution 8,00,000 10,00,000 2,00,000
- Fixed Costs 3,00,000 3,50,000 50,000
= Profit 5,00,000 6,50,000 1,50,000
(To solve this problem, CHANGE has to be calculated and work the figures from there since all the rules of
normal Marginal Costing table apply on change figures also. Data in “Blue colour, italics and bold” is
given in the problem.
Change in Contribution = Change in Fixed costs + Change in Profits
= 50,000 + 1,50,000 = 2,00,000
PV Ratio = Change in Contribution /Change in Sales
= 2,00,000/5,00,000 = 0.4
Contribution = PV Ratio X Sales
= 0.4 X 20,00,000 = 8,00,000 (2002)
= 0.4 X 25,00,000 = 10,00,000 (2003)
Fixed Costs = Contribution – Profits
= 8,00,000 – 5,00,000 = 3,00,000 (2002)
= 10,00,000 – 6,50,000 = 3,50,000 (2003)
Break Even Point = Fixed Costs/PV Ratio
= 3,00,000/0.4 = 7,50,000 (2002)
= 3,50,000/0.4 = 8,75,000 (2003)
Margin of Safety = Actual Level – BEP
= 20,00,000 – 7,50,000 = 12,50,000 (2002)
= 25,00,000 – 8,75,000 = 16,25,000 (2003)
Q. Can BEP be calculated without calculating the fixed costs?
Sol: - PV Ratio = Change in total contribution/Change in sales
Change in sales = Change in total Contribution/PV ratio
= Change in Profits/PV Ratio
20,00,000 – (Sales)BEP= (5,00,000 – 0)/0.4
= 12,50,000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 17 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
(Sales)BEP = 7,50,000
Q. X Ltd has planned the following performance for the year 2004: -
Production 20,000 units
Sales (In Lakhs) 25
Less cost of sales
Raw Mat 06
Labour 03
Production Exp 02
(40% fixed)
Admin Exp 02
(90% fixed)
Sales Exp 05 18
(40% variable)
Net Profit 07
The company achieved the planned results for the half year ending Jun 04. Due to Union
Budget in Jul 04, following changes are expected:-
(a) Raw Material rates shall increase by 10%.
(b) All variable costs except labour shall increase by 10%.
(c) All fixed costs shall increase by 20%.
(d) The company has production capacity of 25000 units pa.
Is it possible to maintain planned profitability for 2004 in the changed circumstances? If
so, at what level?
Profitability Statement
Variable Costs Fixed
Costs
PerUnit
Cost in
Rs
Total in Lakhs
Unit
(Rs)
Total in
Lakhs
Sales (20000 units) 30 6.0 125 25
Labour 15 3.0
Production 06 1.2 0.80
Admin Exp 09 1.8 0.20
Sales Exp 10 2.0 3.00
Total 70 14.0 4.00 70 14
Total 2nd
Half
Contribution 55 11 5.9
Fixed Cost 04 2.4
Profit 07 3.5
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 18 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
The planned profits for the year = Profit for 1st half + expected profits for 2
nd half
7 = 3.5 + (expected profits for 2nd
half)
Expected profits for 2nd
half = 7 – 3.5 = 3.5 lakhs
Expected Fixed Cost for 2nd
Half = 4/2 x 120% = 2.4 lakhs
Expected Contribution in 2nd
Half = Exp Profit + Fixed Costs
= 3.5 + 2.4 = 5.9 lakhs
Expected Contribution /unit =
Selling Price 125
-Variable Costs
Raw Material (30 + 3) 33
Labour 15
Other Expenses (25+2.5) 27.5 75.5
Contribution/unit 49.5
Expected activity for the second half of year
= Expected contribution/contribution per unit
= 5,90,000/49.5
= 11920 units
Since the production level required is only 11920 units which is less than balance
production capacity for the remaining half year ie 12500 units, it is feasible to achieve the
planned target.
Sales Value = 11920 x 125 = 14,90,000
Q. What would be minimum selling price that can be fixed for the 2nd
half year
to maintain the planned profits?
Sol. The minimum SP can be achieved when full capacity ie 12500 units is utilised.
The expected contribution = 5.9 lakhs as calculated above
Contribution per unit = 590000/12500
= 47.2
Variable cost as calculated earlier = 75.5
Selling price = 47.2 + 75.5 = 122.70
Q. The management wants to sell 10000 units in domestic market and export
balance capacity at a selling price lesser by 5% than domestic SP. To earn the same
profit what domestic price should be fixed?
Sol. The expected contribution = 5,90,000
Expected Variable Costs = 12500 x 75.5
= 9,43,750
Expected total sales = 15,33,750
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 19 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Equivalent Units of Sale
Units Wt Equi Units
Domestic 10000 1 10000
Export 2500 0.95 2375
Total 12375
Expected Domestic Selling Price = 15,33,750/12375
= 123.94
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 20 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
APPLICATIONS OF MARGINAL COSTING
There are four major applications of Marginal Costing in Management:
1. Priority for profit maximisation
(a) Under normal circumstances
(b) Under key factor
2. Export Pricing
3. Manufacture Vs Outsource (Make Vs Buy) decision
4. Shutdown point of a factory
PRODUCT A B C D E
Material Cost 10 12 15 8 6
Labour Cost 8 6 8 4 6
Variable Cost 4 4 6 3 2
Fixed Overheads 5 4 6 2 3
Total Cost 27 26 35 17 17
Profit 4 4.5 2 3.5 4.6
Selling Price 31 30.5 37 20.5 21.6
Priority by Company III II V IV I
Contribution 9 8.5 8 5.5 7.6
Priority by Me I II III V IV
The above priority assessment is when there are no constraints of material, labour, market
etc.
To maximise the profit, fixed costs remaining constant, the product which facilitates
maximum contribution per unit should be given priority.
Now suppose that material cost is Rs 5/- Kg and labour cost is Rs 2 per hour.
PRODUCT A B C D E
Material Cost (Rs 5/- per Kg) 10 12 15 8 6
Labour Cost (Rs 2/- per Hr) 8 6 8 4 6
Variable Cost 4 4 6 3 2
Fixed Overheads 5 4 6 2 2
Total Cost 27 26 35 17 17
Profit 4 4.5 2 3.5 4.5
Selling Price 31 30.5 37 20.5 21.6
Contribution per unit 9 8.5 8 5.5 7.6
Consumption - Kg/unit 2 2.4 3 1.6 1.2
Contribution per Kg 4.5 3.54 2.67 3.43 6.33
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 21 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Priority per material limitation II III V IV I
Consumption - Hours per unit 4 3 4 2 3
Contribution per Hr 2.25 2.83 2 2.75 2.53
Priority with Lab constraints IV I V II III
Export Pricing
Product P Cost/Unit Export
Raw Material 50 40 (20% Excise duty concession)
Labour 35 35
Total O/H 20 12 (Only variable taken into a/c)
(60% Var) 3 (Special packing cost)
Total Cost 105 90
Domestic Profit 20 (-) 8 (Rebate against FE earnings)
Selling Price 125 82 (Minimum Export Price – without
any profit)
Min Export Price = Additional Cost (Variable Cost) – Incentives for Export
Make Vs Buy Decision
COMPONENT P Q R S T
Material Cost 6 3 2 5 4
Labour Cost 4 3 4 1 3
Variable O/H 2 2 1 3 2
Fixed Overheads 3 2 2 3 1
Total Cost 15 10 9 12 10
Mkt Price 16 7 8 10 12
Savings - 1 3 1 2 - 2
Buy/ Manufacture (Co Decision) M B B B M
Var Cost 12 8 7 9 9
Mkt Price 16 7 8 10 12
SAVINGS - 4 1 - 1 - 1 - 3
Decision Make Buy Make Make Make (Since Fixed Overheads are sunk cost and will have to be incurred even when purchasing from outside,
they are added to the procurement cost from outside for Make or Buy decision. Thus, products R and S
which appeared to be profitable when outsourced from market, turn out to be loss making proposition).
Other Considerations regarding buy/manufacture decisions:
1. Price Stability in market
2. Quality assurance of supplier
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 22 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
3. Criticality of component
4. Loss of contacts with existing suppliers of raw material etc.
5. Assurance regarding timely supply of component.
Shut Down Point.
Sales 20,00,000
Var Cost 10,00,000
Contribution 10,00,000
Fixed Cost 15,00,000
Loss 5,00,000
If the factory is closed down, 50% of the fixed costs can be saved. Whether factory
should be closed?
If the factory is not closed, the loss is Rs 5 lakhs as shown above. If the factory is
closed:
Sales 0
Contribution 0
Fixed Cost 7,50,000 (50% of costs of Rs 15 lakhs)
Loss 7,50,000
Therefore, it is better to continue operations.
Shut Down point is that point at which the loss if continued is equal to loss if
discontinued.
Sales 15.0
- Var cost 7.5 (50% of Sales – Calculated from given figures)
Contribution 7.5 (Calculated )
- Fixed Cost 15.0 (When operational - Given)
Loss 7.5 (if discontinued - Given)
If the factory is continuing, the expected loss is 7.5 lakhs at shut down point.
The fixed cost if continued = 15 lakhs
Contribution at Shut down point = Fixed cost – loss
= 7.5 lakhs
PV Ratio = Sales
onContributi
= 10,00,000
20,00,000
= 0.5
Therefore, Sales at Shut Down Point = Contribution at SD Point
PV Ratio
= 7.5
0.5
= 15 lakhs
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 23 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
STANDARD COSTING
Standard Costing is setting of the standard and comparison of the actual with the
standards for the purpose of control. It involves taking the remedial measures for the
variances or to set or revise the obsolete standards.
Calculation of variances
Variable Cost Related Fixed Cost Related
1. Raw Material 1. Fixed Overhead
2. Labour
3. Variable Overhead
Raw Material Cost Variances
Raw Material Price Variance Raw Material Usage Variance
The methodology used for calculating the Raw Material Variances is also used for
calculating the Labour and Variable Overhead variances.
Q. Calculate Raw Material variances:
Standard 1000 units of finished product
2000 Kg of Raw Material @ Rs 15/Kg Rs 30000/-
Actual 8500 Units of finished goods
16800 Kg of Raw Material @ 15.50/Kg Rs 260400/-
Sol.
1. Raw Material Cost Variance = (Actual RM Cost – RM cost for actual production
at Standard Rates)
= 260400- 8500x30
= 5400 (Adverse Variance denoted as ‘A’)
2. RM Price Variance = Actual Qty (Actual Price – Standard Price)
= 16800 (15.5 – 15)
= 8400 (A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 24 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
3. RM Usage Variance = Standard Price (Actual Qty – Standard Qty for actual
production)
= 15 (16800 – 8500x02)
= 15 (16800 – 17000)
= 3000 (Favourable Variance denoted as ‘F’)
Q. Calculate RM, Labour and Variable Overhead Variances
Standard for 100 Units of Finished Goods
RMs 1500 Kgs @ Rs 3/- = Rs 4500/-
Labour 600 Hrs @ Rs 4/- = Rs 2400/-
Variable Overhead 600 Hrs @ Rs 1.50= Rs 900/-
Total Variable Cost for Standard 100 Units = Rs 7800/-
Actual for 2500 Units of Finished goods
RMs 37250 Kgs @ Rs 3.10 = Rs 115475/-
Labour 15260 Hrs @ Rs 4.15 = Rs 63329/-
Variable Overhead 15260 Hrs @ Rs 1.40 = Rs 21364/-
Total Variable Cost for Actual production = Rs 200168/-
Sol.
Raw Material Cost Variance = (Actual RM Cost – RM cost for actual production
at Standard rates)
= (115475 – 2500x15)
= 2975 (F)
Raw Material Rate Variance= Actual Quantity (Actual Rate – Standard Rate)
= 37250 (3.1 –3.0)
= 3725 (A)
Raw Material Usage Variance = Standard Rate (Actual RM Usage – Standard
usage for actual production)
= 3.0 (37250 – 2500 x 15)
= 750 (F)
Labour Cost Variance = (Labour Cost for Actual Production – Labour
cost for actual production at standard rates)
= (63329 – 2500 x 6 x 4)
= 3329 (A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 25 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Labour Efficiency Variance = Standard Labour Rate (Actual hrs – Standard Hrs
for actual production)
= 4 (15260 – 2500 x 6)
= 1140 (A)
Labour Rate Variance = Actual Hours (Actual Rate – Standard Rate)
= 15260 (4.15 – 4)
= 2289 (A)
Variable overhead Variance = Actual Variable Overheads – Overheads for
actual production at standard rates)
= (21364 – 2500 x 6 x 1.5)
= 1136 (F)
Variable Overhead Rate Variance = Actual Hrs (Actual Rate – Standard Rate)
= 15260 (1.5 – 1.4)
= 1526 (F)
Variable Overhead Efficiency Variance = Standard Rate (Actual Overhead Hours –
Hrs required at Standard Rate for Actual Production)
= 1.5 (15260 – 15000)
= 1.5 (260)
= 390 (A)
Statement of Variances
Material Cost Variance Rs 2975/- (A)
Material Price Variance Rs 3725/- (A)
Material Usage Variance Rs 750/- (F)
Labour Cost Variance Rs 3329/- (A)
Labour Rate Variance Rs 2289/- (A)
Labour Efficiency Variance Rs 1040/- (A)
Variable Overhead Cost Variance Rs 1136/- (F)
Variable Overhead Rate Variance Rs 1126/- (F)
Variable Overhead Eff. Variance Rs 390/- (A)
(Please note that in all cases, where Rate/price is outside the brackets, it is always
STANDARD)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 26 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Q. Calculate Material, Labour and Variable Overhead Variances from the following
data:
Standard for 10000 units
Raw Material 15000 Kgs @ Rs 9/Kg Rs 135000/-
Labour 30000 Hrs @ Rs 3/Hr Rs 9000/-
Variable Overhead 30000 Hrs @ Rs 1.8/Hr Rs 54000/-
Actuals for 9000 Units
Raw Material 13500 Kg @ Rs 8.75/Kg Rs 118125/-
Labour 27260 Hrs @ Rs 3.10/Hr Rs 84506/-
Variable Overhead 27260 Hrs @ Rs 1.75/Hr Rs 47705/-
Sol.
Material Cost Variance = (Actual cost – Cost at Standard Rates for actual production)
= (118125 – 1.5 x 9 x 9000)
= 3375 (F)
Material Rate Variance = Actual Mat consumed (Actual Rate – Standard Rate)
= 13500 (9 – 8.75)
= 3375 (F)
Material Usage Variance = Standard Rate (Actual Mat consumed– Standard
material for actual production)
= 1.80 (13500 – 13500)
= 000
Labour Cost Variance = Actual Cost – Cost at Standard Rate for actual production
= 84506 – 9000 x 3 x 3
= 3506 (A)
Labour Rate Variance = Actual hrs (Actual Rate – Standard Rates)
= 27260 (3.10 – 3)
= 2726 (A)
Labour Eff. Variance = Standard Rate (Actual Hrs – Standard hrs for actual
production)
= 3 (27260 – 9000 x 3)
= 3 x 260 = 780 (A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 27 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Variable Overhead Variance= Actual Overhead – Overhead at Standard Rate for actual
production
= 47705 – 9000 x 3 x 1.8
= 47705 – 48600
= 895 (F)
Variable Overhead Rate Variance = Actual Hrs (Actual Rate – Standard Rate)
= 27260 (1.75 – 1.8)
= 1363
Variable Overhead Eff Variance = Standard Rate (Actual Hrs – Standard Hrs for
actual production)
= 1.8 (27260 – 9000 x 3)
= 1.8 (260) = 468 (A)
Statement of Variances
Material Cost Variance Rs 3375/- (A)
Material Price Variance Rs 3375/- (A)
Material Usage Variance Rs 000/- (-)
Labour Cost Variance Rs 3506/- (A)
Labour Rate Variance Rs 2726/- (A)
Labour Efficiency Variance Rs 780/- (A)
Variable Overhead Cost Variance Rs 895/- (F)
Variable Overhead Rate Variance Rs 1363/- (F)
Variable Overhead Eff. Variance Rs 468/- (A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 28 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
FIXED OVERHEAD VARIANCES
Fixed Overhead Cost Variance
Fixed Overhead Expenditure Variance Fixed Overhead Volume Variance
Calendar Variance Capacity Variance Efficiency Variance
Example 1:
Calculate Fixed Overhead Variances from the following details: -
Standard Rs
Fixed Overhead 2,00,000
Production (Units) 50,000
Hrs 1,00,000
Days 25
Actual
Fixed Overhead 2,08,000
Production (Units) 51,200
Hrs 1,02,500
Days 26
Solution
Working Notes
(Standard)
Fixed Overhead per unit = 200000/50000 = Rs 4/-
Fixed Overhead per hr = 200000/100000 = Rs 2/-
Fixed Overhead per day = 200000/25 = Rs 8000/-
Hrs available per day = 100000/25 = 4000
No of Hrs per unit = 100000/50000 = 2
1. Fixed Overhead Cost Variance
= Actual Overhead Expenditure – Fixed overheads recovered
= 2,08,000 – 51200x4
= 208000 – 204800 = 3200 (A)
2. Fixed Overhead Expenditure Variance
= Actual Overhead Expenditure – Standard Overhead Expenditure
= 208000 – 200000 = 8000 (A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 29 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
3. Fixed Overhead Volume Variance
= Fixed Overhead Recovered – Standard Fixed Overhead
= 51200 x 4 – 200000
= 204800 – 200000
= 4800 (F)
3(a) Fixed Overhead Calendar Variance
= Standard Fixed Overhead per day (Actual Days – Standard Days)
= 8000 (26 –25)
= 8000 (F)
3(b) Fixed Overhead Capacity Variance
= Standard Fixed Overhead per hr (Capacity Available – Capacity
Utilised)
= Standard Fixed Overhead per hr (No of days worked x hrs per day –
Actual hrs utilised)
= 2 (26 x 4000 – 102500)
= 2 (104000 – 102500)
= 2 (1500)
= 3000 (A)
3(c) Fixed Overhead Efficiency Variance
= Standard Fixed Overhead per hr (Hrs actually taken – Standard Hrs for
actual production)
= 2 (102500 – 2x51200)
= 2 (102500 – 102400)
= 2 (100)
= 200 (A)
Fixed Overhead Cost Variance 3200 (A)
Fixed Overhead Expenditure Variance 8000 (A)
Fixed Overhead Volume Variance 4800 (F)
Fixed Overhead Calendar Variance 8000 (F)
Fixed Overhead Capacity Variance 3000 (A)
Fixed Overhead Efficiency Variance 200 (A)
Example 2:
Calculate Fixed Overhead Variances from the following details: -
Standard Rs
Fixed Overhead 5,00,000
Production (Units) 2,50,000
Hrs 4,00,000
Days 25
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 30 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Actual
Fixed Overhead 4,97,000
Production (Units) 2,46,800
Hrs 3,96,500
Days 24
Solution
Working Notes
Fixed Overhead per unit = 500000/250000 = Rs 2/-
Fixed Overhead per hr = 200000/100000 = Rs 1.25
Fixed Overhead per day = 500000/25 = Rs 20,000/-
Hrs available per day = 400000/25 = 16,000
No of Hrs per unit = 400000/250000 = 1.6
1. Fixed Overhead Cost Variance
= Actual Overhead Expenditure – Fixed Overheads recovered
= 4,97,500 – 2,46,800 x 2
= 4,97,500 – 4,93,600 = 3,900 (A)
2. Fixed Overhead Expenditure Variance
= Actual Overhead Expenditure – Standard Overhead Expenditure
= 4,97,500– 5,00,000 = 2,500 (F)
3. Fixed Overhead Volume Variance
= Fixed Overhead Recovered – Standard Fixed Overhead
= 246800x2– 500000
= 493600 – 500000
= 6400 (A)
3(a) Fixed Overhead Calendar Variance
= Standard Fixed Overhead per day (Actual Days – Standard Days)
= 20000 (25 –24)
= 20000 (A)
3(b) Fixed Overhead Capacity Variance
= Standard Fixed Overhead per hr (Capacity Available – Capacity
Utilised)
= Standard Fixed Overhead per hr (No of days worked x hrs per day –
Actual Hrs Utilised)
= 1.25 (24 x 16000 – 396000)
= 1.25 (384000– 396000)
= 1.25 (12000)
= 15000 (F)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 31 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
3(c) Fixed Overhead Efficiency Variance
= Standard Fixed Overhead per hr (Hrs actually taken – Standard Hrs for
actual production)
= 1.25 (396000 – 1.6x246800)
= 1.25 (396000–394880)
= 1.25 (1120)
= 1400 (A)
Fixed Overhead Cost Variance 3900 (A)
Fixed Overhead Expenditure Variance 2500 (F)
Fixed Overhead Volume Variance 6400 (A)
Fixed Overhead Calendar Variance 20000 (A)
Fixed Overhead Capacity Variance 15000 (F)
Fixed Overhead Efficiency Variance 1400 (A)
Example 3:
Calculate Fixed Overhead Variances from the following details: -
Standard Rs
Fixed Overhead 5,60,000
Production (Units) 14,000
Hrs 70,000
Days 28
Actual
Fixed Overhead 6,12,000
Production (Units) 14,900
Hrs 75,000
Days 29
Solution
Working Notes
Fixed Overhead per unit = 560000/14000 = Rs 40/-
Fixed Overhead per hr = 560000/70000 = Rs 8/-
Fixed Overhead per day = 560000/28 = Rs 20000/-
Hrs available per day = 70000/28 = 2500
No of Hrs per unit = 70000/14000 = 5
1. Fixed Overhead Cost Variance
= Actual Overhead Expenditure – Fixed Overheads recovered
= 612000 – 14900 x 40
= 612000– 596000 = 16000(A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 32 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
2. Fixed Overhead Expenditure Variance
= Actual Overhead Expenditure – Standard Overhead Expenditure
= 612000 – 5,60,000= 52000 (A)
3. Fixed Overhead Volume Variance
= Fixed Overhead Recovered – Standard Fixed Overhead
= 14900 x 40 – 560000
= 596000 – 560000
= 36000 (F)
3(a) Fixed Overhead Calendar Variance
= Standard Fixed Overhead per day (Actual Days – Standard Days)
= 20000 (29 –28)
= 20000 (F)
3(b) Fixed Overhead Capacity Variance
= Standard Fixed Overhead per hr (Capacity Available – Capacity
Utilised)
= Standard Fixed Overhead per hr (No of days worked x hrs per day –
Actual Hrs Utilised)
= 8 (29 x 2500 – 396000)
= 8 (72500 – 75000)
= 8 (2500)
= 20000 (F)
3(c) Fixed Overhead Efficiency Variance
= Standard Fixed Overhead per hr (Hrs actually taken – Standard Hrs for
actual production)
= 8 (75000 – 5x14900)
= 8 (75000–74500)
= 8 (500)
= 4000 (A)
Fixed Overhead Cost Variance 16000(A)
Fixed Overhead Expenditure Variance 52000 (A)
Fixed Overhead Volume Variance 36000 (F)
Fixed Overhead Calendar Variance 20000 (F)
Fixed Overhead Capacity Variance 20000 (F)
Fixed Overhead Efficiency Variance 4000 (A)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 33 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
PROCESS COSTING
Cost Pursuit in a particular process
Further step to cost sheet
Conditions: -
1. The whole process should be distinguishable into various identifiable processes
2. The output of earlier process is input for the next process.
3. Various processes are to be conducted in a particular sequence.
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT To material @ Rs 10 1000 10000
To wages 6000 By Transfer to Process - II @ Rs 20
1000 20000
To Manufacturing Expenses
4000
Total 1000 20000 1000 20000
Process Loss
Loss in weight Scrap
(No realisable Value) (There is realisable value)
Material Scrap Defective Goods
Abnormal Loss Normal Loss Abnormal Gain
(Output = 930 units) Eg 5% inputs Output = 955 units
950-930 = 20 Units Input = 1000 955-950= 5 units
(Loss beyond 5% = 50 units (Output beyond normal output)
normal loss) Normal Output
950 units
Normal Loss
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To material @ Rs 10 1000 10000 By Normal Loss – (5% of 1000 units at
50 500
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 34 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Re 1)
To wages 6000 By Transfer to Process - II @ Rs 21
950 19500
To Manufacturing Expenses
4000
Total 1000 20000 1000 20000
Abnormal Loss
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To material @ Rs 10 1000 10000 By Normal Loss – (5% of 1000 units at Re 10)
50 500
By Abnormal Loss @ Rs 21 (20000/950)
20 420
To wages 6000 By Transfer to Process - II @ Rs 21
930 19080
To Manufacturing Expenses
4000
Total 1000 20000 1000 20000
Abnormal Loss A/c
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To process - I A/c 20 420 By Scrap Value 20 20
By Profit and Loss A/c
400
Total 20 420 20 420
Abnormal Gain
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To material @ Rs 10 1000 10000 By Normal Loss – (5% of 1000 units at Re 10)
50 500
To wages 6000 By Transfer to Process - II @ Rs 21
955 19605
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 35 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
To abnormal gain @ Rs 21
5 105
To Manufacturing Expenses
4000
Total 1005 20105 1005 20105
Abnormal Gain A/c
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To Scrap Value @Re 1
5 5 By Process I 5 105
To Profit and Loss A/c
100
Total 105 5 105
Example 1. Product P is manufactured by sequential process I, II, III. From the
following information, prepare process I, II, and III A/cs and abnormal loss/gain A/c.
ITEM PROCESS - I PROCESS - II PROCESS - III
Misc material 8000 10000 3000
Wages 25000 18000 20000
Mfg Expenditure 15000 12000 10000
Normal Loss (% of Input 5% 8% 6%
Scrap Value of Normal Loss Rs 8/unit - Rs 12/unit
Actual output 925 850 805
1000 units were introduced to process I @ Rs 40 per unit.
Solution.
Working Notes - Process I A/c
1. Normal Quantity = Input – Normal Loss
= 1000 – 50 = 950 units
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 88000 – 400 = 87600
3. Cost/unit = Net Cost /Normal Quantity
= 87600/950 = 92.21
4. Abnormal Loss = Normal Qty – Actual Qty
= 950 – 925 = 25 units
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 36 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Process I A/c
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 40
1000 40000 By Normal Loss – (5% of 1000 units at Rs 8)
50 400
To Misc Material 8000 By Abnormal Loss @ Rs 92.21
25 2305
To wages 25000 By Transfer to Process - II @ Rs 92.21
925 85295
To Manufacturing Expenses
15000
Total 1000 88000 1000 88000
Working Notes - Process II A/c
1. Normal Quantity = Input – Normal Loss
= 925 – 74 = 851 units
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 125295– 0 = 125295
3. Cost/unit = Net Cost /Normal Quantity
= 125295/851 = 147.23
4. Abnormal Loss = Normal Qty – Actual Qty
= 851 – 850 = 1 unit
Process II A/c
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units Transferred from process I @ Rs 92.21
925 85295 By abnormal Loss – (8% of 925 units)
74 0
To Misc Material 10000 By Abnormal Loss @ Rs 147.23
1 147
To wages 18000 By Transfer to Process - III @ Rs 147.23
850 125148
To Manufacturing Expenses
12000
Total 925 125295 925 125295
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 37 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Working Notes - Process III A/c
1. Normal Quantity = Input – Normal Loss
= 850 – 51 = 799 units
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 158148 – 612 = 157536
3. Cost/unit = Net Cost /Normal Quantity
= 157536/799 = 197.17
4. Abnormal gain = Normal Qty – Actual Qty
= 799 – 805 = 06 units
Process III Account
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units Transferred to Process - III @ Rs 147.23
850 125148 By normal Loss @ Rs 12/- for 6% of 850 units
51 612
To Misc Material 3000 By Transfer to finished goods @ 197.17
805 158719
To wages 20000
To Mfg Expenses 10000
To abnormal gain @ 197.17
6 1183
Total 856 159331 856 159331
Abnormal Loss A/c
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To process I A/c 25 2305 By scrap value @ Rs 8/-
25 200
To process II A/c 1 147 By scrap value 1 NIL
By Profit & Loss A/c 2252
Total 26 2452 26 2452
Abnormal Gain A/c
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To Scrap Value Process I A/c @ Rs 12
6 72 By Process III A/c 6 1183
To Profit and Loss A/c
1 1111
Total 6 1183 6 1183
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 38 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Example 2. Product P is manufactured by sequential processes X, Y, Z. From the
following information, prepare process X, Y, and Z accounts and abnormal loss/gain
account.
ITEM PROCESS - I PROCESS - II PROCESS - III
Misc material 6000 5000 2000
Wages 12000 15000 10000
Mfg Expenditure % of wages 50% 80% 30%
Normal Loss (% of Input 10% 8% 5%
Scrap Value of Normal Loss 10% 15% 20%
Actual output 925 840 800
1000 units were introduced to process X @ Rs 20 per unit.
Example 1. A Ltd Co manufactures three chemicals X, Y and Z. Chemical X is
manufactured by process I, Chemical Y by processes I & II and chemical Z by process I,
II and III. The company sells part of output of each process in market at a profit of 10%
above cost. From the following details prepare process accounts I, II and III.
ITEM PROCESS - I PROCESS - II PROCESS - III
Input material (Kg) 10000 600 3000
Rate per Kg Rs 15 30 25
Wages 38000 21000 26000
Mfg Expenditure 13000 10000 8000
Output (Kg) 9600 6800 3750
Qty Sold 1/3rd
3800 3750
Qty Transferred to next Process
2/3rd
3000 000
The loss of input has no realisable value.
*** (Unless abnormal loss or gain is given, normal situation is assumed.)
Solution.
Working Notes - Process A/c I
1. Output = 9600 Kg
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 201000 – Zero = 201000
3. Cost/unit = Net Cost /Output
= 201000 / 9600 = 20.94
4. Selling Price = Cost + Profit
= 20.94 + 2.09 = 23.03
5. Qty Sold = 1/3 x 9600 = 3200
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 39 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
6. Qty Transferred = 2/3 x 9600 = 6400
Process A/c I
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 15
10000 150000 By Loss in Wt (10000 - 9600)
400 000
To wages 38000 By Sales @ 23.03 3200 73696
To Manufacturing Expenses
13000 By Transfer to
process II @ Rs
20.94
6400 134016
To Profit and loss A/c (3200 x 2.09)
6712
Total 10000 207712 10000 207712
Working Notes - Process A/c II
1. Output = 6800 Kg
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 183016 – Zero = 183016
3. Cost/unit = Net Cost /Output
= 183016 / 6800 = 26.91
4. Selling Price = Cost + Profit
= 26.91+ 2.69 = 29.6
5. Qty Sold = 3800
6. Qty Transferred = 3000
Process A/c II
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 30
600 18000 By Loss in Wt (7000 - 6800)
200 000
To units introduced from Process I
6400 134016
To wages 21000 By Sales @ 29.60 3800 112480
To Manufacturing Expenses
10000 By Transfer to
process III @ Rs
3000 80730
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 40 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
26.91
To Profit and loss A/c (3200 x 2.69)
10194
Total 7000 193210 7000 193210
Working Notes - Process A/c III
1. Output = 3750 Kg
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 183016 – Zero = 183016
3. Cost/unit = Net Cost /Output
= 183016 / 3750 = 48.8
4. Selling Price = Cost + Profit
= 48.8 + 4.88 = 53.68
5. Qty Sold = 3750
6. Qty Transferred = 000
Process A/c III
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 25
1000 25000 By Loss in Wt (4000 - 3750)
250 000
To units introduced from process II
3000 80730
To wages 26000 By Sales @ 53.68 3750 201316.5
To Manufacturing Expenses
8000
To Profit and loss A/c (3200 x 2.09)
61586
Total 4000 201316.5 4000 201316.5
Example 2. A Ltd Co manufactures three minerals P, Q and R. Mineral P is
manufactured by process I, Mineral Q by process I & II and mineral R by process I, II
and III. The company sells part of output of each process in market at specified selling
prices. From the following details prepare process accounts I, II and III.
ITEM PROCESS - I PROCESS - II PROCESS - III
Input material (Kg) 8000 200 300
Rate per Kg 50 70 100
Wages 125000 83000 51000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 41 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Mfg Expenditure 42000 21000 15000
Loss (% of input) 10% 12% 8%
Qty Sold (Kg) 1/3 1/2 100
Qty Transferred to next Process
2/3rd
1/2 000
Selling Price 80 120 150
The loss out of process I is sold @ Rs 15, Process II @ Rs 20 and Process III @ Rs 25.
Solution.
Working Notes - Process A/c I
1. Output = 8000 – 10% = 7200
2. Loss = 800 Kg
3. Net Cost = Input Cost – Scrap Value of Normal Loss
= 567000 – 12000 = 555000
4. Cost/unit = Net Cost /Output
= 555000 / 7200 = 77.08
5. Selling Price = 80
6. Qty Sold = 1/3 x 7200 = 2400
7. Qty Transferred = 2/3 x 9600 = 4800
Process A/c I
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 50
8,000 4,00,000 By sale of scrap of Normal Loss (10%) @ Rs 15
800 12,000
To wages 1,25,000 By part production sales @ Rs 80.
2,400 1,92,000
To Manufacturing Expenses
4,200 By Transfer to process II @ Rs 77.08
4,800 3,69,984
To Profit and loss A/c (2400 x 2.92)
6,984
Total 8,000 5,73,984 8,000 5,73,984
Working Notes - Process A/c II
1. Output = 5000 – 12% = 4400
2. Net Cost = Input Cost – Scrap Value of Normal Loss
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 42 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
= 487984 – 12000 = 475984
3. Loss = 600
4. Cost/unit = Net Cost /Output
= 475984 / 72000 = 77.08
5. Selling Price = 125
6. Qty Sold = 2200
7. Qty Transferred = 2200
Process A/c II
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 70
200 14000 By sale of scrap of Normal Loss (12%) @ Rs 20
600 12000
To units introduced from Process I
4800 369984
To wages 83000 By part production sales @ 125
2200 275000
To Manufacturing Expenses
21000 By Transfer to process III @ Rs 108.18
2200 237996
To Profit and loss A/c (2200 x 16.82)
37012
Total 5000 524996 5000 524996
Working Notes - Process A/c III
1. Output = 2500 – 8% = 2300 Kg
2. Net Cost = Input Cost – Scrap Value of Normal Loss
= 333996 – 5000 = 328996
3. Loss = 200
4. Cost/unit = Net Cost /Output
= 328996/ 2300 = 143.04
5. Selling Price = 150
6. Qty Sold = 2300
Process A/c III
DR CR
INPUT UNITS AMOUNT OUTPUT UNITS AMOUNT
To units introduced @ Rs 100
300 30000 By sale of scrap of Normal Loss (8%) @ Rs 25
200 5000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 43 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
To units introduced from Process II
2200 237996
To wages 51000 By Sales @ 150 2300 345000
To Manufacturing Expenses
15000
To Profit and loss A/c (2300 x 6.96)
16004
Total 2500 350000 2500 350000
Process Profit Statement Process – I = Rs 6964
Process – II = Rs 37012
Process – III = Rs 16004
Rs 60000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 44 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
CONTRACT COSTING
Contract Costing. This method is followed in case of construction contracts to find
the profitability of the each construction job. It is related to a particular site.
Contract Account of Site X (Profit and Loss A/c)
Dr Cr
Expenditure
To opening Material Stock
To opening uncertified work
To material sent to site
To wages
To depreciation on eqpt
To supervision charges
To notional profit
To (profit and loss A/c)
To Closing reserve for contingencies
Income By opening reserve for contingencies
By work certified
By uncertified work
By materials returned
By closing stock
By net loss
By Notional Profit
Expenditure – Direct
1. Materials – Sand, Cement, Bricks, Steel, Water, Wooden Blocks, etc
2. Labour
3. Equipment – Depreciation
Expenditure – Indirect
1. Supervision Charges
Case Study- Suppose a project was started on 01 Jan 04. Since the money is paid in
case of construction contracts for part job completed (although some money out of the
total due is always retained by the person giving contract (contractee) to have some
leverage on the contractor so that he does not leave the contract mid way and run away,
running bills are submitted for payment according to the percentage of the work
completed. Veracity of all such claims of the work completion are usually assessed by a
third party who certifies the amount of work completed and his decision is binding on
both the parties. The payment is made at a pre agreed rate for the percentage of work
certified as completed.
Income statement of the Project
From – to Work Done Claim Certification Date
1st Running Bill 01-01-04 1,00,000 02.02.04
31-01-04
- 10% Retention Money 10,000
90,000 Cash Paid
2nd
Running Bill 01.02.04 1,80,000 (Addl 80,000) 3.3.04
29.02.04
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 45 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
- 10% Retention Money 18,000 (Addl 8,000)
1,62,000 Payment entitled
-90,000 (Paid Last Month)
Cash to pay 72,000
3rd
Running Bill 01.03.04 2,50,000 (Addl 70,000) 4.4.04
31.03.04 (Cost = 58,000)
By Principle of conservatism, loss is never carried forward. However, profit is carried
forward and it is called NOTIONAL PROFIT.
Contract Account
Notional Profit (Depends on Stage of Completion) Loss
(To be written off )
Net Profit Reserve for contingency
Stage of Completion
Contract Value - Rs 10 Lac
Work Completed Cum Work SOC
1st Year 3,00,000 3,00,000 30%
2nd
Year 5,00,000 8,00,000 80%
3rd
Year 2,00,000 10,00,000 100%
SOC = Cumulative Work Certified
Total Contract Value
Empirical Rule for Notional Profit Sharing
Stage of Completion Formula for Profit Sharing
Less than 25% Nil
From 25% to less than 50% 1/3 x Notional Profit x %Cash Received
Work Certified
.
From 50% to less than 90% 2/3 x Notional Profit x %Cash Received
Work Certified
.
From 90% to less than 100% Notional Profit x Cumulative Work Certified
Total contract value
.
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 46 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
100% Completed Notional Profit
As the stage of completion increases, more and more notional profit is accrued to the
profit.
Question. X Ltd commenced construction job on 01.07.01 for a total value of Rs 25
Lac to be completed within 3 years. The contract was completed on 31.12.03. From the
following details, prepare contract A/c for the years ended 31 Mar 02, 31 Mar 03 and
31 Mar 2004 and show relevant items in the company balance sheet on these dates.
Item 31.3.02 31.3.03 31.3.04
Work Certified 7,00,000 10,00,000 8,00,000
Closing Uncertified Work 45,000 59,000 000
Material Sent to site 2,45,000 4,31,000 3,15,000
Material returned form site 12,000 14,000 10,000
Closing Stock of material 21,000 25,000 000
Wages paid 1,83,000 3,49,000 2,75,000
Closing outstanding wages 17,000 21,000 000
Supervisory Charges 1,20,000 1,50,000 1,60,000
The company commenced the contract with equipment worth 5 Lac. They purchased
following equipment further: -
Date Value of Equipment 1.1.02 3,00,000
1.10.02 2,00,000
1.07.03 1,00,000
Equipment is to be depreciated at the rate of 10% per annum on SLM.
The contractee pays 75% of work certified immediately on cash and balance only on
completion of contract.
Solution.
Depreciation for Year Ending 31.3.02
Date Cost % Depreciation
1.07.01 5,00,000 7.5% 37,500
1.01.02 3,00,000 2.5% 7,500
45,000
Depreciation for Year Ending 31.3.03
Date Cost % Depreciation
1.04.02 8,00,000 10% 80,000
1.10.02 2,00,000 5% 10,000
90,000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 47 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Depreciation for Year Ending 31.3.04
Date Cost % Depreciation
1.04.03 10,00,000 7.5% 75,000
1.07.02 1,00,000 5% 5,000
80,000
Wages for the year 31.3.02 31.3.03 31.3.04
Wages Paid 1,83,000 3,49,000 2,75,000
Closing Outstanding 17,000 21,000 000
Total 2,00,000 3,70,000 2,75,000
- Opening Outstanding 000 -17,000 21,000
Total Wages 2,00,000 3,53,000 2,54,000
Supervisory charges
31.3.02 31.3.03 31.3.04
Per Annum 1,20,000 1,50,000 1,60,000
No of months 9 12 9
For the year 90,000 1,50,000 1,20,000
Contract Account for Year Ending 31 Mar 02
Dr
To material sent to site 2,45,000
To wages 2,00,000
To supervisory charges 90,000
To depreciation 45,000
Notional Profit 1,98,000
Total 7,78,000
To Net Profit 49,500
To Closing reserves for 1,48,500
Cr
By Work certified 7,00,000
By uncertified work 45,000
By Material Returned 12,000
By Closing Stock of Material 21,000
Total 7,78,000
By Notional Profit 1,98,000
Stage of Completion = Cumulative Work Certified
Total Contract Value
= 7,00,000
25,00,000
As the stage of completion is between 25 and 50%,
Net Profit = 1/3 x Notional Profit x %Cash Received
Work Certified
= 1/3 x 198,000x75%
= Rs 49,500
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 48 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Balance Sheet as on 31.3.02
Liabilities
Reserves
Profit and loss Account 49,500
For contingencies 1,48,500
Current Liabilities
Outstanding Wages 17,000
Assets
Fixed Assets
Eqpts
Opening Cost 5,00,000
Addition 3,00,000
less Accrued Dep 45,000
7,55,000
Current Assets
Material Stock 21,000
Cl uncertified Work 45,000
Contractee Account 1,75,000
(25% of 7 lakhs)
Contract Account for Year Ending 31 Mar 03
Dr
To Opening Mat Stock 21,000
To Opening uncertified work 45,000
To material sent to site 4,31,000
To wages 3,53,000
To supervisory charges 1,50,000
To depreciation 90,000
Notional Profit 1,56,500
Total 12,56,500
To Net Profit 78,250
To Closing reserves for 78,250
Contingency
Cr
By Opening reserves for 1,48,500
contingency
By Work certified 10,00,000
By uncertified work 59,000
By Material Returned 14,000
By Closing Stock of Material 25,000
_______________________________
Total 12,56,500
By Notional Profit 1,56,500
Stage of Completion = Cumulative Work Certified
Total Contract Value
= 17,00,000 = 68%
25,00,000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 49 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
As the stage of completion is between 50 and 90%,
Net Profit = 2/3 x Notional Profit x Cash Received
Work Certified
= 2/3 x 1,56,500x75%
= Rs 78,250
Balance Sheet as at 31.3.04
Liabilities
Reserves
Profit and loss Account 1,27,750
(49,500 + 78,250)
For contingencies 78,250
Current Liabilities
Outstanding Wages 21,000
Assets
Fixed Assets
Eqpts
Opening Cost 8,00,000
Addition 2,00,000
10,00,000
- Accrued Depreciation 1,45,000
8,65,000
Current Assets
Material Stock 000
Closing uncertified Work 59,000
Contractee Account 4,25,000
(25% of 17 lakhs)
Contract Account for Year Ending 31 Mar 04
Dr
To Opening Mat Stock 25,000
To Opening uncertified work 59,000
To material sent to site 3,15,000
To wages 2,54,000
To supervisory charges 1,20,000
To depreciation 80,000
Notional Profit 35,250
Total 8,88,250
To Net Profit 35,250
Cr
By Opening reserves for 78,250
contingency
By Work certified 8,00,000
By Material Returned 10,000
By Closing Stock of Material 000
________________________________
Total 8,88,250
By Notional Profit 35,250
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 50 of 60 - Cost Management
Jamnalal Bajaj Institute of Mgmt Studies
Balance Sheet as at 31.3.04
Liabilities
Reserves
Profit and loss Account 1,63,000
(1,27,750 + 35,250)
Assets
Fixed Assets
Eqpts
Opening Cost 10,00,000
Addition 1,00,000
11,00,000
- Accrued Depreciation 2,15,000
8,85,000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 51 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
STOCK VALUATION
FIFO. The issues are charged on the basis of procurement prices starting from the
oldest procurement. The closing stock is valued at the procurement prices starting from
latest procurement rates.
Advantages. The stock valuation is current (on the basis of latest available rates).
Limitations.
1. The customer may not be properly charged especially in case of jobs where
selling price = cost + margin.
2. Accounting method is cumbersome as each lot of procurement is maintained
separately in the stock Register.
LIFO. The issues are charged on the basis of procurement prices starting from the
last procurement. The closing stock is valued at the procurement prices starting from oldest
procurement rates.
Advantages. The charging to the customer is always appropriate.
Limitations.
1. The Balance sheet does not reflect the true value of the inventory.
2. This accounting method is also equally cumbersome as FIFO as each lot of
procurement is maintained separately in the stock Register.
Question.
Record the following transactions in the stock records of the company.
1.1.04 - Opening Stock 200 Kg @ Rs 40/-
3.1.04 - Purchased from X & Co 500 Kg @ Rs 42/-
5.1.04 - Issued for Job 101 300 Kg
6.1.04 - Issued for Job 103 300 Kg
3.1.04 - Purchased from Y & Co 400 Kg @ Rs 43/-
3.1.04 - Purchased from X & Co 200 Kg @ Rs 42/-
6.1.04 - Issued for Job 102 300 Kg
6.1.04 - Issued for Job 102 200 Kg
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 52 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
Solution.
STOCK REGISTER (FIFO)
Date Details Receipts Issues Balance
Kg @ Value Kg @ Value Kg @ Value
1.1.04 Opening Stock 200 40 8000
3.1.04 Purchased X & Co 500 42 21000 200 40 8000
500 42 21000
700 29000
5.1.04 Issued to Job 101 200 40 8000
100 42 4200
300 12200 400 42 16800
6.1.04 Issued to Job 103 300 42 12600 100 42 4200
8.1.04 Purchased Y & Co 400 43 17200 100 42 4200
400 43 17200
500 21400
11.1.04 Purchased X & Co 200 42 8400 100 42 4200
400 43 17200
200 42 8400
700 29800
13.1.04 Issued to Job 102 100 42 4200 200 43 8600
200 43 8600 200 42 8400
300 12800 400 17000
15.1.04 Issued to Job 102 200 43 8600 200 42 8400
STOCK REGISTER (LIFO)
Date Details Receipt Issues Balance
Kg @ Value Kg @ Value Kg @ Value
1.1.04 Opening Stock 200 40 8000
3.1.04 Purchased X & Co 500 42 21000 200 40 8000
500 42 21000
700 29000
5.1.04 Issued to Job 101 300 42 12600 200 40 8000
200 42 8400
400 16400
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 53 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
6.1.04 Issued to Job 103 200 42 8400
100 40 4000
300 12400 100 42 4200
8.1.04 Purchased Y & Co 400 43 17200 100 40 4000
400 43 17200
500 21200
11.1.04 Purchased X & Co 200 42 8400 100 40 4000
400 43 17200
200 42 8400
700 29600
13.1.04 Issued to Job 102 200 42 8400 100 40 4000
100 43 4300 300 43 12900
300 12700 400 16900
15.1.04 Issued to Job 102 200 43 8600 100 40 4000
100 43 4300
200 8300
STOCK REGISTER (SIMPLE AVERAGE)
Date Details Receipt Issues Balance
Kg @ Value Kg @ Value Kg @ Value
1.1.04 Opening Stock 200 40 8000
3.1.04 Purchased X & Co 500 42 21000 700 41 29000
5.1.04 Issued to Job 101 300 41 12300 400 41 16700
6.1.04 Issued to Job 103 300 41 12400 100 41 4400
8.1.04 Purchased Y & Co 400 43 17200 500 42 21600
11.1.04 Purchased X & Co 200 42 8400 700 42 30000
13.1.04 Issued to Job 102 300 42 12600 400 42 17400
15.1.04 Issued to Job 102 200 42 8400 200 42 9000
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 54 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
STOCK REGISTER (WEIGHTED AVERAGE)
Date Details Receipt Issues Balance
Kg @ Value Kg @ Value Kg @ Value
1.1.04 Opening Stock 200 40 8000
3.1.04 Purchased X
& Co
500 42 21000 700 41.43 29000
5.1.04 Issued to Job
101
300 41.43 12429 400 41.43 16571
6.1.04 Issued to Job
103
300 41.43 12400 100 41.43 4142
8.1.04 Purchased Y
& Co
400 43 17200 500 42.68 21342
11.1.04 Purchased X
& Co
200 42 8400 700 42.46 29742
13.1.04 Issued to Job
102
300 42.46 12738 400 42.46 17004
15.1.04 Issued to Job
102
200 42.46 8492 200 42.46 8512
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 55 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
APPORTIONMENT OF O/H OF SERVICE DEPTTS TO PRODDEPTTS.
P1 P2 P3 S1 S2
Overheads 30000 25000 20000 5000 4000
No of Hrs 10000 8000 12000 8000 8000
% of Service Rendered
S1 50% 20% 20% -- 10%
S2 30% 40% 20% 10% ---
P1 P2 P3 S1 S2
Overheads 30000 25000 20000 5000 4000
S1 2500 1000 1000 -5000 500
32500 26000 21000 0 4500
S2 1350 1800 900 450 -4500
33850 27890 21990 450 0
S1 225 90 90 -450 45
34075 27890 21990 0 45
S2 14 18 9 4 -45
34089 27908 22000 0 0
Hrs 10000 8000 12000
Rate/Hr 3.41 3.48 1.83
Job 501
(Overheads) Labour
Deptt Hrs Rate Total Hrs Rate Total
P1 20 3.41 68.20 20 10 200
P2 15 3.48 52.20 15 10.75 161
P3 25 1.83 45.75 25 6 150
166.15 511
Job Cost Sheet (Job 501)
Material 1050
Labour 511
Overheads 166
1727
Margin 173
1900
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 56 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
Q. Calculate Raw Material variances:
Standard 1000 units of finished product
2000 Kg of Raw Material @ Rs 15/Kg Rs 30000/-
Actual 8500 Units of finished goods
16800 Kg of Raw Material @ 15.50/Kg Rs 260400/-
Sol.
1. Raw Material Cost Variance = (Actual RM Cost – RM cost for actual production at
Standard Rates)
= 260400- 8500x30
= 5400 (Adverse Variance denoted as ‘A’)
2. RM Price Variance = Actual Qty (Actual Price – Standard Price)
= 16800 (15.5 – 15)
= 8400 (A)
3. RM Usage Variance = Standard Price (Actual Qty – Standard Qty for actual
production)
= 15 (16800 – 8500x02)
= 15 (16800 – 1700)
= 3000 (Favourable Variance denoted as ‘F’)
Q. Calculate RM, Labour and Variable Overhead Variances
Standard for 100 Units of Finished Goods
RMs 1500 Kgs @ Rs 3/- = Rs 4500/-
Labour 600 Hrs @ Rs 4/- = Rs 2400/-
Variable Overhead 600 Hrs @ Rs 1.50 = Rs 900/-
Total Variable Cost for Standard 100 Units = Rs 7800/-
Actual for 2500 Units of finished goods
RMs 37250 Kgs @ Rs 3.10 = Rs 115475/-
Labour 15260 Hrs @ Rs 4.15 = Rs 63329/-
Variable Overhead 15260 Hrs @ Rs 1.40 = Rs 21364/-
Total Variable Cost for Actual production = Rs 200168/-
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 57 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
Sol.
Raw Material Cost Variance = (Actual RM Cost – RM cost for actual production at
Standard rates)
= (115475 – 2500x45)
= 2975 (F)
Raw Material Rate Variance = Actual Quantity (Actual Rate – Standard Rate)
= 37250 (3.1 –3.0)
= 3725 (A)
Raw Material Usage Variance = Standard Rate (Actual RM Usage – Standard usage
for actual production)
= 3.0 (372350 – 2500 x 15)
= 750 (F)
Labour Cost Variance = Labour Cost for Actual Production – Labour cost for actual
production at standard rates)
= (63329 – 2500 x 6 x 4)
= 3329 (A)
Labour Efficiency Variance = Standard Labour Rate (Actual hrs – Standard Hrs
for actual production)
= 4 (15260 – 2500 x 6)
= 1140 (A)
Labour Rate Variance = Actual Hours (Actual Rate – Standard Rate)
= 15260 (4.15 – 4)
= 2289 (A)
Variable overhead Variance = Actual Variable Overheads – Overheads for actual
production at standard rates)
= (21364 – 2500 x 6 x 1.5)
= 1136 (F)
Variable Overhead Rate Variance = Actual Hrs (Actual Rate – Standard Rate)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 58 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
= 15260 (1.5 – 1.4)
= 1526 (F)
Variable Overhead Efficiency Variance = Standard Rate (Actual Overhead Hours –
Hrs required at Standard Rate for Actual Production)
= 1.5 (15260 – 15000)
= 1.5 (260)
= 390 (A)
Statement of Variances
Material Cost Variance Rs 2975/- (A)
Material Price Variance Rs 3725/- (A)
Material Usage Variance Rs 750/- (F)
Labour Cost Variance Rs 3329/- (A)
Labour Rate Variance Rs 2289/- (A)
Labour Efficiency Variance Rs 1040/- (A)
Variable Overhead Cost Variance Rs 1136/- (F)
Variable Overhead Rate Variance Rs 1126/- (F)
Variable Overhead Eff. Variance Rs 390/- (A)
Q. Calculate Material, Labour and Varible Overhead Variances from the following
data:
Standard for 10000 units
Raw Material 15000 Kgs @ Rs 9/Kg Rs 135000/-
Labour 30000 Hrs @ Rs 3/Hr Rs 9000/-
Variable Overhead 30000 Hrs @ Rs 1.8/Hr Rs 54000/-
Actuals for 9000 Units
Raw Material 13500 Kg @ Rs 8.75/Kg Rs 118125/-
Labour 27260 Hrs @ Rs 3.10/Hr Rs 84506/-
Variable Overhead 27260 Hrs @ Rs 1.75/Hr Rs 47705/-
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 59 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
Sol.
Material Cost Variance = (Actual cost – Cost at Standard Rates for actual
production)
= (118125 – 1.5 x 9 x 9000)
= 3375 (F)
Material Rate Variance = Actual Mat consumed (Actual Rate – Standard Rate)
= 13500 (9 – 8.75)
= 3375 (F)
Material Usage Variance = Standard Rate (Actual Mat consumed– Standard
material for actual production)
= 1.80 (13500 – 13500)
= 000
Labour Cost Variance = Actual Cost – Cost at Standard Rate for actual production
= 84506 – 9000 x 3 x 3
= 3506 (A)
Labour Rate Variance = Actual hrs (Actual Rate – Standard Rates)
= 27260 (3.10 – 3)
= 2726 (A)
Labour Eff. Variance = Standard Rate (Actual Hrs – Standard hrs for actual
production)
= 3 (27260 – 9000 x 3)
= 3 x 260 = 780 (A)
Variable Overhead Variance = Actual Overhead – Overhead at Standard Rate for
actual production
= 47705 – 9000 x 3 x 1.8
= 47705 – 48600
= 895 (F)
Variable Overhead Rate Variance = Actual Hrs (Actual Rate – Standard Rate)
= 27260 (1.75 – 1.8)
= 1363
Variable Overhead Eff Variance = Standard Rate (Actual Hrs – Standard Hrs for
actual production)
Mgmt study material created/ compiled by - Commander RK Singh [email protected]
Page 60 of 60 - COSTING
Jamnalal Bajaj Institute of Mgmt Studies
= 1.8 (27260 – 9000 x 3)
= 1.8 (260) = 468 (A)
Statement of Variances
Material Cost Variance Rs 3375/- (A)
Material Price Variance Rs 3375/- (A)
Material Usage Variance Rs 000/- (-)
Labour Cost Variance Rs 3506/- (A)
Labour Rate Variance Rs 2726/- (A)
Labour Efficiency Variance Rs 780/- (A)
Variable Overhead Cost Variance Rs 895/- (F)
Variable Overhead Rate Variance Rs 1363/- (F)
Variable Overhead Eff. Variance Rs 468/- (A)