Practical Matters: MSD’s Approach to Asset Management Metropolitan St. Louis Sewer District August 2018 Christopher Pfeuffer, PE Operations Division Manager Metropolitan St. Louis Sewer District [email protected] Ohio One Water Conference Gateway to Success Practical Asset Management Anne Kennedy Utility Performance Consultant Brown and Caldwell [email protected]

Transcript of Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project...

Page 1: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Practical Matters:MSD’s Approach to Asset Management

Metropolitan St. Louis Sewer District

August 2018

Christopher Pfeuffer, PEOperations Division ManagerMetropolitan St. Louis Sewer [email protected] Ohio One Water Conference

Gateway to SuccessPractical Asset Management

Anne KennedyUtility Performance ConsultantBrown and [email protected]

Page 2: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

• MSD formed in 1954 and current service area encompasses 525 square miles around St. Louis, MO

• System includes:• Seven WWTPs for average

350+mgd treatment capacity

• 9,517 miles of collection and trunk sewers and force mains

• 278 pumping stations

Summary

Brown and Caldwell 2

Page 3: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Consent Decree and Collection System AM

• Consent Decree:• Entered into negotiated CD in 2012• Increase collection and treatment capabilities• 23 years, $4.7B effort to build improvements

to address water quality and remove SSOs and abate CSOs

• MSD started their AM journey as part of the CD

Page 4: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Why MSD Needs AMExpeditedor Delayed Spending

ProactivePlant Improvements

AccurateData

CONSENT DECREE CSO TUNNEL CONSTRUCTION PERIOD

CONSENT DECREE REQUIRED INVESTMENT

PLANT AND PUMP STATION INVESTMENT

DELAY

DELAY

EXPEDITE

2020 20262000 2030

Page 5: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Practical Asset Management

Focus on critical assets first!

Page 6: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Multi -Site EvaluationWhere do you want to go?► Establish AM Team► Develop vision, goals, and objectives for asset

management in Program Charter► Align MSD and BC team on project vision, goals, and

objectives Gap AnalysisDeliverables / Program Charter/AM Gap Analysis

• Asset Management will be phased into Operations over several years

• MSD in the driver’s seat for defining what Asset Management means to the organization

• Cross-departmental leadership team, but everyone at MSD has a role in the success of the program

Roadmap to SuccessAsset Management Roadmap to Success

PHASE 1

PHASE 2

PHASE 3

Management Expectations & Asset Management Strategy, Plan, and Program DevelopmentWhat do we need to get there?► Prioritize Plant AM Implementation Plan► Develop standardized templates for key program

components► Establish key asset management processes► Develop communications plan► Document processes for AM from initial asset acquisition

through replacement► Appropriate service levels and others goals to monitor asset

performanceDeliverables / AM Implementation Plan/Program Templates/Key AM Process/Communications Plan/TAMP Implementation Plans

Plan and Program Implementation, and Field CoachingHow do we manage the journey?► Implement coaching and information sharing plan to gain

staff understanding buy-in and ownership► Monitor appropriate KPIs to gauge program progress and

success► Assist with gap closure and implementation (asset priority,

condition, and risk)Deliverables/ Tactical AM Plans/Progress reports/Summary status reports/Updated AM implementation plan/Training materials

Page 7: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

1Phase 1: Charter, Training and Gap Analysis

Page 8: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Phase 1: YEAR 1• Established the Asset

Management Team (AMT) to establish goals and objectives for AM at MSD

• AMT defined what AM means to MSD

• Conducted a gap analysis to determine current state of AM at each plant

PHASE 1

Multi -Site Evaluation

Page 9: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

AM Charter

• Describes where MSD wants to go with Asset Management

• Developed by Asset Management Team

• Copies posted at each facility

Page 10: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Gap Analysis

Tactical• Service Level Requirements and

Performance Measures• Inventory & Asset Profile• Risk and Criticality• Condition Assessment and Monitoring• Operations Strategy• Maintenance Strategy• Renewal & Replacement Strategy• Information Management

Strategic• Vision and Support• Resource Management• Strategic Asset Management Plan• Communication• Level of Service• Performance and Quality Management• Risk Management• Engineering Design & Construction• Capital Planning & Financing• Business Case Evaluation

Page 11: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Gap Analysis

0 50 100 150 200 250

Vision and Support (3.1.1)

Resource Management (3.1.2)

Strategic Asset Management Plan (3.1.3)

Communication (3.1.4)

Level of Service (3.1.5)

Performance and Quality Management (3.1.6)

Risk Management (3.1.7)

Engineering Design & Construction (3.1.8)

Capital Planning & Financing (3.1.9)

Business Case Evaluation (3.1.10)

Category (Section)Current Score Target Score

38 60

34 60606060

4560

60

60

60

3317

2813

13

1728

15

Weighted Gap

│ │ │ │ │ │

Page 12: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Strategic• Risk Management• Communication• Levels of Service

Tactical• Condition Assessment and Monitoring• Risk and Criticality• Inventory and Asset Profile• Maintenance Strategy

Initial Focus Areas From Gap Analysis

Page 13: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

2Phase 2: SAMP, Templates, and Roadmap

Page 14: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

• Strategic Asset Management Plan (SAMP)

• Standardized templates for AM elements that matter most to MSD

• Key AM processes and performance metrics

• Communication and Engagement Plan

Phase 2: YEAR 1 PHASE 2

Management Expectations & Asset Management Strategy, Plan, and Program Development

Page 15: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

SAMP

• AMT approved approach for direction of the AM program

• Focus on consistency on the AM elements

• Aligns with the strategic goals of MSD

Page 16: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Standardized Templates

• Standard templates to promote consistency across MSD• Promotes ‘apples to apples’ comparisons for planning and

decision making

RiskConsequence of Failure

Likelihood of FailureUseful Life

Tactical Asset Management PlanMaintenance Procedures

Standard Operating Procedures

Page 17: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

• Interviewed staff at each facility

• Better understand how they are currently doing work in relation to SAMP

• Facility specific plan to ‘fill in the gaps’ during Phase 3 of the project

TAMP Implementation Plan

Plant Assets Level of Service Risk Management Condition Assessment Maintenance Management Asset Needs Materials Management

Page 18: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

• The plan to implement asset management at MSD• Describes the work to be done, time frame for completion,

and who will be doing the work.

Phase 3 Roadmap

Page 19: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

3Phase 3: Plan and Program Implementation

Page 20: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Phase 3: YEAR 2/3 and Ongoing

20

• Develop a TAMP for each plant

• Provide coaching, mentoring, and SME support during implementation

• Monitor program progress-what works well and what areas need to be adjusted

PHASE 3

Plan and Program Implementation, and Field Coaching

Page 21: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Facility specific plans have been developed to implement AM across MSD.

TAMPs

21

Page 22: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

• An implementation plan (task and schedule) is included in each TAMP.

• This document provides guidance to facility staff to focus on the right AM element at the right time for their facility.

Facility Specific Implementation Plans

22

Page 23: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

MSD has formed several working groups to continue development of their program including the following:

• Maintenance Management Council• Metrics and Dashboards• Monetized Prioritization• PM Program and Scheduling • Condition Monitoring

Additional groups are formed as needed to tackle new initiatives.

MSD Leading the Program

23

Page 24: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Metrics and Dashboards

24

Page 25: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Metrics and Dashboards

Brown and Caldwell 25

Page 26: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Metrics and Dashboards

Brown and Caldwell 26

Page 27: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

• MSD realizes that change management is the hardest part of building a sustainable AM program

• The organization uses facility message boards to keep AM front and center to staff across the organization

• And, MSD meets on a regular basis to share the success stories of their program development

MSD Engagement

27

Page 28: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

MSD Engagement

28

Page 29: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

MSD Engagement

29

Page 30: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

MSD Engagement

30

Page 31: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

People are the key to success. AM is a program and not a project. There will be challenges along the way and the pace may

not always be what you imagined. Change is hard, but if you engage your staff, you will

achieve buy in and results.

Lessons Learned

31

Page 32: Metropolitan St. Louis Sewer District Practical Matters: MSD ......Align MSD and BC team on project vision, goals, and objectives Gap Analysis Deliverables / Program Charter/AM Gap

Thank YouQuestions?