February 11, 2013
Metro Gold Line Foothill Extension
Project Update
Creation/Powers of the Authority
2
Doug TessitorChair
Ed ReyesMember
John FasanaMember
Keith HanksMember
Lara Larramendi Member, Non-Voting
Dan EvansMember, Non-Voting
Bill Bogaard Member, Non-Voting
Sam Pedroza1st Vice Chair
Board of Directors
Alan WapnerMember, Non-Voting
Joint Powers Authority and TAC
• Governance Structure includes Representation by All Corridor Cities- Elected Officials – Joint Powers Authority- City Staff – Technical Advisory Committee
3
Strategic Partnership w/Metro
• General Relationship– Construction Authority plans, designs and builds the line
(per Metro’s design/safety guidelines and specifications)
– Metro operates and maintains the line following construction
• Both agencies play a role in public safety planning and education
• Master Cooperative Agreement – Formalizes roles and responsibilities
– MCA for Pasadena to Azusa and Azusa to Montclair segments signedMarch 2010
Projects partially funded by Measure R
2010 Long Range Plan - Rail
Montclair
4
Projects partially funded by Measure R
Construction Authority Responsibility
Montclair
Planning/Construction Phases
• Pasadena to Azusa Extension – Funded by Measure R/Underway– 11.5 Miles, 5 Cities, 6 Stations/Construction Completion Anticipated 2015
Pasadena-Azusa Azusa-Montclair Airport Ext.
• Azusa to Montclair Extension - Proposed – 12.6 Miles, 6 Stations/Estimated Funding Needed is $780 Million
• Ontario Airport Extension - Proposed– Approximately 8 Miles/Unfunded
Los Angeles-Pasadena
• Los Angeles to Pasadena Extension - Opened 2003– 13.7 Miles, 3 Cities, 13 Stations
5
Pasadena to Azusa
• Fully funded by Measure R
• Construction to be completed 2015
• Two of three design-build contracts awarded– DB1: I-210 Bridge Contract: Skanska USA - $18.6 million
– DB2: Alignment Contract: Kiewit Parsons Joint Venture - $486 million– DB3: Parking Facilities : Procurement began March 2012
Pasadena-Azusa
Status: Pasadena to Azusa
10
6
On Schedule for 2015 Delivery
• DB1 Completed – December 2012• Short-list DB3 Bidders – June 2012
AFC 62/82 Design Packages (substantial completion in 3/13) Turn over Gold Line Bridge to DB2 Contractor M&O (100% +) Property Acquisition/Turn over to DB2
Contractor Award/Full NTP DB2 SEIR Legal Challenge Supplemental EIR Certified San Gabriel River Bridge/USACE Permits Rail Abandonment (West of San Gabriel River Bridge) Grade Crossing Approvals (CPUC) Third Party MCAs and Permits
11
DB1: Gold Line Bridge
12
7
On Time, On Budget DeliverySmart Column Technology: 100 Nights of Late Night Activity:
13
100% Safety Record, >95,000 work hours performed
Majority Domestic Content: More than 90% of the material used to build the bridge is from domestic, and local sources.
Completed Dec. 15 ,2012
14
8
DB2: Pasadena to Azusa Alignment
DuarteMonroviaArcadia
Azusa-CitrusAzusa-AlamedaIrwindale
Adding Six Stations in Five CitiesConstruction Completion - 2015
9
Shared Corridor – Future Condition
• Agreement signed btwn. Metro & BNSF - April 2011
• Discontinue freight service west of San Gabriel River
• Shared use corridor east of San Gabriel River (separate tracks)
Shared-Use ROW
Discontinued ROW
Maintenance & Operation Campus
18
New 24-acre facility – to be located in Monrovia
Provide adequate capacity for Gold Line and other regional lightrail lines – 85 car capacity
10
At-Grade CrossingsRef STREET CITY1 1st Ave and Santa Clara Arcadia2 Mayflower Ave Monrovia3 Magnolia Ave Monrovia4 Monrovia Station Monrovia5 Myrtle Ave Monrovia6 California Ave Monrovia7 Mountain Ave Duarte8 Buena Vista St Duarte9 Duarte Station (West Entr.) Duarte
10 Highland Ave Duarte11 Irwindale Station (West Entr.) Irwindale12 Irwindale Station (East Entr.) Irwindale13 Virginia Ave Azusa14 San Gabriel Blvd Azusa15 Azusa Ave Azusa16 Dalton Ave Azusa17 Pasadena Ave Azusa18 Azusa-Citrus Station Azusa
All CPUC Approved
Structures Overview
• Pasadena to Azusa has 16 crossings that require 22 structures– Some crossings use one structure and some use two
structures for east and west bound tracks• Of these 22 structures
– Nine will be new– Nine will be modifications of existing structures– Four will be total replacements
11
New StructuresNine new structures will be built
• Gold Line Bridge – (I-210 Freeway)
• Colorado Blvd - (Arcadia)
• Santa Anita Ave - (Arcadia)
• Foothill Blvd (LRT & Freight “Twins”) – (Azusa)
• Palm Drive (LRT & Freight) – (Azusa)
• Citrus Drive (LRT & Freight) – (Azusa)
Modified StructuresNine existing structures will be modified
– Primarily seismic retrofits
Baldwin Ave Crossing
• Rosemead Blvd• Michillinda Ave• Baldwin Ave• Huntington Blvd• 5th Ave Pedestrian Tunnel • Foothill Blvd• Palm Dr• Citrus Ave• Kincaid (I-210 Freeway)
12
Replacement StructuresFour existing structures will be completely replaced
San Gabriel River Bridge
• Santa Anita Wash • Alta Vista Wash• Sawpit Wash• San Gabriel River
DB2: Alignment Contract Status
Design nearing completion/construction activities underway:– 62/82 design packages are “approved for construction”
– Clear and grub/track removal/demolition - ongoing (mainline)
– Station construction underway – Duarte
– Bridge construction underway – Arcadia, Azusa, Monrovia
– Removal of vacant properties on M&O site complete, mass grading nearing completion, utility relocation on-going
13
Design Progress – Project-wide
AFC
100%
85%
60%
Design Progress: BridgesBridges at 100%• San Gabriel River Bridge
• Huntington (new)
Bridges at AFC • Palm LRT (new)
• Palm LRT (existing)
• Citrus LRT (new)
• Citrus LRT (existing)
• Palm FRT (new)
• Citrus FRT (new)
• 5th Ave Pedestrian
• Huntington (existing)
• Kincaid
• Foothill LRT existing)
• Foothill LRT (new)
• Foothill FRT (new)
• Rosemead
• Colorado
• Santa Anita Ave
• Santa Anita Wash
• Alta Vista Wash
• Sawpit Wash
• Michillinda
• Baldwin
14
(Agreement pending)
Alignment Overview Schedule
August 2011
July 2011
2012
July 2011
September 2011
Activity Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4
DESIGN:
CONSTRUCTION:
Grading (FRT)
Trackwork (FRT)
Bridges
Station Structures
Station Finishes & Landscape
Operations Campus (M&O)
Site Clearing & Demolition
Retaining Walls
Grading & Drainage
Trackwork
Systems
Testing & Systems Integ.
2012 | 2013 | 2014 | 2015 | 2016
Jan 2013
Start Construction
Freight Relocation Complete = Dec. 2013
Design Substantial Completion = Mar 2013
Construction Activities
Clearing/Grubbing - Irwindale
Bridge Construction – Azusa:(building 2 new LRT bridges, beside freight bridge)- Citrus Ave (pictured)- Palm Dr- Foothill Blvd
15
Station Construction is underway
Highland Ave Grade Crossing Improvements
Construction Activities - Duarte
Waterline Relocation – Monrovia
Colorado Bridge Abutment Demo - Arcadia
Construction Activities
16
Construction - Operations Campus
Demolition Completed – Nov. 2012Mass Grading - Nearing CompletionUtility Relocation - Ongoing
Reaching Key Audiences
17
Current Outreach Activities• Community Hotline• Construction notices, distributed:
- Community walks- City websites- Authority website
• Construction Authority E-News Updates
• Twitter, Facebook and Blog Updates • Community-accessible offices –
open in Azusa, Arcadia and Monrovia• Construction Safety Program – schools
and community• Gold Line Tours – on-going
Sign up to receive updates: www.foothillextension.org
M&O Design Update
18
• Authority is required to provide M&O Facility as part of Funding Agreement with Metro
• M&O Facility will serve existing Gold Line (Phase I and Eastside Extension) in addition to Foothill Extension
• Facility will house up to 85 light rail vehicles at a time• LRVs at the facility will be provided service and inspection, heavy repairs, blow-
down, body repairs, painting, storage, cleaning, and washing• M&O Facility will be located on a ~24 acre lot in Monrovia, bounded by East
Evergreen Ave. (north); Duarte Rd. (south); California Ave. (west); and Shamrock Ave. (east)
Project Background
Site Plan
19
Maintenance and repair operations happen indoors within enclosed facilities
Car Wash Facility wasextended in order to accommodate blowers inside
Landscape buffer zones on all sides and corners
Planning and Design
Landscaping
20
Architectural Design
Designed for LEED Certification
Architectural DesignView from Duarte Rd., from California Corner
21
DB3: Parking & Station-Area Enhancements
DB3: Parking/Amenities Planned at All Future Stations
* may integrate parking into multi-use structure/currently under evaluation
• Separate design-build contract
• Work to be completed late 2015
• Six intermodal parking facilities
– Four parking structures:
• Arcadia – 300 Spaces
• Monrovia – 350 Spaces
• Irwindale – 350 Spaces
• Azusa-Citrus – 200 Spaces
– Two surface parking lots:
• Duarte – 125 Spaces
• Azusa-Alameda – 200 Spaces*
22
Station Enhancements
43
• $6 million FTA grant: Bus/Ped Interface Improvements
• Enhance streets around stations: new bus shelters, benches, pedestrian lights, street trees, bike lockers, sidewalks, crosswalks, etc.
Future Segments
23
Azusa to Montclair Update
• Future work involves refining concept plans, and finalizing the Purpose and Need document, Project Description Report, technical studies, and Draft EIR for public release
– Published Draft EIR – August 2012/FEIR for Board Consideration –Feb 2013
• Authority currently working with Metro to seek funding following completion of the environmental review
Azusa-Montclair
Activity 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Environmental Clearance
Preliminary Design/Advanced Conceptual Engineering
Financing & Procurement
Construction
Schedule as of August 22, 2012
Anticipated Schedule - Azusa to Montclair
(anticipated)
• Project is currently unfunded for construction. Schedule to complete project assumes funding is secured between 2015-2016
24
Azusa to Montclair Extension
• 12.6 mile corridor, six cities, six stations planned• Shared corridor – freight throughout & Metrolink from Pomona east • Two proposed grade separated crossings (Lone Hill and Towne Avenues)
Ontario Airport Extension - Schedule
Activity Timeline
Alternatives Analysis
EIR/EIS
Design, Financing & Procurement
Construction
2013-2015
2015-2017
2018-2021
2022-2026
48
25
Jobs/Economic Benefits
Economics by Construction Segment
26
Project Spending by Category