Agenda • Welcome
• What is this project all about?
• How will the project be built?
• Keeping informed during construction
• Questions and answers
East Side Improvements
• Rte. 113 (Lowell St.) will be realigned at Haverhill St. intersection
• Haverhill St. will be improved with additional travel lane and sidewalk
• Existing traffic signals will be upgraded
4
• New traffic signal at base of I-93 off-ramp at Rte. 113 (No. Lowell St.) intersection
• Rte. 113 will be widened between I-93 SB off-ramp and Albert Street
• New traffic signals at Branch Street/Rte. 113 and Riverside Dr./Rte. 110
6
West Side Improvements
Project Manager: Rich Masucci General Superintendent: Jay Balboni Project Superintendent: Jack Flynn
Bridge Superintendent: Mark Richardson Project Engineer: Kevin Hoyt
E.T.& L . CORP. PROJECT TEAM
M E T H U E N I N T E R C H A N G E
E.T.& L. PROJECT TEAM
E.T.& L. RELEVANT EXPERIENCE Sagamore Rotary Sagamore, MA Braintree-Quincy Quincy, MA Canal St. Bridge Lawrence, MA
MASSDOT - SAGAMORE ROTARY INTERCHANGE
Contract Value: $37 Million
Contract Start Date: 2004
Major Work Involved: Replaced Sagamore Bridge
Rotary Reconstructed Rt. 6 below Rt. 3 Constructed a new Rt. 3 bridge Constructed three temporary
bridges on Rt. 3 and Rt. 6
MASSDOT - BRAINTREE-QUINCY ROADWAY RECONSTRUCTION
Contract Value: $15.9 Million
Contract Start Date: 2007
Major Work Involved: Constructed a new on-
ramp for Rt. 3 Northbound Constructed a new on-
ramp with an 800 ft. viaduct bridge
MASSDOT - CANAL STREET BRIDGE LAWRENCE, MA
Contract Value: $9 Million
Contract Start Date: 2011
Major Work Involved: Constructed a new Canal
Street bridge over the Spicket River Widened Canal Street with
new traffic signals installed
Total Project Duration: 4 years Project Start Date: May 2014 Final Completion: June 2018
SCHEDULE OVERVIEW
Stage Durations
Stage 1 June 2014 – April 2015
Stage 2A January 2015 – August 2015
Stage 2B August 2015 – December 2015
Stage 2C December 2015 – July 2016
Stage 3A June 2016 – November 2016
Stage 3B November 2016 – April 2017
Stage 3C April 2017 – August 2017
Stage 4 August 2017 – June 2018
M E T H U E N I N T E R C H A N G E
STAGE 1 2014 2015 2016 2017 2018
Clearing of project site Removal of buildings Removal of existing I-93 median
barrier and paving of median Widening of River Bridge
I-93
June April
M E T H U E N I N T E R C H A N G E
River Bridge
STAGE 1 2014 2015 2016 2017 2018
Installation of new underground Verizon duct banks
Construction of I -93 SB and NB on-ramps – Open to traffic
Partial construction of I -93 NB and SB on and off-ramps
I-93
June April
M E T H U E N I N T E R C H A N G E
I-93 SB on-ramp
I-93 NB on-ramp I-93 SB on-ramp
I-93 SB off-ramp
I-93 NB off-ramp
STAGE 1 2014 2015 2016 2017 2018
Construction of Sound Walls 1 and 2 Reconstruction of Lowell St. (Rt.
113) and Haverhill St. (Rt. 110) - East of rotary
I-93
June April
M E T H U E N I N T E R C H A N G E
Sound Wall 1
Sound Wall 2
I -93 Northbound traffic shifts to West lanes– 3 lanes in each direction
Construction of East portion of new Bridge 040
STAGE 2A 2014 2015 2016 2017 2018
August January
I-93
M E T H U E N I N T E R C H A N G E
Bridge 040
Construction of temporary East
widening of Bridges 017 and 018 Continue construction of I -93 SB on
and off-ramps
STAGE 2A 2014 2015 2016 2017 2018
August January
I-93
M E T H U E N I N T E R C H A N G E
Bridge 017
I-93 SB on-ramp
I-93 SB off-ramp
Bridge 018
I -93 Northbound traffic shifts to newly constructed East lanes – 3 lanes in each direction
Construction of center portion of new Bridge 040
Continue construction of I -93 SB on and off-ramps
STAGE 2B 2014 2015 2016 2017 2018
August December
I-93
M E T H U E N I N T E R C H A N G E
Bridge 040
I-93 SB on-ramp
I-93 SB off-ramp
STAGE 2B
Widening of North Lowell St. – West of I -93
Installation of utilities and paving of Branch St. – West of I -93
2014 2015 2016 2017 2018
August December
I-93
M E T H U E N I N T E R C H A N G E
Branch St.
I -93 Southbound traffic shifts to median– 3 lanes in each direction
Construction of Western (final) portion of new Bridge 040
Complete construction of I -93 SB off-ramp – Open to traffic
STAGE 2C 2014 2015 2016 2017 2018
December July
I-93
M E T H U E N I N T E R C H A N G E
Bridge 040
I-93 SB off-ramp
Continue construction of I -93 SB on-ramp
Construction of temporary I-93 NB and SB on and off ramps
Reconstruction of Rt. 110/113 - West of rotary
Reconstruction of Bolduc St., Riverside Dr., and N. Lowell St.
STAGE 2C 2014 2015 2016 2017 2018
December July
I-93
M E T H U E N I N T E R C H A N G E
I-93 SB on-ramp
Temp. I-93 SB on-ramp
Temp. I-93 NB off-ramp
Bolduc St.
Riverside Dr.
Complete construction of I -93
SB on-ramp – Open to traffic Demolition of Western portion
of Bridges 017 and 018
STAGE 3A 2014 2015 2016 2017 2018
July November
I-93
M E T H U E N I N T E R C H A N G E
Bridge 017
Bridge 018 I-93 SB on-ramp
Complete construction of storm water basins
Construction of I -93 NB off-ramp – Open to traffic
STAGE 3A 2014 2015 2016 2017 2018
July November
I-93
M E T H U E N I N T E R C H A N G E
I-93 NB off-ramp
Storm water basin
Storm water basin
I -93 Southbound traffic shifts to West and final alignment
Demolition of center portion of Bridge 017 and 018
STAGE 3B 2014 2015 2016 2017 2018
November April
I-93
M E T H U E N I N T E R C H A N G E
Bridge 017
Bridge 018
I -93 Northbound traffic shifts West onto median
Demolition of Eastern portion of Bridges 017 and 018
Complete construction of I -93 NB off-ramp – Open to Traffic
STAGE 3C 2014 2015 2016 2017 2018
I-93
M E T H U E N I N T E R C H A N G E
Bridge 017
Bridge 018
I-93 NB off-ramp
April August
Remove temporary I-93 median paving and install concrete median barrier
Final paving and striping of I -93
STAGE 4 2014 2015 2016 2017 2018
August June
I-93
M E T H U E N I N T E R C H A N G E
STAGE 1 2014 2015 2016 2017 2018
I-93 Traffic Open to Local Traffic
I-93 Breakdown lane closed
M E T H U E N I N T E R C H A N G E
June April
NB SB
STAGE 2A, 2B, 2C 2014 2015 2016 2017 2018
April July
I-93 Traffic Open to Local Traffic
New I-93 SB on-ramp open
New I-93 NB on-ramp open
M E T H U E N I N T E R C H A N G E
NB SB
I-93 Breakdown lane closed
STAGE 3A 2014 2015 2016 2017 2018
July November
Rotary Eliminated
I-93 Traffic Open to Local Traffic
New I-93 NB off-ramp open
New I-93 SB off-ramp open
M E T H U E N I N T E R C H A N G E
NB SB
I-93 Breakdown lane closed
STAGE 3B, 3C 2014 2015 2016 2017 2018
November August
I-93 Traffic Open to Local Traffic
New I-93 SB on-ramp open
M E T H U E N I N T E R C H A N G E
NB SB
Rotary Eliminated I-93 Breakdown lane closed
STAGE 4 2014 2015 2016 2017 2018
August June
I-93 Traffic Open to Local Traffic
New I-93 NB off-ramp open
M E T H U E N I N T E R C H A N G E
NB SB
Rotary Eliminated I-93 Breakdown lane closed
Vincent DeAngelo, Resident Engineer 978-682-3151
Dan Fielding Legislative Liaison, Government & Community Affairs
857-368-8959 [email protected]
Also contact Dan to be added to the project distribution database
Website: http://methuenrotary.mhd.state.ma.us/