Methods Statement-cold Work

1
Mob. Personnel & Equipments Onshore Site Preparation - Fabrication Pipe Ramp Launcher - Fabrication new U-Spool (welding) - Fabrication west/east gooseneck (optional to be fabricated onshore/offshore) - Fab. end flange for new spool & gooseneck (optional) - Hydrotest on fabricated new U-Spool (option) Launching new U-Spool - Install floaters & wire on new U-Spool - Install stability guide on new U-Spool - Side-boom/Backhoe required Offshore Fabrication - Welding West/East Gooseneck to new U-Spool (optional using Flange) Transportation to Offshore - West/East Gooseneck (optional to be fabricated on derrick barge) - Material for Tie-In Spool (west/east) - A-Frame (if any offshore lifting required for tie-in) Offshore Site Preparation - New Trench preparation (backhoe dredger, swamp backhoe, etc) - Installation Cofferdam (west/east point) – using sheet pile / sand bags, etc (optional) - Develops access channel for new U-Spool (TBA during Pre-Lay Survey) Cutting Process - West/East Point for future tie-in on the existing mainline/OLD U-Spool Remove OLD U-Spool TIE-IN (west point) Lift & Lower - Lifting on WEST line & new U-Spool end (west side) – check integrity - 1 st Metrology and Fit-up - Welding west point (tie-in spool will be required) - Lowering (mainline & new U-Spool) west side - Connecting Flange (optional tie-in) TIE-IN (east point) Lift & Lower - Lifting on EAST line & new U-Spool (east side) – check integrity - 2 nd Metrology and Fit-up - Welding east point (tie-in spool will be required) - Lowering (mainline & new U-Spool) east side - Connecting Flange (optional tie-in) Installation of Marking Piles for new U-Spool Installation of Protection Covers - sand bags - concrete mattress (option) - rock dump (option) Demob of personnel/equipment (except for as built survey) As Built Survey Pre-Lay Survey Assumption : Shutdown Operation Pipeline De-Gassing to be done Low level construction HSE Inshore Replacement Location 4.5m minimum offset / parallel distance (depend on trench width and soil shear strength) Towing to offshore TIE-IN (west point) Cofferdam - Lowering new U-Spool in new Trench - 1 st Metrology and Fit-up new U-Spool end to west/east point - Welding west point (tie-in spool will be required) inside Cofferdam - Connecting Flange (optional tie-in) TIE-IN (east point) Cofferdam - 2 nd Metrology and Fit-up new U-Spool end to east point only - Welding east point (tie-in spool will be required) inside Cofferdam - Connecting Flange (optional tie-in) Alternative using WELDING Alternative using WELDING Floaters installation on OLD U-Spool Coordinated Pipeline De- pressurized/shutdown Pipeline De-Gassing / N2 Purging Using WELDING/Flange Using WELDING/Flange Required special equipment for underwater BT installation To be coordinated with all construction preparation Drag / Lift the OLD U-Spool using AHT/Derrick Barge (TBA) In case tie-in using Flange is applied, lifting and lowering works to be minimized. TIE-IN (west point) - Deploy griplock connector and stabbed onto the west line - 1 st Metrology at west point - Fabrication tie-in spool complete with Flangemate adjuster on Board - Fit-up & Bolted TIE-IN (east point) - Deploy griplock connector and stabbed onto the east line - 2 nd Metrology at east point - Fabrication tie-in spool complete with Flangemate adjuster on Board - Fit-up & Bolted Using MECHANICAL CONNECTOR Alternative process if Tie-In using Mechanical Protector is applied. COLD WORK METHOD Pre-Commissioning

description

Simplified method statement for spool pipeline installation.

Transcript of Methods Statement-cold Work

Page 1: Methods Statement-cold Work

Mob. Personnel &

Equipments

Onshore Site Preparation

- Fabrication Pipe Ramp Launcher

- Fabrication new U-Spool (welding)

- Fabrication west/east gooseneck (optional to

be fabricated onshore/offshore)

- Fab. end flange for new spool & gooseneck

(optional)

- Hydrotest on fabricated new U-Spool (option)

Launching new U-Spool

- Install floaters & wire on new U-Spool

- Install stability guide on new U-Spool

- Side-boom/Backhoe required

Offshore Fabrication

- Welding West/East Gooseneck to new

U-Spool (optional using Flange)

Transportation to Offshore

- West/East Gooseneck (optional to be

fabricated on derrick barge)

- Material for Tie-In Spool (west/east)

- A-Frame (if any offshore lifting required

for tie-in)

Offshore Site Preparation

- New Trench preparation

(backhoe dredger, swamp backhoe, etc)

- Installation Cofferdam (west/east point)

– using sheet pile / sand bags, etc (optional)

- Develops access channel for new U-Spool (TBA

during Pre-Lay Survey)

Cutting Process

- West/East Point for future tie-in on the

existing mainline/OLD U-Spool

Remove OLD U-Spool

TIE-IN (west point) – Lift & Lower

- Lifting on WEST line & new U-Spool

end (west side) – check integrity

- 1st Metrology and Fit-up

- Welding west point (tie-in spool will be

required)

- Lowering (mainline & new U-Spool)

west side

- Connecting Flange (optional tie-in)

TIE-IN (east point) – Lift & Lower

- Lifting on EAST line & new U-Spool

(east side) – check integrity

- 2nd

Metrology and Fit-up

- Welding east point (tie-in spool will be

required)

- Lowering (mainline & new U-Spool)

east side

- Connecting Flange (optional tie-in)

Installation of Marking Piles for

new U-Spool

Installation of Protection Covers

- sand bags

- concrete mattress (option)

- rock dump (option)

Demob of

personnel/equipment

(except for as built survey)

As Built Survey

Pre-Lay Survey

Assumption:

� Shutdown Operation

� Pipeline De-Gassing to be done

� Low level construction HSE

� Inshore Replacement Location

� 4.5m minimum offset / parallel

distance (depend on trench width

and soil shear strength)

Towing to offshore

TIE-IN (west point) – Cofferdam

- Lowering new U-Spool in new Trench

- 1st Metrology and Fit-up new U-Spool

end to west/east point

- Welding west point (tie-in spool will be

required) inside Cofferdam

- Connecting Flange (optional tie-in)

TIE-IN (east point) – Cofferdam

- 2nd

Metrology and Fit-up new U-Spool

end to east point only

- Welding east point (tie-in spool will be

required) inside Cofferdam

- Connecting Flange (optional tie-in)

Alternative

using WELDING

Alternative

using WELDING

Floaters installation on

OLD U-Spool

Coordinated Pipeline De-

pressurized/shutdown

Pipeline De-Gassing / N2

Purging

Using WELDING/Flange

Using WELDING/Flange

Required special equipment

for underwater BT installation

To be coordinated with all

construction preparation

Drag / Lift the OLD U-Spool

using AHT/Derrick Barge

(TBA)

In case tie-in using Flange is applied, lifting

and lowering works to be minimized.

TIE-IN (west point)

- Deploy griplock connector and stabbed

onto the west line

- 1st Metrology at west point

- Fabrication tie-in spool complete with

Flangemate adjuster on Board

- Fit-up & Bolted

TIE-IN (east point)

- Deploy griplock connector and stabbed

onto the east line

- 2nd

Metrology at east point

- Fabrication tie-in spool complete with

Flangemate adjuster on Board

- Fit-up & Bolted

Using MECHANICAL CONNECTOR

Alternative process if Tie-In

using Mechanical Protector is

applied.

COLD WORK METHOD

Pre-Commissioning