METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE...
Transcript of METHOD STATEMENT - elmich.com.au · METHOD STATEMENT . ELMICH GREEN WALL . VERTICAL GREENING MODULE...
VGM MStmt Ver2012(Jan) Page 1
METHOD STATEMENT
FOR
ELMICH GREEN WALL
VERTICAL GREENING MODULE (VGM)
PREPARED BY ELMICH PTE LTD
VGM MStmt Ver2012(Jan) Page 2
METHOD STATEMENT
ELMICH GREEN WALL VERTICAL GREENING MODULE (VGM)
1. VGM
1.1 Assemble VGM modules leaving removable top open
1.2 Yellow triangle on front and back panels should be at the top
1.3 Insert custom-fit planting media bag into module
1.4 Fill media bag with planting medium flush with top of module
1.5 Fold mouth of media bag to prevent spillage of media and attach VGM cover
Media Bag Planting Medium VGM top open Assembled VGM
VGM MStmt Ver2012(Jan) Page 3
2. Pre-plant VGMs in Nursery Environment
2.1 Make slits in media bag and insert selected green wall plants,1 plant per aperture
2.2 If side planting is required, cut and remove centre disk of side panel
Make slit in Media Bag to insert plant
Centre disk removed
Centre disk of side panel Planted side panel
VGM MStmt Ver2012(Jan) Page 4
2.3 Allow at least 12 weeks for plants to firmly establish in nursery environment
2.4 Orientate plants to growth from a wall by progressively tilting VGM modules from horizontal to vertical over the 12 weeks
3. Prepare Wall for VGM Installation
3.1 Prime RC wall and/or construct framework (including waterproofing, painting, welding, etc) according to project requirements
RC Wall Staging Framework
VGMs tilted to orientate plants
VGM MStmt Ver2012(Jan) Page 5
3.2 Vertical beams of framework MUST correspond precisely with
VGM width for pilaster installation 3.3 Erect staging for work on high wall 4. Install Pilasters
4.1 Take vertical and horizontal wall measurements to determine position of first pilaster (anchor rails) according to project requirements
4.2 Drill holes at all securing points to required depth using drill bit
diameter corresponding with anchor used. Blow out dust and fragments
Beam does not correspond with VGM width
Setting Tool
Threaded Wedge Anchor
Stainless Steel Bolt
Stainless Steel Washer
Beam does not correspond with VGM width
Wedge, Washer & Bolt
VGM MStmt Ver2012(Jan) Page 6
4.3 Pilaster positions MUST register with width of VGM and all pilaster mounting slots align
4.3 Use assembled VGM modules to assist in accurate alignment of pilasters
4.5 Secure pilaster with stainless steel Stud or Wedge anchors tighten with torque wrench for RC wall or secure with stainless steel nuts and bolts for a constructed framework accordingly
Assembled VGM modules assist in alignment of pilasters
Pilasters
VGM
Pilaster
Stainless Steel Bolt & Washer Stainless Steel Bolt & Nut
RC Wall Framework
VGM MStmt Ver2012(Jan) Page 7
5. Irrigation and Fertigator System
5.1 Secure irrigation tubing to pilasters at specifically spaced holes provided along length of pilasters with cable ties
5.2 Insert arrow drippers into separate points either at rear or rear and front of each VGM to evenly distribute water supply
Cable-tie
Hole for securing tubing
Cable-tie
Hole for securing tubing
Distribute drippers evenly
Dripper to bottom half of VGM
Dripper to top half of VGM
Yellow triangle at top of VGM
VGM MStmt Ver2012(Jan) Page 8
5.3 Install irrigation system, including controller, solenoid valve,
pressure regulator, filters and valves linked to fertiliser supply, to project requirements or as advised, to deliver irrigation and fertiliser at programmable intervals for controlled durations
5.4 A rain sensor (optional) may be installed to override
programmed water release when the green wall receives sufficient water from rain
Solenoid Valve
Controller
Rain Sensor
Over-pressure valve
VGM MStmt Ver2012(Jan) Page 9
6. Mounting
6.1 Attach stainless steel mounting brackets to the 4 corners of
each VGM and cover each with its plastic cover
6.2 Secure mounting bracket to VGM with self-tapping screw to prevent bracket dislodgement before mounting
6.3 Anchor VGM to the pilasters beginning from the bottom row
Anchor VGM to Pilaster
Attach Self-tapping Screw here
Attach Self-tapping Screw here
VGM MStmt Ver2012(Jan) Page 10
6.4 Insert anti-lift arm between tops of mounted VGMs and push, from front to back, until arm clasp locks into pilaster slots
6.5 Plug connectors of manifold/s into corresponding emitters along horizontal irrigation tubing as each VGM row is installed
6.6 Install subsequent rows until all VGM rows are installed
Emitters along tubing
Emitters along tubing
Arm clasp locked into pilaster slots
Insert Anti-lift Arm
Plug connectors into emitters
Plug connectors into emitters
VGM MStmt Ver2012(Jan) Page 11
7. Inspection & Maintenance 7.1 Follow a routine inspection and maintenance regime 7.2 Ensure smooth running of irrigation system
7.3 Weed away invasive unwanted growth
7.4 Prune as necessary
Install bottom row followed by subsequent rows above
Plug in connectors to emitters as each VGM row is installed