METHOD STATEMENT FOR CLEANING AND …...pipework (one litre per 600 litres). Circulate for a minimum...
Transcript of METHOD STATEMENT FOR CLEANING AND …...pipework (one litre per 600 litres). Circulate for a minimum...
![Page 1: METHOD STATEMENT FOR CLEANING AND …...pipework (one litre per 600 litres). Circulate for a minimum of one hour and flush out with fresh mains water. If evidence of bacterial growth](https://reader030.fdocuments.us/reader030/viewer/2022041004/5ea710c4b925a06310195450/html5/thumbnails/1.jpg)
Add one litre of Fernox HP Cleaner per 600 metres of 40mm diameter pipework (one litre per 600 litres). Circulate for a minimum of one hour and flush out with fresh mains water.
If evidence of bacterial growth is still present after one hour consider double dosing and circulate for a further one hour. Flush out with the mains water until the water runs clear.
Final fillFill with Fernox HP-15 or HP-5 premix, or Fernox HP-15c or HP-5c concentrate diluted to the concentration required for the desired frost protection, according to the tables to the right.
Circulate the fluid to ensure that air is purged from the system according to the equipment manufacturers’ instructions.
Check frost protection levels using a Fernox Refractometer. Adjust the level as required with the addition of HP-15c or HP-5c*.
* Even if HP-15 or HP-5 premix is used, this can be under-dosed for frost protection if all of the flushing water is not completely removed with or before the addition of the premix.
www.fernox.com
METHOD STATEMENT FOR CLEANING AND COMMISSIONING GSHP SYSTEMS
Pre-commissioning cleaning
CFERNOX RECOMMENDS: Fernox HP-15c; Fernox HP-15; Fernox HP-5; Fernox HP-5c; Fernox HP-Cleaner;Fernox Refractometer.
Concentration HP-5c 10% 20% 30%Frost Protection -4˚C -9˚C -14˚C
Concentration HP-15c 33% 40% 50%Frost Protection -15˚C -22˚C -34˚C