Method Statement Esprit Control Equipment - Pole …myelectricavenue.info/sites/default/files/Esprit...

37
Method Statement Esprit Control Equipment - Pole Mounted HV/LV Prepared for: SSEPD Project No: 86000 Document Version: 3.1 Date: 06 July 2015

Transcript of Method Statement Esprit Control Equipment - Pole …myelectricavenue.info/sites/default/files/Esprit...

Method Statement Esprit Control

Equipment - Pole Mounted HV/LV

Transformer Structures

Prepared for: SSEPD

Project No: 86000

Document Version: 3.1

Date: 06 July 2015

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

CONFIDENTIAL - This document may not be disclosed to any person other than the addressee or any duly authorised person

within the addressee's company or organisation and may only be disclosed so far as is strictly necessary for the proper

purposes of the addressee which may be limited by contract. Any person to whom the document or any part of it is disclosed

must comply with this notice. A failure to comply with it may result in loss or damage to EA Technology Ltd or to others with

whom it may have contracted and the addressee will be held fully liable therefor.

Care has been taken in the preparation of this Report, but all advice, analysis, calculations, information, forecasts and

recommendations are supplied for the assistance of the relevant client and are not to be relied on as authoritative or as in

substitution for the exercise of judgement by that client or any other reader. EA Technology Ltd. nor any of its personnel

engaged in the preparation of this Report shall have any liability whatsoever for any direct or consequential loss arising from

use of this Report or its contents and give no warranty or representation (express or implied) as to the quality or fitness for

the purpose of any process, material, product or system referred to in the report.

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means electronic,

mechanical, photocopied, recorded or otherwise, or stored in any retrieval system of any nature without the written

permission of the copyright holder.

© EA Technology Ltd July 2015

EA Technology Limited, Capenhurst Technology Park, Capenhurst, Chester, CH1 6ES;

Tel: 0151 339 4181 Fax: 0151 347 2404

http://www.eatechnology.com

Registered in England number 2566313

Version History

Date Version Author(s) Notes

24/04/2013 1.6 Alex Halavin Version sent to SSE. Based on previous documents

provided by SSE.

29/07/2013 1.6.1 Mary Gillie Modifications after meeting with SSE

“Order of installation” inserted as new section 5

Sections 4.1 On-site installation works, 4.2

Detailed Physical Inspection renumbered sections

6 and 5 respectively. Section 5 Equipment

Installation to Section 8 etc.

Schematic diagram for Esprit connection to GMT

utilising MCCB and RCD removed

Recommendations re: access requirements

between Esprit monitor controller and GMT or

PMT rationalised

Requirement to ensure appropriate shielding of

terminals in LV Pillars inserted

CT and Rogowski Coils – warning added re:

installation of Esprit and associated connections

not to introduce additional hazard or interfere

with general operation

Commissioning: “Esprit equipment fitted” advice

label content – “Instructions in case of the unit

failing” requirement inserted

Minor amendments and clarifications to installation

instructions for PLC and CT or Rogowski Coils re:

routing and terminations

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

CONFIDENTIAL - This document may not be disclosed to any person other than the addressee or any duly authorised person

within the addressee's company or organisation and may only be disclosed so far as is strictly necessary for the proper

purposes of the addressee which may be limited by contract. Any person to whom the document or any part of it is disclosed

must comply with this notice. A failure to comply with it may result in loss or damage to EA Technology Ltd or to others with

whom it may have contracted and the addressee will be held fully liable therefor.

Care has been taken in the preparation of this Report, but all advice, analysis, calculations, information, forecasts and

recommendations are supplied for the assistance of the relevant client and are not to be relied on as authoritative or as in

substitution for the exercise of judgement by that client or any other reader. EA Technology Ltd. nor any of its personnel

engaged in the preparation of this Report shall have any liability whatsoever for any direct or consequential loss arising from

use of this Report or its contents and give no warranty or representation (express or implied) as to the quality or fitness for

the purpose of any process, material, product or system referred to in the report.

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means electronic,

mechanical, photocopied, recorded or otherwise, or stored in any retrieval system of any nature without the written

permission of the copyright holder.

© EA Technology Ltd July 2015

EA Technology Limited, Capenhurst Technology Park, Capenhurst, Chester, CH1 6ES;

Tel: 0151 339 4181 Fax: 0151 347 2404

http://www.eatechnology.com

Registered in England number 2566313

Date Version Author(s) Notes

07/11/2013 1.7 Colin Morris Document revised to cover PMT installations only,

formerly generic title appended with “Pole

Mounted LV Substations”

References to devices, equipment, cabinet,

enclosure etc. reviewed and amended where

necessary to improve consistency and clarity

throughout the document

References to sensing equipment being able to

cope with through fault currents removed

(relevant to design, but not to a method

statement).

Schematic diagram for Esprit connection to GMT

removed

Block diagram for wiring of Esprit connections for

GMT installations removed

All references to CTs replaced with references to

Rogowski coils instead

Sections covering PLC and CT/Rogowski coil

connections for GMT removed

Appendix I in previous version (containing

Drummond G Clamp information) removed

SSEPD abbreviation standardised for consistency

throughout document

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

CONFIDENTIAL - This document may not be disclosed to any person other than the addressee or any duly authorised person

within the addressee's company or organisation and may only be disclosed so far as is strictly necessary for the proper

purposes of the addressee which may be limited by contract. Any person to whom the document or any part of it is disclosed

must comply with this notice. A failure to comply with it may result in loss or damage to EA Technology Ltd or to others with

whom it may have contracted and the addressee will be held fully liable therefor.

Care has been taken in the preparation of this Report, but all advice, analysis, calculations, information, forecasts and

recommendations are supplied for the assistance of the relevant client and are not to be relied on as authoritative or as in

substitution for the exercise of judgement by that client or any other reader. EA Technology Ltd. nor any of its personnel

engaged in the preparation of this Report shall have any liability whatsoever for any direct or consequential loss arising from

use of this Report or its contents and give no warranty or representation (express or implied) as to the quality or fitness for

the purpose of any process, material, product or system referred to in the report.

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means electronic,

mechanical, photocopied, recorded or otherwise, or stored in any retrieval system of any nature without the written

permission of the copyright holder.

© EA Technology Ltd July 2015

EA Technology Limited, Capenhurst Technology Park, Capenhurst, Chester, CH1 6ES;

Tel: 0151 339 4181 Fax: 0151 347 2404

http://www.eatechnology.com

Registered in England number 2566313

Date Version Author(s) Notes

25/11/13 1.9 Colin Morris Reference to earth connection for the [doubly insulated cabinet (Esprit + Envoy)] expanded and exemption for plastic cabinet added

Appendix II picture and diagram replaced with current versions from Esprit Installation Guide (MC) Issue 5

Modified to reflect SSE / EATL teleconference discussion on 04/11/13. o Requirement for PMT locations to be surveyed

before works proceed added o Neutral earth requirements for variants PMT,

non-PMT pole added inserted o Esprit cabinet alternative pole mounting

location requirements added o Voltage / PLC connections for variants PMT

pole, non-PMT pole inserted o Requirement for fused leads to be used added

into main text o Current sensor fitment and securing and

constraint requirements added

List of SSE document references specific to PMT

installation added

27/11/13 2.0 Mary Gillie Review version

18/12/13 2.1 Mary Gillie review in light of information from Lyndhurst

Appendix II “Typical arrangements for a PMT”

added

08/01/2014 2.2 Colin Morris Based on Gideon Evans’ review of v2.0 and

including changes from v2.0 to v2.1

13/01/2014 2.3 Mary Gillie Reviewed changes

02/04/2014 2.4 Mary Gillie Alterations made after discussions at New Forest

Depot. Including use of a commando socket and

mounting to arrangement to pole.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

CONFIDENTIAL - This document may not be disclosed to any person other than the addressee or any duly authorised person

within the addressee's company or organisation and may only be disclosed so far as is strictly necessary for the proper

purposes of the addressee which may be limited by contract. Any person to whom the document or any part of it is disclosed

must comply with this notice. A failure to comply with it may result in loss or damage to EA Technology Ltd or to others with

whom it may have contracted and the addressee will be held fully liable therefor.

Care has been taken in the preparation of this Report, but all advice, analysis, calculations, information, forecasts and

recommendations are supplied for the assistance of the relevant client and are not to be relied on as authoritative or as in

substitution for the exercise of judgement by that client or any other reader. EA Technology Ltd. nor any of its personnel

engaged in the preparation of this Report shall have any liability whatsoever for any direct or consequential loss arising from

use of this Report or its contents and give no warranty or representation (express or implied) as to the quality or fitness for

the purpose of any process, material, product or system referred to in the report.

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means electronic,

mechanical, photocopied, recorded or otherwise, or stored in any retrieval system of any nature without the written

permission of the copyright holder.

© EA Technology Ltd July 2015

EA Technology Limited, Capenhurst Technology Park, Capenhurst, Chester, CH1 6ES;

Tel: 0151 339 4181 Fax: 0151 347 2404

http://www.eatechnology.com

Registered in England number 2566313

Date Version Author(s) Notes

07/04/2014 2.5 Colin Morris Figure 1 amended to show revised connection arrangement with fuses inside cabinet. Enclosure dimensions updated.

10/06/2014 2.6 Mary Gillie Updated with comments from John Baker SSE

2.6 Andrew Moon

Updated with comments from John Baker SSE

09/07/2014 2.7 Mary Gillie Reviewed

27/08/2014 2.9 Andrew Moon

Slight changes incorporating comments from John Baker. These include removing bolt references in Section 9 and fused leads.

13/11/2014 3.0 Andrew Moon

Added sub section regarding remote Esprit commissioning via laptop & 3G dongle

06/07/2015 3.1 Andrew Moon

Added section 13 on MC and Rail 350 decommissioning

Final Approval

Approval Type Date Version EA Technology Issue Authority

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page v

Contents

Version History .............................................................................................................................................................................. i

Final Approval .............................................................................................................................................................................. iv

Contents ........................................................................................................................................................................................... v

1. Background ...................................................................................................................................................................... 7

2. Introduction ..................................................................................................................................................................... 7

3. Management of safety ............................................................................................................................................... 8

4. Installation ....................................................................................................................................................................... 9

4.1 First installation – Lyndhurst ............................................................................................ 9

4.2 General requirements for installation .............................................................................. 9

4.3 Order of installation ........................................................................................................ 10

4.4 Detailed visual inspection ............................................................................................... 10

4.5 On-site civil installation works ........................................................................................ 12

4.6 Mounting the cabinet ...................................................................................................... 13

4.7 Installation of Rogowski coils ......................................................................................... 13 4.7.1 Rogowski coils installation instruction at the PMT............................................ 13

4.8 PLC injection point, Esprit power supply installation ................................................... 13 4.8.1 PLC injection point, Esprit power supply (general) ........................................... 13

4.9 Voltage connections installation at a PMT - Specific ..................................................... 16 4.9.1 Installation on PMT pole ...................................................................................... 16 4.9.2 Installation one span out ..................................................................................... 16 4.9.3 Site specific bespoke design ............................................................................... 16 4.9.4 Voltage connections –PMT pole .......................................................................... 16 4.9.5 Voltage connections – one span out .................................................................. 16 4.9.6 Fused leads ........................................................................................................... 17

4.10 Completion ....................................................................................................................... 17

5. Commissioning ........................................................................................................................................................... 18

5.1 Remote commissioning ................................................................................................... 18

6. Decommissioning of the Esprit equipment ............................................................................................... 19

6.1 General requirements for removal ................................................................................. 19

6.2 Decommissioning ............................................................................................................ 19

6.3 Order of removal.............................................................................................................. 20

6.4 Removal of PLC injection points ..................................................................................... 20

6.5 Removal of Rogowski Coils ............................................................................................. 22

6.6 Removal of monitor controller and Rail350 enclosures ............................................... 23 Step 1 – Disconnection of Enclosure Leads Connected to the SIPCs ........................... 23 Step 2 – Disconnection and removal of the Rail350 power supply and modbus

cables .................................................................................................................... 24 Step 3 – Disconnection of the Rail 350 RC cables......................................................... 25 Step 4 – Removal of MC enclosure and Rail350 units from mounting positions ....... 26

6.7 Removal of cable routes and ducting ............................................................................. 27

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page vi

6.8 Site Inspection .................................................................................................................. 27

Appendix I Esprit Monitor Controller ...................................................................................................................... 29

Our Expertise .............................................................................................................................................................................. 36

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 7 of 37

1. Background

This method statement, which responds to the requirements set out by Scottish and Southern Energy

Power Distribution (SSEPD) and EA Technology Limited, has been prepared by EA Technology

Limited, to provide the instructions that should be followed in order to connect Esprit control and

monitoring equipment at pole mounted HV/LV substations.

The latest update to version 3.1 incorporates section 6, “Decommissioning of the Esprit equipment”

into this method statement, providing instructions that should be followed in order to decommission

the Esprit control and monitoring equipment has been included.

2. Introduction

This method statement defines the principles that should be followed in order to connect Esprit

equipment1

.

All equipment should be installed DEAD when possible and LIVE only when it is safe to do so and if

justified by a written risk assessment.

Where it is possible to install this type of equipment DEAD, whilst maintaining supplies to customers

connected to the network to be controlled, this option must be taken. However, it is recognised that

in many cases it will be impractical to make the distribution transformer, the LV pillar or cabinet

DEAD and therefore the guidance within this work instruction must be followed. In order to minimise

time working on a LIVE system, Esprit equipment connection to the energised part of the network

should be carried out last.

Where appropriate, instruction for the installation of equipment will be specific to the chosen

location. The following generic instructions regarding installation will generally apply

1

For the purposes of this document, relating to the installation of the equipment on the trial networks of the My Electric

Avenue project, the Esprit equipment comprises the cabinet containing the EA technology Esprit Monitor Controller along

with a Nortech Envoy mini RTU, the external connections for load monitoring, supply and plc injection plus the Rail 350 unit

and associated connection equipment.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 8 of 37

3. Management of safety

The following requirements will be complied with at all times throughout the installation process.

1. Safety rules and other procedures must be followed whilst undertaking work in accordance

with this work instruction. The following documents are particularly relevant and must be

adhered to at all times:

a. Safety precautions and procedures applicable to low voltage systems as detailed in

section 8 of the Operational Safety rules.

b. When work is to be undertaken in proximity to live LV conductors it is necessary to justify

this decision. A risk assessment complying with PR-PS-421, Justification for Live Low

Voltage Working is therefore required.

2. Prior to commencing work a full assessment of risk will be undertaken in accordance with

SSE (or relevant DNO) Injury Prevention Process. This will include a stage one assessment in

advance of work commencing and a stage two on site assessment which shall be undertaken

prior to work commencing. This assessment must be agreed by all members of the working

party and signed off accordingly.

3. The working party will consist of at least two persons who will be appropriately authorised

to undertake the proposed installation work in accordance with SSE (or relevant DNO)

Operational Safety Rules.

4. System control will be advised prior to work starting and upon completion of the work.

5. Personal Protective Equipment will be worn in accordance with SSE PPE matrix (see S&E

Manual Section 1, Appendix 1 of WI-HSE-001) or relevant DNO PPE policy and safety

procedures.

6. The following reference documents are also relevant for pole mounted installations:

SP-PS-140: Specification for conductor fittings and associated apparatus for use with

LV aerial bundled conductor

TG-PS-569: ABC tension and non-tension fittings, lugs, end caps, main joints and

cable connections

PR-PS-045: Procedure for Safe Access to wood Poles

PR-PS-431: Procedure for Live Working on Low Voltage Overhead Networks

TG-PS-529: Conductors to be used on Pole Mounted Transformers - LV connections

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 9 of 37

4. Installation

4.1 First installation – Lyndhurst

This method statement is for installation of the Esprit technology that is under development. The

method statement is written to encompass the majority of arrangements of Pole Mounted

Transformers (PMTs). However, the PMT where the Esprit will be installed is sited at Lyndhurst.

The characteristics of the PMT are:

One set of fuses leading to 3 spurs.

The PMT is mounted on robust H pole but there are overhanging trees.

The 3 spurs separate from a pole approximately 4 metres from the transformer H pole.

The conductors are ABC and require cable piercing.

4.2 General requirements for installation

This method statement provides details regarding how to install Esprit equipment safely on pole

mounted transformer structures. It focuses on the methods to be followed in order to make the

necessary current connections and Power Line Communication (PLC) injection points. The PLC

injection points also provide the source of power supply for the Esprit control electronics, and for

any data logging / monitoring equipment as necessary. This method statement provides guidance

regarding the suitable positioning and fixing of Esprit equipment for LV overhead line and PMT

installations.

The below installation instructions shall be followed. Some site specific modifications may be

required.

1.1. Esprit equipment, specifically the Esprit monitor controller, will always be installed in

accordance with manufacturer’s instructions (See I2

EV Esprit Monitor Controller Installation

Guide). It will be contained in its own enclosure comprising of a doubly insulated cabinet

with a non-conducting exterior, no external metallic frame, and typical dimensions of 750h

x 550w x 300d which will also enclose the Envoy communications unit. Specific upstream

system communication requirements are not covered within this method statement. This is

referred to as the [doubly insulated cabinet (Esprit + Envoy)]

1.2. Current References – All 3 phase (no neutral) current values will be obtained by using

approved fully insulated sensing transducers (Rogowski coils). The sensors will be installed

around the cable connections at suitable locations as close as practically possible to the

[doubly insulated cabinet (Esprit + Envoy)]. All equipment used must have the necessary

approvals.

1.3. Where a generic installation instruction is to be followed, a full assessment of options for

the connection of current sensors will be made prior to any work commencing.

1.4. Prior to work commencing, a visual inspection of the connection points will be carried out

with particular attention being made to positions where current sensors and PLC injection

connections are to be installed. If there is any doubt regarding the condition of the

connection point, work shall not commence and the issue shall be referred to the person

responsible for instructing the installation.

1.5. In particular, all PMT installations require a survey before works proceed to identify:

Location of the HV and LV earths.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 10 of 37

Type of conductor / insulation on outgoing side of fuse

Routing and connectivity of mains and services

Safe access to pole and pole working (safety clearances)

Consents - pole mounting is not contentious, but access to poles is subject to the terms

and conditions agreed in the respective wayleaves and easements; in all cases the

landowner should be informed prior to the start of work.

Agreement for any tree cutting required.

4.3 Order of installation

The exact arrangements for installation will depend on the site. A site survey will be required in

each case to finalise arrangements. The order of installation and connections will be the same in

each case:

1. Detailed visual Inspection

2. Any civil work required

3. Connection of Rogowski coils

4. PLC injection/power supply

These are described in detail in the Sections 4.4 to 4.9.

4.4 Detailed visual inspection

In addition to the requirements detailed in Sections 0 (

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 11 of 37

Management of safety) and 4.2 (General requirements for installation) a visual inspection shall be

carried out:

1. A detailed visual inspection shall include:

All parts of the [Eldon (Esprit + Envoy) cabinet] or other point of measurement / supply

including checks for damage to insulation, overheating (present and historic).

Overhead lines and connection methods; this shall include the inspection of all assets to

identify any damage/ breakdown of insulation and overheating issues. Identify any need

for tree cutting or other clearing.

Inspection of abnormal connections.

2. Where an unsafe situation is identified, all work on site will cease and appropriate repairs

will be instigated. No Esprit equipment will be installed until repairs have been completed

and any unsafe situation has been rectified.

3. Wherever possible the [doubly insulated cabinet (Esprit + Envoy)] will be fixed in its

permanent position before installation of the associated connections commences.

Care should be taken to ensure that any equipment installed will not interfere with or prevent the

safe operation of any equipment located in the substation and the possibility of damage to the

insulation is minimised.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 12 of 37

4.5 On-site civil installation works

If there is sufficient clearance to the High Voltage Equipment (as in Lyndhurst), the HV will be live

otherwise it must be made dead. Installers will be working under SSEPD safety instructions.

1. Carry out tree cutting or other clearing if access to the pole is not clear.

2. Check the equipment labelling that the equipment: ([doubly insulated cabinet (Esprit +

Envoy)], Rogowski coils, PLC connections are of suitable for the proposed location.

3. For PMT poles, the [doubly insulated cabinet (Esprit + Envoy)] should be mounted above the

anti-climb guard (ACG), preferably on the opposite side of the pole to the fusegear. In

practice, the position will be determined by available pole space avoiding existing equipment

and conductors.

4. For non PMT poles, the [doubly insulated cabinet (Esprit + Envoy)] should be mounted high

enough to ensure it is not readily accessible to third parties, but low enough to be 1.5m clear

of live conductors and equipment. Ideally the cabinet should be accessible for software

modifications via a step ladder without working on the top two steps. However this may not

always be possible whilst maintaining safe heights and clearances.

5. A clearly visible "danger of death" sign should be fitted to the cabinet if not already present

on the pole the cabinet is to be mounted on.

6. ACDs shall be installed generally in accordance with ENA TS 43-90, where there is a

probability of climbing access using the installed equipment.

The [doubly insulated cabinet (Esprit + Envoy)] will be attached to the pole using suitable clamps

that allow for the passage of any cabling down the pole without crimping or crushing. To avoid the

risk of connecting the LV and HV earth, the [doubly insulated cabinet (Esprit + Envoy)] should be

mounted to brackets that do not allow the mounting steelwork to be in a position where it can make

direct contact with the HV steelwork or earth. This can be achieved by using either a stainless steel

bracket coated in 3.4 mm cross linked Polyethylene (XLPE) or a stainless steel bracket with 3.4mm

Nylon bushings in the boltholes for the 10mm supporting coach bolts. This thickness of electrical

insulation is designed to withstand a voltage of 5 kV. This bracket specification shall be termed

‘suitably insulated’ for the remainder of the document.

Care must be taken to ensure that installation of Esprit equipment and associated connections does

not introduce additional hazards or interfere with the general operational requirements of the PMT.

Where necessary cable ties and suitable flexible conduits should be used to ensure a tidy installation

is achieved with sufficient protection against accidental damage.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 13 of 37

4.6 Mounting the cabinet

The cabinet will be provided with a suitably insulated bracket that can be fixed to the pole by 10mm

diameter coach screws at the top and bottom. The coach screws should be 75mm long, as they will

avoid the need to drill through the pole which may introduce risks to the PMT equipment and cables.

1. Mark points where bolts will be inserted into the pole.

2. Drill holes for bolts.

3. Use ‘coach screws’ penetrating right through the pole.

4. Hang cabinet on bolts and secure.

4.7 Installation of Rogowski coils

There is no set arrangement for connection of the Rogowski coils and therefore great caution should

be taken during their installation. The proposed method is described below.

4.7.1 Rogowski coils installation instruction at the PMT

1. Install 3 current sensors (one per phase).

2. Highlight the cables and conductors that require to be monitored as per the written work

instruction.

3. For non PMT pole installations, current sensors may be harder to fit on ABC if the cores have

not already been spread out. These conductors may be under tension - seek advice as to test

and demonstrate the spreading of conductors under tension for the purpose of fitting

Rogowski coils to write a method statement for this process. Note that the cables at

Lyndhurst are already spread on the pole adjacent to the H pole carrying the transformer and

therefore this process is not document here.

4. Starting with the nearest or furthest cable, install and secure the coil / transducer in position

making sure that the arrows on the coil are pointing in the direction that the load is flowing

as per the manufacturer’s instructions. Install the remaining coils / transducers working from

the back towards the front.

5. Once installed, position all coil / transducer cables in their final location – in line with

manufacturer’s instructions.

6. Current sensors should be constrained from moving in the wind (vibration will cause wear,

noise etc.).

7. Current sensor connecting leads to be tagged (for identification at the end to be connected

to the Esprit, before tying together) to limit movement, and are to be made to look neat, and

routed to avoid interfering with existing fuse gear. Where possible, cable guards will be used

to protect all of the leads.

4.8 PLC injection point, Esprit power supply installation

Reminder - This is a Live Network, appropriate PPE must be worn at all times and only approved

insulated tools shall be used, as defined in SSE’s safety policies for working on LV overhead

lines.

4.8.1 PLC injection point, Esprit power supply (general)

The Esprit monitor controller power supply and PLC injection points are combined (Figure 1). For

pole mounted installations, cable piercing or bare wire connectors will be required for PLC injection

and the Esprit power supply. In all cases, the connecting leads will be connection to an IP 67 rated

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 14 of 37

‘commando socket’ fused with a 2A fuse to prevent any failure of the new equipment affecting

existing supplies.

The Esprit control equipment requires PLC injection points; one per phase and neutral (3P+N)

connection.

The connections to the 3 phases and neutral provide the power supply and earthing. Therefore the

connection method used should be suitable approved permanent connections.

The lead will be connected to one side of a commando socket. Connect the bare ends to IPC

connectors (or other suitable connection equipment. Note that the joint made may need to be

packed given that the leads will be 4mm or smaller.

Voltage connections should only be made once all other ends of each cable have been made off and

shrouded to prevent accidental contact with staff or conductors. The commando socket will have a

suitable shroud.

Where necessary cable ties and suitable flexible conduits should be used to ensure a tidy installation

is achieved with sufficient protection against accidental damage. Where possible a cable guard will

be used to protect all leads.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 15 of 37

Figure 1. Schematic diagram representing electrical connection to the PMT. The black outlined box

represents the doubly insulated cabinet (Esprit + Envoy) cabinet.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 16 of 37

4.9 Voltage connections installation at a PMT - Specific

Voltage connection should be made on the outgoing side of the fuse gear.

There are three options available for the installation of the voltage connections:

On the PMT pole

On a pole one span out

Site specific bespoke design

4.9.1 Installation on PMT pole

Install the [doubly insulated cabinet (Esprit + Envoy)] on the PMT pole in the following situation,

where

The installation, including access to the neutral conductor, can be made without infringing

the HV clearance.

The pole is robust and stable such that it is safe to install the [doubly insulated cabinet

(Esprit + Envoy)].

4.9.2 Installation one span out

Install the [doubly insulated cabinet (Esprit + Envoy)] one span out in the following situation:

There is only one spur or the total current required for monitoring purposes can be

measured one span from the transformer.

The pole is robust and stable such that it is safe to install the [doubly insulated cabinet

(Esprit + Envoy)].

4.9.3 Site specific bespoke design

In the event that specific site conditions prevent the use of either of the above options, this method

statement is unsuitable to cover the installation works and a site specific bespoke design and

associated method statement will be required.

4.9.4 Voltage connections –PMT pole

For voltage connections adjacent to PMT fuse gear, conductors will either be ABC or conventional

double insulated (Henlite). For the power and PLC connections:

For 50 or 95mm² aluminium aerial bundled conductor, insulated with a single layer of XLPE

or 50,70,95 or 120mm² PVC double insulated aluminium conductor use SSE approved IPC

connectors.

For conventional conductors, stripping the outer insulating layer, then use IPC connectors.

This process is subject to approval and not required at Lyndhurst. This is not an approved

practice in SSEPD and would need to be approved on a case-by-case basis.

In all cases, check that the arrangement is practical for repairs or post project removal.

4.9.5 Voltage connections – one span out

For non PMT pole installations, voltage connections will be made off on ABC or bare conductor. ABC

connections can be fitted using IPC connectors. For bare conductors, pre-existing overhead line

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 17 of 37

service components used for service joints should be used (line taps for bare conductor). The use

of line taps will need a special dispensation as SSE do not use them as standard.

4.9.6 Fused leads

Fused leads (4mm) will be used, as indicated in 4.8.1. The fuses will be on the OHL side of the

commando socket. Fuse ratings should not exceed 2 Amps.

Where necessary cable ties and suitable flexible conduits should be used to ensure a tidy installation

is achieved with sufficient protection against accidental damage.

4.10 Completion

Ensure that the Esprit control box is securely fixed in its final location and that all cables are secured

along the length by means of cable ties or ducting with identification tags fitted to all cables.

Ensure that all connections at the Esprit control box and PLC connection sockets are secure.

Fix notice to the pole with information about the equipment and emergency number.

Refer to Section 0 ‘Commissioning’ for the procedure with regard to overall commissioning and

labelling requirements.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 18 of 37

5. Commissioning

Commissioning of the Esprit equipment shall be in accordance with the commissioning method

statement (latest version available from EA Technology Limited)

The installer will ensure that the SSEPD network information systems (GIS) are updated appropriately

to record the installation of the monitoring equipment and any modifications made to the PMT. A

note annotated to the pole (as shown on GIS) to say "Monitoring Fitted" would be helpful to the

majority of users.

A record shall be kept for all aspects of commissioning.

5.1 Remote commissioning

Should the Esprit system require remote commissioning, a 3G connected laptop will be placed within

the MC enclosure and connected to the RS232 port via a serial cable. The serial cable and laptop will

be provided onsite by an EA Technology representative.

When in place, the enclosure door should be shut and secured. Once commissioning via the laptop

has taken place, the laptop must be removed, swapping the serial cable from the laptop with the

serial cable from the envoy unit at the service port shown in Figure 9. Once the MC shows an active

connection via the Nortech website, the MC enclosure door can be shut and secured. An EA

technology representative will confirm this.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 19 of 37

6. Decommissioning of the Esprit equipment

Before reading through this section on decommissioning, persons carrying out the decommissioning

must read and understand Section 0 – The Management of Safety, within this document.

Decommissioning persons must adhere to these safety instructions at all times. The

decommissioning work will require live working and therefore must be carried out by either SSEPD

staff or 3rd

party contractors who are authorised for live working.

Suitable safety gear and insulated tools must be used, these must include:

An Inner layer of live working gloves consisting of insulating material (EN60903 Class 0 or

above)

Over gloves capable of providing mechanical protection (compliant with EN388).

A Class 0 Arc Flash safety helmet with safety shield, compliant with the following standards

o EN397:2012 – Industrial Safety Helmets

o EN50365: 2002 - Electrically insulating helmets for use on low voltage installations

o EN166: 2001 – European Standards and Markings for Eye and Face Protection

Arc Flash Protective Coveralls, compliant with the following standards:

o BS EN ISO 13688:2013 - Protective clothing. General requirements

o EN 61482-1-1 (12.4 Cal/cm²) - Live working. Protective clothing against the thermal

hazards of an electric arc.

o EN 61482-1-2:2007 (Class 1) - Live working. Protective clothing against the thermal

hazards of an electric arc.

o IEC 61482-2- Live working. Protective clothing against the thermal hazards of an

electric arc.

o EN ISO 11612 (A1, A2, B1, C1) - Protective clothing - Clothing to protect against

heat and flame

o EN61482-1-2:2007 - Live working. Protective clothing against the thermal hazards of

an electric arc. Test methods. Determination of arc protection class of material and

clothing by using a constrained and directed arc.

Complete range of insulated tools for live working up to 1 000 Volts according to IEC 60900

standard

Steel toe capped insulating boots compliant with:

o EN 50321 Live working up to 1000 volts AC

o EN345-1 & EN 50321 class 0

Suitable safety equipment for working at height

6.1 General requirements for removal

Prior to work commencing, a visual inspection of the connection points will be carried out, with

particular attention being made to positions where current sensors and Service Insulation Piercing

Connectors (SIPCs) have been installed. If there is any doubt regarding the safe removal of the Esprit

equipment, work shall not commence. The issue shall be referred to the person responsible for

instructing the installation.

6.2 Decommissioning

The substation shall be returned to its original state, prior to the Esprit equipment installation.

The removal contractor or DNO representative will ensure that the SSEPD network information

systems (GIS and PLACAR) are updated appropriately to record the removal of the Esprit control and

any monitoring equipment and all (if any) modifications made to the pole mounting equipment.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 20 of 37

6.3 Order of removal

The exact arrangements for removal will depend on the site. Knowledge of each EV cluster PMT and

LV feeder will be used to finalise arrangements with the relevant stakeholders. The order of

disconnections and equipment removal will be the same in each case:

1. Esprit unit commando plug disconnected from PLC injection points (SIPCs of 3) by the

disconnection of the commando power supply socket

2. Disconnection of Rogowski coils from Esprit enclosure socket

3. Disconnection of Rail 350 monitor power supply cable from Esprit enclosure

4. Disconnection of Rogowski Coils from Rail 350 terminals

5. Removal of Rail 350 and Esprit Brackets and Enclosures

6. Removal PLC injection/power supply connections from SIPCs through to a commando

socket

7. Removal of SIPCs from ABC cables

8. Removal of cable routes and ducting

9. Any required civil restoration works

10. A detailed visual inspection

The work required for each of the steps and the options available are described in the next

subsections.

The order that the cables should be disconnected can be summarised as follows.

1. Disconnect the PLC injection supply cable from the SIPCs by cutting the supply cables

below the IPCs and then apply heat shrink caps to the cable core stubs. This should be

carried out one phase at a time, then the neutral last in line with the pre-existing OH Line

procedure for disconnection of a service.

2. Disconnect the PLC injection/power supply by unplugging the commando plug and socket.

3. Rogowski coils are to be removed, starting with the nearest and ending with the rearmost

from the removal contractors position.

4. Remove protective cable capping from the feeder pole, then remove the PLC

injection/supply leads and RC/CT leads for the Esprit and Rail 350 units. Remove from

cable routes then coil and tie the leads. Do not coil less than the minimum bending radii of

the leads.

5. Remove commando socket from the LV feeder pole and move all coils, power and current

sensor leads away from LV pole and store in a secure and dry environment.

6.4 Removal of PLC injection points

Care must be taken to ensure that the removal of PLC Injection Point equipment and connections

does not introduce additional hazards or interfere with the general operational requirements of the

LV feeder phase conductors and fuses and their operation. The commando plug, connected to the

Esprit equipment, must be disconnected before the SIPCs are removed.

Upon satisfactory inspection and identification of the cable access route, the ABC cable can be

prepared for disconnection of the SIPCs supply cable cores and the Esprit monitor controller power

supply. The removal should begin with the identification of SIPC locations on insulated ABC phase

conductors where the phase, neutral and earth connections have been made off to the MC using the

SIPCs.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 21 of 37

Figure 2. Insulated ABC phase conductors with SIPCs installed at the Lyndhurst PMT LV pole.

Removal of the PLC injection points should proceed as follows:

1. The supply cable cores should be cut and heat shrink caps applied to the cable core stubs.

This should be carried out one phase at a time, with the neutral last, in line with the pre-

existing OH Line procedure for disconnection of a service.

2. Physical removal of the Esprit PLC injection/power supply cable by removing the fuse-box

restraining strap.

3. Remove of the cable capping from the LV pole and any other PLC injection/power supply

cable restraints.

4. Lower the fuse box to ground, then coil and pack the PLC injection/power supply cable, fuse

box and commando socket into a pre-labelled box (supplied).

5. The ABC phase conductors should now be restored to their original state except for the SIPCs

remaining in situ.

Service Insulation

Piercing

Connectors for

Insulated

Overhead Lines

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 22 of 37

Figure 3. Insulated ABC phase conductors with SIPCs installed at the Lyndhurst PMT LV pole.

6.5 Removal of Rogowski Coils

Figure 4. Two sets of RCs installed at the Lyndhurst PMT LV pole.

PLC

Injection/Power

supply fuse box

RC set for the

Rail 350

RC set for the

Esprit MC

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 23 of 37

There is no set arrangement for the disconnection of the Rogowski coils and therefore great caution

should be taken when removing these devices. Where a Rail 350 unit is present, two sets of RCs will

be installed; one set for the Esprit MC (blue) and one set for the Rail 350 units (green). These are

picture in Figure 4.

Figure 5. MC Rogowski coil retaining clip.

Remove the MC RCs, by squeezing on the retaining clips at the location shown in Figure 5. The Rail

350 RCs can be remove by pulling apart the black plastic socket and plug located on the green coils.

Remove both the RCs for the MC and the RC for the Rail 350 units at the same time. When removing

RCs, take care not to strike any phase conductors when the RC loops separate. LV ABC phase

conductors may only be flexed or moved using very gentle force.

All RC leads running up to the ABC cables, should now be removed. Where necessary, cable ties and

RC cable capping should be unclipped as a last step to ensure a no loose cable poses an

entanglement hazard.

6.6 Removal of monitor controller and Rail350 enclosures

Step 1 – Disconnection of Enclosure Leads Connected to the SIPCs

The Esprit substation equipment should be removed in a de-energised state. Therefore, the Esprit

enclosure commando plug should be disconnected from PLC injection (of 3) through the

disconnection of the commando power supply socket before any removal working commences.

The Esprit Rogowski coils should now be disconnected from the RC socket on the MC enclosure

casing.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 24 of 37

Step 2 – Disconnection and removal of the Rail350 power supply and modbus cables

Figure 6. Power supply terminal box within MC enclosure.

To remove the Esprit enclosure, the Rail 350 monitor power supply cable should be disconnected

from the terminal block (shown in Figure 6), then unclipped from any retaining cable ties and pulled

though the gland in the Enclosure base. The loose Rail 350 monitor power supply cable should be

coiled and taped together, removing any entanglement hazard.

The Rail 350 Modbus cable is to be removed at this stage. This can be achieved by removing the

green terminal block from the envoy unit base and unscrewing the Modbus cable cores from the

terminals, located in the green terminal block. The Modbus cable should then be unclipped from

any restraining ties with the MC enclosure and pulled through the Modbus cable gland, situated on

the MC enclosure base.

Esprit 3PNE

Power Cable

Back Plate

Mounting Screw

Rail 350 Modbus

Cable

Rail 350

3PNE Power

Cable

Esprit 3PNE

Power Cable

Back Plate

Mounting Screw

Rail 350 Modbus

Cable

Rail 350

3PNE Power

Cable

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 25 of 37

Figure 7. Esprit MC enclosure base.

Step 3 – Disconnection of the Rail 350 RC cables

The Rogowki coils for the Rail 350 units, should be disconnected from the Rail 350 RC terminals

during this step. To achieve this, the Rail 350 enclosure cover should be removed by unscrewing the

four plastic retaining screws, which are located below the transparent lid. The cover be should set

aside in a safe place. The RC leads should now be removed from Rail 350 terminal block (pictured

in Figure 8) and pulled though gland situated in the bottom plate of the Rail 350 enclosure. Any

loose RC cable should be made safe, ready for eventual removal from the LV ABC cable. The specific

terminals to be disconnected are L1+, L1 -, L2 + L2 -, L3 +, L3 – and 3 off SCR.

Rail 350 Modbus

gland and cable MC RC cable

plug and socket MC enclosure power

supply cable and gland MC RC cable

plug and socket

Commando plug

and socket

Coach screw

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 26 of 37

Figure 8. Rail 350 Integrator terminal block with RC lead terminations.

Step 4 – Removal of MC enclosure and Rail350 units from mounting positions

The Esprit MC and Rail 350 enclosures should now be free of any connecting cable preventing their

removal. The Esprit Enclosure has two coach screws securing the MC and supporting bracket to the

LV pole, one is shown in Figure 7. Safe removal of the MC enclosure is a two-person task. The MC

coach screws should only be removed whilst the enclosure is held in place by another removal

contractor.

Once the MC enclosure coach screws have been removed, the Esprit MC enclosure and bracket

should be removed from the LV pole. Once the MC enclosure is safely placed on the ground, the

mounting bracket should be removed from the MC enclosure by removing the retaining screws from

the top and bottom corners at the rear of the enclosure.

The bracket and enclosure should be packed into separate, pre-labelled, boxes (supplied) and

removed from the PMT vicinity into a dry and secure environment.

A similar removal procedure should be followed for the Rail 350 unit, i.e. removing the unit by

unscrewing the coach screws from the LV pole, then remove the mounting bracket from the Rail 350

enclosure.

The cover should be replaced and fastened to the enclosure, ensuring the four plastic retaining

screws are tightened appropriately then pack the items separately into pre-labelled boxes (supplied).

All boxes should be moved into a dry and secure environment.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 27 of 37

6.7 Removal of cable routes and ducting

At the stage, where the SIPCs and RC leads were secured in place be cable capping and/or cable tied

to the LV pole, all cable routes and cabling should now have been removed. If any Esprit associated

cable restraints or brackets are still present, they should be removed at this stage.

6.8 Site Inspection

In addition to the requirements detailed in Sections 0 (

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 28 of 37

Management of safety) and 4.2 (General requirements for installation) a final visual inspection

shall be carried out:

A detailed visual inspection shall include:

The [Eldon (Esprit + Envoy) enclosure] mounting location

The location of cable runs from the [Eldon (Esprit + Envoy) enclosure] to the LV busbar

and

The feeder ABC phase conductors.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 29 of 37

Appendix I Esprit Monitor Controller

The Monitor Controller is connected to the LV mains electricity network, close to the distribution

transformer. The unit monitors the current on each of the three phases and can make intelligent

decisions about the distribution network – issuing commands, via PLC, to connected Intelligent

Control boxes.

Figure 9. Esprit Monitor Controller.

The external enclosure dimensions of the Monitor Controller are: (WxDxH)

320x230x85mm.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 30 of 37

Figure 10. Esprit Monitor Controller (v1.2) mounting points (marked by arrows).

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 31 of 37

Figure 11

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 32 of 37

Figure 12. Esprit Monitor Controller & Envoy unit enclosure design side view.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 33 of 37

Figure 13. Pole-mounted Transformer with HV Overhead Line and LV Overhead Line (Diagram from UK power networks 2012). Note SSEPD transformers quite often have the LV above the transformer which will require an HV outage to allow the unit to be installed.

Private and confidential

Method Statement Esprit Control Equipment - Pole Mounted HV/LV Transformer Structures

86000 - 3.1

P:\Projects\Project Numbers 86000 - 86990\04 Working\04 Tier 2 Project\04 Cluster Installation\02 Installation

Documents\01 Method Statements\02 - MC\Esprit Installation Method Statement 3.1.5 PMT.docx

01 July 2015 Page 34 of 37

Figure 14. Service Insulation Piercing Connector specification sheet.

www.eatechnology.com

Australia | China | Singapore | UAE | Europe | USA

Main reception: +44(0) 151 339 4181

EA Technology, Capenhurst Technology Park,

Capenhurst, Chester, CH1 6ES, United Kingdom

www.eatechnology.com

Australia | China | Singapore | UAE | Europe | USA

Main reception: +44(0) 151 339 4181

EA Technology, Capenhurst Technology Park,

Capenhurst, Chester, CH1 6ES, United Kingdom

Global Footprint

We provide products, services and support for customers in 90 countries, through our offices in

Australia, China, Europe, Singapore, UAE and USA, together with more than 40 distribution partners.

Our Expertise

We provide world-leading asset management solutions for power plant and networks.

Our customers include electricity generation, transmission and distribution companies, together

with major power plant operators in the private and public sectors.

Our products, services, management systems and knowledge enable customers to:

Prevent outages

Assess the condition of assets

Understand why assets fail

Optimise network operations

Make smarter investment decisions

Build smarter grids

Achieve the latest standards

Develop their power skills